nepal-india regional trade and transport project (ida...
TRANSCRIPT
1
Nepal-India Regional Trade and Transport Project
(IDA Credit 5273-NP and IDA Grant H863-NP)
Implementation Review and Support Mission
September 9-14, 2014
Aide Memoire
INTRODUCTION
1. A World Bank (WB) team1 led by Diep Nguyen-van Houtte (Senior Transport Specialist,
Task Team Leader) held an implementation review and support mission for the Nepal-India
Regional Trade and Transport Project (NIRTTP, the Project). The overall mission objective was
to: (i) assess and review implementation progress of all components/activities, procurement and
disbursement; and (ii) discuss and agree on remedial actions to improve progress in order to meet
the overall development objectives and project implementation schedule.
2. The WB team greatly appreciates the cooperation and courtesies extended by the
Government of Nepal (GoN) during the mission. The team would like to thank staff and officials
of the Ministry of Commerce and Supplies (MoCS) and its agencies the Nepal Intermodal
Transport Development Board (NITDB), Trade and Export Promotion Center (TEPC), the
Ministry of Physical Infrastructure and Transport (MoPIT), the Ministry of Finance (MoF), the
Department of Customs (DoC), members of the National Trade and Transport Facilitation
Committee (NTTFC), and the Technical Committee for National Single Window and Trade
Portal. A list of persons met is included in Annex 1.
3. The mission held discussions regarding the implementation of the NIRTTP to review
progress of all project components and to update the project implementation plan. The mission
met the National Trade and Transport Facilitation Committee and the Technical Working Group
for developing National Single Window and Trade Portal.
4. This Aide Memoire (AM) summarizes the discussions that took place during the
Implementation Review and Support Mission. The AM was discussed at a wrap up meeting
chaired by the Acting Secretary of MoCS, Mr. Deepak Subedi on September 12, 2014. As
agreed, this AM will be classified as a public document in accordance with the World Bank’s
Access to Information Policy.
1The team comprised: Diep Nguyen-Van Houtte (Sr. Transport Specialist/Task Leader), Deepak Shrestha (Sr.
Transport Specialist), Ramesh Siva (Lead Information Officer), Charles Kunaka (Senior Trade Specialist), Leanne
Farrell (Environmental Specialist), Drona Raj Ghimire (Environmental Specialist), Mridula Singh (Senior Social
Specialist), Yogesh Bom Malla (Financial Management Specialist), Shambhu Uprety (Procurement Specialist) ,
Purushottam Ojha (Trade Facilitation Consultant) and Bibash Shrestha (Team Assistant).
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
Key Project Data
Project Data Project Performance Ratings
Board Approval: June 28, 2013
Effectiveness Date: September 10, 2013
Original Closing Date: December 31, 2019
MTR Date: October 1, 2016 (planned)
Original Cr/Gr. Amt: US$99 million
Total Amount Disbursed
(As of August 31, 2014): US$8.18 million (8.3
%)
Summary Ratings: Last Now
Achievement of PDO:
Implementation Progress:
Project Management
Procurement:
Financial Management:
Safeguards:
M&E:
Counterpart Funding:
S
MS
MS
MS
MS
MS
S
S
MS
MU
MU
MU
MS
MS
S
MU
HS=Highly Satisfactory; S=Satisfactory; MS= Moderately Satisfactory; MU= Moderately
Unsatisfactory; U=Unsatisfactory; HU=Highly Unsatisfactory; NA=Not Applicable; NR=Not Rated
PROJECT DEVELOPMENT OBJECTIVE
5. The Project Development Objective (PDO) is to decrease transport time and logistics
costs for bilateral trade between Nepal and India and transit trade along the Kathmandu-Kolkata
corridor for the benefit of traders by reducing key infrastructure bottlenecks in Nepal and by
supporting the adoption of modern approaches to border management. The project components
are: (i) Modernize transport and transit arrangements between Nepal and India; (ii) Strengthen
Trade-Related Institutional Capacity in Nepal, including the development of Nepal National
Single Window (NNSW) and Nepal Trade Portal (NTP) and improvement of Trade-Related
Laboratories; and (iii) Improve Select Trade-Related Infrastructure, which entails expanding and
upgrading the Narayanghat-Mugling (N-M) road section, building a Container Freight Station in
Kathmandu, and upgrading the Inland Container Depots at Birgunj and Bhairahawa.
6. Progress towards meeting the Project Development Objectives (PDO) is rated as
“Moderately Satisfactory”. The on-average one year delay in implementation of key activities is
causing some concern about the timely achievement of the PDO.
CURRENT IMPLEMENTATION STATUS
7. The overall Implementation Progress is rated as “Moderately Unsatisfactory” based on
the reasons explained in the following paragraphs.
8. Implementation of the Governance and Peace Action Plan (GPAP). The Public
Information disclosure system has been established by both MoCS and Department of Roads
(DoR) including dissemination through local workshops, information campaign and participatory
community forums (see Annex 2, items 12-21 under in the Governance and Peace Action Plan
(GPAP) section). All safeguards documents had been disclosed in English before negotiations of
the Project in May 2013. The safeguards documents for the N-M road have been translated into
Nepali and disclosed on the DoR website. The Environmental and Social Management
Framework (ESMF) for the MoCS-managed components was disclosed in Nepali at the
3
MOCS website. However, it was subsequently removed from the website due to a technical
error. MOCS has since reposted it. The Environmental Management Plans (EMPs) for the
works at Bhairahawa, Birgunj and Kathmandu Inland Clearance Depots (ICDs) have not
been disclosed in either English or Nepali. MoCS was expected to do this by mid-March 2014
but it still has not been completed. It has been agreed that this will soon be completed.
9. Component A1: Technical Assistance (TA) to Modernize Bilateral and Regional
Transit Regime. There has been little progress in this activity, with few ideas for capacity
development programs and the kind of support needed to strengthen Nepal’s capacity to
negotiate international trade treaties, deal with Non-Tariff Measures (NTMs), strengthen corridor
development, supply chain and logistics frameworks, monitor corridor and logistics performance
and promote exports. The PCO will work with MoCS to propose a detailed work program for
this component and submit for approval of the NTTFC.
10. Study on Transshipment. The Governments of India and Nepal agreed to implement a
functional transshipment modality for cargo passing through Indian ports. The modality of the
transshipment is to be prepared in mutual consultation of concerned authorities of the
Government of Nepal (GoN) and the Government of India (GoI). The NITDB has already
designated the dry ports in Nepal as ports of destination in the shipment of cargo. It was agreed
during the February 2014 supervision mission that the Transshipment Study to be commissioned
under Component A1 would have two aspects: (a) a review of provisions in Indian Customs law
and regulations covering transshipment of cargo to Nepal, including insurance and transportation
arrangements, and development of proposals for reform; and, (b) an assessment of operational
and commercial practices by the shipping industry that may encourage or discourage the
transshipment of cargo to Nepalese ICDs/dry ports. An international consultant has been
recruited to conduct the study, which is expected to be completed by November, 2014. The Bank
team requested to see the inception report and progress reports prepared by the consultant.
The PCO agreed to request the consultant for these reports and forward to the Bank as early
as possible.
11. Study Tours. A study tour organized for 14 participants (7 participants to Kolkata Port
and 7 participants to Mumbai Port in India) was conducted in connection with the above
Transshipment Study. As a No Objection Letter was requested from the Bank only at the last
moment after activities were already organized, the mission discussed that in future, the Bank
would need to agree to the Terms of References (ToRs), format, and members of the study tour
well in advance for any planning and expenditure related to the study tour. Nominations for
members joining the study tour should only be for officials whose responsibilities are
relevant to the learning objectives of the study tour.
12. Component A2: Electronic Data Interchange between Nepal and India. The key
activity in this component is to automate/computerize the Customs Transit Document (CTD),
including the harmonization of the Unique User Importer-Exporter ID code to be used by both
the Indian and Nepali systems. Government has allocated its own budget to DoC for developing
the code. DoC has already prepared directives for this purpose and has agreed to carry out a
stakeholder’s meeting and prepare a detailed work plan including any support needed. DoC
and MoCS representatives agreed to contact the International Finance Corporation (IFC)
4
team and initiate the process for IFC assistance in this component. IFC had offered US$2
million in support for this component for both India and Nepal. However, IFC has now
confirmed that there is no formal agreement with India and therefore the scope/value of the
IFC component will be significantly reduced and support will only be provided to Nepal. IFC
will work with DoC and MoCS over the coming months to clarify the scope/monetary value of
support needed with detailed work plan and clear responsibilities/accountability especially for
the automation of the CTD and electronic data interchange between Nepal and India.
13. Component A3: Support to the Road Transport Regulatory Authority. The support
activities to the Department of Transport Management (DoTM) consists of consultant services
and works for managing axle load control and road safety from the transport management
perspective. As a first step, DoTM has established a separate sub-project office and hired a
national consultant as a Technical Advisor. In the review period, DoTM has initiated various
actions toward generating awareness on road safety including a workshop among DoTM staff,
preparation and distribution of road safety awareness materials including pamphlets, signs and
videos. Regarding the procurement for consulting services for the study on axle load control and
road safety, the evaluation process is near completion and contract award is targeted by end-
September 2014. The proposal of DoTM for developing a web-based Road Accident Information
Management System (RAIMS) and piloting in Kathmandu Valley and along the Kathmandu-
Birgunj Corridor together with the Traffic Police has been principally agreed by the Bank team.
DoTM agreed to carry out further detailed consultations with relevant stakeholders, especially to
ensure commitment for use of the proposed system by the Traffic Police. A clear role and
responsibility of the Traffic Police and DoTM, necessary training, and sustainability of funding
for regular operation and maintenance of such a system are also to be considered while preparing
the detailed work plan for developing and implementation of the system. DoTM agreed to
conduct such consultation workshop with the stakeholders and submit the final proposal and
work plan to initiate the implementation.
14. Component B1: National Single Window and Trade Information Portal (NSW/TIP).
During the mission, meetings were held with the Director General of Customs and the Project
Team in Customs, which is also the sub-PCO for the Project. The Project Team was formed by
DoC to specifically ensure coordination of all reform and modernization efforts within the DoC
including those associated with the NSW component of the Project. DoC briefed the mission
team of the activities they have undertaken with other stakeholder agencies to follow-up on the
priority actions outlined in the earlier work by the Bank’s NSW support consultants (KGH-
Arctiquator). The status of these recommendations and the actions agreed upon are attached as
Annex 4. The mission was pleased to note the progress on the recommendations and follow-up
activities of the earlier NSW technical assistance program.
