modularisation – the next step - presentation by bill meyer, foster wheeler usa corporation

110
Feb 2011 Bill Meyer Modularisation – The Next Step © 2011 FOSTER WHEELER. All rights reserved. William (Bill) Meyer - B.E. (Civil) Hons., MBA. Director Project Execution Development Foster Wheeler USA Corporation Houston, Texas. [email protected]

Upload: iqpc-australia

Post on 09-May-2015

2.630 views

Category:

Documents


5 download

DESCRIPTION

This presentation by William (Bill) Meyer explores the past trends of modularisation, the cost and benefits of modularisation, optimising module sizes and the future of modularisation.

TRANSCRIPT

Page 1: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

William (Bill) Meyer -

B.E. (Civil) Hons., MBA.

Director Project Execution Development

Foster Wheeler USA Corporation

Houston, Texas.

[email protected]

Page 2: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Topics

1. Where is modularisation going? Is there a trend?

2. What is the optimum size of module? Are larger modules

better?

3. What impacts are tomorrow’s modules likely to have on

construction?

Page 3: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Agenda

1. Introduction

2. Historical Perspective – Past Trends

3. Understanding why – Cost / benefit and decision

process

4. Optimising module sizes

5. Summary

6. Q & A

Page 4: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Accent

� Australian

University of Melbourne

� Bachelor of Engineering (Civil) Honors

� MBA

Work

� ½ as specialist Heavy Lift and Transport contractor

– Vice President Mammoet USA

� ½ Foster Wheeler – Engineering, Procurement, Construction contractor

– Director Project Execution Development

– Focus on major project construction execution and project management

Page 5: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

� Global Engineering and Construction Contractor and Power Equipment Supplier

� In business for over 100 years

� Strong history in technology development

� Proven track record of successful project execution

� A global presence

� Over 13,000 resources

� Permanent offices in 28 countries

� Financially strong

Foster Wheeler

Page 6: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Registered Office & Corporate CenterOperating Unit HQs and/or Main Engineering CenterRegional/Local Engineering CenterSales Offices

Bogota

Page 7: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Topics

1. Introduction

2. Historical Perspective – Past Trends

3. Understanding why – Cost / benefit and decision

process

4. Optimising module sizes

5. Summary

6. Q & A

Page 8: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Historical Perspective – past trends

Statoil Mongstad – Norway - 1988

� 221 modules

� 975 tonnes max module

� 6 module yards

Page 9: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Historical Perspective – past trends

Statoil Mongstad – Norway - 1988

� 221 modules

� 975 tonnes max module

� 6 module yards

� Schedule driven

Page 10: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Historical Perspective – past trends

Mobil Coryton – UK - 1993

� Isomerisation unit

� 58 Modules to 350 tonnes

� Barge delivery from one European fabricator

Page 11: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Historical Perspective – past trends

Mobil Coryton – UK - 1993

� Isomerisation unit

� 58 Modules to 350 tonnes

� Barge delivery from one European fabricator

� Schedule driven

Page 12: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Historical Perspective – past trends

ExxonMobil Singapore Aromatics - 1996

� 213 modules – 26,875 tonnes total

� 1150 tonnes max

� 7 module yards

� 39 barge voyages

� Schedule driven

Page 13: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Historical Perspective – past trends

Inco Goro – New Caledonia - 2006

� Nickel mine and ore processing plant

� 599 modules

� 600 tonnes max

� 2 main module

yards

Page 14: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Historical Perspective – past trends

Inco Goro – New Caledonia - 2006

� Nickel mine and ore processing plant

� 599 modules

� 600 tonnes max

� 2 main module

yards

� Cost driven

Page 15: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Historical Perspective – past trends

The Woodside-operated NWSV Phase V LNG Expansion – Australia – 2007

� 75 modules

� 1,800 tonnes max

� Pluto currently nearing completion

Page 16: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Historical Perspective – past trends

