m/s. anandram developers pvt ltd., form...

121
M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 31 FORM IA (Checklist of Environmental Impacts) I. LAND ENVIRONMENT S. No. Information/Checklist confirmation Details thereof (with approximate quantities /rates, wherever possible) with sources of information data 1.1 Will the existing land use get significantly altered from the project that is not constant with the surrounding? (Proposed land use must conform to the approved Master Plan / Development Plan of the area. Change of land use if any and the statutory approval from the competent authority are submitted). Project site comes under Commercial Zone. Documentary evidence for land use classification and land ownership is enclosed as Annexure IV. Attach maps of (i) Site Location; (ii) Surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plan. The proposed Commercial development is located in Saligramam Village, Egmore, Nungambakkam Taluk, and Chennai District. The Topo map showing surrounding features of the Proposed Site (500 m radius) is enclosed as Annexure II. Master Plan is enclosed as Annexure I. Contour plan is enclosed as Annexure-III 1.2 List out all the major project requirements in terms of the land area, built up area, water, power requirement, community facilities, parking needs etc. Total land area: 18149.26 Sq.m Total built-up area: 88779.20 Sq.m Total Water requirement: 438 KLD Fresh water requirement 160 KLD Power requirement : 6.14 MW Mall: Car Parking Provided: 796 Nos. Two Wheeler Parking Provided: 1094 Nos. 1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to the proposed sites? (Such as open spaces, community facilities, details of the existing land use, disturbance to the local ecology). Due to the construction activity, impacts such as air and noise pollution, wastewater generation & disposal and solid waste disposal, are envisaged, but with the efficient implementation of the proposed Environment Management Plan (EMP) adverse impacts will be minimized. Please refer to EMP enclosed. 1.4 Will there be any significant land disturbance resulting in erosion, subsidence & instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc may be given). Based on the type of soil and contour of the surface there won’t be any erosion, subsidence or instability. The project site falls under Zone-III of the seismic category in India and hence the vulnerability to earthquake is not so significant. 1.5 Will the proposal involve alternation of natural drainage systems? (Give The proposal will not alter the natural drainage system. The contour plan of the project site is

Upload: lamcong

Post on 25-May-2018

238 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Form 1A

M/s. Eco Tech Labs Pvt Ltd., Page 31

FORM IA

(Checklist of Environmental Impacts)

I. LAND ENVIRONMENT

S.

No.

Information/Checklist

confirmation

Details thereof (with approximate quantities

/rates, wherever possible) with sources of

information data

1.1 Will the existing land use get

significantly altered from the project

that is not constant with the

surrounding? (Proposed land use

must conform to the approved

Master Plan / Development Plan of

the area. Change of land use if any

and the statutory approval from the

competent authority are submitted).

Project site comes under Commercial Zone.

Documentary evidence for land use classification

and land ownership is enclosed as Annexure –

IV.

Attach maps of

(i) Site Location;

(ii) Surrounding features of the

proposed site (within 500 meters)

and

(iii) the site (indicating levels &

contours) to appropriate scales. If

not available attach only conceptual

plan.

The proposed Commercial development is

located in Saligramam Village, Egmore,

Nungambakkam Taluk, and Chennai District.

The Topo map showing surrounding features of

the Proposed Site (500 m radius) is enclosed as

Annexure –II. Master Plan is enclosed as

Annexure – I. Contour plan is enclosed as

Annexure-III

1.2 List out all the major project

requirements in terms of the land

area, built up area, water, power

requirement, community facilities,

parking needs etc.

Total land area: 18149.26 Sq.m

Total built-up area: 88779.20 Sq.m

Total Water requirement: 438 KLD

Fresh water requirement 160 KLD

Power requirement : 6.14 MW

Mall:

Car Parking Provided: 796 Nos.

Two Wheeler Parking Provided: 1094 Nos.

1.3 What are the likely impacts of the

proposed activity on the existing

facilities adjacent to the proposed

sites? (Such as open spaces,

community facilities, details of the

existing land use, disturbance to the

local ecology).

Due to the construction activity, impacts such as

air and noise pollution, wastewater generation &

disposal and solid waste disposal, are envisaged,

but with the efficient implementation of the

proposed Environment Management Plan (EMP)

adverse impacts will be minimized. Please refer

to EMP enclosed.

1.4 Will there be any significant land

disturbance resulting in erosion,

subsidence & instability? (Details of

soil type, slope analysis,

vulnerability to subsidence,

seismicity etc may be given).

Based on the type of soil and contour of the

surface there won’t be any erosion, subsidence or

instability. The project site falls under Zone-III of

the seismic category in India and hence the

vulnerability to earthquake is not so significant.

1.5 Will the proposal involve alternation

of natural drainage systems? (Give

The proposal will not alter the natural drainage

system. The contour plan of the project site is

Page 2: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Form 1A

M/s. Eco Tech Labs Pvt Ltd., Page 32

details on a contour map showing

the natural drainage near the

proposed project site)

enclosed as Annexure – III.

1.6 What are the quantities of earthwork

involved in the construction activity

– cutting, filling, reclamation etc.

(Give details of quantities of

earthwork transport of fill materials

from outside the site etc.)

Since there is single basement construction in

this project there may be some excavated

materials during construction activities. The

excavated soil obtained will be utilized for

backfilling and leveling the site. No filled

materials from outside is needed.

1.7 Give details regarding water supply,

waste handling etc during the

construction period.

Water Supply

The water requirement during the construction

phase of the project will be 10 KLD. It will be

sourced through groundwater.

Waste Handling

The wastes during the construction phase

comprises of the wastes generated by the workers

as a result of the construction activity.

The wastes generated by the workers will be

treated and disposed of by providing temporary

septic tanks. The construction debris will be used

for the formation of roads within the

development.

1.8 Will the low lying areas get altered?

(Provide details of how low lying

area getting modified from the

proposed activity)

There are no low-lying areas within the site as

well as in the surroundings.

1.9 Whether construction debris &

waste during construction cause

health hazard? (Give quantities of

various types of wastes generated

during construction including the

construction labour and the means of

disposal)

The generation of construction wastes will be

about 10 - 30 kg/m2 of construction area. These

will be used for the formation of roads within the

premises.

The liquid wastes (sewage) generated by the

workers will be treated and disposed of by

providing temporary septic tanks. Therefore no

significant health hazard is observed.

II. WATER ENVIRONMENT

S.

No.

Information/Checklist

confirmation

Details thereof (with approximate quantities

/rates, wherever possible) with sources of

information data

2.1 Give the total quantity of water

requirement for the proposed

project with the breakup of

requirements for various uses.

How will the water requirements

met? State the sources &

quantities and furnish a water

balance statement.

S.

No.

Description Quantity Source of

Supply

I Construction

phase

10 Tanker supply

II Operational phase

a Fresh Water

Requirement

Domestic

Requirement

160 KLD

149 KLD

CMWSSB

Page 3: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Form 1A

M/s. Eco Tech Labs Pvt Ltd., Page 33

Swimming pool

requirement

11 KLD

b

Recycled Water

Requirement

Flushing

requirement

Gardening

requirement

OSR

maintenance

HVAC

165 KLD

10 KLD

6 KLD

103 KLD

Treated STP

Water

2.2 What is the capacity (dependable

flow or yield) of the proposed

source of water?

The Source of water is from CMWSSB. The

required fresh water is 160 KLD.

2.3 What is the quality of water

required, in case, the supply is

not from a municipal source?

(Provide physical, chemical,

biological characteristics with

class of water quality)

The quality of fresh water required will be as per

domestic requirement.

2.4 How much of the water

requirement can be met from the

recycling of treated wastewater?

(Give the details of quantities,

sources and usages)

The wastewater generation from the project is

estimated to be about 299 KLD which will be treated

in proposed Sewage Treatment Plant of 320 KLD

capacity and will be recycled for flushing, gardening

and the remaining excess sewage will be disposed to

local panchayat for road side avenue plantations

2.5 Will there be diversion of water

from other users? (Please assess

the impacts of the project on

other existing uses and quantities

of consumption)

No, there will not be any diversion of water from

other users. The area is mostly of newly developed

area, adequate rainwater harvesting facilities has

been proposed in order to reduce the impact of

ground water.

2.6 What is the incremental

pollution load from wastewater

generated from the proposed

activity? (Give details of the

quantities and composition of

wastewater generated from the

proposed activity)

The wastewater generation from the project is

estimated to be about 299 KLD. During operational

phase the sewage generated will be treated in the

proposed STP (320 KLD). The Quality of

wastewater generated from the proposed

development will be: pH (6.5-8.5), BOD (250-350

mg/l), COD (500-700 mg/l), SS (150 mg/l),

2.7 Give details of the water

requirements met from water

harvesting? Furnish details of

the facilities created.

The rain water from the project site is proposed to be

collected and stored in a rain water collection sump.

The rain water from the roads/pavements and

landscape are proposed to be collected and recharged

through recharge pits and trench proposed along the

boundary.

2.8 What would be the impact of the

land use changes occurring due

to the proposed project on the

runoff characteristics

(quantitative as well as

qualitative) of the area in the

The runoff will increase due to the proposed

residential development. Proper rain water storage

sumps, storm water drains are designed for the

collection and recharge of rainwater. The excess

runoff will flow to the external storm water network.

Hence, no water logging problems anticipated.

Page 4: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Form 1A

M/s. Eco Tech Labs Pvt Ltd., Page 34

post construction phase on a

long-term basis? Would it

aggravate the problems of

flooding or water logging in any

way?

2.9 What are the impacts of the

proposal on the ground water?

(Will there be tapping of ground

water: give the details of ground

water table, recharging capacity,

and approvals obtained from

competent authority, if any)

The source of water is from CMWSSB. Hence there

will be not be a greater impact on ground water.

Rainwater harvesting measures proposed will

mitigate the impact on groundwater.

2.10 What precautions/measures are

taken to prevent the run-off from

construction activities polluting

land & aquifers? (Give details of

quantities and the measures

taken to avoid the adverse

impacts)

Construction area will be kept clean and maintained

without contamination, thereby avoiding pollution of

the surface runoff during construction phase.

Suitable drains as per the prevailing contour of the

plot will be developed and the runoff will be allowed

to flow through the existing storm water drains.

2.11 How is the storm water from

within the site managed? (State

the provisions made to avoid

flooding of the area, details of

the drainage facilities provided

with a site layout indication

contour levels)

Storm water drains within the site are designed based

on the average intensity of rainfall in that area.

Further storm water collection and storage sumps

have been planned to store part of the runoff during

rains.

2.12 Will the deployment of

construction laborers particularly

in the peak period lead to

unsanitary conditions around the

project site (Justify with proper

explanation)

Local laborers from nearby areas will be employed

for the project work and there is no labor camp

proposed inside the project site. Furthermore proper

sanitary facilities like temporary toilets and wash

area will be provided to laborers at the construction

site.

2.13 What on-site facilities are

provided for the collection,

treatment & safe disposal of

sewage? Give details of the

quantities of wastewater

generation, treatment capacities

with technology & facilities for

recycling and disposal )

Temporary toilets will be provided during

construction phase. The sewage generated will be

disposed off through a septic tank arrangement.

The wastewater generated during operation period

will be treated with proposed STP, the treatment

plant capacity, technology and design details is

described in Conceptual plan enclosed along with

this form, for recycling the treated wastewater dual

plumbing system is proposed for flushing and

gardening line.

2.14 Give details of dual plumbing

system if treated waste used is

used for flushing of toilets or

any other use.

Dual Plumbing for Toilet flushing and gardening is

proposed and the dual plumbing line layout is

attached as Annexure – VII.

Page 5: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Form 1A

M/s. Eco Tech Labs Pvt Ltd., Page 35

III. VEGETATION

S.

No.

Information/Checklist

confirmation

Details thereof (with approximate quantities

/rates, wherever possible) with sources of

information data

3.1 Is there any threat of the project to

the biodiversity? (Give a

description of the local ecosystem

with its unique features, if any)

There is no threat to the biodiversity due to the

proposed development. No sensitive species are

prevailing at the project site. The impact on

environment during the construction as well as

during operation, will be limited to project

premises, hence no impact is envisaged on the

surrounding ecological environment.

3.2 Will the construction involve

extensive clearing or modification

of vegetation? (Provided a detailed

account of the trees & vegetation

affected by the project)

There will not be clearing of vegetation since the

site is devoid of any greenery.

3.3 What are the measures proposed to

be taken to minimize the likely

impacts on important site features

(Give details of proposal for tree

plantation, landscaping, creation

of water bodies etc along with a

layout plan to an appropriate

scale)

There will not be any kind of impact due to this

project on site. Within the proposed project site,

green belt area of 2793.27 Sqm is designated for

development. Various species of plants are

proposed to be planted to create a clean and

healthy environment. Green belt area layout is

enclosed as Annexure-VII.

IV. FAUNA

S.

No.

Information/Checklist

confirmation

Details thereof (with approximate quantities

/rates, wherever possible) with sources of

information data

4.1 Is there likely to be any

displacement of fauna-both

terrestrial and aquatic or creation

of barriers for their movement?

Provided the details.

No, the displacement and barrier for movement of

fauna is not envisaged due to the project.

4.2 Any direct or indirect impacts on

the fauna of the area? Provided

details.

No, no negative impacts are envisaged on the

fauna of the area due to this project.

V. AIR ENVIRONMENT

S.

No.

Information/Checklist

confirmation

Details thereof (with approximate quantities

/rates, wherever possible) with sources of

information data

5.1 Will the project increase

atmospheric concentration of gases

& result in heat islands? (Give

As the proposed project consists of a Mall/ Theatre /

Hotel complex building, it has free access from the

surroundings. Hence there will not be any increase

Page 6: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Form 1A

M/s. Eco Tech Labs Pvt Ltd., Page 36

details of background air quality

levels with predicted values based

on dispersion models taking into

account the increased traffic

generation as a result of the

proposed construction)

in atmospheric concentration of gases and formation

of heat islands.

5.2 What are the impacts on generation

of dust, smoke, odorous fumes or

other hazardous gases? Give details

in relation to all the meteorological

parameters.

Dust suppression measures will be adopted during

construction period. No major sources of dust,

smoke, odorous fumes or other hazardous impacts

are anticipated during operation phase.

5.3 Will the proposal create shortage of

parking space for vehicles? Furnish

details of the present level of

transport infrastructure and

measures proposed for

improvement including the traffic

management at the entry & exit to

the project site.

Sufficient parking space is provided within the

project area. Internal traffic circulation will be

smooth and there will not be any idle running of

vehicles due to traffic. Roads, pedestrians and

footpaths are separately earmarked.

Parking provided:

Mall:

Car Parking Provided: 796 Nos.

Two Wheeler Parking Provided: 1094 Nos.

5.4 Provide details of the movement

patterns with internal roads, bicycle

tracks, pedestrian pathways,

footpaths etc, with areas under the

category.

Internal roads will run all along the site and the

pedestrian pathways will be provided on the either

sides of the road.

5.5 Will there be significant increase in

traffic noise & vibrations? Give

details of the sources and the

measures proposed for mitigation

of the above.

In construction phase, the noise generated from the

construction equipments will be reduced through

proper maintenance of all the equipments. Noise

control systems such as equipment foundation pads,

dampeners, silencers and acoustic enclosures will

be used for individual units. In Operation phase, the

major source of noise pollution is from vehicular

transportation and generator sets. But Noise and

vibrations are expected to be minimal due to the

distributed traffic pattern and by the development of

the green cover all along the internal roads. Hence

there is no major impact envisaged.

5.6 What will be the impact of DG sets

& other equipment on noise levels

& vibration in & ambient air

quality around the project site?

Provided details.

DG sets with acoustic enclosures will be used

during construction as well as operational phases of

the project.

The DG sets will be operated only for short

durations in case of power cuts and the flue gases

will be let outside through the stacks with adequate

height as prescribed by CPCB. Use of low sulphur

HSD will reduce the impact on the ambient air

quality.

Page 7: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Form 1A

M/s. Eco Tech Labs Pvt Ltd., Page 37

VI. AESTHETICS

S.

No.

Information/Checklist

confirmation

Details thereof (with approximate quantities

/rates, wherever possible) with sources of

information data

6.1 Will the proposed constructions in

any way results in the obstruction

of a view, scenic amenity or

landscapes? Are these

considerations taken into account

by the proponents?

No, the proposed construction will not obstruct

any view, scenic amenities or landscapes.

6.2 Will there be any adverse impacts

from new constructions on the

existing structures? What are the

considerations taken into account?

No, there will not be any adverse impact due to

this project on the existing structures.

6.3 Whether there are any local

considerations of urban form &

urban design influencing the

design criteria? They may be

explicitly spelt out.

No, the proposed project is developed in an area

earmarked Commercial use zone.

6.4 Are there any anthropological or

archaeological sites or artifacts

nearby? State if any other

significant features in the vicinity

of the proposed site have been

considered.

There are no anthropological or archaeological

sites or artifacts nearby.

VII. SOCIO-ECONOMIC ASPECTS

S.

No.

Information/Checklist

confirmation

Details thereof (with approximate quantities

/rates, wherever possible) with sources of

information data

7.1 Will the proposal results in any

changes to the demographic

structure of local population?

Provide the details.

The project will change the demographic pattern

slightly. There will be alteration in the numbers of

skilled, unskilled and professional work force.

Changes in socio economic pattern are also

envisaged to some extent.

7.2 Give details of the existing social

infrastructure around the proposed

project.

The project site is located nearer to Koyambedu.

The surrounding area is highly populated by

residential components.

7.3 Will the project cause adverse

effects on local communities,

disturbance to sacred sites or other

cultural values? What are the

safeguards proposed?

No, the project will not cause any adverse effect.

Page 8: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Form 1A

M/s. Eco Tech Labs Pvt Ltd., Page 38

VIII. BUILDING MATERIALS

S.

No.

Information/Checklist

confirmation

Details thereof (with approximate quantities

/rates, wherever possible) with sources of

information data

8.1 May involve the use of building

materials with high-embodied

energy. Are the construction

materials produced with energy

efficient processes? (Give details

of energy conservation measures

in the selection of buildings

materials and their energy

efficiency)

The construction materials used are produced with

energy efficient processes.

8.2 Transport and handling of

materials during construction may

result in pollution, noise & public

nuisance. What measures are

taken to minimize the impacts?

Mitigation Measures during Construction Stage:

Air Pollution

Various construction activities related to handling

of loose material are likely to cause generation of

fugitive dust affecting the air quality of the

surrounding area of the project site. To minimize

such impact following measures shall be taken:

All the loose materials, either stacked or

transported, will be provided with suitable

covering such as tarpaulin, etc. Water sprinkling

will be done at the location where dust generation

is anticipated. To minimize the occupational

health hazard, proper personal protective

equipments, i.e. mask, goggles, helmets and safety

shoes will be provided to the workers who are

engaged in construction activity.

Noise Pollution

During the construction stage, expected noise

levels will be in the range of 80-85 dB (A) which

will decrease with increase in distance as per the

Inverse Square Law. Administrative as well as

engineering control of noise will be implemented.

Isolation of noise generation sources and temporal

differentiation of noise generating activities will

ensure minimum noise at receiver’s end. To

prevent any occupational hazard, ear muffler /

plug will be given to the workers working around

or operating plant and machinery emitting higher

noise levels than the permissible limits. There will

be no construction during night hours. Careful

planning of machinery operation and scheduling

of operations will be done to minimise such

impact.

Page 9: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Form 1A

M/s. Eco Tech Labs Pvt Ltd., Page 39

8.3 Are recycled materials used in

roads and structures? State extent

of savings achieved

Construction debris generated will be recycled to

the extent possible in forming roads within the

premises.

8.4 Give details of the methods of

collection, segregation & disposal

of the garbage generated during

the operation phases of the project.

The solid waste will comprise biodegradable

waste e.g. domestic waste, food waste,

horticultural waste etc. and recyclable waste, like

plastics, paper etc.

Biodegradable Wastes: 6.6 Tonnes/day

Non-biodegradable Wastes: 1.8 Tonnes/day

STP Sludge:45 kg/day

Solid Waste Management:

In the building complex, private sweepers would

be engaged for handling domestic waste and

appropriate site will be identified for keeping bin /

container for the collection of waste.

Adequate number of collection bins separately for

biodegradable and non-biodegradable waste will

be provided as per the Municipal Solid Waste

(Management and Handling) Rule, 2000. Separate

colored bins will be provided for biodegradable

and non-biodegradable wastes. All the collection

bins shall be properly maintained and cleared on

regular basis. Waste from such bins shall be

collected separately on daily basis and taken to a

centralized storage facility. The Bio degradable

wastes will be handed over to local municipality,

non biodegradable will be handed over to the

recyclers.

Horticultural wastes:

Leaves, grass and vegetative residues shall be

collected at the secured location such that it will

not hinder daily activity schedule or washed away

by the surface run-off causing choking of drains,

etc. and will be separately disposed off along with

biodegradable waste.

IX. ENERGY CONSERVATION

S.

No.

Information /Checklist

confirmation

Details thereof (with approximate quantities

/rates, wherever possible) with sources of

information data

9.1 Give details of the power

requirements, sources of supply,

backup source etc. What is the

energy consumption assumed per

square foot of built-up areas? How

have you tried to minimize energy

consumption?

The power would be sourced from TNEB from

nearby sub-station. The estimated power

requirement for the project is about 6140 KVA

during operational phase. Power back up is

proposed by using DG sets 3 No. of D.G. sets of

2000 KVA & 1 No.of D.G. set for capacity of

1500 KVA. The energy consumption will be

minimized by using energy efficient lamps, and

by adopting natural lightings and ventilations to

the possible extent.

Page 10: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Form 1A

M/s. Eco Tech Labs Pvt Ltd., Page 40

9.2 What type of, and capacity of, power

back-up you plan to provide?

Power back up is proposed by using DG sets.

DG sets:

3 No. of D.G. sets of 2000 KVA

1 No. of D.G set of 1500 KVA

9.3 What are the characteristics of the

glass you plan to use? Provide

specifications of its characteristics

related to both short wave and long

wave radiation?

Normal Glass. The thickness of glass is 4-6 mm

to keep the U-value of 1.08 W/m2°C.

