modeling of the transmission grid using geo allocation and … · 1 modeling of the transmission...
TRANSCRIPT
1
Modeling of the transmission grid using geo allocation and generalized processes
Presentation at the ISESO - Nov 10th 2015
Simon Köppl, Felix Böing, Christoph Pellinger Research Centre for Energy Economics, Munich
http://www.ffe.de/en/
2
www.ffe.de/mona
- merit order -
- basic data - - scenario - analysis -
- measure classification-
Which grid optimizing measures are technically,
legally and at the same time economically –
including socio-ecological factors - representable?
Uncertainty concerning
framework conditions
Possible future scenarios
Impacts
Profiles
&
Spatial discrepancy
of generation/consumption
Influence on
distribution and
transmission
grid
Variety of measures
which? classifiable? comparable?
1. Motivation: objectives in the project MONA 2030
Co-funded by
and the support of 16 partners
Grid structures
3
www.ffe.de/mona
„The ENTSO-E Grid Map is commonly used“
• No geographical location of the facilities
• Data set represents the „Startnetz“
• Unclear illustration of other European countries
1. Motivation: a brief history of using grid data at FfE
„In Germany, data can be obtained by the BNetzA“
• Simplified electrical parameters
• Data only available as a map
Search for a data set of the European transmission grid for a grid
model in a power plant dispatch model with focus on Germany/Austria
4
www.ffe.de/mona
2. Public grid data sets: The modeling of the transmission grid is conducted via the connection of a variety of data sets
5
www.ffe.de/mona
Electrical parameters
For every line and for every station, relevant electrical characteristics have to be known:
• Status: active/passive/not yet built
• Resistance and reactance (R, X)
• Thermal limits
Validatability
Every data set has to be able to be validated:
• Reliability of the source
• Benchmarking in other data sets
Every data set should be public
Goal: consistent transmission grid model, based on public data
2. Public grid data sets: requirements for a consistent grid model
Geographical location
All network components have to be able to be located
• Exact geographical location
• Electrical connections also beyond network levels
Expandability
• Every data set has to be able to be combined with other data sets and to be expanded at a later point
• Integration of future grid projects and development paths
For the integration in a consistent grid model, a data set has to fulfill certain
characteristics
6
www.ffe.de/mona
Open Street Map
Regulation authorities,
e.g.in Germany
Sc
op
e
Vo
lta
ge
leve
ls
2. Public grid data sets: overview of the used data sets
Ele
me
nts
ENTSO-E Grid Map
Germany comprehensively
(+ Europe as a reduced
peripheric grid)
Europe, North Africa, USA,
parts of Asia and South
America
Europa + peripheric
regions in Africa and Asia
Lo
ca
tio
ns
220 kV–750 kV
comprehensively
Other voltages reduced to
display cross-flows
„Numerate model“:
impedances and
component values of all
network elements
No geo data
220 V – 765 kV
But: uncertain level of
detail of the map
Lines with „wires“ and
„cables“
Georeferenced locations
220 kV–750 kV
110 kV/150 kV at cross-
border lines in certain
countries
Voltage level + number of
circuits
Stylized map,
approximate line course
Grid model TSO
Supply region of the TSO
Mostly, 220 kV and 380 kV
Impedances and
component values of the
lines
No geo data, simplified
overview map
Sources: TenneT TSO GmbH, Static Grid model: https://www.tennettso.de/site/en/Transparency/publications/staticgrid-model/static-grid-model. TenneT TSO GmbH, Bayreuth (2015)
Amprion GmbH, Static grid model: http://www.amprion.net/en/static-grid-model. Amprion GmbH, Dortmund (2015)
Bundesnetzagentur, Daten nach 12f Abs.1 EnWG. Bundesnetzagentur, Bonn (2014)
OpenStreetMap, United Kingdom (UK): https://www.openstreetmap.org/about (2015)
ENTSO-E, Interconnected network of ENTSO-E. Brussels (2014)
7
www.ffe.de/mona
2. Public grid data sets: inconsistent grid node designation and different geographical detail
