nfl-bathinda final.docx

Upload: nikhilgarg732

Post on 02-Jun-2018

229 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/10/2019 NFL-Bathinda Final.docx

    1/65

    1 | P a g e

    INTRODUCTION

    NFL Schedule - A & Mini Ratna Category 2004-2005. - ICompany, is a market leader in the fertilizer Industry in India

    With 17.0% share in Urea production during 2004-2005.

    PERCENTAGE SHARE OF NFL IN

    UREA PRODUCTION

    IN THE COUNTRY (2004-2005)

  • 8/10/2019 NFL-Bathinda Final.docx

    2/65

    2 | P a g e

    NFL was incorporated on 23rd August,

    1974 with two manufacturing Units at

    Bathinda and Panipat. Subsequently, on

    the reorganization of Fertilizer group o

    Companies in 1978, the Nangal Unit o

    Fertilizer Corporation of India came under

    the NFL fold. The Company expanded its

    installed capacity in 1984 by installing and

    commissioning of its Vijaipur gas based

    Plant in Madhya Pradesh.

    NFL Corporate office: Noida

    The Vijaipur Plant was a land mark achievement in project management in India.

    The plant was completed well within time and approved project cost. In recognition of

    this achievement, the project was awarded the First Prize in Excellence in Project

    Management by Govt. of India. Subsequently the Vijaipur plant doubled its capacity to

    14.52 lakh MTs by commissioning Vijaipur Expansion Unit i.e. Vijaipur-II in 1997. The

    plant annual capacities have now been re-rated w.e.f. 1.4.2000 from 7.26 lakh MT of

    Urea to 8.64 lakh MT for Vijaipur-I & Vijaipur-II Plants each.

    Three of the Units are strategically located in the high consumption areas of Punjab and

    Haryana. The Company has an installed capacity of 35.49 lakh MTs of Nitrogenous

    Fertilizers and has recorded an annual sales turnover of Rs.3,474 crores during 2004-05.

    The Companys strength lies in its sizeable presence, professional marketing and strong

    distribution network nationwide.

    NFL, a profitable public sector undertaking operates under the administrative control

    of Deptt. of Fertilizers in the Ministry of Chemicals & Fertilizers.

    Kisan Urea and Kisan Khad NFLs popular brands are sold over a large marketing

    territory spanning the length and breadth of the country. The Company also

    http://www.nationalfertilizers.com/urea.htmhttp://www.nationalfertilizers.com/urea.htmhttp://www.nationalfertilizers.com/khad.htmhttp://www.nationalfertilizers.com/khad.htmhttp://www.nationalfertilizers.com/khad.htmhttp://www.nationalfertilizers.com/urea.htm
  • 8/10/2019 NFL-Bathinda Final.docx

    3/65

    3 | P a g e

    manufactures and markets Biofertilizers and a wide range of industrial products like

    Methanol, Nitric Acid, Sulfur, Liquid Oxygen, Liquid Nitrogen etc. The Company has

    developed Neem coated Urea which on demonstration has improved the crop yield by 4-

    5%. The Company is focusing its thrust to widen the marketing operations of Neem

    coated Urea.

    NFL over the years has developed a team of dedicated professionals in the areas

    of production, maintenance, project management, safety and environment control. These

    professionals are sought after in the Industry both in India & abroad for their Specialized

    Services.

    NFL is known in the industry for its work culture; value added human resources,safety, environment, concern for ecology and its commitment to social upliftment. All

    NFL plants have been certified for ISO-9002 for conforming to international quality

    standards and International Environmental Standard i.e. ISO-14001. With the

    certification of Corporate Office/Marketing operations under ISO-9001:2000, NFL has

    become the first Fertilizer Company in the country to have its total business covered

    under ISO-9001 Certification.

    The System of marketing of Urea has undergone a change w.e.f. 1.4.2003 when

    company has been allowed to market 25% of its produce outside ECA during Kharif

    2003. This percentage of sale outside ECA was raised to 50% in Rabi 2003-04, The

    same portion prevails for 2004-05 and Kharif 2005.

    Need for NFL the National Fertilizers Limited (Public Undertaking) was thought to plan

    two modern large capacity single steam nitrogenous fertilizers plant in order to meet the

    increasing demands.

    On 23 rd August 1974, NFL was formed and registered to set up two modern large

    capacity Nitrogenous Fertilizers plants.

  • 8/10/2019 NFL-Bathinda Final.docx

    4/65

    4 | P a g e

    NFL, Bathinda (Punjab)

    NFL, Panipat (Haryana)

    each with the capacity of 5-11 lakh tones /annum.

    As to set up any plant there are some essential conditions that support the existence

    and working of plants for years, so Bathinda was basically selected as one of the site of

    Fuel based plant as per consumption point of view since Punjab is mainly agriculture

    based state.

    " Feed in " at Bathinda was achieved on 7 th Dec. 1984 and from this project

    ammonia was successfully produced on 28 th May 1979 and urea on 2 nd June 1979.NFL

    was incorporated on 23 rd August 1974 in order to implement this project contract wereentered into with M/s " TOYO ENGINEERING CORPORATION " a well known

    Japanese Engg. Company and Engg. India Ltd (EIL), a public sector and Engg.

    Organization .This contract becomes effective on September 26, 1974 with a guaranteed

    Feed in on the Bathinda Fertilizers project to implement within 36 months from the

    zero date.

    Due to the power requirements and some other factors, later on it was planned to

    set up its own power house known as Captive Power Plant (CPP) with 2 turbo generators

    of 15 MW each.

    National Fertilizers Limited (N.F.L.) is the largest manufacturer of nitrogenous

    fertilizers in the Northern India. It is presently operating four large fertilizers plants, two

    of which are located at Nangal and Bathinda in the Punjab State, one at Panipat in

    Haryana and one at Guna in M.P. While plants at Nangal and Panipat are fuel-oil based,

    and at Bathinda and Guna are gas-oil based. The overall installed capacity of NFL plants

    is 10.42 lakh MT per annum.

  • 8/10/2019 NFL-Bathinda Final.docx

    5/65

    5 | P a g e

    Strategically Located - Urea Plants

    Leading Producer of Nitrogenous Fertilizers in the Country.

    Capital Cost, Feed Stock & Plants Capacity

    Plants Capital Cost(Rs.Crore)

    Feed Stock Existing Capacity

    MT/Year (Lakh MT/Yr.)

    Ammonia Urea CAN Bio-Fert.

    Nangal-I 91.26 Naptha 0.66 - 3.181 -

    Nangal-II 299.19 F.Oil/LSHS 2.97 4.785** - -

    Panipat 338.41 F.Oil/LSHS 2.97 5.115 - -

    Bathinda 349.41 F.Oil/LSHS 2.97 5.115 - -

    Vijaipur-I 516.00 Natural Gas 5.016* 8.646* - -

    Vijaipur-II 1071.00 Natural Gas 5.016* 8.646* - -

    Indore 1.42 Strains - - - 100

    Total 2666.55 19.602 32.307 3.181 100

  • 8/10/2019 NFL-Bathinda Final.docx

    6/65

    6 | P a g e

    PRODUCTS OF NFL

    National Fertilizers is producing Kisan Urea, Kisan Khad and Ankur on

    commercial scale. NFL is also marketing number of Industrial products produced as By-

    Products during the formation of Kisan Urea, Kisan Khad and Ankur in its plant itself.

    FERTILIZERS PRODUCTS

    Kisan Urea:

    Kisan Khad:

    INDUSTRIAL PRODUCTS (BY PRODUCTS)

    Nitric Acid (HNO3)

    Anhydrous ammonia (NH3)

    Ammonium Nitrate (NH4NO3)

    Nitrogen (N2)

    Carbon dioxide (CO2)

    Sodium Nitrate

    Oxygen (O2)

    Carbon (C) from slurry

    IMPLEMENTATION AND PROJECT COST OF NFL BATHINDAUNIT

    As NFL, Bathinda unit was planned to complete in 36 months from the Zero date

    26 Sep.1974, so contract for completing this task was given to the well known Japanese

  • 8/10/2019 NFL-Bathinda Final.docx

    7/65

    7 | P a g e

    company Toyo Engineering corporation limited and Indian Consultancy Companies as

    well.

    The overall approval cost of Bathinda Unit was Rs. 240.47 Crores with a foreign

    exchange component which was mainly from Japanese Yen.

    REQUIREMENTS OF RAW MATERIAL / INPUTS

    Fuel Gas 850 MT / Day

    Coal 1680 MT / Day

    Water 13 MGD

    Power 28 MW

    PROJECT s BENEFITS

    Increased Food Output

    Employment to nearly 800 persons

    Both Central and State Government has been benefited by way of excise duties and otherlocal taxes on Raw materials and other products.

    Scope for marketing by-products such as CO 2 , Nitrogen , Oxygen , Carbon etc.

    NFL won many major awards related to Safety , Productivity , Pollution control , Longest

    accident free period .

    - An OHSAS-18001 certified unit .

    - An ISO-9002 and ISO-14001 certified unit .

  • 8/10/2019 NFL-Bathinda Final.docx

    8/65

    8 | P a g e

    STEAM GENERATION PLANT

    Steam Generation plant is mainly installed for production of steam and then

    distributed to various parts of the plant.

    Here this section of plant installed in National Fertilizers Limited, Bathinda unit produces

    and supplies steam at 100 Kg / cm 2 pressure and nearly 480C temperature to Ammonia

    Plant.

    In todays world steam has gained importance in Industries. It may be used for power

    processes and heating purposes as well.

    BENEFITS OF STEAM

    It is colourless, odourless and tasteless.

    Very economical.

    Non polluting.

    Can be used as heat exchanger.

    It can be easily distributed to various sections of plant.

    Steam is generated in Boilers(Water tube boilers mounted on common base fittedwith mountings and fittings) and then distributed to other parts of plants . For governing

    the quantity of fuel to be burned and for maintaining the required pressure their are many

    automatic fuel feeders, equipments and auxiliaries like pressure gauge etc.

    In the Boilers used at National Fertilizers Limited (Bathinda unit); coal, oil

    natural gas are used as a fuel for production of steam.

    NFL , Bathinda is using steam for two purposes ; first and the main reason is for running

    prime mover and other reason is to exchange heat in the processes taking place their.

    There are three boilers capable of producing steam at the rate of 150 Tonnes/hr

    installed in CPP which were supplied and erected b BHEL. Generally two boilers are

    enough to meet the requirements but third boiler is simultaneously running because if

  • 8/10/2019 NFL-Bathinda Final.docx

    9/65

    9 | P a g e

    steam load consumption increases then the third boiler play its part in order to avoid any

    faulty condition.