9.4 What passive solar architectural

features are being used in the

building? Illustrate the applications

made in the proposed project.

Considering the site and solar analysis each

block was designed individually. The use of

solar passive measures includes the design of

fenestrations in such a way that sufficient day-

lighting is allowed inside the building.

9.5 Does the layout of streets &

buildings maximize the potential for

solar energy devices? Have you

considered the use of street lighting,

emergency lighting and solar hot

water systems for use in the building

complex?

The layout of streets & buildings will maximize

the potential for solar energy devices. Solar

powered street lighting will be adopted partly.

9.6 Is shading effectively used to reduce

cooling/heating loads? What

principles have been used to

maximize the shading of walls on the

East and the West and the Roof?

How much energy saving has been

effected?

Sunshades are proposed to reduce heat ingress

into the buildings. Sun path studies led to the

orientation and position of each block suited to

best protect itself from the harsh sun while

utilizing the natural wind direction to help

facilitate cross ventilation

9.7 Do the structures use energy –

efficient space conditioning, lighting

and mechanical systems? Provide

technical details. Provide details of

the transformers the motor

efficiencies, lighting intensity and

air-conditioning load assumptions?

Are you using CFC and HCFC free

chillers? Provide specifications.

Use of CFLs to reduce the lighting power

density. Energy efficient pumps and drives are

proposed.

9.8 What are the likely effects of the

buildings activity in altering the

micro-climates? Provide a self-

assessment on the likely impacts of

the proposed construction on creation

of heat island & inversion effects?

As per the design of the proposed project,

Sufficient Cross ventilation is provided. Hence

there will not be any change in microclimate due

to the proposed project.

9.9 What are the thermal characteristics

of the building envelope? (a) roof:

(b) external walls: and (c)

fenestration? Give details of the

The U-values of the roof, external wall and

fenestration of the building will meet the

requirements as specified in the Energy

Conservation Building Code (ECBC).

Page 11: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Form 1A

M/s. Eco Tech Labs Pvt Ltd., Page 41

materials used the U-values or the R-

values of the individual components.

Component Permissible

U-Value as

per

ECBC

(W/m2°C)

Resultant

Value due to

the proposed

configuration

(W/m2°C)

Roof (RCC slab

with clay tile)

0.261 0.25

Wall Constructed

using M15 grade

concrete solid

blocks,

0.440 0.440

Fenestration

(Plain glass with

sun colored film /

colored glass)

3.300 3.127

9.10 What precaution & safety measures

are proposed against fire hazards?

Furnish details of emergency plans.

Portable fire extinguishers, fire exit signage and

fire fighting system will be installed inside the

building. Portable fire extinguishers will be

installed. Fire protection and safety measures

proposed are expected to mitigate fire and

explosion hazards. Fire and safety Department

NOC is enclosed as Annexure-XIII.

9.11 If you are using glass as wall

material provides details and

specifications including emissive and

thermal characteristics.

No, glass is not used as wall material.

9.12 What is the rate of air infiltration into

the building? Provide details of how

you are mitigating the effects of

infiltration.

The proposed project is residential building and

hence there is no forced ventilation used. The

residential houses provided with adequate

windows which is almost in open condition for

free movement of fresh air inside the buildings.

9.13 To what extent the non-conventional

energy technologies are utilized in

the overall energy consumption?

Provide details of the renewable

energy technologies used.

Solar powered street lighting will be partly

provided. The layout of streets & buildings will

maximize the potential for solar energy devices.

“I hereby undertake that the data and the information given in the application and enclosures

are true to the best of my knowledge and belief and I am aware that if any part of the data and

information submitted is found to be false or misleading at any stage, the project will be

rejected and clearance given, if any, to the project will be revoked at our risk and cost.”

Date: Signature of the Applicant

Place: [ ]

Page 12: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 57

CHAPTER –1

1.0 Introduction

1.1 GENERAL

M/s. Anandram Developers Pvt. Ltd., proposes to construct its Hyper mall

complex in town survey no. 8/1 (PART), 8/2 to 8/30, 8/33, 13, 14, 15 of

Saligramam village, Mambalam Taluk, Chennai district in the state of Tamil

Nadu. Total land area available is 18,149.26 Sq.m. The total built-up area is

88,779.20 Sq.m. M/s. Anandram Developers Pvt. Ltd have engaged us for

preparing the Environmental Management Plan (EMP) for their proposed

construction of hyper mall, to obtain Environmental Clearance from the State

Environment Impact Assessment Authority (SEIAA).

As per EIA notification, 2006, any new or modernization building and

construction project with built-up area more than 20,000 sq m and less than

1,50,000 sq m falls under activity 8 a and category B and thus requires to

obtain environment clearance from State Environment Impact Assessment

Authority (SEIAA) prior to the start of construction.

1.2 SITE DESCRITPION

The project site is located 13°2'47.03"N latitude and 80°12'10.08"E

longitude. The site is located at town survey no. 8/1 (PART), 8/2 to 8/30, 8/33,

13, 14, 15 of Saligramam village, Mambalam taluk, Chennai district in the state

of Tamil Nadu.

Page 13: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 58

Table 1: Details of Environmental Settings

1.2.1 Topography of the site:

Site is located abutting the Arcot Road and Dr. Banumathi Ramakrishnan

Road connecting Vadapalani to Porur. Nearest Highway is SH 113 (Arcot

Road). Site lies at 0.70 km (South) from KK Nagar; 0.3 km (East) from

Kannika Puram; 0.7 km (West) from Navarathna Colony and 1.0 km

(North) from Saligramam.

Sensitive areas around site: Ramapuram Eri (2.6 km, SW), Coovum river

(1.6 km, North) and Porur lake (6 km, NW).

1.2.2 Site connectivity:

The project site is well connected by road, rail and air ways. The

proposed project is located abutting SH113- Arcot road

The nearest railway station at proximity of the project site is Vadapalani

Metro railway station which is located at 1.1 km distance in North

Eastern direction and Chennai International Airport is at 7.1 km distance

in South west direction to the site.

S.

No. Particulars Details

1. Latitude 13° 2'47.03"N

2. Longitude 80°12'10.08"E

3. Total Plot Area 18,149.26 Sq.m

4. Nearest Highway SH 113 – Arcot Road

5. Nearest Railway Station Vadapalani Metro Rail Station ( 1.0 km, NE)

6. Nearest Airport Chennai International airport (7.1 km, SW)

7. Nearest Town Valasaravakkam (2.8 km, W)

8. Nearest City Chennai (8.28 km, NE)

Page 14: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 59

Fig. 1: Topography of the site

1.3 PROJECT COMPONENTS

The proposal involves construction of Hyper mall/ Food Court/ Multiplex/

Hotels/ Restaurants/ Shops/ Commercial Units with a total built up area of

88,779.20 Sq.m. The area split up and space utilization details are given below,

the project consists of main building with Basement + Ground + 12 floors, a

multi-level car park (MLCP) with Ground + 16 levels and a sub-station of

Basement+G+2. Detailed area break up is given in below Table 2.

Table 2: Land Use Break up Details

S. No Details Area (Sqm)

1. Total Land Area 18149.26

2. Total Ground Coverage Area of Buildings (40.89%) 7421.55

3. Roads and Pavements Area (19.2%) 3488.34

ARCOT ROAD

Velayutham colony

Kannika Puram

Kamaraj Nagar

Project Site

Page 15: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 60

4. Surface or open Parking Area (13.06%) 2370.10

5. STP, Solid Waste Disposal and Other Utilities Area

(0.01%) 256.00

6. Greenbelt development Area (15.39%) 2793.27

7. OSR Area (10.03%) 1820.00

8. Total Builtup area 88779.20

1.3.1 Total Built up Area and Details on Housing Units:

Built up area is calculated as per the latest Circular of MoEF, Dated: 2nd

April, 2012. Built-up area is defined as ''The built-up or covered area on all the

floors put together including basement(s) and other service areas, which are

proposed in the building / construction project" as per the latest Circular of

MoEF, Dated: 2nd

April, 2012. Detailed built-up area calculations are given

below.

Table 3: Built up Area Statement

Name of the

Block/Building

Built-up

Area

(FSI

Area)

Sqm

Built-up

Area

Non FSI

Area

Sqm (stilts)

Built-up Area

Parking Area

& Others if any

(Covered Built

Up Area)

Total Built

Up Area

List of Activities

Involved

Main Building

Basement Floor - 143.94 6722.93 6866.87 Parking

Ground Floor 4921.31 93.32 - 5014.63 Hyper market/

Shops &

showroom

1st Floor 4906.50 149.69 - 5056.19

2nd

Floor 4535.75 192.61 - 4728.36

3rd

Floor 4491.08 192.61 - 4683.69

4th

Floor 4831.23 54.62 - 4885.85 Food Court &

fun centre

5th

Floor 2851.42 610.76 - 3462.18 Theatre/

showroom

6th

Floor 1031.00 701.64 - 1732.64 Theatre/ Bar

7th

Floor 4408.22 433.02 - 4841.24 Theatre/ Bar/

Hotel rooms

8th

Floor 1289.87 1606.07 - 2895.94 Bar, services &

Hotel rooms

Page 16: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 61

9th

Floor 3023.64 175.34 - 3198.98

Longue Bar/

Restaurant/ Hotel

rooms/ Business

centre

10th

Floor 3281.50 285.65 - 3567.15 Banquet hall/

Hotel rooms

11th

Floor 2917.01 283.57 - 3200.58

Gym/ Hotel

room/ Banquet

Hall

12th

Floor 2865.68 140.37 - 3006.05 Hotel rooms/

Business Centre

TOTAL 45354.21 5063.21 6722.93 57140.35 Mall building

Multi Level Car Parking

Ground Level - - 1788.85 Parking

Level 1 - - 1788.85 Parking

Level 2 - - 1788.85 Parking

Level 3 - - 1788.85 Parking

Level 4 - - 1788.85 Parking

Level 5 - - 1788.85 Parking

Level 6 - - 1788.85 Parking

Level 7 - - 1788.85 Parking

Level 8 - - 1788.85 Parking

Level 9 - - 1788.85 Parking

Level 10 - - 1788.85 Parking

Level 11 - - 1788.85 Parking

Level 12 - - 1788.85 Parking

Level 13 - - 1788.85 Parking

Level 14 - - 1788.85 Parking

Level 15 - - 1788.85 Parking

Terrace - 353.19 - 353.19 Swimming pool

& services

Total - 353.19 28621.6 28974.79

Sub-Station Block

Basement Floor 772.71 772.71 Parking

Ground Floor 618.07 - 618.07 DG & MV Panel

First Floor 618.07 618.07 Parking

Second Floor 618.07 - 618.07 Chiller

Terrace 37.14 - 37.14 Head Room

Total - 1273.28 1390.28 2664.06 -

Total Built up

area 88779.2

-

Page 17: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 62

Table 4: Overall Built up Area Statement

FSI (Sqm)

Non FSI

(Sqm) Parking (Sqm)

Total Built Up

Area (Sqm)

Main Building

(Mall)

45354.21 5063.21 6722.93 57140.35

Multi Level Car

Parking

- 353.19 28621.6 28974.79

Sub-Station block - 1273.28 1390.78 2664.06

Total 45354.21 6689.68 36735.31 88779.2

1.4 VEHICLE PARKING FACILITIES

Parking will be provided as per the building bye laws of CMDA. Details

of parking required and to be provided is given below in Table 5.

Table 5: Parking Provided

S. No Details No. of Car

parks

No of two

wheeler

parks

Area allotted

for parking in

(Sqm)

1. Total number of Parks in Basement 137 398 6722.39

2. Total number of parks in MLCP 560 27 28621.6

3. Total Number of parks in Substation 262 1390.78

4. Total number of parks in Ground level

(Surface parking) 99 407 2370.1

5. Total number of Parking provided 796 1094 39104.87

6. No. of parks required 716 737 -

(Note: One car Parking is equal to two 2- wheeler parking.)

1.5 POWER REQUIREMENT

The estimated power requirement during operation is about 6140 KVA

and it will be sourced from the nearby TNEB grid. DG set of 3 x 2000 KVA &

Page 18: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 63

1 x 1500 KVA capacity will be provided to cater essential load requirement

during power failure.

The stack height for the DG sets are calculated based on the CPCB

guidelines as shown below;

Stack Height Design Calculation for 2000 KVA

H = h + (0.2) (kVA) 0.5

= 51.88 + 0.2 (2000) 0.5

= 51.88 + 8.9

= 60.8 ~ 61 m.

Where, H = Total height of stack in meters from ground level

h = Height of the building in meters

The stack height required as per CPCB norms is 61 m for 3 D.G Sets of

capacity 2000 KVA.

Stack Height Design Calculation for 1500 KVA

H = h + (0.2) (kVA) 0.5

= 51.88 + 0.2 (1500) 0.5

= 51.88 + 7.7

= 59.6 ~ 60 m.

Where, H = Total height of stack in meters from ground level

h = Height of the building in meters

The stack height required as per CPCB norms is 60 m for D.G sets of

capacity 1500 KVA.

Page 19: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 64

1.6 BASELINE ENVIRONMENTAL STATUS

Baseline studies are carried out to provide a detailed description of the

existing ecosystem, landscape, infrastructure, cultural heritage and urban

environment. A baseline study describes the initial state of the environment

within the selected boundaries of the study area. The baseline data has been

generated and the secondary data was collected from various Government and

Semi-Government organizations. The details about the existing environmental

values are projected based on the volume of the assessment accomplished

during the period. The various environmental attributes were divided into

primary and secondary studies. Primary attributes such as air environment,

water, soil, noise & biodiversity environment were being assessed by

conducting field studies, on-site monitoring. The baseline studies started with

site visits and survey in the study area for fixing the monitoring locations for

the primary data generation. The baseline environmental data for ambient Air,

Noise, Soil and Ground water is enclosed in Annexure XI. The brief on the

study of bio-diversity is summarized below.

1.6.1 Biodiversity Study

a. Methodology

The ecological status of the study area has been assessed based on the following

methodology:

Primary field surveys to establish primary baseline of the study area

Compilation of information available in published literatures and as

obtained from Forest survey of India, Botanical Survey of India and

Zoological Survey of India.

The flora and fauna studies were carried out within 1 km radius around the

proposed construction site.

Page 20: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 65

b. Flora

The Study of flora involved intensive sample survey of vegetation in the project

site and other locations applying standard methods. To examine the trees and

shrubs, quadrants of 25 x 25 m and for herbs 2 x 2 m were laid. In each of the

larger quadrants (i) Species (ii) their number, and (iii) Girth at Breast Height

(GBH), were measured. (Chaturvedi and Khanna, 1982).

Abundance, relative abundance, density and relative density of each species

diversity and evenness for each of the Zones were calculated using the numerical

data (Ludwig and Reynolds 1988, Lande 1996, Smith and Wilson 1996). The

standard statistical analysis, the normal frequency diagram and distribution of

plants in the study area were analyzed using the procedures of Raunkiaer, 1934.

The analysis carried out as per Raunkiaer’s law of frequency classes provides the

information on the Heterogeneity and Homogeneity of plants and its pattern of

distribution in the study area. The species of vegetation found in each station were

identified and listed according to their families, both in dicotyledons and

monocotyledons of the plant kingdom. The plant species were classified as per the

classifications of “Bentham and Hooker” and identified by using Gambles book on

“Flora of Madras Presidency” and Mathew’s book on “Flora of the Tamil Nadu

Carnatic”.

c. Fauna

Both direct and indirect observation methods were used to survey the fauna.

Visual encounter (search) method was employed to record vertebrate species.

Additionally survey of relevant literature was also done to consolidate the list of

vertebrate fauna distributed in the area (Smith 1933-43, Ali and Ripley 1983,

Daniel 1983, Prater 1993, Murthy and Chandrasekhar 1988). Since birds may be

considered as indicators for monitoring and understanding human impacts on

Page 21: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 66

ecological systems (Lawton 1996) attempt was made to gather quantitative data on

the group by.

Point Survey Method: Observations were made in each site for 15 minutes

duration.

Road Side Counts: The observer traveled by motor vehicles from site to site,

all sightings were recorded (this was done both in the day and night time). An

index of abundance of each species was also established.

Pellet and Track Counts: All possible animal tracks and pellets were

identified and recorded (South Wood, 1978).

Based on the Wildlife Protection Act, 1972 (WPA 1972, Anonymous.

1991, Upadhyay 1995, Chaturvedi and Chaturvedi 1996) species were short-listed

as Schedule II or I and considered herein as endangered species. Species listed in

Ghosh (1994) are considered as Indian Red List species.

Pellet and Track counts method was adopted for this development project

and the assessment results are discussed in Chapter-3.

1.7 ENVIRONMENTAL COMPONENTS

The baseline environmental studies helped in assessing the existing

environmental conditions of the study area and identifying the critical

environmental attributes. This will facilitate the comparison of the resultant

environmental conditions in the post study scenario with the pre- study

conditions and will help in checking the environmental pollution.

1.8 WATER REQUIREMENT

The total water requirement during operation is 438 KLD. Source of water

is CMWSSB. The wastewater generation from the project is estimated to be

about 299 KLD, which will be treated in proposed sewage treatment plant of

320 KLD capacity and will be recycled for flushing, gardening and remaining

Page 22: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 67

excess treated sewage will be disposed to CMWSSSB sewer line and the water

balance chart is shown in Table 6, 7 and 8.

Table 6: Occupancy Load Calculation

S.No. Description Capacity Occupancy Load (Nos.)

A) Theatres

Total No. of seats considered 2121 8484

Total No. of shows 4

Total Number of staffs 10% of the seats 848

B) Hypermarket, Fun centre, Show rooms/ big bazaar

Total Area Considered 17317.41 2886

Area considered / person 6 Sqm

Total number of staffs 10% of the population 289

C) Food Court

Total Area considered 4163.48 1388

Area considered / person 3 Sqm

Total number of staffs 10% of the population 139

D) HOTEL- GUEST ROOM

No. of rooms- 234 468

Beds/room 2

No. of staff 10% of the population 47

E) Restaurant / Longue bar

Total area 415.56 139

No. of person /turn over 3 Sqm

No. of staff 10% of the population 14

f) Banquet hall

Total area 291.73 195

Area/person 1.5 Sqm

No. of staff 10% of the population 20

G) Business Centre/ Gym

Total area 210.46 70

Area / person 3 Sqm

No. of staff 10% of the population 7

Total Occupancy Load 14994

Page 23: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 68

Table 7: Water Requirement Calculation

S.

No. Description Capacity

Basis

(lpcd)

Water Requirement (LPD)

Domestic

(LPD)

Flushing

(LPD)

Total

(LPD)

A) Theatres

No. of Persons 8484 5 16968 25452 42420

(2 lpcd) (3 lpcd) (5 lpcd)

No. of Staffs 848 45 12720 25440 38160

(15 lpcd) (30 lpcd) (45 lpcd)

Total 9332 52 29688 50892 80580

B) Hypermarket, Fun Centre, Show rooms/big bazaar

No. of Persons 2886 5

5772 8658 14430

(2 lpcd) (3 lpcd) (5 lpcd)

No. of Staffs 289 45

4335 8670 13005

(15 lpcd) (30 lpcd) (45 lpcd)

Total 3175 60 10107 17328 27435

C) Food Court

No. of Persons 1388 70 55520 41640 97160

(40 lpcd) (30 lpcd) (70lpcd)

No. of Staffs 139 45 2085 4170 6255

(15 lpcd) (30 lpcd) (45 lpcd)

Total 1527 60 57605 45810 103415

D) Hotel Room

No. of beds 468 180 42120 42120 84240

(90 lpcd) (90 lpcd) (180lpcd)

No. of Staffs 47 45 1410 705 2115

(30 lpcd) (15 lpcd) (45 lpcd)

Total 1030 225 43530 42825 86355

E) Restaurant / Longue Bar

No. of Persons 139 70 5660 4170 9730

(40 lpcd) (30 lpcd) (70 lpcd)

No. of Staffs 14 45 210 420 630

Page 24: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 69

(15 lpcd) (30 lpcd) (45 lpcd)

Total 153 115 5870 4590 10360

F) Banquet hall

No. of Persons 195 15 975 1950 2925

(5 lpcd) (10 lpcd) (15 lpcd)

No. of Staffs 20 45 300 600 900

(15 lpcd) (30 lpcd) (45 lpcd)

Total 215 30 1275 2550 3825

G) Business Centre / Gym

No. of Persons 70 15 350 700 1050

(5 lpcd) (10 lpcd) (15 lpcd)

No. of Staffs 7 45 105 210 315

(15 lpcd) (30 lpcd) (45 lpcd)

Total 77 60 455 910 1365

Table 8: Water Requirement Summary

S.No. Description

Water Requirement (LPD)

Domestic

(LPD)

Flushing

(LPD)

Total

(LPD)

1. Mall, 148530 164905 313335

2. Water requirement for Gardening purposes based on the

Gardening area (2915.43 Sqm (@ 3.5 litres/Sqm) 10204

3. Water requirement for HVAC 103000

4. Swimming Pool requirement 11000

Total water requirement 437539

Water Requirement Summary:

Total Water Requirement = 438 KLD

Fresh water requirement for domestic purposes = 149KLD

Treated water requirement for Flushing purposes = 165 KLD

Treated water requirement for Gardening purposes = 10 KLD

Page 25: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 70

Swimming pool water requirement = 11 KLD

HVAC cooling water requirement = 103 KLD

HVAC Cooling Water Requirement:

Total Cooling tower capacity: 1030 TR

1030 TR: water cooled

1030 TR x 12.5 liters x 8 hours = 103000Say 103 KLD

Fig. 2: Water Balance Chart

Sewage Treatment Plant 320 KLD

Gardening 10KLD

Treated Water 284 KLD (95%)

134 KLD (90%)

Domestic 149 KLD

Flushing 165 KLD 727253KLD

Daily Fresh Water Requirement 160 KLD

Treated water 284 KLD

Z

OSR maintenance 6 KLD

215 KLD

165 KLD (100%) 299 KLD

Swimming Pool 11 KLD

HVAC 103 KLD

Total water requirement 438 KLD

Page 26: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 71

1.9 SOLID WASTE GENERATION

The solid waste from the proposed development will comprise of

compostable wastes like domestic food waste, horticultural waste and

recyclable waste like plastics, paper etc. As per the manual on municipal solid

waste prescribed by Central Public Health and Environmental Engineering

Organization (CPHEEO), the quantity of solid waste generated varies between

0.2-0.6 kg / capita / day. Quantity of solid waste generated from the proposed

commercial building is given below in Table9.

