User-Immovable Asset Management Plan2019/2020
DEPARTMENT OF TRANSPORT AND PUBLIC
WORKS
Western Cape Government
USER IMMOVABLE ASSET MANAGEMENT
PLAN (U-AMP)
2019/20
(Excludes the provincial road network)
Department of Transport and Public Works User- Immovable Asset Management Plan
2019/20 Financial Year
i
Official sign-off
It is hereby certified that this User Immovable Asset Management Plan for 2019/20:
1. Complies with the Government Immovable Asset Management Act, 2007 that requires all government departments to prepare an immovable asset management plan for annual submission to the Custodian department and Provincial Treasury;
2. Is user-specific in that it addresses those immovable asset requirements that the Department requires to fulfil its strategic objectives. It excludes all assets allocated to the Department as a Custodian, as well as the provincial road network;
3. Is in line with the Department of Transport and Public Works Strategic Plan 2015/16–2019/20;
4. Was prepared by the Directorate: Strategic Management Support in consultation with the members of the Departmental Accommodation Committee;
5. Fully meets the requirements of “Immovable Asset Management in National and Provincial Government: Guideline for Users: User Asset Management Plans” (dated 20 October 2008 that guides users on how to prepare effective immovable asset plans that facilitate achievement of strategic objectives; and
6. Is submitted in accordance with Provincial Treasury Circular No. 15/2018 (Supplementary 1 of 2018) dated 20 August 2018 that requires user departments to submit their final 2019/20 U-AMPs no later than 15 February 2019.
APPROVED BY:
JACQUELINE GOOCH
HEAD OF DEPARTMENT (ACCOUNTING OFFICER)
Date: 15 February 2019
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
ii
Contents
Section 1: Introduction ................................................................................................................................................ 1
Section 2: Service delivery objectives and accommodation requirements ................................................... 2
Legislation...................................................................................................................................................................... 2
Approved and funded programme objectives ..................................................................................................... 6
Organisational environment .................................................................................................................................... 10
Portfolio composition ................................................................................................................................................ 10
Section 3: Acquisition plan ....................................................................................................................................... 13
Section 4: Refurbishment plan ................................................................................................................................. 13
Section 5: Repairs/Maintenance ............................................................................................................................ 13
Section 6: Surplus accommodation ....................................................................................................................... 14
Section 7: Budget ....................................................................................................................................................... 14
Section 8: Plan improvement and monitoring ...................................................................................................... 15
Conclusion .................................................................................................................................................................. 15
U-AMP Schedules ....................................................................................................................................................... 16
Schedule 1: Schedule of asset requirements per Budget Programme Objective ......................................... 16
Schedule 1.2: Asset requirements per trading entity reporting to the Department ...................................... 20
Schedule 2.1: Assets currently occupied by or allocated to the user (WCG-owned) .................................. 21
Schedule 2.2: Assets currently occupied by or allocated to the Department (leased-in assets and
buildings) ..................................................................................................................................................................... 23
Schedule 2.3: Assets currently occupied by or allocated to the Department (leased-in-other) ............... 24
Schedule 3.1: Functional performance (WCG-owned) ..................................................................................... 25
Schedule 3.2: Functional performance (leased-in) ............................................................................................. 26
Schedule 4: Current utilisation – WCG-owned and leased-in ........................................................................... 28
Schedule 5: Utilisation improvement plan ............................................................................................................. 30
Schedule 6: Gap analysis ......................................................................................................................................... 40
Schedule 7: Asset plan .............................................................................................................................................. 51
Schedule 8: New asset requirements ..................................................................................................................... 60
Schedule 9: Rehabilitation, Renovations and Refurbishments .......................................................................... 62
Schedule 10: Assets identified for surrender (WCG-owned) .............................................................................. 64
Schedule 11: Repair requirements .......................................................................................................................... 65
Annexure A ................................................................................................................................................................. 70
Legislative mandates ................................................................................................................................................ 70
Policy mandates ........................................................................................................................................................ 71
Annexure B .................................................................................................................................................................. 73
Required Performance Standard ........................................................................................................................... 73
Accessibility Rating .................................................................................................................................................... 73
Suitability Index ........................................................................................................................................................... 74
User Condition Rating ............................................................................................................................................... 75
Operating Performance Index ................................................................................................................................ 76
Functional Performance Index ................................................................................................................................ 77
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
iii
List of tables
Table 1: NDP critical challenges ................................................................................................................................ 3 Table 2: PSG linkages to DTPW’s U-AMP .................................................................................................................. 4 Table 3: Budget programme personnel................................................................................................................. 10 Table 4: Office accommodation norms and standards ..................................................................................... 12 Table 5: Budget Programme Provisions 2019/20 .................................................................................................. 14 Table 6: Required Performance Standard ............................................................................................................ 73 Table 7: Accessibility Rating ..................................................................................................................................... 73 Table 8: Suitability Index ............................................................................................................................................ 74 Table 9: Condition Rating ......................................................................................................................................... 75 Table 10: Operating Performance Index ............................................................................................................... 76 Table 11: Functional Performance Index ............................................................................................................... 77
List of figures
Figure 1: WCG core values ........................................................................................................................................ 2 Figure 2: Provincial Strategic Goals .......................................................................................................................... 4 Figure 3: DTPW asset portfolio .................................................................................................................................. 11 Figure 4: Decision Framework based on the condition assessment of immovable assets ........................... 78
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
iv
Acronyms
AEC Alcohol Evidentiary Centre
AIMS Asset Information Management System
ASD Assistant Director
C-AMP Custodian Immovable Asset Management Plan
CBD Cape Town Central Business District
CD Chief Director/ Chief Directorate
CCTV Closed circuit television
CE-I Centre for e-Innovation
CIIE Construction Industry Innovation and Empowerment
CoCT City of Cape Town
DD Deputy Director
DDG Deputy Director-General
DG Director-General
DTPW Department of Transport and Public Works
DSG Departmental Strategic Outcome-oriented Goals
DRE District Roads Engineer
EMS Emergency Medical Services
eNATIS Electronic National Traffic Information System
EPWP Expanded Public Works Programme
FTE Full-time equivalent
GG Government Garage
GIAMA Government Immovable Asset Management Act, 2007
GLTC Gene Louw Traffic College
GMT Government Motor Transport
HOB Head of Branch
HOD Head of Department
ICT Information and communication technology
ITIH Integrated Information Hub
MEC Member of the [Provincial] Executive Council (Provincial Minister)
MISS Minimum Information Security Standards
MTSF Medium Term Strategic Framework
NDP National Development Plan
OHS Occupational Health and Safety
OLA Operator Licensing Adjudication
OLP Operator Licensing and Permits
PA Public address
PABX Private automatic branch exchange
PERSAL Personnel and Salary Information System
PRE Provincial Revenue and Expenditure
PSG Provincial Strategic Goal
SAPS South African Police Service
SL Salary level
SMS Senior Management Service
TAL Transport Administration and Licensing
U-AMP User Immovable Asset Management Plan
VSSC Vangate Shared Service Centre
WCG Western Cape Government
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
v
Glossary
Acquire For provincial governments, “acquire” is defined in the relevant provincial
land administration law or transfer of custodianship between custodians in
that sphere of government.
Custodian Means a national or provincial department designated in terms of GIAMA
that must plan, acquire, manage and dispose of immovable assets. In this
document, the Custodian is the Department of Transport and Public Works.
Dispose Includes the sale, exchange, donation or letting of provincial state land.
Immovable asset Any immovable asset acquired or owned by government, including Western
Cape Government (WCG)-owned and leased immovable assets. Immovable
assets are further described as land and any immovable improvements on
that land which have enduring value, including assets of a residential, non-
residential or infrastructural nature, and including installed machinery and
equipment that is an integral part of the immovable asset.
Immovable asset
management
Those management processes which aim to ensure that the value of an
immovable asset is optimised throughout its lifecycle.
Lifecycle The National Treasury-prescribed period (per asset class) during which a
custodian can expect to derive economic benefits from the control of that
class of immovable asset.
Maintenance All work on existing immovable asset that is undertaken to:
a) prevent deterioration and failure;
b) restore the immovable asset to its specified level of operation;
c) restore the physical condition to specified standards;
d) recover the immovable asset from structural and service failure; and
e) partially replace components of the immovable asset with
equivalent components.
Reconfiguration Activities to make changes to the configuration of an immovable asset which
change the functionality of the asset.
Refurbishment Comprehensive capital works actions intended to bring an immovable asset
back to its original appearance or state or to extend its lifecycle.
Refurbishment may also be required for historical preservation.
Renovation Renovation works do not necessarily extend functionality or the life of the
asset, but are necessary for the planned life to be achieved. In such cases,
the capital value of the asset is not affected.
Repair Actions to bring an immovable asset back to its original state when the asset
has been accidentally or maliciously damaged.
Strategic plan The strategic plan of a custodian or user as prescribed in the Public Service
Act, 1994, and the Public Finance Management Act, 1999.
Operational plan A detailed plan with clear goals describing the day-to-day management of
an immovable asset to ensure that the value of that immovable asset is
optimised throughout its life cycle, by planning for its upkeep, maintenance
and repair, security, and payment of services.
Surplus In relation to an immovable asset, surplus means that the immovable asset no
longer supports the service delivery objectives of a user.
Surrender plan A plan for the relinquishment of immovable assets (or parts of immovable
assets) where the immovable assets (or parts of immovable assets) no longer
support the service delivery objectives of a user.
Upgrade (extension,
addition)
Comprehensive capital works that increase the value of an existing
immovable asset and extend the area of, or add new functionality to, the
asset in question.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
vi
User A national or provincial department that uses or intends to use an immovable
asset in support of its service delivery objectives, including a custodian that
uses or intends to use an immovable asset in support of its own service
delivery objectives.
Useful life The period during which a user derives benefit from the use of an immovable
asset.
NARRATIVE
NARRATIVE
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
1
Section 1: Introduction
In line with the Government Immovable Asset Management Act (GIAMA), 2007, (Act 19
of 2007), the Department of Transport and Public Works (DTPW) is the Custodian of the
Western Cape Government (WCG) infrastructure portfolio (excluding human settlements),
and therefore exercises a key role in ensuring that infrastructure plays a developmental
role in addressing the challenges of poverty, inequality and unemployment, whilst
ensuring that infrastructure is managed optimally over its life-cycle. The Custodian role of
the DTPW extends to all other departments in the province, including provision for
education, health, social, and general buildings.
Apart from its role as Custodian, the department is required to develop this U-AMP which
provides for its own specific service delivery needs as a user and which extends to
responsibilities that include road network management, transport operations, transport
safety, regulation and integrated planning space, and community-based programmes.
The Department is developing a 20-year infrastructure vision that seeks to consider and
respond to a range of emerging socio-economic, technological and environmental
change phenomena. The intention is that this 20-year vision will iteratively inform the
DTPW’s five-year U-AMPs over that period.
The key strategic intent of the department regarding its existing immovable assets is to
manage and improve the efficiency, effectiveness and sustainability of its property
holdings through reducing costs and improving space utilisation coupled with real
percentage reduction in full-time employee costs. Longer term strategic approach
include the development of a master accommodation plan to achieve efficiencies and
resilience in the accommodation portfolio. A shared office building approach is
supported intending to mitigate growing office accommodation demand as well as
promote integration to further improve efficiencies. The department is continuing to find
sustainable solutions in providing resilient infrastructure that can adequately respond to
climate change and environmental challenges.
This 2019/20 U-AMP presents the final year in the five-year cycle of strategic deliverables
that are described in the DTPW Strategic Plan 2015/16–2019/20. It is a result of various
improvements in planning processes which seek to promote integration. As a user, the
Department is allocated immovable assets comprising of state-owned and leased-in
accommodation to fulfil its strategic objectives. The property portfolio represents a mixture
of old and new buildings located inside the Cape Town Central Business District (CBD) and
elsewhere in the Western Cape. The portfolio of state-owned and leased-in
accommodation allocated to the Department is described in Schedules 2.1, 2.2 and 2.3.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
2
Section 2: Service delivery objectives and accommodation
requirements
Legislation
Vision
The DTPW embraces the WCG’s vision as contained in the Provincial Strategic Plan 2014–
2019:
“An open opportunity society for all.”
The DTPW’s own vision is consistent with the WCG’s vision:
“To lead in the delivery of government infrastructure and related services.”
Mission
“The DTPW delivers infrastructure and services to promote socio-economic outcomes and
safe, empowered and connected communities.”
Values
The DTPW fully subscribes to the core values of the Western Cape Government (WCG):
Figure 1: WCG core values
All these values are underpinned by team work.
Legislative and policy frameworks
Government Immovable Asset Management Act
GIAMA provides for a uniform framework for the management of immovable assets held
or used by the DTPW to help ensure the coordination of the use of immovable assets with
the service delivery objectives. The principles of immovable asset management include:
• immovable assets must be used efficiently and become surplus to the
Department if they do not support service delivery objectives at an efficient level
and if they cannot be upgraded to such a level.
• immovable assets that are currently used must be kept operational to function in
a manner that supports efficient service delivery.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
3
GIAMA requires the Department as a user to prepare an Immovable Asset Management
Plan to be known as a U-AMP in relation to the immovable assets that the Department
uses, or intends to use. A U-AMP is the principal immovable asset strategic planning
instrument which guides and informs all immovable asset management decisions by the
Department.
GIAMA requires the Department in its capacity as a user of immovable assets to develop
a U-AMP that forms part of its strategic planning process. Other sets of legislation,
regulations and policies that contribute to the development of the U-AMP are set out in
Annexure A.
National, provincial and departmental strategic context
National strategic context
The national strategic directives described below guide DTPW’s U-AMP 2019/20.
The National Development Plan (NDP): Vision 2030
The most important critical challenges and recommendations identified in the NDP that
are the most relevant to the functions and activities of DTPW in the context of the U-AMP
are described in Table 1 below.
Table 1: NDP critical challenges
Growth and jobs Expand public employment programmes to two million participants by 2020. As
the number of formal- and informal-sector jobs expands, public work
programmes can be scaled down.
Infrastructure
development
Synchronise and align infrastructure delivery between the spheres of government
to promote sustainable economic growth.
To grow faster and in a more inclusive manner, the country needs higher levels of
capital spending in general, and public investment in particular.
Referring to accommodation, to phase in the principle of users paying for
services rendered.
Spatial
development
Provide infrastructure that is responsive to spatial needs and logic.
Shortened travel distances and increased urban densification.
Provision of rural transport strategies and infrastructure to underpin rural
economic and social development.
Public service
reforms
Development of a skilled and professional public service.
Provincial strategic context
Provincial Strategic Goals (PSGs)
The WCG developed five PSGs for the five-year strategic planning period to give effect to
its strategic priority areas as aligned to the NDP, Medium Term Strategic Framework (MTSF),
and OneCape 2040. Together the PSGs constitute the Provincial Strategic Plan (PSP) 2014–
2019 as illustrated in Figure 2.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
4
Figure 2: Provincial Strategic Goals
The implementation of the DTPW’s U-AMP through Programme 2 supports the
achievement of PSGs 1, 4 and 5, the WCG Game-Changers, as well as the Departmental
Strategic Outcome-oriented Goals (DSGs) are depicted in Table 2 below.
Table 2: PSG linkages to DTPW’s U-AMP
PSG 1: Create opportunities for growth and jobs
Departmental
Strategic Outcome-
oriented Goal (DSG)
Contribution of DTPW Contribution to
Game-Changer MTSF
DSG 1:
Maximise
empowerment and
job creation in the
Western Cape.
