modifide mining plan with progressive mine closure...

86
MODIFIDE MINING PLAN WITH PROGRESSIVE MINE CLOSURE PLAN [SUBMITTED UNDER RULE 29 OF RMMCR, 2017 FOR WORKING LEASE AREA] BAS BHANDARI SOAPSTONE MINE VILLAGE : MORARA TEHSIL : TODA BHIM DISTRICT : KARAULI (RAJ.) MINERAL : SOAPSTONE LEASE AREA : 4.98 Ha. (NON-FOREST AREA) M.L. NO. : 04/1984 LEASE PERIOD : 21/04/95 to 20/04/15 (EXTENDED UPTO 31/03/20) PERIOD OF PERIOD OF MINING : 2016 - 17 to 2020 - 21 LESSEE PREPARED BY SHRI SHAH KASTOORMAL NOMINETED OWNER SHRI SHAH SURENDER R/o: Kalyan Bhawan, Shah building, S.M.S. Highway (Chaura Rasta) District: Jaipur (Raj), Pin Code - 302002 ARUN KUMAR YADAV Reg. No. RQP/AJM/242/2003/A, Valid up to 21/05/2023 OVERSEAS MIN TECH CONSULTANT 501, 5 th floor, Apex Tower, Tonk Road, Jaipur-302015 Tel. No. 0141-2744509; Mobile No.-9460221084 E-Mail-[email protected] Website: www.overseasmintech.com

Upload: others

Post on 24-Oct-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

  • MODIFIDE MINING PLAN

    WITH

    PROGRESSIVE MINE CLOSURE PLAN

    [SUBMITTED UNDER RULE 29 OF RMMCR, 2017 FOR WORKING LEASE AREA]

    BAS BHANDARI SOAPSTONE MINE

    VILLAGE : MORARA

    TEHSIL : TODA BHIM

    DISTRICT : KARAULI (RAJ.)

    MINERAL : SOAPSTONE

    LEASE AREA : 4.98 Ha. (NON-FOREST AREA)

    M.L. NO. : 04/1984

    LEASE PERIOD : 21/04/95 to 20/04/15 (EXTENDED UPTO 31/03/20)

    PERIOD OF

    PERIOD OF MINING : 2016 - 17 to 2020 - 21

    LESSEE PREPARED BY

    SHRI SHAH KASTOORMAL

    NOMINETED OWNER SHRI SHAH SURENDER

    R/o: Kalyan Bhawan, Shah building, S.M.S.

    Highway (Chaura Rasta) District: Jaipur

    (Raj), Pin Code - 302002

    ARUN KUMAR YADAV

    Reg. No. RQP/AJM/242/2003/A,

    Valid up to 21/05/2023 OVERSEAS MIN TECH CONSULTANT

    501, 5th floor, Apex Tower, Tonk Road,

    Jaipur-302015

    Tel. No. 0141-2744509; Mobile No.-9460221084

    [email protected]

    Website: www.overseasmintech.com

  • 1

  • SHRI SHAH KASTOORMAL NOMINETED OWNER SHRI SHAH SURENDER

    R/o: Kalyan Bhawan, Shah building, S.M.S. Highway (Chaura Rasta) District: Jaipur (Raj), Pin Code - 302002

    AUTHORISATION LETTER

    I, Shah Surender for Bas Bhandari Soapstone Mine hereby, authorise Shri Arun Kumar Yadav

    RQP No.RQP/AJM/242/2003/A to prepare the Modified Mining Plan with Progressive Mine Closure

    Plan Under Rule 29 of The Rajasthan Minor Mineral Concession Rules, 2017 in respect of Bas

    Bhandari Soapstone Mine, M. L. No. 04/84 over an area of 4.98Hect. (Forest Diversion Land) for

    mineral Soapstone in Village- Morara, Tehsil- Toda Bhim, District- Karauli, State- Rajasthan of Bas

    Bhandari Soapstone.

    I request the Superintending Mining Engineer, Department of Mines & Geology, Bharatpur to

    make further correspondence regarding modification / withdrawal / re-submission and to collect the

    approved copies of the aforesaid Modified Mining Plan with Progressive Mine Closure Plan with the

    said recognized person on his following address:

    Arun Kumar Yadav

    RQP/AJM/242/2003-A

    Validity up to 21st May 2023

    Address of RQP-501,

    5th Floor, Apex Tower,

    Tonk Road, AJMER-302015

    E-Mail- [email protected]

    Website: www.overseasmintech.com

    T-0141-2744509(O), Mob. - +91-9460221084

    Place : Bharatpur SHAH SURENDER

    Date (NOMINETED OWNER SHRI SHAH SURENDER)

  • ARUN KUMAR YADAV

    AMIE (Mining), FCC [Metal I], RQP, Surveyor (Coal & Metal), EIA Coordinator

    501,5th Floor, Apex Tower, Tonk Road, AJMER- 302015

    E-mail: [email protected], Website- www.overseasmintech.com,

    Tel No.- +91-141-2744509, Mobile No.- 9460221084

    CERTIFICATE

    I, Arun Kumar Yadav, hereby certify that

    “The provisions of Rajasthan Minor Mineral Concession Rules, 2017 have been observed in the

    Modified Mining Plan with Progressive Mine Closure Plan for Bas Bhandari Soapstone Mine, M. L.

    No. 04/84, over an area of 4.98Hect. (Forest Diversion Land) for mineral Soapstone in Village-

    Morara, Tehsil- Toda Bhim, District- Karauli, State- Rajasthan of Bas Bhandari Soapstone and

    wherever specific permission is required the lessee will approach the concerned authorities of

    Department of Mines & Geology for granting the permission.”

    1. It is also certified that the provisions of Mines Act, Rules and Regulations made there under

    have been observed in the aforesaid Modified Mining Plan with Progressive Mine Closure Plan and

    wherever specific permissions are required the lessee will approach the Director General of Mines

    Safety.

    2. It is further certified that the aforesaid Modified Mining Plan with Progressive Mine Closure

    Plan is prepared as per the copies of the records and documents provided by lessee and information

    given as per discussions held with Lessee representative.

    3. It is also certified that the information furnished in the aforesaid Modified Mining Plan with

    Progressive Mine Closure Plan are true and correct to the best of my/ our knowledge & belief and in

    case of default the approval would be withdrawn.

    4. It is also certified that the plans and sections are prepared based on the lease map

    authenticated by the state Governments.

    Place : Jaipur Arun Kumar Yadav

    Date : RQP/AJM/242/2003/A

    Validity:-21St

    May 2023

  • SHRI SHAH KASTOORMAL NOMINETED OWNER SHRI SHAH SURENDER

    R/o: Kalyan Bhawan, Shah building, S.M.S. Highway (Chaura Rasta)

    District: Jaipur (Raj), Pin Code - 302002

    CERTIFICATE

    1. It is certified that the provisions of Mines Act, Rules and Regulations made there under have

    been observed in the Modified Mining Plan with Progressive Mine Closure Plan for Bas

    Bhandari Soapstone Mine M. L. No. 04/84, over an area of 4.98Hect. (Forest Diversion Land)

    for mineral Soapstone in Village- Morara, Tehsil- Toda Bhim, District- Karauli, State-

    Rajasthan of Bas Bhandari Soapstone Mine and wherever specific permissions are required,

    the lessee will approach the Director General of Mines Safety. Further, the standards as

    prescribed by DGMS in respect of miner’s health will be strictly implemented.

    2. The Modified Mining Plan with Progressive Mine Closure Plan for Bas Bhandari Soapstone

    Mine M. L. No. 04/84, over an area of 4.98Hect. (Forest Diversion Land) for mineral

    Soapstone in Village- Morara, Tehsil- Toda Bhim, District- Karauli, State- Rajasthan of Bas

    Bhandari Soapstone Mine complies all the statutory Rules, Regulations, Orders made by the

    Central Government or State Government, Statutory organizations, Court etc. and have been

    taken into consideration. Wherever any specific permission is required, the lessee will

    approach the concerned author

    Place : Bharatpur SHAH SURENDER

    Date (NOMINETED OWNER SHRI SHAH SURENDER)

  • SHRI SHAH KASTOORMAL NOMINETED OWNER SHRI SHAH SURENDER

    R/o: Kalyan Bhawan, Shah building, S.M.S. Highway (Chaura Rasta)

    District: Jaipur (Raj), Pin Code - 302002

    DECLARATION

    1. The Modified Mining Plan with Progressive Mine Closure Plan for Bas Bhandari Soapstone

    Mine M. L. No. 04/84, over an area of 4.98Hect. (Forest Diversion Land) for mineral Soapstone

    in Village- Morara, Tehsil- Toda Bhim, District- Karauli, State- Rajasthan of Bas Bhandari

    Soapstone Mine has been prepared in full consultation with me and I understand its contents

    and agree to implement the same in accordance with law and in case of default the approval

    would be withdrawn.

    2. It is further declared that during the pendency period of the approval of above said document

    or thereafter if any change occurs in the name and address of lessee, it will be informed

    promptly.

    Place : Bharatpur SHAH SURENDER

    Date (NOMINETED OWNER SHRI SHAH SURENDER)

  • SHRI SHAH KASTOORMAL NOMINETED OWNER SHRI SHAH SURENDER

    R/o: Kalyan Bhawan, Shah building, S.M.S. Highway (Chaura Rasta)

    District: Jaipur (Raj), Pin Code - 302002

    UNDERTAKING

    1. I, Shah Kastoormal, Lessee for Bas Bhandari Soapstone Mine M. L. No. 04/84, over an area of

    4.98Hect. (Forest Diversion Land) for mineral Soapstone in Village- Morara, Tehsil- Toda

    Bhim, District- Karauli, State- Rajasthan of Bas Bhandari Soapstone Mine hereby undertake

    that all the commitments so made in the aforesaid Modified Mining Plan with Progressive

    Mine Closure Plan by the RQP Arun Kumar Yadav to be deemed to have been made with my

    knowledge and consent and as such shall be acceptable to me and binding on me in all

    respects.

    2. I, Shah Kastoormal, Lessee for Bas Bhandari Soapstone Mine M. L. No. 04/84, over an area of

    4.98Hect. (Forest Diversion Land) for mineral Soapstone in Village- Morara, Tehsil- Toda

    Bhim, District- Karauli, State- Rajasthan of Bas Bhandari Soapstone Mine hereby also

    undertake that all the measures proposed in this Modified Mining Plan with Progressive Mine

    Closure Plan will be implemented in a time bound manner from the date of approval of this

    Modified Mining Plan with Progressive Mine Closure Plan as proposed.

