m/s. s.r constructions · table: location of noise monitoring stations code location distance (km)...

15
Executive Summary M/s. S.R CONSTRUCTIONS Road Metal & Building Stone Quarry (Lease Area : 24.90 Ha.) at Sy. No: 365-P Demakethapalli Village, Chilamathur Mandal Ananthapur District, Andhra Pradesh. (Production Capacity: 4,44,190 m 3 / Annum) Environment Consultant SRI SAI MANASA NATURE TECH (P) LTD Kalyan Nagar, Hyderabad - 500038 Phone No:040-23816333

Upload: others

Post on 20-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

  • Executive Summary

    M/s. S.R CONSTRUCTIONS

    Road Metal & Building Stone Quarry (Lease Area : 24.90 Ha.)

    at

    Sy. No: 365-P Demakethapalli Village,

    Chilamathur Mandal Ananthapur District, Andhra Pradesh.

    (Production Capacity: 4,44,190 m3/ Annum)

    Environment Consultant

    SRI SAI MANASA NATURE TECH (P) LTD Kalyan Nagar, Hyderabad - 500038

    Phone No:040-23816333

  • 1.0 Introduction

    M/s SR Constructions was granted the quarry lease for Road Metal and Building Stone by

    Assistant Director of Mines & Geology, Anathapuramu, for a period of 10 Years. Later

    ADMG, Ananthapurmu has recommended for a grant of QL over extent of 24.900Ha. After

    careful examination by ADMG, Kurnool for the proposals given by ADMG,

    Ananthapuramu, and grant of QL for Road Metal and Building Stone over an 24.900

    Hectares for a period of 10 years. Vide Notice No. 1317/Q3/2018, Dtd:26.02.21019,

    subject to submission of Approved mining plan along with consent for establishment

    from APPCB & EC from MoEF as per EIA Notification through S.O.1533, Dated: 14.09.2006.

    The Mining Plan is scrutinized by Deputy Director of Mines & Geology, Kurnool, vide

    Letter No.718/MP-ATP/2019, dated: 02.03.2019.

    This lease area proposed production of 4,44,190m3/ Road Metal & Building Stone as per

    the approved Mining Plan.

    2.0 Environment Clearances requirement:

    The proposed activity is categorized as Category B1 project as per Environmental Impact

    Assessment (EIA) Notification on Dated: 14/09/2006 and Amendments the notification of

    MoEFF &CC O.M Dated 12/12/2018. It necessitates obtaining the Environmental

    Clearance from SEAC/SEIAA.

    As per the requirement of EIA notification, necessary application to SEIAA, Andhra

    Pradesh was submitted for approval of Term of Reference (TOR). SEAC meeting

    conducted on 19th June 2019 and recommended for Terms of References. TOR was

    approved by SEAC/SEIAA, Andhra Pradesh

    S.R Constructions has appointed M/s. Sri Sai Manasa Nature Tech (P) Ltd, Hyderabad as

    consultant for getting Environment Clearances from Concerned Departments.

    METHODOLOGY OF EIA

    The EIA/EMP has been prepared based on EIA Notification 2006/2009/2011, as

    amended from time to time and the TOR as follows:

    The various steps involved in the study include:

    Identification of significant environmental parameters and assessing the status

    within the impact zone.

  • Prediction of Impacts envisaged due to proposed scheme on various

    environmental parameters.

    Evaluation of impacts after superimposing the predicted scenario developed by

    using ISCST3 model over the baseline scenario to prepare Environmental

    Management Plan.

    Collection of site-specific meteorological data at the mine site.

    Carrying out a site specific ecological study.

    Carrying out a site specific study for the Core and Buffer Zone for Ambient air,

    Water, Soil, Land use, socio economic status etc.

    Literature review that includes identification of relevant data from various

    government agencies and other sources for socio-economy, demography,

    meteorology, land use, ecology, etc.

    Identify various existing pollution loads due to mining and domestic activities in

    the buffer zone.

    Evaluate the predicted impacts on the various environmental attributes in the

    study area by using scientifically developed and widely accepted Environmental

    Impact Assessment (EIA) Methodologies.

    Preparation of Environmental Management Plan (EMP) outlining the measures for

    improving the environmental quality.

    3.0 EIA STUDY:

    The proposed mine lease boundary is considered as a center, a radial distance of 10 km is

    considered as study area for baseline data collection and environmental monitoring.

    Salient Features of the project

    S.No. Particulars Details

    A. Name of project M/s. S R Constructions

    B. Size of project

    Mining Lease area 24.900Ha.

