MTA Capital Construction 0

MTACC CPOC

ESA – Overview and Budget/Schedule

Risk Assessment

May 21, 2012

Page 2: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 1

MTA – 2009 MTA - 2012FTA2009

FTA2012

Numbers do not include $463 M for rolling stock which is budgeted separately in Rolling Stock Reserve

$Billions

Low Budget LowHigh Medium High 0

1

2

3

4

5

6

7

8

9

ESA - Budget & Schedule Ranges

7.22

3/16

8.24

9/16 1/17 4/18 9/18 12/18 8/19 9/19

7.32

8.01

7.867.81

7.98 8.24

Page 3: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 2

Risk Informed Budget and Schedule

• FTA independently concurs with budget

• Total Risk Informed Values are consistent with MTA’s current Risk Policy of 80%

probability that the project will be delivered at or below the risk informed budget

of $8.24B and schedule of 8/2019– Following this policy the 2009 rebase-lining would have resulted in a $8.01B budget

• $360M of contingency represents approximately 8% of the remaining $4.6B to

be spent

• Over $1.5B in awards are scheduled for the next 12 months; providing greater

cost certainty

• Efficiency in MTACC Projects and inter-agency program will fund additional

$200M commitment need in current ‘10 to ‘14 Plan

• Balance ($720M) to be addressed in ‘15 to ‘19 Plan with expectation that

additional efficiencies in MTACC Projects can cover some of the increase

2

Basis for Risk Assessment

Risk Informed Base Cost &

Schedule

Contingency Total Risk Informed

Value

Revenue Operation Date

December 2017

August 2018

12 months August 2019

Budget $7.72 B $7.88 B $0.36 B $8.24 B

Page 4: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 3

What Changed?

• By mid-2011, MTACC was reporting significant

construction delays in both Manhattan and

Harold

• Delays in Harold resulted in schedule

compression that placed stress on resources

and outages

• Other critical regional projects have put further

pressure on resources and outages

• Both cost and schedule contingency have been

largely consumed

3

Page 5: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 4

Steps Taken

• Developed a new forecast estimate and schedule

• Used as the Basis for Risk Assessment conducted by

Golder Associates

– Independent facilitator and modeler

• Identified major risks driving cost and schedule

• Produced new Risk Informed Base Cost and Schedule

plus Contingency

• Established New Total Risk Informed Value which

provides 80% probability that the final cost and schedule

will be at or below these levels

4

Page 6: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 5

Potential Risks and Mitigations

Page 7: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 6

Rebuilding and Expansion of Harold

Interlocking

Midday Storage Yard

Sunnyside YardNorthern Blvd

Busiest and most complex passenger railroad interlocking in US

Need for critical track outages and craft personnel timed to ESA needs

Page 8: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 7

Major Rail Projects in the New York

Metropolitan Region

PORTAL BRIDGEHIGH SPEED RAIL

MOYNIHAN STATION

HAROLD INTERLOCKING

EA

ST

R

IV

ER

M A N H A T T A NN E W J E R S E Y

EAST RIVER TUNNELS

NORTH RIVER TUNNELS

RELATEDBROOKFIELD

ESA was originally planned before other projects materialized

Page 9: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 8

Highlights in Harold

• Replacing and adding 92 new switches (231% increase)

• Replacing 11 miles of new track (16% increase)

• Constructing five new railroad bridges

• Replacing and installing 313 new catenary poles and signal

towers (43% increase)

• Constructing 1.25 miles of new retaining wall

• Replacing and installing 12 new Central Instrument Locations

for signal (300%)

• Constructing two (1,000 ft long) new by-pass tunnels

Most of this infrastructure will go on line prior to ESA Revenue Service

and will provide a significant benefit to Amtrak and LIRR operations

8

Page 10: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 9

Shared ESA Tunnel Access and Coordination

Issues

• Limited access paths for major equipment and

material

• Portions of tunnels get blocked when installing

track and a variety of systems

• Multiple contractors working in the same tunnels

in both Manhattan and Queens

9

Page 11: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 10

Procurement Risks

• Limited Competition

– Size of Contracts

– Complexity of Contracts

• Upcoming Major Contracts

– Manhattan Structures

– Two Systems Contracts

– GCT Concourse Fit-out

10

Page 12: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 1111

Risk Delays During Installation and Integration

• Installation of a significant number of system

elements

• Interface and integration of new and legacy

systems

Page 13: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 12

Mitigations

• Continue to monitor actual experience

– Not all risks will materialize

• Need a dynamic and flexible approach to

maintain confidence in meeting or exceeding

targets

• Opportunities fall into three categories

– Engineering

– Contract Interface/Coordination

– Policy

12

Page 14: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 13

Potential Mitigations

• Engineering

– Continue the work of the Operational Readiness group formed

with LIRR to address testing and commissioning

– Re-sequencing of Harold cut-overs

– Creating an Obsolescence Review Committee (during

construction) to evaluate systems elements to determine product

end of life cycle and the system or component version to

implement

• Contract Interface/Coordination

– Continue to create additional access points in Queens, Harold

and Manhattan

– Scope transfers between contracts

• Policy Decisions – Potential Service Reductions

13

Page 15: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 14

Summary

14

Risk Informed Base Cost &

Schedule

Contingency Total Risk Informed

Value

Revenue Operation Date

August2018

12 months August2019

Budget $7.88 B $0.36 B $8.24 B

• Continue to use Risk Model as a management tool

• Need to work with all stakeholders on mitigation

strategies

• Periodic reporting to CPOC on progress and success

with mitigation strategies

Page 16: MTACC CPOC ESA Overview and Budget/Schedule Risk Assessmentweb.mta.info/mta/news/books/docs/MayCPOC_MTACC.pdf · 2012-05-21 · ESA - Budget & Schedule Ranges 7.22 3/16 8.24 9/16

MTA Capital Construction 15

IEC Comments

• IEC participated in cost and schedule review and

Risk Assessment and supports the results

• Most significant near-term risk

– Procurement challenges to upcoming large and

complex contracts

15