    Place : Bharatpur SHAH SURENDER

    Date (NOMINETED OWNER SHRI SHAH SURENDER)

  • CONTENTS

    CHAPTER TITLE PAGE NO.

    1 General

    2 Location Accessibility

    3 Details of Approved Mining Plan

    4 Geology & Exploration

    5 Mining

    6 Stacking of Mineral Reject/ Sub grade material and disposal

    of waste

    7 Use of Mineral

    8 Mineral Beneficiation

    9 Environment Management Plan

    10 Other

    11 Progressive Mine Closure Plan

  • LIST OF ANNEXURES

    S. No. Particulars Annexure

    No.

    1. Lease Deed 1

    2. Pollution Consent 2

    3. Environment Clearance 3

    4. Renewal Receipt 4

    5 Approval Letters 5

    6 Forest Diversion Letter 6

    7 Aravalli Certificate & Demarcation 7

    8 Photo ID 8

    9 Photograph of Pit 9

    10 Photograph of Plantation 10

    11 Analysis Report 11

    12 Feasibility Report 12

    13 R.Q.P Certificate 13

  • LIST OF PLATES

    S. No. Particulars Plate Number

    1 Location Plan 1

    2 Key Plan 2

    3 Route Plan 3

    4 Surface plan 4

    5 Surface Geological plan & Sections 5

    6 Year wise development Plan & Section 6

    7 Mine Layout Plan 7

    8 Proposed Arrangement Surface & waste Rock Storage 8 – 8(I)

    9 Environment Management Plan 9

    10 Conceptual Plan 10

    11 Progressive Mine Closure Plan & Section 11

    12 Drill hole Pattern in Development Ends Plan 12

    13 Year Wise Underground Development Plan 13

  • INTRODUCTION

    The Modified Mining Plan with Progressive Mine Closure Plan of bas Bhandari

    Soapstone mine, M. L. No. 04/84 area 4.98ha.( Forest Diversion Land) of Mineral –

    Soapstone, Near Village – Morara, Tehsil – Toda Bhim, and District – Karauli

    (Rajasthan) has been prepared on behalf of Shri Shah Surendra Kumar, sole

    proprietor Shri Shah Kastoormal, Shah Building, S.M.S. Highway, Chaura Rasta,

    Jaipur (Raj.).

    The mining lease was granted on date 21/04/1965 for mineral soapstone in favor of

    Shri Shah Kastoormal R/o Shah Building, S.M.S. Highway, Chaura Rasta, Jaipur

    (Raj.). on registered date 28/07/1965 for 20 years M. L. No. 03/96(O) area 84.76ha.

    of Mineral –Soapstone, Near Village – Morara, Tehsil – Toda Bhim, and District –

    Karauli (Rajasthan). The first renewal of mining lease was vide Letter No. 21170/MM-

    2/84 dated 17/07/1989 for 21/04/85 for 10 years area 84.76ha. of Mineral –

    Soapstone, Near Village – Morara, Tehsil – Toda Bhim, and District – Karauli

    (Rajasthan). The application for second renewal of mining lease was submitted

    Department of Mines & Geology on dated 13/04/1994 for next 20 years area

    84.76ha. of Mineral –Soapstone, Near Village – Morara, Tehsil – Toda Bhim, and

    District – Karauli (Rajasthan).

    The Mining lease period has been extended upto 31/03/2020 due to amendment in

    M.M.D.R. Act by an ordinance in 2015, vide letter no.- ME/Karauli/RP/ML-04/84/110

    on dt.22/06/2015.

    The mine is in working scice 21/04/1965 and there are two working pits in the area,

    which establisk the existence of mineralization in the area. The mining Plan of bas

    bhandari soapstone M.L. No.-04/84 area 04.98ha. was approved under rule 24 of

    MCR 1960 vide RCOM, I.B.M., Ajmer, letter no.- 584(4)(3)947/06 RCM-AJM

    dt.20/11/2012.

    The lease area is in forest land for which diversification has been obtained vide letter

    no.-8B/05/1366/97/FC/191 dt. 19/11/2001.

    Consent to operate has been obtained from RSPCB, Bharatpur vide letter no.-

    F(Mines)/Karoli(Todabhim)/7(1)/2011-12/2505-07 dt. 08/09/2015, staing the project

    does not fall in Aravalli hills.

    A Certificate has been obtained from the Office of Mining Engineer, DGM, Karauli vide

    letter no.- ME/Karauli/RP/ML-04/84/206 on dt.22/06/2015.

    The latest Scheme of Mining with Progressive Mine Closure Plan of Bas Bhandari

    soapstone M.L. No.-04/84 area 04.98ha. was approved under rule 12 & 23(B) of

  • MMCR 1986 vide letter no.- 101-106 SME/Bharat-Cr./Mining Plan/Scheme/FMCPF(96)

    dt.24/05/2016.

    This Modified Mining Plan with Progressive Mine Closure Plan has been prepared

    under Rule 29 Of RMMCR, 2017, and proposed production has 54235MT for the

    mineral Soapstone over an area of 4.98 Ha in Near Village – Morara, Tehsil – Toda

    Bhim, and District – Karauli (Rajasthan), for the period 2016-17 to 2020-21 .

  • CHAPTER – 1

    1.0 GENERAL a) Name and address of Lease holder: (Refer Annexure No. 1)

    Shri Shah Surendra Kumar, sole proprietor Shri Shah Kastoormal

    Address : Kalyan Bhawan, Shah Building, S.M.S. Highway,

    Chaura Rasta

    Tehsil : Jaipur,

    District : Jaipur

    State : Rajasthan,

    Pin code : 302002

    Fax : Nil

    Mobile No. : +91-9414065224

    Telephone No. : +91-141-2568774

    Email id. : [email protected]

    b) Status of Lease holder: (Refer Annexure No. 2)

    Lessee is a Individual. The details of the given below: -

    1) Shri Shah Surendra Kumar, sole proprietor Shri Shah Kastoormal, R/o

    Kalyan Bhawan, Shah Building, S.M.S. Highway, Chaura Rasta, Distt.

    Jaipur (Raj.)

    (c) Minerals which Lease holder intends to mine:

    Lessee is intended to mine Soapstone

    (d) Recognized Person (under rule 22C of MCR, 1960 or a Person employed under

    clause (c) of Sub rule (1) of rule 42 of MCDR, 1988) preparing Mining Plan

    Name : Arun Kumar Yadav (Refer Annexure No. 3)

    Address : 501, 5th Floor, Apex Tower,

    Tonk Road, Jaipur-302015

    Telefax : 0141-2744509(O),

    Mobile No. +91-9460221084

    E-mail : [email protected]

    Registration No. : RQP /AJM / 242 /2003 / A

    Date of Grant/ Renewal : 21st May 2003/21st May 2013

    Valid upto : 21st May 2023

  • CHAPTER – 2

    2.0 LOCATION AND ACCESSIBILITY

    a) Lease Details (Existing Mine) Name of Mine : Bas bhandari Soapstone Mine (M.L. No.-04/84)

    Lat/long of any

    boundary point

    : Block No.- 1 Pillar Latitude (N) Longitude (E)

    J 26048'42.13'' 76048'15.96''

    E 26048'42.01'' 76048'25.73''

    C 26048'46.13'' 76048'26.1''

    C1 26048'46.58'' 76048'28.43''

    C2 26048'47.92'' 76048'31.71''

    C3 26048'50.15'' 76048'30.9''

    C4 26048'47.68'' 76048'27''

    C5 26048'47.45'' 76048'25.99''

    C 26048'46.13'' 76048'26.1''

    Block No.- 2

    Pillar Latitude (N) Longitude (E)

    J 26048'42.13'' 76048'15.96''

    K 26048'42.01'' 76048'16.03''

    B1 26048'46.65'' 76048'12.36''

    B2 26048'51.59'' 76048'10.55''

    B3 26048'53.94'' 76048'18.08''

    R 26048'19.62'' 76048'19.62''

    R1 26048'17.23'' 76048'17.23''

    R2 26048'16.57'' 76048'16.57''

    K 26048'16.03'' 76048'16.03''

    FRP (Temple) Latitude (N) - 26048'37.26''

    Longitude (E) - 76048'15.88''

    Date of grant of lease : 21/04/1965

    Name of lease holder : Shri Shah Surendra Kumar, sole proprietor Shri Shah

    Kastoormal

    Postal Address : R/o Kalyan Bhawan, Shah Building, S.M.S. Highway, Chaura Rasta, District: Jaipur (Raj)

    Email ID : [email protected]

    Mobile No. : +91-9414065224

    b) Details of applied /lease area with location map (fresh area /mine)

    Khasra no.-23,489,839

  • Table No.-1 Status of land

    Forest Non Forest

    Forest (specify) Area

    (ha)

    Waste

    /grazing/agriculture/other land

    Area (ha)

    Forest Diversion Land 4.98 -- --

    Total 4.98

    Total lease area : 04.98 Hectare (Forest Diversion Land)

    District & State : Karauli, Rajasthan

    Tehsil : Toda Bhim

    Village : Morara

    Whether the area falls under

    Coastal Regulation Zone

    (CRZ)

    : No

    Existence of public

    road/railway line, if any

    nearby and approximate

    distance

    :

    The Lease area is located about 0.45 km

    S direction of village Bas Bhandari, M.D.R

    63 is at a distance of 13.9 km E

    direction. S.H 22 is about 19.3 km W

    direction.

    NH/ SH : M.D.R 63 is at a distance of 13.9 km E

    direction. S.H 22 is about 19.3 km W

    direction.

    Railway Station : Nearest railway station is Hindaun city

    which is at a distance of 23.50 kms from

    the mine site in E direction From the

    lease area.

    Medical Facility : Nearest Balghat, Hindaun is about

    23.63km(ENE), 22km(E).

    Educational Facility : The Primary school is about 0.5 kms and

    collage facility is at Balghat, Hindaun

    which is about 23.63km from lease area.

