    Renovation of Qatar radio TV corporationcomplex

    2012

    Monthly Progress

    Report 16(Period: 21- Dec 2011 ~ 20- Jan 2012)

    t a g e n g i n e e r i n g & c o n t r a c t i n g c o . w . l . l p o b o x 3 1 8 4 0 ,

    d o h a q a t a r

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    2/46

    Table of Contents

    1. Prelude

    2. Project Brief

    3. Scope of Work

    4. Issues & Concerns

    5. Site Instructions

    6. Claims/ Variation Orders

    7. Payment Status

    8. Project Organization

    9. Zone Distribution Diagram

    10. Work Breakdown Structure

    11. Construction Progress Summary

    12. Project Status (% Completion)

    13. Time Control

    a. Updated Baseline schedule

    b. Histograms & S-Curve

    14. Submittals Summary:

    a. Method Statements List

    b. Material Submittal List

    c. Shop Drawing Submittal List

    d. Subcontractor Lists

    15. Project Resources

    a. Project Indirect Staff

    b. Project Direct Staff

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    3/46

    c. Subcontractors

    d. Equipment & Plant

    16. Photographs

    17. HSE Monthly report

    18. QA/QC report

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    4/46

    Prelude:

    TAG was awarded the project of Renovation of Qatar Radio & Television Complex on

    3rd May 2010. The Project scope can be divided into three major parts:

    o

    Demolition of Buildings & Structures

    o Construction of New Buildings & Structures

    o Site Development Works involving renovation of existing and construction of

    new roads, pavements, parking sheds irrigation system, surface water

    drainage, external electrical works, boundary wall, soft landscaping etc.

    The complete scope of work is enclosed for reference.

    The project becomes significant and relatively more sensitive as the Contractor is

    working in a live-facility of Qatar Radio and TV station. It has to execute the

    construction work without affecting the broadcast of the Radio and Televisiontransmission and taking full care of the staff working in the premises.

    For this purpose the whole project site is divided into two (02) zones and each zone

    is further divided into sub-zones or plots to limit the effect of the construction

    activities on the broadcast and to have better control over all construction activities.

    A route plan is also prepared for the purpose to maintain the smooth flow of traffic

    within the premises. The zone distribution diagram is enclosed for reference.

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    5/46

    Project Brief:

    General:

    Project Title: Renovation of Qatar Radio TV Corporation Complex

    Employer: Qatar Media Corporation (QMC)

    Client: Public Works Authority (PWA), Ashghal

    Consultant: EHAF Consulting Engineers W.L.L

    Contractor:TAG Engineering & Contracting Co. W.L.L

    Timelines:

    Project Duration: 425 Days (14 Months)

    Maintenance Period: 400 Days

    Date of Commencement:15-June-2010 Date of Site Take-over: 17-June-2010

    Date of Completion:13-August-2011

    Extended Date of Completion: 14-February-2012

    Milestones:

    Administration Building: 245 Days

    Period: (15th June 2010 to 15th Feb 2011)

    Renovation Works/Others: 425 Days

    Period: (15th June 2010 to 13th Aug 2011)

    Contract Value: QR 121,950,000

    Qatar Riyal One hundred twenty one million nine hundred fifty

    thousand only

    Payment Released:

    Advance Payment: Received (10% of Contract Value) = QR 12,195,000

    Progress Payment: 13 Invoices are submitted

    13 Invoices are paid = QR 55,674,958.54

    01 Invoice is pending = QR 4,278,822.93

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    6/46

    Guarantee & Insurances:

    Performance Bond: (10% of Contract Value) = QR 12,195,000 = Submitted on

    23rd May 2010

    Advance Payment Bond: 10% of Contract Value) = QR 12,195,000 = Submitted

    on 23rd May 2010

    Insurances: = QR 1,000,000, Submitted on 23rd May 2010

    Retention: 10%

    Scope of Work:

    The Project consists of the construction of the followings:

    Buildings1. Administration Building2. Big Mosque3. Employees Entry Gate4. Visitors Entry Gate5. VIP Entry Gate6. Small Mosque

    7. Substation8. Store9. OB Garage10.IT Building11.Irrigation Tank No. 0112.Irrigation Tank No. 0213.Irrigation Tank No. 03

    Landscaping:1. Underground Surface Drainage2. Underground Electrical Works3. Construction of New Roads

    4. Rehabilitation of Existing Roads5. Pavements6. Parking Sheds, Pergolas, Tents7. Fountains8. Boundary Wall9. Irrigation System10.Trees & Plants11.Grass

    Scope of Work

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    7/46

    Demolition Works:1. Buildings2. Parking Sheds3. Grass4. Guard Houses5. Water & Septic Tanks

    6. Other Structures

    General Floor Areas: (Area M2)

    1. Administration Building 5172. Big Mosque 3423. Employees Entry Gate 12754. Visitors Entry Gate 12755. VIP Entry Gate 12756. Small Mosque 2727. Substation 8008. Store 412

    9. OB Garage 73810.Extension of IT Building 17611.Irrigation Tank No. 01 16412.Irrigation Tank No. 02 16413.Irrigation Tank No. 03 164

    Landscaping: Areas (M2)1. Underground Surface Drainage2. Underground Electrical Works3. Construction of New Roads 66,9904. Rehabilitation of Existing Roads 21,5005. Pavements 56,0006. Parking Sheds 19,6007. Pergolas & Tents 10,6108. Fountains 03 No.s9. Boundary Wall 2,331 LM10.Irrigation System 68,92011.Trees & Plants 1,25012.Grass 68,920

    Demolition: Number1. Workshop Building in Wooden Structure 012. Garage Building Construction of New Roads 013. Office Buildings 034. Restaurant Cabin 015. Mosque Cabin 016. Wooden Building 057. Cabins 018. Water Pool 019. Clock Tower 0110.Water Tanks 0711.Septic Tanks 05

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    8/46

    12.Guard House 03

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    9/46

    Issues & Concerns:

    Delay in Area Release:The Contractor has not the complete access to the

    Project Site. Following areas in Site Development

    works are not available to the Contractor for Works.

    SITE DEVELOPMENT

    Sr. NoDescriptio

    n

    Planned

    Start of

    Activities

    Status of

    Area

    Release

    ZONE -1

    1 Plot 1 24-Jul-2010 Not

    Available

    2 Plot 2 18-Sep-2010 Not

    Available

    3 Plot 3 14-Oct-2010 Not

    Available

    4 Plot 4 14-Oct-2010 Not

    Available

    5 Plot 5 14-Oct-2010 Not

    Available

    6 Plot 6 12-Dec-2010 Not

    Available

    7 Plot 7 07-Oct-2010 Not

    Available

    ZONE -2

    EXTERNAL

    2 Plot D 15-Jan-2011 Partially

    Available

    INTERNAL

    1 Plot 1 20-Jul-2010 Not

    Available

    2 Plot 2 06-Sep-2010 Not

    Available

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    10/46

    3 Plot 3 27-Oct-2010 Not Available

    4 Plot 4 23-Nov-2010 Not Available

    5 Plot 5 12-Jan-2011 Not Available

    Demolition Works Not Allowed:The demolition of structures under the Contractors scope of work has not

    been allowed to start till date by QMC. This has delayed the schedule of

    Works.

    Non possession of IT Building Area

    Contractor could not commence works as the area is not available toContractor.

    11 KVA Cable in Zone 2 Plot D:The construction of new road at Zone 2 Plot D could not start as the 11KVApower cable is passing under the proposed location of the road. This cable isto be relocated by Karma

    A Telecom Tower is hindering the work progress in Zone 2 Plot C. This is to berelocated to some other area.