• Work opportunities created
through provincial building
infrastructure construction
and maintenance projects. • Expanded Public Works
Programme (EPWP) included
in design of infrastructure
projects.
Energy Security:
Energy
efficiency in
government
buildings.
National Outcome 4:
Decent employment
through inclusive
growth.
STRATEGIC GOAL 5: Embed good governance and integrated service delivery through
partnerships and spatial alignment
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
5
PSG 4: Enable a resilient, sustainable, quality and inclusive living environment
Departmental
Strategic Outcome-
oriented Goal
Contribution of DTPW Contribution to
Game-Changer MTSF
DSG 2:
Manage provincial
infrastructure and
immovable assets in
the Western Cape.
• Immovable asset portfolio
management. • Improvement in the key
reporting parameters reported
on in the annual Property
Efficiency Report. • On-going implementation of
the Office Modernisation
Programme.
• Reduction in water
consumption in general
infrastructure buildings.
• Reduction in electricity
consumption in selected
office accommodation.
• Design and construction of
new buildings in line with
green building principles.
• Clearing of vacant provincially
owned erven.
Integrated Better
Living Model:
Deliver on the
Better Living
Model Exemplar
Project at the
Conradie
Hospital site in
Pinelands.
National Outcome 6:
An efficient,
competitive and
responsive
economic
infrastructure
network.
PSG 5: Embed good governance and integrated service delivery through partnerships and spatial
alignment
Departmental
Strategic Outcome-
oriented Goal
Contribution of DTPW MTSF
DSG 4:
Promote good
governance,
effectiveness and
efficiency throughout
the DTPW.
• On-going implementation of the Office
Modernisation Programme.
• Ongoing Occupational Health and Safety (OHS)
assessments at DTPW facilities.
• Replacement of the Western Cape Land
Administration Act.
National Outcome
12:
An efficient, effective
and development-
oriented public
service.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
6
Approved and funded programme objectives
Budget programme objectives
The existing immovable assets allocated per budget programme are not sufficient to
support the achievement of service delivery objectives. These include office
accommodation, information and communications technology (ICT) facilities required in
line with advances in technology and district road engineering, road camps and houses,
and traffic centres. The extent to which existing allocated immovable assets meet the
functional requirements, the gap between existing and required assets, as well as
proposed solutions to address programme demand are discussed below and are further
described in Schedule 1 per budget programme. The storage space is a transversal
requirement across programmes and is advised that the Custodian addresses the need
collectively.
Programme 1: Administration
This Programme provides for the overall management support to the Department in order
to ensure that it delivers on its mandate in an integrated, efficient, effective and
sustainable manner. Currently the components of the Programme are fragmented in
various state-owned and leased-in buildings within the CBD and this negatively impacts
integration. There is a need for the Custodian to assess the possibility to fully
accommodate the Programme at 9 Dorp Street in accordance with applicable norms
and standards.
Programme 1’s requirements for supporting the achievements of its service delivery
objectives include: an ICT training facility that can accommodate 15–20 seats; storage
space; repair requirements at Alfred Street; and reconfiguring 9 Dorp Street to optimally
accommodate the components of the Programme.
Programme 2: Public Works Infrastructure
This Programme provides balanced provincial government building infrastructure that
promotes integration, accessibility, sustainability, equity, environmental sensitivity,
economic growth and social empowerment. As the implementing agent for infrastructure,
the programme plays a critical role in providing access for communities to education,
health and social services through the provision of education, health and general
infrastructure. This contributes to the attainment of the WCG’s strategic goals of improved
education, an increase in wellness, the eradication of social ills, as well as creating
opportunities for growth and jobs for residents of the province. As part of its function to
promote the effective and efficient utilisation of the immovable asset portfolio, the Programme
has embarked on the preparation of a master accommodation plan. The overall objective of
this plan is to review departmental requirements and developing an accommodation strategy
that improves the efficiency, effectiveness, productivity and well-being of all WCG employees.
Currently the components of the Programme are accommodated at DTPW Head Office
at 9 Dorp Street, and at Atterbury House (leased-in) buildings in the CBD, while the regional
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
7
office is accommodated at York Park in George. Programme 2’s requirements in the CBD
to support the achievement of its service delivery objectives include: space ratification for
the Chief Directorate: Education Infrastructure; office accommodation; alternative
accommodation for the recycling station and plans registry; and storage. In the Garden
Route district, adequate modernised office accommodation is required in George; a
workshop near the York Park building; and adequate parking for Government Garage
(GG) and officials’ vehicles.
Programme 3: Transport Infrastructure
The Programme delivers and maintain transport infrastructure that is sustainable,
integrated and environmentally sensitive, that supports and facilitates social
empowerment and economic growth, and that promotes accessibility and the safe,
affordable movement of people, goods and services. The Programme is responsible for all
the transport infrastructure of provincially proclaimed roads within the road reserve and
its management. To support achievement of its strategic objectives, the Chief Directorate:
Organisation Development is continuing with the redesign of the Chief Directorate: Road
Network Management which might impact on the accommodation needs of the
Programme.
Due to the current fragmentation of various components of the Programme, a proposal
to accommodate the entire Programme at a newly constructed building is to be explored
to ensure integration of all critical functions. Further, the District Roads Engineer (DRE)
offices located at Paarl, Ceres and Oudtshoorn are responsible for the maintenance of
the existing road infrastructure network to standards that optimise the efficient and safe
realisation of these opportunities for long-term sustainability of the province. Scheduled
and preventative maintenance as well as attention to health and safety requirements are
required at the DRE facilities, road camps and road houses.
Programme 4: Transport Operations
Programme 4 plans, regulates and facilitates the provision of integrated land transport
services through coordination and cooperation with national planning authorities,
municipalities, community-based organisations, non-governmental organisations and the
private sector in order to enhance and facilitate the mobility of all communities.
Optimal supporting accommodation is required at DTPW Head Office for programme
support operations, public transport services, transport safety and compliance services,
and transport systems support. Further expansion of the George bus depot is required.
Through the implementation of the Integrated Information Hub (ITIH), the Department is
pioneering the use of smart technology as a force multiplier. The Hub brings together data
from the Transport Management Branch’s Traffic Management, Traffic Law Enforcement,
Transport Operations, and Provincial Regulatory Entity to support evidence-based
decision making. Benefits of the system include more effective speed control, overloading
control, and control of fatigued driving in service of safer roads for residents of, and visitors
to, the Western Cape. With regards to the Fatigue Management Programme, the ITIH will
monitor programme results by scanning vehicle number plates and drivers’ licences at
intervals on long journeys, focusing on public transport and freight vehicles. This will
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
8
generate specific data, including average speed, and time spent resting versus time
spent behind the wheel. Accommodation at the leased-in building in 11 Leeuwen street
is being re-organised to cater for these technological advances.
Programme 5: Transport Regulations
The Programme regulates the transport environment through: the registration and
licensing of vehicles, associations, operators and drivers; promoting safety through traffic
law enforcement services; facilitating communication and road safety education and
awareness; operating weighbridges1; and providing training to traffic policing and other
law enforcement officials.
Optimal supporting accommodation for the Programme is required at Head Office,
Vangate Shared Service Centre (VSSC), regional road-based public transport
representative bodies, impoundment facilities, Provincial Regulatory Entity regional
offices, regional road safety offices, as well as at various regional traffic centres across the
province.
The Directorate: Operating Licensing and Permits situated at the VSSC administers
applications for operating licences. Because this is a service delivery centre, it should be
safe and easily accessible for clients. An archive facility is required to address the
increasing number of documents requiring filing every day. The proposal is for the
Custodian to explore the possibility of converting the existing VSSC storage building into
an archive facility which meets South African archive standards and Minimum Information
Security Standards (MISS).
The Sub-Directorates Formalisation and Empowerment, and Mediation and Stakeholder
Relations are currently located at a leased-in building (Norton Rose, 8 Riebeek Street,
Cape Town). The demand for services from metered taxi industry operators has declined
as a result of the introduction of the Uber and Taxify services, therefore this office no longer
needs to be based in the CBD. It is proposed that this office be relocated to Goulburn
Centre in Goodwood to reduce traffic in the CBD as well as to address clients’ safety,
security and parking concerns about the current location of this office.
As the only 24/7 traffic service in South Africa, and together with its local authority partners,
DTPW Provincial Traffic Services continues to police hazardous locations, and help ensure
a safe and free-flowing road network for all users of provincial roads in the Western Cape.
Providing effective traffic services ideally requires support facilities that are scaled to fit
the volume of traffic in a locality, and the number of crashes recorded there. This
approach can be seen in Beaufort West, where the response to high volumes of traffic
and many crashes has been to locate a traffic centre, a weighbridge, an impoundment
facility, emergency services and radio control service together in a shared space.
A service delivery model for Traffic Management is required to analyse alternative modes
of delivery which in turn will determine suitable locations of traffic centres and related
services. A new office building is required at Gene Louw Traffic College to accommodate
staff of the Chief Directorate: Traffic Management currently accommodated in a leased-
in building (35 Wale Street, Cape Town). Refurbishment of the mobile structures located
1 Included in the Roads User-Immovable Asset Management Plan
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
9
at the Gene Louw College is required to accommodate the Brackenfell traffic centre sited
at premises in Parow, where after relocation of the Directorate: Road Safety Management
from CBD to Parow is required. Prefabs to be refurbished and re-modelled to
accommodate 60 operational and 15 support staff.
Government Motor Transport (GMT)
GMT is a trading entity in the administration of the DTPW with a core mandate of delivering
effective fleet management services to provincial and national government clients in the
Western Cape.
GMT accommodation in Cape Town is currently in four separate locations. Because of this
fragmentation, the lack of parking space to prepare vehicles for delivery, and the security
and related risks associated with moving vehicles between various premises, the DTPW
acquired premises at 3 Rusper Street, Maitland for the construction of a multi-storey
building that could eventually house the whole of GMT. Phase 1 of construction has been
completed and the GMT Directorate: Fleet Services moved there in October and
November 2018. Construction on Phase 2 for the GMT Directorate: Fleet Finance and the
Sub-Directorate Management: Support Services is planned to commence during the
2019/20 financial year and is projected to be completed within approximately two years.
Interim reconfiguration measures are required at Roeland Street and Hope Street to
provide office accommodation while Phase 2 is being built.
Clients in the Garden Route and Central Karoo can expect improved service as the
service capacity at the GMT George Hub expands, and as the Hub makes a pool of
vehicles available for optimal utilisation and to support clients to deliver services more
efficiently.
In support of the City of Cape Town’s Level 5 water restrictions, GMT introduced several
initiatives to save and recycle water. These initiatives included no longer washing vehicles
with potable water, replacing taps with pushbutton taps, and removing taps in the wash
bay areas. GMT now only cleans vehicle interiors and uses mobile service providers clean
vehicle exteriors with waterless products.
Programme 6: Community-Based Programmes
The Programme manages the implementation of programmes and strategies that lead to
the development and empowerment of communities and contractors, including the
professional development, provincial management, and coordination of the EPWP.
Optimal supporting accommodation is required to provide effective community-based
programme support, contractor development, empowerment impact assessments, and
EPWP coordination and compliance monitoring. With the exception of Grabouw, the
supporting accommodation is in an optimal state at regional offices.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
10
Organisational environment
The DTPW functions within an increasingly challenging environment that requires an agile
and resilient organisational life-cycle approach coupled with re-organisation of its
components. In this regard, organisational re-design to be undertaken is the re-alignment
of the Public Works functions to the Infrastructure Delivery Management System, whilst the
re-structuring of Transport Infrastructure is at an advanced stage and the impact of these
changes on accommodation requirements has not been explored. The current funded
budget programme personnel are described in Table 3 below.
Table 3: Budget programme personnel
Programme Number of actual
posts
Number of funded
posts
Number of filled
posts
1: Administration 425 288 290
2: Public Works Infrastructure 603 401 408
3: Transport Infrastructure 999 697 694
4: Transport Operations 75 38 37
5: Transport Regulation 1 084 794 794
6: Community-Based Programmes 96 59 59
3 282 2 277 2 282
Government Motor Transport 188 128 115
Source: COE database as at 17 January 2019; GMT - Personnel and Salary Information System (PERSAL)
as at 15 October 2018
Portfolio composition
As a user, the Department is allocated immovable assets comprising of WCG-owned and
leased-in accommodation to fulfil its strategic objectives. The property portfolio represents
a mixture of buildings in various life-cycle stages. These properties are reflected in
Schedule 2.1, 2.2, 2.3 and Figure 3 below.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
11
Figure 3: DTPW asset portfolio
The asset portfolio of the DTPW is predominantly located in the Cape Town CBD where its
head office is at 9 Dorp Street. Service delivery points are also located in other parts of the
Western Cape. These include facilities for traffic law enforcement, District Road Engineer
offices, the Provincial Regulatory Entity, road camps, the Expanded Public Works
Programme, and public transport administration, operations and licensing.
Functional performance, accessibility and condition rating
Through its provincially-owned and leased-in property portfolio, the Department
endeavours to ensure that its strategic objectives are met. The functional performance
presents the level at which the allocated accommodation supports achievements of
service delivery objectives of the department. These are presented in Schedules 3.1 and
3.2. The functional performance ranges between P4 and P1 where a P4 rating indicates
good public presentation and a high-quality working environment and P1 indicates a
dormant asset where relinquishment is pending. The overall condition of the DTPW
allocated state-owned and leased-in assets range from having no apparent defects, to
being in average condition. No assets shown to be in a failing condition.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
12
The accessibility rating was determined according to the physical location of the
accommodation, accessibility to the public (where applicable), accessibility in terms of
public transport routes, parking and other public areas, as well as accessibility for persons
with disabilities. The accessibility rating ranges between A5 and A1, where an A5 rating
represents well-designed accommodation asset that is universally accessible, and an A1
rating is not at all accessible. With regard to accessibility, most allocated DTPW assets are
accessible to the general public as well as people with disabilities.
The condition rating refers to the physical condition of a building. These condition ratings
are based on the user’s perception of the immovable assets in question. GIAMA requires
the Custodian to assess the condition of its immovable assets at least once every fifth year.
Technical conditional assessments are conducted every year by the Custodian. The
average condition of the General Buildings portfolio, based on a weighted Condition
Grade Index (CGI), aligned with the GIAMA Performance Standard grades, from 1 (worst)
to 5 (best) is 3.78. The overall condition of the General Buildings asset portfolio is relatively
good and the condition profile quite appropriate, given the wide spread of functionalities
within this portfolio. Most of the components in the buildings are in condition C5 and C4.
Objectives to improve the efficient and effective utilisation of accommodation
The WCG embraces the opportunity to improve office accommodation for staff through
modernisation of the workplace. In this regard, the DTPW uses prescribed space norms
and standards that must be adhered to when planning and designing office
accommodation as described in Table 4 below.
Table 4: Office accommodation norms and standards
Description Salary level Area norm
Cellular offices
Personal assistant and office manager 7;9 12 m2
Senior management: Director and CD 13-14 20 m2
Executive management: DDG and DG 15-16 25 m2
Provincial executive n/a 30 m2
Open-plan offices
Support staff (drivers, messengers, etc.) n/a 2,5 m2
Administrative staff Up to 9 6 m2
Middle management 9-12 9 m2
Technical staff 8-12 12 m2 (depending on job functions)
Support spaces
Small meeting rooms - 15 m2 1 – 20 FTEs*
Medium meeting rooms - 25 m2 21 – 40 FTEs
Large meeting rooms - 35 m2 41 – 70 FTEs
Breakaway areas - 6 m2
Store rooms - 2 m2 per 10 FTEs
Core spaces
Network and PABX* rooms - 12 m2 (4 x 3) per Ce-I* requirements
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
13
Description Salary level Area norm
Sick bays - 9 m2 (1 per building)
Cleaners’ room - Up to 3 m2 per 20 FTEs per building
Security control rooms - -
Source: DTPW Norms and Standards.