    Toposheet No. with latitude &

    longitude of all corner

    boundary point/pillar

    : 54B/13

    FRP (Temple) Latitude (N) -26048'37.26''

    Longitude (E) -76048'15.88''

    Block No.- 1

    Pillar Latitude (N) Longitude (E)

    J 26048'42.13'' 76048'15.96''

    E 26048'42.01'' 76048'25.73''

    C 26048'46.13'' 76048'26.1''

    C1 26048'46.58'' 76048'28.43''

    C2 26048'47.92'' 76048'31.71''

  • C3 26048'50.15'' 76048'30.9''

    C4 26048'47.68'' 76048'27''

    C5 26048'47.45'' 76048'25.99''

    C 26048'46.13'' 76048'26.1''

    Block No.- 2

    Pillar Latitude (N) Longitude (E)

    J 26048'42.13'' 76048'15.96''

    K 26048'42.01'' 76048'16.03''

    B1 26048'46.65'' 76048'12.36''

    B2 26048'51.59'' 76048'10.55''

    B3 26048'53.94'' 76048'18.08''

    R 26048'19.62'' 76048'19.62''

    R1 26048'17.23'' 76048'17.23''

    R2 26048'16.57'' 76048'16.57''

    K 26048'16.03'' 76048'16.03''

    c) Attach a general location map showing area and access routes: Refer Plate

    No.1 (d) Site Plan & Demarcation report of lease area are enclosed as Annexure No. 5,

    6 & 7 respectively

  • CHAPTER – 3

    3.0 DETAILS OF APPROVED MINING PLAN

    3.1 Date and reference of earlier approved mining plan

    The mine is in working since 21/04/1965 and there are two working pits in the area,

    which establish the existence of mineralization in the area. The mining Plan of Bas

    Bhandari soapstone M.L. No.-04/84 area 04.98ha. was approved under rule 24 of

    MCR 1960 vide RCOM, I.B.M., Ajmer, letter no.- 584(4)(3)947/06 RCM-AJM

    dt.20/11/2012.Mining operations were started since September 25th 1992 & Mining

    lease executed on 12/08/1992 to twenty years 11/08/2012.

    The latest Scheme of Mining with Progressive Mine Closure Plan of Bas Bhandari

    soapstone M.L. No.-04/84 area 04.98ha. was approved under rule 12 & 23(B) of

    MMCR 1986 vide letter no.- 101-106 SME/Bharat-Cr./Mining

    Plan/Scheme/FMCPF(96) dt.24/05/2016.

    Sr. No. Type of document &

    rule under

    Approval letter no & date Lease area

    in ha.

    Proposal

    from to

    1 Mining Plan under rule

    24 of MCR 1960

    584(4)(3)(179)/94RCM-AJM

    MCCM(N)UDP dated

    29/03/1995

    7.64 ha. 1998-99 to

    2002-03

    2 Mining Plan under rule

    24 of MCR 1960

    584(4)(3)(947)/06RCM-AJM

    MCCM(N)UDP dated

    20/11/2006

    4.98 ha. 2006-07 to

    2010-11

    3 Scheme of Mining

    with PMCP rule 12 &

    23(B) MCDR 1988

    SME/BHARAT/Minig

    Plan/Mejor/Karauli/M.l./3/9

    4/509 dated 04/12/2015

    4.98 ha. 2014-15

    4 Scheme of Mining

    with PMCP rule 12 &

    23(B) MCDR 1988

    amendment 2012

    101-106 SME/Bharat-

    Cr./Mining

    Plan/Scheme/FMCPF(96)

    dt.24/05/2016

    4.98 ha. 2016-17 to

    2020-21

    3.2

    Details of last modifications if any

    NA

    This Modified Mining Plan with Progressive Mine Closure Plan has been prepared

    under Rule 29 Of RMMCR, 2017, for the mineral Soapstone over an area of 4.98 Ha

  • in Near Village – Morara, Tehsil – Toda Bhim, and District – Karauli (Rajasthan), for

    the period 2016-17 to 2020-21 .

    3.3 Give review of earlier approved proposals (if any) in respect of exploration,

    excavation and reclamation etc.

    (i) Exploration-

    Proposal given in approved

    Mining Plan

    Compliance

    Five trenches were proposed in

    approved mining plan period.

    Two trenches is dug in last

    five years.

    (ii) Mine development work-

    Proposal given in

    approved Mining Plan Compliance

    Mining operation was

    proposed by formation of

    the bench of 3.0m height

    and width in opencast

    method.

    Mining operation was also

    proposed by underground

    mining method.

    Mining operation was carried

    out by formation of bench of

    3.0m height and width at

    the proposed site.

    Development in

    underground is undergone

    but it was collapsed.

    (iii) Exploitation

    Proposal given in

    approved Mining Plan

    Compliance

    Year Production in MT

    2008-09 1300 + 2851

    2009-10 1782 + 2592

    2010-11 1782 + 3694

    2011-12 1782 + 5249

    2012-13 1782 + 4558

    Year Production in MT

    2008-09 1336

    2009-10 2245

    2010-11 810

    2011-12 2490

    2012-13 5810

    2013-14 3570

    2014-15 1510

    IV) Waste Management:

    Proposal given in approved

    Mining Plan Compliance

    The waste/Mineral reject is as per

    approved mining plan. The waste

    There are no waste/mineral

    reject is produced during

  • will be dumped at the dump yard

    as shown in layout plan.

    Year Waste in MT

    2008-09 325 + 317

    2009-10 445 + 288

    2010-11 445 + 1274

    2011-12 445 + 1447

    2012-13 445 + 1658

    past five year of plan period.

    The waste is dumped at

    proposed site.

    Year Waste in MT

    2008-09 2540

    2009-10 3050

    2010-11 5400

    2011-12 6050

    2012-13 6420

    2013-14 7120

    2014-15 2040

    V) Afforestation:

    Proposal given in approved

    Mining Plan Compliance

    20 Saplings each year will be

    proposed in the mining plan.

    About 100 saplings are

    planted near the road sides

    and statutory barrier. About

    60 trees are alive at present.

    VI) Sub grade mineral Management:

    Proposal given in approved

    Mining Plan Compliance

    Subgrade mineral is not produced

    during the proposed plan period.

    Subgrade mineral is not

    produced during the

    proposed plan period,

    therefore no staking of

    subgrade is required.

    VII) Reclamation & Rehabilitation:

    Proposal given in approved

    Mining Plan Compliance

    As Soapstone is still exposed at

    the pit bottom hence mining of

    mineral is continue & no

    reclamation & rehabilitation work

    was proposed.

    There is no work was

    undertaken for reclamation

    of mine & work was not

    carried out for rehabilitation.

    VIII) Fly rock Management:

    Proposal given in approved

    Mining Plan Compliance

  • Controlled blasting with short hole

    (32mm dia) will proposed.

    All necessary precautions

    are being taken as per

    regulation 164 of MMR 1961

    IX) Air Quality Management:

    Proposal given in approved

    Mining Plan Compliance

    Water sprinkling on haul road will

    proposed.

    Water sprinkling on haul

    road is continue. The air

    monitoring is done in every

    six month, found that the air

    is free from pollution. The

    report is annexed.

    X) Noise & Ground Vibration:

    Proposal given in approved

    Mining Plan Compliance

    No proposals were made. The monitoring is done in

    every six month found that

    the noise is below the

    standard of RPCB. The

    report is annexed.

    XI) Treatment of water:

    Proposal given in approved

    Mining Plan Compliance

    No proposals were made. Not required.

    XII) Any other significant features:

    Proposal given in approved

    Mining Plan Compliance

    Nil Nil

    3.4Status of compliance of violations pointed out by IBM

    S. No. Inspection & Violation Letter

    no.

    Violation

  • 1. The mine was inspected by Shri

    Harkesh Meena, DCoM, IBM, Ajmer

    on 11/06/2009 the violation

    pointed out and rectification are

    as- Rule 13 (1) the mining is not

    done as proposed in AMP.

    The justification is given

    letter no.-SKM/J/2009-

    10/70 date 31/01/2009

    The copy of violation letter is enclosed as Annexure – 10.

    3.5 Details of any suspension /closure/ prohibitory order issued by any

    government agency under any rule or court of law

    There is not any suspension / closure/ prohibitory order issued by any govt. agency

    under any rule or court of law.

    3.6 In case the MP/SOM is submitted under rules 9 and 10 of the MCDR’88 or

    under rule 22(6) of MCR’1960 for approval of modification, specify reasons

    and justification for modification, under these rules.

    NA

  • PART-A

    CHAPTER-4

    4.1GEOLOGY AND EXPLORATION:

    a) Briefly describe the topography, drainage pattern, vegetation, climate,

    and rainfall data of the area applied/mining lease area.

    Topography:

    Topographically the M.L area is hilly terrain, having highest altitude is 350

    mRL and lowest altitude is 278 mRL. The general trend of ridge is NE-SW dip

    is 65°-70°.

    Drainage Pattern:

    The drainage of this area is followed by seasonal nalah flowing across from

    North-East to South-West side of the M.L. area.

    Vegetation:

    The area bears scantly vegetation. Shurbs of Zizyphus Jujuba (Bear),

    Azatirchta indica (Nim), Maganiferous indica (Mango), Tamaradus indica

    (Tamarind), Ficus religiosa(Pipal), Dhok (Buteafrondosa) are seen around the

    villages. The protected forests consist of moderately dense creepers and

    grassy undergrowth.

    Climate & Rainfall:

    The area is characterized by semi-arid type with an average annual rainfall

    about 660 mm. which is mainly, received during June to September.