    Security Check Posts at five (05) different areas have stopped the works intheir respective areas. These security check posts are to be demolished

    Obstruction in Construction:

    The road works in Zone 2 Plot D are held and cannot progress further as thearea is occupied by the existing buildings of QMC to be demolished.

    Substation:a. Firefighting system is revised by PWA from previously specified FM200

    to Novec 1230. This new system has new requirements which willcause rework in Substation building. The Contractor requests for a Site

    Instruction.

    Connection of Irrigation System with TSE Line:a. As per the new requirement of QMC, the irrigation system is to be

    connected to Main Treated Surface Effluent (TSE) Line. Contractorrequest for Site Instruction in order to commence the job.

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    11/46

    Site Instructions:

    Total Site Instructions issued till date = 13

    Till date ten (10) site instructions have been issued to the Contractor

    1. Site Instruction No. 01 was issued on 23rd August 2010 and it introduced

    the changes in Main Mosque and Small Mosque design

    2. Site Instruction No. 02 was issued on 2nd September 2010 which changed

    the design of Substation. The size of Sub-station was increased by three (03)

    times

    3. Site instruction No. 03 was issued on 29th November 2010 which changed

    the location of Irrigation Tank No. 02 & 03 and the Car Parking in Zone 1 Plot

    A was also changed. It also added modification in Store building was also

    4. Site Instruction No. 04 was issued on 29th November 2010, where the

    Contractor was instructed to stop the works on Administration Building

    5. Site Instruction No. 05 was issued on 13th Feb 2011 which revised the

    design of Small Mosque and Store Building

    6. Site Instruction No. 06 was issued on 13th Feb 2011, which added two new

    buildings i.e., OB-Garage and IT Building in the Contractors scope of Work

    7. Site Instruction No. 07 was issued on 14th Feb 2011 which revised the

    internal finishes of the Administration Building

    8. Site Instruction No. 08 was issued on 07th April 2011 which suggested few

    modifications in Substation

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    12/46

    9. Site Instruction No. 09 was issued on 24th April 2011 which revised the

    design of Site Development

    10.Site Instruction 10 was issued on 1st August 2011 which has revised the

    following scope of work:

    a) Revision in design of Car Parking Shade material from HDPE to PVC

    b) Reconstruction of the existing roads. i.e., demolish the existing roads,

    design and build the new roads. The original scope was to maintain the

    40mm asphalt wearing course

    c) Relocation of Porta cabin from Zone 01 Plot 01 to Zone -01 Plot -07.

    d) Construction of Guard House along with associated roads at Visitors

    Entrance Gate

    11.Site Instruction 11 was issued on 2th November 2011 which has revised the

    following scope of work:

    a) Road Crossings for Future Services requirements

    b) Access to the Small Mosque from the Existing Building

    c) Disable Access Ramp at the Small Mosque

    12.Site Instruction 12 was issued on 27th December 2011 which has revised

    the following scope of work:

    a) Change of roof Covering Material of Gate Buildings

    b) Modifications to the OB Garage

    c) Change of Soft Landscaping Technical Specifications

    13.Site Instruction 13 was issued on 27th December 2011 which has revised

    the following scope of work:

    a) Entry Gate Buildings-Omission of Wash Basins

    b) Thickness of Marble Staircase Steps

    c) Omission of Light Poles

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    13/46

    Claims/Variation Orders

    Total Claims submitted till date: 02

    1. Claim for Extension of Time for Administration Building:

    The Contractor submitted its claim for the total completion of AdministrationBuilding on 1st May 2010. As per the agreement between PWA and

    Contractor, the extended date of completion for Administration Building=

    27th Dec 2011

    2. Claim for Extension of Time for Project Completion:

    The Contractor submitted its claim for the total completion of Project on 1st

    May 2010. As per the agreement between PWA and Contractor following

    dates were agreed for the delay events occurred till 31st March 2011:

    - Extension of Time for Project Completion = 186 days

    - Extended date of completion for project = 14th Feb 2012

    Three (03) delay events are still ongoing, the effect of which is not

    considered in above extension of time. Their further impact will be computed

    in the late submission. These three (03) events are as following:

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    14/46

    - Construction of IT Building

    - Delay in release of structures for demolition

    - Non-availability of Internal Site Development Areas.

