multiple interconnection for generators mig tf
DESCRIPTION
Multiple Interconnection for Generators MIG TF. Bob Wittmeyer 512 762 8895. MIG TF Charter. - PowerPoint PPT PresentationTRANSCRIPT
MIG TF Charter
Examine and investigate the reliability, and market, impacts as well as the interconnection processes/procedures for Generation Units with more than one interconnection in the ERCOT Market. MIG will issue a whitepaper to WMS/ROS at their December meetings
Goal
MIG will issue a whitepaper to ROS/WMS containing a list of: Reliability concerns and mitigation actions, Market pros and cons, Policy/Planning issues related to the interconnection process,
for generation units with multiple interconnections in ERCOT.
For ROS/WMS Approval
Where we areAnswers to most initial questions were sent
out to WMS/ROS.Few questions still under reviewWhite paper is being developedOn Schedule for Final presentation in
December (Draft in November).
General DirectionExisting Protocols pretty well cover MIG’s today.
Some refinement/clarification will be requiredExpect that ERCOT will have the ability to direct a MIG to
a specific point during an “ERCOT emergency”Expect a MIG will be able to request a specific point of
interconnection with Notice {still being worked on but current book ends between 3 – 90 Days - (30-90 more likely)}. (Book ends will be a decision point for WMS/ROS (Dec 09)).
PCRR eligible units will be locked to Sept 99 date not only for Commercial Date, but also Generation Interconnect Node.
New Interconnects will follow SGIA guidelines, just like any other new unit (no priority).
A MIG will likely face the risk of CCN Approval for inclusion in TCOS, before the TSP will build the second point of interconnection.
Next Months Vote (1)Timeline for Market Participant Notice prior to a
Switch3 Days – Min Outage Notice period and max value
to MP30 Days - The TSP shall notification requirement
for relocated Facility.75 Days - keep topology constant for TCR/CRR
calculations.90 Days – RMR requirement and Complex outage
notification timeline.1 Yr – The topology stays the as approved by the
ERCOT Board of Directors