    Proposed Production capacity 4,44,190 m3/ Road Metal & Building

    Stone

    C. Project location

    Village Demakethapalli

    Mandal Chilamathur

    District Ananthapur

  • State Andhra Pradesh

    Survey No 314-A

    Type of Land Government Land

    Toposheet No.

    Latitude & Longitude

    57 G/09

    CGP Latitude (N) Longitude (E)

    1 13°48'11.25 77°39' 46.67

    2 13°48'11.62 77°39' 47.14

    D. Environmental Settings Details(With approx. aerial distance and

    direction from the mining lease boundary)

    .

    Nearest Village Demakethapalli Village - 1.5 Km (NW)

    Nearest City Hindupur Town - 18 km

    Nearest Railway station,

    Airport & Sea port

    Hindupur Railway Station –

    17.5km(NW),

    Kempegowda international Airport(

    Bangalore) - 69km(S)

    Krishnapatnam Port – 261 km(E)

    Interstate boundary Andhra Pradesh and Karnataka

    interstate boundary is at 2.0 Km.

    Archeological Place No Archeological place in the 10km

    study area.

    National Park, Wild Life

    Sanctuary, Wild Life Corridors,

    Biosphere Reserves, Migratory

    routes for Birds. Protected

    Forest etc. within 10 Km radius

    study area

    Nil within the study area

    Reserve Forest and Protected

    Forest within 10 Km radius Errakonda Extension R F - 0.2 km (S)

    Water bodies within 10 km

    radius

    Chinnamma Vanka - 6.1 km (SW)

    Kushavathi River - 8.4 km (E)

    Yagnishetti Palli - 1.0 Km (SE)

    Seismic Zone Zone-III

    E. Cost Details

    Total Project Cost Rs. 90.00 Lakhs

    Cost for Environmental

    Protection Measures

    Capital Cost-Rs. 4.80 Lakhs

    Recurring Cost-Rs. 5.60 Lakhs

  • 4.0 LOCATION MAP AND SITE PHOTOGRAPHS

    Map showing general and specific location of proposed mine site, Topo map with 10 km

    radius, photographs and Google imagery are given in below

    Photographs of Proposed Mine Site

    Google Image of the Proposed Mine Site

  • 5.0 PROJECT & COST ESTIMATES

    The Total cost of project would be around Rs. 9.0.00 lakhs and Proposed EMP Capital

    Cost is Rs: 4.80 Lahks & Recurring Cost is Rs: 5.60 lakhs.

    6.0 METHOD OF MINING

    The mining are proposed to carried out by opencast other than fully mechanized mining

    method with drilling and blasting. The ROM will be sized and sorted in the crusher

    established outside the quarry lease area and loaded on to tippers and tractors using JCB.

    Mining are carried out by formation of bench of height 6mts.

    Drilling and Blasting: Drilling and blasting plays an important role for extraction Rom of

    Road metal and building stone. The primary drilling is done with Crawler drills of 4.5

    "diameter and secondary drilling is done with jackhammers and compressor. The

    compressor attached to the wagon drill has 450CFM capacity and compressor attached to

    jacks can cater needs of 2 jackhammers. Tippers are of 20 Tons capacity will be utilized

    for transportation from the leased area to crusher.

    7.0 Year wise Production for Five Years Period

    The proposed production in 5years of plan is 22,02,058m3 for which total of 23,17,956m3

    of rock mass to be excavated. The excavation is carried out by developing multiple

    benches of 6.0m height and 3.5m width. The quarry operations will be initiated below pit

    of the quarry lease area. The production target for the first five years, along with the

    target for removal of OB and waste is given in below Table

    Year wise Production for next Five years

    Year Total

    Volume M3 Production @ 95 % M3

    Waste @5% M3

    1st year 4,65,396 4,42,126 22,106 2nd year 4,67,568 4,44,190 22,209 3rd year 4,60,464 4,37,441 21,872 4th year 4,65,198 4,41,938 22,097 5th year 4,59,330 4,36,364 21,818 Total 23,17,956 22,02,058 1,10,103

    8.0 Life of the Mine

    Road metal & Building Stone is proposed for life of mine of average rate production is

    4,40,411.6m3 per annum. However, for safer side taking mineable reserve into

    consideration 85,89,288m3 of metal, at the given rate of proposed production, the life

  • of the mine will be 85,89,288/4,40,411.6= 19.5 Years OR Say 20 years based on this

    conceptual plan is prepared.