The Woodside-operated NWSV Phase V LNG Expansion – Australia – 2007

� 75 modules

� 1,800 tonnes max

� Pluto currently nearing completion

� Cost and schedule driven

Page 17: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Historical Perspective – past trends

1. Pre circa 2000, main reason to go modular was for schedule benefits

2. More recently, cost benefits have been the aim

Page 18: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Topics

1. Introduction

2. Historical Perspective – Past Trends

3. Understanding why – Cost / benefit and decision

process

4. Optimising module sizes

5. Summary

6. Q & A

Page 19: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Viable Modular Execution

Benefits > Price you have to pay for those Benefits

Page 20: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Viable Modular Execution

Benefits > Price you have to pay for those Benefits

AND

Risk of NOT achieving those Net Benefits is Low, Manageable &

Risk Goals are Achievable

Page 21: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Modular Execution Benefits can be:

1. Cost reductions

Page 22: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Modular Execution Benefits can be:

1. Cost reductions

2. Schedule reductions

Page 23: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Modular Execution Benefits can be:

1. Cost reductions

2. Schedule reductions

Profit

Compliance

Page 24: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Modular Execution Benefits can be:

1. Cost reductions

2. Schedule reductions

3. Safety enhancements

Page 25: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Modular Execution Benefits can be:

1. Cost reductions

2. Schedule reductions

3. Safety enhancements

4. Quality enhancements

Page 26: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Modular Execution Benefits can be:

1. Cost reductions

2. Schedule reductions

3. Safety enhancements

4. Quality enhancements

5. Reduced impact on Society

Page 27: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Modular Execution Benefits can be:

1. Cost reductions

2. Schedule reductions

3. Safety enhancements

4. Quality enhancements

5. Reduced impact on Society

6. Reduced impact on Environment

Page 28: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Modular Execution Benefits can be:

1. Cost reductions

2. Schedule reductions

3. Safety enhancements

4. Quality enhancements

5. Reduced impact on Society

6. Reduced impact on Environment

7. And many more…

Page 29: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Decision Analysis – Modular or Stick built?

Page 30: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Project

PhaseFEL 1

Conceptual FEL 2

Assess FEL 3

Define

Execution FEL 5

Evaluation

FEL 4

Evaluate Module Options

Modular Execution Decision

Timing is Critical

Page 31: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

e.g. OSBL piping in existing racks

Major storage tanks

Page 32: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Page 33: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Page 34: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Page 35: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Site Survey includes

• Labour

Availability, productivity, quality, craft availability, cost, other projects in area, union impacts, regional / political issues etc

Page 36: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Labour Productivity

0

1000

2000

3000

4000

5000

6000

7000

8000

0 12 24 36 46 50 50 50 56 64 72 80 88 96 104

112

120

128

136

144

Graph 1 - Labor vs time (% of project schedule) – Direct hour impact if productivity shortfall of trainees

Page 37: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Result of productivity shortfall

0

1000

2000

3000

4000

5000

6000

7000

0 12 24 36 46 50 50 50 56 64 72 80 88 96 104

112

120

128

136

144

Graph 2 - Labor vs time (% of project schedule) – Schedule impact if productivity shortfall of trainees

Page 38: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

0

1000

2000

3000

4000

5000

6000

7000

0 12 24 36 46 50 50 50 56 64 72 80 88 96 104

112

120

128

136

144

Graph 4 - Labor vs time (% of project schedule) – Manhours moved offsite

Move manhours offsite to pre-cast, pre-fab, pre-

assembly and modules

Skilled Labour Availability – Move manhours Offsite

Page 39: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Site Survey includes

• Labour

• Weather impacts

Page 40: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Site Survey includes

• Labour

• Weather impacts

• Logistics

On site and to site, route surveys, from fabrication yard, cost and technical capabilities, laydown areas

Page 41: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Site access restrictions can limit size of modules that can be

delivered to site

Page 42: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Logistics are project specific -

– Some sites have their own ports …

Page 43: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Logistics are project specific -

… others are road access only

Page 44: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Site Survey includes

• Labour

• Weather impacts

• Logistics

• Environmental impact

Page 45: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Site Survey includes

• Labour

• Weather impacts

• Logistics

• Environmental impact

• Safety

Page 46: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Site Survey includes

• Labour

• Weather impacts

• Logistics

• Environmental impact

• Safety

• Permit issues

Page 47: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Site Survey includes

• Labour

• Weather impacts

• Logistics

• Environmental impact

• Safety

• Permit issues

• Etc.

