m/s. anandram developers pvt ltd., form...
TRANSCRIPT
M/s. Anandram Developers Pvt Ltd., Form 1A
M/s. Eco Tech Labs Pvt Ltd., Page 31
FORM IA
(Checklist of Environmental Impacts)
I. LAND ENVIRONMENT
S.
No.
Information/Checklist
confirmation
Details thereof (with approximate quantities
/rates, wherever possible) with sources of
information data
1.1 Will the existing land use get
significantly altered from the project
that is not constant with the
surrounding? (Proposed land use
must conform to the approved
Master Plan / Development Plan of
the area. Change of land use if any
and the statutory approval from the
competent authority are submitted).
Project site comes under Commercial Zone.
Documentary evidence for land use classification
and land ownership is enclosed as Annexure –
IV.
Attach maps of
(i) Site Location;
(ii) Surrounding features of the
proposed site (within 500 meters)
and
(iii) the site (indicating levels &
contours) to appropriate scales. If
not available attach only conceptual
plan.
The proposed Commercial development is
located in Saligramam Village, Egmore,
Nungambakkam Taluk, and Chennai District.
The Topo map showing surrounding features of
the Proposed Site (500 m radius) is enclosed as
Annexure –II. Master Plan is enclosed as
Annexure – I. Contour plan is enclosed as
Annexure-III
1.2 List out all the major project
requirements in terms of the land
area, built up area, water, power
requirement, community facilities,
parking needs etc.
Total land area: 18149.26 Sq.m
Total built-up area: 88779.20 Sq.m
Total Water requirement: 438 KLD
Fresh water requirement 160 KLD
Power requirement : 6.14 MW
Mall:
Car Parking Provided: 796 Nos.
Two Wheeler Parking Provided: 1094 Nos.
1.3 What are the likely impacts of the
proposed activity on the existing
facilities adjacent to the proposed
sites? (Such as open spaces,
community facilities, details of the
existing land use, disturbance to the
local ecology).
Due to the construction activity, impacts such as
air and noise pollution, wastewater generation &
disposal and solid waste disposal, are envisaged,
but with the efficient implementation of the
proposed Environment Management Plan (EMP)
adverse impacts will be minimized. Please refer
to EMP enclosed.
1.4 Will there be any significant land
disturbance resulting in erosion,
subsidence & instability? (Details of
soil type, slope analysis,
vulnerability to subsidence,
seismicity etc may be given).
Based on the type of soil and contour of the
surface there won’t be any erosion, subsidence or
instability. The project site falls under Zone-III of
the seismic category in India and hence the
vulnerability to earthquake is not so significant.
1.5 Will the proposal involve alternation
of natural drainage systems? (Give
The proposal will not alter the natural drainage
system. The contour plan of the project site is
M/s. Anandram Developers Pvt Ltd., Form 1A
M/s. Eco Tech Labs Pvt Ltd., Page 32
details on a contour map showing
the natural drainage near the
proposed project site)
enclosed as Annexure – III.
1.6 What are the quantities of earthwork
involved in the construction activity
– cutting, filling, reclamation etc.
(Give details of quantities of
earthwork transport of fill materials
from outside the site etc.)
Since there is single basement construction in
this project there may be some excavated
materials during construction activities. The
excavated soil obtained will be utilized for
backfilling and leveling the site. No filled
materials from outside is needed.
1.7 Give details regarding water supply,
waste handling etc during the
construction period.
Water Supply
The water requirement during the construction
phase of the project will be 10 KLD. It will be
sourced through groundwater.
Waste Handling
The wastes during the construction phase
comprises of the wastes generated by the workers
as a result of the construction activity.
The wastes generated by the workers will be
treated and disposed of by providing temporary
septic tanks. The construction debris will be used
for the formation of roads within the
development.
1.8 Will the low lying areas get altered?
(Provide details of how low lying
area getting modified from the
proposed activity)
There are no low-lying areas within the site as
well as in the surroundings.
1.9 Whether construction debris &
waste during construction cause
health hazard? (Give quantities of
various types of wastes generated
during construction including the
construction labour and the means of
disposal)
The generation of construction wastes will be
about 10 - 30 kg/m2 of construction area. These
will be used for the formation of roads within the
premises.
The liquid wastes (sewage) generated by the
workers will be treated and disposed of by
providing temporary septic tanks. Therefore no
significant health hazard is observed.
II. WATER ENVIRONMENT
S.
No.
Information/Checklist
confirmation
Details thereof (with approximate quantities
/rates, wherever possible) with sources of
information data
2.1 Give the total quantity of water
requirement for the proposed
project with the breakup of
requirements for various uses.
How will the water requirements
met? State the sources &
quantities and furnish a water
balance statement.
S.
No.
Description Quantity Source of
Supply
I Construction
phase
10 Tanker supply
II Operational phase
a Fresh Water
Requirement
Domestic
Requirement
160 KLD
149 KLD
CMWSSB
M/s. Anandram Developers Pvt Ltd., Form 1A
M/s. Eco Tech Labs Pvt Ltd., Page 33
Swimming pool
requirement
11 KLD
b
Recycled Water
Requirement
Flushing
requirement
Gardening
requirement
OSR
maintenance
HVAC
165 KLD
10 KLD
6 KLD
103 KLD
Treated STP
Water
2.2 What is the capacity (dependable
flow or yield) of the proposed
source of water?
The Source of water is from CMWSSB. The
required fresh water is 160 KLD.
2.3 What is the quality of water
required, in case, the supply is
not from a municipal source?
(Provide physical, chemical,
biological characteristics with
class of water quality)
The quality of fresh water required will be as per
domestic requirement.
2.4 How much of the water
requirement can be met from the
recycling of treated wastewater?
(Give the details of quantities,
sources and usages)
The wastewater generation from the project is
estimated to be about 299 KLD which will be treated
in proposed Sewage Treatment Plant of 320 KLD
capacity and will be recycled for flushing, gardening
and the remaining excess sewage will be disposed to
local panchayat for road side avenue plantations
2.5 Will there be diversion of water
from other users? (Please assess
the impacts of the project on
other existing uses and quantities
of consumption)
No, there will not be any diversion of water from
other users. The area is mostly of newly developed
area, adequate rainwater harvesting facilities has
been proposed in order to reduce the impact of
ground water.
2.6 What is the incremental
pollution load from wastewater
generated from the proposed
activity? (Give details of the
quantities and composition of
wastewater generated from the
proposed activity)
The wastewater generation from the project is
estimated to be about 299 KLD. During operational
phase the sewage generated will be treated in the
proposed STP (320 KLD). The Quality of
wastewater generated from the proposed
development will be: pH (6.5-8.5), BOD (250-350
mg/l), COD (500-700 mg/l), SS (150 mg/l),
2.7 Give details of the water
requirements met from water
harvesting? Furnish details of
the facilities created.
The rain water from the project site is proposed to be
collected and stored in a rain water collection sump.
The rain water from the roads/pavements and
landscape are proposed to be collected and recharged
through recharge pits and trench proposed along the
boundary.
2.8 What would be the impact of the
land use changes occurring due
to the proposed project on the
runoff characteristics
(quantitative as well as
qualitative) of the area in the
The runoff will increase due to the proposed
residential development. Proper rain water storage
sumps, storm water drains are designed for the
collection and recharge of rainwater. The excess
runoff will flow to the external storm water network.
Hence, no water logging problems anticipated.
M/s. Anandram Developers Pvt Ltd., Form 1A
M/s. Eco Tech Labs Pvt Ltd., Page 34
post construction phase on a
long-term basis? Would it
aggravate the problems of
flooding or water logging in any
way?
2.9 What are the impacts of the
proposal on the ground water?
(Will there be tapping of ground
water: give the details of ground
water table, recharging capacity,
and approvals obtained from
competent authority, if any)
The source of water is from CMWSSB. Hence there
will be not be a greater impact on ground water.
Rainwater harvesting measures proposed will
mitigate the impact on groundwater.
2.10 What precautions/measures are
taken to prevent the run-off from
construction activities polluting
land & aquifers? (Give details of
quantities and the measures
taken to avoid the adverse
impacts)
Construction area will be kept clean and maintained
without contamination, thereby avoiding pollution of
the surface runoff during construction phase.
Suitable drains as per the prevailing contour of the
plot will be developed and the runoff will be allowed
to flow through the existing storm water drains.
2.11 How is the storm water from
within the site managed? (State
the provisions made to avoid
flooding of the area, details of
the drainage facilities provided
with a site layout indication
contour levels)
Storm water drains within the site are designed based
on the average intensity of rainfall in that area.
Further storm water collection and storage sumps
have been planned to store part of the runoff during
rains.
2.12 Will the deployment of
construction laborers particularly
in the peak period lead to
unsanitary conditions around the
project site (Justify with proper
explanation)
Local laborers from nearby areas will be employed
for the project work and there is no labor camp
proposed inside the project site. Furthermore proper
sanitary facilities like temporary toilets and wash
area will be provided to laborers at the construction
site.
2.13 What on-site facilities are
provided for the collection,
treatment & safe disposal of
sewage? Give details of the
quantities of wastewater
generation, treatment capacities
with technology & facilities for
recycling and disposal )
Temporary toilets will be provided during
construction phase. The sewage generated will be
disposed off through a septic tank arrangement.
The wastewater generated during operation period
will be treated with proposed STP, the treatment
plant capacity, technology and design details is
described in Conceptual plan enclosed along with
this form, for recycling the treated wastewater dual
plumbing system is proposed for flushing and
gardening line.
2.14 Give details of dual plumbing
system if treated waste used is
used for flushing of toilets or
any other use.
Dual Plumbing for Toilet flushing and gardening is
proposed and the dual plumbing line layout is
attached as Annexure – VII.
M/s. Anandram Developers Pvt Ltd., Form 1A
M/s. Eco Tech Labs Pvt Ltd., Page 35
III. VEGETATION
S.
No.
Information/Checklist
confirmation
Details thereof (with approximate quantities
/rates, wherever possible) with sources of
information data
3.1 Is there any threat of the project to
the biodiversity? (Give a
description of the local ecosystem
with its unique features, if any)
There is no threat to the biodiversity due to the
proposed development. No sensitive species are
prevailing at the project site. The impact on
environment during the construction as well as
during operation, will be limited to project
premises, hence no impact is envisaged on the
surrounding ecological environment.
3.2 Will the construction involve
extensive clearing or modification
of vegetation? (Provided a detailed
account of the trees & vegetation
affected by the project)
There will not be clearing of vegetation since the
site is devoid of any greenery.
3.3 What are the measures proposed to
be taken to minimize the likely
impacts on important site features
(Give details of proposal for tree
plantation, landscaping, creation
of water bodies etc along with a
layout plan to an appropriate
scale)
There will not be any kind of impact due to this
project on site. Within the proposed project site,
green belt area of 2793.27 Sqm is designated for
development. Various species of plants are
proposed to be planted to create a clean and
healthy environment. Green belt area layout is
enclosed as Annexure-VII.
IV. FAUNA
S.
No.
Information/Checklist
confirmation
Details thereof (with approximate quantities
/rates, wherever possible) with sources of
information data
4.1 Is there likely to be any
displacement of fauna-both
terrestrial and aquatic or creation
of barriers for their movement?
Provided the details.
No, the displacement and barrier for movement of
fauna is not envisaged due to the project.
4.2 Any direct or indirect impacts on
the fauna of the area? Provided
details.
No, no negative impacts are envisaged on the
fauna of the area due to this project.
V. AIR ENVIRONMENT
S.
No.
Information/Checklist
confirmation
Details thereof (with approximate quantities
/rates, wherever possible) with sources of
information data
5.1 Will the project increase
atmospheric concentration of gases
& result in heat islands? (Give
As the proposed project consists of a Mall/ Theatre /
Hotel complex building, it has free access from the
surroundings. Hence there will not be any increase
M/s. Anandram Developers Pvt Ltd., Form 1A
M/s. Eco Tech Labs Pvt Ltd., Page 36
details of background air quality
levels with predicted values based
on dispersion models taking into
account the increased traffic
generation as a result of the
proposed construction)
in atmospheric concentration of gases and formation
of heat islands.
5.2 What are the impacts on generation
of dust, smoke, odorous fumes or
other hazardous gases? Give details
in relation to all the meteorological
parameters.
Dust suppression measures will be adopted during
construction period. No major sources of dust,
smoke, odorous fumes or other hazardous impacts
are anticipated during operation phase.
5.3 Will the proposal create shortage of
parking space for vehicles? Furnish
details of the present level of
transport infrastructure and
measures proposed for
improvement including the traffic
management at the entry & exit to
the project site.
Sufficient parking space is provided within the
project area. Internal traffic circulation will be
smooth and there will not be any idle running of
vehicles due to traffic. Roads, pedestrians and
footpaths are separately earmarked.
Parking provided:
Mall:
Car Parking Provided: 796 Nos.
Two Wheeler Parking Provided: 1094 Nos.
5.4 Provide details of the movement
patterns with internal roads, bicycle
tracks, pedestrian pathways,
footpaths etc, with areas under the
category.
Internal roads will run all along the site and the
pedestrian pathways will be provided on the either
sides of the road.
5.5 Will there be significant increase in
traffic noise & vibrations? Give
details of the sources and the
measures proposed for mitigation
of the above.
In construction phase, the noise generated from the
construction equipments will be reduced through
proper maintenance of all the equipments. Noise
control systems such as equipment foundation pads,
dampeners, silencers and acoustic enclosures will
be used for individual units. In Operation phase, the
major source of noise pollution is from vehicular
transportation and generator sets. But Noise and
vibrations are expected to be minimal due to the
distributed traffic pattern and by the development of
the green cover all along the internal roads. Hence
there is no major impact envisaged.
5.6 What will be the impact of DG sets
& other equipment on noise levels
& vibration in & ambient air
quality around the project site?
Provided details.
DG sets with acoustic enclosures will be used
during construction as well as operational phases of
the project.
The DG sets will be operated only for short
durations in case of power cuts and the flue gases
will be let outside through the stacks with adequate
height as prescribed by CPCB. Use of low sulphur
HSD will reduce the impact on the ambient air
quality.
M/s. Anandram Developers Pvt Ltd., Form 1A
M/s. Eco Tech Labs Pvt Ltd., Page 37
VI. AESTHETICS
S.
No.
Information/Checklist
confirmation
Details thereof (with approximate quantities
/rates, wherever possible) with sources of
information data
6.1 Will the proposed constructions in
any way results in the obstruction
of a view, scenic amenity or
landscapes? Are these
considerations taken into account
by the proponents?
No, the proposed construction will not obstruct
any view, scenic amenities or landscapes.
6.2 Will there be any adverse impacts
from new constructions on the
existing structures? What are the
considerations taken into account?
No, there will not be any adverse impact due to
this project on the existing structures.
6.3 Whether there are any local
considerations of urban form &
urban design influencing the
design criteria? They may be
explicitly spelt out.
No, the proposed project is developed in an area
earmarked Commercial use zone.
6.4 Are there any anthropological or
archaeological sites or artifacts
nearby? State if any other
significant features in the vicinity
of the proposed site have been
considered.
There are no anthropological or archaeological
sites or artifacts nearby.
VII. SOCIO-ECONOMIC ASPECTS
S.
No.
Information/Checklist
confirmation
Details thereof (with approximate quantities
/rates, wherever possible) with sources of
information data
7.1 Will the proposal results in any
changes to the demographic
structure of local population?
Provide the details.
The project will change the demographic pattern
slightly. There will be alteration in the numbers of
skilled, unskilled and professional work force.
Changes in socio economic pattern are also
envisaged to some extent.
7.2 Give details of the existing social
infrastructure around the proposed
project.
The project site is located nearer to Koyambedu.
The surrounding area is highly populated by
residential components.
7.3 Will the project cause adverse
effects on local communities,
disturbance to sacred sites or other
cultural values? What are the
safeguards proposed?
No, the project will not cause any adverse effect.
M/s. Anandram Developers Pvt Ltd., Form 1A
M/s. Eco Tech Labs Pvt Ltd., Page 38
VIII. BUILDING MATERIALS
S.
No.
Information/Checklist
confirmation
Details thereof (with approximate quantities
/rates, wherever possible) with sources of
information data
8.1 May involve the use of building
materials with high-embodied
energy. Are the construction
materials produced with energy
efficient processes? (Give details
of energy conservation measures
in the selection of buildings
materials and their energy
efficiency)
The construction materials used are produced with
energy efficient processes.
8.2 Transport and handling of
materials during construction may
result in pollution, noise & public
nuisance. What measures are
taken to minimize the impacts?
Mitigation Measures during Construction Stage:
Air Pollution
Various construction activities related to handling
of loose material are likely to cause generation of
fugitive dust affecting the air quality of the
surrounding area of the project site. To minimize
such impact following measures shall be taken:
All the loose materials, either stacked or
transported, will be provided with suitable
covering such as tarpaulin, etc. Water sprinkling
will be done at the location where dust generation
is anticipated. To minimize the occupational
health hazard, proper personal protective
equipments, i.e. mask, goggles, helmets and safety
shoes will be provided to the workers who are
engaged in construction activity.
Noise Pollution
During the construction stage, expected noise
levels will be in the range of 80-85 dB (A) which
will decrease with increase in distance as per the
Inverse Square Law. Administrative as well as
engineering control of noise will be implemented.
Isolation of noise generation sources and temporal
differentiation of noise generating activities will
ensure minimum noise at receiver’s end. To
prevent any occupational hazard, ear muffler /
plug will be given to the workers working around
or operating plant and machinery emitting higher
noise levels than the permissible limits. There will
be no construction during night hours. Careful
planning of machinery operation and scheduling
of operations will be done to minimise such
impact.
M/s. Anandram Developers Pvt Ltd., Form 1A
M/s. Eco Tech Labs Pvt Ltd., Page 39
8.3 Are recycled materials used in
roads and structures? State extent
of savings achieved
Construction debris generated will be recycled to
the extent possible in forming roads within the
premises.
8.4 Give details of the methods of
collection, segregation & disposal
of the garbage generated during
the operation phases of the project.
The solid waste will comprise biodegradable
waste e.g. domestic waste, food waste,
horticultural waste etc. and recyclable waste, like
plastics, paper etc.
Biodegradable Wastes: 6.6 Tonnes/day
Non-biodegradable Wastes: 1.8 Tonnes/day
STP Sludge:45 kg/day
Solid Waste Management:
In the building complex, private sweepers would
be engaged for handling domestic waste and
appropriate site will be identified for keeping bin /
container for the collection of waste.
Adequate number of collection bins separately for
biodegradable and non-biodegradable waste will
be provided as per the Municipal Solid Waste
(Management and Handling) Rule, 2000. Separate
colored bins will be provided for biodegradable
and non-biodegradable wastes. All the collection
bins shall be properly maintained and cleared on
regular basis. Waste from such bins shall be
collected separately on daily basis and taken to a
centralized storage facility. The Bio degradable
wastes will be handed over to local municipality,
non biodegradable will be handed over to the
recyclers.
Horticultural wastes:
Leaves, grass and vegetative residues shall be
collected at the secured location such that it will
not hinder daily activity schedule or washed away
by the surface run-off causing choking of drains,
etc. and will be separately disposed off along with
biodegradable waste.
IX. ENERGY CONSERVATION
S.
No.
Information /Checklist
confirmation
Details thereof (with approximate quantities
/rates, wherever possible) with sources of
information data
9.1 Give details of the power
requirements, sources of supply,
backup source etc. What is the
energy consumption assumed per
square foot of built-up areas? How
have you tried to minimize energy
consumption?
The power would be sourced from TNEB from
nearby sub-station. The estimated power
requirement for the project is about 6140 KVA
during operational phase. Power back up is
proposed by using DG sets 3 No. of D.G. sets of
2000 KVA & 1 No.of D.G. set for capacity of
1500 KVA. The energy consumption will be
minimized by using energy efficient lamps, and
by adopting natural lightings and ventilations to
the possible extent.
M/s. Anandram Developers Pvt Ltd., Form 1A
M/s. Eco Tech Labs Pvt Ltd., Page 40
9.2 What type of, and capacity of, power
back-up you plan to provide?
Power back up is proposed by using DG sets.
DG sets:
3 No. of D.G. sets of 2000 KVA
1 No. of D.G set of 1500 KVA
9.3 What are the characteristics of the
glass you plan to use? Provide
specifications of its characteristics
related to both short wave and long
wave radiation?
Normal Glass. The thickness of glass is 4-6 mm
to keep the U-value of 1.08 W/m2°C.
9.4 What passive solar architectural
features are being used in the
building? Illustrate the applications
made in the proposed project.
Considering the site and solar analysis each
block was designed individually. The use of
solar passive measures includes the design of
fenestrations in such a way that sufficient day-
lighting is allowed inside the building.
9.5 Does the layout of streets &
buildings maximize the potential for
solar energy devices? Have you
considered the use of street lighting,
emergency lighting and solar hot
water systems for use in the building
complex?
The layout of streets & buildings will maximize
the potential for solar energy devices. Solar
powered street lighting will be adopted partly.
9.6 Is shading effectively used to reduce
cooling/heating loads? What
principles have been used to
maximize the shading of walls on the
East and the West and the Roof?
How much energy saving has been
effected?
Sunshades are proposed to reduce heat ingress
into the buildings. Sun path studies led to the
orientation and position of each block suited to
best protect itself from the harsh sun while
utilizing the natural wind direction to help
facilitate cross ventilation
9.7 Do the structures use energy –
efficient space conditioning, lighting
and mechanical systems? Provide
technical details. Provide details of
the transformers the motor
efficiencies, lighting intensity and
air-conditioning load assumptions?
Are you using CFC and HCFC free
chillers? Provide specifications.