    9.0 Water requirement:

    Water will be required mainly for dust suppression, green belt development, drinking and

    other domestic purpose during mining operations. The total requirement of water will be

    16.00 KLD, which will be met from the existing bore wells/Nearby village; NOC will be

    obtained from Gram Panchayat.

    Water Requirement Details

    S.No Purpose Requirement

    (KLD)

    1 Dust suppression 8.0

    2 Green Belt Development 5.0

    3 Domestic Use 3.0

    Total 16.00

    10.0 EIA Study:

    EIA report contains a description of existing environment that would be or might be

    affected directly or indirectly by proposed project. Environmental baseline monitoring is

    a very important stage of EIA. Environmental baseline monitoring, during the

    operational phase, helps in judging the success of mitigation measures in protecting

    the environment. The main objectives of describing the environment, which may be

    potentially affected, are (i) to assess present environmental quality and the

    environmental impacts and (ii) to identify environmentally significant factors. The

    chapter contains information on existing environmental scenario of the proposed

    project study area.

    The proposed mine lease boundary is considered as a centre, a radial distance of 10 km

    is considered as study area for baseline data collection and environmental monitoring.

    The study area of map is given in below.

  • Topo Map (1:50,000) with 10 KM Radius of Study Area

    11.0 AIR QUALITY: Ambient Air Quality

    The ambient air quality monitoring was carried out at 8 locations. The location and

    descriptions of AAQM stations is shown in below Table. The parameters monitored

    during the study period were Particulate Matters (PM10), Particulate Matter (PM2.5),

    Sulphur dioxide (SO2) and Oxides of nitrogen (NOx).The results of AAQM are depicted.

  • Ambient Air Quality Monitoring Locations

    Code Sampling Location Distance (km)

    w.r.t Project site Direction

    w.r.t Project site

    A-1 Project Site -- --

    A-2 Demaketepalli Village 1.0 km NW A-3 Upparapalli Village 8.0 km WNW A-4 Venkatapuram Village 8.0 km SE

    A-5 Chilamatturu 7.0 km NE

    A-6 Tekuledu 7.5 km NE

    A-7 Mamidimakulapalli Village

    3.0 km WSW A-8 Konduru Village 8.0 km NW

    The minimum and maximum level of PM10 recorded within the study area was in the

    range of 65.40µg/m3 to 70.50µg/m3 with the 98th percentile ranging between

    47.55µg/m3 to 70.45µg/m3.

    The 24 hourly average values of NOx were compared with the National Ambient Air

    Quality Standards (NAAQS) and it was found that all sampling stations recorded values

    are below the applicable limits 80 µg/m3 for rural areas.

    The analysis of ambient air quality data for three months consequently indicates

    excellent ambient air conditions at site as well as around the site upstream as well as

    downstream. Particulate matter PM10 as well as PM2.5 is within limits prescribed. SO2 and

    NOx levels are well below the limits prescribed hence overall picture as far as ambient

    air is concerned is positive.

    Figure: Wind rose Diagram (Site Specific)

  • Observations of Windrose: First predominant wind is West followed by East. The total

    wind flow in both directions is 29.6% of the total time. Calm percantage (24.2%) of the

    wind direction is more than that the total time of the both predominent direction.

    13.0 NOISE ENVIRONMENT

    Noise survey has been conducted in the study area covering residential transportation

    commercial and calm zones. Noise pollution in the study area is associated with the

    Industrial activities, Vehicular traffic. To judge the ambient noise level of the area, noise

    levels were recorded at 8 locations in dB (A). The details of location are given in below

    table.

    Table: Location of Noise Monitoring Stations

    Code Location Distance (km) w. r. t. Project

    Direction w. r. t. Project

    N-1 Project Site -- -- N-2 Demaketepalli Village 1.0 km NW N-3 Upparapalli Village 8.0 km WNW N-4 Venkatapuram Village 8.0 km SE N-5 Chilamatturu 7.0 km NE N-6 Tekuledu 7.5 km NE N-7 Mamidimakulapalli Village 3.0 km WSW N-8 Konduru Village 8.0 km NW

    Monitoring results of the Noise level recorded at 8 locations is given in below Table

    Noise Levels during Study Period

    Max., Min. & Equivalent Noise

    levels

    N1 N2 N3 N4 N5 N6 N7 N8

    LMax 69.4 54.8 61.2 64.4 59.6 58.4 62.3 58.4

    LMin 41.8 36.7 36.4 33.4 34.6 36.1 38.9 38.4 Ld 64.9 58.6 57.3 52.2 52.8 54.7 53.8 53.3 Ln 44.9 44.0 43.2 42.1 41.8 41.3 41.2 45.4

    CPCB Ld Ln

    75 55 55 55 55 55 55 55

    70 45 45 45 45 45 45 45

    L min : Minimum Noise Level Recorded L max : Maximum Noise Level Recorded Ld : Day Equivalent Ln : Night Equivalents Ldn : Day-Night Equivalents

    It is observed that the noise values obtained were within the prescribed Ambient Air

    Quality Standards with respect to Noise.

