neustar questions “as the npac” reidway - napm llc · the neustar npac notify pas with...
TRANSCRIPT
Transition Outreach and Education Plan Public Questions List
1 | P a g e
The following table contains responses to written questions submitted through the comments feature on
the LNPA Transition tab of the napmllc.org website, or the TOEP webcasts, for which the party
submitting the question provided authorization to publish, provided the question (i) is of common
interest to the NPAC Community, (ii) has not been previously asked and answered, and (iii) is not
otherwise inappropriate.
Date Submitter Organization Question / Response
8/10/2017 Bill Reidway
Neustar Neustar Questions “as the NPAC”
Q1 Is there a contingency plan for the event iconectiv is not able or willing to
deliver, or service providers are unable to retrieve [the transaction report]?
The report which iconectiv provides is supplemental to SPs own records. If
iconectiv were unable to provide the report, then SPs would be expected to re-create the list of transactions.
Q2
Will larger providers be given priority over smaller providers?
Service Providers will all be treated equally; larger SPs will not be prioritized ahead of smaller providers.
Q3 Will there be a test / dry run of the proposed rollback plan?
A rollback simulation is not practical and is not planned. However, the
report creation and distribution process will be tested, and Service Providers are expected to test their own internal resubmission processes as
a preparatory measure.
Q4
What will trigger the creation of NPA-NXX-X records for pooling?
This is to be determined in discussions with the Pooling Administrator.
Q5
Is there a plan to address inter-SP ports in conflict upon resubmission?
Service Providers will need to coordinate porting activity with their peers
during rollback to prevent inter-SP conflict. Note that these requests will
already have been coordinated once so a second "re-coordination" should
be manageable.
Transition Outreach and Education Plan Public Questions List
2 | P a g e
Date Submitter Organization Question / Response
Q6
When Neustar restarts its NPAC a large volume of timers will expire,
particularly for pending SVs. Does the rollback plan account for any
database clean-up which may be necessary?
The assumption is that the timers will expire as they usually do exiting the
maintenance window. Service Providers should take the appropriate
actions in response to the timer expiration.
Q7
If large numbers of transactions are resubmitted to NPAC manually by the
service providers is there a plan to avoid / mitigate human error?
Service Providers would follow normal porting processes to resubmit
transactions in the event a rollback were required.
Q8
If providers build automated solutions for resubmitting transactions, is
there an expectation that they be throttled in any way, to ensure the LNP
ecosystem isn’t impacted by high volumes?
If Service Providers build automated processes they will be expected to
stay within the defined industry volumes. The NPAC would similarly be
expected to handle the volumes in the same manner as is done today.
Questions “as a Vendor and Service Bureau”
Q1 Should the rollback scenarios be considered temporary, permanent, or
should stakeholders plan for both possibilities?
Rollback should be considered a temporary state, to be resolved as rapidly
as is prudent.
Q2a For how long will providers be asked to keep records of transactions?
Service Providers are expected to retain records of transactions as per their
normal practices. They should be retained for rollback for a minimum of
one week after migration unless notified by the TOM.
Transition Outreach and Education Plan Public Questions List
3 | P a g e
Date Submitter Organization Question / Response
Q2b
Will iconectiv provide their reports only in the event of a rollback, or will they be generated automatically on a daily basis on iconectiv’s SFTP site?
iconectiv will post one or more reports for each participating Service Provider (that has successful transactions) to the SFTP site for download
only in the event of rollback. Note that these reports are intended to supplement, not replace, providers' own records.
Q3
When will the TOM provide details on all milestones and specific dates for
the additional rollback meetings?
The meetings and delivery schedule have been announced in the industry rollback presentations; this will continue in future presentations.
Q4a
How will providers that do not attend the TOM managed open conference bridge/WebEx be notified of a rollback decision?
Notification of a rollback decision will be provided via the open conference bridge, WebEx, and via iconectiv email to the primary contact of all
registered users.
Q4b Will iconectiv send reports directly to the NPAC or to Service Bureaus to
act on behalf of SPs?
iconectiv will post transaction reports for each participant Service Provider
to the SFTP server. All Users will be provided SFTP access and credentials as part of onboarding.
Q5
Can the TOM share the details of its 18-month feasibility study, detailing the options reviewed and criteria used to ensure that its proposed solution
was the most cost-effective and operationally efficient?
The TOM facilitated a series of joint reviews with iconectiv, Neustar, and
the NAPM throughout 2016/17 to develop and evaluate options. The results of this evaluation and NAPM decision have been shared in the various
TOEP sessions and Industry Rollback Working Sessions.
Q6
What protections, if any, are in place to guard against iconectiv being
Transition Outreach and Education Plan Public Questions List
4 | P a g e
Date Submitter Organization Question / Response
unable or unwilling to provide the necessary data for service provider
reflows?
The report which iconectiv provides is supplemental to SPs own records. If
iconectiv were unable to provide the report, then SPs would be expected to re-create the list of transactions.
Q7a
Can the TOM share the report specification availability, format, and testing period information?
This information was provided at the August Industry Rollback Working Session, please refer to the material posted at http://napmllc.org under the
LNPA Transition tab.
Q7b Will the reports be simple transaction logs, or will they have additional
information to compute dependencies and sequencing requirements? Will the reports at a minimum be time-sorted?
The reports will provide a detailed record of every successful transaction as described in the August Industry Rollback Session. The transaction report
specification package (containing the specification spreadsheet, a guide to understanding the spec, and an example file) was distributed 25 August to
all registered users.
Q7c
Will the testing period include providers testing the reports with their vendors and current NPAC?
iconectiv will test the report creation and distribution process with Service
Providers beginning in January 2018. Service Providers may involve other parties, including service bureaus, at their discretion.
Q7d
Will service bureaus and providers be included in the process design and
transaction report format specifications that iconectiv and the TOM will deliver?
Industry feedback regarding the report format and process is always
evaluated when received. The report process and format were designed by iconectiv at TOM request. Industry feedback was solicited at both the July
and August Industry Rollback Working Sessions. Feedback received as of
24 August, prior to release of the specification, was considered for
Transition Outreach and Education Plan Public Questions List
5 | P a g e
Date Submitter Organization Question / Response
inclusion.
Q7e
Will current NPAC validate that they can receive the reports iconectiv will
provide to each provider? Is there a test plan/dry run?
The NPAC does not receive Transaction reports, these are distributed to service providers. The NPAC will only be required to process porting
transactions as normal via CMIP, XML, MUMP, et al.
Q8a
How long may out-of-synch condition between the NPAC and LSMSs be tolerated?
Each SP should make its own determination as to when they are ready to
re-sync an LSMS with the NPAC. We expect that this will be region and Service Provider specific.
Q8b
How will vendors and service providers know that the roll-back is
complete?
A conference bridge and WebEx will be used to provide regular reporting on system status during each transition. These will be opened when
transition begins and will be maintained on an as-needed basis until the region(s) are accepted. In the event of rollback, these will be used to
provide regular reporting on rollback progress to all participants.
Q8c
If the LSMSs are not reconnected immediately, and some providers / service bureaus require an LSMS check for Old-SPID validation as part of
the pre-port activities for the re-flowed transactions, how will this be done?
Each SP should make its own determination as to when they are ready to re-sync an LSMS with the NPAC. We expect that this will be region and
Service Provider specific.
Q9a
Will the industry introduce any changes to standard processing?
No change to standard processing is planned.
Q9b
Will any regular NPAC activity be suspended while the reflow process is
Transition Outreach and Education Plan Public Questions List
6 | P a g e
Date Submitter Organization Question / Response
being executed?
We do not anticipate suspension of regular NPAC activity. However, we
anticipate that Service Providers may elect to prioritize completion of old
(re-flow work) ahead of new work during the period immediately following rollback.
Q10
Will service providers and service bureaus be expected to throttle re-flowed transactions, to avoid exceeding performance parameters in other SOAs /
LSMSs receiving broadcasts and notifications?
If Service Providers build automated processes they will be expected to stay
within the defined industry volumes. The NPAC would similarly be expected to handle the volumes in the same manner as is done today.
Q11
Is there a dry run planned for the selected approach?
A rollback simulation is not practical and is not planned. However, the
report creation and distribution process will be tested, and Service Providers are expected to test their own internal resubmission processes as
a preparatory measure.
Questions “as the Pooling Administrator”
Q1
Will the service providers request that PAS resubmit requests to create the
dash-X elements or will they ask the NPAC directly?
This is to be determined in discussions with the Pooling Administrator.
Q2
Will there be any need on the part of the PA to store, reprocess, or
distribute the NPAC work item history, or history of Part 1B and Part 5
records, as part of roll-back?