Table 9: Quantity of solid waste generated

S.No. Description Occupancy

Per capita

waste

generation

Solid waste Generation (kg/day)

Bio

(kg/day)

Non - Bio

(kg/day)

Total

(kg/day)

A) Theatres 9332 0.2 1120 747 1867

B)

Hypermarket, Fun

Centre, Show

rooms/big bazaar

3175 0.2 380 255 635

C) Food Court 1527 0.6 4581 458 5039

D) Hotel Room 1030 0.6 361 258 619

E) Restaurant/

Longue Bar 153 0.6 54 38 92

F) Banquet Hall 215 0.6 75 54 129

G) Business Centre/

Gym 77 0.2 8 6 14

H) Total 15,509 - 6579 1816 8395

STP Sludge 45 kg/day

Source: Central Public Health and Environmental Engineering Organization

(CPHEEO),

Page 27: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 72

Per capita waste generation for restaurants is 0.6 kg / capita / day and for other

working population is 0.2 kg/day.

Table 10: Waste Composition

S.No Description Quantity

(Tons/day) Mode of treatment / disposal

1.

Biodegradable

Waste (@60% of

waste generated)

6.6

Will be treated in organic waste

convertor within the project site.

Manure generated will be used for

landscaping purpose within project

site.

2.

Non-

Biodegradable

waste (@40% of

waste generated

1.8 Waste will be sold to recyclers

3. STP Sludge 45 kg/day Will be used as a Manure for

greenbelt development

Wastes generated from the households will be segregated into

compostable waste, recyclable and inert waste in the source itself (by the

occupants) in separate bins. Door to door waste collection system will be

adopted. Compostable waste will be treated in organic waste convertor within

the site. Manure generated will be used within the site for landscaping purpose.

Recyclable fraction of waste will be sold to authorized vendors and inert waste

will be send for land filling through authorized agency for waste collection in

the area. Organic waste convertor of various makes like Excel, Nachiket

Engineering, Earth Care equipments are available. These OWC reduce volume

of waste fed by 80% and convert it into manure that can be used for

landscaping purpose. This manure can be stored, packed, sold and used for

landscaping.

Apart from the municipal waste, E-waste comprising of rejected CFL,

bulbs, laptops, TV sets, computers etc will be generated. This waste will be

insignificant in initial stage. Room will be provided within project site for

storing discarded electronics. This will be sold to authorized vendors on regular

basis.

Page 28: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 73

CHAPTER – 2

2.0 ENVIRONMENTAL IMPACT ASSESSEMNT

2.1 INTRODUCTION

This chapter presents the assessment of various impacts due to the

proposed construction project in the study area. Generally, the environmental

impacts can be categorized as either primary or secondary. Primary impacts

are those, which are attributed directly by the project and secondary impacts are

those, which are indirectly induced and typically include the changed patterns

of social and economic activities by the proposed project. The Proposed

construction project would create impact on the environment in two distinct

phases:

Impacts during the construction phase

Impacts during the operation phase

The construction and operational phase of the proposed construction

project comprises of various activities each of which will have impact on some

or other environmental parameters. Various impacts during the construction or

operational phase and the environmental parameters have been studied to

estimate the impacts on environment. The identification and details on impact

of the project activity on each of the above environmental attributes are

discussed below.

2.2 IDENTIFICATION OF IMPACTS

Construction of commercial complex is for the benefit of general

population, however, like any other projects, it also has impacts on existing

Environmental settings and if not properly evaluated and controlled, it may lead

Page 29: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 74

to imbalances. These impacts could be reversible, irreversible, temporary or

permanent.

The identification of impacts is important as it leads to the other elements

such as quantification and evaluation of impacts. Although a number of non-

projects related impacts have been identified while describing the existing

(baseline) environmental status, it is necessary at this stage to identify the types

of the potential impacts which might be caused by the proposed development.

Many techniques are available for identification of impacts. In case of this

project, the "Matrix Method" was adopted, which involves an understanding of

the cause-condition-effect relationship between an activity and environmental

parameters. It is very useful as gross screening tool for impact identification

method. This method has been basically advantageous in recognizing the series

of impacts that could follow from the proposed activities.

The idea was to account for the project activity and identify the types of

impacts that could initially occur. This process was repeated until all possible

types of impacts were identified. With this method the potential impact of the

proposed project has been identified.

Table 11: Overview of potential impacts due to the proposed

commercial complex project

Project activities

Air

qu

ali

ty

No

ise L

evel

Gro

un

d W

ate

r

Qu

ali

ty

Gro

un

d W

ate

r

Qu

an

tity

So

il S

tab

ilit

y/

Ero

sio

n

So

il Q

uali

ty

Tra

ffic

Lev

el

Veg

etati

on

So

cio

Eco

no

mic

Construction Phase

Site Clearance

&Leveling ST,

-ve

ST,

-ve

ST,

-ve

ST,

+ve

Site excavation ST,

-ve

ST, -

ve

ST,

-ve

ST,

+ve

Page 30: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 75

Foundation

(Pile Foundation)

ST,

-ve

ST,

+ve

Material Storage &

Handling

ST,

-ve

ST,

-ve

Generation and

disposal of

construction waste

ST,

-ve

ST,

-ve

Movement of

Vehicles

ST,

-ve

ST,

-ve ST, -ve ST, -ve

Labour’s Camp

ST,

-ve

Operation Phase

Occupancy

LT,

-ve

LT, -

ve

LT,

+ve

Operation of DG

Sets -ve -ve -ve

Sewage Generation

& Discharge

LT,

-ve

LT,

-ve LT, -ve

Rainwater

Harvesting

LT,

+ve

LT,

+ve

Solid waste

Generation

LT,

-ve

Gardening &

Landscaping

LT,

+ve

LT,

+ve

LT,

+ve

LT,

+ve

LT,

+ve

LT,

+ve

Note: ST - Short Term Impact, LT - Long Term Impact, -ve - Negative Impact,

+ve – Positive Impact

2.3 IMPACT EVALUATION

Impact evaluation assesses the expected changes in the environment due

to the proposed project. It is the tool for identifying the magnitude of impact

and forms basis for the development of Environmental Management Plan.

Weight age for each impact is given below. Evaluation of impacts considering

both positive and negative effects on air, noise, land, water and socioeconomic

environment during the construction and operation phase of the project is given

in Table 11 and 12 respectively.

Page 31: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 76

TABLE 12: EVALUATION OF CONSTRUCTION PHASE IMPACT

Environmen

tal

Parameter

Project

Activities

Impact

Type

Sig

nif

ican

t

No

n

Sig

nif

ican

t

Dir

ect

Ind

irec

t

Sh

ort

Ter

m

Lo

ng

Ter

m

Un

avo

idab

le

Irre

ver

sib

l

e M

itig

atio

n

Req

uir

ed

Weigh

tage

CONSTRUCTION PHASE

AIR

ENVIRON

MENT

Site

Clearance

&Levelling

Negative √ √ √ √ √ -4

Site

excavation

Negativ

e √ √ √ √ √ -4

Foundation

(Shallow

Foundation)

Negativ

e √ √ √ √ 0

Material

Storage &

Handling

Negativ

e √ √ √ √ √ -4

Generation

and disposal

of

construction

waste

Negativ

e √ √ √ -4

Vehicular

Movement

Negativ

e √ √ √ -4

Labour’s

Camp

No

Impact -

Public

Health &

Safety

No

Impact -

Economic

Activity

No

Impact -

NOISE

ENVIRON

MENT

Site

Clearance

&Leveling

Negativ

e √ √ √ 0

Site

excavation

Negativ

e √ √ √ -4

Foundation

(Shallow

Foundation)

Negativ

e √ √ √ √ -4

Material

Storage &

Handling

Negativ

e √ √ -1

Page 32: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 77

Generation

and disposal

of

construction

waste

No

Impact -

Vehicular

Movement

Negativ

e √ √ √ -1

Labour’s

Camp

No

Impact -

Public

Health &

Safety

No

Impact -

Economic

Activity

No

Impact -

LAND

ENVIRON

MENT

Site

Clearance

&Leveling

No

Impact -

Site

excavation No Impact -

Foundation

(Shallow

Foundation)

Negativ

e √ √ -1

Material

Storage &

Handling

Negativ

e √ √ √ √ -4

Generation

and disposal

of

construction

waste

Negativ

e √ √ -4

Vehicular

Movement

Negativ

e √ √ √ -1

Labour’s

Camp

No

Impact -

Public

Health &

Safety

No

Impact -

Economic

Activity

No

Impact -

WATER

ENVIRON

MENT

Site

Clearance

&Leveling

Negativ

e √ √ √ -2

Page 33: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 78

Site

excavation

No

Impact -

Foundation

(Shallow

Foundation)

No

Impact -

Material

Storage &

Handling

Negativ

e √ √ √ √ -4

Generation

and disposal

of

construction

waste

Negativ

e √ √ √ √ -4

Vehicular

Movement

Negativ

e √ √ 0

Labour’s

Camp

Negativ

e √ √ √ √ -4

Public

Health &

Safety

No

Impact -

Economic

Activity

No

Impact -

SOCIO

ECONOMI

C

ENVIRON

MENT

Site

Clearance

&Leveling

Negativ

e √ √ √ √ -2

Site

excavation

Negativ

e √ √ √ √ -2

Foundation

(Shallow

Foundation)

Negativ

e √ √ √ √ -2

Material

Storage &

Handling

Negativ

e √ √ √ 0

Generation

and disposal

of

construction

waste

Negativ

e √ √ √ √ -2

Vehicular

Movement

Negativ

e √ √ √ √ -2

Labour’s

Camp

Negativ

e √ √ √ √ -2

Page 34: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 79

Public

Health &

Safety

Positive √ √ √ 6

Economic

Activity Positive √ √ √ 6

TABLE 13: EVALUATION OF OPERATION PHASE IMPACT

Environ

mental

Paramet

er

Project

Activities

Impact

Type

Sign

ific

ant

No

n

Sign

ific

ant

Dir

ect

Ind

irec

t

Sho

rt T

erm

Lo

ng

Ter

m

Un

avo

idab

l

e

Irre

ver

sib

le

Mit

igat

ion

Req

uir

ed

Weig

htag

e

OPERATION PHASE

AIR

ENVIRO

NMENT

Occupancy No

Impact -

Operation of

DG Sets

Negati

ve √ √ √ √ -8

Sewage

Generation &

Discharge

Negati

ve √ √ 0

Rainwater

Harvesting

No

Impact -

Solid waste

Generation

Negati

ve √ √ √ -6

Gardening &

Landscaping

Positiv

e √ √ √ 10

NOISE

ENVIRO

NMENT

Occupancy No

Impact -

Operation of

DG Sets

Negati

ve √ √ √ √ -8

Sewage

Generation &

Discharge

No

Impact --

Rainwater

Harvesting

No

Impact -

Solid waste

Generation

No

Impact -

Gardening &

Landscaping

Positiv

e √ √ √ 10

LAND

ENVIRO

Occupancy Negati

ve √ √ 0

Page 35: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 80

NMENT Operation of

DG Sets

Negati

ve √ √ √ 0

Sewage

Generation &

Discharge

Negati

ve √ √ √ √ -8

Rainwater

Harvesting

Positiv

e √ √ √ 8

Solid waste

Generation

Negati

ve √ √ √ √ -8

Gardening &

Landscaping

Positiv

e √ √ √ 10

WATER

ENVIRO

NMENT

Occupancy Negati

ve √ √ √ √ -8

Operation of

DG Sets

Negati

ve √ √ √ √ -6

Sewage

Generation &

Discharge

Negati

ve √ √ √ √ √ -8

Rainwater

Harvesting

Positiv

e √ √ √ 10

Solid waste

Generation

Negati

ve √ √ 0

Gardening &

Landscaping

Positiv

e √ √ √ 10

SOCIO

ECONOM

IC

ENVIRO

NMENT

Occupancy Positiv

e √ √ √ 10

Operation of

DG Sets

Negati

ve √ √ √ √ -6

Sewage

Generation &

Discharge

Negati

ve √ √ √ √ -6

Rainwater

Harvesting

Positiv

e √ √ √ 8

Solid waste

Generation

Negati

ve √ √ √ -6

Gardening &

Landscaping

Positiv

e √ √ √ 8

Page 36: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 81

2.4 IMPACT ON AIR ENVIRONMENT

2.4.1 Construction Phase

Impacts of construction activities on air quality are cause for concern

mainly in the dry months due to dust particles. The main sources of emission

during the construction period are the movement of equipment at site and dust

emitted during the leveling, grading, earthworks, and other construction related

activities. The dust emitted during the above mentioned activities depend upon

the type of soil being excavated. Existing baseline parameters values are SOx-

9.4 µg/m3, NOx- 19.4 µg/m

3 and SPM- 49.6 µg/m

3. An average of 20-30 %

incremental pollution during construction for air parameters will be envisaged.

However, the impact will be for short duration and confined locally to the

construction site. The composition of dust in this kind of operation is, however,

mostly inorganic and non-toxic in nature.

The impact of such activities would be temporary and restricted to the

construction phase. The impact will be confined within the project boundary

and is expected to be negligible outside the plant boundaries. Proper upkeep

and maintenance of vehicles, sprinkling of water on roads and construction site

are some of the measures that would greatly reduce the impacts during the

construction phase. Thus, it is inferred that no significant impacts are expected

on the overall ambient air quality due to the proposed construction activities.

Transportation of heavy machinery and building materials implies heavy

traffic on the roads leading to the site with possible negative impacts to the

surrounding area (dust, spillage, emissions and noise). Transportation of

construction materials as well as improper storage of building materials,

especially gravel, sand and cement in the construction site will lead to

inadvertent dispersal of materials during heavy rain or high wind during dry

Page 37: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 82

periods. Measures will be adopted for proper handling of construction

materials to reduce the negative impact.

2.4.2 Operation Phase

Ambient air quality at the proposed project site and its surroundings is

monitored and values of the pollutants RPM, PM2.5, NOx and SO2 are within the

limits of NAAQS, 2009 prescribed by the central pollution control board.

There is no major pollutant envisaged from the proposed development. It

is likely that the air quality may be affected slightly due to the emissions from

the vehicular movement. The emission from DG sets will be very negligible

since it will be used only during power cut in the necessary area. However in

the case of DG sets the stack will be properly designed to meet the stipulations

of CPCB. These emissions will be insignificant and the environmental pollutant

levels will be maintained within the prescribed limits. Hence there shall not be

any adverse impact on the air environment around the proposed commercial

complex.

2.5 IMPACT ON AMBIENT NOISE

2.5.1 Construction Phase

During the construction noise levels will increase due to use of machinery

and heavy vehicles in the project area. In terms of noise emission; demolition,

excavation and construction work can be divided into two phases, namely (1)

Demolition and Earthworks and (2) building works. Loading and unloading of

construction materials, fabrication, handling of equipment and material,

operation of power shovels etc. will be the major source of noise during the

construction phase. Various construction activities will cause short-term noise

impact in the immediate vicinity of the project site.

Page 38: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 83

The areas affected are those close to the site and hence the impacts are

localized. At the peak of the construction, marginal increase in noise levels is

expected to occur. The peak noise levels from continuous construction activity

may be as high as 80 - 90 dB (A). The noise control measures during

construction phase shall restrict the noise levels to lower levels. Hence the

overall impact on the ambient noise levels will not be significant.

2.5.2 Operation Phase

There will not be any major impact from noise. This is because no

equipment or other infrastructure facility in the project generates noise more

than 50-60 dB (A). However, the only noise generation source is the DG set.

The promoters have decided to adopt adequate steps to maintain the noise

levels within the prescribed limits. For the same all the DG facility will be

equipped with acoustic enclosure. Apart from this honking will be prohibited at

the site and speed limits will be restricted within the site. This will significantly

help in controlling noise levels at the site. Further the green belt provided

within the site will act as noise barrier between inside and outside environment.

This will act as buffer and protects the site from high noise levels outside the

site.

Traffic will increase during both construction and operation phase of the

project. Vehicles associated with construction would generate intermittent

noise throughout the vicinity of the proposed action. In the operation phase,

vehicular parking is being provided in the basement, ground floor and first

floor of the building where noise levels are expected to increase substantially

during the peak hours due to starting, idling and roaring of vehicles.

Page 39: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 84

2.6 IMPACT ON LAND ENVIRONMENT

No blasting will be done during construction phase of the project. The

rehabilitation and resettlement issues are not involved in the project.

Furthermore the existing environmental conditions of the project site reveal that

the land is not contaminated or polluted.

Top soil will be excavated up to 15 cm from the project site. It will be

stored in covered area during construction phase and will be used for

landscaping in operation phase within project site. The upper/top level of soil

will be affected during construction phase but this will be limited to a portion

of the project area. Also the impact due to exploitation of ground water is

insignificant in the site due to the sourcing of water from other sources during

the operation phases.

2.7 IMPACT ON WATER RESOURCES

2.7.1 Construction Phase

The required water quantity for construction will be utilized from the

available resource in the project area. Impact on water quality during

construction phase may be due to non-point discharges of sewage generated

from the construction work force, stationed at the site. Construction activities

for the proposed development can have minor impact on hydrology

and ground water quality of the area if the construction waste leaches into

ground.

Potential sources of impacts on the hydrology and ground water quality

during the construction phase would be soil runoff, improper disposal of

construction debris, spillage of oil and grease from the vehicles and wastewater

stream generated from on-site activities such as vehicles washing, workshop

etc. Precautions and preventive measure will be taken at the site during

Page 40: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 85

construction to avoid any ground and surface water contamination hence the

overall impact on water environment during construction phase due to proposed

project is likely to be insignificant.

2.7.2 Operation Phase

The total quantity of wastewater generation is likely to be 299 KLD which

will be treated in proposed sewage treatment plant of 320 KLD capacities and

will be recycled for flushing, gardening, OSR and remaining excess treated

sewage will be disposed to CMWSSB.

2.8 IMPACTS DUE TO WASTE DISPOSAL

2.8.1 Stacking and Disposal of Construction Materials

Stacking of construction materials will be confined to the project site only

and also temporary sheds will be provided to store the materials, hence no

impacts on surrounding area will be envisaged. Solid wastes generated due to

proposed project during construction phase include sand, gravel, stone, bricks,

plastic, paper, wood, metal and glass. Recyclables will be sent to authorize

recyclers. Hence there is no significant impact due to waste disposal during the

construction phase.

2.8.2 Operation Phase

The solid waste generated from the project will be collected daily and

moved to a common temporary storage facility by the staff dedicated for waste

collection. The collected Solid waste will be disposed through Organic waste

converter.

Page 41: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 86

2.9 IMPACTS ON ECOLOGICAL RESOURCES

2.9.1 Construction Phase

The impact of construction activities will be primarily confined to the

project site. The project site is a vacant land and devoid of any vegetation. Thus

the site development work will not lead to any significant loss of any important

plant species. Deposition of fugitive dust on leaves of nearby vegetation may

lead to temporary reduction of photosynthesis. Such impacts will, however, be

confined mostly to the initial period of construction phase. Hence the proposed

development will not lead to habitat destruction, fragmentation or vegetation

damage.

2.9.2 Operation Phase

No wastewater will be discharge into the surface water stream. Hence,

there will not be any impact on the aquatic ecology. Also the proposed project

is to be located in an earmarked commercial zone, which does not have any

natural park or sanctuary or forest area in the immediate vicinity. The flora and

fauna pattern in the area will not be disturbed due to the project. Hence the

overall impact on ecological resources due to proposed project is likely to be

insignificant. Moreover the entire project area would be landscaped with

variety of plants.

2.10 IMPACT ON TRAFFIC LEVELS

2.10.1 Construction Phase

The movement of construction equipments will be mostly within the site

during the project. Vehicles bringing in raw materials like sand, cement and

aggregate materials will be moving into the site from outside, which will be

strictly controlled and monitored as per the traffic rules, to avoid any sort of

disturbance to the traffic and safety of the surrounding areas. Hence the impact

Page 42: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 87

due to the vehicular movement during the construction phase would be minor

or insignificant.

2.10.2 Operation Phase

Based on the vehicular density observed during the traffic survey

conducted on the main roads around the proposed site, the existing

infrastructure is capable of taking up additional traffic loads. Also the project is

to be executed phase wise; the increase in traffic will be easily handled by the

existing as well as the future improvements in the transportation infrastructure.

Hence there will not be any impact on the traffic pattern and density.

2.11 IMPACTS ON SOCIO ECONOMIC ENVIRONMENT

The required land for the development is owned by M/s. Anandram

Developers Pvt Ltd. The proposed Mall/ Hotel/ Theatre complex will be open

to members of all communities and castes. The above measure will encourage

mixing of different caste people for their respective festivals and occasions.

This will improve the social welfare and brotherhood among the various

communities and castes.

Also the state of the art facilities proposed in the development is planned

to cater the needs of the occupants which would be able to provide healthy

working atmosphere. Hence it is obvious to assume that the activities of the

proposed development will produce some positive impacts in the socio-

economic status of the area.

2.11.1 Public Health and Safety

As the project is only a construction of Mall/ Hotel/ Theatre complex and

all the construction activities are confined to the project site, no health related

impact would be envisaged within the project area. The people engaged in the

Page 43: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 88

construction activities will be directly exposed to dust generation, which is

likely to cause health related impact. Appropriate mitigation measures like

spraying of water will be adopted to minimize dust emission in the construction

site. Laborers will be provided with suitable Personal Protective Equipment

(PPE) as required under the health and safety norms. Regular health checkups

will be organized.

