monthly public works report - prosper, texas · detailed information contained within the report...

9
Prosper is a place where everyone maers. Monthly Public Works Report October 2017 Town of Prosper Public Works Water Water Conservation Wastewater Streets Physical Address: 601 W. Fifth Street Prosper, Texas 75078 Mailing Address: P.O. Box 307 Prosper, Texas 75078 Phone: 972.347.9969 www.prospertx.gov Statistics at a Glance Surface Water Pumped – 152.4 MG Gallons Flushed – 22.5 MG Work Orders – 606 Right-of-Way Permits – 106 Public Works Inspections – 129 Detailed information contained within the report Public Works Update The Downtown Streets project regarding Parvin Road, Third Street, and Sixth Street is well underway. Parvin Road is nearing completion with minor work to be done, Sixth Street has been paved, and Third Street is under construction, with work anticipated to be completed mid-December 2017. Staff attends mandatory safety meetings each month. This month, the safety meeting was held on Thursday, October 19, 2017. Notices of Non-Compliance were also sent to 1460 Blue Forest Drive, 720 Columbia Drive, 1550 Lakeside Drive, 2960 Gentle Creek Trail. These water customers have been notified of their obligation to test backflow devices in a mailed first notice and a hand delivered second notice. If their backflow devices remain non-compliant 30 days after delivery of the non- compliance notice, they will be subject to disconnection of water services.

Upload: others

Post on 15-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Monthly Public Works Report - Prosper, Texas · Detailed information contained within the report Public Works Update The Downtown Streets project regarding Parvin Road, Third Street,

Prosper is a place where everyone matters.

Monthly Public Works Report

October 2017

Town of Prosper

Public Works

Water

Water Conservation

Wastewater

Streets

Physical Address:

601 W. Fifth Street

Prosper, Texas 75078

Mailing Address:

P.O. Box 307

Prosper, Texas 75078

Phone: 972.347.9969

www.prospertx.gov

Statistics at a Glance

Surface Water Pumped – 152.4 MG

Gallons Flushed – 22.5 MG

Work Orders – 606

Right-of-Way Permits – 106

Public Works Inspections – 129

Detailed information contained within the report

Public Works Update

The Downtown Streets project regarding Parvin Road, Third Street, and Sixth Street is well underway. Parvin Road is nearing completion with minor work to be done, Sixth Street has been paved, and Third Street is under construction, with work anticipated to be completed mid-December 2017.

Staff attends mandatory safety meetings each month. This month, the safety meeting was held on Thursday, October 19, 2017.

Notices of Non-Compliance were also sent to 1460 Blue Forest Drive, 720 Columbia Drive, 1550 Lakeside Drive, 2960 Gentle Creek Trail. These water customers have been notified of their obligation to test backflow devices in a mailed first notice and a hand delivered second notice. If their backflow devices remain non-compliant 30 days after delivery of the non-compliance notice, they will be subject to disconnection of water services.

Page 2: Monthly Public Works Report - Prosper, Texas · Detailed information contained within the report Public Works Update The Downtown Streets project regarding Parvin Road, Third Street,

2

Surface Water Pumped

Water

Staff continues to conduct the monthly flushing program which is required by Texas

Commission on Environmental Quality (TCEQ). The program requires staff to flush each

dead end main lines once a month to ensure the quality of the drinking water and

maintain the free chlorine residual in the water. In October, staff flushed 22.5 MG of

water. The extra flushing is being experienced by Frisco and McKinney also, to maintain a

level of 1.3 Parts Per Million (PPM) for a residual at our outlaying parts of the system. We

have seen the residual fall over night to 0.7 to 0.8 PPM. Low water use, lower residual

levels coming in from NTMWD, high temperatures and large pipes that don’t circulate are

all factors.

Flushing

Page 3: Monthly Public Works Report - Prosper, Texas · Detailed information contained within the report Public Works Update The Downtown Streets project regarding Parvin Road, Third Street,

3

Work Orders

Water Continued

Note: Work orders are possible repairs on equipment or lines, potholes, street signs, etc.

that have been initiated by customers or staff. The work orders total also includes locate

requests and other service requests that are entered into CityWorks.

Right-of-Way Permits

Staff reviewed 106 ROW Permits in October.

Page 4: Monthly Public Works Report - Prosper, Texas · Detailed information contained within the report Public Works Update The Downtown Streets project regarding Parvin Road, Third Street,

4

Water Conservation

Monthly Water Usage/Monthly Goal Comparison

YTD Water Usage Comparison

The Town of Prosper was 44 MG under the Use Adjusted for Growth in the month of

August and 32 MG over the Use Adjusted for Growth in the month of September. Staff

is waiting for NTMWD to update their records for October.

The Town of Prosper was 3.2% above the year-to-date amount 2015-16 Use Adjusted for

Growth Goal in August and 5.0% above the goal for September. Staff is waiting for

NTMWD to update their records for October. It is required by North Texas Municipal

Water District, that we have educational programs in place to reduce the waste and over

use of water.