This is to be determined in discussions with the Pooling Administrator.
Q3
What, if any, coordination is required to ensure proper sequencing of
event processing as part of roll-back? For example, block modifications on
blocks which have not been activated, etc.
Transition Outreach and Education Plan Public Questions List
7 | P a g e
Date Submitter Organization Question / Response
This is to be determined in discussions with the Pooling Administrator.
Q4
When pooled block activations are processed by the Neustar NPAC will
the Neustar NPAC notify PAS with work-item completion / deletion
status, and is the PA expected to re-notify service providers via email, as
today?
In the event of a rollback, the Neustar NPAC and the PA is expected to
return to normal operations and process work in the usual manner.
Q5
How will constituents be notified that the roll-back process is complete,
and that all processing is back to business as usual?
A conference bridge and WebEx will be used to provide regular reporting
on system status during each transition. These will be opened when
transition begins and will be maintained on an as-needed basis until the
region(s) are accepted. In the event of rollback, these will be used to
provide regular reporting on rollback progress to all participants.
Q6
What is the TOM’s test planning and execution schedule for the rollback
solution?
A rollback simulation is not practical and is not planned. However, the report creation and distribution process will be tested, and Service
Providers are expected to test their own internal resubmission processes as a preparatory measure.
Transition Outreach and Education Plan Public Questions List
8 | P a g e
Date Submitter Organization Question / Response
8/16/2017 Syed
Mubeen Saifullah
Neustar Per your slide, if release B is scheduled to end mid-Dec ... how are we
starting to test mid-Nov? How will 7 weeks of testing for an XML SOA product end in Mid-December if any issues are discovered?
The testing schedule is dependent on the type of system: CMIP SOA or LSMS, XML SOA, and XML LSMS have slightly different timelines.
1) Neustar CMIP systems (7 in total) are expected to begin Release B testing
in mid-December (on or about 18 Dec). There is little testing to be done, only 1 week is estimated, to verify the MUMP and NPA Split test cases that
could not be completed under Release A. Although only 1 week is
expected, three weeks are allocated to allow for regression testing and vacations. SPs using these Neustar CMIP systems will likely have already
completed their mandatory testing and will likely have begun Group and Round Robin...once Neustar completes these last few cases then SPs may
include the extra few features in their testing as well. 2) Neustar's XML SOA is expected to begin Release B testing in mid-
November (on or about 13 Nov). Comprehensive SOA testing is expected to take 7 weeks, however 8 weeks are allocated to allow for vacations.
3) Neustar's XML LSMS is expected to begin Release B testing in mid-
November (on or about 13 Nov). Comprehensive LSMS testing is expected to take 3 weeks, however 4 weeks are allocated to allow for vacations.
In all cases it should be noted that if extensive issues are discovered or any
repairs require an extended period for repair that this would necessarily reduce the time available for Service Providers to test those features.
8/16/2017 Syed
Mubeen Saifullah
Neustar In your timeline, where can we understand how much time they have
allocated for a circuit to be installed and tested?
Circuit install and testing is handled during the onboarding process, not as part of vendor certification or SB/SP testing. The TOM strongly
recommends that the Neustar Service Bureau begin onboarding as soon as
possible so as not to unduly burden its customers.
8/16/2017 Syed
Mubeen
Saifullah
Neustar How much time is going to be allocated for Release B CMIP functionality
testing and Required Regression Testing?
The total time allocated for Release B CMIP testing is two and 1/2 months.
We estimate that an LSMS will require 1 week for testing and a SOA will require 2 weeks for testing during this period.
Transition Outreach and Education Plan Public Questions List
9 | P a g e
Date Submitter Organization Question / Response
8/16/2017 Syed
Mubeen Saifullah
Neustar When was mid-December decided for CMIP? What is the Schedule for this
round of testing? This round of testing is from mid-December to 2/28/18. It has been the plan
from the beginning that the CMIP vendors would return to complete CMIP
testing.
8/16/2017 Syed
Mubeen Saifullah
Neustar How are customers who are on a SB and who are using XML going to
complete comprehensive testing? This seems like this schedule is putting XML clients in a very precarious position.
Based upon feedback from the industry, and the goal of allowing as much time as possible for Service Provider testing, additional analysis will be
done of specific vendor testing status, and if appropriate, Service Provider testing will start even if the vendor has not been certified. The remediation
of existing issues may occur outside the existing Release A testing windows and addressed in Release B.
8/16/2017 Syed
Mubeen
Saifullah
Neustar What is the schedule for resolving the PIMs and Change Orders being
discussed at the LNPA? Without these being resolved, how will systems be certified? What happens if issues are discovered and we have to go through
the PIM process for XML?
PIMs and Change Orders are expeditiously being worked through the
LNPA WG to ensure that a disposition is reached and solution is implemented and retested within the existing testing windows. Any issues
that are not resolved in Release A, will be fixed in Release B.
8/16/2017 Syed
Mubeen
Saifullah
Neustar How are systems being certified if there are outstanding issues on the
iconectiv side? In particular with the Change Order at the LNPA about
Error Codes? Do certified systems have to load the iconectiv Error Code File which isn't the same as the current NPAC?
Systems will only certified once all required test cases are completed. Failed
functionality will need to be retested once a fix is in place. Circuit install and testing is handled during the onboarding process, not as
part of vendor certification or SB/SP testing. The TOM strongly recommends that the Neustar Service Bureau begin onboarding as soon as
possible so as not to unduly burden its customers.
Transition Outreach and Education Plan Public Questions List
10 | P a g e
Date Submitter Organization Question / Response
8/16/2017 Syed
Mubeen Saifullah
Neustar Per the previous public statements of the TOM and iconectiv, Service
Provider testing would only happen once vendors were 100% certified. Why has this policy changed? What if issues are not resolved until Release
B or later in the year? How will carriers conduct their own
regression/certification? What is the time-table for resolving all these issues?
Service Provider testing will start even if vendor have not been certified to
ensure that adequate time is allotted for fixing and retesting any issues. The remediation of existing issues may occur outside the existing Release A
testing windows and be addressed in Release B.
8/16/2017 Syed Mubeen
Saifullah
Neustar Considering that "technical issues were identified" and also that many systems under test have exceeded their allocated time for testing, how are
you planning on addressing the extremely tight schedule for Release B testing?
The issues identified in Release A are actively being remediated through the required channels to identify and implement a solution within the
existing timelines. Vendor certification is not being required for the start of Service Provider testing to relieve pressures on existing schedules.
Contingent testing windows have been incorporated into the plan to allow for the resolution and testing of identified issues.
8/16/2017 Syed
Mubeen Saifullah
Neustar XML SOA certification is being allocated 7 or 8 weeks? Your chart says 7
weeks, however you stated 8 weeks verbally.
XML SOA certification testing is 7 weeks.
8/16/2017 Syed Mubeen
Saifullah
Neustar Per your survey 25% of users are employing the service of a SB. If they use XML, the time table I'm looking at puts their testing availability into Feb
2018. How are they supposed to compare to the carriers who have the ability to do testing starting in October?
The schedules was defined to allow for adequate time for testing across all
user groups. However, we will monitor progress closely to make necessary adjustments.
Transition Outreach and Education Plan Public Questions List
11 | P a g e
Date Submitter Organization Question / Response
8/16/17 John
Howison
Cincinnati
Bell
What happens to your timeline if you find issues with XML testing let alone
any rollback testing?
The XML testing schedule incorporates time for issue resolution and
retesting any fixes. We will closely monitor testing and make necessary adjustments for any issues that require remediation outside the existing
testing windows.
8/16/17 John
Howison
Cincinnati
Bell
What is the deadline for the LNPA WG to resolve all the open issues with
LSMS vendor testing?
A deadline has not been specified for the LNPA WG to resolve all open
issues with LSMS vendor testing. However, the LNPA working group recognizes the criticality of resolving these issues in an expedited manner.
Additional meetings were held in July and August to address the open issues.
8/16/17 John Howison
Cincinnati
Bell
Look at your 4th quarter. We do not perform upgrades from November to January. How will this impact LSMS testing if upgrades or patches are
required?
Any patches or upgrades needed for industry testing would be done in test systems only. This should not impact production systems during the
industry freeze period. See previous question for timing of production
upgrades
8/16/17 John
Howison
Cincinnati
Bell
What is the impact of testing my LSMS system IF my vendor is not
certified? Will I need to go back and re-test? How will issues be resolved with my vendor's system and with my system?
The purpose of Service Provider testing is to validate your User Profile. Any test cases currently failing with your vendor system will be fixed and
retested with your vendor and you will not need to re-test. You will, however, need to upgrade to your production LSMS to your vendor's
certified release level as quickly as possible after it has been certified, but no later than when transition is scheduled to begin April 7, 2018.