    Minimum Temp - Varies from 1.0º to 15ºC

    Maximum Temp - Varies from 25º to 45ºC

    b) Brief descriptions of Regional Geology with reference to location of

    lease/applied area Regional Geology Regional Geology

    Geologically mapping of the lease area was done with GPS surveying. The

    generalized geological sequence as observed in the field can summarized as-

    The geological sequence worked out by G.S.I. is given as under: -

    Table 4.1 Stratigraphic succession

    Era/

    Period

    System series Lithology

    Quaternary Recent and sub-

    recent

    - Alluvium, and sand

    Upper

    Proterozoic

    Vindhyan Super

    group

    Bhander Group Sandstone and Limestone

    Rewa Group Shale, Sandstone

  • Kaimur Group Sandstone and Conglomerate

    Semri Group Shale, Sandstone and Limestone

    Proterozoic Delhi Super

    Group

    Alwar Group Quartzite and Conglomerate

    schist

    Pre Aravalli

    Group

    schist, gneiss and migmatites,

    Phyllite, marble, Quartzite

    Igneous activity/Intrusive Dolerite dykes and sills

    c) Local Geology:

    The rock of the area as-

    Recent --- --- Alluvium Soil

    Quartzite, Talc, Chlorite

    schist

    d) (i) Name of exploration agency : Bas Bhandari Soapstone Mine (M.L. No.-

    04/84)

    (ii) Address: Kalyan Bhawan, Shah Building, S.M.S. Highway, Chaura Rasta,

    District: Jaipur, State: Rajasthan, Pin code: 302002

    (iii) E mail address: [email protected] and Mobile No. :

    9414065224

    The lease holder is itself responsible for appointing the exploration agency &

    the exploration done by them.

    e) Details of exploration carried out :

    The minerals Soapstone exposed in two pits up to the considerable depth in

    the M. L. area. Soapstone is found exposed in the depth in the area.

    No. of existing Mining Pits: two

    Dimensions of Pit:

    Pit : Length – 44 m, Width - 25m and Depth – 11 m

    Length – 44 m, Width - 25m and Depth – 11 m

    Details of samples analysis indicating type of sample (surface/sub-

    surface from pits/trenches/borehole etc.) Complete chemical analysis

    for entire strata for all radicals may be undertaken for selected

    samples from laboratory or equivalent. Entire mineralized area may be

    analyzed meter wise with 10% of check samples. (At least for 10% of

    total samples may be analyzed in accordance to BIS and reports from

    laboratory).

    Sample analysis has been undertaken for selected samples from Laboratory

    and the results are enclosed as annexure.

    Table No.- 4.2: Result of Chemical analysis of Mineral

    Soapstone

    Parameters A(% by weight) B(% by weight)

    Si02 45.40 48.00

  • Al203 35.90 33.10

    Fe2o3 2.00 2.00

    Tio2 0.60 0.60

    Cao 3.00 2.80

    Mgo 0.20 0.20

    Na2o 0.30 0.20

    K20 0.30 0.10

    LOI 12.54 14.70

    The location of the sample is from Pit 1.

    f) The surface plan of the lease area may be prepared on a scale of 1:

    1000

    or 1: 2000 with contour interval of maximum of 10 m depending upon

    the

    topography and size of the area duly marked by grid lines showing all

    Features indicated under Rule 28(1) (a) of MCDR 1988.

    The surface plan of the lease area may be prepared on a scale of 1: 2000 with

    contour

    interval of 5 m Refer Plate No.3

    g) Mineral Reserve: -

    Method of estimation of reserve

    Considering the exposures of Soap Stone at place following points are taken for

    reserve estimation.

    Classification code Total

    Reserves

    in MT

    Insecticid

    e Grade in

    MT

    Paper

    Grade

    in MT

    Talc

    Grade

    in MT

    (1) (2) (3) (4) (5) (6)

    Total Mineral resources (A+B)

    A. Mineral reserve

    (1)Proved Mineral reserve

    (2) Probable Mineral reserve

    B. Remaining resource

    (1) Feasibility Mineral reserve #

    (2) Prefeasibility Mineral reserve

    (3) Measured Mineral reserve

    (4) Indicated Mineral reserve

    (5) Inferred Mineral reserve

    (6) Reconnaissance Mineral

    reserve

    111

    121 & 122

    211

    221 & 222

    331

    332

    333

    334

    5,32,704

    2,44,480

    ----------

    ---------

    1,12,494

    ---------

    ---------

    1,75,770

    ---------

    2,66,352

    1,22,220

    -----------

    ---------

    56,247

    ---------

    ---------

    87,885

    ---------

    1,06,54

    1

    48,888

    --------

    ---------

    22,499

    ---------

    ---------

    35,154

    ---------

    1,59,81

    1

    73,332

    --------

    ---------

    33,748

    ---------

    ---------

    52,731

    ---------

  • Reference- The approved mining plan of Bas Bhandari Soapstone Mine (M.L. No.-

    04/84) vide RCOM, I.B.M., Ajmer, letter no.- 584(4)(3)947/06 RCM-AJM

    MCCM(N)UDP dt.20/11/2006.

    h) Reserve Estimation and Categorization of Reserves

    The reserves estimated for the area have been categorized under proved, probable

    and possible categories depending upon the degree of certainty.

    Geological reserves as calculated are 523743MT. Mineral reserve is estimated up-to

    demonstrated reserve i.e. proved and probable reserve. None of the part, of

    delineated mineralized zone is falling in close proximity of applied area boundary;

    therefore there shall be no blockage of mineral within statutory barrier.

    Mineable reserve in retained area will be 215040MT in Soapstone. The Mine

    development at the production rate of 55000MT/annum. Therefore life of mine is

    expected to be 5 years.

    Reserves: -

    Classification code Total

    Reserves

    in MT

    Insecticid

    e Grade in

    MT

    Paper

    Grade

    in MT

    Talc

    Grade

    in MT

    (1) (2) (3) (4) (5) (6)

    Total Mineral resources (A+B)

    A. Mineral reserve

    (1)Proved Mineral reserve

    (2) Probable Mineral reserve

    B. Remaining resource

    (1) Feasibility Mineral reserve

    #

    (2) Prefeasibility Mineral

    reserve

    (3) Measured Mineral reserve

    (4) Indicated Mineral reserve

    (5) Inferred Mineral reserve

    (6) Reconnaissance Mineral

    reserve

    111

    121 & 122

    211

    221 & 222

    331

    332

    333

    334

    5,32,704

    2,44,480

    ----------

    ---------

    1,12,494

    ---------

    ---------

    1,75,770

    ---------

    2,66,352

    1,22,220

    -----------

    ---------

    56,247

    ---------

    ---------

    87,885

    ---------

    1,06,5

    41

    48,888

    --------

    --------

    -

    22,499

    --------

    -

    --------

    -

    35,154

    --------

    -

    1,59,81

    1

    73,332

    --------

    --------

    -

    33,748

    --------

    -

    --------

    -

    52,731

    --------

    -

  • i) Waste Rock Generated

    Overburden

    Top soil of 1 m. depth mixed with scree is present in M. L area Which will be removed before

    stacked separately in statutory barrier. Total volume of top soil will be removed is 11189 m3

    stacked and stacked at a height of 3m and this will acquire an area of 0.3729ha. In statutory

    barrier will be will be used for plantation within the year of commencement of mining

    activity. The total mineral reject during one years will be 6667 m3 which will stacked at a

    height of 5m covering an area of 0.13334hect inside the lease area.

    UNFC Classification

    Details of UNFC classification

    UNFC is a three digit code based system, the economic viability axis

    representing the first digit, the feasibility axis the second digit and the

    geological axis the third digit. Each digit provided Codes 1, 2 and 3 in

    decreasing order. The highest category of resources under UNFC system has

    code (111) and for lowest category the code is (334).

    Code (111): This code is provided for the economically mineable part of the

    measured mineral resources (proved category reserves).

    Code (121): This code is provided for the economically mineable part of the

    indicated mineral resources (probable category reserves).

    Code (211): The part of the measured mineral resources (proved category),

    which as per feasibility study has not found economically mineable. The

    reserves blocked in 7.5 meters buffer zone and 45 meters from permanent

    structure.

    Code (222): The part of the indicated mineral resources (probable category),

    which as per feasibility study has not found economically mineable. The

    reserves blocked in 7.5 meters buffer zone and 45 meters from permanent

    structure.

    Code (333): Tonnage, Grade and mineral contents can be estimated with low

    level of 263confidence and resources are also inferred from geological

    reserves.

  • Table 4.3 - The mineral reserves are computed as per UNFC. The

    reserves are as follows:

    Classification code Total Reserves in MT

    (1) (2) (3)

    Total Mineral resources (A+B)

    A. Mineral reserve

    (1)Proved Mineral reserve

    (2) Probable Mineral reserve

    B. Remaining resource

    (1) Feasibility Mineral reserve #

    (2) Prefeasibility Mineral reserve

    (3) Measured Mineral reserve

    (4) Indicated Mineral reserve

    (5) Inferred Mineral reserve

    (6) Reconnaissance Mineral

    reserve

    111

    121 & 122

    211

    221 & 222

    331

    332

    333

    334

    5,32,704

    2,44,480

    ----------

    ---------

    1,12,494

    ---------

    ---------

    1,75,770

    ---------

    Life of Mine

    The proposed annual production is 54235Tonne.

    So Life of mine = Total mineable reserves/ Annual Production

    = 215040/ 54235

    =3.964years

    = Say 4 Years

  • 5.0 MINING

    A. OPEN CAST MINING:

    a)Briefly describe the existing as well as proposed method for excavation with all

    design parameters indicating on plans /sections

    5.1 Present Method of Mining:

    It is a working lease. The mining of Soap-Stone being carried out since

    1965.At present, there is no mining activity is going on because the lessee

    was busy in some other work.

    5.2 Proposed method of mining: -

    The proposed method of mining is open-cast and Underground mechanized

    method.

    (1) Formation of benches: Existing open pit side benches will be dressed,

    loose from top of the pit will be removed and top of the pit will be

    fenced off with masonry wall.

    (2) Preparatory work: Incline at 300mRL will be cleared off and

    supported of a distance of nearly 10m with concrete arches. And old

    underground working will be abandoned with the help of RCC wall.

    (3) Creation of wall: A water tank of nearly 2000lt. capacity will be

    constructed in cement concrete on 337mRL bench near the mouth of

    proposed incline shaft S-2, the position marked on layout plan.

    (4) Surface drainage: Garlands for drainage of rain water will be made at

    350, 360 & 370mRL contours 2m. high retaining wall is proposed at

    240mRL along the hill slope to divert overflow water from garlands into

    the nalla.

    5.3 Year wise Development for the first five years :-

    Underground development- Year wise development has shown the Plate No. 5

    and Mine entry will be through incline shaft S1& S2. These shafts shape have

    rectangular longer side shaft 4m will be along strike of the ore body and sorter side

    2m will be across the strike direction. Shafts will be sunk on soapstone vein V1,

    keeping the hanging wall quartzite rock exposed on the roof side. Shafts S1 & S2

    distance located between 50m. Inclination of these shaft will be 70 degree NW.