FTE – full-time equivalent.
* PABX – private automatic branch exchange.
** WCG Centre for e-Innovation
In planning for DTPW office accommodation needs, an average of 15 m2 norm was
applied and is described in Schedule 4.
Section 3: Acquisition plan
The DTPW acquisition requirements comprises of the need for newly constructed office
buildings to reduce fragmentation, acquisition of existing office buildings for improved
service delivery to clients and to maximise effective working environments. The detailed
acquisition plan is described in Schedule 8.
Section 4: Refurbishment plan
From time to time it becomes necessary to improve the operations of an immovable asset
to extend its life-cycle as well as reconfigure the asset to meet new service delivery
demands of the department. The refurbishments plan includes current and proposed
refurbishments, configurations and upgrades directed to improve service delivery. The
office modernisation programme is directed to increase capacity of state-owned
buildings thereby reduce the extent of leased-in portfolio. The modernised office buildings
optimise workplaces as they provide versatile spaces, furniture and fittings that increase
the usable area to gross building area. Office modernisation of the third and eighth floors
in 9 Dorp Street is planned for 2019/20 financial year. The modernisation of the 7th, 8th and
9th floors is scheduled to commence in 2019/20 financial year. This will require temporary
decanting of staff. Further refurbishments are described in Schedule 9.
Section 5: Repairs/Maintenance
The performance of capital assets is essential to the health, safety, economic
development and quality of life of recipients of these services. The Department adopted
a strategic shift in its management of infrastructure portfolio to focus on maintenance and
lifecycle cost management within constrained budgetary pressures.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
14
The DTPW General Infrastructure Maintenance Management Strategy, 2017 outlines a
transparent and uniform approach to planned maintenance of the provincial immovable
asset portfolio (excluding human settlements, health and education facilities). During
2017/18, the Chief Directorate: General Infrastructure undertook an exercise to scope all
road camps and associated houses to ascertain the maintenance requirements at these
facilities. It is envisaged that upon completion of the scoping exercise and consultations
with the programme, road camp models will be developed in line with the redesigned
organisational structure currently underway to preserve life of these assets and further
ensure alignment to service delivery objectives.
Section 6: Surplus accommodation
None.
Section 7: Budget
Over the medium term, the provincial budget policy is directed to maximise citizen
impact. This calls for vigilance and improvement in infrastructure budget execution
through integrated planning, good procurement strategies and strengthening processes
for monitoring infrastructure implementation and delivery. Apart from the budget
provisions of the department for its Custodian responsibilities, departmental budget
programmes make provisions to safeguard assets used to fulfil each programme’s
strategic objectives. However, some programmes are solely dependent on provisions
made by the Custodian in line with management of asset life-cycle. Transport
Infrastructure made provision for maintenance of its campsites, houses and mobile homes
while Transport Regulations made provision for routine maintenance of its office buildings,
as per Table 5 below.
Table 5: Budget Programme Provisions 2019/20
Budget Programme Routine Maintenance Current Budget
(2019/20)
3 Transport Infrastructure R 7 394 000
5 Transport Regulations R 110 000
Source: Basic Accounting System
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
15
Section 8: Plan improvement and monitoring
In order to manage its immovable asset portfolio efficiently, the Department is adopting
a strategic approach in the management of its assets across its life-cycle to maximise
value. One such intervention is the Asset Information Management System (AIMS) project
which will digitise and integrate the DTPW asset register. This is an ongoing project that
seeks to modernise the DTPW business model.
The office accommodation norms and standards that were set demonstrates the DTPW’s
commitment to “green” principles across general, health and education infrastructure
and work to mitigate the impact of the water crisis. It is critical that a whole-of-asset
approach is followed which includes making every effort to introduce climate resilience
into the provincial asset portfolio before any building of new infrastructure is considered.
The historic maintenance backlog of social infrastructure requires immediate intervention
to promote and preserve the role that this infrastructure plays. The focus will continue to
address emergency failures brought about by poor maintenance and normal wear and
tear. The existing maintenance backlog is exacerbated by the need for infrastructure to
be resilient to climate change.
To maximise citizen impact, OHS assessments were conducted at various buildings in order
to ensure safety and wellbeing of staff as well as citizens served at these facilities. The
identified OHS related work is depicted in Schedule 11 per facility for implementation by
the Custodian.
The user welcomes the initiatives by the Custodian in line with the recently adopted Green
Building Policy by the National Department of Public Works. The policy identifies the built
environment and more specifically buildings as a key lever to address the challenges
associated with accelerated climate change. The DTPW has identified Smart Buildings as
one such opportunity to contribute to realising system-wide sustainability, through a series
of automated processes that enable centralised control over operations, and is
researching ways to introduce components of smart buildings into its property portfolio.
Conclusion
This U-AMP focuses only on the immovable asset portfolio occupied by the Department
as a user, identifying requirements to best meet its service delivery objectives.
The immovable asset requirements consist of the need for new accommodation and
maintenance of the provincial buildings occupied by, and allocated to, the Department.
The accommodation required to fulfil the service delivery objectives has been
categorised by budget programmes in line with the approved staff establishment. Most
of the immovable asset requirements of the DTPW in 2019/20 are to be addressed through
the modernisation work currently being done in the 9 Dorp Street and York Park building.
The user intends to develop a 5-year U-AMP for the period 2020/21 – 2024/25 in order to
align its requirements to the DTPW Strategic Plan for the same period.
SCHEDULES
SCHEDULES
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
16
U-AMP Schedules
Schedule 1: Schedule of asset requirements per Budget Programme Objective
Programme 1: Administration
Sub-Programme Optimal asset solution Rationale
• Office of the MEC
• Management of the
Department
• Corporate Support
• Departmental Strategy
Head office at 9 Dorp Street, Cape Town to
accommodate 288 funded posts.
To provide the overall management support to the Department.
Programme 2: Public Works Infrastructure
Organisational re-design process to be undertaken for Public Works.
Sub-Programme Optimal asset solution Rationale
• Programme Support
• Planning
• Construction
• Maintenance
• Immovable Asset Management
• Facility Operations
Head office at 9 Dorp Street, Cape Town to
accommodate 401 funded posts.
Garden Route District office, York Park
building
To provide balanced provincial government building infrastructure that
promotes integration, accessibility, sustainability, equity, environmental
sensitivity, economic growth and social empowerment.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
17
Programme 3: Transport Infrastructure
Organisational re-design process underway.
Sub-Programme Optimal asset solution Rationale
• Programme
Support
Infrastructure
• Infrastructure
Planning
• Infrastructure
Design
• Construction
• Maintenance
Head office to provide for planning, design,
construction and maintenance of road
infrastructure network.
3 District Regional Engineering offices in the
following localities:
• Paarl
• Ceres
• Oudtshoorn
Various road camps situated across the
province.
The Chief Directorate: Road Network
Management organisational structure is under
review. Current structure provides for 697
funded posts.
To deliver and maintain transport infrastructure that is sustainable, integrated and
environmentally sensitive, that supports and facilitates social empowerment and
economic growth, and that promotes accessibility and the safe, affordable
movement of people, goods and services.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
18
Programme 4: Transport Operations
Sub-Programme Optimal asset solution Rationale
• Programme
Support
Operations
• Public Transport
Services
• Transport Safety
and Compliance
• Transport Systems
Head office in 11 Leeuwen Street, Cape Town
to accommodate 38 funded posts.
Regional office and bus depot in George.
To plan, regulate and facilitate the provision of integrated land transport services
through coordination and cooperation with national planning authorities,
municipalities, community-based organisations, non-governmental organisations
and the private sector to enhance and facilitate the mobility of all communities.
Programme 5: Transport Regulation
Sub-Programme Optimal asset solution Rationale
• Programme Support
Regulation
• Transport
Administration and
Licensing (TAL)
• Operator Licence
and Permits (OLP)
• Law Enforcement
Head Office in 9 Dorp Street, Cape Town.
Transport Centre at Vangate.
13 Provincial Traffic Centres located across the
Province.
Satellite Operational Centres.
2 Shadow Centres (Breadth Alcohol Testing Centre)
Gene Louw Traffic College in Brackenfell.
3 Provincial Regulatory Entity in the following localities:
• Athlone
• George
• Piketberg
2 Minibus Taxi Offices at Sunbell Building, Bellville and
Goulburn Centre, Goodwood.
6 Impound Facilities across the Province.
The Programme comprises of 794 funded posts.
To regulate the transport environment through the registration and
licensing of vehicles, associations, operators and drivers; to promote
safety through traffic law enforcement services, to facilitate road safety
education and, communication, awareness, and the operation of
weighbridges; and to provide training to traffic policing and other law
enforcement officials.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
19
Programme 6: Community-Based Programmes
Sub-Programme Optimal asset solution Rationale
• Programme Support
Community-Based
• Innovation and
Empowerment
• Coordination and
Compliance
Monitoring
Head Office at Attenbury House,
9 Riebeek Street, Cape Town to
accommodate 59 funded posts.
EPWP Regional office across the
Province.
To manage the implementation of programmes and strategies that lead to the development
and empowerment of communities and contractors, address skills shortage in transport, built
and engineering environment, including the provincial management and coordination of
the EPWP.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
20
Schedule 1.2: Asset requirements per trading entity reporting to the Department
GMT
Optimal asset solution Rationale
GMT is currently domiciled in four buildings situated in Roeland Street, Hope Street (Cape Town),
Hermes Street (Paarden Eiland) and Rusper Street, (Maitland). This Entity has 124 funded posts
Provision of quality and cost-effective vehicle fleet
service to client departments and government entities.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
21
Schedule 2.1: Assets currently occupied by or allocated to the user (WCG-owned)
Site ID
(Property
Code)
Erven
no Town Physical address
Municipality
(local authority) Asset description
Extent of building
(m2)
Accommodation
type
5483 3386 Cape Town 9 Dorp Street City of Cape
Town (CoCT)
Head Office, 9 Dorp
Street
13 188 Offices
2873 564 Cape Town
(CBD)
Alfred, Prestwich,
Chiappini and Hospital
Streets
CoCT Alfred Street/ Chiapinni
Street Complex
11 169 Offices
3376 32654 Athlone 30 Bosduif Road CoCT VSSC 16 803 Offices
18261 2709 Cape Town
(CBD)
Dorp Street CoCT City Bowl Block 2 881 Offices
2820 3475 George St Johns Street George Local
Municipality
York Park Building 10 055 Offices
3259 5101 Vredenburg 2 Toermalyn Street Saldanha Bay
Local
Municipality
Vredenburg Provincial
Traffic Department
19 579 Offices
6073 7558 Parow 16 Tallent Street CoCT Traffic Law Enforcement
Offices (Brackenfell
Traffic Centre)
1 407 Offices
2952 8327
Beaufort
West
N1 Highway Beaufort West
Local
Municipality
Road Camp 159 173 Traffic Centre
20639 113190 Cape Town Next to N2, South of
Cape Town International
Airport Runway
CoCT Satellite Traffic Operation
Centre (N2)
- Traffic Centre
2863 11660 Bellville Robert Sobukwe Road CoCT Provincial Roads
Workshops
48 977 Workshop
3257 17984 Paarden
Eiland
19 Hermes Street CoCT Government Garage:
Paarden Eiland
5 943 GMT vehicle
Holding site
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
22
Site ID
(Property
Code)
Erven
no Town Physical address
Municipality
(local authority) Asset description
Extent of building
(m2)
Accommodation
type
- 95826 Cape Town 49 Hope Street CoCT Government Garage:
Hope Street
5 408 (Including the
basement parking)
GMT vehicle
Holding site
Offices
- 99877 Maitland 3 Rusper Street CoCT GMT: Maitland 18 698 (1,7667
hectares)
GMT vehicle
holding site,
Offices, Vehicle
cleaning
3256 95948 Cape Town Corner of Roeland and
Buitenkant Street
CoCT GMT: Buitenkant Street
Vehicle Rental Service
and Carwash
11 622 GMT vehicle
holding site,
Vehicle cleaning
3255 96174 Cape Town Buitenkant Street CoCT Provincial Vehicle
Parking: Top Yard
8 917 GMT vehicle
holding site
- - Cape Town 34 Roeland Street CoCT GMT – 34 Roeland Street
Office block
- GMT Offices
- 3953 Oudtshoorn Voortrekker Road Oudtshoorn
Municipality
Roads: Oudtshoorn 43 186 Roads Offices
- - Cape Town 13 Dorp Street CoCT Clinsearch House - Offices
- - George - George Impound Facility - Impound Facility
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
23
Schedule 2.2: Assets currently occupied by or allocated to the Department (leased-in assets and
buildings)
Asset Description Town
Date Escalat
ion %
pa
R’
2019/20
R’
2020/21
R’
2021/22
R’
2022/23 Start Expiry
11 Leeuwen Street (Flrs 1,2,3,4 &5) Cape Town 2016/05/01 2019/04/30 8 2 958 479,52 3 165 573,12 3 387 163,20 3 624 264,63
13 Pitt Street (GF & 1st floors) Knysna 2014/05/01 2023/04/30 7 585 158,50 625 381,99 632 478,14 676 751,62
35 Wale Street, 2nd floor Cape Town 2015/12/01 2020/11/30 5,5 765 834,18 807 955,06 852 392,59 899 274,18
Atterbury House 16th Floor Cape Town 2017/04/01 2020/03/31 8 1 852 673,64 2 000 887,53 2 160 958,53 2 333 835,22
Atterbury House 17th Floor Cape Town 2017/07/01 2020/06/30 8 1 473 027,84 1 590 870,67 1 718 139,68 1 855 590,85
Atterbury House 5th Floor Cape Town 2017/04/01 2020/03/31 8 1 816 785,72 1 962 128,86 2 119 098,86 2 288 626,77
Caledon Roads Camp Caledon 2018/09/01 2021/08/31 8 44 695,67 48 271,34 52 133,03 56 303,67
Oosterlig Roads Camp Ceres 2017/01/01 2019/12/31 8 1 226 813,97 1 324 959,06 1 430 955,75 1 545 432,18
Golden Rendevous Building Mossel bay 2017/04/01 2020/03/31 8 514 359,60 555 508,37 599 949,04 647 944,96
