NGAO NGAO Instrumentation WBS ReplanInstrumentation WBS Replan

By Sean AdkinsBy Sean AdkinsApril 25, 2007April 25, 2007

Page 2: NGAO Instrumentation WBS Replan By Sean Adkins April 25, 2007

2

NGAO IWG

• Replanned WBS 3.5• Science case requirements converging• Instrument work prioritized by key items:

– NIR Deployable IFU/imager

– Coronagraphs in the NIR and Visible Imagers

• Optical and mechanical engineering resources will be used for concept development

• Current overall replan presents some problems with timing in relationship to other activities that interact closely with instruments

• Planning to work closely with AO design team on object selection and high order correction for deployable instrument

• Planning to deliver reports on each instrument in two revision cycles• Planning to support overall cost estimation process, but instrument

costing will still be at a “ROM” level

Page 3: NGAO Instrumentation WBS Replan By Sean Adkins April 25, 2007

3

New WBSWBS Tas k Nam e

3.5 Science Instruments

3.5.1 Instrument Requirements & Initial Definitions

3.5.1.1 Top Level Ins trum ent Requirem ents & Definitions

3.5.1.2 Instrument Suite Version 1

3.5.1.2.1 Ins trum ent Function Allocation Review with Science Team

3.5.1.2.2 Sum mary Des criptions of Instruments

3.5.1.3 Instrument Suite Version 2

3.5.1.3.1 Ins trum ent Review with Science Team

3.5.1.3.2 Revised Summary Des criptions of Ins truments

3.5.1.4 Instrument Interfaces

3.5.1.4.1 Hardware Ins trum ent Interfaces

3.5.1.4.2 Software Instrument Interfaces

3.5.2 NIR Deployable IFU (NIR D-IFU)

3.5.2.1 NIR D-IFU Concept Development

3.5.2.2 NIR D-IFU AO Interface Issues

3.5.2.2.1 Object Selection for NIR D-IFU

3.5.2.2.2 AO Des ign for NIR D-IFU

3.5.2.2.3 NIR D-IFU AO Boundary

3.5.2.3 NIR D-IFU Spectrograph Concepts

3.5.2.4 NIR D-IFU Imager Concepts

3.5.2.5 NIR D-IFU Concept Review

3.5.2.5.1 NIR D-IFU Concept Review with Science Team

3.5.2.5.2 NIR D-IFU Concept Review with AO Team

3.5.2.6 NIR D-IFU Report ver 1

3.5.2.7 NIR D-IFU Report ver 2

M3.5.3 Single Object Imagers/Low Resolution Spectrographs (SOI/LRS)

3.5.3.1 SOI/LRS Coronagraph Requirements

3.5.3.2 SOI/LRS Spectrograph Requirements

3.5.3.3 SOI/LRS Concept Developm ent

3.5.3.4 SOI/LRS Concept Review

3.5.3.4.1 SOI/LRS Concept Review with Science Team

3.5.3.4.2 SOI/LRS Concept Review with AO Team

3.5.3.5 SOI/LRS Reports

3.5.3.5.1 SOI/LRS NIR ver 1

3.5.3.5.2 SOI/LRS Visibile ver 1

3.5.3.5.3 SOI/LRS NIR ver 2

3.5.3.5.4 SOI/LRS Visible ver 2

3.5.4 Single Object IFUs (S-IFU)

3.5.4.1 NIR S-IFU Requirem ents Review

3.5.4.2 Vis ible S-IFU Requirements Review

3.5.4.3 Vis ible S-IFU Concept Development

3.5.4.4 S-IFU Concept Review

3.5.4.4.1 S-IFU Concept Review with Science Team

3.5.4.4.2 S-IFU Concept Review with AO Team

3.5.4.5 Single Object IFU Reports

3.5.4.5.1 S-IFU NIR ver 1

3.5.4.5.2 S-IFU Visible ver 1

3.5.4.5.3 S-IFU NIR ver 2

3.5.4.5.4 S-IFU Visible ver 2

3.5.5 Special Purpose High Contrast Instrument (HCI)

3.5.5.1 HCI Requirem ents Development

3.5.5.2 HCI Concept Development

3.5.5.3 HCI Concept & Need Review with Science Team

3.5.6 Interferometer

3.5.7 OHANA

M