norwest private hospital new wing project civil
TRANSCRIPT
Taylor Thomson Whitting (NSW) Pty Ltd
Norwest Private Hospital New Wing Project
Civil Engineering Report
for Health Projects International
1 November 2013
131528
Taylor Thomson Whitting (NSW) Pty Ltd Consulting Engineers ACN 113 578 377
48 Chandos Street St Leonards NSW 2065 PO Box 738 Crows Nest 1585 T 61 2 9439 7288 F 61 2 9439 3146 [email protected] www.ttw.com.au
This document is copyright and is the property of Taylor Thomson Whitting (NSW) Pty Ltd and must not be used without authorisation. © 2013 Taylor Thomson Whitting
Civil
SYDNEY
CANBERRA
MELBOURNE
QEC 22375
Health Projects International 131528 Norwest Private Hospital New Wing Project
Taylor Thomson Whitting (NSW) Pty Ltd Page 2 © 2013 Taylor Thomson Whitting
TABLE OF CONTENTS
Section Page
1.0 INTRODUCTION ........................................................................................................... 3
1.1 PROPOSED WORKS ................................................................................................... 3
1.2 DIRECTOR GENERAL REQUIREMENTS .................................................................... 4
2.0 STORMWATER ............................................................................................................ 5
2.1 EXTERNAL FLOW PATHS AND FLOODING ............................................................... 5
2.2 EXISTING STORMWATER DRAINAGE SYSTEM ........................................................ 5
2.3 PROPOSED STORMWATER DRAINAGE SYSTEM .................................................... 5
2.4 STORMWATER QUALITY ............................................................................................ 6
2.5 CONSTRUCTION PHASE STORMWATER MANAGEMENT ....................................... 6
3.0 CAR PARKING ............................................................................................................. 7
4.0 PAVEMENTS ................................................................................................................ 7
5.0 EXISTING SERVICES .................................................................................................. 7
6.0 CONCLUSION .............................................................................................................. 7
Health Projects International 131528 Norwest Private Hospital New Wing Project
Taylor Thomson Whitting (NSW) Pty Ltd Page 3 © 2013 Taylor Thomson Whitting
1.0 INTRODUCTION
Norwest Private Hospital is preparing a Development Application (DA) for a new wing at the hospital. This report covers the civil engineering issues at the site to support the DA.
This report has been prepared to accompany an Environmental Impact Statement prepared under Schedule 2 of the Environmental Planning and Assessment Regulation for an application for State Significant Development [SSD 13_6074] . This report specifically addresses the relevant matters associated with the Director General’s Environmental Assessment Requirements issued under Section 78A(8A) of the Environmental Planning and Assessment Act 1979.
1.1 Proposed Works
The proposed works includes a new building on top of the car park in the south-western portion of the site. The proposal also includes an additional car parking area between the existing structure and the site boundary to the south, totalling approximately 1,600 m
2.
Figure 1 shows the basement level plan with the new car park area highlighted in red.
Figure 1 Basement level plan
Health Projects International 131528 Norwest Private Hospital New Wing Project
Taylor Thomson Whitting (NSW) Pty Ltd Page 4 © 2013 Taylor Thomson Whitting
Figure 2 Proposed new car park location between existing building and retaining wall
1.2 Director General Requirements
Director General Requirements (DGR’s) addressed in this report are listed below.
10) Sediment, Erosion and Dust Controls. Identify measures and procedures to minimise and manage the generation and off-site transmission of sediment, dust and fine particles.
Response – A conceptual erosion and sediment control plan will be prepared as part of the design drawings.
14) Flooding. As assessment of any flood risk on site and consideration of any relevant provisions of the NSW Floodplain Development Manual (2005), including the potential effects of climate change, sea level rise and an increase in rainfall intensity.
Response – Flood risk at the site is minimal due to the fact that the site is near the top of the catchment. Any overland flow is carried by the road network.
15) Drainage. Detail drainage associated with the proposal, including stormwater and drainage infrastructure.
Response – Drainage details are shown conceptually in this report and will be detailed on design drawings. Increase in stormwater discharges will be mitigated though the use of on-site detention and a proprietary stormwater treatment device.