    Shaft reaches at 274 MRL, drive at 274 MRL (30m depth from the shaft collar) will

    be started from S1, towards S2. The drive at 274 MRL towards NW direction will be

  • started from S2, size of these drive will be 2m *2m. the shaft deepening will

    continue. When shaft reaches at 242 MRL , 242 MRL drive is develop to join the S1

    and S2. The drive at 274 MRL towards NW direction will be started from S2.

    Similarly when drives at 274 MRL reach at distance 25m winze from 274 MRL will

    start. Development in the mine will continue in this way N1 & N2 series of winzes

    274 MRL will be dipping at 70 degree. Winzes from 274 , 242, 210, 178 and 146

    MRL will be developed.

    First Year Development :-

    (1) The shaft S1 will be clean and remove the waste from the shaft. Incline shaft

    S1 will be depend up to 274 MRL (on incline plane) from 295 MRL along

    Soapstone vein. The ore excavated during developing in the incline shaft.

    =size of shaft *length of shaft * sp. Gravity

    =4×2×155×2.7=3348MT

    (2) Incline shaft S2 will be sunk from 312 MRL up to 274 MRL (on incline plane)

    from 295 MRL along Soapstone vein. The ore excavated during developing in

    the incline shaft.

    =size of shaft *length of shaft * sp. Gravity

    =4×2×240×2.7=5184MT

    (3) Drive having dimensions 2m *2m will be developed of length 70 m ore

    excavated during developing the drive.

    =size of shaft *length of shaft * sp. Gravity

    =4×2×296×2.7=3196.8MT

    Total ore excavated during first year= 3348 +5184 +3196.8=11728.8MT

    Second Year Development :-

    (1) The shaft S1 will be deepened up to 242 MRL (on incline plane) from 274

    MRL along Soapstone vein. The ore excavated during developing in the

    incline shaft.

    =size of shaft *length of shaft * sp. Gravity

    =4×2×192×2.7=4147.2MT

    (2) Incline shaft S2 will be sunk from 274 MRL up to 242 MRL (on incline plane)

  • along Soapstone vein. The ore excavated during developing in the incline

    shaft.

    =size of shaft *length of shaft * sp. gravity

    =4×2×192×2.7=4147.2MT

    (3) Drive having dimensions 2m *2m will be developed of length 70 m at 242

    MRL ore excavated during developing the drive.

    =size of shaft *length of shaft * sp. Gravity

    =4×2×361×2.7=3898.8MT

    (4) The winze N1 and N2 will develop in the center of S1 and S2 and in the NW

    of the shaft S2. Ore excavated during developing the winzes.

    =size of shaft *length of shaft * sp. Gravity

    =4×2×183×2.7=1976.4MT

    Total ore excavated during first year=

    4147.2+4147.2+3898.8+1976.4=14169.6MT

    Third Year Development :-

    (1) The shaft S1 will be deepened up to 210 MRL (on incline plane) from 242

    MRL along Soapstone vein. The ore excavated during developing in the

    incline shaft.

    size of shaft *length of shaft * sp. Gravity

    =4×2×192×2.7=4147.2MT

    (2) Incline shaft S2 will be sunk from 242 MRL up to 210 MRL (on incline plane)

    along Soapstone vein. The ore excavated during developing in the incline

    shaft.

    =size of shaft *length of shaft * sp. gravity

    =4×2×192×2.7=4147.2MT

    (3) Drive having dimensions 2m *2m will be developed of length 70 m at 242

    MRL ore excavated during developing the drive.

    =size of shaft *length of shaft * sp. Gravity

    =4×2×361×2.7=3898.8MT

  • (4) The winze N1 and N2 will develop in the center of S1 and S2 and in the NW

    of the shaft S2. Ore excavated during developing the winzes.

    =size of shaft *length of shaft * sp. Gravity

    =4×2×183×2.7=1976.4MT

    Total ore excavated during first year=

    4147.2+4147.2+3898.8+1976.4=14169.6MT

    Fourth Year Development :-

    (1) The shaft S1 will be deepened up to 178 MRL (on incline plane) from

    210 MRL along Soapstone vein. The ore excavated during developing in the

    incline shaft.

    = size of shaft *length of shaft * sp. Gravity

    =4×2×192×2.7=4147.2MT

    (2) Incline shaft S2 will be sunk from 210 MRL up to 178 MRL (on incline plane)

    along Soapstone vein. The ore excavated during developing in the incline

    shaft.

    =size of shaft *length of shaft * sp. gravity

    =4×2×192×2.7=4147.2MT

    (3) Drive having dimensions 2m *2m will be developed of length 70 m at 178

    MRL ore excavated during developing the drive.

    =size of shaft *length of shaft * sp. Gravity

    =4×2×361×2.7=3898.8MT

    (4) The winze N1 and N2 will develop in the center of S1 and S2 and in the NW

    of the shaft S2. Ore excavated during developing the winzes.

    =size of shaft *length of shaft * sp. Gravity

    =4×2×183×2.7=1976.4MT

    Total ore excavated during first year=

    4147.2+4147.2+3898.8+1976.4=14169.6MT

    Fifth Year Development :-

    (1) The shaft S1 will be deepened up to 146 MRL (on incline plane) from

  • 178 MRL along Soapstone vein. The ore excavated during developing in the

    incline shaft.

    =size of shaft *length of shaft * sp. gravity

    =4×2×192×2.7=4147.2MT

    (2) Incline shaft S2 will be sunk from 178 MRL up to 146 MRL (on incline

    plane) along Soapstone vein. The ore excavated during developing in the

    incline shaft.

    =size of shaft *length of shaft * sp. gravity

    =4×2×192×2.7=4147.2MT

    (3) Drive having dimensions 2m *2m will be developed of length 70 m at 146

    MRL ore excavated during developing the drive.

    =size of shaft *length of shaft * sp. Gravity

    =4×2×361×2.7=3898.8MT

    (4) The winze N1 and N2 will develop in the center of S1 and S2 and in the NW

    of the shaft S2. Ore excavated during developing the winzes.

    =size of shaft *length of shaft * sp. Gravity

    =4×2×183×2.7=1976.4MT

    Total ore excavated during first year=

    4147.2+4147.2+3898.8+1976.4=14169.6MT

    5.3. 1 Open Cast development :-

    In the SE part of the pit massive deposit of DDT grade soapstone is available

    therefore open cast mining will be proposed the benches of 3m height will be

    proposed having width will be more than height of the benches.

    First Year Development :-

    The 1239 sq. meter pit will be dug up to 31m deep to produce soapstone the

    benches of 6m at 313 MRL 271 MRL will be prepared.

    ROM excavation = 1239×31Cum.=38409×2.7=103704.3MT

    Soapstone Recovery=103704.3×0.4=41481.72MT

    Waste / Reject of mineral =103704.3×0.6=62222.58MT

  • Second Year Development :-

    The pit will be extent in length and width (1235 sq. m.) to produce soapstone.

    The benches of 6m at 313 MRL to 271 MRL will be prepared.

    ROM excavation = 1235×31(average)Cum.=38285×2.7=103369.5 MT

    Soapstone Recovery=103369.5 ×0.4=41347.8 MT

    Waste / Reject of mineral =103369.5 ×0.6=62021.7 MT

    Third Year Development :-

    The pit will be extent in length and width (1035 sq. m.) to produce soapstone.

    The benches of 6m at 292 MRL to 262 MRL will be prepared.

    ROM excavation = 1235×31(average)Cum.=38285×2.7=103369.5 MT

    Soapstone Recovery=103369.5 ×0.4=41347.8 MT

    Waste / Reject of mineral =103369.5 ×0.6=62021.7 MT

    Fourth Year Development :-

    The pit will be extent in length and width (1035 sq. m.) to produce soapstone.

    The benches of 6m at 294 MRL to 252 MRL will be prepared.

    ROM excavation = 1235×31(average)Cum.=38285×2.7=103369.5 MT

    Soapstone Recovery=103369.5 ×0.4=41347.8 MT

    Waste / Reject of mineral =103369.5 ×0.6=62021.7 MT

    Fifth Year Development :-

    The pit will be extent in length and width (1035 sq. m.) to produce soapstone.

    The benches of 6m at 309 MRL to 267 MRL will be prepared.

    ROM excavation = 1235×31(average)Cum.=38285×2.7=103369.5 MT

    Soapstone Recovery=103369.5 ×0.4=41347.8 MT

    Waste / Reject of mineral =103369.5 ×0.6=62021.7 MT

    Year wise production for First five year:-

    During the first five year some production will be achieved initial develop the

    2m wide mine opening through the soapstone vein of 2m wide. The soapstone

  • recovery will be about 90% of the recovered ore from any working face. The

    Soapstone production from open cast development is 41481.72 MT per annum

    is proposed. Year wise detail of production is given below.

    From U/G

    Year Soapstone in MT Prod.

    Waste rock Face Prod. Rec.% Pit top Prod.

    I (2016-17) 11729 90 10556 1173

    II (2017-18) 14170 90 12753 1417

    III (2018-19) 14170 90 12753 1417

    IV (2019-20) 14170 90 12753 1417

    V (2020-21) 14170 90 12753 1417

    From O/C

    Year ROM Excavation MT Soapstone in MT Waste MT

    I (2016-17) 103704 41482 62223

    II (2017-18) 103370 41348 62022

    III (2018-19) 103370 41348 62022

    IV (2019-20) 103370 41348 62022

    V (2020-21) 103370 41348 62022

    Proposed production when the mine is fully developed: - After first five

    year development balance development will be completed within two years.

    Production of this period will be 14169.6 MT and 18 stopes will be formed. 8m

    thickness corner pillar will be left above the 328m stope for support of adit 328

    MRL. Thus 15 stope will be available for production. Each stope will contain

    63640MT of ore. Balance ore left as pillars for support of the mine will be mined

    out at the end of life of mine (before close of mine).

    It is proposed to break 145000MT/annum soapstone from this mine when the

    mine is fully developed. Taking the stripping ratio of soapstone to waste rock as

    64:36 and recovery factor of 90% production of mine per day will work out to

    be.