Page 48: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Module Yard Survey includes

• Labour

Productivity, cost, flexible workforce, skills, experience etc

Page 49: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Relative Costs to Fabricate Modules and Ship to Project X site

Italy

USA

USA

Japa

nKor

eaKor

eaKor

eaFra

nce

Mex

ico

Mal

aysi

aSin

gapo

reSin

gapo

reM

alay

sia

Philip

pine

sTha

iland

Chi

naC

hina

Vietn

amC

hina

Project and Site Specific

Calendar Date Specific

Module Yard Specific

Page 50: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Module Yard Survey includes

• Labour

• Yard capabilities

Covered fabrication, assembly area, loadout capabilities, management skills and experience, procurement capability, drafting capability, quality systems, safety records etc

Page 51: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Module Yard Survey includes

• Labour

• Yard capabilities

• Size of client management team

required

Page 52: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Module Yard Survey includes

• Labour

• Yard capabilities

• Size of client management team

required

• Shipping type and distances to site

Page 53: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Module Yard Survey includes

• Labour

• Yard capabilities

• Size of client management team

required

• Shipping type and distances to site

• Weather

Page 54: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Module Yard Survey includes

• Labour

• Yard capabilities

• Size of client management team

required

• Shipping type and distances to site

• Weather

• Political factors

Page 55: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Module Yard Survey includes

• Labour

• Yard capabilities

• Size of client management team

required

• Shipping type and distances to site

• Weather

• Political factors

• Etc

Page 56: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Page 57: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Page 58: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Page 59: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Will impact possible module sizes Type of plant

Scale of plant

Page 60: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Will impact possible module sizes Type of plant

Scale of plant

Page 61: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Page 62: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Economics of Modular Execution

For the cost estimates of stick and modular

Need only to focus on DIFFERENTIAL COSTS between stick built

and modular execution

Page 63: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Downside

� Increased cost of steel / minor bulks / foundations

Page 64: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Downside

� Increased cost of steel / minor bulks / foundations

� Increased cost of shipping

Page 65: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Downside

� Increased cost of steel / minor bulks / foundations

� Increased cost of shipping

� Potentially - increased cost of transport and installation

Page 66: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Downside

� Increased cost of steel / minor bulks / foundations

� Increased cost of shipping

� Potentially - increased cost of transport and installation

Page 67: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Downside

� Increased cost of steel / minor bulks / foundations

� Increased cost of shipping

� Potentially - increased cost of transport and installation

Page 68: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Downside

� Increased cost of steel / minor bulks / foundations

� Increased cost of shipping

� Potentially - increased cost of transport and installation

Page 69: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Downside

� Increased cost of steel / minor bulks / foundations

� Increased cost of shipping

� Potentially - increased cost of transport and installation

� Increased cost of Engineering

� Increased cost of client yard management

� Increased cost to set modules / extra field welds / hydro

Page 70: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Upside

� Move labour cost offsite to cheaper / more productive laboursupply

Page 71: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

-

20,000

40,000

60,000

80,000

100,000

120,000

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33

months

-

20,000

40,000

60,000

80,000

100,000

120,000

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33

months

Manhours moved offsite on a past modular project

Site Prep Civil Structural / Mech / Equip Piping E & I Indirects

Page 72: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Upside

� Move labour cost offsite to cheaper / more productive laboursupply

� Reduce indirect costs at site as less directs (construction supervision, consumables etc)

Page 73: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Upside

� Move labour cost offsite to cheaper / more productive laboursupply

� Reduce indirect costs at site as less directs (construction supervision, consumables etc)