Transition Outreach and Education Plan Public Questions List
12 | P a g e
Date Submitter Organization Question / Response
7/19/17 Syed
Mubeen Saifullah
Neustar For Release B, how is the iconectiv/TOM planning on managing testing
efforts for the functions delta (new functions), the mandatory Regression testing for Vendors and Mechanized Users as well as XML testing. Per the
time-table, only 7 weeks are allocated (vs. 8 weeks for Release A), how do
we anticipate fixing any defects which may be discovered during that period?
Vendor testing begins November 13th, 2017. We expect that an XML SOA
will require seven (7) weeks to complete certification and that an XML LSMS will require four (4) weeks to complete certification. If testing begins
promptly, and no major issues are found with the vendor system(s), this
would result in certification near the end of 2017 for SOAs, and somewhat earlier for LSMSs. This allows nine (9) weeks for SP testing of an XML SOA,
and somewhat longer for an XML LSMS. If substantial issues are found during Vendor certification, the additional time for repair and regression
testing would reduce the time available for SP testing.
Please note that Release B includes more components than just the XML interface. These components (MUMP, IVR, billing, etc.) are not dependent
on XML and may be tested beginning as early as January 2nd, 2018.
7/19/17 Syed Mubeen
Saifullah
Neustar When will the industry have an opportunity to review the Roll-Back testing plan?
The new LNPA will test the processes, procedures, and governance as part
of the regional transition testing. Additional details on the overall plan will
be shared in future industry working sessions, but SPs are also encouraged to review their internal transaction request resubmission processes
individually.
7/19/17 Syed
Mubeen
Saifullah
Neustar Will the TOM please include Roll-Back testing on the time-line for
transition?
The rollback testing plan will be developed as the rollback testing plans are
finalized. We are currently gathering industry feedback on the planned approach. Additional details will follow.
7/19/17 Syed
Mubeen Saifullah
Neustar When will specifications around Roll-Back be made available?
Expected availability of the rollback support specifications may be found in
the posted material from the July 12th meeting. Additional information will be provided in the planned August 16th meeting.
Transition Outreach and Education Plan Public Questions List
13 | P a g e
Date Submitter Organization Question / Response
6/14/17 John
Howison
Cincinnati
Bell
Telephone
I understand that during the current vendor testing, defects have been
discovered. Can you please share which test-cases uncovered the defects, and also the details of these defects?
Going forward, what is the defect process management (for tracking)? And
what is the resolution process for these defects?
The TOM is not allowed to provide specific defect information because of the vendor confidentiality provisions agreed to by iconectiv and the
vendors. Please note that identified defects are under investigation.
When issues are discovered during testing they are investigated and
resolved by the vendor and iconectiv, leveraging an internal ticketing system and formal tracking mechanism. Vendors will need to pass all their
assigned test cases to be certified. Some issues may be connectivity issues or configuration issues either on the NPAC or the system under test, others
might be related to the vendor or NPAC software. The foremost goal is to resolve all issues within the vendor test window.
5/17/17 Jerry James LNP Alliance In testing, is iconectiv database real or sample/subset of the whole database or other?
The iconectiv test bed will use data known as the “Midwest Test Data”,
unloaded from the current NPAC testbed. During continued certification testing process, data will be created and managed by iconectiv on behalf of
those certifications tests. Actual regional databases unloads are also used in iconectiv internal testing of data migration, porting flows and performance.
5/17/17 Jerry James LNP Alliance How will you simulate load testing of the new system?
The iconectiv performance verification testing is done with porting
transaction loads (e.g.: create, concur and activate operations) meeting and exceeding the NPAC performance requirements. This is done in an
environment with full size databases and a representative number of
regional LTI, SOA and LSMS simulator instances. The testing flows are based on current industry performance validation practices as shown in
NANC Change Order 397.
Transition Outreach and Education Plan Public Questions List
14 | P a g e
Date Submitter Organization Question / Response
5/17/17 John
Howison
Cincinnati
Bell
Telephone
Will all "sanitized" vendor test results be shared with the Industry?
Sanitized - the vendor names will be changed to protect the guilty. Are all vendors using the same test plan?
Yes, the TOM will share aggregated vendor test results on future TOEP webcasts. Test plans are customized to match the requirements of the
System Under Test. So while the baseline tests are consistent, there can be differences depending on the capabilities implemented by each vendor.
5/17/17 Lori
Shepard
Windstream Would you be able to publish what SOAs/Service Bureaus have tested/plan
to test? We are not planning to publish the SOAs/Service Bureaus that have tested/plan to test. SOA Service Bureaus with a mechanized interface are
required to test with the iconectiv NPAC, and can do so once their vendor's SOA system has been certified with iconectiv.
We will provide aggregated testing results that are not SOA/Service Bureau
specific. We encourage users to reach out to their SOAs/Service Bureau to
understand the status of their testing efforts.
5/17/17 Syed
Mubeen Saifullah
Neustar Can the TOM confirm that iconectiv had a 100% pass rate for their
requirements prior to opening up their NPAC system for testing? Can specific metrics be shared with the industry?
Yes, iconectiv had a 100% pass rate for their requirements prior to opening their NPAC system for external industry testing. The features delivered in
Release A to support vendor and external industry testing were fully tested internally and met all the quality criteria to be released for external industry
testing. Those quality gates include functionality, industry porting and process flows and performance testing.
No additional pre-industry testing metrics are expected to be shared.
However, we will be reporting aggregated industry test results in future
TOEP webcasts.
5/17/17 Syed
Mubeen Saifullah
Neustar Which specific FRS requirements will be addressed in Release A and Release
B? In your previous TOEP seminars you indicated core functionality, however SPID migration are fundamental to porting functionality.
Release B contains XML, NPA Splits, SPID migration, MU/MP process, Pooling Administration Service Interface, and Ancillary Services. All other
FRS requirements are covered in Release A.
Transition Outreach and Education Plan Public Questions List
15 | P a g e
Date Submitter Organization Question / Response
5/17/17 Syed
Mubeen Saifullah
Neustar Will all type of Service Provider be able to participate in Round-
Robin/Group Testing?
Yes. The Group and Round Robin testing is being facilitated by the NANC's
LNPA WG. Questions regarding the participation in those tests should be addressed by the LNPA WG. It is the TOM's understanding that those tests
are focused on wireless-to-wireless, wireline-to-wireline, and intermodal (being between wireless and wireline providers).
5/17/17 Syed
Mubeen Saifullah
Neustar The TOM indicated they would give the industry a statement of readiness
with key metrics of what iconectiv-as-NPAC has completed to prepare for the industry testing. Will the TOM be formally issuing a statement of
readiness? The TOM is not planning on providing any additional statements of testing readiness beyond what was announced in the TOEP webcast.
The TOM is not planning on providing any additional statements of testing
readiness beyond what was announced on the May TOEP webcast.
As indicated on the webcast, Release A has successfully completed
iconectiv’s quality assurance process and is ready for external industry testing, starting with SOA and LSMS CMIP vendors. iconectiv has
completed the following 5 complementary internal testing activities to ensure testing readiness: development testing, independent quality
assurance, internal industry testing, performance testing and solution testing.
4/12/17 John
Howison
Cincinnati
Bell
Telephone
When is iconectiv going to tell the mandatory mechanized users where we
need to order circuits to?
Once each mechanized user has completed registration, iconectiv will provide that user with the details on ordering of its dedicated circuits to the
new iconectiv NPAC data centers.
4/12/17 John Howison
Cincinnati
Bell
Telephone
What about the 1000+ legal entities that have not started Onboarding?
iconectiv is actively conducting outreach to legal entities that have not started onboarding. Through this outreach, a number of NPAC users were
discovered to be defunct. These preliminary conclusions are being verified
and iconectiv's onboarding team will continue its effort to register all active legal entities through Q2 2018. iconectiv is on track to obtain a final
disposition for all legal entities prior to the transition.
Transition Outreach and Education Plan Public Questions List
16 | P a g e
Date Submitter Organization Question / Response
3/15/17 John
Howison
Cincinnati
Bell
Telephone
Will users test to Release A or B?
Release A and B include different components of the system, for example,
the CMIP interface is included in Release A, while Ancillary Services and
XML interface are in Release B. Mechanized users will test only the appropriate functionality that their system utilizes. A mechanized user with
a CMIP interface is expected to test in Release A. A mechanized user with an XML interface is expected to test in Release B.