    FUELS USED

    Coal : To obtain steam of desired Temperature and pressure, coal is burned to give

    major source of heat.

    Initially coal is stored at Coal Handling plant brought from coal sites. It is this section of

    plant where coal is crushed by crushers in order to make small pieces of coal, then after

    crushing it the coal pieces rare passed through heavy electromagnet where iron is

    separated from coal if present. Coal is then sent to Bunkers from where it goes to

    Grinding mill. Grinding mill is grinding coal into powder form.

    Conveyor Belts are being used in the whole plant for transportation of Coal. The powder

    form of coal is sent to the Boilers through pump as pump sucks the coal from grinding

    mills and throws it into the boiler for combustion.

    Fuel Gas : As the Boilers are designed to work on both Coal as well as Fuel Gas so fuel gas can also be p

    Generally coal alone is not burnt Initially but Fuel Gas is mixed coal and then sent to the

    furnace for combustion in order to get desired temperature .Flue gases produced whichare very hot surrounds the water tubes (Tubes carrying water).When hot flue gases

    surrounds the water tubes, the temperature of water in tubes starts rising ,as a result

    Steam is generated.

    WHY AND WHERE STEAM IS REQUIRED

    As National Fertilizers Ltd, Bathinda unit has its own Steam Generation Plant where

    steam is produced which is used for driving Turbo Compressors, Heating Purposes, for

    various reactions taking place in the plant itself.

    Steam is mainly consumed in the Ammonia Plant as nearly 6 to 7 tonnes of steam is

    required to produce 1 tonne of Ammonia. High Pressure Turbines are being used where

  • 8/10/2019 NFL-Bathinda Final.docx

    10/65

    10 | P a g e

    high pressure and temperature is to be maintained so SGP section plays a important role

    for maintaining the said condition.

    There are three boilers (VU-40 type supplied by M/S BHEL) of 150 tonne/hr

    capacity .These boilers are Water Tube Boilers i.e water is inside the tubes and hot air

    surrounds it when coal is burnt ,this makes the water in the tubes boil and steam

    formation takes place. In the beginning coal is burnt with fuel oil in order to get desired

    temperature.

    FIRING SYSTEM

    As coal brought from various sites is in form of big pieces of various sizes , so first

    it is reduced in smaller pieces known as pulverized coal which is then further grinded

    using BOWL MILLS so that it burns completely in the furnace to give proper

    combustion.

    Coal received from material handling plant is stored in coal bunker and is fed to

    bowl mill through a coal feeder .Hot air is also supplied in the mill for heating the coal

    and conveying it to furnace through a fan called EXHAUSTER FAN which takes suction

    from the mill and maintains it under negative pressure. Oversize and un grind able

    material like stones are thrown out by the mill. Pulverized fuel i.e mixture of coal and air

    is supplied to Coal Burner through Exhauster. Coal burners are arranged tangentially onall the four corners of the rectangular furnace at three elevation levels. Thus there are

    total 12 Burners. In between these, three elevations Gas Burners and Start Up

    Burners/Igniters are arranged at two elevations. Thus there are 8 Gas Burners and 8

    Igniters.

    Igniters use LPG .

    The Furnace is a cubical suspended enclosure with water tubes forming its four

    walls. The furnace is designed with sufficient volume to provide for complete and

    efficient combustion at all loads without flame impingent by the reaction of carbon

    present in coal and the oxygen present in the air to form Carbon-Di-Oxide.

    C + O 2 CO 2 + Heat

  • 8/10/2019 NFL-Bathinda Final.docx

    11/65

    11 | P a g e

    WATER AND STEAM SYSTEM

    As the steam being used should be free from impurities like minerals, silica, oxygen,

    Iron etc. in order to insure Safe and Efficient working of Steam turbines and Boilers. For

    this purpose Raw Water is physically and chemically treated and finally supplied to

    Steam Generation Plant from Ammonia plant. This water is called Boiler Feed water

    which is further heated to 240 C by the flue Gases and taken to Steam Drum. Steam

    Drum Acts as storage tank and also separates water from the steam at 315 C and 106

    kg/cm2 pressure water then enters the Ring Header formed at on the bottom of outside

    the furnace and rises by gravity through water wall tubes on the all the four sides, taken

    heat from furnace and enters steam drum as a mixture of steam and water .

    FLUE GAS SYSTEM

    The products of combustion in the furnace consist of carbon-di-oxide, nitrogen, ash.

    After leaving the furnace the heat of these gases called FLUE GASES, is utilized at

    various levels.

    First the steam from steam drum is heated in two super heaters to get the required

    temperatures of 495 0C and then feed water in BANK TUBES is also heated and the gasesleave bank tubes at around 497 0C next the heat is utilized to heat feed water in the

    ECONOMIZER and gases are cooled down to 320 0C. These gases are further cooled

    down to 150 0C in ROTARY AIR HEATER where the air is required for combustion and

    conveying the coal is heated up. These gases then pass through ELECTRO STATIC

    PRECIPITATOR (ESP) where ash is removed. From ESP these gases pass on to

    INDUCED DRAFT FAN which maintains draft in the furnace and finally the gases are

    let off to the atmosphere through a chimney about 80mtr high.

  • 8/10/2019 NFL-Bathinda Final.docx

    12/65

    12 | P a g e

    MAIN EQUIPMENT

    ECONOMIZER

    The main function of Economizer is to preheat the boiler water before it is

    introduced into the steam drum. It recovers some of the heat from the flue gases leaking

    out of the boiler. The economizer is located in the second pass of the boiler above the air

    heater. Each section is composed of number of parallel tubes circuit which is arranged in

    the horizontal rows. All tubes circuit originated from inlet header and discharge at outlet

    header.

    Feed water is supplied to inlet water header via free of stop and check valves. The feed

    water flow is upward through the economizer that is in counter flow to the hot flue gases.

    Any chance of steam generation within the economizer is eliminated by the upward water

    flow that is led to the drum via the economizer outlet link.

    SUPER-HEATER

    The main function of the super-heater is to superheat the steam. Super heater is

    located at the outlet of the furnace.

    OPERATION

    Before lighting off the unit, open wide inlet and outlet header drains, vents links

    drains and main steam line drains. Close all the drains prior to lighting off when the

    headers and links appear free of water drain that senses as a starting drain header drain

    and is kept open after the unit is on line.

  • 8/10/2019 NFL-Bathinda Final.docx

    13/65

    13 | P a g e

    DE SUPER-HEATER

    Mainly the function of De super heater is to reduce the temperature of the steam. De

    super heater are provided in super heater connecting links to permit reduction of steam

    temp. When necessary and to maintain the temperature at design values within the limits

    of the nozzle capacity. Reduction in the steam temperature is accomplished by injecting

    spray water into the path of the steam; the spray water source is the boiler feed water

    system. It is essential that the spray water should be chemically pure and free of

    suspended and dissolved solids. Containing only approved volatile organic treatment

    materials in order to prevent the chemical deposition in the super heater.

    DRUM

    It is necessary to separate the saturated steam from the steam water mixture for

    circulation type boiler. This performance is achieved by steam separators arranged in the

    drum.

  • 8/10/2019 NFL-Bathinda Final.docx

    14/65

    14 | P a g e

    CAPTIVE POWER PLANT

    INTRODUCTION

    National Fertilizers Limited has set a Captive Power Plant (CPP) at their complex at

    BATHINDA, to ensure availability of stable, uninterrupted power and stream to the

    Ammonia and Urea plant. This will minimize the tripping of the Fertilizer Plant due to

    transit voltage dips and power cuts.

    Since inception, Bathinda unit was drawing electric power from Punjab State

    Electricity Board (P.S.E.B). Electricity is the main driving force after steam in the plant,

    being used for moving auxiliary equipments. The unit requires 27MW of power/hr when

    running at full load. There are two 15 MW turbo-generators to generate power. Under

    normal running conditions of the plant and healthiness of the P.S.E.B. grid, we generally

    run in synchronism with the grid merely drawing the power corresponding to the

    minimum charges to be paid to state electricity board. In case of any disturbance in the

    grid, our system gets isolated from the grid automatically. With both generators running,

    we are able to feed power to the whole plant, thus production is not affected. In case only

    one turbo generator is in line and grid cuts off, urea plant is cut off automatically to balance the load with one generator. As soon as the grid becomes stable, the generators

    are again synchronized with it. The power generation of each generator can be varied

    with 2 MW to 15 MW maximum, provision exists to run the generator on 10 % extra load

    continuously for one hour only.

    Operation of C.P.P. is based upon microprocessor based computerized

    instrumentation which allows automatic operation, start up, shut down of the whole or

    part of the plant.

    Latest instrumentation has been used in this plant. It allows controlling process variables

    like flow, pressure, temperature, power factor, voltage, frequency, etc. There is operator

    interface unit (IOU) LIKE A TV screen on which various parameters can be displayed

  • 8/10/2019 NFL-Bathinda Final.docx

    15/65

    15 | P a g e

    and controlled. It allows fully automatic start-up, shut-down of boiler, turbine and other

    auxiliaries.

    NEED FOR C.P.P.

    It was thought to install a captive power plant in which electric power for our

    requirement shall be generated in a COAL FIRED BOILER. The benefits envisaged

    were:

    1. Any disturbance in the PSEB grid used to trip the whole plant. Lot of money was

    lost due to this as each re-startup costs around 40 to 50 lakhs rupees. Moreover,

    frequent tripping s had an ill effect on machines and equipments extending the re-

    startup period.

    2. Three boilers of 150Te/hr steam capacity were initially installed in SGP to keep 25

    boilers running and one stand by as designed steam requirement was less than 300Te/hr.

    but in actual operation steam requirement was more and all three boilers had to be run

    and there was no breathing time for their maintenance. As new boiler was to be installed

    for CPP, its capacity was so designed that it could export around 60Te of steam for process requirement so that only 2 boilers of SGP would be run keeping the 3 rd as stand

    by.

    With these points in mind CPP was installed. The functioning of CPP can be sub-divided

    into parts:

    BOILER AND ITS AUXILIARIES : For generation of high pressure superheated

    steam.

    TURBO-GENERATOR AND ITS AUXILIARIES: To generate power, using

    steam from the boiler.

  • 8/10/2019 NFL-Bathinda Final.docx

    16/65

    16 | P a g e

    Operation of CPP is based upon microprocessor based computerized instrumentation

    which allows automatic operation, start up, shut down of the whole or the part of the

    plant.

