  • Additional Capability; Top hole + main well completion, Step 2.Top hole main well completion, Step 2.

    Typical average well construction sequence; 52 days drilling and 10 days completion work.

    Top Hole Drilling 12 days(Drill for and run 36 and 20)

    19% of the Well Construction Time

    Main Drilling Phase 40 days(Run BOP, drill for and run 13-3/8, 9-5/8

    and 7 casings. Do initial completion)

    65% f th W ll C t ti ti

    Main Completion Phase 10 days

    16% of the Well Construction Time65% of the Well Construction time

    SAVING ON DAY RATE 3 mUSD

    SAVING ON DAY RATE 2,5 mUSD

    SAVING PER WELL Direct day rate savings on drilled well; 20% (5.5 mUSD)

    10

    Cost reduction, increased rig utilization and increased

    Rig can be utilized for 22 days on other well; USD10 mill in increased efficiency

    Cost reduction, increased rig utilization and increased numbers of wells drilled per year.

    Rig Dayrate 450.000,. USD Norshore Atlantic Day Rate 200.000,- USD

  • Well Intervention Vessel

    Light Well Intervention Intervention with Riser

    Module Installation

    Wireline / Tractor Riserless Well Interventionith LRP/L bricator

    Riser Intervention with LRP/EDP - Stiff or Compensated Riser.

    with LRP/Lubricator.

    Rotatable RiserTension Ring

    Lubric. Valve Sec.

    6 5/8 DP Riser or Riser ID 7,25

    11

    LRP/EDP

  • Subsea Construction Vessel

    Alternative to large Crane Vessels

    Sub Sea Module Installation 150 mT compensated Offshore SS Crane.

    Wet Tow Items moved Offshore, hanging below the vessel in safe distance above the Seabed.

    500 sTon Compensated during Transit and Installation.

    Large size Sub Sea EquipmentLarge size Sub Sea Equipment Installation

    Templates / Manifolds / Etc..

    ROV t ROV support - survey

    12

  • Contact:Trond Haugland VP Operationth@norshore [email protected]: +47 99454561www.norshore.no

    Thank You !

    13

  • Vessel specification

    Main particulars

    L h ll 11 40

    Class notation

    Length overall : 115,40 m Breadth molded 22,00 m Depth main deck 9,00 m Deadweight approx 6,500 t

    DNV *1A1 Ship-shaped Drilling Unit Drill(N)-FS E0 DYNPOS AUTRO-DK Heldk SH-LFL* HL(2,8) COMF-V(3) - Clean design

    Capacities

    Moon Pool 7,20 x 7,20 m Speed (dm-4,5m, open moonpool) 14,5 kts 116 Beds

    EquipmentCapacities

    Fresh Water 1,000 m3

    Fuel oil 1,400 m3

    Equipment

    Main engines : MAK (6pcs) 14,600 kW Thrusters : RollsRoyce 2x3,000kW and 4 x 1,500 kW

    Liquid Mud 1,250 m3

    Dry Bulk (Cement/barite) 280 m3

    Hydrocarbon Slop tank 85 m3

    Methanol 7 m3

    Drilling Module Handling tower : NOV (500 sT A&P HC) Top Drive (Continuos Drilling Torque 55200 ft-lb) Drilling Equipment; NOV (including 3x1600 mud pumps) Remote Operated Pipe Handling, NOV.

    Work deck 1,200 m2 Special designed for handling of large size conductors casing.

    Mud Mixing Package; NOV Offshore Crane : NOV (140t AHC, 2500 m wire) ROV : TBN (150 hp / 3000m) Optional LARS : TBN (4,000m AHC), Optional 6 x 100 mT Skid Stations 14

  • Top SideTop Side

    15..\Animation\Noreshore_MPD.wmv

  • Top SideTop Side

    16

  • GA Norshore AtlanticGA Norshore Atlantic

    17

  • GA Norshore Atlantic

    18

  • GA Norshore Atlantic

    19

  • Operability Analysis at North Sea

    Marine Cybernetics - Simulator Simulations

    2 Sigma Values

    High accurancy

    5 mHs maximum Operation Condition5 mHs maximum Operation Condition

    North Sea Less than 10 % WOW.

    Brazil Less than 1 % WOW.

    20

  • Tophole Drilling - A more efficient way of drilling

    North Sea Scenario Norshore Concept

    Tophole Drilling A more efficient way of drilling

    +

    Semi submersible drills entire well; tophole Norshore drill top holes & last part of P & ASemi-submersible drills entire well; tophole drilling, drilling with riser/BOP, well completion.

    75 Days 10 + 65 Days

    Norshore drill top holes & last part of P & A.Drilling rig/ship to perform remaining drill work.

    75 Days 10 + 65 Days

    An oil company with three drilling rigs can drill ~14 wells in one yearWith one Norshore unit and three drilling rigs he can drill ~17 wells in one yearWith one Norshore unit and three drilling rigs he can drill 17 wells in one year

    Well cost reduction of 5 -15 %.Annual increased rig utilization of 10 - 20 %World wide marketWorld wide market

    21

  • Riser to Catwalk

  • Riser to Elevator

  • Skidding XMTRT into Moonpool. g p

  • Lower Cursor frame attached to XMTRT

  • Skidding XMT into Moonpool g p

  • Open Moonpool Door p p

  • Run in with XMT

  • Coil Tubing Operation

    Alternative to SS Rig / Drillship

    Stiff or Compensated Riser

    High V-Door OpeningHigh V Door Opening

    Passive Compensation System Return of HC to the Unit.

    29

  • Slender - Slim Well Drilling, Optionalg, p

    Potential Savings; 35%

    Well Cost Component

    Slender Well % Savings

    Casing 28 %

    Cement & Casing

    30 %g

    Drilling Fluids 44 %

    Rental Tools 20 %

    Logistic 30 %

    Rig Rental 50 %

    30