15. DoC further briefed the mission on the current status of proposed ADB-financed
ASYCUDA World implementation. The Request for Proposal (RFP) for the implementation was
released to UNCTAD on September 1, 2014. UNCTAD has up to 45 days to respond. DoC
remains confident that they will have a signed contract with UNCTAD by early November 2014
and expect that UNCTAD will be able to mobilize and have their consultants working on the
ground by early January 2015 at the latest.
5
16. The mission noted that during the previous mission in February 2014 and subsequent
follow-up discussions with DoC, UNCTAD and ADB, it was assured that UNCTAD would be
on-the ground and working on the implementation of ASYCUDA World by September 2014.
The new schedule as described by DoC already reflects a slippage of four months assuming
contract negotiations and signing are carried out expeditiously and UNCTAD is able to mobilize
their consultant team by January 2015. The mission also noted that per the Management Letter
of April 15, 2014 from the Bank transmitting the revised Aide Memoire from the February 2014
Mission, it would be critical to have a fully operational ASYCUDA World implementation on or
about September 2015 to ensure enough time remaining in the project to complete the NSW
implementation and of the potential for cancellation of this component should this milestone be
missed. The current slippage of four months and the potential for further slippages during the
actual ASYCUDA World implementation is of significant concern to the mission. The mission
recommended that DoC spare no effort to speed up the contracting process with UNCTAD and
that DoC encourage UNCTAD to mobilize and start work as quickly as possible.
17. Selection of ICT Advisor (Procurement). The selection process is underway and the
Evaluation Report has been submitted to the Bank for review. The Bank’s comments on the
Evaluation Report have been sent to the PCO. The mission urges the PCO to review the Bank’s
comments, update the Evaluation Report and resubmit to the Bank as quickly as possible. The
mission also discussed that should this procurement slip too much then it would no longer be
necessary as the Quality Assurance/Supervision Consultant (para 18) will take on this role.
18. Selection of Quality Assurance/Supervision Consultants for NSW and TIP. The
Expressions of Interest for this assignment were received on August 19, 2014. The evaluation
committee expects to complete the short-listing process and submit the Short-List and RFP to
the Bank for No Objection by September 24, 2014.
19. Trade Information Portal (TIP). The mission met with TEPC and DoC on the TIP.
Little progress has been made on procuring the TIP implementation consultants as this is
dependent on the selection of the ICT Adviser (Procurement) or QA/Supervision Consultant,
since their expertise will be needed to develop the bid documents. The mission encouraged
TEPC and DoC to immediately begin the procurement process by issuing the Request for
Expressions of Interest (REOI) immediately in parallel with the remaining steps in the selection
process of the ICT Adviser (Procurement) or QA/Supervision Consultant. TEPC and DoC
agreed that a REOI would be published by September 22, 2014 for this assignment.
20. The mission informed TEPC and DoC of the recent release of the World Bank’s Trade
Information Portal Software Toolkit and its possible applicability for Nepal’s TIP. A
demonstration of the capabilities of the toolkit will be arranged for TEPC and DoC in the near
future.
21. Component B2 – Improvement of Trade-Related Laboratories. The project will
support the development and piloting of two trade-related laboratories which encompass Sanitary
and Phyto-sanitary (SPS), and Customs certification functions, one in Kathmandu Valley and
one at a border post. Following the survey of Nepal’s existing Customs and SPS laboratories by
Kathmandu School of Management (KUSOM) with DFID support, the mission agreed that next
6
steps would be for the Government to prioritize the exports that should be promoted through
consultation with public and private-sector stakeholders, and then for the Bank to send an
international expert on laboratory certification to review assessments done to date and to
propose an action plan for moving forward including helping DoC, MoCS, and Ministry of
Agricultural Development (MoAD) to draft ToRs for a consultant to begin the design of the pilot
laboratories.
22. Component B3 – PCO and NTTFC Strengthening. Additional staff for the PCO hired
since the last supervision mission include a Trade Facilitation and Logistics Technical Adviser
(September 2014) and a Project Manager (September 2014). The Bank reviewed the
procurement of these two (post-review) positions, and sent comments to the PCO about
procurement practices that need to be reviewed and corrected if necessary in future recruitments.
The Bank team reminded the PCO that on-call Environmental and Social specialists remain to be
recruited especially when the work on the Kathmandu ICD is ready to commence.
23. Now that the PCO is fully staffed, the mission reminded the PCO that each consultant
should draft a one-year work plan for his/her post laying out planned activities with clear
timelines, outputs and performance measures, and this work plan should be approved by the
Project Director and NTTFC. The Project Director and NTTFC should review performance at
least every six months and take correction courses of action as required. The mission also
reminded the PCO and NTTFC that a discussion should be held to clarify the roles and
responsibilities of the Project Director, Project Coordinator, Project Manager, Trade
Facilitation and Logistics Adviser among other PCO staff.
24. Given the complexity of this large multi-sector project and the delays experienced so far,
the mission reiterated to MoCS and the NTTFC that a full-time Project Director should be
appointed/hired to manage this project, rather than only part-time as the current practice..
The mission raised concern about the lack of a full-time Project Director for a multi-sectoral
project which is adversely impacting the implementation progress. The mission urges the
Government to give high priority to deputing a full time qualified Project Director with project
management experience as early as possible.
25. NTMs Adviser. The PCO issued an REOI to hire a national NTM Tracking Analyst but
did not receive interest from any qualified applicants. The mission recommended that an
International Adviser would be more appropriate for this post, and that this Adviser would
work with a World Bank expert on NTMs to implement a capacity development program for
Government officials and private sector stakeholders on how to identify, classify NTMs, store
and share the information, and seek ways to address them. The World Bank expert is expected
to arrive after the hiring of the International Adviser.
26. Component C1 – Narayanghat-Mugling Road Improvement Works and Studies for
Birgunj – Kathmandu Corridor. It is noted that the previous Project Coordinator has been
replaced since May 30, 2014. Substantial delay is noted in the award of contracts for the
Narayanghat-Mugling road improvement works (single package with three slices) though the
bids were received on April 4, 2014. The Bank did not provide No Objection to the Bid
Evaluation Report provided by DoR in July 2014 noting anomalies such as accepting bids from
7
bidders who did not provide a total bid price at the time of bid opening. A complaint from one of
the bidders during the bid evaluation process also revealed suspected leakage of confidential
information relating to the bidding process. The Bank team acknowledged receipt of DoR’s
request to cancel the present procurement process and to re-bid the works packages. For the
purpose of re-bidding, DoR agreed to expedite the process for reviewing/revising the cost
estimates, contract packaging, bid documents, and initiating the re-bidding process
expeditiously so that the contracts will be awarded by February, 2015.
27. DoR informed that the Project Manager’s Office (PMO) has updated the Resettlement
Action Plan (RAP) with support from the Project Management Consultant team and initiated its
implementation. The PMO has also initiated the necessary process to obtain forest clearances for
necessary tree cuttings.
28. Corridor Studies. Expressions of Interest for conducting feasibility and detailed designs
for the Mugling-Naubise-Kathmandu (Thankot) road improvement works, road safety audit of
the Birgunj- -Kathmandu Corridor, and the supervision of the N-M road improvement works has
been received and presently in evaluation process. The draft ToR has been prepared and is
presently under discussion. DoR agreed to complete the shortlisting, and prepare and submit
the draft Request for Proposal to the Bank by September 16, 2014.
29. The draft ToR for the Birgunj-Kathmandu Corridor Sustainability Study has been
developed and discussed. DoR agreed to prepare the REOI and initiate the procurement
process immediately.
30. Since the Birgunj-Pathlaiya section is a key section along the Birgunj-Kathmandu
Corridor which handles all traffic to the East and West of Nepal that enters from Raxaul, it was
agreed to initiate the process for conducting detailed designs and required environmental and
social studies for improving this section. Considering an opportunity to utilize performance-
based contracting which allocates design, implementation, and maintenance responsibility to
the bidders, DoR agreed to further explore this mode of contracting/implementation. The
Bank team agreed to send an international expert to initiate discussion and planning for such
performance-based contracts. DoR will also plan to procure the consultant to draft the
independent detailed Environmental Impact Assessment (EIA) and RAP for this road section
about six months after the procurement of the Birgunj-Kathmandu Corridor Sustainability
Study.
31. The mission also agreed that detailed designs for the 18 bridges along N-M road
(currently financed by the Bank’s Road Sector Development Project – RSDP) would be
expedited to the extent possible for completion before June 2015 and financing options
considered as these bridges affect the performance of the Birgunj-Kathmandu Corridor which
will eventually impact the Project Development Objective.
32. Operational Costs for DoR. The Project informed that no operational funds have been
provided for this component by the Government. As agreed during the design stage, Government
should provide operational costs to DoR for this component. Operational costs are needed mainly
for supervision and monitoring by the Project Office and Coordination Office.
8
33. Component C2. Development of Inland Container/Clearance Depot (ICD) in
Kathmandu. There has not been much change in the status of this component since the previous
mission. GoN has been trying to acquire the land at the Chovar site (former Himal Cement
factory) for the construction of the ICD in Kathmandu. However, even though the Government
owns the land title at the Chovar site and the budget speech of 14/15 clearly allocated the land to
the development of the ICD, its acquisition will require a liquidation process which can take a
long time. In the meantime GoN was also exploring another option, which is for the Government
to transfer land to NITDB while starting the liquidation process. The Bank strongly urged MoCS
and the PCO team to work with MoF to take all necessary measures to acquire the land with
free/clear title, including setting up a Committee with relevant stakeholders to specific address
this issue, proactively solve problems and monitor progress on a bi-weekly basis. The mission
reminded the NTTFC, MoCS and the PCO that if land for the proposed ICD is not acquired by
September 2015, the Bank will be forced to cancel this important and transformational
component as there would be insufficient time left to design and build the ICD. To expedite
activities as much as possible, the Bank agreed to NITDB’s proposal to hire a consultant
immediately after the GoN makes the land procurement decision, to initiate a topographical
survey of the proposed area at Chovar and other possible sites to map the available land area
and topography and to prepare a conceptual master plan. This preliminary survey and study is
expected to help in scoping the detailed design services.
34. Component C3. Improvement of Bhairahawa and Birgunj ICDs. The contract for
rehabilitation works of the pavement at Bhairahawa ICD has been signed and the contractor is on
site. The contractor has conducted the joint verification survey, established the site office and
laboratory, and the design is currently being reviewed by the Supervision Consultant. However,
physical works are yet to start mainly due to the monsoon season and some issues related to the
availability of construction materials, especially due to Government’s environmental regulatory
provisions on quarrying of sand and aggregate construction materials. It was agreed to finalize
the design review, update the work schedule based on required resources, check the laboratory
requirements, and expedite activities for the Bhairahawa pavement works. Now that the monsoon
season has concluded, NITDB agreed to conduct a kick-off/launch meeting with the contractor
and Supervision Consultant, including a field visit to Bhairahawa with the Bank team before
end-September, 2014.