2.11.2 Positive Impact

The project will facilitate maximum participation of the local work force

for construction process; this will benefit the local economy, improvement in

economic activity and enhancement in earning opportunities for the local

population. The operation of the project and other allied facilities will improve

the employment opportunities. The project will provide direct and indirect

employment. About 100 – 150 persons will be employed during the operation

stage for the purpose of day-to-day maintenance works. The employment will

have positive impact on the local economy thereby increasing the quality of

life. The proposed rain water recharge facility will augment the ground water

level in the project area. The proposed project will also improve the aesthetics

of the area due to the development of modern buildings.

Page 44: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 89

CHAPTER - 3

3.0 ENVIRONMENTAL MANAGEMENT PLAN

3.1 GENERAL

Environmental Management Plan (EMP) is aimed at mitigating the

possible adverse impacts of the project and for ensuring to maintain the

environmental quality. The environmental management plan consists of the set

of mitigation, management, monitoring and institutional measures to be taken to

eliminate the adverse environmental impacts or reduce them to acceptable

levels.

3.2 AIR POLLUTION CONTROL AND MANAGEMENT

3.2.1 Construction Phase

The impacts will be due to the air emissions like particulate matter (PM10&

PM2.5), CO, NOx and SO2 due to material handling, vehicular movements and

other site activities. The particulate matters will be reduced by frequent

sprinkling water on the road surfaces and on other areas where dust is arising

due to material handling. All the equipments and vehicles used in the

construction and transportation of materials will be maintained properly and

only low sulphur diesel will be used as fuel for DG sets and construction

equipment and vehicles.

The emissions from the DG sets will be let out only through the stacks

with adequate heights as per CPCB norms. This will avoid the deposition of the

particulate matters and other pollutants by facilitating the through dispersion of

pollutants into the atmosphere. The stacking of all the construction materials

will be confined only within the proposed site. Vehicles carrying the raw

material and debris will be covered to minimize dust emissions while travelling.

Page 45: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 90

Adequate parking space will be provided for construction vehicle and

machinery to prevent idling and thus will help in minimizing the emissions.

Wheel wash facility will be provided at the exit point of the site.

3.2.2 Operation Phase

Air emissions are observed during the operation phase of the project. The

air emissions will be reduced by ensuring smoother flow of traffic within the

premises by better traffic management plans. It is proposed to have trees all

through the boundaries of the site and along the either side of the internal roads.

This will reduce the particulate matters from being transported to the nearby

areas. The air emissions from the Diesel Generators will be controlled by using

low sulphur content high speed diesels, periodic maintenance of DG sets as per

the defined schedule of manufacturer and by providing adequate stack heights

as prescribed by CPCB. The stack height for the DG sets are calculated based

on the CPCB guidelines as shown below;

The proposed project to have

4 nos. - D.G. Sets of 3 x 2000 KVA Capacity and 1 x 1500 KVA

3.2.3 Air Pollution Control (APC) Measures

The main source of air emissions from the proposed commercial

development is the Generator Sets the above proposed generator sets will be

used only during TNEB power failure. To control the air emissions from these

D.G sets, adequate stack height is provided to release the exhaust flue gases into

the atmosphere at a height at which efficient dispersion takes place. Since the

DG sets are operated only during power failure, the emission is not continuous

and hence the impact due to these emissions is insignificant.

Page 46: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 91

The stack height for the DG sets are calculated based on the CPCB

guidelines as shown below;

Stack Height Design Calculation for 2000 KVA Generator Set

H = h + (0.2) (kVA) 0.5

= 51.88 + 0.2 (2000) 0.5

= 51.88 + 8.94

= 60.82 ~ 61 m

Where, H = Total height of stack in meters from ground level

h = height of the building in meters

The stack height required as per CPCB norms is 61 m which will be provided

for all 3nos. of 2000 KVA DG sets.

Stack Height Design Calculation for 1500 KVA

H = h + (0.2) (kVA) 0.5

= 51.88 + 0.2 (1500) 0.5

= 51.88 + 7.7

= 59.6 ~ 60 m.

Where, H = Total height of stack in meters from ground level

h = Height of the building in meters

The stack height required as per CPCB norms is 60 m for D.G set of capacity

1500 KVA.

Page 47: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 92

3.3 NOISE CONTROL AND MANAGEMENT

3.3.1 Construction Phase

The noise generated from the construction equipments will be reduced

through proper maintenance of all the equipments which are involved in

construction activities, confining the construction activities only during the day

time and providing barricades all around the project area. The adverse impacts

of noise especially on workers will be reduced by providing ear muffs to the

workers in high noise zones. Noise control systems such as equipment

foundation pads, dampeners, silencers and acoustic enclosures will be used for

individual units as per the requirement to minimize the noise & vibration.

3.3.2 Operation Phase

The increase in the ambient noise levels due to the vehicle transportation

will be controlled by the development of the green cover all along the internal

roads and by implementing better traffic management plans inside the site

premises. The better traffic management plans will significantly reduce the

noise generated due to the congestion caused by the movement of vehicles.

The generator noise is controlled by providing acoustic enclosures. Proper

air ventilation system is designed to allow the maximum aspiration and cooling

airflow required so that the engines do not overheat. Axial flow fan of required

size & numbers provided for proper air ventilation. Acoustic louvers, splitter &

insulated ducts are provided to suppress the noise where required.

Also Noise monitoring was done during the study period. The values were

Leq Day: 52.7 dB (A) Leq Night: 36.5 dB (A). The values were within the

limit. Also during operation care will be taken to ensure that there will not be

any incremental load in the environment.

Page 48: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 93

3.4 SOLID WASTE MANAGEMENT

3.4.1 Construction Phase

Separate raw material handling yard will be demarcated. This will prevent

the contamination of the soil due to the spillage of the construction materials.

Cement will be separately stored under cover in bales. The raw material

handling yard will be located within the project site and separated by

enclosures/barricades. This will keep the working area clean and reduce the soil

contamination.

3.4.2 Operation Phase

During the operation phase the used oil from the DG sets will be collected

in separate drums and handed over to the authorized recyclers by TNPCB.

Hazardous Waste: During the operation phase the used oil, DG filters, oil

mixed cotton waste and oil containers from the DG sets will be collected in

separate place.

Table 14: Generation and disposal of Hazardous waste Quantity per annum

S.

No

Waste

category

Description

of waste

Quantity

in

Tonnes/per

annum

Activity/Activities for which

authorization is required

Collection

& Storage

Transport &

Disposal

1 5.1 Used oil

0.4

MS drums

within the

premises

Disposed to

authorized re –

processors

Non- Hazardous Waste:

It is estimated that the municipal solid wastes will be generated in the

following passion:

Biodegradable wastes : 6579 Kg/day

Non-biodegradable wastes : 1816 Kg/day

Page 49: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 94

In the commercial complex development, Wastes generated from the

households will be segregated into Bio degradable waste and non- bio

degradable waste in the source itself (by the occupants) in separate bins. The

wastes from such bins are collected separately on daily basis and taken to a

separate centralized collection facility by the agency dealing in collection and

disposal of garbage. Appropriate site will be identified for keeping the

biodegradable and Non-biodegradable waste. All the collection bins shall be

properly maintained and cleared on regular basis. The Bio degradable wastes &

inert fractions will be disposed off through the local municipality, and non-bio

degradable recyclable waste will be handed over to authorized recyclers.

Horticulture wastes leaves, grass and vegetative residues shall be collected

at the secured location such that it will not hinder daily activity schedule or

washed away by the surface run-off causing choking of drains, etc. and will be

separately treated and disposed off along with biodegradable waste.STP sludge

will be stabilized, and dewatered for separation of solids, which will be used as

manure in horticulture.

Fig. 3: Solid Waste Management

3.5 WATER AND WASTEWATER MANAGEMENT

3.5.1 Construction Phase

The wastewater generated by the construction workers will be treated and

disposed through septic tank with soak pit arrangement. All the water storage

Solid waste

Source Separation

Biodegradable Waste

Collection point

Local Municipality

Collection point

Non Biodegradable Waste

Sent to authorized recyclers

Page 50: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 95

tanks/containers will be maintained without any leaks. Necessary precaution

and preventive measures will be taken at the site during construction to avoid

any groundwater and surface water contamination.

3.5.2 Operation Phase

It is proposed to use the recycled water for the part of the daily water

demand in the premises. The total water requirement during operation is

438KLD and the fresh water requirement is 160 KLD. The source of water is

taken to be CMWSSB since the quality of borewell water from the baseline

study was found to be TDS 668 mg/L; Total hardness 303 mg/L; sulphates 71.4

mg/L and chlorides 143 mg/L does not comply with drinking water

specification as per IS 10500:2012. Hence it is not recommended for drinking

purpose, and it is also not advisable for other domestic uses due to very high

salt content. In case of emergency, Water Treatment Plant will be proposed for

domestic uses, for which the quality of treated water will be TDS < 500 mg/L;

Total hardness < 300 mg/L; chlorides < 250 mg/L and sulphates < 200 mg/L.

The components of water treatment plant will be aeration tank, settling tank,

sand filter and carbon filter with iron removal media filled in it. The wastewater

generation from the project is estimated to be about 299 KLD, which will be

treated in proposed Sewage Treatment Plant of 320 KLD capacity. Treated

sewage will be reused for flushing, gardening, OSR and the remaining excess

sewage will be disposed through CMWSSB sewer lines. The sewage treatment

design is described in the Annexure - VII.

3.6 STORM WATER MANAGEMENT

3.6.1 Construction Phase

The surface runoff during the construction period will be directed into the

drains separately provided for this purpose.

Page 51: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 96

3.6.2 Operation Phase

Rain water from internal roads etc will be discharged through storm water drain

sloping towards rain water collection sumps. The Rainwater down comer pipes

from terrace level directly connected to rainwater inspection chambers

interlinked and discharged to filtration bed to store Rain water of min. An

overflow pumping main pipe will be laid as lead pipe from rainwater harvesting

trench up to the road for draining the excess water during rainy seasons.

DESIGN PARAMETERS:

Total Plot Area Considered 18149.26 Sqm

Total roads and pavement area 3557.79 Sqm

Total Greenbelt Area 2915.43 Sqm

Total Roof Area 7421.55 Sqm

Intensity of rainfall considered in Chennai : 0.06 m/hr

Co – efficient of runoff considered for roof area : 0. 90

Co – efficient of runoff considered for road/paved area : 0. 75

Co – efficient of runoff considered for landscape area : 0. 1

Hence, the total quantity of rainfall will be: q= a x p x r

q = quantity of rainwater run - off in cu.m / hr.

a = area of catchments drained in Sq.m

p = permeability factor

r = rainfall intensity in m / hr

Table 15: Run –off Calculations

Description Area in

Sqm

coefficient

runoff

Rainfall

intensity in m/hr

Total Rainwater

Runoff (Cum)

Road area 3744.34 0.75 0.06 168.5

Landscape area 2793.27 0.1 0.06 16.8

Page 52: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 97

Roof area 7421.55 0.9 0.06x0.8* 320.6

Total Annual Rainfall Run-off/hr 505.9

Run off to UG sump (will be reused for domestic purpose

after filtration) 160

Total runoff for recharge 345.9

Run off to recharge pit 186.3

Size of RWH Pit (diameter- 1.5m , depth 1.5 m) 2.65

Size of borehole (diameter- 150 mm , depth 3 m) 0.05

No. of Pits Required 50 Nos.

No. of pits Provided 69 nos.

Excess runoff to external storm water drain 159.6

* - Evaporation, Spillage, first flush wastage.

Annual runoff is estimated to be 505.9 cum (Considering 60 mm annual

rainfall in the region)

The runoff from rooftop will be diverted to the rain water collection

trench.

During abnormal rains, the excess runoff after storage and recharge will

be disposed off through the external storm water drains.

a. Details of recharge pit

Recharge through Pits : 69 nos.

A portion of rain water falling over the roofs, road and paved area and the

open area will be used for recharging the ground water. The dimension of pits is

1500 mm diameter and 1500 mm depth. Recharge pits are normally excavated

as any shape, which are sufficiently deep to penetrate the low-permeability

layers overlying the permeable layer. They are similar to recharge basins in

principle, with the only difference being that they are deeper and have restricted

bottom area. In many such structures, the infiltration occurs vertically through

the permeable layer is much higher than the low permeable layer occurring in

the top.

Page 53: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 98

The pits will be filled with gravels (1-10mm) at bottom, coarse sand (1.1-

2mm) at middle and fine sand at the top in graded form. Gravels at the bottom,

coarse sand in between and fine sand at the top so that the silt content that will

come with runoff will be deposited on the top of the fine sand layer and can be

easily be removed. The top sand layer of the recharge pits will be periodically

cleaned to ensure the proper recharge.

Fig. 4 Cross section of recharge pit

Page 54: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 99

b. Recharge Trenches

Recharge trenches are normally excavated as linear pits, which are

sufficiently deep to penetrate the low-permeability layers overlying the

permeable layer. They are similar to recharge basins in principle, with the only

difference being that they are deeper and have restricted bottom area. In many

such structures, the infiltration occurs vertically through the permeable layer is

much higher than the low permeable layer occurring in the top. Recharge

Trench will be constructed in the premises of the company across the slopes.

Trench maintained all along the boundary, the depth of the trenches will be

around 1.5 m. It is planned to remove the entire impervious layer to facilitate

rain water recharge. The width of the proposed trenches is 1 m. Pebbles of

different size will be provided in an ascending order in the tank and a layer of

sand will be provided on top of the filter media. The rain water flowing through

the open land, paved area and green belt area will be used for recharging to

ground water through the above said trenches.

c. Rain Water Storage Sump:

Rain water storage sump 1,60,000 litres capacity- 1 nos. is proposed for

rainwater storage and reuse.

The Rain water storage and harvesting plan has been designed as per the

Rain water harvesting (RWH) & conservation manual by CPWD, Govt .of

India, 2002 & in compliance with Ministry Notification dated 9th December

2016 under 50,000 to 1,50,000 Sqm category.

d. Flood Occurrence:

The highest recorded monthly rainfall in that area and surroundings of

Chennai is 521mm in 2010, considering the previous 5 years day peak rainfall

Page 55: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 100

(Refer Table below from IMD). The storm water management has been done,

the total peak flow at the site by taking 600 mm of highest average rainfall/day

in site, the runoff will be 498.2 cubic meter/hr after development, the recharge

pit, storm water collection sump and storm water collection drain have been

designed in the site to the manage the rain water during heavy rainfall time.

Table 16: DISTRICT RAINFALL (mm) FOR LAST FIVE YEARS

Note : (1) The District Rainfall(mm.)(R/F) shown below are the arithmetic

averages of Rainfall of Stations under the District.

Year

Rainfall (mm)

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2010 63.1 11.2 114.2 11.7 0.1 65.1 23 100.5 97.1 378 521.1 6.8

2011 13.1 0.0 0.7 0.0 14.0 11.3 41.8 93.9 73.6 46.5 493.8 259.5

2012 4.7 0.1 0.0 0.0 191.1 120.2 146.0 195.1 107.5 165.6 224.2 263.7

2013 11.8 41.8 0.0 19.4 10.0 118.0 85.6 330.5 235.5 241.1 447.3 147.5

2014 17 0.0 0.5 0.0 0.0 21.2 67.3 94.5 164 394.3 39.2 134.4

Source: Consolidated Report for Indian Meteorological Department

3.7 LANDSCAPE AND ECOLOGICAL MANAGEMENT

3.7.1 Pre-Construction Phase

a. Assessment of Flora in the Study Area

The Vegetation present within a defined area is termed as a plant community. This

is determined by the nature of the dominant species it contains. By the term

dominant species or dominance it is understood that species of plants having same

life and growth, forms predominating in an area. A systematic order of

angiosperm families recorded in the study area is given in Table.17.

Page 56: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 101

The distribution of vegetation at different sites, its density, dominance,

frequency, Importance Value Index (IVI), economic importance, and medicinal

uses were studied and the results are given in the following sections.

TABLE-17 DISTRIBUTION OF VEGETATION IN THE STUDY

AREA

I. Agricultural

Crops Nil

II. Plantation Nil

III. Natural Vegetation

a. Herbs Hemidesmus indicus, Carissa spinarum,

Heteropogon contortus

b. Shrubs Prosopis juliflora, Dodonaea viscosa, Glycosmis

pentaphylla ,

c. Trees

Azadirachta indica, Arecaceae, Cocos nucifera,

Carica papaya, Psidium guajava, Ficus

benghalensis, Moringa oleifera, Borassus flabellifer,

Musa acuminat.

IV. Endangered

Species Nil

V. Endemic Species Nil

VI. Medicinal

Plants

Ocimum tenuiflorum, Plectranthus amboinicus,

Heliotropium indicum, Moringa oleifera, Solanum

torvum, Trachyspermum ammi

b. Assessment of Fauna in the Study Area

The details of fauna found in the study area are given in the Tables.18

TABLE-18 FAUNA IN THE STUDY AREA

S. NO. Common Name Scientific Name Status

BUTTERFLIES AND INSECTS

1. Common crow Euploea core C

Page 57: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 102

2. Grass yellow Terias hecabe C

3. Dragon fly Agrion sp & Petalura

sp C

4. Grasshopper Hieroglyphus sp C

5. Termite Hamitermes silvestri C

6. Ant Monomorium indicum C

AMPHIBIANS

1. Common Indian Toad Bufo melanostictus C

REPTILES

1. Common Garden lizard Calotes versicolor C

2. Common skink Mabuya carinata C

BIRDS

1. Pond Heron Ardeola grayii C , R

2. Small Egret Egretta intermedia C , R

3. Shikra Accipiter badius C, R

4. Spotted Dove Streptopelia chinensis C, R

5. RoseRingedParakeet Psittacula krameri C, R

6. Pied Crested Cuckoo Clamator jacobinus C, R

7. Koel Eudynamys scolopacea C, R

8. Spotted Owlet Athene brama C , R

9. Indian Roller Coracias benghalensis C, R

10. Whitebreasted

Kingfisher Halcyon smyrnensis C, R

11. Black Drango Dicrurus adsimilis C , R

12. Common Myna Acridotheres tristis C, R

13. Indian Tree Pie Dendrocitta vagabunda C, R

14. House Crow Corvus splendens C, R

15. Jungle Crow Corvus macrorhynchos C, R

16. House Sparrow Passer domesticus C, R

MAMMALS

1. Indian Palm squirrel Funambulus palmarum C, R

2. Indian pipistrella Pipistrellus coromandra C, R

Page 58: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 103

It is proposed to plant plantation on landscape area and all through the

boundaries of the site and along the either side of the internal roads. This will

have positive impact over the fauna of the locality.

3.7.2 Operation Phase

It is proposed to have a landscape area of around 2793.27 Sqm. It is also

proposed to plant only the native species of plantations. In addition to

augmenting present vegetation, it will also check soil erosion, make the

ecosystem more diversified and functionally more stable, make the climate

more conducive and restore balance. As per MOEF EIA Notification, dated 09,

December 2016, minimum of 1 tree for every 80 square meters of land should

be planted and maintained. For plot area of 18149.26 Sq.m, total no. of trees to

be planted is 227. Total no. of trees proposed for plantation is 230. The

following species are proposed for the plantations in the site. Adequate numbers

of these species will be planted in the Landscape and along the boundaries of

the site and along the either sides of the internal roads.

Table 19: Proposed Tree Plantation Within project Site

S.No. Scientific Name Local Name No. of

Trees

Tree Species

1. Azadirachta indica Neem 50

2. Ficus religiosa Arasa Maram 10

3. Tamarindus indica Tamarind 5

4. Pongamia pinata Pungam 50

5. Eugnea Naval 10

6. Terminalia catappa Indian Almond 10

7. Phoenix sylvestris Icham 10

8. Madhuca longifolia Illupi 10

9. Antocephalus cadamba Vellai Kadambu 10

10. Mimusops elengi Magizham tree 30

Page 59: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 104

11. Terminalia arjuna Marudha maram 25

12. Dalbergia sisoo Nukkam 10

Total no. of trees proposed for plantation 230

3.8 SOCIO ECONOMIC DEVELOPMENT PLAN

3.8.1 Construction Phase

Only locally available workforce will be used for the construction purpose. This

will result in the improved economic condition of the people of that area, at

least during the construction period.

Medical checkups will be done at regular intervals to all the employees

working. Trained first aid personnel will be made available round the

clock throughout the construction phase.

The safety procedures will be made available with the respective shift in

charges and the same will be pasted in the workplaces.

All the employees involved in the construction activities will be provided

with the necessary Personal Protective Equipments (PPE) and instated to

use it.

Occupational health and safety orientation training will be given to all

employees consisting of basic hazard awareness, site-specific hazards,

safe working practices, and emergency procedures

Monthly safety assessment meetings will be conducted to identify

potential safety issues (e.g., site access, construction, work practices,

security, transportation of heavy equipment, traffic management,

emergency procedures and fire control and management) and measures to

mitigate them.

Page 60: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 105

3.8.2 Operation Phase

The people of the locality, especially women, may be employed in the

households as service providers/maintenance staffs. This will improve the

circulation of money in the study area. The project also stimulates the auxiliary

developments around the project area. This will result in the development of

necessary infrastructure and amenities at least around the project site.

3.9 ENERGY CONSERVATION

Energy conservation will be one of the focuses during the project planning

and operation stages.

3.9.1 Energy Saving Practices

Use of Energy Efficient low loss – electrical ballast.

Usage of CFL/LED lamps

Use of capacitor banks power factor improvement of EB power

Use of copper wound transformer

Solar lighting is considered partly for external lighting.

Use of occupancy sensors and dimmers for lights in the parking areas

Solar Proposal as per Ministry notification dated 9th December 2016, under

category of buildings 50,000 sqm to 1,50,000 sqm.

Use of solar lighting will be provided at major junction of the roads and

common corridor lighting including stilt floor parking lights which

contributes to 1% of total demand say 32 kVA.

Page 61: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 106

10% of hot water demand will be provided from Solar water heater, (0.5

cum per day capacity of solar water heater will be provided)

3.9.2 Energy Conservation Measures

a. Building Construction Data

In accordance with Energy Conservation Building (ECBC) Code 2007

norms, Chennai comes under warm & humid climate zone. Hence, based on the

ECBC norms, U Values considered are as follows:

b. Roofs & Opaque Walls

Roofs and opaque walls shall comply with either the maximum assembly

U-factor or the minimum insulation R-value. R-value is for the insulation alone

and does not include building materials or air films. The roof insulation shall

not be located on a suspended ceiling with removable ceiling panels.

