nbec 2014 - high performance retrofits

32
Evaluating the Energy Savings of High Performance Building Enclosure Retrofits GRAHAM FINCH, MASC, P.ENG, PRINCIPAL, RDH BUILDING ENGINEERING LTD. VANCOUVER, BC COAUTHOR: BRITTANY HANAM

Upload: rdh

Post on 15-Jul-2015

778 views

Category:

Engineering


1 download

TRANSCRIPT

Page 1: NBEC 2014 - High Performance Retrofits

Evaluating the Energy Savings of High Performance Building Enclosure Retrofits

GRAHAM FINCH, MASC, P.ENG, PRINCIPAL,

RDH BUILDING ENGINEERING LTD. VANCOUVER, BC

COAUTHOR: BRITTANY HANAM

Page 2: NBEC 2014 - High Performance Retrofits

Outline

à Background – Energy

Use in Multi-Unit

Residential Buildings

à Deep Energy Retrofit

Case Study

à Measurement &

Verification of Energy

Savings

à Other Monitoring

Results

Page 3: NBEC 2014 - High Performance Retrofits

NBEC 2011: MURB Energy Study

à  Study looked at energy consumption of

over 60 MURBs in Pacific Northwest

à  Constructed from 1974 -2002

à  5 to 35 storeys in height

à  Half of study buildings underwent a full

building enclosure rehabilitation

à  Assessed actual performance

characteristics in each building

à  Decade of energy consumption

à  Effective R-values

(design vs. in-situ)

à  Airtightness of enclosure & interiors

à  Impact of building enclosure repairs

and upgrades

Page 4: NBEC 2014 - High Performance Retrofits

Energy Use Intensity of Mid- To High-Rise MURBs

Average 39 Buildings = 213 kWh/m2/yr (68 kBtu/sf/yr)

Page 5: NBEC 2014 - High Performance Retrofits

Typical Mid- to High-Rise MURB Energy Consumption

Units of kWh/m2/yr, % of total

Page 6: NBEC 2014 - High Performance Retrofits

Energy Savings from Building Enclosure Rehabilitations

à  Enclosure rehabilitations performed at

study MURBs primarily to address moisture

damage

à  Little incentive for owners to perform energy

upgrades due to increased cost – a huge

missed opportunity

à  Full re-cladding, over-insulation and new

windows at each building

à  Thermal improvements from: exterior

insulation assemblies, improved detailing

(i.e. cladding attachments), better windows

(thermally broken, low-e, argon etc.)

à  Improved air-tightness characteristics during

rehabilitation

Page 7: NBEC 2014 - High Performance Retrofits

Typical Rehabilitation – Typical Detailing

Pre-Rehabilitation

Post-Rehabilitation

Page 8: NBEC 2014 - High Performance Retrofits

Measured Savings from Building Enclosure Rehabilitations

Average 14% Space-Heat Energy Savings & 8% Total Building Energy Savings

Make-up air unit not running prior to rehab (savings negated)

Page 9: NBEC 2014 - High Performance Retrofits

Energy Retrofit Potential for Existing MURBs

à  Study identified several key components to be improved during enclosure rehabilitation work or as part of specific energy retrofits

à  Study found potential for building enclosure retrofits (windows, wall insulation, air-sealing) to reduce space-heat use by up to 90%!

à  Further savings from ventilation upgrades (heat recovery, in-suite systems) & other building system improvements (fireplaces, DHW, lighting etc.)

Page 10: NBEC 2014 - High Performance Retrofits

à  13 storey, 37 suite, multi-unit

residential building

à  Constructed in mid 1980s

à  Building renewals pursued at

decision of owners to upgrade

original building enclosure

à  Aesthetics

à  Poor thermal performance/

comfort

à  Concrete/PT cable repairs

needed

Case Study Renewal Project: Background

Page 11: NBEC 2014 - High Performance Retrofits

Existing Building Enclosure Assessment

à  Representative of typical

1970s to 80s vintage mid- to

high-rise MURBs

à  Exposed concrete walls (R-4),

non-thermally broken

aluminum frame double

glazed windows (R-1.8)

à  High window to wall ratio,

55% - similar to many

modern buildings

à  Overall Effective Enclosure

R-value = 2.8 IP Fig. 1.1 Original detail drawing of a window head and sill, coloured.