3/15/17 Syed
Mubeen Saifullah
Neustar On your industry testing section, you mention that 5 acceptance test plans
have been approved by the NAPM LLC in conjunction with the FCC along with 1 more testing plan which is pending approval. When will these test
plans and the results of their testing be released and made public?
The Acceptance Test Plans are provided to the NAPM LLC and FCC for review as required under the MSA. There are no current plans to further
publicize these documents or their results.
3/15/17 John Howison
Cincinnati
Bell
Telephone
If I have to test to Release A & B - do I have to perform my MANDATED testing twice?
Mechanized users will receive a single test plan that will contain
components of Release A and B based upon their functionality. Provided
testing is successful, users will only have to test once.
2/15/17 Syed Mubeen
Saifullah
Neustar When will iconectiv or the TOM be sharing detailed testing results showing industry readiness? Also, during testing, will there be clear communication
regarding success, defects, and issues discovered? Who will be the primary communicator of these? TOM or iconectiv?
Detailed test results will be provided to the NAPM and FCC in accordance
with the MSA. Note that results will be provided in a form that does not
identify specific vendors or service providers. A summary of testing
progress will be shared by the TOM during the monthly TEOP webcasts.
2/15/17 John
Howison
Cincinnati
Bell
Telephone
What will happen if an LSMS is down at the time of
transition/cutover?
In the event an LSMS is out of service during the transition, that LSMS
would need to be brought up with the new LNPA (iconectiv) and re-
synchronized. The process for doing so will depend in part on how long
the LSMS has been out of service.
Transition Outreach and Education Plan Public Questions List
17 | P a g e
Date Submitter Organization Question / Response
1/18/17 Syed
Mubeen
Saifullah
Neustar When will the TOM or the LNPA include vendors and carriers in the
discussion around Roll Back? There are likely processes and procedures
which will impact the industry and we are respectfully requesting the
need to be part of these discussions.
The rollback capability is currently being defined with Neustar and
iconectiv. The local system vendors have all been invited to join in the
transition process, beginning with onboarding. Participating vendors will
be engaged in the rollback planning as soon as their involvement is
warranted.
1/18/17 Jerry James Jerry James
Associates
How will calls between regions during the transition be handled?
The NPAC data is managed region-by-region today, and the transition
does not directly affect carrier switching systems, so call routing during
transition will not be impacted.
12/13/16 John
Howison
Cincinnati
Bell
What is the impact of operating in the Southeast and Midwest? Do I have
to perform two cutovers?
Yes, if you operate in both of these regions, then you will need to
participate in two regional transitions. If you are working with a Service
Bureau that is implementing the “cutover” on your behalf, we expect your
Service Bureau to manage this change with limited impact to you.
12/13/16 Scharleen
Citron
West Are authorized users everyone who will eventually use the service or just
for initial set-up etc.?
Authorized users are the individuals who will utilize iconectiv's LNPA
NPAC services after transition.
10/27/13 Lisa
DeKalb
BroadRiver
Communicati
on Corp
Is there a task list we can use as a service provider to ensure we are
completing all the on boarding steps in a timely manner?
To get started with onboarding, please begin by registering online at
www.numberportability.com. Once you have registered, you will fill out a
Non-Disclosure Agreement, next a User Agreement, and finally a Regional
User Agreement. For additional questions concerning on-boarding, please
contact iconectiv at 844-820-8039, or you can email iconectiv at:
Transition Outreach and Education Plan Public Questions List
18 | P a g e
Date Submitter Organization Question / Response
10/27/13 John
Howison
Cincinnati
Bell
I have an NCA issue and I need a human contact not a web address to talk
to.
Thank you for your question. For questions concerning on-boarding,
please contact iconectiv at 844-820-8039, or you can email iconectiv at
9/21/16 Mandi
Naylor
Comtech
Telecommuni
cations Corp
Are the costs of services changing at all with the transition?
Pricing is specific to each User and will be provided by iconectiv during
onboarding. Pricing under the contract with the new LNPA is
substantially lower, to the industry overall, than that of the current LNPA
9/21/16 Syed
Mubeen
Saifullah
Neustar Per your August presentation (slide 10), Release A will include: core
NPAC/SMS services, including the CMIP, LTI Interfaces and Data
migration tools.
Release B will include XML, SPID Migration, MUMP, Pooling and
Ancillary Services.
As I’m sure you are aware, the SOA using CMIP today has the
functionality for both SPID Migration and Pooling. If I’m certified on
Release A, per your presentation it seems that I will have to re-certify parts
of my CMIP SOA on Release B. Is that an accurate understanding? If not,
can you please clarify?
Vendor interoperability testing may take place in stages and may require
repetition/re-certification depending on the vendor’s product, feature set,
maturity, performance during testing, or for other reasons. Vendors will
be expected to actively participate as in any major system release or
upgrade.
8/31/16 John
Howison
Cincinnati
Bell
Telephone
When can I expect to be contacted by my iconectiv rep?
If you are the primary contact for your company, you should have already
been contacted. If you have not yet heard from iconectiv, and you are the
primary contact, please contact iconectiv at: LNPA-ACCT-
8/31/16 Ross Olsen AT&T I've heard no mention of the Canada NPAC regional transition. Does your
transition plan include the Canada region?
The LNPA Transition affects only the USA. Canada is not within the scope
of this transition.
Transition Outreach and Education Plan Public Questions List
19 | P a g e
Date Submitter Organization Question / Response
8/31/16 Syed
Mubeen
Saifullah
Neustar iconectiv has stated that only representatives from the User itself can be a
primary contact. In some cases today, Service Bureaus act as the primary
contact, is this a change in policy and can you explain the reasoning
behind it?
Service Bureaus may continue to act as the primary contact for Service
Providers for certain activities and coordination, and this will remain the
preferred approach. However, the NPAC vendor is required to maintain
direct User contacts for some items like NDAs and Regional User
Agreements, so the User can be contacted directly.
8/31/16 Syed
Mubeen
Saifullah
Neustar Also, please confirm whether vendors and mechanized users are expected
to certify against an unfinished system at the end of the release. Or if
vendors/mechanized users will be expected to re-certify if a major bug fix
is identified.
As noted in the webcast, the underlying platform will be completed and
tested first. Thereafter, the CMIP interface will be made available for
Vendor testing. The XML interface will be made available later in the
schedule.
In the event that defects are found during any phase of testing, the TOM
will work with iconectiv to have them corrected. Any re-certification that
may be required would depend on the nature of the defect and resolution.
8/31/16 Syed
Mubeen
Saifullah
Neustar Based on what I just heard, can you please clarify...will testing be different
for vendors?
If you intended to ask "will Vendor certification be different than
Mechanized User certification" then, yes, the two test suites could be
different.
If you intended to ask "will all Vendors be required to pass the same
certification testing" the answer is also yes, certification will be the same
for all Vendors although of course SOA system testing will be different
from LSMS testing, just as it is in today’s environment.
8/31/16 John
Howison
Cincinnati
Bell
Telephone
If I own an LSMS am I considered a Mechanized User or If my vendor
certifies then I am certified? Please clarify.
If you operate an LSMS, then you are considered a Mechanized User. First,
the Vendor that developed your LSMS must certify their product(s) that
you are using. When the Vendor completes certification then you will be
required to test your as-built configuration.
Transition Outreach and Education Plan Public Questions List
20 | P a g e
Date Submitter Organization Question / Response
8/31/16 Ross Olsen AT&T Does the transition include the current Neustar Lab/Testing environment?
The Neustar lab/test environment will not transfer, but the test data
service providers have built in the Neustar testbed will populate the
iconectiv testbed. iconectiv will provide a similar lab/test environment as
required by the contract.
8/31/16 Eric Goble Windstream
Communicati
ons
Assumed no impact to our current Neustar/SOA until cutover?
No impact is expected to your current SOA before cutover.
8/31/16 Eric Goble Windstream
Communicati
ons
As a large service provider across multiple states it sounds like we will
have "dual" systems running for a period of time or can we convert all at
once?
If you operate across multiple regions and those regions are not in the
same cutover group, then you will likely have to maintain multiple
connections during the migration.
8/31/16 Syed
Mubeen
Saifullah
Neustar You just stated that we would be testing against a fully tested system. If I
as a vendor am testing against iconectiv release A, and release B isn't done
yet, how will this be managed?
Release A includes the complete CMIP interface and NPAC/SMS
functionality. Release B includes the complete XML interface and
'additional' functions like Mass Updates/Mass Ports. Each release will be
fully tested before involving vendors.
8/31/16 Eric Goble Windstream
Communicati
ons
Is there a map of the regions we can look at? Is there a time line on each
region?
A region map maybe found at:
https://www.npac.com/the-npac/about/npac-regions
Precise timing for each region has not yet been finalized as the migrations
will not occur until 2018.
