muskoka business and master plan final draft report-10may

233
BUSINESS PLAN AND MASTER PLAN MUSKOKA AIRPORT FINAL REPORT - 10 MAY 2013 Submitted to: The District of Muskoka 70 Pine Street, Bracebridge, Ontario, P1L 1N3 PED-9-2013-4B

Upload: others

Post on 08-May-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Muskoka Business and Master Plan Final Draft Report-10May

BUSINESS PLAN AND MASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT - 10 MAY 2013

Submitted to:

The District of Muskoka70 Pine Street, Bracebridge, Ontario, P1L 1N3

PED-9-2013-4B

Page 2: Muskoka Business and Master Plan Final Draft Report-10May

  

 

 

TOC Page 1  

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Company co

nfid

ential. A

ll rights reserved

.        

FINAL REPORT  10 May 2013 

LIST OF ACRONYMS ............................................................................................................................................ 1 

EXECUTIVE SUMMARY ........................................................................................................................................ i 

1.0  INTRODUCTION ...................................................................................................................................... 1 

1.1   Background ................................................................................................................................................... 1 

1.2  Description of Project ..................................................................................................................................... 1 

1.3  Detailed Requirements and Scope ................................................................................................................. 2 

1.4   Study Approach ............................................................................................................................................. 3 

1.5   Report Organisation ...................................................................................................................................... 4 

2.0  Current Situation .................................................................................................................................... 6 

2.1  Location and Context ..................................................................................................................................... 6 

2.2  Existing Infrastructure and Facilities .............................................................................................................. 6 

2.3  Asset assessment ........................................................................................................................................... 8 

2.4   Air Traffic Activity........................................................................................................................................ 24 

2.5   Financial Assessment ................................................................................................................................... 35 

2.6  Comparisons with Other Competing Airports in Area .................................................................................. 53 

2.7   Stakeholder Consultation ............................................................................................................................. 60 

2.8  Summary of Current Situation ..................................................................................................................... 68 

3.0   Opportunities, Forecasts and Facility Requirements ............................................................................... 71 

3.1   Airport Vision and Objectives ...................................................................................................................... 71 

3.2   Future Opportunities ................................................................................................................................... 71 

3.3   Forecast Air Traffic Activity ......................................................................................................................... 78 

3.4   Forecast Facility Requirements ................................................................................................................... 82 

4.0   LAND Development AND INFRASTRUCTURE Plan ................................................................................... 90 

4.1   Land Development Plan .............................................................................................................................. 90 

4.2   Infrastructure  Expansion and Maintenance (Capital) Plan ....................................................................... 109 

4.3   Phasing Plan .............................................................................................................................................. 114 

4.4   Very Long Term Plan .................................................................................................................................. 116 

5.0   Financial ANALYSIS .............................................................................................................................. 119 

5.1  Status Quo Financial Forecasts .................................................................................................................. 119 

5.2  Business Case For Land Development ........................................................................................................ 120 

5.3  Establishing Appropriate Land Values and Lease Rates ............................................................................ 124 

5.4  Business Case for Increasing Land Rates and Other charges ..................................................................... 125 

PED-9-2013-4B

Page 3: Muskoka Business and Master Plan Final Draft Report-10May

  

 

 

TOC Page 2  

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Company co

nfid

ential. A

ll rights reserved

.        

FINAL REPORT  10 May 2013 

6.0  Business plan ....................................................................................................................................... 130 

6.1  Strategic Direction ..................................................................................................................................... 130 

6.2  Marketing .................................................................................................................................................. 132 

6.3  Action Plan ................................................................................................................................................. 134 

6.4  Financial Forecasts ..................................................................................................................................... 134 

7.0  GOVERNANCE ...................................................................................................................................... 137 

Source: Final Report, Ontario Municipal Airports Data Collection Study, 2011 Update, Leigh Fisher Management Consultants ............................................................................................................................................................ 138 

7.1  Alternative Governance Models ................................................................................................................ 138 

7.2  It’s About More Than Governance ............................................................................................................. 145 

7.3  Policy Makers and Management ............................................................................................................... 146 

7.4  Governance at YQA – Moving Forward ..................................................................................................... 148 

7.5  Implementing an Airport Commission at YQA ........................................................................................... 148 

8.0  RECOMMENDATIONS ........................................................................................................................... 150 

APPENDIX A: LIST OF ORGANIZATIONS CONTACTED ........................................................................................... 1 

APPENDIX B: LIST OF DOCUMENTS REVIEWED .................................................................................................... 1 

APPENDIX C – Airport Zoning Regulations ........................................................................................................... 1 

APPENDIX D – Instrument Approach Procedures ................................................................................................ 1 

APPENDIX E:  Opportunities modelling analysis .................................................................................................. 1 

APPENDIX F: Additional WInd Analsysis Graphs .................................................................................................. 1 

APPENDIX G: Aircraft Runway length information .............................................................................................. 1 

APPENDIX H: New height guidance re wind turbulence ....................................................................................... 1 

APPENDIX I: Typical Lot LAyouts ......................................................................................................................... 1 

APPENDIX J: FINANCIALs .................................................................................................................................... 1 

APPENDIX K: WIND ANALYSIS AND RUNWAY USABILITY ..................................................................................... 1 

PED-9-2013-4B

Page 4: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Acronyms Page 1

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

LIST OF ACRONYMS

 

ACRONYM  MEANING  ACRONYM  MEANING 

ACAP  Airports Capital Assistance Program  LDA  Landing Distance Available 

AIF  Airport Improvement Fee     

AMSCRs  Aircraft Movement Surface Condition Reports 

   

AOM  Airport Operations Manual     

ARCAL  Aircraft Radio Control of Aerodrome Lighting System 

   

ARFF  Aircraft Rescue and Fire Fighting     

ASDA  Accelerated Stop Distance Available     

ATB  Air Terminal Building  MRO  Aircraft Maintenance, Repair and Overhaul  

Avgas  Aviation fuel (for piston aircraft)  NAMO  Northern Airports and Marine Operations 

AWOS  Automated Weather Observing System  NDB  Non‐Directional Beacon 

CAO  Chief Administration Officer  NM  Nautical Mile 

CAP  Canada Air Pilot  NOTAM  Notice to Airmen 

CARs  Canadian Aviation Regulations  ODALS  Omni Directional Approach Lighting System 

CASRs  Canadian Aviation Security Regulations  PAPI  Precision Approach Path Indicator 

CFs  Community Futures  PFC  Passenger Facility Fee (similar to AIF) 

CFS  Canada Flight Supplement  RESA  Runway End Safety Area 

CFS – WAS  Canada Flight Supplement – Water Aerodrome Supplement 

RILS  Runway End Identification Lights 

CIIF  Communities Infrastructure Improvement Fund 

SMS  Safety Management Systems 

COPA  Canadian Owners and Pilots Association  TC  Transport Canada 

CRFI  Canadian Runway Friction Index  TOB  Telecommunications Operations Building 

DF  Direction FInder  TORA  Takeoff Run Available 

DME  Distance Measuring Equipment     

EMAS  Engineered Material Arresting System  VFR  Visual Flight Rules 

ERS  Emergency Response Service  VOR  VHR Omni Directional Radio Range 

FAA  Federal Aviation Administration (US)     

FEC  Filed Electrical Centre     

ICAO  International Civil Aviation Organisation     

IFR  Instrument Flight Rules     

       

       

       

       

 

 

 

PED-9-2013-4B

Page 5: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page i

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

EXECUTIVE SUMMARY

The Muskoka Airport is located along Highway 11 within the District of Muskoka. The airport is located nearly midway between  the  towns of Gravenhurst  and Bracebridge. The  airport  lands encompass  an area measuring approximately 223 hectares (550 acres).   

The airport is an important economic asset for the District, providing vital jobs in the District and being the Gateway to the area and its extensive tourism industry. 

The previous Master Plans (1999) and Business Plans (1996) for the airport have now run their course and with the extensive pressure on the airport to expand its facilities due to demand for additional land development, among other pressures,  the airport needs updated plans  to guide  its development and investment activities.      

The new Business and Master Plan to be developed as part of this study will guide the development and operation  of  the Muskoka  Airport  for  the  next  15‐20  years.  It will  review  the  current  state  of  the Muskoka Airport and make recommendations on how the District can capitalize on existing assets and opportunities to enhance the business and operation of the airport.  

The project includes an examination of: 

1. The airport business operation and financial status, potential, needs and requirements; 

2. Airport infrastructure and facilities, needs and requirements; 

3. Aviation business development, development area expansion and potential  land acquisition; and 

4. Airport governance.  

CURRENT SITUATION

EXISTING INFRASTRUCTURE

The  Airport  sits  on  about  a  550  acre  site,  a  significant  portion  of  which  is  consumed  by  runways, taxiways, apron(s). Only about 22 acres of serviced  land  is currently available  for commercial/revenue purposes. This  land  is  currently all  leased or  sold  (except  for 2  remaining  small  lots). The Airport has additional  land  to  service  and  develop,  probably  in  the  order  of  40‐50  ac,  depending  on  how  it  is developed  and  how  facilities  are  allocated  on  the  site.  Large  portions  of  the  airports  lands  are environmentally sensitive wetlands, focused primarily on the east side, but with some similar but much smaller, environmental areas on the west side as well.  

The Airport has a 6,000 ft x 150 ft runway, which until recently was probably the longest/widest runway within about a 100 mile radius.  This runway is oriented North‐South. This runway has GPS approaches with  limits of  just 500  ft and 1.5 mi  viz  to both ends, as well as NDB approaches with  similar  limits. Weather  data  indicates  these  limits  are  exceeded  some  5%  of  the  time,  so  that  the  airport  is  not available due to weather during these periods.  

The Airport also has a 2180  ft  x 100  ft grass  runway oriented East‐West  that  is available only during summer daylight conditions. 

Other key facilities at the airport include: 

• A terminal building recently upgraded and expanded  in 2007, to  include a unique memorial to Norwegian Air Force training on site during World War II; 

PED-9-2013-4B

Page 6: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page ii

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

• A  partial  parallel  taxiway  that  had  a  pavement  overlay  and  improvements  in  2010/11,  and associated connecting taxiways; 

• An aircraft apron, expanded in 2006, with a number of other private aprons; 

• A  5 bay maintenance garage originally constructed  in the 1950s, with a supporting metal shed built in the 1980s; and 

• A 3 bay equipment shed built in 2009.   

Airport facilities in general are in reasonable shape and users are generally happy with them, other than: 

• The main runway needs to be overlaid in the next couple of years, probably by 2015 to restore the pavement surface; 

• The grass runway surface is less than ideal (and there are issues about its location and sizing), as will be discussed later; 

• There are concerns about lack of a parallel taxiway to accommodate operations during the peak summer season; 

• The aircraft apron can get congested on busy summer weekends. 

In addition to the above, the Airport provides the following operations and services: 

• The  airport  is  open  24  hours  per  day  year  round,  though  traffic  is  very  seasonal, with  low volumes in winter;  

• It has fuelling facilities, including jet fuel and avgas. This facility was installed by Esso and having such a brand is key to a good FBO operation;  

• The airport is also a Customs port of entry, allowing it to cater to US and International traffic. In some  cases  aircraft may have  to  land here  to  clear before heading  to  another  airport  in  the region that does not have Customs, such as Parry Sound;  

• The airport also has a  fleet of vehicles  that  it operates and maintains  in support of  its airport operations.    

CURRENT AIR TRAFFIC ACTIVITY

The current traffic at the airport has some of the following characteristics:  

• Runway use 

• Runway 36 is used the most often, handling 56% of itinerant traffic; 

• The short grass runway is currently used for 2% of itinerant traffic; used only by piston, small turboprops and helicopters. 

• Itinerant traffic at the airport makes up 66% of overall traffic:  

• Helicopters (no runway) represent 5% of this itinerant traffic; 

• Approximately 25% of itinerant movements are IFR; 

• Missed approaches, at 4%, are a relatively high % of itinerant movements, with many of these operations being primarily for training purposes;  

• Local movements represent 34% of total movements. These are primarily training operations. 

 

 

PED-9-2013-4B

Page 7: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page iii

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

• Aircraft Category  

• Piston aircraft are the  largest users of the airport (65%) followed by turboprops (21%), helicopters (8.5%) and jets (5.7%);  

• The most common large aircraft is the military C‐130 (Herc) and Jazz’s CRJ‐200. 

• Aircraft Owner 

• Sierra  Fox  Inc.  (Ferrari  Flight  Training)  used  the  airport  the most    (542 movements; average of 1.5 / day); 

• 5 owners averaged over 1 movement / day. 

Traffic at the airport is distributed and spread as follows:  

• Time of Year 

• Activity varies greatly over the year; 

• The busiest month is July for both local and itinerant movements; 

• The December to February period is very quiet. 

• Day of Week 

• Busiest days are Friday, Tuesday and Thursday for overall traffic; 

• Itinerant traffic is highest on Friday, followed by Saturday.  

• Hour 

• Overall , year round average traffic peaks at 11 am with 5 movements on average, of which 2 are local;  

• There are itinerant traffic peaks at  11 am, 2 pm, and 3 pm; 

• In July, 9 am is the busiest hour with 12 movements on average, of which 6 are local; 

• July Itinerant traffic peaks at  10 am with 7 movements on average; 

• The Planning peak hour (95% percentile) has: 

• 12 movements – itinerant; 

• 28 movements – total (local + itinerant). 

July

PED-9-2013-4B

Page 8: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page iv

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Traffic  at  the  airport  over  the  last  decade has  been  very  volatile.  The  trend  in itinerant  movements  by  engine  type  is shown  in  the  figures  at  right  and  below. Movements  by  piston  aircraft  have  been generally  declining  over  the  last  decade. These  movements  declined  up  till  2004, remained  fairly  steady  between  2005  and 2010,  and  then  appear  to  be  lower  again for  2011  and  2012.  This  trend  for  piston movements  seems  to have  generally been reflected  in  the  total movements,  at  least until  about 2005  at which  time  the piston movements started a flat to declining trend and  total  movements  began  a  steady upward trend.  

Turboprop  aircraft  movements  have been  increasing  steadily  from  1997 through  to 2008 with particularly  strong growth  in  2011  and  2012.    Helicopter movements have been  slowly  increasing until 2009, but have declined since then. Jet  movements  increased  to  2003  but have  been  fairly  steady  since  then, though  these have averaged about a 1% annual growth over  the decade. Overall, the  declines  in  piston movements  over the  last  decade  have  been  gradually offset by gains  in other  types, especially turboprops. 

The trends we’ve seen in GA traffic at the airport are generally representative of what’s been happening in the GA  industry overall, where GA has been slowly declining for 20+ years  in Canada [source:   Stats Canada movement certificates]. The declining segments in the past 10 years (2001‐2011) include: 

• Piston movements, the largest segment of GA, have declined 40% (5.1% /yr); 

• A similar trend was experienced in the US hours flown, which is down 4.1%/yr. 

• Private aircraft movements have declined 26% (3.0%/yr); 

• Local movements have declined 39% (4.9%/yr). 

However, some segments have been increasing between 2001 & 2011: 

• Jet movements have increased 8% (0.8%/yr); 

• Turboprop movements have increased by 35% (3.0%/yr); 

• These increases in turbine aircraft have also occurred in the US;  

• Jet and  turboprop movements have  recovered  strongly  from  the  recession with 6‐7%/yr over 2009‐2011. 

PED-9-2013-4B

Page 9: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page v

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

The US  FAA  forecasts  a  slow decline  in piston  (‐0.1%/yr)  and  growth  in  turbine  (jet &  turboprop) of 4%/yr  for next 20 years, with overall GA growth 1.7%/yr.  In  the US, 2/3rd of GA activity  is  related  to business activity. 

FINANCIAL ASSESSMENT

The airport’s operating revenues can be classified as: 

• Aeronautical, and  

• Non‐aeronautical. 

Aeronautical  revenues  consist  of  the following categories:  

• Aircraft Landing fees; 

• Aircraft Fuel charges; 

• Aircraft parking fees; 

• Call out charges; and 

• Other miscellaneous fees. 

Non‐aeronautical revenues come from the following sources:  

• Land rents; 

• Office rents; 

• Covered tie down rents; 

• The airport Maintenance charge; 

• Vending machine sales; 

• Car rental fees; and  

• Other miscellaneous charges. 

The airport’s revenues have been increasing over the last 3 years, going from just over $ 440k in 2009 to over  $  550k  in  2011, with  an  anomaly  in  2010  due  to  the G8  Economic  Summit  that  took  place  in Muskoka.  The  bulk  of  the  revenues  consisted  of  aeronautical  revenues  (over  75%),  with  non‐aeronautical revenues comprising less than 25%.  

Airports usually try to achieve a balance between aeronautical revenues and non‐aeronautical revenues. This  is  because  the  aeronautical  revenues  can  be more  volatile  as  these  are  directly  tied  to  airport traffic.   On  the other hand, non‐aeronautical  revenues are much more  stable as  these  relate  to  land leases, office rents, etc, which just do not vary as much, and in fact should continue to rise steadily with growth, with  little chance of decline. By achieving a good balance, an airport can therefore  lessen the fluctuations and volatility of  its overall  revenues. Having  said  the above,  it  is much more difficult  for smaller  airports  to  achieve  a  good  balance  than  it  is  for  larger  airports which  have  access  to more sources of revenue.  

The airport’s operating expenses can be grouped into 3 categories: 

• Salaries and wages; 

• Equipment/travel fleet;, and 

PED-9-2013-4B

Page 10: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page vi

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

• Inter‐departmental charges. 

Salaries and wages make up by far the largest  component  of  total  expenses at  over  43%.  This  is  normal  at most airports.  

The  operating  expenses  have increased over the  last 3 years similar to the increases in revenues. However, these  increases  have  actually  been less  in  percentage  terms  than revenues.  These  expenses  have  gone from  just over $ 750k  in 2009  to  just under $ 850k  in 2011, again with  the anomaly in 2010 for the G8 summit. 

As illustrated in the graph below, the airport’s expenses have clearly continually exceeded the airport’s revenues over the last 3 years, with a net operating loss of over $ 315k in 2009, but decreasing to a net loss of just under $ 290k by 2011. This improvement in the operating loss is good news for the airport.  

By  comparison,  according  to recent  information  available about other Municipal airports in Ontario,  this  loss  is  higher  than the average loss at these airports of about $ 143k. But we need to remember  that  this  is  just  an average,  with  some  airports higher  than  this  and  others lower.  As  well,  it  is  difficult  to compare  directly  with  other airports  as  they  all  tend  to  use slightly different  accounting  and allocation rules. Finally, Muskoka is  the  only  airport  we  know  of that  sells  land  in Ontario.  If we were  to  correct  for  this  by converting  the  current  sales  to lease  revenue  instead,  the annual  operating  deficit  would drop by a  further $ 40k+.     So  in reality there may be a much smaller difference between Muskoka and the Municipal average.   

In addition to operating revenues and expenses, the airport also expends funds on capital improvements to the airport facilities. These capital expenses can be grouped into 2 key categories: 

• Capital  expenses  for  the  expansion  of  the  airport,  including  any  new  facilities,  land development, etc; and 

• Expenses  required  for  the major maintenance and  repairs  to  the airport’s  facilities,  including pavement overlays, building roof replacements, and other structural, mechanical and electrical upgrades. 

PED-9-2013-4B

Page 11: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page vii

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

The airport typically sets aside about 400k‐550k per year into the airport’s Capital Reserve Fund to pay for the improvements. This works out to about 1‐1.5% of the value of the current assets, which appears to be consistent with our experience of requirements at other airports (once capital assistance programs are factored out).  

In  addition  to  the  capital  that  the  airport  contributes  to  the  reserve  fund  to  pay  for  the  various improvements, the airport also has access to FedNor and other capital assistance grant programs. These grants can provide up to 1/3 of the funds required for qualifying projects. In recent years the airport has been able to tap into this fund for a variety of projects like a taxiway extension and terminal expansion. As well, the airport recently received funds from the Government of Norway to expand the terminal to house the Little Norway Memorial there. 

There are a variety of other funding programs available to airports, such as: 

• Northern Ontario Heritage Fund Corporation (NOHFC); 

• Airport Capital Assistance Program (ACAP); 

• Building Canada Fund (BCF); 

• Various Infrastructure funds that come and go. 

The airport does not have access  to  the  first 2 of  these as  it  is not  in Northern Ontario per provincial guidelines  nor  does  it  have  scheduled  passenger  service.  But  the  airport would  have  access  to  the various  infrastructure  funds  that  come  and  go  depending  on  both  federal  and  provincial  politics. Airports that have timely development ready proposals can take advantage of these programs to get up to 2/3 funding for key capital projects. 

COMPARISON WITH OTHER COMPETING AIRPORTS

Part of the scope of work for this study was to compare the Muskoka Airport with a number of adjacent airports that it feels that it competes with for tenants, traffic, etc. These airports include the following: 

‐ Peterborough Municipal Airport; 

‐ Lake Simcoe Regional Airport; 

‐ Parry Sound Municipal Airport.  

Compared to the three competing airports, Muskoka appears to have the following advantages: 

• It has a high concentration of based aircraft servicing firms: full‐service; 

• Its provision of specialty services is a plus;  

• It has a competitive runway length and width, and good accessibility due to weather; 

• It is a year‐round base for public services; 

• It is a Customs port of entry (though all but Parry Sound have this);  

• It has branded  fuel  (which  is  important  to attract commercial/corporate  sector and especially turbos and jets, though only Parry Sound does not have this; 

• It has a good base of turbo and  jet traffic to use as spring board for additional growth and for revenue purposes;  

PED-9-2013-4B

Page 12: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page viii

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT 10 May 2013 

Comparisons with Competing Airports    Muskoka Peterborough Lake Simcoe Parry Sound

Owner/Operator  District  City/Private Operator City (80%)/Twp (20%) Muni. 

Services Corp. Township/Airport Commission 

Population 60,000+ (2011)

Seasonal pop can be double 118.975 (2011)+2.1% from 2006 

446,063 (2011)+5.7% from 2006 

42,162 (2011)+3.0% from 2006 

Economic Sectors Tourism 

Forest fire district (MNR) 

Industrial, RetailRegional health centre  

Post‐secondary 

Industrial manufacturingMilitary (CFB Borden) Casino, Post‐secondary  

Tourism, RetailRegional heath centre  

Forest fire district (MNR) 

Aerodrome Status  Certified Certified Registered Registered

Runway (longest paved)  6,000’ x 150’ 7,000’ x 100’  6,000’ x 100’ 4,000’ x 75’ 

Crosswind  2,200 x 100 turf 1,800 x 100 turf ‐ ‐

Visual Aids, Navaids and Approaches 

Medium intensity lighting;      PAPI  Rwy 18; NDB Best Approach limits: 500 ft, 1.5mi 

Medium Intensity lighting;      PAPI Rwys 09/27; NDB Best Approach limits: 500 ft, 1.5mi  

Medium intensity lighting;PAPI Rwys 10/28; VOR/DME Best Approach limits: 370/380 ft, 1.25mi  

Medium intensity lighting; APAPI Rwy 36; NDB Best Approach limits: 500 ft, 1.5mi 

Aircraft Services Branded Fuel / oil

Major / minor repair Catering 

Branded Fuel  / oilMajor / minor repair Catering by FBO 

Branded Fuel / oilMajor / minor repair 

Catering 

Fuel / oil Major / minor repair 

Passenger Services 

New terminal (vending, Wi‐Fi)AOE/15 and Customs 

Car rental& taxi (call‐out) Access to off‐site restaurant 

New terminalAOE/15 and Customs 

Taxi, car rental (call‐out) Restaurant 

Executive passenger lounge(Free Wi‐Fi), AOE/24 and 

Customs Car Rental x 3 

Newly renovated business centre 

Taxi, car rental (call‐out) Café 

# of Based Businesses  9  17 8 11

# of Based Aircraft (CCAR)  76  137 45 54

Traffic (Total 2011)  17,019 33,717 20,580 7,805 (2009)

              (Itinerant)  11,282 6,651 6,138 ‐

Land 223 h (550 acres)  

Limited Developed land  Sale / lease 

276 h (682 acres)26.5 ha (57 lots) – 4 sites incl. 

30 acres of serviced Airport industrial park 

240 (595) Commercial Development Plan: 4 areas; serviced and un‐serviced lots 

Recent private & commercial hangar development; training facility; industrial expansion 

Financial ‐$287K in 2011 (excl. grants & 

sale of land revenue) ‐$200K in 2009  ‐ 

‐$100K (if remove grant, sale of land, & tax revenue 

Other  Little Norway Memorial $28M expansion (2009 ‐ ) 

Seneca College flight training  

$15M Expansion;  “Airport Economic Employment 

District” 

Airport Industrial Park; numerous hangars; Float plane 

base 

PED-9-2013-4B

Page 13: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page ix

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

On the other hand, it is weak in a number of particular areas, as follows:  

• It currently does not have available developed  land, though we will show some 35+ acres can easily be brought on stream quickly, once a plan is agreed to; 

• It does not have as large a population base on which to draw activity from, though tourism is a growing sector to exploit; and 

• It does not have the industrial base that airports like Peterborough and Lake Simcoe have.   

 So what can we conclude from this comparison?  

• For  its size and  location, the airport has good competitive facilities,  in many ways, as good, or better  than  its  competitors,  especially  in  terms  of  runway  length/width/strength  (only  Lake Simcoe has better approaches in poor weather and Muskoka could easily match this). 

• It has a very good concentration of local aviation businesses that can form a strong nucleus from which to expand;  

• Given  its  population  base,  it  has  a  reasonable  amount  of  traffic  to  form  a  basis  for  future growth; 

• Increased tourism should probably be a key focus for future growth and turbo prop and jet operations should be a focus within this.

STAKEHOLDER CONSULTATION

Extensive consultations were undertaken for this study, much more than was originally planned. These consultations  took  the  form of one on one  interviews  (both  in person  and over  the phone)  and  self administered web‐based surveys. The following groups were consulted: 

The general public (through self administered web based surveys); 

In‐coming Pilots (via one on one interviews); 

In‐coming Visitors (via one on one interviews); 

Tenants and Businesses (with one on one interviews both in person and over the phone); 

Economic Development and Tourism Staff (via email enquiries and phone follow‐up); and 

Elected Officials and Senior District Staff (through one on one telephone interviews).   

There were a total of 37 responses received online from the general public. These respondents tended to be very  familiar with  the airport and activities  there as many of  them appeared  to be users of  the airport.  As  a  result  they were  very  aware  of  the  economic  contributions  of  the  airport  to  the  local economy,  to  the  services  it  offered,  including  emergency  response  like medivac,  and  they  generally supported the expansion of the airport.  

Some key comments from these stakeholders included: 

The Airport should be run by non‐government or private group (with governance a key issue); 

More promotion should be done to make people aware of the airport; 

A  restaurant would be a key asset at  the airport  that would attract visiting pilots and  locals, alike; 

The airport needs an appropriate plan to guide the future development of the airport.  

PED-9-2013-4B

Page 14: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page x

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

A total of 35 interviews were carried out with in‐coming pilots and in‐coming visitors. These groups were really similar  in that sometimes pilots were  interviewed (when they were the key travellers) and other times the visitors or passengers were interviewed (in cases where the aircraft was chartered or rented).  

Some key characteristics of these users were: 

Nearly 50% were visiting from the US, mainly nearby US States; 

Many,  again  close  to  50%,  arrived  via  chartered or  rented  aircraft  like NetJets,  Shoreline,  LJ  Aviation; 

The aircraft mix for these users was approximately 40% jets, 30% turbos, and 25% pistons;  

Most  (over ½)  just stayed  for  less  than 1 day, some 20%  less  than 1 hour, and approximately 25% stayed for up to 1 week; 

Nearly ¾ of users chose the airport due to  its proximity to their cottages, while other reasons included to clear Customs, or to visit friends or to play golf; 

Most of the respondents were frequent visitors to the airport, with each accounting for up to an average of 10 annual trips, but then for 25% of the visitors, it was their first time; 

All of these users rated the airport quite high, with an average score of 4.6 out of 5; 

Key comments received were: 

o  the airport had friendly staff that provided good service (some of the best in the area), 

o  there was a nice museum; 

o they liked the pilot lounge and the wi‐fi provided; and 

o generally  the  airport  facilities  were  excellent  and  didn’t  really  require  any improvements  (though  some  did  mention  things  like  an  ILS,  showers  in  the  pilots lounge, tie‐downs, closer car rentals  and a parallel taxi would be nice).  

Information  from  tenants  and  based  businesses  at  the  airport  was  obtained  through  one  and  one interviews and through an online survey. A total of 23 responses were obtained.  

The tenant and business respondents indicated that they saw the strengths of the airport as:  

Location; 

Runway length and orientation; 

Economic potential; 

The fuel services offered; and 

The fact that it had a runway maintained year round.  

They saw the key weaknesses of the airport as being:  

Development restrictions (how and what they could develop); 

Lack of available land to grow; 

Lack of a restaurant; 

Lack of a full length taxiway; 

Management and political issues at the airport; and 

PED-9-2013-4B

Page 15: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xi

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Lease policy and term issues.  

The tenants wanted to see the following changes at the airport in terms or new facilities and services:  

Credit card or keylock for self serve fuel; 

Restaurant and / or a meeting area; 

More organized events to draw aircraft in and promote the airport; 

Operational  and  management  changes,  including  a  commission  instead  of  municipal government 

The acquisition of land to protect for future growth prospects for the airport.  

Economic Development and Tourism staff noted the following from the responses received: 

The airport is highly important for tourism to the area; 

The economic sectors benefitting from airport were:  tourism, construction, and aviation; 

There is little to no manufacturing left in area and these were previously key users of charters at the airport;  

There are a number of major tourism developments underway or planned in the area that could increase demand for tourism and for the airport.  

Key  issues  that  came  out  of  the  discussions with  elected  officials  and  senior  District  staff were  as follows: 

There was a general recognition of the economic importance of the airport;  

There were concerns about its financial viability;  

The funding formula vs the perceived benefit of the airport came up repeatedly; 

The issue of selling vs leasing land was of interest to a number of the elected officials;  

Governance and how to better manage the airport was a concern; 

Many felt the Airport could be better promoted; 

A sound Infrastructure plan for the Airport was of vital necessity; and 

An on‐site restaurant would be a good idea for the airport. 

SUMMARY OF CURRENT SITUATION AT THE AIRPORT

Based on our review, we believe that: 

The airport has reasonable facilities for its current requirements; 

These facilities put the airport in a good position to compete with other airports in the area;  

But it needs additional developed lands to meet forecast requirements; 

The existing tenant and business base at the airport provides a strong base from which to grow; 

The existing traffic mix at the airport is strong and trending in a positive direction; 

The airport financial situation is consistent with other Municipal airports, and this is improving, though; 

PED-9-2013-4B

Page 16: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xii

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

The airport is challenged in terms of programs for capital assistance; 

Current  financial  accounting  and  budgeting  practices  are  sound  and  consistent  with  best practices; 

Most users are generally happy with the airport’s facilities and services; though 

There are a number of issues to deal with from the tenant’s and businesses at the airport.       

OPPORTUNITIES

To identify potential future development opportunities at the airport, we took the following approach:   

We  used  an  investment  attraction model  developed  in  consultation with  FedNor,  for  use  by airports and communities;   

We assessed investments, expansions and related activities at competing airports in the broader  region to see what they were undertaking; 

We  considered  general  trends  in  the  broader  aviation  industry  and more  specifically  in  the general aviation component;  

We held discussions with key airport stakeholders to see what input they could provide;  

We reviewed activities and trends at Southern Ontario Airports in general to identify how these could create opportunities for the Muskoka Airport; 

Through this process we identified the following opportunities: 

Enhanced maintenance, repair and overhaul (MRO) services; 

Hangar developments, both small T‐hangar type and larger corporate type; 

Expanded flight training; 

Aircraft Sales; 

Expanded FBO activities; 

Organized promotional events; 

Increased tourism; and 

Self serve avgas. 

We identified, reviewed and subsequently rejected a number of other potential opportunities, such as:  

Scheduled airline service, at least probably within the next 10 years;   

Base for aircraft manufacturing &/or assembly, on a larger scale;  

Post‐Secondary Aviation / Aerospace Training (incl. MRO, engineering, airport management, at least on  larger scale);  

Expanded base for public services;  

Maintenance base for scheduled carriers.  

The following are a number of key findings from our opportunities assessment:   

• There are a lot of potential opportunities for the Muskoka Airport to pursue in order to expand operations and investment at the airport;  

PED-9-2013-4B

Page 17: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xiii

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

• A  lot  of  the  potential  development  and  whether  or  not  it  is  realized  depends  on  local entrepreneurs and whether or not they “step up to the plate”, and whether or not they receive support from the community;  

• An  important key to airport expansion  is building on activities and uses you already have. This brings you better returns, and is easier than attracting new users, activities, etc.; 

• The  types  of  opportunities  available  need  to  be  qualified  in  terms  of  the  potential  scale  of activity; and 

• To capitalise on opportunities the airport must first have the appropriate facilities in place, or at least a plan to develop these facilities and then it must aggressively market itself and pursue the potential opportunities.  

FORECAST ACTIVITY

We  developed  forecasts  for  future  aircraft movement  activity  at  the  airport  under  three  different scenarios:  

Status quo: 

o This  assumed  that  there would be no  additional development  at  the  airport,  that no tenants  would  leave  as  a  result  and  that  traffic  growth  and  mix  would  continue according to recent trends;  

Medium growth case: 

o This scenario assumes that land development will occur and that this development will be at a 25% slower pace than historical, with only 15 acres of  land developed over the next 20 years.  

o There will be additional traffic growth at the airport over and above the trend line based on the projected mix of new tenants and new uses.  

High Growth case: 

o This  scenario  assumes  that  land development will  occur  at  a  faster  rate  (+25%)  than historical, with up to 25 acres of land developed over the next 20 years; 

o There  will  also  be  additional traffic growth at the airport over and above  the  trend  line based on  the  projected  mix  of  new tenants and new uses.  

The  implications of these  levels of development on air traffic at YQA are shown  in the  following figures.  

For itinerant movements: 

The  Base  Case  forecast  has  these growing  from  12,250  to  13,350 movements in 20 years; 

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

2012 2017 2022 2027 2032

Itinerant MovementsBase Case Medium High

PED-9-2013-4B

Page 18: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xiv

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

The Medium Case forecast projects these to grow  from 12,250 to almost 14,600  in this same period; while 

The  High  Case  suggests  itinerant operations  could  approach  16,000  in  20 years. 

With respect to Total Movements: 

The Base Case forecast grows these from some 16,450 to about 18,100 in 20 years; 

The  Medium  Case  forecast  has  these growing  from  16,450  to  over  19,000  in this same period; while 

The  High  Case  suggests  total  operations could approach 22,000 in 20 years’  

In terms of aircraft types, we forecast that: 

Jet  traffic will  continue  to  grow  at  a  higher  rate  than  total  traffic  and  account  for  a  higher proportion of total traffic under all scenarios than today; 

Turbo‐prop traffic will experience a similar trend; while 

Piston‐engine  traffic will  decline  under  all  scenarios,  but moving  from  the  base  case  to  the medium  to  the high case,  this segment of  traffic would consistently account  for higher piston volumes (but again less than today, even in the high case);  

Local movements would grow from today’s levels, but only marginally in the base and medium cases, with much higher activity in the high scenario.   

 

Year 2012 2017 2022 2027 2032 2017 2022 2027 2032

Redevelopment Scenarios Medium Case High Case

Jet engines 683 849 1,026 1,237 1,398 888 1,121 1,335 1,561

Turbo-propellers 2,772 3,189 3,689 4,330 4,796 3,309 3,917 4,509 5,172

Piston engines 7,861 7,436 7,148 7,106 6,675 7,703 7,587 7,431 7,372

Helicopters 934 1,077 1,259 1,491 1,708 1,100 1,297 1,514 1,770

Local 4,197 4,697 4,724 4,780 4,780 5,900 5,946 5,983 6,029

Total 16,447 17,247 17,847 18,944 19,358 18,899 19,868 20,772 21,904

 

While these traffic forecasts still do not represent significant growth, even  in the high case at just 30% more  traffic  than  today’s  levels,  the  segments  that have  significant  revenue opportunities are  in  fact growing the  fastest and will  impact the revenue side much  faster and better than the cost side  (to be illustrated later).  

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

20,000

22,000

2012 2017 2022 2027 2032

Total Movements

Base Case Medium High

PED-9-2013-4B

Page 19: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xv

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

FORECAST FACILITY REQUIREMENTS

Based on our review of existing facilities, their capacities and comparing these with the forecast traffic, both  in  terms of  volume  and mix we  feel  that  the  following  improvements need  to be made  to  the airport’s facilities: 

 

RUNWAYS

The existing main  runway at  the airport  (18‐36)  is more  than adequate  in  terms of  length and width. However,  its  orientation  is  not  necessarily  the  best  to  satisfy  the  requirements  of  the  full  range  of aircraft serving the airport.   

Transport Canada  recommends  that an airport’s  runway system provide at  least 95% usability  for  the aircraft that  it  is  intended to serve. While the main runway provides an estimated 98.6% coverage for larger aircraft, it only provides 95.4% usability for the lighter aircraft that currently comprise over 75% of aircraft movements at the airport.  This usability does not consider gusts, which would reduce this 95.4% figure  well  below  95%. Most  airports  use  this  usability  criterion  as  a  base  level  that  needs  to  be exceeded  and  consequently  they  try  to maximize  the  actual  usability,  as  opposed  to  using  this  95% figure as a target to be achieved.  

On the basis of the winds at the airport and  the above discussion, we therefore  feel that a crosswind runway at  the airport  is a basic  requirement. This  crosswind  runway  function  is  currently met with a grass  runway oriented  as 09‐27. However,  to maximize  the  runway  system availability  the  crosswind runway should be paved and eventually extended.  

As a result of various discussions, comments, previous work, and an assessment of  land development options available, we looked at a number of possible orientations for a crosswind runway and concluded that any orientations  from 09‐27 around  to 12‐30 would provide a  similar  additional usability  to  the existing runway. In terms of the length of this crosswind runway, a maximum  length of 2,800 ft should be more  than  adequate  to handle  the  range of  smaller  aircraft  serving  the  airport,  at  least over  the medium to long term.       

TAXIWAYS

The airport has a very limited taxiway system, comprising a partial parallel taxiway along the north‐west half of the main runway, with a number of connecting taxiways. With most of the main developments at the airport concentrated at this north‐west corner and the main aircraft apron in the south‐west corner, the  lack of a full parallel taxiway to this runway  is manifesting  itself  in  increased delays and comments from both local users and visiting pilots.  

Over the  long term, a full parallel taxiway should be provided to the main runway to be able to better handle  aircraft operations on  the  ground. However, we  feel  that  the provision of  a paved  crosswind runway (in a 12‐30 configuration) would defer the need for a full parallel taxiway well into the future.      

AIRCRAFT APRON AND PASSENGER TERMINAL

The aircraft apron  is currently at or over capacity for a number of very busy weekends  in the summer. While space should be protected to the north and south of the existing apron for future expansion, we feel  that  demand  management  techniques  should  be  employed  first  to  defer  the  need  for  any expansion.  

The current passenger terminal should be more than adequate to serve forecast needs for the entire 20 year period of this plan. The only proviso to this would be if the airport were to obtain scheduled airline 

PED-9-2013-4B

Page 20: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xvi

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

service, which is considered unlikely, at least in the short to medium term. Should the airport become a base for scheduled airline services, then both the terminal and the apron would need to be expanded.     

NAVAIDS

The  current  list  of  airfield  lighting,  navaids,  and  instrument  procedures  for  the  airport  is  probably sufficient  for the current traffic  levels at the airport. However,  if the airport wants to be aggressive  in growing  its  traffic  and  especially  some of  the  important  elements  like  jets  and  larger  turbo‐props,  it would benefit from the implementation of LPV approaches, installation of RILS and in the installation of a PAPI on Runway 36.    

LAND DEVELOPMENT

The single  largest deficiency  in current  facilities at  the airport  is  in  the area of  land  for development. There  is  effectively  no  land,  other  than  2  lots  left  remaining  undeveloped,  and  these  lots  are  being pursued by a number of current tenants very eager to develop them.  

We have prepared the forecasts below for future  land requirements. As  it  is difficult to forecast these requirements because the variables are quite wide ranging, from how aggressively the airport may wish to pursue future growth, to how aggressive the competition may react, we have produced 3 scenarios.  

Total additional land under the 3 scenarios is forecast to range from as little as an additional 15 acres to as much as 35 acres over the 20 years of the plan.  

 

      Additional Land Requirements by Time Period (Acres)  

0‐5 years  6‐10 years  11‐15 years  16‐20 years  Total 

Medium Growth  5  4  6    15 

High Grow  9  6  5  5  25 

Very High Growth  10  10  8  7  35 

OTHER FACILITIES AND SERVICES

Other  facilities  and  services  at  the  airport  should  generally  be  adequate  for  the  20  year  period.  For instance, the current airport access  is forecast to be more than sufficient for a very  long time. As well, the  current  approach  to  providing  utilities,  such  as  water  (from  wells)  and  sewer  (through  septic system),  should  continue  to  serve  the  airport  well,  unless  a  policy  decision  is made  either  at  the provincial or municipal level that would encourage “central” type systems.    

LAND DEVELOPMENT PLAN

To respond to the need for additional  land for development at the airport, we developed a number of options, starting with previous work that had been undertaken by District/Airport Staff.   

After  carefully  assessing  each  of  the  options  on  the  basis  of  costs  to  construct,  potential  revenues, amount of  land provided, risks, constraints and anticipated economic  impacts, we concluded that Plan B‐R would best satisfy the airport’s requirements over the 20 year planning period for this study.   

 

PED-9-2013-4B

Page 21: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xvii

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Key features of this plan included: 

The relocation of the grass runway further north and re‐oriented to a 12‐30 direction; 

Development of a 9‐10 acre subdivision just south of the existing MAR development capable of accommodating large MRO facilities to smaller T‐hangars and aircraft tie‐downs;  

Development  of  an  additional  25+  acre  subdivision  in  the  south  east  corner  of  the  airport, capable of supporting similarly wide ranging uses; and 

Creation of some additional landside type lots along Beaver Creek Road; 

Total  estimated  costs  would  be  in  the  order  of  $  5.3M  for  the  land  development  aspects (Including  taxiways, but excluding  land acquisition) and about $ 1.1 to 1.5M to pave the grass runway (depending on length chosen).  

According to our forecasts for future land development requirements, this option should be capable of meeting  forecast  requirements  to  the  end  of  the  planning  period,  even  under  a  very  high  growth scenario.    

PLAN B-R

 

 However, we feel that the airport also needs to consider a bold, very long term plan in order for it to adequately compete with airports in the same area and in order to be able to attract new progressive companies that may have the capabilities to contribute significantly to the local economy.  

PED-9-2013-4B

Page 22: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xviii

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

VERY LONG TERM PLAN

Key features of the very long term plan include: 

Building upon the development plan proposed for the first 20 years; 

PED-9-2013-4B

Page 23: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xix

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Designating  the  lands  to  the west of  the airport  (and east of Highway 11)  for mixed  industrial (which they are already zoned for) and aviation related uses; 

Protecting  for  the  possibility  of  realigning  the Gravenhurst  Parkway  to  be  re‐routed  through these new lands, so as to be the primary access to this future development, from both the north and the south; 

Realigning the existing north‐south portion of the Gravenhurst Parkway further to the west and re‐purposing  it to act as a service road to open up new  lots by extending the current westside developments further to the south to front along the extended full parallel taxiway; and 

Making provision for a possible future extension of Runway 12‐30 further to the west  into the area vacated by realigning the Gravenhurst Parkway. This could provide a runway length in the vicinity of 4,500 ft +/‐ .          

INFRASTRUCTURE (CAPITAL) PLAN

The airport has extensive infrastructure facilities, including: 

Runways, taxiways, aprons, and the associated electrical (lighting),  

Various buildings, including the terminal, maintenance building, and various equipment storage buildings, and 

A varied equipment fleet required to operate and maintain the airport. 

The airport  is  fortunate  in  that  this  study has  identified  that  this  inventory of current  facilities, other than  the need  to provide a paved crosswind  runway, some  improved navaids and additional  taxiways and  roads  to  service  the  proposed  new  land  developments,  should  be  capable  of  satisfying  airport requirements  for  the next 20 years. But all of  these  facilities, whether  the existing or  the new ones, require the occasional major maintenance and repairs in order to continue to provide useful service.  

Many of  the  current airport  facilities have been  recently upgraded or expanded, and  the airport has identified that the only major work still left to be done is a major overlay to the main runway, planned for about 2015 at a cost of close to $ 4M, a roof replacement of the maintenance garage at an estimated cost of $ 85k, planned for 2013 and a number of miscellaneous pavement repairs over the next couple of years.         

We estimate that the replacement value of airport  facilities  is probably  in  the order of $ 25M‐ $30M. Based on our experience at other airports,  the airport  should be  spending  some $ 0.5M annually on average to upgrade, maintain and repair these facilities. This would work out to about $ 10M over the next 20 years.  

As part of this work, we have  identified a rough “maintenance and repair” program that works out to nearly $ 6.5M over the next 20 years (or about $ 7.5M in inflated dollars). Key features of this program include the previously mentioned overlay of the main runway (which by itself is more than  

half  of  the  cost  of  the  total  program),  and  other  various  overlays  to  existing  taxiways,  aprons,  roof replacement on  the  terminal building, and other  structural/mechanical/electrical upgrades, as well as electrical upgrades to the airfield.     

FINANCIAL PLAN

In  order  to  determine  whether  or  not  the  airport  could  afford  to  pay  for  many  of  the  various improvements presented above, especially the land development related investments, we constructed a number of financial models, one for each of the development scenarios previously presented under the 

PED-9-2013-4B

Page 24: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xx

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

assumption  that  current  rates  and  charges  would  remain  relatively  unchanged  and  an  additional scenario that modeled the implications of raising various rates and charges, especially the land sale and land lease rates.     

Some interesting results from the financial modeling are as follows:  

Under a status quo scenario, where the airport chooses not to expand any facilities and just to continue operating as today, the annual operating deficit would go from just over $ 300k today to just under $ 100k by the end of the 20 year planning period. This would result in a cumulative operating deficit over the 20 years of over $ 4.5M. 

If  the  airport  chooses  to  develop  along  the  lines  of  the medium  growth  case  (still  keeping current rates and charges), an operating surplus could be expected by around 2029/30 with the operating surplus growing to just under $ 70k by 2032. The cumulative operating deficit over 20 years would be just under $ 3.0M, a significant improvement over the status quo case.  

Under  the  high  growth  scenario  (again  still  keeping  current  rates  and  charges),  an operating surplus could be expected as early as 2021/22 with the operating surplus growing to over $ 600k by 2032. In this case there would be a cumulative operating surplus over 20 years of close to $ 2.2M, again a significant  improvement over the status quo case, but over the medium case as well. 

Significantly raising the land sales rates and land lease rates by close to 50% (considered the true market value of airport  lands) and adjusting other  rates upwards more marginally provides a significant improvement in the case of the medium growth scenario, with the operating surplus eliminated by about 2021/22, with an operating deficit of close  to $ 150k by 2032 but with a cumulative operating deficit of over $ 1.3M. 

Extrapolating  for  a high  growth  scenario  (as  this was not modeled) with  revised  rates would indicate  that  an operating  surplus must be  achievable  several  years earlier  (about 2020)  and that the cumulative operating surplus over 20 years could approach $ 4M.          

This is all positive news, but when we add in the capital requirements as well, we find that in none of the scenarios can we cover the full capital costs of the airport. The table below summarizes this.   

 

 

 

COMPARISON Status Quo Medium Growth High Growth Medium GrowthBase Rates Base rates Base rates Revised rates

(Cumulative over 20 years)Opening Reserve in 2012 1,538,706$ 1,538,706$ 1,538,706$ 1,538,706$ Retained Earning (Ops) 4,924,690-$ 2,920,234-$ 2,226,070$ 1,307,924-$ Revenue from Land Sales 828,159$ 1,301,117$ 1,217,399$

Revenue from Development Levy 26,549$ Planned Capex (Development/Capacity) 5,152,496-$ 7,465,289-$ 5,152,495-$ Planned Capex (Maintenance) 7,429,585-$ 7,429,585-$ 7,429,585-$ 7,429,585-$

Projected Surplus / (Shortfall) 10,815,569-$ 13,135,450-$ 9,828,980-$ 11,107,350-$

NPV (Surplus / (Shortfall) 6,448,198-$ 8,656,543-$ 7,353,954-$ 7,483,970-$

PED-9-2013-4B

Page 25: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xxi

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

From this financial analysis we suggest the following lessons: 

Regardless of  the  financial scenario,  the airport will need  to continue  to contribute  in  the range of an average of about $ 500,000 per year into the airport reserve fund, much as it has been doing in past years;  

Considering  only  funding  shortfalls  for  the  airport,  the  status quo, whereby no money  is invested in expanding the airport facilities, but money is spent on maintaining those already existing,  is  a  feasible  option,  as  this  results  in  the  lowest  overall  NPV  of  the  scenarios actually modelled, and would be  similar  to  the projected best case NPV with high growth rates and increased land sale prices; 

Investing  in only modest expansion of the airport without adjusting current rates (many of which  are  too  low  in  absolute  terms,  but  also  too  low  in  comparative  terms with  other airports), does not appear to be as attractive as the status quo. 

Major  investments  in  additional  facilities  at  the  airport,  combined  with  aggressive  land development and  increases  in key  fees such as  land sales,  land  leases, among others, can pay  large dividends and  in  the end more  than pay  for  themselves, as  illustrated with  the projected NPV of a High Growth case with increased fees;  

Aggressive  land development and marketing, both of which can attract additional traffic to the airport, combined with appropriate  increases  in  fees charged across all aspects of  the airport’s  operations,  can  result  in  achieving  airport  operating  surpluses  as  early  as  2020, depending on the scenario;       

Any of the “investment” related options, would pay additional dividends to the community in  terms  of  the  economic  impacts  of  the  associated  investments, whereas  a  status  quo option would forgo the potentially significant economic spin‐off economic impacts of these investments, both on an  initial  investment basis, as well as continued contributions due to operations;  

A more aggressive  land sale policy should be considered as a means of  lowering the  initial capital investment shortfalls, as once many of these land development investments are well underway,  the airport should be  in position  to generate annual operating surpluses  (2020 +/‐).           

BUSINESS PLAN

The business plan comprises the following elements:  

The Strategic Direction; 

A Marketing Plan; 

An action Plan; and   

A financial plan. 

The District has continually re‐affirmed the strategic direction for the airport that it “….is a commercial General Aviation (GA) airport that promotes and supports the social and economic needs of the District of Muskoka”. 

Within this, the District must lay out a more detailed role statement together with goals and objectives, as well  as  identifying  key  success  factors  in  order  to  have  a more  consistent  vision  and measurable parameters with which to work.  

PED-9-2013-4B

Page 26: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xxii

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

On the marketing side, it is important to clearly identify: 

The target market for the airport; 

Understand how the 5 P’s of marketing should be applied; and 

Have an appropriate and very strong brand to use in the marketing of the airport. 

An  action plan must be developed  to  implement  all of  the  aspects of  the overall business plan. Key elements of the action plan should be as follows: 

SHORT-TERM (2013)

Approve development plan B‐R; 

Increase land lease and sales rates as well as the AMC; 

Confirm development intent of existing tenants and negotiate agreements 

Acquire land  to the east to permit grass runway relocation  

MEDIUM TERM (2014-2018)

Move to an Airport Commission operating structure; 

Reduce landing fee exemptions from 5 tonnes to 3 tonnes for based aircraft, and from 3 tonnes to 1 tonne for visiting aircraft 

Approve  a  new  one‐time  development  service  fee  similar  to  (but  slightly  less  than)  Lake Simcoe’s (waived for Phase 1 i.e., implement before 2019; 

Approve a new one‐time airport development permit fee similar to (but slightly less than) Lake Simcoe’s (waived for Phase 1 i.e., implement before 2019); 

Approve  a  new  one‐time  airport  development  levy  similar  to  (but  slightly  less  than)  Lake Simcoe’s (waive for Phase 1 i.e., implement before 2019) 

Develop  comprehensive  marketing  program,  including marketing materials  (brand  message, logo, print materials etc.), key messages, advertising plan,  

Implement  land development program on a phased approach  i.e.,  line up  customers prior  to developing the land 

With respect to the financial forecasts for the business plan,  it  is demonstrated that the most positive financial  scenario  would  be  to  aggressively  develop  and  market  new  commercial  lands.    To  be conservative however, the  financial targets/forecasts should be based on a medium development and traffic  scenario.  However,  additional  revenues  should  be  expected  to  be  achieved  through  a more aggressive land development timeline, complemented by aggressive marketing efforts.  

GOVERNANCE

The  airport  is  owned  and  operated  by  the District  of Muskoka.  The District  comprises  the  Towns  of Bracebridge, Gravenhurst, Huntsville, and the Townships of Georgian Bay, Muskoka Lakes and Lake of Bays.    The  airport  is  operated  (managed)  within  the  Planning  and  Economic  Development  (PED) department  of  the  District.    The  District  is  responsible  for  operating, marketing  and  developing  the airport.  This can be referred to as the Regional or District Model. 

 

PED-9-2013-4B

Page 27: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xxiii

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

The current governance structure is illustrated in the figure below.  

Airport  staff  report  through  the  Commissioner  PED who  reports  to  the  District  Chief  Administrative Officer  (CAO).  For  airport matters,  the  CAO  and  the  Commissioner  of  PED  report  to District  Council through the Planning and Economic Development Committee.  This PED Committee also receives advice from a 13 member Airport Advisory Committee  chaired by a District Councillor and  comprising other District  Councillors,  and  interested  community members  including  commercial  tenants,  local  pilots, among others. 

There are a variety of airport governance models, as follows:   

Local Government ownership and operation 

o Regional / District owns and operates (current situation) 

o Individual municipality owns and operates  

Local Government owns and independent not‐for‐profit organization operates 

o Airport Commission 

o Airport Authority 

Local Government owns and private sector operates 

Private sector owns and operates 

The particular models  in place at any specific airport tend to be as a result of both history and choice. Some key factors influencing the choice between the different models are: 

The degree of financial self‐sufficiency. Generally, governments do not like to provide capital or operating  financial  subsidies without  having  a  significant  say  in  how  the  airport  is managed. Accordingly more  of  the  smaller  airports  that  are  not  self‐sufficient  tend  to  be  government operated and more of the large airports have varying degrees of autonomy. 

Degree of autonomy.  There is a broad range of ownership models and the degree of autonomy in  decision making  is  equally  broad.  Autonomy  tends  to  be  closely  linked  to  financial  self‐sufficiency. 

District Council

CAO

Other Department s (HR, Legal, Finance, Engineering , trades, property management  etc.)

Airport Manager

Full Time Airport Staff

Planning & Economic Development (PED)

Airport Advisory Committee

Seasonal Airport Staff

Planning & Economic Development Committee

Airport purchases internal services from other departments

PED-9-2013-4B

Page 28: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xxiv

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Labour practices.  There can be significant differences in public sector and private sector labour practices, and this can influence the ownership model. 

There is no single structure that will best apply to the management and operation of municipal airports.  It is highly dependent on a number of factors, including: 

Scope and complexity of activities; 

Actual benefit derived by the municipality; 

Level of service decided upon; 

Interest in the community; 

Municipal organization itself; 

Number of participating municipalities; 

Influence of airport users; 

Willingness  of  volunteers  from  inside  and  outside  of  the  aviation  community  to  contribute, participate and serve on an advisory committee; 

Degree of cooperation among participants such as Tourism, Economic Development, Chambers of Commerce, etc.; and 

Entrepreneurial spirit / business orientation of airport management.  

Successful airports, regardless of ownership or operations structure are characterized by: 

 A strong commercial focus, with an emphasis on maximizing non‐aeronautical revenues; 

An entrepreneurial focus in the airport management team; 

A strong customer service focus; 

Effective links to the community; 

A commitment  to consultations and a partnership approach with aircraft operators and other key stakeholders; and 

Effective planning processes with publicly available planning documents. 

It is the consultant team’s opinion that the two most viable options for YQA are the Status Quo, and the creation of an Airport Commission. 

The status quo is working; however it is understood that opportunities are sometimes lost or stalled due to delays in the decision making process. 

Having  the  airport operated by  an  incorporated Airport Commission  could offer  the  following  added benefits: 

Subject matter experts  in the policy maker role. The Commissioner / Chairman would have an aviation background and would be dedicated to proactively promoting the airport; 

Broader representation from key stakeholder groups; 

The  planning  and  decision making would  be  put  in  the  hands  of  a  smaller  group, who  are subject matter experts with a  single  focus and not being pulled  in many directions. Decision making would be quicker and subject matter experts would not need to be brought up to speed on technical issues; 

PED-9-2013-4B

Page 29: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xxv

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

More commercial focus; 

Council being freed from external lobbying efforts; 

Council would continue to be represented  in the policy maker role, would still be  in control of budgets, and would be kept informed / updated regularly through formal reporting. 

The study team recommend that the District seriously consider moving to an Airport Commission model to operate the airport. To arrive at a final decision they should consult widely with other airports. They should  especially  consult  with  airports  that  have  moved  from  the  municipal model  to  the  Airport Commission model,  to  learn  from  their experience and  to gather valuable  insight  into  the conversion process.      

RECOMMENDATIONS

We make the following recommendations with respect to this study: 

LAND DEVELOPMENT PLAN

1. Land  development  at  the  airport  over  the  next  20  or  so  years  should  be  per  Plan  B‐R.  Key 

features of this plan are: 

a. Relocate the grass runway ; 

b. Carry  out  additional  surveys  to  determine what  length  of  runway might  be  possible 

without the need to purchase additional lands to the east, with the intent of achieving a 

runway of between 2,000 and 2,200 ft;  

c. If necessary, purchase land to the east of the grass runway to accommodate a length at 

least as long as the grass runway is today;  

d. Develop  the  west  part  of  the  area  vacated  by  the  grass  runway  into  a  9‐10  acre 

subdivision with a mix of large, medium and smaller lots;  

e. Develop  the east  lands  to  the  south of  the new grass  runway  into a new 25 acre +/‐ 

subdivision providing a mix of large, medium sized and smaller lots; 

f. Develop a number of lots along the north side of Beaver Creek Road for aviation or even 

non‐aviation related landside type uses (those not requ 

g. iring access to taxiways); 

h. Develop  lands  in  the area east of  the  threshold of Runway 18  for  covered  tie downs 

using Quonset hut type construction; 

i. Develop some area between  the parallel  taxiway and  the north end of Runway 18  for 

low‐cost, uncovered tie downs;   

j. Phase  the  land development  so  as  to meet  the  anticipated demand  in  a  just  in  time 

manner.  

2.  Over the very long term, the airport should consider mixed use of the lands located west of the 

airport between  the Gravenhurst Parkway and Highway 11. The key  features of  this very  long 

term plan would include the following: 

a. Relocation of  the Gravenhurst Parkway  to  the west  to provide  the primary means of 

access to the industrial lands located there; 

b. Designating the lands to the west for mixed industrial and aviation related uses; 

PED-9-2013-4B

Page 30: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xxvi

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

c. Closing portions of the current Gravenhurst Parkway and re‐purposing other portions to 

provide land access to both existing and new developments areas; 

d. Relocating the abandoned north portion of the current Gravenhurst Parkway alignment 

further west  to  accommodate  future development  all  along  a  future parallel  taxiway 

along the westside of the main runway (18‐36);  

e. Making provision for the potential extension of the crosswind runway (12‐30) further to 

the east, permitting a total length of some 4,500 ft +/‐.    

f. This long term plan should be revisited and better defined in the next 10 year update to 

this Master Plan or at such a time that any development proposals are brought forward 

to develop the lands to the west. 

INFRASTRUCTURE PLAN  

3. Pave the grass runway  initially to about 2,000 ft or whatever  length may be possible given the 

constraints of the lands to the east.    

4. Give consideration to paving the new runway  (12‐30) to a  length of about 2,800  ft  in order to 

provide better accessibility to and usability of the airport for smaller aircraft that cannot sustain 

higher  crosswind  components  and  to make  the  airport more  attractive  to wider  spectrum of 

users.  This  should  be  done  sooner  rather  than  later,  but we  acknowledge  it will  be  a  policy 

decision based on availability of funds and a variety of other considerations. 

5. Implement  LPV  approaches  to  the main  runway  to  improve  the  reliability  of  airport  access, 

install RILS on the runway to aid pilots on approach and install a PAPI on Runway 36 to improve 

the safety of this approach;   

6. Protect for the eventual extension of the parallel taxiway to 18‐36 all the way to the south; 

7. Reserve  sufficient  space  for a  terminal area apron expansion  to both  the north and  south  to 

accommodate both forecast growth in aircraft parking and potentially unforeseen growth; 

8. Reserve sufficient space for a terminal building expansion and associated car parking area.; 

9. Develop a more detailed major maintenance and repairs plan; 

10. Test alternative airport café/restaurant concepts.  

FINANCIAL PLAN  

11. The  airport must  ensure  that  land  sales  through  its  land  sale  policy  are  properly  valued.  To 

ensure this, the airport must work with  local appraisers to ensure that they better understand 

the true value of airport lands. 

12. The airport  should  implement a  series of  supporting  fees and  charges  that are  similar  to but 

lower than competitors  like Lake Simcoe. These  fees could  involve development permit  levies, 

development service fees, etc.  

13. The airport should consider  increasing other fees as well,  including the AMC and others. These 

fees  should be  constantly  reviewed against  the  competitor airports and adjusted accordingly, 

with the goal being to maximize the airport’s revenues. 

14.  The airport  should aggressively pursue  land  sales as a means of attracting additional  tenants 

and to raise the necessary funds to pay for the various expansions.  

PED-9-2013-4B

Page 31: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page xxvii

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

BUSINESS PLAN  

15. While the current airport logo and brand appear to be strong, consideration should be giving to 

reviewing  this  to  see  if  this could be enhanced  to better  reflect a more aggressive marketing 

approach for the airport. 

16. The business plan for the airport should be based on conservative targets and assumptions with 

respect  to  growth  and  land development, but  at  the  same  time  the  airport  should  pursue  a 

much more aggressive approach that can pay much stronger dividends.  

GOVERNANCE  

 

17. We recommend that the District seriously consider moving to an Airport Commission model to 

operate the airport. To arrive at a final decision they should consult widely with other airports. 

They should especially consult with airports that have moved from the municipal model to the 

Airport Commission model,  to  learn  from  their experience and  to gather valuable  insight  into 

the conversion process.  

PED-9-2013-4B

Page 32: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 1

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

1.0 INTRODUCTION

1.1 BACKGROUND

In 1996 when  the Muskoka Airport was being  transferred  to  the District of Muskoka, a Business and Marketing Plan was prepared by  LPS Aviation  Inc.  It  identified  short  term objectives and a  long  term vision  for  the  airport.  That  report  also  examined  governance  options,  management  approaches, infrastructure conditions and needs, operational  requirements, and marketing approaches. Aspects of the  Business  and  Marketing  Plan  were  updated  in  2003  to  include  more  detailed  marketing  and branding strategy and  in 2006 to reaffirm the vision and develop updated short term objectives given new regulatory requirements and upgrades in infrastructure and operations.  

The Business and Marketing Plan was  followed by  the preparation of an Airport Master Plan  in 1999. The Master Plan was also prepared by LPS Aviation  Inc. and had a 15 year time horizon. This plan was prepared after consultation with aviation and community stakeholders and included an aviation activity analysis,  a  review  of  the  Airport  facilities,  an  assessment  of  deficiencies  and  requirements,  and  a development and land use plan.  

Since the preparation of the above noted reports, many changes to infrastructure and operations have occurred  at  the Muskoka  Airport.    A  land  sale  policy was  developed  in  2000, which  resulted  in  the subsequent  sale of 9  lots  for aviation‐related businesses. Several other  lots and  tie‐downs have been leased. New  infrastructure  improvements  include  the  renovation of  the Airport  terminal building and the  additional  of  the  Little Norway Memorial,  expanded  aprons  and  taxiways,  new  runway  lighting, enhanced security  features  (e.g.  fencing and wildlife plan), and new storage  facilities.  In addition,  the District of Muskoka now operates the Imperial Oil facility (FBO). 

More recently,  in response to an  increasingly  limited supply of development ready  land at the airport, each of the development area options identified in the 1999 Airport Master Plan were reviewed through a Background Report to the Muskoka Airport Development Plan (2011). A detailed  investigation of the Eastside Development Area was recently carried out and just completed prior to the commencement of this current study.  

Since  the  original Master  and  Business  and Marketing  plans  are  reaching  the  end  of  their  expected timeframes and  in consideration of  the many changes undergone at  the Airport  since  the documents were prepared, the District of Muskoka decided it was time to prepare a new Business and Master Plan for the Muskoka Airport. 

1.2 DESCRIPTION OF PROJECT

The new Business and Master Plan to be developed as part of this study will guide the development and operation of the Muskoka Airport for the next 15‐20 years. This plan will replace the existing Business and Marketing Plan  (1996) and  the Airport Master Plan  (1999).  It will  review  the current state of  the Muskoka Airport and make recommendations on how the District can capitalize on existing assets and opportunities to enhance the business and operation of the airport.  