Karin Building (DTPW) Vredendal 2017/04/01 2022/03/31 7,5 209 890,20 221 434,20 233 613,12 246 461,88
Keerom Street (Erf 3519, 3524, 3525, 3526) Cape Town 2018/05/01 2019/04/30 10 38 914,38 43 584,11 48 814,20 54 671,91
Business Centre Shop 9 Laingsburg 2011/01/01 2021/08/31 8 170 298,10 183 070,46 196 800,74 211 560,79
Orion Gebou Caledon 2016/10/01 2021/10/31 8 528 504,66 570 785,03 616 447,83 665 763,66
Rentzburghof George 2016/03/01 2021/02/28 7 773 027,25 827 139,12 885 038,91 946 991,68
Seppie Greef Building Oudtshoorn 2017/04/01 2022/03/31 10 2 702 292,12 2 972 521,33 3 269 773,47 3 596 750,81
Sunbell Building, 8th Floor Bellville 2017/05/01 2025/04/30 8 665 604,04 708 052,36 764 696,57 825 872,28
Velapi Roads Camp Caledon 2017/04/01 2027/02/28 7 89 418,60 95 677,90 1 102 375,35 109 541,63
WCP Taxi Council Parking Bellville 2013/10/01 Indefinite 0 21 184,20 21 184,20 21 184,20 21 184,20
Winkelshoek Piketberg 2019/01/01 2023/12/31 8 215 433,18 232 667,82 251 281,20 271 383,69
Norton Rose 1,2,5,6& 40 parking bays Cape Town 2012/11/01 2019/04/30 10 799 889,27 879 878,20 967 866,03 1 064 652,62
Waldorf Building (Floors: 1, 6-12, Shop 10,
Basement 1-3) +147 parking and storage
Cape Town 2018/04/01 2023/03/31 6,5 18 092 400,36 19 268 406,38 20 520 852,80 21 854 708,23
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
24
Schedule 2.3: Assets currently occupied by or allocated to the Department (leased-in-other)
Asset Description Town
Date Escalat
ion %
pa
R’
2019/20
R’
2020/21
R’
2021/22
R’
2022/23 Start Expiry
9 Dorp Str Wheelchair ramp Cape Town 2012/04/01 2022/03/31 6 8 072,88 8 557,25 9 070,69 9 614,93
Fisantekraal Repeater Station (annual lease) Laingsburg 2017/01/01 2021/12/31 10 17 569,20 19 326,12 21 258,73 23 384,60
Puttersvlei Repeater Station (annual lease) Beaufort West 2016/12/01 2021/11/30 8 13 146,48 14 198,20 15 334,06 16 560,78
Rammetjieskraal Repeater Station Laingsburg 2013/11/01 2019/04/30 7 13 611,13 14 972,24 16 469,47 18 116,41
Table Mountain Repeater Station Cape Town 2018/06/01 2025/05/31 8 135 873,27 146 743,13 158 482,58 171 161,19
Zuurbraak repeater station Swellendam 2001/06/01 Indefinite 10 3 000,00 3 000,00 3 000,00 3 000,00
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
25
Schedule 3.1: Functional performance (WCG-owned)
See Annexure B for details
Asset description Town Current Use
Required
performance
standard
Condition
rating*
Accessibility
rating*
Suitability
Index
Operating
Performance
Index
Functional
Performance
Index
9 Dorp Street Complex Cape Town Offices P4 C4 A4 A 1 A1
Alfred Street/Chiapinni
Street Complex Cape Town Offices P3 C3 A4 A 2 A2
VSSC Athlone Offices P3 C3 A3
B 2 B2
City Bowl Block Cape Town Offices P1 C1 A1 C 2 C2
York Park George Offices P3
C1 A3 B 3 B3
Vredenburg Traffic
Department Vredenburg Offices
P3
C4 A3 B 1 B1
Brackenfell Traffic
Department Parow Offices
P3
C4 A3 B 1 B1
Traffic Centre Beaufort West Traffic Centre P3 C4 A3 B 1 B1
Satellite Traffic Operation
Centre N2 Highway Traffic Centre P1 C2 A2 C 2 C2
Provincial Roads Workshops Bellville Workshop P3 C4 A4 A 1 A1
GMT: Paarden Eiland Paarden Eiland Office and Garage P2 C3 A4 A 1 A1
GMT: Hope Street Cape Town Offices and Garage P3 C5 A4 A 1 A1
GMT: Maitland Maitland Offices and Garage P3 C4 A4 A 1 A1
GMT: 34 Roeland Street
Office block Cape Town Offices P3 C3 A4 A 1 A1
Provincial Vehicle Parking
(Top Yard) Cape Town Parking P3 C3 A3 B 2 B2
GMT: Buitenkant Street Cape Town Offices, garage
and Car wash P3 C3 A4 A 1 A1
Provincial Roads
Department: Oudtshoorn Oudtshoorn Offices P3 C4 A4 A 1 A1
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
26
Schedule 3.2: Functional performance (leased-in)
Description Town Current
Use
Required
performance
standard
Condition
rating*
Accessibility
rating*
Suitability
Index
Operating
Performance
Index
Functional
Performance
Index
11 Leeuwen Street (Flrs
1,2,3,4 &5) Cape Town Offices P3 C4 A4 A 1 A1
13 Pitt Street (GF & 1st floors) Knysna Offices P4 C4 A4 A 1 A1
35 Wale Street, 2nd floor Cape Town Offices P4 C4 A4 A 1 A1
Atterbury House 16th Floor Cape Town Offices P4 C4 A4 A 1 A1
Atterbury House 17th Floor Cape Town Offices P4 C4 A4 A 1 A1
Atterbury House 5th Floor Cape Town Offices P4 C4 A4 A 1 A1
Caledon Roads Camp Caledon Road
Camp P3 C4 A3 A 1 A1
Oosterlig Roads Camp Ceres Road
Camp P3 C4 A3 A 1 A1
Golden Rendevous Building Mossel Bay Offices P3 C4 A3 A 1 A1
Karin Building (DTPW) Vredendal Offices P3 C4 A3 A 1 A1
Keerom Street (Erf 3519, 3524,
3525, 3526) Cape Town Parking P3 C4 A3 A 1 A1
Business Centre Shop 9 Laingsburg Offices P3 C4 A3 A 1 A1
Orion Building Caledon Offices P3 C4 A3 A 1 A1
Rentzburghof George Offices P3 C4 A3 A 1 A1
Seppie Greef Building Oudtshoorn Offices P3 C4 A3 A 1 A1
Sunbell Building, 8th Floor Cape Town Offices P3 C4 A4 A 1 A1
Velapi Roads Camp Caledon Road
Camp P3 C4 A4 A 1 A1
WCP Taxi Council Parking Bellville Parking P3 C4 A4 A 1 A1
Winkelshoek Piketberg Offices P3 C4 A4 A 1 A1
Norton Rose 1,2,5,6& 40
parking bays Cape Town Offices P4 C4 A4 A 1 A1
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
27
Description Town Current
Use
Required
performance
standard
Condition
rating*
Accessibility
rating*
Suitability
Index
Operating
Performance
Index
Functional
Performance
Index
Waldorf Building (Floors: 1, 6-
12, Shop 10, Basement 1-3)
+147 parking and storage
Cape Town Offices P3 C4 A4 A 1 A1
* See Annexure B for details.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
28
Schedule 4: Current utilisation – WCG-owned and leased-in
Programme Personnel Number of funded posts per
functional area
Applicable norm/
standard (m2) Area per m2 utilised
1: Administration Executive [1] 3 25 75
Senior Management [2] 14 20 280
Other [3] 271 12 3 252
288
3 607
2: Public Works Infrastructure Executive 1 25 25
Senior Management 15 20 300
Other 385 12 4 620
401
4 945
3: Transport Infrastructure Executive 25
Senior Management 4 20 80
Other 693 12 8 316
697
8 396
4: Transport Operations Executive 25
Senior Management 4 20 80
Other 34 12 408
38
488
5: Transport Regulation Executive 1 25 25
Senior Management 8 20 160
Other 785 12 9 420
794
9 605
6: Community Based
Programme
Executive 25
Senior Management 3 20 60
Other 56 12 672
59 732
GRAND TOTAL 2 277 27 773
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
29
Programme Personnel Approved posts per functional
area
Applicable norm/
standard (m2) Area per m2 utilised
GMT
Executive 25
Senior Management 3 20 60
Other 125 12 1 500
128 1 560
Source: COE database as at 13 December 2018; GMT APP 2018/19
[1] Executive: MEC, HOD and HOBs (Member of the [Provincial] Executive Council, Head of Department and Heads of Branches).
[2] Senior Management: Chief Directors and Directors
[3] All levels below SMS, average of 15m2
Note: Norms and standards derived from the Transport and Public Works “Guideline for the preparation of a U-AMP”.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
30
Schedule 5: Utilisation improvement plan
Programme 1: Administration
Unit Assets allocated Current
utilisation
level [1]
Excess/shortage of
assets
Utilisation improvement actions
Chief Directorate: Policy
and Strategy Integration
Non-allocated on the 1st floor,
9 Dorp Street
Over Shortage – Office
accommodation.
Reconfigure 9 Dorp Street to provide for Chief Director and
Personal Assistant.
Directorate: Operational
Support
8th Floor, 9 Dorp Street Shortage – storage
space.
A universal approach in providing storage for the Department
must be determined by the Custodian.
Directorate: Strategic
Management Support
1st Floor, 9 Dorp Street Shortage – office
accommodation
Reconfigure small boardroom to make space for two staff
members SL 1-9
Directorate: Knowledge
Management
1st Floor, 9 Dorp Street Shortage – Office
space and ITC
training facility.
Provide 2 x DD + 12 SL 1-9 seats - to be accommodated
outside of registry as staff is currently seating at the Registry
(security zone).
Provide 15/20-seater ICT training facility in 9 Dorp Street.
Chief Directorate:
Financial Management
Ground floor, 9 Dorp Street Shortage – Office
accommodation &
storage space
Reconfigure ground floor, 9 Dorp Street to provide
accommodation for the Chief Director and Personal Assistant.
Directorate: Financial
Governance
6th Floor, Waldorf Building, St
Georges Mall
The current temporary arrangements at Waldorf building and
5th Floor at 9 Dorp Street are not adequate.
Directorate: Financial
Accounting
5th Floor, 1st Floor 11 Leeuwen
Street
Reconfigure Head Office to provide office accommodation,
boardrooms, breakaway rooms, store room, closed offices.
Directorate: Logistics
and Asset Management
Alfred Street Complex Shortage – Office
accommodation.
1 Cubicle suitable for 2 people
Ground floor, 9 Dorp Street Shortage – storage
space.
Require area for breaks and storage space.
Chief Directorate: Supply
Chain Management
Ground floor, 9 Dorp Street Storage space required for: tender files; LOGIS procurement
documentation; Integrated Procurement System
documentation; redundant computers; office furniture which is
earmarked for storage. Space required for breaks.
[1] Utilisation criteria: Over-utilised: when the space currently in use is greater than the usable space (allocated m2); underutilised: when the space currently in
use is less than the usable space (allocated m2).
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
31
Programme 2: Public Works Infrastructure
Organisational re-design process to be undertaken for Public Works.
Unit Assets
allocated
Current
utilisation
level [1]
Excess/shortage of
assets Utilisation improvement actions
Chief Directorate:
General Infrastructure
Directorate:
Programme/ Project
Infrastructure Delivery
6th Floor, 9 Dorp
Street
Over Shortage - Office
accommodation, Plans
Registry, storage.
New permanent accommodation is required urgently to accommodate
80 operational staff (cleaning, tea staff and workshop team). In addition,
permanent alternative space for the Plans Registry of about 220m2
None of these can be accommodated on the modernised 6th floor, new
office accommodation at 13 Dorp Street should be considered to meet
this urgent requirement.
Storage and accommodation space is required in the CBD for service
providers of statutory maintenance including HVAC, fire detection,
plumbing, general and electrical maintenance.
Alternative space is required for the recycling station currently located at
C&D garage in Dorp Street.
Technical Services:
George
Offices: George Over Shortage - Office
accommodation,
workshop and parking.
Adequate modernised office accommodation is required for the George
office on the 4th floor in York Park.
Additional space is required to accommodate the workshop near the
York Park building.
Adequate parking for Government Garage (GG) and officials' vehicles in
and around York Park.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
32
Unit Assets
allocated
Current
utilisation
level [1]
Excess/shortage of
assets Utilisation improvement actions
Chief Directorate:
Education
Infrastructure
Directorate:
Education
Infrastructure Policies,
Strategies and
Systems
Directorate:
Education
Programme/ Project
Infrastructure Delivery
15th and 18th
Floor, Atterbury
House, 9
Riebeek Street
Over Shortage - Office
accommodation.
Provide new accommodation on 10th floor 27 Wale Street, to
accommodate Chief Directorate. A total of 50m2 is required to optimally
accommodate the Chief Directorate staff. 226 m2 is required to
accommodate the architects, engineers and technical admin staff. Total
area required by Chief Directorate and 2 Directorates = 1 801m2.
Additional space required including workstations at applicable standards
for new approved structure to accommodate existing staff numbers and
5 additional vacancies (Total = 5 + 99 + 22 = Grand Total 126)
A space ratification process was compiled in 2014 for a total number of
126 staff and it was established that 1801m² would be required to
accommodate Education Infrastructure Policies, Strategies and Systems.
Currently, a total number of 127 staff has been planned for and thus, the
allocation of ±1801m² should be increased to ±1900m² to cater for the
new accommodation requirements (see further down below).
10th floor of 27 Wale Street only provides ±1130m² of usable office
accommodation and this would not cater for the entire Chief
Directorate. Adjacent office accommodation (in the same building and
preferably 2 adjacent floors for efficient business procedures and service
delivery) is required in addition to the 10th floor of 27 Wale Street would
be required.
50m² is only for the office of the Chief Director and does not cater for the
Administration support staff that reports to the Chief Director. 226m² is not
sufficient to cater for the architects, engineers and technical staff across
2 directorates.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
33
Unit Assets
allocated
Current
utilisation
level [1]
Excess/shortage of
assets Utilisation improvement actions
Chief Directorate:
Education
Infrastructure
Directorate:
Education
Infrastructure Policies,
Strategies and
Systems
Directorate:
Education
Programme/ Project
Infrastructure Delivery.
15th and 18th
Floor, Atterbury
House, 9
Riebeek Street
Over 58m2 required to
accommodate staff.
Metro: Staff require
360m2
Workspace support
area:
- 60m2 for
boardroom
- 32m2 for meeting
rooms
- 28m2 for storage
space (1.13m2 per 5
FTEs)
- 32m2 for
breakaway area
and kitchen (16m2
per 50 FTEs)
- 60m2 for Network
Printing Hubs (12m2
per 25 FTEs)
- 5m2 for server room.
Total area required:
1 801m2
Currently, the Chief Directorate is located on the entire 15th and about
half of the 18th floor of Atterbury House. 2 small meeting rooms, 2 normal
size meeting rooms and a boardroom are provided to the Chief
Directorate for use however for the past 2 years this space is not sufficient
for critical and efficient service delivery.
Additional kitchen facilities are to be provided as well as break-away
areas for the staff during lunch - current kitchen with break-away is not
sufficient.
Adequate breakaway and storage areas are to be provided for the
cleaning staff.
Additional store rooms for project documents are to be provided - there
is currently only 3 store rooms provided.
The Chief Directorate: Immovable Asset Management needs to revise
the space ratification in line with the business procedures and
requirements of the new structure for the Chief Directorate Education
Infrastructure.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
34
Unit Assets
allocated
Current
utilisation
level [1]
Excess/shortage of
assets Utilisation improvement actions
Chief Directorate:
Health Infrastructure
Directorate: Health
Infrastructure Policies,
Strategies and
Systems
Directorate: Health
Programme/ Project
Infrastructure Delivery
5th Floor, 9 Dorp
Street
Over
Shortage - Office
accommodation
Additional space will be required (including workstations) once OD has
finished organisational design process currently underway for Public
Works.
Reconfigure existing storerooms and printing rooms to get better
utilisation from the allocated store rooms with fitment of permanent
storage racks / opti-plan etc."
Chief Directorate:
Immovable Asset
Management
4th Floor, 9 Dorp
Street
Shortage - Storage
Space
Reconfigure Head Office, 9 Dorp Street to provide storage space.
[1] Utilisation criteria: Over utilised: when the space currently in use is greater than the usable space (allocated m2); underutilised: when the space currently in
use is less than the usable space (allocated m2).
