• How are ecological systems affected by changes in land use and climate across a range of spatiotemporal scales?
• How do changes in the availability and distribution of the Nation’s water affect ecological systems?
• How do the patterns and movement of genes and organisms across the continent affect biodiversity and the spread of infectious diseases and invasive species?
A continental research platform to provide the capacity to forecast future states of ecological systems for the advancement of science and the benefit of society
www.neoninc.org
NEON Robotic Deployment: Imaging as a Biological Sensor
17 May 2005 20 May 2005 26 May 2005 13 June 2005
Lowerslope
Upperslope
Plant Growth Dynamics – Rhododendron (NIMS project)
Sensor
SensorSensor
Sensor
MicroserverSensor Node
Package
MicroserverSensor Node
Package
NIMSNodeNIMS
NodeCable
StaticSensor Node
Cable
Nat
iona
l Eco
logi
cal O
bse
rvat
ory
Net
wor
k (N
EO
N)
Nat
iona
l Eco
logi
cal O
bse
rvat
ory
Net
wor
k (N
EO
N)
NEON Infrastructure Platforms
FIU Sentinel Remote Sensing
Context, scaling, explanatory variables
NEON CyberinfrastructureN
atio
nal E
colo
gica
l Ob
serv
ator
y N
etw
ork
(NE
ON
)
Sensor
SensorSensor
Sensor
MicroserverSensor Node
Package
MicroserverSensor Node
Package
NIMSNodeNIMS
NodeCable
StaticSensor Node
Cable
Geographically distributed infrastructure connected via cyberinfrastructure into national observatory network
Emerging technologies (sensor, analytical, communication, and information) to investigate the structure, dynamics, and evolution of systems at a continental scale and forecast change.
New collaborative environments (simulation, computation, visualization, and knowledge systems) are needed to facilitate the integration of research, education, and dialog across a wide range of biological, geophysical, and social sciences.
Legacy data repositories and facilities for analysis and synthesis
Transformative in understanding complexity of natural and human environments
Nat
iona
l Eco
logi
cal O
bse
rvat
ory
Net
wor
k (N
EO
N)
WHY NOW?
Why multi-scale distributed sensor-networking will transform ecology
Very Large Array
Computing
Internet
Supercomputers Field ecologyRadioastronomy
Single Telescopes
… because it has done so over and over again
NEON
Individual observations
Nat
iona
l Eco
logi
cal O
bse
rvat
ory
Net
wor
k (N
EO
N)
Conceptual Design StageConceptual Design Stage Preliminary Design/ Readiness Stage
Board Approved Stage Construction
Concept development – Expend approximately 1/3 of total pre-construction planning budget
Develop construction budget based on conceptual design
Estimate ops $
Prelim design over ~1-2 years. Expend approx 1/3 of total pre-construction planning budget
Construction estimate based on prelim design
Update ops $ estimate
Final design over ~1 year. Approx 1/3 of total pre-construction planning budget
Construction ready budget & contingency estimates
Preliminary Design
Develop site-specific preliminary design, environmental impacts
Develop enabling technology
Bottoms-up cost and contingency estimates
Develop preliminary operations cost estimate
Final Design
Development of final construction-ready design and mgmnt plan
Industrialize key technologies
Refine bottoms-up cost and contingency estimates
Formulate/Review Risk Assessment and Mitigation, and Management Plan
Complete recruitment of key staff
Conceptual design
Formulation of science questions
Requirements definition, prioritization, and review
Development of conceptual design
Top down parametric cost and contingency estimates
Initial proposal submission to NSF
Construction per baseline
Pro
ject
evo
luti
on
Bu
dg
et e
volu
tio
nO
vers
igh
t e
volu
tio
n Merit review, apply 1st and 2nd NAS ranking criteria
Forward estimates of Preliminary Design costs and schedules
Establishment of interim review schedules and competition milestones
Forecast international and interagency participation and constraints
Conceptual design review
NSF Director approves Internal Management Plan
Formulate/approve Project Development Plan & budget; include in NSF Facilities Plan
Preliminary design review and integrated baseline review
Evaluate ops $ projections