Table 20: U-values of the roof and opaque wall of the building

The U-values of the roof and opaque wall of the building will meet

the requirements as specified in the Energy Conservation Building Code

(ECBC)

ECBC

Clause:

(Reference)

Component

Permissible

U-Value as

perECBC

(W/m2°C)

Resultant Value due to the

proposed configuration

(W/m2°C)

4.3.1 Roof U-0.261 R-3.5

4.3.3 Wall U-0.44 R-2.1

Page 62: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 107

c. Vertical Fenestration

Vertical fenestration shall comply with the maximum area weighted U-

factor and maximum area weighted SHGC requirement. Vertical fenestration

area is limited to a maximum of 60% of the gross wall area for the prescriptive

requirement.

Table 21: Vertical Fenestration

Description

WWR=40% 40%

<WWR<=60%

Maximum

U-factor

Maximum

SHGC

Maximum

SHGC

Glass 3.3 0.25 0.20

d. Electrical & LV Systems

a. Copper conductor cables are specified for sizes of 16 sq mm and

below, this will reduce losses and improve reliability.

b. All lifts shall be provided with AC variable voltage, variable

frequency drives (ACVVF).

c. Power factor shall be maintained 0.95 or higher. This will reduce

electrical power distribution losses in the installation.

d. Timers and photo-electric sensors shall be used to switch ON / OFF

external landscape and facade lighting.

e. Compact Fluorescent Lamps (CFL’s) with high frequency ballast

shall be used for plant rooms, corridors and BOH areas.

Page 63: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 108

f. All fluorescent light fixtures are specified to incorporate electronic

chokes which have less watt-loss compared to electro-magnetic

chokes and result in superior operating power factor. This indirectly

saves energy. Electronic chokes also improves life of the fluorescent

lamps.

g. All fluorescent light fixtures are specified to incorporate high

frequency ballast. Due to high frequency ballast florescent tube

consume less energy.

h. Energy efficient fluorescent lamps & CFL lamps which give approx.

30% more light output for the same watts consumed and therefore

require less nos. of fixtures and corresponding lower point wiring

costs.

i. An APFC relay based on thyristor switching is proposed to effect

the power factor correction / improvement within a few cycles of

deviation from the setting & also to reduce inrush currents.

j. Transformers shall have minimum no load losses as compared to

conventional transformers.

e. Plumbing & Fire Fighting

a. VFD based hydro pneumatic system.

b. Efficient condensate return & recovery system for domestic hot

water.

c. Pumps & equipment selected on “best” energy efficiency point.

Page 64: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 109

3.10 SOIL ENVIRONMENT

The top soil is filled up material (Debris) of 1.4 m; Brown Sandy clay is

upto 3m; brown clayey sand upto4.5m; brown silty sand upto 9m; black sandy

clay upto 10.5m; black silty clay upto 13.5m; black clayey sand upto 15.0m;

Black silty clay upto 22.5m and greenish sandy clay with lime stone upto 29m

Details are enclosed in the Geotechnical Soil report attached as Annexure – VI.

3.11 FIRE PROTECTION MEASURES

It is proposed to provide extensive fire protection system for the entire

apartments. It is proposed to provide the facility externally in the area and

internally only in the common areas. The facility is to be terminated at the

tapping point on each floor but the total system is being planned compactable to

entire building. The fire-fighting system involves following arrangements:

Table 22: Fire fighting arrangements

Components Amplified with console, 5 watt ring type recess mounting

speaker, microphone, zone selector panel and wiring.

Speaker

location

One each in lift lobby area

Fire alarm

system

Hooter and manual call point (MCP) will be provided in all

floors near each stair case.

MCP /

Hooter

Tyco

PA Tyco / Fire pro

Page 65: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 110

3.11.1 Fire Fighting System

a. Construction Phase:

1. Dry riser 100 mm diameter pipes with hydrant outlets on the floors

constructed with a fire service inlet to boost the water in the riser from

fire services pumps.

2. Drums filled with water of 2000 litres capacity with 2 fire buckets on

each floor.

3. Water storage tank with 20000 litres capacity which is used for the

construction and other purposes.

b. Operation Phase:

1. Wet riser / 1000 sqm of area covering all floors with landing valves along

with delivery hoses for each block. To feed the wet-riser, an underground

sump of capacity 75,000 liters will be provided with refilling facilities for

each block.

2. Hose reel assembly, Manual fire call points will be provided in each floor

area.

3. Automatic sprinkler system will be provided covering at all floors

4. First Aid firefighting equipment will be provided at all the floors in

accordance with IS 2190:1992.

5. A trained Fire Officer with a crew along with fire control room will be

arranged to maintain as well as to operate the fire protection systems in

case of any need.

3.11.2 Fire Extinguishers

In addition to fire protection system the portable fire extinguishers of

various types are provided near lift lobby in each floor, pump room, transformer

room, DG room and lift machine room etc for fighting light hazard fire. All the

extinguishers used in the project area would be with BIS mark and are located

at an easily accessible position without obstructing the normal passage.

Page 66: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 111

The fire extinguishers used in the project area are given below:

One dry chemical powder extinguisher of 10 kgs capacity and 2

fire buckets filled with clean, dry, fine sand will be provided for

every 8 cars in the parking areas.

One CO2 extinguisher of 2 kgs capacity will be provided near the

entrance to each main switchboard room.

Two dry chemical powder extinguishers each of 5 kgs capacity

will be provided near EB transformer yard.

One dry chemical powder extinguisher of 10 kgs capacity will be

provided near the entrance to each generator room.

One CO2 extinguisher of 2 kgs capacity will be provided inside

each lift machine room.

One water type gas cartridge extinguisher of 9 lts capacity will be

kept near each stair case landing on every floor.

All the extinguishers used in the project area would be with BIS

mark and are located at an easily accessible position without

obstructing the normal passage.

3.11.3 Public address system

In addition to this, it is also proposed to provide public address system in

each floor near stair case area. This will help in addressing / altering the people

residents by the security personal through microphone arrangement.

3.12 RISK ASSESSMENT, DISASTER MANAGEMENT AND

SAFETY MEASURES

3.12.1 Risk Management Plan

Page 67: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 112

A well - defined Risk Management Plan is made as follows:

STEP 1: Define the Projects/Tasks

Site Clearing

Excavation

Raft

RCC slab

Block work / plastering

External plastering

Joinery - frame fixing

Flooring

Interior works

Windows fixing

Flooring

False ceiling

Painting

Services

I.Electrical

II.Plumbing

III.Fire fighting

Equipments

i. Elevator

ii. STP /WTP

iii. Hard and landscape

STEP 2: Identify the Hazards

a) Are you using (Tick boxes)

Page 68: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 113

[ ] Plant/Equipment

[ ] Portable Electrical

Equipment

[ X ] Pressure Vessels/Boilers

[ X ] Hazardous Substances

[ ] Scaffolding

[ ] Ladders

[ ] Lifts/Hoists/Cranes/Dogging /

Rigging/Load Shifting Machinery

b) Does the project/task involve (Tick boxes)

[ ] using tools/equipment with

moving part(s)

[ ] using tools/equipment that

vibrate

[ x ] working with x-rays ,or

lasers

[ ] electrical wiring

[ x ] asbestos removal

[ ] welding

[ x ] hazardous waste

[ ] excavation / trenches

(>1.5m)

[ ] working around electrical

installations

[ ] working near traffic

[ ] working at a height (>3m)

[ ] working in isolation

[] working in a confined space

[ ] manual handling

[ ] repetitive or awkward movements

[ x ] lifting or moving awkward or heavy

objects

c) Is there (Tick boxes)

Page 69: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 114

[ ] noise

[ ] dust/fumes/vapors/gases

[ x ] extreme temperatures

[ x ] risk of fire/explosion

[ ] slippery surfaces/trip hazards

[ x ] poor ventilation/air quality

[ x ] a poorly designed work area for the

project/task

STEP 3: Assess the Risk

Table 23: Risk Assessment during Construction Phase

Activities Air

Pollution

Water

Pollution

Noise

Pollution

Soil

Pollution

Occupational

Hazard

A. Material Handling:

Cement +M - - +M +M

Steel - - + - +M

Sand - - - - -

Stone - - - - +L

Wood - - - - -

Glass - - - - +H

Hardware - - - - -

Color - +H - +H -

Page 70: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 115

B. Construction Machinery

Rotary

Driller +L - +H - +H

Mixers +M - +M +L +M

Excavator +L - +L - +H

Material

Lift - - +L - +H

Risk Factor:

+ : Positive

- : Negative

L : Low

M : Medium

H : High

For any projects/tasks that present a high or extreme risk, a Safe Work Method

Statement must be completed.

STEP 4: Control the Risk

Note how you will control the risk following the priorities listed to the

right. This may include controls like redesigning the workplace, using guards or

barriers, ventilation, using lifting equipment or personal safety equipment.

Eliminate the Hazard

Keep the Hazard and People Apart

Change the Work Methods

Page 71: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 116

Use Personal Protection

Note any specific risk assessments required for high-risk hazards. Check

whether any hazards noted in step 2 require further assessment or action.

[ x ] hazardous substance risk

assessment

[] test and tag electrical

equipment

[ ] confined spaces risk assessment

[ ] sound level test

a) Note Permits/Licenses/Registration required

[x ] Demolition work

[ ] Electrical wiring

[ x ] Pressure vessels

[ x ] Friable asbestos removal

[ x ] Ionizing radiation sources

[ ] registers for chemicals, Personal

protective Equipment, training,

ladders, lifting gear

b) Note certificates of competency/licenses for operators

[ ] Scaffolding

[ ] Rigging

[ ] Load shifting machinery

operation

[ ] Pesticide application

[ ] Crane operation

[ ] Hoist operation

c) Note emergency systems required

[ ] first aid kit [ ] Fire control

Page 72: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 117

[ ] extended first aid kit

[ ] emergency stop button

[ ] additional emergency

procedures

[ ] remote communication mechanism

[ x ] others

STEP 5: Actions Required to Control the Risk

A. During construction to reduce pollution:

Manual water sprinkling during dust excavation

Using RMC to reduce air pollution

Dust cover for Trucks

New Construction Machinery

Equipment will work intermittently

Rotary drillers instead of acoustic drillers

Vehicular trips will not be at peak traffic hour

Ear Plugs to workers

No noise polluting work in night shifts

B .Safety & Hygienic Measures:

Adequate drinking water, toilet and bathing facilities

There will be free medical camps and first aid rooms for workers

Safety equipments like helmets, safety shoes etc. to personnel and

visitors

Personnel protective equipments like leather gloves, goggles and ear

muffs when required

Personnel working on heights will wear safety equipments and will not

work alone

Page 73: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 118

To prevent any accidents, the entire area under construction will be

cordoned off with tin sheets and safety tape is run outside this fence

Regular pest control will be done

Adequate fire fighting equipments will be provided

Operational Phase:

Risks in the complex will be due to natural calamities like earthquake,

flooding and others such as fire and accidental hazards. All precautions will be

taken to control these risks. Fire fighting system shall be provided as per

regulations of Chief Fire Officer. For earthquake resistance, the structural

design shall be as per is certified as per IS code 875 and IS- 1893-2002 for

Seismic Zone 3 of Chennai.

a. First Aid Facilities:

Construction projects will comes under the highly hazard or specific

hazard category. Requirement of the first aid provision at work depends on

several factors including size of the undertaking, number of employees, hazard

arising , access to medical services, workers in isolated locations, etc.,

Construction phase we have plan to appoint one trained first aider for this

proposed development project, and a registered nurse.

b. First Aid Room:

Location, Work Space, Work Environment, Signs & Management –

the First Aid room easily accessible during working hours and also close to road

access. The first aid room should be easily recognizable signs.

First Aid Minimum Requirements for this proposed construction project:

Page 74: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 119

Furniture & Fittings: Wash basin with hot and cold water supplies, Desk, work

bench or dressing trolley, Telephone, Electric power points, Couch with

blankets and pillows.

Medical Requirements: Examination Table, Examination Lamp, Stretcher

Lifting Frame or similar device for transporting patients, First aid kit, Dressing

clothes and gloves, soap, disposable towels, trays and bowls.

3.13 DISASTER MANAGEMENT PLAN

A disaster or emergency is a threatening condition that requires urgent

action. Effective emergency action can avoid the escalation of an event into a

disaster. Emergency management involves plans and institutional arrangements

to engage and guide the efforts of government, non-government, voluntary and

private agencies in comprehensive and coordinated ways to respond to the

entire spectrum of emergency needs.

The overall objective of an Emergency Response Plan (ERP) is to make use

of the combined resources at the site and outside services to achieve the

following:

1. To localize the emergency and if possible eliminate it;

2. To minimize the effects of the accident on people and property;

3. Make the rescue and medical treatment of casualties more effective;

4. Safeguard other people;

5. Evacuate people to safe areas;

6. Informing and collaborating with statutory authorities;

7. Initially contain and ultimately bring the incident under control;

8. Preserve relevant records and equipment for the subsequent enquiry into

the cause and circumstances of the emergency;

9. Investigating and taking steps to prevent reoccurrence.

Page 75: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 120

The ERP is therefore related to identification of sources from which hazards

can arise and the maximum credible loss scenario that can take place in the

concerned area. The plan takes into account the maximum credible loss

scenario - actions that can successfully mitigate the effects of losses/ emergency

need to be well planned so that they would require less effort and resources to

control and terminate emergencies, should the same occur.

Main hazards identified for the project include hazards pertaining to fires in

buildings and fire in diesel storage areas, earthquake and LPG leakage and an

ERP pertaining to these is described in the following section.

3.13.1 Response in case of earthquake

a. Earthquake Preparedness

1. Know how and where to take cover during a quake

2. Anchor furniture over 42”. Do not stack furniture

3. Move tall bookcases away from exits. Do not use them as room dividers

4. Anchor computers, equipment, and display cases

5. Store heavy items at floor level

6. Back up critical data. Keep duplicates off-site

b. Response Procedures for Occupants

If indoors:

1. Take cover under a piece of heavy furniture or against an inside wall and

hold on.

2. Stay inside: The most dangerous thing to do during the shaking of an

earthquake is to try to leave the building because objects can fall on you.

If outdoors:

Move into the open, away from buildings, streetlights, and utility wires. Once in

the open, stay there until the shaking stops.

If in a moving vehicle:

Page 76: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 121

Stop quickly and stay in the vehicle. Move to a clear area away from buildings,

trees, overpasses, or utility wires. Once the shaking has stopped, proceed with

caution. Avoid bridges or ramps that might have been damaged by the quake.

1. After the earthquake be prepared for aftershocks.

2. Although smaller than the main shock, aftershocks cause additional

damage and may bring weakened structures down.

3. Aftershocks can occur in the first hours, days, weeks, or even months

after the quake.

4. Help injured or trapped persons.

5. Give first aid where appropriate. Do not move seriously injured persons

unless they are in immediate danger of further injury. Call for help.

6. Remember to help those who may require special assistance--infants, the

elderly, and people with disabilities.

7. Stay out of damaged buildings.

8. Use the telephone only for emergency calls.

c. Response Procedure for Emergency Team

1. Formulate an Emergency Response Team for earthquake response.

2. Using the public address system, inform people of response procedures

discussed above.

3. Inform the necessary authorities for aid.

4. Ensure no person is stuck beneath any debris, in case of a structural

failure.

5. Ensure that all occupants standing outside near the buildings are taken to

open areas.

6. Ensure that the first aid ambulance and fire tender vehicles are summoned

if necessary.

7. Inform the nearby hospitals if there are any injuries.

8. Check the utilities and storage tanks for any damage.

Page 77: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 122

3.13.2 Response in case of fire

a. Fire Preparedness

1. Note the location of alarms and extinguishers. Know how to use them

2. Leave fire doors closed at all times

3. Clear obstructed corridors, aisles and room exits

4. Limit use of extension cords and multiple outlets

5. Do not use mechanical rooms or utility rooms for storage

b. Response Procedures for Occupants

1. Required response during in the event of a fire should be described in

signs located in the lobby.

2. On sighting a fire, it should be immediately informed to the environment

manager giving the exact location and type of fire in detail.

3. Initiate the Emergency Response Team for fires.

4. If the fire is small, engage in extinguishing the fire using the nearest fire

extinguisher.

5. Guide the Emergency Response Team staff to the emergency assembly

point.

6. The Emergency Response Team should immediately inform the nearest

dispensary and security force. If required a fire tender should be

summoned.

7. The response team should immediately move to the point of fire and take

all necessary steps to stop the fire. If the fire is not controllable and

spreads then the manager in charge should inform the district authorities

and call for external help.

8. The Emergency Response Team will provide immediate relief to the

injured at the scene of incident. Any injured persons should be evacuated

on priority to the dispensary or one of the nearest hospitals based on their

condition.

Page 78: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 123

c. Instructions for occupants

1. Get out of buildings as quickly and as safely as possible.

2. Use the stairs to escape. When evacuating, stay low to the ground.

3. If possible, cover mouth with a cloth to avoid inhaling smoke and

gases.

4. Close doors in each room after escaping to delay the spread of the fire.

5. If in a room with a closed door.

6. If smoke is pouring in around the bottom of the door or if it feels hot,

keep the door closed.

7. Open a window to escape or for fresh air while awaiting rescue.

8. If there is no smoke at the bottom or top and the door is not hot, then

open the door slowly.

9. If there is too much smoke or fire in the hall, slam the door shut.

10. Stay out of damaged buildings.

11. Check that all wiring and utilities are safe.

A state of the art fire fighting system is proposed for the project to

prevent and control fire outbreaks. The fire fighting system will consist of

portable fire extinguishers, hose reel, wet riser, yard hydrant, automatic

sprinkler system, and manual fire alarm system. The buildings will also be

provided with automatic fire detection and alarm system.

3.14 Environment Monitoring Plan

Environmental monitoring plan is a vital process of any management plan

of the development project. This helps in signaling the potential problems that

resulting from the proposed project and will allow for prompt implementation

of effective corrective measures. The environmental monitoring will be

required for the construction and operational phases. The main objectives of

environmental monitoring area:

Page 79: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 124

To assess the changes in environmental conditions,

To monitor the effective implementation of mitigation measures,

Warn significant deteriorations in environmental quality for further

prevention action.

The emissions from each of the diesel generator shall be monitored for exit

concentration of Sulphur dioxide, Oxides of Nitrogen and Particulate Matter on

regular intervals. The frequency of monitoring shall be decided in consultation

with the TNPCB. Sampling ports in the stacks/vents shall be provided in

accordance with CPCB guidelines.

Table 21: Environmental Monitoring Plan

S. No. Description Frequency of Sampling and

Analysis

Construction Phase

1. Ambient Air Quality Once in six month – 24 hourly

2. Stack Emissions from DG set Once in six month

3. Ambient Noise Level Once in six month

4. Soil Quality Once in six month

5. Ground Water Once in six month

Operation Phase

1. Ambient Air Quality Once in six month – 24 hourly

2. Stack Emissions from DG Set Once in six month

3. Ambient Noise Level Once in six month

4. Treated Sewage Once in a week

5. Ground Water Once in six months

Page 80: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 125

Additional Details on EMP:

High Rise Building:

The proposal involves construction of commercial buildings with a total

built up area of 88779.2 Sqm. The Area split up and space utilization details are

given in section1.3. The project consists of mall building; with Ground + 12

Floors and a Multi-Level Car Parking with Ground + 16 levels. The height of

the building is 51.88 meters. As per MOEF Notification the road width and

firefighting compliance is applicable for building height above 15 meters. NOC

from Tamil Nadu Fire and Rescue services Department & Airport Authority of

India has been obtained and enclosed as Annexure XIII. Conditions quoted in

both the NOC will be complied during construction. Further in the proposed

project, sufficient Road Width (9 m) has been provided for easy movement of

vehicles. In case of emergency, Ashok Nagar Fire station, is located within 5

km distance respectively.

Table 22: Budgetary allocation for environmental management during

Construction phase

Description Budgetary Allocation

(Rs. In Lakhs)

Capital

Expenses

Operational

Expenses

Drinking Water & Sanitation

(Temporary Toilet) Facilities

3.5 8

Storm Water Management 2.0 5.0

Solid Waste/Debris

Management

0.7 4.0

Environmental Monitoring 0 4.0

Dust Suppression Measures 3 5

Occupational Health &

Safety

5 7

Total 14.2 33

Table 23: Budgetary allocation for environmental management during

Page 81: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Conceptual Plan

M/s. Eco Tech Labs Pvt. Ltd., Chennai. Page 126

Operation phase

Description Budgetary Allocation (Rs. In Lakhs)

Capital

Expenses

Operational/

Maintenance Expenses

(Per Annum)

Sewage Treatment Plant &

Recycling System

30 5

Rain Water Harvesting

System

10 2.1

Solid Waste Management 5 2.0

Environmental Monitoring 5 1.5

Energy Conservation 10 3

Greenbelt Development 12 2.0

Total 72 15.6

*********

Page 82: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

RISK ASSESSMENT, DISASTER MANAGEMENT AND SAFETY MEASURES

A well - defined Risk Management Plan is made as follows:

STEP 1: Define the Projects/Tasks

Site Clearing

Excavation

Raft

RCC slab

Block work / plastering

External plastering

Joinery - frame fixing

Flooring

Interior works

Windows fixing

Flooring

False ceiling

Painting

Services

I.Electrical

II.Plumbing

III.Fire fighting

Equipments

i. Elevator

ii. STP /WTP

iii. Hard and landscape

STEP 2: Identify the Hazards

a) Are you using (Tick boxes)

[ ] plant/equipment

[ ] portable electrical equipment

[ x ] pressure vessels/boilers

[ x ] hazardous substances

[ ] scaffolding

[ ] ladders

[ ] lifts/hoists/cranes/dogging/rigging/load

shifting machinery

b) Does the project/task involve (Tick boxes)

[ ] using tools/equipment with

moving part(s)

[ ] using tools/equipment that

vibrate

[ ] working around electrical installations

[ ] working near traffic

[ ] working at a height (>3m)

[ ] working in isolation

Page 83: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

[ x ] working with x-rays ,or lasers

[ ] electrical wiring

[ x ] asbestos removal

[ ] welding

[ x ] hazardous waste

[ ] excavation / trenches (>1.5m)

[] working in a confined space

[ ] manual handling

[ ] repetitive or awkward movements

[ x ] lifting or moving awkward or heavy

objects

c) Is there (Tick boxes)

[ ] noise

[ ] dust/fumes/vapours/gases

[ x ] extreme temperatures

[ x ] risk of fire/explosion

[ ] slippery surfaces/trip hazards

[ x ] poor ventilation/air quality

[ x ] a poorly designed work area for the

project/task

STEP 3: Assess the Risk

Table 24: During Construction Phase:

Activities Air

Pollution

Water

Pollution

Noise

Pollution

Soil

Pollution

Occupational

Hazard

A. Material Handling:

Cement +M - - +M +M

Steel - - + - +M

Sand - - - - -

Stone - - - - +L

Wood - - - - -

Glass - - - - +H

Hardware - - - - -

Colour - +H - +H -

B. Construction Machinery

Rotary Driller +L - +H - +H

Mixers +M - +M +L +M

Excavator +L - +L - +H

Material Lift - - +L - +H

Risk Factor:

+ : Positive

- : Negative

L : Low

M : Medium

Page 84: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

H : High

For any projects/tasks that present a high or extreme risk, a Safe Work Method

Statement must be completed.