35. The Supervision Consultant for Bhairahawa ICD pavement works and Birgunj Shed
Extension works has been appointed, and has started mobilization activities and the design of the
Birgunj Shed Extension works. The Bank team advised the NITDB Project Team to expedite the
preparation of design and bid documents for the Birgunj Shed Extension works so that the
contract could be signed by January, 2015. Regarding the railway track improvement works
within Birgunj ICD, the NITDB is recommended to expedite the design activities in close
coordination with Indian Railways. NITDB plans to visit the relevant Indian Railways offices to
coordinate for necessary design and implementation of proposed railway track improvement
works and to look for options to procure services for the design and implementation works.
Thus, for Component C3, the next steps are:
Conduct a kick-off/launch meeting with the contractor and Supervision Consultant,
including a field visit to Bhairahawa with the Bank team before end-September, 2014
9
Initiate works on the Bhairahawa ICD pavement by end September, 2014
Complete the design of Birgunj Shed Extension works by early October, 2014
Procure the contract for Birgunj Shed Extension works by January 2015
Coordinate with Indian Railways and finalize the process for procuring services for the
design and implementation of railway track improvement works at Birgunj
36. Corridor Monitoring System. The mission discussed with NITDB the development of
the Corridor Monitoring and Evaluation Data Management System (CMEDMS). The Bank
fielded a mission to Nepal in June 2014 during which there were discussions on the technical
aspects of the system. NITDB then proposed a two-step process starting with a quick (4-6 week)
initiating consultancy to essentially: a) document what data are available in the various
counterparts especially in India; b) What data are needed and not available; c) willingness of
entities (especially in India) to share the data; and d) what Memorandum of Understandings
(MOUs), Protocols or Agreements need to be negotiated and signed and with whom to provide
data. The second phase would be the design and building of the system. The first step was
conceived as a way to lay the ground for a sustainable system, not one based on ad-hoc
arrangements. While this approach was much more involved than had originally been envisaged,
the mission agreed to it as it helps improve the design and the cost in terms of resources and time
was minimal. NITDB had since published a REOI for the first stage work. EOIs have been
received and evaluated and the RFP has been issued on September 15, 2014. It is expected that
procurement for the second stage works will commence in January 2015.
37. Results Monitoring and Evaluation (M&E). A Satisfactory rating of Monitoring and
Evaluation (M&E) is maintained as the PCO has been able to submit consolidated progress
reports to date. The overall monitoring and evaluation for the Project is managed by the PCO.
Each implementing agency or sub-PCO will monitor its own work plan and indicators and report
to the PCO for consolidation. The newly-recruited PCO Project Manager will work with sub-
Project Coordinators to develop detailed work plans and monitoring plans. A template has been
developed and is included in Annex 7. NITDB is directly responsible for two of the three PDO
indicators. The first results indicators were determined using an elaborate survey conducted by
KUSOM. However, the surveys have been financed under a contract between KUSOM and
DfID. The mission urged NITDB to consider engaging a relevant agency or KUSOM as soon as
possible to discuss how NITDB plans to continue gathering the data. This was critical as data is
expected to be gathered semi-annually and included in the monitoring reports. Based on the
available data the PDO indicators are shown below.
PDO Indicator Process Baseline Year 1
Target
Year 1
Actual
Time associated with meeting
regulatory requirements for import,
export and transit activities (days)2
Import 14 14 14
Export 14 14 14
Border Crossing time at Raxaul- Import 2.3 2.3
2 From Doing Business Trading Across Borders (2014)
10
Birgunj border post.3 Export
Total time between cargo
offloading at Kolkata to arrive in
Birgunj by road and rail
Road 10 10
Rail 22 22
Total time Birgunj to Kathmandu
for trucks (days) 4
Road
38. Procurement. PCO/MoCS: Procurement Performance Rating for the Project has been
downgraded to “Moderately Unsatisfactory”. The Bank team reviewed the implementation
status of the procurement plan. Though the procurement process is moving, there has been delays
due to the overly complex decision-making process which could be simplified. To normalize the
procurement process with those adopted in all public entities, it is recommended that the Bid
Evaluation Committee (BEC) evaluates the bids/proposals and forwards its report with
recommendation to the Project Director. Then the Project Director makes the procurement
decision as per the prevailing rules and regulations of the country. The Project Coordination
Committee’s role is mainly to provide overall coordination and guidance to the Project. Day-to-
day procurement activities should be taken by the Procurement Specialist/Consultant, Bid
Evaluation Committee and Project Director with necessary advice from relevant sub-PCO
technical units and experts. For evaluating bids and proposals, the Bid Evaluation Committee
should comprise the Procurement Specialist/Consultant and relevant technical experts
(consultants, experts from other GoN agencies, etc.). Going forward, the PCO is required to
obtain technical clearance from the Bank in the procurement of consultants/experts to ensure
quality procurement including adequacy of the experts' qualifications and experience for the
assignment, even if the procurement activity falls under the post-review category in the approved
procurement plan.
39. Based on the Bank's observations on the PCO's current capacity to manage procurement,
the PCO has to make improvements in the points mentioned above to be retained on the current
risk rating of "SUBSTANTIAL". The Bank procurement team is currently reassessing the
Project’s procurement capacity and risk rating.
40. It is also recommended that the PCO organize a joint procurement and FM orientation
program as soon as possible for all project officials involved in procurement and FM processing,
reviewing and decision making to enhance their capacity and facilitate project implementation.
The PCO had planned to conduct -the orientation/training workshop on September 26 2014 and
the World Bank team will provide resource persons for the program.
41. DoR: The bidding of works contracts of Narayanghat - Mugling Road has suffered
delays as discussed above in paragraph 26. DoR has expressed its commitment to avoid such
practices in the future by making necessary corrective arrangements including awareness raising
programs among the bidding community.
3 KUSOM survey data for September – October 2013
4 KUSOM survey data for September – October 2013
11
42. Financial Management. MoCS PCO- The budget of NPR 238.06 million is approved
for FY2014/15. The annual work program is approved and expenditures of about NPR 1.39
million were incurred until September 11, 2014 in FY2014/15. The review team noted that the
Government counterpart fund is sufficient and previous agreed actions have been complied with.
Expenditures of NPR 38.37 million were incurred out of an approved budget of NPR 76.78
million in FY2013/14.
43. There are no overdue IPRs. The first trimester IPR of FY2014/15 is due on December 31,
2014 and the audited project account of FY2013/14 is due on January 15, 2015. The project has
submitted the unaudited project account of FY2013/14.
44. DoR PCO: The budget of NPR 1,192.67 million is approved for FY2014/15 and so far
there is no expenditure as the annual work program is not yet approved. The review team noted
that previous agreed actions have been complied with. However, Government counterpart funds
have not been provided to DoR for Component C1. Expenditures of NPR 22.23 million were
incurred out of approved budget of NPR 304.25 million in FY2013/14. The expenditures related
to the IDA part (GoN Reimbursable) have been reimbursed to the Government Treasury.
45. The third trimester IPR of FY2013/14 is now overdue. The first trimester IPR of
FY2014/15 is due on December 31, 2014; the unaudited project account of FY2013/14 is due on
October 15, 2014; and the audited project account of FY2013/14 is due on January 15, 2015.
46. Based on information provided on the budget for FY2014/15, the review team noted that
the counterpart funding of GoN is “Moderately Unsatisfactory”. Based on the completion of the
agreed actions and the progress made on financial management, the performance rating for
financial management is “Moderately Satisfactory”. Agreed Actions include:
i. Submission of the third trimester IPR of FY2013/14 (by DoR PCO) by September 12,
2014
ii. Conduct FM/Procurement training of Sub PCOs (by MoCS PCO) by October 31, 2014
47. Environmental Safeguards: MoCS/PCO: For the ICD and laboratory subprojects,
given their current status it was agreed with MoCS that a full-time environmental specialist is not
yet needed; therefore, the NITDB’s Technical Adviser is currently taking responsibility for
ensuring EMP/ESMF compliance at the Bhairahawa ICD (the only subproject getting to the
construction phase), and appropriate incorporation of safeguard measures into Birgunj ICD
designs and construction plans. The environmental safeguards actions linked to the works at the
ICDs include:
Following up on and ensuring disclosure of all safeguards docs, including summaries in
Nepali (both locally and on the MoCS website), and forwarding links/records to the WB;
Reviewing the final designs and bid docs for Birgunj ICD to make sure they reflect all the
EMP requirements and commitments;
Developing and publicizing site-specific grievance mechanisms / ways for local
communities to get in touch with MoCS/NITDB about construction impacts, etc., for any
ICD works, and ensuring grievances get documented and addressed;
Making sure contractors know the EMP requirements;
12
Managing the Supervision Consultant – e.g. reviewing their monitoring reports, making
sure they are doing their job and commenting on environmental compliance aspects,
following up on any non-compliance issues and recommendations;
Making occasional site visits during construction to visually inspect environmental
management aspects and have discussions with contractors and supervision consultants
about any challenges or issues of non-compliance (recommend at least once per quarter);
Preparing progress summaries on ESMF implementation for WB missions;
Making sure that, as the next ICD and laboratory projects go forward, environmental
screening is carried out and full assessments (or audits, in the case of existing laboratory
facilities) are done if required;
48. As described in paragraph 8, the ESMF for the MoCS- managed components has been
disclosed in Nepali, however by technical error it was removed and recently it has been
uploaded again; and the EMPs for the works at Bhairahawa, and Birgunj ICDs have not been
disclosed in either English or Nepali. MoCS was expected to do this by mid-March 2014 but
still has not. It has been agreed that this will be completed urgently.
49. DoR Staffing: Pre-construction EMP-related activities for the N-M road are meanwhile
currently being handled by the Environmental Safeguards Expert consultant in DoR’s Geo-
Environment and Social Unit (GESU) hired under the World Bank Road Sector Development
Project (RSDP), as well as the Project in Charge for N-M road who is personally managing all
government liaison tasks related to forest clearances and utility/public infrastructure shifting.
The project plans to retain this Expert (through GESU) full-time once the RSDP project closes
(expected in June 2015). The mission cautiously agreed to this staffing arrangement, but
recommended that staffing needs be reviewed prior to contractor mobilization, when the
workload will increase substantially -- especially since the RSDP workload will likely also
remain high for a period of overlap, and two new major consultant contracts with environmental
components (for Kathmandu-Naubise-Mugling road upgrading, and Strategic ESA /
Sustainability Study) will also be getting underway. If needed, DoR should bring on an
additional environmental consultant on an intermittent basis to backstop the Environmental
Safeguards Expert.