Evaluate forward design costs and schedules
Forecast interagency/international decision milestones
NSF approves submission to NSB
Apply NAS 3rd ranking criterion
NSB ranking
OMB/Congress budget negotiations based on Prelim design budget
Annual reassessment of baseline and projected ops budget for projects not started construction
Finalization of interagency and international requirements
Final design review, approve baseline
Congress appropriates MREFC funds & NSB approves obligation
Periodic external review during construction
Review of project reporting
Site visit and assessment
MREFC $
Expenditure of budget and contingency per baseline
Refine ops budget
NS
F a
pp
rova
l
NS
B a
pp
rova
l
OM
B/C
on
gre
ss a
pp
rova
l
Funded by R&RA or EHR $
NSF oversight defined in Internal Management Plan, updated by development phase
Proponents development strategy defined in Project Development Plan Described by Project Execution Plan
Conceptual Design StageConceptual Design Stage Preliminary Design/ Readiness Stage
Board Approved Stage Construction
Concept development – Expend approximately 1/3 of total pre-construction planning budget
Develop construction budget based on conceptual design
Estimate ops $
Prelim design over ~1-2 years. Expend approx 1/3 of total pre-construction planning budget
Construction estimate based on prelim design
Update ops $ estimate
Final design over ~1 year. Approx 1/3 of total pre-construction planning budget
Construction ready budget & contingency estimates
Preliminary Design
Develop site-specific preliminary design, environmental impacts
Develop enabling technology
Bottoms-up cost and contingency estimates
Develop preliminary operations cost estimate
Final Design
Development of final construction-ready design and mgmnt plan
Industrialize key technologies
Refine bottoms-up cost and contingency estimates
Formulate/Review Risk Assessment and Mitigation, and Management Plan
Complete recruitment of key staff
Conceptual design
Formulation of science questions
Requirements definition, prioritization, and review
Development of conceptual design
Top down parametric cost and contingency estimates
Initial proposal submission to NSF
Construction per baseline
Pro
ject
evo
luti
on
Bu
dg
et e
volu
tio
nO
vers
igh
t e
volu
tio
n Merit review, apply 1st and 2nd NAS ranking criteria
Forward estimates of Preliminary Design costs and schedules
Establishment of interim review schedules and competition milestones
Forecast international and interagency participation and constraints
Conceptual design review
NSF Director approves Internal Management Plan
Formulate/approve Project Development Plan & budget; include in NSF Facilities Plan
Preliminary design review and integrated baseline review
Evaluate ops $ projections
Evaluate forward design costs and schedules
Forecast interagency/international decision milestones
NSF approves submission to NSB
Apply NAS 3rd ranking criterion
NSB ranking
OMB/Congress budget negotiations based on Prelim design budget
Annual reassessment of baseline and projected ops budget for projects not started construction
Finalization of interagency and international requirements
Final design review, approve baseline
Congress appropriates MREFC funds & NSB approves obligation
Periodic external review during construction
Review of project reporting
Site visit and assessment
MREFC $
Expenditure of budget and contingency per baseline
Refine ops budget
NS
F a
pp
rova
l
NS
B a
pp
rova
l
OM
B/C
on
gre
ss a
pp
rova
l
Funded by R&RA or EHR $
NSF oversight defined in Internal Management Plan, updated by development phase
Proponents development strategy defined in Project Development Plan Described by Project Execution Plan
Nat
iona
l Eco
logi
cal O
bse
rvat
ory
Net
wor
k (N
EO
N)
Growing A Budget – PlanningDesign Costs – 10% of MREFC request
Community development, NRC Studies, R&D, Project Management, Engineering
Nat
iona
l Eco
logi
cal O
bse
rvat
ory
Net
wor
k (N
EO
N)
Growing A Budget
ResearchR&D to nurture the communityR&D to develop projectProject specificR&D changes to existing programsCollaborative (Cross directorate,
cross agency)
Maintenance and Operations10 to 35% of MREFC request30 year commitment