  • 14.0 WATER ENVIRONMENT

    GROUND WATER MONITORING

    Selected water quality parameters for water resource of the study area have been used

    for describing the water environment and assessing the impacts. About 8 ground water

    samples were collected in the study area to assess the water quality. Water samples are

    drawn from the hand pumps being used by the villagers for domestic needs. The

    locations of water sampling stations have been shown in below Table.

    Table: Ground Water Sampling Locations in the Study Area

    Code Location Source of collection

    Distance (km) w.r.t.

    Project

    Direction w.r.t. Project

    GW-1 Project Site Ground Water -- --

    GW-2 Demaketepalli Village Ground Water 1.0 km NW

    GW-3 Upparapalli Village Ground Water 8.0 km WNW

    GW-4 Venkatapuram Village Ground Water 8.0 km SE

    GW-5 Chilamatturu Ground Water 7.0 km NE

    GW-6 Tekuledu Ground Water 7.5 km NE

    GW-7 Mamidimakulapalli Village

    Ground Water 3.0 km WSW

    GW-8 Konduru Village Ground Water 8.0 km NW

    Observation of Ground Water

    pH varies from 7.25 at Project site Location 7.16 village (GW1) to 7.74 at

    Demaketepalli Village (GW2) in the Study period.

    Hardness varies from 425 mg/l at Chilamatturu village (GW5) to 1010mg/l at

    Venkatapuram Village (GW4) in the Study Period.

    Total dissolved solids varyfrom 675 mg/l at Chilamatturu village (GW7) to 2050mg/l

    at Mamidimakulapalli Village (GW7) in the Study period.

    15.0 LAND ENVIRONMENT (SOIL CHARACTERISTICS)

    Soil samples were collected from 8 locations to assess the existing soil conditions

    representing various land use conditions and geological features and each these

    locations were identified randomly from where soil was collected from 30 cm below the

    surface. The samples were collected, labelled in the field with number and site name

    and sent to laboratory for analysis. The soil sampling locations are given in below Table.

  • Table: Soil Sampling Locations in the Study Area

    Code Location Distance (km) w.r.t.to Project

    Direction w.r.t.to Project

    S-1 Project Site -- --

    S-2 Demaketepalli Village

    1.0 km NW

    S-3 Upparapalli Village 8.0 km WNW

    S-4 Venkatapuram Village

    8.0 km SE

    S-5 Chilamatturu 7.0 km NE

    S-6 Tekuledu 7.5 km NE

    S-7 Mamidimakulapalli Village

    3.0 km WSW

    S-8 Konduru Village 8.0 km NW

    It is observed that the all the values are within the prescribed Standards with respect to

    Soil.

    16.0 Land Use Pattern in Study Area:

    Land use pattern of the study area (10 km from the project site) is shown below Table.

    Land Use (Area & Percentage) Pattern of 10km Area

    S.No. Particulars/Land Use AREA (Ha.)

    PGA (%)

    1. Built-up Land 1507 4.8 2. Water Bodies 2951 9.4 3. Barren Land 6374 20.3 4. Agriculture lands 17049 54.3 5. Forests 4301 17.8

    Total 31414 100

    17.0 ECOLOGY AND BIODIVERSITY

    The vegetation in the following forest located in 10 km radius is The area identified for

    the APIIC industrial park, Gollapuram village, Hindupur mandal of Anantapur district is

    referred to hereafter as the core zone while its surroundings extending up to 10 km

    radius is referred to as the buffer zone. Total area of the park is The core zone is a non-

    forest & forest wasteland sparsely covered by a few shrubs and some trees. Major part

    of the land was under dry rain-fed cultivation the original landscape has been modified

    and the open areas are used as grazing lands. Karanj (Pongamia pinnata), ber (Ziziphus

    nummularia), mesquite (Prosopis juliflora), lantana camara, custard apple (Annona

    squamosa), Anisomeles indica, Calotropis procera, Calotropis gigantea, Cassia auriculata.