    3. Claim for Cost Impact of Site Instruction No. 01:

    Cost Impact of Site Instruction No. 01 has been submitted for Consultants

    review & approval on

    02-10-11

    4. Claim for Cost Impact of Site Instruction No. 02:

    Cost Impact of Site Instruction No. 02 has been submitted for Consultants

    review & approval on 02-10-11

    5. Claim for Cost Impact of Site Instruction No. 03:

    Cost Impact of Site Instruction No. 03 has been submitted for Consultants

    review & approval on 02-10-11.

    6. Claim for Cost Impact of Site Instruction No. 05:

    Cost Impact of Site Instruction No. 05 has been submitted for Consultants

    review & approval on 16-10-11

    7. Claim for Cost Impact of Revision in design of Parking Sheds

    Cost Impact of Site Instruction No. 10 has been submitted for Consultants

    review & approval on 04-10-11

    8. Claim for Cost Impact of additional works in Visitors Gate:

    Cost Impact of Site Instruction No. 10 has been submitted for Consultants

    review & approval on 17-10-11

    9. Claim for Cost Impact of Shifting Porta-cabins on instruction of

    PWA

    Cost Impact of Site Instruction No. 10 has been submitted for Consultants

    review & approval on 17-10-11

    10. Claim for Cost Impact of Additional Buildings-OB GARAGE

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    15/46

    Cost Impact of Site Instruction No. 06 has been submitted for

    Consultants review & approval on 09-1-12

    Payment Status:

    The Contractor has received an advance payment of QR 12,195,000. The Elevenprogress invoices were submitted by the contractor as following.

    Sr.

    No.Description Period

    Amount

    of Invoice

    Submission

    Date

    Date of

    Release

    1.Advance Payment

    Invoice--

    QR

    12,195,00023-May-2010

    2. Progress Invoice -02

    15th June 2010

    to 31st July

    2010

    QR

    2,098,36222-Aug-2010

    3. Progress Invoice -03

    1st August

    2010 to 31st

    August 2010

    QR

    1,408,91902-Sep-2010

    4. Progress Invoice -04

    1st

    -September-

    2010 to 31st

    -September-

    2010

    QR

    2,115,05629-Sep-2010

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    16/46

    5.Combined Progress

    Invoice (02)

    15th June 2010

    to -30th

    September

    2010

    QR

    5,512,5842nd Oct-2010 25 thOct-2010

    6. Progress Invoice (03)

    1st -October-

    2010 to 31st October 2010

    QR2,449,392

    2nd Nov-2010 13 thDec-2010

    7. Progress Invoice (04)

    1st -November-

    2010 to 30th

    November

    2010

    QR

    2,043,9142nd Dec-2010 10 thJan-2011

    8. Progress Invoice (05)

    1st -December-

    2010 to 31st

    December

    2010

    QR

    3,661,549.8

    9

    2nd January-2011 27thFeb-2011

    9. Progress Invoice (06)

    1st -January-

    2010 to 31st

    January 2011

    QR

    4,080,283.1

    9

    2nd February

    201102ndMar-2011

    10.Combined Progress

    Invoice (07)