    BOILER

    The basic principle of this boiler is the same as discussed earlier for SGP boiler that is

    formation of steam by heating boiler feed water inside furnace fired by coal and heavy

    oil, utilization of heat of the gases and venting these gases at a safe height. Main

    differences between the two boilers are:

    SGP boiler is tangentially fired where as CPP boiler is front fired with 6 coal

    burners and 6 oil gun fixed inside the coal housing.

    SGP boiler can be loaded up to 30% load with oil firing only whereas CPP boiler

    can be fully loaded with oil alone.

    Height of combustible zone in CPP boiler is more and it has residence time of 1.5 sec

    where SGP boiler has 1.0 sec.Mills used for pulverizations of coal in SGP are negative pressure bowl mills whereas in

    CPP ball tube mill are used which are positive pressure mills.

    Due to more residence time and better pulverization the efficiency of CPP boiler is

    about 4% higher.

    Boiler feed water required for steam generation can be fully generated in CPP itself.

    A part of the steam generated is exported for process use in ammonia plant and rest

    is utilized for power generation in turbo generators as described below:

  • 8/10/2019 NFL-Bathinda Final.docx

    17/65

    17 | P a g e

    DESCRIPTION

    MITSUI RILEY TYPE BOILER

    Maximum evaporation 2,30,000 kg/hr

    Design process for boiler 124kg/cm 2G

    Steam temp at outlet 495 0C

    Heating surface 1250m 2

    FUEL COAL SYSTEM

    The purpose of fuel coal system is to pulverize coal to dry coal and to convey the

    pulverized coal from ball tube mill to burners by primary air for coal firing.

    Fuel coal system consists of three systems:

    coal supply system.

    primary air system.

    seal air system.

    COAL SUPPLY SYSTEM

    PRIMARY AIR SYSTEM

    The primary air system performs two functions. It provides the proper amount of air

    required to convey the pulverized coal to the burners and the heat necessary to dry coal so

    it can be pulverized and burned efficiently. The details of primary air fan are:-

    Coal bunkers

    Coalfeeders

    Crushersdryers

    Ball tubemill

  • 8/10/2019 NFL-Bathinda Final.docx

    18/65

    18 | P a g e

    Make MEIDEN

    Degree of protection IP 55

    No of poles 4

    Frequency 50Hz

    RPM 1475

    Power factor 0.89

    Insulation class F

    Rated power 195kW

    Type of construction IEC-34

    Normal temp rise limit 70 0C

    SEAL AIR SYSTEM

    The seal air is distributed to the components by the sealing of the mill system by the

    sealing air fan. The sealing air fan takes suction from silencer and discharges it to a

    common header. The controller for each mill system provides a constant differential

    pressure to protect against coal leaking into the bearings and seals. This system should be

    in service before being placed in operation.

    CRUSHER DRYER SYSTEM

    Crusher-dryer performs the CRUSHING function. Metered coal from the feeders blends

    with a properly heated amount of air from the primary air fan and enter the crusher dryer.

    The non clogging pre crushing flash dryer operates continuously at constant speed.

    Rotating hammers drive the incoming coal against a breaker plate and adjustable crusher

    block, increasing the surface area of the coal and mixing it with the incoming preheated

    air.

  • 8/10/2019 NFL-Bathinda Final.docx

    19/65

    19 | P a g e

    BALL TUBE MILL

    Grinding the coal to the proper fineness is done by ball tube mill. The crushed coal and

    air mixture from the crusher dryers enter the mill through the mill inlet boxes on both

    ends of the mill. The mill barrel rotating at constant speed, contains thousands of

    kilograms of various sizes of hardened steel balls which cascade down upon the entering

    coal and pulverize it to talcum powder consistency. The heated primary air, entering with

    coal, not only completes the drying process, but now conveys the coal dust from the mill

    through the mill output boxes to the classifiers on both ends of the mill. The

    specifications of the ball tube mill are as:-

    Make MEIDEN

    Degree of protection IP 55

    Insulation class F

    No of poles 4

    Voltage 3300V

    Frequency 50Hz

    Current 98A

    Power factor 0.89Type of construction IEC-34

    Power rating 445kW

    Connection Y

    Temp. risk limit normal 70 0C

    RPM 1430

    The pulverized coal from the BTM is fed to the boilers with the help of primary air fans.

    The coal is burnt in the boiler to generate steam to move the turbines. The forced and

    induced draft fans are used to assist in the combustion of fuel and steam production.

    These two major types of fans supporting the units operation.

  • 8/10/2019 NFL-Bathinda Final.docx

    20/65

    20 | P a g e

    FORCED DRAFT FAN

    The forced draft fans supply the proper amount of secondary air required to support the

    combustion of the fuel delivered to the boiler. The details of the FD fan are:

    Make MEIDEN

    Rating Continuous

    Insulation class F

    Rated power 320kW

    Voltage 3300V

    Power factor 0.85

    Current 71A

    RPM 980

    Poles 6

    Connection Y

    CAPTIVE POWER PLANT

  • 8/10/2019 NFL-Bathinda Final.docx

    21/65

    21 | P a g e

    INDUCED DRAFT FAN

    The induced draft fans control the furnace draft by drawing the gases of combustion

    through the boiler, regenerative air heaters, delivering them to the stack. Thus the FD fan

    provides combustion air for the furnace while the ID fan removes flue gases from furnace

    through chimney. The details of the ID fan are:

    Make MEIDEN

    Rating continuous

    Insulation class F

    Rated power 295kW

    Voltage 3300V

    Power factor 0.83

    Current 67.5A

    RPM 735

    Poles 8

    Connection Y

    POWER GENERATION

    In C.P.P. two generators of 15MW capacity generate a voltage of 11KV which is fed to

    the two transformers in the yard. The rating of the transformers is 31.5/25 KVA, these

    two values depend upon the cooling which we provide, as here 25KVA capacity is when

    cooling is oil natural air natural and 31.5KVA capacity is when cooling is oil natural air

    forced. Both these transformers step up the voltage level to 132KV. From the

    transformers the three phases pass through the lightning arrestors (LA). After this they

    pass on to the isolator. After this the two lines pass on to the TRANSMISSION pole

    called DOUBLE CIRCUIT TRANSMISSION. Then these lines go to the M.R.S. i.e.

    main receiving station.

  • 8/10/2019 NFL-Bathinda Final.docx

    22/65

    22 | P a g e

    TURBINE

    The turbine used is supplied by M/S SGP of AUSTRIA. It is condensing cum

    extraction turbine designed as single casing reaction turbine with single control stage and

    high pressure (HP), mild pressure (MP) and low pressure (LP) reaction parts.

    The turbine is fed with high pressure steam at 100kg from boiler and flows through

    various control valves for normal and emergency operation. It gets high velocity through

    the nozzle group and then passes over the impellers fixed on to the rotor and fixed

    diffusers thus rotating the turbine. The enthalpy of steam is utilized in steps. Steam is also

    extracted from various stages. HP 1 at 10.4kg/cm 2, HP 2 at 8.1kg/cm 2, feed water bleed at

    4.3kg/cm 2 and LP bleed at 0.9kg/cm 2.

    The exhaust steam from the turbine is condensed in a condenser maintained under

    vaccum to extract maximum steam enthalpy. The output of the turbine depends on flow

    of steam and heat difference that is on condition of steam at the main steam valve and the

    pressure at the turbine outlet or condenser pressure. The turbine is connected to the

    generator through speed reducing gears.

    The exhaust steam is condensed in a condenser using cooling water. The resultingcondensate can be fed back to LP heater but is normally sent to the polishing water plant.

    As shall be clear from the attached block diagram various bleeds from the turbine are

    utilized for heating purpose. HP 1 and HP 2 are used for heating boiler feed water in HP 1

    and HP 2 heaters. Feed water bleeds is used for heating the feed water tank and LP bleed

    is used for heating the polish water make up to the feed water tank.

    A lubrication system is also there to lubricate the various bearings of the turbine, gears

    and generator. Normally the oil pump driven by the turbine shaft supplies oil but

    auxiliary motor driven pumps are used for start up and during shutdown. A turning gear

    has been provided for slow cooling of turbine rotor.

  • 8/10/2019 NFL-Bathinda Final.docx

    23/65

    23 | P a g e

    Latest instrumentation has been used in this plant. Baileys net work -90

    microprocessor based instrumentation system is being used. The NETWORK 90

    SYSTEM is a distributed process control system. Using a series of integrated control

    nodes. The network 90 system allows controlling process variables like flow, pressure

    and temperature according to a control configuration. There is operator interface unit

    (OIU) like a TV screen on which various parameters can be displayed and controlled. It

    allows fully automatic start-up/shut-down of boiler, turbine and other auxiliaries.

    DESCRIPTION

    Make Simmering Graz Panker, Austria

    Type Multifunction (28 stages)Capacity 65 T/H at 15 MW

    RPM 6789 at 50 Hz

    Critical speed 3200-3600 RPM

  • 8/10/2019 NFL-Bathinda Final.docx

    24/65

    24 | P a g e

    UREA PLANT

    In this plant 1500 metric tons of uncoated pilled urea per stream day are produced by

    signal train wing

    The plant can be divided into four sections:

    Synthesis Section

    Decomposition Section

    Recovery & Crystallization

    Prilling section

    Different steps being carried out in these sections for urea production can be described as

    follows:

    SYNTHESIS SECTION

    In MITSUI TOATSU TOTAL RECYCLE C IMPROVED PROCESS liquid

    Ammonia is recycled since it is easier to handle but require equipments like Rectification

    Column storage tanks etc. and higher capacity liquid Ammonia pumps.

    In this section, urea is synthesized in urea is synthesized in urea reactor CO2 is

    received from Ammonia Plant at a pressure of 0.2 kg/cm2 and 20oC and is compressed in

    a Centrifugal booster compressor, UGB-101 to 32 kg/cm2 in a 3 stage unit. The

    Compressor supplied by M/s BHEL has a normal capacity of 25256 NM3/hr and has 2 barrels 2 M.C.L. 805 and MCL 455. The drive of the Compressor is a extraction and

    condensing type of steam turbine supplied by M/s BHEL. The turbine is driven by 40K

    super-heated steam and has a rated output of 5792 KW.