50. N-M road EMP implementation: DoR is currently working to secure forest clearances
for tree cutting and necessary permissions for shifting of utilities and public infrastructure,
including conducting consultations with relevant stakeholders and user groups to coordinate cuts
in services during the shifting and to finalize the new alignments / locations for affected
infrastructure. The mission emphasized the need to document all such consultation events. DoR
further agreed to start defining the afforestation program and hold discussions with Department
of Forests and other relevant partners / stakeholders, so that the plan can start being implemented
by the time tree felling begins. DoR will further review the EMP and compile a comprehensive
pre-construction stage work plan and schedule by October 15, 2014 to ensure all pre-
construction activities are on track.
51. Strategic ESA / Sustainability Study: For the Birgunj-Kathmandu Corridor Strategic
Environmental and Social Assessment (ESA) / Sustainability Study, a field visit and
consultations with key stakeholders was carried out by a joint World Bank - DoR team including
13
environmental and social specialists in May 2014. The World Bank developed initial draft ToRs
for the study, which were shared and discussed with DoR during the mission. As a next step,
DoR will provide comments on the draft ToR to the World Bank by September 30, 2014. DoR
will also propose specific measures or activities to advance capacity on biodiversity
management in the roads sector in their revisions to the ToR.
52. Summary of key agreed actions by DOR relating to environmental safeguards include:
To immediately share with the Bank the records from consultations with water user
groups and water supply division on shifting of water supply lines;
To ensure ongoing documentation of all consultation events related to utility shifting and
any other pre-construction activities;
To internally discuss and agree to approach for afforestation program, and define detailed
program and budget with input from Department of Forests, other potential partners and
stakeholders, by April 2015 (in advance of tree felling);
To develop a work plan for all pre-construction EMP activities and share with the Bank
by October 15, 2014;
To review staffing adequacy on environmental management prior to contractor
mobilization on N-M road, and to hire additional consultant on intermittent basis to
backstop Environmental Safeguards Expert if required;
To re-issue contract for Environmental Safeguards Expert under NIRTTP project funds
by July 1, 2015, when the existing contract through RSDP expires;
To provide comments on draft ToR for Strategic ESA / Sustainability Study by
September 30, 2014; and,
To propose specific measures or activities to advance capacity on biodiversity
management in the roads sector in their revisions to the Strategic ESA / Sustainability
Study ToR.
53. Social Safeguards. The focus of the mission was to review the progress made towards
implementation of the Resettlement Action Plan (RAP) on N-M road including documentation of
consultations and grievance management and quarterly progress reports. Additionally, the
comprehensive draft ToR for feasibility and detailed preparation of K-N-M road and the
proposed Strategic Environmental and Social Assessment for Birgunj-Kathmandu Corridor were
discussed. Social safeguards is rated Satisfactory for the following reasons:
a. Implementation of RAP – DoR has made substantial progress to resettle the affected
households. During the course of verification and design modification, the number of
affected households affected by the bridge and road works has reduced from 74 to 45. A
representative Village Development Consultative Committee and the Compensation
Determination Committee were set up to finalize the compensation and rehabilitation
package for affected households. All 45 affected households have received the first
installments including 5 households affected by bridge works (see Annex 5 for details).
Remaining activities to ensure resettlement and rehabilitation will be completed before
the mobilization of contractors.
14
b. Documentation – Discussions with the project staff indicate that consultations are held
regularly for which minutes are prepared. However, grievances are mostly verbal and
field staff address them. The progress report consolidates data which needs to be
supported with brief write-ups on the process of implementation. It was agreed that a log
book will be maintained to document each complaint received including the nature of the
complaint and actions taken to resolve it. DoR will submit a comprehensive report on
consultations and grievance management to be included in the progress report which will
be submitted by October 31, 2014.
c. Corridor Studies – Detailed discussions were held on the ToR for the preparation of
Kathmandu-Naubise-Mugling road to explain the level of social assessment required at
different stages of project preparation. It was agreed that the feasibility will include a
rapid assessment of impact area, consultation, resettlement and rehabilitation framework,
institutional assessment, broad mitigation measures, monitoring indicators and cost
implication. These will be detailed out during the design phase and a Resettlement Action
Plan (RAP) will be prepared. For the strategic study, a detailed social assessment is not
required. It was advised that the Consultant should use the various studies carried out for
the entire Kathmandu-Birgunj Corridor which include feasibility and detailed RAPs, and
others to establish the scale of impact. It was agreed that the ToR will be accordingly
revised.
d. Staff – Currently the project is dependent on the Social Specialist hired for the Bank-
supported RSDP project to coordinate and monitor the implementation progress.
However, there will be a vacancy with RSDP coming to closure by June 2015. Although
positions for Social and Environment Specialists have been created in the Geo-
Environment and Social Unit (GESU), these have yet to be adequately staffed.
Recognizing the increase in responsibility including reviewing project documents for new
sections, preparing progress reports, etc., it was agreed that the project will mobilize a
Social Specialist (consultant) on July 1, 2015.
e. Citizen’s Feedback: It is encouraging to note that DoR has created a web-based
grievance management system for the sector as a whole. The Governance Peace and
Action plan agreed upon during negotiations includes provisions for setting up a citizen’s
feedback mechanism. The current arrangement on grievance mechanism might dissuade
citizens to give feedback. It is suggested that DoR could perhaps explore the possibility
of creating an additional tab on the department’s website to facilitate engagement with
citizens.
15
NEXT STEPS
54. The PCO and implementation agencies agreed to expedite the implementation of
activities listed in the Project Implementation Plan (Annex 2). The following key next steps were
agreed:
Component A1
a. The PCO needs to work with MoCS and the NTTFC to propose a work program for this
component.
b. The Bank team requested to see the inception report and progress reports prepared by the
Transshipment Study consultant.
Component A2
c. DoC to work with MoCS, CBEC, and GoI to expedite the computerization of the
Customs Transit Document, and to engage with IFC on their offered support. The World
Bank Group Board will be notified by the mid-term review of the new reduced amount of
support from the IFC.
Component A3
d. DoTM to complete the procurement of the consulting services for the axle load study and
transport safety study.
e. DoTM to complete consultations and develop the work plan for the development and
piloting of the Road Accident Information Management System (RAIMS) in Kathmandu
Valley and along the Kathmandu-Birgunj Corridor.
Component B1
f. PCO/DoC/TEPC to complete the procurement for the QA and Supervision Consultant for
SW/TIP.
g. PCO/DoC/TEPC to initiate the procurement of the Consultant to build the Trade
Information Portal.
Component B2
h. DoC and Ministry of Agricultural Development to lead the consultation process with
MoCS, trade-related agencies and private sector stakeholders to prioritize products for
export promotion. The Bank will send an international expert on laboratory certification
to review assessments done to date and to propose an action plan for moving forward.
Component B3
i. PCO to ensure that hired consultants draft a one-year work plan for his/her post laying
out planned activities with clear timelines, outputs and performance measures.
j. PCO and NTTFC should hold a discussion to clarify the roles and responsibilities of the
Project Director, Project Coordinator, Project Manager, Trade Facilitation and Logistics
Adviser among other PCO staff.
k. MoCS to consider appointing/hiring a full-time Project Director to manage this project.
16
Component C1
l. DoR to accelerate the re-bidding process for N-M road improvement works.
m. DoR to complete shortlisting and issue RFP for the consulting services including CSC for
N-M road, feasibility and detailed designs for the Mugling-Naubise-Kathmandu road
improvement and road safety audit of the Birgunj-Kathmandu Corridor.
n. DoR to finalize the TOR and initiate the procurement of the consulting services to
conduct the Environmental Sustainability Study for the Birgunj-Kathmandu Corridor.
o. DoR to plan and explore the use of performance-based contracts for improving and
maintaining Birgunj- Pathlaiya road.
p. DoR to accelerate the detailed designs for works on the 18 bridges along N-M road.
Component C2
q. MoCS/PCO to proactively follow-up with MoF and other relevant stakeholders on land
acquisition for Kathmandu ICD as a matter of urgency.
r. NITDB to hire a consultant to conduct a survey and prepare a topographical map and
conceptual design for the Kathmandu ICD.
Component C3
s. NITDB to complete the design of Birgunj Shed Extension works by end September 2014
and procure the contractor for the works by January 2015.
t. NITDB to complete procurement of consulting services to develop the CMEDMS
system.
Procurement
u. PCO to organize a joint procurement and FM orientation program as soon as possible (by
end-September, 2014) and notify the Bank of the date.
Financial Management
v. DoR to send the third trimester IPR of FY2013/14 (due August 31, 2014) by September
12, 2014; submit the first trimester IPR of FY2014/15 by December 31, 2014; the
unaudited project account of FY2013/14 by October 15, 2014; and the audited project
account of FY2013/14 by January 15, 2015.
Safeguards
w. MoCS to disclose the ESMF for the MoCS-managed components in Nepali; and the
EMPs for the works at Bhairahawa, Birgunj and Kathmandu ICDs in English and Nepali
immediately.
x. DoR will review the EMP and compile a comprehensive pre-construction stage work plan
and schedule by October 15, 2014 to ensure all pre-construction activities are on track.
y. DoR will provide comments on the draft ToR for the Corridor Sustainability Study to the
World Bank by September 30, 2014, including proposing specific measures or activities
to advance capacity on biodiversity management in the roads sector, and incorporating
comments discussed on the social safeguards front.
z. DoR to complete remaining activities related to ensure resettlement and rehabilitation
along N-M road before the mobilization of contractors.
17
55. Next Mission : The next implementation support and review mission is planned for
February/March, 2015 although interim missions for sub-projects may be arranged before the
next main mission.