The project includes an examination of: 

5. The airport business operation and financial status, potential, needs and requirements; 

6. Airport infrastructure and facilities, needs and requirements; 

7. Aviation business development, development area expansion and potential  land acquisition; and 

PED-9-2013-4B

Page 33: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 2

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

8. Airport governance.  

1.3 DETAILED REQUIREMENTS AND SCOPE

A more detailed list of the requirements and the specific scope of this project is provided below:  

1. The Business and Master Plan will: 

a. Make  recommendations with an associated business case  to capitalize on  the existing assets at the Muskoka Airport; 

b. Identify  business  or  service  changes  that  will  enhance  the  financial  position  and operation of the Airport and provide for sustainability; 

c. Identify infrastructure and instrument procedure  improvements that would benefit the Airport operation, business and financial position; 

d. Identify  the  potential  of  Runway  09/27  to  contribute  to  the  growth,  development, safety and financial position of the Airport and to benefit Muskoka municipalities; 

e. Identify the timelines and triggers for any recommended changes; 

f. Identify the financial resources and implications for the Airport Capital Budget required to implement the changes and determine the feasibility of such changes; 

g. Review the development area options planning undertaken to date including the design and  engineering  work  for  the  eastside  development  initiative  and  make recommendations respecting: 

i. Implications related to existing and potential infrastructure improvements; 

ii. Phasing of development; 

iii. Resources  (both  financial  and  operational)  needed  to  support  future development; and 

iv. Future development options.   

h. Identify any abutting  land  that  should be acquired  to  implement any of  the proposed changes with an associated business case; 

i. Provide an updated Master Plan map with phasing for the Airport; and 

j. Evaluate the effectiveness of the current governance model for the Airport.  

2. In addressing the above, at a minimum, the following questions are to be answered: 

a. What is the current state of the Muskoka Airport, including: 

i. Current function and character of the operation; 

ii. Existing businesses; 

iii. Existing facilities, infrastructure and services; 

iv. Patterns  of  activity  and  use  (e.g.  primary  users,  non‐aviation  and  community use, aircraft movements, seasonality, land use); 

v. Existing  constraints  (environmental,  topographical,  business,  social,  etc)  that affect the airport operation or potential; 

vi. General costs and revenue sources; and  

PED-9-2013-4B

Page 34: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 3

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

vii. Deficiencies. 

b. Are the vision and objectives for the airport still relevant? If not, what should the vision and objectives be for the Muskoka Airport? 

c. How does the Airport fit into the transportation system in Muskoka? What value does it provide to the region and the municipalities within the District of Muskoka? 

d. How  does  the  Airport  compare  to  other  airports  of  similar  size  and  function? What changes  could  the  District  of Muskoka make  to  be more  competitive  and  financially sustainable? 

e. What  are  the  regulations  and  requirements  that  provide  a  framework  for  Airport operation  and  development?  What  planning  criteria  should  be  used  for  new development taking into account any emerging regulations and requirements? 

f. What are the challenges and constraints that would affect development at the airport? 

g. Based on the current function and status of the Airport, what are the opportunities that make  sense  for  the  operation  and  development  of  the  Muskoka  Airport?  More specifically: 

i. Based  on  trends  in  aviation,  tourism,  and  the wider  economy, what  are  the opportunities  and  challenges  for  growth  and  business  development  that will affect the Muskoka Airport?  

ii. What businesses exist at the Airport and what potential  is there  for expansion or attraction of new aviation and non‐airside aviation space businesses?   

iii. What is the benefit of Runway 09/27 and what potential does this runway have to  contribute  to  growth,  development  and  financial  position  at  the  Airport? What improvements should be considered and what would be the timeline with triggers  for  implementation? What  financial  resources would  be  required  to undertake those  improvements and  is there a business case to undertake such improvements? 

iv. After  reviewing  the  background  to  the  proposed  eastside  development initiative,  are  there  any  opportunities  or  constraints  that  have  not  been identified? How should the development of this area proceed?  

h. To  capitalize  on  the  existing  assets  of  the  Airport,  what  infrastructure,  business,  or service changes or improvements are technically feasible and financially viable in order to enhance operations? What would be required and what would trigger such changes? What financial resources would be necessary to implement the changes and what is the business case for such investment? What benefits would be expected? 

i. How can the Airport increase and improve its revenues and financial status so that it can become financially sustainable?   

1.4 STUDY APPROACH

The study was undertaken through a number of key tasks as follows:  

Review of past studies, current facilities, and historical and current traffic patterns; 

Assessment of current operations, including management, financial and governance; 

PED-9-2013-4B

Page 35: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 4

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Stakeholder consultation; 

Review of airport vision, and objectives; 

Forecasting  of  future  activity,  potential  opportunities  and  associated  infrastructure requirements; 

Preparation and assessment of  alternative airport development options; 

Interim Presentation  to  the Planning  and Economic Development Committee and  the Airport Advisory Committee; 

Development of a Financial and Business Plan for the Airport 

Discussion  of  future  airport  governance models  and  associated  recommendations  on  future governance  

Preparation of a draft report documenting all of the findings of this study 

Final  Presentation  to  the  Planning  and  Economic  Development  Committee  and  the  Airport Advisory Committee of the draft report; 

Finalization of all of the study work into a final report.  

Early  into the study,  it became quite clear that there were a  lot of divergent views among the various committee members,  airport  stakeholders,  users,  etc,  as  to what  direction  the  airport  should  take, whether  this  be  related  to  development,  operations,  facilities,  governance,  finances,  etc.  As  a consequence,  it was decided that an extensive stakeholder consultation process would be undertaken with the various stakeholder groups. Stakeholders consulted and the method these were consulted are as follows:  

General Public – through on‐line surveys; 

Tenants and Businesses  ‐   through face to face  interviews, over the phone and through an on‐line survey; 

Incoming Pilots – in person interviews on the ramp; 

Incoming Visitors ‐ in person interviews on the ramp; 

Economic Development and Tourism Staff – via emailed surveys; and 

Elected Officials ‐ over the phone surveys. 

1.5 REPORT ORGANISATION

The work carried out as part of this study is organised and presented in a number of sections as follows: 

SECTION 2: CURRENT SITUATION

This section presents the current situation at the airport and deals with topics such as: 

Existing Infrastructure and facilities; 

Current air traffic at the airport;  

The  airport’s financial situation; 

A comparison with other competing airports in the area; 

PED-9-2013-4B

Page 36: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 5

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

The results of the stakeholder consultation program; and 

A summary of the current conditions.  

SECTION 3: FUTURE OPPORTUNITIES, FORECASTS AND FACILITY REQUIREMENTS

In this part of the report we deal with the following: 

Airport Vision and objectives; 

Future opportunities for the airport; 

Forecast air traffic activity; 

Forecast facility requirements.  

Subsequent sections document the following: 

SECTION 4: DEVELOPMENT PLAN

SECTION 5: FINANCIAL ASSESSMENT

SECTION 6: BUSINESS PLAN

SECTION 7: GOVERNANCE. AND

SECTION 8: RECOMMENDATIONS

 

   

PED-9-2013-4B

Page 37: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 6

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

2.0 CURRENT SITUATION

2.1 LOCATION AND CONTEXT

The Airport  is  located along Highway 11 within  the District of Muskoka. The airport  is  located nearly midway  between  the  towns  of  Gravenhurst  and  Bracebridge,  but  is  actually  within  the  town  of Gravenhurst. The airport  lands encompass an area measuring approximately 223 hectares (550 acres).  The  shape  of  the  property  follows  the  configuration  of  the  runways  with  a  northward  extension surrounding the main runway and short eastward and westward extensions surrounding the turf runway at the south end of the property.  The northern and western perimeters are demarcated by Highway 11 and  the  Gravenhurst  Parkway, while  the  eastern  and  southern  boundaries  lie  adjacent  to  privately owned land and the Beaver Creek Institution, respectively.  

Figure 2‐1: Airport Location 

 

2.2 EXISTING INFRASTRUCTURE AND FACILITIES

ELEVATION

The elevation of the airport varies from 277.06m (909ft) ASL at the north end of the property (at threshold of Runway 18) to 281.03m (922ft) ASL at the south end (at threshold of Runway 09). 

Muskoka Airport 

PED-9-2013-4B

Page 38: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 7

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

TOPOGRAPHY AND VEGETATION

Airport lands lie on a glacial lake (glaciolacustrine) deposit with some exposed bedrock.  The topography is relatively flat along the main runway, but rises to high points north of the terminal building and west of the turf runway, which are characterized by rock outcrops.  Lands to the east and south of the airfield generally lie at lower elevations.    

The vegetation on airport property and surrounding lands consists of a mix of coniferous and deciduous trees.   Ground cover on the airfield consists of grass.   Gravel pits are  located at the southern and east central sections of the property.  

Surrounding terrain consists of rolling terrain with rock outcroppings and wetlands scattered throughout, including Wright Lake located east of the airport.   

OBSTACLES AND AIRPORT ZONING

Airport zoning regulations are in place for the airport (see Appendix C).  These regulations are required to  maintain  an  obstacle  free  airspace  in  the  vicinity  of  a  certified  airport.    They  protect  aircraft operations at  the airport,  including approaches,  take‐off and  landing operations, and also ensure  that potential and future development of adjacent non‐airport lands are compatible with the airport. 

Zoning  for Runway 18‐36 protects  for a non‐precision reference Code 3 runway strip measuring 150m (492 ft) in width ( 75 m (246 ft) being on each side of the centre‐line of the runway).  It is noted that in the AOM, Runway 18‐36  is certified as a 3C non‐precision runway, yet the width of the runway strip  is given as 91.4 m  (300  ft)  in width, which corresponds with a non‐instrument reference Code 3 runway strip. This  is a  temporary  change due  to a number of  trees  that are  located  to  the northwest of  the airport on private  lands and the airport has not been able to gain access to trim these. However,  it  is recommended  that  the  airport  continue  to protect  for  a 150 m  (492  ft) wide  runway  strip  to match current zoning  in place, for that point  in time that the trees on private property  issue gets resolved. In any case, this is not an urgent issue to resolve as the current instrument procedures with limits of 502+ft limit the airport to non‐instrument status anyway (see following discussion).    

Vehicles using Highway 11 represent obstacles on the approach to Runway 18.  In order to ensure non‐infringement of the approach surface to Runway 18 by all vehicle heights, the threshold is displaced by 243.8 m (800 ft).  

INSTRUMENT APPROACH PROCEDURES

There are 3 instrument approach procedures for the airport, with approach limits as follows (see Appendix D for approach diagrams): 

RNAV (GNSS) Runway 18: 

o The LNAV approach has limits of 505 ft and 1 ½ mi visibility for all aircraft categories; 

o The circling approach has limits of 518 ft for category A to C aircraft and 618 ft for 

category D aircraft, with visibility limits of 1 ½ mi for A/B categories and 2 mi for C/D 

aircraft. 

RNAV (GNSS) Runway 36: 

o The LNAV approach has limits of 502 ft and 1 ½ mi visibility for all aircraft categories; 

o The circling approach has the same limits as the above circling approach.  

NDB A (GNSS) Runway 18: 

PED-9-2013-4B

Page 39: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 8

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

o This procedure has only a circling approach  with limits of 538 ft  for category A to C 

aircraft and 618 for category D aircraft, with visibility limits of 1 3/4 mi for A/B 

categories and 2 mi for C/D aircraft.  

METEOROLOGY

Meteorological records published by Environment Canada  for Muskoka are based on data collected at the airport’s weather station over a 30 year period starting in 1971.   

TEMPERATURE

The average daily temperature is +4.9o C with the hottest month occurring in July and the coldest month in  January.    The  aerodrome  reference  temperature  is  24.2o  C.    This  represents  the  average  of  the maximum daily  temperature  for  the hottest month of  the  year  and  is of  relevance  in determining  a suitable runway length for aircraft take‐offs and landings.   

WINDS

Year‐round winds prevail from the west and northwest and can be expected most often in the summer and northwest winds in the fall and winter.  The maximum gust recorded was in October 1973, when a gust from the west measured 68 knots (126 km/hr). 

A  feasibility  study  for  relocation  of  the  crosswind  runway  (Crosswind  Runway  Relocation  Feasibility Study completed by Genivar in 2011) noted that during daylight summer hours during the period 1990‐2008, nearly 85% of all winds were less than 10 knots.  Winds over 10 knots, were predominantly from the northwest and southeast.   

The  characteristics of wind play  a determining  role  in  the number  and orientation of  runways  at  an airport.  Transport Canada recommends that the number and orientation of the runways should ensure that there is at least one runway available for the aircraft the aerodrome is intended to serve 95% of the time (more discussion is provided on this in section 3.4). 

VISIBILITY

Visibility is generally clear and favours operation of aircraft by Visual Flight Rules (VFR).  According to the previous Muskoka Master  Plan, VFR  visibility  conditions were  recorded  92.5% of  the  time.   Visibility conditions  defining  Instrument  Flight  Rules  (IFR),  in which  cloud  ceiling  is  below  304.8 m  (1,000  ft) and/or visibility is below 4.6 km (3 miles) were recorded 7.5% of the time.   

Apart from determining which type of flight rules applies for the operation of aircraft, visibility plays an important role in determining which type of visual aids to provide at an airport.  As an example, visibility conditions defining IFR requires the use of approach lighting aids.  This is addressed under the section on airfield lighting. 

PRECIPITATION

On average, during the year there are 122.9 days with more than 0.2 mm of rainfall and 80 days with more than 0.2 cm of snowfall.  This data is useful in estimating the use of snow removal equipment and the occurrence of runway contamination.    

2.3 ASSET ASSESSMENT

Assessment of airport facilities and infrastructure is based on Transport Canada standards and recommended practices for airport design and land use at and in the vicinity of airports.  Proposed 

PED-9-2013-4B

Page 40: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 9

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

changes to Transport Canada’s aerodrome standards (TP312 4th edition), were not available at the time of preparation of this report.  

An inventory of facilities and infrastructure is based on the site visit conducted on July 31st and August 1st , 2012 and consultation with airport staff, officials from the District of Muskoka and airport tenants.  Valuable information was also obtained from the following sources: 

Airport Operations Manual for Muskoka Airport dated September 7, 1988 and amended September 6, 2005; 

Muskoka Airport Master Plan dated September 1999; 

Muskoka Airport Pavement Re‐Evaluation – Runway and Apron Surfaces dated October 11th, 2011; 

Muskoka Airport Layout (Infrastructure map with contours) dated November 14th, 2011; 

Nav Canada ‐ Canadian Airport Charts dated November 15th, 2012; 

Nav Canada ‐ Canada Flight Supplement dated November 15th, 2012; and 

Nav Canada – Canada Air Pilot November 15st, 2012. 

The assessment is divided into five sections: 

Airfield; 

Building structures; 

Fuelling facilities and airport vehicles; 

Groundside facilities; and 

Utilities and site servicing. 

AIRFIELD

DESIGN AIRCRAFT

The  Airport Operations Manual  (AOM)  identifies  the  de Havilland Dash  8  (reference  Code  C)  as  the design aircraft  for  the primary  runway.   The airport’s 1999 master plan  lists  the B737‐200  (reference Code C) as the critical aircraft.  Reference Code C aircraft are those aircraft with a wingspan measuring 24 m (78.7 ft) up to but not including 36 m (118.1 ft) and an outer main gear wheel span measuring 6 m (19.7 ft) up to but not including 9 m (29.5 ft).  Examples are listed in Table 2‐1.  The DHC‐8‐400 (Q400) differs from other Dash 8 aircraft in that its outer main gear wheel span, 9.54 m (13.3 ft), falls within the wheel span  range of  reference Code D aircraft  (measuring 9 m  (19.7  ft) up  to but not  including 14 m (45.9 ft). This wheel span dimension is important in determining the width of taxiways.  

The airfield can accommodate reference Code C aircraft larger than the de Havilland Dash 8 and B737‐200,  including  jet  aircraft  such  as  the A320  and  B737‐700.    Runway  18‐36  offers  sufficient width  to accommodate  larger aircraft and  is  frequently used by  the Lockheed C130  (reference Code D aircraft) according to tower records of aircraft movements. 

More discussion on the design aircraft is provided in section 3.4 dealing with future requirements.    

PED-9-2013-4B

Page 41: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 10

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

RUNWAYS

The airport has 2 runways: 18‐36 and 09‐27. The layout of the airport site is illustrated in Figure 2 ‐2. 

Table 2‐1: Aircraft by Reference Code 

Aircraft  Wing span (m) 

Outer Main Gear Wheel Span (m) 

Engine Type  Maximum Take‐off 

Weight (kg) 

Operators in Canada 

HS748  31.23  ‐  Turboprop  23,133  Calm Air 

ATR 42‐300  24.57  4.68  Turboprop  16,700  Calm Air, First Air 

ATR 72  27.05  4.66  Turboprop  22,500  First Air 

DHC‐8‐100 (Q100)  25.89  8.49  Turboprop  16,466  Air Canada‐Jazz 

DHC‐8‐300 (Q300)  27.43  8.42  Turboprop  19,500  AC‐Jazz 

DHC‐8‐400 (Q400)  28.40  9.54  Turboprop  29,257  AC‐Jazz, WestJet 

Convair 580  32.12  8.52  Turboprop  25,855  Nolinor 

CRJ705/900  24.85  4.99  Jet  38,329  Air Canada‐Jazz 

Embraer 175  26.00  6.31  Jet  38,790  Air Canada 

Embraer 190  28.72  7.22  Jet  51,800  Air Canada 

Airbus A319  34.10  8.95  Jet  75,900  Air Canada 

Airbus A320  34.10  8.98  Jet  77,400  Air Canada 

Boeing 737‐200  28.35  6.36  Jet  58,105  First Air, Nolinor 

Boeing 737‐600  34.32  6.99  Jet  65,544  WestJet 

Boeing 737‐700  34.32  6.99  Jet  70,080  WestJet 

Boeing 737‐800  34.32  7.00  Jet  79,016  WestJet, Sunwing 

RUNWAY 18-36

Runway 18‐36 is the airport’s primary runway facing north at 001o (36) and south at 181o (18).  It has a length of 1,829 m (6,000 ft) and width of 45 m (147.6 ft), and is certified as a reference code 3C runway in the AOM.   The threshold of Runway 18  is displaced by 243.8 m (800 ft) to avoid penetration of the approach surface by vehicles travelling on Highway 11.   

The  runway  is  equipped  with  lighting  for  day  and  night  use  plus  non‐precision  approaches,  which enables  aircraft  to  conduct  approaches  under  certain  low  visibility  conditions.    The  runway  has GPS approaches with limits of just 500 ft (152 m) and 1.5 miles (2.4 km) horizontal visibility to both ends plus NDB approaches with  similar  limits.   Based on meteorological data described earlier,  these  limits are exceeded approximately 5% of the time, so that the runway  is not available due to ceiling or visibility during these periods.  Paved with asphalt, the runway is available for use during the winter months.  The runway has a slight longitudinal slope of 0.15% rising 2.7 m (9 ft) from the north threshold to the south threshold.    The  pavement  load  rating  (PLR)  of  9  permits  the  operation  of  aircraft  weighing  up  to 90,270kg (200,000lb).  This is suitable for supporting some reference Code D aircraft at maximum take‐off weight, such as the Lockheed C130 (MTOW of 79,379kg) and others at reduced weights, such as the B757‐200. 

Runway  18‐36  dates  back  to  the  1950s  replacing  two  of  the  airport’s  turf  runways  that  had  been constructed in the 1930’s as part of the airport’s original triangular three‐runway configuration.  During the 1950’s, the runway was expanded and paved by the Department of National Defence with runway lighting added before  the end of  the decade.   Resurfacing of  the  runway was completed  in 1980 and 1994, when a reduced width overlay was installed.   

 

PED-9-2013-4B

Page 42: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 11

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Figure 2‐2: Airport Layout  

 

 

PED-9-2013-4B

Page 43: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 12

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

In 2011, Exp Services carried out a pavement re‐evaluation of the runway and apron surfaces.   In their report, they rated the pavement in fair to good condition describing it as generally old asphalt pavement with underlying granular layer.  Other notable observations included the following: 

Frequent to extensive block cracking and open paving joints; 

Low severity dips and bumps in a few areas on the southern half of the runway; 

Low severity rutting in a few isolated areas; 

Some grass growing in the cracks near the edges of the runway at the north end; 

Poor to fair surface drainage to the gravel strip area to the east and at the south turn‐around area. 

The  report  concluded  that  the  pavement  would  continue  to  deteriorate  and  recommended rehabilitation  by  2015  through  careful  monitoring  and  maintenance.    A  new  asphalt  surface  was recommended using Cold‐In‐Place Recycling described in further detail in the report.    

Runway 18‐36  is a valuable asset to the airport as the  length and pavement  loading rating are suitable for  the operation of a range of aircraft  including narrow‐body  jets such as  the B737 and A320.   Some reference code D aircraft such as the B757‐200, could operate at the airport, but would suffer take‐off weight limitations due to the runway length. 

It  is  recommended  that  the  airport  carry  out  the  rehabilitation  of  the  pavement  as  advised  by  Exp Services, though as noted later in the report, the airport may wish to consider lower cost alternatives to rehabilitating this pavement, if available at the time. 

RUNWAY 09-27

Runway 09‐27 is the airport’s crosswind runway facing east at 090o and west at 270o.  It measures 670 m (2,199  ft)  in  length  and 30 m  (100  ft)  in width  and  is  certified  as  a  reference  code 1A  runway.    The runway  is  only  equipped  for  day  use  (runway  edge  and  threshold  markers)  and  non‐instrument approaches, which restricts aircraft to approaches during good visibility conditions.  The runway surface is turf and has limited availability during the winter months.  The threshold at Runway 09 is 2.01 m (6.6 ft) higher than at the threshold of Runway 27, which yields a minimal runway slope of 0.3%.  Due to the runway’s short length, aircraft accommodated are limited to light single and twin engine aircraft, such as the Cessna 172 and Piper PA‐31 Navajo.   

Runway 09‐27 has  the primary  role of  serving  light  single and  twin engine aircraft  that are  restricted when crosswind components exceeding 10 knots occur on Runway 18‐36.   

Runway 09‐27  is also situated on top of a  large gravel deposit.   Highlighted  in the 1999 airport master plan as a potential source of revenue for the airport’s reserve fund, extraction of gravel has taken place and an open pit is situated south of the runway strip in close proximity to the threshold of Runway 09.   

The runway is currently used by the local flying school and light aircraft owners and accommodated 2% of  itinerant movements  in  2011.    The  runway  is  in  good  condition with  the  following  observations recorded during the site visit: 

Close proximity of open gravel pit to runway strip at west end of the runway; 

No evidence of water erosion; 

Bumpy surface noted by pilots. 

PED-9-2013-4B

Page 44: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 13

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Options to dealing with this runway in the future are discussed in sections 3‐4 – future requirements and sections 4‐1‐ the development plan. 

TAXIWAYS

The airfield is equipped with several taxiways, some of which are private and others comprising part of the  airfield.    Three  taxiways  are described  in  the AOM  and published  in NavCanada’s  airport  charts. Their location is illustrated in Figure 2‐2: 

Taxiway Alpha; 

Taxiway Bravo; and 

South Apron Taxiway. 

TAXIWAY ALPHA

Taxiway  Alpha  provides  a  connection  between  Runway  18‐36  and  a  partial  parallel  taxiway  serving airport tenants at the north end of the property.  Located approximately 160 m (525 ft) from the end of Runway 18,  it measures 121 m (397 ft)  in  length and 15 m (50 ft)  in width and  is  listed as a reference Code B taxiway in the AOM.  The width, however, is sufficient to accommodate reference Code C aircraft with a wheel base less than 18m.  Paved with asphalt, the pavement has a PLR of 9 under 0.5 MPa tire pressure.  The taxiway was originally built as an asphalt paved taxiway in 1983. 

Taxiway Alpha plays a significant  role  for north  field  tenants as  it permits aircraft  to exit or enter  the runway closer to the displaced threshold of Runway 18 and reduces the length of runway used for back‐tracking.  It is in good condition.  

It is recommended that the airport protect this taxiway to reference Code C standards to accommodate the  future  role of  the  taxiway as part of a  reference Code C  taxi  route between Runway 18‐36 and a future full length parallel taxiway to the South Apron. 

TAXIWAY BRAVO

Taxiway Bravo provides a connection between Runway 18‐36 and the above‐mentioned partial parallel taxiway  that  serves  airport  tenants  at  the north end of  the property.    Located  approximately 886 m (2,906 ft) from the end of Runway 36 (or nearly midway along the length of this runway), it measures 76 m (249 ft) in length and 22.9 m (75 ft) in width and is listed as a reference Code B taxiway in the AOM.  This  coding  is based on  the  fact  that  Taxiway Bravo  connects  to  the parallel  taxiway which  varies  in width  from  15.2m  (50ft)  in  the  older  original  section  to  10.7m  (35ft)  at  both  the  north  and  south sections.  Since aircraft could use any one of these taxiway sections, the Code B designation protects for the  most  limited  width  (10.7m/35ft).    The  width  of  Taxiway  Bravo,  however,  is  sufficient  to accommodate reference Code C aircraft with a wheel base  less than 18 m (59 ft).   Paved with asphalt, the taxiway was designed to meet a PLR of 9 under 0.5 MPa tire pressure and built in 2003. 

Taxiway Bravo plays a significant role for all users as it permits aircraft to exit or enter the runway closer to the mid‐point of Runway 18‐36 and reduces the length of runway used for back‐tracking to the main apron or north field aprons.  It is in good condition.  

It is recommended that the airport protect the taxiway to reference Code C standards to accommodate the  future  role of  the  taxiway as part of a  reference Code C  taxi  route between Runway 18‐36 and a future full length parallel taxiway to the South Apron. 

PED-9-2013-4B

Page 45: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 14

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

SOUTH APRON TAXIWAY

The South Apron Taxiway connects the threshold of Runway 36 with the South Apron, which serves the terminal building.    It measures 60m  in  length and 90 m  in width and  is  listed as a  reference Code C taxiway in the AOM. 

Paved with asphalt, the taxiway was included in the pavement re‐evaluation completed by Exp Services in 2011.  In their findings, Exp Services highlighted the following deficiencies: 

Frequent to extensive block cracking with most sealed; 

Narrow low severity depressions along some cracks; 

Very slight rolling/uneven surface; and  

Poor surface drainage to perimeter grassy areas. 

Rehabilitation of the taxiway is recommended as described above for Runway 18‐36. 

PARALLEL TAXIWAY

The parallel  taxiway  is described  in the 1999 airport master plan as a “new 355‐metre extension with unknown aircraft load rating constructed in 1998” and is illustrated connecting to Taxiway Alpha.  That section of the taxiway that connects with Taxiway Alpha was originally constructed  in 1983 measuring 15.2m  (50ft)  in width.    In 1998,  the  taxiway was extended  southward and  constructed  to a width of 10.7m (35ft).    In 2010, the taxiway was extended towards the north to connect with the north end of Runway 18‐36 (north of displaced threshold).  This extension was paved with asphalt and constructed to a width 10.7m (35ft).  The taxiway currently measures 885 m (2,904 ft) and its separation from Runway 18‐36  varies  from  102.6 m  (337  ft)  at  Taxiway  Bravo  to  151 m  (495  ft)  as measured  from  taxiway centreline  to  runway  centreline.    This  exceeds  the  93 m  (305  ft) minimum  separation  between  the taxiway centreline and runway centreline recommended by Transport Canada  for taxiways and a non‐precision reference Code 3C runway. 

The parallel taxiway also plays a significant role for mid‐field and north field tenants as it serves as a taxi route  for  arriving  and  departing  aircraft  and  reduces  runway  occupancy  time  associated with  back‐tracking on the main runway. It is in good condition.  

It is recommended that the land between Taxiway Bravo and the South Apron be reserved for the future extension of  the  taxiway southward  to  the South Apron  to  reduce  runway occupancy  time associated with back‐tracking on Runway 18‐36. 

SOUTH TAXIWAY AND GRASS TAXIWAY

A paved taxiway connects the South Apron (terminal apron) with tenant facilities south of the terminal building and  leads  to a grass  taxiway, which,  in  turn, provides access  to  the  threshold of Runway 09.  Although not  listed  in  the AOM, during  the  site  visit,  the  routing of  the  taxiway was  identified with pylons between the  South Taxiway serving Muskoka Aircraft Refinishing hangars and Runway 09‐27.   

APRONS

Three aprons are listed in the AOM and illustrated in Figure 2‐2, as follows: 

PED-9-2013-4B

Page 46: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 15

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

SOUTH APRON

The South Apron is located adjacent to the terminal building west of the threshold of Runway 36.  The eastern section of the South Apron was constructed in 1951 and expanded towards the west in 1980 for a total area measuring 90 m (295 ft) by 95 m (310 ft).   A new section measuring approximately 126 m (413 ft) by 95 m (310 ft) was added in 2006 with a PLR of 9, which matches the PLR of Runway 18‐36 and the  South Apron  taxiway.    The  original  section  of  the  South Apron was  re‐surfaced  in  1994  and  re‐evaluated by Exp Services in 2011, which identified the following deficiencies: 

Frequent to extensive block cracking, most sealed; and 

Narrow low severity depressions along most joints and cracks. 

The  South  Apron  represents  the  airport’s  primary  apron  serving  the  air  terminal  building,  fuelling facilities and the Ministry of Natural Resources’s hangar.  It also serves as a taxi route between the south field  tenants and Runway 18‐36.   The apron  is heavily used during  the peak summer months  for  long term and  short  term parking of aircraft and often  reaches  capacity depending on  the  size of aircraft parked and  the duration of parking.   The airport currently uses a pavement marking scheme  to assist pilots to taxi in and out of the apron without conflicting with parked aircraft. 

Rehabilitation of the original section of apron is recommended as described above for Runway 18‐36. 

PRIVATE SOUTH APRON

The Private South Apron  is owned by a tenant, Muskoka Aircraft Refinishing, who occupy airport  lands south of the terminal building. Located west of Runway 18‐36 and south of the terminal building,  it  is accessed via the South Taxiway.   Serving private hangar facilities, the apron measures 36 m (118 ft) by 85.5 m (280.5 ft) and is paved with asphalt. 

PRIVATE CENTRE APRON

The Private Central Apron  is  located west of Runway 18‐36 and accessed  from Taxiway Alpha and the partial parallel taxiway.  The apron serves private hangar facilities. 

TIE-DOWN PARKING AREAS

The airport offers tie‐down facilities for parking of light aircraft.  A total of 10 pavement‐edge tie‐downs are  located on the South Apron on the west and east  facing edges north of the terminal building.   An additional 12 tie‐downs are located on a grass parking area east of the South Taxiway serving Muskoka Aircraft Refinishing. 

AIRFIELD LIGHTING

RUNWAY LIGHTS

Runway 18‐36 is the only runway equipped with intensity lighting (all medium intensity) as follows: 

Runway edge lights;  

Threshold lights at the threshold of Runway 36; 

Displaced threshold wing bar lights at the displaced threshold of Runway 18; and  

Runway end lights. 

PED-9-2013-4B

Page 47: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 16

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

As a reference Code 3C runway, Runway 18‐36 requires medium intensity runway edge lights for use at night.    As  a  runway  that  supports  non‐precision  approaches,  this  meets  Transport  Canada’s recommendation  for use of  these  lights  as  a  visual  aid during  the day when  low  visibility  conditions require non‐precision approaches.  The threshold and runway end lights are installed at each end of the runway as required for runways equipped with runway edge lights. 

Much of the airfield lighting was upgraded about 5 years ago, so this is generally all in good condition. 

In addition, the use of Runway Identification Lights (RILS) is recommended at the displaced threshold for Runway 18 in accordance with Transport Canada guidelines which recommend provision of these lights where a runway threshold is permanently displaced from the runway extremity and additional threshold conspicuity is necessary. 

PRECISION APPROACH PATH INDICATORS

Runway 18 is equipped with a Precision Approach Path Indicator system of lights, also referred to by the acronym PAPI.   This type of visual approach slope  indicator system  is required for Runway 18 because the  runway  serves  turbojet  powered  aircraft  that  require  some  form  of  approach  guidance  during daylight and night‐time hours.    In addition, the presence of two transportation corridors  (Gravenhurst Parkway and Highway 11) represents a significant hazard  in the event of an aircraft under‐shooting or overrunning the runway. 

The airport should consider the installation of PAPI’s on the approach to Runway 36 in support of turbo‐jet powered aircraft operations at the airport (see further discussion section 4.2). 

APPROACH LIGHTS

Transport  Canada  recommends  a  simple  approach  lighting  system,  also  referred  to  by  the  acronym ODALs, for a runway supporting non‐precision approaches.   

Runway 18‐36 is currently not equipped with approach lights, but should consider installation of ODALS for both approaches at some time in the future, should the runway be upgraded to non‐precision status with approaches that would provide non‐precision  limits. At a length of 450m, these lights could easily be accommodated within  the constraints of  the  federal  institutions  to  the south and  the Gravenhurst Parkway and Highway 11 to the north.  In the meantime, the airport should consider at  least  installing Runway Identification Lights (RILS) to provide better guidance at night and during times of poor visibility (see further discussion section 4.2). 

TAXIWAY AND APRON EDGE LIGHTS

The South Apron Taxiway and South Apron are the only parts of the airfield equipped with taxiway and apron edge  lights.   Given  the  importance of  the South Apron Taxiway and South Apron as one of  the airport’s key taxi routes and designated apron for aircraft parking, these  lights are required to provide visual guidance to aircraft taxiing at night. 

Taxiways  Alpha  and  Bravo  are  equipped  with  taxiway/runway  intersection  lights.    Taxiway/apron intersection lights are also located where the South Apron Taxiway intersects with the South Apron. 

APRON FLOODLIGHTING

Apron floodlighting  is available at the South Apron because the apron  is  intended for use during night time hours.  The floodlighting consists of the following units: 

PED-9-2013-4B

Page 48: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 17

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

On the west facing edge of the air terminal building’s roof; 

On apron tower  lighting  installation  located south of terminal building consisting of two  large metal halide fixtures with a third light that illuminates the public car parking lot; 

At fuel farm consisting of three light fixtures to illuminate the fuel farm and refuelling area. 

AIRCRAFT RADIO CONTROL OF AERODROME LIGHTING SYSTEM (ARCAL)

The  airport  is  equipped with  an Aircraft Radio Control of Aerodrome  Lighting  System  (ARCAL) which enables pilots to control airport lighting when required.  The system controls the following lights: 

Runway lights on Runway 18‐36; 

Taxiway edge lights, taxiway/runway intersection lights, taxiway/apron intersection lights; and 

PAPI unit serving Runway 18. 

The  system  is Type K which allows pilots  to adjust  the  intensity of  the  lights  to  low, medium or high intensity settings.  The ARCAL system is of economic value to the airport as it saves costs by permitting the airport  to  switch off  the  lights at night when  the airfield  is not  in use and  removing  the need  to provide staff to switch the lights on and off. 

AIRFIELD SIGNAGE AND MARKERS

AIRFIELD SIGNAGE

The airfield is equipped with four types of signs as follows:  

Mandatory instruction signs; 

Mandatory frequency/aerodrome traffic frequency sign; 

Information signs; and 

Road holding position signs. 

Mandatory  instruction  signs  are  required  to  identify  a  location  beyond which  an  aircraft  taxiing  or vehicle should not proceed without authorization from air traffic control or verification that the runway is clear.   They  include  runway designation signs, which are  located at  the  following  intersections with Runway 18‐36: 

On both sides of the South Apron Taxiway;   

On Taxiway Alpha; 

On Taxiway Bravo; and 

Private taxiway intersection with north turn‐around area of runway.   

A mandatory  frequency/aerodrome  traffic  frequency  sign  is  recommended  by  Transport  Canada  at airports without  control  towers,  such  as Muskoka Airport.    This  type of  sign  is  located on  the  South Apron Taxiway in line with the taxiway holding position marking at the intersection with Runway 18‐36. 

Information signs are required where there is an operational need to identify by sign, a specific location or  routing  information.    They  include  runway  exit  signs  and  direction  signs.    Runway  exit  signs  are located at the following locations:  

PED-9-2013-4B

Page 49: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 18

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

On  Runway  18‐36  at  intersection with  Taxiway  Alpha  to  indicate  direction  to  Taxiway  Alpha when approaching from the north and from the south; and 

On  Runway  18‐36  at  intersection with  Taxiway  Bravo  to  indicate  direction  to  Taxiway  Bravo when approaching from the north and the south. 

Road holding position signs are required at all road entrances to a runway.  Road holding position signs are located at the AWOS Road and the VHF DF Road where they intersect with Runway 18‐36.    

All signs on the airfield are fibre optic for night time use. 

It is noted that there are no signs identifying the location of Runway 09‐27.  The airport should consider the installation of a mandatory frequency/aerodrome traffic frequency sign and a mandatory instruction sign on the grass taxiway to assist pilots not familiar with the layout of the runways. 

AIRFIELD MARKERS

The use of retro‐reflective blue taxiway markers on Taxiways Alpha and Bravo meets Transport Canada’s recommended use of markers where taxiway centre  line or edge  lights or taxiway centre  line markers are not provided. 

AIRFIELD PAVEMENT MARKINGS

Pavement markings are located on Runway 18‐36, Taxiways Alpha, Bravo, South Apron Taxiway, partial parallel taxiway plus South Apron and Private South Apron. 

RUNWAY PAVEMENT MARKINGS

All  pavement  markings  displayed  on  Runway  18‐36  are  required  according  to  Transport  Canada standards for a paved reference Code 3 runway.  Markings displayed are as follows: 

Runway designation markings; 

Runway centre line markings; 

Threshold markings; 

Aiming point markings; and 

Touchdown zone markings. 

Arrows identifying the displaced threshold at Runway 18 conform with Transport Canada standards for a permanently displaced threshold. 

The absence of runway side stripe markings between the thresholds is permitted given the contrast that exists between the dark edges of the runway and the light coloured gravel dominating the runway strip. 

TAXIWAY PAVEMENT MARKINGS

All  taxiways display a  taxiway  centre  line marking and a  taxi‐holding position marking as  required by Transport Canada standards.   The former  is required when serving a reference Code 3 runway such as Runway 18‐36 while the latter is required to identify the holding position short of the runway.  

APRON PAVEMENT MARKINGS

The South Apron displays aircraft  stand  taxilane markings and aircraft  stand markings  to  identify  taxi routes  and  parking  positions  on  the  apron,  respectively.    Both  meet  Transport  Canada 

PED-9-2013-4B

Page 50: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 19

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

recommendations; the former providing guidance from the taxiway centreline to a point on the apron where aircraft  stand markings commence and  the  latter  for designating parking positions on a paved apron. 

Taxi‐holding position markings are recommended on north field tenant aprons and taxiways to identify the  limits of  the  taxiway  strip associated with  the partial parallel  taxiway.   Since Taxiways Alpha and Bravo are currently limited to reference Code B aircraft, the latter is limited to aircraft wide enough to accommodate reference Code B aircraft, and the markings should be  located 21.5 m (70.5 ft) from the taxiway centreline as recommended by Transport Canada.   

WIND DIRECTION INDICATORS

According to the AOM, there were three wind direction indicators at the airport.  These were located as follows:  

Northwest of Runway 36 threshold; 

West of Runway 36 threshold; and 

Southwest of Runway 18 threshold. 

Only  one  of  the wind  direction  indicators  remains  in  its  original  location  following  the  2006  apron expansion,  this  being  the  indicator  southwest  of  Runway  18  threshold.    The  indicator  northwest  of Runway 36 threshold was relocated to a site northeast of Runway 36 threshold, while the indicator west of Runway  36  threshold was  removed  in  the  same  year  as  it was  too  close  to  the  terminal building expansion.   The remaining two units   meet the Transport Canada standard that an aerodrome shall be equipped with at least one wind direction indicator.  Two of the units serving Runway 18‐36 are lighted for use at night to complement night time operations on the runway.   

AERODROME ROTATING BEACON

The  airport  is  equipped  with  an  aerodrome  rotating  beacon  as  required  by  Transport  Canada  for aerodromes intended for use at night.  The beacon is located approximately 366 m (1,200 ft) northwest of the threshold of Runway 36 elevated to a height of 25.1 m (82.5 ft) above ground level. 

Operation  of  the  beacon  is  independent  of  the  ARCAL  system,  as  it  is  equipped  with  a  photocell activation system. 

NAVIGATIONAL AIDS

The airport  is equipped with an NDB  (Non‐Directional Beacon) unit  in support of an NDB A approach.  The NDB unit is located off airport lands approximately 3.5 NM (6.5 km) northeast of the airport.  It also serves high level and low level en‐route navigation. 

A VHF Direction Finder  is also  located at the airport to assist air traffic control  in  locating aircraft.   It  is currently located east of the southern section of Runway 18‐36, as illustrated in Figure 2‐2.  

AUTOMATED WEATHER OBSERVING SYSTEM (AWOS)

The airport  is equipped with an AWOS  station  to observe and disseminate weather conditions at  the Muskoka Airport.  The station is located on the east side of Runway 18‐36. 

EMERGENCY POWER GENERATOR

The emergency power generator is an essential component of the airport’s power supply during power grid failures. This unit is located in a separate building adjacent to the FEC.  

PED-9-2013-4B

Page 51: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 20

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

AIRSIDE ROADS

The AOM  identifies several airside roads  in the airport site  layout  illustrated  in Appendix A  including a perimeter road and separate roads to access the AWOS, VHF Direction Finder and bomb disposal site. 

Planned relocation of the VHF Direction Finder (to permit new lands to be developed) will require a new gravel road for access to the installation and relocation of the mandatory hold signage. 

A gravel perimeter road encompassing the entire property is desirable for wildlife control and access to distant parts of the airfield without driving on the runways. 

AIRFIELD DRAINAGE

Airfield drainage  is generally enhanced by the  inherent good drainage characteristics of the underlying sands and gravel of the glaciolacustrine deposit.  Piping systems collect water along the western side of Runway 18‐36 and drain  it  towards  lands along  the eastern perimeter of  the property.   The District’s engineering and public works department has recommended  inspection of airfield drainage systems  in the near future.   

The  Exp  Services  pavement  evaluation  report  identified  localized  areas where  surface  drainage was deficient including the following: 

Poor to fair surface drainage to the gravel strip area to the east of Runway 18‐36; and 

Poor surface drainage to the perimeter grassy areas to the north and south of the south turn‐around area of Runway 18‐36 and the south section of the South Apron. 

SUMMARY

Table 2‐2: Summary – Airfield Assessment   

Asset  Recommendation 

Runway 18‐36  Pavement rehabilitation as per Exp Services report Runway 09‐27   Taxiway Alpha  Re‐certification to reference Code C standards 

Taxiway Bravo  Re‐certification to reference Code C standards South Apron Taxiway  Pavement rehabilitation as per Exp Services report Partial Parallel Taxiway   Grass Taxiway  Consider provision of taxiway edge markers and signage South Apron  Pavement rehabilitation as per Exp Services report Approach Lights  Consider installation of RILS on both approaches to Runway 18‐36 PAPIS  Consider installation on approach to Runway 36 Airfield Signage  Provision of signage identifying Runway 09‐27 Taxiway Pavement Markings  Addition of taxiway hold markings on tenant taxiways Apron Pavement Markings  Addition of taxiway hold markings on tenant aprons Airside Road – VHF DF Road  Relocation to new location of VHF DF installation Airside Road – Perimeter Road  Extension to north field to improve access to northeast lands 

 

BUILDING STRUCTURES

AIR TERMINAL BUILDING

The ATB is located at the southwest end of airport lands adjacent to the South Apron and accessed from Airport Road which connects with Gravenhurst Parkway.  

PED-9-2013-4B

Page 52: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 21

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

According  to  the  1999 Master  Plan,  the  ATB was  originally  constructed  in  1968.    The  building was rehabilitated  in 1986 and again  in 2007, when  it was  increased  in size to  incorporate the Little Norway Memorial,  a  Royal  Norwegian  Air  Force  cultural  attraction.    The  interior  of  the  building  offers  the following functions: 

Public areas: 

o Little Norway Memorial exhibit room; 

o Waiting/holding room area; 

o Public washrooms; 

Public facilities: 

o A conference room; 

o Three public telephones, one in each of the two airside entrances and one at the flight planning computer desk; and 

o Vending machines for soft drinks and snacks. 

Airport administration and mechanical rooms:  

o Reception desk and administration office; 

o Airport manager’s office; 

o Janitorial service room; 

o Mechanical room; and 

o Storage room for catering supplies. 

Rental areas: 

o One office for rental car tenant; 

o Two empty spaces available for lease. 

Pilot lounge: 

o Flight planning computer, telephone and wireless internet; 

o Kitchen area with complementary coffee; 

o Visitor lounge with television and vending machines; 

o Washroom; and 

o Vacant room (potential use for resting/sleeping). 

The terminal building is in excellent condition.  Any expansion of the building could be met by expanding the building  towards  the north where  the new  section of  the  South Apron  already exists  and would facilitate short walking distance between aircraft and terminal facilities.   Any expansion would require relocation of the equipment garage and tie‐down facilities to sites on the north facing perimeter of the South Apron.    

AIRPORT MAINTENANCE FACILITIES

The airport is equipped with a maintenance garage, metal shed and equipment shed.   

PED-9-2013-4B

Page 53: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 22

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

MAINTENANCE GARAGE AND COLD STORAGE SHED

The maintenance garage is a 5‐bay facility for the storage and servicing of airport vehicles.  This facility is located at the north end of airport lands accessible from the airside via the airport perimeter road and the groundside via Gravenhurst Parkway.  Constructed in the 1950’s, the garage is in good condition. 

The metal cold storage shed was built in the 1980’s in support of the maintenance garage. 

EQUIPMENT SHED

An equipment shed  is  located north of the terminal building.   Constructed  in 2009,  it  is a 3‐bay facility used for the storage of airport vehicles that is accessible from the airside only via the South Apron. 

 

FIELD ELECTRICAL CENTRE (FEC)

The FEC is located groundside to the south west of the terminal building. It plays an essential role to the airport in providing all power to the airfield lighting and the switch gear, constant current regulators, ARCAL system, etc. 

SOUTH BUILDING

A building dating back to the 1930’s  is  located on south airport  lands  in close proximity to the Beaver Creek  Institution.   The building held wartime  functions during  the Second World War, but  is currently leased by the Beaver Creek Institution for non‐aviation purposes.  

SUMMARY

Table 2‐3: Summary – Assessment of Buildings Structures   

Asset  Recommendation 

Air Terminal Building  No immediate or imminent issues 

Equipment Garage  No immediate or imminent issues 

 

FUELLING FACILITIES AND AIRPORT VEHICLES

FUELLING FACILITIES

Fuelling facilities are located at the airport for aircraft and airport maintenance vehicles. 

FUEL FOR AIRCRAFT

A new aircraft fuelling facility  is  located at the southern perimeter of the South Apron.   Constructed  in 2006  by  Imperial Oil  on  land  leased  to  them,  the  facility  is  owned  by  Imperial Oil,  operated  by  the District of Muskoka and the fuel supplied by Imperial Oil.  It consists of two 50,000 litre tanks, one for jet fuel (Jet A‐1) and the other for Avgas (100LL).   A mobile refuelling truck, also owned by Imperial Oil,  is equipped  for  over‐wing  and  single  point  refuelling  of  jet  fuel  and  enables  fuelling  of  aircraft  at  any location at the airport. 

FUEL FOR AIRPORT MAINTENANCE VEHICLES

An airside fuelling facility for airport maintenance vehicles is located at the maintenance garage.  Tanks with dispensing equipment are available for diesel powered vehicles only.  Floodlighting of the facility 

PED-9-2013-4B

Page 54: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 23

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

enables fuelling at night time, which is valuable to snow removal operations during the shorter daytime hours of the winter. 

The facility is in good condition.  

AIRPORT SERVICE VEHICLES AND EQUIPMENT

The airport is equipped with its own fleet of vehicles for snow removal and other maintenance activities.   

GROUNDSIDE FACILITIES

AIRPORT ACCESS ROAD AND TERMINAL AREA PARKING

The main access  to  the airport  is via  the Gravenhurst Parkway, which connects  to Highway 11  to  the north via Ecclestone Dr  (Regional Road 118) and to the south via Bethune Dr  (Regional Road 41). This southern access  is much more circuitous  than  the northern  route. The Gravenhurst Parkway provides direct  access  to  north  field  tenant  facilities  and  airside  entry  gates  along  the western  perimeter  of airport  lands.    It also connects with a  separate  road  ‐ Airport Road  ‐  that accesses  south  field  tenant facilities and the air terminal building.   Airport Road  is paved with asphalt and connects with a  large parking area  that serves  the south  field tenants  and  the  terminal  building.    Terminal  area  parking  is  available  at  an  asphalt  paved  lot immediately west of the terminal and a gravel surface  lot to the south.   The former has a capacity for five vehicles, while the latter is large enough for another four vehicles. 

FENCING

A chain  link  fence  is  in use at  the airport  for  security purposes and wildlife control.   New  sections of fence were installed on the eastern perimeter in 2009 through a Community Adjustment Fund Grant.  

UTILITIES AND SITE SERVICING

The airport’s power, water, sewage treatment systems and natural gas are discussed in the following paragraphs.   

ELECTRICITY

Electrical power requirements at the airport are met by more than one source.  At the north end of the airport, power  requirements are  fed  from a  source originating at Highway 11.   At  the  south end, an underground source is provided from the southern boundary.  An independent power supply consisting of automatic natural gas generators provides power to the terminal building, fuelling facilities and the airfield lighting system. 

WATER SUPPLY AND SEWAGE TREATMENT

Water  supply  at  the  airport  relies on wells while  sewage  treatment  is based on  individual  tanks  and septic  fields.   Municipal water and  sewage  systems are  located on  the  south airport property  line  to service the Beaver Creek Institution.  The 1999 airport master plan noted the spare capacity available on the municipal systems servicing the Beaver Creek Institution and the long term value this would bring to the airport. 

It is recommended that the airport should at least protect for connecting with both municipal water and sewage systems at some time in the future.   Whether or not these connections would ever be provided would be dependent on a combination of environmental and other policies at that time, from a number of levels of government, such as provincial, regional or municipal.  

PED-9-2013-4B

Page 55: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 24

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

NATURAL GAS

The airport obtains natural gas from a gas main located at a mid‐field point on the property.  As noted earlier, natural gas is used to generate electrical power for airfield lighting systems, the terminal building and the fuelling facilities. 

2.4 AIR TRAFFIC ACTIVITY

TRENDS IN AIRCRAFT ACTIVITY AT THE AIRPORT

Aircraft activity at YQA has overall slowly declined up till 2004 and since then has slowly increased – see Figure 2‐3. The  trend has been similar  for both  itinerant and  local movements, except  in 2012 where local movements have declined significantly while itinerant movements have increased. 

Figure 2‐4  shows  the  trend  in movements at YQA by operator  type, where  interestingly,  commercial movements in general appear to be rising while private movements have been generally declining. More specifically, movements  by  domestic  air  carriers  have  been  increasing  since  2004.  Domestic  private movements  have  been  decreasing  since  2003,  but  are  up  slightly  in  2012.  International  private movements have been declining since their peak in 2004. Other commercial movements have continued to decline since 2001 while government movements have been slowly increasing 

 

Figure 2‐3:  Annual Itinerant and Local Movements at Muskoka Airport, 1997 to 2012 

 

 

The  trend  in  itinerant movements by engine  type  is shown  in Figures 2‐5 and 2‐6.  It  is clearly evident from  Figure  2‐5  that movements by piston  aircraft have been  generally declining.  These movements declined up till 2004, remained fairly steady between 2005 and 2010, and then appear to be lower again for 2011 and 2012. This trend for piston movements seems to have generally been reflected in the total movements, at  least until about 2005 at which  time  the piston movements started a  flat  to declining trend and total movements began a steady upward trend.  

 

 

2,000  

4,000  

6,000  

8,000  

10,000  

12,000  

14,000  

16,000  

18,000  

20,000  

97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12est

Year

Total

Itinerant

Local

Source: Statistics Canada 2012 estimated from Jan‐Oct data

PED-9-2013-4B

Page 56: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 25

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Figure 2‐4:  Annual Itinerant at Muskoka Airport by Operator Type, 1997 to 2012 

 

 

Figure 2‐5.  Annual Itinerant at Muskoka Airport by Engine Type, 1997 to 2012 

 

As  illustrated  in  Figure  2‐6,  turboprop  aircraft movements  have  been  increasing  steadily  from  1997 through  to 2008 with particularly strong growth  in 2011 and 2012.   Helicopter movements have been slowly  increasing until 2009, but have declined since then. Jet movements  increased to 2003 but have been fairly steady since then. Overall, the declines in piston movements over the last decade have been gradually offset by gains in other types, especially turboprops. 

 

 

 

 

1,000  

2,000  

3,000  

4,000  

5,000  

6,000  

7,000  

97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12est

Year

Domestic air carrier  Domestic other commercial Domestic private  International air carrier International private  Government

Source: Statistics Canada 2012 estimated from Jan‐Oct data

7,000  

8,000  

9,000  

10,000  

11,000  

12,000  

13,000  

14,000  

97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12est

All & Piston Total itinerant Piston engines

PED-9-2013-4B

Page 57: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 26

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Figure 2‐6:  Annual Itinerant at Muskoka Airport by Engine Type, 1997 to 2012 

 

Trends  in movements by  aircraft weight have  been  consistent with  the  changes observed by  engine category. Movements of  aircraft under 2  tonnes  remained  steady  from 1998  to 2001, declined  from 2002 to 2004 and have not changed greatly since. Movements of aircraft  in the 2‐4 tonne range have fluctuated but currently are at close to their 15‐year low. For aircraft weighing 4‐9 tonnes, there was a slow increase until 2008 which accelerated in the last 4 years, consistent with the growth in turboprop activity. Movements of  aircraft over 9  tonne peaked  in 2008  and despite  increasing  in 2012  are  still below 2008 levels. Generally, declines in small aircraft movements (< 2 tonne) have been offset by gains of aircraft in the medium weight categories (4‐9 tonne). 

 

Figure 2‐7:  Annual Itinerant at Muskoka Airport by Aircraft Weight, 1997 to 2012 

 

 

 

 

 

250  

500  

750  

1,000  

1,250  

1,500  

1,750  

2,000  

2,250  

2,500  

2,750  

3,000  

97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12est

Excluding PistonJet engines Turbo‐propellers

Helicopters Gliders

7,000  

8,000  

9,000  

10,000  

11,000  

12,000  

13,000  

14,000  

97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12est

All and Under 2,000 kg Total itinerant 2,000 kg and under

PED-9-2013-4B

Page 58: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 27

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Figure 2‐8:  Annual Itinerant at Muskoka Airport by Aircraft Weight, 1997 to 2012 

 

 

TRENDS IN GENERAL AVIATION (GA) IN CANADA

Overall, GA has been  slowly declining  in Canada  for more  than 20  years,  although  this  varies by GA segment. The segments which have declined in the past 10 years (2001‐2011) include: 

Movements of piston aircraft, the largest segment of GA, have declined 40% (5.1% /year). This is consistent with  the  trend  in the US, where hours  flown by piston aircraft have declined by an average of 4.1% per year over that period; 

Private aircraft movements declined 26% (3.0%/year) 

Local movements declined 39% (4.9%/year) 

The jet and turboprop segments of GA are, however, increasing – between 2001 & 2011: 

Jet movements increased 8% (0.8%/year) 

Turboprop movements increased by 35% (3.0/year) 

A  similar  trend  in  turbine aircraft activity  is also occurring  in  the US, but growth  in activity has been lower  in  the  US  –  growth  for  jets  of  1.9%/year  and  turboprops  of  1.4%/year.  Jet  and  turboprop movements  in Canada have  recovered  strongly  from  recession with 6‐7%/year growth between 2009 and 2011.  In  the US, 2/3rd of GA activity  is related by business activity. Muskoka  traffic has generally followed the overall trend for GA in Canada. 

 

 

 

 

 

 

200  

400  

600  

800  

1,000  

1,200  

1,400  

1,600  

1,800  

2,000  

2,200  

97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12est

Over  2,000 kg 2,001 to 4,000 kg 4,001 to 5,670 kg

5,671 to 9,000 kg 9,001 to 18,000 kg

18,001 to 35,000 kg 35,001 kg and over

PED-9-2013-4B

Page 59: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 28

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Figure 2‐9.  Aircraft Sales by Engine Type, 2000 to 2011 

Future  activity  in  GA  is reflected  partly  in  the demand  for  new  GA aircraft. As shown in Figure 2‐9,  production  of  GA aircraft  dropped  following 2008  recession  to  under half  the  2007  value,  and there  has  been  little growth  since  2009.  This  is due  partly  to  the  average price  of  GA  aircraft increasing  by  90%. Production  levels of piston and  jet  aircraft  are  both down  sharply,  while production  of  turboprops is  up  slightly.  The  introduction  of  very  light  jets  (VLJs)  in  the  mid‐2000s  spurred  optimism  for  a resurgence  in GA, but so far they have not been realizing the high expectations. The  largest selling VLJ initially,  the Eclipse 500, had problems and production  ceased 2008. Embraer’s Phenom 100 was  the second highest selling GA aircraft in 2010 with 100 sold, but sold less than 50 in 2011.  

FAA forecasts a slow decline in piston movements (‐0.1%/year) and growth in turbine (jet & turboprop) GA movements of 4%/year for next 20 years, with overall GA growth 1.7%/year. 

TRENDS IN GA AT OTHER ONTARIO MUNICIPAL AIRPORT

As with the Muskoka Airport, traffic has generally declined at the smaller Ontario municipal airports. Stats show that at the 14 airports without towers or FSS’s reporting traffic from 1997 to 2011:   

Total movements declined by 1.3%/yr with local movements declining  by 4.1%, but itinerant 

traffic  increasing by 1.7%/yr 

The decline has been more prominent since 2006 

At another 6 of these airports, traffic declined so significantly that the airport stopped reporting 

traffic 

At the 5 Municipal airports with FSS’s,  from 1997 to 2011 traffic also declined but not quite as 

quickly (‐0.9%/yr), although both itinerant and local movements declined

At Muskoka, total traffic has been very volatile, but generally at the same level in 2011 as in 2001 or 1997 but less than 1998/2000 peak, though itinerant is down (13%), while local is steady or slightly up over this period.   

CURRENT AIRCRAFT ACTIVITY

In 2011  the airport had a  total of 17,020 aircraft movements, 11,287  (66%) were  itinerant and 5,733 (34%) were local. A breakdown of the 2011 movements by runway, fixed wing/helicopter, IFR/VFR and approach  type  is  presented  in  Table  2‐x.  Runway  36  was  used most  often,  accounting  for  56%  of 

PED-9-2013-4B

Page 60: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 29

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

itinerant movements.  The  grass  runway, Runway  09‐27, was used  for only 237 movements, most of which used Runway 27. Total use of 09‐27 accounted for 2% of itinerant movements. Usage of the grass runway has been  very  low,  ranging  from 181  to 260, over  the past 9  years. Helicopters  (not using a runway)  accounted  for  563 movements,  5%  of  itinerant movements.  Almost  a  quarter  of  itinerant movements were  IFR, while missed approaches accounted  for a relatively high proportion of  itinerant movements at 4%1.  

 

Table 2‐4:  Summary of Movements at Muskoka Airport in 2011 

Segment  Runway  Movements  % of Itin.  IFR  % IFR  Arrive  Depart 

Itinerant  18  3,789  34%  925  24%  1,933  1,856    36  6,267  56%  1,463  23%  3,060  3,207 

   9  57  0.5%  1  2%  36  21    27  180  1.6%  3  2%  122  58 

   Helicopter  563  5%  2  0%  286  277    Missed Approach  431  4%  156  36%  216  215 

   Total Itinerant  11,287  100%  2,550  23%  5,653  5,634 

Local     5,733  34% of total           

Total     17,020                

Source: Statistics Canada NCAMS data 

As  shown  in  Figure  2‐10,  7,319 movements  at  the  airport  in  2011 were  by  piston  aircraft,  65%  of itinerant movements, while turboprops accounted for 15% and helicopters 8% of itinerant movements. Corporate jets had 603 movements (5%) and regional and narrow‐body jets had 40 movements (0.4%) in 2011.  Only  piston,  small  turboprops  and  rotary wing  aircraft  used  the  grass  runway.  US  registered aircraft had 580 movements, accounting for 5% of itinerant movements. Almost 2,000 movements were operated by air carriers with a flight number. 

Figure 2‐10:  Itinerant Movements at Muskoka Airport by Runway and Aircraft Category 

 

                                                                 1 This is a high level of missed approaches. This is generally due to training operations where operators are practicing missing approaches.   

0

1000

2000

3000

4000

5000

6000

7000

18 36 9 27 Helicopter Area

HelicopterPistonSmall TurbopropMedium TurbopropLarge TurbopropCorporate JetRegional Jet

9517,3191,699524147603

Runway

Itinerant Movements

Source: Statistics Canada NCAMS 

PED-9-2013-4B

Page 61: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 30

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

While most of the aircraft activity at the airport is generally by smaller aircraft as illustrated above, there is an interesting component of traffic with large aircraft, above 20 tonnes. A breakdown of the 171 movements of aircraft over 20 tonnes is provided in Table 2‐5. 

Table 2‐5.  Summary of Movements of Aircraft over 20 Tonnes in 2011 

Owner Type

Carrier ID Aircraft Manufacturer Model Aircraft Category Weight (t)

# Engines

Move-ments

Carrier BRMA, TRKR, CFC C30J Lockheed C130J Hercules Large Turboprop 74 2 8

Carrier TIGR, CNUK, CFC C130 Lockheed C-130 Hercules Large Turboprop 70 4 82 Carrier VPCNI MD87 McDonnell

Douglas MD-87 Medium Jet 64 2 2

Private - US B737 Boeing 737-2R8C Medium Jet 63 2 2 Private - Canada E190 Embraer 190 Regional Jet 48 2 3 Private - Canada G550 Gulfstream GV-SP Corporate Jet 42 2 4 Private - US GLF5 Gulfstream G V Corporate Jet 41 2 8 Carrier JZA CRJ9 Bombardier Inc. RJ900 Regional Jet 38 2 1 Private - US GLF4 Gulfstream G IV Corporate Jet 33 2 12 Private - US GLF3 Gulfstream G-1159A Corporate Jet 31 2 2 Carrier JZA CRJ2 Bombardier Inc. RJ200 Regional Jet 23 2 26 Carrier CAV AT72 Aerospatiale ATR 72-500 Large Turboprop 23 2 2 Private - Canada A748 British Aerospace 748 Large Turboprop 21 2 1 Carrier WATER F900 Dassault Aviation Mystere Falcon

900 Corporate Jet 21 2 12

Source: Statistics Canada NCAMS data 

                                                                   Table 2‐6: Summary of Movements by Aircraft Owner 2011 

The most common  large aircraft to use  the  airport  are  the  C‐130 Hercules with  82 movements,  and Jazz CRJ‐200s with 26 movements. Excluded from this table were C‐17 Globemaster  movements  that accounted  for  6  missed approaches.  These  aircraft occasionally  do  fly  bys  en‐route to/from  CFB  Trenton.  The  C‐130 flights  are  operated  by  DND  for searh and rescue operations.   DND chooses  to  operate  these  flights from  YQA  due  to  the  long,  wide runway,  low  flight  activity  in  the area and closeness to CFB Trenton. These  flights  provide  significant revenue  to  the airport,  in  terms of fuel sales. 

Activity  at  the  airport  by  aircraft owner  is  summarised  in  Table  2.6 at  right.  The  most  frequent  user, 

PED-9-2013-4B

Page 62: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 31

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

accounting for 542 flights  in 2011, was Sierra Fox  Inc, which  is the owner of the Ferrari Flight Training school  at  the  airport.  Other  flight  school  activity  is  quite  prevalent, with  the  Brampton  Flying  Club recording 380 movements, Seneca College 311, Island Air Flight School 188, the Wellington Flying Club 86 and B.P Flight Training  Inc 65. The second most  frequent user was Toronto Airways, a commercial operator, accounting for 480 movements, in most cases chartering passengers into and out of Muskoka for tourism/cottage activities. The Ontario Ministry of Natural Resources aircraft accounted for the next highest number of movements at the airport with a total of 466  in 2011. The other users were a wide mix of commercial operators, chartered aircraft, private  flights by both based and visiting aircraft and other government operations    

Activity at the airport is very seasonal, as shown in Figure 2‐11, with five times as many movements in the busiest month,  July, as  in  the quietest months  (December  to February). This  reflects  the  summer tourism focus of the airport. July as the busiest month had a total of 2,785 movements, with 1,896 (2/3) being itinerant and the other 916 (1/3) local.   

Activity also varies significantly over the days of the week. As shown in Figure 2‐11, Friday is the busiest day  in  July with an average of 80  itinerant movements and 38  local movements. Thursday  is  the next busiest, due largely to high local activity, followed by Saturday due largely to high itinerant activity. 

 

Figure 2‐10: Movements at Muskoka Airport in 2011 by Month 

 

 

If we look at the average distribution of traffic over the days of the week using the total annual activity, as illustrated in Figure 2‐12, we find that Friday is still typically the busiest day, but traffic in this case is more equally distributed over the different days than it is during the peak summer months.  

 

 

 

 

 

0

500

1,000

1,500

2,000

2,500

3,000

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Movements per Month

Local

Itinerant

Source: Statistics Canada NCAMS data

PED-9-2013-4B

Page 63: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 32

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Figure 2‐11: Movements at Muskoka Airport in 2011 by Day of Week in Busiest Month (July) 

 

Figure 2‐13 shows the hourly distribution of traffic averaged over all of the days of the year. This traffic is shown to build up over the morning hours to 11 am, settle into a certain activity level through the mid day through to about 3pm and then slowly decline throughout the afternoon and evening periods. The average hourly traffic during this mid afternoon period is about 5 movements per hour. 

 

Figure 2‐12. Movements at Muskoka Airport in 2011 by Day of Week Averaged over the Year 

 

 

 

 

 

 

0

20

40

60

80

100

120

Mon Tues Wed Thu Fri Sat Sun

Movements  on Day

Local

Itinerant

Source: Statistics Canada NCAMS data

0

10

20

30

40

50

60

Mon Tues Wed Thu Fri Sat Sun

Movements  on Day

Local

Itinerant

PED-9-2013-4B

Page 64: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 33

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Figure 2‐13: Movements at Muskoka Airport in 2011 by Hour of the Day Averaged over Year 

 

 

During the peak month of July, hourly activity shows quite a different pattern than the yearly average.  In this case, activity  is greatest between 9 and 10 am averaging close to 12 movements per hour, due largely to the high number of  local movements. Itinerant movements,  like  in the previous graph, don’t vary greatly during  the day‐time period, 9 am  to 5 pm,  ranging  from 4  to 7 movements per hour on average, but they do tend to peak earlier at 9, 10 and 11 am. 