    1st Feb 2011-

    to 31thMarch

    2011

    QR

    3,918,173.7

    8

    2nd March & 2nd

    April 201114thMay-2011

    11. Progress Invoice (08)

    1st -April- 2011

    to 30thApril

    2011

    QR

    4,769,618.0

    1

    2nd May 201108thJune-

    2011

    12 Progress Invoice (09)

    1st -May- 2011

    to 31stMay-

    2011

    QR

    9,111,872.7

    4

    2nd June 2011 26th July 2011

    13 Progress Invoice (10)

    1st -June- 2011

    to 30th June-

    2011

    QR

    4,993,084.7

    0

    3rd July 2011

    28th

    September

    2011

    14 Progress Invoice (11)

    1st -July- 2011

    to 31th July-

    2011

    QR

    5,609,751.6

    6

    2nd August 201110th October

    2011

    15 Progress Invoice (12)1st -Aug- 2011to 15th Sep-

    2011

    QR2,421,986.8

    9

    15th September

    2011

    3rd December

    2011

    16 Progress Invoice (13)

    15th Sep -

    2011 to 31st

    Oct- 2011

    QR

    3,075,024.0

    2

    2nd November

    2011

    26th

    December

    2011

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    17/46

    17 Progress Invoice (14) 1st November

    2011 to 30th

    Nov- 2011

    QR

    3,983,961.8

    9

    2nd December-

    2011

    22nd January

    2012

    18 Progress Invoice (15) 1st December

    2011 to 31th

    Dec- 2011

    QR

    4,278,822.9

    3

    2nd January-

    2011

    Not Released

    Yet

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    18/46

    Project Organization (OBS)

    Zone Distribution Diagram

    In order to have better control and maintain the work flow at site, the project sitehas been divided into two zones. i.e,

    o Zone 01

    o Zone 02

    Each zone is further divided into two parts i.e,

    http://f/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/CTPWUOIX/QRT-OBS%20For%20submission%20to%20PWA.xlsxhttp://f/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/CTPWUOIX/QRT-OBS%20For%20submission%20to%20PWA.xlsxhttp://f/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/CTPWUOIX/QRT-OBS%20For%20submission%20to%20PWA.xlsx
  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    19/46

    o Facility Expansion: Expansion of Qatar TV Complex

    o Existing facility Renovation: Renovation of Existing

    Qatar TV Complex

    The facility expansion is further divided into smaller areaswhich are called Plots in Zone Distribution Diagram asfollowing:

    o Plot A, B, C, D, E, etc.

    The Existing Facility Renovation is further divided into smaller areas which arecalled Plots in Zone Distribution Diagram as following:

    o Plot 1, 2, 3, 4, 5 etc.

    Zone Distribution Diagram is enclosed for reference.

    Work Breakdown Structure (WBS)

    The project has been divided into 5 major tiers to efficiently monitor and control theworks at site. These are as following:

    Renovation of Qatar Radio & TV Corporation

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    20/46

    o Preliminaries:

    It includes are the contractual and administrative activities anddocumentation after the letter of award and up to the award of Contractand taking over of site.

    o Mobilization:

    It includes the activities for mobilization of Contractors resources and sitefacilities to the project site.

    o Submissions:

    This tier enlists the activities for all the submissions to be made by theContractor throughout the project life. i.e., schedules, materialsubmissions, shop drawings etc.

    o Procurement:

    This tier enlists the activities for all the submissions to be made by theContractor throughout the project life. i.e., schedules, materialsubmissions, shop drawings etc.

    o Construction:

    o Construction tier has been further divided into following:

    o Buildings & Structures:

    o Site Development

    o Boundary Wall

    o Project Closing:

    The 05 major tiers of WBS have been further divided into work packages to havebetter control and monitoring at each facet of the project.

    The WBS is enclosed for reference.

    Work Breakdown Structure:

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    21/46

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    22/46

    Construction Progress Summary

    Highlights of the Month:

    Buildings & Structures:

    o Administration Building:

    o Fixing of False ceiling is completed

    o Fixing of Wood Cladding is completed

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    23/46

    o HVAC work is completed

    o Fixing of Windows & Doors is completed

    o Fixing of External Interlocks is in progress

    o Main Mosque:

    o Fixing of Hilal is completed

    o Fixing of Windows is completed

    o MEP work is completed

    o Fixing of External Interlocks is completed

    o Visitors Gate:

    o Construction of Guard House is started as per SI 10 is completed &

    Plaster work is completedo Formwork fixing for AC Plinth at Part-A is completed

    o Roof treatment at part-A & C is completed

    o Flooring Tiles & Marble fixing is in progress

    o HVAC work is in progress

    o Small Mosque:

    o Paint Work external & Internal is completed

    o Wall Tiles in Ablutions Area is completed

    o Paint of Lobby area internal side is completed

    o Expansion joint is completed

    o Employee Gate:

    o Fixing of marble in 1st floor (part-C) is completed

    o Fixing of windows & Doors is in progress

    o Fixing of lift is in progress

    o Fixing of Mable Cladding is in progress

    o VIP Gate:

    o Fixing of porcelain tiles is completed & Skirting is completed

    o Fixing of lift is in progress

    o Concrete of up-stand of stairs is completed

    o Fixing of Mable Cladding is in progress

    o Substation Building:

    o Fixing of Doors & windows is completed

    o Roof treatment is completed

    o Fixing of GRC is completed

    o Fixing of Chequered plate is completed

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    24/46

    o Irrigation Tank No.1:

    o Repair works in central partition wall is completed

    o MEP work is in progress

    o Irrigation Tank No.2:

    o Repair works in central partition wall are completed

    o MEP work is in progress

    o Irrigation Tank No.3:

    o Repair works in central partition wall are in progress

    o MEP work is in progress

    o OB Garage:

    o 1st Coat of primer in external side is completed

    o Installation of Steel Structure at Garage Area is in progress

    o Fixing of Block work at Garage area is in progress

    o IT Building:

    o There is no progress at IT Building as the proposed area for IT Building

    is not released to the Contractor yet.

    o Site Development Works:

    o Zone-1 / Plot A (Parking Area):

    o Paint works at Boundary Wall in progress

    o Parking sheds installation is in progress

    o Fixing of Interlock is in progress

    o Soft landscaping is in progress

    o Zone-2 / Plot A (Parking Area):

    o Main Irrigation Line works are finished

    o Installation of Boundary Wall is 100% completed & Paint works

    are going on.o Parking sheds installation is in progress

    o Fixing of Interlock is in progress

    o Zone-1 / Plot C :

    o Main Irrigation Works are finished

    o Pavement Works are in progress

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    25/46

    o Boundary Wall Installation is completed.

    Paint works are going on.o Fixing of Interlock is in progress

    o Zone-1 / PlotD:

    o Base course on area is completed

    o Installation of Boundary Wall is completed

    o Fixing of Interlock is in progress

    o Zone-2 / Plot D & E

    o The Roads works are completed

    o Fixing of Interlock is in progress

    o Placing of Pergola foundation is in progress

    o Zone 2/Plot B

    o Laying of Sub base & prime coat is completed

    o Boundary Wall installation is completed

    o Demolition Works:

    The Contractor could not commence demolition works according to theProgramme. The Contractor requested the Engineer's representative to issuea schedule of Structure for demolition

    Project Status:Sr Area Description Total Equival Work done Amounts Actual Progress

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    26/46

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    27/46

    The approved Clause -14 Programme of Works was seriously disrupted because of

    various Site Instructions and the delay events occurred at site. Because of these

    variations, the baseline schedule cannot be used for correct monitoring & control

    purposes. The Contractor has submitted its claim for Extension of Time (EOT-2) for

    approval

    For the progress monitoring with the actual site situation, the Contractor submitted

    an Intended schedule for the priority buildings and the available site development

    areas. The present status is given below:

    Contractor 's Schedule Performance

    Progress % Completion measured (Amount

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    28/46

    wise)Contractor Value: 121,950,000

    Earned Progress: 56.91%

    Planned Progress: 100%

    Earned Value : 69,405,828

    Planned Value:

    121,950,000

    S.P.I

    (Revenue) =EV/PV = 0.569

    Contractor 's Schedule

    Performance

    Progress % Completion measured (Man-hours

    wise)Contractor MH:

    1,110,511

    Earned Progress:

    64.47%

    Planned Progress: 100%

    Earned MH :

    715,960

    Planned MH:

    1,110,511

    S.P.I (Man-hours) = EV/PV = 0.645

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    29/46

    Submittals Summary & Details

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    30/46

    PROJECT RESOURCES

    Projects Indirect Staff:

    SN. DESCRIPTIONTOTAL MANHOURS TO

    DATE

    TOTAL MANHOURS PER

    DAY

    PRESENT

    ABS

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    31/46

    1Project Manager

    4,430

    10 1

    2Construction Manager

    2,430

    10 1

    3Contracts Manager

    4,730

    10 1

    4MEP Manager/Engineer

    6,030

    10 1

    5Planning Incharge

    8,050

    10 1

    6Proc. & Sc Engineer

    16,950

    30 3

    7Site Engineer

    14,550

    10 1

    8Area Controller

    9,200

    30 3

    9Planning Engineer

    5,290

    10 1

    10Engineer FEDC

    6,870

    10 1

    11Admin Incharge

    4,560

    10 1

    12Document Controller

    6,850

    20 2

    12QC Engineer/Inspector

    4,550

    30 3

    13 Architect 7,150

    10 1

    14Quantity Surveyor

    11,390

    20 2

    15Surveyor

    16,860

    30 3

    16Safety Officer/ Nurse

    17,750

    40 4

    17Drafts Man

    51,490

    70 7

    18 Supervisor/Asst.Supervisor

    31,820

    180 18

    20Electrician

    12,430

    30 3

    21Surveyor Helper

    9,620

    20 2

    22HSE Workers

    16,960

    30 3

    23 Operator 48,790 120 12

    35Drivers 30,920

    190 19

    36Purchase Officer

    5,250

    20 2

    37Planning Asst.

    8,030

    20 2

    38Administration

    6,210

    20 2

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    32/46

    39Accountant

    4,550

    10 1

    40Camp Staff

    18,850

    60 6

    41Store Incharge/ Store Helper

    15,890

    60 6

    42Tea Boy

    11,390

    20 2

    44Misc helpers 20,090

    80 8

    Total4

    39,9301230 123

    Projects Direct Staff:

    SN.DESCRIPTION

    TOTAL MANHOURS TO

    DATE

    TOTAL MANHOURS PER

    DAYPRESENT

    Foreman277,2

    1816 2

    2 Leadman 201,804 96 12

    3 Carpenter 104,1

    20480 60

    4 Mason62,

    582384 48

    5 Steel Fixer 430,8

    12192 24

    6 Scaffolder 34,

    52680 10

    7 Labour 28,

    254552 69

    8 Marble fixer 1,

    93680 10

    9 Fitter / Plumber

    4,

    810 72 9

    10 Elect. Technician16,

    4840 0

    11 A.C Technician4,

    6300 0

    12 Painter 11,

    43664 8

    13 Welder 8,

    61216 2

    14 Rigger 9,

    00424 3

    Total1,196,2

    282056 257

    Sub-Contractors:

    SN.DESCRIPTION TOTAL MAN

    HOURS TODATE

    TOTAL MANHOURS PER

    DAYPRESENT

    Sub Contractor name Type Of Work

    1SULTAN BIN (Plaster Work)

    15,812

    0 0

    2BSF (Steel Supplier)

    31,260

    0 0

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    33/46

    3SMC(MEP) (MEP Work)

    8,284

    80 10

    4HASAS/Soomy (Plaster Work)

    14,300

    0 0

    6TECHSO

    (Block work & Plasterwork)

    30,736

    96 12

    7REGENCY (Softland Scaping)

    31,4

    76104 13

    8AL-AZAM (Earth Work)

    33,536

    0 0

    9REDCO (Precast Boundary wall)

    13,246

    0 0

    10SARDAR /Unicon (Water Proofing)