Use of CFLs to reduce the lighting power
density. Energy efficient pumps and drives are
proposed.
9.8 What are the likely effects of the
buildings activity in altering the
micro-climates? Provide a self-
assessment on the likely impacts of
the proposed construction on creation
of heat island & inversion effects?
As per the design of the proposed project,
Sufficient Cross ventilation is provided. Hence
there will not be any change in microclimate due
to the proposed project.
9.9 What are the thermal characteristics
of the building envelope? (a) roof:
(b) external walls: and (c)
fenestration? Give details of the
The U-values of the roof, external wall and
fenestration of the building will meet the
requirements as specified in the Energy
Conservation Building Code (ECBC).
M/s. Anandram Developers Pvt Ltd., Form 1A
M/s. Eco Tech Labs Pvt Ltd., Page 41
materials used the U-values or the R-
values of the individual components.
Component Permissible
U-Value as
per
ECBC
(W/m2°C)
Resultant
Value due to
the proposed
configuration
(W/m2°C)
Roof (RCC slab
with clay tile)
0.261 0.25
Wall Constructed
using M15 grade
concrete solid
blocks,
0.440 0.440
Fenestration
(Plain glass with
sun colored film /
colored glass)
3.300 3.127
9.10 What precaution & safety measures
are proposed against fire hazards?
Furnish details of emergency plans.
Portable fire extinguishers, fire exit signage and
fire fighting system will be installed inside the
building. Portable fire extinguishers will be
installed. Fire protection and safety measures
proposed are expected to mitigate fire and
explosion hazards. Fire and safety Department
NOC is enclosed as Annexure-XIII.
9.11 If you are using glass as wall
material provides details and
specifications including emissive and
thermal characteristics.
No, glass is not used as wall material.
9.12 What is the rate of air infiltration into
the building? Provide details of how
you are mitigating the effects of
infiltration.
The proposed project is residential building and
hence there is no forced ventilation used. The
residential houses provided with adequate
windows which is almost in open condition for
free movement of fresh air inside the buildings.
9.13 To what extent the non-conventional
energy technologies are utilized in
the overall energy consumption?
Provide details of the renewable
energy technologies used.
Solar powered street lighting will be partly
provided. The layout of streets & buildings will
maximize the potential for solar energy devices.
“I hereby undertake that the data and the information given in the application and enclosures
are true to the best of my knowledge and belief and I am aware that if any part of the data and
information submitted is found to be false or misleading at any stage, the project will be
rejected and clearance given, if any, to the project will be revoked at our risk and cost.”
Date: Signature of the Applicant
Place: [ ]
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 57
CHAPTER –1
1.0 Introduction
1.1 GENERAL
M/s. Anandram Developers Pvt. Ltd., proposes to construct its Hyper mall
complex in town survey no. 8/1 (PART), 8/2 to 8/30, 8/33, 13, 14, 15 of
Saligramam village, Mambalam Taluk, Chennai district in the state of Tamil
Nadu. Total land area available is 18,149.26 Sq.m. The total built-up area is
88,779.20 Sq.m. M/s. Anandram Developers Pvt. Ltd have engaged us for
preparing the Environmental Management Plan (EMP) for their proposed
construction of hyper mall, to obtain Environmental Clearance from the State
Environment Impact Assessment Authority (SEIAA).
As per EIA notification, 2006, any new or modernization building and
construction project with built-up area more than 20,000 sq m and less than
1,50,000 sq m falls under activity 8 a and category B and thus requires to
obtain environment clearance from State Environment Impact Assessment
Authority (SEIAA) prior to the start of construction.
1.2 SITE DESCRITPION
The project site is located 13°2'47.03"N latitude and 80°12'10.08"E
longitude. The site is located at town survey no. 8/1 (PART), 8/2 to 8/30, 8/33,
13, 14, 15 of Saligramam village, Mambalam taluk, Chennai district in the state
of Tamil Nadu.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 58
Table 1: Details of Environmental Settings
1.2.1 Topography of the site:
Site is located abutting the Arcot Road and Dr. Banumathi Ramakrishnan
Road connecting Vadapalani to Porur. Nearest Highway is SH 113 (Arcot
Road). Site lies at 0.70 km (South) from KK Nagar; 0.3 km (East) from
Kannika Puram; 0.7 km (West) from Navarathna Colony and 1.0 km
(North) from Saligramam.
Sensitive areas around site: Ramapuram Eri (2.6 km, SW), Coovum river
(1.6 km, North) and Porur lake (6 km, NW).
1.2.2 Site connectivity:
The project site is well connected by road, rail and air ways. The
proposed project is located abutting SH113- Arcot road
The nearest railway station at proximity of the project site is Vadapalani
Metro railway station which is located at 1.1 km distance in North
Eastern direction and Chennai International Airport is at 7.1 km distance
in South west direction to the site.
S.
No. Particulars Details
1. Latitude 13° 2'47.03"N
2. Longitude 80°12'10.08"E
3. Total Plot Area 18,149.26 Sq.m
4. Nearest Highway SH 113 – Arcot Road
5. Nearest Railway Station Vadapalani Metro Rail Station ( 1.0 km, NE)
6. Nearest Airport Chennai International airport (7.1 km, SW)
7. Nearest Town Valasaravakkam (2.8 km, W)
8. Nearest City Chennai (8.28 km, NE)
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 59
Fig. 1: Topography of the site
1.3 PROJECT COMPONENTS
The proposal involves construction of Hyper mall/ Food Court/ Multiplex/
Hotels/ Restaurants/ Shops/ Commercial Units with a total built up area of
88,779.20 Sq.m. The area split up and space utilization details are given below,
the project consists of main building with Basement + Ground + 12 floors, a
multi-level car park (MLCP) with Ground + 16 levels and a sub-station of
Basement+G+2. Detailed area break up is given in below Table 2.
Table 2: Land Use Break up Details
S. No Details Area (Sqm)
1. Total Land Area 18149.26
2. Total Ground Coverage Area of Buildings (40.89%) 7421.55
3. Roads and Pavements Area (19.2%) 3488.34
ARCOT ROAD
Velayutham colony
Kannika Puram
Kamaraj Nagar
Project Site
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 60
4. Surface or open Parking Area (13.06%) 2370.10
5. STP, Solid Waste Disposal and Other Utilities Area
(0.01%) 256.00
6. Greenbelt development Area (15.39%) 2793.27
7. OSR Area (10.03%) 1820.00
8. Total Builtup area 88779.20
1.3.1 Total Built up Area and Details on Housing Units:
Built up area is calculated as per the latest Circular of MoEF, Dated: 2nd
April, 2012. Built-up area is defined as ''The built-up or covered area on all the
floors put together including basement(s) and other service areas, which are
proposed in the building / construction project" as per the latest Circular of
MoEF, Dated: 2nd
April, 2012. Detailed built-up area calculations are given
below.
Table 3: Built up Area Statement
Name of the
Block/Building
Built-up
Area
(FSI
Area)
Sqm
Built-up
Area
Non FSI
Area
Sqm (stilts)
Built-up Area
Parking Area
& Others if any
(Covered Built
Up Area)
Total Built
Up Area
List of Activities
Involved
Main Building
Basement Floor - 143.94 6722.93 6866.87 Parking
Ground Floor 4921.31 93.32 - 5014.63 Hyper market/
Shops &
showroom
1st Floor 4906.50 149.69 - 5056.19
2nd
Floor 4535.75 192.61 - 4728.36
3rd
Floor 4491.08 192.61 - 4683.69
4th
Floor 4831.23 54.62 - 4885.85 Food Court &
fun centre
5th
Floor 2851.42 610.76 - 3462.18 Theatre/
showroom
6th
Floor 1031.00 701.64 - 1732.64 Theatre/ Bar
7th
Floor 4408.22 433.02 - 4841.24 Theatre/ Bar/
Hotel rooms
8th
Floor 1289.87 1606.07 - 2895.94 Bar, services &
Hotel rooms
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 61
9th
Floor 3023.64 175.34 - 3198.98
Longue Bar/
Restaurant/ Hotel
rooms/ Business
centre
10th
Floor 3281.50 285.65 - 3567.15 Banquet hall/
Hotel rooms
11th
Floor 2917.01 283.57 - 3200.58
Gym/ Hotel
room/ Banquet
Hall
12th
Floor 2865.68 140.37 - 3006.05 Hotel rooms/
Business Centre
TOTAL 45354.21 5063.21 6722.93 57140.35 Mall building
Multi Level Car Parking
Ground Level - - 1788.85 Parking
Level 1 - - 1788.85 Parking
Level 2 - - 1788.85 Parking
Level 3 - - 1788.85 Parking
Level 4 - - 1788.85 Parking
Level 5 - - 1788.85 Parking
Level 6 - - 1788.85 Parking
Level 7 - - 1788.85 Parking
Level 8 - - 1788.85 Parking
Level 9 - - 1788.85 Parking
Level 10 - - 1788.85 Parking
Level 11 - - 1788.85 Parking
Level 12 - - 1788.85 Parking
Level 13 - - 1788.85 Parking
Level 14 - - 1788.85 Parking
Level 15 - - 1788.85 Parking
Terrace - 353.19 - 353.19 Swimming pool
& services
Total - 353.19 28621.6 28974.79
Sub-Station Block
Basement Floor 772.71 772.71 Parking
Ground Floor 618.07 - 618.07 DG & MV Panel
First Floor 618.07 618.07 Parking
Second Floor 618.07 - 618.07 Chiller
Terrace 37.14 - 37.14 Head Room
Total - 1273.28 1390.28 2664.06 -
Total Built up
area 88779.2
-
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 62
Table 4: Overall Built up Area Statement
FSI (Sqm)
Non FSI
(Sqm) Parking (Sqm)
Total Built Up
Area (Sqm)
Main Building
(Mall)
45354.21 5063.21 6722.93 57140.35
Multi Level Car
Parking
- 353.19 28621.6 28974.79
Sub-Station block - 1273.28 1390.78 2664.06
Total 45354.21 6689.68 36735.31 88779.2
1.4 VEHICLE PARKING FACILITIES
Parking will be provided as per the building bye laws of CMDA. Details
of parking required and to be provided is given below in Table 5.
Table 5: Parking Provided
S. No Details No. of Car
parks
No of two
wheeler
parks
Area allotted
for parking in
(Sqm)
1. Total number of Parks in Basement 137 398 6722.39
2. Total number of parks in MLCP 560 27 28621.6
3. Total Number of parks in Substation 262 1390.78
4. Total number of parks in Ground level
(Surface parking) 99 407 2370.1
5. Total number of Parking provided 796 1094 39104.87
6. No. of parks required 716 737 -
(Note: One car Parking is equal to two 2- wheeler parking.)
1.5 POWER REQUIREMENT
The estimated power requirement during operation is about 6140 KVA
and it will be sourced from the nearby TNEB grid. DG set of 3 x 2000 KVA &
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 63
1 x 1500 KVA capacity will be provided to cater essential load requirement
during power failure.
The stack height for the DG sets are calculated based on the CPCB
guidelines as shown below;
Stack Height Design Calculation for 2000 KVA
H = h + (0.2) (kVA) 0.5
= 51.88 + 0.2 (2000) 0.5
= 51.88 + 8.9
= 60.8 ~ 61 m.
Where, H = Total height of stack in meters from ground level
h = Height of the building in meters
The stack height required as per CPCB norms is 61 m for 3 D.G Sets of
capacity 2000 KVA.
Stack Height Design Calculation for 1500 KVA
H = h + (0.2) (kVA) 0.5
= 51.88 + 0.2 (1500) 0.5
= 51.88 + 7.7
= 59.6 ~ 60 m.
Where, H = Total height of stack in meters from ground level
h = Height of the building in meters
The stack height required as per CPCB norms is 60 m for D.G sets of
capacity 1500 KVA.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 64
1.6 BASELINE ENVIRONMENTAL STATUS
Baseline studies are carried out to provide a detailed description of the
existing ecosystem, landscape, infrastructure, cultural heritage and urban
environment. A baseline study describes the initial state of the environment
within the selected boundaries of the study area. The baseline data has been
generated and the secondary data was collected from various Government and
Semi-Government organizations. The details about the existing environmental
values are projected based on the volume of the assessment accomplished
during the period. The various environmental attributes were divided into
primary and secondary studies. Primary attributes such as air environment,
water, soil, noise & biodiversity environment were being assessed by
conducting field studies, on-site monitoring. The baseline studies started with
site visits and survey in the study area for fixing the monitoring locations for
the primary data generation. The baseline environmental data for ambient Air,
Noise, Soil and Ground water is enclosed in Annexure XI. The brief on the
study of bio-diversity is summarized below.
1.6.1 Biodiversity Study
a. Methodology
The ecological status of the study area has been assessed based on the following
methodology:
Primary field surveys to establish primary baseline of the study area
Compilation of information available in published literatures and as
obtained from Forest survey of India, Botanical Survey of India and
Zoological Survey of India.
The flora and fauna studies were carried out within 1 km radius around the
proposed construction site.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 65
b. Flora
The Study of flora involved intensive sample survey of vegetation in the project
site and other locations applying standard methods. To examine the trees and
shrubs, quadrants of 25 x 25 m and for herbs 2 x 2 m were laid. In each of the
larger quadrants (i) Species (ii) their number, and (iii) Girth at Breast Height
(GBH), were measured. (Chaturvedi and Khanna, 1982).
Abundance, relative abundance, density and relative density of each species
diversity and evenness for each of the Zones were calculated using the numerical
data (Ludwig and Reynolds 1988, Lande 1996, Smith and Wilson 1996). The
standard statistical analysis, the normal frequency diagram and distribution of
plants in the study area were analyzed using the procedures of Raunkiaer, 1934.
The analysis carried out as per Raunkiaer’s law of frequency classes provides the
information on the Heterogeneity and Homogeneity of plants and its pattern of
distribution in the study area. The species of vegetation found in each station were
identified and listed according to their families, both in dicotyledons and
monocotyledons of the plant kingdom. The plant species were classified as per the
classifications of “Bentham and Hooker” and identified by using Gambles book on
“Flora of Madras Presidency” and Mathew’s book on “Flora of the Tamil Nadu
Carnatic”.
c. Fauna
Both direct and indirect observation methods were used to survey the fauna.
Visual encounter (search) method was employed to record vertebrate species.
Additionally survey of relevant literature was also done to consolidate the list of
vertebrate fauna distributed in the area (Smith 1933-43, Ali and Ripley 1983,
Daniel 1983, Prater 1993, Murthy and Chandrasekhar 1988). Since birds may be
considered as indicators for monitoring and understanding human impacts on
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 66
ecological systems (Lawton 1996) attempt was made to gather quantitative data on
the group by.
Point Survey Method: Observations were made in each site for 15 minutes
duration.
Road Side Counts: The observer traveled by motor vehicles from site to site,
all sightings were recorded (this was done both in the day and night time). An
index of abundance of each species was also established.
Pellet and Track Counts: All possible animal tracks and pellets were
identified and recorded (South Wood, 1978).
Based on the Wildlife Protection Act, 1972 (WPA 1972, Anonymous.
1991, Upadhyay 1995, Chaturvedi and Chaturvedi 1996) species were short-listed
as Schedule II or I and considered herein as endangered species. Species listed in
Ghosh (1994) are considered as Indian Red List species.
Pellet and Track counts method was adopted for this development project
and the assessment results are discussed in Chapter-3.
1.7 ENVIRONMENTAL COMPONENTS
The baseline environmental studies helped in assessing the existing
environmental conditions of the study area and identifying the critical
environmental attributes. This will facilitate the comparison of the resultant
environmental conditions in the post study scenario with the pre- study
conditions and will help in checking the environmental pollution.
1.8 WATER REQUIREMENT
The total water requirement during operation is 438 KLD. Source of water
is CMWSSB. The wastewater generation from the project is estimated to be
about 299 KLD, which will be treated in proposed sewage treatment plant of
320 KLD capacity and will be recycled for flushing, gardening and remaining
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 67
excess treated sewage will be disposed to CMWSSSB sewer line and the water
balance chart is shown in Table 6, 7 and 8.
Table 6: Occupancy Load Calculation
S.No. Description Capacity Occupancy Load (Nos.)
A) Theatres
Total No. of seats considered 2121 8484
Total No. of shows 4
Total Number of staffs 10% of the seats 848
B) Hypermarket, Fun centre, Show rooms/ big bazaar
Total Area Considered 17317.41 2886
Area considered / person 6 Sqm
Total number of staffs 10% of the population 289
C) Food Court
Total Area considered 4163.48 1388
Area considered / person 3 Sqm
Total number of staffs 10% of the population 139
D) HOTEL- GUEST ROOM
No. of rooms- 234 468
Beds/room 2
No. of staff 10% of the population 47
E) Restaurant / Longue bar
Total area 415.56 139
No. of person /turn over 3 Sqm
No. of staff 10% of the population 14
f) Banquet hall
Total area 291.73 195
Area/person 1.5 Sqm
No. of staff 10% of the population 20
G) Business Centre/ Gym
Total area 210.46 70
Area / person 3 Sqm
No. of staff 10% of the population 7
Total Occupancy Load 14994
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 68
Table 7: Water Requirement Calculation
S.
No. Description Capacity
Basis
(lpcd)
Water Requirement (LPD)
Domestic
(LPD)
Flushing
(LPD)
Total
(LPD)
A) Theatres
No. of Persons 8484 5 16968 25452 42420
(2 lpcd) (3 lpcd) (5 lpcd)
No. of Staffs 848 45 12720 25440 38160
(15 lpcd) (30 lpcd) (45 lpcd)
Total 9332 52 29688 50892 80580
B) Hypermarket, Fun Centre, Show rooms/big bazaar
No. of Persons 2886 5
5772 8658 14430
(2 lpcd) (3 lpcd) (5 lpcd)
No. of Staffs 289 45
4335 8670 13005
(15 lpcd) (30 lpcd) (45 lpcd)
Total 3175 60 10107 17328 27435
C) Food Court
No. of Persons 1388 70 55520 41640 97160
(40 lpcd) (30 lpcd) (70lpcd)
No. of Staffs 139 45 2085 4170 6255
(15 lpcd) (30 lpcd) (45 lpcd)
Total 1527 60 57605 45810 103415
D) Hotel Room
No. of beds 468 180 42120 42120 84240
(90 lpcd) (90 lpcd) (180lpcd)
No. of Staffs 47 45 1410 705 2115
(30 lpcd) (15 lpcd) (45 lpcd)
Total 1030 225 43530 42825 86355
E) Restaurant / Longue Bar
No. of Persons 139 70 5660 4170 9730
(40 lpcd) (30 lpcd) (70 lpcd)
No. of Staffs 14 45 210 420 630
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 69
(15 lpcd) (30 lpcd) (45 lpcd)
Total 153 115 5870 4590 10360
F) Banquet hall
No. of Persons 195 15 975 1950 2925
(5 lpcd) (10 lpcd) (15 lpcd)
No. of Staffs 20 45 300 600 900
(15 lpcd) (30 lpcd) (45 lpcd)
Total 215 30 1275 2550 3825
G) Business Centre / Gym
No. of Persons 70 15 350 700 1050
(5 lpcd) (10 lpcd) (15 lpcd)
No. of Staffs 7 45 105 210 315
(15 lpcd) (30 lpcd) (45 lpcd)
Total 77 60 455 910 1365
Table 8: Water Requirement Summary
S.No. Description
Water Requirement (LPD)
Domestic
(LPD)
Flushing
(LPD)
Total
(LPD)
1. Mall, 148530 164905 313335
2. Water requirement for Gardening purposes based on the
Gardening area (2915.43 Sqm (@ 3.5 litres/Sqm) 10204
3. Water requirement for HVAC 103000
4. Swimming Pool requirement 11000
Total water requirement 437539
Water Requirement Summary:
Total Water Requirement = 438 KLD
Fresh water requirement for domestic purposes = 149KLD
Treated water requirement for Flushing purposes = 165 KLD
Treated water requirement for Gardening purposes = 10 KLD
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 70
Swimming pool water requirement = 11 KLD
HVAC cooling water requirement = 103 KLD
HVAC Cooling Water Requirement:
Total Cooling tower capacity: 1030 TR
1030 TR: water cooled
1030 TR x 12.5 liters x 8 hours = 103000Say 103 KLD
Fig. 2: Water Balance Chart
Sewage Treatment Plant 320 KLD
Gardening 10KLD
Treated Water 284 KLD (95%)
134 KLD (90%)
Domestic 149 KLD
Flushing 165 KLD 727253KLD
Daily Fresh Water Requirement 160 KLD
Treated water 284 KLD
Z
OSR maintenance 6 KLD
215 KLD
165 KLD (100%) 299 KLD
Swimming Pool 11 KLD
HVAC 103 KLD
Total water requirement 438 KLD
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 71
1.9 SOLID WASTE GENERATION
The solid waste from the proposed development will comprise of
compostable wastes like domestic food waste, horticultural waste and
recyclable waste like plastics, paper etc. As per the manual on municipal solid
waste prescribed by Central Public Health and Environmental Engineering
Organization (CPHEEO), the quantity of solid waste generated varies between
0.2-0.6 kg / capita / day. Quantity of solid waste generated from the proposed
commercial building is given below in Table9.
Table 9: Quantity of solid waste generated
S.No. Description Occupancy
Per capita
waste
generation
Solid waste Generation (kg/day)
Bio
(kg/day)
Non - Bio
(kg/day)
Total
(kg/day)
A) Theatres 9332 0.2 1120 747 1867
B)
Hypermarket, Fun
Centre, Show
rooms/big bazaar
3175 0.2 380 255 635
C) Food Court 1527 0.6 4581 458 5039
D) Hotel Room 1030 0.6 361 258 619
E) Restaurant/
Longue Bar 153 0.6 54 38 92
F) Banquet Hall 215 0.6 75 54 129
G) Business Centre/
Gym 77 0.2 8 6 14
H) Total 15,509 - 6579 1816 8395
STP Sludge 45 kg/day
Source: Central Public Health and Environmental Engineering Organization
(CPHEEO),
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 72
Per capita waste generation for restaurants is 0.6 kg / capita / day and for other
working population is 0.2 kg/day.