Figure  2‐15  illustrates  the  frequency  distribution  of  hourly  itinerant  traffic  at  the  airport.  This  graph shows  that  the  busiest  hour  recorded  by  the  NavCanada  data  had  24  itinerant  movements.  This occurred between 11am and 12 noon on April 7, 2011. 

 

Figure 2‐14. Movements at Muskoka Airport in 2011 by Hour of the Day in Busiest Month (July) 

 

 

0

1

2

3

4

5

6

0 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Movements per Hour

Hour

Local

Itinerant

0

2

4

6

8

10

12

0 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Movements per Hour

Hour

Local

Itinerant

Source: Statistics Canada NCAMS data

PED-9-2013-4B

Page 65: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 34

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

A  commonly accepted definition  for  “design peak hour” movements at airports  is defined as a  “95th percentile” traffic level. This means that at this particular traffic level, 95% of hourly movements would be accommodated  in hours with  less than this  level of traffic, while there would be 5% of movements that would occur  in hours with higher  traffic  than  this  level.   For 2011,  the 95th %tile  itinerant  traffic peak would be 12 movements per hour.   

Figure 2‐15. Frequency Distribution of Hourly Itinerant Aircraft Movements at Muskoka 

   

Figure 2‐16 illustrates the same distribution as the above figure, but in this case for Total aircraft movements (i.e. itinerant + local). In this case, the busiest hour in the year had a total of 55 movements and this occurred on August 12 between 7pm and d8pm.  The 95th %tile or “design peal hour” for total movements is shown as 28 movements per hour, so we could anticipate a typical design peak could consist of 12 itinerant operations and 16 local movements.      

Figure 2‐16. Frequency Distribution of Hourly Itinerant + Local Aircraft Movements at Muskoka 

 

PED-9-2013-4B

Page 66: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 35

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

2.5 FINANCIAL ASSESSMENT

In 1996, the District acquired the multi‐million dollar airport facility for $1.00 from Transport Canada. At the  time,  the airfield was  in good condition, but  the buildings and vehicle  fleet were dated and  there was no established reserve to fund ongoing costs. 

The objective of airport financial management  is to provide facilities  in a cost effective manner,  i.e., to obtain maximum benefits while limiting municipal costs to a level commensurate with municipal needs and benefits.  The following section describes the current and historical financial situation at the airport and provides commentary on how well the District has achieved these financial management objectives. 

REVENUES

Airport  revenue  is  income  received by  the  airport, derived  from business  activities  conducted  at  the airport.  

Revenues are typically categorized as “aeronautical” or “non‐aeronautical”. 

Aeronautical revenues are directly associated with aircraft operations and passenger processing on the airfield and  in the terminal. Aeronautical revenues typically  include charges  levied on a per  aircraft  basis,  and  charges  levied  on  a  per  passenger  basis.    Aeronautical  revenues  can include:  landing  fees,  terminal  fees,  aircraft  parking  fees,  bridge  fees,  tie‐down  fees,  call‐out charges,  fuel  concessions, airport noise  fees,  security  fees, passenger  service  charges, ground handling charges, emissions‐related aircraft charges, etc. 

Non‐Aeronautical  revenues  are  derived  from  activities  that  are  not  directly  related  to  the operation of aircraft, including land leases (or sales) airside and groundside, space leases in the terminal  building,  food  and  beverage,  and  retail  concessions,  car  rental  concessions,  vehicle parking, advertising, etc. 

Airport  revenues  are  driven  by  a  number  of  factors,  including  but  not  limited  to:  the  economic environment;  the  governance  and  management  model;  traffic;  lease  agreements;  legislation  and regulation; number and diversity of concessions; numbers and types of based tenants, etc. 

In general,  revenues  from operation of  the airport are used  to cover airport operations, maintenance and capital improvement expenditures.  Generating revenues is also critical to support airport growth.   

There are generally three areas of potential revenue for an airport: 

Airport User Fees – those charges which the airport owner assesses the user as a share of the cost for using airport facilities or providing services 

Lease of Land and Building Space to Aviation Interests for their commercial or personal use and benefit 

Lease of Land and Building Space  to Non‐Aviation  Interests  for  their commercial or personal use and benefit 

Airport revenues are earned through based tenants, and other operators: 

Air carriers (scheduled and charter) and airline servicing companies (ground handling, catering) who are direct customers of many airport services; 

General  aviation  (flight  training  schools,  corporate,  private,  public  service  operators,  flying clubs); 

PED-9-2013-4B

Page 67: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 36

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Aircraft  /  aviation  services  (fixed based operators,  aircraft  assembly, maintenance  and  repair organizations, aircraft sales / rentals); 

Airport commercial services (food & beverage, retail); 

Ground transportation (car rental, taxi licenses, buses); 

Logistics / freight forwarding operators; 

Other industrial / commercial; 

Government  agencies (although some receive free space); 

Agricultural (e.g. farming) (insufficient available land at Muskoka); and 

Recreational (e.g. golf course) (insufficient available land at Muskoka). 

As  Muskoka  airport  is  a  general  aviation  airport,  which  has  limited  available  land,  the  revenue generating focus is on GA activities and aircraft and aviation services. 

Within  their unique environment, airports should attempt  to operate  in a business  like  fashion  to  the greatest  extent  possible.  As  such,  airport management  should  have  in  place  the  following  tools  to facilitate the planning and implementation of a revenue generation program: 

Guiding policies defining whether each user will pay a  fair share or some users will pay more than others; 

Standards  for rental rate calculations defining what components are  included and the  formula used; 

Standard leases to define responsibilities, cost and profit sharing; 

Records of financial information for cost/revenue analysis. 

Detailed revenue data for the Muskoka airport was available for 2009‐2011.   Figure 2‐17 shows that net operating revenues increased from $441K in 2009 to $553K in 2011 representing a 25% increase during this period.  These figures include net fuel sales (gross sales less cost of sales) as aeronautical revenue, to better compare with airports that do not operate a fuel concession themselves.  The ‘sale of assets’ ($104K in 2009 and $46K in 2011) has also been removed, as has grants ($10K in 2010).  This increase in operating revenue  is consistent with the trend of  increased  jet and turboprop traffic at the airport, as described in the earlier section.  Note that the 2010 revenues are particularly high due to the G8 Summit that took place in the area. 

Typically  the major source of  revenue at airports  is based on  the numbers of aircraft  landing at, and passengers  flowing  through,  the airport.   This  traffic  is variable and  is  influenced by external  factors outside of  the airport operator’s control. Traffic  is dependent on a number of  things such as aircraft operator decisions,  the economic  situation, passengers’ propensity  to  travel,  competing airports and other modes of travel.  Most airports aim to maximize non‐aeronautical revenue and to reduce reliance on aeronautical revenue in an effort to protect themselves in the event of major traffic declines.   They do this by diversifying their revenue sources and finding ways to bring in steady streams of revenue to help  cover  the  fixed  costs  associated  with  operating  an  airport.    This  is  typically  accomplished  by capturing any available commercial opportunities, e.g., leasing (or selling) underutilized land (airside or groundside), food and beverage concessions, retail concessions, etc.  

 

 

PED-9-2013-4B

Page 68: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 37

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Figure 2‐17: Airport Revenues: Aeronautical vs Non‐Aeronautical 2009‐2011 

 

Figure 2‐17 also shows the airport’s heavy reliance on aeronautical revenues which account for approximately 75% of total revenues.   

Aeronautical Revenues  

Aeronautical revenue at the Muskoka airport  includes net  fuel sales, call‐out  fees, ramp  fees  (landing, parking, GPU), and miscellaneous (catering sales, pilot supplies/hats, and sewage service charge). 

Aeronautical revenue at the airport increased from $337K in 2009 to $416K in 2011 representing a 23% increase during this period.  Call out fees increased the most (99%) followed by ramp fees (46%) and net fuel sales (17%). 

 

Figure 2‐18: Airport Revenues: Aeronautical Revenue Breakdown 2009‐2011 

 

$336,629 

$433,930  $415,729 

$104,743 

$153,802 $137,531 

$‐

$100,000 

$200,000 

$300,000 

$400,000 

$500,000 

$600,000 

$700,000 

2009 2010 2011

Muskoka Airport ‐ RevenuesAeronautical Non‐Aeronautical

$17,752  $24,661  $16,263 

$73,642 

$119,492 $107,821 

$6,900 

$10,100 $13,705 

$238,335 

$279,677 $277,940 

$‐

$50,000 

$100,000 

$150,000 

$200,000 

$250,000 

$300,000 

$350,000 

$400,000 

$450,000 

2009 2010 2011

Muskoka Airport ‐ Aeronautical Revenues

Net Fuel Sales

Fees ‐ Call‐Outs

Fees ‐ Ramp

Fees ‐Miscellaneous

PED-9-2013-4B

Page 69: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 38

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Net fuel sales are by far the largest aeronautical revenue generator at the airport representing between 65‐70%  of  total  aeronautical  revenue,  or  50%  of  total  operating  revenue  (excluding  grants  and  land sales). 

The airport operates the fuel facilities and services at the airport, selling approximately 1 million litres of fuel a year; mostly jet fuel (90%). Ornge is by far the largest purchaser of jet fuel at the airport (30‐40% of total fuel by volume2).  In 2011, gross fuel sales revenue was $1.6 million, or an average of $1.61 per litre.    Net fuel revenue in 2011 was $278K or approximately $0.28 per litre.  If staffing costs are added to  the  cost  of  providing  the  fuel  service,  the  airport  generates  approximately  $0.18  per  litre  in  net revenue which is a reasonable return. 

Approximately  $15K  ‐  $23K  per  year  in  net  fuel  revenue  is  attributable  to  piston  aircraft  ($4‐6  per landing) compared to an estimated +/‐ $250K year in net fuel revenue attributable to turboprop and jet aircraft.     While piston  aircraft do not  generate much  in  fuel  revenue  (or pay  landing  fees),  they do generate land rents and are economic generators for the region.  

Ramp fees include aircraft parking, landing fees, and GPU usage, and generate approximately $100K a year in aeronautical revenue.   Landing fees generate the most ramp revenue (80%) followed by aircraft parking (15‐20%).  Ramp fee revenue increased 10% between 2010 and 2011. 

Landing  fees are charged  for  the use of  the  runways,  taxiways and aprons  that aircraft use.    In 2011, landing  fee  revenue at  the Muskoka Airport was $89K  representing a 5%  increase over 2010.    Some airports charge different fees for based aircraft and visiting aircraft.   Muskoka does not charge  landing fees for based aircraft weighing less than 5,000 kg i.e., piston and small turboprop aircraft.  The average landing fee at Muskoka in 2011 was $16; however over 75% of the aircraft landing at the airport do not pay landing fees; therefore the average landing fee of paying aircraft was about $6. 

 

Figure 2‐19: Fuel Sales by Volume 2008‐2011 

 

 

 

                                                                 2 While the local based operator purchases a lot of fuel at the airport, these fuel purchases are not all necessarily related to local EMS services.    

92,073  91,209  90,269  83,615 

686,831  678,637 884,931  901,607 

0

200,000

400,000

600,000

800,000

1,000,000

1,200,000

2008 2009 2010 2011

Litres Sold

Muskoka Airport ‐ Fuel Sales (L)

TFA‐1

100LL

PED-9-2013-4B

Page 70: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 39

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Figure 2‐20: Fuel Sales and Costs in Dollars 2009‐2011 

 

 

As  shown  in  Figure  2‐22, Muskoka  Airport’s  landing  fees  are  a  little  higher  compared  to  others  for corporate and  regional  jets  (particularly Peterborough); but on par  for medium and  small  turboprops and piston aircraft. 

 

Figure 2‐21: Airport Ramp Fees 2010‐2011 

 

 

 

 

$238,335  $279,677  $277,940 

$‐

$200,000 

$400,000 

$600,000 

$800,000 

$1,000,000 

$1,200,000 

$1,400,000 

$1,600,000 

$1,800,000 

2009 2010 2011

Muskoka Airport ‐ Fuel Sales ($)

Fuel Sales Aviation Fuel (cost of sales) Net Fuel Sales

$15,397  $21,174 

$85,142 $89,275 

$1,860 

$1,680 

$‐

$20,000 

$40,000 

$60,000 

$80,000 

$100,000 

$120,000 

2010 2011

Muskoka Airport Ramp Fees (2010‐2011)

GPU Usage Fees

Landing Fees

Aircraft Parking Fees

PED-9-2013-4B

Page 71: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 40

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Figure 2‐22: Landing Fee Comparison (non‐based aircraft) 

 

 

In 2011, aircraft parking revenue was $21K, which is a 31% increase from 2010. Aircraft parking revenue represents approximately 15‐20% of ramp  fee revenue and 5% of total aeronautical revenue.   Aircraft parking is generally charged by the amount of time the aircraft is parked on the ramp, with charge rates depending on the maximum take‐off weight (MTOW) of the aircraft and/or the engine type.   Muskoka Airport’s parking fees for non‐based aircraft are  lower than the average of the comparison airports for larger  corporate  and  regional  jets  (average  $49),  medium  turboprops  and  smaller  corporate  jets (average  difference  $27),  and  for  smaller  turboprops  (average  $20).   However, Muskoka’s  rates  are higher than average for piston aircraft (average $10). 

 

Figure 2‐23: Overnight Parking Fee Comparison (non‐based aircraft) 

 

$105

$48$40

$0

$120

$48

$28

$0

$70

$50

$35

$0

$115

$58 $58

$0

$105

$42

$26

$0

$116

$42

$26

$0

$‐

$20 

$40 

$60 

$80 

$100 

$120 

$140 

CL60(corp. jet)

B1900(Medium Turboprop)

PC‐12 (Small Turboprop)

C172 (Piston)

Landing Fee Comparison (non‐based)Muskoka Lake Simcoe Peterborough Niagara District Oshawa Kingston

$40

$25 $25

$15

$78

$29

$17

$10$15 $15 $15

$8

$20$16

$12$8

$75

$40 $40

$10

$69

$37

$21

$11

$‐

$10 

$20 

$30 

$40 

$50 

$60 

$70 

$80 

$90 

CL60(corp. jet)

B1900(Medium Turboprop)

PC‐12 (Small Turboprop)

C172 (Piston)

Overnight Parking Fee Comparison (non‐based)

Muskoka Lake Simcoe Peterborough Niagara District Oshawa Kingston

PED-9-2013-4B

Page 72: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 41

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Airport Improvement Fee 

Airport  Improvement  Fees  (AIFs)  have  become  common  place  at  airports  in  Canada  and  around  the world,  to  help  fund  capital  improvements.    AIFs  are  typically  charged  on  a  per  passenger  basis  on scheduled  flights, with  carriers  collecting and  remitting  the AIF  to  the airport.   As Muskoka does not have  scheduled  service,  an  AIF  administered  in  the  traditional  fashion  is  not  possible.    However, charging  an  AIF  type  fee  at  a  GA  airport  is  possible;  however  not  commonplace.  For  example,  the Oshawa Airport charges an AIF as follows: 

Table 2‐6: Oshawa Municipal Airport AIF Structure  

OSHAWA MUNICIPAL AIRPORT AIF  (effective July 1, 2011) 

Private  Commercial 

Oshawa Based Aircraft (effective Oct 1, 2011)  $60 annually  $100 annually 

Non‐Oshawa Airport Tenants < 2,000 kg  n/a 

Non‐Oshawa Airport Tenants 2,000 kg‐ 3,999 kg  n/a 

Non‐Oshawa Airport Tenants 4,000 kg‐ 4,999 kg  $10 / landing 

Non‐Oshawa Airport Tenants 5,000 kg‐ 9,999 kg  $15 / landing 

Non‐Oshawa Airport Tenants 5,000 kg‐ 19,999 kg  $20 / landing 

Non‐Oshawa Airport Tenants 20,000 kg‐ 44,999 kg  $25 / landing 

Non‐Oshawa Airport Tenants 45,000 kg +  $30/ landing 

A similar AIF  rate structure at Muskoka would result  in an  increase of approximately $18K  in revenue each  year  (based on 2011  traffic) which  could be used  to offset  the District’s  contribution  to  capital reserve.    If  itinerant  aircraft weighting  less  than  4,000  kg were  charged  $5  per  landing  versus being exempt, this amount could increase to $38K3.  

Non‐Aeronautical Revenues 

Non‐aeronautical revenue at Muskoka Airport includes rent (tenant land leases, office rent, covered tie‐downs,  and  airport maintenance  charges)  and  other  small  items  such  as  vending machine  sales.    It excludes sale of assets and grants as this skews the results and makes  it difficult  to compare to other airports that do not sell land; however other airports lease land and lease revenues may be included.  At Muskoka,  land sales revenues are transferred to the Capital Reserve, so this  in  itself tends to skew the results in that Muskoka therefore cannot account for annual lease rents for the properties sold. 

Non‐aeronautical  revenue  (excl.  grants  and  sales of  assets)  increased  from $105K  to $138K between 2009 and 2011 which is a 31% increase during this time period.  Rent accounts for the largest proportion of  non‐aeronautical  revenue  (90%),  and  increased  34%  during  this  two  year  period;  not  due  to  fee increases (other than CPI), but rather due to the addition of several new tenants.  

Muskoka  Airport  does  not  currently  generate  revenues  from  vehicle  parking,  cafe/restaurant,  car rental/ground transport, or small retail concessions.  

 

 

                                                                 

3 These estimates are provided only for discussion purposes and none of these have been incorporated into any of the financial analyses or recommendations later in this report.  

PED-9-2013-4B

Page 73: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 42

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Land Sales Revenue  

The Airport is one of only several in Ontario (and in Canada) that sell airport lands versus leasing them.  Muskoka has in place a documented “Land Sale, Lease and Rental Policy”.   The purpose of the land sale policy  is  to “encourage growth and development of  the airport  for aviation purposes as an  important economic generator for the area”.   

 

 Figure 2‐24: Non Aeronautical Revenues 2009 – 2011   

 

 

Key elements of the policy include:  

land is only considered for sale if it is for commercial (aviation) purposes;  

tenants are required to meet the legislative and regulatory requirements of all three levels of government;  

final decision on any sale rests with the District; 

no temporary structures or buildings are permitted on leased or purchased sites other than during the construction period (maximum 1 year);  

new tenants (after 2001) are required to invest at least $75,000;  

the District retains the right of first refusal on any sale of property by an owner; and  

the cost of disbursements (e.g. survey, appraisal, etc.) are added to the sale price. 

The process for land sales is illustrated in Figure 2‐25. 

Existing tenants in the year 2000 had until the end of the calendar year to purchase their sites subject to the principles outlined in the policy and subject to approval by District Council.  At that time, initial sales were completed with four airport tenants, representing 22,450m2 (5.5 acres) of airside land.    

Effective  January 1, 2001,  land  is only  considered  for  sale  for  commercial  (aviation) purposes.    Since 2000, a total of nine (i.e., five additional) land sales have been completed, representing 40,700m2 (10.6 acres) of land.  All commercial development since 2001 has been on purchased land.  At the time of this study 9 of the 27  lots  (33%) were owned privately; and all available  land was either owned or  leased, 

$94,669 

$143,020 $126,681 

$9,600 

$9,900 

$10,197 

$‐

$20,000 

$40,000 

$60,000 

$80,000 

$100,000 

$120,000 

$140,000 

$160,000 

$180,000 

2009 2010 2011

Muskoka Airport ‐ Non‐Aeronautical Revenues

Recovery of Write‐Off

Rent ‐ Airport

Sales ‐ Vending Machine

Rent

PED-9-2013-4B

Page 74: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 43

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

except  for  2  lots  still  left  undeveloped  (and  for which  there  is  interest  from  a  number  of  potential users)4.   

Figure 2‐25: Process for Selling Airport Lands   

 

 

Land  sales  prices  depend  on  appraised  value  (fair market  value), which  changes  depending  on  year (time) and  the  location of  the parcel at  the airport.    In accordance with municipal bylaw 2003‐52, at least one appraisal is required for each sale, and the appraisal is used as guide for Council when setting sale price,  in addition  to history or  related properties.   Land sales  revenue  is deposited  in  the Capital Reserve.  On average, the District has received about $60,000 per acre of land sold in sales recorded in the 2005‐2010 period. More recent appraisals since then have valued the lands at around $ 75,000 per acre.  Tenants  located  on  owned  land  at  the  airport  also  pay  a  $0.80/m2/year  airport maintenance charge (AMC). 

Based  on  several  land  appraisals  reviewed,  the  methodology  employed  by  the  appraiser  is  the comparable  sales  methodology.    The  appraiser  appears  to  be  comparing  against  other  industrial properties  in Muskoka,  and  especially  un‐serviced  industrial  parcels,  as  the  airport  does not  provide water  and  sewer  services.  As  well,  the  appraiser  compares  to  previous  airport  sales  (which  were themselves appraised by comparing to other industrial lands). This approach is generally the standard in 

                                                                 4 An additional lot become available as a result of a lease termination in late 2011 making a total of 2 lots available. 

Application to Purchase Land

Report to PED Committee(to initiate sale proceedings)

Professional Land Appraisal(Fair Market Value)

Appraisal value shared with PED Committee & an acceptable sale price determined(using the fair market value as a guide)

Sale price conveyed to Purchaser

Purchaser submits letter of intent confirming: - purchase price- intended usage for the property- acceptance of Muskoka’s Airport Land Sales Policy

Legal Department prepares an “Offer to Purchase”

Report to PED Committee recommending acceptance of “Offer to Purchase”

Subject Lands Declared Surplus

Sale finalized by Legal Department(following Public Notice of Sale)

Lower Purchase price proposal shared with PED

Committee & an acceptable sale price

determined

If all three conditions are met (Price, Usage, Policy)

If a lower purchase price is proposed(and other two conditions are met)

“YES”to lower

price

“NO”to lower

price

Once Offer is executed and returned to DMM

Muskoka Airport Land Sale Process

PED-9-2013-4B

Page 75: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 44

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Canada (i.e., comparing to similar industrial lands in the adjacent area, whether serviced or un‐serviced, as appropriate).  

Figure 2‐26: Airport Land Sales Since 2000   

 

The appraisers’ reports indicate that there are 3 standard approaches to establishing fair market value in Canada (and this is generally the case elsewhere as well). These are: 

Comparison approach; 

Cost approach; and  

Income approach.  

The appraisal reports then choose to use the comparison approach as they say that the cost approach is typically applied  to  land with buildings and  that  the  income approach  is more appropriate  for  income producing properties.   

 In the US, the standard approach tends to be to compare against other comparable airports, but then there  tend  to be more airports  in  the US. For  instance, an ACRP Guidebook5 states  that “the value of airport property  is usually dictated by  location, size, uses and  income generating potential.   The ACRP report  suggests  comparing  lease  rates  at  comparable  sized  airports  offering  similar  levels  of  service.  Market area, size of airport and demographics of the region should all be considered when establishing comparables  as well  as  the number of based  aircraft,  size of based  aircraft,  and  indicators of  traffic volume (incl. fuel volume). As shown in the table below, the base lease rate at Muskoka for un‐serviced land  is  $0.58  / m2  less  than  at  Lake  Simcoe,  and  the  AMC  is  $0.20  less,  for  a  total  of  $0.78  / m2 

                                                                 5 ACRP Report 47 “Guidebook for Developing and Leasing Airport Property”, Section 4.5 “Valuation” 

PED-9-2013-4B

Page 76: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 45

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

difference.    This  is  a  significant  difference  that  would  result  in  greater  revenues  to  the  airport,  if captured.  

Based  on  this  review  of  current  appraisals  at  the  airport, we would  conclude  that  these  have  been significantly undervaluing  the airport  lands. We  feel  that  the approach of comparing with un‐serviced industrial  lands  in  the adjacent  region  (while appropriate  to  some extent) has been used  in an unfair way.  In  fact, airport  lands are valued  less  than  these  similar  lands due  to a number of  “market” and “restriction” reasons. But on the other hand, the approach ignores the fact that the airport lands are not really fully “un‐serviced”. They do provide some level of improvements in terms of road access, taxiway access, grading and drainage improvements, etc. If the airport lands were valued similar to the industrial lands, their value would actually be in the range of about $ 100,000 per acre instead of about $ 75,000. Valuing these lands by comparing to competing airports like Lake Simcoe, would value the lands at over $ 120,000 per acre. And we will  illustrate  later  in this report that valuing the  lands on a cost approach would put the value of the lands at between $ 100,000 and $ 160,000 per acre. 

 

Table 2‐7: Comparison of Lease Rates with Other Airports (Lake Simcoe Airport)    

  Base Lease Rate / yr  AMC / yr  Total  

Muskoka  $0.91 / m2 (un‐serviced) 

escalates with CPI  

$0.80 / m2 

reviewed every 5 yrs 

$1.71 / m2 (excl. tax) 

Lake Simcoe  $3.34 /m2t2 (serviced)  

$1.49 m2 (un‐serviced) 

$1.08 / m2  $4.48  / m2 (serviced) 

$2.57 / m2 (un‐serviced) 

Parry Sound  N/A  N/A  N/A 

Peterborough  N/A  N/A  N/A 

Tenants  leasing  land at the airport pay a total of $1.71/m2/yr + tax ($0.91/m2/yr base  lease rate, plus the AMC of $0.80/m2/yr), plus  realty  taxes  as  valued by MPIC.    The  airport pays  the property  taxes upfront and is then reimbursed by tenants.   Base lease rates and the rates described in individual leases are adjusted annually on  the  lease anniversary date based on  the December  to December Consumer Price  Index  (CPI) percentage.   The  lease  rate  therefore  increases with CPI; however  the AMC  remains stable until airport management makes changes.  The lease rate and AMC fee are reviewed, according to bylaw, every five years to ensure they are near a fair market value. 

Whether an airport sells or leases land, the following general principles should apply: 

Protect the aeronautical requirements of the airport; 

Highest and best long‐term use of the land; and 

Inspire  growth  and  development  of  aviation  purposes  and  attract  general  industry  to  the Region. 

The benefits and challenges of selling land versus leasing are summarized in the table below. 

The principles as outlined  in the District’s  land use policy for the most part meet the best practices as outlined  in  the  table above; with one key exception:    the minimum development  investment by  land owners  in Muskoka  is minimal  ($75K), particularly given the  limited supply of available  land. Based on 

PED-9-2013-4B

Page 77: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 46

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

the value of construction and making the best use of land, this number should probably be 2 to 3 times higher.  

The  land  sale  policy  has  probably  generated  in  the  order  of  about  $  500,000  in  revenue  (in  today’s dollars) to the District for use on capital projects since 2000. On the other hand, if we estimate the value of  the “lost annual revenue” due  to  land sales,  this could be  in  the range of say $40,0006 per year or close  to  15%  of  the  annual  deficit  (assuming  that  land  sales  account  for  about  half  of  the  current developed lands). So the discussion of land sales vs land lease really becomes one of where do we want the money to go, and where would the money be best allocated. More insight is provided on this topic later in the financial analysis and forecasts section.  

Table 2‐8: Comparison of Leasing vs Selling Lands 

SELLING AIRPORT LANDS  LEASING AIRPORT LANDS 

Benefits 

Immediate cash infusion 

Can provide funds for future airport development 

Is attractive to more businesses and investors    

Provides opportunities for greater economic benefits due to increased investments  

Downloads servicing and access costs to proponents 

Challenges 

Limits future airport expansion (once the land is gone, it’s gone) 

Airport owner not in control of lands; however can set development terms 

Available capacity could be controlled by “tenants” 

Best Practices 

Airport owner approval of all land sales and subsequent development proposals 

Airside parcels for aviation use only and charged user fees 

Minimum parcel size (e.g., 1 acre) 

Minimum investment (e.g. $1‐5M) 

Maximum time limit to build (e.g., within 1 year) 

Mandatory AMC agreement for airside lots) 

Mandatory airport site plan agreement consistent with Master Plan and Land Use Plan 

Proceeds from land sales to a dedicated airport reserve fund 

Benefits 

Ongoing revenue stream (land rental) 

Airport owner in control of development and land uses 

Better control over open and competitive access to service providers 

Available capacity controlled by airport owner; fosters competitiveness and service 

Challenges 

Tenants have more difficult to secure financing for capital projects 

Tenants generally request serviced parcels 

Best Practices 

Market rates (with escalation) 

Incentives 

Airport owner management control of land (incl. sub‐leases) 

Development standards to ensure quality and consistency in buildings   

                                                                 6 This is calculated as approximately 10 acres (41,000m2) that are leased instead of sold at $0.9 per m2 annually 

PED-9-2013-4B

Page 78: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 47

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

OPERATING EXPENSES

Airports face a number of challenges related to economics and financial viability, including having high fixed  costs.    Airports  are  like  mini‐cities,  and  have  high  infrastructure  costs  related  to  terminal buildings,  runways,  taxiways and aprons, maintenance buildings, specialized vehicles and equipment, parking  facilities,  security  systems,  site  services  (water,  sewer,   utilities), etc.   The  cost of acquiring, maintaining and replacing this  infrastructure exists even  if there  is no  incoming revenue as an offset.  To make this more challenging, many costs, especially for capital and major maintenance, are “lumpy” i.e., very infrequent and very large. 

Operating expenses at the Muskoka Airport, as illustrated in Figure 2‐27 (excluding the cost of sales for fuel) have increased from $756.4K in 2009 to $840.3K in 2011. This is an 11% increase during this period; approximately half  the rate of overall operating revenue. This  is  impressive, particularly during a  time when  the  regulatory  burden  has  increased  for  certified  airports  (e.g.,  SMS,  wildlife  management programs, etc.).  As noted on the revenue side, operating expenditures in 2010 were higher due to the G8 Summit, but also due to the accounting for staff sick leave. 

 

Figure 2‐27: Airport Operating 2009 ‐ 2011   

 

The largest operating expenditure categories are salaries and wages (43% of total operating expenses); travel fleet (18%) for District fleet services including fuel, service, limited repairs and replacement costs; and  inter‐departmental  charges  (9%).     Other  smaller operating expenditures  include: office  supplies, printing,  courier,  computer  services;  materials  and  equipment;  utilities;  phones;  fuel  –  fleet  and equipment; building maintenance; grounds maintenance; equipment  repair; operating supplies;  taxes; insurance; advertising and promotion; professional services; aircraft servicing;   airport  furniture;   bank charges; accounts receivable write‐offs; and admin‐planning.  

It  is  difficult  to  compare  operating  costs with  other  airports  as  not  every  airport  has  the  same  cost structure. For example, not all airports operate an FBO  like Muskoka, so  therefore  their staffing costs will be less, and not all airports are charged for inter‐departmental services, as at Muskoka. 

$331,734  $376,640  $363,344 

$152,370 

$139,563 $139,717 

$58,600 

$74,332 $77,100 

$‐

$100,000 

$200,000 

$300,000 

$400,000 

$500,000 

$600,000 

$700,000 

$800,000 

$900,000 

$1,000,000 

2009 2010 2011

Muskoka Airport ‐ Operating Expenses

Inter‐departmental chargesTravel ‐ Fleet

Salaries & Wages 

PED-9-2013-4B

Page 79: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 48

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

OPERATING INCOME / LOSS

The operating  loss at  the airport  in each of  the past  three years has been  in  the order of $300K  (see Figure 2‐28 below – note  revenue  includes net  fuel  income and excludes  the sale of assets and grant revenues, as well as  funds  transferred  to  the capital  reserve).    If  revenues  from  land sales and grants were  included  in  these  figures  (see Figure 2‐29),  the  loss would decrease  to approximately $241K  (in 2011).  

Figure 2‐28: .Airport Operating Income (Loss) (Excluding Sale of Assets and Grants) 2009 ‐ 2011   

 

 

Figure 2‐29: Airport Operating Income (Loss) (Including Sale of Assets and Grants) 2009 ‐ 2011   

 

 

The positive news is that the annual loss (excluding land sales and grants revenue) has been decreasing in the past few years.  However, the average annual loss is larger than that of the average among non‐

$441,372 

$587,732  $553,260 

$756,403 

$881,734 $840,266 

‐$315,031  ‐$294,002  ‐$287,006 ‐$400,000 

‐$200,000 

$‐

$200,000 

$400,000 

$600,000 

$800,000 

$1,000,000 

2009 2010 2011

Muskoka Airport ‐ Operating Income (Loss) Over Expenses (Excluding Sale of Assets & Grants)

TOTAL OPERATING REVENUES

TOTAL OPERATING EXPENSES

$545,232 

$656,179 $599,297 

$756,403 

$881,734 $840,266 

‐$211,171  ‐$225,555  ‐$240,969 ‐$400,000 

‐$200,000 

$‐

$200,000 

$400,000 

$600,000 

$800,000 

$1,000,000 

2009 2010 2011

Muskoka Airport ‐ Operating Income (Loss) Over Expenses (Including Sale of Assets & Grants)

TOTAL OPERATING REVENUES

TOTAL OPERATING EXPENSES

PED-9-2013-4B

Page 80: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 49

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

ACAP eligible municipal airports in Ontario ($142.7K in 2010) and this is larger than its competing airport set as will be shown later in Section 2.6.  

It  is  important  to note at  this point, however,  that  it  is  the overall observation of having a  loss  larger than  the  average  that  is  important  when  comparing  against  the  average  among  Ontario municipal airports, not  the percentage or absolute value. Some airports  included  in  the Ontario average may or may not include fleet replacement costs, internal charges, land sales, grants, etc.   

Other reasons for the large deficit can be attributed to: 

Small population base.    In 2011,  the District population was approximately 60,000, excluding the transient and tourist population that occupy cottages and seasonal homes, which can more than double  the number  of people  in  the District during  the busy  summer periods.   A  small population base means there are less households over which to spread the required tax levy to support  the  airport  and  there  are  less  households  to  generate  demand  for  aircraft  services, whether charter, etc. 

Lack of industrial activity.  The District is heavily reliant on tourism (seasonal) and there is very little  industrial or other economic activity  in  the District. This  is a price  insensitive sector  that could increase revenues, if present, both due to the volume of activity and to price insensitivity; 

Relatively small number of based aircraft.  There are approximately about 75 based aircraft at the  airport,  compared  to  Peterborough with  close  to  140,  or  Buttonville with  approximately 250+.  Based aircraft require hangars and fuel, and often use the services of other tenants such as aircraft maintenance and repair; 

Landing fee exemptions and traffic make‐up.  While 65% of the traffic at the Muskoka Airport is itinerant, 76% of the  traffic are not paying  landing  fees  (65% of  itinerant  traffic  is  from piston aircraft); 

Lack of available land.  Muskoka is out of development ready land to lease or sell; and 

Land sale versus  lease policy. While  the  land  sales policy  is certainly a  lure  for  tenants,  sales revenue provides a one‐time  cash  infusion versus an ongoing  revenue  stream. The estimated value of the lost annual revenue due to land sales is in the order of $40K7 per year, or close to 15%  of  the  deficit  (assuming  that  land  sales  account  for  approximately  half  of  the  current developed lands). 

Many of the other municipal airports tend to be smaller than Muskoka and hence tend to have lower operating  costs  as  a  result,  so  that  the  average  size of  their deficits would  tend  to be lower.  

Taking into account all of the above factors, the size of the Muskoka Airport deficit may not in the end be  that much  larger  than  the  average  of  other  airports  as  it would  first  appear,  and  in  fact,  after correcting  for differences  in accounting, grants, etc, could  in  fact be nearly  in  line with many of these other airports. Certainly,  in our  review we did not  find anything out of  line  in  the way  the Muskoka Airport conducted its business and accounted for the various financial items.   

                                                                 7 This is calculated as approximately 10 acres (41,000m2) that are leased instead of sold at $0.9 per m2 annually.  

PED-9-2013-4B

Page 81: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 50

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

It  is  important  to  remember  that municipal airports  in Canada generally do not generate a profit, or even  break‐even  (see  Section  2.6  for  additional  information).    The majority  cannot  cover  operating costs, let alone capital expenditures.  Airports do, however, generate economic value by: 

Improving transportation services to business and recreational travellers, corporations and the general public; 

Being a key piece of infrastructure in attracting new business / industry;  

Providing important emergency medical services to locals that may need to be air lifted to larger centres for important emergency services; 

Employing people  in the community, both at the Airport and businesses  located at the airport; and 

Creating  opportunities  for  itinerant  air  travelers  to  spend  their  money  in  the  community (accommodation, restaurants, entertainment). 

CAPITAL EXPENSES / RESERVE

The Airport’s budget  shows $7.5 million  in planned  capital expenditures over  the next  twenty  years; $6.7M in the first ten years.  (See Table 2‐9). This includes $4M for a runway overlay in 2014 and $2.5M associated with  development  of  the  East  side  lots  (some  planned  for  2012 which  has  not  yet  taken place).  The amounts for the runway work8 and garage roof replacement appear reasonable.  However, the budget  in  years 10  through 20 appears  to be missing  some  items,  such as additional overlays of apron  and  taxiway pavements  that will be  required,  structural/mechanical/electrical upgrades  to  the terminal building, potential upgrades to the airfield electrical system, among others. We will account for these items in the revised capital plan financial assessment in Sections 4.2, 4.3 and 5.     

Muskoka Airport  is not eligible  for  federal ACAP  funding as  it does not  receive year‐round  scheduled passenger  service.  It  is  also  not  eligible  for  Northern  Ontario  Heritage  Fund  Corporation  (NOHFC) funding  due  to  its  geographic  location,  as  are  other  airports  in  the  ‘north’;  however  Muskoka  is considered to be in the ‘north’ for FedNor purposes. This adds to the challenge of funding major capital projects. 

In recent years, Muskoka airport has taken advantage of recent infrastructure programs including: 

$400K  from  the Communities Adjustment  Fund  for  fencing,  gates,  sand  shed  and  equipment shelter; 

$88K from FedNor to extend the taxiway; and  

$560K+  in funding from FedNor and $350K from the Government of Norway for the Passenger Terminal expansion and the creation of the Little Norway Memorial.  

While  infrastructure programs come and go, smart airports are prepared – they know what they need and are ready to submit applications for funding when programs are announced.   Like Muskoka, other airports  in the area have also been very successful  in securing  infrastructure funding; some to a much larger  scale.    For  example,  Collingwood,  Haliburton/Stanhope,  Atikokan  and  Sioux  Narrows  each 

                                                                 8 We suggest consideration of an alternate approach to the runway overlay which could potentially reduce the cost to about $ 2.5M later in this report. Further discussion is provided in the infrastructure/capital plan section (4.2).  

PED-9-2013-4B

Page 82: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 51

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

received $1.3 ‐ $2.5M from the Building Canada Fund (BCF) for runway work; Red Lake received $4.3M for a terminal replacement; Peterborough received $28.6M through  Infrastructure Stimulus Fund  (ISF) for  apron  and  runway  expansion  as well  as  terminal  and  groundside development;  and  Lake  Simcoe received $14M for upgrades and expansion.  

The District has been prudent by setting aside $400‐$550K a year  for recapitalization of assets  (major capital), which is equivalent to approximately 1.1‐1.6% of the replacement cost of the assets (valued at approximately $35M). While  this  is  slightly  less  than  the  rule of  thumb of 1.5‐2%  replacement  value ($525K ‐ $700K), this is much more than most airports budget (and in fact many don’t budget this at all), and assumes that there will be some external funding available. 

PED-9-2013-4B

Page 83: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 52

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

 

Table 2‐9: Current Airport Capital Plan and Planned Expenditures from 2012 Budget  

Opening Balance Uncommited Airport Capital Reserve Fund December 2011 1,538,706$ * plan is to contribute $500K / year from taxes

Capital P lan from 2012 budget + 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022-2031 T OT A L T o tal 2012-2021

Opening Balance $1,538,706 $833,706 $1,158,706 $1,658,706 -$1,841,294 -$1,647,294 -$1,147,294 -$647,294 -$1,164,294 -$664,294 -$164,294

Transfer from Taxes $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $5,000,000

Revenue from Land Sales

Planned Capex -$1,205,000 -$175,000 -$4,000,000 -$306,000 -$1,017,000 -$775,000 7,478,000-$ 6 ,703,000-$

Year-End Balance - Reserve Fund $833,706 $1,158,706 $1,658,706 -$1,841,294 -$1,647,294 -$1,147,294 -$647,294 -$1,164,294 -$664,294 -$164,294 $4,060,706

TOTAL 2012-2031 7,478,000-$

TOTAL 2012-2021 6,703,000-$

* fund should accommodate 10 year capital plan EXCLUDING the rehab of main runway in 2014. $2M from reserve fund, another $2M from Debt Reduction Reserve Fund

does not account for financing from external sources

PED-9-2013-4B

Page 84: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 53

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

2.6 COMPARISONS WITH OTHER COMPETING AIRPORTS IN AREA

MUNICIPAL AIRPORTS IN ONTARIO 

Muskoka Airport is currently owned and operated by the District of Muskoka and is therefore classified as a municipal airport. 

There were 84 municipal airports in Ontario in 2011, excluding the 20+ owned by the Province or in the National Airport System (NAS) airports. As shown in Figure 2‐1, the majority of these airports (46, 55%) are  located  in  the  South, while  38  (45%)  are  in  the North.   Muskoka  Airport  is  considered  ‘North’, although it is quite evidently on the border. 

Figure 2‐30:  Municipal Airport in Ontario 

 

Of  these  84 municipal  airports,  only  19  (23%)  have  year‐round  scheduled  passenger  service  and  are eligible  for  ACAP  funding.  Twelve  of  these  are  in  North  and  7  in  South.  Muskoka  Airport  has  no scheduled service and is not eligible for ACAP funding. The majority (63%) of the municipal airports has runways less than 5,000 ft, but most (80%) are paved. 

Generally the financial situation of municipal airports  in Ontario  is poor. A survey of these airports for FedNor  in 2011  (data  for 2010)  found  that 78%  (42/53) who  responded  considered  themselves  “not financially  self  sustaining”,  i.e.,  insufficient  cash  flow  to  cover  operational  costs,  let  alone  capital expenditures. Only 1 airport responding considered themselves “viable” i.e., able to cover operating and capital  expenditures. Not  surprisingly,  this  airport  had  significant  commercial  activity  and was  ACAP eligible. Eleven responding airports considered themselves “self‐sustaining” i.e., able to cover operating expenses, although  the  financial  reporting  is  inconsistent, and when details were examined,  some of these airports were not in fact self‐sustaining, as in some cases they included “grants” to cover budget deficits as income.  

COMPARATIVE AIRPORTS

The  above material  sets  a  context within which  the Municipal  airports  in Ontario operate, but what about more  direct  competitors  to  the Muskoka  airport?  For  this  study  and  as  a  requirement  of  the Terms of Reference, three airports of similar size and function, were chosen as a basis of comparison to the Muskoka airport, because they are considered competitors from a number of perspectives, including 

PED-9-2013-4B

Page 85: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 54

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

that  they are general aviation airports  that are within a  two hour drive of Toronto, equipped with a paved runway and have experienced significant development within the past five years.  These include the following: 

‐ Peterborough Municipal Airport; 

‐ Lake Simcoe Regional Airport; 

‐ Parry Sound Municipal Airport.  

The airports are discussed in the following paragraphs.     

PETERBOROUGH MUNICIPAL AIRPORT

The Peterborough Municipal Airport is owned by the City of Peterborough and is currently operated by a private property management firm.  By road, the airport is approximately 130 km from Toronto (1 hr/26 min) and 160 km from the Muskoka Airport.  The airport is certified and equipped with a paved runway measuring 2,134 m (7,000 ft) by 30.5 m (100 ft) and a grass runway measuring 543 m (1,782 ft) by 30.5 m (100 ft).   

The airport dates back  to  the 1960’s and supported scheduled airline services  from  the 1970’s  to  the 1990’s.   Currently,  it serves general aviation aircraft and a variety of aviation related activities ranging from  aircraft  maintenance,  manufacturing  and  storage  to  flight  training,  charter  services  and government related aircraft services  (RCMP and air ambulance providers).   According  to the Canadian Civil Aircraft Register, a total of 137 aircraft are based at the airport, comprised of mainly piston aircraft (121),  but  also  some  turbo‐fan  (9),  turbo‐prop  (6)  and  rotary  aircraft  (1).    Non‐aviation  activities encompass light industrial and restaurant enterprises. 

The  airport has undergone  significant development  to  the  airfield  and  commercial  lands.    Starting  in 2009, expansion works totalling $28 million have resulted  in an extension of Runway 09‐27 to 7,000ft, extension  and  strengthening  of  taxiways  and  aprons,  a  new  air  terminal  building  and  four  sites  for commercial development encompassing 26.5 hectares of land.  These works were funded jointly by the City  of  Peterborough,  Province  of  Ontario  and  the  federal  government  through  the  Infrastructure Stimulus Fund. 

The airport plans  to upgrade airfield  facilities and develop commercial  lands  to accommodate Seneca College  flight training and  increase corporate aircraft traffic.   This  includes apron expansion, paving of the grass runway, extension of Taxiway Bravo to a full length taxiway and expansion and renovation of a city‐owned building. 

The  airport’s  2009 master  plan  highlighted  the  future  of  Buttonville  Airport  as  having  a  significant impact on the airport.  Forecasts called for 35,120 movements by 2031 in the medium case and 56,179 movements in the high case.  The planned closure of Buttonville Airport has already resulted in Seneca College’s decision  to  relocate  its  flight  training operation  to Peterborough Airport.   Growth  in aircraft movements has been strong in recent years.  In 2011, the airport recorded 33,717 aircraft movements, more  than  tripling  from 9,910 movements recorded  in 2007.   The bulk of  this growth has occurred  in local movements as growth in itinerant movements has been slower increasing from 5,390 movements in 2007 to 6,657 movements in 2011. 

LAKE SIMCOE REGIONAL AIRPORT

The Lake Simcoe Regional Airport  is  located approximately 115 km from Toronto (1 hr/22 min) and 67 km south of the Muskoka Airport.  Ownership of the airport is shared between the City of Barrie (80%) and the Township of Oro‐Medonte (20%) and operation is delegated to a municipal service corporation, 

PED-9-2013-4B

Page 86: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 55

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Lake Simcoe Regional Airport  Inc.   The airport  is  registered and  is configured with one paved  runway measuring 1,829 m (6,001 ft) in length by 30.5 m (100 ft) in width. 

The airport was constructed  in 1991 following a recommendation by the Province of Ontario’s Ontario Airport  System  Plan,  to  build  a  new  airport  for  the Barrie  area  to  service  a  growing  population  and support economic growth.    It  currently  serves various general aviation aircraft and  supports a mix of aviation activities encompassing aircraft service and repair, charter, manufacture and flight training.  It is also used as a base by the OPP and Hydro One Helicopters.  The Canadian Civil Aircraft Register lists 38 piston powered fixed wing aircraft and 7 turbo‐shaft rotary wing aircraft for a total of 45 aircraft based at the airport.   

The airport has grown significantly in size since 1991.  Expansion works in 1993 extended the runway to 1,524 m (5,000 ft) and introduced a large apron and a new air terminal building.  Since 2009, significant upgrades have been undertaken, including a re‐surfacing and extension of the runway to 1,829 m (6,001 ft), introduction of a partial parallel taxiway and upgrading of fuel equipment and airport infrastructure.  Noteworthy, is the development of four commercial areas encompassing fully serviced and un‐serviced lots for general aviation businesses, light corporate and private aircraft hangar development, large scale commercial developments and non‐aviation related uses including agriculture.  The cost of the upgrades has  totalled  $15 million,  which  has  been  funded  by  the  City  of  Barrie,  Township  of  Oro‐Medonte, Province of Ontario and federal government through the Infrastructure Stimulus Fund. 

The  airport  is  expected  to  benefit  significantly  following  the  Province  of Ontario’s  announcement  in 2012  identifying and defining  the airport as  the “Lake Simcoe Regional Airport Economic Employment District”  a  part  of  Ontario’s  “Growth  Plan  for  the  Greater  Golden  Horseshoe,  2006”,  under  the province’s “Places  to Grow Act, 2005”.   Uses permitted under  this plan are  limited  to airport  facilities and  accessory  uses,  airport‐related  manufacturing,  assembly,  maintenance,  processing,  fabrication, storage and warehousing, airport related training facilities, research and wholesaling establishments and office uses. 

Growth  in  aircraft movements has been  slow  in  recent  years.    In  2007,  the  airport  recorded  19,183 movements and  in 2009, peaked at 24,198 before dropping  to  the 20,500  level  in 2010.    In 2011,  the airport  recorded  20,580  aircraft movements.    Local movements  comprise  a  significant  share  of  total movements, representing approximately 70% of traffic in 2011 and 67% in 2007.  Itinerant movements totalled 6,216 movements  in 2007 and peaked at 7,221 movements  in 2009 before dropping to 6,144 movements in 2011.  

PARRY SOUND MUNICIPAL AIRPORT

The Parry Sound Municipal Airport is also located approximately 67 km from the Muskoka Airport, but is situated north of Muskoka.   Driving distance from Toronto  is 206 km (2 hours/14 min), which makes  it the  furthest study airport  from Toronto.   Ownership  is  jointly held by Seguin Township  (80%) and  the Town of Parry Sound (20%) and operation is the responsibility of the Parry Sound Area Municipal Airport Commission.  The airport is registered and equipped with one paved runway measuring 1,219 m (4,000 ft) by 22.9 m (75 ft). 

Parry Sound Municipal Airport was opened in 1979 with one runway, apron and taxiway.  It is unique in that  it  is connected  to a  float plane base at Robert’s Lake north of  the airfield.   The airport currently serves  general  aviation  aircraft  and  aviation  related  tenants  offering  aircraft  service  and  repair, manufacture and flight training.  A total of 54 aircraft are based at the airport according to the Canadian Civil Aircraft Register, comprised of 53 piston powered fixed wing aircraft and 1 turbo‐shaft helicopter.  A significant area of airport lands constitutes the Airport Industrial Park noted for its use by non‐aviation related tenants carrying out light industrial and manufacturing activities. 

PED-9-2013-4B

Page 87: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 56

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Recent upgrades and expansion works have  focused on  increasing  the number of hangars,  improving provision  of  utility  services  (electric,  telephone,  lighting)  and making  new  power, water  and  sewer connections.    In 2010, a 2 hectare area east of  the  runway was developed  for up  to 21 new private hangars and three commercial hangars.   In 2012, a training facility was  introduced  in addition to three hangars.  New expansion works have been launched to increase hangars and commercial development.  Various sources of  funding have been used,  including Fednor and the Northern Ontario Heritage Fund Corporation. 

The airport is keen to attract more corporate aircraft and plans to extend the runway to 1,524 m (5,000 ft) – 1,676 m (5,500 ft) in the long term.  In 2009, the airport recorded 7,705 aircraft movements. 

COMPARISON 

A comparison of the four airports is summarized in Table 2‐10 below, though due to poor availability of information  from  the Parry Sound Airport,  the comparisons are not as complete as would have been desired. The  following observations  are noted  in  terms of how Muskoka Airport  relates  to  the  three comparison airports: 

‐ All airports are municipally owned, but ownership of Muskoka Airport is by the Regional District, which  encompasses  six  area municipalities, whereas  it  encompasses  only  one  or  two  at  the other airports.  Consensus and decision making may be more easily achieved amongst a smaller group of municipalities than in a larger group. 

‐ Whereas operation of the Muskoka Airport  is managed from a municipal department, at other airports  it  is  carried  out  by  specialized,  independent  bodies,  either municipally  controlled  or private.  Consensus and decision making may be more easily achieved by an independent body.  

‐ While Muskoka  Airport  benefits  from  a  boost  in  local  population  from  cottagers  during  the summer  months,  Peterborough  and  Lake  Simcoe  Regional  Airports  are  supported  by  a significantly larger year‐round population that is experiencing steady growth.  

‐ Cottagers also provide an economic boost to the Muskoka economy, but Peterborough and Lake Simcoe Regional Airports are supported by an economic base that  is more diverse than  in the District of Muskoka and is experiencing growth.  

‐ All airports benefit  from cottage  related  tourism, but Lake Simcoe Regional Airport and Parry Sound Municipal, to some extent represent, provide direct competition to Muskoka Airport for cottage traffic in central Ontario, depending on where the cottages are actually located. 

‐ The Muskoka  Airport  is  a  certified  airport, which  places  it  at  an  advantage  over  its  closest competitors in terms of attracting a scheduled commercial passenger service.  Transport Canada regulations  require  an  airport  to  be  certified  if  serving  a  scheduled  commercial  passenger service (though the 2 registered airports could probably easily be certified, if necessary). 

‐ Runway  length  at Muskoka Airport meets  the maximum  range  capability of most piston  and turbo‐prop aircraft.  Larger jet powered aircraft, such as the Boeing BBJ, however, could opt for an airport with a  longer  runway,  such as Peterborough Municipal Airport, depending on how heavy and far they intended to fly.  

‐ Runway width at Muskoka Airport offers the widest runway at 45 m (147.7m), which provides pilots  with  the  greatest margin  of  safety  during  take‐off  and  landing  operations,  especially during more marginal weather conditions.  This can be expected to attract larger aircraft. 

‐ All airports could  improve  their visual aids  in  support of  instrument operations  (i.e. approach lighting),  but  Peterborough  Municipal  Airport  and  Lake  Simcoe  Regional  Airport  are  better equipped than Muskoka Airport, as each offers PAPI units on both approaches. 

PED-9-2013-4B

Page 88: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 57

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

‐ In terms of navaids, Muskoka Airport compares well with the other airports, in that it is capable of  accommodating  non‐precision  approaches,  but  the  current  limits  are  to  non‐instrument standards  and  consequently  falls behind  Lake  Simcoe Regional Airport, which offers  the best approach limits (370/380 ft, 1.25mi). 

‐ The Muskoka Airport compares well with the other airports in terms of aircraft fuel availability, and FBO/passenger services supported by an attractive new air  terminal building.    It  is noted, however, that it is the only airport without a restaurant/cafe on airport lands. 

‐ The Muskoka Airport  also  compares well  in  terms of  the number of businesses based  at  the airport  and  the  range  of  aviation  related  services  available.    Non‐aviation  related  activities, however, are limited. 

‐ The airport  lags behind  the others  in  its ability  to accommodate new businesses as  the  three other airports have developed elaborate commercial areas  to  serve aviation and non‐aviation related activities.  

‐ The airport  is second to the Peterborough Municipal Airport  in terms of based aircraft, but  its ability to expand this number  is  limited  in comparison to the other airports, which are actively developing commercial lands to accommodate based aircraft. 

‐ The Muskoka  Airport  occupies  less  land  than  the  Peterborough Municipal  Airport  and  Lake Simcoe  Regional  Airport.    This  could  potentially  leave  it  at  a  disadvantage  in  terms  of accommodating new development9.   

‐ The Muskoka Airport ranks third  in terms of aircraft movements recorded  in 2011.   Growth  in movements is slow in comparison to Peterborough Municipal Airport, but comparable to growth at Lake Simcoe Regional Airport. When we look more closely at the make‐up of traffic at these airports and how the different segments of traffic have been growing, we find: 

o The  Lake  Simcoe  &  Peterborough  traffic  is  primarily  local  traffic  (70‐80%),  while Muskoka  has  double  the  number  of  itinerant  movements  and  only  ~30%  of  total movements are local, which puts it on a better financial footing (as local traffic does not pay any  fees) and  itinerant movements  tend  to bring  tourist business activities  to  the region; 

o Total  traffic  has  been  very  variable  at  Lake  Simcoe  &  Peterborough  due  to  the fluctuation in local traffic 

o Local movements were declining at both Lake Simcoe & Peterborough  in the past, but have increased sharply at Peterborough since 2008 due to Kawartha Lakes Flight Centre Expansion and will increase further with Seneca College’s move to Peterborough 

o Itinerant traffic over the past 5‐10 years has increased 50% at Peterborough, but has not changed  significantly  at  Lake  Simcoe  and  Muskoka,  though  in  aggregate,  Muskoka currently (2011) handles almost twice the itinerant traffic that the other airports handle; 

o Muskoka  has  experienced much  stronger  growth  in  turboprop movements  than  the other  2  airports,  with  Muskoka  currently  handling  over  2000  annual  turbo  prop operations to Peterborough’s 535 and Lake Simcoe’s 774; 

                                                                 9 Comparable site area was not available for Parry Sound Airport. As well, detailed traffic data was also not available for Parry Sound that would allow a more direct comparison like at the other 2 airports.  

PED-9-2013-4B

Page 89: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 58

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

o Muskoka  handles  a  significantly  larger  number  of  jets  than  Peterborough  and  Lake Simcoe,  recording  633  jet  movements  in  2011  compared  with  393  and  243  jet movements at Peterborough and Lake Simcoe, respectively.   Growth  in  jet movements at Muskoka is similar to Peterborough and at both airports this has been much greater than at Lake Simcoe.   

‐ Based on limited financial performance figures for the three comparison airports, all the airports operate in the red (though no data was available for Lake Simcoe). However, Muskoka appears to be running the largest deficit on operating revenues (though accounting differences might be contributing  to much of  this difference). But on  the other hand,  the other airports have been investing significantly into expanded facilities (i.e. spending significant capital) so that looking at the bigger picture, these airports are probably running much higher total financial deficits (and as we will see later, Muskoka does not have to invest much into new facilities in the future, so that on a total cash basis  it  is possible that Muskoka may have the  least financial deficit going forward) .    

‐ Upgrades and expansion works at Muskoka Airport have fallen short of those undertaken at the other  airports  in  the  past  five  years,  in  particular,  Peterborough Municipal  Airport  and  Lake Simcoe Regional Airport, where millions of dollars have been spent as noted earlier.  Even Parry Sound Municipal Airport has undertaken extensive upgrades. 

‐ The  three comparative airports currently outpace  the Muskoka Airport with  regards  to  future upgrades  and  expansion  plans,  as  well.  These  airports  are  aiming  to  attract  more  general aviation activity and,  in particular, corporate aviation through runway extensions, expansion of aprons  and  taxiways,  and  an  increase  in  commercial  development  lands  and  hangars.    The commercial development lands are also intended to grow non‐aviation related activities. 

So  in  summary,  compared  to  the  three  competing  airports, Muskoka  appears  to  have  the  following advantages: 

• It has a high concentration of based aircraft servicing firms; full‐service 

• Its provision of specialty services is a plus  

• It has a competitive runway length and width, and good accessibility due to weather 

• It is a year‐round base for public services 

• It is a Customs port of entry (though all but Parry Sound have this)  

• It has branded  fuel  (which  is  important  to attract commercial/corporate  sector and especially turbos and jets, though only Parry Sound does not have this 

• It has a good base of turbo and jet traffic to use as a spring board for additional growth and for revenue purposes  

 

   

PED-9-2013-4B

Page 90: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 59

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Table 2‐10: Comparisons with Competing Airports  

  Muskoka Peterborough Lake Simcoe Parry Sound

Owner/Operator  District  City/Private Operator City (80%)/Twp (20%) Muni. 

Services Corp. Township/Airport 

Commission 

Population 60,000+ (2011)

Seasonal pop can be double 118.975 (2011)+2.1% from 2006 

446,063 (2011)+5.7% from 2006 

42,162 (2011)+3.0% from 2006 

Economic Sectors Tourism 

Forest fire district (MNR) 

Industrial, RetailRegional health centre  

Post‐secondary 

Industrial manufacturingMilitary (CFB Borden) Casino, Post‐secondary  

Tourism, RetailRegional heath centre  

Forest fire district (MNR) 

Aerodrome Status  Certified  Certified  Registered  Registered 

Runway (longest paved)  6,000’ x 150’  7,000’ x 100’   6,000’ x 100’  4,000’ x 75’  

Crosswind  2,200 x 100 turf  1,800 x 100 turf  ‐  ‐ 

Visual Aids, Navaids and Approaches 

Medium intensity lighting;      PAPI  Rwy 18; NDB Best Approach limits: 500 ft, 1.5mi 

Medium Intensity lighting;      PAPI Rwys 09/27; NDB Best Approach limits: 500 ft, 1.5mi  

Medium intensity lighting;PAPI Rwys 10/28;  VOR/DME Best Approach limits: 370/380 ft, 1.25mi  

Medium intensity lighting; APAPI Rwy 36; NDB Best Approach limits: 500 ft, 1.5mi 

Aircraft Services Branded Fuel / oil

Major / minor repair Catering 

Branded Fuel  / oilMajor / minor repair Catering by FBO 

Branded Fuel / oilMajor / minor repair 

Catering 

Fuel / oil Major / minor repair 

Passenger Services 

New terminal (vending, Wi‐Fi)AOE/15 and Customs 

Car rental& taxi (call‐out) Access to off‐site restaurant 

New terminalAOE/15 and Customs 

Taxi, car rental (call‐out) Restaurant 

Executive passenger lounge(Free Wi‐Fi), AOE/24 and 

Customs Car Rental x 3 

Newly renovated business centre 

Taxi, car rental (call‐out) Café 

# of Based Businesses  9  17  8  10 

# of Based Aircraft (CCAR)  76  137  45  54 

Traffic (Total2011)  17,019  33,717  20,580  7,805 (2009) 

Traffic (Itinerant)  11,282  6,651  6,138  ‐ 

Land 223 h (550 acres)  

Limited Developed land  Sale / lease 

276 h (682 acres)26.5 ha (57 lots) – 4 sites incl. 

30 acres of serviced Airport industrial park 

240 (595) Commercial Development Plan: 4 areas; serviced and un‐serviced lots 

Recent private & commercial hangar development; training facility; industrial expansion 

Financial ‐$287K in 2011 (excl. grants & 

sale of land revenue) ‐$200K in 2009  ‐ 

‐$100K (if remove grant, sale of land, & tax revenue 

Other  Little Norway Memorial $28M expansion (2009 ‐ ) 

Seneca College flight training  

$15M Expansion;  “Airport Economic Employment 

District” 

Airport Industrial Park; numerous hangars; Float 

plane base 

PED-9-2013-4B

Page 91: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 60

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

On the other hand, it is weak in a number of particular areas, as follows:  

• It currently does not have available developed  land, though we will show some 35+ acres can easily be brought on stream, 

• It does not have as large a population base on which to draw activity from, though tourism is a growing sector to exploit, and 

• It does not have the industrial base that airports like Peterborough and Lake Simcoe have   

So what can we conclude from this comparison?  

• For  its  size and  location,  the airport has good competitive  facilities,  in many ways as good or better  than  its  competitors,  especially  in  terms  of  runway  length/width/strength  (only  Lake Simcoe has better approaches in poor weather and Muskoka could easily match this); 

• It has a very good concentration of local aviation businesses that can form a nucleus from which to expand;  

• Given  its  population  base,  it  has  a  reasonable  amount  of  traffic  to  form  a  basis  for  future growth; 

• Increased  tourism  should  probably  be  a  key  focus  for  future  growth  and  turbo  prop  and  jet operations should be a focus within this.   

2.7 STAKEHOLDER CONSULTATION

In a study of this nature, stakeholder consultations typically involve identifying key stakeholder groups, like  tenants, airlines, adjacent property owners, business associations,  regulatory agencies, etc.  In  the case of  the  latter groups, where  there  is  really only one entity within each  category,  representatives from each of  these groups would be  interviewed. However, with  the  former groups, where  there are typically many participants or members, a representative sample, such as 30‐40%, would generally be interviewed.   For  this particular study,  it became clear at  the very early stages of  the study  that  there was a  lot of interest  in the study from current tenants, and that that there were very diverging opinions about the airport and what its future should look like as identified through reading past material on various plans and proposals  that had been put  forward and had been rejected. These views about diverging visions were  re‐enforced  after  our  initial meeting with  key  staff,  the  Planning  and  Economic  Development Committee and the Airport Advisory Committee.    As a  consequence of  this, a decision was made  to deviate  from  the original  stakeholder  consultation plan and  instead put  together a much broader plan that would solicit  interest and  input  from a much wider group of stakeholders. The groups consulted and the means for the consultations were as follows:   

General Public: 

o Feedback was obtained through an on‐line survey designed by the consultants;  

Tenants: 

o One on one  interviews were  carried out with  a  long  list  (majority) of  tenants.  These 

interviews were mostly in person, but a number were also via phone. As well, meetings 

were also held with representatives of  the adjacent Beaver Creek & Fenbrook Federal 

Institutions to inform them of the process, solicit their input and to discuss any issues. 

PED-9-2013-4B

Page 92: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 61

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Visiting Pilots 

o These  were  interviewed  in  person  as  they  arrived  at  the  terminal,  using  a  survey 

developed by the consultants;  

Visiting Travellers 

o The same survey was used here as  for  the pilots,  the only difference being  that  these 

visitors  would  have  been  passengers  on  visiting  aircraft,  rather  than  the  pilots 

themselves;  

Economic Development and Tourism Staff 

o Input  from  this  segment was  solicited using a  survey designed by  the  consultant and 

circulated  to members of  the  relevant economic development units at  the  six District 

Municipalities  and  the  Tourism  agency  via  email with  responses  by  email  and  some 

phone follow‐up; 

Elected Officials and District Management 

o One on one  (generally phone)  interviews were  conducted with each of  the Municipal 

Mayors,  the District Chair  and  a number of  senior  staff.  There was no  formal  survey 

questionnaire used,  but  the discussions were used  to  identify  the  various hot  issues, 

concerns, expectations, etc, with respect to the airport, including finances, governance, 

services, operations, costs, etc.        

GENERAL PUBLIC

A survey of  the general public was conducted  in August  to September 2012. Members of  the general public were invited to participate in an on‐line web‐based survey through notices at the airport, in local newspapers and through word of mouth. A total of 37 responses were received.  

Most (80%) of respondents were from the local area  

Bracebridge 32%, 

 Gravenhurst 16%, 

Muskoka Lakes 14%, 

Lake of Bays 8%, 

Huntsville 5%, and  

Georgian Bay 5%.  

All respondents indicated they use the airport,  

the large majority (60%) use the airport occasionally,  

while 32% use it regularly.  

Their reason for using the airport was mixed:  

40% use it for leisure,  

35% for business, and  

25% both.  

With respect to the Little Norway Memorial at the terminal: 

PED-9-2013-4B

Page 93: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 62

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

66% of respondents indicated that they had visited it; 

23% said they knew of the memorial but had not visited it, and 

11% indicated they were not aware of the memorial.  