8/31/16 Jerry James LNP Alliance Will IP to IP routing be available under the iconectiv system?
IP-to-IP routing is being accomplished today. If providers are using NPAC
fields to IP route today, they will continue to be able to do so when the
iconectiv NPAC is in place.
8/31/16 Lauren
Calaby
Intermedia Will iconectiv offer a similar service as Neustar's Port PS service?
iconectiv will provide a capability called Port Query Service.
Transition Outreach and Education Plan Public Questions List
21 | P a g e
Date Submitter Organization Question / Response
7/21/16 Jim Falvey Eckert
Seamans on
behalf of the
LNP Alliance
How is it that you can say that the press has confirmed that the MSA has
been approved when the FCC has not issued a public order approving the
MSA? What press are you referring to? And won't the MSA actually be
approved only when an FCC order is issued approving it?
During the webcast, the TOM said “As of today, we understand that the
press is reporting that the FCC has confirmed that the Master Services
Agreement between iconectiv and the NAPM has been approved”. We
mentioned this because, shortly before the webcast, we learned that a
publication had reported it. We have subsequently learned that an FCC
order approving the MSA has been released.
7/21/16 John
Howison
Cincinnati
Bell
Telephone
20 years later - Why can't iconectiv make Onboarding easier?
Onboarding, as detailed during the webcast, must necessarily verify a
minimal set of regulatory, legal, and technical information to meet FCC
and Industry requirements. The iconectiv process is very similar to what is
done today to onboard with the current NPAC.
7/21/16 James
Nelson
State of NH -
DESC
Will Law Enforcement/PSAP users also use the iconectiv website to
register for access?
Soon after the signing of the MSA, Service Providers, Service Bureaus and
Providers of Telecom Related Services (PTRS) will be able register with the
iconectiv NPAC. Instruction for registration will be provided at that time.
Plans for outreach to the Law Enforcement, Wireless Do Not Call
(WDNC), and other users of ancillary services are underway and will be
shared in the coming months. Information on how to register will be
shared at that time.
7/21/16 Bridget
Alexander
JSI Will iconectiv have to be added as an insured on all SP and Service Bureau
insurance policies?
All Service Providers and Providers of Telecom Related Services
registering with the iconectiv NPAC must furnish a certificate showing
that either (1) iconectiv has been specifically added to their insurance
policy as an additional insured or (2) evidence that their insurance policy
includes coverage for all of their vendors (which would include iconectiv)
as additional insureds. Additional details will be provided during the
onboarding process.
Transition Outreach and Education Plan Public Questions List
22 | P a g e
Date Submitter Organization Question / Response
6/21/16 John
Howison
Cincinnati
Bell
Telephone
What did the TOM learn at the NENA conference?
The TOM met with a number of industry participants and revisited the
state of the transition as presented in the TOEP webcast series. Project
schedule is a continuing area of interest and that testing, in particular,
seems to be the biggest concern.
6/21/16 John
Howison
Cincinnati
Bell
Telephone
"What is the status of "The Contract”?
The MSA (Master Services Agreement, "the Contract") remains in review
with the FCC.
6/21/16 John
Howison
Cincinnati
Bell
Telephone
Onboarding Webinars - when?
We do not have a specific schedule for onboarding yet as the MSA is not
yet approved. We will provide more detail as soon as approvals complete
and information is available.
6/21/16 John
Howison
Cincinnati
Bell
Telephone
How many people have you met with in face to face events?
The number varies by event of course; overall the face-to-face events have
been attended by roughly 100 in total.
Transition Outreach and Education Plan Public Questions List
23 | P a g e
Date Submitter Organization Question / Response
6/21/16 James
Falvey
Eckert
Seamans
Cherin &
Mellott, LLC
You mentioned on the webcast you will release "revised Gantt charts" once
the MSA is approved. Could you release current Gantt charts so
companies can understand the interdependencies in the process?
Could you release a Gantt chart with MSA approval listed as Day 1? Are
there financial or other restrictions on the TOM performing this type of
work at this time?"
An approximate Gantt chart is included in the TOP posted at the NAPM
LLC site (https://napmllc.org) on the "LNPA Transition" tab under the
"Reference Documents" menu selection. Additional detail on some
components has been provide in the April and prior webcasts, the material
for which is also posted to the website above.
In terms of issuing an MSA Day 1 Gantt chart, it’s not quite as simple as a
proportional change rippling through the work plan. The TOM has heard
stakeholder concerns around planning Q4 activities, due to resource
bandwidth, higher volumes, blackout periods and other constraints. Some
activities can be re-sequenced to avoid these periods, while for other tasks,
there are stronger dependencies which limit flexibility. Additionally, some
activities can be accelerated by deploying more iconectiv resources, while
others can’t. However, this can only scale so far, there are minimum times
independent of resources applied.
All of this needs to be brought together, and until the MSA is approved
and start dates for key activities like data center construction are known,
we won’t be able to best fit together all the moving pieces to orchestrate a
transition that is well-tested, orderly, and as timely as appropriate. Once
we have clarity on front-end approvals, the TOM will work with iconectiv,
Neustar, the FCC, the NAPM, industry and other stakeholders to define
an optimum transition schedule based on all the factors involved.
6/21/16 Rachel
Hamilton
Walnut
Telephone
Company
How do we verify our info in NPAC - just call the help desk?
Contact Neustar, the current LNPA, to verify your Primary and Secondary
contacts in the NPAC. The help desk is one good way to contact Neustar.
6/21/16 John
Howison
Cincinnati
Bell
Telephone
The NPAC sends out a contact email every month. Are you using that list?
Are you using the LNPA WG Contact List?
The contact email lists are a supplementary component of the overall
outreach list. However, the Primary and Secondary contacts in the NPAC
are the official contacts and are expected to be more reliable.
Transition Outreach and Education Plan Public Questions List
24 | P a g e
Date Submitter Organization Question / Response
6/21/16 John
Howison
Cincinnati
Bell
Telephone
Is the Mechanized User Test Plan available?
The onboarding process for Mechanized Users, and more detailed
onboarding plans generally, will be released following MSA approval.
Specific test plans for Mechanized Users will be tailored to their systems
and will be co-developed/shared during onboarding.
6/21/16 John
Howison
Cincinnati
Bell
Telephone
Why do I have to re-test things that my vendor has already tested?
As noted in the FAQ: Vendors’ LSMS and SOA products must be certified
for proper function. However testing the 'vanilla' product is not the same
as testing the actual in-service system as configured. So, once Vendor
certification is complete, all of the local systems (LSMS/SOA) that connect
to the NPAC must be tested to verify that their specific configuration and
connection settings are being supported correctly.
5/25/16
John
Howison
Cincinnati
Bell
Telephone
What is the value of attending the face-to-face meeting in Indianapolis in
June if there is no formal agenda or presentation?
In-person meetings provide stakeholders the opportunity to share
perspectives and ask questions about the LNPA transition. These events
offer a less formal and structured environment than allowed by the
webcast format.
5/25/16 John
Howison
Cincinnati
Bell
Telephone
Is a list of the questions asked at the LNPA WG face-to-face meeting
available?
No. However, questions of general interest arising from such in-person
meetings will be added to the Frequently Asked Questions list maintained
by the TOM and posted to https://www.napmllc.org.
Note that in-person meetings will not be used to announce new
information.
5/25/16 John
Howison
Cincinnati
Bell
Telephone
TOEP Events - No formal presentation and no agenda - Why should I
attend?
In-person meetings provide stakeholders the opportunity to share
perspectives and ask questions about the LNPA transition. These events
offer a less formal and structured environment than allowed by the
webcast format. Attendance is entirely at your discretion.
Transition Outreach and Education Plan Public Questions List
25 | P a g e
Date Submitter Organization Question / Response
5/25/16 John
Howison
Cincinnati
Bell
Telephone
iconectiv can add resources at their end but I can't at my end. So I do not
like the shortened testing interval.
As discussed in the May 25, 2016 TOEP webcast, iconectiv has added
resources to support a larger number of users testing at the same time. Enabling more testing in parallel can shorten the overall testing period
without impacting the testing period for each user.
5/25/16 John
Howison
Cincinnati
Bell
Telephone
If my vendor tests my LSMS against iconectiv what can be gained by me
re-testing the same LSMS if on the same release?
Please see the response to question “If my Vendor tests - do I have to
test?” below. Note that, as described in the FAQ, “vendor” means an
LSMS (or SOA) software developer. We refer to an entity that operates an
LSMS as a Service Provider or Service Bureau. If you use a mechanized
Service Bureau to connect to the NPAC, then their testing will be
mandatory but yours will be optional.