STEP 4: Control the Risk

Note how you will control the risk following the priorities listed to the right. This may

include controls like redesigning the workplace, using guards or barriers, ventilation,

using lifting equipment or personal safety equipment.

Eliminate the Hazard

Keep the Hazard and People Apart

Change the Work Methods

Use Personal Protection

Note any specific risk assessments required for high-risk hazards. Check whether any

hazards noted in step 2 require further assessment or action.

[ x ] hazardous substance risk

assessment

[] test and tag electrical equipment

[ ] confined spaces risk assessment

[ ] sound level test

a) Note Permits/Licenses/Registration required

[x ] Demolition work

[ ] Electrical wiring

[ x ] Pressure vessels

[ x ] Friable asbestos removal

[ x ] Ionizing radiation sources

[ ] registers for chemicals, Personal

protective Equipment, training,

ladders, lifting gear

b) Note certificates of competency/licenses for operators

[ ] Scaffolding

[ ] Rigging

[ ] Load shifting machinery operation

[ ] Pesticide application

[ ] Crane operation

[ ] Hoist operation

c) Note emergency systems required

[ ] first aid kit

[ ] extended first aid kit

[ ] emergency stop button

[ ] additional emergency procedures

[ ] Fire control

[ ] remote communication mechanism

[ x ] others

STEP 5: Actions Required to Control the Risk

A. During construction to reduce pollution:

Page 85: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

Manual water sprinkling during dust excavation

Using RMC to reduce air pollution

Dust cover for Trucks

New Construction Machinery

Equipment will work intermittently

Rotary drillers instead of acoustic drillers

Vehicular trips will not be at peak traffic hour

Ear Plugs to workers

No noise polluting work in night shifts

B .Safety & Hygienic Measures:

Adequate drinking water, toilet and bathing facilities

There will be free medical camps and first aid rooms for workers

Safety equipments like helmets, safety shoes etc. to personnel and visitors

Personnel protective equipments like leather gloves, goggles and ear muffs when

required

Personnel working on heights will wear safety equipments and will not work

alone

To prevent any accidents, the entire area under construction will be cordoned off

with tin sheets and safety tape is run outside this fence

Regular pest control will be done

Adequate fire fighting equipments will be provided

Page 86: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Project Summary

M/s. Eco Tech Labs Pvt. Ltd., Chennai Page 17

S.

No. Description Proposed Residential Building

Project Name :

Mall/ Hotel/ Theatre complex ‘Matrix

Mall’ by M/s. Anandram Developers Pvt

Ltd.,

1. Geographical coordinates of the Project Site Latitude: 13°02'47.03"N

Longitude: 80°12'10.08"E

2. Category 8 (a)

3. Village Name

Survey Numbers

Saligramam Village

Town survey no. 8/1 (PART), 8/2 to 8/30,

8/33, 13, 14, 15

4.

Total Plot Area 18,149.26 Sqm

Ground coverage area 7421.55 Sq.m

Roads and pavement area 3488.34 Sq.m

Green belt area 2793.27 Sq.m

OSR AREA 1820.00 Sq.m

Utilities Area (STP, SWM, Transformer

yard, DG Area) 256.00 Sq.m

5.

Total Built-up Area:

Give description ( Number of blocks with

floors)

88779.20 Sqm

Floor Total Built-up

Area (Sqm)

Main

Building

(Mall)

57140.35

MLCP 28974.79

Sub-Station 2664.06

Total 88779.20

6. Estimated Population 14994 Nos.

7.

Solid Waste Generated

Bio degradable :

Non Biodegradable:

STP Sludge :

Biodegradable waste: 6579 kg/day

Non Biodegradable waste: 1816kg/day

STP Sludge: 45 kg/day

8. Electricity load Demand

Proposed Back up DG

6140 KVA

3 nos. of D.G. Sets of 2000 KVA each &

1 no. of 1500 KVA

Page 87: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

M/s. Anandram Developers Pvt Ltd., Project Summary

M/s. Eco Tech Labs Pvt. Ltd., Chennai Page 18

9. No. of RWH pits with specifications

Recharge pits: 69 Nos.

Dimension of Recharge pit: 1.5m dia and

1.5 m depth

10.

Total Water Requirement 438 KLD

Domestic Fresh Water Requirement 149 KLD

Flushing water Requirement 165 KLD

Gardening water Requirement 10 KLD

HVAC Requirement 103 KLD

Swimming Pool water Requirement 11 KLD

11. Parking Required

Parking provided : Car

Parking provided : Two wheeler

Parking Required as per DTCP norms:

Cars: 716 Nos.

2W: 737 Nos.

Parking Provided:

Cars: 796 Nos.

2W: 1094 Nos.

12.

Green belt Area

Tree Belt Area

(Specifications Width X length in meter

Number of trees proposed to plant

Other landscaping Area

(Specifications of area)

Total number of Herbs

Total number of Sherbs

Area proposed as grass pavers if applicable

Green Belt area – 2793.27 Sqm

No. of trees proposed to be planted: 230

Nos.

13.

Solar:

Quantity of solar power generation

If stand alone street lights of numbers

If water heaters capacity of solar panels

Solar Street lights proposed: 15 Nos.

Total load consumption using solar

energy: 5219 KWHr per annum

14.

Energy conservation :

Total energy required-

Total energy saved using energy consumption

measures (%)

6140 KVA

569382.48 KWHr

Total Energy saved = 47.80%

15. Total project cost 266.39 Crores

16. Water Source

In Process of obtaining permission for

water supply & excess treated sewage

disposal from CMWSSB.

Page 88: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

tb

G_ ,nwrdb H,..,;-fU Andhra BemX:;;; N,* (}r,r,}r

(

(

(

(

*{d 3

lNFr,, ri,,oS,bd$"$oY [xY Y

IN

fulveLro roR e ti4or.riHs ot.tr-v

Flk.l'ltrili:R 1;iH:{::ftHTAltY

& co.

f::i.,.1r..r l.-a l,;.h mn L y

SGMAB/FO/CTSno16/ll

ItO$70

,il.o 5o jl ?orr. Eooo I Io I qr:

Ei elr*n *q' ror ANDHRA BANK

9- -'(

(

(

(

t?

l

I

,fi**s r 00 roo+ "

Page 89: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33
Page 90: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

NOTES :-

REFERENCE DRAWINGS

REV.DRAWING NO.

ORIGINAL SIZE:-

CAD FILE NAME:

AREA DETAILS:-

LEGEND:-

Page 91: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

cc)EoonL '--

it'.A.FLo;'6:>I

-oo-0)c

=o_=

Y@o

clF

o.9

.9a

9'=_oaaE>

, c)

i6(otr-€*.o-=--R(9

i:3c-bp>

Eco6.Q

Ca.9f.oo'.-avo=E

-ly

f!l!

EC

EbOE

(/);i

=Po

oC=f

Eot

U

HE

E

E.

. O

)O

g. -

co o c'- o

/6v-dlv*N

X;0)

o I o 6r'X'

9; t.

Hat.li

O:

"U

H6E

3-Y

Lt-a--F

eaP5F

5e-o.^ L,

(D;

Oo (, Y

o+-

- d

L n

FE

.--y.-: - - - -E

e;!g;o)o

cE

hozz=>

AO

\|Ed

:,.O

-O$'ii$F

-

o.-$o:a

om'E

'-- a

0)r_co

za

f.-NNI

s?o

- D

=

"'

_! fr

-^.=M

orb(U

E.2<^t-e:8_E

=

9..Looo

ozcE+

.=F

uv-I

E

f.- C

.)acso)

::' t .., :.,. .....' ..... :p:.g, .--!.

cI -;E

Yts

.E-aH

.;C

L I;

E P

o =

r;58O

=coo€

o z

j{IJ_JE

Oo_cFLaEG

t*-).=

-rr

bEo.EO

r'-

L :.

-o ..,6.. .

.

,,>

..E,,.,

o-O

;i

^.ic>

5c

=d

8O

97

-.: 6-c

*68@o

x=,.9.=

XyE

(uvg--aa.=

EgtsB

tuE

e+f

E2'-v

-Rn

u::g,idlanFY

;v =

.F

()-LlJ

=otIL

;o.b

o.9. Y

-FO

lrLl9coo

c6

-(uX

Fc.6O

c@=

9:!lcd9

;orr o)

XN

-cvO

o-;rN

.. ; u s-)l.L

f..- C

)A

N.,-.

...-..-C

'..: 6

- 'Y

-=o

runo-;ir\l,LO

q.FN

r;ioElr)alLo)r'-=

aYco.rz.ooA

RC

)Q

Si

f=€qs

q.Ar=

0).. S

6 E

E

z-Lt-F

7ia(oJzH€bc=Ld1.=t\

1 r^

Page 92: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

*.

\oIq)

Utrb8

mEr

aXtE

<i

atdq)L't(}La-E

(v),xaL/€

Fgo.t.-EI

*zoFuf-,1lq(nF

rl

zFJ

UzriFLI

UITF{I

orI]U

Eql

U

t-FiO

g€e5ES

E

tafle,itsH

gtr€?5F

EE

YE

iE

H

€ 2 5 5

(uat,

oo(g3(,=v)

EotrflEolo

P€q

s &

EC

lEc

6 F#

zbE;

HfE

F=

L f =

JEfifi

;tt=oEoGotroEIexooa

h!it\

- h

3'\3 F

oEi

H

'\'.€E

'Fa E

'^--:

.g!o I s

y?

:lEg

$5E

gEtr rH

-{" €..:. +

Eg(gtu

z25F

lrl .

d fiHr

-f$J

gs:

ET

E.c(J

E E

Eb

eeE

6qlll €

?HF

d?

sas

== g,trooo@'do=

pz(atlr

aL

Jg3d2 + r

8 EE

od#E2 7z^tu*.:92.8"6 E

FE

n €=-E

-fi g $,*5.{z

=a E

9 toq,(J

oBE

ilHE

qf;E

Efri

# Hgs=

sH!a:

Page 93: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

u0G

Jq$l

a60trqiqot(!F

.XF

.' 6o\oN

IE<

. =t

<itr

!'tv'6YatstT

3xtF

{X+

x63u)!i\o(\rn+

Ia)

E

U)

u)NI

+$oAD

z.hho)lr0,zN\oIoE

!(ltzthC

)Ivthar..

\oFi

z

*'N&

.wF

\wscqr?

s##s#sbi

s'Ei

si#

$

&wl

slsl

I

(IIccc)

oooLg(D

U)o

p=;ico.-

r<o<,'rt

x <

"j'E

o)o

;o=

>

oF

Vo o(o

OE

E!

oc7

(EoLoJ_ocoofL0,coO

+J!a'.

q)

&>i

Ib0+

Jao>i

H(J-r-r,ELI

rhv

ul

!.oIJJ

0.Izoutot!oul

F

Page 94: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

-_:IIiIIIII

f

c9CD

ooo(l'Ia6q)

o(gIU

=No(E

=(!Ex(U

EoIa!o(E

=!?J(I,p'bo-c

oah

toG(J

z

aFzlr"l

FzO

.F'-oa0)o

oo_0)E

coGoG'6(so_(I'oo)-.Eooc0

avao)t@ot-:aoC

)(5U:oU

'coC)

0)L=O.u)ao)

.NU)

.S(ULo

o)

;c0

coGc)oJoI0)Lom

co'r.o\cirr)bNItr$o$9oJ

'L' G

r

d06t!

0)z=)-v

o'3' Fo.._ctrqo.iq>

-a-O

\ (d

^; o

1'1;;N

:=

NX

:o'a=

qtsE

$ErT

>'=

e'FE

gd-i':6+

3-cN

3

9CY

)i,:

Co

ttll

=

F{

i:-i

l"^ d. :

; Z

osul

<r

o. "i3

J >

+(

r'\Ot]c)N=

ornZ

Ii+fr

F3

!JtllF

Eo)

o =

Eo

6:ltJ

D.'

F*

LHz

zU)

NC

O$

ro(o

Page 95: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

t

traoc)oooE.o)q)ooU'

ots.Fooxoc)-t-.-:oxq)o)q)o,

l,o)E

bn=

=.

Eg

o.: U

'(/)bO

(D.9trEoo.=

og:ct-E

c9,9

(E

6Po.9-c

o5E

_3,9E

E-o- oo",e-cdpbEP

.o=F

Aox(()Yoo--o

o)-v

.=

Jfr

| giI^

OU

,F

r(Dh

Et

: E

tsnxlt:!l

Qo

br.IlPE

=BE

o:

lB;E

E!fii=

EE

Eif€r.;e

o,t.a:5 6 €

o o

E f =

E =

Ee n €

H

:E#sE

;iE€

isEE

sHei:

iEE

gEE

ggE.G

HtsaE

s-oBE

!69otiJ=

E€;af;5ube

;;Eg;:=

*cP

EE

€E;gfr$

=5*;g;E

sEE

eE;=

EfiE

gE+

F E

a€ E : 4 E

:

; *HE

E ?; €;'g-

g o€{€EE

"rEga

rotroE;giiaE

po-1gg1 -c'-ooE

€g

o_

-og-og(U6B(E

uiE

q)

-cA

oL

69o_!(trvt:

'-3 .e^

wofi

P

ooP3

FAao.D o-3eu,

o-o

IE

ip|ocr

coo=H

5E:F

* e Y,5

i. P

EP

x.=-

o)Etrd\

o=E

=5

EE

trb 8yt8.

a P3

r=a

€-E

oroEli0)

3.qc.-coxE"

*E;gE

:oaH

SE

qEF

nF

f!:gE

E-

y (5

0 >

-c Jy

g E

H *s::

eO

i_=F

E

ffrE*f

'E

F s

+€s:iE

ft E

gts'=t

Z

.xPa

'64+

= I

ft::=efi

\JG

E =

P

:B eF

,gEe.=

F

strXP

u6 s

cEsE

:EltJoeo',4----_H

= F

H

:€ET

*?=

=

Esefr;*g

g H o

EE

=gE

tE=

E =

F

E F

EE

€2E

; i qlsE

leg:

E E

:E

F;gE

-HfiE

i E

€;€EE

eo E

g a: =

;0t=5 F

icf*E

Eg

r i E

!neF;g

oF,,.l

'- :j'c

o::eEF

'ei

E € e,?E

F€iE

E

;9 *c.jiE

P.?c

o o E

-HtH

FB

RtrO

Y^rzE

5 E E

E

egieE

2- 0

eHH

Fn

$3 E F

96'e

t- .=

':g iE

B

H: E

s Al

E3,ii5s-:O

6*{.**sF

B̂/5i

-vS"E

G=

z'e.q=G

}:Et- o

e'E;

!. tr

9.1

5r{.E3+

tx$E?s,srootr

.-r.=c!$

ZF

8H=

q\ i

QR

}r\

BF

" Fr' x

e-s 64i.Fdv.

i 4E

^>lr,

E;E

1En

a 6s9

lo'

=E

tut:!F

:Og :>

.O

SU

\gI

F

Fe;z

Page 96: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

o,;.-ooE

==

#Edvd

G

EE

-E

-+.ogc

og--e.9)=

FO

EE

l:o-=ts

eg E

8='

0.c.=E

tr3q

E;=

B g

E6e

P E

.A

E

go=

tsaE

5 A

o'=I6

3-E 5

EE

E

;HJ-

do;o=dl

-EbP

. ?e

=E

b € I =

Eee'H

3E

::luntsUd=

q .I:8

: € E

3 b =E

g E

P fr E

cE'=

-!9.c.x>

o==

E:E

'Z

- EE

'atO

-c.E(u

.E A

:=

F:E

E;63

E€B

-:=o

EP

gE

#';a:-6u'c-;tr6=

3E;F

EE

iI.0 l:;

E=

=0

E 3E

# Efi;€

t P

H-E

6F=

;d tr?bo E

FE

?=

*1

g 3g

o, )\e

h g6

iI 5tr

6 a-a

96-o)9c).=

-c.

EF

Lo.ihrnuo.aa$s6o,P

.o.'6o0)g6IlU

.,c

B€

?=orno5'aaoc)ah'6;aEE

FO

iF-

(D

AolE€o

(D!

6EE

EflE

oc.(l){i(0

EE

E,btu

il *O

EE

E-e{

e 3 i *3 eS

EE

Fofr

E

;EJZ

Y

["Etg

E€ra€E

B

bGb

;EgE

H

\$H6=

EE

='

?E;E

: "H

E;i€€ *E

gH

E;E

:fr.t€c.,

ts

HE

eE

E:=

,Efi; E

BC

Fx=

{ sE

*r"rg q::E

$#€ fr9883=

esEe+

eE :sE

sFfr 5+

g:t;{

pEH

efr; c=E

?€E

E€

EH

gE;E

ZN

=8

EE

gi gfrgilE: E

HE

fie:E

E

Er!!-E

;; nfr=E

E'le: g;tg;E

;Ftg

EE

i; E

I;-i! e rbH

eE

b8fi ;E

E€gif

$E=

=;

ss:E

gii€EE

EgE

F:E

A.P

sfi€F

:P €:;

f FH

€ ;?fiE';E

f E€E

5b-u' a IE

:.Hga

gE;€

r:€n=t E

aFsE

€ ggE.F

+E

i;t E

EF

gE; E

;'f!E

i i E 3 t

E E

E fr P

T .' r +

s E E

E uE

h=E

g o-; H

BF

E?cgB

E;

c€,H t F

etg;!E efiE

,^hiE

^"FE

;'Ei;

$3 E S

QhF

F.i;

: E g ar r

,2#,>'og*

+*.:.ofE

{-vS

rqz.aro>

,"trh-od'E

;LtrO5ra.E3+

3

.s$E?s+ta-.--'=€.+

a

E8:

O.::

6p ir\

'frX

i;res 5?*=

5 "dfx>

iail rE1f,n^<

a$9r6+

.81.

h isoAuJ

\O

'

F

Fd

z

Page 97: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

(Eo_O

)flaoEoaN-o!:q)oqEooooGoEC

9-o)c)o'd_ooo=u>I

U'

(I'oooo=o(Uo.lt(E

;aac)ooF<ic)oo(!ooE==oI

;aGooq)Loa6a(sq)o

E:

Eu,eE

ii I E

E;

EE

E;^E

€ ;F

; E

fre$*=e H

dEi

gf E:xE

F

lo .c

:E

Ef;E

EF

F E

*i:iE

E

:ER

\BE

EsE

P9 $$ E

sFs

H

€E

EE

;Bs'i gf':l5

pa :b:3 :

EE

:ItstE sg;F

s :i E

g;E

g

tr :E

Eitl €fi5;€ fi: isai

E;e

gFeE

t€ Ft:zi

EE

Fitfr

E

f;EH

EE

fiI3€ ;t;te €etAE

$ l3:H

EE

;EE

= qE

tfi[ E

g gEgE

9

oE;

=6:*tE

;f;;6-=

E

= '*

EF

E:

q)

Ei_c

B*€E

{I :E

E+

E

Eg E

tEt

E

frHp iE

€Fi$ E

E:ai

st:F

*!:E

rtF

€BgE

i=s6:E

R

e;E

i H:I$E

;EE

5E€:E

iE F

F€t i

.=sd

=F

* BItqnI*E

IEP

:F; F

E E

iiF

H

Eie $;rE

i$eEr-riE

e; c; qEgl

="

e EeE

HB

gFiF

fifiar*$€€ 5E fi53;

fr

EE

E* E

EE

F;tfi€f;frfif;E

r t:EB

EE

*tEi ggg gE

;iIf eEcgE

HiE

E €x5;E

IEg

-E

6i E

pF

SS

bE

,? 3=

.- ;

-8 =

9'\s5

eH n bH

EigE

E e*€ 5 H

g ;€'€E

o-oEoo-oo(5Looo=.ots,=oao3=ooooEdti

=K $>6

Zo)

.930:d!N

.=

.Yc)->f,6

x(uv.:(/,-o

r;6\r}rarnCT

Elo=9

o'edEE

!{G

A

Pg

z'6>,'.q

h-oe'i

3Ltrll3F

C.E

Z;2

6i$9?silcoE6r=F

3HsaiQ

Ri

$$;zJ>-.:d'l.q.a>

ro.JG3ert[ol,+p6(qI-aF:z

6a

EF

ry9$3 E

F*aA

E-'F

:5EE

;Fga

, 38i'5

i .:.&

*.:.

utJolu0-JIz-oulFutrOi[,',E

F

Page 98: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

i'Hg

EE

€S

.Eb

5=p

o#;tgE^c6s;sptasg;

L

E q€

SE

Pezd8E

.EI=

E5E

H$e€sE

E.A

Ets

F

fr E

O-A.^--=

.Y

sst ;E

E*Q

E

E:

oo'CIH

'HE

: F

: o 5

Xi*cX

Ygl.9

.; =

a iE

;6E

if; E

#=

hv=9E

'9 9

E-E

tr:trI6't

a =

qE g

g

2- I

0.s:Euq.=

)6s3 H

;;gE

a(.F'