Table 10: Waste Composition
S.No Description Quantity
(Tons/day) Mode of treatment / disposal
1.
Biodegradable
Waste (@60% of
waste generated)
6.6
Will be treated in organic waste
convertor within the project site.
Manure generated will be used for
landscaping purpose within project
site.
2.
Non-
Biodegradable
waste (@40% of
waste generated
1.8 Waste will be sold to recyclers
3. STP Sludge 45 kg/day Will be used as a Manure for
greenbelt development
Wastes generated from the households will be segregated into
compostable waste, recyclable and inert waste in the source itself (by the
occupants) in separate bins. Door to door waste collection system will be
adopted. Compostable waste will be treated in organic waste convertor within
the site. Manure generated will be used within the site for landscaping purpose.
Recyclable fraction of waste will be sold to authorized vendors and inert waste
will be send for land filling through authorized agency for waste collection in
the area. Organic waste convertor of various makes like Excel, Nachiket
Engineering, Earth Care equipments are available. These OWC reduce volume
of waste fed by 80% and convert it into manure that can be used for
landscaping purpose. This manure can be stored, packed, sold and used for
landscaping.
Apart from the municipal waste, E-waste comprising of rejected CFL,
bulbs, laptops, TV sets, computers etc will be generated. This waste will be
insignificant in initial stage. Room will be provided within project site for
storing discarded electronics. This will be sold to authorized vendors on regular
basis.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 73
CHAPTER – 2
2.0 ENVIRONMENTAL IMPACT ASSESSEMNT
2.1 INTRODUCTION
This chapter presents the assessment of various impacts due to the
proposed construction project in the study area. Generally, the environmental
impacts can be categorized as either primary or secondary. Primary impacts
are those, which are attributed directly by the project and secondary impacts are
those, which are indirectly induced and typically include the changed patterns
of social and economic activities by the proposed project. The Proposed
construction project would create impact on the environment in two distinct
phases:
Impacts during the construction phase
Impacts during the operation phase
The construction and operational phase of the proposed construction
project comprises of various activities each of which will have impact on some
or other environmental parameters. Various impacts during the construction or
operational phase and the environmental parameters have been studied to
estimate the impacts on environment. The identification and details on impact
of the project activity on each of the above environmental attributes are
discussed below.
2.2 IDENTIFICATION OF IMPACTS
Construction of commercial complex is for the benefit of general
population, however, like any other projects, it also has impacts on existing
Environmental settings and if not properly evaluated and controlled, it may lead
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 74
to imbalances. These impacts could be reversible, irreversible, temporary or
permanent.
The identification of impacts is important as it leads to the other elements
such as quantification and evaluation of impacts. Although a number of non-
projects related impacts have been identified while describing the existing
(baseline) environmental status, it is necessary at this stage to identify the types
of the potential impacts which might be caused by the proposed development.
Many techniques are available for identification of impacts. In case of this
project, the "Matrix Method" was adopted, which involves an understanding of
the cause-condition-effect relationship between an activity and environmental
parameters. It is very useful as gross screening tool for impact identification
method. This method has been basically advantageous in recognizing the series
of impacts that could follow from the proposed activities.
The idea was to account for the project activity and identify the types of
impacts that could initially occur. This process was repeated until all possible
types of impacts were identified. With this method the potential impact of the
proposed project has been identified.
Table 11: Overview of potential impacts due to the proposed
commercial complex project
Project activities
Air
qu
ali
ty
No
ise L
evel
Gro
un
d W
ate
r
Qu
ali
ty
Gro
un
d W
ate
r
Qu
an
tity
So
il S
tab
ilit
y/
Ero
sio
n
So
il Q
uali
ty
Tra
ffic
Lev
el
Veg
etati
on
So
cio
Eco
no
mic
Construction Phase
Site Clearance
&Leveling ST,
-ve
ST,
-ve
ST,
-ve
ST,
+ve
Site excavation ST,
-ve
ST, -
ve
ST,
-ve
ST,
+ve
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 75
Foundation
(Pile Foundation)
ST,
-ve
ST,
+ve
Material Storage &
Handling
ST,
-ve
ST,
-ve
Generation and
disposal of
construction waste
ST,
-ve
ST,
-ve
Movement of
Vehicles
ST,
-ve
ST,
-ve ST, -ve ST, -ve
Labour’s Camp
ST,
-ve
Operation Phase
Occupancy
LT,
-ve
LT, -
ve
LT,
+ve
Operation of DG
Sets -ve -ve -ve
Sewage Generation
& Discharge
LT,
-ve
LT,
-ve LT, -ve
Rainwater
Harvesting
LT,
+ve
LT,
+ve
Solid waste
Generation
LT,
-ve
Gardening &
Landscaping
LT,
+ve
LT,
+ve
LT,
+ve
LT,
+ve
LT,
+ve
LT,
+ve
Note: ST - Short Term Impact, LT - Long Term Impact, -ve - Negative Impact,
+ve – Positive Impact
2.3 IMPACT EVALUATION
Impact evaluation assesses the expected changes in the environment due
to the proposed project. It is the tool for identifying the magnitude of impact
and forms basis for the development of Environmental Management Plan.
Weight age for each impact is given below. Evaluation of impacts considering
both positive and negative effects on air, noise, land, water and socioeconomic
environment during the construction and operation phase of the project is given
in Table 11 and 12 respectively.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 76
TABLE 12: EVALUATION OF CONSTRUCTION PHASE IMPACT
Environmen
tal
Parameter
Project
Activities
Impact
Type
Sig
nif
ican
t
No
n
Sig
nif
ican
t
Dir
ect
Ind
irec
t
Sh
ort
Ter
m
Lo
ng
Ter
m
Un
avo
idab
le
Irre
ver
sib
l
e M
itig
atio
n
Req
uir
ed
Weigh
tage
CONSTRUCTION PHASE
AIR
ENVIRON
MENT
Site
Clearance
&Levelling
Negative √ √ √ √ √ -4
Site
excavation
Negativ
e √ √ √ √ √ -4
Foundation
(Shallow
Foundation)
Negativ
e √ √ √ √ 0
Material
Storage &
Handling
Negativ
e √ √ √ √ √ -4
Generation
and disposal
of
construction
waste
Negativ
e √ √ √ -4
Vehicular
Movement
Negativ
e √ √ √ -4
Labour’s
Camp
No
Impact -
Public
Health &
Safety
No
Impact -
Economic
Activity
No
Impact -
NOISE
ENVIRON
MENT
Site
Clearance
&Leveling
Negativ
e √ √ √ 0
Site
excavation
Negativ
e √ √ √ -4
Foundation
(Shallow
Foundation)
Negativ
e √ √ √ √ -4
Material
Storage &
Handling
Negativ
e √ √ -1
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 77
Generation
and disposal
of
construction
waste
No
Impact -
Vehicular
Movement
Negativ
e √ √ √ -1
Labour’s
Camp
No
Impact -
Public
Health &
Safety
No
Impact -
Economic
Activity
No
Impact -
LAND
ENVIRON
MENT
Site
Clearance
&Leveling
No
Impact -
Site
excavation No Impact -
Foundation
(Shallow
Foundation)
Negativ
e √ √ -1
Material
Storage &
Handling
Negativ
e √ √ √ √ -4
Generation
and disposal
of
construction
waste
Negativ
e √ √ -4
Vehicular
Movement
Negativ
e √ √ √ -1
Labour’s
Camp
No
Impact -
Public
Health &
Safety
No
Impact -
Economic
Activity
No
Impact -
WATER
ENVIRON
MENT
Site
Clearance
&Leveling
Negativ
e √ √ √ -2
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 78
Site
excavation
No
Impact -
Foundation
(Shallow
Foundation)
No
Impact -
Material
Storage &
Handling
Negativ
e √ √ √ √ -4
Generation
and disposal
of
construction
waste
Negativ
e √ √ √ √ -4
Vehicular
Movement
Negativ
e √ √ 0
Labour’s
Camp
Negativ
e √ √ √ √ -4
Public
Health &
Safety
No
Impact -
Economic
Activity
No
Impact -
SOCIO
ECONOMI
C
ENVIRON
MENT
Site
Clearance
&Leveling
Negativ
e √ √ √ √ -2
Site
excavation
Negativ
e √ √ √ √ -2
Foundation
(Shallow
Foundation)
Negativ
e √ √ √ √ -2
Material
Storage &
Handling
Negativ
e √ √ √ 0
Generation
and disposal
of
construction
waste
Negativ
e √ √ √ √ -2
Vehicular
Movement
Negativ
e √ √ √ √ -2
Labour’s
Camp
Negativ
e √ √ √ √ -2
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 79
Public
Health &
Safety
Positive √ √ √ 6
Economic
Activity Positive √ √ √ 6
TABLE 13: EVALUATION OF OPERATION PHASE IMPACT
Environ
mental
Paramet
er
Project
Activities
Impact
Type
Sign
ific
ant
No
n
Sign
ific
ant
Dir
ect
Ind
irec
t
Sho
rt T
erm
Lo
ng
Ter
m
Un
avo
idab
l
e
Irre
ver
sib
le
Mit
igat
ion
Req
uir
ed
Weig
htag
e
OPERATION PHASE
AIR
ENVIRO
NMENT
Occupancy No
Impact -
Operation of
DG Sets
Negati
ve √ √ √ √ -8
Sewage
Generation &
Discharge
Negati
ve √ √ 0
Rainwater
Harvesting
No
Impact -
Solid waste
Generation
Negati
ve √ √ √ -6
Gardening &
Landscaping
Positiv
e √ √ √ 10
NOISE
ENVIRO
NMENT
Occupancy No
Impact -
Operation of
DG Sets
Negati
ve √ √ √ √ -8
Sewage
Generation &
Discharge
No
Impact --
Rainwater
Harvesting
No
Impact -
Solid waste
Generation
No
Impact -
Gardening &
Landscaping
Positiv
e √ √ √ 10
LAND
ENVIRO
Occupancy Negati
ve √ √ 0
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 80
NMENT Operation of
DG Sets
Negati
ve √ √ √ 0
Sewage
Generation &
Discharge
Negati
ve √ √ √ √ -8
Rainwater
Harvesting
Positiv
e √ √ √ 8
Solid waste
Generation
Negati
ve √ √ √ √ -8
Gardening &
Landscaping
Positiv
e √ √ √ 10
WATER
ENVIRO
NMENT
Occupancy Negati
ve √ √ √ √ -8
Operation of
DG Sets
Negati
ve √ √ √ √ -6
Sewage
Generation &
Discharge
Negati
ve √ √ √ √ √ -8
Rainwater
Harvesting
Positiv
e √ √ √ 10
Solid waste
Generation
Negati
ve √ √ 0
Gardening &
Landscaping
Positiv
e √ √ √ 10
SOCIO
ECONOM
IC
ENVIRO
NMENT
Occupancy Positiv
e √ √ √ 10
Operation of
DG Sets
Negati
ve √ √ √ √ -6
Sewage
Generation &
Discharge
Negati
ve √ √ √ √ -6
Rainwater
Harvesting
Positiv
e √ √ √ 8
Solid waste
Generation
Negati
ve √ √ √ -6
Gardening &
Landscaping
Positiv
e √ √ √ 8
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 81
2.4 IMPACT ON AIR ENVIRONMENT
2.4.1 Construction Phase
Impacts of construction activities on air quality are cause for concern
mainly in the dry months due to dust particles. The main sources of emission
during the construction period are the movement of equipment at site and dust
emitted during the leveling, grading, earthworks, and other construction related
activities. The dust emitted during the above mentioned activities depend upon
the type of soil being excavated. Existing baseline parameters values are SOx-
9.4 µg/m3, NOx- 19.4 µg/m
3 and SPM- 49.6 µg/m
3. An average of 20-30 %
incremental pollution during construction for air parameters will be envisaged.
However, the impact will be for short duration and confined locally to the
construction site. The composition of dust in this kind of operation is, however,
mostly inorganic and non-toxic in nature.
The impact of such activities would be temporary and restricted to the
construction phase. The impact will be confined within the project boundary
and is expected to be negligible outside the plant boundaries. Proper upkeep
and maintenance of vehicles, sprinkling of water on roads and construction site
are some of the measures that would greatly reduce the impacts during the
construction phase. Thus, it is inferred that no significant impacts are expected
on the overall ambient air quality due to the proposed construction activities.
Transportation of heavy machinery and building materials implies heavy
traffic on the roads leading to the site with possible negative impacts to the
surrounding area (dust, spillage, emissions and noise). Transportation of
construction materials as well as improper storage of building materials,
especially gravel, sand and cement in the construction site will lead to
inadvertent dispersal of materials during heavy rain or high wind during dry
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 82
periods. Measures will be adopted for proper handling of construction
materials to reduce the negative impact.
2.4.2 Operation Phase
Ambient air quality at the proposed project site and its surroundings is
monitored and values of the pollutants RPM, PM2.5, NOx and SO2 are within the
limits of NAAQS, 2009 prescribed by the central pollution control board.
There is no major pollutant envisaged from the proposed development. It
is likely that the air quality may be affected slightly due to the emissions from
the vehicular movement. The emission from DG sets will be very negligible
since it will be used only during power cut in the necessary area. However in
the case of DG sets the stack will be properly designed to meet the stipulations
of CPCB. These emissions will be insignificant and the environmental pollutant
levels will be maintained within the prescribed limits. Hence there shall not be
any adverse impact on the air environment around the proposed commercial
complex.
2.5 IMPACT ON AMBIENT NOISE
2.5.1 Construction Phase
During the construction noise levels will increase due to use of machinery
and heavy vehicles in the project area. In terms of noise emission; demolition,
excavation and construction work can be divided into two phases, namely (1)
Demolition and Earthworks and (2) building works. Loading and unloading of
construction materials, fabrication, handling of equipment and material,
operation of power shovels etc. will be the major source of noise during the
construction phase. Various construction activities will cause short-term noise
impact in the immediate vicinity of the project site.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 83
The areas affected are those close to the site and hence the impacts are
localized. At the peak of the construction, marginal increase in noise levels is
expected to occur. The peak noise levels from continuous construction activity
may be as high as 80 - 90 dB (A). The noise control measures during
construction phase shall restrict the noise levels to lower levels. Hence the
overall impact on the ambient noise levels will not be significant.
2.5.2 Operation Phase
There will not be any major impact from noise. This is because no
equipment or other infrastructure facility in the project generates noise more
than 50-60 dB (A). However, the only noise generation source is the DG set.
The promoters have decided to adopt adequate steps to maintain the noise
levels within the prescribed limits. For the same all the DG facility will be
equipped with acoustic enclosure. Apart from this honking will be prohibited at
the site and speed limits will be restricted within the site. This will significantly
help in controlling noise levels at the site. Further the green belt provided
within the site will act as noise barrier between inside and outside environment.
This will act as buffer and protects the site from high noise levels outside the
site.
Traffic will increase during both construction and operation phase of the
project. Vehicles associated with construction would generate intermittent
noise throughout the vicinity of the proposed action. In the operation phase,
vehicular parking is being provided in the basement, ground floor and first
floor of the building where noise levels are expected to increase substantially
during the peak hours due to starting, idling and roaring of vehicles.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 84
2.6 IMPACT ON LAND ENVIRONMENT
No blasting will be done during construction phase of the project. The
rehabilitation and resettlement issues are not involved in the project.
Furthermore the existing environmental conditions of the project site reveal that
the land is not contaminated or polluted.
Top soil will be excavated up to 15 cm from the project site. It will be
stored in covered area during construction phase and will be used for
landscaping in operation phase within project site. The upper/top level of soil
will be affected during construction phase but this will be limited to a portion
of the project area. Also the impact due to exploitation of ground water is
insignificant in the site due to the sourcing of water from other sources during
the operation phases.
2.7 IMPACT ON WATER RESOURCES
2.7.1 Construction Phase
The required water quantity for construction will be utilized from the
available resource in the project area. Impact on water quality during
construction phase may be due to non-point discharges of sewage generated
from the construction work force, stationed at the site. Construction activities
for the proposed development can have minor impact on hydrology
and ground water quality of the area if the construction waste leaches into
ground.
Potential sources of impacts on the hydrology and ground water quality
during the construction phase would be soil runoff, improper disposal of
construction debris, spillage of oil and grease from the vehicles and wastewater
stream generated from on-site activities such as vehicles washing, workshop
etc. Precautions and preventive measure will be taken at the site during
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 85
construction to avoid any ground and surface water contamination hence the
overall impact on water environment during construction phase due to proposed
project is likely to be insignificant.
2.7.2 Operation Phase
The total quantity of wastewater generation is likely to be 299 KLD which
will be treated in proposed sewage treatment plant of 320 KLD capacities and
will be recycled for flushing, gardening, OSR and remaining excess treated
sewage will be disposed to CMWSSB.
2.8 IMPACTS DUE TO WASTE DISPOSAL
2.8.1 Stacking and Disposal of Construction Materials
Stacking of construction materials will be confined to the project site only
and also temporary sheds will be provided to store the materials, hence no
impacts on surrounding area will be envisaged. Solid wastes generated due to
proposed project during construction phase include sand, gravel, stone, bricks,
plastic, paper, wood, metal and glass. Recyclables will be sent to authorize
recyclers. Hence there is no significant impact due to waste disposal during the
construction phase.
2.8.2 Operation Phase
The solid waste generated from the project will be collected daily and
moved to a common temporary storage facility by the staff dedicated for waste
collection. The collected Solid waste will be disposed through Organic waste
converter.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 86
2.9 IMPACTS ON ECOLOGICAL RESOURCES
2.9.1 Construction Phase
The impact of construction activities will be primarily confined to the
project site. The project site is a vacant land and devoid of any vegetation. Thus
the site development work will not lead to any significant loss of any important
plant species. Deposition of fugitive dust on leaves of nearby vegetation may
lead to temporary reduction of photosynthesis. Such impacts will, however, be
confined mostly to the initial period of construction phase. Hence the proposed
development will not lead to habitat destruction, fragmentation or vegetation
damage.
2.9.2 Operation Phase
No wastewater will be discharge into the surface water stream. Hence,
there will not be any impact on the aquatic ecology. Also the proposed project
is to be located in an earmarked commercial zone, which does not have any
natural park or sanctuary or forest area in the immediate vicinity. The flora and
fauna pattern in the area will not be disturbed due to the project. Hence the
overall impact on ecological resources due to proposed project is likely to be
insignificant. Moreover the entire project area would be landscaped with
variety of plants.
2.10 IMPACT ON TRAFFIC LEVELS
2.10.1 Construction Phase
The movement of construction equipments will be mostly within the site
during the project. Vehicles bringing in raw materials like sand, cement and
aggregate materials will be moving into the site from outside, which will be
strictly controlled and monitored as per the traffic rules, to avoid any sort of
disturbance to the traffic and safety of the surrounding areas. Hence the impact
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 87
due to the vehicular movement during the construction phase would be minor
or insignificant.
2.10.2 Operation Phase
Based on the vehicular density observed during the traffic survey
conducted on the main roads around the proposed site, the existing
infrastructure is capable of taking up additional traffic loads. Also the project is
to be executed phase wise; the increase in traffic will be easily handled by the
existing as well as the future improvements in the transportation infrastructure.
Hence there will not be any impact on the traffic pattern and density.
2.11 IMPACTS ON SOCIO ECONOMIC ENVIRONMENT
The required land for the development is owned by M/s. Anandram
Developers Pvt Ltd. The proposed Mall/ Hotel/ Theatre complex will be open
to members of all communities and castes. The above measure will encourage
mixing of different caste people for their respective festivals and occasions.
This will improve the social welfare and brotherhood among the various
communities and castes.
Also the state of the art facilities proposed in the development is planned
to cater the needs of the occupants which would be able to provide healthy
working atmosphere. Hence it is obvious to assume that the activities of the
proposed development will produce some positive impacts in the socio-
economic status of the area.
2.11.1 Public Health and Safety
As the project is only a construction of Mall/ Hotel/ Theatre complex and
all the construction activities are confined to the project site, no health related
impact would be envisaged within the project area. The people engaged in the
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 88
construction activities will be directly exposed to dust generation, which is
likely to cause health related impact. Appropriate mitigation measures like
spraying of water will be adopted to minimize dust emission in the construction
site. Laborers will be provided with suitable Personal Protective Equipment
(PPE) as required under the health and safety norms. Regular health checkups
will be organized.
2.11.2 Positive Impact
The project will facilitate maximum participation of the local work force
for construction process; this will benefit the local economy, improvement in
economic activity and enhancement in earning opportunities for the local
population. The operation of the project and other allied facilities will improve
the employment opportunities. The project will provide direct and indirect
employment. About 100 – 150 persons will be employed during the operation
stage for the purpose of day-to-day maintenance works. The employment will
have positive impact on the local economy thereby increasing the quality of
life. The proposed rain water recharge facility will augment the ground water
level in the project area. The proposed project will also improve the aesthetics
of the area due to the development of modern buildings.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 89
CHAPTER - 3
3.0 ENVIRONMENTAL MANAGEMENT PLAN
3.1 GENERAL
Environmental Management Plan (EMP) is aimed at mitigating the
possible adverse impacts of the project and for ensuring to maintain the
environmental quality. The environmental management plan consists of the set
of mitigation, management, monitoring and institutional measures to be taken to
eliminate the adverse environmental impacts or reduce them to acceptable
levels.