1 Every starting/ending
point of a line has to be
georeferenced
2 Problem: unclear positions
+ inconsistent designation
of grid nodes
3 Additionally: increased
computing effort due to a
lot of grid nodes
„X-Knoten Vierraden-Krajnik“
KW Emsland – UW Emsland
„Staatsgrenze Györ/HU
„Frankfurt/SW“ – „Frankfurt N“
4 Solution: geographical
aggregation of grid nodes
8
www.ffe.de/mona
Determination of the
“catchment area of a grid
node“
Drawing a circle with a specified radius around the grid node
2. Public grid data sets: reducing the complexity - approach for a geographical grid node aggregation
Overlapping of the circles
All circle centers in one
grid region
• Assembling of the circles to
one polygon
• Grid node in the center of
the polygon as „main node“
• Aggregation of the obtained
grid node
Circle centers in different
grid regions
• Formation of different
polygons: one polygon per
grid region
• Afterwards analogous
procedure as seen on the
left
9
www.ffe.de/mona
2. Public grid data sets: data sources for the planned grid expansion in Europe
Standardized collection of
project data
• Location
• Status of implementation
• Grid region
• Type of project:
line/transformer/
Q-compensation/…
• Electrical parameters
• Legal basis of the project
• Time of completion
2
European Grid
development plans
• GDP Germany
• GDP Austria
• …
3
Specific project
desciptions
1
National grid
development plans
Ten-Years-Network-Development-Plan
of the ENTSO-E (TYNDP)
Detailed desciptions of grid projects
(e.g. HVDC projects, cross border
interconnectors)
10
www.ffe.de/mona
2. Public grid data sets: Resulting grid node list and line list
ID Name Optional Grid region Voltage Geometry Source
688 Schkopau SCHK DE83 110 kV, 380 kV 01010020787F000007708… OSM
689 X-Knoten Vierraden-Krajnik
DE81,PL 220 kV 01010020787F00004E203… manual
690 Magdeburg 50Hertz DE81 110 kV, 220 kV 01010020787F0000C2D30… OSM
691 Herrenwyk HVDC Baltic Cable
DE21 110 kV, 380 kV 01010020787F0000585CB… OSM
692 Waldeck Waldeck I+II DE24 380 kV 01010020787F00001EF00… OSM
ID_line ID_station1 ID_station2 Voltage I R X Length
00209399 336 755 220 kV 1.360 A 0.3 Ω 1.5 Ω 5.0 km
11209008 370 494 220 kV 30 km
11208783 372 373 380 kV
00208775 419 398 380 kV 3.600 A 1.5 Ω 19.1 Ω 78 km
00400040 21 157 380 kV 2.720 A 0.5 Ω 5.2 Ω 19 km
1 Extract of the grid node list
2 Extract of the lines list
11
www.ffe.de/mona
3. Process Model: inhomogeneous and inconsistent data situation as common challenge in data aggregation
power plant type
fuels
chp
voltage level
…
Electric Storage
storage type
storage medium
voltage level
…
Grid
voltage level
AC/DC
number of circuits
reactance
…
Element:
Identification
data:
Power Plants
• Inconsistent allocation of parameters and scenarios
• Inconsistent aggregation of devices
• Each element is considered as an individual case
The various elements of the power system are classified by different
identification data.
Starting situation:
12
www.ffe.de/mona
3. Process Model: the definition of processes
energy source input technical component energy source output
attribute of a process
optional
examples:
natural gas gas turbine electrical energy (AC) + heat
380kV AC power line 380kV AC
380kV AC power line 380kV AC underground cable
380kV AC power line 380kV AC overhead line
process:
13
www.ffe.de/mona
3. Process Model: creating a tree of processes
Advantages:
• Consistent aggregation on
different levels for all
elements
• Both instances and
parameters are assigned to
processes
• top-down approach for
parameters
• Simple amalgamation of
parameters to form
instances
380kV AC – Power Line – 380kV AC
+ Overhead Line
380kV AC – Power Line – 380kV AC
+ Overhead Line + Quad Package
Electricity – Power Line – Electricity
Power AC – Power Line – Power AC
Extra High Voltage AC – Power Line – Extra
High Voltage AC
220kV AC – Power Line – 220kV AC
380kV AC – Power Line – 380kV AC
380kV AC – Power Line – 380kV AC
+ Overhead Line + Triple Package
Electricity – Transformer – Electricity
Power AC – Transformer – Power AC
Extra High Voltage AC – Transformer –
High Voltage AC
...