    Waltheria indica, Aristida setacea, Scilla indica, Stylosanthes hamata, Solanum

    xanthocarpum were common wild plants found in the core zone. There were some trees

  • of mango (Mangifera indica), neem (Azadirachta indica), tamarind (Tamarindus indica),

    karanj (Pongamia pinnata), copper pod (Peltophorum pterocarpum), siamese cassia

    (Cassia siamea) within the industrial park. The existing industries are growing avenue and

    greenbelt species in 33% of the total area within their site.

    18.0 ENVIRONMENT POLLUTION CONTROLLED MEASURES

    Air Quality Mitigation Measures

    As already indicated the ground level concentration of PM10, is well within limits.

    In addition to the above the following measures will be adopted:

    1. Effective watering at the time of mining operation i.e., excavation and loading.

    2. Greenbelt will be developed within 7.5 m buffer zone.

    3. Material should be transported by truck which will be covered by tarpaulin.

    4. Sprinkling of water over unpaved roads.

    Noise and Vibration Control Measures

    The ambient noise level monitoring carried out has revealed that the ambient noise levels

    are well within the prescribed limits. However, the following measures will further tend to

    abate the noise level and vibration:

    A thick tree plantation.

    Regular preventive maintenance of machinery and the transport vehicles.

    Provision of silencers, to module the noise generated by the machines, where

    required.

    Equipment’s with permissible noise level will be procured.

    Provision of protective devices like ear muffs/ear plugs will be provided to

    workmen.

    In this mine only vehicular movement will cause noise and same will be reduced

    by vehicle speed restriction and maintenance.

    Speed of trucks entering or leaving the mine will be limited to moderate speed of

    25kmph to prevent undue noise from empty trucks.

    Soil and Land Use Pattern and Mitigation Measures

    There is no top soil generation in this five years plan period. No major impact on soil of

    the study area is envisaged due to mining activities as-

    Proper mitigation measures will be adopted to control dust emission by water

    sprinkling.

    There will be no outside discharge from mining lease area.

    There is no toxic element present in the mineral which may contaminate the soil.

  • 19.0 SOCIO-ECONOMIC ENVIRONMENT

    Impact on Socio-Economic Environment

    The socio-economic impacts af the proposed project could be assessed in terms of

    demand supply aspects for good and services in the area, pressure on natural resources

    and infrastructure, grouth of industry, sustainability of livelihoods and employment. Some

    indirect impacts can also be understood in terms of public health and safety, preserving

    local culture and aesthetics of the archaeological monuments and heritage precincts.

    Based on a close understanding and assesment.

    Corporate Environment Responsibility (CER)

    The mining will not produce significant adverse impact rather it will have positive impact

    as it will provide employment to local people. However, corporate environment

    responsibility, welfare activities will be taken up.

    The budget provision towards CER which is in addition to the budget provided for the

    District Mineral Fund of Rs.12lakh/annum is as under:

    Table: Budget for Corporate Environment Responsibility

    S.No Description Cost (In Lakhs)

    1 Assistance in sanitation and drinking water facilities 3.0

    2 Assistance in skill development 2.0

    3 Assistance to self-help groups & assistance to local villagers during local festivals etc.

    2.0

    4 Road maintenance and repair 3.0 5 Fund towards agricultural improvement in the area 2.0

    Total (In Lakhs) 12.0

    20.0 Budget for Environmental Protection

    It is necessary to include the environmental cost as a part of the budgetary cost

    component. The project authorities propose to undertake the following environmental

    works to achieve the environmental quality as desired. The budget for environmental

    protection has been formulated and given in below table.

    Table: Budget for Environmental Protection

    S.No. Work Name Capital cost

    (in Rs.)

    Annual Recurring cost

    (in Rs.)

    1 Occupational Health & Safety - 1,70,000

  • CONCLUSION

    As discussed, it is safe to say that the project is not likely to cause any significant impact

    on the ecology of the area, as adequate preventive measures will be adopted to contain

    the various pollutants within permissible limits. Green belt development around the area

    will also be taken up as an effective pollution mitigative technique, as well as to control

    the pollutants released from the premises of the proposed quarry.

    ----- ******** -----

    2

    Air Pollution Control : Gunny bags/ cloth for covering drill rods, Water sprinkling haul roads & greenbelt, developing greenbelt

    1,50,000 1,00,000

    3 Water Pollution Control: Constructing garland drains with silt traps & Check dam

    2,30,000 50,000

    4 Greenbelt Development 1,00,000 1,20,000 5 Medical Examination - 40,000 6 Environment Monitoring - 80,000

    Total 4,80,000 5,60,000