Page 5: Monthly Public Works Report - Prosper, Texas · Detailed information contained within the report Public Works Update The Downtown Streets project regarding Parvin Road, Third Street,

5

Water Education

Fats, Oils, and Grease (FOG) Update

Staff is working on the Planter Project, which is an effort to

bring awareness of water conservation and recycling. Staff

worked with the National Art Society to have Prosper

students design artwork for the planters that encourages

water conservation and recycling. The planter boxes are in

the process of being wrapped.

Quarterly Grease Trap Inspections

The FOG Outreach Plan has been implemented to comply with the EPA’s Administrative

Order. The FOG Outreach Plan is a large section of our required CMOM Plan. Grease

interceptors will be inspected on a quarterly basis for the first year to determine a

mandated cleaning schedule businesses must follow. Grease interceptors that are not

emptied regularly can contribute to Sanitary Sewer Overflows. Staff inspected 23

grease interceptors in October and have processed 26 Notice of Violations this quarter

period.

Page 6: Monthly Public Works Report - Prosper, Texas · Detailed information contained within the report Public Works Update The Downtown Streets project regarding Parvin Road, Third Street,

6

Wastewater

Public Works Inspections

Wastewater Update

Public Works completed 129 inspections this month. Prior to Development Services issuing a Certificate of Occupancy, Public Works cameras the sewer service, inspects the right-of-way, the sidewalk, and Town maintained improvements.

Staff continues to inspect and perform maintenance on manholes and wastewater

mains throughout Town as requested by the EPA. This acts as preventative maintenance

to ensure lines are in acceptable condition and not in need of repair.

The Wastewater Department continues to clean all the lift stations once a month to

reduce pump failure and reduce backups.

Staff initiated televised inspection process at Tanners Mill, Phase 1c by removing all caps

and pouring water down service lines and televising Block O, Block L, and Block M, as

well as inspected service lines at Star Trail marking the defective service lines for repair.

Staff televised La Cima, Phase 5 & 6C approximately 7,146.81 feet, and found issues at

608 East Third Street, 1110 Twin Oaks Drive and La Cima Boulevard.

Staff conducted repairs and replaced sewer service stub outs and caps at Prosper

Trail & Woodview Drive, 2801 Meadowbrook Boulevard, Star Trail Parkway, and

1921 Foxglen Drive.

Staff installed sewer services at 508 Third Street, 510 Third Street and 604 Third Street.

Page 7: Monthly Public Works Report - Prosper, Texas · Detailed information contained within the report Public Works Update The Downtown Streets project regarding Parvin Road, Third Street,

7

Streets The Street Division continues to replace street signs in Town, which are required to be

hi-intensity, to meet the new federal requirement for letter size and letter configuration.

Staff also continues to identify and fix/replace signs and poles around town that have

been damaged due to the severe weather.

The Adopt-A-Street Program has a total of 21 streets that are required to have quarterly

clean-ups. The program covers twenty miles of roadway. There are no streets available

for adoption at this time.

The Streets Department continues to mow and trim trees in Right-of-Way and inspect

any drainage issues along the streets in an attempt to prevent or reduce traffic hazards.

Staff replaced a damaged pole/sign at Glacier Point Court and Newport Drive, Hickory

Creek Road and Preston Road, Moonlight Trail, Prosper Trail (east of Dallas Parkway),

and the northeast corner of Coleman Street & First Street.

The Streets Department painted 6” guardrail on Prosper Trail, west of Preston Road.

Staff repaired areas at 8844 Highpoint in collaboration with a repair that the Water

Department conducted, and the corner of Hays Road and Chandler Circle.

Staff conducted patch work at Dallas Parkway and First Street, Broadmoor Lane &

Prosper Trail, County Road 27, Fishtrap Road (west of Gee Road), North case alley ways,

and Frontier Parkway.

The Streets Department installed new road signs/directional signs at 3602 East First

Street, 3737 East First Street, Cook Lane & Prosper Trail, Copper Canyon Drive, Preston

Road (South of Frontier), Coleman and Talon, and Evening Sun Drive.

Staff performed road grading on Legacy Road (Fishtrap Road to Frontier Parkway),

Parvin Road (Legacy Drive to Good Hoop Road), Harper Road, Prosper Road, Prosper

Trail, County Road 933, West Fifth Street, Mahard Road (west of tracks), and County

Road 27.

Staff replaced 15” concrete pipe drainage culvert at 307 North Parvin Street, a 12” pipe

culvert at 308 Sixth Street.

Staff prepared concrete forms and set rebar at 1840 Winding Creek Road, digging out a

drainage ditch 12” x 40’.

Page 8: Monthly Public Works Report - Prosper, Texas · Detailed information contained within the report Public Works Update The Downtown Streets project regarding Parvin Road, Third Street,

8

Updated Town of Prosper Population Signs

Streets Continued

Before After

Legacy and Frontier Guardrail Maintenance

Before & After Before & After

Page 9: Monthly Public Works Report - Prosper, Texas · Detailed information contained within the report Public Works Update The Downtown Streets project regarding Parvin Road, Third Street,

9

Streets Continued

Street Department helped one of Prosper’s young residents recover his lost football

Streets Department staff member Charles Martinez made a little boy’s day by helping

him recover his lost football that found its way in the storm drain. Once again, Public

Works department saves the day and proves that the needs and wants of the Prosper

citizens are its priority. Thank you Streets Department for going above and beyond in

contributing in making the Town of Prosper a better place.