    8,750

    0 0

    11AL-MOHANA (Road Work)

    22,536

    0 0

    12GULF GRC (Grc)

    4,866

    40 5

    13BARQ (MEP Work)

    159,536

    504 63

    14

    DRIVER

    26,8

    76

    0 0

    17AL MASNID (Wood works)

    6,112

    64 8

    18HORISON (Fall ceiling)

    8,718

    144 18

    19AWAN (Painting)

    2,392

    88 11

    20MURSHAD

    1,984

    64 8

    21EXCEL

    3,272

    120 15

    22AH IBRAHIM

    1,552

    0 0

    23BHARATH (Marble Fixing work)

    1,852

    104 13

    Total 427,096

    1408 176

    Project Equipment & Plant:

    SN. DESCRIPTION UNITREFERENCE NO.

    INOPERATIO

    N

    STANDBY

    TOTAL

    1 POWER GENERATORS No --- 7 1 8

    2 J.C.B No --- 3 0 3

    3 BOBCATS No --- 3 0 3

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    34/46

    4 TOWER LIGHTS No --- 3 0 3

    5 TOWER LIGHTS No --- 3 0 3

    6 HILTI DRILL/BREAKER No --- 4 0 4

    7 PLATE COMPACTORS No --- 4 0 4

    8 CRANE 25 TON No --- 1 0 19 PNEUMATIC HAMMER No. --- 2 0 2

    10 AIR COPRESSOR No. --- 2 0 2

    11 CONCRETE MIXER No. --- 6 0 6

    12 RIG MACHINE No. --- 0 0 0

    13 TELE HANDER No. --- 2 0 2

    14 EXCAVATOR No. --- 1 0 1

    15VIBRATORY ROLLER 1TON

    No. ---3 0

    3

    16 WATER BOUZER No. --- 1 0 1

    17 DUMP TRUCK No. --- 5 0 518 WHEEL LOADER No. --- 0 0 0

    19 PTR roller No. --- 0 0 0

    20 MOTOR GRADER No. --- 0 0 0

    21VIBRATORY ROLLER 18TON

    No. ---0 0

    0

    22 CRANE 20 TON No. --- 0 0 0

    23 ASPHAULT PAVER No. --- 0 0 0

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    35/46

    Site Progress Photographs

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    36/46

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    37/46

    Main Mosque

    FIXING OF INTERLOCKS IS IN PROGRESS (DATED: 21-01-12)

    FIXING OF WOODEN DOOR & WINDOWS IS COMPLETED

    (DATED: 21-01-12)

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    38/46

    Employee Gate

    Proposed Store

    STORE BUILDING IS COMPLETED (DATED: 21-01-12)

    FIXING OF MARBLE CLADDING IS IN PROGRESS (DATED:

    21-01-12)

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    39/46

    Small Mosque

    Site Development

    FIXING OF TILES & AC UNITS IS COMPLETED (DATED:

    21-01-12)

    GRANITES & WINDOWS IS COMPLETED (DATED: 21-

    01-12)

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    40/46

    FIXING OF PARKING SHED AT ZONE-2/PLOT-A IS COMPLETED

    (DATED: 21-01-12)

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    41/46

    FIXING OF PARKING SHEDS COLUMNS AT ZONE-2/PLOT-A IS

    COMPLETED (DATED: 21-01-12)

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    42/46

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    43/46

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    44/46

    PERGOLAS STRUCTURE

    OB-GARAGE BUILDING

    FIXING OF STEEL STRUCTURE AT GARAGE AREA IS IN PROGRESS

    (DATED: 21-01-12)

    FIXING OF PERGOLA AT ZONE-2/ Plot-D IS IN PROGRESS (DATED: 21-

    01-12)

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    45/46

    HSE MONTHLY REPORT

  • 7/27/2019 Monthly Report-21-December to 20-January 20 11.doc

    46/46

    QA/QC REPORT