List of Annexes
1. List of persons met
2. Updated Project Implementation Plan (PIP)
3. Results Framework and Monitoring matrix
4. Follow up on key actions for NSW/TIP
5. Progress of RAP/Social Safeguards Implementation Plan
6. Environmental Safeguards Action Plan
7. Proposed template for sub-project reporting/monitoring
18
ANNEX 1: LIST OF PEOPLE MET
National Planning Commission
1. Mr. Swarnim Wagle, Member, National Planning Commission
Ministry of Finance (MoF)
2. Mr. Surya Prasad Acharya, Director General, Department of Customs
3. Mr. Ramesh Sharma Paudyal, IT Director, Customs Reform and Modernization Section,
Department of Customs
Ministry of Commerce and Supplies (MoCS)
4. Mr. Deepak Subedi, Acting Secretary, MoCS
5. Ms. Chandra Kala Paudel, Joint Secretary, MoCS
6. Mr. Jib Raj Koirala, Joint Secretary, MoCS
7. Mr. Toya Nath Gyawali, Joint Secretary, MoCS
8. Mr. Mahesh Timsina, Under-Secretary/Project Coordinator, PCO
9. Mr. Navaraj Dhakal, Under-Secretary, MoCS
10. Mr. Keshab Prasad Prasai, Under-Secretary/Accounts Officer, PCO
11. Mr. Chandra Kishor Mishra, Procurement Specialist, PCO
12. Mr. Moti Bahadur Shrees, Section Officer, PCO
13. Mr. Ishwari Prasad Ghimire, Executive Director, Nepal Trade & Export Promotion Centre
14. Mr. Surendra Nath Gongal, Deputy Director, Nepal Trade & Export Promotion Centre
15. Mr. Hemendra Shahi, Acting Executive Director, NITDB
16. Mr. Sunil Poudyal, Technical Advisor, NITDB
17. Mr. Rabindra Pokharel, Engineer NITDB
18. Mr. Murari Prasad Gautam, Project Manager, PCO
19. Mr. Himal Thapa, Trade Facilitation and Logistics Adviser, PCO
Ministry of Physical Infrastructure and Transport (MoPIT)
20. Mr. Devendra Karki, Director General, DoR
21. Mr. Sanjaya Kumar Shrestha, Deputy Director General, DoR
22. Mr. Keshab Sharma, Deputy Director General, DoR
23. Mr. Ajay Kumar Mull, Sr. Divisional Engineer, DoR
24. Mr. Rupak Rajbhandari, Sr. Divisional Engineer, DoR
25. Mr. Shiva Prasad Nepal, Unit Chief, Geo-Environment & Social Unit, DoR
26. Mr. Shyam bahadur Khand, Project Manager, N-M Road, DOR
27. Ms. Meera Shrestha, Environmental specialist, GESU, DOR
28. Ms. Rama Shrestha, Social specialist, GESU, DOR
29. Mr. Kashi Raj Dahal, Director General, DoTM
30. Mr. Sharad Adhikary, Director, DoTM
31. Mr. Padam Bahadur Shahi, Technical Adviser, DoTM
Ministry of Agricultural Development
32. Dr. Pradhyumna Raj Pandey, Sr. Agriculture Economist, MoAD
33. Mr. Arun GC, Agri-Extension Officer, MoAD
Federation of Nepalese Chambers of Commerce and Industry (FNCCI)
34. Mr. Rajan Sharma, Executive Member/Co-Chairperson
19
ANNEX 2:
Nepal India Regional Trade and Transport Project – Project Implementation Plan (PIP)
Updated September 11, 2014
# Responsible Agency
Activity Date Due/Comments Project Status
General Conditions
1. MoCS through Ministry of Law and Justice
Legal Opinion for the Project Immediately Done
2. MoCS Letter from PD to WB informing of achievement of Legal Covenants 3-7 in order to declare the Project effective
Immediately Done
Legal Covenants 3. PCO (MOCS) Project Operations Manual detailing the roles and responsibilities of the
PCO and of each implementing agency July 15, 2013 Done
4. PCO (MOCS) Mandate the NTTFC with terms of reference to be responsible for providing overall leadership and policy guidance on key policies and implementation decisions regarding the Project.
July 15, 2013 Done
5. PCO (MOCS) Assign a dedicated Project Coordinator, and maintain such Project Coordinators for a period of at least two years
July 15, 2013 Done
6. DoC Formalize (i) the terms of reference for the Technical Committee for the National Single Window and Trade Portal; (ii) the terms of reference for the Project Coordinator for the National Single Window; and (iii) the terms of reference for the Project Coordinator for the National Trade Portal, all to be implemented under Part B1 of the Project.
July 15, 2013 Done
7. PCO (MOCS) (i) Furnish to the Bank an annual work program and budget for FY2013/14 which includes this Project in the Red Book, and (ii) assign two separate budget codes for the Project, one for the PCO and the other for the DoR.
August 15. 2013 Done
Disbursement Procedures
8. PCO (MOCS) and DoR
Authorized Signatures: A letter should be furnished to the World Bank providing the name(s) and specimen signature(s) of the official(s) authorized to sign Applications (Disbursement Guidelines, subsection 3.1)
Upon effectiveness Done
9. PCO (MOCS) and DoR
Create Designated Accounts (DA), two segregated Accounts Upon effectiveness Done
10. PCO (MOCS) and DoR
Created account in Client Connection/ activate secure ID tokens Upon effectiveness Done
20
11. PCO (MOCS) and DoR
Provide completed and signed applications for withdrawal, together with supporting documents (Year 1 disbursements expected to be at least USD2,359,594 but hoping for USD12.5 million)
Upon effectiveness Done
Governance and Peace Action Plan 12. PCO (MOCS) and
DoR Information Disclosure : A proactive public disclosure system will be established (as discussed in Information disclosure section)
Immediately when needed
Done
13. PCO (MOCS) and DoR
Information Disclosure: Information will be disseminated through local workshops, group discussions, information campaigns, and participatory community forums.
Periodically Done
14. PCO (MOCS) and DoR
Information Disclosure: Consultations and participatory planning with project-affected people, CSOs, and other stakeholders during implementation.
Periodically Ongoing
15. PCO (MOCS) and DoR
Information Disclosure: Establishment of Local Consultative Forum (LCF) at VDC to ensure ongoing dissemination of project information to affected households, and structure, regulate and strengthen communication between roadside communities.
Immediately Ongoing
16. PCO (MOCS) and DoR
Complaint Handling: Develop grievance-redress mechanisms so citizens and CSOs can lodge complaints about technical, fiduciary and environmental/social impacts. DoR is in the process of developing this system for all of its projects and the entire Department.
Immediately Ongoing
17. PCO (MOCS) and DoR
Complaint Handling: Establish Local Consultative Forum (LCF) at VDC to involve affected communities and local government structures in social impact management, grievance resolution and monitoring.
Immediately Ongoing
18. PCO (MOCS) and DoR
Monitoring and Citizen Feedback: Proactive disclosure of information and social accountability mechanisms to solicit stakeholder and user feedback will be implemented.
Immediately Ongoing
19. DoR Monitoring and Citizen Feedback: Use third-party monitoring for the Narayanghat-Mugling road
By Year 2 To be done during implementation
20. PCO (MOCS) and DoC
Monitoring and Citizen Feedback: Seek feedback from Nepal Business Forum on progress on National Single Window and Trade Portal.
Periodically Business community represented in NTTFC
21. PCO (MOCS) and DoR
Procurement: Use e-bidding for receiving bids from contractors, which has shown to significantly increase in competition and has proved to be an effective measure to reducing collusion and coercion among bidders.
All bids Begun from National Competitive Bidding of pavement restoration of Bhairahawa ICD
21
Procurement 22. PCO (MOCS) Send General Procurement Notice (GPN) for entire Project to WB for No
Objection Aug 2, 2013 Done
23. PCO (MOCS) and DoR
Publish GPN on MoCS/DoR websites, UN/DG Market and local newspaper August 7, 2013 Done
24. PCO (MOCS) Send updated PP to WB for No Objection August 15, 2013 Done
25. PCO (MOCS) Procurement Training – Find the next session and organize to attend August 26, 2013 Done
Component A1–TA to Modernize Bilateral Transit Regime 26. PCO (MOCS) Selection of Trade Facilitation and Logistics Adviser
- Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
TORs to be submitted to WB by September 5, 2013
Done National Consultant hired August 2014
27. PCO (MOCS) Selection of NTM Tracking Analyst - Draft TORs - REOI then publish on website/local paper - Selection and contract award
TORs to be submitted to WB by September 30, 2013 –Budget will be
revisited
Reissue REOI for International
Consultant/Adviser
28. PCO (MOCS) Study on Transshipment - Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
TORs to be submitted to WB by September 15,
2013
Contract signed and the expert visited both Kolkata and
Mumbai Ports. Draft report expected November 2014
Component A2–Electronic Data Interchange between Nepal and India 29. DoC Manage activities to ensure achievement of Electronic Data Interchange and
automation of the Customs Transit Document (CTD) between Nepal and India (through IFC financing and management)
To be determined DoC/MoCS to interact with IFC asap to develop work plan
and start implementation
Component A3 – Capacity Development for DoTM Transport Management 30. DoTM thru PCO Selection of Technical Adviser
- Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
TORs to be submitted to WB by August 14, 2013
Done
31. DoTM thru PCO Selection of Project Assistant - Draft TORs
TORs to be submitted to WB by August 14, 2013
Done
22
- REOI then publish on website/local paper - Selection and contract award
32. DoTM thru PCO Study for road safety and axle load control - Draft TORs (completed) - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
Draft RFP sent to WB by November 1, 2013 (after
Technical Advisor is in place)
Evaluation of proposals to be completed by
September 19, 2014
33. DoTM thru PCO Study for road safety from transport management perspective - Draft TORs (completed) - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
Draft RFP sent to WB by November 1, 2013 (after
Technical Advisor is in place)
Cancelled – combined with study
in Activity #32
Component B1 – Single Window and Trade Portal 34. DoC thru PCO Selection of IT Procurement Adviser
- Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
Individual consultancies changed to firm contract for all specialists as Trade Portal/Single Window as well as DoC ICT capacity strengthening Program Management and Quality Assurance Support (international firm w/ local firm World Bank to propose draft terms of reference by August 21, 2014
Re-evaluation to be completed and contract signed by end-September, 2014
35. DoC thru PCO Selection of Project Assistant (Local) - Draft TORs - REOI then publish on website/local paper - Selection and contract award
Done
36. TEPC thru PCO Selection of Quality Assurance Advisory Firm for Supervision - Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
EoI evaluation to be completed by September 19, 2014
37. TEPC thru PCO Selection of Project Assistant (Local) - Draft TORs - REOI then publish on website/local paper - Selection and contract award
To be decided
38. DoC thru PCO Selection of Various IT Resources, Equipment, etc… - Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
To be initiated after consultation with Selected QA firm/ ICT Adviser
39. DoC and TEPC Selection of Firm to Design and Build Trade Portal REOI to be published REOI to be published
23
thru PCO - Draft Bid Docs - REOI to WB for N.O. then publish on website/local paper - Shortlist and RFP to WB for N.O. - RFP to shortlisted firms - Selection to WB for N.O. - Contract award
September 1, 2013 after WB N.O. Bidding documents to be
submitted on September 15
September 17, 2014
40. DoC and TEPC thru PCO
Selection of Firm to Design and Build Single Window - Draft Bid Docs - REOI to WB for N.O. then publish on website/local paper - Shortlist and RFP to WB for N.O. - RFP to shortlisted firms - Selection to WB for N.O. - Contract award
REOI to be published February 2014 after WB
N.O.