3.2 AIR POLLUTION CONTROL AND MANAGEMENT
3.2.1 Construction Phase
The impacts will be due to the air emissions like particulate matter (PM10&
PM2.5), CO, NOx and SO2 due to material handling, vehicular movements and
other site activities. The particulate matters will be reduced by frequent
sprinkling water on the road surfaces and on other areas where dust is arising
due to material handling. All the equipments and vehicles used in the
construction and transportation of materials will be maintained properly and
only low sulphur diesel will be used as fuel for DG sets and construction
equipment and vehicles.
The emissions from the DG sets will be let out only through the stacks
with adequate heights as per CPCB norms. This will avoid the deposition of the
particulate matters and other pollutants by facilitating the through dispersion of
pollutants into the atmosphere. The stacking of all the construction materials
will be confined only within the proposed site. Vehicles carrying the raw
material and debris will be covered to minimize dust emissions while travelling.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 90
Adequate parking space will be provided for construction vehicle and
machinery to prevent idling and thus will help in minimizing the emissions.
Wheel wash facility will be provided at the exit point of the site.
3.2.2 Operation Phase
Air emissions are observed during the operation phase of the project. The
air emissions will be reduced by ensuring smoother flow of traffic within the
premises by better traffic management plans. It is proposed to have trees all
through the boundaries of the site and along the either side of the internal roads.
This will reduce the particulate matters from being transported to the nearby
areas. The air emissions from the Diesel Generators will be controlled by using
low sulphur content high speed diesels, periodic maintenance of DG sets as per
the defined schedule of manufacturer and by providing adequate stack heights
as prescribed by CPCB. The stack height for the DG sets are calculated based
on the CPCB guidelines as shown below;
The proposed project to have
4 nos. - D.G. Sets of 3 x 2000 KVA Capacity and 1 x 1500 KVA
3.2.3 Air Pollution Control (APC) Measures
The main source of air emissions from the proposed commercial
development is the Generator Sets the above proposed generator sets will be
used only during TNEB power failure. To control the air emissions from these
D.G sets, adequate stack height is provided to release the exhaust flue gases into
the atmosphere at a height at which efficient dispersion takes place. Since the
DG sets are operated only during power failure, the emission is not continuous
and hence the impact due to these emissions is insignificant.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 91
The stack height for the DG sets are calculated based on the CPCB
guidelines as shown below;
Stack Height Design Calculation for 2000 KVA Generator Set
H = h + (0.2) (kVA) 0.5
= 51.88 + 0.2 (2000) 0.5
= 51.88 + 8.94
= 60.82 ~ 61 m
Where, H = Total height of stack in meters from ground level
h = height of the building in meters
The stack height required as per CPCB norms is 61 m which will be provided
for all 3nos. of 2000 KVA DG sets.
Stack Height Design Calculation for 1500 KVA
H = h + (0.2) (kVA) 0.5
= 51.88 + 0.2 (1500) 0.5
= 51.88 + 7.7
= 59.6 ~ 60 m.
Where, H = Total height of stack in meters from ground level
h = Height of the building in meters
The stack height required as per CPCB norms is 60 m for D.G set of capacity
1500 KVA.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 92
3.3 NOISE CONTROL AND MANAGEMENT
3.3.1 Construction Phase
The noise generated from the construction equipments will be reduced
through proper maintenance of all the equipments which are involved in
construction activities, confining the construction activities only during the day
time and providing barricades all around the project area. The adverse impacts
of noise especially on workers will be reduced by providing ear muffs to the
workers in high noise zones. Noise control systems such as equipment
foundation pads, dampeners, silencers and acoustic enclosures will be used for
individual units as per the requirement to minimize the noise & vibration.
3.3.2 Operation Phase
The increase in the ambient noise levels due to the vehicle transportation
will be controlled by the development of the green cover all along the internal
roads and by implementing better traffic management plans inside the site
premises. The better traffic management plans will significantly reduce the
noise generated due to the congestion caused by the movement of vehicles.
The generator noise is controlled by providing acoustic enclosures. Proper
air ventilation system is designed to allow the maximum aspiration and cooling
airflow required so that the engines do not overheat. Axial flow fan of required
size & numbers provided for proper air ventilation. Acoustic louvers, splitter &
insulated ducts are provided to suppress the noise where required.
Also Noise monitoring was done during the study period. The values were
Leq Day: 52.7 dB (A) Leq Night: 36.5 dB (A). The values were within the
limit. Also during operation care will be taken to ensure that there will not be
any incremental load in the environment.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 93
3.4 SOLID WASTE MANAGEMENT
3.4.1 Construction Phase
Separate raw material handling yard will be demarcated. This will prevent
the contamination of the soil due to the spillage of the construction materials.
Cement will be separately stored under cover in bales. The raw material
handling yard will be located within the project site and separated by
enclosures/barricades. This will keep the working area clean and reduce the soil
contamination.
3.4.2 Operation Phase
During the operation phase the used oil from the DG sets will be collected
in separate drums and handed over to the authorized recyclers by TNPCB.
Hazardous Waste: During the operation phase the used oil, DG filters, oil
mixed cotton waste and oil containers from the DG sets will be collected in
separate place.
Table 14: Generation and disposal of Hazardous waste Quantity per annum
S.
No
Waste
category
Description
of waste
Quantity
in
Tonnes/per
annum
Activity/Activities for which
authorization is required
Collection
& Storage
Transport &
Disposal
1 5.1 Used oil
0.4
MS drums
within the
premises
Disposed to
authorized re –
processors
Non- Hazardous Waste:
It is estimated that the municipal solid wastes will be generated in the
following passion:
Biodegradable wastes : 6579 Kg/day
Non-biodegradable wastes : 1816 Kg/day
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 94
In the commercial complex development, Wastes generated from the
households will be segregated into Bio degradable waste and non- bio
degradable waste in the source itself (by the occupants) in separate bins. The
wastes from such bins are collected separately on daily basis and taken to a
separate centralized collection facility by the agency dealing in collection and
disposal of garbage. Appropriate site will be identified for keeping the
biodegradable and Non-biodegradable waste. All the collection bins shall be
properly maintained and cleared on regular basis. The Bio degradable wastes &
inert fractions will be disposed off through the local municipality, and non-bio
degradable recyclable waste will be handed over to authorized recyclers.
Horticulture wastes leaves, grass and vegetative residues shall be collected
at the secured location such that it will not hinder daily activity schedule or
washed away by the surface run-off causing choking of drains, etc. and will be
separately treated and disposed off along with biodegradable waste.STP sludge
will be stabilized, and dewatered for separation of solids, which will be used as
manure in horticulture.
Fig. 3: Solid Waste Management
3.5 WATER AND WASTEWATER MANAGEMENT
3.5.1 Construction Phase
The wastewater generated by the construction workers will be treated and
disposed through septic tank with soak pit arrangement. All the water storage
Solid waste
Source Separation
Biodegradable Waste
Collection point
Local Municipality
Collection point
Non Biodegradable Waste
Sent to authorized recyclers
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 95
tanks/containers will be maintained without any leaks. Necessary precaution
and preventive measures will be taken at the site during construction to avoid
any groundwater and surface water contamination.
3.5.2 Operation Phase
It is proposed to use the recycled water for the part of the daily water
demand in the premises. The total water requirement during operation is
438KLD and the fresh water requirement is 160 KLD. The source of water is
taken to be CMWSSB since the quality of borewell water from the baseline
study was found to be TDS 668 mg/L; Total hardness 303 mg/L; sulphates 71.4
mg/L and chlorides 143 mg/L does not comply with drinking water
specification as per IS 10500:2012. Hence it is not recommended for drinking
purpose, and it is also not advisable for other domestic uses due to very high
salt content. In case of emergency, Water Treatment Plant will be proposed for
domestic uses, for which the quality of treated water will be TDS < 500 mg/L;
Total hardness < 300 mg/L; chlorides < 250 mg/L and sulphates < 200 mg/L.
The components of water treatment plant will be aeration tank, settling tank,
sand filter and carbon filter with iron removal media filled in it. The wastewater
generation from the project is estimated to be about 299 KLD, which will be
treated in proposed Sewage Treatment Plant of 320 KLD capacity. Treated
sewage will be reused for flushing, gardening, OSR and the remaining excess
sewage will be disposed through CMWSSB sewer lines. The sewage treatment
design is described in the Annexure - VII.
3.6 STORM WATER MANAGEMENT
3.6.1 Construction Phase
The surface runoff during the construction period will be directed into the
drains separately provided for this purpose.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 96
3.6.2 Operation Phase
Rain water from internal roads etc will be discharged through storm water drain
sloping towards rain water collection sumps. The Rainwater down comer pipes
from terrace level directly connected to rainwater inspection chambers
interlinked and discharged to filtration bed to store Rain water of min. An
overflow pumping main pipe will be laid as lead pipe from rainwater harvesting
trench up to the road for draining the excess water during rainy seasons.
DESIGN PARAMETERS:
Total Plot Area Considered 18149.26 Sqm
Total roads and pavement area 3557.79 Sqm
Total Greenbelt Area 2915.43 Sqm
Total Roof Area 7421.55 Sqm
Intensity of rainfall considered in Chennai : 0.06 m/hr
Co – efficient of runoff considered for roof area : 0. 90
Co – efficient of runoff considered for road/paved area : 0. 75
Co – efficient of runoff considered for landscape area : 0. 1
Hence, the total quantity of rainfall will be: q= a x p x r
q = quantity of rainwater run - off in cu.m / hr.
a = area of catchments drained in Sq.m
p = permeability factor
r = rainfall intensity in m / hr
Table 15: Run –off Calculations
Description Area in
Sqm
coefficient
runoff
Rainfall
intensity in m/hr
Total Rainwater
Runoff (Cum)
Road area 3744.34 0.75 0.06 168.5
Landscape area 2793.27 0.1 0.06 16.8
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 97
Roof area 7421.55 0.9 0.06x0.8* 320.6
Total Annual Rainfall Run-off/hr 505.9
Run off to UG sump (will be reused for domestic purpose
after filtration) 160
Total runoff for recharge 345.9
Run off to recharge pit 186.3
Size of RWH Pit (diameter- 1.5m , depth 1.5 m) 2.65
Size of borehole (diameter- 150 mm , depth 3 m) 0.05
No. of Pits Required 50 Nos.
No. of pits Provided 69 nos.
Excess runoff to external storm water drain 159.6
* - Evaporation, Spillage, first flush wastage.
Annual runoff is estimated to be 505.9 cum (Considering 60 mm annual
rainfall in the region)
The runoff from rooftop will be diverted to the rain water collection
trench.
During abnormal rains, the excess runoff after storage and recharge will
be disposed off through the external storm water drains.
a. Details of recharge pit
Recharge through Pits : 69 nos.
A portion of rain water falling over the roofs, road and paved area and the
open area will be used for recharging the ground water. The dimension of pits is
1500 mm diameter and 1500 mm depth. Recharge pits are normally excavated
as any shape, which are sufficiently deep to penetrate the low-permeability
layers overlying the permeable layer. They are similar to recharge basins in
principle, with the only difference being that they are deeper and have restricted
bottom area. In many such structures, the infiltration occurs vertically through
the permeable layer is much higher than the low permeable layer occurring in
the top.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 98
The pits will be filled with gravels (1-10mm) at bottom, coarse sand (1.1-
2mm) at middle and fine sand at the top in graded form. Gravels at the bottom,
coarse sand in between and fine sand at the top so that the silt content that will
come with runoff will be deposited on the top of the fine sand layer and can be
easily be removed. The top sand layer of the recharge pits will be periodically
cleaned to ensure the proper recharge.
Fig. 4 Cross section of recharge pit
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 99
b. Recharge Trenches
Recharge trenches are normally excavated as linear pits, which are
sufficiently deep to penetrate the low-permeability layers overlying the
permeable layer. They are similar to recharge basins in principle, with the only
difference being that they are deeper and have restricted bottom area. In many
such structures, the infiltration occurs vertically through the permeable layer is
much higher than the low permeable layer occurring in the top. Recharge
Trench will be constructed in the premises of the company across the slopes.
Trench maintained all along the boundary, the depth of the trenches will be
around 1.5 m. It is planned to remove the entire impervious layer to facilitate
rain water recharge. The width of the proposed trenches is 1 m. Pebbles of
different size will be provided in an ascending order in the tank and a layer of
sand will be provided on top of the filter media. The rain water flowing through
the open land, paved area and green belt area will be used for recharging to
ground water through the above said trenches.
c. Rain Water Storage Sump:
Rain water storage sump 1,60,000 litres capacity- 1 nos. is proposed for
rainwater storage and reuse.
The Rain water storage and harvesting plan has been designed as per the
Rain water harvesting (RWH) & conservation manual by CPWD, Govt .of
India, 2002 & in compliance with Ministry Notification dated 9th December
2016 under 50,000 to 1,50,000 Sqm category.
d. Flood Occurrence:
The highest recorded monthly rainfall in that area and surroundings of
Chennai is 521mm in 2010, considering the previous 5 years day peak rainfall
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 100
(Refer Table below from IMD). The storm water management has been done,
the total peak flow at the site by taking 600 mm of highest average rainfall/day
in site, the runoff will be 498.2 cubic meter/hr after development, the recharge
pit, storm water collection sump and storm water collection drain have been
designed in the site to the manage the rain water during heavy rainfall time.
Table 16: DISTRICT RAINFALL (mm) FOR LAST FIVE YEARS
Note : (1) The District Rainfall(mm.)(R/F) shown below are the arithmetic
averages of Rainfall of Stations under the District.
Year
Rainfall (mm)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2010 63.1 11.2 114.2 11.7 0.1 65.1 23 100.5 97.1 378 521.1 6.8
2011 13.1 0.0 0.7 0.0 14.0 11.3 41.8 93.9 73.6 46.5 493.8 259.5
2012 4.7 0.1 0.0 0.0 191.1 120.2 146.0 195.1 107.5 165.6 224.2 263.7
2013 11.8 41.8 0.0 19.4 10.0 118.0 85.6 330.5 235.5 241.1 447.3 147.5
2014 17 0.0 0.5 0.0 0.0 21.2 67.3 94.5 164 394.3 39.2 134.4
Source: Consolidated Report for Indian Meteorological Department
3.7 LANDSCAPE AND ECOLOGICAL MANAGEMENT
3.7.1 Pre-Construction Phase
a. Assessment of Flora in the Study Area
The Vegetation present within a defined area is termed as a plant community. This
is determined by the nature of the dominant species it contains. By the term
dominant species or dominance it is understood that species of plants having same
life and growth, forms predominating in an area. A systematic order of
angiosperm families recorded in the study area is given in Table.17.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 101
The distribution of vegetation at different sites, its density, dominance,
frequency, Importance Value Index (IVI), economic importance, and medicinal
uses were studied and the results are given in the following sections.
TABLE-17 DISTRIBUTION OF VEGETATION IN THE STUDY
AREA
I. Agricultural
Crops Nil
II. Plantation Nil
III. Natural Vegetation
a. Herbs Hemidesmus indicus, Carissa spinarum,
Heteropogon contortus
b. Shrubs Prosopis juliflora, Dodonaea viscosa, Glycosmis
pentaphylla ,
c. Trees
Azadirachta indica, Arecaceae, Cocos nucifera,
Carica papaya, Psidium guajava, Ficus
benghalensis, Moringa oleifera, Borassus flabellifer,
Musa acuminat.
IV. Endangered
Species Nil
V. Endemic Species Nil
VI. Medicinal
Plants
Ocimum tenuiflorum, Plectranthus amboinicus,
Heliotropium indicum, Moringa oleifera, Solanum
torvum, Trachyspermum ammi
b. Assessment of Fauna in the Study Area
The details of fauna found in the study area are given in the Tables.18
TABLE-18 FAUNA IN THE STUDY AREA
S. NO. Common Name Scientific Name Status
BUTTERFLIES AND INSECTS
1. Common crow Euploea core C
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 102
2. Grass yellow Terias hecabe C
3. Dragon fly Agrion sp & Petalura
sp C
4. Grasshopper Hieroglyphus sp C
5. Termite Hamitermes silvestri C
6. Ant Monomorium indicum C
AMPHIBIANS
1. Common Indian Toad Bufo melanostictus C
REPTILES
1. Common Garden lizard Calotes versicolor C
2. Common skink Mabuya carinata C
BIRDS
1. Pond Heron Ardeola grayii C , R
2. Small Egret Egretta intermedia C , R
3. Shikra Accipiter badius C, R
4. Spotted Dove Streptopelia chinensis C, R
5. RoseRingedParakeet Psittacula krameri C, R
6. Pied Crested Cuckoo Clamator jacobinus C, R
7. Koel Eudynamys scolopacea C, R
8. Spotted Owlet Athene brama C , R
9. Indian Roller Coracias benghalensis C, R
10. Whitebreasted
Kingfisher Halcyon smyrnensis C, R
11. Black Drango Dicrurus adsimilis C , R
12. Common Myna Acridotheres tristis C, R
13. Indian Tree Pie Dendrocitta vagabunda C, R
14. House Crow Corvus splendens C, R
15. Jungle Crow Corvus macrorhynchos C, R
16. House Sparrow Passer domesticus C, R
MAMMALS
1. Indian Palm squirrel Funambulus palmarum C, R
2. Indian pipistrella Pipistrellus coromandra C, R
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 103
It is proposed to plant plantation on landscape area and all through the
boundaries of the site and along the either side of the internal roads. This will
have positive impact over the fauna of the locality.
3.7.2 Operation Phase
It is proposed to have a landscape area of around 2793.27 Sqm. It is also
proposed to plant only the native species of plantations. In addition to
augmenting present vegetation, it will also check soil erosion, make the
ecosystem more diversified and functionally more stable, make the climate
more conducive and restore balance. As per MOEF EIA Notification, dated 09,
December 2016, minimum of 1 tree for every 80 square meters of land should
be planted and maintained. For plot area of 18149.26 Sq.m, total no. of trees to
be planted is 227. Total no. of trees proposed for plantation is 230. The
following species are proposed for the plantations in the site. Adequate numbers
of these species will be planted in the Landscape and along the boundaries of
the site and along the either sides of the internal roads.
Table 19: Proposed Tree Plantation Within project Site
S.No. Scientific Name Local Name No. of
Trees
Tree Species
1. Azadirachta indica Neem 50
2. Ficus religiosa Arasa Maram 10
3. Tamarindus indica Tamarind 5
4. Pongamia pinata Pungam 50
5. Eugnea Naval 10
6. Terminalia catappa Indian Almond 10
7. Phoenix sylvestris Icham 10
8. Madhuca longifolia Illupi 10
9. Antocephalus cadamba Vellai Kadambu 10
10. Mimusops elengi Magizham tree 30
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 104
11. Terminalia arjuna Marudha maram 25
12. Dalbergia sisoo Nukkam 10
Total no. of trees proposed for plantation 230
3.8 SOCIO ECONOMIC DEVELOPMENT PLAN
3.8.1 Construction Phase
Only locally available workforce will be used for the construction purpose. This
will result in the improved economic condition of the people of that area, at
least during the construction period.
Medical checkups will be done at regular intervals to all the employees
working. Trained first aid personnel will be made available round the
clock throughout the construction phase.
The safety procedures will be made available with the respective shift in
charges and the same will be pasted in the workplaces.
All the employees involved in the construction activities will be provided
with the necessary Personal Protective Equipments (PPE) and instated to
use it.
Occupational health and safety orientation training will be given to all
employees consisting of basic hazard awareness, site-specific hazards,
safe working practices, and emergency procedures
Monthly safety assessment meetings will be conducted to identify
potential safety issues (e.g., site access, construction, work practices,
security, transportation of heavy equipment, traffic management,
emergency procedures and fire control and management) and measures to
mitigate them.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 105
3.8.2 Operation Phase
The people of the locality, especially women, may be employed in the
households as service providers/maintenance staffs. This will improve the
circulation of money in the study area. The project also stimulates the auxiliary
developments around the project area. This will result in the development of
necessary infrastructure and amenities at least around the project site.
3.9 ENERGY CONSERVATION
Energy conservation will be one of the focuses during the project planning
and operation stages.
3.9.1 Energy Saving Practices
Use of Energy Efficient low loss – electrical ballast.
Usage of CFL/LED lamps
Use of capacitor banks power factor improvement of EB power
Use of copper wound transformer
Solar lighting is considered partly for external lighting.
Use of occupancy sensors and dimmers for lights in the parking areas
Solar Proposal as per Ministry notification dated 9th December 2016, under
category of buildings 50,000 sqm to 1,50,000 sqm.
Use of solar lighting will be provided at major junction of the roads and
common corridor lighting including stilt floor parking lights which
contributes to 1% of total demand say 32 kVA.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 106
10% of hot water demand will be provided from Solar water heater, (0.5
cum per day capacity of solar water heater will be provided)
3.9.2 Energy Conservation Measures
a. Building Construction Data
In accordance with Energy Conservation Building (ECBC) Code 2007
norms, Chennai comes under warm & humid climate zone. Hence, based on the
ECBC norms, U Values considered are as follows:
b. Roofs & Opaque Walls
Roofs and opaque walls shall comply with either the maximum assembly
U-factor or the minimum insulation R-value. R-value is for the insulation alone
and does not include building materials or air films. The roof insulation shall
not be located on a suspended ceiling with removable ceiling panels.
Table 20: U-values of the roof and opaque wall of the building
The U-values of the roof and opaque wall of the building will meet
the requirements as specified in the Energy Conservation Building Code
(ECBC)
ECBC
Clause:
(Reference)
Component
Permissible
U-Value as
perECBC
(W/m2°C)
Resultant Value due to the
proposed configuration
(W/m2°C)
4.3.1 Roof U-0.261 R-3.5
4.3.3 Wall U-0.44 R-2.1
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 107
c. Vertical Fenestration
Vertical fenestration shall comply with the maximum area weighted U-
factor and maximum area weighted SHGC requirement. Vertical fenestration
area is limited to a maximum of 60% of the gross wall area for the prescriptive
requirement.