  • 8/10/2019 NFL-Bathinda Final.docx

    25/65

    25 | P a g e

    U R E A S Y N T H E S I S

    2NH 3 + CO 2= NH 2 COO NH 4 H = - 37.64 Kcals.(i)

    NH 2COO NH 4= NH 2 CO NH 2 + H 2O, H = 6.32 Kcals..(ii)

    Where as reaction (i) is exotheromic and rapidly goes to completion (ii) is

    endothermic and is always incomplete. The overall reaction is exothermic and hence heat

    has to be removed continuously for the equilibrium reaction to proceed. The conversion

    of ammonium carbamate to urea depends upon:

    i) Reaction temp. and pr.

    ii) Mol ratio of NH 3/CO 2, H2O/CO 2 of the feed reactants.

    iii) Residence time

    The conversion increases with the increase of temp. NH 3/CO 2 ratio and residence

    time and decreases with H 2O/CO 2 ratio since the presence of water tends to shift reaction

    (ii) in the backward direction. The Pr. employed depends on the reaction temp. and has

    to kept higher than the dissociation pressure of ammonium carbamate at that temp.

    Further since the dehydration of ammonium carbamate to urea takes place in Liq. phaseonly, the Pr. employed must also be higher than the Vap. Pr. of ammonium carbamate

    which is rather high.

    Higher ratio of NH 3/CO 2 increases conversion and helps to minimize corrosion. As

    this ratio increases the load on recovery section increases since excess NH 3 over

    stoichiometric requirement has to be recovered and recycled back to reactor. This excess

    Ammonia can either be recycled as (a) Liq. NH 3 or (b) carbamate, in which case it

    becomes necessary to inject CO 2 into carbamate condensers.

    The compressed CO 2 is washed with water in a packed bed tower called methanol

    Absorber for removal of entertained methanol in CO 2 which is normally 1000 ppm. The

    washed CO 2 is further compressed to a pressure of 260 kg/cm in a two stage compressor,

  • 8/10/2019 NFL-Bathinda Final.docx

    26/65

    26 | P a g e

    UGB-102 supplied by M/s KOBE STEEL, JAPAN. This reciprocating Compressor has a

    normal capacity of 26260 Nm/hr and is driven by a 2.2 MW Synchronized motor. Anti

    corrosion air at the rate of 65 Nm/hr is fed to CO 2 at the suction of Centrifugal CO2

    Booster Compressor.

    Liquid Ammonia at 11 C and 18 kg/cm pressure is received in the Ammonia

    Reservoir, UFA-401 from the Horton Sphere. Ammonia Booster Pump UGA-404 A & B

    booster the pressure of the feed pumps UGA-101 A D. The Ammonia Feed Pumps are

    of URACA MAKE driven by 3.3 kV/450 KW and have capacity of 53.2 m/hr., 178

    RPM and 89% efficiency. The ammonia feed pumps deliver the liquid ammonia at 260

    kg/cm to Ammonia Pre-heater. The pre-heated ammonia at 65 C is fed to the Urea

    Reactor at bottom.

    The Recycled Carbamate solution of CO 2 concentration, 7.5 Lit per 25 ML, at 105 C

    and 260 kg/cm pressure is delivered to the Urea Reactor at bottom by Recycle

    Carbamate Solution Pumps UGA-102 A & B. These pumps are centrifugal type and are

    driven by backpressure steam turbine, supplied by M/s EBARA of Japan and have

    capacity of 81 m/hr.

    The three feeds i.e. CO2 liquid Ammonia and Recycled pump solution are fed to a Ti

    lined multi wall Urea Reactor. The Urea Reactor is a multi wall shell having wall

    thickness of 37mm x 4 = 148mm as thickness. Ti liner thickness is 6mm from bottom to

    7900mm, 5mm upto 3950mm, 4mm for next 3950mm and 3mm for rest height. Top and

    bottom dish end cladded Layer Urea Reactor. The Urea Reactor is a 12-layered C.S.

    vessel with Ti Liner thickness of 5 mm, 4 mm and 3 mm for the 1/6, 1/6 and 2/3rd of

    total height of the Reactor from Bottom. The Reactor top temperature is maintained at

    200 C maximum. The effluents from Urea Reactor from top are let down to 17.5 kg/cm

    pressure through a pressure control valve PCV-101 and fed to the high pressure

    Decomposer at 124 C.

  • 8/10/2019 NFL-Bathinda Final.docx

    27/65

    27 | P a g e

    DECOMPOSITION SECTION

    MISTSUI TOATSU TOTAL RECYCLE C IMPROVED PROCESS is a conventional

    process.

    The decomposition reaction, NH 4 COO NH 2-------2NH 3 + CO 2 is favoured by lower

    pr. of system or by low partial pr. of one of the reaction products i.e NH3 and CO2.

    Conventional Process mean the process where decomposition is affected by lowering in

    pressure in successive stages followed by indirect heating whereas the processes where

    decomposition takes place by lowering the partial pr. of either NH 3 or CO 2 followed by

    indirect heating are called STRIPPING PROCESSES.

    The Reactor effluents at 17.5 kg/cm and 124 C enters the upper part of High

    Pressure Decomposer UDA-201 having 4 sieve trays at upper and falling film heater at

    lower section. The flashed gases go up and liquid flows down through sieve trays. On

    trays the high temperature gas from Reboiler, U-EA-201 and falling film heater contacts

    with the liquid flowing down. The sensible heat of gas and heat of condensation of water

    vapour are used to evaporate the excess ammonia and to decompose the carbamate.

    This helps in minimizing water evaporation and thus reducing water recycle to

    reactor. The Reboiler further heats the liquid by 12 kg/cm steam to release excess

    ammonia and carbamate as gases. The temp. at middle is maintained at 151 C by a

    temperature control valve TCV 201. The temp. at bottom is maintained at 165 C

    through TCV-202. The falling film heater is used to minimize residence time in order to

    reduce Biuret formation and hydrolysis of urea.

    Anti corrosive air is fed to high Pr. Decomposer and Reboiler through air compressor

    UGB-201 @ 2,500 ppm as air. Overhead gases from HD are absorbed in HAC (High

    Pressure Absorber Cooler). The bottom liquid flows to L.D. (Low Pressure decomposer)

    at 2.5 K, 145 C Upper Part, having 4 sieve trays. A similar phenomenon occurs in the

    low Pr. Decomposer. The Reboiler UEA-202 provides heat using 7 kg/cm steam for

  • 8/10/2019 NFL-Bathinda Final.docx

    28/65

    28 | P a g e

    decomposition and hot stream from H.D. heats up solution from LD in a Exchanger

    before entering the upper part. The t emperature is maintained at 130 C at middle by

    TCV-203. Small amount of CO 2 is fed below packed bed for improved stripping of

    decomposed gases. The over head gases from low Pr. Decomposer are absorbed in low

    Pressure Absorber U-EA-402. Bottom liquid flows to 3rd stage of Decomposer called

    Gas Separator U-DA-203. The upper part o f gas Separator operates at 106 C, 0.3 K and

    lower part with packed bed operates at 92 C and atmospheric pressure. The sensible heat

    of solution from low pressure decomposer is enough for evaporating the over head gases.

    In the lower part air, containing trace amount of NH and CO 2 is blown under the packed

    bed, by off gas recycle blower UGB-401. The Urea solution is concentrated to 70 72%

    and sent to crystallization section.

    CRYSTALLIZATION AND PRILLING SECTION

    The Urea solution obtained from the last Decomposition stage i.e. Gas Separator contains

    27% H 2O since for every mole of urea one mole of H 2O is formed. Urea has to be

    concentrated to 99.5% before prilling.

    MTC C- IMPROVED PROCESS employes Crystallisation remelt Prilling route

    and uses spray nozzles for prilling. The prilling tower is of induced draft type.

    The solution from Gas Separator enters lower part of Crystallizer, U-FA-201. The

    upper part is vacuum concentrator with two stage ejectors and Barometric condenser.

    In Vacuum concentrator, operating at 75 m m Hg and 60 C, water is evaporated and

    supersaturated urea solution comes down through barometric low into the crystallizer,

    where Urea crystals grow. The heat required for water evaporation comes from:

    i) Sensible heat of feed urea solution.

    ii) The heat of urea crystallization

  • 8/10/2019 NFL-Bathinda Final.docx

    29/65

    29 | P a g e

    iii) Heat recovered by urea slurry circulated through High Pressure Absorber.

    The Crystallizer is operated at 60 C and atmospheric pressure, so that slurry

    leaving the bottom contains about 30-35% urea crystal by weight.

    Hot water from hot water pump is used in jackets of crystallizer and pipe to avoid

    crystal build up on vessel walls, which may cause choking otherwise.

    The urea slurry is pumped from Crystallizer bottom to Centrifuges U-CF-201 A-E

    (1000 rpm, 43 Te/hr of slurry ) maintaining minimum recirculation to Crystallizer to

    prevent chocking of lines.

    Biruate remains with mother liquor, which after separation from the urea crystals in

    the centrifuges is recycled back to the system. Because of excess ammonia in reactor

    biurate, thus recycled is converted back to Urea.

    NH 2CO NH CO NH 2 + NH 3 ------- 2 NH 2 CO NH 2

    (Biuret )

    Urea crystals separated from slurry with 2 4 % moisture are discharged to

    fluidising dryer UFF-301 at 110 C. The mother liquor flows down to Mother Liquor

    Tank, provided with steam coils. Mother Liquor is pumped back to crystallizer via LCV-

    207. A part of mother liquor going to low Pr. absorber has been cut off and instead dust

    chamber overflow solution has been lined up.

    Air is blown from Blower U-GB-301 ( 82360 NM3/hr) and heated to 110 C in air

    heater. This hot air dries the crystals to 0.1 to 0.3% moisture content. Dried crystals are

    conveyed by a pneumatic duct to cyclones at the prilling tower top. The collected

    crystals are melted in melter ( 137 C ) and Urea melt is sprayed through 12 Nos. acoustic

    granulators. Prills are cooled in fluidizing bed called CFD, installed a the Prilling Tower

    Bottom. Air/cyclone is scrubbed for urea dust in dust separators (2 Nos.). Air containing

  • 8/10/2019 NFL-Bathinda Final.docx

    30/65

    30 | P a g e

    Urea dust from P.T. column is scrubbed with water and passed through 144 sets of

    polyurethane filters before exhaust to atmosphere to reduce air pollution.

    INSIDE PRILLING TOWER

    RECOVERY SECTION

    The gases from Gas separator are condensed in off gas condenser UEA-406 to 62 C

    and enter the bottom of off gas Absorber DA-402 (OGA). Condensed liquid flows down

    to off Gas Absorber Tank UFA- 203. After cooling to 36 C, liquid is sent to top portion

    of OGA as absorbent. OGA bottom fluid is recycled as absorbent at OGA middle

    position (2nd bed).