To be initiated after consultation with
Selected QA firm/ ICT Adviser and after
operationalization of ASYCUDA World
Component B2 – Trade-Related Laboratories 41. DoC thru PCO Selection of Technical Adviser
- Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
Assess mid-year To be determined
42. PCO (MOCS) with DFTQC and DoC
Initial survey Detailed study and Work plan on moving forward with trade-related laboratories including change management workshops/sessions
- Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
DFID to contract Kusom for initial survey work
WB expert to arrive in November, 2014 to
help develop work plan for moving
forward
Component B3 – PCO and NTTFC Strengthening 43. PCO (MOCS) PCO Office Lease - Rental Immediately Done
44. PCO (MOCS) PCO Furniture Purchase Immediately Done
45. PCO (MOCS) PCO Equipment Purchase Immediately Done
46. PCO (MOCS) PCO Vehicles Purchase Immediately Done
47. PCO (MOCS) Selection of Technical Adviser/Project Manager - Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
TORs to be sent to WB by August 31, 2013
Selected and joined
PCO on Sep. 03, 2014
24
48. PCO (MOCS) Selection of Full-time Procurement Specialist - Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
TORs to be sent to WB by August 31, 2013
Done
49. PCO (MOCS) Selection of Part-time/Intermittent Procurement Specialist - Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
TORs to be sent to WB by August 31, 2013
Selection done, and will be contracted as and when necessary on intermittent basis
50. PCO (MOCS) Selection of Finance Assistant - Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
TORs to be sent to WB by August 31, 2013
Done
51. PCO (MOCS) Selection of Environmental Safeguards Specialist - Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
TORs to be sent to WB by August 31, 2013
To be done after finalizing land for Kathmandu ICD
52. PCO (MOCS) Selection of Social Safeguards Specialist - Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
TORs to be sent to WB by August 31, 2013
To be done after finalizing land for Kathmandu ICD
53. PCO (MOCS) Selection of Various Secretarial/Support posts - Draft TORs - REOI then publish on website/local paper - Selection and contract award
TORs to be sent to WB by August 31, 2013
Some support staff have been selected
54. PCO (MOCS) Selection of Monitoring and Evaluation (M&E) Specialist - Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
TBD
To be done as and when necessary on
intermittent basis
55. PCO (MOCS) Selection of NTTFC Secretariat Post 1 (Trade Facilitation Adviser) - Draft TORs - REOI (to WB for N.O. if prior review) then publish on website/local
Assess the need at a later date. TORs by December
2013
To be determined if needed
25
paper - Selection and contract award (to WB for N.O. if prior review)
56. PCO (MOCS) Selection of NTTFC Secretariat Post 2 (Marketing and Administrative/Mgt skills)
- Draft TORs - REOI then publish on website/local paper - Selection and contract award
Assess the need at a later date. TORs by December
2013
To be done as and when
necessary
Component C1 – NM Road and Future Project Preparation 57. DoR Update PP to WB for No Objection August 6, 2013 PP to be updated and
sent to WB by September 19, 2014
58. DoR N-M Road and site office refurbishment - Bidding docs to WB for N.O. - Bid Invitation - Public Opening of Bids - Bid Evaluation Report and Award Recommendation to WB for N.O. - Contract signing
August 6, 2013 September 6, 2013 October 21, 2013 December 5, 2013 February 9, 2013
Re-bidding will be initiated asap with
goal of having contracts signed by
February 2015
59. DoR Procurement of 3 pickup trucks to WB for N.O. – follow PP August 6, 2013 Done
60. DoR Mugling Office Refurbishment – follow PP Part of N-M road works contract in #58
61. DoR Birgunj-Kathmandu Sustainability Study including biodiversity and road safety aspects
REOI to be issued by end-September
62. DoR Consulting services for feasibility and detail design of improvement works in Mugling – Naubise – Kathmandu road section, road safety audit for Kathmandu-Birgunj Corridor, and supervision of Narayanghat- Mugling road works
DoR agreed to complete the
shortlisting, and prepare and submit the draft RFP to the
Bank by end-September, 2014
63. DoR Design studies for 18 bridges along N-M road In process through consultants financed
by RSDP, to be completed by June
2015
64. DoR Bridge rehabilitation pilot (for one or two of 18 bridges along N-M road) to be decided based on activity 63
26
Component C2 – CFS/ICD in Kathmandu 65. NITDB/MoCS Selection of Technical Adviser Done
66. NITDB/MoCS Selection of Supervision Consultant for Bhairahawa and Birgunj Works Done
67. NITDB/MoCS Land allocation for CFS/ICD in Kathmandu TBD Overdue. Not yet finalized
68. NITDB/MoCS Selection of Design and Supervision Consultant for Kathmandu CFS/ICD To be done when land is allocated
69. NITDB/MoCS Design studies for CFS/ICD in Kathmandu (follow PP) Soon after site allocation Budget allocated for topographical survey
in fiscal year 2014/15. PD working to find the proposed
land
70. NITDB/MoCS Environmental and social safeguards studies for CFS/ICD in Kathmandu - Study completed - Public disclosure - Public consultation
August 31, 2013
To be done after land is allocated
71. NITDB/MoCS Construction of CFS/ICD in Kathmandu(follow PP) - Bidding docs to WB for N.O. - Bid Invitation - Public Opening of Bids - Bid Evaluation Report and Award Recommendation to WB for N.O. - Contract signing
To be done after land is allocated and
designs completed
Component C3 – Birgunj and Bhairahawa ICD Improvement 72. NITDB/MoCS Bhairahawa ICD Pavement Rehabilitation
- Bidding docs to WB for N.O. - Bid Invitation - Public Opening of Bids - Bid Evaluation Report and Award Recommendation to WB for N.O. - Contract signing
August 14, 2013 September 6, 2013 October 21, 2013 November 29, 2013 January 10, 2013
Contract under
execution Conduct a kick-
off/launch meeting with the contractor
and Supervision Consultant, including
a field visit to Bhairahawa with the
Bank team before end-September, 2014 Initiate works on the
27
Bhairahawa ICD pavement by end September, 2014
73. NITDB/MoCS Birgunj ICD Shed Extension - Finalize bidding docs - Bidding docs to WB for N.O. - Bid Invitation - Public Opening of Bids - Bid Evaluation Report and Award Recommendation to WB for N.O. - Contract signing
Engineering Design and Bidding documents to be submitted to Bank after the employment of Supervision Consultant
Conceptual designs completed and
detailed designs to be completed by end-
September, 2014. Works contractor to
be recruited by January, 2015
74. NITDB/MoCS Corridor Monitoring System specifications software and skills - Draft TORs/specifications - REOI (to WB for N.O. if prior review) then publish on website/local
paper - Selection and contract award (to WB for N.O. if prior review)
Three separate procurement contracts – 1) procurement of goods – NCB (September 30), 2) survey work (August 31),
3) Managed service, competitive selection
(August 31).
NOL to ToR of "Data capture Frame work
for Kolkata-Kathmandu corridor
monitoring" obtained and EoIs' evaluation
completed.
75. NITDB/MoCS/PCO Semi-annual data collection and reporting of Project Development indicators
NITDB to discuss corridor data
collection with Prof. Biswo Paudel
PCO Project Manager
to commence in September 2014
28
Annex 3: Results Framework and Monitoring
South Asia: Nepal-India Regional Trade and Transport Project
.
Project Development Objective
The proposed Project Development Objective is to decrease transport time and logistics costs for bilateral trade between Nepal and India and transit trade along
the Kathmandu-Kolkata corridor for the benefit of traders by reducing key infrastructure bottlenecks in Nepal and by supporting the adoption of modern
approaches to border management.
.
Project Development Objective Indicators
Cumulative Target Values
Data Source/ Responsibi
lity for
Indicator Name Core Unit of
Measure
Baselin
e YR1 YR2 YR3 YR4 YR5
YR6-
End Target Frequency
Methodology Data
Collection
Time associated with
meeting regulatory
requirements for
import, export and
transit activities (days)
No Days 14 14 14 12 9 8 7 Annual DoC PCO/MoC
S
Border Crossing time
at Raxaul-Birgunj
border post.
No Days 2.3 2.3 2.3 2.3 1.5
1.5 1.5 Semi-
annual
Customized
Corridor
Monitoring
System and
survey data
NITDB
Total time between
cargo offloading at
Kolkata to arrive in
Birgunj by road and
rail, and Birgunj to
Kathmandu for trucks
No Days
Road:
10
Rail: 22
Road: 10
Rail: 22
Road: 10
Rail: 22
Road:
9.0
Rail: 20
Road:
9.0
Rail: 20
Road:
8.0
Rail:
17.6
Road: 8.0
Rail: 17.6
Semi-
annual
Customized
Corridor
Monitoring
System and
survey data
NITDB
29
Intermediate Results Indicators
Cumulative Target Values
Data Source/ Responsibili
ty for
Indicator Name Core Unit of
Measure Baseline YR1 YR2 YR3 YR4 YR5
YR6 - End
Target Frequency Methodology
Data
Collection
Component 1: Modernize transport and transit arrangements between Nepal and India
Percentage of transit goods
cleared through electronic
CTD
No % 0 0 0 20
40
50 100 Semi-annual
Nepal Customs
and
Indian Customs
DoC
Component 2: Strengthen Trade-Related Institutional Capacity in Nepal
Growth in Hit Rate for
Trade Portal No % 0 0 0 Base Year 20 30 40 Semi-annual
Website
statistics
MoCS
(through
TEPC)
Agencies Integrated into
Single Window No Number 0 0 0 2 3 4 5 Semi-annual
Project
Implementation
Progress and
Supervision
reports
DoC
Labs Developed or
Improved and Operational No Number 0 0 0 1 1 1 1 Semi-annual
Project
Implementation
Progress and
Bank Site
Supervision
reports
MoCS
Component 3: Improve Trade-Related Infrastructure
Km of Road Improved Yes Km 0 0 0 33 33 33 33 Semi-annual
Supervision
Consultant and
Bank Site
Supervision
reports
DoR
ICDs/CFSs Built or
Improved No Number 0 0 1 2 2 3 3 Semi-annual
Supervision
Consultant and
Bank Site
Supervision
reports
NITDB
30
Annex 4: Recommendations from NSW-TIP Consultants (KGH Arctiquator) Recommendations from NSW-TIP Consultants (KGH Arctiquator)
Sub-committee Decision Rec# Decision Activity
TC2-3 Operational Model (Business
Model) – Recommended to
establish a government owned
special purpose vehicle to
operate the NNSW
The identification of a task team to establish the framework
and terms of reference for the government owned special
purpose vehicle.