Table 21: Vertical Fenestration
Description
WWR=40% 40%
<WWR<=60%
Maximum
U-factor
Maximum
SHGC
Maximum
SHGC
Glass 3.3 0.25 0.20
d. Electrical & LV Systems
a. Copper conductor cables are specified for sizes of 16 sq mm and
below, this will reduce losses and improve reliability.
b. All lifts shall be provided with AC variable voltage, variable
frequency drives (ACVVF).
c. Power factor shall be maintained 0.95 or higher. This will reduce
electrical power distribution losses in the installation.
d. Timers and photo-electric sensors shall be used to switch ON / OFF
external landscape and facade lighting.
e. Compact Fluorescent Lamps (CFL’s) with high frequency ballast
shall be used for plant rooms, corridors and BOH areas.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 108
f. All fluorescent light fixtures are specified to incorporate electronic
chokes which have less watt-loss compared to electro-magnetic
chokes and result in superior operating power factor. This indirectly
saves energy. Electronic chokes also improves life of the fluorescent
lamps.
g. All fluorescent light fixtures are specified to incorporate high
frequency ballast. Due to high frequency ballast florescent tube
consume less energy.
h. Energy efficient fluorescent lamps & CFL lamps which give approx.
30% more light output for the same watts consumed and therefore
require less nos. of fixtures and corresponding lower point wiring
costs.
i. An APFC relay based on thyristor switching is proposed to effect
the power factor correction / improvement within a few cycles of
deviation from the setting & also to reduce inrush currents.
j. Transformers shall have minimum no load losses as compared to
conventional transformers.
e. Plumbing & Fire Fighting
a. VFD based hydro pneumatic system.
b. Efficient condensate return & recovery system for domestic hot
water.
c. Pumps & equipment selected on “best” energy efficiency point.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 109
3.10 SOIL ENVIRONMENT
The top soil is filled up material (Debris) of 1.4 m; Brown Sandy clay is
upto 3m; brown clayey sand upto4.5m; brown silty sand upto 9m; black sandy
clay upto 10.5m; black silty clay upto 13.5m; black clayey sand upto 15.0m;
Black silty clay upto 22.5m and greenish sandy clay with lime stone upto 29m
Details are enclosed in the Geotechnical Soil report attached as Annexure – VI.
3.11 FIRE PROTECTION MEASURES
It is proposed to provide extensive fire protection system for the entire
apartments. It is proposed to provide the facility externally in the area and
internally only in the common areas. The facility is to be terminated at the
tapping point on each floor but the total system is being planned compactable to
entire building. The fire-fighting system involves following arrangements:
Table 22: Fire fighting arrangements
Components Amplified with console, 5 watt ring type recess mounting
speaker, microphone, zone selector panel and wiring.
Speaker
location
One each in lift lobby area
Fire alarm
system
Hooter and manual call point (MCP) will be provided in all
floors near each stair case.
MCP /
Hooter
Tyco
PA Tyco / Fire pro
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 110
3.11.1 Fire Fighting System
a. Construction Phase:
1. Dry riser 100 mm diameter pipes with hydrant outlets on the floors
constructed with a fire service inlet to boost the water in the riser from
fire services pumps.
2. Drums filled with water of 2000 litres capacity with 2 fire buckets on
each floor.
3. Water storage tank with 20000 litres capacity which is used for the
construction and other purposes.
b. Operation Phase:
1. Wet riser / 1000 sqm of area covering all floors with landing valves along
with delivery hoses for each block. To feed the wet-riser, an underground
sump of capacity 75,000 liters will be provided with refilling facilities for
each block.
2. Hose reel assembly, Manual fire call points will be provided in each floor
area.
3. Automatic sprinkler system will be provided covering at all floors
4. First Aid firefighting equipment will be provided at all the floors in
accordance with IS 2190:1992.
5. A trained Fire Officer with a crew along with fire control room will be
arranged to maintain as well as to operate the fire protection systems in
case of any need.
3.11.2 Fire Extinguishers
In addition to fire protection system the portable fire extinguishers of
various types are provided near lift lobby in each floor, pump room, transformer
room, DG room and lift machine room etc for fighting light hazard fire. All the
extinguishers used in the project area would be with BIS mark and are located
at an easily accessible position without obstructing the normal passage.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 111
The fire extinguishers used in the project area are given below:
One dry chemical powder extinguisher of 10 kgs capacity and 2
fire buckets filled with clean, dry, fine sand will be provided for
every 8 cars in the parking areas.
One CO2 extinguisher of 2 kgs capacity will be provided near the
entrance to each main switchboard room.
Two dry chemical powder extinguishers each of 5 kgs capacity
will be provided near EB transformer yard.
One dry chemical powder extinguisher of 10 kgs capacity will be
provided near the entrance to each generator room.
One CO2 extinguisher of 2 kgs capacity will be provided inside
each lift machine room.
One water type gas cartridge extinguisher of 9 lts capacity will be
kept near each stair case landing on every floor.
All the extinguishers used in the project area would be with BIS
mark and are located at an easily accessible position without
obstructing the normal passage.
3.11.3 Public address system
In addition to this, it is also proposed to provide public address system in
each floor near stair case area. This will help in addressing / altering the people
residents by the security personal through microphone arrangement.
3.12 RISK ASSESSMENT, DISASTER MANAGEMENT AND
SAFETY MEASURES
3.12.1 Risk Management Plan
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 112
A well - defined Risk Management Plan is made as follows:
STEP 1: Define the Projects/Tasks
Site Clearing
Excavation
Raft
RCC slab
Block work / plastering
External plastering
Joinery - frame fixing
Flooring
Interior works
Windows fixing
Flooring
False ceiling
Painting
Services
I.Electrical
II.Plumbing
III.Fire fighting
Equipments
i. Elevator
ii. STP /WTP
iii. Hard and landscape
STEP 2: Identify the Hazards
a) Are you using (Tick boxes)
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 113
[ ] Plant/Equipment
[ ] Portable Electrical
Equipment
[ X ] Pressure Vessels/Boilers
[ X ] Hazardous Substances
[ ] Scaffolding
[ ] Ladders
[ ] Lifts/Hoists/Cranes/Dogging /
Rigging/Load Shifting Machinery
b) Does the project/task involve (Tick boxes)
[ ] using tools/equipment with
moving part(s)
[ ] using tools/equipment that
vibrate
[ x ] working with x-rays ,or
lasers
[ ] electrical wiring
[ x ] asbestos removal
[ ] welding
[ x ] hazardous waste
[ ] excavation / trenches
(>1.5m)
[ ] working around electrical
installations
[ ] working near traffic
[ ] working at a height (>3m)
[ ] working in isolation
[] working in a confined space
[ ] manual handling
[ ] repetitive or awkward movements
[ x ] lifting or moving awkward or heavy
objects
c) Is there (Tick boxes)
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 114
[ ] noise
[ ] dust/fumes/vapors/gases
[ x ] extreme temperatures
[ x ] risk of fire/explosion
[ ] slippery surfaces/trip hazards
[ x ] poor ventilation/air quality
[ x ] a poorly designed work area for the
project/task
STEP 3: Assess the Risk
Table 23: Risk Assessment during Construction Phase
Activities Air
Pollution
Water
Pollution
Noise
Pollution
Soil
Pollution
Occupational
Hazard
A. Material Handling:
Cement +M - - +M +M
Steel - - + - +M
Sand - - - - -
Stone - - - - +L
Wood - - - - -
Glass - - - - +H
Hardware - - - - -
Color - +H - +H -
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 115
B. Construction Machinery
Rotary
Driller +L - +H - +H
Mixers +M - +M +L +M
Excavator +L - +L - +H
Material
Lift - - +L - +H
Risk Factor:
+ : Positive
- : Negative
L : Low
M : Medium
H : High
For any projects/tasks that present a high or extreme risk, a Safe Work Method
Statement must be completed.
STEP 4: Control the Risk
Note how you will control the risk following the priorities listed to the
right. This may include controls like redesigning the workplace, using guards or
barriers, ventilation, using lifting equipment or personal safety equipment.
Eliminate the Hazard
Keep the Hazard and People Apart
Change the Work Methods
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 116
Use Personal Protection
Note any specific risk assessments required for high-risk hazards. Check
whether any hazards noted in step 2 require further assessment or action.
[ x ] hazardous substance risk
assessment
[] test and tag electrical
equipment
[ ] confined spaces risk assessment
[ ] sound level test
a) Note Permits/Licenses/Registration required
[x ] Demolition work
[ ] Electrical wiring
[ x ] Pressure vessels
[ x ] Friable asbestos removal
[ x ] Ionizing radiation sources
[ ] registers for chemicals, Personal
protective Equipment, training,
ladders, lifting gear
b) Note certificates of competency/licenses for operators
[ ] Scaffolding
[ ] Rigging
[ ] Load shifting machinery
operation
[ ] Pesticide application
[ ] Crane operation
[ ] Hoist operation
c) Note emergency systems required
[ ] first aid kit [ ] Fire control
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 117
[ ] extended first aid kit
[ ] emergency stop button
[ ] additional emergency
procedures
[ ] remote communication mechanism
[ x ] others
STEP 5: Actions Required to Control the Risk
A. During construction to reduce pollution:
Manual water sprinkling during dust excavation
Using RMC to reduce air pollution
Dust cover for Trucks
New Construction Machinery
Equipment will work intermittently
Rotary drillers instead of acoustic drillers
Vehicular trips will not be at peak traffic hour
Ear Plugs to workers
No noise polluting work in night shifts
B .Safety & Hygienic Measures:
Adequate drinking water, toilet and bathing facilities
There will be free medical camps and first aid rooms for workers
Safety equipments like helmets, safety shoes etc. to personnel and
visitors
Personnel protective equipments like leather gloves, goggles and ear
muffs when required
Personnel working on heights will wear safety equipments and will not
work alone
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 118
To prevent any accidents, the entire area under construction will be
cordoned off with tin sheets and safety tape is run outside this fence
Regular pest control will be done
Adequate fire fighting equipments will be provided
Operational Phase:
Risks in the complex will be due to natural calamities like earthquake,
flooding and others such as fire and accidental hazards. All precautions will be
taken to control these risks. Fire fighting system shall be provided as per
regulations of Chief Fire Officer. For earthquake resistance, the structural
design shall be as per is certified as per IS code 875 and IS- 1893-2002 for
Seismic Zone 3 of Chennai.
a. First Aid Facilities:
Construction projects will comes under the highly hazard or specific
hazard category. Requirement of the first aid provision at work depends on
several factors including size of the undertaking, number of employees, hazard
arising , access to medical services, workers in isolated locations, etc.,
Construction phase we have plan to appoint one trained first aider for this
proposed development project, and a registered nurse.
b. First Aid Room:
Location, Work Space, Work Environment, Signs & Management –
the First Aid room easily accessible during working hours and also close to road
access. The first aid room should be easily recognizable signs.
First Aid Minimum Requirements for this proposed construction project:
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 119
Furniture & Fittings: Wash basin with hot and cold water supplies, Desk, work
bench or dressing trolley, Telephone, Electric power points, Couch with
blankets and pillows.
Medical Requirements: Examination Table, Examination Lamp, Stretcher
Lifting Frame or similar device for transporting patients, First aid kit, Dressing
clothes and gloves, soap, disposable towels, trays and bowls.
3.13 DISASTER MANAGEMENT PLAN
A disaster or emergency is a threatening condition that requires urgent
action. Effective emergency action can avoid the escalation of an event into a
disaster. Emergency management involves plans and institutional arrangements
to engage and guide the efforts of government, non-government, voluntary and
private agencies in comprehensive and coordinated ways to respond to the
entire spectrum of emergency needs.
The overall objective of an Emergency Response Plan (ERP) is to make use
of the combined resources at the site and outside services to achieve the
following:
1. To localize the emergency and if possible eliminate it;
2. To minimize the effects of the accident on people and property;
3. Make the rescue and medical treatment of casualties more effective;
4. Safeguard other people;
5. Evacuate people to safe areas;
6. Informing and collaborating with statutory authorities;
7. Initially contain and ultimately bring the incident under control;
8. Preserve relevant records and equipment for the subsequent enquiry into
the cause and circumstances of the emergency;
9. Investigating and taking steps to prevent reoccurrence.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 120
The ERP is therefore related to identification of sources from which hazards
can arise and the maximum credible loss scenario that can take place in the
concerned area. The plan takes into account the maximum credible loss
scenario - actions that can successfully mitigate the effects of losses/ emergency
need to be well planned so that they would require less effort and resources to
control and terminate emergencies, should the same occur.
Main hazards identified for the project include hazards pertaining to fires in
buildings and fire in diesel storage areas, earthquake and LPG leakage and an
ERP pertaining to these is described in the following section.
3.13.1 Response in case of earthquake
a. Earthquake Preparedness
1. Know how and where to take cover during a quake
2. Anchor furniture over 42”. Do not stack furniture
3. Move tall bookcases away from exits. Do not use them as room dividers
4. Anchor computers, equipment, and display cases
5. Store heavy items at floor level
6. Back up critical data. Keep duplicates off-site
b. Response Procedures for Occupants
If indoors:
1. Take cover under a piece of heavy furniture or against an inside wall and
hold on.
2. Stay inside: The most dangerous thing to do during the shaking of an
earthquake is to try to leave the building because objects can fall on you.
If outdoors:
Move into the open, away from buildings, streetlights, and utility wires. Once in
the open, stay there until the shaking stops.
If in a moving vehicle:
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 121
Stop quickly and stay in the vehicle. Move to a clear area away from buildings,
trees, overpasses, or utility wires. Once the shaking has stopped, proceed with
caution. Avoid bridges or ramps that might have been damaged by the quake.
1. After the earthquake be prepared for aftershocks.
2. Although smaller than the main shock, aftershocks cause additional
damage and may bring weakened structures down.
3. Aftershocks can occur in the first hours, days, weeks, or even months
after the quake.
4. Help injured or trapped persons.
5. Give first aid where appropriate. Do not move seriously injured persons
unless they are in immediate danger of further injury. Call for help.
6. Remember to help those who may require special assistance--infants, the
elderly, and people with disabilities.
7. Stay out of damaged buildings.
8. Use the telephone only for emergency calls.
c. Response Procedure for Emergency Team
1. Formulate an Emergency Response Team for earthquake response.
2. Using the public address system, inform people of response procedures
discussed above.
3. Inform the necessary authorities for aid.
4. Ensure no person is stuck beneath any debris, in case of a structural
failure.
5. Ensure that all occupants standing outside near the buildings are taken to
open areas.
6. Ensure that the first aid ambulance and fire tender vehicles are summoned
if necessary.
7. Inform the nearby hospitals if there are any injuries.
8. Check the utilities and storage tanks for any damage.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 122
3.13.2 Response in case of fire
a. Fire Preparedness
1. Note the location of alarms and extinguishers. Know how to use them
2. Leave fire doors closed at all times
3. Clear obstructed corridors, aisles and room exits
4. Limit use of extension cords and multiple outlets
5. Do not use mechanical rooms or utility rooms for storage
b. Response Procedures for Occupants
1. Required response during in the event of a fire should be described in
signs located in the lobby.
2. On sighting a fire, it should be immediately informed to the environment
manager giving the exact location and type of fire in detail.
3. Initiate the Emergency Response Team for fires.
4. If the fire is small, engage in extinguishing the fire using the nearest fire
extinguisher.
5. Guide the Emergency Response Team staff to the emergency assembly
point.
6. The Emergency Response Team should immediately inform the nearest
dispensary and security force. If required a fire tender should be
summoned.
7. The response team should immediately move to the point of fire and take
all necessary steps to stop the fire. If the fire is not controllable and
spreads then the manager in charge should inform the district authorities
and call for external help.
8. The Emergency Response Team will provide immediate relief to the
injured at the scene of incident. Any injured persons should be evacuated
on priority to the dispensary or one of the nearest hospitals based on their
condition.
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 123
c. Instructions for occupants
1. Get out of buildings as quickly and as safely as possible.
2. Use the stairs to escape. When evacuating, stay low to the ground.
3. If possible, cover mouth with a cloth to avoid inhaling smoke and
gases.
4. Close doors in each room after escaping to delay the spread of the fire.
5. If in a room with a closed door.
6. If smoke is pouring in around the bottom of the door or if it feels hot,
keep the door closed.
7. Open a window to escape or for fresh air while awaiting rescue.
8. If there is no smoke at the bottom or top and the door is not hot, then
open the door slowly.
9. If there is too much smoke or fire in the hall, slam the door shut.
10. Stay out of damaged buildings.
11. Check that all wiring and utilities are safe.
A state of the art fire fighting system is proposed for the project to
prevent and control fire outbreaks. The fire fighting system will consist of
portable fire extinguishers, hose reel, wet riser, yard hydrant, automatic
sprinkler system, and manual fire alarm system. The buildings will also be
provided with automatic fire detection and alarm system.
3.14 Environment Monitoring Plan
Environmental monitoring plan is a vital process of any management plan
of the development project. This helps in signaling the potential problems that
resulting from the proposed project and will allow for prompt implementation
of effective corrective measures. The environmental monitoring will be
required for the construction and operational phases. The main objectives of
environmental monitoring area:
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 124
To assess the changes in environmental conditions,
To monitor the effective implementation of mitigation measures,
Warn significant deteriorations in environmental quality for further
prevention action.
The emissions from each of the diesel generator shall be monitored for exit
concentration of Sulphur dioxide, Oxides of Nitrogen and Particulate Matter on
regular intervals. The frequency of monitoring shall be decided in consultation
with the TNPCB. Sampling ports in the stacks/vents shall be provided in
accordance with CPCB guidelines.
Table 21: Environmental Monitoring Plan
S. No. Description Frequency of Sampling and
Analysis
Construction Phase
1. Ambient Air Quality Once in six month – 24 hourly
2. Stack Emissions from DG set Once in six month
3. Ambient Noise Level Once in six month
4. Soil Quality Once in six month
5. Ground Water Once in six month
Operation Phase
1. Ambient Air Quality Once in six month – 24 hourly
2. Stack Emissions from DG Set Once in six month
3. Ambient Noise Level Once in six month
4. Treated Sewage Once in a week
5. Ground Water Once in six months
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 125
Additional Details on EMP:
High Rise Building:
The proposal involves construction of commercial buildings with a total
built up area of 88779.2 Sqm. The Area split up and space utilization details are
given in section1.3. The project consists of mall building; with Ground + 12
Floors and a Multi-Level Car Parking with Ground + 16 levels. The height of
the building is 51.88 meters. As per MOEF Notification the road width and
firefighting compliance is applicable for building height above 15 meters. NOC
from Tamil Nadu Fire and Rescue services Department & Airport Authority of
India has been obtained and enclosed as Annexure XIII. Conditions quoted in
both the NOC will be complied during construction. Further in the proposed
project, sufficient Road Width (9 m) has been provided for easy movement of
vehicles. In case of emergency, Ashok Nagar Fire station, is located within 5
km distance respectively.
Table 22: Budgetary allocation for environmental management during
Construction phase
Description Budgetary Allocation
(Rs. In Lakhs)
Capital
Expenses
Operational
Expenses
Drinking Water & Sanitation
(Temporary Toilet) Facilities
3.5 8
Storm Water Management 2.0 5.0
Solid Waste/Debris
Management
0.7 4.0
Environmental Monitoring 0 4.0
Dust Suppression Measures 3 5
Occupational Health &
Safety
5 7
Total 14.2 33
Table 23: Budgetary allocation for environmental management during
M/s. Anandram Developers Pvt Ltd., Conceptual Plan
M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 126
Operation phase
Description Budgetary Allocation (Rs. In Lakhs)
Capital
Expenses
Operational/
Maintenance Expenses
(Per Annum)
Sewage Treatment Plant &
Recycling System
30 5
Rain Water Harvesting
System
10 2.1
Solid Waste Management 5 2.0
Environmental Monitoring 5 1.5
Energy Conservation 10 3
Greenbelt Development 12 2.0
Total 72 15.6
*********
RISK ASSESSMENT, DISASTER MANAGEMENT AND SAFETY MEASURES
A well - defined Risk Management Plan is made as follows:
STEP 1: Define the Projects/Tasks
Site Clearing
Excavation
Raft
RCC slab
Block work / plastering
External plastering
Joinery - frame fixing
Flooring
Interior works
Windows fixing
Flooring
False ceiling
Painting
Services
I.Electrical
II.Plumbing
III.Fire fighting
Equipments
i. Elevator
ii. STP /WTP
iii. Hard and landscape
STEP 2: Identify the Hazards
a) Are you using (Tick boxes)
[ ] plant/equipment
[ ] portable electrical equipment
[ x ] pressure vessels/boilers
[ x ] hazardous substances
[ ] scaffolding
[ ] ladders
[ ] lifts/hoists/cranes/dogging/rigging/load
shifting machinery
b) Does the project/task involve (Tick boxes)
[ ] using tools/equipment with
moving part(s)
[ ] using tools/equipment that
vibrate
[ ] working around electrical installations
[ ] working near traffic
[ ] working at a height (>3m)
[ ] working in isolation
[ x ] working with x-rays ,or lasers
[ ] electrical wiring
[ x ] asbestos removal
[ ] welding
[ x ] hazardous waste
[ ] excavation / trenches (>1.5m)
[] working in a confined space
[ ] manual handling
[ ] repetitive or awkward movements
[ x ] lifting or moving awkward or heavy
objects
c) Is there (Tick boxes)
[ ] noise
[ ] dust/fumes/vapours/gases
[ x ] extreme temperatures
[ x ] risk of fire/explosion
[ ] slippery surfaces/trip hazards
[ x ] poor ventilation/air quality
[ x ] a poorly designed work area for the
project/task
STEP 3: Assess the Risk
Table 24: During Construction Phase:
Activities Air
Pollution
Water
Pollution
Noise
Pollution
Soil
Pollution
Occupational
Hazard
A. Material Handling:
Cement +M - - +M +M
Steel - - + - +M
Sand - - - - -
Stone - - - - +L
Wood - - - - -
Glass - - - - +H
Hardware - - - - -
Colour - +H - +H -
B. Construction Machinery
Rotary Driller +L - +H - +H
Mixers +M - +M +L +M
Excavator +L - +L - +H
Material Lift - - +L - +H
Risk Factor:
+ : Positive
- : Negative
L : Low
M : Medium
H : High
For any projects/tasks that present a high or extreme risk, a Safe Work Method
Statement must be completed.