    Air from top of OGA is blown to gas Separator by GB-401 Blower. The gases from

    Low Pr. Decomposer are absorbed in Low Pr. Absorber (EA-402) bubbling a Sparger.

    Dust Chamber over flow solution (10-15% Urea) is used as absorbent. Low Pr. AbsorberTemp. is controlled at 45 C and CO2 concentration 2.2 Lit/25 ml.

  • 8/10/2019 NFL-Bathinda Final.docx

    31/65

    31 | P a g e

    Solution from L.A. is pumped by GA-402 A/B to High Pr. Absorber (DA-401)

    middle through mixing cooler where liquid ammonia is mixed and serves as medium in

    the absorber.

    The gases from HD top are bubbled through a sparger in High Pr. Absorber cooler

    EA-401, where 65% of CO 2 is absorbed. Remaining gases from HAC go to HA and are

    cooled down to 80 C max. in middle cooler at the bottom of H.A. 35% CO 2 is absorbed

    in packed bed by a mixture of lean carbamate from Low Pr. Absorber through FCV-401

    and liquid ammonia from GA-404 A/B (Temp. 60 C max) through FCV-402. The

    scrubbed gas then passes through five Nos. of bubble cap trays in order to absorb residual

    CO 2 by a mixture of aqueous ammonia (GA-405 A/B) and liquid ammonia (GA-404

    A/B) through FCV-403. Ammonia gas from High Pr. Absorber, Temp. 50 C is pure andcondensed in five Nos.of condensers (EA-404 A-E) and purge condenser EA-403.

    Liquid Ammonia flows down to Ammonia Reservoir FA-401. Non-condensable gases

    (inerts mostly) flows to Ammonia Recovery Absorber (EA-405 1 to IV). Recovery loop

    pressure is controlled by PCV-405 (16.5 17.5 K) at top of EA-405 IV. Cold steam

    condensate is fed (FCV-408) for absorption. Aqueous ammonia is with drawn from

    Recovery Absorber Bottom by GA-405 A/B.

  • 8/10/2019 NFL-Bathinda Final.docx

    32/65

    32 | P a g e

    IMPROVEMENTS CARRIED OUT FOR AUGMENTATION OF

    PLANT CAPACITY

    Urea plant at Bathinda has a rated capacity of 1550 Te/day. With retro fittings and

    innovative operational practices, the plant is being run at 105-110% on consistent basis.

    The retro fittings carried out are listed as under:-

    1) CO 2 Booster Compressor

    1. The capacity was increased by 3200 Nm/hr by increasing the suction pressure

    from 0.08 kg/cm to 0.18 kg/cm.

    2. The suction header from Ammonia Plant has been provided with insulation so as

    to deliver the CO 2 gas to Booster suction a t a temperature approximately 6 C

    lower than the normal value.

    2) Ammonia Booster Pumps

    Impeller dia of the booster pump was increased from 284 mm to 310 mm and the

    motor rating changed from 52 KW to 72.5 KW, the delivery flow of the booster pumps

    increased by 10%.

    3) Ammonia Recovery System

    1. The capacity of ammonia pump UGA-405 was increased from 8.0 m/hr to 18

    m/hr.

    2. The material of construction of recovery absorbers tubes changed from carbon

    steel to S.S.

  • 8/10/2019 NFL-Bathinda Final.docx

    33/65

    33 | P a g e

    4) Prilling Section

    1. The conventional spray nozzles for molten urea changed to Accoustic

    Granulators. This has improved the product quality considerably.

    2. Secondary air flow increased by removing obstructions on air path.

    3. Water spray system provided for cooling ambient air during summer months at

    the inlet of CFD Blower.

    The innovative operational practices introduced is :

    Utilisation of Dust Chamber Over-flow solution

    The process route of utilization of dust chamber over flow solution via gas separator

    has been changed to via low-pressure absorber. This has contributed in increase in

    production of about 9 Te/day.

    WATER AND POLLUTION

    AIR POLLUTION

    The sources of air pollution in urea plant is the air from prilling tower which is the

    process of cooling of molten urea being sprayed from the top of the tower gets

    entertained with urea dust. In order to contain the urea dust emissions in the Exit air, the

    air is scrubbed with water and subsequently passes through 144 polyurethane filters

    before being discharged to atmosphere. The normal emission level in the exit air is 30-40

    mg/Nm against the prescribed norms of 50 mg/Nm.

  • 8/10/2019 NFL-Bathinda Final.docx

    34/65

    34 | P a g e

    LIQUID POLLUTANTS

    The sources of liquid pollutants in Urea Plant are :-

    i) Dust Chamber over-flow solution

    The over-flow dust chamber is being completely utilized after introduction of

    innovative operational practice mentioned above.

    ii) Dilute urea solution during start-up and shut-down of plant

    To take care of the dilute urea solution during start-up and shut down of the plant 3

    SS Tanks of 100 m, 100 m and 200 m capacity have been provided. The three tanks

    are equipped with steam coils for concentration of the Urea solution. The solution, thus

    stored, is reprocessed after the plant conditions are normalized.

    iii) C.F.D. Washing

    The frequency of CFD Washing is 1 months during summer months and threemonths during winter months. The washed water from CFD containing urea is stored in a

    pacca solution pit of 250 m capacity. This pit has been provided with a pump and the

    stored solution is reprocessed during normal operation of the plant.

    iv) Leaks from pumps and effluents generated during flushing of strainers:

    The pollutants generated are diverted to a effluent pit.

    The effluent is subsequently sent to the Bio Urea Hydrolyser in the Effluent

    Treatment Plant for Hydrolysis of the Urea.

  • 8/10/2019 NFL-Bathinda Final.docx

    35/65

    35 | P a g e

    HYDROLYSIS OF UREA

    In aqueous solution, urea is sufficiently stable upto 80 C. Above that temp. it

    changes into Ammonium isocyonote and subsequently into ammonium carbonate.

    CO (NH 2)2 = NH 4 NCO

    NH 4 NCO + 2 H 2O = (NH 4)2CO 3

    Which changes into ammonium hydro-carbonate and this ultimately dissociates into

    ammonia and carbon-di-oxide.

    (NH 4)2 CO 3 = NH 4 HCO 3 + NH 3

    NH 4 HCO 2 = CO 2 + H 2O + NH 3

    The overall hydrolysis reaction is shown by the equation:

    (NH 4)2 CO 3 + H 2O 180 C 2NH 3 + CO 2

    NFL has been the market leader for manufacturing and marketing of Urea. The

    capacity utilization during the year 2004-2005 has been 106.2%.

  • 8/10/2019 NFL-Bathinda Final.docx

    36/65

    36 | P a g e

  • 8/10/2019 NFL-Bathinda Final.docx

    37/65

    37 | P a g e

    OFFSITES AND UTILITIES PLANTS

    D.M. WATER PLANT

    Water in its natural form contains a no. of dissolved salts such as sulphates, chlorides

    and Nitrates of calcium Magnesium and Sodium. If water is used as such in Boilers for

    raising steam, these salts will form scale on the tubes , which in addition to heat losses

    leads to many other problems. Hence, removal of these salts from the water becomes

    quite essential. ION exchange resins are used for this purpose of salts removal.

    The deminerlising water plant of NFL Bathinda was supplied by M/s ION

    Exchange (India) Ltd. Delhi.

    It consisted of Four units each of Cation, Anion, Primary Mixed bed, and Six

    secondary Mixed Bed and three units of condensate cation. At the time of setting up of

    captive power plant, another stream to augment the existing capacity of Polish Water

    generation was installed by M/s BPMEL. It consisted of one unit each of cation, Anion,

    Primary Mixed Bed, two secondary mixed beds and two condensate cations.

    Filtered water is received from Raw Water Filtration Plant into two filtered water

    reservoirs Feed water pumps discharge water from these reservoirs to cation units. There

    are total five feed water pumps each having a capacity of 130 m/hr and four cation units.

    Three of these are charged with 13125 litres of cation resin and fourth unit is having

    11900 of resin. Cationic lons like Na+, Ca++ and Mg++ present in the water are removed

    in the CATION UNITS Once exhausted, these units are regenerated with the counter

    current flow of dilute sulphuric acid.

    The present day resins are made of cross linked polystyrene and cross linking is

    done by Di-vinyl Benzene.

  • 8/10/2019 NFL-Bathinda Final.docx

    38/65

    38 | P a g e

    Cationic resins are made of sulphonated Polystyrene SO 3 H+ can be represented as RH+ .

    Anionic resin is similarly made but is chloromethylated and then aminated. The final

    product is quarternary ammonium compound a strong base and is represented by ROH.

    C A T I O N U N I T

    In the cation unit free H+ lon of the resin is replace by Ca++ . Mg++ or Na+ lons

    as per the following reactions:

    RH + NaCl = RNa + HCl

    2RH + Mg SO 4 = R 2Mg+H 2SO 4

    2RH + Ca (HCO 3)2 = R 2Ca + 2 CO 2 + 2 H 2O

    Neutral salts are converted to respective mineral acid and alkaline salt spilt into

    CO 2 gas. The outlet water will have a low pH.

    D E G A S S E R

    From the cation units water move to degasser. Here free CO 2 content of the

    water is stripped off with the help of air by passing the water over rasching ring packed

    bed. Water from Degasser is received into three Nos. degassed water sumps each having

    a capacity of 40m. From these sumps degassed water pumps discharge water into anion

    units. There are total five Nos. of pumps and each having a capacity of 150 m/hr.

  • 8/10/2019 NFL-Bathinda Final.docx

    39/65

    39 | P a g e

    ANION UNITS

    Anionic impurities of water besides CO2 and Silica are removed in the Anion

    Units. There are total four nos. of Anion Units. Two; units are having 7920 Ltrs. Of

    resin while rest of the two are having 5965 and 8400 Ltrs. Of resin. Anions present in the

    water get removed as per the following reactions :

    2 ROH + H 2SO 4 = R 2 SO 4+2H 2O

    ROH+HCl = RCl+H 2O

    2 ROH + H 2SiO 3 = R 2 SiO 3 + 2 H 2O

    Once the unit gets exhausted, it is regenerated with counter current flow of 4%

    NaOH solution.

    M I X E D B E D U N I T S (PRIMARY)

    Certain amount of sodium and silica ions gets slipped from cation and anion units.Very large volume of resin is required to check these leakage if tackled individually.