Completed. Automation & Simplification of
Trade and Transport (Single Window) Sub-
Committee headed by the DG, Customs has
been created for the purpose. The committe
comprises of DoC, Ministry of Commerce and
Supplies, Ministry of Agriculture, Nepal Rastra
Bank, Department of Transport Management,
Trade and Export Promotion Center, Nepal
Intermodal Transport Development Committee,
FNCCI and Nepal Freight Forwarders
Association
TC3-1 UN Recommendation 33 on
Single Window implementation
models discusses three types of
SW models - which one is best
for Nepal
Options to be discussed:
1. Single Authority, one authority performs all tasks on behalf
of other departments
2. Integrated model, all SW processes are integrated and
performed inside the central NNSW
3. Interfaced Model, processing is distributed and performed
by responsible departments
4. Mixed - for some departments, the integrated model is
feasible and for others, the interfaced model is preferred
Option 4 is strongly recommended
Sub-committee proposes to implement mixed
model as per the recommendation taking into
consideration that various govt. agencies like
IRD, OCR etc. already have their own systems,
but various other agencies have different IT
capabilities.In case of DoC, E-
Customs(ASYCUDA World) will interface
with NNSW.
31
TC3-9 Implementation of Tariff
Management - Integrated and
online Tariff, including non-
tariff measures for other, non-
Customs related procedures.
Where and how should this be
implemented in relation to e-
Customs Master Plan
- Coordination with e-Customs Master Plan
-Options to be discussed:
1. Implement a master tariff within the Customs domain as
part of ASYCUDA, administered by DoC and synchronized
with online tariff for NNSW and NNTIP
2. Implement a new integrated tariff as part of the NNSW
domain, administered by DoC and synchronized with/re-used
by Customs backend and NNTIP
3. Implement a new integrated tariff as part of Customs,
synchronized with NNSW and NNTIP
Option 2 is recommended as ICT infrastructure should be
consolidated for e-Customs, NNSW and NNTIP, and to
ensure the multi-agency perspective to tariff
administration.
Option 1 is recommended by the sub-
committee. Since tariff is primary component of
customs clearance process, it is advisable that
master tariff is implemented as part of
ASYCUDA, administered by DoC and
synchronized with online tariff for NNSW and
NNTIP. This will maintain the integrity of the
master Tariff database and avoid redundancies.
TC3-11 A Ceretificate Authority (CA) is
essential for the implementation
of digital signatures. How
should this be implemented in
the perspective of NNSW
- Establishment of CA within NNSW (DoC)
- Implementation of administrative procedures and
organization to manage digital signatures
- Technical implementation
- Options to be discussed:
1. Follow-up and address Government of Nepal to prioritize
this area in the e-Government programme
2. Implement a CA in the scope of CA until a national CA is
set up
Option 2 is recommended in order to quickly support an
operational NNSW
Option 1 is recommended by the sub-committee
as implementing a CA is not practically feasible
for any other agency.
TC3-12 Electronic payments will
facilitate efficient NNSW
processes and necessary steps to
implement this in Nepal should
be taken by the banking
community.
1. Ensure the banking community sets up an e-Payment
Gateway to address and facilitate electronic payments
2. Facilitate Internet banking payments
Option 1 is recommended
As recommended in option 1, ensure the
banking community sets up an e-Payment
Gateway to address and facilitate electronic
payments.
32
TC3-14 Deployment of NNSW, NNTIP
and other services on shared or
separate ICT infrastructure
Options to be discussed:
1. Deploy, operate and maintain NNSW and NNTIP ICT-
services on separate ICT-infrastructure
2. Use share ICT-infrastructure for NNSW, NNTIP and related
services in a national datacentre
Option 2 is recommended
Use share ICT-infrastructure for NNSW,
NNTIP and related services in a national
datacentre as recommened. In the case of e-
Customs, since it is being implemented in an
interfaced model, it will be in a separate
infrastructure
Streamlining of SAD processing
at the Customs Check Posts
Internal Customs business process reengineering Internal Customs business process
reengineering will be carried out during
ASYCUDA World Implementation
Centralized and harmonized
Customs Tariff Code system for
the implementation of NNSW
Initiate work item in NTTFP Committee to harmonize and
centralise distribute the Tariff Code system for customs
clearance and permit/license processing activities
Initiate work item in NTTFP Committee to
harmonize and centralise distribute the Tariff
Code system for customs clearance and
permit/license processing activities
Data harmonization for NNSW Initiate work item in NTTFP Committee to identify
documents/information to be process by NNSW and from DH
working group for on-going maintenance of NNSW Data Set
Initiate work item in NTTFP Committee to
identify documents/information to be process by
NNSW and from DH working group for on-
going maintenance of NNSW Data Set
TC4A–
GT-3
Non-Tariff measures resolution
– will non-tariff measures be
mapped to Goods Nomenclature
codes?
Mapping of non-tariff measures to HS codes is essential for
the operation of NNSW
Mapping of non-tariff measures to HS codes is
essential for the operation of NNSW
TC5-1 Agree on one single overall
NNSWTP Implementation Plan
This decision trigger all other activities Request for the agreed Implementation Plan
from NTTFC/MOCS
TC5-2 Implement a Communication
Strategy and Plan
Communication with stakeholders, NNSWTP implementation
will commence
- Regular consultations (Focal Point meeting)
should be carried on
- Regular meeting of Automation and
Simplification of Trade and Transport (Single
Window) Sub-committee
- Recommend to develop the terms of reference
for communication strategic plan as soon as
possible by the sub-committee
33
TC5-3 Appoint a Communication Focal
Point
Cooperation with stakeholders for the management, planning,
delivery of communication content and messages, orientation
package, tailored communication packages
- Project Management Office (to be formed)
from DoC will be the Communication Focal
Point.
- Focal points are being collected from the
Stakeholders
TC5-17 Implement a 24 months
NNSWTP Capacity Building
programme to run in parallel
with the technical
implementation
Structured capacity building can commence addressing human
capacities, routines, processes and organisation.
To be carried out according to the
recommendation during implementation. QA
advisory firm to recommend the Capacity
Building Programme
TC5-18 Develop and conduct a one day
information programme to all
staff in involved agencies on the
Nepal National Single Window
and National Trade Portal based
on the orientation Package
presented in this report
One day NNSWTP information activities addressing all
stakeholders.
To be carried out according to the
recommendation. Planned for 2nd trimester
TC5-19 Tender and recruit an
international training
expert/company to support the
development of train-the-trainers
(T-T-T) programme to build a
sustainable pool of trainers,
together with the pool of trainers
develop basic training
curricula’s for trade facilitation
and prioritized technical areas,
and to deliver a first round of
training on these areas for key
people
International expert recruited. Basic initial training delivered.
Train the Trainer concept introduced
To be carried out as per the Capacity Building
Plan to be developed by the QA firm
34
TC5-20 Tender and recruit an
international expert for support
in developing standard
operational procedures, routines
and guidelines for NTP and
NSW (use the supervision
facility provided by the World
Bank by requesting competence
and capacity for this work in the
ToR for supervision)
International expert recruited. Routines, guidelines and SOPs
identified and developed together with stakeholders.
- To be carried out according to the
recommendation after the QA Supervision Firm
is recruited
- QA Supervision Firm recruitment is in process
TC5-21 Develop an official
communication package for the
NNSWTP. The package should
be developed in both English
and Nepalese anguages and
should include e.g.; official
folder, presentation material,
common website information,
statements and quotes from
highest possible level within
Government showing support
for the introduction of the
NNSWTP
Official Communication package in English and Nepalese
incl. website, brochures, etc.
To be carried out in regular basis. Other major
work and recommendations to be made by the
QA supervision firm
TC5-22 Develop a specific information
programme for the private sector
starting with a NNSWTP
Awareness raising information
seminar. The seminar should
address the important issues for
the Private Sector in relation to
trade facilitation and
implementation of the
NNSWTP. Proposed agenda
items are included in the report.
The seminars should be
conducted in Nepali and English
during evenings, so also SMEs
can attend
To be carried out according to the
recommendation. Planned for 3rd trimester
35
Roles and Responsibilities of Participating Agencies for NNSW
SN Stakeholder Roles
1 Department of Customs • Registration of Customs Agent
• Export/Import (E/I) clearance
• Receives permit/license/recommendation from other agencies to release goods.
2 Ministry of Commerce and Supplies
Department of Commerce and
Supply Management (DOCSM)
• Register Business firm.
• Issue Recommendation/Approve letter to commercial bank to change(customs posts, Quantity etc.)
in LC
• Issue Recommendation to approve exceed limit of amount for transaction
• Issue Recommendation to Calcutta for releasing every consignment in import
• Issue Recommendation to Customs office to release prohibited/Partially prohibited goods
• Receives Recommendation from other government agencies for further recommendation to
customs
Nepal Transit and Warehousing
Company Ltd
• Receive information from customs office and endorsed delivery order only in TIA
3 Ministry of Agricultural Development
Department of Food Technology and
Quality Control
• Issue Import permit for Food products
• Release certificate during import clearance
• Quarantine quality Certificate for export
• Receives quarantine request letter from customs during import
• Receives quarantine request application form for goods import/export permit from
exporter/Importer
Department of Plant Resources • Export permit
• Import Permit
• Recommendation letter for export
• Receives quarantine request application form for goods import/export permit from
exporter/Importer.
Central Plant Quarantine Office • Issue Import permit
• Issue phytosanitary certificate for export
• Receive application from Exporter/Importers
36
Plant Quarantine Check post • Release certificate during import
• Receives quarantine request letter from customs during import
Central Animal Quarantine Office • Issue certificate for export/Import
• Issue animal health certificate and phytosanitary certificate
• Receives quarantine request application form for goods import/export permit from
exporter/Importer
Animal Quarantine Check Posts • Issue Quarantine release certificate
• Receives quarantine request letter from customs during import
4 Nepal Rastra Bank • Endorsed BN no.1 (export) and BN no.4 (import) is received from customs posts
• Endorsed BN no.3 is received from Commercial bank
5 Department of Transport
Management
• Issue recommendation letter for Vehicles
6 Trade and Export Promotion Center • Issue GSP Form A
• Recommendation to export/import goods for exhibition
7 Federation of Nepalese Chambers of
Commerce and Industry
• Specific District level Chambers Issue Certificate of Origin (CO).