Of the people that visited  it, many thought that  it was an excellent,  interesting feature that makes the terminal unique. Some thought that it could be expanded and advertised more to tourists.  

The respondents saw the role of the Muskoka Airport to be: 

A service that is a must for the community to support economic growth and generate revenue; 

A gateway to cottage country; 

Municipal infrastructure which has the potential to be expanded; 

A service to local pilots and encourages tourism. 

70% of respondents  indicated they were aware of the economic contribution the airport brings to the community and that they benefit directly from it. Reasons indicated included: 

Aircraft is based at YQA; 

Access to cottage country (friends, family, etc, in the area); 

Purchase fuel, oil, etc and some take a taxi into town for the day; 

Opens up potential for new businesses and growth of current ones; 

Uses for emergencies (police, fire, medical, etc). 

Three‐quarters  of  the  respondents  indicated  that  they  think  the  airport  is  a  positive  economic contributor to the local economy for the following reasons: 

The airport supports businesses and creates employment; 

It is a critical part of Muskoka’s infrastructure to grow, and  

It generates revenue. 

But at the same time, some saw some negatives from the airport such as:  

It did not generate enough revenue to outweigh the total costs, and  

They believed it has future potential, but this is not currently being realised.  

Some 70% of respondents said they would support airport expansion for the following reasons: 

Expansion would attract new businesses and pilots to the area; 

There is land available to easily grow airport activities; 

It would generate more revenue and employment; 

They see potential for commercial flights in the future; 

Expansion would capitalize on aviation related businesses looking to relocate. 

70% of  respondents were aware of  the  community  support  services  that were available  through  the airport, such as emergency response/medivac, etc, and they felt that these benefitted the community.  

Some general comments provided by respondents at the end of the survey were as follows: 

PED-9-2013-4B

Page 94: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 63

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

The airport should be run by non‐government or be private;  

Some saw governance as a key issue; 

More promotion should be done to make people aware of the airport; 

A restaurant would be a key asset; 

The airport needs an appropriate plan for the future. 

It should be noted that while the survey was open to the general public, it is evident from some of the responses  that  these were  generally provided by people using  the  airport or have  an  interest  in  the airport,  and  as  such,  the  results  tend  to  reflect  the  opinions  of  that  group,  rather  than  the  general public. 

TENANTS AND BUSINESSES

Tenants and adjacent businesses were  interviewed one on one during a site visit  in early August 2012 together  with  later  phone  interview.  A  total  of  10  one  on  one  interviews  took  place.  In  addition, information was also garnered from tenants and businesses through an online survey that they could fill in  anonymously  or with  their  contact  information.    There were  a  total  of  13  online  questionnaires completed.  As  part  of  this  process we  also  held meetings with  representatives  of  the  Beaver  Creek Federal  Institution  located  immediately to the south of the airport so that they were aware of the on‐going study and so that we could raise and discuss any  issues that may be of concern with respect to growth at the airport.      

The tenant and business respondents indicated that they saw the strengths of the airport as:  

Location; 

Runway length and orientation; 

Economic potential; 

The fuel services offered; and 

The fact that it had a runway maintained year round.  

They saw the key weaknesses of the airport as being:  

Development restrictions (how and what they could develop); 

Lack of available land to grow; 

Lack of a restaurant; 

Lack of a full length taxiway; 

Management and political issues at the airport; and 

Lease policy and term issues.  

The tenants wanted to see the following changes at the airport in terms or new facilities and services:  

Credit card or keylock for self serve fuel; 

Restaurant and / or a meeting area; 

More organized events to draw aircraft in and promote the airport; 

PED-9-2013-4B

Page 95: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 64

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Operational  and  management  changes,  including  a  commission  instead  of  municipal government; 

The acquisition of land to protect for future growth prospects for the airport.  

Tenants were asked about  their aircraft movement growth prospects over  the next 10 years, under 2 scenarios:  a  status quo with no  changes  to  facilities  and  services,  and with  all of  the  above  changes implemented. The responses for the projected aircraft movement growth were as follows:  

                        3 years    5 years    10 years 

Status quo with no changes             24%       25%         26% 

With all of the above changes            71%       83%        105% 

When  asked  about  the  additional  opportunities  that  the  tenants  felt  the  airport  could  serve,  the responses were as follows:  

Air shows, fly‐ins and other events; 

A restaurant to attract both GA and local community; 

Additional private hangar businesses; 

Further development of Runway 09‐27 to attract more businesses. 

Roadblocks that the tenants raised that would affect opportunities included: 

High costs; 

Weather and the seasons; 

Airport  staffing; 

Political  ‐ changes in council lead to repeating same issues over and over; 

Lack of a vision of the future of the airport; 

Lack of openness and information from management. 

INCOMING PILOTS

Incoming pilots were surveyed by airport  staff  during  August  and September  2012  when  their duties permitted. Responses were collected  through  in‐person interviews with pilots and a  total of 20 were collected. 

Flight  characteristics  obtained from  the pilots  surveyed were as follows: 

Origin: 

o 55%  were  from Canada;  

o 45% Ontario, and  

PED-9-2013-4B

Page 96: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 65

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

o 45% from the US (mainly bordering states). 

Aircraft Type: 

o 40% arrived using jet aircraft;  

o 30% turboprops; and  

o 25% pistons. 

Aircraft Ownership: 

o 37% rented the aircraft (e.g. ,NetJets);  

o 21% were corporately owned,; 

o 26% privately owned; and  

o 16% aircraft owned by charter company operating the aircraft.  

Duration of stay: 

o 65% stayed less than 24 hours, with 20% of these staying less than 1 hour; and  

o 35% stayed over a day; 

o 47% indicated the aircraft will make a quick turn and depart after dropping passengers off or re‐fuelling and a short visit; while 

o 53% said the aircraft would stay for the duration of the occupants visit to Muskoka.  

On average, the pilots flew 10 trips/year to YQA (for  a total of 203 trips over 20 respondents), but for 25% of the pilots this was their first time this year. 

Trip purpose: 

o Tourism  was quoted  by  80%  of respondents  with the  following breakdown: 

Cottage 53%,  

General tourism 20%,and  

Golf 7%). 

The  main  reason  pilots  chose  to use  YQA  was  because  of  its proximity  to  their  cottage  or  that of  their  passenger’s.  Only  15% indicated  that  they  considered other  airports  and  chose  YQA due to airport services, runway length, terminal/FBO, fuelling facilities, the location and fees.  

PED-9-2013-4B

Page 97: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 66

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

The  incoming pilots rated the airport  infrastructure and services very highly  (with an average score of 4.6 out of 5). The length of runway, overall terminal and customer service received scores of 5.0, while the lowest score was for rental cars which received a score of 3.9. 

Half of  the pilots  indicated  that  they  felt no  improvements were  required  to  the airport. Those pilots who noted they’d like to see changes said they would like to see: 

‐ more apron tie‐downs;  

‐ a parallel taxiway; 

‐ closer car rentals;  

‐ an ILS; and  

‐ a pilot rest area & showers.  

No negative comments were provided, but many positive comments were provided, including that they liked the customer service (one of best in area), pilot lounge and wi‐fi. 

INCOMING VISITORS

As with the survey of  incoming pilots, visitors arriving by aircraft were surveyed by airport staff during August and September 2012 when their duties permitted. The survey form and process was the same as with  the  incoming pilots, except  that  in  this case  the passengers were  interviewed, as  the pilots may have been busy or the flight was a charter, in which case the pilots felt the passengers were the best to answer the questions. These results should actually be read with the incoming pilots results.  There were a total of 15 interviews collected in this manner, so that with the pilot interviews, the total was 35.  

Flight characteristics of the visitors were as follows: 

73% were from the US;  

a third of these were staying less than 1 day and a third were staying 7 days or more; 

53% arrived on jet aircraft, most owned by NetJets, LJ Aviation, Shoreline or privately; 

The main reason for the trip was to go to a cottage in the region / tourism; 

On  average  these  visitors  flew  to  YQA  8  times  per  year  (117  total  trips  over  15  responses), although for 25% it was their first time this year. 

The main  reason  visitors  gave  for  using YQA was: 

proximity to their cottage (53%); 

the availability of  immigration & customs services (20%),; 

for visiting friends or to play golf; and 

it was a suitable airport for flight training. 

Feedback  on  the  airport  facilities  and services  was  all  positive  –  almost  all 

PED-9-2013-4B

Page 98: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 67

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

indicate no  improvements needed, except extended Customs hours. Positive comments  included: nice museum, friendly service and staff and that the airport was very accommodating during their visit.  

ECONOMIC DEVELOPMENT AND TOURISM STAFF

Economic development and tourism staff of the District of Muskoka and Towns and Townships within the district were contacted to collect  information on significant economic developments  in the region, how  these developments could affect demand at  the airport, and how  the airport can be used as an economic driver for their community. A total of 6 responses were received. 

Main points provided were as follows: 

Tourism is very important for Muskoka and the Region is quite highly rated: 

o In 2012 National Geographic  voted Muskoka as one of  the 10 Best Trips  for  Summer 2011; and 

o The Muskoka Bay Club was voted the 9th best course  in Canada by Score Golf Top 100 Courses in Canada in 2012’ 

The airport is highly important for tourism as this becomes a key access; 

The economic sectors benefitting from the airport are:   

o Tourism: lakeside resorts, lodges, and cottages; and golf 

o Construction:  the  airport  helps  to drive demand  for high  end property development; and  

o Aviation: aviation industries that would locate at the airport will drive jobs.  

There  is no key manufacturing  left  in the area – previously these companies were key users of charter aircraft at YQA, and it would not appear that any might return, though obviously airport related would be a key; 

Major  tourism  developments  under  consideration  in  the  area  could  increase  demand  at  the airport. Some of these include: 

o Possible  development  of  71  acres  of  prime  waterfront  known  as Muskoka  Regional Centre in Gravenhurst; 

o Bigwin Island Development – a golf course and with residential development with ¾ of the lots still unsold; 

o Patterson Key Lodge, recently renovated as potential to attract more visitors; 

o But there are no significant manufacturing opportunities on the horizon. 

With  the closing of Buttonville Airport  in Toronto,  there  is optimism  that some of  these users and their aircraft might choose to relocate to Muskoka.    

ELECTED OFFICIALS

Discussions were held with  9  elected  officials  in  the  region  and  some  key  senior  staff  and  the main points raised were as follows: 

Recognition of the economic importance of airport; 

Financial viability concerns as the airport is losing some$ 800k/yr; 

PED-9-2013-4B

Page 99: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 68

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Funding formula vs perceived benefit and related equity issues across the municipalities;  

The issue of selling vs leasing land; 

Governance was a big concern; 

Airport promotion seemed to be lacking; 

An appropriate infrastructure plan needed to be defined; 

On site restaurant should be provided. 

2.8 SUMMARY OF CURRENT SITUATION

The following summarises key aspects of our review of the current situation at the airport:  

FACILITIES AND INFRASTRUCTURE

• The current facilities at the airport are generally in fairly good condition, with many of these 

having been recently upgraded; 

• The length of the runway, its width and the associated services provided, including fuel 

(branded), Customs clearance, and full service place the airport on par or better than many of its 

competitors;   

• Key deficiencies or items requiring addressing, include:   

• The main runway is in need of a major overlay/rehab to repair the pavements (planned for 2014/15); 

• The main aircraft apron is approaching capacity during busy summer peaks;  • Runway capacity is an issue during busy summer weekends, with lack of a parallel 

taxiway considered as one of the key constraints to this runway capacity (more discussion later in future options);  

• The grass runway is a key asset that should be maintained in order to provide improved accessibility/availability for the airport  (more discussion later in future options);   

• The airport has run out of developed land to service and support its operations (options are developed later in development discussion). 

EXISTING TRAFFIC

• Traffic at the airport has fluctuated widely in last 10+ years: • Traffic peaked in the late 1990s and is still below this level today. 

• Base line trends suggest traffic may just barely return to the previous peak within next 20 years: • But the make‐up of today’s traffic is much different than past traffic and this make‐up 

will continue to evolve:  o With fewer small piston aircraft,  o More turbo‐props and jets , and probably steady local operations. 

• In comparison to other Ontario municipal airports:  

• The airport compares favourably to others, generally performing better in some areas 

such as proportion of itinerants, steady local, increasing turbo‐props and jets . 

• In comparison to other North American (NA) GA airports:  

• Traffic make‐up and growth generally is consistent with other similar NA airports.  

PED-9-2013-4B

Page 100: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 69

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINANCIAL

• The airport has consistently run an operating deficit, with this deficit at over $ 300k in 2009, but 

dropping gradually to under $ 300k by 2011; 

• This is consistent with most Municipal airports in Ontario, where the average deficit is estimated 

at about $ 143k per year (though much of  this difference could be due to accounting 

differences); 

• Contributions to the capital reserve fund of some $ 500k per year increase the total funding 

deficit to close to $ 800k per year;  

• The airport has access to a number of federal capital assistance programs, but is restricted from 

participating in some, and is generally not eligible for any provincial assistance programs.  

OTHER COMPETING AIRPORTS

• Other competing airports in the area have been very aggressive with expansion plans to cater to 

growth in  traffic; 

• These airports have been able to generally get 2/3 funding from a mix of federal and provincial 

programs to fund these expansions; 

• These other airports are generally governed by a mix of airport commission, private 

operator/airport authority, or municipal services corporation; 

• All of these airports have more developed land available than Muskoka; 

• These other communities also generally have a better industrial and employment base on which 

to build traffic; 

• However, Muskoka compares favourably with these airports in terms of facilities, mix of traffic and based businesses and tenants. 

STAKEHOLDERS

• Users and stakeholders at the airport are generally satisfied with the airport and the services 

provided, with some key differences among them; 

• The general public is reasonably knowledgeable about activities at the airport and they 

generally support the airport and possible expansions; 

• In‐coming pilots and visitors rate the airport quite high in terms of facilities and services 

offered; 

• Tenants and businesses located at the airport are reasonably happy with the facilities 

and services provided, however they have a number of issues related to: 

o Governance; 

o Leases , and  

o Development plans; 

• Elected officials are generally concerned about the airport’s: 

o Financial viability; 

o An equitable funding formula, and 

o Governance.     

PED-9-2013-4B

Page 101: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 70

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

 

SUMMARY  

So in summary, we believe that: 

The airport has reasonable facilities for its current requirements; 

These facilities put the airport in a good position to compete with other airports in the area; 

But it needs additional developed lands to meet forecast requirements; 

The existing tenant and business base at the airport provides a strong base from which to grow; 

The existing traffic mix at the airport is strong and trending in a positive direction; 

The airport financial situation is consistent with other Municipal airports, and this is improving, 

though 

The airport is challenged in terms of programs for capital assistance; 

Most users are generally happy with the airport’s facilities and services; though 

There are a number of issues to deal with from the tenant’s and businesses at the airport.      

PED-9-2013-4B

Page 102: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 71

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

3.0 OPPORTUNITIES, FORECASTS AND FACILITY REQUIREMENTS

3.1 AIRPORT VISION AND OBJECTIVES

It  is  important to understand the  long term vision established for the airport by the District Council as this vision is what is intended to shape any activities at the airport, as well as to direct any key decision making, whether it be related to future development, current operations, negotiations for new tenants, etc.  

From the 2006 Business Plan the stated vision for the airport was as follows:  

“Continue  to be a  commercial airport which promotes and  supports  the  social and economic needs of the District of Muskoka”. 

In 2008, in the District’s Strategic Priorities, Goal 3 was stated as follows:  

“Develop  the Muskoka Airport as an economic development  tool  that supports  the social and business needs of Muskoka”. 

In the 2012 Strategic Priorities, the District again reinforced the following vision as part of Goal 3: 

“…..develop the Muskoka Airport as an economic development tool that supports the social and business needs of Muskoka”. 

It  is clear from the above that the District has established a very clear vision for the airport that states that the airport is to be developed as an economic development tool to support the social and business needs of the District of Muskoka.    

From  this  statement  and  others,  it  is  also  clear  that  the  District  views  the  Airport  as  an  important contributor to the business and social fabric of the community and that it is a part of a greater focus on tourism and business and is an important element of the overall transportation system in the District.   

This vision  is consistent with  that established by many municipal governments  for  their airports, with the realisation that airports are an  important contributor to the social and economic well being of any region.  

 

3.2 FUTURE OPPORTUNITIES

In any business  there are always  future opportunities  for expansion or  to grow  the business whether they  are  only  limited,  as  in  the  case  of  sunset  industries,  or  very  significant,  as  in  the  case  of  new innovative  industries, such as high tech and the  internet.   The challenge  in any  industry, and especially airports,  is to  identify the specific opportunities that exist  in that  industry and within the specific  local and region context that the airport or industry operate.  

For  the  Muskoka  Airport,  we  have  tried  to  identify  future  opportunities  through  a  number  of approaches as follows: 

We  used  an  investment  attraction model  developed  in  consultation with  FedNor,  for  use  by airports  and  communities.    This model  includes  a  two‐step  process  that  first  evaluates  the community’s strengths  in the aerospace sector; and then assesses a community’s readiness to attract new investment.  

o The  District’s  aerospace  strengths  or  assets  were  broken  into  four main  categories (aerospace  product  and  services;  airport  infrastructure;  aerospace  training  and 

PED-9-2013-4B

Page 103: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 72

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

education supply; and location / access); each with its own set of criterion.  While each criterion within the main categories  is scored equally on a scale of 0‐5, the number of criterion in each main category determines the importance of the category in the overall score.  Airport  infrastructure  represents  41%  of  the  total.    For  this  step  of  the assessment,  Muskoka  Airport  was  compared  to  Parry  Sound,  Peterborough,  Lake Simcoe, Oshawa, Kingston, Niagara District, and Haliburton/Stanhope.   Muskoka ranked 5th out of 8 as shown in the summary table below. Details are found in Appendix E.  

Table 3‐1:  Aerospace Strength Comparison  

 

o The investment readiness component of the model uses the criteria/investment factors found in Ontario’s Local Economies in Transition Initiative (LETI) combined with a series of aerospace and aviation opportunities.  As shown in the summary table below, the top five opportunities  for Muskoka  are: Hangars,  FBO, MRO  services,  Flight  Training,  and Aircraft Sales.  Details are found in Appendix E. 

Table 3‐2:  Investment Readiness Analysis 

 

 

We assessed investments, expansions and related activities at competing airports in the broader  region to see what they were undertaking, such as: 

o Peterborough has extended  their  runway  to attract  larger  corporate  jets  to meet  the demands  of  their  corporate  and  industrial  businesses,  and  they  are  also  planning  to pave their crosswind runway to attract Seneca College flight training; 

MUSKOKAPARRY SOUND

PETERBOROUGHLAKE SIMCOE

(BARRIE)OSHAWA KINGSTON

NIAGARA DISTRICT

HALIBURTON / STANHOPE

AEROSPACE PRODUCTS & SERVICES

15 12 18 13 17 11 9 4

AIRPORT INFRASTRUCTURE

25 19 27 25 22 25 22 11

AEROSPACE / AVIATION TRAINING & EDUCATION

3 4 5 6 6 4 4 3

LOCATION / ACCESS 3 3 4 5 6 7 5 4

score 46 38 54 49 51 47 40 22rank 5 7 1 3 2 4 6 8

INVESTMENT FACTORS(from Ontario's Local Economies in Tarnsition

Initiative (LETI)WEIGHT

12121212121212121212

120rank

2.7 12.0

Air

craf

t M

anu

fact

uri

ng

&/o

r A

ssem

bly

Exp

and

ed P

ost

Sec

on

day

S

pec

ialt

y / T

ech

nic

al

Bas

e fo

r P

ub

lic S

ervi

ces

(med

evac

, fire

fight

ing,

M

RO

Ser

vice

s (in

cl. a

/c c

onve

rsio

ns,

Flig

ht

Tra

inin

g

8.7 1.8 7.2 1.1 8.4 11.16.7 7.1 9.0 10.7 10.8 3.9

Aer

on

auti

cal R

ecre

atio

nal

Han

gar

s (p

rivat

e / c

orpo

rate

)

[OT

HE

R]

Mai

nte

nan

ce B

ase

for

Sch

edu

led

Car

rier

sA

viat

ion

Eq

uip

men

t M

anu

fact

uri

ng

Co

ld W

eath

er T

esti

ng

Air

Car

go

Bas

e / L

og

isti

cs

Cen

tre

Tes

t F

ligh

ts

Air

craf

t S

ales

LABOUR FORCELOCAL INDUSTRY 8.0 4.8 10.2 6.0 6.0 4.8 1.8

FB

O

(incl

. avi

atio

n fu

el)

Aer

on

auti

cal R

&D

Aer

osp

ace

Su

pp

ly C

hai

n

En

try

6.6 4.5

TRANSPORTATION / DISTRIBUTION 10.5 12.0 12.0 8.4 12.0 8.4 2.2 8.010.8 11.4 2.6 5.4 8.0 9.48.0 4.4 9.8

12.0 12.0TAXES 12.0 12.0 12.0 12.0 12.0 12.0

11.6 12.0 12.0 12.0 12.0 10.412.0 12.0 12.0 12.012.0 12.0

UTILITIES 12.0 12.0 12.0 12.012.0 12.0 12.0 12.0

LOCAL BUSINESS ENVIRONMENT 9.9 10.5 10.4 10.8 10.5 10.8 10.8 9.912.0 12.0 12.0 12.0 12.0 12.012.0 12.0 12.0 12.0 12.0 12.0

11.3 10.1PROPERTY AVAILABILITY AND COST 9.6 9.7 7.3 8.1 7.3 8.1

10.8 10.8 9.8 9.0 10.1 10.19.4 9.4 12.0 7.512.0 7.5

12.0INCENTIVES / BUSINESS SUPPORT PROGRAMS 9.6 9.6

9.4 9.6 11.0 8.5

12.0EDUCATION & TRAINING 8.0 8.0 10.0 10.0 7.8 10.0 10.0 8.4

9.6 9.6 9.6 7.3 12.09.6 9.6 9.6 9.6 9.6 9.67.5

12.0 12.0 12.0 12.0QUALITY OF LIFE 12.0 12.0 12.0 12.0 12.0 12.07.8 8.0 11.6 11.0 9.0 10.0

12.0 12.0 12.0 12.012.091.2 96.4 89.3 98.8 87.9 110.288.7 97.7 94.9 99.6 102.0

15 2 3 10 16 8 1 17107.6 95.3 85.8 96.8 111.0 0.0

14 7 11 5 4 12 9 13 6

PED-9-2013-4B

Page 104: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 73

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

o Lake Simcoe has been investing heavily in additional land to satisfy anticipated aviation related  industries  locating there and  is also planning to extend their runway to be able to accommodate larger aircraft; and 

o Parry Sound has been developing  large areas of additional  land to accommodate more aircraft  hangars  and  as well  they  hope  to  accommodate  a  range  of  aviation  related industries.    

We  considered  general  trends  in  the  broader  aviation  industry  and more  specifically  in  the general aviation component;  

o Here  we  know  that  with  the  baby  boom  generation  retiring,  there  will  be  lots  of shortages for jobs like pilots, mechanics, sales, management, etc.;    

o Decline  in  private  and  small  piston  aircraft  usage  and  increase  in  corporate,  share ownership and charter turboprop and jet aircraft usage.  

We held discussions with key airport stakeholders. Opportunities arising from these discussions indicated: 

o There  is  a  keen  interest  to  expand  the  existing  maintenance,  repair  and  overhaul activities at the airport, mainly on the painting related side, but in other related areas as well; 

o There is a lot of demand for additional hangars and T‐hangars to store private aircraft; 

o There are additional opportunities for flight training activities. 

We reviewed activities and trends at Southern Ontario Airports in general to identify that: 

o The closing of Buttonville Airport will provide opportunities for Muskoka to provide land for hangars for private and possibly some corporate aircraft;  

o Capacity constraints at the Billy Bishop Toronto City Airport, will force some private and corporate customers to relocate their aircraft and associated hangars; 

o Policies  at  Toronto  Pearson  favouring  big  commercial  traffic  will  lead  to  continued relocation of corporate and other traffic to outlying airports;  

o Some airports  in  the  region have been expanding and actively pursuing  the displaced traffic (e.g., Peterborough and Lake Simcoe), while other airports are not (e.g., Oshawa).  

A summary of our findings for this opportunities analysis is summarized in the discussion below.  

ENHANCED MAINTENANCE REPAIR AND OVERHAUL (MRO)

Our experience at airports  is  that  the greatest opportunities  for expansion at an airport are  typically from entrepreneurs who currently  live with  the community and are based at  the airport. Some great examples of this can be found in: 

Kelowna with Kelowna Flightcraft (one of the largest large aircraft operators in Canada outside the major carriers and a large MRO);  

Abbotsford with Cascade Aerospace, another large MRO operation, and specialist in fire fighting aircraft; 

IMP (Halifax), among others; and  

PED-9-2013-4B

Page 105: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 74

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Muskoka  Aircraft  Refinishing  (MAR)  and  Lake  Central  Air  Services  (LCAS)  are  good Muskoka examples. 

These businesses resulted from local entrepreneurs who lived in the community having an idea to invest in  a  particular  opportunity.  They  lived within  that  community  and wanted  to  live  and  invest  there. Looking at these businesses, there is no over‐riding reason for these activities being located where they are other than the fact the owner for family and life style reasons wanted to stay in the community.   

At Muskoka, there is significant opportunity to work with MAR and LCAS to expand their MRO services and  facilities  as  there  is  a  great  interest on  the part of  these  companies  to  expand  at  the Muskoka Airport. But in addition, other local businesses such as Grassroots Aviation and Freedon Flite might also be  interested  in  expanded  opportunities,  especially  if  their  larger  counterparts  succeed  and  provide opportunities  for synergistic  investments.     Known demand  from MAR and LCAS  is  for probably  in the range of about 5 acres +/‐ adjacent to their existing facilities.  

These known developments from MAR and LCAS would lead to: 

Retention  of  existing  anchor  tenants  who  could  otherwise move  elsewhere  if  they  cannot expand at Muskoka Airport; 

Additional land development, and therefore additional land rents or land sales;  

Incremental fuel sales and associated revenues, as well as additional landing fee revenues and possibly parking revenues; and  

More jobs at the airport and within the community and the associated economic spin‐offs from these jobs. 

HANGAR DEVELOPMENTS

Based on our discussions with current stakeholders and potential investors, as well as our assessment of the  implications of Buttonville, Toronto City Centre and Toronto Pearson airports, we feel that there  is significant  potential  for  new  hangar  developments  at  the  airport. Many  of  these  could  be  for  small private aircraft, such as float planes currently  located along the many  lakes  in the area, or relocations from the noted airports above; to  larger aircraft that might relocate  from Greater Toronto Area  (GTA) airports. We  also have  identified  that  there  are  investors  and  stakeholders out  there who would be willing to put their money down to build and operate some of these facilities 

These investments would lead to: 

Additional land development, and therefore additional land rents or land sales; 

Incremental  fuel  sales  and  associated  revenues,  as  well  as  additional  landing  fee  revenues (although most based aircraft are exempt from paying landing fees), and AMC revenues; 

Incremental taxes; 

Increased tourism in the area and the subsequent economic spin offs; and 

These  new  users  would  also most  likely  seek  support  and maintenance  from  some  of  the existing tenants so there would be synergistic effects.  

There  is,  however,  competition  from  other  airports  and  to  capture  these  opportunities,  the  District would need to develop sufficient lands to handle these additional users. In addition, the District would need  to advertise and market  these  lands and  then be very proactive and aggressive  in wooing  these new potential tenants.  

PED-9-2013-4B

Page 106: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 75

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

EXPANDED FLIGHT TRAINING

There  is currently one  flight  training school  located at  the airport.  In addition  to  this,  there are other schools that come up and carry out flight training activities here  like the Brampton Flying Club, Seneca College, the Waterloo‐Wellington Flying Club, among others.  

Visitors to Muskoka are generally affluent and are a good market  for  flight training.  In addition, there are forecasts for  large  looming shortages of pilots both  in Canada and  internationally. Flight schools at some airports, like Seneca College at Buttonville (relocating to Peterborough) and possibly others, need to relocate or in some cases may wish to relocate with increasing traffic at their current home airports. Muskoka with its relatively uncongested airspace could easily attract additional flight training, especially based flight training. But it would require a paved second runway to attract such additional training, as a minimum, and appropriate buildings and associated apron space.  

The benefits of additional flight training activities would be:  

Additional land development, and therefore additional land rents or land sales; 

Incremental fuel sales and associated revenues;  

Increased awareness of tourism in the area and the subsequent economic spin offs; and 

These new users would most  likely seek support and maintenance  from some of  the existing tenants so there would be synergistic effects.  

AIRCRAFT SALES

There are a number of  local businesses established on the airport that currently conduct aircraft sales related activities, such as Grass Roots Aviation, Aztec/Nomad and Freedom Flite (ultra lights). There may be  some  opportunities  to  attract  additional  businesses  like  these  if  enough  land  were  available. However, aircraft sales operations are usually tied to the airport closest to the manufacturing site. There are  existing  and well‐established  sales  and distribution networks;  therefore  this  is  considered only  a small opportunity.  The benefits would be similar to the ones noted above for the other uses, but on a much smaller scale due to the lower intensity of these activities.    

EXPANDED FBO ACTIVITIES

The airport  is currently operating a full service Fixed Based Operator (FBO) services at the airport with the  provision  of  fuelling,  catering,  aircraft  handling,  and  cleaning  services.  From  the  pilot  and  user interviews,  it  is  quite  evident  that  the  airport  is  doing  a  great  job  in  this  area  and  has  an  excellent reputation  for  its services. There  is an opportunity  to better promote and market  the services, which may  attract  additional  traffic  and  consequently  increased  revenues  from  fuel  sales,  landing  fees, catering, etc.  

There is one service that a typical FBO also provides that is currently not being provided: hangar space to  store aircraft. There  is also potential  to provide  such  space and associated  services. But  then,  this service  may  best  be  provided  by  working  closely  with  the  private  sector  to  provide  the  hangars themselves, in concert with the hangar spaces noted above in the second item in this discussion.  

While  there  is  potential  as  noted,  the  seasonality  of  the market  in Muskoka  is  a  real  challenge  to establishing a full FBO type facility as seen at many other airports. Continuing to market and expand the current airport run approach would appear to be the best way to continue to exploit this opportunity.       

PED-9-2013-4B

Page 107: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 76

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

ORGANIZED PROMOTIONAL EVENTS

The importance of airport and community promotion and the contributions to the local economy cannot be over stressed. Many communities sponsor air shows and fly‐ins, etc, to promote not only their airport and associated facilities, but the community itself. Such events can be expensive to put on, but there are lots  of  volunteers  out  there  to  help with  such  activities,  including  the  fund  raising  associated with putting on such events. This minimizes the net investment required for these promotional events.  

These activities can contribute  to  the bottom  line of  the airport by  increasing  landing  fees,  fuel sales, parking  fees, etc, especially over the  longer term, due to the awareness that they bring. These events themselves can also contribute direct economic spin offs  to  the communities  involved. An airport  like Muskoka needs  to do everything  it  can  to  try  to  attract every  last  landing  fee,  fuel  sale, etc.    to  try maximize  revenues  and  to  help  make  ends meet,  as  the marginal  cost  of  attracting much  of  this additional  revenue  is  typically  less  than  the  incremental  revenue. Such promotional events  should be used to spur traffic in off peak periods, if possible, but in any case, the events should be off peak so as to not interfere with peak traffic.  

The airport has done a commendable job in the past with hosting a variety of events. Recent examples include: 

Grand Opening of Little Norway Memorial (2007) 

G8 Summit (2010) 

Touch‐A‐Truck (2010/2011/2012) 

Dockside Festival (2004) 

Cadet Ceremonies & Exercises (2010/2011/2012/2013) 

School Tours (Public Schools & College Programs) (several annually) 

Youth Groups Tours (Girl Guides, Scouts, etc.) (several annually) 

Onsite Club Tours (Probus clubs, Rotary clubs, etc.) 

Offsite Club Presentations (Probus clubs, Rotary clubs, Church groups, etc.) 

OPP and Military Training Exercises (several annually) 

Norwegian Memorial Plaque unveiling (2012) 

Interprovincial Air Tour (2012). 

In order to capitalize on the opportunities and benefits associated events, the airport should continue to work  closely  with  community  groups  and  associations  like  COPA,  Muskoka  Tourism,  Chambers  of Commerce, and set up and continue to support appropriate committees of volunteers to both fund raise for and to organize the various events.  

INCREASED TOURISM

The prime industry in Muskoka is tourism. As such, the District is committed to increasing tourism in the region  through a variety of promotional efforts. While many of  the  tourists may arrive by  land based means, such as cars and buses, there will be an important portion that will choose to arrive by air, such as  the  more  affluent  segment  and  those  travelling  long  distances,  particularly  from  the  US.  This increased tourism will not only benefit the District, but will have positive implications for the airport in terms of  additional  aircraft movements which will  result  in  increased  revenues  for  landing  fees,  fuel sales, parking fees, etc.    

To capitalize on this opportunity the airport would have to work cooperatively with Muskoka Tourism, Chambers of Commerce, etc to market and advertise the airport.  

PED-9-2013-4B

Page 108: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 77

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

SELF SERVE AVGAS

Many airports that we have worked with have self serve (card lock) AvGas facilities. The advantages of such facilities are that they can provide service 24 hours per day (could be a guaranteed fuel stop), even when there are no staff on site, while during peaks they could reduce staff requirements, and the fuel could  be  offered  at  a  lower  price  than  a  full  service  operation would  charge  (like  at many  car  gas stations). We understand that the current contract with Imperial Oil does not permit self service, but it is an opportunity to consider for the longer term when the current contract expires, as this could lead to lower  costs  (freeing  up  staff)  as well  as  increased  sales.   Our  discussions with  local  users  and  pilots indicated a very strong desire for such an opportunity.    

OTHER OPPORTUNITIES

As  part  of  our  assessment, we  looked  at  other  opportunities  that were  deemed  to  probably  not  be feasible over the short term. These were as follows: 

• Scheduled  airline  service  –  The  airport  is  too  close  to  Toronto  to warrant  airline  service  by majors  like  Jazz or Porter, etc. Compounding  this,  the market  size  is much  too  small and  the directionality (low loads in off‐peak direction) and seasonality (summer only) are also concerns. In all  likelihood, there may eventually be some demand to warrant such services, but probably with smaller aircraft (in the 15‐20 seat range) and probably not within the next 10 years. Service by  larger aircraft, such as Porter Airlines’ 70 seat Q400s, would probably be  in the very distant future unless there were some very large tourist related developments in the area.   

• Base  for aircraft manufacturing &/or assembly – Typically such activity would require a higher population base  (year‐round)  than available at Muskoka and  the availability of  skilled  labour. This would be true  for  larger manufacturing/assembly operations, however smaller operations such  as  the  activities  currently being undertaken by Grass Roots  and Aztec/Nomad10 may be viable.  

• Post‐Secondary Aviation / Aerospace Training  (incl. MRO, engineering, airport management) – We feel that based on our experience at other airports and during other work, that this area is already  generally  well  served  in  Ontario.    However,  this  does  not  necessarily  rule  out  all activities  in  this  sector.    For  instance, MAR’s  proposal  for  an  aircraft  painting  course  at  its proposed facilities tends to be unique and seems to be a good niche to explore.  

• Expanded  base  for  public  services  –  The  airport  is  already  home  to  the Ministry  of  Natural Resources and Northern Air Solutions (which operates some EMS services on behalf of ORNGE), so there would appear to be little opportunity to attract other public services.   

• Maintenance base  for  scheduled  carriers – Similar  to  the manufacturing point above,  the  low year‐round population and access  to pools of  skilled  labour works against  the Muskoka area. However,  the  proposed MAR  investment  at  the  airport  is  a  niche  and  is  NOT  the  kind  of maintenance requiring larger pools of skilled workers. This is a matter of scale.  

                                                                 10 Found Aircraft Canada, a manufacturer of  small bush planes  looked at Muskoka before  settling on Parry  Sound  for  its  operations.  Their  decision  to  locate  elsewhere  was  primarily motivated  by  the availability of NOHFC funding, which wasn’t available to Muskoka. 

 

PED-9-2013-4B

Page 109: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 78

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

• On‐site restaurant / café – The visitor surveys and discussions with some stakeholders/tenants clearly  indicated  that  there  is  a desire  to have  an on‐site  restaurant/café. Other  airports  like Parry Sound have a full service restaurant. However, in our assessment, we feel that the existing restaurant down the road (along the highway) may serve needs adequately or at least this works against the provision of an on‐site facility. More discussion is provided on this item later in the report.  

To summarize, the following are a number of key findings from the above discussion:   

• There are a lot of potential opportunities for the Muskoka Airport to pursue in order to expand operations and investment at the airport;  

• A  lot of  the potential development and whether or not  it  is  realized depends on  local entrepreneurs and whether or not they “step up to the plate” and are then supported;  

• An  important  key  to  airport  expansion  is  building  on  activities  and  uses  you  already have. This brings you better returns, and  is easier than attracting new users, activities, etc.; 

• The types of opportunities available need to be qualified in terms of the potential scale of activity, with the obvious potential generally being  for a “smaller scale” rather than one you might find at other larger airports, due primarily to the low population base and consequent small pool of skilled workers; and 

• To  capitalise on opportunities  the  airport must  first have  the  appropriate  facilities  in place, or at least a plan to develop these facilities and then it must aggressively market itself and pursue the potential opportunities.  

         

3.3 FORECAST AIR TRAFFIC ACTIVITY

FORECAST TRAFFIC UNDER STATUS QUO SCENARIO

TRAFFIC AND ECONOMIC GROWTH

Aviation  traffic  is  generally  related  to  economic  conditions  with  activity  increasing  when  economic conditions  improve and  it decreases during economic downturns.   This  relationship was examined by comparing  itinerant and  local aircraft movements at YQA with Ontario and Canadian GDP over the 16 years, 1997 to 2012 – see Figure 3‐1. The relationship with Ontario and Canadian GDP was found to be very weak. Movements declined  in  2002‐2004 while  economic  growth was  strong  and  there was no decline  in  movements  in  2009  during  “the  great  recession”.  The  correlation  between  GDP  and movements was negative  for  itinerant movements, which makes no sense, and was only 0.1  for  local movements.  The  results  were  almost  the  same  for  both  Ontario  and  Canadian  GDP.  Clearly,  the dependence of traffic at YQA on the overall economy  is weak and  is overwhelmed by dependence on local factors.  

FORECAST MOVEMENTS – BASE CASE

The  expected  numbers  of movements  at  YQA were  estimated  under  a  Status Quo  scenario  for  the airport where there are no changes  in runway  layout, minimal changes  in  land available at the airport for commercial development and no major tenants  leave the airport, or new ones are attracted to the airport. The forecasts assume general trends continue with: 

GDP increasing from 1.9% in 2012 to 2.5% in 2014, then declining gradually to 1.9% in 2032, and 

PED-9-2013-4B

Page 110: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 79

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Very slow growth in total movements, with piston declining and turboprop and jet movements increasing 

 

Figure 3‐1:  Comparison of Aircraft Movements at YQA and Economic Growth 

 

 

 

Figure 3‐2: Actual and Forecast Movements at YQG, 1997 to 2032, Under Status Quo Scenario 

 

 

 

 

80

90

100

110

120

130

140

150

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012

GDP In

dex (100 in

 1997)

Movements

Itinerant Local Ontario GDP Index Canada GDP Index

Source: Statistics Canada

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

20,000

98 00 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 32Year

Local Helicopters Piston engines Turbo‐propellers Jet engines

Local

Helicopter

Piston

Turboprop

Jet

Actual Forecast

PED-9-2013-4B

Page 111: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 80

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Under this scenario, jet aircraft movements  increase at an average rate of 4.0% per year, helicopters at 3.2% per year, and turboprop aircraft at 2.8% per year. Movements of piston aircraft are forecast to decline by 1.8% per year, while local movements increase very slowly at 0.5% per year. Overall, both itinerant and total movements increase by 0.4% per year. 

The current and  forecast numbers of movements by aircraft segment are presented in Table 3‐3. 

 

 

Table 3‐3: Forecast Movements by Aircraft Segment under the Status Quo ‐ Base Case Scenario 

Status Quo – Base Case   Annual Movements 

Current  Forecast 

   Segment  2012  2017  2022  2027  2032   

   Jet engines  683  850 1,033 1,241 1,472    Turbo‐propellers  2,772  3,221 3,670 4,118 4,567    Piston engines  7,861  7,217 6,626 6,083 5,584    Helicopters  934  1,120 1,313 1,516 1,727    Local  4,197  4,334 4,471 4,607 4,744    Total  16,447  16,742 17,112 17,565 18,095 

 

FORECAST TRAFFIC UNDER MEDIUM AND HIGH SCENARIOS

Opportunities  identified  in  the  previous  sections  were  used  to  create  Medium  and  High  Case development  scenarios  for use  in preparing  forecasts of potential  traffic  at  the  airport.  In  each  case assumptions were made about the capture rate of the various identified opportunities. 

For both the Medium and High Case scenarios,  it  is assumed that the  following types of opportunities are realized: 

MAR development goes ahead 

This spawns additional support developments 

T hangar and private hangar developments are initiated 

For the Medium Case, it is assumed that  

The take‐up of commercial lands on the airport increases from 22 to 37 acres over the next 20 years. This corresponds to development which is 25% slower over the next 20 years than during the past 20 years.  

Flight training activity stays at current levels.  

Activity levels are assumed to increase consistent with the new level and type of business activity at the airport.  

For the High Case scenario, similar assumptions were made to the Medium Case, except that: 

Land take up is about 25% higher over next 20 years as compared to that over the last 20 years (increasing from 22 to 47 acres), with a similar mix of activities to that of the Medium Case 

Average Annual Growth 2012‐2032 

Jet engines  4.0% 

Turbo‐propellers  2.8% 

Piston engines  ‐1.8% 

Helicopters  3.2% 

Itinerant  0.4% 

Local  0.5% 

Total  0.4% 

PED-9-2013-4B

Page 112: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 81

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Flight training is assumed to return to historic highs reached in the late 1990s.      

The implications of these levels of development on air traffic at YQA are shown in the figures below.  

For itinerant movements: 

The Base Case forecast has these growing from 12,250 to 13,350 movements in 20 years 

The Medium Case  forecast projects  these  to grow  from 12,250  to almost 14,600  in  this same period, while 

The High Case suggests itinerant operations could approach 16,000 in 20 years 

Figure 3‐3: Forecast Movements by Scenario  

 

With respect to Total Movements: 

The Base Case forecast grows these from some 16,450 to about 18,100 in 20 years 

The Medium Case forecast has these growing from 16,450 to over 19,000  in this same period, while 

The High Case suggests total operations could approach 22,000 in 20 years  

A more detailed breakdown of the forecast traffic by engine category is provided in Figure 3‐4 and Table 3‐4 below. In summary, we forecast that: 

Jet  traffic will  continue  to  grow  at  a  higher  rate  than  total  traffic  and  account  for  a  higher proportion of total traffic under all scenarios than today 

Turbo‐prop traffic will experience a similar trend, while 

Piston‐engine  traffic will  decline  under  all  scenarios,  but moving  from  the  base  case  to  the medium  to  the high case,  this segment of  traffic would consistently account  for higher piston volumes (but again less than today, even in the high case)  

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

20,000

22,000

2012 2017 2022 2027 2032

Total Movements

Base Case Medium High

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

2012 2017 2022 2027 2032

Itinerant MovementsBase Case Medium High

PED-9-2013-4B

Page 113: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 82

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Local movements would grow from today’s levels, but only marginally in the base and medium cases, with much higher activity in the high scenario.   

While these traffic forecasts still do not represent significant growth, even  in the high case at just 30% more  traffic  than  today’s  levels,  the  segments  that have  significant  revenue opportunities are  in  fact growing the  fastest and will  impact the revenue side much  faster and better than the cost side  (to be illustrated later).  

Figure 3‐4: Forecast Movements by Engine Type  

 

 

Table 3‐4: Forecast Movements by Engine Type  

Year 2012 2017 2022 2027 2032 2017 2022 2027 2032

Redevelopment Scenarios Medium Case High Case

Jet engines 683 849 1,026 1,237 1,398 888 1,121 1,335 1,561 Turbo-propellers 2,772 3,189 3,689 4,330 4,796 3,309 3,917 4,509 5,172 Piston engines 7,861 7,436 7,148 7,106 6,675 7,703 7,587 7,431 7,372 Helicopters 934 1,077 1,259 1,491 1,708 1,100 1,297 1,514 1,770 Local 4,197 4,697 4,724 4,780 4,780 5,900 5,946 5,983 6,029 Total 16,447 17,247 17,847 18,944 19,358 18,899 19,868 20,772 21,904

 

3.4 FORECAST FACILITY REQUIREMENTS

Airport facility requirements are driven by a number of factors, including the need to: 

Handle  current  traffic  levels at  the airport  in a  safe,  reliable and consistent manner, under a variety of weather and wind conditions, 

Provide various facilities for differing users such as aircraft, passengers, cargo, etc, 

Accommodate  these  various  uses  through  the  provision  of  an  adequate  land  base,  surface access and appropriate utilities and services, such as power, water, sewer, etc, and 

Expand to handle increased traffic levels at the airport. 

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

Jet engines Turbo‐propellers Piston engines Helicopters Local

Movements by Category2012 2022 Base Case 2022 Medium Case 2022 Hign Case

PED-9-2013-4B

Page 114: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 83

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

The  following discussion presents our  forecasts  for  additional or expanded  facilities  at  the  airport  to handle both existing  traffic  levels  in a better way and to also meet the requirements of the projected growth forecast for the airport. The topic is dealt with further in sections 4.2 through 4.4 where how to, when to and at what cost to provide the additional facilities is dealt with.  

AIRFIELD

RUNWAYS

A  sufficient  number  and  adequate  lengths  of  runways  at  an  airport  are  key  to  an  airport’s  success. Without  these,  the airport may not attract or be able  to handle  the  traffic  that may wish  to use  the airport. The “capacity” of this runway system then also affects the  level and number of other facilities that will need to be provided. 

First let’s look at the number of runways required for the Muskoka airport.  

The airport currently has the main runway (18‐36) which  is a 6,000 ft long x 150 ft wide paved runway oriented in a north/south direction. The airport also has a secondary grass/dirt runway (09‐27) oriented east/west and located in the south portion of the airport lands. 

Transport Canada recommends that runways should provide at  least 95% usability for the aircraft that the  airport  is  designed  to  serve.  Rather  than  get  into  a  detailed  technical  analysis  here,  we  have provided a lot of detail on the wind analysis and requirements in Appendix K.  

From the analysis, we have concluded that it is desirable to have a second runway at the airport in order to provide  increased usability and coverage over a broad  spectrum of wind conditions. We have also shown that this second runway can be oriented anywhere  from 09‐27 to 12‐30 and provide the same incremental increase over the usability provided by the main runway alone. 

Now, what about the length of these runways? 

The  conventional  approach  to  runway  length  design  is  to  define  the  “critical”  aircraft  and  then determine its runway length requirement. Our preferred approach is to study a whole variety of aircraft as our experience is that there is never really just one “critical” aircraft, especially at a general aviation airport like Muskoka.     

Figure 3‐5 compares the runway length requirements of the different aircraft using Muskoka airport and the  frequency  of  the  associated  aircraft  movements  that  these  particular  aircraft  represent.  This information is built up from our extensive data base of other studies that we have carried out on runway length  requirements  for a wide variety of aircraft at a wide variety of airports. The data  in  the graph matches up the runway length requirements with the actual movements of the aircraft types using the Muskoka Airport. A detailed  table with all of  the aircraft,  their  runway  length  requirements, and  the frequency of use at Muskoka is provided in Appendix G.   

This graph shows that there are quite a number of aircraft (close to 1,000 per year) currently using the airport  that  require more  than  the 6,000  ft now available,  if  they were  to operate at  their maximum capabilities. However, many of these aircraft, whether they are the Netjets bizjets, private jets, or even the larger Air Canada jets (like the A320s) coming in for painting at MAR, are flying from generally close by destinations (like nearby US states or Montreal/Toronto) so that their fuel requirements and hence weights are reduced, so that they can operate on a shorter runway.  

On  the basis of  this  analysis, we  recommend  that  the  length of  runway 18‐36  should be  considered sufficient to satisfy the current and probably  forecast requirements as the main runway. We  feel that shortening the runway would not appear to make any sense as  it could potentially exclude some very lucrative  traffic  to  the airport. On  the other hand, extending  the  runway  could make  sense  in  that  it 

PED-9-2013-4B

Page 115: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 84

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

could attract aircraft from further afield than just the nearby US states or provinces. This is what other airports  like  Peterborough  are  counting  on.  However,  given  the  financial  implications  of  such  an extension  and  the  potentially  limited  returns,  we  do  not  feel  that  such  an  extension  would  be worthwhile.      

Now what about  the  length of  the crosswind  runway? The crosswind  runway  should be designed  for aircraft that cannot use the main runway during periods of higher winds that would  limit them to use the crosswind runway. As noted above in the wind analysis, the main runway has close to 99% usability for aircraft that can accept a crosswind component of over 13 knots. So these aircraft can use the main runway under virtually any conditions. However, the smaller aircraft that can only contend with 10 kt crosswinds only have about 95% usability on this runway, or less, depending on gusts.  

 

Figure 3‐5: Runway Length Requirements vs Aircraft Movements  

 

 

In looking more closely at Figure 3‐5 and studying the detailed list of aircraft using the Muskoka airport and  their  runway  length  requirements  (see  Appendix  G),  we  feel  that  the  required  length  for  the crosswind  runway would  be  about  2,800  ft.  From  Figure  3‐5 we  see  that  a  3,000  ft  runway would accommodate  about  80%  of  the  aircraft  operations  at  the Muskoka Airport. We  have  chosen  about 2,800 ft as the preferred length as looking more closely at the table in Appendix G there are no aircraft requiring  lengths of between 2,800  ft and 3,000  ft and  in  fact,  there are virtually no aircraft needing lengths of between 2,800 ft and 3,400 ft (as confirmed by the very short bar for 3,000 ft to 3,500 ft  in Figure  3‐8).  A  2,800  ft  runway,  in  accommodating  about  80%  of  runway movements would  in  fact accommodate nearly 100% of  the aircraft which would have a 10 knot crosswind component at  their design crosswind limit.  

As noted in earlier sections, the current crosswind runway 09‐27 is 2,200 ft and some previous reports such as the PSMI report considered a 2,000 ft length as an option for a relocated crosswind. This option is looked at again in the next section on development. Looking closely at the data in Figure 3‐5, we see that  a  2,000  to  2,200  ft  length  would  be  capable  of  accommodating  about  60%  of  total  runway 

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0

500

1,000

1,500

2,000

2,500

3,000

3,500

Required Runway Length (ft)

Annual Movements Cummulative % of Total Mov.

Source: Statistic Canada, Aircraft manufacturer web sites

Current Runway Length

Weight restricted Movements

PED-9-2013-4B

Page 116: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 85

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

movements. If we were to look more closely at the make‐up of these aircraft 9data in Appendix G), we would see that this would account for probably some 80% of the aircraft that would be limited to the 10 knot crosswind criteria for design purposes.            

So  to  summarize  our  recommendations  with  respect  to  runway  requirements,  we  recommend  the following: 

The existing main runway should be maintained at its current length of 6,000 ft 

The width of this main runway should be left at its current width of 150 ft, based on the types of aircraft that are intended to use the airport. 

A crosswind runway with an initial length of about 2,000+/‐ ft should be provided.  This runway should  be  protected  for  an  eventual  length  of  about  2,800  ft  to maximize  usability  of  the airport’s runway system.  

This crosswind runway need only be 75 ft wide to accommodate the types of aircraft that could use it11.   

TAXIWAYS

The current taxiway system serving the airport  is quite  limited, comprising a partial parallel taxiway to the main runway at  its north end and 2 associated connecting taxiways, as well as a taxiway accessing the main aircraft apron and associated development at the south end.  

Based  on  our  experience,  the  capacity  of  this  current  runway  and  taxiway  system  is  about  25 movements per hour during busy periods. As noted  in  the air  traffic section earlier  in  this  report,  the current peak hour for operations is estimated at about 28 movements per hour and this typically occurs on busy summer weekends. The fact that the current system is virtually at capacity is manifesting itself with complaints  from  local pilots as well as  the  fact  that  there are a  lot of missed approaches at  the Airport (though some of these are conducted as a matter of training). 

The capacity of the current runway/taxiway system at the airport could be  increased by extending the current partial parallel  taxiway  to  the main  runway  along  its  full  length. Currently during  north  flow conditions, landing aircraft destined to the main apron must turn around and then taxi on the runway to get to the apron. As well, aircraft  located along the developed  lands to the north must also taxi along the runway for a good portion to reach the south threshold to depart. During south flow conditions, we have a similar but reverse situation where aircraft departing  from the main apron must taxi along the runway to get to the north threshold while aircraft destined for the north lands must taxi on the runway after landing. Extending the taxiway the full length of the runway would allow taxiing aircraft to stay on the taxiway system and avoid taxiing on the runway. This would increase the runway capacity to about 45‐50 movements per hour from the current 28 or so.      

This  parallel  taxiway,  as  a minimum,  could  be  extended  along  the  full  length  of  the  runway  and  be designed  to only accommodate  the  smaller aircraft  (Code B), as  is  the case  currently with  the partial parallel to the north. Alternatively,  it could be designed to handle the full range of aircraft serving the airport (Code C).  

The timing of the need for such a full parallel is affected by a number of factors. The first would be the increase  in  the peak hour  traffic. Given  that  the annual  traffic  is  forecast  to grow  from  some 16,000 

                                                                 11 It may be prudent to protect for a widening to 100 ft in the future should it become necessary. 

PED-9-2013-4B

Page 117: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 86

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

annual movements today to some 19,000 over 20 years (in the medium growth case), the expectation would be that the peak hour volume would grow proportionately to about 33 peak hour movements. With the current volume putting the system at capacity, any  increase  in volume would exacerbate the current situation. However, given the very peaky nature of traffic, the airport should try to manage the peaks and attempt to spread them out more. This will tend to happen naturally if no additional capacity is provided. An  important question would be how  long  could  the  capacity  situation be  tolerated and how would users  react. Given  the  limited projected growth  in  traffic  from maybe 28 movements per hour to only about 33 per hour within 20 years, we would suggest that consideration be given to trying to defer the need for a parallel taxiway for at least 10 years.  

A second  factor  that would affect  the need  for a  full parallel  taxiway could be  the provision of a  fully paved crosswind runway. As will be discussed later in the development plan section, provision of a new runway  in a 12‐30 orientation could off  load the demand on the main runway during the key summer peaks to the point that aircraft could easily taxi along the main runway without causing (severe) delays either along the runway or along the partial parallel taxiway adjacent to it.  

Additional taxiways would be required to serve the various new land developments. These new taxiways are discussed along with the land development plan in a later section of this report.                     

AIRCRAFT APRON

The existing aircraft apron gets very busy during summer weekends to the point that  it  is “bursting at the seams”. This currently only happens for a couple of the summer holiday weekends and during “camp day”. As with the parallel taxiway issue, this capacity issue can be managed through trying to spread the peaks  as  additional  natural  growth  happens. As well, with  additional  development  that will  occur  in terms of expanded MAR  facilities and possibly others,  this may open up opportunities  to share apron facilities during  those  very peaky weekends,  so  that  any  investment  in  expansion of  the main  apron could be deferred  for quite some  time. For  this plan, we assume  that under  the base case, additional apron facilities can be deferred to the end of the 20 year planning horizon.   

The only  factor  that could drive a  real need  to expand  the apron would be commencement of airline service at the airport by someone like Porter that would use large turbo‐props like its Q400s. But this is considered unlikely  in  the short  to medium  term  for reasons discussed  in  the  forecasts section.   Even service by smaller aircraft like 18‐19 seat aircraft may not be sufficient to require an aircraft expansion, depending on what times these services may be scheduled, as these aircraft are in fact similar in size to what one would find on the apron in a typical busy weekend.     

NAVAIDS

The airport currently has a number of instrument approach procedures to runway 18‐36 that provide for approach  limits  of  just  over  500  ft  and  1 ½ mi  visibility. With  these  limits,  this  runway  is  currently unavailable for about 5+% of the time due to cloud ceiling or visibility restrictions. A very low cost means of improving this availability by in the order of 3% to 4% would be to provide LPV (Localizer Performance with Vertical guidance) approaches which have the capability to improve the limits down to about 250 ft and  1 mi  visibility,  depending  on  the  obstacle  environment  in  the  immediate  vicinity  of  the  airport. These  approaches  are  satellite  based  and many  of  the  users  at Muskoka would  probably  have  the required  technology  in  the cockpit of  their aircraft, as  the equipment only costs about $15,000  these days. Definitely, the various jets that currently serve the airport would be so equipped, as would many of  the  higher  end  private  props  and  the  commercial  props.  The  cost  of  providing  these  approaches would probably be in the range of some $25,000 +/‐, depending on competitive forces in the market at time of purchase.  

PED-9-2013-4B

Page 118: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 87

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Given  the  low cost of LPV approaches, the airport should seriously consider providing  these given  the benefits  in increased availability. However, in deciding to provide these, the airport must consider that this  will  move  the  airport  category  from  non‐instrument  to  instrument  non‐precision12.  This  has implications  for  the  Airport’s  AOM,  the  various  obstacle  limitations  surfaces,  and  the  associated additional tree clearing that would be required.            

Runway  lighting  provided  on  Runway  18‐36  currently  consists  of medium  intensity  edge  lights  and medium  intensity threshold and end  lights. There are no approach  lights on either end of the runway. While approach lights would be beneficial in improving the approach guidance, they are not necessary in the case of the current approach  limits. Even with new LPV approaches, should they be provided, the airport could function without these as they would only reduce  limits from 1 mi to ¾ mi  in the case of LPV approaches. At about $ 200k to  install for each end of the runway, these would be expensive and difficult  to  justify.  Instead, we would  recommend  that  the airport  consider  the  installation of RILS  to provide better guidance on approach. At a cost of only $ 20k  for each end of the runway, these are a better investment, at least over the shorter term.  

Runway 18 currently is equipped with a PAPI to aid pilots in making visual approaches to this runway as well as aiding  those using  the  instrument approach procedures  to  this end. Runway 36, which  is  the most  heavily  used  runway,  does  not  have  a  PAPI.  Pilots  using  this  runway would  benefit  from  the installation a PAPI and safety levels would increase. At an estimated cost of about $ 75k, this would not be expensive given the benefits. We believe serious consideration should be given to installing PAPIs on Runway 36 and as a consequence we have included these in the capital budget.   

PASSENGER TERMINAL

The  existing  passenger  terminal  was  just  expanded  and  renovated  in  2007.  This  terminal  should continue  to be adequate  to meet  forecast needs probably  for  the next 20 years  (in  terms of sizing)13. There are only two reasons anticipated that may require the terminal to be expanded. The first would be if the airport were to obtain scheduled airline service in aircraft larger than 19 seats, such as a Porter Airlines operation.  In this case a  large expansion would be required, but  in any case this  is considered highly unlikely  for  reasons discussed previously.    The  second  reason would be  for  the provision of  a restaurant, which has often been mentioned  in the past. This second  item  is discussed further  later  in the development plan.     

                                                                 12 The airport currently has Federal Zoning in place that classifies the main runway at the airport as a Code 3C non‐precision runway. However, due to a number of tree violations on private property located around the airport, the airport has chosen to downgrade the runway classification to non‐instrument. This is consistent with the current instrument approaches that have limits just above 500 ft, or visual limits. To be able to reduce the limits below 500 ft to take advantage of LPV would require that the offending off site trees be trimmed and the airport be re‐classified to non‐precision per the Federal Zoning which is in fact in place.   13 The terminal may require a number of maintenance items over the next 20 years depending on how well the building itself performs and stands up to use. In the capital plan, we have suggested that this building will probably need major roof repairs by the end of the 20 year period, as well as some electrical/mechanical updates, based on our experience at other airports. Provisional budget items and timing have been suggested. But in the end the decision to upgrade or do major maintenance should be based on actual conditions at the time, so that the facility and the capital plan should be reviewed continually to revise on the basis of actual conditions.     

PED-9-2013-4B

Page 119: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 88

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

SERVICES

Given the  limited growth projected for the airport, and the  limited expansion required of key facilities, the various services like fuel, and airport maintenance, etc., should probably be adequate over the next 20 years.    

UTILITIES

The  airport  lands  do  not  currently  have  any  water  and  sewer  connections.  Instead  current  airport developments are  serviced  through  the use of ground wells and  sewer  service  is via  septic  tanks and septic beds.  

There  is a nearby sewage treatment facility that services the Corrections Canada facility  located to the south of the airport. However, the capacity of this  facility  is dedicated  to Corrections Canada.  If there was a desire or a need  to extend  these  services  to  the airport,  then an appropriate  capacity  sharing agreement would need to be negotiated. However, the cost of then extending the services to the airport would be expensive. The current  septic  systems have been more  than adequate  to  serve  the current developments and  the  soils  conditions at  the airport  site are generally quite  conducive  to  the use of septic systems, so it would be difficult to justify the expense of extending sewer services to the airport site.     

Having  said  the above,  the airport may nonetheless want  to at  least make provision  for  the eventual extension of water and sewer services to the site, should environmental regulations change or should local policies be amended to require such provision.  

AIRPORT ACCESS

The primary access to the airport is provided from Highway 11 via Ecclestone Drive (Regional Road 118) to  the Gravenhust  Parkway.  This  route  accesses  the  airport  from  the north. A  second,  though more circuitous, access  is provided  from the south via Highway 11/Bethune Drive  (Regional Road 41) to the Gravenhurst Parkway. This access system should be more than sufficient to meet the long term needs of the airport given that traffic to the airport and the surrounding areas is currently quite light and traffic growth will be limited to only 20%‐30% over the next 20 years.      

DEVELOPABLE LAND REQUIREMENTS

There are a total of about 22 acres of aviation related lands developed at the airport. These are spread over  29  lots, with  2  lots  remaining  undeveloped  (but  there  is  significant  interest  from  a  number  of parties to develop this lot). When the District took over the airport in 1996, there was some 10 acres of the  land developed  for aviation uses. Since that time, the remaining  lands have been developed, with acceleration of development in the last 10 years or so.  

In  terms  of  future  forecasts  for  land  requirements,  this  is  difficult  to  estimate  given  the  many uncertainties  involved with  the markets, how  the District may  react or  take advantage of  the various opportunities we have identified, and what the competing airports may be doing. As a consequence, we have developed a number of scenarios for the demand for future land as illustrated in Table 3‐5. 

The assumptions behind these scenarios are as follows: 

In the medium case, land development happens at a rate which is 25% less than last 20 years; 

In the high case, this development occurs at 25% faster rate than in last 20 years; and 

In the very high case,  land development could experience about 70% more growth than  in the past.   

PED-9-2013-4B

Page 120: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 89

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

 

Table 3‐5: Forecast Aviation Related Developed Land Requirements   

  Additional Land Requirements by Time Period (Acres)  

0‐5 years  6‐10 years  11‐15 years  16‐20 years  Total 

Medium Growth  5  4  6    15 

High Grow  9  6  5  5  25 

Very High Growth  10  10  8  7  35 

 

PED-9-2013-4B

Page 121: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 90

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

4.0 LAND DEVELOPMENT AND INFRASTRUCTURE PLAN

4.1 LAND DEVELOPMENT PLAN

The airport has effectively run out of development ready  land with only 2  lots currently still available. These lots are located up in the current northwest development area. Currently, there is excess demand for additional lots, with a number of current tenants asking for a total of at least 4‐5 lots, totalling in the order of 5 acres or more.  

Over the last few years, the District of Muskoka has struggled to define a plan to respond to the demand for  additional  development  due  to  concerted  public  opposition  and  disagreement  to  any  of  the proposed  development  areas  and  concern  from  Council members  about  the  cost  implications  and business case to support a plan. A key purpose of this current study is to review past planning work and to then recommend a sound development plan with an appropriate business case to justify it.  

Before  getting  into  the development plan,  it may be useful  to  review previous proposals  to develop additional land on the airport. These previous proposals are illustrated schematically in Figure 4‐1.   

PREVIOUS LAND DEVELOPMENT PROPOSALS

THE FIELD LOT DEVELOPMENT

This proposal would have relocated the grass runway to a 14‐32 orientation located further to the north and east of  its current  location. This move would have  freed up  some 9‐10 acres  immediately  to  the south  of  the  existing MAR  development.  Total  development  cost  for  this  proposal would  have  been about $ 2M, including the cost of relocating the grass runway.  

This proposal was defeated primarily by recreational pilots due to their opposition to moving the grass runway and  replacing  this with an orientation  that  they  felt was not appropriate and at a  length  that they felt was too short (just under 2,000 ft vs the existing length of 2,200 ft). 

THE WOODLOT DEVELOPMENT

This development proposal would have created additional  lots  immediately to the west of the current Muskoka Aircraft Refinishing (MAR) development site in the southwest corner of the airport. Total area of the site was about 8 developed acres, providing some 5 lots at an estimated cost of about $ 3.2M.  

Although  this proposal was consistent with  the existing Master Plan and met  the key  requirement  to provide  some additional  lots  to allow MAR  to expand  their  facilities  immediately  to  the west of  their existing facilities, it was judged to be too expensive to proceed. 

EAST SIDE DEVELOPMENT PROPOSAL

The east  side development was  the proposal under  consideration and  review when  the decision was made  to hire  a  consultant  to develop  a Master Plan  and Business Pan  for  the  airport.  This proposal provided some 25 acres of development  in 16  lots  located to the east side  lands of the airport. At an estimated cost of under $ 4M, this plan would have left the existing grass runway in its current location.  

As a result of our initial review of the work carried out to date on development options, a decision was made to take a completely new look at development options for the airport. To start this new process, a list of constraints to development was initially derived so that we could have a clear view of the factors shaping the potential future developments. 