    Hence, these are removed in mixed bed units. It consists of a bed of mixed cation and

    anion resins which acts as infinite pairs of cation and anion units.

    A mixed bed unit will produce water of conductivity around 0.5 micro mho/cm. This

    water is stored in DM water tanks. These are two Nos. of DM water tanks each having a

    capacity of 1500 m. 1400 Ltrs. Each of cation and anion resin is charged in three mixed

    bed units while in fourth unit this quantity is 1800 Ltrs.

  • 8/10/2019 NFL-Bathinda Final.docx

    40/65

    40 | P a g e

    C O N DE N S A T E C A T I O N U N I T S

    Steam condensate is received from Ammonia, Urea and CPP. It contains lonic

    and colloidal iron. Colloidal iron is removed in colloidal filters while ionic iron is

    removed in condensate cation units. Condensate coming from Ammonia and Urea Plants

    is first cooled to around 45OC in condensate cooler. There are total five Nos. of

    condensate cation units. Three units are charged with 1810 Ltrs. Of resin while two are

    charged with 4200 Ltrs. Of resin. After polishing the condensate it is stored in DM

    Water Tanks.

    SECONDARY MIXED BED UNITS

    DM Water from DM water tank is pumped to secondary mixed bed units with the

    help of DM water pumps, for achieving the desired level of purity of water there are total

    5 Nos. of pumps and each having a capacity of 190 M3/hr.in the secondary mixed bed

    units final traces of impurities are removed again with the help of mixed bed of cation

    and anion resins. There are total six Nos. of these units. Four of these are charged with

    1400 Ltrs. Of cation resin and 2200 Ltrs.of ANION Resin while rest of the two are

    charged with 1600 Ltrs.and 2600 Ltrs.of cation and anion resins. After passing throughsecondary mixed bed units polish water of following specifications is obtained.

    PH : 7 +_ 0.2

    Conductivity : 0.2 Micro mhos/cm

    Total iron as Fe : 0.015 mg/lit

    Silica : 0.015 mg/lit

    Hardness : Nil.

    Polish water thus obtained is stored in Polish Water Tanks. There are two polish

    water tanks each having a capacity of 1500 M3. It is pumped to Ammonia Plant and

    Captive Power Plant with the help of five Nos. Polish water pumps each having a

    capacity of 220 M3/hr.

  • 8/10/2019 NFL-Bathinda Final.docx

    41/65

    41 | P a g e

    FLOW DIAGRAM OF DEMINERALIZATION OF WATER

    COOLING WATER SYSTEMS

    The cooling water systems provided at NFL Bathinda are closed recirculating type

    supplying cooling water to various consumers in the plant. There are total three systems

    supplying cooling water to different sections as mentioned:

  • 8/10/2019 NFL-Bathinda Final.docx

    42/65

    42 | P a g e

    Emergency cooling water pump is in continuous service for ammonia storage area. It

    takes suction normally from CT -2; however, provision is there so that it can take suction

    from CT-1

    DESIGN BASIC

    Barometric pr. 971 millibars

    Dry bulb temp. 39 0C

    Wet bulb temp 28 0C

    Degree of approach 5 0C

    Relative humidity 81.1% at 31.4 0C

    Various other design conditions for all three cooling water systems are given below;

    SI no. System Consumer

    1. CT-1 Ammonia plant

    2. CT-2 Urea plant, boilers,

    instrument air

    compressors, service air

    compressors, caustic

    dissolving facility and

    sulphur recovery plant

    3. CT-3 Crystallization section of

    urea plant

    4. Emergency pumps (

    can be connected

    with CT-1 or CT-2)

    Ammonia storage area,

    instrument air

    compressors emergency

    diesel set

  • 8/10/2019 NFL-Bathinda Final.docx

    43/65

    43 | P a g e

    INSTRUMENT AIR COMPRESSOR HOUSE

    There are four compressors of reciprocating type. Air is sucked from atmosphere and

    fed to L.P. stage. Air is compressed at 2.4 Kg & sends to H.P. stage after passing through

    intercooler where air compressed up to 9Kg. This air is cooled to - 15 C. It is oil and dust

    free.

    PERFORMANCE:

    TYPE KIRLOSKAR, HITACHI

    MODEL TC-BTD-AH

    CYLINDER BORE X No.

    FIRST STAGE 487mm

    SECOND STAGE 267mm

    STROKE 200mm

    SPEED 590RPM

    CAPACITY

    At suction conditions 1884mc/Hr At 600 RPM

    Suction pressure 0.99 Kg/cm

  • 8/10/2019 NFL-Bathinda Final.docx

    44/65

    44 | P a g e

    BAGGING PLANT

    The Bagging Plant can be divided into two main sections:

    1. Storage System

    2. Reclamation System

    Under Storage system, 3 conveyors, come, namely; PJD-101, PJD-102, PJD-103,

    PJD-103 is the over head conveyor inside silo. One tripper is provided over PJD-103

    which can be placed at any convenient position depending upon the requirement. By

    means of the tripper, the material can be poured over any vibrofeeder desired. Tripper is

    designated as PJD-104.

    The reclaimation system comprises six electro magnetic vibrofeeders, seven No.

    of belts conveyors namely PJDs 106, 107,109, 109A Seven No. of weighing machines,

    stitching machines & loading platform namely A-0 A-1,A-2, B-1, B-2, C-1 and C-2. In

    addition to these there are 3 bunkers / platform, one empty bag storage and one filled

    bags storage. By operating flap gate No. 102, the material can be directly fed to PJD-107

    without taking it to silo.

    The plant has a capacity to load 2250 Te/day of packed material either in Road

    Wagons or Road Trucks or in both. The loading platforms can accommodate seven

    trucks at a time or three and half BCN Type wagons or 7 CRT type wagons.

    The weighing machines are microprocessor based and have speed of 12 to 14

    bags per minute. The machines run with an accuracy of +- 50 grams. The system of

    counter checking of weight of filled bags is rigorously followed to ensure correct

    weightment.

  • 8/10/2019 NFL-Bathinda Final.docx

    45/65

    45 | P a g e

    The plant is provided with a Central Control Room from where the system is

    started or stopped. The two systems of Storage and Reclaiming are separately provided

    with safety inter-locks to trip the belts in case one belt in the link trips.

    The Urea silo is designed to accommodate 30 days production. For reclaiming

    Urea from silo, front end Pay Loaders are used.

    The plant is also provided with an empty bag Storage and over-head E.O.T. crane

    for shifting the bags from the storage to the loading platform.

    The filled bags storage is provided for stacking the filled Urea Bags.

    Both jute and HDPE bags are used for filling of product Urea. The stitching

    thread used is poly thread is used.

    The consumption of bags is approximately 104 lakhs per annum and of thread

    41600 KMs.

    Normally two operators, one Heavy Equipment Operator, 7 stitchers, 7 fillers and

    28 loaders besides sealman and weight checking staff are deployed every shift. The Shift

    Engineer coordinates the operational activities of the plant and also coordinates with the

    Transportation Section for the movement of finished goods.

    The spilled urea or the urea from the ruptured bags is recycled back to the system

    by 2 bucket elevators, which transport the material from the loading platform to the

    Conveyor PJD-109.

    Normally Loco-motive is used for shunting of Rail wagons. However, a winch is

    also provided to take care of exigencies when the loco-motive is not available.

  • 8/10/2019 NFL-Bathinda Final.docx

    46/65

    46 | P a g e

    PROJECT REPORT

    Project Overview:The project gives the brief overview of the project and the main aim is to study about

    the description of existing VS new boilers and its accessories.

    BRIEF DESCRIPTION OF BOILERS AT BATHINDA UNIT

    The Steam generation plants at Bathinda unit have identical 3 nos pulverized coal tired

    boilers (VU-40 BHEL make) at each place with design capacity of I50 Te / hr of steam at

    pressure 105 ata & temperature 495 C. These boilers were commissioned in 1978.

    The Fourth boiler supplied by MES (MITSUI ENGINEERING & SHIPBUILDING CO.

    LTD.), Japan is designed to operate at MCR load (230 TPH) either with combination of

    coal & FO or FO exclusively. The boiler was commissioned in 1988. Fuel Oil is

    continuously used at optimum level as support fuel.

    DETAILS OF EXISTING BOILERS: MES Make Boiler: The Boiler (Mitsui-Riley RX type) is of two drums type with

    welded wall, radiant and conventional super heaters and economizer. The firing

    system is balanced draft type with forced draft fan and induced draft fan and main

    fuels are pulverized coal and FO / LSHS. The boiler is of natural circulation type.

    MES make boilers are equipped with DCS system (Bailey Japan (now ABB)make Network 90 with MFC 01 controllers and ABBs PPB system as HMI)

    for control of process parameters, electrical drives. BMS system is integrated into

    the same DCS. Trip interlock is realized through solid-state electronic system of

    M/s Bailey. All field instruments are electronic microprocessor.

  • 8/10/2019 NFL-Bathinda Final.docx

    47/65

    47 | P a g e

    EXISTING BOILER PARAMETERS

    Unit No. 4

    Make MES, Japan

    Boiler capacity (TPH) 230 SG

    Super heated steam outlet pressure 105 kg /cm

    Super heated steam outlet temperature 495 5 c

    Fuel Case I Variable Coal + Fixed FO

    Case II Variable FO up to 100% MCR

    No of Burners 14

    Main Burners 6 Dual Fuel Burners (Coal + Oil)

    Pilot Burners 6 (with LDO Firing)

    Start up Burners 2 (With LDO Firing)

    Year of Commissioning 1988

    TECHNICAL DATA OF 210 T / HR. CAP. FRONT FIRED

    PULVERISED FUEL FEED MESS BOILER.

    EXISTING TECHNICAL DATA

    BOILER / FURNACE UNIT

    Type Of Unit 1 Two drum natural circulation top supported.

    Type Of FURNACE Dry bottom front firing.

    Steam temperature control 2 stage spray control.

    DRUM

    Design Code IBR with amendments up to 1985

    Design Pressure (kg/cm2g) Steam Drum Water Drum

    124.0 124.5

    Overall length (Meters) 9.3 8.5

    (shell plate length) (7.2) (6.9)

    a. Number of Drums 1 1

  • 8/10/2019 NFL-Bathinda Final.docx

    48/65

    48 | P a g e

    b. Drum centre to centre distance 6.5

    Internal diameter (mm) 1630/1676 1181/1219

    (tube / shell plate side)

    Thickness of shell plate 148.7/102.8 108.8/71.2

    (min nished thickness)(mm) (tube / shell plate)

    Thickness of head plate 96 70

    Material IBR IBR REG 234-C. S-47

    (equivalent ASME) (ASME: SA-515 Gr.70)

    Minimum tensile strength 47

    at room temperature (kg/Sq. mm)

    0.2 percent proof stress 19.2at design temperature (kg/Sq. mm)

    STEAM SEPARATORS

    Type Cyclone and dryer carton

    Number 31 Cyclones and 32 dryer cartons.