5/25/16 Jerry James Jerry James
Associates
Before going "live" with the new LNPA, will the testing be real time and
with real data?
As described in the FAQ, iconectiv NPAC testing will include use of a live
system operating with the “Midwest Testbed Data” as is done by the
current NPAC.
5/25/16 John
Howison
Cincinnati
Bell
Telephone
I have a Test LSMS Platform. Can I run my certification tests from the test
LSMS or do I have to run my tests from the live LSMS?
Your production configuration must be validated, not necessarily the
production system. During onboarding, iconectiv will work with you to
develop an appropriate test plan and assess which system(s) to test.
Transition Outreach and Education Plan Public Questions List
26 | P a g e
Date Submitter Organization Question / Response
4/20/16 John
Howison
Cincinnati
Bell
Telephone
What entities will be required to perform certification testing besides
vendors? Service Providers? On the FAQs it says that vendors can test on
behalf of SPs, does that mean Service Provider testing is optional? Service
Provider Testing: why do I have to test IF my vendor has already certified
my release? The only difference may be options and IP addresses...this is
why I pay my vendor. For a system that I know already works.
Clarification of terms may be helpful: we refer to vendors as those that
develop and sell local systems (LSMS/SOA) but do not operate them. We
refer to Service Bureaus as those that operate local systems (acquired from
Vendors) on behalf of Service Providers and PTRS. Note that some
Vendors may separately operate a Service Bureau business.
The Vendors’ LSMS and SOA products must be certified for proper
function. However this is not the same as testing the actual in-service
system as configured. So, once Vendor certification is complete, all of the
local systems (LSMS/SOA) that connect through a mechanized interface to
the NPAC, must be tested to verify that their specific configuration and
connection settings are being supported correctly. Testing for other users
(e.g., Service Providers using Service Bureaus or non-mechanized NPAC
users) is optional.
4/20/16 John
Howison
Cincinnati
Bell
Telephone
Will iconectiv attempt to automate SPID updates?
SPID migrations will continue to operate as defined in the Functional
Requirements Specifications (FRS). Automation of the processing of SPID
migration data provided by the NPAC is a feature that would need to be
provided by a downstream system (e.g. LSMS vendor or systems
integrator).
4/20/16 John
Howison
Cincinnati
Bell
Telephone
How will test results from ad-hoc testing (i.e., testing outside the
mandated test cases that vendors are required to execute) be reviewed and
addressed?
The incoming LNPA will provide test engineers and a help desk to
facilitate the testing process, including trouble reporting and problem
resolution. In addition, the TOM will share aggregated test results with
the Industry to provide an overall view of testing while maintaining
anonymity for individual testers.
Transition Outreach and Education Plan Public Questions List
27 | P a g e
Date Submitter Organization Question / Response
4/20/16 John
Howison
Cincinnati
Bell
Telephone
What did you present at the outreach event last week?
There was no presentation and no new information was released. In -
person meetings offer stakeholders a forum to share perspectives and ask
questions about the LNPA transition. These events are informal and
intended in large part to gather stakeholder input.
4/20/16 John
Howison
Cincinnati
Bell
Telephone
How will performance testing be executed and measured? There is no
detail provided in the latest published timeline.
Performance testing is part of the overall transition plan. Details are not
yet ready for release.
4/20/16 John
Howison
Cincinnati
Bell
Telephone
How do I get a copy of the FRS? What about things the Neustar NPAC
does that are not in the FRS? Will iconectiv do these things too?
All functionality required of the current NPAC will be part of the iconectiv
NPAC and is within the scope of this transition. The associated FRS
(functional requirements specification) is available at
https://www.npac.com on the “The NPAC” tab under “Software
Releases”.
Some included components, beyond the core NPAC/SMS are: mass ports,
mass updates, most regular and custom/ad hoc reports, ELEP service (also
known as LEAP), WDNC service, and Bulk Data Download (BDD) file
support. If you have a question about a specific feature that is not the
subject of an FRS requirement, please contact us.
4/20/16 John
Howison
Cincinnati
Bell
Telephone
Will a failover exercise be part of testing? During vendor testing? During
Service Provider testing?
An extensive suite of testing is integral to the project plan and will be
implemented in multiple levels from Vendor through Service Provider
and Ancillary Services user. Testing will cover the functional and
operational elements of the system including security, disaster, continuity,
and performance components.
4/20/16 John
Howison
Cincinnati
Bell
Telephone
Will I have to pay iconectiv to test?
Total cost of services through the new LNPA are expected to be lower
than those of the current LNPA. Fees for the different NPAC services will
be communicated during your onboarding process.
Transition Outreach and Education Plan Public Questions List
28 | P a g e
Date Submitter Organization Question / Response
4/20/16 John
Howison
Cincinnati
Bell
Telephone
Where will iconectiv's test bed be located and is there a document for
interconnection?
The network interconnection locations for the new LNPA production and
test platforms are not the same as Neustar’s current locations. During the
onboarding process, the new LNPA will provide the details required for
interconnection.
4/20/16 Scott
Hillman
Verizon Statement that connectivity to iconectiv Midwest NPAC TESTBED from
LSMS and SOA systems would not require T1 connections by service
providers is inaccurate. All service providers with a mechanized interface
will need to establish circuits to the new iconectiv datacenters.
The datacenters for the new LNPA are not in the same locations as those
of the current LNPA. The new LNPA will support testing over VPN
connections over the Internet. While T1s will be supported, they are not
required for testing.
4/20/16 John
Howison
Cincinnati
Bell
Telephone
Will iconectiv perform any kind of verification to ensure that some SPs are
not hoarding numbers and have release back non-working numbers?
iconectiv will perform all tasks for which the LNPA is responsible in
accordance with the relevant specification or regulation. This includes a
range of block pooling and snapback activities in support of number
management.
4/20/16 Scharleen
Citron
Intrado /
West Safety
Services
When will the MSA be available for review? Will we be able to access the
MSA from the NAPM website? Will there be time to review the MSA and
submit comments?
The MSA has been released by the FCC under a protective order and is
available for review by permitted parties. Additionally, a redacted, public-
inspection version (outside the protective order) has been made available
on the napmllc.org website.
4/20/16 John
Howison
Cincinnati
Bell
Telephone
Last Webcast you stated you would be at the LNPA WG AFTER the
Raleigh-Durham meeting in JULY - What happened?
TOEP schedule announcements and the list of events which the TOM
expects to attend in 2016 are posted on napmllc.org. The current event list
includes both the May and July LNPA Working Group meetings. Prior
TOEP participants, and those identified in TOEP mailing lists, will receive
updates by email.
Transition Outreach and Education Plan Public Questions List
29 | P a g e
Date Submitter Organization Question / Response
4/20/16 John
Howison
Cincinnati
Bell
Telephone
Mass Ops Modify plus, will it work as before? And will it still be free?
Mass Update/Mass Create/Mass Release/Mass Activate/Mass
Disconnect/Create Activate
Mass actions (like mass updates, creates, releases, and activates) will be
supported by the new LNPA and operate as defined in the FRS.
Total cost of services through the new LNPA are expected to be lower
than those of the current LNPA. Fees for the different NPAC services will
be communicated during your onboarding process.
4/20/16 John
Howison
Cincinnati
Bell
Telephone
Will iconectiv's locations be geographically diverse?
Yes, geographic diversity is part of the high availability/redundancy
requirements that the new LNPA must meet.
4/4/16 Justin Akin River Road Asset Management
How will pricing be determined for non-NAPM members with regard to
the ENUM registry?
ENUM registry is outside the scope of the LNPA transition. Please
contact your current ENUM registry provider for details.
4/4/16 Justin Akin River Road Asset Management
Why is the IP transition not a part of the LNPA transition?
IP transition is a separate initiative with multiple components that is
being evaluated on its own timetable. It is expected that, if there are any
NPAC updates required for IP transition, they will be incorporated when
available.
4/4/16 Justin Akin River Road Asset Management
Will Telcordia be able to introduce new revenue opportunities outside of
the core services outlined in their RFP?
Telcordia is a commercial enterprise and can pursue revenue
opportunities beyond the services outlined in the RFP. However, there
are restrictions that prohibit Telcordia from using its position as the
LNPA to favor its other service offerings.
Transition Outreach and Education Plan Public Questions List
30 | P a g e
Date Submitter Organization Question / Response
4/4/16 Justin Akin River Road Asset Management
Why does the FCC consider Telcordia (a subsidiary of Ericsson - who
provides wireless network support services to major carriers) to be a
neutral administrator?
Section E of the FCC’s March 27, 2015 selection order captures the FCC’s
neutrality considerations and the steps that Telcordia has taken to
address neutrality.