 

PED-9-2013-4B

Page 122: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 91

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Figure 4‐1: Previous Land Development Proposals at Muskoka Airport 

 

 

CONSTRAINTS TO NEW DEVELOPMENT

OBSTACLE LIMITATION SURFACES

Transport Canada is the Canadian agency responsible for airports. It issues all standards and associated documents that dictate how airports are to be designed, operated, maintained, etc.  It  is basically also the licensing body that permits airports and airlines to operate, etc.  

Their document, TP312, Aerodrome Standards and Recommended Practices, 4th ed, March 1993, spells out the various standards that apply to design of airports. A key element important to the development at and around airports is the definition of Obstacle Limitation Surfaces, which define the airspace areas that must be protected  to allow  for  the  safe operation of  flights at  the airport. The Muskoka Airport used to be operated by Transport Canada and to protect these Obstacle Limitation Surfaces Transport Canada enacted Federal Airport Zoning Regulations to protect these areas with federal legislation.    

The  current  obstacle  limitation  surfaces  for  the  airport  are  illustrated  in Appendix  C.  These  surfaces identify the various limits to the location and height of development both on and off the airport. These obstacle limitation surfaces would obviously need to be changed if, for instance, the grass runway were relocated or a new runway be built, etc.          

PED-9-2013-4B

Page 123: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 92

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

ELECTRONIC PROTECTION AREAS

Similar to Transport Canada, NavCanada is the agency responsible for Air Traffic Control, Navigation and Airspace  Management  in  Canada.  In  order  to  protect  the  facilities  required  to  support  the  safe navigation and control of aircraft, they  issue standards and guidelines for the protection of the proper functioning of their various navigation aids. This information is published in TP1247, Land Use in Vicinity of Airports.  

The only key electronic navigation aid  located on the airport site  is the Direction Finder  (DF). This  is a radio frequency transmitter that pilots use to locate the airport. The DF is currently located on the east side of the main runway close to  its south end. As part of the planned development to the east of this runway, NavCanada has agreed to relocate this DF further to the north as shown in Figure 4‐2.  

Figure 4‐2: Electronic Protection Requirements Around the Direction Finder Equipment             

 

The protected areas around this DF specify that no (metallic) structure can subtend angle greater than 1.20 as measured from the base of the antenna and that no metallic structure can be  located within a 365m  radius  of  the  antenna.  The  protected  areas  around  the  DF  are  illustrated  in  Figure  4‐2  as concentric lines around the DF antenna site.   

ENVIRONMENTAL LANDS

There are a number of areas located on and around the airport site that have been identified in previous studies as requiring protection for environmental reasons. These are primarily wetland areas that are important habitat for various local species. In addition, most of the airport site is located on an 

PED-9-2013-4B

Page 124: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 93

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

underground aquifer and as this is an important source of fresh water, it is important to protect against any contamination of this aquifer.   The key areas identified to be protected for environmental reasons are identified in Figure 4‐3.     Figure 4‐3: Environmentally Sensitive Lands at the Airport            

 

LAND OWNERSHIP

This is a key constraint in that the airport must best use its own land reserves before accessing others. This constraint is at best a soft constraint as the airport can choose to buy adjacent lands that it does not own, if it feels that it requires the additional lands. However adjacent land owners may not wish to sell 

PED-9-2013-4B

Page 125: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 94

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

or may not wish to have airport activities located in even closer proximity to them than may be the case today.  So  they  could  resist  any  purchases  or  even  any  proposed  expropriations,  should  the  Airport choose to take this route.      The  current  airport  boundaries  together with  existing  development  features  discussed  below  are  all illustrated in Figure 4‐4.   Figure 4‐4: Airport Boundaries and Current Developments   

 

Beaver Creek & Fenbrook Federal Institutions 

Gravenhurst Parkway 

Existing Developments 

Gravenhurst Parkway 

Existing Developments 

Airport  Boundary 

PED-9-2013-4B

Page 126: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 95

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

EXISTING DEVELOPMENT

 There  are  a  number of  existing  developments  located both on  and off  the  airport  site  that  act  as  a constraint to any new development, as illustrated in Figure 4‐4. These are: 

BEAVER CREEK AND FENBROOK FEDERAL INSTITUTIONS

There are 2 Federal Prison  facilities co‐located on a site  immediately south of  the airport:  the Beaver Creek minimum security facility and the Fenbrook medium security site.  This prison site constrains any expansion of the airport site to the south. Otherwise,  it does not really place any other restrictions on airport development or operations, being one of the very few, if not the only, prison site in Canada that does not restrict the use of the airspace above the prison site.  

GRAVENHURST PARKWAY

This roadway runs primarily north‐south along  the western boundary of  the airport site and currently constrains any expansion of the airport site to the west, as well as basically sterilizing some key potential development lands just to the north of the current terminal/main apron site due to it close proximity to the runway (and the need to protect for a future parallel taxiway extension in this area).  

EXISTING ON-SITE HANGARS AND OTHER BUILDINGS

There  is  quite  a  number  of  existing  on‐site  buildings,  hangars,  etc,  that  also  constrain  new developments. The extent of the existing development is illustrated in Figure 4‐4 as shaded areas.  A number of  these above developments and  constraints might be  considered  soft  constraints  in  that they  could be moved,  eliminated or  adjusted,  if necessary, but  at  a  cost, which may or may not be minor. For  instance,  the Gravenhurst Parkway could be  relocated/re‐routed,  if desired, as part of any future developments to the west of the airport site.       

NEW EMERGING WIND TURBULENCE THINKING

As a result of a number of incidents at Amsterdam (Schipol) Airport combined with concern relating to encroaching development at the airport, the Amsterdam Airport Authority undertook some significant and  ground  breaking  research  into  the  effect  of  tall  buildings  in  the  vicinity  of  runway  ends.  The research, which was  both  theoretical  in  nature  and  then  followed  up with  actual  field  trials  using  a building mock‐up and test flights with a 747 and a Fokker 100, showed that additional protection over and above the typical International Civil Aviation Organisation (ICAO)14 Obstacle Limitation Surfaces was required  to protect against wind  turbulence created by  tall buildings  in  the vicinity of  runway ends15.  Subsequent  to  this  work  in  2006,  the  Amsterdam  Airport  has  adopted  the  proposed  guidelines  to 

                                                                 14 This is the international body tasked with issuing airport standards. Transport Canada standards and guidelines are then generally consistent with these, especially for its international airports.   15 Wind Criteria Due to Obstacles at and around Airports, National Aerospace Laboratory, NLR‐CR‐2006‐261, May 2008  

PED-9-2013-4B

Page 127: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 96

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

protect against wind turbulence effects. Further to this, ICAO has issued this information as guidance to member states and indicated that they are studying the information16.      The guidance issued suggests that the height of development in the vicinity of runway ends be limited to less  than a 1:35  slope emanating  from  the  runway  threshold and centreline and extending down  the sides of  the  runway  for up  to 1500m.  The  implications of  this  guidance  are  illustrated  in  Figure  4‐5, where the height contours are shown around the runway ends and down the sides of the runway.       Figure 4‐5: New Thinking on Restrictions Near Runway Ends due to Wind Turbulence Effects   

   We  should  note  that  this  wind  turbulence  information  is  just  guidance  issued  for  information  for member states to be aware of given the concerns. ICAO has not adopted any standards relating to this information and neither has any other national jurisdiction responsible for airports. The only airport to adopt these as standards has been the Amsterdam Airport, as this is where the problem originated and this  is where  the  key  concern  has  been  identified. However,  given  the  potential  implications  of  this information, we know  that other progressive airports and professionals are definitely considering  this                                                                  16 Criteria for Obstacle Induced Wind Disturbances at Amsterdam Schipol Airport, ICAO Aerodrome Meteorological Observation and Forecast Study Group, Ninth Meeting, 26‐30 September 2011, Montreal, AMOFSG/9‐SN No.25 8/8/11.    

PED-9-2013-4B

Page 128: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 97

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

information.   We  also  feel  that  this  information definitely warrants due  consideration  in  the  case of development  at  the  Muskoka  Airport,  especially  given  the  fact  that  smaller  aircraft  will  be  more susceptible  to  these wind  turbulence effects  than  larger aircraft  . More discussion  is provided on  this topic later in the presentation of options. As well, Appendix H also provides more discussion material.  

DEVELOPMENT PLAN OBJECTIVES

Before discussing alternative development options and attempting to determine which option may be the best option,  it  is  important to establish key objectives for this process that will not only drive how these options are  formulated and generated but  then how  these options are  compared against each other and evaluated to reach a decision on which option may be the best.   The following objectives are proposed for this development plan: 

• The usability of the airport should be maximized in order to be capable of not only handling the current  fleet  of  aircraft  serving  the  airport,  but  also  to  attracting  additional  traffic  that  can contribute important additional revenues to the airport;  

• It  is  important  to maximize  the  amount  of  developable  land  that  can  be  created.  The  land provided should at least meet, if not exceed, the forecast land requirements generated for this study. Meeting  the  forecast  land  needs would  be  a minimal  objective,  but  exceeding  these would be preferred as this provides additional flexibility for the airport’s future growth; 

• The land created for development should be able to respond to the projected mix of uses, which comprises in reasonably equal parts, larger lots for MRO type activities and larger aircraft types,  medium sized lots for private/corporate sized aircraft and possibly aircraft sales, and smaller lots for small aircraft T‐hangars, tie‐down areas, etc.;   

• The plan should attempt to provide the additional land and associated  facilities for a minimum construction cost; 

• Operating and maintenance costs considerations are also important, and the proposed options should minimize these, as well; 

•  The proposals must respect and work within the constraints inherent in the current site, though as  noted  above,  some  of  these  constraints  are  soft  and  may  be  adjustable  under  certain circumstances.  As  well,  the  plan  should  attempt  to minimize  creating  constraints  to  future development, if and where possible ;  

• The plan should present minimum risks to the airport. These risks may come from a number of sources, such as current tenants possibly  leaving due to development restrictions, or  imposing operating penalties or restrictions due to development not considering all appropriate  location factors;  

• The importance of generating additional revenues for the airport cannot be overstated given the airport’s current financial situation. So options must maximize the additional revenue potential associated with the proposed developments; 

• The economic impacts of any proposed developments should be maximized, as in general, it will be difficult for municipal airports like Muskoka to actually generate positive financial results.                

DEVELOPMENT OPTIONS

The  Terms  of  Reference  for  this  study  indicated  that  the  starting  point  for  any  assessment  of development options should be the current plan to develop the eastside lands. This development plan is contained in Figure 4‐6. We have named this plan – Plan A.  

PED-9-2013-4B

Page 129: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 98

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

The key features of this plan are that it:  

Keeps Runway 09‐27 – the grass runway – in its current location; 

Develops the Eastside Area in phases with some 16 lots over 25 ac; 

Would cost close to $ 4M to implement in its final form;  

Could also allow protection  for  future development of Westside Woodlot – 4‐5  lots – 8+/‐ ac. This part has been added by SNC as a  long term protection area,  in case demand was to reach the point where this may be required, so we have shown this as dashed lines. 

The advantages of this plan are: 

2  runways  provide  excellent  usability  at  an  estimated  97+%  (@10kt  crosswinds)  and  99+% (@13kt crosswinds) under the assumption that the grass runway remains a grass runway; 

Smaller aircraft have good access with lower crosswinds than with just 1 runway, though  if the grass runway remains as is the “quality” of this runway and the usability would not be the same as if thus runway were paved; 

It retains capability to extend and even pave the grass strip in the future, if desirable; 

The maximum  length  of  this  runway within  the  property  is  estimated  at  about  3,000  ft  ,  if extended into the rock pile to the west (and using the Beaver Creek Rd as the western constraint and the east property line as the other constraint);   

The plan provides an additional 25 ac of developed land17  compared to only 22 ac now; 

This eastside area  is  relatively  inexpensive  to develop at $160k/ac  (excluding water &  sewer) and it is easily phased: 

o Alternatively, this eastside area would cost an estimated $ 2.5M excluding taxiways, or some $ 100k/ac; 

o By comparison, the created value of the eastside  lands  is estimated at some $ 60k/ac., which is much less than the investment cost. 

Some disadvantages of this plan are: 

It locates the additional lands requested by Muskoka Aircraft Refinishing (MAR) to the eastside and  forces  them  to have  split operations  from  their current westside  facilities, and  they have expressed a desire to keep operations together; 

The taxiway provided to service this development is quite long as it needs to “wrap around” the entire development and becomes the single most expensive element of this plan; 

The plan as  it stands does not appear to fully  incorporate the constraints from the NavCanada DF which restricts the height of the lots to the north of the eastside area to about 9m (this item 

                                                                 17 or 33 additional ac if the 8 ac in the west is included. This woodlot area, would be reserved for future and this is more difficult to phase, given blasting requirements, etc 

 

PED-9-2013-4B

Page 130: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 99

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

was  in  fact  incorporated) with progressively higher development permitted  to  the  south  (this feature did not appear to be completely incorporated in the plan18);  

It does not take into consideration the new wind turbulence information available, which when factored into the plan would NOT permit any lots with development heights to 15m as required by MAR, and any other potentially new MRO type developments.      

 

Figure 4‐6: Plan A‐ Current Plan for Eastside Area Developed by Staff – Adjusted by SNC1   

 1Added dashed Woodlot Development to the west 

 Figure 4‐7 illustrates this Plan A adjusted to reflect the more detailed constraints from the DF as well as the  new  height  guidance  related  to  wind  turbulence.  We  have  labelled  this  Plan  A1.  Other  than 

                                                                 18 We tried to contact NavCanada on numerous occasions during this study and failed to make contact as the individuals we contacted failed to return our calls. We have used our interpretation of their current guidelines as contained in TP1247 in this assessment based on our previous experience in this area. However, we should note that NavCanada has recently been reviewing these various guidelines and updating these to generally be more consistent with international guidelines as published by the International Civil Aviation Organization (ICAO).    

PED-9-2013-4B

Page 131: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 100

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

consideration of this new height guidance and the NavCanada DF, all features of this option would be the same as Plan A described above.    The implications of these 2 constraints are as follows: 

The maximum height of buildings on the eastside would be limited to 5m in the south and west, to about 10m in the north east; 

Uses of  this  land would be  limited  to small aircraft hangars  in  the south and west  to medium hangars (10+/‐m) in the north and east lots, basically all similar to current developments on the airport; 

MRO type hangars for larger aircraft like the A320s (15m+/‐ in height) would not be possible;  

The main  runway, 18‐36, and 09‐27, both contribute equally  to  the  restrictions  in eliminating MAR buildings here.  

 Therefore even this revised option does not respond appropriately to a number of the key development objectives established for this plan.   Figure 4‐7: Plan A1‐ Current Plan for Eastside Area‐ With New Height Guidance   

   

PED-9-2013-4B

Page 132: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 101

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

As a result of our concern about the above plan not being able to satisfy some of the basic objectives of this development planning study, as well as a number of other issues related to the plan with respect to the efficiency of the layout, we decided to reformulate this plan to see how we could best improve it.   One of the key issues with development Plan A and its variants was the height guidance with respect to wind  turbulence.  As  discussed  in  Appendix  H,  we  determined  that  implementation  of  the recommendations  of  the  Amsterdam  guidelines  was  just  too  restrictive  for  the  small  site  here  at Muskoka. While we still  felt  that adherence  to  the principles established  in  the Amsterdam work was very  important, we  felt we needed  to  relax  these guidelines somewhat  for Muskoka  in an attempt  to find a compromise between  this wind  turbulence  thinking and necessary development at  the airport. This  process  led  to  the  consideration  of  1:25  height  guidance  for  Muskoka  instead  of  the  1:35 recommended per the Amsterdam work, as discussed  in Appendix H. This appendix also discusses the implications of not implementing the wind turbulence guidelines.  Figure 4‐8 illustrates the revised Plan A (now labelled as Plan A‐R) that resulted from this re‐thinking and optimisation/improvement process.   Figure 4‐8: Plan A – R:  Eastside Area Plan Optimized   

  In this version of the plan, we have reconfigured the lots for the eastside development to be developed more economically and  to  try  to better  fit with  the proposed height contour guidelines. The previous 

PED-9-2013-4B

Page 133: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 102

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

plan had a  long  taxiway serving  lots  that were oriented  in a different configuration and  the  lots were located only on one side of the taxiway. In this case we have created a partial parallel to 18‐36 and then 2 stub taxiways that then have lots on either side (in the case of the north stub) or they do double duty of  land service and runway access as  in the case of the south stub. The amount of taxiway required  in this case to purely service the lots is much less than the previous option at only about 950m vs 1250m, for a reduction of 25%.   To better illustrate the potential development heights associated with this revised plan, we have added buildings to each  lot that are coded with respect to the maximum permissible heights:  less than 10m, between 10 and 15 and more than 15m.   As before, the DF restrictions limit heights at the north end of the site to about 9m, and in the middle to about 13m.  The new 1:25 wind  turbulence  contours  are  also  illustrated  in  this plan  and while  these contours now allow greater development heights, there are still no lots that would allow buildings of up to 15m, especially taking into account the combined effects with the DF restrictions.  The effect of the new guidelines, reconfiguration and application of DF restrictions still results in most of the  lots  being  limited  to  less  than  15m  in  development  height,  similar  to  most  of  the  current developments in the northwest portion of the airport. In fact, most lots are limited to less than 10m in height,  with  only  4‐5  lots  permitting  buildings  over  10m,  but  less  than  15m.    While  this  is  an improvement over the previous A plan options, this still does not provide sufficient land area for larger MRO type activities, similar to what current tenants like MAR and Lake Central Airways would engage in.    The total area developed for the eastside  lands  in this version  is similar to before at about 24 acres,  in terms of the eastside area itself, but we have added about 3 acres of possible landside development to the south of Runway 09‐27 along Beaver Cr Rd to be more consistent with the other plan to be discussed next.   As noted earlier, we have reconfigured this plan to take the long length of previous taxiway and use this more efficiently. In this version of this plan, we have been able to create a full parallel to 09‐27 so that if and when the runway is paved, it could off load demand on 18‐36 as well as providing a more “into the wind” option for the smaller aircraft.  Runway 09‐27 in this configuration has a maximum length within the existing property of about 3,000 ft, using the Beaver Cr Rd as the western constraint and the east property line (with no tree trimming) as the eastern constraint.       If  land were  to be purchased  to  the east,  this  runway  could be extended  to about 430019+/‐  ft. Care would need to be taken when constructing in these lands to the east, as this is an environmental area. However,  per  the  environmental  report  for  this  area,  much  of  the  work  would  appear  to  be 

                                                                 19 This length is provided for discussion purposes only as similar lengths have repeatedly been suggested by members of the Airport Advisory Committee. However, our analysis in section 3.4 clearly points out that something in the range of about 2,800 ft would probably be the maximum length required to handle the variety of aircraft serving the airport that might not be able to use the main runway during certain wind conditions. 

PED-9-2013-4B

Page 134: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 103

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

concentrated  in areas where  the existing vegetation  is  in abundance and  could afford  to be partially eliminated or relocated20.  If  this  runway were  to be extended  to about 4,300  ft +/‐, as  some members of  the Airport Advisory Committee have suggested, this would result in a classification of the runway as a Code 3 runway (non‐instrument). Per Transport Canada OLS requirements, the runway would then need a 45m strip width each side of the runway and 1:7 transitional surfaces. This transitional surface would be violated by the existing Muskoka Aircraft Refinishing hangar. The limitations imposed by this hangar would restrict this runway to a Code 2 non‐instrument runway with a 30m strip width and 1:5 transitional surfaces each side of the runway. This would limit this runway to a length of about 3900 ft as a consequence.   The estimated development costs for this Plan A‐R are:  

$ 3.5M for the land development, including taxiways (for land access only), roads, drainage, etc., (about $ 145k/acre or $ 85k/acre excluding taxiway costs) and 

$  1.5M  to  pave  the  grass  runway  (2,000+/‐  ft)  plus  another  $  0.7M  to  build  the  associated taxiway access, if and when it is decided to pave these. 

These costs do not include any land acquisition costs associated with extending the grass runway to the east, as at this time we are only proposing a runway of about 2,000 ft. And  in any case, up to 3,000 ft could  be  built  within  the  current  property  boundary  before  requiring  any  additional  land  to  be purchased.   As the above plan and its variations fail to meet the various key development objectives for this plan, we attempted to identify an alternate approach by learning from the shortcomings of the above plan.   Plan B‐R was developed as a result. This plan is illustrated in Figure 4‐9  This plan moves  the grass  runway  to  try  to  create  additional  land  for development.  In  this  case,  the runway is shown in a 12/30 configuration, as this appears to be one of the best options for maximizing runway usability for light aircraft, as noted previously in the analysis of wind direction and usability. The runway is shown as far north as possible to maximize the available development lands to the east. This location and orientation also should also eliminate the need for any off‐site tree trimming at the west of this runway.   This plan has 2 primary development areas:  one that was previously referred to as the Field Lots; and a second area  located to the east of the main runway and to the south of the relocated “grass” runway. We show 2 sub‐options in this plan for developing the lands to the east, as we will discuss in more detail below.   

Figure 4‐9 shows the DF  limitations for this plan, where  it  is clear that none of the development  lands would be limited to less than 15m per the DF restrictions, as all of the proposed development lands are located further away from this facility than they were in the case of Plan A and its variants. 

                                                                 20 Additional review of this interpretation should be solicited from the environmental consultants who undertook the initial study.   

PED-9-2013-4B

Page 135: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 104

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Figure 4‐9: Plan B – R:  Eastside Area Plan Variant by SNC    

     Figure 4‐9 also illustrates the implications of the revised 1:25 contours for wind turbulence. In this case, newly created “field  lots”  just south of the existing Muskoka Aircraft Refinishing (MAR) buildings could be  developed  to  over  15m  in  height  (a  total  of  4  lots  in  the western  part  of  this  area), while  the remaining area could be over 10m, if necessary. We have used the same coding with hatched buildings as in the previous slide to better illustrate the associated building height restrictions.  In the eastside lands, there are about 3 lots that could be developed at over 15m, with an additional 6 at over 10m but  less  than 15. The  remaining  lots would need  to be  less  than 10m, which would  still be quite adequate for many of the envisioned uses at the airport, as most of these buildings are generally less than 10m now.     Two alternate layouts are shown for the eastside lands as follows:  

The first shows space for common type T‐hangars and some apron tie downs, mixed with some mid size lots for private or corporate type aircraft and larger lots for maintenance type activities like Muskoka Aircraft Refinishing, Lake Central Air Services (LCAS) and Grass Roots; 

The  second  layout  (inset)  shows more  individual  lots  that would  generally  accommodate  the same  uses,  but  uses  like  T‐hangars  and  tie  downs  would  be  developed  by  individuals  on appropriate lots. (Some lot development layouts for some of these are illustrated in Appendix J).  

PED-9-2013-4B

Page 136: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 105

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

This plan also includes some landside only lots shown in a pinkish shade. There are 2 groups of these: in the south east portion of the eastside lands and under the Runway 36 approach.   The total lands developed in this plan include: 

25+ acres of primarily airside development for the eastside lands (similar to Plan A‐R)  

9 acres of airside lands in the field lots, and 

about 2‐3 acres under the runway 36 approach that would be landside development only, again similar to Plan A‐R 

The  runway  in  this  option  could  initially  be  about  2,00021  ft  long, with  some minimal  tree  trimming possibly  required  to  the  east  and  north.    If  land were  purchased  to  the  east,  this  runway  could  be extended to a maximum length of about 3400+/‐ ft, using the Gravenhurst Pkwy as the constraint to the west and the Beaver Creek to the east.   Our analysis  in an earlier section showed that about 2,800  ft  is probably the maximum runway  length that would be required for this runway, to provide the wind coverage required for the smaller aircraft using the airport. This would require the purchase of lands to the east22.   The estimated development costs for this plan would be as follows:  

 $ 3.6 M  for  the eastside  lands  (this  is  similar  to  the costs  in Plan A‐R and  the per acre  costs would also be similar)  

 $ 1.7 M  for  the   “field  lots”    including  relocating  the DF and grass  runway  (with  the per acre costs here higher at $ 170k including the taxiway or $ 140k excluding this) 

 $ 1.5 M to pave the grass runway (2,000+/‐ ft),  if and when this were to occur, though  in this case, no additional taxiway costs would be involved.   

These costs do not include any land acquisition costs associated with extending the grass runway to the east.   The  following  summarizes  our  comparison  of  the  2  sets  of  options  that  we  generated  for  this development plan. This comparison is illustrated in Table 4‐1. In this comparison it is appropriate to also consider  the  do‐nothing  option,  as  this  puts  the  development  options  themselves  in  a  proper perspective.         In the case of the do‐nothing or status quo option, we would have the following: 

We would merely protect for the current situation with the existing runways; 

                                                                 21 This is based on information, drawings and pictures provided in the PSMI study. More detailed on‐site surveys would be required to establish an actual length possible without any need to access the property to the east for tree trimming, or to identify what level of tree trimming may be required. If this runway were paved, it could extend further to the west by some 300‐400 ft, crossing the main runway and extending beyond. This may be one means of getting the length of 2,000 to 2,00 ft without needing to purchase lands to the east.    22 These lands are estimated to costs between $50,000 and $200,000 depending on how much land would actually need to be purchased and on the market value at the time of purchase. 

PED-9-2013-4B

Page 137: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 106

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

The usability would be about 97% for a 10 kt cross wind and about 98.5 for 13 kts; 

The existing 22 ac of developed land would be all that would be available to generate land rents (and much of  this  land  is actually  sold  (compared  to  leased)  so  that  the  revenue has already gone into the existing reserve fund); 

With  this  option  there would  be  no  required  investment  in  any  new  facilities,  though  some investment would be required to upgrade and maintain the facilities, such as runway overlays, etc., as will be discussed in sections 4.2 and 4.3;  

There would be  little  incremental revenue, at  least  from  land rents, but there would be some growth  in aircraft movements, and consequently fuel sales,  landing fees, etc, though obviously not as much growth as in the development options; 

The airport would be foregoing the potential economic  impact of any new developments, such as  Muskoka  Aircraft  Refinishing  (MAR)’s  proposal  to  expand  their  current  facilities,  as  this customer would go elsewhere for their expansion. 

There  is also a  risk  that  someone  like MAR or LCAS might even pull up  stakes and  take  their existing operations elsewhere, so not only would the airport forego new economic impacts, they may in fact lose some of the existing economic benefits of airport activity.  Now let’s look more carefully at the 2 key development options presented: Plan A‐R and Plan B‐R.    

In terms of usability, both options provide virtually identical usability on the basis that the grass runway  is paved and extended to satisfy all of the aircraft that can operate at maximum 10 kt crosswind. Plan A‐R more than doubles the amount of land available for development by adding some 27 ac23  to  the current 22 ac, but Plan B‐R can add an additional 37‐38 ac  (compared  to existing) or 35% more than Plan A‐R; 

Even with the revised wind turbulence assumptions, the east side development in Plan A‐R still cannot accommodate any  lots up to 15m. This risks MAR and other MROs going elsewhere for their expansion. But in any case, MAR at least does not want to be in the east side lands; 

On  the  other  hand,  Plan  B‐R  provides  lots  with  over  15+m  height  capability  immediately adjacent MAR, allowing easy expansion, but as well, provides higher development  lots  in  the eastside area as well, for other similar and possibly synergistic developments;  

The capital costs for the development are similar in each option, in that the major development to the east is about the same cost and the cost of paving (if and when) the grass runway is also the same cost.  However, if we look closely at the total costs shown, Plan B‐R costs a total of $ 6.8M vs $ 5.7 M for Plan A‐R, which is 20% more cost for 35% more land developed; 

Incremental revenues will be higher in Plan B‐R over the long term, due to the additional lands that can be developed, as will the potential incremental economic impacts also be higher. As will be shown  in a  later section, the  incremental revenues  from development eventually eliminate the current fiscal gap in annual revenues, sometime between 2020 and 2030 depending on what assumptions are made as to the pace of development;   

                                                                 23 These areas do not include the additional lands that could be developed in the west rock pile or any other lands discussed later that are located in the north part of the airport lands.  

PED-9-2013-4B

Page 138: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 107

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

 Table 4‐1: Comparison of Development Options     

 

OPTION   USABILITY  DEVELOPABLE LAND (ac)  

RISKS   CONSTRAINTS   $ CAPEX  INCREMENTAL REVENUE POTENTIAL  

INCREMENTAL ECONOMIC IMPACT POT’L  

Status Quo – Protect runways 

97% (10kt) 98.5% (13kt)  

22 ac  current  

MAR and others may go elsewhere  

No additional land for development  

$ 0   $ 0   ‐ 

Plan A ‐ R 99.5% (10kt) 98.5% (13kt)  

Additional  24 ac  in east 2‐3 ac landside 

MAR and others may go elsewhere 

Height limits NO MAR + Other development 

$ 3.5M (east) $1.5M runway $0.7M taxiway 

>$100k/yr revenue3  or >$ 2M in value4 (assumes 100% take‐up )  

Up to $ 8M  in  direct economic impacts annually 

Plan B ‐ R  99.5% (10kt) 98.5% (13kt)  

Additional 25+ ac  to the east   9 ac in field lots 2‐3 ac landside 

Land to east may not be purchasable 

While a total of 7+/‐ lots at 15+m and another 6 +/‐ at 10+m, other lots still height restricted  

$ 3.6M (east) $ 1.7M (west) $1.5M runway 

>$140k/yr revenue3  or Up to $ 3M in value4 (assumes 100% take‐up)  

> $11M  in  direct economic impacts annually 

Notes: 

1. Plan A‐R can provide a 3,000+/‐ ft runway with no land acquisition required 

2. Plan B‐R requires  land acquisition to the east (15‐20 ac) to achieve same 3,000 +/‐ ft runway length  3. Based on about $ 1/m2 lease rate 4. Reflects a land value of about $ 80k/ac.

  

PED-9-2013-4B

Page 139: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 108

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Both  options  can  accommodate  a  2,800‐3,000+/‐  ft  crosswind  runway,  though  in  Plan  B‐R, additional land will be required to be purchased to the east for this to be possible (and there is a risk  that  this  may  be  difficult  to  purchase),  whereas  in  Plan  A‐R  this  length  could  be accommodated within the current property boundary; 

Overall, the airfield system and resulting aircraft operations are probably similar in both options, though Plan B‐R may be considered to have a slightly better configuration in that it doesn’t have buildings in as close proximity to the runway, as is the case with the MAR hangar to Runway 09 in Plan A‐R as well as the big drop off to the south of runway 09‐27.  

In terms of implementation and phasing, Plan B‐R should result in lower expenditures in earlier years, as this option would be easier to phase; 

As well,  Plan  B‐R would  better  satisfy  an  immediate  requirement  to  provide  lands  for MAR expansion.  

All  in all Plan B‐R would appear to be the best plan for development at the Muskoka Airport.  It would maximize  the  amount  of  land  available  for  development,  thus  improving  the  airport’s  revenue  and economic picture, while also improving overall airside operations, with the provision of a possible paved cross wind runway and associated taxiway infrastructure.   The above discussion has  focused on alternative  land development options  for  the airport’s key  lands located in the southern portion of the airport site. But there are a number of opportunities, both short term and longer term, for developing some smaller areas and parcels in the north of the airport site.   Figure 4‐10: Additional Land Development Opportunities in Airport North      

  The  first  is  to develop  some  tie down  facilities along  Taxiway  A  in  the  area  to  the  north  and south  of  the  Compass  Rose,  as  illustrated  in Figure  4‐10.  Previous  studies  have  suggested that the taxiway in this area should be relocated closer to the runway as it is located further from the  runway  than necessary. This would  free up some  land  to  expand  the  land  parcels  in  this area (to the west). However, we do not feel that such  investment  would  be  useful  as  it  would 

PED-9-2013-4B

Page 140: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 109

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

cost much more than it could return in future revenues. However, using the extra land located between the taxiway and runway  for tie downs would be an  inexpensive way to make use of this “extra”  land. There is a potential to provide about ½ ac of tie downs that could generate $ 2k in annual revenues for virtually no cost.   The second possible opportunity to develop some additional lands in this north part of the airport site is located  to the east of the threshold of Runway 18. This  is also  illustrated  in Figure 4‐10. This  is a thin sliver of land sandwiched in between the runway (strip) and the environmental area immediately to the east. There  is  just enough width here  to  locate  some aircraft  storage  facilities utilizing Quonset Huts, similar  to  those  located  on  the west  side  of  the  runway.  The  soils  here  are  sandy  and  could  easily support a grass/dirt type taxiway and road into these lots at little cost. There is a total area of probably 3‐5  acres  that  could  be  developed  for  these  facilities,  and  this  could  generate  upwards  of  $  30,000 annually in land rents and AMC.   In  discussions with  key  stakeholders, we  understand  that  there  are  a  lot  of  aircraft,  especially  float types, being  stored on private  lands  spread  throughout Muskoka. These  inexpensive  storage  facilities would be attractive to such owners and would generate revenues for the airport, not only  in terms of land rents, but for fuel and other sales. 

4.2 INFRASTRUCTURE EXPANSION AND MAINTENANCE (CAPITAL) PLAN

EXPANSION

In parallel with the proposed land developments to accommodate forecast and proposed growth at the airport,  the  airport must  also plan  for  the  expansion of  the  airport’s  infrastructure  to  support  these other activities. This infrastructure plan should include the following expansionary elements:   Parallel taxiway to 18‐36: 

As discussed  in an earlier  section, during most weekends  in  summer, demand  is approaching where there is a need for a full parallel taxiway; 

The  guideline we use  is when peak operations exceed 25 +/– on  a  repeated basis we would probably need to consider a full parallel ‐ we are effectively there now; 

Through some demand management and peak spreading we could delay this, say 5 to 10 years, or  so, depending on how  successful  the demand management  strategies were  (though as we note below, we could defer this for a long time if we extend and pave the grass runway); 

The cost to extend the parallel taxiway south to form a full parallel is estimated at about $ 1.2 ‐ $  1.3 M,  assuming  it  is  extended  for  the  larger  aircraft  (similar  pavement  strengths  to main runway and main apron); 

Optionally, this parallel could be for only light aircraft as these are the most frequent to use the runway system; 

But as discussed below, the need for this parallel taxiway could be deferred for quite some time (possibly to the latter part of the 20 year planning period for this plan), if the grass runway were paved; 

Consequently, we recommend that only protection be put in place for the eventual extension of this parallel  taxiway along  the entire  length of Runway 18‐36, and  that a decision on actually constructing  it be deferred  indefinitely. For maximum flexibility to respond to uncertain future 

PED-9-2013-4B

Page 141: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 110

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

demand types and mix, this protection should be for full Code C type aircraft (even though the airport may choose to construct its width and pavement for Code B (smaller. lighter) aircraft).       

Extending and paving the grass runway to about 2800 ft: 

In earlier  sections, we made  the  case  that  to provide adequate usability at  the airport  for all types of aircraft, but especially the lighter aircraft, there is a need for a second paved runway; 

While a direct replacement for the current grass runway would only need to be about 2,000 ft, this runway should eventually be extended to about 2,800 ft to allow more aircraft to use it year round, with 2,800 ft probably accommodating around 80% of the aircraft using the airport, and possibly close to 100% of the aircraft that could not use the main runway during periods of high crosswinds; 

The estimated cost to pave this runway would be about $ 1.1 M for 2,000 ft or $ 1.5M for the 2,800 ft, excluding lighting24. 

Paving this runway at a cost of $ 1.5M would be similar to the cost of constructing the parallel taxiway at some $ 1.2M‐ $1.3M; 

Paving the runway would eliminate the need for the parallel taxiway, if a significant number of operations could use this runway during busy periods; 

This would be much more efficient use of scare funds than constructing the parallel taxiway, as this  taxiway  only  provides  some  possible  runway  capacity  improvements,  that  can  also  be provided by the paving this runway; 

The parallel taxiway does not provide any land access to developable lands, otherwise it would probably be considered the better investment; 

We  therefore  recommend  that  the second  runway proposed as part of  the development Plan Option B‐R, i.e, new runway 12‐30, be paved; 

Given  the  discussions  at  the  Airport  Advisory  Committee,  together with  comments  received from  private  pilots  and  given  the  competitive  environment with  the  competing  airports  and their  aggressive  expansion  plans,  we  recommend  that  consideration  be  given  to  initially constructing this crosswind runway to a full 2,800 ft, if appropriate funding can be obtained25;         

Building more than about 2,000 ft would require the purchase of lands to the east of the airport. These  lands  should be purchased  soon  to allow  the  runway  to be extended  to  the proposed 2,800 ft. In purchasing these lands, the airport may wish to protect for an ultimate maximum to about  3400  ft, which  is  the maximum  possible  using  the  Beaver  Creek  (with  an  appropriate 

                                                                 24 It may be sufficient to make this runway a day time VFR runway only, so that no lighting would be required. However, it would be appropriate to plan for its eventual lighting, should future circumstances require. Lighting would probably add about $0.5 M to the cost of the runway.  25 We have not carried out a separate business case for paving and extending this runway. But we did include a 2,800 ft paved runway in all of the financial analyses as a base item along with the proposed developments. The results of the financial analysis clearly show that aggressive development at the airport, with the consequent increase in traffic, has the potential to improve the airport’s financial situation beyond that possible by not investing at all, or only investing in more limited expansions.     

PED-9-2013-4B

Page 142: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 111

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

setback) as the maximum eastern extent of this runway. Also see discussion on very  long term plan in section 4.4). 

Expansion of the main aircraft/terminal apron: 

The  forecast  facility  requirements discussion  indicated  that an expansion of  the aircraft apron could probably be deferred  to  the end of  the 20 year planning period,  if appropriate demand management  strategies were  implemented  to  cope with  extreme peaks  experienced on  very busy weekends;  

As well, we do not  foresee  the  feasibility of any  scheduled  commercial airline  services at  the airport,  at  least  over  the  next  10  years,  but we  could  see  these  at  a  later  time, which may require an expansion of the apron; 

In order  to protect  for  future apron expansion capability,  the airport  should  reserve  the area immediately to the north of the existing apron for future expansion.  

The passenger terminal: 

The passenger  terminal  should  generally be  adequate  in  terms of  size  for  a  long  time  in  the future, given current traffic and the probability that little will change; 

However, should scheduled service be provided, this terminal could require expansion; 

For  a  carrier  like  Porter  (with  70  seat  Q400s),  the  expansion  could  be  significant,  requiring security, etc; 

But such a service would be probably 10 years away, at least, if ever; 

A scheduled service by a smaller carrier operating something  like a 18‐19 seat aircraft may be more likely, but even this is very uncertain; 

A much smaller terminal expansion would be required for these smaller aircraft; 

In any case, allowance should be made for space for either of these eventualities. 

Airport restaurant: 

Restaurants at airports of this size are typically very hard to justify and they don’t make money. In this case, it is even more difficult given the truck stop restaurant up the road; 

Having said the above, we understand that there  is a true desire to have a destination café or some facility that could attract visiting pilots to come and buy food, buy some gas, possibly pay some landing fee, all factors that do have an economic impact on the community;  

Other competing airports have such restaurant/café facilities, so to remain competitive, it would be desirable to provide something; 

The only  suggestion we can make  that would minimize expenditures/losses, while capitalizing on  the economic benefits,  is a  small  facility  that could be operated much  like at gas  stations, where the staff multi‐task and thus the facilities would be very simple, providing coffee, drinks, sandwiches,  desserts  and with  no  cooking  facilities, with  airport/terminal  staff  handling  the goods, activities, cash, etc. For “hot food”, it may be possible to have a deal with the truck stop up the road to deliver these on an as ordered/required basis;  

A test could be carried out within  the existing  facility, and  if  it proves successful, the terminal could be expanded slightly airside to accommodate this activity; 

PED-9-2013-4B

Page 143: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 112

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Providing  an  on‐site  restaurant  could  provide  synergies  with  the  current  aircraft  catering business as many of  the  food  items may already  then be on‐site, and some of  the associated facilities like freezers, etc could be shared.     

MAINTENANCE

In addition to expanding existing facilities to meet growth projections, to satisfy current deficiencies or to provide facilities as a result of a wish list or to meet some policy objectives, it is important to invest as well  in the maintenance of the current  facilities. Some of the  facilities maintenance  is done under the operating budgets (if the items cost less than $ 50,000), but must be taken care of in the Capital budgets if the costs are greater than this.  

Key future maintenance projects identified in the current capital plan or added by the consultants are as follows:  

The main runway – 18‐36 

In 2011, Exp Services carried out a pavement re‐evaluation of the runway and apron surfaces.  In their  report,  they  rated  the pavement  in  fair  to  good  condition describing  it  as  generally old asphalt pavement with underlying granular layer; 

The  report  concluded  that  the  pavement would  continue  to  deteriorate  and  recommended rehabilitation by 2015 through careful monitoring and maintenance.  A new asphalt surface was recommended using Cold‐In‐Place Recycling described in further detail in the report; 

Proposed budget for this work was estimated at $ 4M;   

We  concur with  the  recommendation  to monitor  the pavements  and plan  for  a 2015  rehab. However,  we  also  recommend  consideration  of  alternative  techniques  such  as  hot  in  place recycling, which is being used extensively in Western Canada, but currently is not been done in Ontario.  It  is anticipated  that such alternatives should be available  in Ontario by  the  time  the runway needs to be overlaid. We estimate that the rehab cost with such an approach could be reduced to about $ 2.5M, but then the service  life before another rehab  is required would be shorter (10‐15 years vs 15‐20 for the approach recommended by Exp); 

In addition,  to  the 2015 rehab, given  its 15‐20 year  life, another rehab will be required  in  the 2030‐2035  timeframe. Given  the  time  frame  for our  study  (to 2032), we have  chosen not  to include this additional item at this time, but the situation will just need to be monitored at the time; 

As well as major rehabs, the runway will require occasional patching and crack sealing, etc. The current budget shows $ 90k in 2013 and an additional $ 90k in 2019. Much of the crack sealing can be done  in the operating budget, as can some of the patching. But s well,  if saved up and done  less often,  this work can be done  in  larger “lumps” and capitalised. This  item should be monitored and  it may necessary to actually repeat  this  item  in the budget  in something  like 5 year increments. 

The Crosswind Runway 09‐27 (or 12‐30) 

The current “grass runway” only requires the occasional grading and rolling which is done with operating funds; 

In  this  plan,  we  recommend  moving  the  current  runway  to  a  12‐30  orientation  and  that consideration be given to paving this runway; 

PED-9-2013-4B

Page 144: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 113

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

As consequence, if the runway is paved, then an allowance should be made for a future overlay of this runway, sometime in the 2028 – 2032 timeframe.  

Taxiways 

Many  of  the  taxiways  at  the  airport were  overlaid  over  the  last  few  years.  Therefore,  these should generally be good for another 15‐20 years; 

For  capital  planning  purposes we  have  chosen  to  include  the  next  overlays  to  occur  around 2030+/‐ and have shown about $ 1M for this; 

As with all  facilities, careful continual monitoring of conditions  is paramount and adjustments made to actually timing based on current condition at the time.   

Aprons 

The main aircraft apron was expanded in 2007, and this portion should be good for some time; 

The  older  portion  of  the  apron will  be  upgraded  as  part  of  the  runway  project  in  2015  and should consequently be looked at again at the same time as the main runway gets overlaid again towards the end of the planning period;  

Given a 15‐20 year for asphalt pavements, the new portion of the apron will  likely need to be upgraded  in  the  2022  to  2027  time  frame. We  have  tentatively  shown  an  upgrade  to  occur around 2024 in the financial model for the capital plan. 

Passenger Terminal Building  

The passenger terminal building was significantly expanded  in 2007 as part of the  inclusion of the Little Norway memorial;  

At the time substantial improvements were made to all of the older portions of the building to bring these up to date as well; 

Over time, many of the elements of the terminal, whether structural (as in the case of items like windows, or roof, etc) or mechanical and electrical, will deteriorate and require upgrading; 

A reasonable service  life for many of these elements  is about 20‐25 years, so that by 2027 +/‐, there may need to be some investments in this area; 

In the proposed capital plan we have shown some tentative dollars for some upgrades  in 2025 to electrical/mechanical at about $ 50k and structural at about $ 100k in 2027.     

Maintenance and Storage Buildings 

The maintenance  and  storage  buildings  at  the  airport were  all  built  at  different  times  and consequently have different service lives; 

Some of these buildings are small and the maintenance will be done from operating funds;  

The major item identified in the capital plan in this area is a garage roof replacement estimated at about $ 85k and planned for 2013. 

Airfield Lighting 

The airfield  lighting system underwent a major upgrade a few years ago (2009), at which time many of the items like the lights and constant current regulators were replaced; 

PED-9-2013-4B

Page 145: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 114

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Given about a 20‐25  year service life for many of these items, most of these should be OK until the end of the planning period for this study or beyond; 

However,  technology  is  changing  and many  airports  are  switching  to  LED  lighting  to  save on operating costs, due to lower consumption and longer life of these new fixtures; 

As a consequence, we have shown an allowance  in  the capital plan around 2022 +/‐  for some type of upgrade to the lighting system; 

As well, we anticipate that given the age of the field electrical centre which provides power to the  lighting  system,  some  future  investments may  be  required  to  this. We  have  tentatively shown  dollars  for  this  in  2021.  As well, with  the  changes  occurring  in  technologies  and  the substantial energy savings possible as a result, the airport may wish to upgrade the equipment in the FEC to take advantage of these savings; 

While  technically not an  issue  related  to maintenance, we also recommend  the  installation of PAPis on runway 36, as discussed in the requirements section (3.4).        

This proposed maintenance plan  is tentative and based on our experience at other airports. It was not part of the terms of reference to do detailed assessments of the various facilities. But we feel that the plan as  laid out should be quite reflective of future requirements. But as  in any plan, the facilities and their condition must be monitored periodically and re‐assessments made as to current conditions and when  the  facilities  should  be  replaced  or  upgraded.  A major  re‐assessment  of  the  capital  plan  for maintenance items should probably be carried out in about 10 years or less.  

More  discussion  on  the  financial  implications  of  the  various  capital  requirements  is  provided  in  the financial discussions in the next section (5.0). The phasing and timing of the various capital expenditures are summarized in the following section.   

4.3 PHASING PLAN

The above discussions have dealt with the provision of development  lands and appropriate associated infrastructure  to  meet  the  forecast  needs  of  the  airport.  As  well,  we  have  discussed  the  capital requirements for maintaining the existing or planned future facilities.  

The following material summarizes our recommendations with respect to the timing of the provision of these additional  facilities.  In addition, we  incorporate  into  this discussion  the  requirement  to update various existing facilities such as the existing runway, and other facilities, so that we create a complete Capital Plan for the airport that includes expansionary projects and major maintenance as well. 

Our  recommended phasing plan  for both  the expanded  facilities under  the high case growth scenario and the updating or modernizing of the existing facilities is summarized in Table 4‐2.   

Table 4‐3 presents the same information for the medium growth case.   

Table 4‐2: Proposed Phasing Plan (High Growth Case) 

  Project                      Cost ($M)      Year    Trigger 

Short term (0‐5 years) 

Grass Runway Relocation 

PED-9-2013-4B

Page 146: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 115

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

o Land purchase & DF relocation      0.5        2013    Land Demand26 

o Construction              0.3        2014    Land Demand  

o Paving                  1.5        2016    Policy decision 

Phase 1 Field Lots                 0.6        2014    Land Demand   

Phase 2 Field Lots                 0.5        2017    Land Demand 

Runway 18‐36 rehabilitation          4.027      2015    Pavement Condition 

Runway repairs                 0.09      2013    Condition 

Garage roof replacement            0.09      2013    Condition 

Install PAPIs Runway 36             0.80      2017    Safety 

Medium term (6‐10 years) 

Phase 1 East Side Lots               1.0        2020    Land Demand 

Phase 2 East Side Lots               0.9        2024    Land Demand 

FEC Upgrade                  0.5        2021    Condition 

Airfield Lighting Upgrades            0.1        2022    Condition/policy 

Runway repairs                 0.09      2019    Condition 

Long term (11‐20 years)  

Phase 3 East Side Lots               0.9        2028    Land Demand 

Apron overlay                  0.1        2024    Condition 

Terminal mechanical/electrical          0.05      2025    Condition 

Terminal Roof                  0.1        2027    Condition 

Taxiway Overlays                1.0        2031    Condition 

Runway overlay  12/30              0.4        2028    Condition 

Table 4‐3: Proposed Phasing Plan (Medium Growth Case) 

  Project                      Cost ($M)      Year    Trigger 

Short term (0‐5 years) 

Grass Runway Relocation 

o Land purchase & DF relocation      0.5        2013    Land Demand28 

o Construction              0.3        2014    Land Demand  

Phase 1 Field Lots                 0.6        2014    Land Demand   

                                                                 26 Land demand for this phasing plan assumed to follow most likely demand scenario 27 This could be reduced to around $ 2.5M if new technique like hot in place asphalt were used, but new pavement life would be reduced to around 10 years instead of about 15 years for current plan.   28 Land demand for this phasing plan assumed to follow most likely demand scenario 

PED-9-2013-4B

Page 147: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 116

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Runway 18‐36 rehabilitation          4.029      2015    Pavement Condition 

Runway repairs                 0.09      2013    Condition 

Garage roof replacement            0.09      2013    Condition 

Install PAPIs Runway 36             0.80      2017    Safety 

Medium term (6‐10 years) 

Grass Runway Paving              1.5        2018    Policy Decision 

Phase 2 Field Lots                 0.5        2019    Land Demand 

Phase 1 East Side Lots               1.0        2022    Land Demand 

FEC Upgrade                  0.5        2021    Condition 

Airfield Lighting Upgrades            0.1        2022    Condition/policy 

Runway repairs                 0.09      2019    Condition 

Long term (11‐20 years)  

Apron overlay                  0.1        2024    Condition 

Terminal mechanical/electrical          0.05      2025    Condition 

Terminal Roof                  0.1        2027    Condition 

Taxiway Overlays                1.0        2031    Condition 

Runway overlay  12/30              0.4        2028    Condition 

4.4 VERY LONG TERM PLAN

The Muskoka Airport  is well  located  just outside, but still  in close proximity  to, Canada’s most heavily populated area – the Golden triangle of Southern Ontario. There are many opportunities created with this proximity  in that there will always be a  large  local source of tourists and visitors, as well as skilled workers nearby, especially as the population and employment in this part of the province continues to expand outwards  from the Greater Toronto Area. But  in addition to this population and employment, there will be other opportunities created as aviation  is generally an expanding  industry with no sign of turning negative in any way (at least in the long term view).  

Forecasts for the aviation industry show greater need for trained aviation professionals, whether pilots, or mechanics and a greater need  for aircraft, whether new or to maintain the ever expanding aircraft fleet.  This will  create  ever  expanding  opportunities  for  airports  in  the  future. While  the  outlook  for general  aviation  overall  is  not  as  rosy  as  for  the  aviation  industry  as  a whole,  there will  always  be significant opportunities to take advantage of for those creative enough to identify these.  

In  an  earlier  section  of  this  report we  have  reviewed  the  facilities  and  plans  of  some  of  the  areas’ competing airports. Many of these airports have put in place bold plans to expand their facilities to cater to potential  future growth. There  is  the old adage  that  says: “build  it and  they will come”. While we don’t necessarily  subscribe  to  this, we do know  that  if you don’t have a plan and  that  if you are not prepared  to accommodate  future growth, but as well,  if you are not actively marketing your  facilities and aggressively chasing the  opportunities, then definitely the traffic will not come.  

                                                                 29 This could be reduced to around $ 2.5M if new technique like hot in place asphalt were used, but new pavement life would be reduced to around 10 years instead of about 15 years for current plan.   

PED-9-2013-4B

Page 148: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 117

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

The  Muskoka  Airport  currently  has  excellent  facilities,  better  in  many  ways  than  some  of  its  key competitors,  is well  located, and has a very good reputation among many of  its users. The airport also currently  has  a  good mix  of  locally  based  entrepreneurs who  are willing  to  invest  in  the  airport  to expand the products and services and job opportunities within the community. With the proposed plan above, the airport should be able to meet forecasted needs easily for the next 20 years +/‐, depending on actual growth achieved, but what about beyond that period? And what if the airport is so successful in attracting new developments that it runs out of lands earlier than anticipated?  

We feel that the Airport should have a bold  long term strategy to deal with future airport growth. It  is well positioned to do so given the availability of lands in the vicinity of the airport. Having such a context will not only aid the airport in its efforts to attract new tenants, but it will also act as a catalyst to keep and inspire the current tenants to further invest in the airport. 

Figure  4‐11  presents  our  recommendations  for  a  very  long  term  plan  for  the Muskoka  Airport.  Key features of this long term plan include:  

Building upon the development plan proposed for the first 20 years, which includes: 

o Retention of the existing 6,000 ft Runway 18‐36, 

o Construction of  the new Runway 12‐30  to 2,800  ft, with protection  for up  to 3,400  ft with a possible extension to the east, 

o Development of the east lands for mixed uses 

o Development of the field lots for MRO and associated uses,  

o Allocation of lands along Beaver Creek Road for landside commercial activities, 

Retain  the designation on  the  lands  to  the west of  the airport  (and east of Highway 11)  for a mixed of industrial (which they are already zoned for) and aviation related uses; 

Protecting  for  the  possibility  of  realigning  the Gravenhurst  Parkway  to  be  re‐routed  through these new lands, so as to be the primary access to this future development, from both the north and the south;  

Realigning the existing north‐south portion of the Gravenhurst Parkway further to the west and re‐purposing  it to act as a service road to open up new  lots by extending the current westside developments further to the south to front along the extended full parallel taxiway; and 

Making provision for a possible future extension of Runway 12‐30 further to the west  into the area vacated by realigning the Gravenhurst Parkway. This could provide a runway length in the vicinity of 4,500 ft +/‐ .          

 

 

 

 

 

 

 

 

PED-9-2013-4B

Page 149: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 118

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Figure 4‐11: Very Long Term Development and Infrastructure Plan   

 

 

PED-9-2013-4B

Page 150: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 119

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

5.0 FINANCIAL ANALYSIS

This  section  looks  at  the  Airport’s  finances  and  forecasts  the  airport’s  financial  picture  taking  into account the forecast traffic, required new infrastructure, recommended land development and options for adjusting various charges and compares this to a status quo forecast with none of these elements. 

5.1 STATUS QUO FINANCIAL FORECASTS

The Status Quo (Base Case) financial forecasts are based on the following assumptions:  

No changes to the certification status of the airport; 

Traffic forecasts as provided in Section 3.3 of this report (status quo) which affect ramp fees and the cost of fuel sold; 

No changes to the structure of the aeronautical fee schedule; however rates will increase by 2% per year with the exception of aviation fuel which will  increase 5% p.a. (as will the cost of fuel sold); 

No changes to the current governance structure or staffing levels; 

No new land sales or leases; [see comment below]; 

Operating expenditures  increase at 2% p.a. except utilities,  fuel  (fleet and equipment),  taxes, insurance, travel fleet, and cost of fuel sold that each increase at 5% p.a.; 

Continued contributions to capital reserves funded through tax levies. 

Given these assumptions, it is projected that the airport will suffer an operating loss of close to $ 312K in 2013, decreasing to approximately $ 260K by 2022 and to just over $ 130k by 2032. The improvement in the financial situation is based primarily on the mix of traffic (as the increase in traffic over this period is small) and related revenues associated with landing fees and fuel sales with larger aircraft.  

 

Table 5‐1: Forecast Revenue and Expenses Under the Status Quo Scenario       

  2012 (budget) 

2013  2017  2022  2027  2032 

Revenues  $1,834,700  $1,954,722  $2,454,168  $3,242,395  $4,266,982  $5,598,339 

Expenses  $2,158,506  $2,266,215  $2,750,150  $3,506,343  $4,478,597  $5,732,715 

Operating Income Over Expenses 

‐$323,806  ‐$311,493  ‐$295,982  ‐$263,848  ‐$211,616  ‐$134,376 

As there is no land development in this scenario, the funding of the status quo capital plan remains the same as described earlier and would just involve maintenance and repairs to the current infrastructure. There would also be no land sales and land sales revenue or any lease revenue either.  

Table 5‐2 shows the resulting cash flow under this status quo scenario. Under the assumption that the Airport receives FedNor funding for 1/3 of all capital  improvements, the funding deficit required to be covered through taxes would average just over $ 600,000 annually over the first 5 years of the plan. In 

PED-9-2013-4B

Page 151: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 120

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

the next 5 years, this funding requirement would drop to an average of about $ 400,000 per year, and thereafter nearly $ 280,000  for the next 5 years. The simple total of the  funding shortfall over this 20 year period would be over $ 10,000,000 or an overall average of just over $500,000 per year.    

 

 Table 5‐2: Forecast Cash Flow and Capital Requirements Under the Status Quo Scenario  

   

5.2 BUSINESS CASE FOR LAND DEVELOPMENT

Development at the airport will result in additional traffic as described in Section 3.3. This will increase revenues  in  a  couple of ways:  there will be  additional  revenues  associated with  the  land  leases  and AMC;  and  there will  also  be  additional  revenues  from  the  additional  traffic  generated  by  the  land developments, which will lead to increases in landing fees, fuel sales, parking charges, etc.  

The table below summarizes the  implications of the Medium and High traffic growth scenarios on the financial situation at the airport, based on the following additional assumptions: 

No changes to the certification status of the airport; 

No changes to the current governance structure; 

Staffing levels are assumed to increase due to the expanded developments30; 

Traffic forecasts as provided  in Section 3.3 of this report which affect ramp revenues  including fuel sales; 

No changes to the structure of the aeronautical fee schedule; however rates will increase rates by 2% per year with the exception of aviation fuel which will increase 5% p.a. (as will the cost of fuel sold); 

                                                                 30For simplicity we have assumed that staffing levels increase, adding about $50,000 in additional staff costs in 2015, and thereafter this amount increases in line with inflation.    

SIMPLE CASH FLOW 2012 2013-2017 2018-2022 2023-2027 2028-2032 TotalOpening Balance Reserve 1,538,706$ 1,538,706$ Retained Earning (Ops) -$ 1,522,563 1,392,752-$ 1,174,263-$ 835,112-$ 4,924,690-$

Revenue from Land Sales -$ Planned Capex (Maintenance) -$ 4,336,600-$ 806,694-$ 319,697-$ 1,966,594-$ 7,429,585-$ Projected Surplus / (Shortfall) 1,538,706$ 4,320,457-$ 2,199,446-$ 1,493,960-$ 2,801,706-$ 10,815,569-$

NPV (surplus/Shortfall) 6,448,198-$

864,091-$ 439,889-$ 298,792-$ 560,341-$

603,895-$ 391,487-$ 279,610-$ 442,345-$

Avg annual amount to be financed through taxes &/or other during 5 year period - if airport pays two thirds (other 1/3 - FedNor)

Avg annual amount to be financed through taxes &/or other during 5 year period - if airport pays 100%

PED-9-2013-4B

Page 152: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 121

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Current base land lease rates escalated at CPI (use 2% p.a.); 

Current AMC land lease rates escalated at CPI (use 2% p.a.); 

Land development – 35 acre development (option B‐R)  including taxiways, parallel runway and paving the grass runway at a total cost of $7 million; however with a phased approach, only $6.5 M is spent in the 20 year planning period; 

Land take‐up of 35 available acres is per phasing plan in earlier section, with: 

o 25 acres total developed under a High Case scenario; and  

o 15 acres developed under a Medium Case scenario (over 20 years).  

Developed  land  is assumed  to be 50% sold and 50%  leased with  the exception of  the  initial 5 acres in 2014 which is assumed to be all sold; 

Operating expenditures  increase at 2% p.a. except utilities,  fuel  (fleet and equipment),  taxes, insurance, travel fleet, and cost of fuel sold that each increase at 5% p.a.; 

No additional staff are required due to land development or infrastructure expansion; 

The operating expenses associated with materials and equipment,  fuel  (fleet and equipment), building maintenance and  supplies, grounds maintenance and  supplies, and equipment  repair do  increase with  land development  and  the  increase  is based on  two‐thirds of  the  increases associated with airfield area: 

o Medium case:  1.5% growth in 2017 and 18% growth in 2022; 

o High case:  15% growth in 2017, 3.9% in 2022, 3.7% in 2027, and 1.3% in 2032.  

The following two tables below show the operating financials for the period 2013 through 2032, in five year increments (including land lease revenues but excluding land sales revenues). 

Table 5‐3 shows that under the medium growth scenario with no major changes to current rates that the  operating  deficit  would  reduce  over  time  to  the  point  that  around  2029/30,  the  airport  could achieve an operating surplus, and  thereafter,  this surplus would  increase over  time,  reaching about $ 70,000 in 2032 vs a loss of about $ 325,000 in 2012.  

Under the high growth scenario, illustrated in Figure 5‐4, the deficit is shown to decrease much faster so that  breakeven  is  potentially  achieved  in  about  2021 with  a  surplus  of  over  $  330,000  by  2027  and reaching over $ 600,000 by 2032.  

Both of these scenarios clearly show the benefits in developing the additional lands due to not only the additional  revenues  that  this would generate  from  land  leases, but as well  the additional  traffic  that would also be generated as a result.  

The next two tables below show a summary of cash flows during the 20 year planning period under both the Medium and High growth scenarios.   As presented earlier,  the capital estimates are shown under two  sets of assumptions:  that  the District has  to pay 100% of all  capital  costs, or;  that  the District  is responsible  for  two‐thirds of  the  capital  funding, with  the  remaining one‐third being  funded  through government programs (e.g., FedNor).  

 

 

 

PED-9-2013-4B

Page 153: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 122

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Table 5‐3: Forecast Revenues and Expenses for the Medium Growth Scenario      

  2012 (budget) 

2013  2017  2022  2027  2032 

Revenues (incl asset sales) 

$1,834,700  $1,981,637  $2,654,202  $4,123,047  $5,113,787  $6,658,768 

Expenses  $2,158,506  $2,287,996  $2,948,181  $3,996,762  $5,156,822  $6,591,380 

Operating Income Over Expenses (excl asset sales) 

‐$323,806  ‐$306,359  ‐$293,979  ‐$145,180  ‐$43,046  $67,389 

 

Table 5‐4: Forecast Revenues and Expenses for the High Growth Scenario      

  2012 (budget) 

2013  2017  2022  2027  2032 

Revenues (incl asset sales) 

$1,834,700  $2,055,618  $3,385,659  $5,033,349  $7,087,766  $9,403,652 

Expenses  $2,158,506  $2,347,162  $3,394,211  $4,966,227  $6,756,724  $8,789,548 

Operating Income Over Expenses (excl asset sales) 

‐$323,806  ‐$291,544  ‐$172,468  $67,122  $330,342  $614,104 

 

Per  Table  5‐5,  during  the  first  five  years  of  the  development  plan  (2013‐2017),  over  $  700,000  is required in tax levies each year to cover capital expenditures and operating losses, even with the grants from FedNor to cover 1/3 of the capital costs. This is due to the high costs incurred during this period for the land development and the major runway overlay. This shortfall remains at this same level during the next 5 year period (2018‐2022) at just over $ 700,000 per year, before dropping significantly to just over $ 100,000 per year in the next 5 year period (2023‐2027). The funding shortfall rises again in the last 5 year period as a number of major maintenance items are necessary at that time.  

Recall  from  the  status quo discussion  that  the  simple  total of  the  funding  shortfall over  the 20  year planning  period was  just  under  $  11,000,000.  In  this  case,  the  total  funding  shortfall  is  just  over  $ 13,000,000 over the 20 year planning period. The NPV of this cumulative loss is about $ 8.5M vs $ 6.5M for the status quo. This  is primarily due to the fact that while  land  is developed to stimulate growth  in traffic  and  growth  in  revenues  (cumulative  loss  is only  $  3.0M  vs  $  4.5M  in  status  quo),  the  land  is actually being sold or leased at less than the cost to actually develop it. The additional revenues that are generated as a consequence of the additional traffic fail to make up the difference. 

 

 

 

PED-9-2013-4B

Page 154: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 123

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Table 5‐5: Forecast Cash Flows and Capital Funding Requirements for the Medium Growth Scenario  

 

 

Table 5‐6 shows the projected cash flows for the High Growth Scenario. In this case, the funding shortfall is higher in the first 5 years of the development plan, at over $ 900,000 required per year. However, the funding shortfall drops significantly to about $ 290,000 per year in the second 5 year period. After that, between land sales and improved revenues from operations, the airport’s funding shortfall would drop to an average of only $ 50,000 ‐ $ 100,000 annually for the next 10 years.   

The simple  total of  the  funding shortfall  in  this case  is  just under $ 10,000,000, which  is a reasonable improvement over the status quo at just under $ 11,000,000 or the medium case at about $ 13,000,000.  This  funding  shortfall  is  reduced  significantly  due  to  the  large  amount  of  retained  earnings  from operations in this case ($ 2.2M vs a loss of $ 3.0M in the medium case) as well as the land sales, now at some $ 1.3 M. These positive changes easily make up for the additional costs of the capital plan ($ 7.4M in this case vs $ 5.1M in the medium case).  The NPV of the cumulative loss in this case is estimated at about $ 7.3M vs $ 8.5M for the medium case or $ 6.5M for the status quo. 

The  above  financial  analysis  clearly  shows  that  additional  land  development  at  the  airport  can contribute  to  improved  revenues  through  additional  land  sales  and  lease  revenues,  as  well  as  the stimulation  in traffic that would result. However, to achieve the best results, the  lands must be priced appropriately  and  the  airport  needs  to  be  aggressive  in  the  development  as  modest  levels  of development do not produce the same improvements as more substantial levels.     