Health Projects International 131528 Norwest Private Hospital New Wing Project
Taylor Thomson Whitting (NSW) Pty Ltd Page 5 © 2013 Taylor Thomson Whitting
2.0 STORMWATER
2.1 External Flow Paths and Flooding
Flow paths were identified from topographic maps and a site visit. An existing overland flow path travels from Bella Vista Farm to the north, south through the roundabout and southwest on Norbrik Drive. The overland flow path does not have any impact on the proposed works.
No floodways have been identified in the vicinity of the site. Flooding information is not shown on Council’s LEP maps. The site has been assessed through a site visit and does not appear to be flood affected under current and future climate scenarios.
2.2 Existing Stormwater Drainage System
The majority of the existing site drains to an on-site detention (OSD) tank in the southern corner of the site. This tank is 16.3m x 25.0m with a storage volume of 397 m
3. Stormwater
is treated by a CDS P1009L gross pollutant trap before entering the OSD tank. There is a 50 kL rainwater re-use tank adjacent to the OSD tank.
The as-built hydraulic services drawings indicate that the area of the proposed car park bypasses the OSD and discharges via a pit in the southern corner of the site.
2.3 Proposed Stormwater Drainage System
The new building on top of the existing car park will discharge to the existing OSD tank utilising existing stormwater infrastructure. There will be no change to catchment areas or peak flows for this section of the site.
The new car parking area will have a separate OSD tank to meet the requirements of the Upper Parramatta River Catchment Trust’s On-site Detention Handbook, referenced in The Hills Shire Council Design Guidelines. A standard OSD calculation sheet has been included as an attachment to this document. The OSD required is:
• 73 m3 of storage volume;
• A 52 mm orifice on the primary outlet; and
• A 100 mm orifice on the secondary outlet.
The OSD tank will be located at the south-eastern end of the new car park area and discharge to the existing stormwater line running parallel to the site boundary.
Figure 3 Proposed car park drainage
Note that the new car park will not discharge via the existing OSD or re-use systems. It will discharge to the existing system that bypasses the OSD tank. The impact on peak flows is mitigated by the proposed OSD tank, so there will be no impact on the existing drainage network.
Health Projects International 131528 Norwest Private Hospital New Wing Project
Taylor Thomson Whitting (NSW) Pty Ltd Page 6 © 2013 Taylor Thomson Whitting
Figure 4 Existing stormwater systems outlets, south-eastern corner of the site
2.4 Stormwater Quality
The Hills Shire Council Design Guidelines states that “All proposals are to incorporate WSUD measures”. The document refers to Water Sensitive Urban Design Technical Guidelines for Western Sydney (NSW Government Stormwater Trust and UPRCT, May 2004) for the requirements of WSUD measures. The treatment criteria in the document are outline in Table 1.
Table 1 Stormwater Quality Targets
POLLUTANT/ISSUE
RETENTION CRITERIA
RETENTION CRITERIA
Coarse sediment 80% of average annual load for particles 0.5 mm or less
Fine particles 50% of average annual load for particles 0.1 mm or less
Total phosphorus 45% retention of average annual load
Total nitrogen 45% retention of average annual load
Litter 70% of average annual litter load greater than 5 mm
Hydrocarbons, motor fuels, oils and grease.
90% of average annual pollutant load
A proprietary stormwater treatment device, such as a Humes Jellyfish or a SPEL Basin can be specified to meet stormwater quality requirements. It is recommended that the treatment device be located downstream of the OSD tank to reduce the peak flow through the device and optimise the efficiency.
2.5 Construction Phase Stormwater Management
Construction works are to be carried out in accordance with the “Blue Book” erosion and sediment control requirements. The controls will depend on construction staging and methodology, but will most likely include sediment fences, sandbags around pits and a vehicle wash down. An erosion and sediment control plan will be prepared as part of the design drawings.
Health Projects International 131528 Norwest Private Hospital New Wing Project
Taylor Thomson Whitting (NSW) Pty Ltd Page 7 © 2013 Taylor Thomson Whitting
3.0 CAR PARKING
A preliminary review of the new parking layout indicates that the aisle width and parking spaces comply with the requirements of AS/NZS 2890.1.