    Arrangement Double sided in line

    Size overall diameter (mm) 255

    BOILER BANK

    1) Arrangement In line

    2) No of gas passes 1

    a. Heating surface (M2) Furnace 1250

    Bank 1000

    b. Furnace volume (M3) 990

    HEADERS

    Location Nos. Size Type Of Connection

    OD(mm)

  • 8/10/2019 NFL-Bathinda Final.docx

    49/65

    49 | P a g e

    a. Lower front Furnace 1 406.4 Welded

    b. Lower rear Furnace 1 406.4 Welded

    c. Lower sides Furnace 8 273.1 Welded

    d. Upper sides Furnace 8 273.1 Welded

    ECONOMISER

    Type Bare Tube

    Tube spacing(mm)

    a. Vertical 88.9

    (transverse to gas flow)

    b. Horizontal 63.5

    (Parallel to gas ow)

    Tube arrangement In-line

    Number of assemblies 28

    (transverse row to gas ow)

    Number of assemblies 44

    (Parallel row to gas ow)

    a. Direction of gas ow Down ow

    b. Direction of water flow Up ow Tube material IBR IBR REG 36/42-C, S -41/51-S-C

    (equivalent ASME) (ASME, SA-210 Gr. A1)

    Size of tube OD (mm) 63.5

    Heating surface m2 (approx) 1520

    Header diameter, Length and thickness(mm) 2 73.1 4740, 30

    SUPERHEATERS Design Code IBR with amendments up to 1985

    Design pressure (kg/cm2g) 124 LTSH ITSH HTSH

    a. Type Pendent Pendent

    b. Number of assemblies 7 38 38 19

    (transverse row to gas ow)

  • 8/10/2019 NFL-Bathinda Final.docx

    50/65

    50 | P a g e

    c. Number of elements per 66 24 8 8

    assembly

    (parallel row to gas ow)

    Flow Parallel Counter Combined

    a. Tube diameter (mm) 44.45 63.5 57.15 50.8

    b. Tube thickness (mm) 4.4 6.3 5.7 5.1

    c. Transverse pitch (mm) 812.8 152.4 152.4 304.8

    d. Longitudinal pitch (mm) 50.8 127 114.3 101.6

    Material IBRREG ASME ASME IBRREG

    (equiv. ASME} 56A-2.25 SA- SA- 56A- 2 .25

    CRIMO 213 213 CRIMO

    -39-S-C Gr. Gr. -39-S-C

    (ASME SA-213 T11 T11 (ASME

    SA-

    Gr, T22) 213 Gr,

    T22)

    No of groups 7 38 38 19

    (transverse row to gas ow)

    Tubes per group 66 24 8 8

    (transverse row to gas ow)

    DESUPERHEATER FOR SUPERHEATER a. Type of De-superheater Water spray

    b. Number 2 (1 SETS for 1st STAGE)

    (1 SET for 2nd STAGE)

    c. Material 11/4 Cr-1/2 M0 (ASTM A182 Gr. P11)

  • 8/10/2019 NFL-Bathinda Final.docx

    51/65

    51 | P a g e

    d. Necessary piping, valves Yes

    and ttings provided.

    e. Size (mm) 1st stage 2nd stage

    (inside DIA) 25.4 38

    REGENRATIVE AIR HEATER

    Type Ljungstrom

    Bearing Type & Size Thrust bearing 780 mm

    Basket material

    -cold end Corrsion Resistant Low Alloy Steel

    -Hot end Mild Steel

    Arrangement Vertical

    Number of passes 1

    Effective height of Cold end Hot end

    Baskets (mm) 300 1950 (2x975)

    Heating surface total 12340

    (approx) (m2)

    STEAM COIL AIR PREHEATER

    Type Fin Tube

    Aux_ Steam Parameters

    - Flow (kg/hr) 4010 (LSHS at 100% MCR)

    - Temp (C) 300

    - Pressure (kg/cm2) 11

    Construction details Welding Type (Header to tube)Overall size (mm) 2815L x 655W x 4245H

    Design Temperature (LSHS 30% MCR)

    - inlet (C) 30

    - Outlet (C) 100

    Heat transfer area 814

  • 8/10/2019 NFL-Bathinda Final.docx

    52/65

    52 | P a g e

    provided (m2)

    Tube outside dia x approx. 16 x 2 x 38

    Thickness x pitch

    (mm x mm x mm)

    FEEDERS

    Type and Make Type: Gravimetric feeder

    Make: Yamato scale Co., LtdCapacity max. 17 ton / h. feeder

    Overall dimensions 4.1L X 2.0w X 1.8w (m)

    Reference to dimensioned Ref. No. EO18

    sketch

    Construction materials Body: Carbon steel

    Inner surface Stainless steel

    Accessories provided Ref. No. EO18

    Motor rating, type make ditto and 0.75 KW for weighing conveyor

    0.40 KW for clean-out conveyor

  • 8/10/2019 NFL-Bathinda Final.docx

    53/65

    53 | P a g e

    DETAILS OF PROPOSED FUEL CONVERSION WORK FUEL

    CHANGEOVER FROM FO / LSHS TO NG / RLNG IN MES

    BOILERS (BOILER #4)

    The upgrade for fuel change over project of each plant broadly comprises of following

    sub systems:

    a. New Pulverized coal cum NG Fired Burners equipped with gas ignitor and flame

    scanner.

    b. Burner Register dampers (Manual operated / Auto operated Secondary air damper

    along with actuators.

    c. Modification of Wind box to install the new along with insulation and cladding.d. Burners throat refractory modification.

    e. NG Piping from pressure reducing station to Boiler #4.

    f. NG control station and field instruments for monitoring and safety shutdown.

    g. NG train to burners with safety shut off valve.

    h. NG piping for igniters / support firing.

    i. New DCS system for BMS and boiler operation and control.

    j. Cabling from field instruments of NG system to the new DCS panels.

    DETAILS OF PROPOSED FUEL CONVERSION WORK FUEL

    CHANGEOVER FROM FO / LSHS TO NG / RLNG IN MES

    BOILERS (BOILER #4) INSTALLED AT BATHINDA

    The upgrade for fuel change over project of each plant broadly comprises of following

    sub systems:

    a. New Pulverized coal cum NG fired Burners equipped with gas ignitor and flame

    scanner.

    b. Burner Register dampers (Manual operated) / Auto Operated Secondary air dampers

    along with actuators.

  • 8/10/2019 NFL-Bathinda Final.docx

    54/65

    54 | P a g e

    c. Modification of Wind box to install the new burners along with insulation and

    cladding.

    d. Burners throat refractory modification.

    e NG Piping from pressure reducing station to Bolier #4.

    f. NG control station and field instruments for monitoring and safety shutdown.

    g NG train to burners with safety shut off valves.

    h. NG piping for igniters / support firing.

    i. New DCS system for BMS and Boiler operation and control

    j. Cabling from field instruments of NG system to the new DCS panels.

    RECEIVING, INSPECTION, HANDLING STORAGE AND

    INSTALLATION INSTRUCTION OF NEW PC S TYPE

    BURNERS

    RECEIVING, INSPECTION AND HANDLING

    Conrm receipt of all equipment on each Bill of Material. A systematic inventory

    procedure for the storage area will facilitate retrieval and installation. Inspect the burners

    for damage upon receipt and prior to off- loading to storage. Conrm the bracing is in

    place and secure and that damage did not occur due to shifting in transit. Ln particular,

    inspect the linkages, operator handles, and pilot taps to conrm no pieces are bent or

    broken. Confirm the vane drive rings are properly arranged on the guides and have not

    moved during shipment.

    The PC S Type Burners are to be off-loaded into a suitable storage area using the lifting

    lugs. These components are shipped on pallets which are intended to protect the

    equipment during transport and storage, but the pallets are not suitable for lifting by

    forklift. Do not lift the burners or ports using the barrel stiffener bars or any other burner

    hardware except the lifting lugs.The burner weight is approximately 2200 kg, not including the actuator or burner elbow

    The burners should be left attached to their pallets to prevent damage to linkages, drive

    rings, etc. until immediately before lifting to install on the walls. lf for some reason the

  • 8/10/2019 NFL-Bathinda Final.docx

    55/65

    55 | P a g e

    pallet must be removed ahead of time, blocking must be used to prevent damage to

    components.

    STORAGE

    The PC S-Type Burners have the following short-term (3 months or less) storage

    requirements:

    a. The burners to be stored in such a manner as to protect them from water and dirt and to

    avoid damage from collision and falling objects or debris. They are to be left on their

    shipping pallets while in storage.

    b. All electrical and electronic equipment are to be stored indoors in a semi- controlled

    environment with a non-condensing atmosphere.

    c. All small loose pieces (bolts, nuts, clips, etc.) will be adequately prepared and packed

    for protection against rust and impact damage. These are to be stored in such a manner as

    to protect them from water and dirt, and to avoid damage from collision and falling

    objects or debris. These should be stored in their shipping containers until they are

    needed for installation.

    INSTALLATION INSTRUCTIONS

    General

    The following instructions describe procedures to remove PC fired burners and install PC

    S-Type Burners. Removal instructions are provided for future reference, for the unusual

    situation where removal is necessary to facilitate major maintenance or for burner

    replacement due to catastrophic damage of some kind. Installation instructions are

    provided as they combine with burner replacement. For initial burner installation as part

    of new boiler construction, installation will generally commence with item F. Consult the

    respective Erection Arrangement drawings for Erection Notes and further detailed

    information. The Erector is to determine the most suitable means of removing the

    existing burners and installing new burners. Each burner elevation and location needs to

    be checked, taking into account access and interferences with platform steel, building

  • 8/10/2019 NFL-Bathinda Final.docx

    56/65

    56 | P a g e

    steel, auxiliary equipment, steam piping, fuel piping, cable trays etc. The erector must

    identify and install new burners in their appropriate locations by burner or port number,

    as per General Arrangement drawings. Numbers are stencilled on each burner.