� Reduced cost of camp construction due to lower peak

Page 74: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Upside

� Move labour cost offsite to cheaper / more productive laboursupply

� Reduce indirect costs at site as less directs (construction supervision, consumables etc)

� Reduced cost of camp construction due to lower peak

� Improved productivity (weather, flexible workforce, site accessibility, material flows, etc)

Page 75: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Upside

� Move labour cost offsite to cheaper / more productive laboursupply

� Reduce indirect costs at site as less directs (construction supervision, consumables etc)

� Reduced cost of camp construction due to lower peak

� Improved productivity (weather, flexible workforce, site accessibility, material flows, etc)

� Reduced schedule reduces construction indirects

Page 76: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Upside

� Move labour cost offsite to cheaper / more productive laboursupply

� Reduce indirect costs at site as less directs (construction supervision, consumables etc)

� Reduced cost of camp construction due to lower peak

� Improved productivity (weather, flexible workforce, site accessibility, material flows, etc)

� Reduced schedule reduces construction indirects

� [Positive impact to NPV if revenue stream begins earlier]

Page 77: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Neutral

� Shipping of module materials to yard versus shipping to site

Page 78: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Neutral

� Shipping of module materials to yard versus shipping to site

Page 79: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Module

versus

Stick built

Cost

Differentials

Modular versus Stick built costs

$0.0

$10.0

$20.0

$30.0

$40.0

$50.0

$60.0

$70.0

$80.0

$90.0

$100.0

Modular Cost Stick built Cost

Installation cost ∆

Shipping cost ∆

Const. Mngmt cost ∆

Foundation cost ∆

Steel cost ∆

Engineering cost ∆

Camp cost ∆

Labour cost

Savings

Mill

ion

s $

Existing Project Data

(Note – All projects have different cost drivers )

Page 80: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Marginal Cost of Construction

Marginal Cost of Construction / manhour =

Wages for Direct Labour

+ Indirect Labour (incl Inspection and QA)

+ Payroll Burdens / Benefits / Allowances / Premiums /

Camp Costs / Subsistence for Direct and Indirect Labour

+ Management Costs / Field Offices / Indirect Facilities

+ Construction Equipment / Small Tools and Consumables

+ Scaffold

+ Stick Built Materials Laydown and Distribution

+ ETC

Page 81: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Benefits

Construction

Site

Labour Productivity 2.20

Marginal Cost of Construction / mh $105.00

Relative Manhour Cost c/w Gulf Coast $231.00

Page 82: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Benefits

Construction Module

Site Yard

Labour Productivity 2.20 1.20

Marginal Cost of Construction / mh $105.00 $55.00

Relative Manhour Cost c/w Gulf Coast $231.00 $66.00

Page 83: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Benefits

Economic Productivity Factor

Construction Module

Site Yard

Labour Productivity 2.20 1.20

Marginal Cost of Construction / mh $105.00 $55.00

Relative Manhour Cost c/w Gulf Coast $231.00 $66.00

Economic Productivity Ratio 3.50 : 1

Page 84: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Benefits

Economic Productivity Factor using a Far East Module Yard

Construction Module

Site Yard

Labour Productivity 2.20 3.50

Marginal Cost of Construction / mh $105.00 $12.10

Relative Manhour Cost c/w Gulf Coast $231.00 $42.35

Page 85: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Benefits

Economic Productivity Factor using a Far East Module Yard

Construction Module

Site Yard

Labour Productivity 2.20 3.50

Marginal Cost of Construction / mh $105.00 $12.10

Relative Manhour Cost c/w Gulf Coast $231.00 $42.35

Economic Productivity Ratio 5.45 : 1

Page 86: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost Benefits

Economic Productivity Factor

Construction Module

Site Yard

Labour Productivity 2.55 3.50

Marginal Cost of Construction / mh $125.00 $12.10

Relative Manhour Cost c/w Gulf Coast $318.75 $42.35

Economic Productivity Ratio 7.53 : 1

Page 87: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Modular versus Stick built costs