I =c

Q;

s€f.EK

.E

=frP

re,26>

tI8;.i**of;FF

gz'a.o>

...trL-od.E

;Ltr!IZ

;<lvo

.irf,9T

S€

l6E.iF

.a

EF

Eiv'G

fraav=

tr\

'S

^ Xi

;.:

g j g

jd('Jt'id^*>

tail.sEi

Hn

i 6$

9laiE

,fF

:OI i>6!sEF

dz

Page 99: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

t\@o)o

rf)roqra)

.q(\do

oooJro $

oqoqo

o(!ctat)

oa?C

!o

oaC.l

oo

so.toc;

oc;

\-cttoo(o

@(f)

uJou(2uFuUEF

oqlFtgEUI,Elalul6lFITtul-ilrt>lctIL

ltl.,llE

l

tEt

'lE

I

II E

I+

t c

I

:l"elnlE

I

-t a

I

itF

I

EIiI

EIE

I

il '=l

Et s

I

sl El

.=tb

I

slE

I

lll,lE

l.l=

l

ou?oo,q

oqoqo

l'-qooo

1r)|r,

s

oq(t)

ou?orq

rOo-i

rDc;ro

f..--

t-roo;ao

soN

(r)J

C!

qrO

F-

ot-oN@

o(s=o

oa?oN

oo()\s

t-oqc!o

coo)ot(oro;

CO

ro;oo(o

u?(oolO

)

orOt-oq?

ou?rO

oAIr)-i

$c\lc\r

@(f)cc;

aoN

t-l'.cots

CO

c)0)

F-

(oN(f)

(o(0c;N

o)O)

|r)N

o(Ua(f)

oc!o@o

c!$tr)N

qoco

F--

(oNrr)N

C.,l

F-$

o)(f)

c.j

c{(o

ooqt-O)

C\t

qNq

ooaO

oU?

ou?ro

ooo|r)

r.c)

Ac.i

\tol(\l@(o

qsNoc{

o(9(\(f)

c)0)an

O)

slr)cO

co(f)C\l

NN(f)

0)(g

o

oc!oqo

(oCO

coc{

oIo

rf)troN

q<.

s

lOF-N|r)N

oroNvco

6lNC9

NN..ts

orOtou?

ou?rO

oorOci

oosN

N(od

cq@c\tN

o)notC

OC

Oocc)(,

vq@(o

O)

.;N

O)

d

c)(!oc?

oryocO

sc{oN

oqooo

t-(or{)

rr)

sNooN

ocr)

F-@(o

@\(o

(o\(o

oqc)

oIroq

lr)od

r{)c;

rOv@

6)o(oC

O

a\fas

o)e?@(-)

J

oco

N

oLG'

o

o(9oc!

co(oa?N

(ooq

od

(ot-t-c!qt-

@(odo

c',f..-

srO

oIou?

ou?oqo

@Gi

lr)-:oci

otr)o

rOf-..

rsa?C

\

(f)

NC!

q+oll--

6ooJ

vrr)

o(DLG

'

EI

o

oqoc.l

[email protected]

oqroF(oC

O

ooA

rof.-(f)(o

rOc!N

odroc{c.i

Eoo)Eo.9o-o-oo

cmcoE

J-c)J E

cooGc0)

.=o(I)o,c 0)

NI€lFlI

=$oo@U'

co(t)o()a'=m(l)oactc.oac)-co

q.F6ooc,ooEFo)gGoCo'cg7 lIIIl-l€toILILl3toIEli

-lu)lol=-o,

3a)

Joxo E

oNcllfr

N= N+nollN= E

FI-l=a,Cc)

ooG=a>-_oc0)

o

zoo(,oLoO:d

a)oo0)tz

FlO

J

ooOJ

L(Do(D

zoU'

0)O=o)oo(Doz.

oG!sE+ccLLc2

tlz2occ

ol(Doooo'-o;(l)r',c

.Eooq)

=(I,tL(oo)

U) 'l

I

aooG=C)

(oo'-o(D

zz

coooc)o-(U

a

ooo(so aI

o-l

ooIEo

o€o

Lo()(oo

dEG0ic

Nroctn

F-o(!E5c=(I

--ooo)-

o;)o((u).=

(fLr

EF.

ro:,EU)

o

lcl=t?lFljl!

EI

llrslNl+

ffilol(sl(goo)co0)Eo0)z

o=oa0)o-c.Eo)o3:

a

Page 100: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

o0,-FEgIutllEF

l-fIt-!IttL

c,C')

c.)o$(o@od)v,(I'

ao(Jot!GoLoo

(9o)ooo(o(l)

oEftttr(g

.9agU

'(g

= (!=x(u

Eo.;o(d

I5ooooooYo3oooz

NIdl

ou?o-oI

oqooc;

@(?,

oioe.{

(Jc)L(JoLo

oqooro

lr)oo)@

zoFoLoLLo

rosq

(oc.j

o(E

oLo,oc)Lz

(o(o\tq(9

o(I,c)oJ

srr)o

c)Lct

U)

(toC

\.1oocj

o{N

ooo

coNc;oooo

cf)c\Ioo

rrI\q.c)c.j

oooI

ou?oqo

oorioc!

|r)orf)o

(of.-r@

f.-o)|f,r--

|r)F

-

oqo6oo

vro

ooLo

o(f)oC

-,1o@

NNo

oooooiv

oooo

osF

.oi

ooc., i 1.,.

r l-'

olt?N

ou?oq?

o6looci

oAroct

$C!

lONF

.-|f)co

c{vN

(ooioqct

Nrot-]..-

oN@

Ect

a

o(oN

o@oNv

(orr)N

oo

@@oiF-

o)ci

rrjF

-r(,@

oo(r)

(or-N

|r)\

lo\o

oc(o

oqort?

-oN

o|r)

oN

oc\tF

-

N

@F-

coo).+Eo-9

N|r)Ni-

o!(o

c)(E

a(f)

o.lo€

roo{ol

oo(o|f)

s@

o,u?v(oo(o

o(f,

so.lo)

@c.i

6o.,i

olOtoq

o(|on

tr)o|f);

(oolscf)

'd

o?NC.l

(oo)qC

O(f)

:ooJ

ro@

(o@

oc{oo

o|!o

oCO

No

vd)

c{c!

@|r)O

)s

st-o)

Na?o,|r)

s(9tcioc"j

o)o)r--

r{)o)|f)

loo?lo

oq(v)

ou?orq

N|r)

roo@

slN@

q(oot\t'-

NooJ

@@[email protected]

(f)F.

o)

qcO

oNo@

r)N

(r)(o

(f,

cO(oN

o)(o

c{\N(oO

)(o

o(f)

(oo)

s$qo,

orooI-

ou?ooo

(f)

(ON

la)ro

O)

o)(tr

o)C\,I

6\irN

NNctNo

oovrri

oooo

g(!a

or?c!

[email protected]

oro(o

ooo

@r()ci(o

(oc{qcf)

a?O)

F-

c.jN

ocCD

EohFo.cc)o

Eoo)Fo_c=

C-Jo)cc)J

0.)Eoo6c)

;oq)o)

NE=vooU)

mooC)a.Eco(I)ac'6(Do

c.o(uC)

ooco)o.ctoG)

Ec)E0)60)o3c=oo

Eoao=bJo-0)x

o3Nr)tl

?tr

d)(\3Nf6otlN= tr

c=aoEoof(u

=aoo

0)-(DEz

EF=aE0)E-o(D

o

zc)-oU'

oco)=0)o(l)(Jz

tlzz(I)

(uo)

o)(I'po-o'=6C

J

;q)c

.90)c)C)

:ou-U)

zU'

o(U

=o(oGoo)c.EG'

(Dm

dz

z

o)c.Y(l)

a

oaLodoa

U)

aoooG

'

oo

oodo

Lo

NEFoo$o).2a€)ooo=oN.c6c)T

D

NEooGq,oo(D=--O(o()'=oc)co

NEr(U

D= o(l)fo=$(Uo,C'=ooco

NErr-oo(I'oc'-(U0)co(D

=f

NEFoaU'

0)o-o)EJ-oootaEoo

c.)(I'ao

EFcr,(D(uaooC)

Go)o.v(It

Ogla

NEFoaac)

'=(6o)-o(l)E$==I

NE2\Po(u(I'o.s(Uooa0)z

g\+{a*&-/

t

rt

Page 101: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

+

UUJ(-PuoF

ueIEttIJoouEI

IIIIFL

ago-

=@I

.cU'

(!(-)

oLoc0o'ioo-fitoo)-'-Goc0tsocooOfito

o)No)I

(\IoU)

;L(Eo-o)$Io

oo(oooEtra!

.9(!U'(E

-6ExL(!Eot(DLlgJoan^- (.),Y

O)

LJO;;o3o(l)E(uz.

JJooul uJ

==

oo660oro

EE

9FI'tF

*q-(oororoo|r)d.q-Joci

c)cF

= IC)

=

60)

E=/\-c6oc)-xooo_P

9oo-o)

a)trltr-dt

o-6oL

L

E;n

o(l)=!

E

=-=

EC

axg(o(l);bH

o-=g

4-;*(Ui(!

b-n'=bb:!

-FF

Jco=89P

,3353

o(!0)L0)

J

zl-slz.:<at(odroc)

zlzqlr)1r)(.J

RN

ErrS

rrS.rb

-ru)r

E

.Ieadg-t

X=

s? oP

;frfi .P

=pqx=

;o

irr*:oosfr E

U.F

He"tL

E=

:*EF

aEE

i(;6U^E

;OC

D6

-XiliE

;EtrE

;-,€P'iE

EE

,At

XE

ee;EE

J"(/JLU:<

rou-u- lO

F-

-qo

lr)oN

o)*,^N

-lx

,5"=€ {B

-+,I-

Ex

Rq

*ulA

O)-r

oFoix

o?x(9r$@

otsf

CD

EzJlr)@a)(o

o@dOJ

NzvN'lr)

ll N

- F

-I

-tr c"jeil*E

=I

+(O

O|r)\t

;c.c\c;(o(O

OC

r)Xo@

-S'^

tr:xdN

ro(c;N

rlI(e

Errurrtlb

L>i

H

x 9_(g

Y

.^ --

o, :

sg:

oEX

-c*eq

; o

lrrOO

,ao

92 =qE

:5E

E=

Fb.

9'n+X

.e3

6sE€H

PoE

6=oIa

6ofo.Y(l)!9s

;i-!.3EE

E€

Y9.tsfihX

(J-

P=

6y-=.=

J vae.

<tLlL

NEz@^lLr'@

$€6zEx

€ao'6e6oo

(oro@

(f,

c!or.@@

st,-

sso)N

ooo

zoo@

NEz:aroros.9H=

oE

Eo!t

olt)E=U'

ooo)oE-oU'

c)o)0)EU)

c)P0)E-oo

og,(l)EU'

og,oE-o=o

oE9=

26o

oooo(J

(U

()([f\

o(5a

zS

lNl*l-lS

l3o

--3*c ,^

ocL=r6.Q

EU

6qoE

E.coF

Et-

Es

Erl)N

Eo

co

Eo

FF

-Ltrlt_[ltl!)-!>yxod:

q e;

x E

ieq

;oirroo)n"

q)9N

9? .JF

Ph

=dt

E;.F

E3

EF

sf frEqE

-=oit

::EE

€9856

b,E=

8.:Ee

.r589P.3

J"AE

<tLtr

tr tr

=c.l

-(oE

3q85o€-oE

;l.--\

Nc.j

cl3rEg'a#raoooellEF

o\

Eooq$

Eoooi

Eu?o)

Eooc'i

Eoq(f)

oo,(EJ

Fo6l

ooof--

orO(oN

orOcdN

oq(')

EoL

orf)N

oqF

-.

oq(oc!

orocttC

.l

Page 102: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

z.aoq(!(\<\

co

zzzzzzztzlzlzlzLY

Y(f)oN

o@(oco

oo(oco@cov

c.i ci d

cci c"i +

oi(\@

roo)N@

o(\coN

N@

EE

zz@sfO

r(Oq.q

qSci

|r)o,Oo)

oc)o

EZo

.:to^

cY)

5xc; crr

OX

Nd

tl

NcD

@l

klbl-lol;lflc)

.9.aO6Fo'-TL

-Ncq$tf)

(I)(D0)()c)

(s(u(EG

OE

ee€Eild)O

OO

o)

8;EE

€EE

oroooo#P

P33E

;(5GG

N(o

ooaaoa\

'6'6 '6'a

'a

PcE

99e'H

aoto66gE

EE

SE

EE

EE

PB

TII

I'L LL

[L LL

Lo

z<)

tloo$0)

-i*z-6;Etla

tlsttttttll

ro(l)^n-nr(D

:

==

x::'o>

e

Yr#-

=$oo)

xi;68(Oci d

g) cc A

!*too::

ii H H

3;O

.ltrE4:tj:Z

P-e)R

>>

-=

9=

9;EE

q,dlt>

-$ox.od!coo--T

cO>

cooo:-'rof=

ooggE

P,P

'EB

-*E

EE

EF

HU

HE

bg9co-i-{v.cAbc?

.,(DO

rr-nllll.,xr=

'_Lrld ^4.d2

a q

aaooLE)

ILl(,t-tztIul

zl<@no)o@

z-v,qO

)o@

I(o0)(gc)oc)

.2oo)ooLL

N$i

,rzlz3

oro()

*-!'- ll

x!o

bo -tr

ll $

-N*-

>Q

>

,ooqE

ritrs"l<co

@,^--X

$x+

UH

6ct N

orooooPx

o)., 9x;;

coo::

"p&;

nlox\Y

rf)o()@

RE

rn,ttttrrllSrr

a X

seoeBc.i

3 *i"

G'

..r e$Q

eshs=

gtsLA

gL

=rr

:.8 [

3li dF

PE

,-c

EE

i.EB

fiEF

=:g

s EE

.EfiF

9;ss. s E

E E

?E !:

E E

;nE,E

EE

^'€EesE

q 6E

eEE

b;IE

illrol-lgoeo)(!.9o(DLEF'Tt-L

*=4

6s\*s

Zij

-FF

s55I

..i c; .ri ooiF

-xI

or t'-

ox\o(o

llo(oooo(Uao)co.ori

llo'u)o-coO0)(o

Nz,;

Ett^tt

exYt^

c{-x

9q5ll^oEE

9

=R

L E

3 6F

E^9a6C

.:-eE;

b;ib.s5q 6;p

t1

$Lg()tsooo(5.9,ooGF.9Lll-

zu)rO,,

ttrflp*

;EE

qE

!xH

-oro$iqsol

o^950E

*qN

q

oxt-o

il0)o(Dooo-ooI=.9l!

tlE'ao-Eo0)(t)

Ezll@ri@

trll ojll

9xc;x

EE

-llaAE

E

9

=.R

b- Ic->

b at'$oE

Gq

+c

? 9l;rtsiX

9or

o#:j

o6il.

Page 103: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

t\t\\

I\\''.

i

II

z,:aol-froco

Io-oItto3+o,oo.9oo(EoII.EgCL

oFctG'

o.(Eogoo

zveNool

oooO(,

8dLU)E

St=

B

;q? rl

-Rs

pi e

<q,

+.9

_eE'aEo=.aEooo-o.

aEoov€9r

b,=ha*sn

EE

Er

gb+

igbr.-E

o

^E3E

F

E h'3 t

x3 F

=E

s-

;F

E F

oqocl (E

a

e€ P

tH

>e

=cL@

=('cl

o>.c

ztrF

.-Pcc.v

.v.

-(\oqqo, (0@

tl,6

!toBo

GX

-cL I

E=

I ^>o-oorx.!rE

U5-C

)<u

'u00>

=-

b8'g!br.9 b:E

'6-o

E8;

ztzoC;

r()o)<

irI@qsrI

04,qNF

-olr)

tl

tlPO

^Xl

E$e

Hd '

tro-€b14

rr

ocrE'=

';(D**o_*bflo-a-co)E

E'E

g5E9e=

(U()E(1).=

utl

llu?(oxoc!o.9oexGoLo(Dao-c!tlo'd.

c,CL

0E.9a)=={)U'oooEo)

o

N

co-zzE

.!ZIZ

(\I C

D

CO

Or(O

@s

(0(0t+IN(0c;Io@tl

Page 104: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

U)nu0.J2I0uou

E'oo)

=,

'jjG=(Eoo(DooItctEc)oooogIGo

ztf)f.-ol(a

ctcoooGo(!€e---1F

x-'-ooooooerolr)u"

(\loroIEj:-rr'(r)V=o-cIt!o.U

=

ro@cct

X.roo;(,(E

b'6;otro.'aoxeE

":'E

cr-LfEottso€0,P(g=

o^5E

c06 E

rEoE

Oo-O

.EEc,

o

o.9o:r 6ril

Eo)

ooFo

-YO

9G'

-L3q)E(I'z

Y-,=

E6

E5E

=

A=

EE

fr ;E

g,X

bpE

EoE

EF

EH

#b 9 b 0-gc:l:-0o

8.8 = H

E

oq,Yo

EfF,E

6zE5

9>h

J=oobboo

ro@oro@@

@Nd

,98--

ttE

FoE

Eq)ooEa

oq)Ea

Ec)oc.)

Eo

zo-9'6=

(/)

caco

eEoou, !tP

'6E

8trg

EoU?

EE

|tr)o(o

-ooLooJ

0oE-oo

oc"j

oros-

EftEFo

|r)

rf)\O+qxr.r)t*A+q

N

tr:!scoxcolf)

cf)

-tOXNI tl

tl

o_

ooc"j

u?L0)oJ

EE

zzlz .!a

lr)-@

o)doi

Eo6E-o u)I

t--O

? (\l

:'3(/,+c.^8ilxro@

E

oc;

ro

uq+N

F

-Z-tzX6-E,

cf)

u?qXqXNtl

ONzzo|:@

(oN

odtr,^-o c{A

a^i

.>=

'6+fiu:/<

F

\U

oX(oN

qso;N0)tu) Eq@

v

ilrloO-

o-<

:.?Fo(\lLo@,.rFF;c)0)IIo)o6IoF

oooo(oo

oooozg,ooooc)(E

ooo.Eo(!o

Page 105: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

NEzs\cf)

tof.-F-Xlr)\N+OxXo

EE

zzro o)dN

@

Ec)o) .^

;q(/) \r+.

i u',

(,-+(l)XO

LocCJ

Eoi

il ll

o-

f--cci

EE

zzPP

U>

r)"1 N

O

c? c.j

-s^N-z

E

R.q

Y'

co (oorLc)C

(o^^-^vfc!i/(/),ri-

m^

)"' a

!Jv'=c:{xoq{^oo=X

;cO

nc',1 5

eO-

Crv

\il

ll

o-<

rOF--

c;T

EE

x>

>c

i<Y

F-

@F

-droNoo 'ri I

9Xq:

gaoo)Y

'+(D

x@E

o6lo)v(ro->

.ll lr

ll

="da+

5opo'Y

X

Eco

ooL

z.vo,o?|..-C

\j

cct

X.roO

rgoJ_h'6;o';oxeE

{:'=

oo-o50,aE

=-o+o

06 0-

oEO

- q)Loo

N----Z

-P

FF

V-

ooooootr)O

OO

OK

)sO

O-O

r--N

N

o69qc!oa)/

(v,E

q) o

coo

o ! '=

Fo

E I

=38

;=

i-A

O:

-ooPi;

EF

n'"6rcY

'mq)

>

F.E

.E':

E*

53539v^E

^^!nrE

-E;i0)

v*':-*x(/,-u!-=

-gO2

=

-6=,.