STEP 4: Control the Risk
Note how you will control the risk following the priorities listed to the right. This may
include controls like redesigning the workplace, using guards or barriers, ventilation,
using lifting equipment or personal safety equipment.
Eliminate the Hazard
Keep the Hazard and People Apart
Change the Work Methods
Use Personal Protection
Note any specific risk assessments required for high-risk hazards. Check whether any
hazards noted in step 2 require further assessment or action.
[ x ] hazardous substance risk
assessment
[] test and tag electrical equipment
[ ] confined spaces risk assessment
[ ] sound level test
a) Note Permits/Licenses/Registration required
[x ] Demolition work
[ ] Electrical wiring
[ x ] Pressure vessels
[ x ] Friable asbestos removal
[ x ] Ionizing radiation sources
[ ] registers for chemicals, Personal
protective Equipment, training,
ladders, lifting gear
b) Note certificates of competency/licenses for operators
[ ] Scaffolding
[ ] Rigging
[ ] Load shifting machinery operation
[ ] Pesticide application
[ ] Crane operation
[ ] Hoist operation
c) Note emergency systems required
[ ] first aid kit
[ ] extended first aid kit
[ ] emergency stop button
[ ] additional emergency procedures
[ ] Fire control
[ ] remote communication mechanism
[ x ] others
STEP 5: Actions Required to Control the Risk
A. During construction to reduce pollution:
Manual water sprinkling during dust excavation
Using RMC to reduce air pollution
Dust cover for Trucks
New Construction Machinery
Equipment will work intermittently
Rotary drillers instead of acoustic drillers
Vehicular trips will not be at peak traffic hour
Ear Plugs to workers
No noise polluting work in night shifts
B .Safety & Hygienic Measures:
Adequate drinking water, toilet and bathing facilities
There will be free medical camps and first aid rooms for workers
Safety equipments like helmets, safety shoes etc. to personnel and visitors
Personnel protective equipments like leather gloves, goggles and ear muffs when
required
Personnel working on heights will wear safety equipments and will not work
alone
To prevent any accidents, the entire area under construction will be cordoned off
with tin sheets and safety tape is run outside this fence
Regular pest control will be done
Adequate fire fighting equipments will be provided
M/s. Anandram Developers Pvt Ltd., Project Summary
M/s. Eco Tech Labs Pvt. Ltd., Chennai Page 17
S.
No. Description Proposed Residential Building
Project Name :
Mall/ Hotel/ Theatre complex ‘Matrix
Mall’ by M/s. Anandram Developers Pvt
Ltd.,
1. Geographical coordinates of the Project Site Latitude: 13°02'47.03"N
Longitude: 80°12'10.08"E
2. Category 8 (a)
3. Village Name
Survey Numbers
Saligramam Village
Town survey no. 8/1 (PART), 8/2 to 8/30,
8/33, 13, 14, 15
4.
Total Plot Area 18,149.26 Sqm
Ground coverage area 7421.55 Sq.m
Roads and pavement area 3488.34 Sq.m
Green belt area 2793.27 Sq.m
OSR AREA 1820.00 Sq.m
Utilities Area (STP, SWM, Transformer
yard, DG Area) 256.00 Sq.m
5.
Total Built-up Area:
Give description ( Number of blocks with
floors)
88779.20 Sqm
Floor Total Built-up
Area (Sqm)
Main
Building
(Mall)
57140.35
MLCP 28974.79
Sub-Station 2664.06
Total 88779.20
6. Estimated Population 14994 Nos.
7.
Solid Waste Generated
Bio degradable :
Non Biodegradable:
STP Sludge :
Biodegradable waste: 6579 kg/day
Non Biodegradable waste: 1816kg/day
STP Sludge: 45 kg/day
8. Electricity load Demand
Proposed Back up DG
6140 KVA
3 nos. of D.G. Sets of 2000 KVA each &
1 no. of 1500 KVA
M/s. Anandram Developers Pvt Ltd., Project Summary
M/s. Eco Tech Labs Pvt. Ltd., Chennai Page 18
9. No. of RWH pits with specifications
Recharge pits: 69 Nos.
Dimension of Recharge pit: 1.5m dia and
1.5 m depth
10.
Total Water Requirement 438 KLD
Domestic Fresh Water Requirement 149 KLD
Flushing water Requirement 165 KLD
Gardening water Requirement 10 KLD
HVAC Requirement 103 KLD
Swimming Pool water Requirement 11 KLD
11. Parking Required
Parking provided : Car
Parking provided : Two wheeler
Parking Required as per DTCP norms:
Cars: 716 Nos.
2W: 737 Nos.
Parking Provided:
Cars: 796 Nos.
2W: 1094 Nos.
12.
Green belt Area
Tree Belt Area
(Specifications Width X length in meter
Number of trees proposed to plant
Other landscaping Area
(Specifications of area)
Total number of Herbs
Total number of Sherbs
Area proposed as grass pavers if applicable
Green Belt area – 2793.27 Sqm
No. of trees proposed to be planted: 230
Nos.
13.
Solar:
Quantity of solar power generation
If stand alone street lights of numbers
If water heaters capacity of solar panels
Solar Street lights proposed: 15 Nos.
Total load consumption using solar
energy: 5219 KWHr per annum
14.
Energy conservation :
Total energy required-
Total energy saved using energy consumption
measures (%)
6140 KVA
569382.48 KWHr
Total Energy saved = 47.80%
15. Total project cost 266.39 Crores
16. Water Source
In Process of obtaining permission for
water supply & excess treated sewage
disposal from CMWSSB.
tb
G_ ,nwrdb H,..,;-fU Andhra BemX:;;; N,* (}r,r,}r
(
(
(
(
*{d 3
lNFr,, ri,,oS,bd$"$oY [xY Y
IN
fulveLro roR e ti4or.riHs ot.tr-v
Flk.l'ltrili:R 1;iH:{::ftHTAltY
& co.
f::i.,.1r..r l.-a l,;.h mn L y
SGMAB/FO/CTSno16/ll
ItO$70
,il.o 5o jl ?orr. Eooo I Io I qr:
Ei elr*n *q' ror ANDHRA BANK
9- -'(
(
(
(
t?
l
I
,fi**s r 00 roo+ "
NOTES :-
REFERENCE DRAWINGS
REV.DRAWING NO.
ORIGINAL SIZE:-
CAD FILE NAME:
AREA DETAILS:-
LEGEND:-
cc)EoonL '--
it'.A.FLo;'6:>I
-oo-0)c
=o_=
Y@o
clF
o.9
.9a
9'=_oaaE>
, c)
i6(otr-€*.o-=--R(9
i:3c-bp>
Eco6.Q
Ca.9f.oo'.-avo=E
-ly
f!l!
EC
EbOE
(/);i
=Po
oC=f
Eot
U
HE
E
E.
. O
)O
g. -
co o c'- o
/6v-dlv*N
X;0)
o I o 6r'X'
9; t.
Hat.li
O:
"U
H6E
3-Y
Lt-a--F
eaP5F
5e-o.^ L,
(D;
Oo (, Y
o+-
- d
L n
FE
.--y.-: - - - -E
e;!g;o)o
cE
hozz=>
AO
\|Ed
:,.O
-O$'ii$F
-
o.-$o:a
om'E
'-- a
0)r_co
za
f.-NNI
s?o
- D
=
"'
_! fr
-^.=M
orb(U
E.2<^t-e:8_E
=
9..Looo
ozcE+
.=F
uv-I
E
f.- C
.)acso)
::' t .., :.,. .....' ..... :p:.g, .--!.
cI -;E
Yts
.E-aH
.;C
L I;
E P
o =
r;58O
=coo€
o z
j{IJ_JE
Oo_cFLaEG
t*-).=
-rr
bEo.EO
r'-
L :.
-o ..,6.. .
.
,,>
..E,,.,
o-O
;i
^.ic>
5c
=d
8O
97
-.: 6-c
*68@o
x=,.9.=
XyE
(uvg--aa.=
EgtsB
tuE
e+f
E2'-v
-Rn
u::g,idlanFY
;v =
.F
()-LlJ
=otIL
;o.b
o.9. Y
-FO
lrLl9coo
c6
-(uX
Fc.6O
c@=
9:!lcd9
;orr o)
XN
-cvO
o-;rN
.. ; u s-)l.L
f..- C
)A
N.,-.
...-..-C
'..: 6
- 'Y
-=o
runo-;ir\l,LO
q.FN
r;ioElr)alLo)r'-=
aYco.rz.ooA
RC
)Q
Si
f=€qs
q.Ar=
0).. S
6 E
E
z-Lt-F
7ia(oJzH€bc=Ld1.=t\
1 r^
*.
\oIq)
Utrb8
mEr
aXtE
<i
atdq)L't(}La-E
(v),xaL/€
Fgo.t.-EI
*zoFuf-,1lq(nF
rl
zFJ
UzriFLI
UITF{I
orI]U
Eql
U
t-FiO
g€e5ES
E
tafle,itsH
gtr€?5F
EE
YE
iE
H
€ 2 5 5
(uat,
oo(g3(,=v)
EotrflEolo
P€q
s &
EC
lEc
6 F#
zbE;
HfE
F=
L f =
JEfifi
;tt=oEoGotroEIexooa
h!it\
- h
3'\3 F
oEi
H
'\'.€E
'Fa E
'^--:
.g!o I s
y?
:lEg
$5E
gEtr rH
-{" €..:. +
Eg(gtu
z25F
lrl .
d fiHr
-f$J
gs:
ET
E.c(J
E E
Eb
eeE
6qlll €
?HF
d?
sas
== g,trooo@'do=
pz(atlr
aL
Jg3d2 + r
8 EE
od#E2 7z^tu*.:92.8"6 E
FE
n €=-E
-fi g $,*5.{z
=a E
9 toq,(J
oBE
ilHE
qf;E
Efri
# Hgs=
sH!a:
u0G
Jq$l
a60trqiqot(!F
.XF
.' 6o\oN
IE<
. =t
<itr
!'tv'6YatstT
3xtF
{X+
x63u)!i\o(\rn+
Ia)
E
U)
u)NI
+$oAD
z.hho)lr0,zN\oIoE
!(ltzthC
)Ivthar..
\oFi
z
*'N&
.wF
\wscqr?
s##s#sbi
s'Ei
si#
$
&wl
slsl
I
(IIccc)
oooLg(D
U)o
p=;ico.-
r<o<,'rt
x <
"j'E
o)o
;o=
>
oF
Vo o(o
OE
E!
oc7
(EoLoJ_ocoofL0,coO
+J!a'.
q)
&>i
Ib0+
Jao>i
H(J-r-r,ELI
rhv
ul
!.oIJJ
0.Izoutot!oul
F
-_:IIiIIIII
f
c9CD
ooo(l'Ia6q)
o(gIU
=No(E
=(!Ex(U
EoIa!o(E
=!?J(I,p'bo-c
oah
toG(J
z
aFzlr"l
FzO
.F'-oa0)o
oo_0)E
coGoG'6(so_(I'oo)-.Eooc0
avao)t@ot-:aoC
)(5U:oU
'coC)
0)L=O.u)ao)
.NU)
.S(ULo
o)
;c0
coGc)oJoI0)Lom
co'r.o\cirr)bNItr$o$9oJ
'L' G
r
d06t!
0)z=)-v
o'3' Fo.._ctrqo.iq>
-a-O
\ (d
^; o
1'1;;N
:=
NX
:o'a=
qtsE
$ErT
>'=
e'FE
gd-i':6+
3-cN
3
9CY
)i,:
Co
ttll
=
F{
i:-i
l"^ d. :
; Z
osul
<r
o. "i3
J >
+(
r'\Ot]c)N=
ornZ
Ii+fr
F3
!JtllF
Eo)
o =
Eo
6:ltJ
D.'
F*
LHz
zU)
NC
O$
ro(o
t
traoc)oooE.o)q)ooU'
ots.Fooxoc)-t-.-:oxq)o)q)o,
l,o)E
bn=
=.
Eg
o.: U
'(/)bO
(D.9trEoo.=
og:ct-E
c9,9
(E
6Po.9-c
o5E
_3,9E
E-o- oo",e-cdpbEP
.o=F
Aox(()Yoo--o
o)-v
.=
Jfr
| giI^
OU
,F
r(Dh
Et
: E
tsnxlt:!l
Qo
br.IlPE
=BE
o:
lB;E
E!fii=
EE
Eif€r.;e
o,t.a:5 6 €
o o
E f =
E =
Ee n €
H
:E#sE
;iE€
isEE
sHei:
iEE
gEE
ggE.G
HtsaE
s-oBE
!69otiJ=
E€;af;5ube
;;Eg;:=
*cP
EE
€E;gfr$
=5*;g;E
sEE
eE;=
EfiE
gE+
F E
a€ E : 4 E
:
; *HE
E ?; €;'g-
g o€{€EE
"rEga
rotroE;giiaE
po-1gg1 -c'-ooE
€g
o_
-og-og(U6B(E
uiE
q)
-cA
oL
69o_!(trvt:
'-3 .e^
wofi
P
ooP3
FAao.D o-3eu,
o-o
IE
ip|ocr
coo=H
5E:F
* e Y,5
i. P
EP
x.=-
o)Etrd\
o=E
=5
EE
trb 8yt8.
a P3
r=a
€-E
oroEli0)
3.qc.-coxE"
*E;gE
:oaH
SE
qEF
nF
f!:gE
E-
y (5
0 >
-c Jy
g E
H *s::
eO
i_=F
E
ffrE*f
'E
F s
+€s:iE
ft E
gts'=t
Z
.xPa
'64+
= I
ft::=efi
\JG
E =
P
:B eF
,gEe.=
F
strXP
u6 s
cEsE
:EltJoeo',4----_H
= F
H
:€ET
*?=
=
Esefr;*g
g H o
EE
=gE
tE=
E =
F
E F
EE
€2E
; i qlsE
leg:
E E
:E
F;gE
-HfiE
i E
€;€EE
eo E
g a: =
;0t=5 F
icf*E
Eg
r i E
!neF;g
oF,,.l
'- :j'c
o::eEF
'ei
E € e,?E
F€iE
E
;9 *c.jiE
P.?c
o o E
-HtH
FB
RtrO
Y^rzE
5 E E
E
egieE
2- 0
eHH
Fn
$3 E F
96'e
t- .=
':g iE
B
H: E
s Al
E3,ii5s-:O
6*{.**sF
B̂/5i
-vS"E
G=
z'e.q=G
}:Et- o
e'E;
!. tr
9.1
5r{.E3+
tx$E?s,srootr
.-r.=c!$
ZF
8H=
q\ i
QR
}r\
BF
" Fr' x
e-s 64i.Fdv.
i 4E
^>lr,
E;E
1En
a 6s9
lo'
=E
tut:!F
:Og :>
.O
SU
\gI
F
Fe;z
o,;.-ooE
==
#Edvd
G
EE
-E
-+.ogc
og--e.9)=
FO
EE
l:o-=ts
eg E
8='
0.c.=E
tr3q
E;=
B g
E6e
P E
.A
E
go=
tsaE
5 A
o'=I6
3-E 5
EE
E
;HJ-
do;o=dl
-EbP
. ?e
=E
b € I =
Eee'H
3E
::luntsUd=
q .I:8
: € E
3 b =E
g E
P fr E
cE'=
-!9.c.x>
o==
E:E
'Z
- EE
'atO
-c.E(u
.E A
:=
F:E
E;63
E€B
-:=o
EP
gE
#';a:-6u'c-;tr6=
3E;F
EE
iI.0 l:;
E=
=0
E 3E
# Efi;€
t P
H-E
6F=
;d tr?bo E
FE
?=
*1
g 3g
o, )\e
h g6
iI 5tr
6 a-a
96-o)9c).=
-c.
EF
Lo.ihrnuo.aa$s6o,P
.o.'6o0)g6IlU
.,c
B€
?=orno5'aaoc)ah'6;aEE
FO
iF-
(D
AolE€o
(D!
6EE
EflE
oc.(l){i(0
EE
E,btu
il *O
EE
E-e{
e 3 i *3 eS
EE
Fofr
E
;EJZ
Y
["Etg
E€ra€E
B
bGb
;EgE
H
\$H6=
EE
='
?E;E
: "H
E;i€€ *E
gH
E;E
:fr.t€c.,
ts
HE
eE
E:=
,Efi; E
BC
Fx=
{ sE
*r"rg q::E
$#€ fr9883=
esEe+
eE :sE
sFfr 5+
g:t;{
pEH
efr; c=E
?€E
E€
EH
gE;E
ZN
=8
EE
gi gfrgilE: E
HE
fie:E
E
Er!!-E
;; nfr=E
E'le: g;tg;E
;Ftg
EE
i; E
I;-i! e rbH
eE
b8fi ;E
E€gif
$E=
=;
ss:E
gii€EE
EgE
F:E
A.P
sfi€F
:P €:;
f FH
€ ;?fiE';E
f E€E
5b-u' a IE
:.Hga
gE;€
r:€n=t E
aFsE
€ ggE.F
+E
i;t E
EF
gE; E
;'f!E
i i E 3 t
E E
E fr P
T .' r +
s E E
E uE
h=E
g o-; H
BF
E?cgB
E;
c€,H t F
etg;!E efiE
,^hiE
^"FE
;'Ei;
$3 E S
QhF
F.i;
: E g ar r
,2#,>'og*
+*.:.ofE
{-vS
rqz.aro>
,"trh-od'E
;LtrO5ra.E3+
3
.s$E?s+ta-.--'=€.+
a
E8:
O.::
6p ir\
'frX
i;res 5?*=
5 "dfx>
iail rE1f,n^<
a$9r6+
.81.
h isoAuJ
\O
'
F
Fd
z
(Eo_O
)flaoEoaN-o!:q)oqEooooGoEC
9-o)c)o'd_ooo=u>I
U'
(I'oooo=o(Uo.lt(E
;aac)ooF<ic)oo(!ooE==oI
;aGooq)Loa6a(sq)o
E:
Eu,eE
ii I E
E;
EE
E;^E
€ ;F
; E
fre$*=e H
dEi
gf E:xE
F
lo .c
:E
Ef;E
EF
F E
*i:iE
E
:ER
\BE
EsE
P9 $$ E
sFs
H
€E
EE
;Bs'i gf':l5
pa :b:3 :
EE
:ItstE sg;F
s :i E
g;E
g
tr :E
Eitl €fi5;€ fi: isai
E;e
gFeE
t€ Ft:zi
EE
Fitfr
E
f;EH
EE
fiI3€ ;t;te €etAE
$ l3:H
EE
;EE
= qE
tfi[ E
g gEgE
9
oE;
=6:*tE
;f;;6-=
E
= '*
EF
E:
q)
Ei_c
B*€E
{I :E
E+
E
Eg E
tEt
E
frHp iE
€Fi$ E
E:ai
st:F
*!:E
rtF
€BgE
i=s6:E
R
e;E
i H:I$E
;EE
5E€:E
iE F
F€t i
.=sd
=F
* BItqnI*E
IEP
:F; F
E E
iiF
H
Eie $;rE
i$eEr-riE
e; c; qEgl
="
e EeE
HB
gFiF
fifiar*$€€ 5E fi53;
fr
EE
E* E
EE
F;tfi€f;frfif;E
r t:EB
EE
*tEi ggg gE
;iIf eEcgE
HiE
E €x5;E
IEg
-E
6i E
pF
SS
bE
,? 3=
.- ;
-8 =
9'\s5
eH n bH
EigE
E e*€ 5 H
g ;€'€E
o-oEoo-oo(5Looo=.ots,=oao3=ooooEdti
=K $>6
Zo)
.930:d!N
.=
.Yc)->f,6
x(uv.:(/,-o
r;6\r}rarnCT
Elo=9
o'edEE
!{G
A
Pg
z'6>,'.q
h-oe'i
3Ltrll3F
C.E
Z;2
6i$9?silcoE6r=F
3HsaiQ
Ri
$$;zJ>-.:d'l.q.a>
ro.JG3ert[ol,+p6(qI-aF:z
6a
EF
ry9$3 E
F*aA
E-'F
:5EE
;Fga
, 38i'5
i .:.&
*.:.