4.0 PAVEMENTS
The pavement will be a ground supported flexible pavement, jointed concrete pavement or a suspended slab on piers subject to geotechnical recommendations.
5.0 EXISTING SERVICES
Existing services have been located through a dial-before-you-dig search. No external services are located in the area covered by the proposed works.
6.0 CONCLUSION
This report outlines the civil development requirements of the proposed new wing at Norwest Private Hospital.
The existing stormwater system can be utilised for the building works, while the new car park will require an OSD tank and a stormwater quality improvement device.
Prepared by: Authorised by:
TAYLOR THOMSON WHITTING TAYLOR THOMSON WHITTING
(NSW) PTY LTD (NSW) PTY LTD
Tim Henderson Stephen Brain
Engineer Technical Director H:\2013\131528\Stormwater\Norwest Hospital Stormwater.doc
Health Projects International 131528 Norwest Private Hospital New Wing Project
Taylor Thomson Whitting (NSW) Pty Ltd Page 8 © 2013 Taylor Thomson Whitting
Project:
Site Address
Job No:
Designer:
Telephone:
OSD Area:
L.G.A
Site Area 0.16 ha 1,600 m2
Total Roof Area 1E-15 ha 0 m2
Area of Site draining to OSD Storage 0.16 ha 1,600 m2
Residual Site Area (Lot Area - Roof Area) 0.160 ha
Area Bypassing Storage 0 ha
Area Bypassing / Residual Site Area 0.0% 30% Max
No. of Dwellings on Site 1
Site Area per Dwelling 0.160 ha
Roof Area per Dwelling 0.000 ha
Detention
Basic SSR Vols Ext Detention Storage 300 m3/ha Total Storage 455 m
3/ha
Basic SRDs Primary Outlet 40 L/s/ha Secondary Outlet 150 L/s/ha
Residual Lot Capture in OSD Tank 100%
Adjusted SRDs 40 L/s/ha 150 L/s/ha
Detention
Basic SSR Volume Ext Detention Storage 48.00 m3
Total Storage 72.80 m3
Total Rainwater Tank Credits 0.00 m3
0.00 m3
Storage Volume Total 72.80 m3
Storage Volume Ext Detention Storage 48.00 m3
Flood Detention Storage 24.80 m3
OSD Discharges Primary Outlet 6.40 L/s Secondary Outlet 24.00 L/s
RL of Top Water Level of Storage 77.800 m 77.800 m
RL of Orifice Centre-line 76.500 m 76.500 m
Number of Orifices 1 1
Estimated Downstream Flood Level 76.50 1.5 yr ARI 76.50 100 yr ARI
Downstream FL - RL of Orifice Cente-line 0.00 Satisfactory 0.00 m
Design Head to Orifice Centre 1.300 m TWL Ext Detn Storage - RL Orif ice 1.300 m
Calculated Orifice Diameter 52 mm Satisfactory 100 mm
RL of Minimum Habitable Floor Level 81.000 m
RL of Minimum Garage Floor Level 78.000 m
Length of Overflow Weir 1.50 m
Site Runoff Coefficient 0.76
Storm Intensity (5 min 100 yr ARI) 219 mm/h
Peak Flow over Weir 74.0 L/s
Depth of Flow over Weir 97 mm
Freeboard to Habitable Floor 3103 mm
Freeboard to Garage Floor 103 mm
OSD Tank Bypass
Extended Detention
Satisfactory
Satisfactory
Satisfactory
OSD Calculations
Overflow Weir & Freeboard Calculation
Satisfactory
On-Site Detention Calculation Sheet for Upper Parramatta River Catchment
HED Secondary Outlet
Satisfactory
Basic OSD Parameters
Extended Detention
Norwest Private Hospital
Norbrik Drive, Bella Vista
131528
T Henderson
(02) 9439 7288
Satisfactory
Site Data
Satisfactory
Upper Parramatta River Catchment
Baulkham Hills Shire Council
Baulkham Hills Shire Council
11