$0.0

$20.0

$40.0

$60.0

$80.0

$100.0

$120.0

$140.0

Modular Cost Stick built Cost

Installation cost ∆

Shipping cost ∆

Steel cost ∆

Engineering cost ∆

Camp cost ∆

Labour cost

Modular versus Stick built costs

Modular Cost Stick built Cost

Installation cost ∆

Shipping cost ∆

Steel cost ∆

Engineering cost ∆

Camp cost ∆

Labour cost

Modular versus Stick built costs

Modular Cost Stick built Cost

Installation cost ∆

Shipping cost ∆

Steel cost ∆

Engineering cost ∆

Camp cost ∆

Labour cost

COST DRIVEN MODULAR

PROJECT

SCHEDULE DRIVEN

MODULAR PROJECT

COST DRIVEN STICK BUILT

PROJECT

Page 88: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Agenda

1. Introduction

2. Historical Perspective – Past Trends

3. Understanding why – Cost / benefit and decision

process

4. Optimising module sizes

5. Summary

6. Q & A

Page 89: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Manhour Density is Key

Page 90: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Manhour Density is Key

Page 91: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Manhour Density is Key

� The more manhours in a given shipping volume, the greater the cost benefit to moving those manhours offsite.

� This benefit must outweigh the cost to ship those manhoursback to site.

Page 92: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Cost of module shipment vs. module “size”

Co

st

($ m

illi

on

)

Module size / weight Large

Lin

er

serv

ices

Specialist Heavy Lift

Ships

Semi-Submersibles

Page 93: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Page 94: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Manhour Density is Key

� The more manhours in a given shipping volume, the greater the cost benefit to moving those manhours offsite.

� This benefit must outweigh the cost to ship those manhoursback to site.

� Second order effects then must be taken into account, such as extra steel costs, site transport and installation costs etc.

Page 95: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Manhour Density is Key

Page 96: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

� Identify the labour intensive sections on the site…(highlighted red)

Page 97: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

� Aggregate where feasible…

Page 98: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

� Construct off-site

Page 99: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Page 100: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Interconnectivity factors

Page 101: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Interconnectivity factors

Page 102: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Interconnectivity factors

�� Additional hookup at the interfaceAdditional hookup at the interface

�� Additional ship spaceAdditional ship space

�� Additional Installation costsAdditional Installation costs

�� Delta steelDelta steel

Page 103: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Interconnectivity factors

Page 104: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Interconnectivity factors

�� Additional hookup at the interfaceAdditional hookup at the interface

�� Additional ship spaceAdditional ship space

�� Additional Installation costsAdditional Installation costs

�� Delta steelDelta steel

Page 105: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Vertical and horizontal splits for this CCR

Page 106: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Agenda

1. Introduction

2. Historical Perspective – Past Trends

3. Understanding why – Cost / benefit and decision

process

4. Optimising module sizes

5. Summary

6. Q & A

Page 107: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Summary

1. Where is modularisation going? Is there a trend?

� More modularisation is the trend for jobs in high labour

cost areas / low quantity of skilled labour areas

� Trend will be driven by demand for resources and energy

� Market segment dependant

� BRIC – IC low , BR depends on location of site and yards

Page 108: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Summary

2. Are larger modules better?

� Depends on plant scale and type / shipping

distances and costs / logistics constraints

� Relative costs of shipping vs. big / small / splitting

� For any given shipping cost curve – typically yes!

� Manhour density of plant modules > breakeven

� Height of C. of G!

Page 109: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

Summary

3. What impacts are tomorrow’s modules likely to have on

construction?

� In general – reduces construction risk (but shifts it to E&P)

� Construction equipment

� Technology exists to move and install large loads

� Crane size development driven by larger equipment items

and need for longer reach, not primarily module sizes

� Innovation is still key!

Page 110: Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler USA Corporation

Feb 2011Bill Meyer

Modularisation – The Next Step

© 2011 FOSTER WHEELER. All rights reserved.

ANY QUESTIONS ?