utJolu0-JIz-oulFutrOi[,',E
F
i'Hg
EE
€S
.Eb
5=p
o#;tgE^c6s;sptasg;
L
E q€
SE
Pezd8E
.EI=
E5E
H$e€sE
E.A
Ets
F
fr E
O-A.^--=
.Y
sst ;E
E*Q
E
E:
oo'CIH
'HE
: F
: o 5
Xi*cX
Ygl.9
.; =
a iE
;6E
if; E
#=
hv=9E
'9 9
E-E
tr:trI6't
a =
qE g
g
2- I
0.s:Euq.=
)6s3 H
;;gE
a(.F'
I =c
Q;
s€f.EK
.E
=frP
re,26>
tI8;.i**of;FF
gz'a.o>
...trL-od.E
;Ltr!IZ
;<lvo
.irf,9T
S€
l6E.iF
.a
EF
Eiv'G
fraav=
tr\
'S
^ Xi
;.:
g j g
jd('Jt'id^*>
tail.sEi
Hn
i 6$
9laiE
,fF
:OI i>6!sEF
dz
t\@o)o
rf)roqra)
.q(\do
oooJro $
oqoqo
o(!ctat)
oa?C
!o
oaC.l
oo
so.toc;
oc;
\-cttoo(o
@(f)
uJou(2uFuUEF
oqlFtgEUI,Elalul6lFITtul-ilrt>lctIL
ltl.,llE
l
tEt
'lE
I
II E
I+
t c
I
:l"elnlE
I
-t a
I
itF
I
EIiI
EIE
I
il '=l
Et s
I
sl El
.=tb
I
slE
I
lll,lE
l.l=
l
ou?oo,q
oqoqo
l'-qooo
1r)|r,
s
oq(t)
ou?orq
rOo-i
rDc;ro
f..--
t-roo;ao
soN
(r)J
C!
qrO
F-
ot-oN@
o(s=o
oa?oN
oo()\s
t-oqc!o
coo)ot(oro;
CO
ro;oo(o
u?(oolO
)
orOt-oq?
ou?rO
oAIr)-i
$c\lc\r
@(f)cc;
aoN
t-l'.cots
CO
c)0)
F-
(oN(f)
(o(0c;N
o)O)
|r)N
o(Ua(f)
oc!o@o
c!$tr)N
qoco
F--
(oNrr)N
C.,l
F-$
o)(f)
c.j
c{(o
ooqt-O)
C\t
qNq
ooaO
oU?
ou?ro
ooo|r)
r.c)
Ac.i
\tol(\l@(o
qsNoc{
o(9(\(f)
c)0)an
O)
slr)cO
co(f)C\l
NN(f)
0)(g
o
oc!oqo
(oCO
coc{
oIo
rf)troN
q<.
s
lOF-N|r)N
oroNvco
6lNC9
NN..ts
orOtou?
ou?rO
oorOci
oosN
N(od
cq@c\tN
o)notC
OC
Oocc)(,
vq@(o
O)
.;N
O)
d
c)(!oc?
oryocO
sc{oN
oqooo
t-(or{)
rr)
sNooN
ocr)
F-@(o
@\(o
(o\(o
oqc)
oIroq
lr)od
r{)c;
rOv@
6)o(oC
O
a\fas
o)e?@(-)
J
oco
N
oLG'
o
o(9oc!
co(oa?N
(ooq
od
(ot-t-c!qt-
@(odo
c',f..-
srO
oIou?
ou?oqo
@Gi
lr)-:oci
otr)o
rOf-..
rsa?C
\
(f)
NC!
q+oll--
6ooJ
vrr)
o(DLG
'
EI
o
oqoc.l
oqroF(oC
O
ooA
rof.-(f)(o
rOc!N
odroc{c.i
Eoo)Eo.9o-o-oo
cmcoE
J-c)J E
cooGc0)
.=o(I)o,c 0)
NI€lFlI
=$oo@U'
co(t)o()a'=m(l)oactc.oac)-co
q.F6ooc,ooEFo)gGoCo'cg7 lIIIl-l€toILILl3toIEli
-lu)lol=-o,
3a)
Joxo E
oNcllfr
N= N+nollN= E
FI-l=a,Cc)
ooG=a>-_oc0)
o
zoo(,oLoO:d
a)oo0)tz
FlO
J
ooOJ
L(Do(D
zoU'
0)O=o)oo(Doz.
oG!sE+ccLLc2
tlz2occ
ol(Doooo'-o;(l)r',c
.Eooq)
=(I,tL(oo)
U) 'l
I
aooG=C)
(oo'-o(D
zz
coooc)o-(U
a
ooo(so aI
o-l
ooIEo
o€o
Lo()(oo
dEG0ic
Nroctn
F-o(!E5c=(I
--ooo)-
o;)o((u).=
(fLr
EF.
ro:,EU)
o
lcl=t?lFljl!
EI
llrslNl+
ffilol(sl(goo)co0)Eo0)z
o=oa0)o-c.Eo)o3:
a
o0,-FEgIutllEF
l-fIt-!IttL
c,C')
c.)o$(o@od)v,(I'
ao(Jot!GoLoo
(9o)ooo(o(l)
oEftttr(g
.9agU
'(g
= (!=x(u
Eo.;o(d
I5ooooooYo3oooz
NIdl
ou?o-oI
oqooc;
@(?,
oioe.{
(Jc)L(JoLo
oqooro
lr)oo)@
zoFoLoLLo
rosq
(oc.j
o(E
oLo,oc)Lz
(o(o\tq(9
o(I,c)oJ
srr)o
c)Lct
U)
(toC
\.1oocj
o{N
ooo
coNc;oooo
cf)c\Ioo
rrI\q.c)c.j
oooI
ou?oqo
oorioc!
|r)orf)o
(of.-r@
f.-o)|f,r--
|r)F
-
oqo6oo
vro
ooLo
o(f)oC
-,1o@
NNo
oooooiv
oooo
osF
.oi
ooc., i 1.,.
r l-'
olt?N
ou?oq?
o6looci
oAroct
$C!
lONF
.-|f)co
c{vN
(ooioqct
Nrot-]..-
oN@
Ect
a
o(oN
o@oNv
(orr)N
oo
@@oiF-
o)ci
rrjF
-r(,@
oo(r)
(or-N
|r)\
lo\o
oc(o
oqort?
-oN
o|r)
oN
oc\tF
-
N
@F-
coo).+Eo-9
N|r)Ni-
o!(o
c)(E
a(f)
o.lo€
roo{ol
oo(o|f)
s@
o,u?v(oo(o
o(f,
so.lo)
@c.i
6o.,i
olOtoq
o(|on
tr)o|f);
(oolscf)
'd
o?NC.l
(oo)qC
O(f)
:ooJ
ro@
(o@
oc{oo
o|!o
oCO
No
vd)
c{c!
@|r)O
)s
st-o)
Na?o,|r)
s(9tcioc"j
o)o)r--
r{)o)|f)
loo?lo
oq(v)
ou?orq
N|r)
roo@
slN@
q(oot\t'-
NooJ
(f)F.
o)
qcO
oNo@
r)N
(r)(o
(f,
cO(oN
o)(o
c{\N(oO
)(o
o(f)
(oo)
s$qo,
orooI-
ou?ooo
(f)
(ON
la)ro
O)
o)(tr
o)C\,I
6\irN
NNctNo
oovrri
oooo
g(!a
or?c!
oro(o
ooo
@r()ci(o
(oc{qcf)
a?O)
F-
c.jN
ocCD
EohFo.cc)o
Eoo)Fo_c=
C-Jo)cc)J
0.)Eoo6c)
;oq)o)
NE=vooU)
mooC)a.Eco(I)ac'6(Do
c.o(uC)
ooco)o.ctoG)
Ec)E0)60)o3c=oo
Eoao=bJo-0)x
o3Nr)tl
?tr
d)(\3Nf6otlN= tr
c=aoEoof(u
=aoo
0)-(DEz
EF=aE0)E-o(D
o
zc)-oU'
oco)=0)o(l)(Jz
tlzz(I)
(uo)
o)(I'po-o'=6C
J
;q)c
.90)c)C)
:ou-U)
zU'
o(U
=o(oGoo)c.EG'
(Dm
dz
z
o)c.Y(l)
a
oaLodoa
U)
aoooG
'
oo
oodo
Lo
NEFoo$o).2a€)ooo=oN.c6c)T
D
NEooGq,oo(D=--O(o()'=oc)co
NEr(U
D= o(l)fo=$(Uo,C'=ooco
NErr-oo(I'oc'-(U0)co(D
=f
NEFoaU'
0)o-o)EJ-oootaEoo
c.)(I'ao
EFcr,(D(uaooC)
Go)o.v(It
Ogla
NEFoaac)
'=(6o)-o(l)E$==I
NE2\Po(u(I'o.s(Uooa0)z
g\+{a*&-/
t
rt
+
UUJ(-PuoF
ueIEttIJoouEI
IIIIFL
ago-
=@I
.cU'
(!(-)
oLoc0o'ioo-fitoo)-'-Goc0tsocooOfito
o)No)I
(\IoU)
;L(Eo-o)$Io
oo(oooEtra!
.9(!U'(E
-6ExL(!Eot(DLlgJoan^- (.),Y
O)
LJO;;o3o(l)E(uz.
JJooul uJ
==
oo660oro
EE
9FI'tF
*q-(oororoo|r)d.q-Joci
c)cF
= IC)
=
60)
E=/\-c6oc)-xooo_P
9oo-o)
a)trltr-dt
o-6oL
L
E;n
o(l)=!
E
=-=
EC
axg(o(l);bH
o-=g
4-;*(Ui(!
b-n'=bb:!
-FF
Jco=89P
,3353
o(!0)L0)
J
zl-slz.:<at(odroc)
zlzqlr)1r)(.J
RN
ErrS
rrS.rb
-ru)r
E
.Ieadg-t
X=
s? oP
;frfi .P
=pqx=
;o
irr*:oosfr E
U.F
He"tL
E=
:*EF
aEE
i(;6U^E
;OC
D6
-XiliE
;EtrE
;-,€P'iE
EE
,At
XE
ee;EE
J"(/JLU:<
rou-u- lO
F-
-qo
lr)oN
o)*,^N
-lx
,5"=€ {B
-+,I-
Ex
Rq
*ulA
O)-r
oFoix
o?x(9r$@
otsf
CD
EzJlr)@a)(o
o@dOJ
NzvN'lr)
ll N
- F
-I
-tr c"jeil*E
=I
+(O
O|r)\t
;c.c\c;(o(O
OC
r)Xo@
-S'^
tr:xdN
ro(c;N
rlI(e
Errurrtlb
L>i
H
x 9_(g
Y
.^ --
o, :
sg:
oEX
-c*eq
; o
lrrOO
,ao
92 =qE
:5E
E=
Fb.
9'n+X
.e3
6sE€H
PoE
6=oIa
6ofo.Y(l)!9s
;i-!.3EE
E€
Y9.tsfihX
(J-
P=
6y-=.=
J vae.
<tLlL
NEz@^lLr'@
$€6zEx
€ao'6e6oo
(oro@
(f,
c!or.@@
st,-
sso)N
ooo
zoo@
NEz:aroros.9H=
oE
Eo!t
olt)E=U'
ooo)oE-oU'
c)o)0)EU)
c)P0)E-oo
og,(l)EU'
og,oE-o=o
oE9=
26o
oooo(J
(U
()([f\
o(5a
zS
lNl*l-lS
l3o
--3*c ,^
ocL=r6.Q
EU
6qoE
E.coF
Et-
Es
Erl)N
Eo
co
Eo
FF
-Ltrlt_[ltl!)-!>yxod:
q e;
x E
ieq
;oirroo)n"
q)9N
9? .JF
Ph
=dt
E;.F
E3
EF
sf frEqE
-=oit
::EE
€9856
b,E=
8.:Ee
.r589P.3
J"AE
<tLtr
tr tr
=c.l
-(oE
3q85o€-oE
;l.--\
Nc.j
cl3rEg'a#raoooellEF
o\
Eooq$
Eoooi
Eu?o)
Eooc'i
Eoq(f)
oo,(EJ
Fo6l
ooof--
orO(oN
orOcdN
oq(')
EoL
orf)N
oqF
-.
oq(oc!
orocttC
.l
z.aoq(!(\<\
co
zzzzzzztzlzlzlzLY
Y(f)oN
o@(oco
oo(oco@cov
c.i ci d
cci c"i +
oi(\@
roo)N@
o(\coN
N@
EE
zz@sfO
r(Oq.q
qSci
|r)o,Oo)
oc)o
EZo
.:to^
cY)
5xc; crr
OX
Nd
tl
NcD
@l
klbl-lol;lflc)
.9.aO6Fo'-TL
-Ncq$tf)
(I)(D0)()c)
(s(u(EG
OE
ee€Eild)O
OO
o)
8;EE
€EE
oroooo#P
P33E
;(5GG
N(o
ooaaoa\
'6'6 '6'a
'a
PcE
99e'H
aoto66gE
EE
SE
EE
EE
PB
TII
I'L LL
[L LL
Lo
z<)
tloo$0)
-i*z-6;Etla
tlsttttttll
ro(l)^n-nr(D
:
==
x::'o>
e
Yr#-
=$oo)
xi;68(Oci d
g) cc A
!*too::
ii H H
3;O
.ltrE4:tj:Z
P-e)R
>>
-=
9=
9;EE
q,dlt>
-$ox.od!coo--T
cO>
cooo:-'rof=
ooggE
P,P
'EB
-*E
EE
EF
HU
HE
bg9co-i-{v.cAbc?
.,(DO
rr-nllll.,xr=
'_Lrld ^4.d2
a q
aaooLE)
ILl(,t-tztIul
zl<@no)o@
z-v,qO
)o@
I(o0)(gc)oc)
.2oo)ooLL
N$i
,rzlz3
oro()
*-!'- ll
x!o
bo -tr
ll $
-N*-
>Q
>
,ooqE
ritrs"l<co
@,^--X
$x+
UH
6ct N
orooooPx
o)., 9x;;
coo::
"p&;
nlox\Y
rf)o()@
RE
rn,ttttrrllSrr
a X
seoeBc.i
3 *i"
G'
..r e$Q
eshs=
gtsLA
gL
=rr
:.8 [
3li dF
PE
,-c
EE
i.EB
fiEF
=:g
s EE
.EfiF
9;ss. s E
E E
?E !:
E E
;nE,E
EE
^'€EesE
q 6E
eEE
b;IE
illrol-lgoeo)(!.9o(DLEF'Tt-L
*=4
6s\*s
Zij
-FF
s55I
..i c; .ri ooiF
-xI
or t'-
ox\o(o
llo(oooo(Uao)co.ori
llo'u)o-coO0)(o
Nz,;
Ett^tt
exYt^
c{-x
9q5ll^oEE
9
=R
L E
3 6F
E^9a6C
.:-eE;
b;ib.s5q 6;p
t1
$Lg()tsooo(5.9,ooGF.9Lll-
zu)rO,,
ttrflp*
;EE
qE
!xH
-oro$iqsol
o^950E
*qN
q
oxt-o
il0)o(Dooo-ooI=.9l!
tlE'ao-Eo0)(t)
Ezll@ri@
trll ojll
9xc;x
EE
-llaAE
E
9
=.R
b- Ic->
b at'$oE
Gq
+c
? 9l;rtsiX
9or
o#:j
o6il.
t\t\\
I\\''.
i
II
z,:aol-froco
Io-oItto3+o,oo.9oo(EoII.EgCL
oFctG'
o.(Eogoo
zveNool
oooO(,
8dLU)E
St=
B
;q? rl
-Rs
pi e
<q,
+.9
_eE'aEo=.aEooo-o.
aEoov€9r
b,=ha*sn
EE
Er
gb+
igbr.-E
o
^E3E
F
E h'3 t
x3 F
=E
s-
;F
E F
oqocl (E
a
e€ P
tH
>e
=cL@
=('cl
o>.c
ztrF
.-Pcc.v
.v.
-(\oqqo, (0@
tl,6
!toBo
GX
-cL I
E=
I ^>o-oorx.!rE
U5-C
)<u
'u00>
=-
b8'g!br.9 b:E
'6-o
E8;
ztzoC;
r()o)<
irI@qsrI
04,qNF
-olr)
tl
tlPO
^Xl
E$e
Hd '
tro-€b14
rr
ocrE'=
';(D**o_*bflo-a-co)E
E'E
g5E9e=
(U()E(1).=
utl
llu?(oxoc!o.9oexGoLo(Dao-c!tlo'd.
c,CL
0E.9a)=={)U'oooEo)
o
N
co-zzE
.!ZIZ
(\I C
D
CO
Or(O
@s
(0(0t+IN(0c;Io@tl
U)nu0.J2I0uou
E'oo)
=,
'jjG=(Eoo(DooItctEc)oooogIGo
ztf)f.-ol(a
ctcoooGo(!€e---1F
x-'-ooooooerolr)u"
(\loroIEj:-rr'(r)V=o-cIt!o.U
=
ro@cct
X.roo;(,(E
b'6;otro.'aoxeE
":'E
cr-LfEottso€0,P(g=
o^5E
c06 E
rEoE
Oo-O
.EEc,
o
o.9o:r 6ril
Eo)
ooFo
-YO
9G'
-L3q)E(I'z
Y-,=
E6
E5E
=
A=
EE
fr ;E
g,X
bpE
EoE
EF
EH
#b 9 b 0-gc:l:-0o
8.8 = H
E
oq,Yo
EfF,E
6zE5
9>h
J=oobboo
ro@oro@@
@Nd
,98--
ttE
FoE
Eq)ooEa
oq)Ea
Ec)oc.)
Eo
zo-9'6=
(/)
caco
eEoou, !tP
'6E
8trg
EoU?
EE
|tr)o(o
-ooLooJ
0oE-oo
oc"j
oros-
EftEFo
|r)
rf)\O+qxr.r)t*A+q
N
tr:!scoxcolf)
cf)
-tOXNI tl
tl
o_
ooc"j
u?L0)oJ
EE
zzlz .!a
lr)-@
o)doi
Eo6E-o u)I
t--O
? (\l
:'3(/,+c.^8ilxro@
E
oc;
ro
uq+N
F
-Z-tzX6-E,
cf)
u?qXqXNtl
ONzzo|:@
(oN
odtr,^-o c{A
a^i
.>=
'6+fiu:/<
F
\U
oX(oN
qso;N0)tu) Eq@
v
ilrloO-
o-<
:.?Fo(\lLo@,.rFF;c)0)IIo)o6IoF
oooo(oo
oooozg,ooooc)(E
ooo.Eo(!o
NEzs\cf)
tof.-F-Xlr)\N+OxXo
EE
zzro o)dN
@
Ec)o) .^
;q(/) \r+.
i u',
(,-+(l)XO
LocCJ
Eoi
il ll
o-
f--cci
EE
zzPP
U>
r)"1 N
O
c? c.j
-s^N-z
E
R.q
Y'
co (oorLc)C
(o^^-^vfc!i/(/),ri-
m^
)"' a
!Jv'=c:{xoq{^oo=X
;cO
nc',1 5
eO-
Crv
\il
ll
o-<
rOF--
c;T
EE
x>
>c
i<Y
F-
@F
-droNoo 'ri I
9Xq:
gaoo)Y
'+(D
x@E
o6lo)v(ro->
.ll lr
ll
="da+
5opo'Y
X
Eco
ooL
z.vo,o?|..-C
\j
cct
X.roO
rgoJ_h'6;o';oxeE
{:'=
oo-o50,aE
=-o+o
06 0-
oEO
- q)Loo
N----Z
-P
FF
V-
ooooootr)O
OO
OK
)sO
O-O
r--N
N
o69qc!oa)/
(v,E
q) o
coo
o ! '=
Fo
E I
=38
;=
i-A
O:
-ooPi;
EF
n'"6rcY
'mq)
>
F.E
.E':
E*
53539v^E
^^!nrE
-E;i0)
v*':-*x(/,-u!-=
-gO2
=
-6=,.