 

 

 

 

 

 

 

SIMPLE CASH FLOW 2012 2013-2017 2018-2022 2023-2027 2028-2032 TotalsOpening Balance Reserve 1,538,706$ 1,538,706$ Retained Earning (Ops) -$ 1,508,064 1,080,684-$ 437,537-$ 106,052$ 2,920,234-$ Revenue from Land Sales 386,155$ 442,004$ -$ -$ 828,159$ Planned Capex (Development/Capacity) 1,499,182-$ 3,653,313-$ $0 -$ 5,152,496-$ Planned Capex (Maintenance) 4,336,600-$ 806,694-$ 319,697-$ -$1,966,594 7,429,585-$ Projected Surplus / (Shortfall) 1,538,706$ 5,418,986-$ 5,098,688-$ 757,234-$ 1,860,542-$ 13,135,450-$

NPV (Surplus / Shortfall) 8,656,543-$

1,083,797-$ 1,019,738-$ 151,447-$ 372,108-$

733,650-$ 752,137-$ 132,265-$ 254,113-$

Avg annual amount to be financed through taxes &/or other during 5 year period - if airport pays two thirds (other 1/3 - FedNor)

Avg annual amount to be financed through taxes &/or other during 5 year period - if airport pays 100%

PED-9-2013-4B

Page 155: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 124

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Table 5‐6: Forecast Cash Flows and Capital Funding Requirements for the High Growth Scenario 

 

5.3 ESTABLISHING APPROPRIATE LAND VALUES AND LEASE RATES

Now  let’s  look at  the pricing of  land  sales and  the associated  leasing  rates, as we had  indicated  in a previous  section  that  we  felt  that  the  value  of  airport  lands  was  being  underestimated  by  recent appraisals. This was because they did not consider sufficient factors in their analysis in that they did not necessarily compare apples to apples in their “comparison” approach and they completely avoided the cost based side. As well, the implications of under pricing the lands became clearly evident in the above scenario analysis where  in the medium growth scenario, the airport’s funding deficit actually  increases with development as the lands are being sold/priced at below the cost of developing them.   

Based on the three appraisals reviewed from 2010, the weighted average sales price per square meter is $18.71, or $75,717 per acre.   

As shown  in Table 5‐7 below, the full cost (versus phased cost) to develop the various airport  lands as identified in the development options section is estimated at about $ 140,000 ‐ $ 150,000 per acre if we take into account the full costs of the land preparation including the cost of adding the taxiway access to the lots. If we exclude the cost of the taxiway access to the developments, then the price per acre drops to under about $ 85,000. This latter figure should be the lowest sale price charged to recover the costs. The former figure should be the highest charged. In fact, most airports will choose a number somewhere in between as they know they will recover some of the money through aircraft movements, etc., as was demonstrated with the financial comparisons between the Medium Growth and High Growth scenarios.   

These “land cost” numbers are clearly much higher than the typical $ 75,000 “appraised values”, and it makes absolutely no  sense  to  sell  land at  less  than  it would cost  to develop. While  it  is  important  to remember that developing the  lands at the airport will have other direct  impacts such as retaining an existing anchor tenant or two who could move to another airport  if expansion at Muskoka was not an option;  increased  fuel sales and  landing  fees due  to additional  traffic; and  increased employment and 

SIMPLE CASH FLOW 2012 2013-2017 2018-2022 2023-2027 2028-2032 Totals

Opening Balance Reserve 1,538,706$ 1,538,706$

Retained Earning (Ops) -$ -$ 1,210,168 210,566-$ 1,117,324$ 2,529,481$ 2,226,070$ Revenue from Land Sales -$ 550,071$ 260,924$ 235,360$ 254,762$ 1,301,117$ Planned Capex (Development/Capacity) -$ 3,632,210-$ 1,378,423-$ 1,243,374-$ 1,211,282-$ 7,465,289-$ Planned Capex (Maintenance) -$ 4,336,600-$ 806,694-$ 319,697-$ 1,966,594-$ 7,429,585-$

Projected Surplus / (Shortfall) 1,538,706$ 7,090,201-$ 2,134,759-$ 210,387-$ 393,632-$ 9,828,980-$

NPV (Surplus / (Shortfall) 7,353,954-$

1,418,040-$ 426,952-$ 42,077-$ 78,726-$

939,912-$ 295,845-$ 51,707$ 111,946$

Avg annual amount to be financed through taxes &/or other during 5 year period - if airport pays 100%

Avg annual amount to be financed through taxes &/or other during 5 year period - if airport pays two thirds (other 1/3 - FedNor)

PED-9-2013-4B

Page 156: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 125

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

resulting spin‐off effects in the District, even considering these other effects, it would still make no sense to sell the land at less than cost.     

 

Table 5‐7: Comparison of Appraised Land Values vs Developed Cost Based Land Values      

  Development Option A‐R  Development Option B‐R 

(2013 dollars) (Eastside Lots – 25 acres) (Eastside Lots and Field 

Lots – 35 acres) 

Total Cost (excl. paving the grass runway but incl. taxiway work) 

$3,515,000 $5,242,000

per acre $140,600 $149,771

Total Cost (excl. paving the grass runway & excl. taxiway work) 

$2,090,000 $2,999,000

per acre $83,600 $85,686

Sell at $18.71 / m2 ($75,717 / acre)  $1,892,925 $2,650,095

Lease at $0.91 / m2 / yr ‐ annual revenue $92,066 $128,892

SENSITIVITY ANALYSIS – LAND RATES

Another key method to value  land  is to compare to other similar or competitor airports.  In the earlier financial section we had provided rates for the Lake Simcoe Airport, which is the closest key competitor airport. Unfortunately,  similar  information  could not be obtained  from  the other airports. Comparing with the Lake Simcoe rates we find the following:   

Lake Simcoe has a Base Lease Rate of $1.49/m2 which  is 64% higher  than Muskoka’s current base lease rate of $0.91/m2; 

Even choosing a Base Lease Rate of $1.20/m2, which is half way between current rate and Lake Simcoe’s, could result in about 32% more land revenue than with the current base lease rate of $0.91/m2; 

At a base lease rate of $ 1.49/m2, the imputed land value would be about $121K per acre. This is mid way in the range suggested above for a cost based approach to land values ($85k ‐ $ 150k);  

At a base  lease rate of $ 1.20/m2, (or mid way between the Lake Simcoe rate and the current Muskoka rate) the imputed land value would be close to $ 100K per acre;  

Based on the above, we suggest that to remain competitive, consideration be given to choosing a land value rate of about 10% less than Lake Simcoe, which would work out to about $ 110k per acre, or about $ 1.35/m2.  

5.4 BUSINESS CASE FOR INCREASING LAND RATES AND OTHER CHARGES

Clearly, based on the above financial analysis, there is room to improve the airport’s financial situation even more than noted through investigation of a better business plan and an improvement in the rates charged to users and tenants. This is discussed further below.  

Based  on  the  discussions  above  we  clearly  need  to  raise  the  land  rates,  both  for  land  sales  and associated  lease rates. As well, a comparison with the nearest competitor, and the only one where we could get detailed rate information from (Lake Simcoe Airport), clearly shows that rates at Muskoka can be raised. These include higher AMC rates, Development Service and Permit fees, etc.      

PED-9-2013-4B

Page 157: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 126

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

The proposed financial forecasts for this study are based on the following assumptions: 

No changes to the certification status of the airport; 

No changes to the current governance structure; 

Staffing levels are assumed to increase due to the expanded developments31; 

Medium traffic growth (see section 3.3); 

Implementation  of  Development  Plan  B‐R  (phased)  including  taxiways,  parallel  runway  and paving the grass runway at a cost of $7M ($6.5M within planning period);  

Land take‐up of 35 available acres is assumed to be 15 acres during the planning period; 

Land‐take up  is assumed to be 100% sold  in year 2014,; with remaining parcels 50% sold, 50% leased in years 2019, and 2022; 

Increase in land sales rates by 47% to $111,304 / acre (2013$); 

Increase  land  lease  rates by 47%  to $1.34/m2  (Lake Simcoe’s  rates  less 10%) escalated by 2% p.a. with these increases only applied to new leases32; 

Increase AMC by 21% to $0.97 / m2 (Lake Simcoe’s rates less 10%), escalated by 2% p.a.; 

A new one‐time Development Service Fee of $0.40/ft2 (building area) to be drawn upon by the Airport  to  review  the  development  application.  This  is  equivalent  to  $7,841/acre.  Unused portions of fee to be returned to the tenant. Assume 50% of the fee will be used.  Building area assumed to be 45% of land area.  Fees waived on development taking place in 2014; 

A new one‐time Airport Development Permit Fee of $0.90/ft2 (building area) to be drawn upon by the Airport to review the development permit submission and provide periodic site review as required.  This  is  equivalent  to  $17,642/acre. Unused  portions  of  fee  returned  to  the  tenant. Assume 50% of the fee will be used.  Building area assumed to be 45% of land area.  Fees waived on development taking place in 2014; 

A new one‐time Airport Development Levy of $4.64/ft2 (building area) excluding space used for storage of aircraft.  Total building area assumed to be 45% of land area, however 90% of that is assumed  to  be  for  aircraft  storage.    Rate  therefore  applies  only  to  980  ft2  per  acre  sold  or leased; 

Reduction in exemptions for landing fees (from 5 tonnes to 3 tonnes for based aircraft, and from 3 tonnes to 1 tonne for visiting aircraft; no other changes to the aeronautical rate structure; 

Aeronautical  fee  schedules  (rates) will  increase  rates  by  2%  per  year with  the  exception  of aviation fuel which will increase 5% p.a. (as will the cost of fuel sold); 

Ramp fee revenues increase with traffic and with CPI rate increases; 

                                                                 31 For simplicity we have assumed that staffing levels increase, adding about $50,000 in additional staff costs in 2015, and thereafter this amount increases in line with inflation. We have kept this assumption constant across all expanded development scenarios.     32 As existing leases come up for renewal, these should be re‐negotiated to the new rates. However, for simplicity, these new rates have not been applied to leases that will come up for renewal, making the analysis conservative. 

PED-9-2013-4B

Page 158: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 127

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Fuel revenues increase with traffic plus a 5% rate increase per year; 

Operating expenditures  increase at 2% p.a. except utilities,  fuel  (fleet and equipment),  taxes, insurance, travel fleet, and cost of fuel sold that each increase at 5% p.a. 

The operating expenses associated with materials and equipment,  fuel  (fleet and equipment), building maintenance and  supplies, grounds maintenance and  supplies, and equipment  repair do  increase with  land development  and  the  increase  is based on  two‐thirds of  the  increases associated with airfield area:  1.5% growth in 2017 and 18% growth in 2022; 

In the case where the District should choose to move to an Airport Commission, costs associated with setting up a Commission (e.g., legal) are assumed to be offset by increased revenue due to additional marketing and more aggressive revenue targets. 

Table 5‐8 shows  the  forecast  revenues and expenses  for  this case with  increased  rates but combined with  only  the Medium  Growth  Scenario. With  this  combination  of  increased  rates,  a  breakeven  is achieved on operating income in 2021/22. By comparison, in the Medium Growth scenario with current rates, breakeven was not achieved until 2029/30.    

 Table 5‐8: Forecast Revenues and Expenses with an Increased Rate Package Medium Growth Scenario          

  2012 (budget) 

2013  2017  2022  2027  2032 

Revenues (incl asset sales) 

$1,834,700  $2,030,413  $2,710,066  $4,434,429  $5,200,753  $6,755,076 

Expenses  $2,158,506  $2,288,396  $2,948,614  $3,997,240  $5,157,350  $6,591,963 

Income (excl sale of assets & dev. Levy) 

‐$323,806  ‐$257,983  ‐$238,608  $21,828  $43,403  $138,435 

Table 5‐9: Forecast Cash Flows and Capital Funding Requirements for the High Growth Scenario 

 

SIMPLE CASH FLOW 2012 2013-2017 2018-2022 2023-2027 2028-2032 TotalsOpening Balance Reserve 1,538,706$ 1,538,706$ Retained Earning (Ops) -$ 1,243,995 601,725-$ 27,683-$ 565,479$ 1,307,924-$ Revenue from Land Sales 567,650$ 649,749$ -$ -$ 1,217,399$ Revenue from Development Levy -$ 26,549$ -$ -$ 26,549$ Planned Capex (Development/Capacity) 1,499,182-$ 3,653,313-$ $0 -$ 5,152,495-$ Planned Capex (Maintenance) 4,336,600-$ 806,694-$ 319,697-$ -$1,966,594 7,429,585-$

Projected Surplus / (Shortfall) 1,538,706$ 4,973,421-$ 4,385,434-$ 347,380-$ 1,401,114-$ 11,107,350-$

NPV (Surplus / (Shortfall) 7,483,970-$

994,684-$ 877,087-$ 69,476-$ 280,223-$

644,537-$ 609,486-$ 50,294-$ 162,227-$

Avg annual amount to be financed through taxes &/or other during 5 year period - if airport pays 100%

Avg annual amount to be financed through taxes &/or other during 5 year period - if airport pays two thirds (other 1/3 - FedNor)

PED-9-2013-4B

Page 159: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 128

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Table 5‐9 shows the simple cash flows over the 20 year period for this proposed package of rates. The simple funding shortfall in this case is over $ 600,000 for the first 10 years, dropping to about $ 50,000 for the next  five, and then rising again to approach $ 160,000  in the  last 5. The total  funding shortfall over the 20 years is about $ 11,000,000 with an NPV of this shortfall at about $ 7.5M. 

Table 5‐10  summarises a  comparison over all of  financial  scenarios modelled above. We  should note that  the basic CAPEX plan  for maintaining  the existing  facilities at  the airport  is  the same  in all of  the options (at about $ 7.4M as a simple addition of the inflated costs over the 20 years). This includes the runway  overlays,  roof  replacements,  building  structure maintaining, HVAC,  lighting  upgrades,  etc. As well, the value of the initial reserve at the start of 2013 is also the same across all scenarios at about $ 1.5M.  

Table 5‐10: Comparison of Financial Cash Flow Results across Scenarios      

 

 

In  the  status quo case,  the  large cumulative operating  loss over  the 20 year period of about $ 5.0M, combined with the $ 7.4M CAPEX plan to maintain current facilities results in a cumulative cash shortfall of close to $ 11 M. The NPV of this shortfall, however, is only about $ 6.5M. In the Medium Growth case, combined with maintaining current rates, operating income improves to a loss of only $ 3.0 M as a result of additional  land  leases and  increased  traffic.  IN  this case  land  sales  revenues of over $ 800,000 are achieved. However, these improvements are not enough to pay for the expansionary CAPEX associated with the land development and capacity increases (at over $ 5 M), so that the funding shortfall over the 20 year period actually increases to about $ 13.0M (or an NPV of $ 8.6M). 

In the High Growth Scenario (still with current rates), the operating income improves significantly due to higher activity at the airport resulting from more development (25 acres vs 15) and the associated spin‐offs in traffic and revenues. In this scenario, the airport actually achieves a cumulative operating surplus of over $ 2.2 M over the 20 year period. The airport also receives over $ 1.3 M  in  land sales. But even together all of the above  improvements are still not enough to even pay for the expanded facilities. In this  case,  the  total  funding  shortfall over  the 20 years drops  to  just under $ 10 M, which  is a $ 1 M improvement over the Status Quo and a $ 3.2 M improvement over the Medium Growth scenario (with NPV now of about $ 7.3M).  

Looking at  the  last column  in Table 5‐10, we  see  the effects of  the  increased  rates with  the Medium Growth  scenario. Compared  to  the Medium Growth with current  rates, we  see  the operating  income 

COMPARISON Status Quo Medium Growth High Growth Medium GrowthBase Rates Base rates Base rates Revised rates

(Cumulative over 20 years)Opening Reserve in 2012 1,538,706$ 1,538,706$ 1,538,706$ 1,538,706$ Retained Earning (Ops) 4,924,690-$ 2,920,234-$ 2,226,070$ 1,307,924-$ Revenue from Land Sales 828,159$ 1,301,117$ 1,217,399$

Revenue from Development Levy 26,549$ Planned Capex (Development/Capacity) 5,152,496-$ 7,465,289-$ 5,152,495-$ Planned Capex (Maintenance) 7,429,585-$ 7,429,585-$ 7,429,585-$ 7,429,585-$

Projected Surplus / (Shortfall) 10,815,569-$ 13,135,450-$ 9,828,980-$ 11,107,350-$

NPV (Surplus / (Shortfall) 6,448,198-$ 8,656,543-$ 7,353,954-$ 7,483,970-$

PED-9-2013-4B

Page 160: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 129

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

improves to a net loss of only just over $ 1.3M vs a cumulative loss of over $ 3.0M. We also see a 50% increase  in  land  sales and associated  fees over  the  current pricing  case. Together  these  rate and  fee increases are able to reduce the cumulative funding shortfall by some $ 2 M over the Medium case with the  current  rates  (to  about  $  11.0M).  But  these  higher  rates  are  not  as  effective  at minimizing  the funding shortfall as  is the case with more aggressive development as seen  in the high growth scenario (where the funding shortfall was  just under $ 10 M.  In this medium case with the  increased rates, the NPV is just under $ 7.5M). 

While we have not modelled a High Growth Scenario with increased fees, it is quite easy to extrapolate that such a scenario would result in across the board improvements in all of the numbers in Table 5‐10. We project  that under  such as  scenario,  the  total  funding  shortfall over  the 20  year period analyzed could drop to in the range of $ 7 M to $ 8 M and the NPV would be somewhere between $ 6.0M and $ 6.5M.     

So what can we learn from the above financial analyses? 

We suggest the following lessons from the above: 

Regardless of  the  financial scenario,  the airport will need  to continue  to contribute  in  the range of an average of about $ 500,000 per year into the airport reserve fund, much as it has been doing in past years;  

Considering  only  funding  shortfalls  for  the  airport,  the  status quo, whereby no money  is invested in expanding the airport facilities, but money is spent on maintaining those already existing,  is  a  feasible  option,  as  this  results  in  the  lowest  overall  NPV  of  the  scenarios actually modelled, and would be  similar  to  the projected best case NPV with high growth rates and increased land sale prices; 

Investing  in only modest expansion of the airport without adjusting current rates (many of which  are  too  low  in  absolute  terms,  but  also  too  low  in  comparative  terms with  other airports), does not appear to be as attractive as the status quo. 

Major  investments  in  additional  facilities  at  the  airport,  combined  with  aggressive  land development and  increases  in key  fees such as  land sales,  land  leases, among others, can pay  large dividends and  in  the end more  than pay  for  themselves, as  illustrated with  the projected NPV of a High Growth case with increased fees; 

Aggressive  land development and marketing, both of which can attract additional traffic to the airport, combined with appropriate  increases  in  fees charged across all aspects of  the airport’s  operations,  can  result  in  achieving  airport  operating  surpluses  as  early  as  2020, depending on the scenario;       

Any of the “investment” related options, would pay additional dividends to the community in  terms  of  the  economic  impacts  of  the  associated  investments, whereas  a  status  quo option  would  forgo  the  potentially  significant  economic  spin‐off  impacts  of  these investments, both on an  initial  investment basis, as well as continued contributions due to operations;  

A more aggressive  land sale policy should be considered as a means of  lowering the  initial capital investment shortfalls, as once many of these land development investments are well underway,  the airport should be  in position  to generate annual operating surpluses  (2020 +/‐).           

PED-9-2013-4B

Page 161: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 130

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

6.0 BUSINESS PLAN

This section provides a brief outline of a proposed business plan for the airport, based on our findings from the above analyses, with a focus on Strategic Direction, An Action Plan, Marketing and a Financial Plan.  

6.1 STRATEGIC DIRECTION

MISSION / AIRPORT ROLE

The Muskoka Airport  is  a  commercial General Aviation  (GA)  airport  that  promotes  and  supports  the social and economic needs of the District of Muskoka. 

VISION

The  long‐term vision of  the airport  is  that  it will continue  to operate as a commercial entity which  is developed as an economic development tool that supports the social and business needs of Muskoka, in an efficient and financially prudent manner. 

AIRPORT OPERATOR’S ROLE

The mission or role of the District as the airport owner and operator is to: 

Manage and operate the airport in a safe, secure and financially responsible manner; and 

Advance economic and community development. 

VALUES

The values outlined in the 2006 Strategic Business Plan continue to be valid:    

Ensuring safety 

Excellence in customer service 

Providing the community with a transportation link and an aviation business node 

An effective and cost efficient operation 

Open and effective communication 

Positive relationships and teamwork 

Integrity, accountability and dedication  

 

 

 

 

 

 

PED-9-2013-4B

Page 162: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 131

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

OBJECTIVES AND GOALS

OBJECTIVE  GOALS 

To  ensure  that  the  airport  facilities  and  equipment continue  to be maintained  to  TC  regulatory  standards and that all regulations are met and the Airport retains its certification. 

continue to have successful TC inspections and audits 

To minimize the financial burden on the taxpayers.  Maximize operating  revenues  

Minimize operating costs  

Secure external capital funding 

Reduce tax levy  

Reduce lengthy decision making processes 

To  foster  aviation  related  business  growth  and development. 

Expand  amount  of  occupied  land    through expansion  by  existing  tenants  and  attracting  new complementary aviation tenants 

 

To support tourism growth in Region.  Enhance promotion of airport 

Increase  numbers  of  itinerant  GA  related  to tourism 

Provide attractive  facilities  to  foster new  itinerant traffic 

 

Create more jobs in Region  Develop  additional  airport  lands  to  attract  new aviation related business by aggressively marketing the airport 

KEY SUCCESS FACTORS

Development ready land to accommodate growth from existing and new tenants; 

Full‐FBO service; 

Strong  Airport  “champion”  and  proactive  management  with  entrepreneurial  spirit;  Strong commercial focus with an emphasis on maximizing non‐aeronautical revenues; 

Strong marketing efforts to identify and chase new opportunities; 

Strong customer service focus; 

Effective links to the community with strong community support;  

Accountability and empowerment of airport management; 

Effective decision making processes; and 

Effective communication and collaboration with partners including Muskoka Tourism, Economic Development, Chamber of Commerce, aircraft operators and other key stakeholders;  

PED-9-2013-4B

Page 163: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 132

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

6.2 MARKETING

TARGET MARKET

The airport should focus its marketing efforts on the following group, in priority order: 

Existing  tenants who have plans  for expansion.    It  is  anticipated  that existing  tenants have  a demand for approximately 5 acres of land (large hangars); 

Aviation  businesses  that  could  provide  services  that  complement  those  provided  by  existing tenants (med‐large hangars); 

Corporate  aircraft  owners  that  will  be  displaced  from  the  Greater  Toronto  Area  (Pearson, Buttonville, Toronto City Centre) (small‐med hangars); 

Private aircraft owners that will be displaced from the Greater Toronto Area (T‐hangars); 

New flight school to be based at the airport (office, classroom and hangar space); 

Itinerant GA (private / recreational) (fuel sales). 

 

MARKETING MIX / FIVE P’S

Products and Services  – The Muskoka airport offers its customers superior facilities and services including:  

o Airfield infrastructure – long runway, good navaids, precision approaches   

o Full‐serve fuel (AvGas and Jet) 

o Ground handling and catering 

o Tie‐downs and hangars 

o Maintenance  –  airframe  and  powerplant  maintenance,  as  well  as  avionics,  aircraft painting  

o Efficient  ground  transportation  service  including  rental  cars  (available  upon  advance request) 

o Food service at a nearby restaurant 

o Proximity to GTA with excellent road network 

o Many  tourism  related amenities  (hotels, B&B, attractions,, eco and wildnerness  tours (Algonquin Park)  

Pricing  

o Competitive rate structure 

o Market rate pricing on land 

o Land sales policy (very attractive to prospective tenants) 

Place – when and where to market to target audience; mechanism through which services are provided to the customer 

PED-9-2013-4B

Page 164: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 133

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Promotion – airport should employ a variety of methods to aggressively market available  land, and to promote the airport, including: 

o Advertising in appropriate trade magazines 

o Identifying key customers and contacting each directly 

o Attending appropriate conferences attended by target audiences 

o Joint marketing  efforts with  Tourism Muskoka,  local  tourism  operators,  Chambers  of Commerce, PED,  

People  –  Develop  new  and  enhance  existing  working  relationships  with  Tourism  Muskoka, Chambers  of  Commerce,  local  tour  operators,  COPA,  CBAA,  and  potential  federal  funding partners  

AIRPORT BRANDING

A brand or positioning statement defines what  the brand stands  for.    It should  identify what sets  the organization  apart,  and why  the  organization  is  unique.    Competitors  should  not  be  able  to  simply substitute their name for yours.  The brand identity is a set of identifiers such as logos. 

While  the Muskoka Airport has a brand  identifier  in  its  logo  (shown at  right) that  somewhat  reflects  aviation  as  shown  in  the  graphic  of  a  pilot, within  a natural  setting,  and  with  the  identifier  “The  Little  Norway  Memorial”,  the airport does not appear to have a strong brand statement (or tag line), though “A Proud Legacy” does show up in their material, but clearly separate from the logo.   

Examples of brand messages (tag lines), and logos at other airports include: 

Campbell River Airport (YBL) – Minutes from Your True Nature    

Penticton Regional Airport – Gateway to the South Okanagan  

Lake Simcoe – Central Ontario’s Best Connection   

Parry Sound Airport – the Natural Place to Land    

 

Oshawa Airport – Your Aviation Gateway to the City of Oshawa and the Region of Durham 

It  is  recommended  that  the airport develop a  strong brand message  focused on  the  target audience and/or the unique aspects of tourism in Muskoka.  The current message that hints at the “the home of the Little Norway Memorial” is interesting and should be used in more of the airport’s marketing, but a stronger brand could also be pursued. Something  like “A Full Service Gateway  to Algonquin Park”, or “Gateway to Muskoka Cottage Country” might also complement the Region’s tourism focus. The intent here is not to necessarily suggest the final product but to recommend that stronger brand message be developed. 

PED-9-2013-4B

Page 165: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 134

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

6.3 ACTION PLAN

SHORT-TERM (2013)

Approve development plan B‐R; 

Increase land lease and sales rates as well as the AMC; 

Confirm development intent of existing tenants and negotiate agreements 

Acquire land  to the east to permit grass runway relocation  

MEDIUM TERM (2014-2018)

Move to an Airport Commission operating structure; 

Reduce landing fee exemptions from 5 tonnes to 3 tonnes for based aircraft, and from 3 tonnes to 1 tonne for visiting aircraft 

Approve  a  new  one‐time  development  service  fee  similar  to  (but  slightly  less  than)  Lake Simcoe’s (waived for Phase 1 i.e., implement before 2019; 

Approve a new one‐time airport development permit fee similar to (but slightly less than) Lake Simcoe’s (waived for Phase 1 i.e., implement before 2019); 

Approve  a  new  one‐time  airport  development  levy  similar  to  (but  slightly  less  than)  Lake Simcoe’s (waive for Phase 1 i.e., implement before 2019) 

Develop  comprehensive  marketing  program,  including marketing materials  (brand  message, logo, print materials etc.), key messages, advertising plan,  

Implement  land development program on a phased approach  i.e.,  line up  customers prior  to developing the land 

6.4 FINANCIAL FORECASTS

In  Section  5  it  is  demonstrated  that  the most  positive  financial  scenario  would  be  to  aggressively develop and market new  commercial  lands.   To be  conservative however,  the  financial  forecasts are based  on  a medium  development  and  traffic  scenario.    Additional  revenues  can  be  expected  to  be achieved through a more aggressive land development timeline, complemented by aggressive marketing efforts.  The financial forecasts include the following detailed assumptions: 

No changes to the certification status of the airport; 

No changes  to  the current ownership structure however a move  to an Airport Commission as the operator33; 

Staffing levels are assumed to increase due to the expanded developments34;  

                                                                 33 Costs to implement a Commission structure (particularly legal costs) are considered to be offset by incremental revenue not already built into the financial model 34For simplicity we have assumed that staffing levels increase, adding about $50,000 in additional staff costs in 2015, and thereafter this amount increases in line with inflation. We have kept this assumption constant across all expanded development scenarios.     

PED-9-2013-4B

Page 166: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 135

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Medium traffic growth (see section 3.3); 

Implementation  of  Development  Plan  B‐R  (phased)  including  taxiways,  parallel  runway  and paving the grass runway at a cost of $7M ($6.5M within planning period);  

Land take‐up of 35 available acres is assumed to be 15 acres during the planning period 

Land‐take up  is assumed to be 100% sold  in year 2014,; with remaining parcels 50% sold, 50% leased in years 2019, and 2022 

Increase in land sales rates by 47% to $111,304 / acre (2013$) 

Increase  land  lease  rates by 47%  to $1.34/m2  (Lake Simcoe’s  rates  less 10%) escalated by 2% p.a.; 

Increase AMC by 21% to $0.97 / m2 (Lake Simcoe’s rates less 10%), escalated by 2% p.a.; 

A new one‐time Development Service Fee of $0.40/ft2 (building area) to be drawn upon by the Airport  to  review  the  development  application.  This  is  equivalent  to  $7,841/acre.  Unused portions of fee to be returned to the tenant. Assume 50% of the fee will be used.  Building area assumed to be 45% of land area.  Fees waived on development taking place in 2014 

A new one‐time Airport Development Permit Fee of $0.90/ft2 (building area) to be drawn upon by the Airport to review the development permit submission and provide periodic site review as required.  This  is  equivalent  to  $17,642/acre. Unused  portions  of  fee  returned  to  the  tenant. Assume 50% of the fee will be used.  Building area assumed to be 45% of land area.  Fees waived on development taking place in 2014; 

A new one‐time Airport Development Levy of $4.64/ft2 (building area) excluding space used for storage of aircraft.  Total building area assumed to be 45% of land area, however 90% of that is assumed  to  be  for  aircraft  storage.    Rate  therefore  applies  only  to  980  ft2  per  acre  sold  or leased. 

Reduction in exemptions for landing fees (from 5 tonnes to 3 tonnes for based aircraft, and from 3 tonnes to 1 tonne for visiting aircraft; no other changes to the aeronautical rate structure 

Aeronautical  fee  schedules  (rates) will  increase  rates  by  2%  per  year with  the  exception  of aviation fuel which will increase 5% p.a. (as will the cost of fuel sold); 

Ramp fee revenues increase with traffic and with CPI rate increases; 

Fuel revenues increase with traffic plus a 5% rate increase per year; 

Operating expenditures  increase at 2% p.a. except utilities,  fuel  (fleet and equipment),  taxes, insurance, travel fleet, and cost of fuel sold that each increase at 5% p.a. 

The operating expenses associated with materials and equipment,  fuel  (fleet and equipment), building maintenance and  supplies, grounds maintenance and  supplies, and equipment  repair do  increase with  land development  and  the  increase  is based on  two‐thirds of  the  increases associated with airfield area:  1.5% growth in 2017 and 18% growth in 2022; 

Costs associated with setting up a Commission (e.g., legal) are assumed to be offset by increased revenue due to additional marketing and more aggressive revenue targets. 

 

Given these assumptions, the airport will begin to see an operating profit in 2021/22. 

PED-9-2013-4B

Page 167: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 136

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

 

  2012 (budget) 

2013  2017  2022  2027  2032 

Revenues (incl asset sales) 

$1,834,700  $2,030,413  $2,710,066  $4,434,429  $5,200,753  $6,755,076 

Expenses  $2,158,506  $2,288,396  $2,948,614  $3,997,240  $5,157,350  $6,591,963 

Income (excl sale of assets & dev. Levy) 

‐$323,806  ‐$257,983  ‐$238,608  $21,828  $43,403  $138,435 

 

The table below shows a summary of cash flows during the planning period.  Assuming that the District is responsible for two‐thirds of the capital funding, with the remaining one‐third being funded through government programs  (e.g., FedNor), during  the  first  ten years of  the development plan, slightly over $600,000 is required in tax levies each year to cover capital expenditures and operating losses; however this drops significantly in the next five year period and continues at much lower levels. 

 

 

 

 

 

 

SIMPLE CASH FLOW 2012 2013-2017 2018-2022 2023-2027 2028-2032 TotalsOpening Balance Reserve 1,538,706$ 1,538,706$ Retained Earning (Ops) -$ 1,243,995 601,725-$ 27,683-$ 565,479$ 1,307,924-$ Revenue from Land Sales 567,650$ 649,749$ -$ -$ 1,217,399$ Revenue from Development Levy -$ 26,549$ -$ -$ 26,549$ Planned Capex (Development/Capacity) 1,499,182-$ 3,653,313-$ $0 -$ 5,152,495-$ Planned Capex (Maintenance) 4,336,600-$ 806,694-$ 319,697-$ -$1,966,594 7,429,585-$

Projected Surplus / (Shortfall) 1,538,706$ 4,973,421-$ 4,385,434-$ 347,380-$ 1,401,114-$ 11,107,350-$

NPV (Surplus / (Shortfall) 7,483,970-$

994,684-$ 877,087-$ 69,476-$ 280,223-$

644,537-$ 609,486-$ 50,294-$ 162,227-$

Avg annual amount to be financed through taxes &/or other during 5 year period - if airport pays 100%

Avg annual amount to be financed through taxes &/or other during 5 year period - if airport pays two thirds (other 1/3 - FedNor)

PED-9-2013-4B

Page 168: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 137

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

7.0 GOVERNANCE

Airport ownership and operating models vary. The particular models are a  result of both history and choice. The key influencing factors are: 

The degree of financial self‐sufficiency. Generally, governments do not like to provide capital or operating  financial  subsidies without  having  a  significant  say  in  how  the  airport  is managed. Accordingly  more  of  the  smaller  airports  that  are  not  self‐sufficient  (which  is  the  greatest portion) tend to be government operated and more of the larger airports have varying degrees of autonomy. 

Degree of autonomy.  There is a broad range of ownership models and the degree of autonomy in  decision making  is  equally  broad.  Autonomy  tends  to  be  closely  linked  to  financial  self‐sufficiency. 

Labour practices.  There can be significant differences in public sector and private sector labour practices, and this can influence the ownership model. 

The broad categories of airport operation can be thought of as: 

Local Government ownership and operation 

o Regional / District owns and operates (current situation) 

o Individual municipality owns and operates  

Local Government owns and an independent not‐for‐profit organization operates 

o Airport Commission 

o Airport Authority 

Local Government owns and private sector operates 

Private sector owns and operates 

In Ontario  and  in  Canada,  there  terms  “Authority”,  “Commission”  and  “Society”  are  used  loosely  as there are many permutations and combinations within each of the basic models depending on how they were established, and the level of delegation given to the operator. 

Based on a recent study35 done for the Ontario Ministry of Transportation, there are some 84 Municipal Airports in Ontario. These are distributed geographically as follows:  

46 in the South; and  

38 in the north. 

These various municipal airports are operated by a variety of models, as listed above. The distribution of the operating models used at these Ontario municipal airports is illustrated in the graph below. Per this data, some 46 of these airports, or 55%, are currently operated by the municipalities that own them. An additional 18, or 21%, are operated by Airport Commissions or Airport Authorities. The remaining 20, or 

                                                                 35 Final Report, Ontario Municipal Airports Data Collection Study, 2011 Update, Leigh Fisher Management Consultants. 

PED-9-2013-4B

Page 169: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 138

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

24%,  are  operated  by  private  entities36.    The  proportion  of  airports  operated  by  either  Airport Commissions/Authorities or the private sector is higher in the south than it is in the north (52% vs 37%). 

 

Source: Final Report, Ontario Municipal Airports Data Collection Study, 2011 Update, Leigh Fisher Management Consultants 

 

7.1 ALTERNATIVE GOVERNANCE MODELS

CURRENT GOVERNANCE MODEL – DISTRICT OWNED AND OPERATED

The airport was transferred to the District in 1996 as part of the federal government’s National Airports Policy.  At the time, it was recognized by Council that the airport was important to Muskoka’s economy, and an essential link in Muskoka’s transportation infrastructure.  It was also recognized that there was a “community  of  interest”  in  the  Airport  which  affected more  than  one municipality.    In  July  2005, Muskoka District Council re‐confirmed its commitment to retain ownership and operation of the airport as a regional asset following the expiration of the transfer agreement with Transport Canada in October 2006. 

The District  of Muskoka,  a  regional municipality within whose  boundaries  are  located  the  Towns  of Bracebridge, Gravenhurst, Huntsville, and the Townships of Georgian Bay, Muskoka Lakes and Lake of Bays,  owns  the  Airport.    The  airport  is  operated  (managed)  within  the  Planning  and  Economic Development  (PED) department of  the District government.   The District  is  responsible  for operating, marketing and developing the airport.  This can be referred to as the Regional or District Model. 

                                                                 36 In many cases, small airports with little traffic are operated on behalf of the municipality by the local flying club, especially when they are the most frequent user.    

PED-9-2013-4B

Page 170: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 139

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Airport staff report through the Commissioner of PED who reports to the District Chief Administrative Officer  (CAO).  For  airport matters,  the  CAO  and  the  Commissioner  of  PED  report  to District  Council through the Planning and Economic Development Committee.  This PED Committee also receives advice from a 13 member Airport Advisory Committee  chaired by a District Councillor and  comprising other District  Councillors,  and  interested  community members  including  commercial  tenants,  local  pilots, among others. 

The airport budget  (operating and capital)  is prepared by PED and approved by Council on an annual basis.    The  costs  not met  by  revenues  associated with  the  airport  are  funded  through  the District’s budgeting process.  

There  are  4  full  time  employees  at  the  airport  (in  additional  to  3  seasonal  co‐op  students,  for  the equivalent of 5.04 FTE’s). All are employees of the District and fall within the collective agreements of the District.   

The airport purchases internal corporate services such as human resources, legal, finance, engineering, trades, and property management, from other District departments.    

 

 

 

 

 

This type of government owned and operated governance model, with the airport reporting through a government department works best when the airport has a heavy general aviation focus, is recognized as an economic driver  for the Region, and when many smaller municipalities benefit  from the airport.  This type of model also allows for workforce flexibility (e.g., cross‐training within the District and part‐time support from other departments). 

Other benefits of this model include:  

very  few  requirements  for  special  arrangements  as  airport  staff  are  employees  of  the municipality; 

District Council

CAO

Other Department s (HR, Legal, Finance, Engineering , trades, property management  etc.)

Airport Manager

Full Time Airport Staff

Planning & Economic Development (PED)

Airport Advisory Committee

Seasonal Airport Staff

Planning & Economic Development Committee

Airport purchases internal services from other departments

PED-9-2013-4B

Page 171: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 140

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

mobile  maintenance  equipment  can  be  stored  and  maintained  in  municipal  garages  i.e., reducing the necessity of duplicate facilities at the airport; 

shared support services, equipment and facilities can lower costs; 

all  municipalities  participate  through  the  governance  structure  through  their  elected representatives; 

costs are shared among all municipal tax payers within the region; 

the  District  as  the  airport  owner  and  operator  typically  qualifies  for  infrastructure  subsidy and/or capital programs (e.g., recent infrastructure stimulus programs); 

tax levies are available to cover operating and capital requirements. 

This model does however have its challenges, including: 

decision making can be politically driven and/or lengthy; 

many political/government stakeholders each trying to represent their own communities; 

many government stakeholders without a background in aviation;  

municipal budgets are already stressed, and the airport needs to compete with other municipal priorities; 

shared support services can increase the time to action / implement; 

when  funding  programs  come  along, municipalities  often  have  to  choose  their  top  ranked priority, and often airport requirements come after sewers, roads and water treatment facilities; 

property  taxes  accrue  to  the  municipality  within  which  the  airport  is  located  (in  this  case Gravenhurst), versus to the District; 

the taxing regime can often be perceived as unfair (inequitable distribution vs the benefits); 

Advisory Committees may not function properly,  if there are too many members, of  if there  is unbalanced representation, of if the individuals appointed are not appropriate to the tasks. 

SINGLE LOCAL GOVERNMENT OWNS AND OPERATES

This model is essentially the same as having a Region or District own and operate the airport; however only one area municipality/City/Town owns and operates the airport. 

This type of model works best when the airport  is recognized as an economic driver  for primarily one municipality; typically the municipality with significant population and/or economic activity. 

The benefits of this model are the same as with the Region / District model. However, because there are fewer interests to be represented, approvals and decision making is typically quicker. 

The challenges of  this model area also  the same as with  the Region   District model; however  if more than one municipality benefits, cost sharing (if an agreement can be negotiated) can be more difficult to manage; particularly if one opts out. Additionally, those municipalities without direct involvement in the operation of the airport may feel a  lack of control or  influence over airport decisions that could affect them. 

An example of this model within Ontario is the City of Kingston. 

 

PED-9-2013-4B

Page 172: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 141

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

 

 

GOVERNMENT OWNED, AIRPORT COMMISSION OPERATES

With this model, the local government owns the land and buildings.  A not‐for‐profit Airport Commission (similar to a Municipal Board) is established by one or more municipal governments under power of the Municipal Act or by Provincial legislation.   If incorporated, the Commission could have independent and legal authority of its own.   The Commission is a partially autonomous body with delegated powers over some airport issues.  These powers and delegations are set through Municipal bylaws.  

The Commission’s management board typically includes a mix of elected councillors and individuals with aviation  experience  nominated  by  the  municipality(ies).    The  Commission  reports  to  Council  who approves the operational and capital budgets on an annual basis. 

While financial self‐sufficiency is not required, it is desired, and this model works well when the airport has  a  strong  commercial  focus.   Under  this model,  funding,  if  required,  continues  to  come  from  the municipality(ies). 

How  the  airport  staff  are  employed  is  up  to  the municipality when  the  Commission  is  set  up.  For example, airport staff can either be employed by the Commission (if  incorporated as a  legal entity), or could remain employed by the municipality.    

Corporate services can either be provided by airport staff, or can be purchased from the municipality or other external parties.   

 

Municipal Council

City Manager / CAO

Other Departments

AIRPORT

Airport Manager

Dedicated Airport Staff

Municipal Department

Airport Advisory Committee

PED-9-2013-4B

Page 173: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 142

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

 

 

The primary benefits of this model are: 

The airport is operated like a business to the greatest extent possible; 

The  Commission  has  operational  independence within  approved  budgets  i.e.  an  arms‐length relationship with the government owner, thus providing airport specific  focus which  facilitates decision making and implementation; 

The municipality retains control over budgets; 

There is a balance of stakeholder interests and more aviation experts on the Commission, again facilitating decision making and implementation; and 

The Commission acts as a “champion” for the airport and may take a more energetic interest in the airport;  

As with all models, the Commission also has its challenges, for example: 

It is not free from political influence, although there is less than with a government owned and operated model;  

From the government owner’s perspective, it loses direct control over operational decisions; 

The local government contributions still have to compete with other municipal priorities;, and 

The Commission would need  to consider broader regional economic development goals when making airport focused decisions. 

Examples of Airport Commissions  in Ontario are  found  in Parry Sound, Gore Bay‐Manitoulin, Niagara District (St. Catherines), and Manitoulin East. 

Airport Manager

Terminal Operations

AirsideOperations

Municipal Council

Airport OwnerMunicipality (ies)

Planning & Engineering

BD & Marketing

Corporate Services 

Airport Commission

PED-9-2013-4B

Page 174: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 143

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

GOVERNMENT OWNED, AIRPORT AUTHORITY OPERATES

With this model, the local government owns the land and buildings.  A not‐for‐profit Airport Authority is established as a non‐share capital corporation incorporated under Canada Corporations Act Part II, or by provincial  legislation.    The Authority operates  the  airport  independently under  its own  set of bylaws (different than the Federal Airport Authority model), and has no direct ties to a municipal body.     The Authority  has  significant  control  over  all  aspects  of  its  business,  and  is  most  often  self‐sufficient financially. Employees may or may not be unionized.   

 

 

 

The  Authority  is  governed  by  a  Board  of  Directors  typically  nominated  by  the  airport  owner  and community at large.  Board membership typically comprises a good mix of outside experts.     

Financial  self‐sufficiency  is  typically expected  (cover operational and  capital  costs), based on a  strong commercial revenue stream.  

Airport staff are typically employed by the corporation, although there are examples  in Ontario where the  staff  remain  employees  of  the municipality.    As with  a  Commission,  corporate  services  can  be provided directly by airport staff, or purchased externally or from the municipality.  

Authorities can typically borrow money at commercial rates. 

The primary benefits of this model are: 

The Authority is independent and free from political influence; 

A strong airport commercial focus; 

Ability to borrow on the commercial market; 

The  Board has broad stakeholder representation and has a good mix of experts; 

As with all models, the Authority also has its challenges, for example: 

Airport Manager / CEO

Terminal Operations AirsideOperations

Board of Directors

Airport OwnerMunicipality

Planning & Engineering BD & Marketing

Corporate Services 

PED-9-2013-4B

Page 175: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 144

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

It almost always needs to ensure financial self‐sustainability  

Examples of Airport Authorities in Ontario are found in North Bay, Sudbury, Kenora, and Lake Simcoe. 

GOVERNMENT OWNED, PRIVATE OPERATOR

With this model, the local government owns the land and buildings, but contractors out the operations to a private operator i.e., a service contract.  The operator prepares the annual budgets, and submits to the  municipality  for  approval,  then  works  within  that  budget.    The  airport  owner  retains  the responsibility for airport development and funding.  The owner also retains the liability risk yet has little control over the private contractor’s actions. 

This type of model works best when the municipality lacks experience in airport management, and there is interest from the private sector, often a based tenant. 

The challenges associated with this model is that the contract must provide the private sector operator with sufficient ability to earn a profit, and there is likely no access to shared services.  Additionally, if the contactor  suddenly becomes unable  to manage  the  airport,  there may not  readily be  a  replacement contractor or trained municipal staff to step in, even on a temporary basis. 

Examples of privately operated airports in Ontario include Hamilton, Peterborough, and Red Lake. 

 

 

PRIVATELY OWNED AND OPERATED

With  this model,  the  private  sector  owns  the  land,  infrastructure  and  equipment,  and  operates  the airport.  The private operator is responsible for operating, marketing and developing the airport. 

This  type  of model works  best when  there  is  sufficient  commercial  revenue  stream  for  the  private owner/operator to make a profit. The benefits of this model are that, there is no financial risk or burden to  the municipality,  and  tax  revenues  continue  to  accrue  to  the municipality  in which  the  airport  is located. 

The challenges however are that  it could be more expensive for the user (although some would argue that private sector operation  is more efficient than government), the municipality has no control over 

Private Sector Airport Manager

Dedicated Airport Staff (private sector)

Municipal Council

Airport OwnerMunicipality

City Manager / CAO

PED-9-2013-4B

Page 176: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 145

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

the services or  facilities provided, and  the municipality  loses all potential  revenue streams other  than taxes.  The biggest risk is that an important municipal asset could be lost if the operator ceases to exist.   

Examples of a privately owned and operated airport in Ontario include Sault Ste. Marie. 

SUMMARY

Figure 7‐1 below summarizes the benefits and challenges associated with each model. 

Figure 7‐1: Comparison of Alternative Airport Governance Models  

 

7.2 IT’S ABOUT MORE THAN GOVERNANCE

There is no single structure that will best apply to the management and operation of municipal airports.  It is highly dependent on a number of factors, including: 

Owner Operator Pros Cons

Region / District

Region / District

• Shared funding among all municipalities or tax payers who benefit

• Ability to retain internal or shared services• ability to cross‐utilize some vehicles & 

equipment • Tax levy spread out over larger regional tax 

base with more tax payers

• Many political stakeholders with equal voices;• Council not airport experts• Potential for political &/or lengthy decision 

making• Airport competes with other infrastructure 

priorities for funding• Potential for one or more municipalities to opt out 

of cost share agreement• Loss of control from other municipalities

Single Municipality

Single Municipality

• Similar to Region/District, except:• Fewer municipal and political stakeholders 

with decision making power; could facilitate approvals

• Similar to Region/District, except:• No opportunity to opt out, or “loss of control” 

issues

Region / Municipality

Airport Commission

• Operated like a business to the greatest extent possible

• Municipalcontrol maintained over budgets• Operational independence within approved 

budgets ;  faster decision making• Ability to retain internal or shared services• Balance of stakeholder interests; many with 

aviation experience• Airport champion• Council freed from external lobbying efforts

• Ownerhas less operational control / influence, though there are still opportunities for political influence

• Goal of regional economic development needs to be balanced with attention to bottom line

• Local government contributions still have to compete with other municipal priorities

• Owner retains liability risk; yet little control over private operator’s actions

Region / Municipality

Airport Authority

• Operated like a business• Independence; free from political influence• Board typically comprised of a good mix of 

external experts• Ability to borrow as municipal funding typically 

not available (or in most cases required)• Airport Champion

• Must ensure financial self‐sufficiency• Usually no access to shared services, although 

possible• Owner retains liability risk; yet little control over 

private operator’s actions

Region /Municipality

Private • Experienced  & interested airport  operator (usually a based tenant)

• Non‐unionized environment

• If contractor leaves unexpectedly; leaves a big hole to fill

• No access to shared services• Owner retains liability risk; yet little control over 

private operator’s actions

Private Private • No risk or financial burdenon municipality • Municipalasset (economic generator) could be lost if operator closes

• Access to capital 

PED-9-2013-4B

Page 177: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 146

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Scope and complexity of activities; 

Actual benefit derived by the municipality; 

Level of service decided upon; 

Interest in the community; 

Municipal organization itself; 

Number of participating municipalities; 

Influence of airport users; 

Willingness  of  volunteers  from  inside  and  outside  of  the  aviation  community  to  contribute, participate and serve on an advisory committee; 

Degree of cooperation among participants such as Tourism, Economic Development, Chambers of Commerce, etc.; and 

Entrepreneurial spirit / business orientation of airport management.  

Successful airports, regardless of ownership or operations structure are characterized by: 

 A strong commercial focus, with an emphasis on maximizing non‐aeronautical revenues; 

An entrepreneurial focus in the airport management team; 

A strong customer service focus; 

Effective links to the community; 

A commitment  to consultations and a partnership approach with aircraft operators and other key stakeholders; and 

Effective planning processes with publicly available planning documents. 

7.3 POLICY MAKERS AND MANAGEMENT

Regardless of  the airport management approach,  responsibilities are  typically divided between policy makers and management. In a public service operation policy makers may be at the government  level, while  in a Commission model, the Commission body  is the policy maker; and  in airport authorities and private airports, the policy maker role is held by the Board of Directors.  

THE ROLE OF POLICY MAKERS

Policy makers are normally responsible for: 

Selecting the airport manager; 

Setting goals for management; 

Overseeing the airport manager’s responsibilities; 

Establishing policies for airport operations and development; 

Working with management to develop a strategic plan and to guide implementation of the plan; 

Approving contracts; 

Acting as an advocate for the airport; 

PED-9-2013-4B

Page 178: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 147

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Reviewing and approving budgets and financial reports; and 

Monitoring financial performance. 

Airport policy makers are guided by: 

A code of ethics governing their own behaviour; 

Bylaws  –  the  rules  of  order  and  protocol  for  documenting  official  acts.    Policy makers  also approve new bylaws; 

Rules and regulations that typically set out the meaning of bylaws in more detail; 

Contracts and ordinances defining the Board’s relationship with the airport users and tenants; and 

The position descriptions for airport staff. 

To be effective, policy makers must be: 

Knowledgeable about the key financial information about the airport; 

Willing to promote the airport in their public activities; 

Supportive of airport management; 

Generally knowledgeable about the airport environment and trends in airport development and operations; and 

Clear of any conflicts of interest. 

The conflict of interest issue is one that frequently arises with the appointment of policy makers. People active  in aviation  (e.g.  general aviation operators, air  carrier management)  can believe  that  they will make a valuable contribution  to airport policy making, but can have conflicts. For example, a general aviation owner may be interested in low airport fees, but as a policy maker he/she should be interested in the financial viability of the airport. 

THE ROLE OF AIRPORT MANAGEMENT

Regardless  of  the  governance  model,  the  core  role  of  the  airport  management  remains  largely unchanged and includes: 

Operating  the  airport  in  a  safe  and  secure  manner  in  accordance  with  legislation  and regulations;  

Coordinating / reporting to the airport owner; 

Implementing policies developed by the policy maker; 

Maintaining all facilities – airfield, buildings, services etc.; 

Community relations including explaining the role and importance of the airport to the public; 

Financial planning and financial management; 

Environmental management; 

Planning the airport’s future; 

Staffing to achieve the airport’s goals; 

PED-9-2013-4B

Page 179: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 148

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Ensuring that training and tools are  in place to enable staff to effectively undertake their  jobs; and 

Ensuring that there are standardized methods of operation.  

 

7.4 GOVERNANCE AT YQA – MOVING FORWARD

The  District  has  already  confirmed  and  re‐confirmed  that  the  airport  is  viewed  as  an  economic generator.    However, many  stakeholders  interviewed  indicated  a  desire  to  change  the  governance model at YQA to add a more commercial focus.   

It is the consultant team’s opinion that the two most viable options for YQA are the Status Quo, and the creation of an Airport Commission. 

The status quo is working; however it is understood that opportunities are sometimes lost or stalled due to delays in the decision making process. 

Having  the  airport operated by  an  incorporated Airport Commission  could offer  the  following  added benefits: 

Subject matter experts  in the policy maker role. The Commissioner / Chairman would have an aviation background and would be dedicated to proactively promoting the airport; 

Broader representation from key stakeholder groups; 

The  planning  and  decision making would  be  put  in  the  hands  of  a  smaller  group, who  are subject matter experts with a  single  focus and not being pulled  in many directions. Decision making would be quicker and subject matter experts would not need to be brought up to speed on technical issues; 

More commercial focus; 

Council being freed from external lobbying efforts; 

Council would continue to be represented  in the policy maker role, would still be  in control of budgets, and would be kept informed / updated regularly through formal reporting. 

7.5 IMPLEMENTING AN AIRPORT COMMISSION AT YQA

The Commission would be incorporated under the Municipal Act or by Provincial legislation as a not‐for‐profit organization.  Specific powers and delegations would need to be set by Municipal bylaws. This is at  the  discretion  of  the District;  however  to  achieve  the most  benefit  from  a  change  in  governance model, the more autonomy given to the Commission, the better. 

The Commission would be made up of  representatives appointed by  the District as owner, as well as individuals with  aviation experience nominated by municipalities who have  a  range of  skills  sets  and experience  in  airport  management,  aviation,  legal,  finance,  business  etc.    Strategic  recruitment  of Commissioners should be done to fill gaps in key skill sets or to diversify representation of stakeholder groups.   The Airport Manager / Executive Director would be a non‐voting member of the Commission. The Commission’s role would be that of ‘policy maker’ as generally described above, but specifically to: 

Set strategic direction; 

Recommend annual business plan to Council for adoption; 

PED-9-2013-4B

Page 180: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 149

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Establish and approve policies and rate structures; 

Provide resource and financial oversight 

Approve land and facility leases, and sale of land within Council approved land sales policy; 

Determine expected performance levels, then monitor performance against plan; 

Ensure legal, fiscal and ethical integrity of the organization; 

Promote  the organization’s  image and  take  the  lead with  respect  to  the  relationship with key stakeholders and Council; 

Take an active role in business development / marketing; 

Provide direction to the Airport Manager; 

Conduct an annual performance review of the Airport Manager; 

Provide regular reporting to Council. 

Individual Commissioners would not have a mandate to direct activities of the airport. 

The  Airport Manager  /  Executive  Director  would  be  responsible  for  the  day‐to‐day  operations  and administration of  the  airport,  including  staffing,  issuing  contracts, paying bills,  recommending  leases, and preparing the annual business plans. 

Council’s role would be to approve the operational and capital budgets, and approve any borrowing for capital projects. 

The  Commission would  operate  the  airport  in  accordance with  approved  budgets.    Any  operational deficits would continue to be  funded by tax  levies.  If borrowing  is required, this could be done by the Commission up  to a  set amount pre‐established by Council,  in accordance with  terms  set by Council.  The  Commission would  be  responsible  for maintaining  and  arranging  for  the  audit  of  its  own  set  of financial  statements.    The  accounting  books  of  the  airport  will  no  longer  be  a  subset  of  the  PED department. 

Airport  staff  could  continue  to  be  employed  by  the  District,  or  could  be  employed  directly  by  the Commission.  When making a decision, consideration should be given to existing collective agreements, and the availability of qualified staff. 

Procurement  could  continue  to  be  done  through  the  District’s  procurement  department  if  this  is deemed the most efficient method. If this is the case, the Commission will need to accept the District’s procurement terms and conditions.  

The  Commission  would  become  the  “certificate  holder”  in  the  eyes  of  Transport  Canada  and  will become  responsible  for  operating  the  airport  in  accordance  with  legislative  and  regulatory requirements.  The airport owner (the District) will retain environmental liability; while the Commission holds all other liability e.g., public.  Both the Commission and the District will need insurance.  

Setting up the Commission  is a complex undertaking and will require the services of  legal counsel. It  is recommended that the District, should it choose to adopt this model, speak at length with other airports who have gone through this process. 

 

PED-9-2013-4B

Page 181: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 150

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

8.0 RECOMMENDATIONS

Based on the various consultations, analysis, forecasts, discussions and assessments carried out as part of this study, we make the following recommendations. These recommendations are grouped into key areas as follows:   

• Land development plan 

• Infrastructure Plan 

• Financial Plan 

• Business Plan 

• Governance  

LAND DEVELOPMENT PLAN

1. Land development at the airport over the next 20 or so years should be per Plan B‐R. The key 

features of this plan are as follows: 

a. Relocate the grass runway some 700‐800m to the north and orient this new runway in a 

12‐30 direction to better accommodate the needs of the airport’s smaller aircraft; 

b. Carry out additional surveys and a more detailed assessment to determine what actual 

length of  runway may be possible without  the need  to purchase  lands  to  the east  to 

achieve a length similar to what is there today (2,000 – 2,200 ft); 

c.  If necessary, purchase land to the east of the grass runway to accommodate a length at 

least as long as the grass runway is today;  

d. Develop  the  west  part  of  the  area  vacated  by  the  grass  runway  into  a  9‐10  acre 

subdivision  comprising  a mix  of  some  larger  lots  to  accommodate Muskoka  Aircraft 

Refinishing and/or   any other MRO  tenant  that may be  interested,  some  smaller  lots 

capable  of  handling  a  mix  of  some  private  aircraft  hangars,  T‐hangars  and  aircraft 

parking/tie‐down areas;  

e. Develop  the east  lands  to  the  south of  the new grass  runway  into a new 25 acre +/‐ 

subdivision  providing  a mix  of  large  lots  to  accommodate  potential  additional MRO 

activities, medium lots for aircraft hangars and supporting uses to MRO and smaller lots 

for a mix of T‐hangars, aircraft tie‐downs, and other uses; 

f. Develop a number of lots along the north side of Beaver Creek Road for aviation or even 

non‐aviation related landside type uses (those not requiring access to taxiways); 

g. Develop  lands  in  the area east of  the  threshold of Runway 18  for  covered  tie downs 

using Quonset hut type construction; 

h. Develop some area between  the parallel  taxiway and  the north end of Runway 18  for 

low‐cost, uncovered tie downs;   

i. Phase  the  land development  so  as  to meet  the  anticipated demand  in  a  just  in  time 

manner. For the 2 major subdivisions, the phasing would probably be in 4‐6 acre chunks. 

For the others, it should be as determined at the time. 

PED-9-2013-4B

Page 182: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 151

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

2. Over the very long term, the airport should consider mixed use of the lands located west of the 

airport between  the Gravenhurst Parkway and Highway 11. The key  features of  this very  long 

term plan could include the following: 

a. Relocation of  the Gravenhurst Parkway  to  the west  to provide  the primary means of 

access to the industrial lands located there; 

b. Reaffirming  the designation of  the  lands  to  the west  for mixed  industrial and aviation 

related uses; 

c. Terminating the south portion of the current Gravenhurst Parkway to provide access to 

the terminal area and MAR only; 

d. Relocating the abandoned north portion of the current Gravenhurst Parkway alignment 

further west  to  accommodate  future development  all  along  a  future parallel  taxiway 

along the westside of the main runway (18‐36);  

e. Making provision for the potential extension of the crosswind runway (12‐30) further to 

the east, permitting a total length of some 4,500 ft +/‐.   

f. This long term plan should be revisited and better defined in the next 10 year update to 

this Master Plan or at such a time that any development proposals are brought forward 

to develop the lands to the west. 

INFRASTRUCTURE PLAN  

3. Pave the grass runway  initially to about 2,000 ft or whatever  length may be possible given the 

constraints of the lands to the east. This will provide for better operations at the airport in terms 

of  ground  flows  as well  as  improving  the  accessibility of  the  airport.  This will  also make  the 

airport more attractive to some users, especially flight schools and others using smaller aircraft.     

4. Give consideration to paving the new runway  (12‐30) to a  length of about 2,800  ft  in order to 

provide better accessibility to and usability of the airport for smaller aircraft that cannot sustain 

higher  crosswind  components  and  to make  the  airport more  attractive  to wider  spectrum of 

users.  This  should  be  done  sooner  rather  than  later,  but we  acknowledge  it will  be  a  policy 

decision  based  on  availability  of  funds  and  a  variety  of  other  considerations.    Consideration 

should also be given to providing lighting along this runway, but this can be deferred to a later 

time in the future, depending on the actual use of this runway; 

5. Implement  LPV  approaches  to  the main  runway  to  improve  the  reliability  of  airport  access, 

install RILS on the runway to aid pilots on approach  and install a PAPI on Runway 36 to improve 

the safety of this approach;   

6. Protect  for the eventual extension of the parallel taxiway to 18‐36 all the way to the south to 

open up the lands to the west of this area and to improve the capacity of the main runway. Only 

construct this taxiway when required for  land access or capacity, but  in any case, probably not 

until the latter part of this 20 year plan; 

7. Reserve  sufficient  space  for a  terminal area apron expansion  to both  the north and  south  to 

accommodate  both  forecast  growth  in  aircraft  parking  and  potentially  unforeseen  growth  in 

terms  of  future  scheduled  carrier(s).  The  likelihood  is  that  an  apron  expansion may  not  be 

required until sometime in the 10‐20 year time frame, depending on how well the airport does 

in managing peak demands and when, if at all, a scheduled service may start up; 

PED-9-2013-4B

Page 183: Muskoka Business and Master Plan Final Draft Report-10May

  

 

Page 152

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

8. Reserve sufficient space for a terminal building expansion and associated car parking area. This 

may only be required sometime in the 10‐20 year time frame, depending on whether the airport 

attract becomes a base with a scheduled airline service; 

9. Develop  a more  detailed major maintenance  and  repairs  plan  along  the  lines  that we  have 

proposed  and  then  implement  on  an  as  required  basis,  continually monitoring  the  various 

facilities’ conditions so as to be able to adjust the timing of the major maintenance and repairs; 

10. Test alternative airport café/restaurant concepts, starting with minimalist concepts to prove the 

concepts and then working up from there should trials prove successful.  

FINANCIAL PLAN  

11. The  airport must  ensure  that  land  sales  through  its  land  sale  policy  are  properly  valued.  To 

ensure this, the airport must work with  local appraisers to ensure that they better understand 

the true value of airport lands. 

12. The airport  should  implement a  series of  supporting  fees and  charges  that are  similar  to but 

lower than competitors  like Lake Simcoe. These  fees could  involve development permit  levies, 

development service fees, etc.  

13. The airport should consider  increasing other fees as well,  including the AMC and others. These 

fees  should be  constantly  reviewed against  the  competitor airports and adjusted accordingly, 

with the goal being to maximize the airport’s revenues. 

14.  The airport  should aggressively pursue  land  sales as a means of attracting additional  tenants 

and to raise the necessary funds to pay for the various expansions.  

BUSINESS PLAN  

15. While the current airport logo and brand appear to be strong, consideration should be giving to 

reviewing  this  to  see  if  this could be enhanced  to better  reflect a more aggressive marketing 

approach for the airport. 

16. The business plan for the airport should be based on conservative targets and assumptions with 

respect  to  growth  and  land development, but  at  the  same  time  the  airport  should  pursue  a 

much more aggressive approach that can pay much stronger dividends.  

GOVERNANCE  

17. The District should consider moving to an Airport Commission Model to govern and manage the 

airport. This should allow the airport to focus on more commercial and customer service related 

activities  and  would  be  consistent  with  a  recommendation  to  more  aggressively  pursue 

development and land sales as means of improving the airport’s revenues.   

        

PED-9-2013-4B

Page 184: Muskoka Business and Master Plan Final Draft Report-10May

  

 

A‐1

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

APPENDIX A: LIST OF ORGANIZATIONS CONTACTED

The following organizations were contacted by SNC Lavalin Team members in August / September / October 2012.    While all organizations / people were contacted, not all were available for interview.   