    Mineable reserve and anticipated life of mine :-

  • Mineable reserves in retained area will be 235519MT in soapstone. The mine

    development will be in a period of five years during this period nearly 28000MT

    of soapstone will be mined out the balance 207519MT at the production rate of

    54235MT/annum will be mined in 4 years. Therefore life of mine is expected to

    be five years.

    Proposed method of mining :-

    Underground mining and Open cast mining with mechanized method will be

    proposed for this mine.

    Open cast mining :-

    It is proposed to stock mass deposit of the block 1, the open cast mining will

    continue.

    5.3.2 Underground mining :-

    (a) Mode of entry

    For mode of entry please refer to plate 5. Main entry to the mine is proposed

    by an incline shaft of 4m * 2m cross section at 300MRL Location of this shaft

    showing in plate No. 5.

    This shaft will be concrete lined from shaft collar to a depth of 7m shaft will be

    divided to compartments of equal size as show plate No. 11. A section of the

    shaft at 272 MRL is shown on plate 12. Landing platform of the 272MRL also

    show Plate No. 12.

    Electrical cable compressed air and water mains will be housed in compartment

    1 and the ladder way will be housed in compartment 2 as show in plan.

    Second way out for the mining will be at 235MRL through adit of 3m*2m cross

    section as marked in Plate No. 5. Adit is located as 1069N, 1033E grid point.

    Adit will be driven through.

    Vein V1 keeping Quartzite on the top and in the hanging wall. Masonry wall

    shall be constructed along the Eastern wall of this adit for a distance of 10m

    this will be connected with working of lower horizons by ladder way.

    (b) System of winding/hoisting :-

    Incline shaft will be equipped with redline and a skip of 1MT capacity proposed

  • be hauled on these rails for ore hoisting. A diesel operated 20 H.P. which is

    proposed to install at 313MRL Eastern side open cast benches in line with the

    shaft pulley to hoist skip from the inclined shaft. Diesel which is proposed to be

    replaced by an electric hoist of 50H.P. at the time mine come to full production.

    Skip will be stationed at level loading point in the shaft, skip will be filled by

    operating ore bin doors in the shaft.

    (c) Underground layout :-

    It is the mine at 272MRL has shown plate No. 11. 3lbs 2feet gauge rail track

    will be installed from shaft platform to the development end/stop ore chute in

    the level. 1 MT capacity mine cars will be used for level transportation , stop

    blocks will be provided to stop inadvertent fall of mine cars in the shaft even if

    the level shaft doors are open.

    (d) Ventilation:-

    Ventilation of the mine for the first two years will be the natural motive column.

    A contra rotating 20HP fans of 36000cfm discharge and 7” water gauge will be

    installed as exhaust fan in 335MRL adit to overcome the resistance of the mine.

    Fan will be installed on the masonry plate from on the footwall side of the adit.

    A ventilation door of 1.8m height and 1.8m width will be installed adjacent to

    the plate from for the fan. Another ventilation lock door will installed 10m inside

    the Adit, position of fans and ventilation doors marked on plate X. Intake fresh

    air is shown with blue color and the return air is shown in red color ventilation

    doors and the drop doors on winze are shown by letter „D‟ on plate No. 15.

    Ventilation circuit of the mine at the end of fifth year is described as below.

    Nearly 36000cfm air will enter into the mines through 224MRL drive N and a

    part of air travel down 224 MRL for ventilation of the shaft 216MRL drive N. Air

    will rise up through 244 MRL raise and after travelling through 272 MRL drive N

    will rise up through 272 MRL raise to 300 MRL and after ventilation 300 MRL

    drive N it will be sucked up by the ventilation fan and will be discharged to the

    atmosphere.

    5.4 Extent of Mechanization :-

    A 20 H.P. diesel operated hoist for hoisting the run of mine ore has been

    proposed for the first five years. This hoist will be replace by 50 H.P. winder at

    the time mine reaches rated production.

    A 1000cfm, 120 ps. Stationary, electrical compressor and Atlas copco

    pneumatic drills, 6 numbers with six sets of T.C. rods are proposed.

  • A small workshop, electrical substation and can lam room is proposed.

    BLASTING

    Underground development:-

    Drilling pattern proposed for underground development is given in plate No. 12.

    Blasting operations shall be carried out by certified blaster with experienced

    helper. Use of special gelanite is proposed for blasting operations in this mine.

    Approved type resistivity meter and exploder will be provided for blasting

    purposes. Rolled plastic clay pieces in 10 cm to 20 cm length will be used for

    stemming wooden stemming rods of rods of 2m will be supplied for stemming.

    Charging: -

    Before charging the drill holes will be cleared thoroughly with compressed air

    bottom of hole will be plugged with 10 cm rolled clay piece and stemmed well.

    Primming cartridge will be first inserted for inverse initiation.

    Wooden spacers will be provided to reduce the charge per hole to avoid crushing of

    soapstone. Max three 2cm cartridges will be inserted in a hole of 1.8m in the host

    rock part and 2 cartridges separated by wooden spacers in a hole of 1.8m in

    soapstone rest of the hole will be stemmed with plastic clay rolls. Holes will be

    connected in series. Continuity and resistance tests will be made holes will then

    exploded with the help o exploder wooden spacer will also reduce vibration and

    throw of broken rocks besides reducing changes of crushing of soapstone.

    Opencast Development :-

    Blasting will be done in overburden and ore. Drilling will be done jackhammer and

    tractors, compressor.

    Drilling: Drilling will be done by jack hammer of 32 m dia. Burden & spacing for

    holes will be kept Kept 1.0 m & 1.2 m respectively, and the depth of hole will be

    1.5 m.

    Blasting: The blasting will be occasionally required to remove over –burden.

    Blasting will be done with all the safety measures.

    Type of explosive:

    1. Primary Explosive

    2. ANFO (A.N. 94%, F.O. 6%)

    3. Safety/ Detonating Fuse

    4. Ordinary Detonator

    More details of blasting is given below in point 5.8.

    Mucking: The Brocken material (waste rock) will be removing by dumpers/trucks.

  • The specification of the mining machinery to be deployed is given

    below:

    Table: - 5.1

    Safety precaution :-

    As per regulation number 164 of MMR 1961, before a shot is charged , all person in

    the vicinity will be send to take proper shelter . Steps will be take of prevent any

    person approaching the safety precaution like efficient siron will be blown prior to

    the blasting and at the end of blasting.

    The blasting will be done by qualified blaster/mining mate under super vision mines

    manager.

    (i) Vibration Control

    Vibration caused due to blasting will be controlled by the following steps: -

    1. Blast holes will always be initiated by short delay detonators, rather than

    adopting instantaneous detonating. Short delay in blasting of successive blast

    holes will effectively reduce the vibration problem.

    2. Number of holes per shot and blast will be kept to minimum, to guide the the

    throw in the desired direction while keeping vibration and noise to

    minimum.

    3. Multiple blasting and “V” pattern of firing will be adopted to minimize forward

    throw and have a good rock pile.

    4. Mostly, holes will be fired towards the free face.

    5. Use of ANFO which has low velocity of detonation, will also reduce the

    vibration.

    6. Blasting shall not be permitted within 100 m of surface structure.

    7. Peak particle velocity at a distance of 100 m from the shot hole, shall not

    S.

    No.

    Machine No’s Capacity

    1 Air Compressor 1 256 CFM

    2 Jack Hammer 2 32 mm dia

    3 Excavator 1 1.2 m3

    4 Dumper 1 20 Tonne

    5 Tractor 2 35 HP

    6 Water Pump 1 5 HP

    7 Wagon Drill 1 100mm dia

  • exceed 10mm/ sec.

    8. The flying fragments shall be controlled by muffled blasting and will not

    project beyond the distance of 300 m.

    9. Proper spacing & burden will be maintained.

    10. Optimum utilization of the explosives will be ensured.

    11. Direction of the hole will be maintained towards free face.

    12. Electric delay detonator will be used.

    13. Deck charging will be practiced for required fragmentation.

    (ii) Noise Control

    Noise control will be achieved by following the measures below: -

    1. Shooting of large numbers of small well designed blast holes hastily planned daily.

    2.Detonating fuse if not used for trunk lines.

    3.Blasts will be planned to eliminate.

    4.No plaster shooting is taken up as this is main reason of noise pollution.

    (iii) Fly rock hazard control

    1.Stemming length will not be kept less than the burden.

    2.It will be ensured that the burden will not be excessive.

    3.Inter row delay will be selected in manner, if required so that that each row

    pushes its

    burden in a forward rather than in an upward direction.

    Storage of explosives :-

    Explosive should be stored in ½ MT magazine to be located in another lease area

    village “Garhi” sanctioned to the party adjoining Bas Bhandari lease area.

    Application for explosive magazine license has already been submitted and is under

    consideration of appropriate Competent authority.

    Conceptual Mining Plan :-

    Conceptual mining plan up to the life of mine based on the geological, mining and

    environmental considerations-

    Parameters used of ultimate pit design :

    Areas considered Proved Reserves

    Bench height Maximum of 6m

    Ultimate pit bottom Up to 300 MRL

    Overall pit slope 450

    Gradient of haul road/ramp 1 to 16

  • Barriers Blasting safety zone as per MMR

    1961, 7.5m boundary barrier

    Mineable Reserves: Mineable Reserves in retained area will be 215040MT in soapstone. The

    mine development at the production rate of 554235MT /annum.

    Therefore life of mine is expected to be 4 year.

    Geological consideration: The area having 523743MT reserve in minerals the area will be

    Explored by putting 10 trial pit and 2 shafts in next 5 year.

    Mining consideration : Mining is proposed by mechanized opencast and underground

    method. Two bench maximum 6m height and width less than height of bench. The rate of

    production 55000 MT per annum during mining plan period.

    Environmental consideration : Monitoring of air , water & soil will be carried out as per

    CCoMs circular no 3/92. The top soil is not generated during mining plan period.

    The annual plantation of 20 saplings will be carried out . no toxics substances/chemical will be

    used.

    Time frame of completion of mineral exploration programme in lease hold area. Give

    broad description identifying potential area to be covered in the given time frame-

    Exploration will be complete by 2018 & all reserves will be proved & come under UNFC 111

    category.

    Whether Ultimate pit limit has been determined & demarcated on surface Geological

    plan :

    At the end of life period 31. 03. 2020 , the lease area under ultimate pit limit will be 3.2

    hectare with maximum excavation up to 485 MRL .