Page 12: NBEC 2014 - High Performance Retrofits

Existing Mechanical System Assessment

à  Original mechanical systems

largely in place

à  Electric baseboard heating

à  Gas-heated make-up air for

ventilation, <80% efficient

(to corridors)

à  14 decorative gas fireplaces at

upper floor suites – few

replaced by owners

à  Hot-water boiler & tanks

replaced few times before

Page 13: NBEC 2014 - High Performance Retrofits

Metered Energy Data

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

Jul  200

6Sep  20

06Nov  200

6Jan  20

07Mar  200

7May  200

7Jul  200

7Sep  20

07Nov  200

7Jan  20

08Mar  200

8May  2008

Jul  200

8Sep  20

08Nov  200

8Jan  20

09Mar  200

9May  200

9Jul  200

9Sep  20

09Nov  200

9Jan  20

10Mar  201

0May  201

0Jul  201

0Sep  20

10Nov  201

0Jan  20

11Mar  201

1May  201

1Jul  201

1

Mon

thly  Ene

rgy  Co

nsum

ptoin,  ekW

h

Suite  Electricity,  kWh

Common  Electricity  (Strata),  kWh

Gas,  ekWh

Page 14: NBEC 2014 - High Performance Retrofits

Typical Year Energy Consumption

à  Calendarize and weather normalize

 -­‐

 10,000

 20,000

 30,000

 40,000

 50,000

 60,000

 70,000

 80,000

Mon

thly  Ene

rgy  Co

nsum

ption,  ekW

h Suite  Electricity,  kWh Common  Electricity,  kWh Gas,  ekWh

Gas46%

Suite  Electricity36%

Common  Electricity  (Strata)18%

Annual Breakdown

Page 15: NBEC 2014 - High Performance Retrofits

Energy Modeling to Evaluate Energy Efficiency Measures

à  Reviewed measured utility data (gas and electricity) for past 5 years

à  Calibrated whole building energy model developed to evaluate potential

Energy Efficiency Measures (EEMs)

Electric  Baseboard  Heating22%

Fireplaces9%

Ventilation  Heating25%

Hot  Water11%

Lights  -­‐ Common2%

Lights  -­‐ Suite7%

Plug  and  Appliances  (Suites)8%

Equipment  and  Ammenity  (Common)

16%

Total Energy

Consumption =

225 kWh/m2/yr

Average in MURB Study

was 213 kWh/m2/yr

Energy costs $65,500/yr

total ($1770/suite)

Page 16: NBEC 2014 - High Performance Retrofits

à  Plan to renew building

aesthetic to more modern

appearance à  Metal panels with color

features

à  Stucco features

à  New windows

à  New skylights at penthouse

à  New entrance door

à  Enclosed balconies

à  New roof and decks

à  Adds value

Building Enclosure Renewal Design

Page 17: NBEC 2014 - High Performance Retrofits

à  Exterior wall insulation with low

conductivity cladding attachment

& high effective R-value

à  Windows Upgrades à  Double & triple glazed low-

conductivity frames (R-4 to R-6)

à  Airtightness improvements

à  Roof insulation

à  Fireplace upgrade

à  Make-up air unit (ventilation)

à  Heat recovery ventilation

Potential Energy Efficiency Measures (EEMs)

Page 18: NBEC 2014 - High Performance Retrofits

Cost Payback Analysis – Building Enclosure & Mechanical EEMs

Energy Efficiency Measure /

Incremental Upgrade

% Total Energy Savings

(% Electrical Heat Savings)

$ Savings per year

Incremental Cost with

Utility Incentives

Simple Payback

Wall Insulation & Improv. Cladding Attachment 4% (19%) $4,800 $0 Immediate

Double Glazed Fibreglass Windows 7% (30%) $7,600 $2,700 0.4 years

Triple Glazed Fibreglass Windows R-5 10% (44%) $11,000 $60,000 6 years

Airtightness 2% (7%) $1,800 $0 Immediate

Fireplace Replacement 2% (8%) $2,100 $14,000 7 years

In-Suite HRV Installation 6% (-32%) -$4,400 $74,000 n/a

Make-up Air Unit Replacement 5% (0%) $1,600 $23,500 15 years

Enclosure EEMs (triple glazed) 20% (87%) $21,900 $60,000 2.7 years

Enclosure & Mechanical EEMs (triple glazed) 30% (62%) $19,700 $166,800 8.5 years

Page 19: NBEC 2014 - High Performance Retrofits

Predicted Annual Energy Savings

Electric  Baseboard  Heating3% Fireplaces

9%

Ventilation  Heating24%

Fans1%

Hot  Water11%Lights  -­‐ Common

1%Lights  -­‐ Suite

7%

Plug  and  Appliances  (Suites)8%

Equipment  and  Ammenity  (Common)