ORGANIZATION  Person  Title 

Beaver Creek Institution – Correctional Service Canada 

Pam Gray  Assistant Warden 

Discount Car and Truck Rental  Paul LaLumiere  District Manager Ferrari Flight Training  Sandor Ferrari  Owner Lake Central Air Services  Elton Townsend  Owner Lake Simcoe Regional Airport  Mike Drumm  Airport Manager Muskoka Airport  Mark Stirling  Airport Manager Muskoka Aircraft Refinishing  Mike Goudie  Owner Muskoka District Council  John Klinck  Muskoka District Chair Muskoka Flying Club  Earle Robinson  President Nav Canada  Dean Edwards  Site Supervisor Northern Air Solutions  Heather and Gerald 

Vandertas Owners 

Ontario Ministry of Natural Resources  Larry D’Andrea  Senior Engineer Ontario Ministry of Natural Resources ‐  Air Services 

Bob Crowell  Operations Manager for OMNR Air Services 

Parry Sound Municipal Airport  Neil Pirie  Airport Manager Peterborough Municipal Airport  Nancy Hewitt  Airport Administrator Private Hangar Owner  Craig Thompson  Owner Planning & Economic Development  Committee – Muskoka District 

Lori‐Lynn Giaschi‐Pacini  Chair 

Private Hangar and Industrial Facility  Rob Clark  Industrial Facility Owner Town of Bracebridge  Graydon Smith  Mayor   Cheryl Kelley  Director Economic Development Township of Georgian Bay  Larry Braid  Mayor   Jennifer Schnier  Economic Development Officer Town of Gravenhurst  Paisley Donaldson  Mayor Town of Gravenhurst   

Tony Rossi  Director ‐ Economic Development & Communications 

Town of Huntsville  Claude Doughty  Mayor   John Finley  Economic Development and Grants Township of Lake of Bays  Bob Young  Mayor   Stephen Szczerbak   Planner Township of Muskoka Lakes  Alice Murphy  Mayor   Allen Edwards  Township Councillor   Ron Brent  Township Councillor   Lisa McMurray  Community Economic Development Officer Michael Wotherspoon  Michael Wotherspoon  Owner 

Air Muskoka  Dave Gonfors  Owner Grassroots Aviation  Bob Marsh  Owner Muskoka Tourism Agency  Michael Lawley        

                    

 

 

 

PED-9-2013-4B

Page 185: Muskoka Business and Master Plan Final Draft Report-10May

  

 

B‐1

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

APPENDIX B: LIST OF DOCUMENTS REVIEWED

DOCUMENT 

A Muskoka Airport Marketing and Business Development Strategy, November 2003 

Aerodrome Standards and Recommended Practices, TP312E, 4th Edition, March 1993, Corrigendum No. 2 Issued April 2005 

Aircraft Movement Statistics: Airports Without Air Traffic Control Towers: Annual Report (TP 577) 2011 

Airport Income and Development Review, March 2008 

Airport Operations Manual – The District Municipality of Muskoka ‐ Muskoka Airport, Amendment #3, September 6, 2005 

Airport Overview, Briefing for City Council, City of Peterborough, May 12, 2008 

Aviation Land Use in the Vicinity of Airports, TP 1247E, May 2005 

Background Report: Muskoka Airport Development Plan, May 30, 2011 

Background Report: Muskoka Airport Development Plan, Presentation, June 9, 2011 

Canada Air Pilot, CAP 4, Ontario, 15 NOV 12, Nav Canada 

Canadian Airport Charts, 15 NOV 12, Nav Canada 

Canada Flight Supplement, 15 NOV 12, Nav Canada 

District Municipality  of Muskoka  Report No:  14  (2011)‐2: Airport Woodlot  (Option  2) Development Area  and Muskoka Aircraft Refinishing Ltd. Proposal, District Council Resolutions 104/2011 and 112/2011 and Resolution R41/2011‐PED (Tabled) First of Four Airport Reports, September 14, 2011 

District Municipality  of Muskoka  Report  No:  14  (2011)‐3: Muskoka  Airport  Financial  Plan  –  Revised  District Council Resolution 104/2011, Second of Four Airport Reports, September 19, 2011 

District Municipality of Muskoka Report No: PED‐10‐2011‐2: Muskoka Airport Development Plan – Background Report, May 31, 2011 

District Municipality of Muskoka Report No: PED‐12‐2011‐5: Muskoka Airport Scoped Wetland Assessment 

District  Municipality  of  Muskoka  Report  No:  PED‐13‐2011‐2:  Creation  of  a  New  Development  Area  at  the Muskoka Airport, July 2, 2011 

District Municipality of Muskoka Memorandum: Expiry of the Transfer Agreement for the Muskoka Airport, May 11, 2005 

District  Municipality  of  Muskoka  2010  Tax  Supported  Operating  &  Capital  Budget  Planning  &  Economic Development, April 12, 2010 

District  Municipality  of  Muskoka  2011  Tax  Supported  Operating  &  Capital  Budget  Planning  &  Economic 

PED-9-2013-4B

Page 186: Muskoka Business and Master Plan Final Draft Report-10May

  

 

B‐2

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Development, March, 2011 

District  Municipality  of  Muskoka  2012  Tax  Supported  Operating  &  Capital  Budget  Planning  &  Economic Development, February, 2012 

District Municipality of Muskoka, Detailed Stormwater Management Report, June 8, 2012 

District Municipality of Muskoka, Muskoka Airport, On‐Site Sewage System Report, June 8, 2012 

East Side Development Fence Route 2012, Drawing  

FedNor Minister Air Drops Money on Parry Sound Business Centre, Airport; Northern Ontario Business, January 10, 2011 

Final  Environmental  Impact  Study  for  Lands  East  of Muskoka  Airport  The  District Municipality  of Muskoka, December 2005 

Lake Simcoe Regional Airport, Commercial Development Opportunities, 2011 

Muskoka Airport Advisory Committee Orientation Presentation, February 13, 2012 

Muskoka Airport Cross‐wind Runway Relocation Feasibility Study, Gravenhurst, ON, Final Report, December 2011 

Muskoka Airport Eastside Development Areas Presentation, 2011 

Muskoka Airport, East Development Proposed Lots, Drawing, February 2012 

Muskoka Airport Economic Impact Study, November 15, 2005 

Muskoka Airport Economic Impact Study, November, 2001 

Muskoka Airport Layout, November 14, 2011 

Muskoka Airport Layout with Air Photo, November 14, 2011 

Muskoka Airport Master Plan, September 1999 

Muskoka Airport Pavement Re‐Evaluation – Runway and Apron Surfaces, October 11, 2011 

Muskoka Airport Scoped Wetland Assessment District Municipality of Muskoka, June 2011 

Muskoka Airport Windrose Usability Study, Gravenhurst, ON, Final Report, November 2010 

Muskoka Airport Zoning Regulations, SOR/84‐567, Current to December 10, 2012 

Ontario Municipal Airports Data Collection Study, 2011 Update 

Parry Sound Airport Expands; Northern Ontario Business, August 20, 2010 

Parry Sound Airport Expands Again; Northern Ontario Business, June 17, 2010 

Parry Sound Airport Spreads its Wings; Northern Ontario Business, June 12, 2008 

PED-9-2013-4B

Page 187: Muskoka Business and Master Plan Final Draft Report-10May

  

 

B‐3

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Peterborough Municipal Airport Master Plan, October 28, 2009 

Review of the Greater Toronto Airports Authority “Needs Assessment Study – Pickering Lands”, Implications for General Aviation in the Greater Golden Horseshoe, Ontario, September 2011 

Scope of Work – Preliminary Muskoka VHF/DF Relocation, Nav Canada EPD – December 20, 2011 

Stormwater Management Drawings, Muskoka Airport East Development, June 8, 2012 

Strategic Business Plan for the Muskoka Airport, January 2006 

Study of Municipal Airports in Ontario, Final Report, September 2006 

The Eagle has Landed in the Parry Sound Area; Cottage Country Now.ca, April 4, 2012 

The  Location,  Boundary  of  and  Uses  Permitted  in  the  Lake  Simcoe  Regional  Airport  Economic  Employment District, September 24, 2012 

Transport  Canada  Letter  to Mark  Stirling: Muskoka Airport Operations Manual  – Amendment  #3  and Airport Emergency Response Plan, August 2, 2006 

2009 Muskoka Airport Economic Impact Study, November 4, 2009 

Wind Criteria Due to Obstacles at and around Airports, National Aerospace Laboratory, NLR‐CR‐2006‐261, May 2008 

Criteria for Obstacle Induced Wind Disturbances at Amsterdam Schipol Airport, ICAO Aerodrome Meteorological Observation and Forecast Study Group, Ninth Meeting, 26‐30 September 2011, Montreal, AMOFSG/9‐SN No.25 8/8/11.    

 

 

 

 

 

 

 

 

 

  

PED-9-2013-4B

Page 188: Muskoka Business and Master Plan Final Draft Report-10May

  

 

C‐1

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

APPENDIX C – AIRPORT ZONING REGULATIONS

 

 

PED-9-2013-4B

Page 189: Muskoka Business and Master Plan Final Draft Report-10May

  

 

D‐1

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

APPENDIX D – INSTRUMENT APPROACH PROCEDURES

 

PED-9-2013-4B

Page 190: Muskoka Business and Master Plan Final Draft Report-10May

  

 

D‐2

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

 

PED-9-2013-4B

Page 191: Muskoka Business and Master Plan Final Draft Report-10May

  

 

D‐3

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

PED-9-2013-4B

Page 192: Muskoka Business and Master Plan Final Draft Report-10May

  

 

D‐4

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

PED-9-2013-4B

Page 193: Muskoka Business and Master Plan Final Draft Report-10May

  

 

 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

APPENDIX E: OPPORTUNITIES MODELLING ANALYSIS

                                       

PED-9-2013-4B

Page 194: Muskoka Business and Master Plan Final Draft Report-10May

  

 

  E‐1 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

STEP 1: INVESTMENT READINESS – MUSKOKA AIRPORT  

 

MUSKOKA PARRY SOUND PETERBOROUGH LAKE SIMCOE (BARRIE) OSHAWA KINGSTON NIAGARA DISTRICT HALIBURTON / STANHOPE

AEROSPACE PRODUCTS & SERVICES 15 12 18 13 17 11 9 4

2 2 2 2 4 3 2 114 12 18 12 30 4 10 4

2 2 3 2 3 3 2 1

based on FedNor survey (2010) and confirmed in 2012

based on FedNor survey (2010) and confirmed in 2012

manufacturing /parts/assembly, medevac, MRO, charter, F&B, FBO

charter, MRO, airport services, flight training, FBO,F&B, other

charter, MRO, airport services, flight training, FBO, museum, F&B, other

scheduled and charter passenger service, FBO, flight training, airport services, air traffic control services

charter, flight training, FBO, MRO Aircraft hangars, public services (MNR)

3 1 2 2 3 2 2 03 largest groups (6, 5, 5) 3 largest groups (5, 3, 3) ocused on MRO and a/c parts & man 3 charter almost more than one in most categories focused on scheduled passenger service focused on tourism related flights focused on aircraft hangars

5 3 5 2 3 0 0 0

Aztec Nomad, Grass Roots, Muskoka Aircraft, Trinity, Muskoka

A/C RefinishingEmhiser, Found, ProSafe

Artech, Kadex, Int'l AC support & turbine engine sales, Shield Source, Flying Colour Corp.

Aero Covers, Dominion-Pegasus viation museums, 1 engine technology comp None tourism related flights, MRO for DND None

2 3 3 3 1 1 1 1

Azted Nomad, Grass Roots, Muskoka Aircraft, Trinity, Muskoka

A/C Refinishing - pot'l for R&D

pot'l R&D and SJIF for Found A/C, Northern Ontario Heritage Fund

Corporationpot'l R&D and SJIF, ISF

Infrastructure Stimulus Fund: Contributed towards $15.32 million

expansion (2010) Unknown Unknown Unknown Unknown

1 1 3 2 3 2 2 1

AAIC Ont Chapter, but no members in north; Mukoka Futures - interest

unknown

AAIC Ont Chapter, but no members in north; Mukoka Futures - interest

unknown

AAIC Ont Chapter, CBDB interest unknown

UnknownAAIC Ont Chapter, CBDB interest

unknownUnknown City and Region very interested in developing airport Unknown

AIRPORT INFRASTRUCTURE 22 19 25 23 22 25 22 9

4 3 4 4 2 3 3 16,000' 4,000' 7,000' 6,000' 4,000' 4,929' 5,000' 2,500'

2 2 4 3 4 4 3 1

NDB, med intensity lighting NDB, med intensity lighting NDB, ARCAL, high intensity lightingB, DME, new LPV, med intensity ligh NDB, DME, LOC, high intensity lighting NDB, ILS, high intensity lighting NDB, ARCAL, medium intensity lightingCode 1 Non-Instrument Runway (low

intensity lighting

3 2 3 3 2 2 1 2

phone, AOE/15, taxi, car rental phone, foodphone, food; AOE/15, new terminal

bld with more services

phone, food; AOE/24, wifi, washrooms, outdoor deck,

boardroom, taxi,

at aerodrome but not in ATB - phone, food, car rental; AOE/50

at aerodrome but not in ATB - phone, food, car rental; AOE/30

phone, AOE/15Washrooms, showers, change rooms,

snack in terminal

5 3 4 4 5 5 5 2

fuel, storage, minor repair, major repair, parking, tie-downs, plug-ins,

customs

fuel, storage, minor repair, major repair, parking, tie-downs, plug-ins

fuel, storage, minor repair, major repair, parking, tie-downs, customs

fuel, storage, minor repair, major repair, parking, tie-downs, customs

fuel, storage, minor repair, major repair, parking, tie-downs, customs

fuel, storage, minor repair, major repair, parking, tie-downs, customs

fuel, storage, minor repair, major repair, parking, tie-downs, customs

Township-owned commercial/hangar building for heated indoor maintenance

and/or for storage of up to 5 aircraft• Two-bay vehicle workshop, fuel, storage

1 4 4 4 4 4 4 3

airport has some land avail. for sale

Variety of municipal industrial properties throughout Seguin, as well as vacancies

in the Parry Sound Area Municipal Airport's Industrial Park

lots availale and expanding lots and expandingunknown, but assumed avail as pursuing

oppsunknown, but assumed avail as pursuing opps unknown, but assumed avail as pursuing opps

unknown, but assumed avail as pursuing opps, Township-owned “T Hangar"

complex with a storage capacity of 16 aircraft

• Township-owned commercial/hangar building for heated indoor maintenance

and/or for storage of up to 5 aircraft4 2 3 3 2 3 3

community plan to develop aerospace / aviation sector

Re-instatement of CANPASS designation Fourth Phase of Expansion, Eagle Air Building Industrial Expansion

Project

Airport Development Program almost complete

Business Development Plan Runway extension and terminal expansion completed MP (2007) Economic (2009) currently in planning but limited area (5.3 ha airside) Runway extension, MNR base

3 0 2 2 0 0 0 2

Ornge seasonal base, MNR year-round noneTransport Canada, Seneca College

to start in Jan 2013Ontario Provincial Police, Hydro

One HelicoptersMNR for their forestry firefighting base

3 3 3 2 3 4 3FedNor, Regional/Municipal

Funding, Communities Adjustment Fund

FedNor, other studies FedNor, other studies ISF FedDev, other studies ACAP, FedDev, other studies FedDev, other studies ??

AEROSPACE / AVIATION TRAINING & EDUCATION 3 4 5 6 6 4 4 3

0 0 0 0 0 0 0 0

1 1 4 5 4 3 3 3

Georgian college (Barrie) Georgian college (Barrie) GTA universities (Seneca) GTA universities, Georgian College GTA universities GTA universities, Kingston, Ottawa, Montreal GTA universities, Niagara Region GTA universities

1 0 0 0 0 0 0 0

A/C owner training

1 3 1 1 2 1 1 0

Ferarri Georgan Bay Airways, BP Flight Training W.M. Aeroflight Future Air 2 flight schools unknown St. Catharines Flying Club

LOCATION / ACCESS 3 3 4 5 6 7 5 4

3 3 4 5 5 4 5 4

Muskoka to Toronto 2 hrs drive Parry Sound to Toronto 2.5 hrs Peterborough to TO 1 hr 45 min drive To Toronto - ~60-80 mins Oshawa to TO 45 min drive Kingston to TO 3 hr drive St. Catharines to TO 1.25 hr drive 3 hr drive to TO

0 0 0 0 0 2 0 0Service to Toronto, Moosonee

0 0 0 0 1 1 0 0no connections no connections

score 46 38 54 49 51 47 40 22rank 5 7 1 3 2 4 6 8

Availability of Scheduled Passenger Service

Regional Aviation / Aerospace Activity

Availabilty of Pilot Training(type = fixed wing or rotary winglicense = recreational, private or commercial, militaryratings = instrument, night, floats, etc.)

Availability of Other Specialized Aerospace / Aviation Technical Training

Labour Supply(# graduates annually from post-secondary institutions with specialty aviation / aerospace programs)

Development Plans

Availability of Aircraft Services at Airport(incl. customs for cargo, and hours of operations)

Year-Round Base for Public Services(e.g., OMNR, MOHLTC/ORNGE, police, post-secondary institutions)

Access to Funding / Incentives(grants, loans, etc.)

Distance to provincial, national or international distribution centre for products / services(Toronto, Winnipeg, Minneapolis)

Availability of Specialized Technical Aerospace / Aviation Training(post-secondary credits)

Existence of Aviation / Aerospace Business Network or Association(group in CD interested in aviation / aerospace industry)

Runway Length and Type (main runway)

Availability of Navigational and Visual Aids at AirportsNavigational aids (ILS, VOR, NDB etc.)Visual aids (runway lighting, approach lighting, etc.)

Availability of Public Facilities (passenger services) at Airport(phone, food, taxi, medical, car rental, customs)

Availability of Land for Development or Buildings for Lease

Number of aerospace / aviation businesses at aiport

Diversity of aerospace / aviation sector at airport(based on 21 NAICs)

Degree of Concentration(in one or more business areas based on NAICs)

Existence of customized, unique or specialty aviation / aerospace services

Access to Incentives / Funding(grants, loans, etc.)

PED-9-2013-4B

Page 195: Muskoka Business and Master Plan Final Draft Report-10May

  

 

  E‐2 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

 

PED-9-2013-4B

Page 196: Muskoka Business and Master Plan Final Draft Report-10May

  

 

  E‐3 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

 

PED-9-2013-4B

Page 197: Muskoka Business and Master Plan Final Draft Report-10May

  

 

  E‐4 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

 

PED-9-2013-4B

Page 198: Muskoka Business and Master Plan Final Draft Report-10May

  

 

  E‐5 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

 

  

 

PED-9-2013-4B

Page 199: Muskoka Business and Master Plan Final Draft Report-10May

  

 

F‐1

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

APPENDIX F: ADDITIONAL WIND ANALSYSIS GRAPHS

    

 

0.00%

2.00%

4.00%

6.00%

8.00%

10.00%

12.00%

14.00%

09‐27 10‐28 11‐29 12‐30 13‐31 14‐32 15‐33 16‐34 17‐35 18‐36

Xwind Severity and Coverage by Runway Direction 

Year Round all Periods

<10kt <13kt >5kt

0.00%

2.00%

4.00%

6.00%

8.00%

10.00%

12.00%

14.00%

16.00%

09‐27 10‐28 11‐29 12‐30 13‐31 14‐32 15‐33 16‐34 17‐35 18‐36

Xwind Severity and Coverage by Runway Direction 

Summer Daytime Only 

<10kt <13kt >5 kt

PED-9-2013-4B

Page 200: Muskoka Business and Master Plan Final Draft Report-10May

  

 

G‐1

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

APPENDIX G: AIRCRAFT RUNWAY LENGTH INFORMATION

Aircraft Weight (lbs.)

Engine Type No. Seats

Reference Field

Length

Adjusted Field

Length

Movements

in 2010a

Reference Field Length < 2,000 ft (610m) Piper Super Cub PA-18 2,888 Piston 1 2 410 504 116Cessna 175 Skylark 2,400 Piston 1 650 800 22Lake Buchaneer LA-4 2,694 Piston 1 660 812 284Cessna 182 Skylane 3,100 Piston 1 705 867 220Piper Cherokee PA-28 2,227 Piston 1 725 892 386Cessna 177 Cardinal 4,409 Piston 1 845 1,040 195Navajo PA-31 6,793 Piston 2 930 1,112 85BN Islander 6,614 Piston 1 1,160 1,392 2Cessna 180 8,494 Turbo Prop 1 1,204 1,445 112Piper Tri-Pacer PA-22 2,000 Piston 1 1,210 1,489 7Lancair Columbia 300 3,400 Piston 1 4 1,250 1,415 0Beaver -DHC 2 5,294 Piston 1 1,250 1,500 16Cessna 172 2,312 Piston 1 1,250 1,500 2,663Diamond Katana 1,653 Piston 1 1,263 1,554 0Cessna 152 1,670 Piston 1 1,340 1,608 239Found Bush Hawk FBA2 3,800 Piston 1 1,350 1,661 31Cessna Skylane-182 3,100 Piston 1 4 1,350 1,839 220Cessna 185 3,311 Piston 1 1,365 1,638 152Extra EA 500 4,740 Turbo Prop 1 6 1,400 1,560 0Turbo Beaver 8,017 Turbo Prop 1 1,400 1,680 0Beechcraft B80 8,017 Piston 2 1,400 1,680 0Cirrus Sr22 3,400 Piston 1 4 1,570 1,974 210Beechcraft C90 10,099 Turbo Prop 2 1,600 1,920 55Otter DHC -3 8,000 Piston 1 1,630 1,956 0Cessna 310 5,419 Piston 2 1,700 2,040 44Extra Flugzeugbau GmbH 400 4,407 Piston 1 6 1,705 2,543 0Piper Saratoga PA-32-301 3,600 Piston 1 5 1,759 2,309 22Cessna 340 5,996 Piston 2 1,760 2,104 9Adams A500 6,300 Piston 2 6 1,800 1,880 0Aero / Ibis AE 270 8,280 Turbo Prop 1 7 1,805 2,229 0Cessna Stationair CE-206H 3,600 Piston 1 6 1,850 2,392 188Beechcraft 200 12,516 Turbo Prop 2 1,900 2,280 62Raytheon/Beech Bonanza A36 3,650 Piston 1 5 1,913 2,723 10

    

PED-9-2013-4B

Page 201: Muskoka Business and Master Plan Final Draft Report-10May

  

 

G‐2

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Aircraft Weight (lbs.)

Engine Type No. Seats

Reference Field

Length

Adjusted Field

Length

Movements

in 2010a

Reference Field Length < 3,000 ft (915m) Short SC 7-3 12,500 Turbo Prop 2 2,020 2,424 0Cessna Caravan CE-208-675 8,000 Turbo Prop 1 10 2,053 2,352 230Cirrus SR 20 3,000 Piston 1 4 2,063 2,566 51Socata Trinidad GT TB-20 3,086 Piston 1 4 2,083 2,542 0Piper Malibu - PA-46-350 4,340 Piston 1 5 2,090 2,385 4Cessna 414 6,647 Piston 2 2,185 2,612 2Twin Otter DHC-6 12,500 Turbo Prop 2 2,280 2,736 6Pilatus PC-12 9,920 Turbo Prop 1 8 2,300 2,813 979Cessna Grand Caravan CE-208B 8,750 Turbo Prop 1 10 2,420 2,822 230Piper Meridian PA-46-500 5,092 Turbo Prop 1 5 2,438 2,865 2Mooney Ovation M-20S 3,368 Piston 1 4 2,500 2,982 0Piper Seneca PA-34-220 4,750 Piston 2 5 2,510 2,690 51Fairchild Dornier 228-212 14,000 Turbo Prop 2 19 2,600 3,610 0Socata TBM 700 6,614 Turbo Prop 1 6 2,840 3,332 2

    

PED-9-2013-4B

Page 202: Muskoka Business and Master Plan Final Draft Report-10May

  

 

G‐3

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Aircraft Weight (lbs.)

Engine Type No. Seats

Reference Field

Length

Adjusted Field

Length

Movements in

2010a Reference Field Length < 4,000 ft (1,220m)

Raytheon Baron 58 5,500 Piston 2 5 3,000 3,446 43Mitsubishi MU-2 11,574 Turbo Prop 2 3,000 3,587 20Bombardier DH7-150 45,000 Turbo Prop 4 50 3,000 3,850 2Bombardier DH8-100 34,400 Turbo Prop 2 40 3,100 3,804 20Bombardier DH8 Q200 36,300 Turbo Prop 2 40 3,146 3,448 7Citation Ultra 16,583 Jet 2 3,160 3,834 76Bombardier DH8-200 36,200 Turbo Prop 2 40 3,255 3,893 7Citation Mustang C510 11,861 Jet 2 3,275 3,973 2Cessna CJ1 CE-525 10,600 Jet 2 7 3,280 4,200 25C130 Hercules 153,770 Turbo Prop 4 3,290 3,883 82Raytheon King Air 350 15,000 Turbo Prop 2 10/15 3,300 4,024 24Bombardier CL-415 Water Bomber 43,700 Turbo Prop 2 n/a 3,400 3,844 15Raytheon King Air B200 12,500 Turbo Prop 2 8/15 3,411 3,767 62Cessna CJ2 CE-525A 12,375 Jet 2 8 3,420 3,984 0Cessna CJ3 CE-525B 13,870 Jet 2 8 3,450 4,046 2Cessna Citation Encore CE-560 16,630 Jet 2 9/11 3,490 4,278 76Learjet 35 17,000 Jet 2 3,500 4,185 4Fairchild Dornier 328-110 31,000 Turbo Prop 2 33 3,570 4,274 0Cessna Citation Excel CE-560-Xl 20,000 Jet 2 10 3,590 4,346 49Cessna Bravo CE-550 14,800 Jet 2 9/11 3,600 4,258 27Bombardier DH8-300 41,000 Turbo Prop 2 56 3,600 4,552 8Raytheon King Air C90 10,110 Turbo Prop 2 6/12 3,650 4,223 0Bombardier DH8 Q300 43,000 Turbo Prop 2 50/56 3,681 4,057 8Cessna Citation Sovereign CE-680 30,000 Jet 2 11/12 3,694 4,234 0Raytheon Premier 1-390 12,500 Jet 2 7 3,792 4,893 10Shorts 330-200 22,850 Turbo Prop 2 30 3,800 4,600 0Raytheon/Beech 1900D 17,120 Turbo Prop 2 14/19 3,813 4,280 386Raytheon Beechjet BE-400A 16,300 Jet 2 9 3,906 4,742 26Sino SJ30-2 13,500 Jet 2 6 3,993 4,340 0

    

PED-9-2013-4B

Page 203: Muskoka Business and Master Plan Final Draft Report-10May

  

 

G‐4

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Aircraft Weight (lbs.)

Engine Type No. Seats

Reference Field

Length

Adjusted Field

Length

Movements

in 2010a

Reference Field Length < 5,000 ft (1,525m) Beechjet 400 16,292 Jet 2 4,000 4,783 26ATR 72-500 49,600 Turbo Prop 2 74 4,010 4,326 2Embraer 110 Bandeirante 12,980 Turbo Prop 2 19 4,050 4,674 0Saab 2000 50,160 Turbo Prop 2 50 4,215 4,861 0Piaggio Avanti P180 11,550 Turbo Prop 2 8/9 4,250 4,716 73Shorts 360-300 27,000 Turbo Prop 2 36 4,280 4,450 0Bombardier Lear 40 LR-45 20,350 Jet 2 7 4,285 5,283 0ATR 42-500 41,000 Turbo Prop 2 50/60 4,300 4,780 0Saab 340 28,940 Turbo Prop 2 34 4,330 4,648 0Bombardier Lear 45 LR-45 20,500 Jet 2 9 4,350 5,380 10Cessna Caravan II RA-406 9,850 Turbo Prop 1 9/13 4,363 4,898 0Fairchild Dornier 328Jet 34,500 Jet 2 35 4,535 5,241 0Fairchild Dornier Envoy 3 Corp 34,524 Jet 2 20/32 4,535 5,249 0Bombardier DH8 Q400 64,500 Turbo Prop 2 78 4,580 5,104 2Falcon 50 40,137 Jet 2 4,890 5,772 8Falcon 900 (& 900 EX) 46,038 Jet 2 4,935 5,825 12Citation VI 21,825 Jet 2 4,950 5,842 8Challenger 300 38,845 Jet 2 4,950 5,842 20

    

PED-9-2013-4B

Page 204: Muskoka Business and Master Plan Final Draft Report-10May

  

 

G‐5

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Aircraft Weight (lbs.)

Engine Type No. Seats

Reference Field

Length

Adjusted

Field Length

Movements

in 2010a

Reference Field Length < 6,000 ft (1,830m) Learjet 55 21,492 Jet 2 5,000 5,901 2Raytheon Hawker 800XP 28,000 Jet 2 11/12 5,032 6,041 36Bombardier Lear 45XR LR-45 21,500 Jet 2 9 5,060 5,428 10

Embraer 120 Brasilia 26,400Turbo Prop 2 30 5,120 5,340 0

Citation X 35,758 Jet 2 5,200 6,138 29Hawker 700 26,946 Jet 2 5,350 6,315 2Hawker 1000 33,069 Jet 2 5,350 6,315 8Gulfstream G100 1125 24,650 Jet 2 9 5,395 6,543 0Gulfstream 3 68,194 Jet 2 5,400 6,374 2Falcon 2000 40,999 Jet 2 5,440 6,421 8Bombardier Lear 60 LR-60 23,500 Jet 2 8/10 5,450 6,506 6Galaxy GALX 35,450 Jet 2 5,500 6,492 8Westwind WW24 22,850 Jet 2 5,500 6,492 2Astrajet ASTR 24,649 Jet 2 5,500 6,492 0Gulfstream 2 65,637 Jet 2 5,500 6,492 0G150 Gulfstream Galaxy 26,014 Jet 2 5,500 6,492 6G200 Gulfsteam Galaxy 35,450 Jet 2 5,500 6,492 8Embraer ERJ-135 44,092 Jet 2 37 5,650 6,669 0Challenger 600 43,573 Jet 2 5,699 6,727 92Challenger 601 43,573 Jet 2 5,699 6,727 92Challenger 604 43,573 Jet 2 5,699 6,727 92Gulfstream 4 73,199 Jet 2 5,700 6,728 12

Raytheon/Beech 1900C 16,600Turbo Prop 2 19 5,730 6,470 386

Regional Jet CRJ2 50,705 Jet 2 50 5,800 6,846 26Gulfstream 5 91,190 Jet 2 5,910 6,976 6

Aircraft Weight (lbs.)

Engine Type No. Seats

Reference Field

Length

Adjusted

Field Length

Movements

in 2010a

Reference Field Length > 6,000 ft (1,830m) Gulfstream 650 99,647 Jet 2 6,000 7,082 0B737 152,116 Jet 2 150 6,500 7,672 2A320 Airbus 171,958 Jet 2 150 6,500 7,672 0MD 87 140,212 Jet 2 109 7,700 9,088 2Note: a. Itinerant Movements at YQA in 2011 by aircraft type

 

PED-9-2013-4B

Page 205: Muskoka Business and Master Plan Final Draft Report-10May

  

 

    H‐1

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

APPENDIX H: NEW HEIGHT GUIDANCE RE WIND TURBULENCE

As a result of a number of incidents at Amsterdam (Schipol) Airport combined with concern relating to encroaching development at the airport, the Amsterdam Airport Authority undertook some significant and  ground  breaking  research  into  the  effect  of  tall  buildings  in  the  vicinity  of  runway  ends.  The research, which was  both  theoretical  in  nature  and  then  followed  up with  actual  field  trials  using  a building mock‐up and test flights with a 747 and a Fokker 100, showed that additional protection over and above the typical  International Civil Aviation Organisation (ICAO) Obstacle Limitation Surfaces was required  to  protect  against wind  turbulence  created  by  tall  buildings  in  the  vicinity  of  runway  ends.  Subsequent  to  this  work  in  2006,  the  Amsterdam  Airport  has  adopted  the  proposed  guidelines  to protect against wind turbulence effects. Further to this, ICAO has issued this information as guidance to member states and indicated that they are studying the information.      The guidance issued suggests that the height of development in the vicinity of runway ends be limited to less  than a 1:35  slope emanating  from  the  runway  threshold and centreline and extending down  the sides of  the  runway  for up  to 1500m. The  implications of  this  guidance are  illustrated  in  Figure H‐1, where the height contours are shown around the runway ends and down the sides of the runway.       Figure H‐1: New Thinking on Restrictions Around Runway Ends due to Wind Turbulence Effects   

   

PED-9-2013-4B

Page 206: Muskoka Business and Master Plan Final Draft Report-10May

  

 

    H‐2

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

We  should  note  that  this  wind  turbulence  information  is  just  guidance  issued  for  information  for member states to be aware of given the concerns. ICAO has not adopted any standards relating to this information and neither has any other national jurisdiction responsible for airports. The only airport to adopt these as standards has been the Amsterdam Airport, as this is where the problem originated and this  is where  the  key  concern  has  been  identified. However,  given  the  potential  implications  of  this information, we know  that other progressive airports and professionals are definitely considering  this information.  We also feel that this definitely warrants due consideration in the case of development at the Muskoka Airport, especially given  the  fact  that  smaller aircraft will be more  susceptible  to  these wind turbulence effects than larger aircraft . More discussion is provided following.   Let’s look at the issue of Transport Canada/ICAO standards with respect to Obstacle Limitation Surfaces versus  the new wind  turbulence  information as developed  for Amsterdam/Schipol Airport and under review by ICAO. Figure H‐2 illustrates a comparison.     In the top portion of this figure we see a typical OLS as would be  implemented for a  large airport  like Schipol (or Toronto‐Pearson, Montreal‐Dorval, etc). In this case we assume a precision approach runway environment where the runway strip width would be 150m and the transitional surface would slope at 1:7.   Figure H‐2:  Comparison ‐ Hangar Locations Affected by OLS Restrictions vs Wind Turbulence Guidance     

 

PED-9-2013-4B

Page 207: Muskoka Business and Master Plan Final Draft Report-10May

  

 

    H‐3

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

A typical hangar to house an A320 aircraft  (at 15m high), as  is being considered  for MAR at Muskoka, would  be  located  about  300m  from  the  runway  centreline  to  allow  room  for  a  taxiway,  associated clearances and room to park an aircraft in front of the hangar. As shown, this hangar would not even be limited by the transitional surface at this location, as the aircraft tail on the apron would be more critical and this would actually force the hangar further away and lower than the transitional surface.  Per  the new wind  turbulence guidance,  this hangar,  if  located as  shown,  should only be  about 8‐9m high.  In  fact, a 15m high hangar, per  these new guidelines  should be about 525m  (35 x 15)  from  the runway  centreline and not 300m. This difference between  the OLS and wind  turbulence guidance,  is significant enough  in this case, but becomes even more significant at smaller airports, as  illustrated  in the bottom portion of this same figure.        At a smaller airport,  like Muskoka, where the runway would be non‐precision  instead of precision, the runway strip would be 75m instead of 150m, and the taxiway clearances would also be less, so that per the OLS, the same 15m hangar could be closer to 200m from runway centreline vs 300m in the case of precision.  This  difference  between  the  location  allowed  per  the  OLS  and  that  permitted  re  wind turbulence  is much  greater.  This  should make  us more  concerned  about wind  turbulence  effects  at smaller airports  than would be  the case at  larger airports. And given  the  fact  that smaller aircraft are even more susceptible to wind turbulence, this should become an even greater issue at smaller airports.     Figure H‐3 shows another look at a similar 15m hangar in an environment similar to Muskoka. Again, if the runway were non‐precision, with a 75m runway strip and with a 1:7 transitional surface, per the OLS it would be possible  to  locate a 15m hangar as  close as 175m  from  runway  centreline,  compared  to 525m per the wind turbulence guidance. This would still leave room for a parallel Code C taxiway and an apron  in  front of  the hangar  to park an A320  (though  the aircraft  tail would need  to be  towards  the hangar and not the runway).    Figure H‐3: Another Comparison of Hangar Locations Affected by OLS Restrictions vs Wind Turbulence Guidance       

  

PED-9-2013-4B

Page 208: Muskoka Business and Master Plan Final Draft Report-10May

  

 

    H‐4

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

The  implications  of  this  wind  turbulence  guidance  information  are  illustrated  below  in  Figure  H‐4 superimposed on the original plan developed by staff  for the eastside development –  labelled here as Plan A. In this figure, it is evident that the contours associated with Runway 18‐36 (shown in solid green) would limit the height of buildings along the west edge of the development to only about 5+m and the buildings along the east side to about 10+m. At the same time, contours associated with Runway 09‐27 (shown  in dashed purple) would  limit hangars  along  the  south  edge of  the  subdivision  to  about 5m, those  in  the middle  to about 10m and  those at  the north end  to  less  than 15m. However, when  the combined effect of the contours from both runways is considered, there could effectively be no hangars taller than about 10+m. Consequently this plan could not satisfy a basic requirement to provide hangars with at least 15m height in order to accommodate MRO requirements such as MAR.     Figure H‐4: Wind Turbulence Guidance Contours for Plan A     

  Applying this wind turbulence guidance to an alternate plan developed by SNC (referred to as Plan B), as illustrated in Figure H‐5, improves the situation somewhat. In this case, maybe 3 lots are created in the SW corner of the Westside development that could permit hangars up to about 15m. But even here the wind  turbulence guidance  is very  restrictive and  there are no  lots where on  the east  side  that  could accommodate hangars of up to 15m.  As a consequence, we chose to revisit this information and given our commitment to this concept given our understanding of its importance to small airports ‐ ask – how much can we relax the suggested wind 

PED-9-2013-4B

Page 209: Muskoka Business and Master Plan Final Draft Report-10May

  

 

    H‐5

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

turbulence guidelines without significantly compromising these? And ‐ how much do we need to change these to be able get achieve the developments heights that are anticipated at the Muskoka airport?  Figure H‐5: Wind Turbulence Guidance Contours for Plan B   

   In response to the first question, our experience with fluid dynamics, flow analysis and even electronic interference  issues, tells us that we can  increase the 1:35 slope by probably 20‐30% before we should see any discernible  impacts on  the wind  turbulence. A 1:25 slope would be  the equivalent of such an increase.  This  is  shown  as  a  dashed  blue  line  in  Figure H‐6  below, where  the  15m maximum  height hangar  is  shown  to move  from 525m  from  the  runway with  the 1:35  slope  to about 375m  from  the runway with a 1:25 slope. By comparison, at a conventional 1:7 with typical development, this 15m bldg would probably be over 200m from the runway, as illustrated in an earlier chart above (H‐2). Or in the case of at a larger airport with precision zoning, this might be a closer to 300m. The implications of using a compromise 1:25 slope consequently puts these high buildings at about halfway between the TC OLS standard  and  that  associated  with  the  wind  turbulence  information.  Or,  for  larger  airports,  this compromise would result in a similar location for these hangars (300m vs 375m).       In  terms of  the second question,  in  the previous concepts, we  showed  that  there were a  lot of areas where development would be  restricted  to about 10‐12m. Raising  the  limits by 20‐30% should create sufficient  areas  where  development  heights  could  approach  15m.  These  will  be  illustrated  in  the following options.            

PED-9-2013-4B

Page 210: Muskoka Business and Master Plan Final Draft Report-10May

  

 

    H‐6

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

 Figure  H‐6:    Comparison  of  Hangar  Locations  Affected  by  OLS  Restrictions  vs  Adjusted  Wind Turbulence Guidance 

 Figure H‐7 illustrates the revised 1:25 contours for Plan A‐R. We have added buildings to each lot that are coded with respect to max heights: less than 10m, between 10 and 15 and more than 15m. While these contours would allow greater development heights, there are still no lots that would allow buildings of up to 15m, especially taking into account the DF restrictions, also noted in the figure. And there are only about 4‐5 lots permitting building of over 10m, which is an improvement over using the 1:35 contours, but still not enough of an improvement to allow the 15m hangars that larger MROs like MAR would require.    

Figure H‐8  illustrates  the effects of  the  revised 1:25 contours on Plan B‐R.  In  this case, newly created “field lots” just south of the existing Muskoka Aircraft Refinishing (MAR) buildings could be developed to over 15m in height (a total of 4 lots in the western part of this area), while the remaining area could be over 10m, if necessary. We have used the same coding with hatched buildings as in the previous slide.   In  the  eastside  lands,  there  are  now  about  3  lots  that  could  be  developed  at  over  15m,  with  an additional 6 at over 10m but  less than 15. The remaining  lots would need to be  less than 10m, which would still be quite adequate for many of the envisioned uses at the airport, as most of these buildings are generally less than 10m now.   At  this  point  it  is  useful  to  discuss  the  implications  of  not  implementing  the  above wind  turbulence guidelines. For simplicity, we will focus our discussions on the recommended development plan B‐R.   Without  getting  into  detail  with  respect  to  the  theory  and  the  detailed  processes  of  how  wind turbulence  effects occur, wind  turbulence  is usually  created when winds blow over  and  / or  around buildings.  This  causes  lower  pressures  on  the  downstream  side  of  the  buildings  that  then  cause turbulence on this side. These wind turbulence effects can result in serious downdrafts, that in the case of aircraft, can slam these aircraft right into the ground on approach (or even on departure).      

PED-9-2013-4B

Page 211: Muskoka Business and Master Plan Final Draft Report-10May

  

 

    H‐7

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

Figure H‐7: Wind Turbulence Guidance Contours for Plan A‐R 

    

 

Figure H‐8: Wind Turbulence Guidance Contours for Plan B‐R 

 

 

PED-9-2013-4B

Page 212: Muskoka Business and Master Plan Final Draft Report-10May

  

 

    H‐8

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

FINAL REPORT  10 May 2013 

To get a better sense of this discussion, let’s look at Figure H‐8. The predominant runway used at Muskoka is Runway 36 with approaches being conducted from the south and departures to the north.  Winds at the airport frequently blow from the west and northwest as illustrated in the wind rose charts contained in Appendix K. When these winds blow over the existing MAR buildings located to the west side of the runway, and in the future, the proposed new buildings to the south of those already existing, wind turbulence effects will be generated that will have the potential to make an aircraft on final approach to lose altitude and potentially crash short of the runway or be slammed right down into the runway itself, depending on wind speed and direction. For this wind turbulence to be severe enough to cause such a drastic reaction, the wind speed would need to be substantial as well. Without carrying out a detailed analysis, we cannot speculate as to what the “critical” wind speeds would be, but we can say that given the wind directions involved and the speeds from the wind rose, there would be “limited” occurrences of these critical winds when the runway would need to be closed to operations during these events. If an alternate runway is available during these events (such as Runway 27 or the new proposed 30), then it would be a simple matter of using the alternate runway.   In a similar fashion, winds blowing from the east over the planned eastside developments would create potential turbulence as well for aircraft approaching on Runway 36.  These same winds, blowing across the runway, whether over the Westside developments of the eastside ones, could have turbulence implications for aircraft departing on Runway 18. Runway 30 (the second most available runway direction) would be affected by potential wind turbulence when winds blow from the south and southwest. Such winds would also potentially impact departures on Runway 12.  The implications of the wind turbulence issue, if the proposed guidelines are not taken into consideration, would be that there would need to be operational limitations identified that would close the appropriate runway during wind events that could cause significant enough turbulence effects. Given the newness of this information and the limited information currently available, it is difficult to speculate how often these “significant” enough would occur. But our guess would be that these would be “not frequent”. Having said this, safety is of paramount concern and the wind effects are currently not well understood and winds and their turbulent effects are difficult to forecast. Given this, we prefer to err on the side of caution and suggest that it is best to consider these new guidelines than to ignore and face the consequences later.   In the development plans that we have recommended, we have considered these effects. However, in considering the effects of wind turbulence, while the proposed plans have looked differently than they would have otherwise looked had we not considered these effects, we do not feel that the airport has lost any development potential as a result. We feel we have been able to satisfy the requirements that we have forecast for the various uses (taking development height into consideration). The only lost “potential” is that we cannot populate the entire airport site with “taller” buildings. And this would not be realistic in any case, as the reality of the “demand” is that there will be demand for a mix of lower buildings in the range of 5‐10m for smaller aircraft, buildings in the 10‐15m range for medium size aircraft and buildings in the 15m+/‐ range for larger aircraft.    

PED-9-2013-4B

Page 213: Muskoka Business and Master Plan Final Draft Report-10May

 

 

I‐1

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

APPENDIX I: TYPICAL LOT LAYOUTS

The following show some typical lot layouts at a number of airports to illustrate potential lot sizes for the Muskoka Land Development.   

SAMPLE T-HANGAR DEVELOPMENTS SPRINGBANK

     The above shows sample T‐hangar developments from a large GA airport in Canada. A combination of smaller to medium sized T‐hangars is shown. These are very typical arrangements common at similar Canadian airports. The hangars can be  longer of shorter and would need  to be a multiple of  the design aircraft, but  these are seen  to range between 55m and 85m. Corresponding lot sizes would be about 45m‐50m x 100m +/‐ for double width small T‐hangars and about 45m +/‐ x 100m +/‐ for the single larger T‐hangars.      

PED-9-2013-4B

Page 214: Muskoka Business and Master Plan Final Draft Report-10May

 

 

    I‐2

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

AIRCRAFT HANGARS AT BUTTONVILLE

 Here at Buttonville we see lot sizes for corporate private of slightly different sizes, ranging to samller depths of only about 80m due to the layout, but would probably typically be more like 100m to 120m. Lot widths are shown to vary from 40m to 80m.      

PED-9-2013-4B

Page 215: Muskoka Business and Master Plan Final Draft Report-10May

 

 

    I‐3

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

T-HANGARS AT NANAIMO

  At Nanaimo, we see a similar situation to Springbank, with typical lots for T‐hangars being 30m +/‐ wide with depths of 100m +/‐.     

PED-9-2013-4B

Page 216: Muskoka Business and Master Plan Final Draft Report-10May

 

 

    I‐4

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

CORPORATE AIRCRAFT HANGARS AT CALGARY

  The figure above shows some typical corporate hangars at Calgary. Typical lot sizes again tend to show lot depts. Of about 120m with lot widths varying from 60m to 70 and even up to 100m wide, depending on how many aircraft and the size to be accommodated. 

   

PED-9-2013-4B

Page 217: Muskoka Business and Master Plan Final Draft Report-10May

 

 

    I‐5

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

SAMPLE B757 AND A321 HANGAR LOTS  

In the following pages we attach a discussion on lot sizes at other airports that we had done for a previous client.     

PED-9-2013-4B

Page 218: Muskoka Business and Master Plan Final Draft Report-10May

 

 

    I‐6

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

 

Notes on Lot Sizing for Commercial Lands at CRIA 

 Background Paper for  

CRIA Commercial Land Development Plan              

 Prepared by: SNC Lavalin Inc..  For: City of Cranbrook (Project: V2240.65) October 2010   

PED-9-2013-4B

Page 219: Muskoka Business and Master Plan Final Draft Report-10May

 

 

    I‐7

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Comparative Review 

In order to establish appropriate lot sizes to use for this commercial lands development plan, a quick survey was conducted of other similar sized and larger airports. This survey involved a combination of checking of our (PAPI) files  from previous work  that we had done  (using CAD  files), as well as using aerial photos available on Google Earth. The airports surveyed, as illustrated below, generally involved mostly BC airports, but do include some info on some small international airports, such as in the Bahamas and Turks and Caicos.  

The data below is categorised into airside and landside uses.  

Airport  Development Type Width (m) 

Depth (m) Typical Area (m2) 

Airside Uses

Cranbrook  Small hangar – private  50 100 5,000

  Small hangar – maintenance 

60 100 6,000

  Small forestry base 60 100 6,000

Kamloops  Small hangar – maintenance 

50 115 5,750

  Small hangar – maintenance 

60 115 6,900

  Small hangar – general use 

70 100 7,000

  Small hangar – general use 

50 100 5,000

  Small hangar – general use 

100 80 8,000

  Large forestry base 300 200 60,000

  “T” Hangars  50 110 5,500

Prince George  Small hangar – general use 

100 80 8,000

  Small hangar – general use 

70 80 5,600

  Small hangar – general use 

70 100 7,000

  Small hangar – general use 

80 80 6,400

Abbotsford  Large aircraft maintenance 

230 300 69,000

  Mid size hangar  120 100 12,000

  Mid size hangar  120 80 9,600

  General aviation – flying school 

120 150 18,000

  “T” Hangars ‐ single 50 60+ 3,000+

  “T” Hangars ‐ double 80 60+ 4,800+

Pemberton  General airside lots 40 120 4,800

Kelowna  Large aircraft maintenance 

300 300 90,000

  Small hangars/general aviation 

100 100 10,000

PED-9-2013-4B

Page 220: Muskoka Business and Master Plan Final Draft Report-10May

 

 

    I‐8

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Airport  Development Type Width (m) 

Depth (m) Typical Area (m2) 

  Small hangars/general aviation 

120 100 12,000

Vancouver  Fixed based operator (FBO) 

160 150 24,000

  Fixed based operator (FBO) 

120 80 9,600

  Helicopter terminal/base 100 150 15,000

  Small aircraft maintenance 

50 80 4,000

Calgary  General use/corporate/FBO 

70 110 7,700

  General use/corporate/FBO 

100 110 11,000

  General use/corporate/FBO 

90 110 9,900

  General use/corporate/FBO 

60 150 9,000

  General use/corporate/FBO 

70 150 10,500

  General use/corporate/FBO 

120 150 18,000

Nassau   Large FBO  200 180 36,000

(Bahamas)  Small FBO  80 120 9.600

  Aircraft Maintenance  120 250 30,000

Marsh Harbour  Small FBO  120 100 12,000

(Bahamas)  Small FBO  200 120 24,000

  Small FBO  80 80 6,400

Providenciales  Small FBO  150 120 18,000

(Turks&Caicos)  Small FBO  100 120 12,000

  Small FBO  70 150 10,500

General Landside Uses

Vancouver  Small industrial/office combo 

50 Variable 5,000+/‐

  Small industrial/office combo 

60 variable 6,000+/‐

  Small warehouse/industrial 

80 Variable 8,000+/‐

  Small warehouse/industrial 

120 Variable 10,000+/‐

Cranbrook  Warehouse/industrial 75 140 10,500

  Warehouse/industrial 75 75 5.625

  Warehouse/industrial 75 110 8,250

  Industrial/office  40 100 4,000

  Industrial/office  50 80 4,000

  Industrial/office  70 90 6,300

Kamloops  Warehouse/industrial 70 120 8,400

PED-9-2013-4B

Page 221: Muskoka Business and Master Plan Final Draft Report-10May

 

 

    I‐9

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Airport  Development Type Width (m) 

Depth (m) Typical Area (m2) 

  Warehouse/industrial 70 90 6,300

  Warehouse/industrial 60 100 6,000

  Industrial/office  60 100 6,000

  Industrial/office  80 90 7,200

  Industrial/office  70 110 7,700

 

CONCLUSIONS 

Based on the above comparisons, it was established that an appropriate size for typical airside lots for general uses should be in the order of about 50m x 100m (or about 5,000m2 in area). These general uses could accommodate hangars for private or corporate aircraft, aircraft maintenance activities for smaller aircraft. The depth of these lots could also accommodate Fixed Based Operators who would build a hangar and facilities to handle multiple aircraft, but these uses could require several  lots  in terms of width, depending on the size of the  facility. Two  lots could provide  a  total  area of  about  10,000m2 while  3  lots would  provide  a  total  area of  15,000 m2.  These  sizes  are consistent with small FBOs as evidenced in the above table.    

With respect to  landside  lots, typical dimensions for developments  in Cranbrook and Kamloops and smaller type developments  in  Vancouver  tended  to  indicate  lot  sizes  averaging  some  4,000m2  to  10,000m2. Most  of  these tending to be in the middle of this range around 6,000 to 8,000 m2. Frontages varied between 40 and 120m. Based on this data,  it suggested that the  landside lots be sized at about 8,000m2 +/‐ for warehousing/industrial and for closer to about 6,000m2 for the office/industrial types.  

 

PED-9-2013-4B

Page 222: Muskoka Business and Master Plan Final Draft Report-10May

 

 

    J‐1

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

APPENDIX J: FINANCIALS

PED-9-2013-4B

Page 223: Muskoka Business and Master Plan Final Draft Report-10May

  

 

J‐2

Muskoka Airport – Status Quo – Current Rates ‐ Financial Forecasts 

    

STATUS QUO

OPERATING REVENUES 2009 2010 2011 2012 (budget) 2013 f 2014 f 2015 f 2016 f 2017 f 2018 f 2019 f 2020 f 2021 f 2022 f 2023 f 2024 f 2025 f 2026 f 2027 f 2028 f 2029 f 2030 f 2031 f 2032 f 2013-2032Aeronautical Fees - Miscellaneous 17,752$ 24,661$ 16,263$ 16,500$ 17,340$ 17,687$ 18,041$ 18,401$ 18,769$ 19,145$ 19,528$ 19,918$ 20,317$ 20,723$ 21,137$ 21,560$ 21,991$ 22,431$ 22,880$ 23,337$ 23,804$ 24,280$ 24,766$ 25,261$ 421,316$ Fees - Ramp 73,642$ 119,492$ 107,821$ 103,700$ 121,458$ 127,356$ 133,585$ 140,164$ 147,112$ 153,870$ 160,979$ 168,457$ 176,323$ 184,599$ 192,791$ 201,385$ 210,402$ 219,864$ 229,792$ 239,768$ 250,217$ 261,161$ 272,625$ 284,634$ 3,876,541$ Fees - Call-Outs 6,900$ 10,100$ 13,705$ 13,000$ 13,260$ 13,525$ 13,796$ 14,072$ 14,353$ 14,640$ 14,933$ 15,232$ 15,536$ 15,847$ 16,164$ 16,487$ 16,817$ 17,153$ 17,496$ 17,846$ 18,203$ 18,567$ 18,939$ 19,317$ 322,183$ Fuel Sales 1,002,889$ 1,351,198$ 1,585,078$ 1,559,000$ 1,657,314$ 1,761,827$ 1,872,932$ 1,991,042$ 2,116,601$ 2,245,989$ 2,383,287$ 2,528,977$ 2,683,573$ 2,847,620$ 3,017,569$ 3,197,660$ 3,388,500$ 3,590,729$ 3,805,027$ 4,028,440$ 4,264,969$ 4,515,387$ 4,780,508$ 5,061,196$ 61,739,148$

Aeronautical 1,101,183$ 1,505,451$ 1,722,867$ 1,692,200$ 1,809,372$ 1,920,395$ 2,038,353$ 2,163,679$ 2,296,836$ 2,433,644$ 2,578,726$ 2,732,583$ 2,895,749$ 3,068,789$ 3,247,661$ 3,437,093$ 3,637,711$ 3,850,177$ 4,075,195$ 4,309,391$ 4,557,193$ 4,819,395$ 5,096,837$ 5,390,408$ 66,359,188$ Non-Aeronautical -$ Rent 94,669$ 143,020$ 126,681$ 131,000$ 133,620$ 136,292$ 139,018$ 141,799$ 144,635$ 147,527$ 150,478$ 153,487$ 156,557$ 159,688$ 162,882$ 166,140$ 169,462$ 172,852$ 176,309$ 179,835$ 183,432$ 187,100$ 190,842$ 190,842$ 3,242,798$ Sales - Vending Machine 453$ 882$ 653$ 1,000$ 1,020$ 1,040$ 1,061$ 1,082$ 1,104$ 1,126$ 1,149$ 1,172$ 1,195$ 1,219$ 1,243$ 1,268$ 1,294$ 1,319$ 1,346$ 1,373$ 1,400$ 1,428$ 1,457$ 1,486$ 24,783$ Sale of Asset 103,860$ 46,037$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Rent - Airport 9,600$ 9,900$ 10,197$ 10,500$ 10,710$ 10,924$ 11,143$ 11,366$ 11,593$ 11,825$ 12,061$ 12,302$ 12,548$ 12,799$ 13,055$ 13,317$ 13,583$ 13,855$ 14,132$ 14,414$ 14,703$ 14,997$ 15,297$ 15,602$ 260,225$ Recovery of Write-Off 21$ -$

Non-Aeronautical 208,603$ 153,802$ 183,568$ 142,500$ 145,350$ 148,257$ 151,222$ 154,247$ 157,332$ 160,478$ 163,688$ 166,961$ 170,301$ 173,707$ 177,181$ 180,724$ 184,339$ 188,026$ 191,786$ 195,622$ 199,534$ 203,525$ 207,596$ 207,931$ 3,527,806$ Total Operating Revenues Before Grants

1,309,786$ 1,659,253$ 1,906,435$ 1,834,700$ 1,954,722$ 2,068,652$ 2,189,575$ 2,317,926$ 2,454,168$ 2,594,123$ 2,742,414$ 2,899,545$ 3,066,050$ 3,242,495$ 3,424,842$ 3,617,817$ 3,822,050$ 4,038,203$ 4,266,982$ 4,505,013$ 4,756,728$ 5,022,920$ 5,304,433$ 5,598,339$ 69,886,994$

Grants 68,447$ -$ TOTAL OPERATING REVENUES 1,309,786$ 1,727,700$ 1,906,435$ 1,834,700$ 1,954,722$ 2,068,652$ 2,189,575$ 2,317,926$ 2,454,168$ 2,594,123$ 2,742,414$ 2,899,545$ 3,066,050$ 3,242,495$ 3,424,842$ 3,617,817$ 3,822,050$ 4,038,203$ 4,266,982$ 4,505,013$ 4,756,728$ 5,022,920$ 5,304,433$ 5,598,339$ 69,886,994$

OPERATING EXPENSESSalaries & Wages (21000) 331,734$ 376,640$ 363,344$ 354,000$ 361,080$ 368,302$ 375,668$ 383,181$ 390,845$ 398,661$ 406,635$ 414,767$ 423,063$ 431,524$ 440,155$ 448,958$ 457,937$ 467,095$ 476,437$ 485,966$ 495,685$ 505,599$ 515,711$ 526,025$ 8,773,294$ Staff Expenses (22000) 7,010$ 3,214$ 4,999$ 7,700$ 7,854$ 8,011$ 8,171$ 8,335$ 8,501$ 8,671$ 8,845$ 9,022$ 9,202$ 9,386$ 9,574$ 9,765$ 9,961$ 10,160$ 10,363$ 10,570$ 10,782$ 10,997$ 11,217$ 11,442$ 190,832$ Office Supplies, Printing, Courier, Computer Services 3,785$ 3,495$ 4,318$ 3,450$ 3,500$ 3,570$ 3,641$ 3,714$ 3,789$ 3,864$ 3,942$ 4,020$ 4,101$ 4,183$ 4,266$ 4,352$ 4,439$ 4,528$ 4,618$ 4,711$ 4,805$ 4,901$ 4,999$ 5,099$ 85,041$ Materials & Equipment 524$ 626$ 3,048$ 4,200$ 4,284$ 4,370$ 4,457$ 4,546$ 4,637$ 4,730$ 4,824$ 4,921$ 5,019$ 5,120$ 5,222$ 5,327$ 5,433$ 5,542$ 5,653$ 5,766$ 5,881$ 5,999$ 6,119$ 6,241$ 104,090$ Utilities (natural gas & electricity) 30,293$ 32,554$ 32,718$ 36,000$ 37,800$ 39,690$ 41,675$ 43,758$ 45,946$ 48,243$ 50,656$ 53,188$ 55,848$ 58,640$ 61,572$ 64,651$ 67,883$ 71,278$ 74,841$ 78,583$ 82,513$ 86,638$ 90,970$ 95,519$ 1,249,893$ Phones 4,417$ 4,067$ 4,326$ 4,660$ 4,753$ 4,848$ 4,945$ 5,044$ 5,145$ 5,248$ 5,353$ 5,460$ 5,569$ 5,681$ 5,794$ 5,910$ 6,028$ 6,149$ 6,272$ 6,397$ 6,525$ 6,656$ 6,789$ 6,925$ 115,490$ Fuel - Fleet & equipment 1,219$ 1,530$ 2,070$ 1,200$ 1,500$ 1,575$ 1,654$ 1,736$ 1,823$ 1,914$ 2,010$ 2,111$ 2,216$ 2,327$ 2,443$ 2,566$ 2,694$ 2,828$ 2,970$ 3,118$ 3,274$ 3,438$ 3,610$ 3,790$ 49,599$ Building Maintenance (supplies & services incl. internal ) 11,149$ 20,615$ 13,600$ 7,120$ 13,000$ 13,260$ 13,525$ 13,796$ 14,072$ 14,353$ 14,640$ 14,933$ 15,232$ 15,536$ 15,847$ 16,164$ 16,487$ 16,817$ 17,153$ 17,496$ 17,846$ 18,203$ 18,567$ 18,939$ 315,866$ Grounds Maintenance (supplies & services) 13,868$ 17,771$ 19,473$ 22,000$ 22,440$ 22,889$ 23,347$ 23,814$ 24,290$ 24,776$ 25,271$ 25,777$ 26,292$ 26,818$ 27,354$ 27,901$ 28,459$ 29,029$ 29,609$ 30,201$ 30,805$ 31,421$ 32,050$ 32,691$ 545,233$ Equipment Repair (parts & labour) 4,079$ 3,784$ 2,475$ 4,000$ 4,080$ 4,162$ 4,245$ 4,330$ 4,416$ 4,505$ 4,595$ 4,687$ 4,780$ 4,876$ 4,973$ 5,073$ 5,174$ 5,278$ 5,383$ 5,491$ 5,601$ 5,713$ 5,827$ 5,944$ 99,133$ Operating Supplies 11,949$ 20,737$ 10,836$ 13,125$ 13,388$ 13,655$ 13,928$ 14,207$ 14,491$ 14,781$ 15,076$ 15,378$ 15,686$ 15,999$ 16,319$ 16,646$ 16,979$ 17,318$ 17,665$ 18,018$ 18,378$ 18,746$ 19,121$ 19,503$ 325,281$ Taxes 20,743$ 33,914$ 28,399$ 25,600$ 26,880$ 28,224$ 29,635$ 31,117$ 32,673$ 34,306$ 36,022$ 37,823$ 39,714$ 41,700$ 43,785$ 45,974$ 48,273$ 50,686$ 53,221$ 55,882$ 58,676$ 61,609$ 64,690$ 67,924$ 888,813$ Insurance 9,984$ 10,086$ 11,900$ 11,300$ 11,865$ 12,458$ 13,081$ 13,735$ 14,422$ 15,143$ 15,900$ 16,695$ 17,530$ 18,407$ 19,327$ 20,293$ 21,308$ 22,373$ 23,492$ 24,666$ 25,900$ 27,195$ 28,555$ 29,982$ 392,328$ Advertising & Promotion 3,075$ 15,199$ 2,416$ 10,700$ 8,000$ 8,160$ 8,323$ 8,490$ 8,659$ 8,833$ 9,009$ 9,189$ 9,373$ 9,561$ 9,752$ 9,947$ 10,146$ 10,349$ 10,556$ 10,767$ 10,982$ 11,202$ 11,426$ 11,654$ 194,379$ Professional Services 22,195$ 31,080$ 40,031$ 39,500$ 40,000$ 40,800$ 41,616$ 42,448$ 43,297$ 44,163$ 45,046$ 45,947$ 46,866$ 47,804$ 48,760$ 49,735$ 50,730$ 51,744$ 52,779$ 53,835$ 54,911$ 56,010$ 57,130$ 58,272$ 971,895$ Communications (contractor) 12,250$ -$ Aircraft Servicing 11,225$ 12,028$ 10,753$ 11,000$ 11,220$ 11,444$ 11,673$ 11,907$ 12,145$ 12,388$ 12,636$ 12,888$ 13,146$ 13,409$ 13,677$ 13,951$ 14,230$ 14,514$ 14,805$ 15,101$ 15,403$ 15,711$ 16,025$ 267,271$ Airport Furniture 23,698$ 28,707$ -$ Finance Charges 9,697$ 13,790$ 18,677$ 20,000$ 20,400$ 20,808$ 21,224$ 21,649$ 22,082$ 22,523$ 22,974$ 23,433$ 23,902$ 24,380$ 24,867$ 25,365$ 25,872$ 26,390$ 26,917$ 27,456$ 28,005$ 28,565$ 29,136$ 29,136$ 495,084$ A/R write-offs 22,989$ 102$ 11,366$ -$ Travel - Fleet 152,370$ 139,563$ 139,717$ 165,896$ 174,191$ 182,900$ 192,045$ 201,648$ 211,730$ 222,317$ 233,432$ 245,104$ 257,359$ 270,227$ 283,738$ 297,925$ 312,822$ 328,463$ 344,886$ 362,130$ 380,237$ 399,249$ 419,211$ 440,171$ 5,759,785$ Inter-departmental charges (mail, office services, finance, computer serv, GIS, drafting) 58,600$ 74,332$ 77,100$ 94,605$ 96,497$ 98,427$ 100,396$ 102,403$ 104,452$ 106,541$ 108,671$ 110,845$ 113,062$ 115,323$ 117,629$ 119,982$ 122,382$ 124,829$ 127,326$ 129,872$ 132,470$ 135,119$ 137,822$ 140,578$ 2,344,626$ Admin - Planning 1,800$ 37,900$ 38,700$ 47,800$ 50,000$ 51,000$ 52,020$ 53,060$ 54,122$ 55,204$ 56,308$ 57,434$ 58,583$ 59,755$ 60,950$ 62,169$ 63,412$ 64,680$ 65,974$ 67,293$ 68,639$ 70,012$ 71,412$ 72,841$ 1,214,868$ Aviation Fuel (cost of sales) 764,554$ 1,071,521$ 1,307,138$ 1,273,400$ 1,353,703$ 1,439,070$ 1,529,821$ 1,626,295$ 1,728,852$ 1,834,537$ 1,946,682$ 2,065,683$ 2,191,958$ 2,325,952$ 2,464,767$ 2,611,867$ 2,767,746$ 2,932,928$ 3,107,968$ 3,290,452$ 3,483,651$ 3,688,194$ 3,904,746$ 4,134,013$ 50,428,885$

1,520,957$ 1,953,255$ 2,147,404$ 2,158,506$ 2,266,215$ 2,377,399$ 2,494,862$ 2,618,979$ 2,750,150$ 2,885,458$ 3,028,280$ 3,179,053$ 3,338,243$ 3,506,343$ 3,680,505$ 3,864,246$ 4,058,115$ 4,262,693$ 4,478,597$ 4,703,477$ 4,940,667$ 5,190,868$ 5,454,818$ 5,732,715$ 74,811,684$ OPERATING INCOME OVER EXPENSES (incl. sale of assets) 211,171-$ 225,555-$ 240,969-$ 323,806-$ 311,493-$ 308,747-$ 305,287-$ 301,054-$ 295,982-$ 291,336-$ 285,866-$ 279,508-$ 272,194-$ 263,848-$ 255,664-$ 246,429-$ 236,065-$ 224,490-$ 211,616-$ 198,464-$ 183,940-$ 167,948-$ 150,385-$ 134,376-$ 4,924,690-$

OPERATING INCOME OVER EXPENSES (excl. sale of assets) 107,311-$ 225,555-$ 194,932-$ 323,806-$ 311,493-$ 308,747-$ 305,287-$ 301,054-$ 295,982-$ 291,336-$ 285,866-$ 279,508-$ 272,194-$ 263,848-$ 255,664-$ 246,429-$ 236,065-$ 224,490-$ 211,616-$ 198,464-$ 183,940-$ 167,948-$ 150,385-$ 134,376-$ 4,924,690-$

Capex -$ 175,000-$ -$ 4,161,600-$ -$ -$ -$ 101,355-$ -$ 585,830-$ 119,509-$ -$ 124,337-$ 63,412-$ -$ 131,948-$ 538,347-$ -$ -$ 1,428,246-$ -$ 7,429,585-$

Cash Flow 211,171-$ 225,555-$ 240,969-$ 323,806-$ 486,493-$ 308,747-$ 4,466,887-$ 301,054-$ 295,982-$ 291,336-$ 387,221-$ 279,508-$ 858,023-$ 383,357-$ 255,664-$ 370,766-$ 299,477-$ 224,490-$ 343,564-$ 736,811-$ 183,940-$ 167,948-$ 1,578,631-$ 134,376-$ 12,354,275-$