*+
-'p !l
o89=
BE
.:G'
6)
oE(!LEt
(!o(E
ExL=oF(!J
s€iz-l<ll
;'-=ooE
6oo
(o(o@Lr);
(oNorr)(o
stt..
$$N
,98=
6E
Eo!t
c)(Il=(It
!LoE=
0)0)EfU)
q)L0)--of
c)o)oE=a
c)hL0)E=a
.lJEf
zNN
|-..N
rO
o_go=(/,
FGC)
c(I'(E
od-
C(tra
o?od)O
F9'6;o.=
otrt
Eq
EO\
E$
EE$
Ez
Ez
oc)
ooJ
Eo
o-0)=do
oNCO
of--
oN
o()N
q
a)$
FoL
roN
@F
-@N
odC\t
Eoo=.EL([=EI(!Lo0,
o0)o0)Eq)Q
)aooGJoGo
ffi/f-/t
!.J)(si\
tr:l\gfP
*r!fi9Ira i
t4!hPt5;ii-"tE
uirrEil'ITtttILr.g
(D>'(E
J
\
i
l
I
AN
Nl{)O;|f)(oIt-o
\fcr)
|r)No
+tL
NN
NO)
os
(\l\sN
a!o
ovs1..-
cf)\NN
F-NN
(ocr)
ztl|r)
$@
(oK)
lirf--
CO
ooroN
Nz.:<oo-
f.-c',1
rocr)
@co\r
NNo)o)
-|.-
\ro
rf)s
ozq)GJ
Nco
s
Nr{)(!o-tr)N-o)q,oU
t
fitoF
o)cloo(Eo
oooo)ozLoc,oo(It
ooo(Jt!o
'E'E
z. z.Y
Joo tf)
o$(or''- [
+
o)PO
)NxEa
x9+
oP
,Lo o
EE
=
RtY-oN=
@o
|4q--ro
X
tt!'N
o
9c.ibxxO
o =
n=f.-o-o oo
Eqvolr)(oNOqt-
C)
cr)vsN
cf)r.-^iN
t--
NN
(oco
dzt4(L
t-qlf)cr)s
o)@N6
N\o)o,
Nztlo
Lr)f'-
oof'-F*
roNrr)t-@
zJzo
rOF.
oLr)|r)f.-
rf)f.-
o(!J
oO
(Dac)cir-
oO$O
zo
NNF
-
o(!LL
NoooLL
COOoLolJ_
vLc)
;lJ-
8L'91lA
Scqseld uoN
60'8W
'LEz8'e9
69'000'0
pues ^llrs00'6
09'v
9t'8 tC
S0'02
0'6t0'6e
e9'e79L'09
t9'900'0
00'0pues /ie^elC
09'700't
00'92vL'91
cu ot
0'8 !0'Le
60'0/9Z
'ZZ
vvz00'0
00'0Ie13 Ipueg
00'€0v'l
zHs
LO'LI
tc0'vl
0'6 L0'te
e6'8969'6 t
t8'e L
eVt
vt'l[e13,{pueg
0r'6209'LZ
,L'rztc
0'020'8 t
0'8tzz'9L
,0'tzI l'9
00'000'0
[a13 Ipueg09'LZ
09'92
Lt'6'H
C0'8t
0'020'89
z8'8600'0
I L.t000
00'0A
e13 Agl1g
09'9z08'0 t
9t'zeH
C0'tt
o'rzU
9Yt8'vL
t;LO
L LI.8L't
t6'0,(etC
,ipueS08'0 t
09'6
w'8,
INS
c4seld uoNLLY
tv'v,L'' LL
60'z00'0
pues ^l|!s09.6
09'L
tt'vLts
cqseld uoN2,8'Ll
,u t,uvL'6'
t9'000'0
pues fltts09'/
09't
96'Llcs
0'zz0'6 t
0lveg'6t
LZ'9V
,v900'0
00'0pues,ia^el3
09't0z't
89'6 ttc
0'020'8
t,udc
60'zLe9'lz
00'000'0
,{el3Ipueg0z'r
0?'ltH
8
qJEuau
.Tl
o-O!<
o-€
q
%ilaluoceJnlslolN
lEJnlE
N
c)oa,o-#6o=
i.o
td1d
1-lsau!J
ulul9/0'0
tuulgzi'0
tuur
00'z
tutu
9L'i11og 1o edltl
oIr.uoJl
oNoloHorog
sl!ur!'l Fraqragy
% (o^ars S
Iu! paulelag alcluea) s;sfe;euy a4S
ulere(u) qldeo
'S60 009 - leuuoqC
'ureuer6l1eg le .,lle4 xl.rleu1 aql ul eore U
!'l lo uollcnrlsuog : pefo.t6 Jo eueN
qlnsag 1sa1 ftoleroqe'l lo alqPl
'a
-iIII
t,L'v,-14
OL
0'020'Lz
Ub Z
Otr',
t60000
00'0[eto ItttS
00'6200'Lz
8e't9H
C0 9r,
0'tz0/9
8Z'66
zL000'0
00000'0
IetC IlttS
00 Lz00'9 t
99',92IN
Sc[seld uoN
zv 0t89'69
00'0000
000pues IiltS
00'9 t09't t
zL'9t,t-tJ
0'?eO
'ZZ
0'9988'.L6
0L tzol
00'0000
,iet3,ilttS09'e t
09'0 t
r0 8tlc
0'60'02
ia7,8't9
89'ZZ
UJ Y
l,00'0
00'0ttetC
[pueS09'0 t
00'6
sIrElxsu
-Tl
-o-oi<
o-{
g
%lualuocaJnls!ol^l
IEJnleN
c)a*ao
td-ld
1-'lsoull
LUtU
9/0'0tutu
gZV
'Otur,u
00'zturu
9L'V11og 1o adA
loI
r.uouoN
oloHorog
s1!urllOraqragy
yo (ela1g g1
u! paulElag elcrye6) s;sfeleuy azls ulE
J9(u) qrdeO
wg'L- 9't qldao lH
s-----ru 8'01 - 9'6 qrdeo tH
E - . -
ur 9't - z't qldso tHs ....'.'..
r.uru u! azls ol3luEd
t'0
ru 9'6 - 9'/ qldao lHs' - -
u.r Z'C
- t'l qldao LHE
-T
0'0
UOI
ozn90n0sUJ
OL
08
-Ito-oo-r1
o€o
0600r
'€60 009 - leuuaqf,'ueue;311e9le ,,lle[N
xlJleru aql,, u! eaJe U!] Jo uolpnllsuoJ
3rd03d rvclNH
9flo3s) rHJ-
I Hg A
AU
Nf, S
ISA
'IVN
V gZ
IS N
IVU
T
w 9'/,Z
- 9'92 qldsq lHg -
ruru ul azls alc!ilPd
T.0
ru 9'92 - 8'01 qldao tHs- -
T0'0
r00 00OT
oz0t0n0s09080600r'€60 009 - leuuorll 'ueuer81;e5 le ,,llel1l xplenj aql,, ul ealp lJll lo uolpnJlsuo3
3f dogd fvslNH
tftof I
3Hl 1'oo-no€o+
I Hg f,A
UN
] SIS
AT
VN
V A
ZIS
NIV
U'
w6z- Lz qldao zH
s . .-ur9'0!-6qldaqzH
s---w
Lz- 9, qtdeo zHg-. -
ru 9t - g'cl t$doo zHs- -
ru 6 - 9'? qldeo zHg -----
ur 9't - e qldaq zHs .'.......
rutu u! ozls alcluBd
T'0
ur g'cl - 9'01, rDdoo zH
s - . - '\
w t, - V
', tlldao ZH
g -
'r..
r000O
I
0zUE
ovU:
09OL
0806007
'oooof!oE{L(05
/'/
--4
-r''2<
=
-:'1''
//.;
.la'
/.
i,
!/t
'€60 009 - leuuaql 'ueure;81;e5 le ,,llelN xulen aql,, u! eare U
ll lo uolpnrtsuo]
Z H
g AA
UN
S S
ISA
'IVN
V IIZ
IS N
IVU
C
o\tr)
.C; o
3Ee
sfrfie);
@,q
a FE
Ni(o9
\.
6U=
c !q(I'E
6;AA
_fuo(D?iO(5s
0
ooo@
EoTo)NooGc-doo-c)
cn
UJU{IzoUFiloIF sJ)so
ricue;srsuoc
7 r(lrsuapaA
rlelau
Efts
66EB
;F@
lt(5I
oILCJ
aoFCoEoc(Do-o$
o= ooEfz
zt\
(o(\l
rt)F
F^6-N(')
(o(o
@N
s(o
(oE
_b*oC
9N
N(o
c)o
ou?Nol+N
|r)(oN
olr);N
onN
relel Josssulsrql
'-6aoo
G1loU)
-v.
co
'ti cr
AF>ou>-
o';d)>1n
o_: e(l)vooE
oqc{
rONN\i
(9o)ooo@I(6oo(E(g
.9(gat,(5:=(!ExL(E
=oFIEo(E
hJooPao
o>aco
(Uo<J)
c=(D
qc!
EO
3Ee
BsF
s>
;(ou?sr 6 E
NY
^oP
cotr
qoU()
'Ec
!r2 (gC
6o.;gl ii(D
O
(UE
oc)ao)6'o-
oiioi.*-+
'*T
@l
lltltltltltltltlEl I
ot I
3l I
ilt I
3t I
cl I
Ft
II(t)t
I
*l I
Ltlot
I
'llIt_l)o| /g
I (EH
I iB4
I l#E
I ips
I I'U
I lrl
I tt'
tt:ttEttL| 1'6
I;1,
1.+
rat
t--,{;
fcuelstsuoc/ A
lrsuapoA
Delau
E=ts
35tsa
EU)
.c)
GIa.o)
U'
o)Fcooc(D(L$a
U'
= _9o(D-oEz
z(o
6)$6l
ooh5s
(o
N(.J
3
_6*totO
rC
f)(o
-c(Doo(ae{
oLr)N
F-
No)
reriel 1ossau13rqI
o$i
Eot
+r'O.6.H
q)
a-8=f11
=ooOe
OF
=(6
'E(,
ooc)oE-qc
gEd
l.=No)N
{tiII!,,t
Iqtttill"tlrt
elBcs ol loN'e60 009 - lP
uuerlc 'ureuel6l;e3lp,,lleht xltlE
lu aql., u! paJE u!-t Jo uollcntlsuoc
: lcalold Jo erueN
\\
NO
IJYJO
T IIT
OH
!TU
Og
3rdoJd avslNB
JeJ'9ao :H
t
CA
P: 2,65,000 Litres
RA
W W
ATE
RU
.G.S
UM
PC
AP
: 4,00,000 Litres
FILTER
ED
WA
TER
U.G
.SU
MP
CA
P: 5,00,000 Litres
FIRE
RE
SE
RV
EU
.G.S
UM
P
FLOO
R LVL
GR
OU
ND
FLOO
R LVL
BAS
EMEN
T
SO
FTEN
ER
FILTER
SA
ND
PR
ES
SU
RE
CH
LOR
INE
DO
ZER
SA
LT RE
GE
NE
RA
TION
TAN
K
CA
RB
ON
FILTER
AC
TIVA
TED
RA
W W
ATE
R P
UM
PS
HO
T WA
TER
GE
NE
RA
TOR
HO
T WA
TER
GE
NE
RA
TOR
-2(H
OR
IZON
TAL TY
PE
)1,00,000 K
.Cal/H
r
MA
KE
-UP
WA
TER
PU
MP
S
HO
T WA
TER
GE
NE
RA
TOR
1,00,000 K.
CA
L/H
NO
-21,00,000 K
.C
AL/H
NO
-1
PR
ES
SU
RIS
ED
DA
Y O
ILTA
NK
500 LD
AY
OIL
TAN
K 500 L
FOR
HW
BO
ILER
MA
KE
-UP
TAN
KS
OFT W
ATE
R
HO
RIZO
NTA
L TYP
E H
OT
WA
TER
MIX
ING
TAN
K
VE
RTIC
AL TY
PE
HY
DR
OP
NE
UM
ATIC
PR
ES
SU
RE
PU
MP
(2 WO
RK
ING
+ 1 STA
ND
-BY
)P
RE
SS
UR
E V
ES
SE
L2 N
OS
HY
DR
OP
NE
UM
ATIC
BA
LL FLOA
T VA
LVE
BA
RR
EL
TAN
K
OIL
HO
T WA
TER
GE
NE
RA
TOR
-1(H
OR
IZON
TAL TY
PE
)1,00,000 K
.Cal/H
r
OVE
RH
EAD
TAN
KFILTE
RE
D W
ATER
R.O
WA
TERO
VE
RH
EADFIR
E RE
SER
VEO
VER
HEA
D TA
NK
TANK
RO
PLA
NT
HIG
H P
RE
SS
UR
E P
UM
PS
FLOO
R LVL
FOU
RTH
DW
S
FWS
HW
SH
WR
FWS
FWS
BO
RE
WELL
FLOO
R LVL
FIRST
FLOO
R LVL
SEC
ON
D
FLOO
R LVL
THIR
D
(MO
NO
BLO
CK
PU
MP
)(I W
OR
KIN
G+1 S
TAN
D-B
Y)
HO
T WA
TER
RE
TUR
N/
CIR
CU
LATIO
N P
UM
PS
LEG
END
NO
TES :
TO G
UES
T RO
OM
TOILE
TS
(HN
S S
YSTEM)
SY
STEM
)
TRE
ATED W
ATERO
VER
HEA
D TA
NK
FLOO
R LVL
FIFTH
FLOO
R LVL
SIX
TH
FLOO
R LVL
SEV
ENTH
FLOO
R LVL
EIG
HTH
FLOO
R LVL
NIN
ETH
FLOO
R LVL
TENTH
FLOO
R LVL
TERR
ACE
FLOO
R LVL
GR
OU
ND
CA
P: 1,40,000 Litres
TRE
ATE
D W
ATE
RU
.G.S
UM
P
(MO
NO
BLO
CK
PU
MP
)(I W
OR
KIN
G+1 S
TAN
D-B
Y)
TRE
ATE
D W
ATE
R TO
OV
ER
HE
AD
TAN
KV
ER
TICA
L TYP
E H
YD
RO
PN
EU
MA
TICP
RE
SS
UR
E P
UM
P(2 W
OR
KIN
G + 1 S
TAN
D-B
Y)
PR
ES
SU
RE
VE
SS
EL
2 NO
S H
YD
RO
PN
EU
MA
TIC
LOW
ER
FILTER
TO TAP
BY
-PA
SS
CAR
TRID
GE
CAN
DLE
U.V
.FILTER
HO
USE
KEE
PING
TAP
PAN
TRY
DW
S
VER
TICA
L TYPE
HYD
RO
PNEU
MATIC
PR
ESS
UR
E PUM
P(2 W
OR
KIN
G + 1 STAN
D-BY)
PR
ESS
UR
E VESS
EL2 N
OS
HYD
RO
PNEU
MATIC
FWSLAD
IES
TOILET
TOILET
GEN
TS
RESTA
UR
ANT
TO B
AR /
TO K
ITCH
ENFO
R D
RIN
KING
TO K
ITCH
ENFO
R C
OO
KING
TO IC
E CU
BEM
ACH
INER
YTO
KITCH
EN
FOR
DISH
WAS
H , U
TILITY , ETC.
FIRE FIG
HTIN
G PU
MPS
HYD
RO
PNEU
MA
TIC SY
STEM FO
RD
OM
ESTIC
WA
TER
SUPP
LY FO
RH
OTE
L FLOO
RS
WATER
TRE
ATME
NT PLAN
TH
YDR
OPN
EUM
ATIC
SYSTEM
FOR
DO
MES
TIC W
ATE
R SU
PPLY
FOR
SH
OP FLO
OR
S
HYD
RO
PNEU
MA
TIC SY
STEM FO
RFLU
SHIN
G W
ATE
R SU
PPLY
FOR
SH
OP FLO
OR
S
HO
T WATER
SYSTEM
MEZZA
NIN
EFO
UR
TH
FLOO
R LVL
LADIE
STO
ILETTO
ILETG
ENTS
DW
SFW
SD
WS
FWS
LADIE
STO
ILETTO
ILETG
ENTS
LADIE
STO
ILETTO
ILETG
ENTS
DW
SH
WS
HW
R
DW
SH
WS
HW
R
(GR
AVITY
(HN
S S
YSTEM)
TO G
UES
T RO
OM
TOILE
TS
(HN
S S
YSTEM)
SY
STEM
)(G
RA
VITY
(HN
S S
YSTEM)
TO G
UES
T RO
OM
TOILE
TS
(HN
S S
YSTEM)
SY
STEM
)(G
RA
VITY
(HN
S S
YSTEM)
TO G
UES
T RO
OM
TOILE
TS
(HN
S S
YSTEM)
SY
STEM
)(G
RA
VITY
(HN
S S
YSTEM)
FILTER
TO TAP
BY
-PA
SS
CAR
TRID
GE
CAN
DLE
U.V
.FILTER
HO
USE
KEE
PING
FILTER
TO TAP
BY
-PA
SS
CAR
TRID
GE
CAN
DLE
U.V
.FILTER
HO
USE
KEE
PING
FILTER
TO TAP
BY
-PA
SS
CAR
TRID
GE
CAN
DLE
U.V
.FILTER
HO
USE
KEE
PING
FILTER
TO TAP
BY
-PA
SS
CAR
TRID
GE
CAN
DLE
U.V
.FILTER
HO
USE
KEE
PING
FILTER
TO TAP
BY
-PA
SS
CAR
TRID
GE
CAN
DLE
U.V
.FILTER
HO
USE
KEE
PING
TAP
PAN
TRY
TAP
PAN
TRY
TAP
PAN
TRY
TAP
PAN
TRY
TAP
PAN
TRY
PR
ISM
CO
NS
ULTAN
CY
GEN
ER
AL S
CH
EM
ATIC
0
PLU
MB
ING
LAYO
UT
CH
ER
ALATH
AN
AS
SO
CIA
TES
-------------
PC/C
HE/P
L-0
1
WO
RKIN
G D
RAW
ING
PR
IVATE L
IMIT
ED
AN
AN
DR
AM
DEVELO
PER
S
MALL A
T S
ALIG
RAM
AM
CH
EN
NAI.
PR
OPO
SED
MATR
IX
DIA
GR
AM
FO
R W
ATER
SU
PPLY S
YS
TEM
PR
OP
OS
ED
HY
PE
R M
ALL /FO
OD
CO
UR
T / MU
LTIPLEX /H
OTE
L / RE
STA
UR
AN
TS / SHO
PS/ C
OM
ME
RC
IAL U
NITS
740741
742743
744745
746747
748749
750751
752753
754755
756757
758759
760761
762763
764765
766767
768769
770771
772
794
795
796
797
798
799
800
801
802
803
804
805
806
807
808
809
810
811
812
813
814
815
816
817
818
819
820
821
822
823
824
825826
827828
829830
831
840851
852853
854855
856857
858859
860861
862
863864
865866
867868
869870
871872
873874
875876
877878
879880
881882
883884
885886
887888
889
SEW
AGE TR
EATEM
ENTP
LANT
FIR
E R
ES
ER
VE
WA
TER
U.G
.SU
MP
Physically
Challenged
Parking
U.G
.SU
MP
RA
IN W
ATE
R U
.G S
UM
P
BA
SE
ME
NT
EN
TR
Y
SU
B - S
TATIO
N
853853
853853
853
FILTER
ED
WA
TER
U.G
.SU
MP
RA
W W
ATE
R U
.G.S
UM
P
TRE
ATE
D W
ATE
R U
.G.S
UM
P
SE
WA
GE
TRE
ATE
ME
NT P
LAN
T
PU
MP
RO
OM
FOR
STP
C'
C
D'
D
RE
F. DW
G. N
O. P
C/C
HE
/PL/037
PU
MP
RO
OM
FIRE R
ESE
RV
E WA
TER
U.G
.SUM
P
PR
ISM
CO
NS
ULTAN
CY
PLU
MB
ING
LAYO
UT
WO
RKIN
G D
RA
WIN
G
PC
/CH
/PL-0
10
0
PLAN
DETAIL O
F PR
EC
AST R
CC
CO
VERFO
R S
TOR
M W
ATER D
RA
IN
AA'
STO
RM
WATER
DR
AINS
ECTIO
N - AA'
GL
SEC
TION
XX'
X
PLAN
X'
RAIN
WA
TER
PER
CO
LATION
CU
MC
OLLE
CTIO
N W
ELL D
ETAILSS
CA
LE : N
.T.S
PR
OPO
SED
MA
TR
IX M
ALL A
TS
ALIG
RA
MAM
CH
ER
ALATH
AN
AS
SO
CIA
TES
FILTE
R B
ED
10
FILTER
BED
FILTER
BED
CA
PA
CITY
: 1,10,000
Y=';
EV
GU
Oh
ro 'o.-s
u<.
oji s
^F ;o)D
Ou..
9"-X
NiNO
O)
+co
4N;NGrn
U|.n
:- @
(!N3v6tq
3rGo)
G'
P+
ul 6oF+
)zG
<a-Fl)=o;ul^U
t:<
;lJbol-o
a-ufUa
Z:
dd,tr:<
;
c{e.l
C\
F\
.r<z
'6r\g.
trrr;+
o>\
LA<
^' a 1
--o:i"-
9.\|.
=u
UIU
d
t-,rP,.ti-dtat'L.-.othg
!'r
-8=€6dl^=
\J)
tJ',-,t
v)q.2de\&-h
=-U<
iiz1-___/)!i.Z;:.-t;!.
lht<Ltt)
P
rn$
Nct?
Nrlr-l
.++g\md\0N
tr(UL
J
ttt4(Dt-l-!.
bo
tt)V'
t-(cFLc)
tF
TiT
Ere
!9=;
=:o+
t^*
.=lE
-ciro':oD
-zFqA
G*=
!€Po-q
'FP
E:h
o. d F.E
=?E
ivl
iPF
F'l
*F.E
$'v=;€m
l,O
F.;t-rrg
a+5cdU
q€Em
'iln€E
E:O
trOX
H=
;lrll
=atrtr
Fl
e!14\tr<
l )E
Rco-G
)ot
{'- H
El
>89e--
FI
KE
ES
iollloooi:)=gIJL
CJI
j)lDG
I
i =
>
oo-E9aor.$(l)-C
EA
(6-
PR
EiE
.; (d
:F=
!xnbF
zU
:i.Eiro;'io=-P
62.:o.ri€p=E
lEE
(Jru!
-o)m
LL^
oNo':(d
=4:=
lFo:f
9Flol:
>O
\OO
EF
9orc)XZ
r-'A'otr
O-\vd
-cjct-i:L+
Cc.)b!c)
ci=99=
E
=sl 5=
,9=
z4h
zP(6t-OJ
trlr.
o(!()\CJ
Pl-U
h
&;
rJ?.
.-t ci
4'/ F
{
trs
n;t*FE
{iiig**g$gq
IES
S{€ a5*g-
xsn.=
::€I€a €i;:
g'irg€ E
;g EE
iEg* aas
npE=
nY E
-{r*'* ivfr
Axe;aE
gEl;
?;r n
-3$sE3 gT
-;gEt E
{E_
;HE
3Ea€;iE
iI;I9*Ar€ats8 H
€Ea*F
, 1?Bg
fr
iE
H*siE
Si€*e€€€ atii
EaEs E
q 3}3*€g: E${€?ar ;t?B
79 A
l€ +
t;*r.
F ggig3 nugi*gg: $€E
3#€e 3 E H
E g p
E
11E.T€lL)E
)ustr6r5
.:aa4glat
2C81c4;t
rlo56flrqd€D,I6\n!6f*ql+tro€diO
!
@.:rs{JApeEry=Tcsod3v;it.qlo&
Fr
Hr-'lF
{F
.{F
*{$&w
4'lF
q
hI5rL'C
f4tV,
A,lrlwt4"F
ll'--lptA
.F
(A\tF
lf-'l
ItARHe4.'|
fv.F
qftlF
{
zw{
IdII{iI