    Optimum Exploitation and Utilization of mineral :

    Utilization of all grades minerals will be ensured.

    Whether the site (s) for disposal of waste rock & unsalable ores has/have been

    examined for adequacy land suitability long term use in the event of continuation of

  • mining activity :

    No waste generated during the life of mine.

    Environmental Aspects : Monitoring of air , water & soil will be carried out as per

    CCoMs circular no 3/92. The top soil is not generated during mining plan period.

    The annual plantation of 150 saplings will be carried out . no toxics substances/chemical will

    be

    used.

    Whether back filling of pit (s) recovery of ore/mineral up to techno -economically

    feasible depth envisaged. If so, describe the broad features of the proposal:

    The area is partly backfilled and partly convert in to water reservoir during the life of

    mine.

    Post mining land use envisaged :

    The un –mined land of non mineable area (statutory barrier zone) shall be used for

    plantation.

    Ultimate reclamation :

    The activity wise reclamation rehabilitation is given table.

    PROPOSED RECLAMATION & REHABILITATION TILL END OF LIFE OF MINE (IN

    HECTARE)

    S.No

    .

    Description reclamati

    on &

    rehabilit

    ation till

    end of

    last

    MP/MS

    period

    To be

    reclama

    tion &

    rehabilit

    ation till

    end of

    present

    plan

    period

    To be

    reclam

    ation &

    rehabili

    tation

    till end

    of life

    of mine

    (20

    years)

    To be

    reclama

    tion &

    rehabilit

    ation

    after

    end of

    life of

    mine

    Rema

    rk

    1 Mining(Quar

    ry)

    0 0.00 3.20 1.70 Nil

    2 Waste 0 0.00 0 0 Nil

  • dump (Soil

    & MR)

    3 Infrastructu

    re

    0 0.00 0 0.1000 Nil

    4 Processing

    Plant

    0 0.00 0 0 Nil

    5 Mineral

    Stack

    0 0.00 0 0 Nil

    6 Sub grade

    stack

    0 0.00 0 0 Nil

    7 Road 0 0.1000 0 0.1000 Nil

    8 Water

    Course/

    pond

    0 0.00 0 1.50 Nil

    Total Reclamation 0 0.1000 3.20 3.40 Nil

  • CHAPTER – 6

    6.1 STACKING OF MINERAL REJECT/SUB GRADE MATERIAL AND DISPOSAL

    OF WASTE

    Rate of yearly generation of waste and proposals for disposal of waste for

    next five year

    Year Waste of cum Area spread Sqm.

    I(2016-2017) 23480 3500

    I(2017-2018) 23496 3500

    I(2018-2019) 23496 3500

    I(2019-2020) 23496 3500

    I(2020-2021) 23496 3500

    6.2 Nature of mineral reject and waste generated :

    The lease area is predominantly outcropping with pegmatite and schist rock.

    Therefore ROM reject is pegmatite rock with impurities and waste is schist rock.

    6.3 Quantity of top soil , Waste and rejects generated:

    No top soil generated will be mine area next five year.

    Year Waste of cum Reject in cum.

    I(2016-2017) 23480 Nil

    I(2017-2018) 23496 Nil

    I(2018-2019) 23496 Nil

    I(2019-2020) 23496 Nil

    I(2020-2021) 23496 Nil

    6.4 Buildup of dumps from year to year to be shown in yearly plans and

    sections with description of method & manner of disposal of waste rock,

    designed capacity & height of individual dump and precautions envisaged

    for confinement of dumps together with design details of the protective

    works.

    The waste /reject will generate during the next 5 year period is dumped within lease area. The

    waste is dumped in terraces of 6m height. A stone wall is proposed to be

    constructed near toe of waste dump so as to prevent the spreading of loose

    material . A garland drain of size 1.0*1.0m is proposed at the bottom side of the

    dump so as to prevent washout from the dumps. The grazing land is below 5% of

  • area so that is no need to get NOC for dumping.

    6.4 Rate of yearly generation of sub grade mineral with reference to

    threshold values and proposal for stacking for next five years :

    No sub grade mineral is generated in next five years.

    6.5 Quantity and Grade of sub grade material available at the mine as on

    date duly supported by plans and sections and descriptive statement

    inclusive of the precaution adopted for storage:

    No sub grade material is available at the mine as on date.

  • CHAPTER – 7

    7.1 USE OF MINERAL

    Soapstone: The chemical composition is required by customers depending on their

    use. The Soapstone of mineral will be used for cosmetics products like Telco Powder,

    Soap, detergents, Paper, Textiles, Pharmaceuticals, and Pesticides etc.

    Paper Industry – 80% Brightness, LOI 4%, white colour

    Cosmetic Industry – 90% Brightness, LOI 7%, white colour

    Insecticides Industry – 70% Brightness, LOI 8-10%, white to yellow colour

    7.2 Change in the specification, if any, imposed by the user industries and /or

    specification required in the case of new user industries, if any, to be given:

    No change in specification by the user industries.

    7.3 Efforts made for utilization of sub grade material including fines:

    No efforts will require.

  • CHAPTER – 8

    Mineral Beneficiation

    8.1 Results of any beneficiation investigations conducted and changes

    made in existing mineral beneficiation plant and tailing disposal, if any with

    benefits expected.

    No beneficiation investigation has been conducted by lessee beneficiation of

    mineral. At present no beneficiation plant is working for beneficiation of minerals .

    There is no proposal for mineral processing at mine site. As mentioned earlier, Bas

    Bhandari Soapstone will be excavated manually. The minerals so excavated will be

    made in gitty form manually with the help of hammers.

    Mineral Bas Bhandari soapstone are also sorted on the basis of its grade & uses in

    industryes wise minerals will be stacked separately for its use.

    As such, no chemical treatment for its benefaction is done, hence other details are

    nil.

    8.2 Beneficiation test done, if any , on sub grade mineral including fines and

    proposal for investigations of new or additional beneficiations facility, if

    any :

    As no beneficiations test is done over sub grade because there is no sub grade

    mineral , hence other information required under mineral beneficiation head is nil.

  • CHAPTER-9

    9.1 Environment Management Plan:

    Various position indicating edge of working present in the area at the end of 5 year

    mining plan period is shown over surface plan. During above period no top soil was

    generated. The summarized details of various aspects covered under environmental

    management plan , indicating proposal made in mining plan, actual implementation

    etc are given below:

    Environmental Management Plan

    S.

    No

    .

    Salient

    point

    Proposal as

    per approved

    mining plan

    Position

    at the

    end of 5

    year of

    mining

    plan

    Proposal for next 5

    year modified mining

    plan period

    1 Top soil

    storage

    preservati

    on and

    utilization

    The top soil

    generated will

    be stacked

    separately and

    use for

    plantation

    Soil was

    not

    generated

    during

    mining

    plan

    period

    No top soil will be

    generated during modified

    mining plan period

    2 Land

    reclamatio

    n &

    rehabilitati

    on

    Mineral is

    exposed at pit

    bottom hence

    no proposal

    was made

    No action

    was

    required

    Even after completion of

    five year modified mining

    plan period, mineral will

    be available at pit bottom

    , hence no proposal was

    required

    3 Waste

    dump

    managem

    ent

    As generation

    of waste will be

    dumped at the

    site shown in

    the layout plan

    There is

    only

    minerals

    fines

    generated

    during

    the plan

    As generation of waste

    will be dumped at the site

    shown in the layout plan.

    Retaining wall will be

    proposed to erect.

  • period,

    which is

    stacked

    at the site

    proposed

    4 Afforestati

    on

    programm

    e with

    precaution

    proposed

    for

    survival &

    protection

    of

    plantation

    It was

    proposed to

    plant 20

    saplings per

    year

    The

    plantation

    has been

    done , at

    present

    60 plant

    are alive

    It is proposed to 30

    saplings per year due care

    will be taken survival of

    plants.

    The year wise plantation

    programme will be as

    under

    Year NO. of Plants Area

    covered

    1st 30 100

    2nd 30 100

    3rd 30 100

    4th 30 100

    5th 30 100

    Survival rate will be maintained

    80%

    5 Quality of

    air

    No proposal

    was made

    No action

    was

    required

    The quarterly monitoring

    will be done

    6 Quality &

    make of

    water level

    including

    surface

    and

    ground

    No proposal

    was made

    No action

    was

    required

    The potable water is

    available near lease area.

    The chemical analysis of

    every year will be done

  • water

    7 Noise level No proposal

    was made

    No action

    was

    required

    Ear mufflers will be

    provided to drillers and

    monitoring will be done

    every six month

    8 Vibration No proposal

    was made

    No action

    was

    required

    Monitoring will be done

    every six month

    9 Treatment

    of water &

    effluent

    toxic

    substance

    before

    discharge

    No proposal

    was made

    No action

    was

    required

    No proposal is required

    10

    Recirculatio

    n of treated

    water

    Not applicable Not

    applicable

    Not

    applicable

    Not applicable

    11 Fly rock

    problem

    and

    precaution

    Not applicable Not

    applicable

    Blasting will be done by

    qualified blaster under

    supervision of mines

    manager and all necessary

    precaution are being

    taken as per regulation

    164 of MMR 1961

    9.2 DETAILS OF EMPLOYMENT

    It is a small scale manual working mine. The present employment potential of

    the mine is not more than 34 persons. However, for the proposed mining and as

    per statutory requirements of acts and rules sufficient supervisory, skilled and

    unskilled persons will be employed to run the mine systematically and safely to

    raise the targeted production of 500 TPD. The employment potential required is

    given below:

  • S.No

    .

    PARTICULARS NUMBER

    1.

    Managerial and Supervisory personel

    (i) Mines manager (As per MMR,1961) 1

    (ii) Mining engineer (As per MCDR, 1988) 1

    (iii) Mining Geologist (Part time) 1

    (iv) Mining mate/Supervisor 1

    (v) Driller cum Blaster 2

    Total 6

    2. Skilled:

    (i) Tractor/Dumper driver 2

    (ii) Excavator Operator 1

    Total 3

    3. Semi- skilled:

    (i) Helpers 2

    (ii) Clerk-cum-store keeper 1

    Total 3

    4. Un-Skilled:

    (ii) Workers for production of Soapstone 20

    (iv) Miscellaneous job 2

    Total 22

    Total 34

  • CHAPTER-10

    OTHER

    SOCIO – ECONOMIC BENEFITS:

    Science the villagers in the nearby villages are not able to make sufficient earnings

    from agricultural produce they prefer to work in the mines and get additional

    income. This will improve their overall standard of living. Moreover they stay back

    in the village rather than migrating to other places for alternate employment. The

    mining in the roads, communication facility, health and educational facilities etc.