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
35
Programme 3: Transport Infrastructure
Organisational re-design process underway
Unit Assets allocated
Current
utilisation
level [1]
Excess/shortage of assets Utilisation improvement actions
Chief Directorate: Road Network Management 3rd Floor, 9 Dorp Street Over
Shortage - Office
accommodation
Currently under-going OD re-design,
improvements include office
accommodation, boardrooms,
breakaway rooms, store room,
computer server room, Plan Room,
Technical Library, Back-up server room,
Fireproof Vault. Reduction of passage in
Mechanical open plan section as
discussed with Public Works as per Plan.
Directorate: Road Planning 3rd Floor, 9 Dorp Street Shortage - Office
accommodation,
Directorate: Road Design 3rd Floor, 9 Dorp Street Shortage - Office
accommodation, Plan
Room, Technical Library,
Back-up server room,
Interactive Design room
(3D design), Fireproof
Vault.
Directorate: Construction and Maintenance 2rd Floor, 9 Dorp Street Shortage - Office
accommodation
Directorate: Regional Roads Management 2nd Floor, 9 Dorp Street Shortage - Office
accommodation
Soil Laboratory (Relocation) Chiappini Street Shortage - Office
accommodation, and
delivery/loading zone
Relocate Soil Laboratory
Provincial Roads Workshop (Bellville) Workshop Bellville Shortage - Office
accommodation
Reconfigure current accommodation at
Bellville
[1] Utilisation criteria: Overutilised: when the space currently in use is greater than the usable space (allocated m2); underutilised: when the space currently in
use is less than the usable space (allocated m2).
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
36
Programme 4: Transport Operations
Unit Assets allocated
Current
utilisation
level [1]
Excess/shortage of assets Utilisation improvement actions
Chief Directorate: Transport
Operations
3rd Floor, 11 Leeuwen Street Over
Shortage - Office
accommodation
Re-configure 11 Leeuwen Street Building.
Directorate: Land Transport
Development and Systems
and Freight
4th Floor, 11 Leeuwen Street
Directorate: Land Transport
Contracts
2nd Floor, 11 Leeuwen Street
Directorate: Land Transport
Safety
3rd Floor, 11 Leeuwen Street
Directorate: Land Transport
Integration and Oversight
4th Floor, 11 Leeuwen Street
George Depot George depot Shortage - Depot Reconfigure the Depot
[1] Utilisation criteria: Overutilised: when the space currently in use is greater than the usable space (allocated m2); underutilised: when the space currently in
use is less than the usable space (allocated m2).
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
37
Programme 5: Transport Regulation
Unit Assets allocated
Current
utilisation
level [1]
Excess/shortage of
assets Utilisation improvement actions
Directorate: Transport
Administration and
Licensing
2nd Floor, 9 Dorp Street,
ground floor VSSC,
Over
Shortage - Office
accommodation
Reconfigure Head Office, 9 Dorp Street to provide meeting
rooms, breakaway rooms, storeroom and Electronic National
Traffic Information System (eNaTIS) server room.
9 Dorp Street, 2nd floor: Storage space
VSSC, ground floor: revamp the current public counter to
provide for two private/closed public consultation rooms
Preferably open door from the administration side. Storage
space
Directorate: Transport
Administration and
Licensing (George)
York Park Building, 4th
floor
Relocation The TAL service needs to be relocated to the ground floor.
Directorate: Operator
Licensing Adjudication
(OLA)
VSSC: half of the
Ground Floor (Sharing
Space), 1st and 2nd Floor.
Shortage - Office
accommodation
Reconfigure VSSC 1st Floor to provide factory. Reinforce a floor
to provide strong room for storage of adjudication documents
Directorate: Operator
Licensing and Permits (OLP)
VSSC: half of the
Ground Floor (sharing
space), 1st and 2nd Floor.
Reconfigure VSSC ground floor to provide service interface, 2nd
and 3rd floor to provide additional office space.
Directorate: Provincial
Transport Registrar
Offices - Head Office Reconfigure VSSC 4th floor to provide additional
accommodation for the Registrar.
Chief Directorate: Traffic
Management
2nd Floor, 35 Wale Street Construct new office accommodation at the Gene Louw Traffic
College to provide for optimal office accommodation of the
Chief Directorate support staff. The Directorate Road Safety
Management to be relocated to Parow, where the Brackenfell
Traffic Centre is currently located, and in turn relocate the
Brackenfell Traffic Centre to the existing prefabs at the Gene
Louw Training College. Prefabs to be upgraded and re-
modelled to accommodate 60 operational and 15 support staff.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
38
Unit Assets allocated
Current
utilisation
level [1]
Excess/shortage of
assets Utilisation improvement actions
Directorate: Road Safety
Management -
Vredenburg/ Saldanha Bay
Offices - Saldanha Reconfigure existing accommodation at current traffic centre
offices to provide optimal office accommodation. 1 x ASD (SL
9), 1 x Principal Road Safety Officer (SL 8) and 1 x Road Safety
Officer (SL 7) needs to be accommodated.
Metro: Somerset West
Traffic Centre at Vangate
Inspection centre
Somerset West
Additional space is needed for a back office.
Additional storage space is needed.
Security upgrading is needed.
Reconfigure the VSSC to provide for adequate vehicle
inspection space.
Brackenfell Traffic Centre
(currently situated in
Parow)
Traffic centre Shortage - Office
accommodation
Revamp the current mobile structures at Gene Louw College to
accommodate the Brackenfell traffic centres staff currently
located in Parow. Additional space is needed for staff at Paarl
(satellite office). Additional space is needed at Radio Control
Centre for 24/7 operation. A backup radio facility is needed at
Tygerberg.
N2/ Southern Cape George shadow centre Office accommodation for 3 road safety officers or alternatively
be accommodated at the York Park Building.
Directorate: Traffic Training Brackenfell Shortage - indoor
shooting range
Reconfigure Gene Louw Traffic College to provide indoor
shooting range – In progress.
Gene Louw Traffic Centre Brackenfell Shortage – skid pan Reconfigure Gene Louw Traffic College to provide skid pan – In
progress
Chief Directorate: GMT Offices - Head Office Shortage - Office
accommodation
Phase-in the relocation of the GMT Offices to 3 Rusper Street,
Maitland.
[1] Utilisation criteria: Overutilised: when the space currently in use is greater than the usable space (allocated m2); underutilised: when the space currently in
use is less than the usable space (allocated m2).
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
39
Programme 6: Community-Based Programmes
Unit Assets allocated Current utilisation
level [1] Excess/shortage of assets
Utilisation improvement
actions
Chief Directorate: EPWP 17th Floor, Atterbury
House, 9 Riebeek
Street
Optimal –
Decanting
accommodation
Shortage - Office accommodation and storage
space
Provide office
accommodation and
storage space for the
Directorate: Professional
Development
Accommodation is
optimal at various
regional offices.
Directorate: EPWP CIIE*
Directorate: EPWP
Coordination
Shortage - Office accommodation
Regional Offices: CIIE
Directorate: Professional
Development
Over Shortage - office accommodation and storage
space.
[1] Utilisation criteria: Overutilised: when the space currently in use is greater than the usable space (allocated m2); underutilised: when the space currently in
use is less than the usable space (allocated m2).
* Construction Industry Innovation and Empowerment.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
40
Schedule 6: Gap analysis
Programme 1: Administration
Optimal Assets Gap between optimal assets and currently
utilised assets
Quantified need statement Priority
1=high
10=low
Office
accommodation
Reconfigure accommodation at 9 Dorp
Street, Cape Town for Chief Directorate:
Policy and Strategy Integration
Provide office accommodation for the Chief Director and Personal
Assistant.
1
Reconfigure existing accommodation at 9
Dorp Street Cape Town for Chief Directorate:
Financial Management
New appointments, accommodation required for Chief Director and
Personal Assistant. Storage space of 4m x 8m is needed.
1
Reconfigure existing accommodation at 9
Dorp Street Cape Town for Directorate:
Financial Governance
Currently accommodated at Waldorf and 9 Dorp Street buildings.
Provide optimal accommodation for 61 staff members where 30 of these
are auditors to be accommodated for 10 months annually. Three closed
offices (Assurance Services, Payrolls and Payment Vouchers and Fraud
and Loss Control) required for confidentiality.
Storeroom facilities consisting of:
- 1 financial year expenditure vouchers
- 1 financial year Payroll report
- Safe
- Reserve stock face value forms
1
Reconfigure existing accommodation at 9
Dorp Street Cape Town for Directorate:
Financial Accounting
Currently 64 staff members are accommodated at 9 Dorp Street,
including four interns. Centralised accommodation is required. Two
closed offices (Banking, Cash and Salaries) are required for reasons of
confidentiality.
1
Reconfigure existing accommodation at
Alfred Street Complex Cape Town for
Directorate: Logistics and Asset
Management
1 Cubicle suitable for 2 people.
Storage space and area for breaks.
1
Storage space Reconfigure storage space at 9 Dorp Street,
Cape Town for the Directorate: Operational
Support
Storage for events equipment (double the space at 9 Dorp Street, 8th
floor).
1
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
41
Optimal Assets Gap between optimal assets and currently
utilised assets
Quantified need statement Priority
1=high
10=low
Reconfigure storage space at 9 Dorp Street,
Cape Town for the Chief Directorate: Supply
Chain Management
Storage space required for: tender files; LOGIS procurement
documentation; Integrated Procurement System documentation;
redundant computers; office furniture which is earmarked for storage.
Space required for breaks.
1
Additional desks Reconfigure 9 Dorp Street for the
Directorate: Strategic Management Support
Provide two extra desks with internet and telephone connection cables
to cater for additional staff members between SL* 1-9.
1
Office
accommodation
and ICT Training
facility
Reconfigure 9 Dorp Street for the
Directorate: Knowledge Management
Provide 2 x DD + 12 SL 1-9 seats - to be accommodated outside of
registry as staff is currently seating at the Registry (security zone).
Provide 15/20-seater ICT training facility in 9 Dorp Street.
1
SL – salary level.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
42
Programme 2: Public Works Infrastructure
Organisational re-design process to be undertaken for Public Works.
Optimal
Assets
Gap between optimal assets and currently
utilised assets
Quantified need statement Priority
1=high
10=low
Head Office
accommodation in
the Cape Town CBD
Reconfigure existing accommodation at 9
Dorp Street Cape Town to accommodate
Chief Directorate: Immovable Asset
Management
Storage space required (20m2) and rest rooms. 2
Reconfigure 6th floor at 9 Dorp Street Cape
Town to accommodate:
Chief Directorate: General Infrastructure
Directorate: Programme/ Project Infrastructure
Delivery-General
New permanent accommodation is required urgently to
accommodate facility operational staff of 80 people
(cleaning, tea staff and workshop team).
6th floor capacity is inadequate to accommodate the need
1
New office
accommodation at
13 Dorp Street should
be considered to
meet this urgent
requirement.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
43
Optimal
Assets
Gap between optimal assets and currently
utilised assets
Quantified need statement Priority
1=high
10=low
Head Office
accommodation in
the Cape Town CBD
Reconfigure 6th floor at 9 Dorp Street Cape
Town to accommodate:
Chief Directorate: General Infrastructure
Directorate: Programme/ Project Infrastructure
Delivery-General
In addition, permanent alternative space for the Plans
Registry of about 220m2
6th floor capacity is inadequate to accommodate the need
1
Storage and accommodation space is required in the CBD
for service providers of statutory maintenance including
HVAC, fire detection, plumbing, general and electrical
maintenance.
6th floor capacity is inadequate to accommodate the need
2
Alternative space is required for the recycling station
currently located at C&D garage in Dorp Street.
3
Technical Services: George Adequate modernised office accommodation is required
for the George office on the 4th floor in York Park.
Additional space is required to accommodate the workshop
near the York Park building.
Adequate parking for GG and officials' vehicles in and
around York Park.
1
Provide accommodation for the Chief
Directorate: Education Infrastructure
Currently, Education Infrastructure has planned for a total
number of 127 staff and therefore, the allocation of ±1801m²
should be increased to ±1900m² to cater for the new
accommodation requirements.
Immovable Asset Management to revise the space
ratification to be in line with the business procedures and
requirements of the new structure for the Chief Directorate
Education Infrastructure.
1
Reconfigure existing accommodation at 9
Dorp Street Cape Town to accommodate
Chief Directorate: Health Infrastructure
Reconfigure existing storerooms and printing rooms to get
better utilisation from the allocated store rooms with fitment
of permanent storage racks / opti-plan etc."
Additional space will be required (including workstations)
once the organisational design process has been
concluded for Public Works.
1
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
44
Programme 3: Transport Infrastructure
Organisational re-design process underway.
Optimal assets Gap between
optimal assets
and currently
utilised assets
Quantified need statement Priority
1=high
10=low
Head Office
accommodation
in the Cape
Town CBD
Reconfigure
existing
accommodation
at 9 Dorp Street
Cape Town for
Directorate:
Road Design
The office space required.
• Current staff 45 with 25 additional in recruitment.
• 24 staff currently seconded and due for return within 12 months
• 12 full time consultants in Dorp Street, 24 scattered between Loop Street and other locations.
At least two boardrooms are needed of about 6 m x 4 m each, a total of 48m2.
The Plan Room on the 1st Floor 9 Dorp Street should be adequate for future use (nearly 200m2).
Backup server room space of 12m2needed.
Fireproof Vault of 8 m x 4 m needed.
Interactive room (3D Design)
1
3rd Floor, 9 Dorp
Street, Cape
Town
Reconfigure the plugs and network points; procurement of desks to optimally accommodate staff;
minor reconfiguration to accommodate new and existing staff of the Chief Directorate. Relocate staff
currently located at 140 Loop Street to the 3rd floor.
Construction of a server room.
1
Oudtshoorn DRE Reconfigure
existing
accommodation
at Oudtshoorn
DRE
Upgrade the lab. 1
Soil Laboratory Soil Laboratory
(Relocation)
The lab requirements need to be re-evaluated in line with the new proposed organisational structure. 2
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
45
Programme 4: Transport Operations
Optimal assets Gap between optimal assets and currently
utilised assets
Quantified need statement Priority
1=high
10=low
Head Office
accommodation
in the Cape
Town CBD
Reconfigure existing accommodation at 11
Leeuwen Street Cape Town to provide for the
entire Programme.
Redesign is required in line with the Programme staff establishment and the new
ITIH
1
Expanding the extent of the George Depot
by approximately 7 000 m²
The following is required: Filling of ground, paving the extent of expansion,
moving current fencing to extent of expansion, additional fencing.
New accommodation for one (1) person is required.
1
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
46
Programme 5: Transport Regulation
Optimal assets Gap between optimal assets and
currently utilised assets Quantified need statement
Priority
1=high
10=low
Head Office
accommodation
in the Cape
Town CBD
Provide accommodation for staff of
the Directorate: Transport
Administration and Licensing.
A total 55 staff members are currently accommodated at 9 Dorp Street (2nd
Floor).
2 x conference facilities are required for 10-15 people each.
2 x store rooms are required.
1 x eNaTIS server room is required.
Two additional workstations and a breakaway room are required on the
Ground Floor, 9 Dorp Street (Walk-In Centre)
1 x storage space
2
VSSC VSSC, ground floor: revamp the current public counter to provide for two
private/closed public consultation rooms Preferably open door from the
administration side. Storage space
1
Provide accommodation for staff of
the Directorate: Transport
Administration and Licensing: Metro.
This office was supposed to be
accommodated at VSSC as staff are
allocated subsidised/GG vehicles
(provision for parking is required)
A total of 16 staff are currently accommodated in Metro area
1 x store room is required.
2 x counselling rooms are required to discuss confidential cases with members
of the public.