    Very important point : Prior and during the erection I installation of the burners please

    note to take Care regarding burner swirl orientation which is CW - Clockwise direction or

    CCW - Counter Clockwise Direction as per the burner drawings. The direction of burner

    orientation CW and CCW is to be ascertained by standing in front of the wind box on the

    firing oor prior to installat ion and carrying out full welding. Follow welding

    requirements in accordance with the drawings.

    BURNER DATA

    Size & Type of Burner 18" Coal Nozzle and 38" PC S-Type

    Emission Guarantees by Burner NA

    No. of Burners per boiler Six (4 Operating + 2 Standby)

    Capacity of each Burner (%MCR) 25%

    Type of air control & accessories Lead lag arrangement, FD fan Inlet guide

    Vane

    Burner Throat Dia, inch 38"

    Type & No. of Gas spuds One No. Super Spud (Main Spud)

    Construction of Spuds Fix SpudSwirler/ impeller information Impeller

    Burner turndown (Coal) 1: 2.25

    Burner turndown (NG/RLNG) 1:4

    Q Fired per Burner, Mkcal/hr 40.0

    Total Fuel (NG / RLNG) Fired, kg/hr 12550

    Fuel (NGI RLNG) Fired per Burner, kg/hr 3138

    Minimum Fuel (NG / RLNG) Fired per Burner,

    kg/hr

    785

    Burner Inlet Pressure during maximum Fuel

    (NG/ RLNG)Firing, kg/cm2

    0.7

    Burner Inlet Pressure during minimum Fuel

    (NG / RLNG) Firing kg/cm2

    0.05

  • 8/10/2019 NFL-Bathinda Final.docx

    57/65

    57 | P a g e

    Main NG Header Pressure Very High Trip

    kg/cm2

    1.5

    Main NG Header Pressure Very High

    Alarm,Kg/cm2

    1.4

    Main NG Header Pressure Very Low Trip

    Kg/cm2

    0.01

    Main NG Header Pressure Very Low

    Alarm,kg/cm2

    0.02

    NOTES:

    4 Burners (any two levels) may be operated during PC firing.

    Performance of PC Burners is subjected to Pulverized Coal size at the burner inlet as

    below

    99% passing through 50 mesh

    75% passing through 200 mesh

    Any four Burners in two elevation (Bottom & Middle) suggested to be operated during

    solo NG ring for the load range of 70% to 100% MCR. Based on the actual performance

    of the Boiler on solo NG firing (particularly the SH performance) the operation

    philosophy will be finalised and provided.

    NEW PC-S TYPE BURNERS

    INTRODUCTION

    The burners are of Babcock & Wilcox (USA) design. Type PC "S Type" with Central

    NG Gun Gas Spud, total 6 Nos. burners installed on each boiler, mounted two abreast

    endosed in the existing wind box which is mounted on the boiler front wall. the burners

    are dual fuel fired capable of firing Pulverized coal and Natural Gas up to 100% MCRSteam generation. The offered burner is proven and in operation world over supplied by

    Babcock & Wilcox(USA). The burners are Designed. Engineered and Manufactured by

    Thermax Limited Pune under the technology transfer agreement between the two

    companies The indnidual burners are designed to operate only as follows:

    a. Individual burners on Solo Pulterised Coal or Natural Gas firing.

  • 8/10/2019 NFL-Bathinda Final.docx

    58/65

    58 | P a g e

    b. Burners can be fired in combination firing mode with Natural Gas and Pulverised Coal

    together. Individual burners on Variable Pulverised Coal firing and Variable Natural Gas

    Firing (During Pulverised Coal firing the burners shall start in a pair only of the

    designated elevation selected by the operator)

    The burners have the capability to fire Pulverized coal equivalent to 100% steam

    generation by operating any 4 numbers (any two levels) with 25% NG support firing

    through the main NG burners i.e. Minimum 6.25% each burner capacity. It is always

    advice to keep the pilot burners firing NG in operation till PC firing is stabilised.

    Each PC S Type" bu rner is equipped to fire pulverized coal up to maximum rated burner

    input of 40.0 Mkcal/hr At this input the unit can be operated at maximum rated load withany two of the three mills in service while supplying pulverised coal to four (04) burners.

    The burners are installed and located in a common wind box. where secondary air

    admitted to the wind box is equally available to all the burners.

    Each burner is equipped with an FPS gas-fired igniter.

    GENERAL INFORMATION & DESCRIPTIONS

    GENERAL INFORMATION

    The PC S Type burner offers more reliable field performance through improvements in

    mechanical and functional design The PC S Type burner is ideally suited for front wall

    fired units The PC S Type burner provides for independent control of air flow and air

    turbulence to each burner. Secondary air flow to the burner is controlled by the positioing

    of an adjustable sliding damper installed at the entrance to the air sleeve.

    TO Provide proper mixing of the fuel and air swirl is imparted by means of adjustable

    spin vanes located in the air sleeve The burner orientations are as follows;

    CW Clockwise burner.

    CCW Counter clockwise burner

  • 8/10/2019 NFL-Bathinda Final.docx

    59/65

    59 | P a g e

    The orientation of the burner depends on the direction of opening of spin vanes. If the

    spin vanes are opening in the clockwise direction then the burner is CW and vice versa as

    viewed from boiler front/firing floor. An air flow monitor located in the air sleeve

    upstream of the spin vanes, allow for air measurement to individual burners and

    facilitates balancing of air flow on multi burner applications. Thus it provides a local

    indication of relative secondary air flow to facilitate sliding disk adjustment to balance

    SA among the burners. Hence individual burner combustion air differential pressures

    (Differential Pressure) "DP" can be measured in mmwc.

    SECONDARY AIR DISTRIBUTION AND CONTROL .

    Secondary air is provided from two FD fans (Existing) and is preheated initially in two

    Steam coil air preheaters (Existing) and later in common Regenerative Air Heater(Existing) Flow control of this air is provided by FD fan inlet Vane. Secondary air, along

    with primary air, is controlled to satisfy theoretical and excess air requirements for good

    combustion throughout the operating range during coal firing. The secondary air flow

    shall always be kept at 30% of the MCR air flow flowing through all the burners nearly

    equally during tho first light up or cold start of the boiler on NG firing with a single

    burner In addition. total boiler airflow is always maintained at or above 30% of full load

    air flow ensuring the total boiler airflow is always throughput which shall not be reduced

    below the purge flow rate of the boiler regardless of load.

    Hot secondary air (SA) entry from the air heaters flows toward the furnace through

    bottom portion of the wind box of the unit. Hot SA duct is equipped with an air flow

    (Existing) measuring device. The secondary air flow is subsequently distributed to the

    burners.

    The SA is freely admitted to the burner wind box and available to all burners in that wind

    box, SA flow to each burner is regulated by an automated pneumatic actuator device

    which controls the burner adjustable sliding air damper at the entrance to the air sleeve.

    SA enters the burner past the sliding air damper, continues through the burner throat

    adjustable spin vanes located in the airsleeve and exits through the burner throat into the

    furnace To provide proper mixing ol the fuel and air, swirl is imparted by means of

    adjustable spin vanes located in the air sleeves.

  • 8/10/2019 NFL-Bathinda Final.docx

    60/65

    60 | P a g e

    COAL FlRlNG 0PERATlON AND ADJUSTMENTS (EXISTING NFL SCOPE)

    The Pulveriser / Mill primary air damper controls the primary air flow rate to the burners,

    while the coal feeder controls fuel flow. The burner line isolation valves are intended to

    isolate the pulveriser and related equipment from hot furnace gases and provide rapid and

    positive fuel shut off. These valves should always be either fully Opon or fully cloud,

    They should never be used to adjust coal rate to the burners. The ratio of primary air to

    coal shall be [email protected] C, as well as the temperature of the mixture, is established to

    satisfy several pulveriser and burner requirements,

    Normal coal/air temperature exiting the pulveriser is about 79.50 C. Excessively hightemperatures lend to cause choking in the burner nozzle, and increase the Possibility of

    nozzle fires. Low temperatures can result in Insufficient drying of the coal, pulveriser

    choking and poor combustion. Operating with high primary airflow will tend to decrease

    coal fineness, adversely affecting combustion and increasing unburned carbon, High PA

    also increases erosion and can cause flame instability. Low primary air flow may result in

    plugged burner lines, burner line fires, dribble at the pulveriser, and poor coal distribution

    discharging from the coal nozzle.

    Natural Gas fired igniters are provided on the main burners and are of Continuous duty

    equivalent to 10,0% capa city of main burner These ignit ers are must to be kept in

    continuous services firing natural gas throughout the main PC burner operation on

    pulverized coal while the pulverised coal is being delivered from each pulveriser and

    burner, These igniters are firing natural gas as a support flame to the main pulversied fuel

    in order to be self sustaining and stabilize the main flames of pulverised coal at

    conditions when flames may not be self-sustaining. Flame stability, while firing coal, is

    impacted by several factors. Primary air flow and coal / air temperature have already

    been discussed. ln addition, the ignition properties of the coal are of prime importance.

    Key factors include the quantity and quality of volatile matter; and the quantity of inert

    matter (ash and moisture). Coals with lower volatile matter and/or increased inert matter

    will result in reduced flame stability. Boiler load and load on the particular pulveriser will

  • 8/10/2019 NFL-Bathinda Final.docx

    61/65

    61 | P a g e

    also Impact stability, as will the firing pattern of burners in service. Below 40% of the

    respective capacity of the pulveriser the flames are not expected to be self sustaining and

    Stable. Flame stability has to be assessed during early operation on coal. These

    assessments have to include reduced load conditions on the boiler and on individual

    pulveriser/burners, Flame scanners are also installed on the main PC fired Burners which

    are intended to safeguard operation and prevent burner operation without stable and

    satisfactory flames.

    Control of the fuel to active burners and airflow to burners is best accomplished by

    properly adjusted automatic combustion controls. Conditions may arise where automatic

    Operation is not possible or not desirable for both the fuel and air. In these cases, operate

    with both in manual operation Always operate with the fuel and air controls in the same

    mode either both on manual or both on automatic.Combustion system tuning is performed to determine the optimum operating for the PC S

    Type burners, The PC S Type burner spin vane settings are to be finalized for all burners

    during early operation ring pulverized coal. The final settings should be flirty uniform

    tor all burners. The burner air dampers are positioned by automated linear actuators for

    appropriate Cooling or light off position, and operating position. with specific settings

    determined for each burner. Coal and air distribution to the furnace and resultant ow

    patterns through the furnace, change in correspondence to which pulversiers are in

    service.

    Tuning it performed varying which pulverisers are in service to determine and