NPV (2013-32) 6,448,198-$

AIRPORT'S PRESENTATION FORMAT

PED-9-2013-4B

Page 224: Muskoka Business and Master Plan Final Draft Report-10May

  

 

J‐3

Muskoka Airport – Medium Growth – Current Rates ‐ Financial Forecasts 

 

MEDIUM GROWTH

OPERATING REVENUES 2009 2010 2011 2012 (budget) 2013 f 2014 f 2015 f 2016 f 2017 f 2018 f 2019 f 2020 f 2021 f 2022 f 2023 f 2024 f 2025 f 2026 f 2027 f 2028 f 2029 f 2030 f 2031 f 2032 f 2013-2032Aeronautical Fees - Miscellaneous 17,752$ 24,661$ 16,263$ 16,500$ 17,000$ 17,340$ 17,687$ 18,041$ 18,401$ 18,769$ 19,145$ 19,528$ 19,918$ 20,317$ 20,723$ 21,137$ 21,560$ 21,991$ 22,431$ 22,880$ 23,337$ 23,804$ 24,280$ 24,766$ 413,055$ Fees - Ramp 73,642$ 119,492$ 107,821$ 103,700$ 122,047$ 128,623$ 135,631$ 143,109$ 151,121$ 158,659$ 166,594$ 174,947$ 183,742$ 193,322$ 202,913$ 213,005$ 223,626$ 234,803$ 246,646$ 255,606$ 264,915$ 274,616$ 284,666$ 295,110$ 4,053,702$ Fees - Call-Outs 6,900$ 10,100$ 13,705$ 13,000$ 13,000$ 13,260$ 13,525$ 13,796$ 14,072$ 14,353$ 14,640$ 14,933$ 15,232$ 15,536$ 15,847$ 16,164$ 16,487$ 16,817$ 17,153$ 17,496$ 17,846$ 18,203$ 18,567$ 18,939$ 315,866$ Fuel Sales 1,002,889$ 1,351,198$ 1,585,078$ 1,559,000$ 1,684,469$ 1,820,037$ 1,966,514$ 2,124,781$ 2,295,784$ 2,479,998$ 2,678,993$ 2,893,956$ 3,126,167$ 3,377,010$ 3,585,539$ 3,806,944$ 4,042,021$ 4,291,614$ 4,556,619$ 4,818,372$ 5,095,160$ 5,387,849$ 5,697,352$ 6,024,633$ 71,753,812$

Aeronautical 1,101,183$ 1,505,451$ 1,722,867$ 1,692,200$ 1,836,517$ 1,979,259$ 2,133,357$ 2,299,726$ 2,479,379$ 2,671,780$ 2,879,372$ 3,103,364$ 3,345,059$ 3,606,185$ 3,825,022$ 4,057,250$ 4,303,694$ 4,565,225$ 4,842,849$ 5,114,353$ 5,401,259$ 5,704,472$ 6,024,865$ 6,363,448$ 76,536,435$ Non-AeronauticalRent 94,669$ 143,020$ 126,681$ 131,000$ 133,620$ 136,292$ 139,018$ 141,799$ 144,635$ 147,527$ 150,478$ 153,487$ 156,557$ 159,688$ 162,882$ 166,140$ 169,462$ 172,852$ 176,309$ 179,835$ 183,432$ 187,100$ 190,842$ 190,842$ 3,242,798$ Land Lease - Incremental 8,294$ 8,460$ 8,630$ 13,203$ 13,467$ 13,737$ 14,011$ 14,292$ 14,577$ 14,869$ 15,166$ 15,470$ 15,779$ 16,095$ 186,051$ AMC - Incremental -$ 16,718$ 17,052$ 17,393$ 17,741$ 18,096$ 33,224$ 33,888$ 34,566$ 58,762$ 59,937$ 61,136$ 62,359$ 63,606$ 64,878$ 66,175$ 67,499$ 68,849$ 70,226$ 71,630$ 903,733$ Sales - Vending Machine 453$ 882$ 653$ 1,000$ 1,000$ 1,020$ 1,040$ 1,061$ 1,082$ 1,104$ 1,126$ 1,149$ 1,172$ 1,195$ 1,219$ 1,243$ 1,268$ 1,294$ 1,319$ 1,346$ 1,373$ 1,400$ 1,428$ 1,457$ 24,297$ Sale of Asset 103,860$ 46,037$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Land Sales - Incremental -$ 386,155$ 170,539$ 271,465$ 828,159$ Rent - Airport 9,600$ 9,900$ 10,197$ 10,500$ 10,500$ 10,710$ 10,924$ 11,143$ 11,366$ 11,593$ 11,825$ 12,061$ 12,302$ 12,548$ 12,799$ 13,055$ 13,317$ 13,583$ 13,855$ 14,132$ 14,414$ 14,703$ 14,997$ 15,297$ 255,122$ Recovery of Write-Off 21$ -$

Non-Aeronautical 208,603$ 153,802$ 183,568$ 142,500$ 145,120$ 550,895$ 168,035$ 171,395$ 174,823$ 178,320$ 375,485$ 209,046$ 213,227$ 516,862$ 250,305$ 255,311$ 260,417$ 265,626$ 270,938$ 276,357$ 281,884$ 287,522$ 293,272$ 295,321$ 5,440,161$ Total Operating Revenues Before Grants

1,309,786$ 1,659,253$ 1,906,435$ 1,834,700$ 1,981,637$ 2,530,154$ 2,301,392$ 2,471,121$ 2,654,202$ 2,850,100$ 3,254,857$ 3,312,409$ 3,558,285$ 4,123,047$ 4,075,327$ 4,312,561$ 4,564,111$ 4,830,851$ 5,113,787$ 5,390,710$ 5,683,143$ 5,991,994$ 6,318,137$ 6,658,768$ 81,976,596$

Grants 68,447$ TOTAL OPERATING REVENUES 1,309,786$ 1,727,700$ 1,906,435$ 1,834,700$ 1,981,637$ 2,530,154$ 2,301,392$ 2,471,121$ 2,654,202$ 2,850,100$ 3,254,857$ 3,312,409$ 3,558,285$ 4,123,047$ 4,075,327$ 4,312,561$ 4,564,111$ 4,830,851$ 5,113,787$ 5,390,710$ 5,683,143$ 5,991,994$ 6,318,137$ 6,658,768$ 81,976,596$

-$ OPERATING EXPENSES -$ Salaries & Wages (21000) 331,734$ 376,640$ 363,344$ 354,000$ 361,080$ 368,302$ 375,668$ 383,181$ 390,845$ 398,661$ 406,635$ 414,767$ 423,063$ 431,524$ 440,155$ 448,958$ 457,937$ 467,095$ 476,437$ 485,966$ 495,685$ 505,599$ 515,711$ 526,025$ 8,773,294$ Staff Expenses (22000) 7,010$ 3,214$ 4,999$ 7,700$ 7,854$ 8,011$ 8,171$ 8,335$ 8,501$ 8,671$ 8,845$ 9,022$ 9,202$ 9,386$ 9,574$ 9,765$ 9,961$ 10,160$ 10,363$ 10,570$ 10,782$ 10,997$ 11,217$ 11,442$ 190,832$ Office Supplies, Printing, Courier, Computer Services 3,785$ 3,495$ 4,318$ 3,450$ 3,500$ 3,570$ 3,641$ 3,714$ 3,789$ 3,864$ 3,942$ 4,020$ 4,101$ 4,183$ 4,266$ 4,352$ 4,439$ 4,528$ 4,618$ 4,711$ 4,805$ 4,901$ 4,999$ 5,099$ 85,041$ Materials & Equipment 524$ 626$ 3,048$ 4,200$ 4,284$ 4,370$ 4,457$ 4,546$ 4,707$ 4,801$ 4,897$ 4,995$ 5,095$ 6,132$ 6,255$ 6,380$ 6,507$ 6,637$ 7,021$ 7,161$ 7,304$ 7,547$ 7,698$ 7,852$ 118,645$ Utilities (natural gas & electricity) 30,293$ 32,554$ 32,718$ 36,000$ 37,800$ 39,690$ 41,675$ 43,758$ 45,946$ 48,243$ 50,656$ 53,188$ 55,848$ 58,640$ 61,572$ 64,651$ 67,883$ 71,278$ 74,841$ 78,583$ 82,513$ 86,638$ 90,970$ 95,519$ 1,249,893$ Phones 4,417$ 4,067$ 4,326$ 4,660$ 4,753$ 4,848$ 4,945$ 5,044$ 5,145$ 5,248$ 5,353$ 5,460$ 5,569$ 5,681$ 5,794$ 5,910$ 6,028$ 6,149$ 6,272$ 6,397$ 6,525$ 6,656$ 6,789$ 6,925$ 115,490$ Fuel - Fleet & equipment 1,219$ 1,530$ 2,070$ 1,200$ 1,500$ 1,576$ 1,656$ 1,740$ 1,828$ 1,920$ 2,017$ 2,119$ 2,226$ 2,338$ 2,456$ 2,580$ 2,710$ 2,846$ 2,990$ 3,140$ 3,298$ 3,464$ 3,638$ 3,821$ 49,863$ Building Maintenance (supplies & services incl. internal ) 11,149$ 20,615$ 13,600$ 7,120$ 13,000$ 13,261$ 13,527$ 13,799$ 14,076$ 14,358$ 14,646$ 14,940$ 15,240$ 15,546$ 15,858$ 16,176$ 16,501$ 16,832$ 17,169$ 17,514$ 17,865$ 18,223$ 18,589$ 18,962$ 316,083$ Grounds Maintenance (supplies & services) 13,868$ 17,771$ 19,473$ 22,000$ 22,440$ 22,890$ 23,349$ 23,817$ 24,294$ 24,781$ 25,277$ 25,784$ 26,301$ 26,828$ 27,365$ 27,914$ 28,473$ 29,043$ 29,625$ 30,219$ 30,824$ 31,442$ 32,072$ 32,714$ 545,451$ Equipment Repair (parts & labour) 4,079$ 3,784$ 2,475$ 4,000$ 4,080$ 4,163$ 4,247$ 4,333$ 4,420$ 4,510$ 4,601$ 4,694$ 4,789$ 4,886$ 4,985$ 5,085$ 5,188$ 5,293$ 5,400$ 5,509$ 5,620$ 5,733$ 5,849$ 5,967$ 99,351$ Operating Supplies 11,949$ 20,737$ 10,836$ 13,125$ 13,388$ 13,655$ 13,928$ 14,207$ 14,491$ 14,781$ 15,076$ 15,378$ 15,686$ 15,999$ 16,319$ 16,646$ 16,979$ 17,318$ 17,665$ 18,018$ 18,378$ 18,746$ 19,121$ 19,503$ 325,281$ Taxes 20,743$ 33,914$ 28,399$ 25,600$ 26,880$ 28,224$ 29,635$ 31,117$ 32,673$ 34,306$ 36,022$ 37,823$ 39,714$ 41,700$ 43,785$ 45,974$ 48,273$ 50,686$ 53,221$ 55,882$ 58,676$ 61,609$ 64,690$ 67,924$ 888,813$ Insurance 9,984$ 10,086$ 11,900$ 11,300$ 11,865$ 12,458$ 13,081$ 13,735$ 14,422$ 15,143$ 15,900$ 16,695$ 17,530$ 18,407$ 19,327$ 20,293$ 21,308$ 22,373$ 23,492$ 24,666$ 25,900$ 27,195$ 28,555$ 29,982$ 392,328$ Advertising & Promotion 3,075$ 15,199$ 2,416$ 10,700$ 8,000$ 8,160$ 8,323$ 8,490$ 8,659$ 8,833$ 9,009$ 9,189$ 9,373$ 9,561$ 9,752$ 9,947$ 10,146$ 10,349$ 10,556$ 10,767$ 10,982$ 11,202$ 11,426$ 11,654$ 194,379$ Professional Services 22,195$ 31,080$ 40,031$ 39,500$ 40,000$ 40,800$ 41,616$ 42,448$ 43,297$ 44,163$ 45,046$ 45,947$ 46,866$ 47,804$ 48,760$ 49,735$ 50,730$ 51,744$ 52,779$ 53,835$ 54,911$ 56,010$ 57,130$ 58,272$ 971,895$ Communications (contractor) 12,250$ -$ Aircraft Servicing 11,225$ 12,028$ 10,753$ 11,000$ 11,220$ 11,444$ 11,673$ 11,907$ 12,145$ 12,388$ 12,636$ 12,888$ 13,146$ 13,409$ 13,677$ 13,951$ 14,230$ 14,514$ 14,805$ 15,101$ 15,403$ 15,711$ 16,025$ 267,271$ Airport Furniture 23,698$ 28,707$ -$ Finance Charges 9,697$ 13,790$ 18,677$ 20,000$ 20,000$ 20,400$ 20,808$ 21,224$ 21,649$ 22,082$ 22,523$ 22,974$ 23,433$ 23,902$ 24,380$ 24,867$ 25,365$ 25,872$ 26,390$ 26,917$ 27,456$ 28,005$ 28,565$ 29,136$ 485,947$ A/R write-offs 22,989$ 102$ 11,366$ -$ Travel - Fleet 152,370$ 139,563$ 139,717$ 165,896$ 174,191$ 182,900$ 192,045$ 201,648$ 211,730$ 222,317$ 233,432$ 245,104$ 257,359$ 270,227$ 283,738$ 297,925$ 312,822$ 328,463$ 344,886$ 362,130$ 380,237$ 399,249$ 419,211$ 440,171$ 5,759,785$ Inter-departmental charges (mail, office services, finance, computer serv, GIS, drafting) 58,600$ 74,332$ 77,100$ 94,605$ 96,497$ 98,427$ 100,396$ 102,403$ 104,452$ 106,541$ 108,671$ 110,845$ 113,062$ 115,323$ 117,629$ 119,982$ 122,382$ 124,829$ 127,326$ 129,872$ 132,470$ 135,119$ 137,822$ 140,578$ 2,344,626$ Admin - Planning 1,800$ 37,900$ 38,700$ 47,800$ 50,000$ 51,000$ 52,020$ 53,060$ 54,122$ 55,204$ 56,308$ 57,434$ 58,583$ 59,755$ 60,950$ 62,169$ 63,412$ 64,680$ 65,974$ 67,293$ 68,639$ 70,012$ 71,412$ 72,841$ 1,214,868$ Aviation Fuel (cost of sales) 764,554$ 1,071,521$ 1,307,138$ 1,273,400$ 1,375,884$ 1,486,616$ 1,606,260$ 1,735,533$ 1,875,210$ 2,025,676$ 2,188,217$ 2,363,799$ 2,553,471$ 2,758,361$ 2,928,688$ 3,109,533$ 3,301,546$ 3,505,414$ 3,721,872$ 3,935,673$ 4,161,756$ 4,400,826$ 4,653,629$ 4,920,954$ 58,608,919$ Additional Staffing Costs 50,000$ 51,000$ 52,020$ 53,060$ 54,122$ 55,204$ 56,308$ 57,434$ 58,583$ 59,755$ 60,950$ 62,169$ 63,412$ 64,680$ 65,974$ 67,293$ 68,639$ 70,012$

1,520,957$ 1,953,255$ 2,147,404$ 2,158,506$ 2,287,996$ 2,424,541$ 2,620,893$ 2,778,805$ 2,948,181$ 3,129,309$ 3,323,584$ 3,532,019$ 3,755,706$ 3,996,762$ 4,203,601$ 4,422,274$ 4,653,488$ 4,897,989$ 5,156,822$ 5,414,309$ 5,685,701$ 5,971,869$ 6,273,442$ 6,591,380$ 84,068,671$ OPERATING INCOME OVER EXPENSES (incl. sale of assets) 211,171-$ 225,555-$ 240,969-$ 323,806-$ 306,359-$ 105,613$ 319,501-$ 307,684-$ 293,979-$ 279,210-$ 68,727-$ 219,609-$ 197,421-$ 126,286$ 128,274-$ 109,713-$ 89,376-$ 67,138-$ 43,036-$ 23,599-$ 2,558-$ 20,125$ 44,695$ 67,389$ 2,092,075-$

OPERATING INCOME OVER EXPENSES (excl. sale of assets) 315,031-$ 225,555-$ 287,006-$ 323,806-$ 306,359-$ 280,542-$ 319,501-$ 307,684-$ 293,979-$ 279,210-$ 239,265-$ 219,609-$ 197,421-$ 145,180-$ 128,274-$ 109,713-$ 89,376-$ 67,138-$ 43,036-$ 23,599-$ 2,558-$ 20,125$ 44,695$ 67,389$ 2,920,234-$

Capex 675,000-$ 918,000-$ 4,161,600-$ -$ 81,182-$ 1,656,121-$ 664,436-$ -$ 585,830-$ 1,553,620-$ -$ 124,337-$ 63,412-$ -$ 131,948-$ 538,347-$ -$ -$ 1,428,246-$ -$ 12,582,080-$

Cash Flow (incl. land sales) 981,359-$ 812,387-$ 4,481,101-$ 307,684-$ 375,161-$ 1,935,331-$ 733,162-$ 219,609-$ 783,250-$ 1,427,335-$ 128,274-$ 234,050-$ 152,789-$ 67,138-$ 174,983-$ 561,946-$ 2,558-$ 20,125$ 1,383,551-$ 67,389$ 14,674,156-$

NPV (2013-32) 8,656,543-$

AIRPORT'S PRESENTATION FORMAT

PED-9-2013-4B

Page 225: Muskoka Business and Master Plan Final Draft Report-10May

  

 

J‐4

Muskoka Airport – High Growth – Current Rates ‐ Financial Forecasts 

 

HIGH GROWTH

OPERATING REVENUES 2009 2010 2011 2012 (budget) 2013 f 2014 f 2015 f 2016 f 2017 f 2018 f 2019 f 2020 f 2021 f 2022 f 2023 f 2024 f 2025 f 2026 f 2027 f 2028 f 2029 f 2030 f 2031 f 2032 f 2013-2032Aeronautical Fees - Miscellaneous 17,752$ 24,661$ 16,263$ 16,500$ 17,000$ 17,340$ 17,687$ 18,041$ 18,401$ 18,769$ 19,145$ 19,528$ 19,918$ 20,317$ 20,723$ 21,137$ 21,560$ 21,991$ 22,431$ 22,880$ 23,337$ 23,804$ 24,280$ 24,766$ 413,055$ Fees - Ramp 73,642$ 119,492$ 107,821$ 103,700$ 123,102$ 130,859$ 139,188$ 148,138$ 158,026$ 167,392$ 177,361$ 187,976$ 199,279$ 211,398$ 221,618$ 232,349$ 243,617$ 255,449$ 267,951$ 279,907$ 292,420$ 305,547$ 319,258$ 333,612$ 4,394,447$ Fees - Call-Outs 6,900$ 10,100$ 13,705$ 13,000$ 13,260$ 13,525$ 13,796$ 14,072$ 14,353$ 14,640$ 14,933$ 15,232$ 15,536$ 15,847$ 16,164$ 16,487$ 16,817$ 17,153$ 17,496$ 17,846$ 18,203$ 18,567$ 18,939$ 19,317$ 322,183$ Fuel Sales 1,002,889$ 1,351,198$ 1,585,078$ 1,559,000$ 1,756,906$ 1,979,934$ 2,231,275$ 2,514,522$ 2,833,726$ 3,115,673$ 3,425,673$ 3,766,517$ 4,141,274$ 4,553,319$ 4,889,417$ 5,250,325$ 5,637,872$ 6,054,026$ 6,500,898$ 6,890,789$ 7,304,064$ 7,742,126$ 8,206,460$ 8,698,642$ 97,493,437$

Aeronautical 1,101,183$ 1,505,451$ 1,722,867$ 1,692,200$ 1,910,268$ 2,141,659$ 2,401,946$ 2,694,772$ 3,024,506$ 3,316,474$ 3,637,112$ 3,989,252$ 4,376,008$ 4,800,880$ 5,147,922$ 5,520,298$ 5,919,866$ 6,348,619$ 6,808,776$ 7,211,422$ 7,638,025$ 8,090,044$ 8,568,937$ 9,076,337$ 102,623,123$ Non-Aeronautical -$ Rent 94,669$ 143,020$ 126,681$ 131,000$ 133,620$ 136,292$ 139,018$ 141,799$ 144,635$ 147,527$ 150,478$ 153,487$ 156,557$ 159,688$ 162,882$ 166,140$ 169,462$ 172,852$ 176,309$ 179,835$ 183,432$ 187,100$ 190,842$ 190,842$ 3,242,798$ Land Lease - Incremental 7,972$ 1,692$ 11,447$ 12,391$ 33,503$ AMC - Incremental -$ 16,718$ 17,052$ 17,393$ 31,933$ 32,572$ 33,224$ 56,480$ 57,610$ 58,762$ 59,937$ 81,514$ 83,145$ 84,808$ 86,504$ 110,292$ 112,498$ 114,748$ 117,043$ 119,384$ 1,291,617$ Sales - Vending Machine 453$ 882$ 653$ 1,000$ 1,020$ 1,040$ 1,061$ 1,082$ 1,104$ 1,126$ 1,149$ 1,172$ 1,195$ 1,219$ 1,243$ 1,268$ 1,294$ 1,319$ 1,346$ 1,373$ 1,400$ 1,428$ 1,457$ 1,486$ 24,783$ Sale of Asset 103,860$ 46,037$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Land Sales - Incremental -$ 386,155$ 163,916$ 260,924$ -$ 235,360$ 254,762$ 1,301,117$ Rent - Airport 9,600$ 9,900$ 10,197$ 10,500$ 10,710$ 10,924$ 11,143$ 11,366$ 11,593$ 11,825$ 12,061$ 12,302$ 12,548$ 12,799$ 13,055$ 13,317$ 13,583$ 13,855$ 14,132$ 14,414$ 14,703$ 14,997$ 15,297$ 15,602$ 260,225$ Recovery of Write-Off 21$ -$

Non-Aeronautical 208,603$ 153,802$ 183,568$ 142,500$ 145,350$ 551,130$ 168,274$ 171,640$ 361,154$ 193,050$ 196,911$ 486,058$ 227,910$ 232,469$ 237,118$ 509,047$ 267,484$ 272,833$ 278,290$ 573,067$ 312,033$ 318,273$ 324,639$ 327,315$ 6,154,043$ Total Operating Revenues Before Grants

1,309,786$ 1,659,253$ 1,906,435$ 1,834,700$ 2,055,618$ 2,692,788$ 2,570,220$ 2,866,412$ 3,385,659$ 3,509,524$ 3,834,023$ 4,475,310$ 4,603,918$ 5,033,349$ 5,385,040$ 6,029,345$ 6,187,349$ 6,621,453$ 7,087,066$ 7,784,489$ 7,950,058$ 8,408,317$ 8,893,575$ 9,403,652$ 108,777,166$

Grants 68,447$ -$ TOTAL OPERATING REVENUES 1,309,786$ 1,727,700$ 1,906,435$ 1,834,700$ 2,055,618$ 2,692,788$ 2,570,220$ 2,866,412$ 3,385,659$ 3,509,524$ 3,834,023$ 4,475,310$ 4,603,918$ 5,033,349$ 5,385,040$ 6,029,345$ 6,187,349$ 6,621,453$ 7,087,066$ 7,784,489$ 7,950,058$ 8,408,317$ 8,893,575$ 9,403,652$ 108,777,166$

-$ OPERATING EXPENSES -$ Salaries & Wages (21000) 331,734$ 376,640$ 363,344$ 354,000$ 361,080$ 368,302$ 375,668$ 383,181$ 390,845$ 398,661$ 406,635$ 414,767$ 423,063$ 431,524$ 440,155$ 448,958$ 457,937$ 467,095$ 476,437$ 485,966$ 495,685$ 505,599$ 515,711$ 526,025$ 8,773,294$ Staff Expenses (22000) 7,010$ 3,214$ 4,999$ 7,700$ 7,854$ 8,011$ 8,171$ 8,335$ 8,501$ 8,671$ 8,845$ 9,022$ 9,202$ 9,386$ 9,574$ 9,765$ 9,961$ 10,160$ 10,363$ 10,570$ 10,782$ 10,997$ 11,217$ 11,442$ 190,832$ Office Supplies, Printing, Courier, Computer Services 3,785$ 3,495$ 4,318$ 3,450$ 3,500$ 3,570$ 3,641$ 3,714$ 3,789$ 3,864$ 3,942$ 4,020$ 4,101$ 4,183$ 4,266$ 4,352$ 4,439$ 4,528$ 4,618$ 4,711$ 4,805$ 4,901$ 4,999$ 5,099$ 85,041$ Materials & Equipment 524$ 626$ 3,048$ 4,200$ 4,284$ 4,370$ 4,457$ 4,546$ 5,333$ 5,439$ 5,548$ 5,659$ 5,772$ 6,117$ 6,240$ 6,365$ 6,492$ 6,622$ 7,004$ 7,144$ 7,287$ 7,529$ 7,680$ 7,833$ 121,721$ Utilities (natural gas & electricity) 30,293$ 32,554$ 32,718$ 36,000$ 37,800$ 39,690$ 41,675$ 43,758$ 45,946$ 48,243$ 50,656$ 53,188$ 55,848$ 58,640$ 61,572$ 64,651$ 67,883$ 71,278$ 74,841$ 78,583$ 82,513$ 86,638$ 90,970$ 95,519$ 1,249,893$ Phones 4,417$ 4,067$ 4,326$ 4,660$ 4,753$ 4,848$ 4,945$ 5,044$ 5,145$ 5,248$ 5,353$ 5,460$ 5,569$ 5,681$ 5,794$ 5,910$ 6,028$ 6,149$ 6,272$ 6,397$ 6,525$ 6,656$ 6,789$ 6,925$ 115,490$ Fuel - Fleet & equipment 1,219$ 1,530$ 2,070$ 1,200$ 1,500$ 1,575$ 1,654$ 1,736$ 2,097$ 2,202$ 2,312$ 2,427$ 2,549$ 2,780$ 2,919$ 3,065$ 3,219$ 3,380$ 3,680$ 3,864$ 4,057$ 4,315$ 4,531$ 4,758$ 58,619$ Building Maintenance (supplies & services incl. internal ) 11,149$ 20,615$ 13,600$ 7,120$ 13,000$ 13,260$ 13,525$ 13,796$ 16,182$ 16,506$ 16,836$ 17,173$ 17,516$ 18,563$ 18,935$ 19,313$ 19,700$ 20,094$ 21,254$ 21,679$ 22,113$ 22,848$ 23,305$ 23,771$ 369,369$ Grounds Maintenance (supplies & services) 13,868$ 17,771$ 19,473$ 22,000$ 22,440$ 22,889$ 23,347$ 23,814$ 27,933$ 28,492$ 29,062$ 29,643$ 30,236$ 32,043$ 32,684$ 33,338$ 34,005$ 34,685$ 36,687$ 37,421$ 38,170$ 39,439$ 40,228$ 41,032$ 637,587$ Equipment Repair (parts & labour) 4,079$ 3,784$ 2,475$ 4,000$ 4,080$ 4,162$ 4,245$ 4,330$ 4,416$ 4,505$ 4,595$ 4,687$ 4,780$ 4,876$ 4,973$ 5,073$ 5,174$ 5,278$ 5,383$ 5,491$ 5,601$ 5,713$ 5,827$ 5,944$ 99,133$ Operating Supplies 11,949$ 20,737$ 10,836$ 13,125$ 13,388$ 13,655$ 13,928$ 14,207$ 14,491$ 14,781$ 15,076$ 15,378$ 15,686$ 15,999$ 16,319$ 16,646$ 16,979$ 17,318$ 17,665$ 18,018$ 18,378$ 18,746$ 19,121$ 19,503$ 325,281$ Taxes 20,743$ 33,914$ 28,399$ 25,600$ 26,880$ 28,224$ 29,635$ 31,117$ 32,673$ 34,306$ 36,022$ 37,823$ 39,714$ 41,700$ 43,785$ 45,974$ 48,273$ 50,686$ 53,221$ 55,882$ 58,676$ 61,609$ 64,690$ 67,924$ 888,813$ Insurance 9,984$ 10,086$ 11,900$ 11,300$ 11,865$ 12,458$ 13,081$ 13,735$ 14,422$ 15,143$ 15,900$ 16,695$ 17,530$ 18,407$ 19,327$ 20,293$ 21,308$ 22,373$ 23,492$ 24,666$ 25,900$ 27,195$ 28,555$ 29,982$ 392,328$ Advertising & Promotion 3,075$ 15,199$ 2,416$ 10,700$ 8,000$ 8,160$ 8,323$ 8,490$ 8,659$ 8,833$ 9,009$ 9,189$ 9,373$ 9,561$ 9,752$ 9,947$ 10,146$ 10,349$ 10,556$ 10,767$ 10,982$ 11,202$ 11,426$ 11,654$ 194,379$ Professional Services 22,195$ 31,080$ 40,031$ 39,500$ 40,000$ 40,800$ 41,616$ 42,448$ 43,297$ 44,163$ 45,046$ 45,947$ 46,866$ 47,804$ 48,760$ 49,735$ 50,730$ 51,744$ 52,779$ 53,835$ 54,911$ 56,010$ 57,130$ 58,272$ 971,895$ Communications (contractor) 12,250$ -$ Aircraft Servicing 11,225$ 12,028$ 10,753$ 11,000$ 11,220$ 11,444$ 11,673$ 11,907$ 12,145$ 12,388$ 12,636$ 12,888$ 13,146$ 13,409$ 13,677$ 13,951$ 14,230$ 14,514$ 14,805$ 15,101$ 15,403$ 15,711$ 16,025$ 267,271$ Airport Furniture 23,698$ 28,707$ -$ Finance Charges 9,697$ 13,790$ 18,677$ 20,000$ 20,000$ 20,400$ 20,808$ 21,224$ 21,649$ 22,082$ 22,523$ 22,974$ 23,433$ 23,902$ 24,380$ 24,867$ 25,365$ 25,872$ 26,390$ 26,917$ 27,456$ 28,005$ 28,565$ 29,136$ 485,947$ A/R write-offs 22,989$ 102$ 11,366$ -$ Travel - Fleet 152,370$ 139,563$ 139,717$ 165,896$ 174,191$ 182,900$ 192,045$ 201,648$ 211,730$ 222,317$ 233,432$ 245,104$ 257,359$ 270,227$ 283,738$ 297,925$ 312,822$ 328,463$ 344,886$ 362,130$ 380,237$ 399,249$ 419,211$ 440,171$ 5,759,785$ Inter-departmental charges (mail, office services, finance, computer serv, GIS, drafting) 58,600$ 74,332$ 77,100$ 94,605$ 96,497$ 98,427$ 100,396$ 102,403$ 104,452$ 106,541$ 108,671$ 110,845$ 113,062$ 115,323$ 117,629$ 119,982$ 122,382$ 124,829$ 127,326$ 129,872$ 132,470$ 135,119$ 137,822$ 140,578$ 2,344,626$ Admin - Planning 1,800$ 37,900$ 38,700$ 47,800$ 50,000$ 51,000$ 52,020$ 53,060$ 54,122$ 55,204$ 56,308$ 57,434$ 58,583$ 59,755$ 60,950$ 62,169$ 63,412$ 64,680$ 65,974$ 67,293$ 68,639$ 70,012$ 71,412$ 72,841$ 1,214,868$ Aviation Fuel (cost of sales) 764,554$ 1,071,521$ 1,307,138$ 1,273,400$ 1,435,050$ 1,617,222$ 1,822,518$ 2,053,876$ 2,314,603$ 2,544,899$ 2,798,109$ 3,076,512$ 3,382,616$ 3,719,176$ 3,993,704$ 4,288,495$ 4,605,046$ 4,944,963$ 5,309,970$ 5,628,436$ 5,966,001$ 6,323,812$ 6,703,083$ 7,105,100$ 79,633,190$ Add'l staff costs due development 50,000$ 51,000$ 52,020$ 53,060$ 54,122$ 55,204$ 56,308$ 57,434$ 58,583$ 59,755$ 60,950$ 62,169$ 63,412$ 64,680$ 65,974$ 67,293$ 68,639$ 70,012$

1,520,957$ 1,953,255$ 2,147,404$ 2,158,506$ 2,347,162$ 2,555,142$ 2,837,143$ 3,097,136$ 3,394,211$ 3,655,306$ 3,940,390$ 4,251,789$ 4,592,055$ 4,966,227$ 5,277,448$ 5,610,255$ 5,966,198$ 6,346,943$ 6,756,724$ 7,119,128$ 7,502,261$ 7,908,290$ 8,336,621$ 8,789,548$ 105,249,978$ OPERATING INCOME OVER EXPENSES (incl. sale of assets) 211,171-$ 225,555-$ 240,969-$ 323,806-$ 291,544-$ 137,646$ 266,923-$ 230,724-$ 8,552-$ 145,781-$ 106,367-$ 223,521$ 11,863$ 67,122$ 107,592$ 419,090$ 221,151$ 274,509$ 330,342$ 665,360$ 447,796$ 500,027$ 556,955$ 614,104$ 3,527,188$

OPERATING INCOME OVER EXPENSES (excl. sale of assets) 315,031-$ 225,555-$ 287,006-$ 323,806-$ 291,544-$ 248,509-$ 266,923-$ 230,724-$ 172,468-$ 145,781-$ 106,367-$ 37,403-$ 11,863$ 67,122$ 107,592$ 183,729$ 221,151$ 274,509$ 330,342$ 410,599$ 447,796$ 500,027$ 556,955$ 614,104$ 2,226,070$

Capex 675,000-$ 918,000-$ 4,161,600-$ 1,591,812-$ 622,398-$ -$ 101,355-$ 1,378,423-$ 585,830-$ 119,509-$ -$ 1,367,712-$ 63,412-$ -$ 131,948-$ 1,749,629-$ -$ -$ 1,428,246-$ -$ 14,894,874-$

Cash Flow 966,544-$ 780,354-$ 4,428,523-$ 1,822,536-$ 630,950-$ 145,781-$ 207,721-$ 1,154,902-$ 573,966-$ 52,388-$ 107,592$ 948,622-$ 157,739$ 274,509$ 198,394$ 1,084,268-$ 447,796$ 500,027$ 871,292-$ 614,104$ 11,367,686-$

NPV (2013-32) (incl. sale of assets) 7,353,954-$

AIRPORT'S PRESENTATION FORMAT

PED-9-2013-4B

Page 226: Muskoka Business and Master Plan Final Draft Report-10May

  

 

J‐5

Muskoka Airport – Medium Growth – Increased Rates ‐ Financial Forecasts 

 

MEDIUM GROWTH - BIZ PLAN

OPERATING REVENUES 2009 2010 2011 2012 (budget) 2013 f 2014 f 2015 f 2016 f 2017 f 2018 f 2019 f 2020 f 2021 f 2022 f 2023 f 2024 f 2025 f 2026 f 2027 f 2028 f 2029 f 2030 f 2031 f 2032 f 2013-2032Aeronautical Fees - Miscellaneous 17,752$ 24,661$ 16,263$ 16,500$ 17,000$ 17,340$ 17,687$ 18,041$ 18,401$ 18,769$ 19,145$ 19,528$ 19,918$ 20,317$ 20,723$ 21,137$ 21,560$ 21,991$ 22,431$ 22,880$ 23,337$ 23,804$ 24,280$ 24,766$ 413,055$ Fees - Ramp 73,642$ 119,492$ 107,821$ 103,700$ 170,354$ 177,776$ 185,661$ 194,044$ 202,994$ 211,655$ 220,753$ 230,312$ 240,356$ 251,231$ 262,500$ 274,333$ 286,761$ 299,816$ 313,608$ 323,933$ 334,659$ 345,830$ 357,407$ 369,435$ 5,253,420$ Fees - Call-Outs 6,900$ 10,100$ 13,705$ 13,000$ 13,260$ 13,525$ 13,796$ 14,072$ 14,353$ 14,640$ 14,933$ 15,232$ 15,536$ 15,847$ 16,164$ 16,487$ 16,817$ 17,153$ 17,496$ 17,846$ 18,203$ 18,567$ 18,939$ 19,317$ 322,183$ Fuel Sales 1,002,889$ 1,351,198$ 1,585,078$ 1,559,000$ 1,684,469$ 1,820,037$ 1,966,514$ 2,124,781$ 2,295,784$ 2,479,998$ 2,678,993$ 2,893,956$ 3,126,167$ 3,377,010$ 3,585,539$ 3,806,944$ 4,042,021$ 4,291,614$ 4,556,619$ 4,818,372$ 5,095,160$ 5,387,849$ 5,697,352$ 6,024,633$ 71,753,812$

Aeronautical 1,101,183$ 1,505,451$ 1,722,867$ 1,692,200$ 1,885,083$ 2,028,678$ 2,183,658$ 2,350,937$ 2,531,533$ 2,725,063$ 2,933,824$ 3,159,027$ 3,401,977$ 3,664,405$ 3,884,925$ 4,118,901$ 4,367,159$ 4,630,574$ 4,910,154$ 5,183,031$ 5,471,360$ 5,776,051$ 6,097,977$ 6,438,152$ 77,742,470$ Non-AeronauticalRent 94,669$ 143,020$ 126,681$ 131,000$ 133,620$ 136,292$ 139,018$ 141,799$ 144,635$ 147,527$ 150,478$ 153,487$ 156,557$ 159,688$ 162,882$ 166,140$ 169,462$ 172,852$ 176,309$ 179,835$ 183,432$ 187,100$ 190,842$ 190,842$ 3,242,798$ Land Lease - Incremental 12,214$ 12,458$ 12,707$ 19,442$ 19,831$ 20,228$ 20,632$ 21,045$ 21,466$ 21,895$ 22,333$ 22,780$ 23,235$ 23,700$ 273,966$ AMC - Incremental -$ 20,020$ 20,420$ 20,829$ 21,245$ 21,670$ 39,786$ 40,582$ 41,394$ 70,369$ 71,777$ 73,212$ 74,676$ 76,170$ 77,693$ 79,247$ 80,832$ 82,449$ 84,098$ 85,780$ 1,082,248$ Sales - Vending Machine 453$ 882$ 653$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 1,000$ 20,000$ Sale of Asset 103,860$ 46,037$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Land Sales - Incremental -$ 567,650$ 250,693$ 399,056$ 1,217,399$ Development Service Fee 17,660$ 28,112$ 45,773$ Airport Development Permit Fee 39,736$ 63,251$ 102,987$ Development Levy 10,244$ 16,306$ 26,549$ Rent - Airport 9,600$ 9,900$ 10,197$ 10,500$ 10,710$ 10,924$ 11,143$ 11,366$ 11,593$ 11,825$ 12,061$ 12,302$ 12,548$ 12,799$ 13,055$ 13,317$ 13,583$ 13,855$ 14,132$ 14,414$ 14,703$ 14,997$ 15,297$ 15,602$ 260,225$ Recovery of Write-Off 21$ -$

Non-Aeronautical 208,603$ 153,802$ 183,568$ 142,500$ 145,330$ 735,887$ 171,581$ 174,993$ 178,473$ 182,022$ 533,871$ 219,830$ 224,207$ 770,024$ 268,545$ 273,896$ 279,354$ 284,921$ 290,599$ 296,391$ 302,299$ 308,325$ 314,472$ 316,924$ 6,271,944$ Total Operating Revenues Before Grants

1,309,786$ 1,659,253$ 1,906,435$ 1,834,700$ 2,030,413$ 2,764,565$ 2,355,239$ 2,525,930$ 2,710,006$ 2,907,085$ 3,467,696$ 3,378,857$ 3,626,184$ 4,434,429$ 4,153,470$ 4,392,797$ 4,646,513$ 4,915,495$ 5,200,753$ 5,479,422$ 5,773,660$ 6,084,376$ 6,412,449$ 6,755,076$ 84,014,415$

Grants 68,447$ TOTAL OPERATING REVENUES 1,309,786$ 1,727,700$ 1,906,435$ 1,834,700$ 2,030,413$ 2,764,565$ 2,355,239$ 2,525,930$ 2,710,006$ 2,907,085$ 3,467,696$ 3,378,857$ 3,626,184$ 4,434,429$ 4,153,470$ 4,392,797$ 4,646,513$ 4,915,495$ 5,200,753$ 5,479,422$ 5,773,660$ 6,084,376$ 6,412,449$ 6,755,076$ 84,014,415$

-$ OPERATING EXPENSES -$ Salaries & Wages (21000) 331,734$ 376,640$ 363,344$ 354,000$ 361,080$ 368,302$ 375,668$ 383,181$ 390,845$ 398,661$ 406,635$ 414,767$ 423,063$ 431,524$ 440,155$ 448,958$ 457,937$ 467,095$ 476,437$ 485,966$ 495,685$ 505,599$ 515,711$ 526,025$ 8,773,294$ Staff Expenses (22000) 7,010$ 3,214$ 4,999$ 7,700$ 7,854$ 8,011$ 8,171$ 8,335$ 8,501$ 8,671$ 8,845$ 9,022$ 9,202$ 9,386$ 9,574$ 9,765$ 9,961$ 10,160$ 10,363$ 10,570$ 10,782$ 10,997$ 11,217$ 11,442$ 190,832$ Office Supplies, Printing, Courier, Computer Services 3,785$ 3,495$ 4,318$ 3,450$ 3,500$ 3,570$ 3,641$ 3,714$ 3,789$ 3,864$ 3,942$ 4,020$ 4,101$ 4,183$ 4,266$ 4,352$ 4,439$ 4,528$ 4,618$ 4,711$ 4,805$ 4,901$ 4,999$ 5,099$ 85,041$ Materials & Equipment 524$ 626$ 3,048$ 4,200$ 4,284$ 4,370$ 4,457$ 4,546$ 4,707$ 4,801$ 4,897$ 4,995$ 5,095$ 6,132$ 6,255$ 6,380$ 6,507$ 6,637$ 7,021$ 7,161$ 7,304$ 7,547$ 7,698$ 7,852$ 118,645$

Utilities (natural gas & electricity) 30,293$ 32,554$ 32,718$ 36,000$ 37,800$ 39,690$ 41,675$ 43,758$ 45,946$ 48,243$ 50,656$ 53,188$ 55,848$ 58,640$ 61,572$ 64,651$ 67,883$ 71,278$ 74,841$ 78,583$ 82,513$ 86,638$ 90,970$ 95,519$ 1,249,893$ Phones 4,417$ 4,067$ 4,326$ 4,660$ 4,753$ 4,848$ 4,945$ 5,044$ 5,145$ 5,248$ 5,353$ 5,460$ 5,569$ 5,681$ 5,794$ 5,910$ 6,028$ 6,149$ 6,272$ 6,397$ 6,525$ 6,656$ 6,789$ 6,925$ 115,490$ Fuel - Fleet & equipment 1,219$ 1,530$ 2,070$ 1,200$ 1,500$ 1,576$ 1,656$ 1,740$ 1,828$ 1,920$ 2,017$ 2,119$ 2,226$ 2,338$ 2,456$ 2,580$ 2,710$ 2,846$ 2,990$ 3,140$ 3,298$ 3,464$ 3,638$ 3,821$ 49,863$ Building Maintenance (supplies & services incl. internal ) 11,149$ 20,615$ 13,600$ 7,120$ 13,000$ 13,261$ 13,527$ 13,799$ 14,076$ 14,358$ 14,646$ 14,940$ 15,240$ 15,546$ 15,858$ 16,176$ 16,501$ 16,832$ 17,169$ 17,514$ 17,865$ 18,223$ 18,589$ 18,962$ 316,083$ Grounds Maintenance (supplies & services) 13,868$ 17,771$ 19,473$ 22,000$ 22,440$ 22,890$ 23,349$ 23,817$ 24,294$ 24,781$ 25,277$ 25,784$ 26,301$ 26,828$ 27,365$ 27,914$ 28,473$ 29,043$ 29,625$ 30,219$ 30,824$ 31,442$ 32,072$ 32,714$ 545,451$ Equipment Repair (parts & labour) 4,079$ 3,784$ 2,475$ 4,000$ 4,080$ 4,163$ 4,247$ 4,333$ 4,420$ 4,510$ 4,601$ 4,694$ 4,789$ 4,886$ 4,985$ 5,085$ 5,188$ 5,293$ 5,400$ 5,509$ 5,620$ 5,733$ 5,849$ 5,967$ 99,351$ Operating Supplies 11,949$ 20,737$ 10,836$ 13,125$ 13,388$ 13,655$ 13,928$ 14,207$ 14,491$ 14,781$ 15,076$ 15,378$ 15,686$ 15,999$ 16,319$ 16,646$ 16,979$ 17,318$ 17,665$ 18,018$ 18,378$ 18,746$ 19,121$ 19,503$ 325,281$ Taxes 20,743$ 33,914$ 28,399$ 25,600$ 26,880$ 28,224$ 29,635$ 31,117$ 32,673$ 34,306$ 36,022$ 37,823$ 39,714$ 41,700$ 43,785$ 45,974$ 48,273$ 50,686$ 53,221$ 55,882$ 58,676$ 61,609$ 64,690$ 67,924$ 888,813$ Insurance 9,984$ 10,086$ 11,900$ 11,300$ 11,865$ 12,458$ 13,081$ 13,735$ 14,422$ 15,143$ 15,900$ 16,695$ 17,530$ 18,407$ 19,327$ 20,293$ 21,308$ 22,373$ 23,492$ 24,666$ 25,900$ 27,195$ 28,555$ 29,982$ 392,328$ Advertising & Promotion 3,075$ 15,199$ 2,416$ 10,700$ 8,000$ 8,160$ 8,323$ 8,490$ 8,659$ 8,833$ 9,009$ 9,189$ 9,373$ 9,561$ 9,752$ 9,947$ 10,146$ 10,349$ 10,556$ 10,767$ 10,982$ 11,202$ 11,426$ 11,654$ 194,379$ Professional Services 22,195$ 31,080$ 40,031$ 39,500$ 40,000$ 40,800$ 41,616$ 42,448$ 43,297$ 44,163$ 45,046$ 45,947$ 46,866$ 47,804$ 48,760$ 49,735$ 50,730$ 51,744$ 52,779$ 53,835$ 54,911$ 56,010$ 57,130$ 58,272$ 971,895$ Communications (contractor) 12,250$ -$ Aircraft Servicing 11,225$ 12,028$ 10,753$ 11,000$ 11,220$ 11,444$ 11,673$ 11,907$ 12,145$ 12,388$ 12,636$ 12,888$ 13,146$ 13,409$ 13,677$ 13,951$ 14,230$ 14,514$ 14,805$ 15,101$ 15,403$ 15,711$ 16,025$ 267,271$ Airport Furniture 23,698$ 28,707$ -$ Finance Charges 9,697$ 13,790$ 18,677$ 20,000$ 20,400$ 20,808$ 21,224$ 21,649$ 22,082$ 22,523$ 22,974$ 23,433$ 23,902$ 24,380$ 24,867$ 25,365$ 25,872$ 26,390$ 26,917$ 27,456$ 28,005$ 28,565$ 29,136$ 29,719$ 495,666$ A/R write-offs 22,989$ 102$ 11,366$ -$ Travel - Fleet 152,370$ 139,563$ 139,717$ 165,896$ 174,191$ 182,900$ 192,045$ 201,648$ 211,730$ 222,317$ 233,432$ 245,104$ 257,359$ 270,227$ 283,738$ 297,925$ 312,822$ 328,463$ 344,886$ 362,130$ 380,237$ 399,249$ 419,211$ 440,171$ 5,759,785$ Inter-departmental charges (mail, office services, finance, computer serv, GIS, drafting) 58,600$ 74,332$ 77,100$ 94,605$ 96,497$ 98,427$ 100,396$ 102,403$ 104,452$ 106,541$ 108,671$ 110,845$ 113,062$ 115,323$ 117,629$ 119,982$ 122,382$ 124,829$ 127,326$ 129,872$ 132,470$ 135,119$ 137,822$ 140,578$ 2,344,626$ Admin - Planning 1,800$ 37,900$ 38,700$ 47,800$ 50,000$ 51,000$ 52,020$ 53,060$ 54,122$ 55,204$ 56,308$ 57,434$ 58,583$ 59,755$ 60,950$ 62,169$ 63,412$ 64,680$ 65,974$ 67,293$ 68,639$ 70,012$ 71,412$ 72,841$ 1,214,868$ Aviation Fuel (cost of sales) 764,554$ 1,071,521$ 1,307,138$ 1,273,400$ 1,375,884$ 1,486,616$ 1,606,260$ 1,735,533$ 1,875,210$ 2,025,676$ 2,188,217$ 2,363,799$ 2,553,471$ 2,758,361$ 2,928,688$ 3,109,533$ 3,301,546$ 3,505,414$ 3,721,872$ 3,935,673$ 4,161,756$ 4,400,826$ 4,653,629$ 4,920,954$ 58,608,919$

Add'l staff costs due development 50,000$ 51,000$ 52,020$ 53,060$ 54,122$ 55,204$ 56,308$ 57,434$ 58,583$ 59,755$ 60,950$ 62,169$ 63,412$ 64,680$ 65,974$ 67,293$ 68,639$ 70,012$ 1,520,957$ 1,953,255$ 2,147,404$ 2,158,506$ 2,288,396$ 2,424,949$ 2,621,309$ 2,779,230$ 2,948,614$ 3,129,751$ 3,324,034$ 3,532,478$ 3,756,175$ 3,997,240$ 4,204,088$ 4,422,772$ 4,653,995$ 4,898,507$ 5,157,350$ 5,414,848$ 5,686,250$ 5,972,430$ 6,274,014$ 6,591,963$ 84,078,390$

OPERATING INCOME OVER EXPENSES (incl. sale of assets) 211,171-$ 225,555-$ 240,969-$ 323,806-$ 257,983-$ 339,616$ 266,070-$ 253,300-$ 238,608-$ 222,666-$ 143,661$ 153,621-$ 129,991-$ 437,190$ 50,618-$ 29,974-$ 7,482-$ 16,988$ 43,403$ 64,575$ 87,409$ 111,947$ 138,435$ 163,113$ 63,976-$

OPERATING INCOME OVER EXPENSES (excl. sale of assets and Development Levy) 315,031-$ 225,555-$ 287,006-$ 323,806-$ 257,983-$ 228,035-$ 266,070-$ 253,300-$ 238,608-$ 222,666-$ 117,275-$ 153,621-$ 129,991-$ 21,828$ 50,618-$ 29,974-$ 7,482-$ 16,988$ 43,403$ 64,575$ 87,409$ 111,947$ 138,435$ 163,113$ 1,307,924-$

Capex 675,000-$ 918,000-$ 4,161,600-$ -$ 81,182-$ 1,656,121-$ 664,436-$ -$ 585,830-$ 1,553,620-$ -$ 124,337-$ 63,412-$ -$ 131,948-$ 538,347-$ -$ -$ 1,428,246-$ -$ 12,582,080-$

Cash Flow (incl. land sales & dev charges) 932,983-$ 578,384-$ 4,427,670-$ 253,300-$ 319,790-$ 1,878,787-$ 520,775-$ 153,621-$ 715,821-$ 1,116,431-$ 50,618-$ 154,312-$ 70,894-$ 16,988$ 88,545-$ 473,773-$ 87,409$ 111,947$ 1,289,811-$ 163,113$ 12,646,056-$

NPV (2013-32) 7,483,970-$

AIRPORT'S PRESENTATION FORMAT

PED-9-2013-4B

Page 227: Muskoka Business and Master Plan Final Draft Report-10May

  

 

K‐1

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

APPENDIX K: WIND ANALYSIS AND RUNWAY USABILITY

A  sufficient  number  and  adequate  lengths  of  runways  at  an  airport  are  key  to  an  airport’s  success. Without  these,  the airport may not attract or be able  to handle  the  traffic  that may wish  to use  the airport. The “capacity” of this runway system then also affects the  level and number of other facilities that will need to be provided. 

First let’s look at the number of runways required for the Muskoka airport.  

The airport currently has the main runway (18‐36) which  is a 6,000 ft long x 150 ft wide paved runway oriented in a north/south direction. The airport also has a secondary grass/dirt runway (09‐27) oriented east/west and located in the south portion of the airport lands. 

Per 3.1.1.1 of TP312, Transport Canada recommends the following37:    

“The number and orientation of runways at an aerodrome should be such that the usability factor of the aerodrome is not less than 95% (emphasis added) for the aeroplanes that the aerodrome is intended to serve”.           

Further, this document goes on to recommend in 3.1.1.2 that:   

“in the application of 3.1.1.1 it should be assumed that landing or take‐off of aeroplanes is, in normal circumstances, precluded when the cross‐wind component exceeds:  

- 37 km/hr (20 kts) in the case of aeroplanes whose reference field length is 1500m or over, except that when poor runway braking action owing to an insufficient longitudinal coefficient of friction is experienced with some frequency, a cross‐wind component not exceeding 24 km/h (13 kts) should be assumed;

-24 km/hr (13 kts) in the case of aeroplanes whose reference field length is 1200m or up to but not including 1500m; and

-19 km/h (10 kts) in the case of aeroplanes whose reference field length is less than 1200m.”

For Muskoka, given that the largest aircraft meant to use the runway require more than 1500m (say 4920 ft), then it would be the first item above, ie, 20 kt crosswind component that would apply to the calculation of annual usability. However, given that during the winter the runway is often wet as it is covered in snow and/or slush, while similarly in summer there may be frequent rain, then the cross‐wind component should be reduced to 13 kts for this runway, as noted.  

We should note that the above refers to the case for the “design” of the runway or system of runways. During actual “operations”, Air Traffic Control and the pilot will select whether or not they can  land or depart on any particular runway on the basis of “actual” winds and the certification level of the aircraft. So for instance, on a dry day, an A320 coming into YQA for painting at MAR could still land as long as its maximum certified cross‐wind component of 33 kt gusting to 38 kt  is not exceeded. If the runway was wet, then the cross‐wind component that the aircraft could take might be  limited to as  little as 15 kts, 

                                                                 37 This recommendation and the other associated ones discussed are consistent with other international jurisdictions including 

the US federal Aviation Administration (FAA) and the International Civil Aviation Organisation (ICAO). 

PED-9-2013-4B

Page 228: Muskoka Business and Master Plan Final Draft Report-10May

  

 

K‐2

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

including gusts, as illustrated in Figure K‐138, depending on the actual direction of the wind39. But on the other  hand,  even  in  wet  conditions,  the  aircraft  could  still  land  at  close  to  its  certified  cross‐wind component  as  long  as  the  angle  of  the wind  to  the  aircraft was  less  than  about  30  degrees.  So  in practice, even  if 13 kts  is used  to  calculate  the “design” usability of  the  runways,  the actual usability would be much higher as many aircraft will be able to “operate” at much higher cross‐wind components (even considering the effects of gusts discussed below). 

TP312 goes on to recommend in 3.1.1.3 that: 

“The  selection  of  data  to  be  used  for  the  calculation  of  the  usability  factor  should  be  based  on reliable wind distribution statistics that extend over as  long a period as possible, preferably of not less than five years. The observations used should be made at least eight times daily and spaced at equal intervals of time.” 

Figure K‐1: Allowable Crosswind Component For Selecting Operating Runway 

 

Source: Presentation by Earle Robinson  to  the Airport Advisory Committee, date  ‐‐‐‐. Original Source NavCanada Document …………………..  

It then also notes the following:                                                                   38 NavCanada has a similar chart for use under dry conditions. The minimum cross wind component in this case is 25 knots, with all other limits also proportionately higher.   39 In the case where the wind was at 90 degrees to the main runway, the maximum crosswind component would be limited to 15 knots under wet conditions (or 25 knots under dry conditions). However, per the wind rose charts shown later in Figures K‐2 and K‐3, these most severe of conditions (wind at 90 degrees to the runway) only apply about 10% of the time. In most cases the aircraft would be limited to much higher crosswind components, especially during dry conditions, with at many times the aircraft’s limits being more critical than the runway limits.     

PED-9-2013-4B

Page 229: Muskoka Business and Master Plan Final Draft Report-10May

  

 

K‐3

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

“Note – these winds are mean winds (emphasis added). Reference to the need for some allowance for gusty conditions is made in ……………….”  

Data used  to calculate  the usability  factors below meets  the above criteria  in  that  the wind data was collected  hourly  over  all  24  hour  periods  for  at  least  19  years.  The  data was  for  “mean” winds  per normal practice. The Transport Canada recommendations note where there may be a lot of gusts, then appropriate adjustments may be necessary  to  the above, but unfortunately gust  information  is  rarely available other than through the anecdotal observations of local pilots.  

So from the above, we can conclude that while the recommendation states that an adequate number of runways should be provided to achieve not less than 95% usability, in fact usability will actually vary due to 2 key  factors;  the usability will always be higher  for  the design or critical aircraft as  they can  take higher cross‐wind components, higher than the minimum used to calculate usability under virtually all conditions; and then also, the usability could be lower due to the effects of gusts.  

In any case, due to the variability and uncertainty in the actual usability, airports tend to try to maximize the usability as much as possible and at reasonable cost vs relying on  the  fact  that  the basic usability calculations may indicate that a usability of at least 95% is achieved. Our experience is that airports use this  “not  less  than 95%” usability not  so much  as  a  target  to be  achieved, but  as  a base  level  to be exceeded.  

The discussion so far has focussed on the “design” aircraft or the aircraft that the design of the runways is  meant  to  accommodate,  and  these  are  generally  large  aircraft  for  which  a  13  kt  cross‐wind component  is used  for “design” purposes. However, most of  the aircraft  serving  the airport  (close  to 80%  as will  be  shown  later)  are  actually  smaller  aircraft  for which  the maximum  design  cross‐wind component  is  only  10  kts.  In  determining  the  appropriate  number  of  runways  for  the  airport, appropriate consideration also needs to be given to these aircraft. 

Table  K‐1  summarises  the  runway  usability  for  Runway  18‐36  based  on  the  data  assembled  by PSMI/Genivar in a number of studies carried out in 201140 and subsequently reassessed by SNC Lavalin.  

Table K‐1: Runway Usability for Runway 18‐36 

           Runway Usability 

  Maximum Permissible Crosswind Component 

10 kts  13 kts 

Runway 18‐36  95.4%  98.6% 

This table shows that for the design (larger) aircraft the usability of runway 18‐36 would be an estimated 98.6%  using  the  crosswind  component  of  13  kts.  This  usability  is  considered  more  than  enough, especially knowing that the 13 kt crosswind figure for the design aircraft is on the low side and most, if not all of the design aircraft, will in fact be able to operate at higher crosswind components (though the 

                                                                 40 Muskoka Airport, Windrose Usability Study, Final Report, Pride Schropp McComb Inc (PSMI), November 2010 and Muskoka Airport, Crosswind Runway Relocation Feasibility Study, Final Report, Genivar (ex PSMI), December 2011 

PED-9-2013-4B

Page 230: Muskoka Business and Master Plan Final Draft Report-10May

  

 

K‐4

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

effect  of  gusts  will  tend  to  counter  this  factor).  Therefore,  we  conclude  that  the  current  runway orientation is appropriate to meet the needs of the design or critical aircraft serving the airport. 

For  smaller  aircraft  (which  comprise  around  80%  of  runway  operations),  using  a  10  kt  crosswind component would result  in a usability of only 95.4%. While many of  the aircraft even  in  this category would  be  able  to  accept  crosswind  components  higher  than  the  10  kts,  the  effect  of  gusts  would probably tend to reduce the usability to well below 95%. As a consequence, we would argue that the airport needs a second runway to cater to the needs of these smaller aircraft. 

The airport currently has a second runway – 09‐27 ‐ but this runway is very short at 2,200 ft and it is not paved. 

Given that there would be a need  for an additional runway, would  it make sense to pave the existing grass runway or would a better orientation be available that would maximise the usability of the overall airport? As well, based on previous work, consideration was given  to  relocating  this  runway  to make room  for additional  land development. So  looking at a different or better orientation  for  this  second runway would be appropriate. 

To  find  out  the  answer  to  this  question, we  carried  out  some  detailed  assessments  of  the  available weather data.  

Figure K‐2 illustrates a summary of the analysis of year round wind conditions at the airport site.                 

 

Figure K‐2: Runway Availability by Runway Direction – Year round, all periods  

 

84.00%

86.00%

88.00%

90.00%

92.00%

94.00%

96.00%

98.00%

100.00%

09‐27 10‐28 11‐29 12‐30 13‐31 14‐32 15‐33 16‐34 17‐35 18‐36

Runway Availability by Runway Direction Year Round all Periods

10kt Xwind 13kt Xwind Calms&<10kt

PED-9-2013-4B

Page 231: Muskoka Business and Master Plan Final Draft Report-10May

  

 

K‐5

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Wind rose data is captioned as an inset in the middle of the graph. This wind rose shows the frequency of  winds  blowing  from  the  various  directions.  It  is  evident  from  this  wind  rose  that  winds  blow predominantly from two key quadrants: West‐Northwest‐North and South‐Southeast. There is generally little wind from the other two quadrants and  in fact winds almost never blow from the east side from about 00 around to 1200. The most frequent wind blows from due west and occurs about 6% of the time (as a % of the yearly winds). 

The existing runway orientations at the airport are shown as 2 solid blue  lines  in the wind rose chart. The  north‐south  line  is  18‐36  and  the  east‐west  line  is  09‐27.  Runway  18‐36  would  appear  to  be generally well aligned with  the  year  round winds while 09‐27 would appear  to be  less  so.  It  is quite evident  from  looking at  the wind  rose  that  the  ideal  runway alignment,  if  there were  to be only one runway, would be a NW to SE orientation. 

The graph portion of Figure K‐2 shows the usability for the different runway directions all the way from 09‐27 (on the left) to 18‐36 (to the right). The existing runways in this case are shown as vertical dashed blue  lines. What  is  interesting  from  this  graph  is  that  neither  18‐36  nor  09‐27  provides  very  good usability compared  to  the other directions  shown.  In  fact  for a 10 kt crosswind component  (solid  red line),  the  best  runway  orientation would  be  13‐31  or  14‐32.  Each  of  these  directions would  provide usability of about 97.5% vs 95.5%  for 18‐36 or 94.9%  for 09‐27. Looking closely at the  line  for a 13 kt crosswind (dashed red), we see that this component  is  less sensitive to direction changes and typically averages usability of 98.5% to 99.5%. Nonetheless, this  line also shows that the best direction for year round usability is either 13‐31 or 14‐32. 

 In Appendix F, we  illustrate some additional graphs with respect to the wind analyses that show what we would define as a “quality” index with respect to crosswind components. These graphs show that for the runway directions that maximize the usability, the “frequency” of the greater crosswind components is minimized, whereas with lower usability, the “frequency” of greater crosswinds is higher.    

During the discussions, meetings and consultations with users, tenants, pilots and the Airport Advisory Committee,  there was a  lot of attention brought on summer conditions at  the airport, as  the existing grass runway (09‐27) can currently only be used  in the summer months and during daylight conditions only. 

Figure  K‐3  illustrates  the  distribution  of  summer winds  and  the  analysis of  the  implications  of  these winds for runway usability. 

The following conclusions can be drawn from this information: 

Winds  in the summer appear to be more focused from the West –Northwest, and  in fact a bit more from the West 

The best runway orientation from the perspective of a 10 kt crosswind in the summer, however, is still either 13‐31 or 14‐32 (similar to the year round conditions), with usability of just over 97% vs 94.1% for 09‐27 and 93.6% for 18‐36. 

Based on a 13 kt crosswind, the best runway orientation would also be 13‐31 or 14‐32 at 99.3% usability, and again with smaller variation across the different directions.  

And as with the year round case, the  frequency of greater crosswinds would be  less for these runway orientations that have maximum usability.        

This above wind analysis  is  interesting  in pointing out the best runway orientation  if we were starting over with a green field site. However, we already have the main runway at 18‐36 and the wind analysis shows that this runway provides very good usability for the larger aircraft that are intended to use it (at over  98.5%).  The  more  direct  question  at  hand  at  this  point  should  probably  be:  which  runway 

PED-9-2013-4B

Page 232: Muskoka Business and Master Plan Final Draft Report-10May

  

 

K‐6

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

orientation  for  a  second  runway  would  maximize  overall  airport  usability,  or  re‐phrased  –  which additional  runway  direction would  contribute  highest  to  the  increase  in  airport  usability?    Table  3‐6 provides the answer to this question. 

From Table K‐2  it  is  interesting that there  is  little difference  in the additional contribution that each of the different runway directions studied would make to the base 18‐36 direction. The highest usability is achieved by adding a runway  in the 10‐28 or 11‐29 direction  (99.6%), but 09‐27 and 12‐30 would also work well in that overall usability would only be 0.1% less, which is effectively a negligible difference and considered well within  the margin  of  error  of  the  analysis.  A  13‐31  direction would  see  the  overall usability drop to only 99.1%, which starts to be a more appreciable loss of total usability. This direction does  not  perform  as well  in  this  case,  as much  of  the  advantage  of  this  direction would  already  be accounted for by the existing runway 18‐36.  

 

Figure K‐3: Runway Availability by Runway Direction – Summer daytime only  

 

 

 

 

 

 

84.00%

86.00%

88.00%

90.00%

92.00%

94.00%

96.00%

98.00%

100.00%

09‐27 10‐28 11‐29 12‐30 13‐31 14‐32 15‐33 16‐34 17‐35 18‐36

Runway Availability by Runway Direction Summer Daytime Only 

10kt Xwind 13kt Xwind Calms&<10kt

PED-9-2013-4B

Page 233: Muskoka Business and Master Plan Final Draft Report-10May

  

 

K‐7

FINAL REPORT  10 May 2013 

BUSINESS PLAN ANDMASTER PLAN

MUSKOKA AIRPORT

Table K‐2: Runway Usability for 2 runway configurations (at 10kt crosswinds and year round winds) 

      Runway      Airport Usability   

      18‐36 only        95.5% 

      With 09‐27        99.5% 

      With 10‐28        99.6% 

      With 11‐29        99.6% 

      With 12‐30        99.5% 

      With 13‐31        99.1% 

This above analysis and resulting conclusions are based on the year round winds only. However, given that the summer usability varied little from the year round in Figure K‐2 and K‐3, an additional, separate analysis was not undertaken for the summer conditions.  

PED-9-2013-4B