To stand over
until new posts
are created
with 2013
revised staff
establishment
can be funded
and filled.
Provide accommodation for staff of
the Directorate: Transport
Administration and Licensing: West
Coast
(Provision to be made at the new
planned shared office
accommodation,
Vredenburg/Vredendal)
A total of 6 staff members are currently accommodated in the West Coast
region.
1 x store room is required (Malmesbury).
1 x counselling room is required to discuss confidential cases with members of
the public.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
47
Optimal assets Gap between optimal assets and
currently utilised assets Quantified need statement
Priority
1=high
10=low
Provide accommodation for staff of
the Directorate: Transport
Administration and Licensing: Cape
Winelands/ Overberg.
(Provision to made at Paarl/Caledon
shared office accommodation)
A total of 6 staff members are currently accommodated in the Cape
Winelands/ Overberg region.
1 x store room is required (Paarl).
1 x counselling room is required to discuss confidential cases with members of
the public.
Provide accommodation for staff of
the Directorate: Transport
Administration and Licensing: Garden
Route / Central Karoo.
A total of 7 staff members are currently accommodated in the Eden/ Central
Karoo region.
1 x store room is required (George).
1 x counselling room is required to discuss confidential cases with members of
the public (George).
2
Provide accommodation for staff of
the Chief Directorate: GMT
Complete construction phases of 3 Rusper Street, Maitland to accommodate
GMT.
1
Directorate: GMT Technical Hub in
George.
Custodian to complete construction of the Hub currently underway 1
VSSC
Accommodation
Provide accommodation for staff of
the Directorate: OLA.
A suitable conference facility for 10 to 20 people and a storeroom are
required.
A tribunal room for up to 100 people is required.
2
Provide accommodation for staff of
the Directorate: OLP.
3 x conference facilities for 20 people each are required.
2 storerooms are required.
A filing room and an archive room are required.
A rest room is required.
1
Provide accommodation for staff of
the Directorate: OLP Garden Route
Region, George.
1 storeroom and 1 conference facility for 10-15 people are required.
Provide accommodation for staff of
the Directorate: OLP West Coast
Region, Piketberg.
1 storeroom and 1 conference facility for 10-15 people are required.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
48
Optimal assets Gap between optimal assets and
currently utilised assets Quantified need statement
Priority
1=high
10=low
Provide accommodation for staff of
the Directorate: Provincial Transport
Registrar
2 x conference facilities (on the ground floor as the meetings are always under
harsh conditions) for 12-15 people and a store room are required.
New office
accommodation
Chief Directorate: Traffic
Management
Construct new office accommodation at the Gene Louw Traffic College to
provide for optimal office accommodation of the Chief Directorate support
staff. The Directorate Road Safety Management to be relocated to Parow,
where the Brackenfell Traffic Centre is currently located, and in turn relocate
the Brackenfell Traffic Centre to the existing prefabs at the Gene Louw Training
College. Prefabs to be upgraded and re-modelled to accommodate 60
operational and 15 support staff.
1
All traffic centres. Research and development A service delivery model for Traffic Management is required to analyse
possible modes of delivery which in turn will determine suitable locations of
traffic centres and related services. Direction signs indicating location of all
traffic centres are required.
1
Brackenfell
Traffic Centre
Relocate Brackenfell traffic Centre
from Parow to Mobile structure at
Gene Louw College
Revamp the current mobile structures at Gene Louw College to
accommodate the Brackenfell traffic centres staff currently located in Parow.
Additional space is needed for staff at Paarl (satellite office). Additional space
is needed at Radio Control Centre for 24/7 operation. A backup radio facility is
needed at Tygerberg.
1
Road Safety
Management
Head Office
Relocate Directorate: Road Safety
Management staff currently located
at 35 Wale Street to Parow
Utilised the same premises where Brackenfell traffic Centre occupies in Parow
to relocate Directorate: Road Safety Management
1
Road Safety
Management -
District/ Regional
office
accommodation
West Coast
Provide accommodation for staff of
the Directorate: Road Safety
Management - Vredenburg/
Saldanha Bay.
Reconfigure existing accommodation at current traffic centre offices to
provide optimal office accommodation. 1 x ASD (SL 9), 1 x Principal Road
Safety Officer (SL 8) and 1 x Road Safety Officer (SL 7) needs to be
accommodated.
1
Upgrading traffic
centres
Metro: Somerset West Traffic Centre
at Vangate.
Additional space is needed for a back office.
Additional storage space is needed.
Security upgrading is needed.
Reconfigure the VSSC to provide for adequate vehicle inspection space.
2
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
49
Optimal assets Gap between optimal assets and
currently utilised assets Quantified need statement
Priority
1=high
10=low
N1/ West Coast Region. Laingsburg Traffic Centre needs to be relocated due to limited office space.
Worcester Traffic Centre currently situated in town needs to be relocated to
the N1.
Vredenburg Traffic Office needs to be relocated as the WCG-owned building
it currently occupies is located far from the N7.
The Vredendal Traffic Centre needs to be relocated.
Office space or satellite office space is needed in Citrusdal as an extension of
Vredendal.
N2/ Southern Cape Office facilities at Caledon need improvements.
New offices are needed at Barrydale/ Hermanus.
There is a need to establish a radio control room in George.
Office accommodation for 3 road safety officers or alternatively be
accommodated at the York Park Building.
Gene Louw
Training
Academy
Indoor shooting range In Progress 1
Advanced driver training
(construction of skid pan)
In progress 1
Agility Track The surface of current agility track at Gene Louw Traffic College needs an
upgrade. The surface is an even which leads to injuries. It is required that the
agility track be included into the asset register and the surface be upgraded
to ensure proper utilization as part of the Traffic Officer Curriculum.
1
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
50
Programme 6: Community-Based Programmes
Optimal assets Gap between optimal assets and currently
utilised assets
Quantified need statement 2019/20
priority
Head Office
accommodation
in the Cape
Town CBD
Reconfigure existing accommodation at
27 Wale Street Cape Town for Chief
Directorate: EPWP
Staff currently located at a decanting space at 17th Floor Atterbury House.
Three storerooms are needed.
1
Reconfigure existing accommodation at
27 Wale Street Cape Town for Directorate:
Professional Development
Staff currently located at decanting space, 17th Floor, Atterbury House.
Additional office accommodation for 19 staff members and 2 graduate
interns.
Storage space required with the following specifications:
• Marketing material that includes, gazebos, fold-up tables and chairs, table
cloths, various pop up banners, display items for posters, application forms,
pamphlets, branded items for distribution at youth events, etc.
• Equipment for marketing, partnership liaison and campus meetings with
bursars, i.e. mobile printer, three laptops, projectors, for safekeeping in a
steel cabinet.
• Bursary application forms that contain private information (last 2 years prior
to archiving).
• Photo frames and gold paper for award ceremonies (+200).
• Bulk paper for peak time printing.
• Numerous files, partner company agreements, etc.
• Binding machines.
• First aid kits required for campus visits and events.
• Annual MiSS Committee reports and historical data since 2006 for statistical
purposes.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
51
Schedule 7: Asset plan
Programme 1: Administration
Unit Projected demand
(location, projected staff, indicative area (m2)
Budgeted full
accommodation costs
2019/20 2019/20 2020/21
Chief Directorate: Policy and Strategy
Integration
Provide office accommodation for the Chief Director and personal assistant. To be determined by
Custodian
Directorate: Operational Support Storage for events equipment (double the space at 9 Dorp street).
Directorate: Strategic Management
Support
Provide two extra desks with connection cables to cater for additional staff members
between SL 1-9
Directorate: Knowledge Management Provide 2 x DD + 12 SL 1-9 seats - to be accommodated outside of registry as staff is
currently seating at the Registry (security zone). Provide 15/20-seater ICT training facility in
9 Dorp Street.
Directorate: Financial Governance Currently accommodated at NBS Waldorf and 9 Dorp Street buildings. Provide optimal
accommodation for 61 staff members where 30 of these are auditors to be
accommodated for 10 months every year. Three closed offices (Assurance Services,
Payrolls and Payment Vouchers, and Fraud and Loss Control) are required for reasons of
confidentiality. Storeroom facilities consisting of; 1 financial year expenditure vouchers; 1
financial year payroll report and a safe. A reserve stock face value forms.
Directorate: Financial Accounting Currently 64 staff accommodated at 9 Dorp Street including four interns. Centralised
accommodation required. Two closed offices (Banking and Cash and Salaries) required
for confidentiality.
Directorate: Logistics and Asset
Management
Storage space and area for breaks.
1 Cubicle suitable for 2 people.
Chief Directorate: Supply Chain
Management
Storage space required for: tender files; LOGIS procurement documentation; Integrated
Procurement System documentation; redundant computers; office furniture which is
earmarked for storage. Space required for breaks.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
52
Programme 2: Public Works Infrastructure
Organisational re-design process to be undertaken for Public Works.
Unit Projected demand
(location, projected staff, indicative area (m2)
Budgeted full
accommodation costs
2019/20 2019/20 2020/21
Directorate: Technical
Services: George
Adequate modernised office accommodation is required for the George office on the 4th floor in
York Park.
Additional space is required to accommodate the workshop near the York Park building.
Adequate parking for GG and officials' vehicles in and around York Park.
To be determined by
Custodian
Chief Directorate: General
Infrastructure
Directorate: Programme/
Project Infrastructure Delivery-
General
New permanent accommodation is required urgently to accommodate facility operational staff
of 80 people (cleaning, tea staff and workshop team). In addition, permanent alternative space
for the Plans Registry of about 220m2
None of these can be accommodated on the modernised 6th floor, new office accommodation
at 13 Dorp Street should be considered to meet this urgent requirement.
Storage and accommodation space is required in the CBD for service providers of statutory
maintenance including HVAC, fire detection, plumbing, general and electrical maintenance.
Alternative space is required for the recycling station currently located at C&D garage in Dorp
Street.
Chief Directorate: Education
Infrastructure
Directorate: Education
Infrastructure Policies,
Strategies and Systems
Directorate: Education
Programme/ Project
Infrastructure Delivery.
A space ratification was compiled in 2014 for a total number of 126 staff and it was established
that 1801m² would be required to accommodate Education Infrastructure. Currently, Education
Infrastructure has planned for a total number of 127 staff and therefore, the allocation of ±1801m²
should be increased to ±1900m² to cater for the new accommodation requirements.
The Chief Directorate: Immovable Asset Management needs to revise the space ratification to be
in line with the business procedures and requirements of the new structure for the Chief
Directorate Education Infrastructure.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
53
Unit Projected demand
(location, projected staff, indicative area (m2)
Budgeted full
accommodation costs
2019/20 2019/20 2020/21
Chief Directorate: Health
Infrastructure
Directorate: Health
Infrastructure Policies,
Strategies and Systems
Directorate: Health
Programme/ Project
Infrastructure Delivery
Reconfigure existing storerooms and printing rooms to get better utilisation from the allocated
store rooms with fitment of permanent storage racks / opti-plan etc."
Additional space will be required (including workstations) once OD is finished organisational
design process currently underway for Public Works.
To be determined by
Custodian
Chief Directorate: Immovable
Asset Management
4th Floor, 9 Dorp Street, Shortage - Storage Space Reconfigure Head Office, 9 Dorp Street to
provide storage space.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
54
Programme 3: Transport Infrastructure
Organisational re-design process underway.
Unit Projected demand
(location, projected staff, indicative area (m2)
Budgeted full
accommodation costs
2019/20 2019/20 2020/21
Directorate: Road Design Office space required.
• Current staff 45 with 25 additional in recruitment
• 24 staff currently seconded and due for return within 12 months
• 12 full time consultants in Dorp Street, 24 scattered between Loop Street and other
locations.
At least two boardrooms are needed of about 6 m x 4 m each, a total of 48m2.
The Plan Room on the 1st Floor 9 Dorp Street should be adequate for future use (nearly 200m2).
However, the Plan Room can only be moved if alternatively, accommodated.
Backup server room space of 12m2needed.
Fireproof Vault of 8 m x 4 m needed.
Interactive room (3D Design)
To be determined by
Custodian
Soil Laboratory (Relocation) The lab requirements need to be re-evaluated in line with the new proposed organisational
structure.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
55
Programme 4: Transport Operations
Unit Projected demand
(location, projected staff, indicative area (m2)
Budgeted full
accommodation costs
2019/20 2019/20 2020/21
Chief Directorate: Transport
Operations
Currently located at 11 Leeuwen Street. Office accommodation is required for CD, Personal
Assistant and Office Manager.
To be determined by
Custodian
Directorate: Land Transport
Development and Systems
and Freight
Staff members are currently located on the 4th floor at 11 Leeuwen Street.
In total (Chief Directorate and Directorates) 70 permanent staff members (excluding current and
future interns) need to be accommodated in 11 Leeuwen Street, and this may require
reconfiguration of the floor layouts.
Directorate: Land Transport
Contracts
A total staff complement of 15 are accommodated on the 2nd floor at 11 Leeuwen Street.
Redesign is required. The current layout will provide insufficient space for all staff members of both
Directorates.
Directorate: Land Transport
Safety, the Project Office and
Chief Director’s office.
A total staff complement of 20 needs to be accommodated.
Currently staff members are occupied on 3rd Floor, 11 Leeuwen Street.
Redesign is required.
Directorate: Land Transport
Integration and Oversight
Staff members are currently accommodated on the 4th Floor, 11 Leeuwen Street.
Redesign/ reconfiguration of the office layout are needed.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
56
Programme 5: Transport Regulation
Unit Projected demand
(location, projected staff, indicative area (m2)
Budgeted full
accommodation costs
2019/20 2019/20 2020/21
Chief Directorate: Transport
Regulation
Reconfigure existing accommodation at 9 Dorp Street. This is a new component. Accommodation
is needed for a total of 12 staff members. Four staff members are already accommodated on 4th
Floor, 11 Leeuwen Street, along with staff of Land Transport Development, Systems and Freight.
To be determined by
Custodian
Directorate: Transport
Administration and Licensing
The total of 55 staff members are currently accommodated at 9 Dorp Street (2nd Floor).
2 x conference facilities for 10-15 people are required.
2 x store rooms are required.
1 x eNaTIS server room is required.
Two additional workstations and a breakaway room are required at Ground Floor, 9 Dorp Street
(Walk-In Centre).
At VSSC the board room of the Licence Inspectorate must be converted into a smaller counselling
room for confidential discussions with debtors, whilst the rest of the current board room area will
address the limited (cramped up) space of the main adjacent office where there are 6
workstations.
The public counter area of the Licence Inspectorate may be re-allocated to the PRE.
Directorate: Transport
Administration and Licensing:
Metro
A total of 16 staff members are currently accommodated in the Metro area.
1 x store room is required.
2 x counselling rooms are required to discuss confidential cases with members of the public. To stand over until new
posts created with 2013
revised staff
establishment are
funded and filled.
Directorate: Transport
Administration and Licensing:
West Coast
A total of 6 staff members are currently accommodated in the West Coast region.
1x store room is required (Malmesbury).
1 x counselling room is required to discuss confidential cases with members of the public.
Directorate: Transport
Administration and Licensing:
Cape Winelands/ Overberg
A total of 6 staff members are currently accommodated in the Cape Winelands/ Overberg
region.
1 x store room is required (Paarl).
1 x counselling room is required to discuss confidential cases with members of the public
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
57
Unit Projected demand
(location, projected staff, indicative area (m2)
Budgeted full
accommodation costs
2019/20 2019/20 2020/21
Directorate: Transport
Administration and Licensing:
Garden Route / Central
Karoo
A total of 12 staff members are currently accommodated in the Garden Route/ Central Karoo
region.