• FNCCI and DOIND committee approve goods for issuing CO
• Receives requests as application form from exporter to approve goods for CO
8 Nepal Freight Forwarder's
Association
• Prepare License, Permit, Certificate of Origin (LPCO) for Export
37
Annex 5: NIRTTP Updated Social Safeguards Status for N-M Road Project, August, 2014 S.N. Activities Taken Actions
Status Date Target Date Remarks
1 Budget allocation Completed April 2014
2. Preparation of social safeguard documents (IEE, RAP, SAP, &VCDP) Completed and Updated RAP
June 2014
3 Appointing Social Mobilizers (SM)/ SDRS of Consultant Completed Completed
4 Orientation to Project Staff and VDC Completed May 2014
5 Distribution of RAP and VCDP in Local Language in all concerned VDCs and PAF
Distributed to VDCs &PAF
August 2014
6 Conduct Consultation meeting with Project Affected Persons (PAPs) On going July 2014
7 Verification of PAFs Completed June 2014
8 Preparation Status report of PAF Completed August 2014
9 Formation of local consultative Forums in all 4 VDCs Completed 12 May, 2014
10 Formation of Grievance Redress Committee (GRC) Completed 14 May,2014
11 Orientation of LCF members Ongoing May, 2014
12 Ministry/Department officially authorizes to the PM for Initiate preliminary action for acquisition of houses, business establishment and other structures
Completed April 2014
13 Formation of Compensation Determination Committee Completed April 2014
14 Meeting of the CDC Completed April 2014
15 Finalization of Compensation Value Completed
16 PIC to Deposit money with CDO NA Distribution by PIC office
17 Issue Notice of Compensation Completed 27 June, 2014
18 Assistant to PAFs in preparing Papers for Compensation Claim Completed 27 June, 2014
19 Disbursement of First installment to PAFs Completed for 45 structures
11 July, 2014 Disbursement of First installment to PAF for 1 structure is remaining
20 Update the status (Data base) of Resettlement of PAF & vulnerable group
Completed August 2014
21 PAFs starts dismantling the structures X X October, 2014
22 Disbursement of Second installment of Compensation X X November, 2014
23 Conducts Training Need Assessment (TNA) X X September, 2014
24 Finalizes of Training X X September, 2014
25 Project identifies master trainers/ Training organization X X October, 2014
26 Implementation of livelihood training formation of women SHGs X X October, 2014
27 Disbursement of R&R and business displacement allowances X X December, 2014
28 Evaluation of Implementation of Livelihood training X X December, 2014
38
29 Monitoring on social safeguard compliance by GESU team and Supervision Consultants
Continuous May, 2014
30 Evaluation of Resettlement Action Plan (RAP) (Midterm will be in December 2014 and end term will be after an year)
X X December, 2014
Note: CDO = Chief District Officer, CDC = Compensation Determination Committee, CFC = Compensation Fixation Committee MoPIT = Ministry of Physical Infrastructure and Transport, MoH = Ministry of Home, MoF = Ministry of Finance, PM = Project Manager, SC = Supervision, Consultant, SDRS= Social Development & Resettlement Specialist, LCF = Local Consultative Forum, SM= Social Mobilizer, GRC = Grievance Redress Committee, IND.C = Individual Consultant, SHG= Self Helping Group
39
Annex 6 - Environmental Safeguards Action Plan
1. MoCS PCO Staffing. The PCO is committed to hire an Environmental Specialist to oversee the application of the ESMF to
the ICDs and trade-related laboratory subprojects; however, the mission agreed that full-time support is not yet needed, given that at
present only the Bhairahawa ICD is under construction (and the supervision consultant includes an environmental specialist to conduct
on-site monitoring and supervision of EMP compliance), while the Birgunj ICD is still in design stage and the Kathmandu ICD and
the two planned laboratories are yet to get underway. Therefore, in the immediate term, the PCO’s Technical Advisor will manage the
review of supervision monitoring reports for Bhairahawa ICD and resolving any non-compliance issues. Nonetheless, to ensure
appropriate capacity is on board to ensure full ESMF compliance as activities requiring environmental review unfold for the various
ICD and laboratory subprojects, the mission requested that the PCO initiate the process to hire an intermittent environmental specialist
(retainer basis) in the short term. This individual could then be scaled up to full-time as and when the workload demands it.
Upcoming PCO tasks related to ESMF compliance include reviewing Bigunj ICD designs to ensure that recommendations from the
environmental screening and assessment and requirements of the EMP and ESMF are incorporated; reviewing all bidding documents
to ensure appropriate inclusion of all EMP and ESMF items; periodic on-site monitoring at construction sites; and review and follow-
up on environmental findings in supervision consultant monitoring reports.
Action: PCO to draft TORs for intermittent (retainer basis) environmental specialist by October 30, 2014 and share with the
World Bank for comments and No Objection
2. N-M road Pre-construction EMP activities. DoR updated the mission on progress related to key pre-construction EMP
activities for N-M road, including tree cutting and shifting of utilities and public infrastructure. The mission also reviewed and
verified the cost provisions for all Environmental Management Plan (EMP) requirements, either in the contractor BOQ line-items,
BOQ provisional sums, or through the DoR’s budget allocation for the N-M road. Specific issues are described below:
The project has submitted all necessary documentation to the Department of Forest (DoF) for forest clearances. The Project-In-
Charge is regularly liaising with DoF to ensure smooth and efficient processing of the clearance request, and has verbal assurances
of the clearance by November. Actual tree-cutting will be done by the contractor during the pre-construction period. However, in
the meantime, DoR needs to develop the afforestation program (which, as per the EIA, should also support wildlife and
biodiversity enhancement objectives). It was agreed that DoR will review the EMP requirements, discuss internally and agree to
an approach with DoF and other potential partners / stakeholders as applicable so that the plan is fully developed in advance of
construction.
For electric poles, the Electricity Authority Office has indicated the need for a joint site verification with DoR to determine
specifically where the 303 affected poles will be relocated to. This process is expected to be completed by end of September. The
actual moving of poles will either be carried out by the contractor or by NEA (with charge-back).
40
Other affected public and community infrastructure such as water supply and irrigation lines, hand pumps, walls, etc. will be
shifted and rehabilitated by the contractor during the pre-construction period. Nonetheless, DoR must first carry out consultations
with relevant stakeholders and user groups regarding coordinating cuts in services during the shifting, as well as to make any
needed final adjustments to the new alignments / locations for affected infrastructure. The mission emphasized the need to
document all consultation events and to share such documentation with the Bank.
To ensure that all relevant pre-construction EMP activities are on track, DoR will carefully review the EMP and compile a work
plan for pre-construction phase including specific tasks and schedule.
Actions:
DoR to immediately share with the Bank the records from consultations with water user groups and water supply division on
shifting of water supply lines.
DoR to ensure ongoing documentation of all consultation events related to utility shifting and any other pre-construction
activities.
DoR to internally discuss and agree to approach for afforestation program, and define detailed program and budget with input
from DoF, other potential partners and stakeholders, by April 2015 (in advance of tree felling).
DoR to develop a work plan for all pre-construction EMP activities and share with the Bank by October 15, 2014.
3. Environmental staffing at DoR. Staffing issues for environmental management aspects of N-M road were reviewed during
the mission. Currently, the Environmental Safeguards Expert consultant to DoR’s Geo-Environment and Social Unit (GESU) hired
under the World Bank Road Sector Development Project (RSDP) is providing intermittent support to NIRTTP for N-M road pre-
construction activities in addition to her work on RSDP. Furthermore, DoR’s Project in Charge for NM road is personally managing
all government liaison tasks related to forest clearances and utility / public infrastructure shifting. DoR explained that the Expert will
continue to support both projects until RSDP project closes (expected in June 2015). At that point, DoR is committed to re-issue the
Expert consultant contract as full-time under NIRTTP.
4. The mission expressed concern that environmental staffing may be stretched thin, especially once contractors begin to
mobilize for NM road construction, as the workload under RSDP is heavy and will continue as such until that project closes and
pending works (like bioengineering, reinstatement of disposal and quarry areas, etc.) are finished. In addition, additional
environmental specialist time will be required of DoR to interface with the consultants and review draft deliverables for the feasibility,
design and detailed ESIA studies for Kathmandu-Naubise-Mugling road, as well as the Strategic ESA / Sustainability Study, and
review/input into contract documents. GESU has commendably received recent approval to hire two additional permanent staff (one
social and one environmental), but these positions will likely take many months to fill in light of GoN administrative requirements and
lengthy procedures; these permanent staff will furthermore be responsible for supporting projects across the sector and will not likely
41
be available to substantively support NIRTTP on safeguards matters. The mission therefore cautiously agreed to DoR’s environmental
staffing arrangement for NM road, but recommended that the arrangement be reviewed prior to contractor mobilization. If needed, the
project should bring on an additional environmental consultant on an intermittent basis to backstop the Environmental Safeguards
Expert, in particular during the overlap months before RSDP-related tasks come to a close and while contractors are mobilizing and
initiating construction activities along NM road.
Actions:
DoR to review staffing adequacy on environmental management prior to contractor mobilization on NM road, and to hire
additional consultant on intermittent basis to backstop Environmental Safeguards Expert if required.
DoR to re-issue contract for Environmental Safeguards Expert under NIRTTP project funds by July 1, 2015, when the
existing contract through RSDP expires.
5. Strategic ESA / Sustainability Study. For the Birgunj-Kathmandu Corridor Strategic Environmental and Social Assessment /
Sustainability Study, a field visit and consultations with key stakeholders was carried out by a joint World Bank - DoR team including
environmental and social specialists in May 2014 to scope the study (a trip report is presented in Annex X). As agreed during that
visit, the World Bank developed initial draft ToRs for the study, which were shared and discussed with DoR during the mission. As a
next step, DoR will provide comments on the draft ToR to the World Bank by September 30, 2014. Following Bank review and
further discussions if required, DoR will share the ToR with other concerned government agencies (in particular, DoF and Ministry of
Environment) for any further observations or comments, before submitting them formally for No Objection to the Bank and initiation
of the procurement process.
Action: DoR to provide comments on draft ToR for Strategic ESA / Sustainability Study by September 30, 2014.
6. Capacity strengthening on biodiversity management in roads sector. The mission discussed DoR’s previous request for
support to develop capacity on biodiversity management for the roads sector. It was agreed that the ToR for the Strategic ESA /
Sustainability Study should include activities to begin to address DoR’s identified needs – for example, to include developing
guidance resources and manuals for good practice biodiversity management in road design and construction. DoR will propose
specific such activities in the ToR.
Action: DoR to propose specific measures or activities to advance capacity on biodiversity management in the roads sector in
their revisions to the Strategic ESA / Sustainability Study ToR.
42
Annex 7 – Sub-Project Monitoring Template
Draft format for Activities, Tasks, Timelines, Deliverables, Partners, Resources, etc.
Component A:
Sub Component 1.1:
Objective:
Responsible Staff:
Activity TASKS Jan-14
Feb-14
Mar-14
Apr-14
May-14
Jun-14
Jul-14
Aug-14
Sep-14
Oct-14
Nov-14
Dec-14
Milestones/ deliverables
Completed in Project Year 1 or 2 or 3 or 4
Partners & Stakeholders
Complementary/ leveraged activities
Resources/working modalities