15%

Enclosure  Savings21%

Modeled Post-Retrofit: 177 kWh/m2

à  Pre-retrofit = 225 kWh/m2/yr

à  Building enclosure EEMs (insulation, windows, airtightness) à  20% savings overall

à  87% electric baseboard

heating savings

Page 20: NBEC 2014 - High Performance Retrofits

Building Enclosure Renewals

à  $3.6M renewals project,

7-month construction period

à  Work primarily from exterior

with access to suites for

window installations

Page 21: NBEC 2014 - High Performance Retrofits

Building Enclosure Renewals Performed

à  Over clad and exterior insulate walls

with mineral wool & fiberglass clip

cladding attachment (R-16 effective)

à  New triple glazed fiberglass windows

(R-5 effective)

à  New roof and decks

à  Improved air-tightness

à  Measured Pre-Post reduction of

0.71 to 0.32 cfm/ft2 @75Pa

(55% Improvement)

à  Overall new enclosure R-value

R-9.1 vs R-2.8 original

Existing

Upgraded

Page 22: NBEC 2014 - High Performance Retrofits

Exterior Insulation, Stucco, & Metal Panel Overcladding

Page 23: NBEC 2014 - High Performance Retrofits

New High Performance Triple Glazed Windows

Page 24: NBEC 2014 - High Performance Retrofits

Completed Building Enclosure Renewals

Page 25: NBEC 2014 - High Performance Retrofits

Measured Energy Savings & Other Research

à  Measurement & Verification Plan (IPMVP)

à  Energy savings metering primarily through utility

meters (smart meters & sub-meters)

à  Supplemental sensors installed to measure

indoor conditions (T/RH/CO2), airflows,

pressures, occupant comfort, fireplace use

à  Air-tightness testing (Pre-Post Renewals)

à  Tracer Gas Testing (Post Renewals

à  See Other NBEC Paper (Lorne Ricketts)

Page 26: NBEC 2014 - High Performance Retrofits

Metered Savings: Suite Electricity

à  Total Electricity Reduction of 33%

à  63% Reduction in Electric Baseboard Heating

-

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Ele

ctri

city

Con

sum

pti

on

, kW

h Calibrated Model Pre-Retrofit Calibrated Model Post-Retrofit

Page 27: NBEC 2014 - High Performance Retrofits

Metered Savings: Natural Gas

à  2% Reduction in Gas (Fireplaces)

-

10,000

20,000

30,000

40,000

50,000

60,000

70,000

Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

Gas

Con

sum

pti

on

, ekW

h

Calibrated Model Pre-Retrofit Calibrated Model Post-Retrofit

Page 28: NBEC 2014 - High Performance Retrofits

Metered & Modeled Energy Savings: Year 1

à  Overall Energy Use Intensity (EUI) reduced from

226 to 183 kWh/m2/yr

à  Overall 19% Reduction in Energy Consumption

à  Predicted ~20% prior to retrofit

à  Energy models can be accurate predictors of actual energy

use, but only with good calibration

à  Pilot Study demonstrates building enclosure renewals can

predictable & successful in reducing energy consumption

à  Further savings possible (many windows left open year

round)

Page 29: NBEC 2014 - High Performance Retrofits

à  Plan to upgrade mechanical

ventilation system (old

central pressurized

corridor)

à  Most effective retrofit is to

install continuous

ventilation to each suite &

utilize insuite HRV/ERVs

à  Compartmentalization of

suites and corridors

à  Measure ongoing energy

savings

Next Steps

Page 30: NBEC 2014 - High Performance Retrofits

Summary

à  Significant opportunities exist to reduce energy consumption of MURBs

à  Pilot project demonstrates the potential for cost effective incremental EEMs at time of retrofit work & new construction

à  Total building energy savings of ~20% for building enclosure improvements predicted and demonstrated

à  Ventilation assessment at time of building enclosure renewals

à  Replicating the success of this project is a huge opportunity for the entire retrofit industry

Page 31: NBEC 2014 - High Performance Retrofits

Acknowledgements

à  RDH – Brittany Hanam, Lorne Ricketts, Robin Urquhart, James Higgins

à  Homeowner Protection Office, Branch of BC Housing

à  BC Hydro

à  FortisBC

à  National Resources Canada

à  Enbridge Gas

à  City of Vancouver

à  City of North Vancouver

à  City of Surrey

à  City of New Westminster

à  City of Richmond

Page 32: NBEC 2014 - High Performance Retrofits

Questions

Graham Finch [email protected] - 604.873.1181