1 x store room is required (George).
1 x counselling room is required to discuss confidential cases with members of the public
(George).
To be determined by
Custodian
Directorate: GMT Complete construction phases of the 3 Rusper Street, Maitland to accommodate GMT
Directorate: GMT, Technical
Hub in George
Complete construction of the GMT Technical Hub in George
Chief Directorate: Traffic
Management
Construct new office accommodation at the Gene Louw Traffic College to provide for optimal
office accommodation of the Chief Directorate support staff. The Directorate Road Safety
Management to be relocated to Parow, where the Brackenfell Traffic Centre is currently located,
and in turn relocate the Brackenfell Traffic Centre to the existing prefabs at the Gene Louw
Training College. Prefabs to be upgraded and re-modelled to accommodate 60 operational and
15 support staff.
Directorate: OLA Reconfiguration and refurbishment is required.
A suitable conference facility for 10 to 20 people and a storeroom are required.
A tribunal room for up to 100 people is required.
Directorate: OLP Reconfiguration and Refurbishment is required.
3 x conference facilities for 20 people each are required.
2 storerooms are required.
A filing room and archive room are required.
A rest room is required.
Directorate: OLP Garden
Route Region: George
Reconfiguration and refurbishment is required.
1 storeroom and 1 conference facility for 10-15 people are required.
Directorate: OLP West Coast
Region: Piketberg
1 storeroom and 1 conference facility for 10-15 people are required.
Directorate: Provincial
Transport Registration
conference facilities for 12-15 people and a storeroom are required.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
58
Unit Projected demand
(location, projected staff, indicative area (m2)
Budgeted full
accommodation costs
2019/20 2019/20 2020/21
Chief Directorate: Traffic
Management
Construct new office accommodation at the Gene Louw Traffic College to provide for optimal
office accommodation of the Chief Directorate support staff.
To be determined by
Custodian
Brackenfell Traffic Centre
(currently situated in Parow)
Revamp the current mobile structures at Gene Louw College to accommodate the Brackenfell
traffic centres staff currently located in Parow. Prefabs to be upgraded and re-modelled to
accommodate 60 operational and 15 support staff.
Directorate: Road Safety The Directorate Road Safety Management to be relocated to Parow, where the Brackenfell Traffic
Centre is currently located.
Directorate: Road Safety
Management - Vredenburg/
Saldanha Bay
Reconfigure existing accommodation at current traffic centre offices to provide optimal office
accommodation. 1 x ASD (SL 9), 1 x Principal Road Safety Officer (SL 8) and 1 x Road Safety
Officer (SL 7) needs to be accommodated.
Metro: Somerset West Traffic
Centre at Vangate
Additional space is needed for a back office.
Additional storage space is needed.
Security upgrading is needed.
Reconfigure the VSSC to provide for adequate vehicle inspection space.
N1/ West Coast Region Additional space is needed for staff at Paarl (satellite office). Additional space is needed at Radio
Control Centre for 24/7 operation. A backup radio facility is needed at Tygerberg. Laingsburg
Traffic Centre needs to be relocated due to limited office space.
Worcester Traffic Centre situated in town needs to be relocated to the N1. Investigate renting the
Ultra City site when it relocates further down the N1.
Vredenburg Traffic Office needs to be relocated as the WCG-owned building it currently
occupies is far from the N7.
The Vredendal Traffic Centre located on the third floor needs to be relocated. Office space or a
satellite office is needed in Citrusdal as an extension of Vredendal.
N2/ Southern Cape Improvement of office facilities is needed at Caledon.
New offices are needed at Barrydale/ Hermanus.
There is a need to establish a radio control room in George.
Office accommodation for 3 road safety officers or alternatively be accommodated at the York
Park Building.
All traffic centres Direction signs indicating location of traffic centres are needed.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
59
Programme 6: Community-Based Programmes
Unit Projected demand
(location, projected staff, indicative area (m2)
Budgeted full
accommodation costs
2019/20 2019/20 2020/21
Directorate: EPWP CIIE Staff members are currently located at, 17th Floor Atterbury House.
Three storerooms are needed.
To be determined by
Custodian
Directorate: EPWP Coordination
and Compliance
Staff members are currently located at 17th Floor Atterbury House.
40 m2 of storage space is required.
Directorate: Professional
Development
Staff members are currently located at decanting space, 17th Floor Atterbury House.
Additional office accommodation for 19 staff members and 2 graduate interns.
Storage space required with the following specifications:
• Marketing material that includes, gazebos, fold-up tables and chairs, table cloths, various
pop up banners, display items for posters, application forms, pamphlets, branded items for
distribution at youth events, etc.
• Equipment for marketing, partnership liaison and campus meetings with bursars, i.e. mobile
printer, three laptops, projectors, for safekeeping in a steel cabinet.
• Bursary application forms that contain private information (last 2 years prior to archiving).
• Photo frames and gold paper for award ceremonies (+200).
• Bulk paper for peak time printing.
• Numerous files, partner company agreements, etc.
• Binding machines.
• First aid kits required for campus visits and events.
Annual MiSS Committee reports and historical data since 2006 for statistical purposes.
Directorate: EPWP CIIE Regional
Offices
Staff members of this Directorate are located in Ceres, George, Beaufort West, Grabouw and
Saldanha. Accommodation is optimal at these facilities.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
60
Schedule 8: New asset requirements
Town Description Details
Cape Town New Office Building Provide newly constructed office building to make provision for the new proposed organisational structure
of the Chief Directorate: Road Network Management
Brackenfell New Office and traffic centre Provide newly constructed building at Gene Louw College to accommodate head office staff and
relocation of the Brackenfell traffic centre from the Parow
Caledon Traffic centre Acquire accommodation for the relocation of the Caledon traffic centre. Need accommodation to
relocate traffic centre possibility of utilising a shared office building for a small-scale Beaufort West model.
Worcester Traffic centre
impound facility
Custodian to conduct urgent feasibility study of acquiring the Shell Ultra-City site for the relocation of the
Worcester office.
Laingsburg Traffic centre Acquire accommodation for the relocation of the Laingsburg traffic centre and need to be located close
to the N1. Current condition of the building is not user friendly.
Leeu Gamka Traffic centre Currently no accommodation. Need to acquire new accommodation at the same location as the
Department of Health, Emergency Medical Services station in Leeu Gamka for a small-scale Beaufort West
model.
Oudtshoorn Traffic centre Acquire accommodation for the relocation of the Oudtshoorn traffic centre. Current condition of the
building is not user friendly.
Mossel Bay Traffic centre
Impound facility
Acquire accommodation for the relocation of the Mossel Bay traffic centre. Will be part of the shared office
buildings on the ground floor as this is better access for the public.
Van
Rhynsdorp
Traffic centre Vredendal centre to be relocated to the Van Rhynsdorp for a small-scale Beaufort West model. Acquire
accommodation to relocate closer to the N7, to service the international corridor towards Namibia.
Citrusdal Traffic centre No traffic centre is located between the existing Vredendal and Vredenburg office. Acquire new traffic
centre in Citrusdal for a small-scale Beaufort West model.
Barrydale Traffic centre No traffic centre in place between the existing Worcester and Oudtshoorn office. Acquire new traffic centre
in Barrydale for a small-scale Beaufort West model.
Swellendam Impound facility Require Impound facility
Rawsonville Impound facility Impound facility
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
61
Town Description Details
Brackenfell Office accommodation
Traffic centre
Construct new office accommodation at Gene Louw Traffic College for the relocation of Chief Directorate:
Traffic Management.
Relocation of the Brackenfell traffic centre from Parow to revamped mobile structures at Gene Louw Traffic
College.
Ceres Ceres Road Camp Reconfigure for efficiency
George GMT Regional Office and
vehicle holding site in George
The current GMT Regional office is operating from a small office in the EMS Rescue base in George, with
parking space for only two government vehicles utilised by the staff. There is a need for office
accommodation for seven (7) GMT officials and parking for 160 vehicles.
Cape Town GMT Cape Town Office
Accommodation
Provide office accommodation in phased manner as part of the strategy to relocate GMT Cape Town and
Paarden Eiland to 3 Rusper Street, Maitland.
Maitland GMT Maitland Rusper Street
vehicle holding facility To provide a solution to accommodate 750 additional parking spaces adjacent to 3 Rusper Street, Maitland
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
62
Schedule 9: Rehabilitation, Renovations and Refurbishments
Please see “Section 4: Refurbishment plan”
Project name Town
IDMS
Stage/Project
Status
Total
project cost
Total
expenditure
(until 31
March 2019)
Total
available
MTEF forward
estimates
R’000 R’000 2019/20 2020/21 2021/22
R’000 R’000 R’000
Modernisation 9 Dorp Street (6th Floor) Cape Town Works
Completed 24 780 22 700 2 080 - -
Modernisation 9 Dorp Street (7th Floor) Cape Town Infrastructure
Planning 23 352 853 3 293 18 706 500
Modernisation 9 Dorp Street (8th & 9th Floor) Cape Town Infrastructure
Planning 32 576 3 713 28 545 318
Modernisation 9 Dorp Street (enablement work ground, 4th
and 8th floors) Cape Town
Works
Completed 5 023 5 023 - - -
Modernisation 9 Dorp Street Atrium Phase 2 Cape Town Works 2 368 800 1468 100
Modernisation York Park Ground and First Floor George Works
Completed 41 713 35 536 5 347 830 -
Modernisation York Park Master Plan and 4th Floor George Infrastructure
Planning 25 000 200 3 000 20 000 1 800
GMT Rusper Street – Office Accommodation – Phase 2 Maitland Procurement
Planning 100 795 12 538 46 130 41 466 661
13 Dorp Street Precinct Cape Town Infrastructure
Planning - - 400 - -
Modernisation-(Minor)- Gene Louw Traffic College Bellville Works
Completed 9 410 7 435 1 975 -
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
63
Project name Town
IDMS
Stage/Project
Status
Total
project cost
Total
expenditure
(until 31
March 2019)
Total
available
MTEF forward
estimates
R’000 R’000 2019/20 2020/21 2021/22
R’000 R’000 R’000
Modernisation- Gene Louw Traffic College: Shooting Range Bellville Infrastructure
Planning 14 436 1 482 11 044 1 908 -
Mossel Bay SSC Mossel Bay Works 58 680 11 000 30 343 16 337 1 000
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
64
Schedule 10: Assets identified for surrender (WCG-owned)
Town Asset description Surrender rationale Date to be surrendered to
Custodian
Potential contingent liabilities
(contractual obligations)
Cape Town N2 Mobile Traffic Law Enforcement
Satellite Office
Safety and security risks immediately None
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
65
Schedule 11: Repair requirements
Asset Repair description Status
R' million
Comment Total
Estimated
Cost
2019/20 2020/21 2021/22
Alfred Street complex. General Maintenance including electrical, fire,
accessibility, security and OHS compliance. (Block B
stores)
Planning. 20 15 5 -
-
Replace the roof and ceilings. (All buildings) Planning. 10 5 5 - Shared Office
Building.
Chiappini Street Soil
Laboratory.
General Maintenance including electrical, fire,
accessibility, security and OHS compliance as well
as repairs to roofs, prefab laboratories and parking
area. (This should be considered in context of
possible relocation of the lab)
Planning. 11 11 - - -
Ceres DRE. General Maintenance including electrical, fire,
accessibility, security and OHS compliance as well
as repairs to roofs and air conditioning.
Replace/repair prefab building structures.
Procured. 3 3 - - Leased-in
building.
Ceres road camps
and houses.
General maintenance to houses. Proper
infrastructure at the various satellite offices (road
camps) This infrastructure should consist of locker
room/s, meeting room/ administrative office, stores,
toilet/ shower facilities as well as liveable sleeping
facilities for “roaming construction teams”.
Likely to relocate by the middle of November 2019.
The new location can accommodate the staff from
the DRE office and supporting teams from the area
and the staff from Cape Winelands District
municipality.
Associated road camps
Malmesbury; Hopefield; Piketberg; Clanwilliam;
Klawer and Vanrhynsdorp.
Planning. 15 3 6 6 -
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
66
Asset Repair description Status
R' million
Comment Total
Estimated
Cost
2019/20 2020/21 2021/22
Oudtshoorn DRE
Office.
Parking area to be paved and replace sewer
reticulation system. Planning. 3.5 3.5 - - -
Oudtshoorn
road camps and
houses.
General maintenance to houses. Proper
infrastructure at the various satellite offices (road
camps) This infrastructure should consist of locker
room/s, meeting room/ administrative office, stores,
toilet/ shower facilities as well as liveable sleeping
facilities for “roaming construction teams”.
Associated road camps
Laingsburg; Prins Albert; Klaarstroom; Leeu Gamka;
Beaufort West; De Rust; Uniondale; Plettenberg Bay;
George; Oudtshoorn and Ladismith.
Planning. 15 3 6 6 -
Paarl DRE. General Maintenance including electrical, fire,
accessibility, security and OHS compliance as well
as repairs to roofs and air conditioning.
Replace/repair prefab building structures.
Planning. 15 3 6 6 -
Paarl office
accommodation,
roads camps and
houses.
General maintenance to houses.
Proper infrastructure at the various satellite offices
(road camps). This infrastructure should consist of
locker room/s, meeting room/ administrative office,
stores, toilet/ shower facilities as well as liveable
sleeping facilities for “roaming construction teams”.
Associated road camps
Botrivier; Caledon; Stanford; Napier; Worcester;
Ashton; Swellendam and Barrydale
Bellville Mechanical
Workshop.
General Maintenance including electrical, fire,
accessibility, security and OHS compliance as well
as repairs to roofs and air conditioning.
Replace/repair prefab building structures and
provide ablution and kitchen facilities
Planning. 10 10 - - -
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
67
Asset Repair description Status
R' million
Comment Total
Estimated
Cost
2019/20 2020/21 2021/22
Vangate Shared
Service Centre.
Re-organise the front desk to provide professional
image. Revamp storeroom into an archive facility
to address filing challenge. General maintenance
and address defects on entire building including
water proofing, floor coverings, mechanical,
electrical and structural.
Scoping. 15 5 10 - Shared Office
Building
GMT Warehouse
Maitland.
Critical
Install an overhead sprinkler system. Install the
required emergency key boxes/ push bar locks to
allow easy access to evacuation routes in the
event of an emergency, evacuation signs.
Replace loose/ unstable vibracrete pillars and
slabs.
Scoping. 2.5 2.5 - - -
GMT Hope Street General Maintenance including electrical, fire,
accessibility, security and OHS compliance.
Replace/repair main sewer line.
Scoping. 2.5 2.5 - - -
GMT Roeland Street General Maintenance including electrical, fire,
accessibility, security and OHS compliance. Scoping. 4 4 - - -
Piketberg: Provincial
Regulatory Entity.
Fire compliance, Emergency key box, Install
security burglars on the windows, alarm and an
intrusion detection system
Planning. 3.5 3.5 - - The current
building (church
street) is the
owned
accommodation
building and the
future plan to do
extension in the
existing building
to solve the
shortage of
accommodation.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
68
Asset Repair description Status
R' million
Comment Total
Estimated
Cost
2019/20 2020/21 2021/22
Swellendam Traffic
Centre.
General Maintenance including electrical, fire,
accessibility, security and OHS compliance.
Convert garage into conference/ training facility to
accommodate ± 50 people.
Provide burglar bars/ security gates.
Renovation of courtyard.
Replace doors (front entrance and back exit) of
the office and safety gates.
Erect new carport.