*+

-'p !l

o89=

BE

.:G'

6)

oE(!LEt

(!o(E

ExL=oF(!J

s€iz-l<ll

;'-=ooE

6oo

(o(o@Lr);

(oNorr)(o

stt..

$$N

,98=

6E

Eo!t

c)(Il=(It

!LoE=

0)0)EfU)

q)L0)--of

c)o)oE=a

c)hL0)E=a

.lJEf

zNN

|-..N

rO

o_go=(/,

FGC)

c(I'(E

od-

C(tra

o?od)O

F9'6;o.=

otrt

Eq

EO\

E$

EE$

Ez

Ez

oc)

ooJ

Eo

o-0)=do

oNCO

of--

oN

o()N

q

a)$

FoL

roN

@F

-@N

odC\t

Eoo=.EL([=EI(!Lo0,

o0)o0)Eq)Q

)aooGJoGo

ffi/f-/t

!.J)(si\

tr:l\gfP

*r!fi9Ira i

t4!hPt5;ii-"tE

uirrEil'ITtttILr.g

(D>'(E

J

Page 106: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

\

i

l

I

AN

Nl{)O;|f)(oIt-o

\fcr)

|r)No

+tL

NN

NO)

os

(\l\sN

a!o

ovs1..-

cf)\NN

F-NN

(ocr)

ztl|r)

$@

(oK)

lirf--

CO

ooroN

Nz.:<oo-

f.-c',1

rocr)

@co\r

NNo)o)

-|.-

\ro

rf)s

ozq)GJ

Nco

s

Nr{)(!o-tr)N-o)q,oU

t

fitoF

o)cloo(Eo

oooo)ozLoc,oo(It

ooo(Jt!o

'E'E

z. z.Y

Joo tf)

o$(or''- [

+

o)PO

)NxEa

x9+

oP

,Lo o

EE

=

RtY-oN=

@o

|4q--ro

X

tt!'N

o

9c.ibxxO

o =

n=f.-o-o oo

Eqvolr)(oNOqt-

C)

cr)vsN

cf)r.-^iN

t--

NN

(oco

dzt4(L

t-qlf)cr)s

o)@N6

N\o)o,

Nztlo

Lr)f'-

oof'-F*

roNrr)t-@

zJzo

rOF.

oLr)|r)f.-

rf)f.-

o(!J

oO

(Dac)cir-

oO$O

zo

NNF

-

o(!LL

NoooLL

COOoLolJ_

vLc)

;lJ-

Page 107: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

8L'91lA

Scqseld uoN

60'8W

'LEz8'e9

69'000'0

pues ^llrs00'6

09'v

9t'8 tC

S0'02

0'6t0'6e

e9'e79L'09

t9'900'0

00'0pues /ie^elC

09'700't

00'92vL'91

cu ot

0'8 !0'Le

60'0/9Z

'ZZ

vvz00'0

00'0Ie13 Ipueg

00'€0v'l

zHs

LO'LI

tc0'vl

0'6 L0'te

e6'8969'6 t

t8'e L

eVt

vt'l[e13,{pueg

0r'6209'LZ

,L'rztc

0'020'8 t

0'8tzz'9L

,0'tzI l'9

00'000'0

[a13 Ipueg09'LZ

09'92

Lt'6'H

C0'8t

0'020'89

z8'8600'0

I L.t000

00'0A

e13 Agl1g

09'9z08'0 t

9t'zeH

C0'tt

o'rzU

9Yt8'vL

t;LO

L LI.8L't

t6'0,(etC

,ipueS08'0 t

09'6

w'8,

INS

c4seld uoNLLY

tv'v,L'' LL

60'z00'0

pues ^l|!s09.6

09'L

tt'vLts

cqseld uoN2,8'Ll

,u t,uvL'6'

t9'000'0

pues fltts09'/

09't

96'Llcs

0'zz0'6 t

0lveg'6t

LZ'9V

,v900'0

00'0pues,ia^el3

09't0z't

89'6 ttc

0'020'8

t,udc

60'zLe9'lz

00'000'0

,{el3Ipueg0z'r

0?'ltH

8

qJEuau

.Tl

o-O!<

o-€

q

%ilaluoceJnlslolN

lEJnlE

N

c)oa,o-#6o=

i.o

td1d

1-lsau!J

ulul9/0'0

tuulgzi'0

tuur

00'z

tutu

9L'i11og 1o edltl

oIr.uoJl

oNoloHorog

sl!ur!'l Fraqragy

% (o^ars S

Iu! paulelag alcluea) s;sfe;euy a4S

ulere(u) qldeo

'S60 009 - leuuoqC

'ureuer6l1eg le .,lle4 xl.rleu1 aql ul eore U

!'l lo uollcnrlsuog : pefo.t6 Jo eueN

qlnsag 1sa1 ftoleroqe'l lo alqPl

Page 108: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

'a

-iIII

t,L'v,-14

OL

0'020'Lz

Ub Z

Otr',

t60000

00'0[eto ItttS

00'6200'Lz

8e't9H

C0 9r,

0'tz0/9

8Z'66

zL000'0

00000'0

IetC IlttS

00 Lz00'9 t

99',92IN

Sc[seld uoN

zv 0t89'69

00'0000

000pues IiltS

00'9 t09't t

zL'9t,t-tJ

0'?eO

'ZZ

0'9988'.L6

0L tzol

00'0000

,iet3,ilttS09'e t

09'0 t

r0 8tlc

0'60'02

ia7,8't9

89'ZZ

UJ Y

l,00'0

00'0ttetC

[pueS09'0 t

00'6

sIrElxsu

-Tl

-o-oi<

o-{

g

%lualuocaJnls!ol^l

IEJnleN

c)a*ao

td-ld

1-'lsoull

LUtU

9/0'0tutu

gZV

'Otur,u

00'zturu

9L'V11og 1o adA

loI

r.uouoN

oloHorog

s1!urllOraqragy

yo (ela1g g1

u! paulElag elcrye6) s;sfeleuy azls ulE

J9(u) qrdeO

Page 109: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

wg'L- 9't qldao lH

s-----ru 8'01 - 9'6 qrdeo tH

E - . -

ur 9't - z't qldso tHs ....'.'..

r.uru u! azls ol3luEd

t'0

ru 9'6 - 9'/ qldao lHs' - -

u.r Z'C

- t'l qldao LHE

-T

0'0

UOI

ozn90n0sUJ

OL

08

-Ito-oo-r1

o€o

0600r

'€60 009 - leuuaqf,'ueue;311e9le ,,lle[N

xlJleru aql,, u! eaJe U!] Jo uolpnllsuoJ

3rd03d rvclNH

9flo3s) rHJ-

I Hg A

AU

Nf, S

ISA

'IVN

V gZ

IS N

IVU

T

Page 110: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

w 9'/,Z

- 9'92 qldsq lHg -

ruru ul azls alc!ilPd

T.0

ru 9'92 - 8'01 qldao tHs- -

T0'0

r00 00OT

oz0t0n0s09080600r'€60 009 - leuuorll 'ueuer81;e5 le ,,llel1l xplenj aql,, ul ealp lJll lo uolpnJlsuo3

3f dogd fvslNH

tftof I

3Hl 1'oo-no€o+

I Hg f,A

UN

] SIS

AT

VN

V A

ZIS

NIV

U'

Page 111: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

w6z- Lz qldao zH

s . .-ur9'0!-6qldaqzH

s---w

Lz- 9, qtdeo zHg-. -

ru 9t - g'cl t$doo zHs- -

ru 6 - 9'? qldeo zHg -----

ur 9't - e qldaq zHs .'.......

rutu u! ozls alcluBd

T'0

ur g'cl - 9'01, rDdoo zH

s - . - '\

w t, - V

', tlldao ZH

g -

'r..

r000O

I

0zUE

ovU:

09OL

0806007

'oooof!oE{L(05

/'/

--4

-r''2<

=

-:'1''

//.;

.la'

/.

i,

!/t

'€60 009 - leuuaql 'ueure;81;e5 le ,,llelN xulen aql,, u! eare U

ll lo uolpnrtsuo]

Z H

g AA

UN

S S

ISA

'IVN

V IIZ

IS N

IVU

C

Page 112: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

o\tr)

.C; o

3Ee

sfrfie);

@,q

a FE

Ni(o9

Page 113: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

\.

6U=

c !q(I'E

6;AA

_fuo(D?iO(5s

0

ooo@

EoTo)NooGc-doo-c)

cn

UJU{IzoUFiloIF sJ)so

ricue;srsuoc

7 r(lrsuapaA

rlelau

Efts

66EB

;F@

lt(5I

oILCJ

aoFCoEoc(Do-o$

o= ooEfz

zt\

(o(\l

rt)F

F^6-N(')

(o(o

@N

s(o

(oE

_b*oC

9N

N(o

c)o

ou?Nol+N

|r)(oN

olr);N

onN

relel Josssulsrql

'-6aoo

G1loU)

-v.

co

'ti cr

AF>ou>-

o';d)>1n

o_: e(l)vooE

oqc{

rONN\i

Page 114: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

(9o)ooo@I(6oo(E(g

.9(gat,(5:=(!ExL(E

=oFIEo(E

hJooPao

o>aco

(Uo<J)

c=(D

qc!

EO

3Ee

BsF

s>

;(ou?sr 6 E

NY

^oP

cotr

Page 115: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

qoU()

'Ec

!r2 (gC

6o.;gl ii(D

O

(UE

oc)ao)6'o-

oiioi.*-+

'*T

@l

lltltltltltltltlEl I

ot I

3l I

ilt I

3t I

cl I

Ft

II(t)t

I

*l I

Ltlot

I

'llIt_l)o| /g

I (EH

I iB4

I l#E

I ips

I I'U

I lrl

I tt'

tt:ttEttL| 1'6

I;1,

1.+

rat

t--,{;

fcuelstsuoc/ A

lrsuapoA

Delau

E=ts

35tsa

EU)

.c)

GIa.o)

U'

o)Fcooc(D(L$a

U'

= _9o(D-oEz

z(o

6)$6l

ooh5s

(o

N(.J

3

_6*totO

rC

f)(o

-c(Doo(ae{

oLr)N

F-

No)

reriel 1ossau13rqI

o$i

Eot

+r'O.6.H

q)

a-8=f11

=ooOe

OF

=(6

'E(,

ooc)oE-qc

gEd

l.=No)N

Page 116: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

{tiII!,,t

Iqtttill"tlrt

elBcs ol loN'e60 009 - lP

uuerlc 'ureuel6l;e3lp,,lleht xltlE

lu aql., u! paJE u!-t Jo uollcntlsuoc

: lcalold Jo erueN

\\

NO

IJYJO

T IIT

OH

!TU

Og

3rdoJd avslNB

JeJ'9ao :H

t

Page 117: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33
Page 118: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

CA

P: 2,65,000 Litres

RA

W W

ATE

RU

.G.S

UM

PC

AP

: 4,00,000 Litres

FILTER

ED

WA

TER

U.G

.SU

MP

CA

P: 5,00,000 Litres

FIRE

RE

SE

RV

EU

.G.S

UM

P

FLOO

R LVL

GR

OU

ND

FLOO

R LVL

BAS

EMEN

T

SO

FTEN

ER

FILTER

SA

ND

PR

ES

SU

RE

CH

LOR

INE

DO

ZER

SA

LT RE

GE

NE

RA

TION

TAN

K

CA

RB

ON

FILTER

AC

TIVA

TED

RA

W W

ATE

R P

UM

PS

HO

T WA

TER

GE

NE

RA

TOR

HO

T WA

TER

GE

NE

RA

TOR

-2(H

OR

IZON

TAL TY

PE

)1,00,000 K

.Cal/H

r

MA

KE

-UP

WA

TER

PU

MP

S

HO

T WA

TER

GE

NE

RA

TOR

1,00,000 K.

CA

L/H

NO

-21,00,000 K

.C

AL/H

NO

-1

PR

ES

SU

RIS

ED

DA

Y O

ILTA

NK

500 LD

AY

OIL

TAN

K 500 L

FOR

HW

BO

ILER

MA

KE

-UP

TAN

KS

OFT W

ATE

R

HO

RIZO

NTA

L TYP

E H

OT

WA

TER

MIX

ING

TAN

K

VE

RTIC

AL TY

PE

HY

DR

OP

NE

UM

ATIC

PR

ES

SU

RE

PU

MP

(2 WO

RK

ING

+ 1 STA

ND

-BY

)P

RE

SS

UR

E V

ES

SE

L2 N

OS

HY

DR

OP

NE

UM

ATIC

BA

LL FLOA

T VA

LVE

BA

RR

EL

TAN

K

OIL

HO

T WA

TER

GE

NE

RA

TOR

-1(H

OR

IZON

TAL TY

PE

)1,00,000 K

.Cal/H

r

OVE

RH

EAD

TAN

KFILTE

RE

D W

ATER

R.O

WA

TERO

VE

RH

EADFIR

E RE

SER

VEO

VER

HEA

D TA

NK

TANK

RO

PLA

NT

HIG

H P

RE

SS

UR

E P

UM

PS

FLOO

R LVL

FOU

RTH

DW

S

FWS

HW

SH

WR

FWS

FWS

BO

RE

WELL

FLOO

R LVL

FIRST

FLOO

R LVL

SEC

ON

D

FLOO

R LVL

THIR

D

(MO

NO

BLO

CK

PU

MP

)(I W

OR

KIN

G+1 S

TAN

D-B

Y)

HO

T WA

TER

RE

TUR

N/

CIR

CU

LATIO

N P

UM

PS

LEG

END

NO

TES :

TO G

UES

T RO

OM

TOILE

TS

(HN

S S

YSTEM)

SY

STEM

)

TRE

ATED W

ATERO

VER

HEA

D TA

NK

FLOO

R LVL

FIFTH

FLOO

R LVL

SIX

TH

FLOO

R LVL

SEV

ENTH

FLOO

R LVL

EIG

HTH

FLOO

R LVL

NIN

ETH

FLOO

R LVL

TENTH

FLOO

R LVL

TERR

ACE

FLOO

R LVL

GR

OU

ND

CA

P: 1,40,000 Litres

TRE

ATE

D W

ATE

RU

.G.S

UM

P

(MO

NO

BLO

CK

PU

MP

)(I W

OR

KIN

G+1 S

TAN

D-B

Y)

TRE

ATE

D W

ATE

R TO

OV

ER

HE

AD

TAN

KV

ER

TICA

L TYP

E H

YD

RO

PN

EU

MA

TICP

RE

SS

UR

E P

UM

P(2 W

OR

KIN

G + 1 S

TAN

D-B

Y)

PR

ES

SU

RE

VE

SS

EL

2 NO

S H

YD

RO

PN

EU

MA

TIC

LOW

ER

FILTER

TO TAP

BY

-PA

SS

CAR

TRID

GE

CAN

DLE

U.V

.FILTER

HO

USE

KEE

PING

TAP

PAN

TRY

DW

S

VER

TICA

L TYPE

HYD

RO

PNEU

MATIC

PR

ESS

UR

E PUM

P(2 W

OR

KIN

G + 1 STAN

D-BY)

PR

ESS

UR

E VESS

EL2 N

OS

HYD

RO

PNEU

MATIC

FWSLAD

IES

TOILET

TOILET

GEN

TS

RESTA

UR

ANT

TO B

AR /

TO K

ITCH

ENFO

R D

RIN

KING

TO K

ITCH

ENFO

R C

OO

KING

TO IC

E CU

BEM

ACH

INER

YTO

KITCH

EN

FOR

DISH

WAS

H , U

TILITY , ETC.

FIRE FIG

HTIN

G PU

MPS

HYD

RO

PNEU

MA

TIC SY

STEM FO

RD

OM

ESTIC

WA

TER

SUPP

LY FO

RH

OTE

L FLOO

RS

WATER

TRE

ATME

NT PLAN

TH

YDR

OPN

EUM

ATIC

SYSTEM

FOR

DO

MES

TIC W

ATE

R SU

PPLY

FOR

SH

OP FLO

OR

S

HYD

RO

PNEU

MA

TIC SY

STEM FO

RFLU

SHIN

G W

ATE

R SU

PPLY

FOR

SH

OP FLO

OR

S

HO

T WATER

SYSTEM

MEZZA

NIN

EFO

UR

TH

FLOO

R LVL

LADIE

STO

ILETTO

ILETG

ENTS

DW

SFW

SD

WS

FWS

LADIE

STO

ILETTO

ILETG

ENTS

LADIE

STO

ILETTO

ILETG

ENTS

DW

SH

WS

HW

R

DW

SH

WS

HW

R

(GR

AVITY

(HN

S S

YSTEM)

TO G

UES

T RO

OM

TOILE

TS

(HN

S S

YSTEM)

SY

STEM

)(G

RA

VITY

(HN

S S

YSTEM)

TO G

UES

T RO

OM

TOILE

TS

(HN

S S

YSTEM)

SY

STEM

)(G

RA

VITY

(HN

S S

YSTEM)

TO G

UES

T RO

OM

TOILE

TS

(HN

S S

YSTEM)

SY

STEM

)(G

RA

VITY

(HN

S S

YSTEM)

FILTER

TO TAP

BY

-PA

SS

CAR

TRID

GE

CAN

DLE

U.V

.FILTER

HO

USE

KEE

PING

FILTER

TO TAP

BY

-PA

SS

CAR

TRID

GE

CAN

DLE

U.V

.FILTER

HO

USE

KEE

PING

FILTER

TO TAP

BY

-PA

SS

CAR

TRID

GE

CAN

DLE

U.V

.FILTER

HO

USE

KEE

PING

FILTER

TO TAP

BY

-PA

SS

CAR

TRID

GE

CAN

DLE

U.V

.FILTER

HO

USE

KEE

PING

FILTER

TO TAP

BY

-PA

SS

CAR

TRID

GE

CAN

DLE

U.V

.FILTER

HO

USE

KEE

PING

TAP

PAN

TRY

TAP

PAN

TRY

TAP

PAN

TRY

TAP

PAN

TRY

TAP

PAN

TRY

PR

ISM

CO

NS

ULTAN

CY

GEN

ER

AL S

CH

EM

ATIC

0

PLU

MB

ING

LAYO

UT

CH

ER

ALATH

AN

AS

SO

CIA

TES

-------------

PC/C

HE/P

L-0

1

WO

RKIN

G D

RAW

ING

PR

IVATE L

IMIT

ED

AN

AN

DR

AM

DEVELO

PER

S

MALL A

T S

ALIG

RAM

AM

CH

EN

NAI.

PR

OPO

SED

MATR

IX

DIA

GR

AM

FO

R W

ATER

SU

PPLY S

YS

TEM

Page 119: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

PR

OP

OS

ED

HY

PE

R M

ALL /FO

OD

CO

UR

T / MU

LTIPLEX /H

OTE

L / RE

STA

UR

AN

TS / SHO

PS/ C

OM

ME

RC

IAL U

NITS

740741

742743

744745

746747

748749

750751

752753

754755

756757

758759

760761

762763

764765

766767

768769

770771

772

794

795

796

797

798

799

800

801

802

803

804

805

806

807

808

809

810

811

812

813

814

815

816

817

818

819

820

821

822

823

824

825826

827828

829830

831

840851

852853

854855

856857

858859

860861

862

863864

865866

867868

869870

871872

873874

875876

877878

879880

881882

883884

885886

887888

889

SEW

AGE TR

EATEM

ENTP

LANT

FIR

E R

ES

ER

VE

WA

TER

U.G

.SU

MP

Physically

Challenged

Parking

U.G

.SU

MP

RA

IN W

ATE

R U

.G S

UM

P

BA

SE

ME

NT

EN

TR

Y

SU

B - S

TATIO

N

853853

853853

853

FILTER

ED

WA

TER

U.G

.SU

MP

RA

W W

ATE

R U

.G.S

UM

P

TRE

ATE

D W

ATE

R U

.G.S

UM

P

SE

WA

GE

TRE

ATE

ME

NT P

LAN

T

PU

MP

RO

OM

FOR

STP

C'

C

D'

D

RE

F. DW

G. N

O. P

C/C

HE

/PL/037

PU

MP

RO

OM

FIRE R

ESE

RV

E WA

TER

U.G

.SUM

P

PR

ISM

CO

NS

ULTAN

CY

PLU

MB

ING

LAYO

UT

WO

RKIN

G D

RA

WIN

G

PC

/CH

/PL-0

10

0

PLAN

DETAIL O

F PR

EC

AST R

CC

CO

VERFO

R S

TOR

M W

ATER D

RA

IN

AA'

STO

RM

WATER

DR

AINS

ECTIO

N - AA'

GL

SEC

TION

XX'

X

PLAN

X'

RAIN

WA

TER

PER

CO

LATION

CU

MC

OLLE

CTIO

N W

ELL D

ETAILSS

CA

LE : N

.T.S

PR

OPO

SED

MA

TR

IX M

ALL A

TS

ALIG

RA

MAM

CH

ER

ALATH

AN

AS

SO

CIA

TES

FILTE

R B

ED

10

FILTER

BED

FILTER

BED

CA

PA

CITY

: 1,10,000

Page 120: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

Y=';

EV

GU

Oh

ro 'o.-s

u<.

oji s

^F ;o)D

Ou..

9"-X

NiNO

O)

+co

4N;NGrn

U|.n

:- @

(!N3v6tq

3rGo)

G'

P+

ul 6oF+

)zG

<a-Fl)=o;ul^U

t:<

;lJbol-o

a-ufUa

Z:

dd,tr:<

;

c{e.l

C\

F\

.r<z

'6r\g.

trrr;+

o>\

LA<

^' a 1

--o:i"-

9.\|.

=u

UIU

d

t-,rP,.ti-dtat'L.-.othg

!'r

-8=€6dl^=

\J)

tJ',-,t

v)q.2de\&-h

=-U<

iiz1-___/)!i.Z;:.-t;!.

lht<Ltt)

P

rn$

Nct?

Nrlr-l

.++g\md\0N

tr(UL

J

ttt4(Dt-l-!.

bo

tt)V'

t-(cFLc)

tF

TiT

Ere

!9=;

=:o+

t^*

.=lE

-ciro':oD

-zFqA

G*=

!€Po-q

'FP

E:h

o. d F.E

=?E

ivl

iPF

F'l

*F.E

$'v=;€m

l,O

F.;t-rrg

a+5cdU

q€Em

'iln€E

E:O

trOX

H=

;lrll

=atrtr

Fl

e!14\tr<

l )E

Rco-G

)ot

{'- H

El

>89e--

FI

KE

ES

iollloooi:)=gIJL

CJI

j)lDG

I

i =

>

oo-E9aor.$(l)-C

EA

(6-

PR

EiE

.; (d

:F=

!xnbF

zU

:i.Eiro;'io=-P

62.:o.ri€p=E

lEE

(Jru!

-o)m

LL^

oNo':(d

=4:=

lFo:f

9Flol:

>O

\OO

EF

9orc)XZ

r-'A'otr

O-\vd

-cjct-i:L+

Cc.)b!c)

ci=99=

E

=sl 5=

,9=

z4h

zP(6t-OJ

trlr.

o(!()\CJ

Pl-U

Page 121: M/s. Anandram Developers Pvt Ltd., Form 1Aenvironmentclearance.nic.in/writereaddata/formB/MODIEC/...M/s. Anandram Developers Pvt Ltd., Form 1A M/s. Eco Tech Labs Pvt Ltd., Page 33

h

&;

rJ?.

.-t ci

4'/ F

{

trs

n;t*FE

{iiig**g$gq

IES

S{€ a5*g-

xsn.=

::€I€a €i;:

g'irg€ E

;g EE

iEg* aas

npE=

nY E

-{r*'* ivfr

Axe;aE

gEl;

?;r n

-3$sE3 gT

-;gEt E

{E_

;HE

3Ea€;iE

iI;I9*Ar€ats8 H

€Ea*F

, 1?Bg

fr

iE

H*siE

Si€*e€€€ atii

EaEs E

q 3}3*€g: E${€?ar ;t?B

79 A

l€ +

t;*r.

F ggig3 nugi*gg: $€E

3#€e 3 E H

E g p

E

11E.T€lL)E

)ustr6r5

.:aa4glat

2C81c4;t

rlo56flrqd€D,I6\n!6f*ql+tro€diO

!

@.:rs{JApeEry=Tcsod3v;it.qlo&

Fr

Hr-'lF

{F

.{F

*{$&w

4'lF

q

hI5rL'C

f4tV,

A,lrlwt4"F

ll'--lptA

.F

(A\tF

lf-'l

ItARHe4.'|

fv.F

qftlF

{

zw{

IdII{iI