The order states “FCC has undertaken a careful and extensive review of
Telcordia’s fitness to serve as a neutral LNPA”. It also states, “Telcordia
has proposed safeguards to ameliorate possible undue influence from
Ericsson…We find that, when considered together in light of the
safeguards and conditions that we adopt in this Order, Telcordia will not
be subject to undue influence by Ericsson, nor will Ericsson adversely
affect Telcordia’s ability to serve as a neutral LNPA.”
3/9/16 Eliza
Wygant
West Safety Systems / Intrado
What type of testing will be needed if you don't know the type of
connection you currently have vs. what you will need after transition?
For example I am not sure if I am using a mechanized interface,
mechanized SBs, LTI SBs, IVR, or Help Desk?
iconectiv will determine your current status using the NPAC SMS data
and will contact you for onboarding at the appropriate stage. During
onboarding your connection details and profile information will be
determined and updated/corrected as needed. This will inform the
required testing. If you have questions as to your onboarding group,
please send an email to [email protected].
3/9/16 Jerry James LNP Alliance During the testing, will the iconectiv database be "live" and mirror
the existing database or be a "mock" database?
The iconectiv testbed will be a live NPAC testbed containing the
same Midwest region test data as the Neustar test bed.
3/9/16 John
Howison
Cincinnati
Bell
Telephone
What is the projected testing timeframe? Best guess?
The projected testing timeframe was covered during the 1/27/16
TOEP webcast. Materials from the webcast are available on the
napmllc.org website.
3/9/16 John
Howison
Cincinnati
Bell
Telephone
If my Vendor tests - do I have to test?
Vendors and mechanized service providers, mechanized service bureaus
and mechanized PTRS users will need to complete industry testing. In
some cases, service bureaus may test on behalf of service providers.
Transition Outreach and Education Plan Public Questions List
31 | P a g e
Date Submitter Organization Question / Response
3/9/16 John
Howison
Cincinnati
Bell
Telephone
Any cost to test with iconectiv?
Information related to iconectiv testing costs, if any, will be
available upon completion and approval of the iconectiv MSA.
3/9/16 John
Howison
Cincinnati
Bell
Telephone
To onboard we need to know where the systems are, so where are we
connecting to? This takes a while.
The network interconnection locations for iconectiv have been identified
and will be different than Neustar’s current locations. As part of the
onboarding process, iconectiv will provide the location details required
for interconnection.
3/9/16 John
Howison
Cincinnati
Bell
Telephone
Who is our account manager and when and how do we get RUAs?
Once the contract with iconectiv is executed, iconectiv representatives will
begin their outreach to existing users of the NPAC. Additionally, you can
reach iconectiv at [email protected] for any LNPA transition
related questions.
3/9/16 John
Howison
Cincinnati
Bell
Telephone
How do we get a copy of the NDA? The User Application?
Details on the onboarding process were covered during the 3/9/16 TOEP
webcast and are available on the napmllc.org website. iconectiv will
provide materials as part of the onboarding process.
3/9/16 John
Howison
Cincinnati
Bell
Telephone
What is the timeline for the Onboarding process? Is there a deadline? Is
there a cost? This looks just like the old NPAC process...
The projected onboarding timeframe was covered during the 1/27/16
TOEP webcast. Materials from the meeting are available on the
napmllc.org website. New and existing onboarding processes have many
similar elements.
3/9/16 John
Howison
Cincinnati
Bell
Telephone
The folks on the call do not have travel budgets.
Recurring TOEP webcasts are the primary means to distribute transition
information and do not require travel or budget for fees of any kind.
3/9/16 John
Howison
Cincinnati
Bell
Telephone
What happened to polling for the LNPA WG meeting in Raleigh?
Polling on this webcast focused on broad communications and public
safety conferences to understand the degree of LNPA stakeholder interest
in these events, and to enable capacity planning. There was less
uncertainty with regard to LNPA WG attendance and interest in the
transition.
Transition Outreach and Education Plan Public Questions List
32 | P a g e
Date Submitter Organization Question / Response
3/9/16 Sherry
Lichtenburg
NRRI Why is NARUC not included here?
The initial list of conferences was developed to reach various groups of
users of the NPAC system (including LEA and WDNC). NARUC is
primarily attended by regulators. However, a presence at NARUC may
be arranged. The TOM will evaluate the level of interest in NARUC
support in future TOEP events and surveys.
3/9/16 John
Howison
Cincinnati
Bell
Telephone
Why didn't we have this option (Publication Authorized) at the first TOM
update?
Based on the feedback received on the TOEP webcasts, the TOM has
established an "opt in" process to provide attendees the ability to request
their questions and responses be made public.
3/9/16 John
Howison
Cincinnati
Bell
Telephone
Who is my iconectiv rep?
You can reach iconectiv at [email protected] for any LNPA
transition related questions. Once the contract with iconectiv is executed,
iconectiv representatives will begin their outreach to existing users of the
NPAC.
3/9/16 John
Howison
Cincinnati
Bell
Telephone
Onboarding!? Why not use a Telco term - Interconnection?
Onboarding is a 5 step process. It involves (1) Initiating outreach with the
user (2) Executing a Non-Disclosure Agreement between user and
iconectiv (3) Gathering information via the Transition User Application
(4)Executing Regional User Agreement(s) between users and iconectiv,
and (5) Establishing connectivity. Interconnection is just a portion of the
onboarding process.
3/9/16 John
Howison
Cincinnati
Bell
Telephone
What are my projected costs for interconnection to the iconectiv NPAC?
As part of the onboarding process, iconectiv will provide the details
required for interconnection and estimation of costs.
3/9/16 John
Howison
Cincinnati
Bell
Telephone
Why not purchase the existing NPAC from Neustar? It works and
everybody is already connected?
In March 2010, the NAPM announced its intention to begin a competitive
process to select a new LNPA. This process resulted in the FCC
approving the NANC recommendation that Telcordia d.b.a. iconectiv
serve as the next LNPA in its March 27, 2015 selection order. Further
details of the selection process can be found in the FCC LNPA selection
order.
Transition Outreach and Education Plan Public Questions List
33 | P a g e
2/18/16 James
Falvey
LNP
Alliance,
FISPA, Open
Technology
Institute at
New America
1. The TOM TOEP FAQ (“FAQ”) posted on the NAPM website stipulates
that the only mechanism by which interested parties may submit input,
feedback or direct questions relative to the LNPA transition to the TOM
is through the “Comments” form on the NAPMLLC.org website. The
FAQ also claims that the TOM’s goal is to provide “transparent
communications” regarding the LNPA Transition.
a. Has the TOM recorded and archived all input submitted
through the Comments section?
Yes
b. Has the TOM recorded and archived all questions submitted
through the two prior webcasts?
Yes
c. Has the TOM recorded and archived all its
communications, including reports to NAPM, the FCC, or the
NANC?
No, it has recorded some of those listed.
d. Will all questions submitted in the Comments and the
webcasts by any party and the applicable responses be
available to the public for review on the NAPM website? If not,
why not?
Written questions submitted through the napmllc.org website or
during a TOEP webcast with authorization for publication will be
published with a response on the napmllc.org website so long as
the question (i) is of common interest to the NPAC Community,
(ii) has not been previously asked and answered, and (iii) is not
otherwise inappropriate. More generally, responses to questions
of common interest to the NPAC community, whether submitted
through the napmllc.org site, during a TOEP webcast or in any
other manner, will also be published in the FAQ. Questions that
are not of general interest will be logged but omitted from
publication, including, for example, specific individual requests
(e.g., requests to be added to distribution lists). To the extent that
information needed to respond to a particular question is
confidential or not yet available, the question will be logged for
response when the information becomes available.
e. The TOM Engagement Letter Summary posted on the NAPM
website February 16, 2016 states that the TOM’s reporting to the
Transition Outreach and Education Plan Public Questions List
34 | P a g e
Date Submitter Organization Question / Response
NAPM will include “written outlines, executive summaries,
presentations, memoranda, analysis of issues, and schedules
prepared in connection with the engagement as requested by the
NAPM and sufficient to document and to evidence the advice
and Services . . . .” Will all such communications (“Industry
Reports”), including reports to NAPM, the FCC, and the NANC
be made available to the public for review on the NAPM website?
If not, why not?
The TOM publishes all materials developed for general audiences
through TOEP webcasts and the napmllc.org website. The NAPM
LLC and the FCC release materials following their own respective
release processes.