Planning. 4.5 4.5 - - -
George Traffic Centre. General Maintenance including electrical, fire,
accessibility, security and OHS compliance. The
proud Provincial Traffic Services emblem needs to
be erected in front of the building.
Scoping. 3.5 - 3.5 - -
Gene Louw Traffic
College.
General Maintenance including electrical, fire,
accessibility, security and OHS compliance. Agility
track upgrade.
Planning. 5 5 - - -
Knysna Traffic Centre. OHS, Install smoke detectors/ fire alarm, PA system,
CCTV cameras. OHS, Replacement of the broken
tiles on the balcony, fit barrier glass window to
separate staff from public, overhead hanging
evacuation and fire equipment signs,
replacement/ fitment of door locks and slide barrel
locks and burglar bars/security door, fasten fire arm
safe to ground and secure environment.
Planning. 0.5 - - 0.5 Leased-in.
Mossel Bay Traffic
Centre.
General Maintenance including electrical, fire,
accessibility, security and OHS compliance. Fasten
fire arm safe to ground and secure environment,
burglar bars/security gate, evacuation steps/ramp.
Planning. 1 - - 1 Leased-in.
Oudtshoorn Traffic
Centre.
General Maintenance including electrical, fire,
accessibility, security and OHS compliance.
Enlargement of reception area.
Scoping. 1 - 1 - Leased-in.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
69
Asset Repair description Status
R' million
Comment Total
Estimated
Cost
2019/20 2020/21 2021/22
Laingsburg Traffic
Centre.
General Maintenance including electrical, fire,
accessibility, security and OHS compliance. Supply
and display the required overhead hanging
evacuation and fire equipment signs. Provide
manual override on the automated security gates
in the event of a power failure to ensure escape
routes is still accessible. Fit work station/ counter in
new administration section.
Scoping. 1 - 1 - Leased-in.
Beaufort West Traffic
Centre.
Check OHS compliance. Supply and display the
required overhead hanging evacuation and fire
equipment signs, PA system.
Scoping. 1 - - 1 Shared office
building.
Brackenfell Traffic
Centre. (located in
Parow)
General Maintenance including electrical, fire,
accessibility, security and OHS compliance.
Install additional air-conditioning.
Planning 3.5 - - 1 -
Worcester Traffic
Office.
General Maintenance including electrical, fire,
accessibility, security and OHS compliance.
Additional toilet facilities, including for disabled.
Upgrade existing perimeter security fence. Enatis
point radio control. Provision of security measures to
the perimeter fence in place to reduce or eliminate
the security breaches.
Construction 3 3 - - -
Vredenburg Traffic
Centre.
General Maintenance including electrical, fire,
accessibility, security and OHS compliance.
Repair two magnetic systems of security gates of
office building. Aircon for the impound masters’
office. New office accommodation for impound
Master. Electric fencing. Bullet trap to be moved to
the strong room. Firearms safe to be affix to the wall
or floor
Scoping. 3 - 3 - -
Vredendal Traffic
Centre.
General Maintenance including electrical, fire,
accessibility, security and OHS compliance.
Firearms safe to be affix to the wall or floor.
Scoping. 1 - - 1 Leased-in.
ANNEXURES
ANNEXURES
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
70
Annexure A
Legislative mandates
Function Legislation
Transport Administrative Adjudication of Road Traffic Offences Act, 1998 (Act 46 of 1998)
Advertising Along Roads and Ribbon Development Act, 1940 (Act 21 of 1940)
National Land Transport Act, 2009 (Act 5 of 2009)
National Road Traffic Act, 1996 (Act 93 of 1996)
National Qualifications Framework Act, 2008 (Act 67 of 2008)
Road Safety Act, 1972 (Act 9 of 1972)
Road Traffic Act, 1989 (Act 29 of 1989)
Road Traffic Management Corporation Act, 1999 (Act 20 of 1999)
Road Transportation Act, 1977 (Act 74 of 1977)
Western Cape Provincial Road Traffic Administration Act, 2012 (Act 6 of 2012)
Western Cape Road Transport Act Amendment Law, Law 8 of 1996
Western Cape Toll Road Act, 1999 (Act 11 of 1999)
Cape Roads Ordinance, 1976 (Ordinance 19 of 1976)
Public Works
and Property
Management
Government Immovable Asset Management Act, 2007 (Act 19 of 2007)
National Building Regulations and Building Standards Act, 1977 (Act 103 of 1977)
National Heritage Resource Act, 1999 (Act 25 of 1999)
Western Cape Land Administration Act, 1998 (Act 6 of 1998)
Transversal Appropriation Bill (Annual)
Basic Conditions of Employment Act, 1997 (Act 75 of 1997)
Basic Conditions of Employment Act, 1997 (Act of 1997): Ministerial Determination 4:
Expanded Public Works Programme, gazetted 4 May 2012
Broad-Based Black Economic Empowerment Act, 2003 (Act 53 of 2003)
Competition Act, 1998 (Act 89 of 1998)
Construction Industry Development Board Act, 2000 (Act 38 of 2000)
Consumer Protection Act, 2008 (Act 68 of 2008)
Control of Access to Public Premises and Vehicles Act, 1985 (Act 53 of 1985)
Criminal Procedure Act, 1977 (Act 51 of 1977)
Division of Revenue Act (Annual)
Employment Equity Act, 1998 (Act 55 of 1998)
Firearms Control Act, 2000 (Act 60 of 2000)
Intergovernmental Relations Framework Act, 2005 (Act 13 of 2005)
Labour Relations Act, 1995 (Act 66 of 1995)
Local Government: Municipal Systems Act, 2000 (Act 32 of 2000)
National Environmental Management Act, 1998 (Act 107 of 1998)
Occupational Health and Safety Act, 1993 (Act 85 of 1993)
Preferential Procurement Policy Framework Act, 2000 (Act 5 of 2000)
Prevention and Combating of Corrupt Activities Act, 2004 (Act 12 of 2004)
Promotion of Access to Information Act, 2000 (Act 2 of 2000)
Promotion of Administrative Justice Act, 2000 (Act 3 of 2000)
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
71
Function Legislation
Protection of Personal Information Act, 2013 (Act 4 of 2013)
Provincial Archives and Records Service of the Western Cape Act, 2005 (Act 3 of
2005).
Public Finance Management Act, 1999 (Act 1 of 1999)
Public Service Act, 1994 (Proclamation 103 published in Government Gazette15791
of 3 June 1994)
Public Administration Management Act, 2014 (Act 11 of 2014)
Radio Act, 1952 (Act 3 of 1952)
Skills Development Act, 1998 (Act 97 of 1998)
Western Cape Land Use Planning Ordinance, Amendment Act, 2009 (Act 1 of 2009)
Western Cape Procurement (Business Interests of Employees) Act, 2010 (Act 8 of
2010)
Western Cape Monitoring and Support of Municipalities Act, 2014 (Act 4 of 2014)
Policy mandates
Function Policies
Transport National Freight Logistics Strategy, 2005
National Public Transport Strategy, 2007
National Road Safety Strategy, 2009-2015
National Road Safety Strategy, 2011-2020
National Rural Transport Strategy, 2007
Road Access Guidelines
Road Infrastructure Strategic Framework for South Africa
Road Safety Strategy for the Western Cape Province, 2005
Western Cape Policy Statement on Transport for Special Needs Passengers, 2009
White Paper on National Transport Policy, 1996
White Paper on Provincial Transport Policy, 1997
Public Works
and Property
Management
National Infrastructure Maintenance Strategy
Western Cape Provincial Acquisition Policy
Western Cape Provincial Government White Paper on the Management of
Provincial Property, 2004
Western Cape Infrastructure Framework, 2013
Western Cape Provincial Property Disposal Policy
Expanded
Public Works
Programme
Guidelines on the implementation of the Expanded Public Works Programme
Guidelines on the Implementation of the National Youth Service
Transversal Departmental Monitoring and Evaluation Framework and Manual
Departmental Monitoring and Evaluation Framework and Manual
Departmental Records Management Policy
Guidelines on the implementation of the Expanded Public Works Programme
Guidelines on the Implementation of the National Youth Service
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
72
Function Policies
Medium Term Budget Policy Statement 2016-2019
Provincial Strategic Plan, 2015/16-2019/20
Western Cape E-Mobility Policy
Western Cape Government Transversal Management System
White Paper on Human Resource Management, 1997
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
73
Annexure B
Methodology for determining Functional Performance of Accommodation
Required Performance Standard
The required performance rating is allocated in accordance with the function that the
accommodation is required to perform. Table 7 below can be used to determine the
required performance rating for each immovable asset.
Table 6: Required Performance Standard
Performance standard Condition standard Index
Highly sensitive function with critical
results (e.g. hospital operating theatre) or
high profile public building (e.g.
Parliament Building).
Accommodation to be in best possible
condition. Only minimal deterioration will be
tolerated.
P5
Business operations requiring good public
presentation and high-quality working
environments.
Accommodation to be in good condition
operationally and aesthetically, benchmarked
against industry standards for that particular
class of accommodation.
P4
Functionally-focussed accommodation
at utility level (e.g. school).
Accommodation to be in reasonable condition,
fully meeting operational requirements.
P3
Functions are providing essential support
only, with no critical operational role (e.g.
storage) or accommodation has limited
life.
Condition needs to meet minimum operational
requirements oy.
P2
Functions have ceased and
accommodation is dormant; pending
relinquishment, etc.
Condition can be allowed to deteriorate or
marginally maintained at minimal cost.
P1
Accessibility Rating
The accessibility rating provides an indication of the accommodation’s physical location
in relation to the service delivery objectives. This includes where the accommodation is
(address) as well as the accessibility of the accommodation for the general public, or
members that have to conduct their business at the accommodation. Table 8 below can
be used to allocate an accessibility rating for the accommodation.
Table 7: Accessibility Rating
General description Rating
The accommodation ‘s location fully supports service delivery objectives; is fully accessible
to the general public with well-designed public areas and parking; fits in the current
neighbourhood and environmental elements; and is accessible for the physically
challenged.
A5
The accommodation’s location supports service delivery objectives; is fairly accessible to
the general public with moderately designed public areas and parking; fits in the current
neighbourhood and environmental elements; and is accessible for the physically
challenged to the main areas.
A4
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
74
General description Rating
The accommodation’s location partially supports service delivery objectives; is accessible
to the general public with limited public areas and parking; does not fully fit in the current
neighbourhood and environmental elements; and has limited accessibility for the
physically challenged.
A3
The accommodation’s location limits support service delivery objectives; is not generally
accessible to the general public with limited public areas and parking; does not fir in the
current neighbourhood and environmental elements; and is not accessible for the
physically challenged.
A2
The accommodation’s location does not meet service delivery objectives; is not at all
accessible to the general public and should not be used for the current service delivery
objectives.
A1
Suitability Index
The required performance standard allocated in Table 6 as well as the accessibility rating
allocated in Table 7 is used as cross references to determine the suitability index of the
asset as indicated in Table 8 below.
Table 8: Suitability Index
Accessibility rating
Required
performance
standard
A1
(very poor)
A2
(poor)
A3
(fair)
A4
(good)
A5
(excellent)
P5 C C B A A
P4 C C B A A
P3 C B B A A
P2 C B A A A
P1 C C C C C
A Accommodation is fully suitable for its required function
B Accommodation meets the minimum suitability criteria for its function.
C Accommodation does not meet the required suitability criteria.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
75
User Condition Rating
The condition rating is utilised to give a brief indication of the physical condition of the
asset (It should be noted that this is not a full condition assessment). Table 9 below is used
to allocate a condition rating to the accommodation.
Table 9: Condition Rating
Condition
status General description Rating
Excellent Accommodation has no apparent defects. Appearance is as new.
Risk index: No effect on service capability. No risk. C5
Good
Accommodation exhibits superficial wear and tear, with minor defects and
minor signs of deterioration to surface finishes.
Risk index: Intermittent, minor inconvenience to operations. Probability of risk to
health and safety or property is slight. Low cost implication.
C4
Fair
Accommodation is in average condition, deteriorated surfaces require
attention; services are functional, but require attention, backlog maintenance
work exists.
Risk index: Constant inconvenience to operations. Some risk to health and
safety or property. Medium cost implications.
C3
Poor
Accommodation has deteriorated badly, with serious structural problems.
General appearance is poor with eroded protective coatings; elements are
broken, services are not performing; significant number of major defects exists.
Risk index: Major disruption to service capability, high probability of risk to health
and safety or property. High cost implication/financial loss.
C2
Very Poor
Accommodation has failed; is not operational and is unfit for occupancy.
Risk index: Accommodation is unusable, immediate high risk to security, health
and safety or property. Significant cost impact.
C1
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
76
Operating Performance Index
The operating performance is determined by a cross reference between the required
performance standard and the condition rating. Table 10 below is used to determine the
operating performance index.
Table 10: Operating Performance Index
Required
performance
standard
Condition Rating
C1
(very poor)
C2
(poor)
C3
(fair)
C4
(good)
C5
(excellent)
P5 3 3 3 2 1
P4 3 3 2 1 1
P3 3 3 2 1 1
P2 3 2 1 1 1
P1 2 2 1 1 1
1 Accommodation standards exceeds the level expected for functional and operational
requirements.
2 Functional Performance meets the standards expected for functional and operational
requirements
3 Functional Performance does not meet the standard expected for functional and operational
requirements
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
77
Functional Performance Index
The functional performance rating is determined by utilising the suitability index as well as
the operating performance index that was determined in the previous steps. Table 11
below can be utilised to determine the functional performance rating.
Table 11: Functional Performance Index
Operating performance index
Suitability index 1 - Optimal 2 - Minimum 3 - Outside
Optimal - A A1 A2 A3
Minimum – B B1 B2 B3
Outside - C C1 C2 C3
Functional
Performance
Index
Description
A1 The asset is operating optimally and is fully suitable for its required function
A2 The asset meets the minimum operating criteria and is fully suitable for its required
function
A3 The asset does not meet the minimum operating requirements but is fully suitable
for its required function
B1 The asset meets the minimum operating and suitability criteria for its required
function
B2 The asset does not meet the minimum operating criteria but meets the minimum
suitability criteria for its required function
B3 The asset does not meet the minimum operating criteria but meets the minimum
suitability criteria for its required function
C1 The asset does not meet the minimum operating criteria but meets the minimum
suitability criteria for its required function
C2 The asset meets the minimum operating criteria but does not meet the minimum
suitability criteria
C3 The asset does not meet the minimum operating criteria and does not meet the
minimum suitability criteria
The functional performance index should be utilised by the User to select the
appropriate action for the asset. Figure 4 below illustrates the decision framework
(prioritisation) that must take place based on the outcome of the analysis of the different
inputs as outlined earlier. In the event that a facility has been indicated as a Group C
facility then a feasibility study must be undertaken to ascertain the future use of the facility.
The feasibility study will include prioritisation criteria such as population demographics,
costing implications, available budgets etc. There are shortcomings in the outcome of the
functional performance index calculation in that it will not always display a true reflection
of the functionality of the building. The building can be in a relatively good condition and
in the correct location but, for example, due to advancement in technology and
changed and increased operational requirements, may no longer be suitable for the
facility as it stands. Furthermore, a facility may be functional, correctly placed and in good
condition but may be too small to serve the population in the area and may thus need to
be replaced.
Department of Transport and Public Works
User- Immovable Asset Management Plan
2019/20 Financial Year
78
Figure 4: Decision Framework based on the condition assessment of immovable assets
Western Cape Transport and Public Works
9 Dorp Street, Cape Town, 8001
Private Bag X9185, Cape Town,
Tel: +27 86 021 2414
Website: www.westerncape.gov.za
Email: [email protected]