MS/HFUC1 059/013 harley'" Method Statement C1 059 Grenfell Tower Activity: Installing Windows from Mast Climber Site Details Main Contractor: Sub Contractor: Site Address: Rydon Harley Facades Ltd Grenfell Tower Grenfell Road Netting Hill London W111TQ Project Manager: Ben Bailey Site Foreman: Mark Osbourne (Taff) Introduction: The works described comprise the complete fac;ade refurbishment of Grenfell Tower, a 1970's tower block located in Kensington, London, with insulation, high performance double glazed windows and aesthetic metal cladding panels. All operatives undertaking manual work will hold a relevant and valid CSCS card, as well as being competent and trained for the task being carried out. Harley will ensure that regular tool box talks are carried out, with training provided where necessary. This method statement relates to the installation of the window cassettes and glass installed from inside the building. Start Date: 10/09/2015 Timescale: 10 weeks Prepared By: Ben Bailey Hours of Work: 7 .30am - 4.30pm Grenfell Tower o harley· RYD00089712_0001 RYD00089712/1

Upload: others

Post on 15-May-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MS/HFUC1 059/013 harley

MS/HFUC1 059/013

harley'" Method Statement

C1 059 Grenfell Tower

Activity: Installing Windows from Mast Climber

Site Details

Main Contractor: Sub Contractor:

Site Address:

Rydon Harley Facades Ltd

Grenfell Tower Grenfell Road Netting Hill London W111TQ

Project Manager: Ben Bailey

Site Foreman: Mark Osbourne (Taff)

Introduction: The works described comprise the complete fac;ade refurbishment of Grenfell Tower, a 1970's tower block located in Kensington, London, with insulation, high performance double glazed windows and aesthetic metal cladding panels.

All operatives undertaking manual work will hold a relevant and valid CSCS card, as well as being competent and trained for the task being carried out. Harley will ensure that regular tool box talks are carried out, with training provided where necessary.

This method statement relates to the installation of the window cassettes and glass installed from inside the building.

Start Date: 10/09/2015 Timescale: 10 weeks Prepared By: Ben Bailey Hours of Work: 7 .30am - 4.30pm

Grenfell Tower o harley·

RYD00089712_0001 RYD00089712/1

Page 2: MS/HFUC1 059/013 harley

MS/HFUC1 059/013

Description of work activity: Installation of window frames and glass Persons Involved Mark Osbourne Site Foreman

Various Experienced trained operatives

Hazards Identified: General Hazards: falls from height, falls of materials from height, electric shock, moving & reversing plant and equipment, manual handling injuries, slips/trips/falls/cuts/puncture wounds.

Site Specific Hazards: Scaffold & Mast climber access. Neighbouring school/academy.

First Aiders: Mark Osbourne

Tools Cordless impact drill, Spanners Equipment Mast Climber, Scaffold/Electric Hoist

Work Sequence, Procedure & Control Measures

The purpose of this method statement is to describe how the Curtain Walling system & associated items are constructed installed, with reference to the following risk assessments:

• ## • ##

Upon arrival at site, operatives should introduce themselves to the Rydon Site Manager and attend a site induction. They should familiarise themselves with the site fire strategy (provided by Rydon) and the site welfare facilities provided by the main contractor (Rydon). The works described below form the installation procedure of the window frame system, in accordance with the approved construction issue drawings. The system is the Metal Technology 5-20 Hi Thermally Broken Aluminium Window system. Operatives must view the installation manual before starting work. The material will be delivered to site, with the lorry accompanied during delivery and unloading. These materials will be stored in an area as advised by Rydon. Materials will be loaded onto the mast climber by 2 or more operatives, following manual handling principles and breaking-down loads where appropriate. Where the mast climbing platforms are to be accessed by scaffold, Rydon will provide a suitable winch/hoist that can pick the frames up from ground level, rotate, and lower into the required platform. Sequence:

1) The site foreman will identify the correct window to be installed by cross-referencing the elevation drawings against the window schedule.

2) The window will be carried to the mast climber I loading area by 2 or more operatives. Do not remove protective films or any loose parts attached to the frames at this point in time.

3) The frame will then be lifted into the mast climber by a sufficient number of operatives (suggested 2 on the ground and 2 in the platform) through the access gate. The handrails are not to be removed, or the platform otherwise tampered with. Where a winch I hoist is to be used, lifting straps are to be fitted around 2 equally spaced mullions on the frame (to keep the load balanced). One man must operate the winch whilst one man directs the operator. In both instances the SWL of all equipment MUST be adhered to, with the lowest SWL of any component involved in a task taken as the maximum load for the operation.