    The mining will help in in direct employment generation. So mining activities will

    bring overall socio economic benefit to local resident of the surrounding villages.

    Place : Jaipur Arun Kumar Yadav

    Date : RQP/AJM/242/2003/A

    Validity:-21St May 2023

  • PROGRESSIVE

    MINE

    CLOSURE PLAN

  • INTRODUCTION

    The Modified Mining Plan with Progressive Mine Closure Plan of bas Bhandari Soapstone

    mine, M. L. No. 04/84 area 4.98ha.( Forest Diversion Land) of Mineral –Soapstone, Near

    Village – Morara, Tehsil – Toda Bhim, and District – Karauli (Rajasthan) has been prepared

    on behalf of Shri Shah Surendra Kumar, sole proprietor Shri Shah Kastoormal, Shah

    Building, S.M.S. Highway, Chaura Rasta, Jaipur (Raj.).

    LOCATION AND ACCESSIBILITY

    a) Lease Details (Existing Mine) Name of Mine : Bas bhandari Soapstone Mine (M.L. No.-04/84)

    Lat/long of any

    boundary point

    : Block No.- 1 Pillar Latitude (N) Longitude (E)

    J 26048'42.13'' 76048'15.96''

    E 26048'42.01'' 76048'25.73''

    C 26048'46.13'' 76048'26.1''

    C1 26048'46.58'' 76048'28.43''

    C2 26048'47.92'' 76048'31.71''

    C3 26048'50.15'' 76048'30.9''

    C4 26048'47.68'' 76048'27''

    C5 26048'47.45'' 76048'25.99''

    C 26048'46.13'' 76048'26.1''

    Block No.- 2

    Pillar Latitude (N) Longitude (E)

    J 26048'42.13'' 76048'15.96''

    K 26048'42.01'' 76048'16.03''

    B1 26048'46.65'' 76048'12.36''

    B2 26048'51.59'' 76048'10.55''

    B3 26048'53.94'' 76048'18.08''

    R 26048'19.62'' 76048'19.62''

    R1 26048'17.23'' 76048'17.23''

    R2 26048'16.57'' 76048'16.57''

    K 26048'16.03'' 76048'16.03''

    FRP (Temple) Latitude (N) - 26048'37.26''

    Longitude (E) - 76048'15.88''

    Date of grant of lease : 21/04/1965

    Name of lease holder : Shri Shah Surendra Kumar, sole proprietor Shri Shah

    Kastoormal

    Postal Address : R/o Kalyan Bhawan, Shah Building, S.M.S. Highway, Chaura Rasta, District: Jaipur (Raj)

  • Email ID : [email protected]

    Mobile No. : +91-9414065224

    b) Details of applied /lease area with location map (fresh area /mine)

    Khasra no.-23,489,839

    Table No.-1 Status of land

    Forest Non Forest

    Forest (specify) Area

    (ha)

    Waste

    /grazing/agriculture/other land

    Area (ha)

    Forest Diversion Land 4.84 -- --

    Total 4.84

    Total lease area : 04.84 Hectare (Forest Diversion Land)

    District & State : Karauli, Rajasthan

    Tehsil : Toda Bhim

    Village : Morara

    Toposheet No.

    : 54B/13

    PRESENT LAND USE PATTERN:-

    S. No. Head Area Put On Use At Start Of Plan In Ha.

    1 Pit & Dump 3.5

    2 Road & Other Infrastructure 0.50

    3 Plantation 0.40

    4 Unused Land 0.58

    Grand Total 4.98

    METHODE OF MININING:-

    The proposed method of mining is open-cast and underground mechanized

    method.

    (1) Formation of benches: Existing open pit side benches will be

    dressed, loose from top of the pit will be removed and top of the pit

    will be fenced off with masonry wall.

  • (2) Preparatory work: Incline at 300mRL will be cleared off and

    supported of a distance of nearly 10m with concrete arches. And old

    underground working will be abandoned with the help of RCC wall.

    (3) Creation of wall: A water tank of nearly 2000lt. capacity will be

    constructed in cement concrete on 337mRL bench near the mouth of

    proposed incline shaft S-2, the position marked on layout plan.

    (4) Surface drainage: Garlands for drainage of rain water will be made

    at 350, 360 & 370mRL contours 2m. high retaining wall is proposed

    at 240mRL along the hill slope to divert overflow water from garlands

    into the nalla.

    MINERAL PROCESSING:- Sizing And Sorting Will Be Done.

    GEOLOGY AND EXPLORATION:

    a) Briefly describe the topography, drainage pattern, vegetation, climate, and

    rainfall data of the area applied/mining lease area.

    Topography:

    Topographically the M.L area is hilly terrain, having highest altitude is 350 mRL and

    lowest altitude is 278 mRL. The general trend of ridge is NE-SW dip is 65°-70°.

    Drainage Pattern:

    The drainage of this area is followed by seasonal nalah flowing across from North-

    East to South-West side of the M.L. area.

    Vegetation:

    The area bears scantly vegetation. Shurbs of Zizyphus Jujuba (Bear), Azatirchta

    indica (Nim), Maganiferous indica (Mango), Tamaradus indica (Tamarind), Ficus

    religiosa(Pipal), Dhok (Buteafrondosa) are seen around the villages. The protected

    forests consist of moderately dense creepers and grassy undergrowth.

    Climate & Rainfall:

    The area is characterized by semi-arid type with an average annual rainfall about 660

    mm. which is mainly, received during June to September.

    Minimum Temp - Varies from 1.0º to 15ºC

    Maximum Temp - Varies from 25º to 45ºC

    b) Brief descriptions of Regional Geology with reference to location of

    lease/applied area Regional Geology Regional Geology

  • Geologically mapping of the lease area was done with GPS surveying. The

    generalized geological sequence as observed in the field can summarized as-

    The geological sequence worked out by G.S.I. is given as under: -

    Table 4.1 Stratigraphic succession

    Era/ Period System series Lithology

    Quaternary Recent and

    sub-recent

    - Alluvium, and sand

    Upper

    Proterozoic

    Vindhyan

    Super group

    Bhander Group Sandstone and Limestone

    Rewa Group Shale, Sandstone

    Kaimur Group Sandstone and Conglomerate

    Semri Group Shale, Sandstone and

    Limestone

    Proterozoic Delhi Super

    Group

    Alwar Group Quartzite and Conglomerate

    schist

    Pre Aravalli

    Group

    schist, gneiss and migmatites,

    Phyllite, marble, Quartzite

    Igneous activity/Intrusive Dolerite dykes and sills

    c) Local Geology:

    The rock of the area as-

    Recent --- --- Alluvium Soil

    Quartzite, Talc, Chlorite

    schist

    d) (i) Name of exploration agency : Bas Bhandari Soapstone Mine (M.L. No.-04/84)

    (ii) Address: Kalyan Bhawan, Shah Building, S.M.S. Highway, Chaura Rasta, District:

    Jaipur, State: Rajasthan, Pin code: 302002

    (iii) E mail address: [email protected] and Mobile No. :

    9414065224

    The lease holder is itself responsible for appointing the exploration agency & the

    exploration done by them.

    e) Details of exploration carried out :

    The minerals Soapstone exposed in two pits up to the considerable depth in the M. L.

    area. Soapstone is found exposed in the depth in the area.

    No. of existing Mining Pits: two

    Dimensions of Pit:

    Pit : Length – 44 m, Width - 25m and Depth – 11 m

    Length – 44 m, Width - 25m and Depth – 11 m

    Year wise detail of production :-

  • From U/G

    Year Soapstone in MT Prod.

    Waste rock Face Prod. Rec.% Pit top Prod.

    I (2016-17) 11729 90 10556 1173

    II (2017-18) 14170 90 12753 1417

    III (2018-19) 14170 90 12753 1417

    IV (2019-20) 14170 90 12753 1417

    V (2020-21) 14170 90 12753 1417

    From O/C

    Year ROM Excavation MT Soapstone in MT Waste MT

    I (2016-17) 103704 41482 62223

    II (2017-18) 103370 41348 62022

    III (2018-19) 103370 41348 62022

    IV (2019-20) 103370 41348 62022

    V (2020-21) 103370 41348 62022

    Rate of yearly generation of waste and proposals for disposal of waste for

    next five year

    Year Waste of cum Area spread Sqm.

    I(2016-2017) 23480 3500

    I(2017-2018) 23496 3500

    I(2018-2019) 23496 3500

    I(2019-2020) 23496 3500

    I(2020-2021) 23496 3500

    Quantity of top soil , Waste and rejects generated:

    No top soil generated will be mine area next five year.

    Year Waste of cum Reject in cum.

  • I(2016-2017) 23480 Nil

    I(2017-2018) 23496 Nil

    I(2018-2019) 23496 Nil

    I(2019-2020) 23496 Nil

    I(2020-2021) 23496 Nil

    PROGRESSIVE MINE CLOSURE PLAN UNDER RULE 23B OF AMENDED MCDR’ 2003

    1.2 Impact Assessment

    1.2.1 Impact on Land Use Pattern

    In proposed method of mining is open-cast and underground mechanized

    method., the top crust of earth i.e. scree is completely removed below which

    mineral deposited is exploited. The overburden is completely removed to

    provide access to the mineral deposit. In this manner land use pattern of an

    area always changes in the form of voids formed due to excavation of mineral

    and waste dumps left after mining. Therefore, measures are required for

    reclamation of land affected due to mining and waste dumping to improve the

    aestheticism of the area as well as to protect the land environment.

    1.2.2 Impact on Air Quality

    The air environment of the area is affected by several factors apart from

    the mining. The damaged roads, other mines, agricultural practices in the area,

    movements of vehicles add air pollution. The sources of air pollution in the area

    due to mining will be mainly from dust generation by plying of trucks and

    dumpers on unpaved mine road. The dust is also generated during drilling

    whereas quality of air is affected due to emission of gases from different

    machineries and Smoke generated during blasting which is momentarily, &