Transition Outreach and Education Plan Public Questions List
35 | P a g e
2. Although the TOM and the Commission claim that transparency is
required, the current method of communication—where only the TOM sees
all the questions and dictates which ones will be answered—is completely
lacking in transparency absent additional disclosure on the part of the
TOM. Relative to this point:
a. Is the TOM prepared to release all communications, including
Industry Reports, and those questions and comments submitted
through the previously described Comments form and prior and
future webcasts to all interested parties? If so, when? If not, why not?
Please see the responses to 1d and 1e.
b.Has the TOM organized all such communications into categories,
quantifying the number of questions in each category for the purpose
of prioritization and weighting? If so, what methods were used? If
not, why not?
TOEP webcast questions are categorized according to area of focus
(e.g., schedule, testing, customer experience, etc.) to gauge the level
of participant interest in each area and prioritize topics for future
outreach and education efforts.
c.Are there any categories that the TOM has chosen not to address?
For example, LNP Alliance members have asked a number of
questions on the two webinars about costs and yet the FAQs are
completely silent on the issue of costs. The lack of disclosure
described above makes it impossible for the vast majority of
companies in the industry to have input into the LNPA Transition
process. The fact that the TOM can only be accessed by non- NAPM
carriers through the NAPM website and only through one-way
webinars should be of obvious concern to the Commission. There
must be communication between all industry members in order to
have a meaningful collaborative process, as takes place in the LNPA
Working Group, ATIS, or the NANC, for example. Why are interested
parties who have signed the Protective Order not given this
collaborative opportunity as a critical component of transparency
obligations?
No categories of questions are excluded. As explained above, to the
extent that the information needed to respond to a particular
question is confidential or not yet available; the question will be
logged for response when the required information becomes
available. As mentioned during the January 27, 2016 webcast, the
Transition Outreach and Education Plan Public Questions List
36 | P a g e
Date Submitter Organization Question / Response
TOM will participate in NANC meetings and industry conferences
to facilitate as much collaborative discussion of issues of interest as
possible. The pace of these collaborative discussions will increase
and their scope broaden over time as more information becomes
available and the transition proceeds.
With respect to costs, please note that the NPAC invoices sent to
each individual service provider show and explain the transition
costs that the service provider is incurring. As additional
information regarding costs becomes available, the information,
like information about all relevant issues, will be discussed during
a TOEP Webcast and published in the FAQ.
d. What are the long list of “action items” that have been opened and
closed, or remain pending? There is no reason why non-NAPM
carriers should not have access to this information.
Action items pertain to specific tasks assigned to iconectiv, Neustar,
NAPM LLC, and the TOM. Any action items of general interest will
be discussed during a TOEP webcast or published in the FAQ.
3. The TOM’s FAQ response to a question regarding coordination with the
IP Transition states that the: IP transition is a separate initiative with
multiple components that is being evaluated on its own timetable. It is
expected that if there are NPAC updates required for IP transition, they will
be incorporated when available. This answer is unresponsive to the
question. The IP transition is not a future development; it is happening now.
Does the TOM, under the TOM Engagement Letter, have the responsibility
to identify and contemplate potential inter-dependencies between the two
transitions as part of its core responsibilities? Does the TOM have a process
to stay informed about the IP Transition? If so, how is the TOM insinuating
itself into the IP Transition implementation process (e.g., through
communications with the NANC and/or FCC Staff) in order to stay
informed of potential interdependencies?
The TOM interacts with many stakeholders engaged in IP transition,
including the Federal Communications Commission (“FCC”) and various
service providers, including, but not limited to, participants in meetings
of the NANC and TOEP webcasts as well as members of the NAPM LLC.
For the sake of clarity, however, IP transition is not part of the defined
LNPA transition scope, and it does not fall within the TOM’s contractual
responsibilities under the engagement letter entered into with the NAPM
LLC with the oversight of the FCC.
Transition Outreach and Education Plan Public Questions List
37 | P a g e
Date Submitter Organization Question / Response
4. Obviously, any delay of the LNPA Transition is costly to the industry and
to consumers. When does the TOM anticipate having a definitive schedule,
presumably based on a fully executed iconectiv agreement? When does the
TOM expect a fully executed iconectiv agreement to be executed and when
will such agreement be made public?
The FCC, NAPM LLC, iconectiv, and other stakeholders directly involved
in the contracting process are working to complete these agreements. It is
not possible to forecast a specific completion date. Once the agreements
have been finalized and approved, the updated transition schedule will
be published.
5. When will we know the complete transition timeline and have a basis for
estimating the costs of the LNPA Transition for carriers and any changes to
carriers’ costs resulting from the LNPA Transition?
It is not possible to forecast a specific contract execution date. Once the
agreements have been finalized and approved, the updated transition
schedule will be published, which will permit parties to develop more
precise estimates of the costs and cost savings of transition.
6. The FCC directed the NAPM to hire a transition manager “familiar with
communications infrastructure.” What are the technical capabilities and
subject matter expertise of the members of the TOM as it relates to this
project, including prior experience implementing number portability
systems in the U.S.?
With oversight by the FCC, the NAPM LLC conducted an extensive
evaluation process to select PwC as TOM. PwC and the TOM team members
have significant engineering, telecommunications, number portability,
systems migration, and large program management experience.
7. The NAPM recently made a summary of the TOM Engagement Letter
public. Will the TOM and the NAPM make the actual Engagement Letter
and all associated documents public? The LNP Alliance has asked this of the
Commission and directly of the NAPM. If not, why not, given that the
industry and consumers are paying for the TOM’s services?
A detailed summary of the TOM engagement letter, including the full scope
and deliverables, as well as terms, fees, and incentives, has been published
on the napmllc.org website.
Transition Outreach and Education Plan Public Questions List
38 | P a g e
Date Submitter Organization Question / Response
8. As for the project planning by small/medium carriers, the fourth quarter
is a difficult and very busy period due to increased consumer activity,
budget planning activity, end-of-year sales/implementation activity, the
holidays, and resource limitations. Will the TOM take such factors
concerning fourth quarter demands into consideration when planning its
testing periods?
Yes
9. Will the network interconnections with iconectiv be in the same location
as Neustar or different? When will these locations be identified?
The network interconnection locations for iconectiv have been identified
and will be different than Neustar’s current locations. As part of the
onboarding process, iconectiv will provide the details required for
interconnection.
10. Testing should be mandatory because all carriers rely on other carriers to
be in compliance with porting and routing of traffic, which by definition are
bilateral activities. How can any provider or service bureau be permitted to
go “live” without a firm requirement to pretest their network and systems
to ensure no disruptions or delays in porting and routing?
NPAC testing requirements are determined by the industry through the
LNPA WG and its subcommittees. All parties are welcome to join these
discussions. Any mechanized system that has direct connectivity to the
NPAC will be required to become certified through the testing process.
Testing is optional, but welcomed, for those accessing the NPAC through
non-mechanized interfaces such as the LTI GUI, IVR and Help Desk
interfaces. The TOM will work with iconectiv to implement measures so all
interested users can access the new NPAC/LNPA to validate the use of their
non-mechanized interfaces.
Transition Outreach and Education Plan Public Questions List
39 | P a g e
Date Submitter Organization Question / Response
11. How will non-carrier providers that obtain direct access to numbers
under the FCC’s new process for providing direct access to non-carriers be
treated in the testing process? Will testing be mandatory for non-carriers to
ensure proper porting and routing?
All providers, regardless of how they obtain numbers, will be taken into
consideration during the development of the testing procedures for NPAC
functionality. All mechanized systems with direct connectivity to the NPAC
will have to be certified through the testing process. Testing will be optional
for service providers accessing the NPAC through non-mechanized
interfaces (i.e., LTI GUI, IVR and Help Desk interfaces). The specific testing
requirements and procedures will be determined by the industry through
the LNPA WG and its subcommittees.
12. How will the TOM handle notification to each carrier to ensure
compliance with any network changes or system modifications prior to
testing? Will any issues be made public so other carriers may be alerted?
The TOM will continue to keep stakeholders apprised of transition-related
activities. As the transition progresses, iconectiv will also conduct outreach
activities to engage all NPAC users regarding their testing options and
obligations as part of the onboarding process.
13. What industry conferences will TOM representatives attend to meet
with carriers and answer questions? Will these questions and responses be
posted on the NAPM website?
TOM participation at industry conferences is still being finalized. Once final,
these events and times will be publicized through TOEP webcasts, the
napmllc.org website, and other means. The TOM attended Incompas in
April; other events on the preliminary 2016 list include CTIA, NTCA,
NENA, APCO, and IACP conferences.
14. Will there be requirements to notify end user customers of the LNPA
Transition? What are those requirements and when will they be
implemented?
All transition stakeholders, including the general public and end users, will
continue to be engaged through the Transition Outreach and Education
Program.