Grenfell Tower 2 o harley·

I

RYD00089712_0002 RYD00089712/2

Page 3: MS/HFUC1 059/013 harley

MS/HFUC1 059/013

4) When the mast climber is loaded and checked to make sure the SWL has not been exceeded, the gate can be closed and the machine taken up to the required working level.

5) The frame will then be lifted from the mast climbing platform and onto the support rails already fixed to the building by a suitable number of operatives (minimum of 2, but 4 may be required for the larger frames).

6) Operatives will check the line and level of the frame, making adjustments where necessary.

7) Operatives will install the fixing channel and screw down through the frame to retain the window frame in place, and fill voids around the frame with rigid setting expanding foam.

8) The window perimeter will then be sealed with EPDM & adhesive to stop water ingress

Operatives working in the mast climber must be trained and understand the risks involved when using plant. At no stage should any of the operatives climb on the hand rail. The mast climber will require daily (at the start of the shift) and weekly (at the beginning of the week) inspections and a record kept in the Harley site office. Any defect or any concerns should be reported to the site manager immediately, who will make any necessary arrangements. Harsco will conduct thorough examinations at 6 weekly intervals. Operatives must not stack items on the edge of the platform, or use the handrails to lean materials against.

Operatives are only permitted to use either 11 Ov power tools or cordless tools, which must be PAT tested.

lt is important that good housekeeping is maintained, with all packaging, empty pallets and waste materials taken to the skip at break times and at the end of each working day. Operatives are reminded that they must follow the site waste management plan, and must therefore dispose of waste in the correct receptacle.

All operatives should read and understand the method statement and risk assessment before carrying out the works. If an operative is unsure of the requirements then they should ask their line manager or site manager to explain further. All operatives should have a good understanding of English- their comprehension will be tested. This sequence of work is under constant review by Harley management, and may be changed to introduce methods of best practice. Site work is always reviewed and monitored for safety and quality by a Harley site supervisor.

Grenfell Tower 3 o harley·

RYD00089712_0003 RYD00089712/3

Page 4: MS/HFUC1 059/013 harley

MS/HFUC1 059/013

First Aid

+ Welfare Provision:

Required PPE:

Hazardous Substances:

Other:

Emergency Procedures

Status:

Grenfell Tower

On-Site First Aider:

First Aid Box Location:

Location of Nearest Hospital (A&E)

No No No

Mark Osbourne, Rydon Personnel

Rydon Site Compound

St Mary' s Hospital Praed Street London Greater London W21NY

No No No No Additional PPE may be required for certain activites as indicated by specific risk assessments. All workers are responsible for taking care of their PPE. Defective equipment must be reported to Harley site manager and replaced. Where possible, use mechanical lifting equipment to keep manual handling to a minimum - all rules with regards to operation of plant etc apply. All lorries will use a banksman to enter and leave site, making sure all wheels are clean and loads are secured. Smoking is prohibited on site at all times. All operatives must attend a site induction, follow site rules and take note of fire evacuation proceedures and muster points. Working platform is provided by the form of a Mast climbing working platform (MCWP) - all persons operating machinery must hold the relevant licences or inductions. In the event of an accident inform the First Aider immediately, for a major injury call -immediately. If in doubt, call NHS Direct on -or ~or advice. Complete accident report book and RIDDOR if applicable. Other action taken as per company H&S policy. In the event of a fire sound the alarm and make your way to the nearest assembly point via a safe route. Do not attempt to tackle the fire unless it is safe and you are trained to do so. Call-mmediately for a major fire. If you discover material that you suspect contains asbestos, STOP WORK IMMEDIATELY and notify a Harley site manager/supervisor. Wait for further instructions and not return to the area until told to do so and o if the area is safe. RA/HFUC1 059/13 Ben Bai Date: 10/09/15 Issued Rev. -

4 o harley·

RYD00089712_0004 RYD00089712/4

Page 5: MS/HFUC1 059/013 harley

MS/HFUC1 059/013

By signing this form you confirm that you have read and understood the method statement outlined and associated risk assessments, and that you agree to comply with the safe

working procedures in place.

DATE NAME I SIGNATURE

Grenfell Tower 5 §~§harle y '"

RYD00089712_0005 RYD00089712/5