Notation:
element = eg. conv. power plants
instance = eg. „CCGT Irsching“
14
www.ffe.de/mona
3. Process Model: Implementation in a database environment using a dynamic allocation algorithm
Sources: Hofmann et al., Wirtschaftlichkeitsvergleich unterschiedlicher Übertragungstechnik im Höchstspannungsnetz anhand der 380-KV-Leitung Wahle-Mecklar. Hannover (2010)
APG Austrian Power Grid (APG), Static grid data in: https://www.apg.at/de/netz/anlagen/leitungsnetz. Vienna (2015)
DIW, Electricity Sector Data for Policy-Relevant Modeling - Data Documentation and Application to the German and European Electricity Markets. Berlin (2014)
YearRegionProcess
Instance
Value
Reactance (X)
220kV AC – Power
Line – 220kV ACEU 2030 0.075
Germany 2030 0.014
Power AC – Power
Line – Power ACEU 2030 0.029
Current (I)
220kV AC – Power
Line – 220kV ACEU 2030 1286
380kV AC – Power Line
– 380kV AC (overhead)Austria 2277
380kV AC – Power Line
– 380kV AC (overhead)Germany 2720
Node 137 –
Node 138
(Germany)
2019
Pa
ram
ete
rE
lem
en
t
380kV AC – Power Line –
380kV AC (overhead,
quadruple bundle)
1
2
3
4
5
6
380kV AC – Power Line
– 380kV AC (overhead)
2030
2030
15
www.ffe.de/mona
4. Integration of grid data in energy system models: the energy system can be modeled as a network of processes
Natural Gas – Gas Turbine –
220kV AC
220kV AC – Power Line –
220kV AC (overhead, triple)
380kV AC – Transformer –
220kV AC
20kV AC – Electric Storage –
20kV AC (Li-Ionen-Battery)
16
www.ffe.de/mona
4. Integration of grid data in energy system models: Providing nodal load and production data
Sources: Pellinger, Christoph et al., Merit-Order der Energiespeicherung im Jahr 2030. Forschungsstelle für Energiewirtschaft e.V., Munich (2012)
Forschungsstelle für Energiewirtschaft e.V.: The FfE Regionalized Energy System Model (FREM). Forschungsstelle für Energiewirtschaft e.V., Munich (2014)
Carr, Luis et al., Erneuerbare Energien - Potenziale und ihre räumliche Verteilung in Deutschland in: Flächennutzungsmonitoring V – Methodik, Analyseergebnisse
Flächenmanagement. Leibniz-Institut für ökologische Raumentwicklung e. V., Forschungsstelle für Energiewirtschaft e.V., Dresden, Munich (2013)
FREM
FfE Regionalized Energy System
Model
2 Allocation to grid nodes:
Geographically / direct allocation /
using the HV grid
1 Flexible and consistent data basis
for geographically and temporally
highly resolved generation/demand
data at all aggregation levels
17
www.ffe.de/mona
5. Resulting transmission grid model
• Detailed presentation of the German and Austrian transmission grid, simple expansion to
other countries, if data is available
• Simplified illustration of other European countries: mostly one grid node per country, modeling
of the transmission grid via cross border capacities (one country as a copper plate)
Characteristics of the grid model
• Final aggregation radius of grid
node 5 km
• 448 grid nodes in DE and AT
• Display of 1134 line sections + 696
projects with line parameters
(voltage, max. current, R, X)
18 18
1. Added value only if detailed grid data is provided
2. Temporal inconsistency due to varying publishing dates of
data sets
3. Varying and not clear designations for substations which
requires an manual allocation in many times
Validation of the grid model with other grid
models is crucial and an ongoing task
Weak spots of the model
6. Critical review
19
www.ffe.de/mona
7. Conclusion and outlook
1 For a consistent model of the transmission grid, it is necessary to
amalgamate different, public data sets.
3 The described process model is a transparent approach to
standardize and complement grid data sets with appropriate
simplifications and assumptions.
5 Besides any smart allocation algorithm, a transmission grid model still
requires a significant amout of work for filling the database with input
data…
4 The process model also allows a simple integration of grid data into
dispatch models.
2 The latest publications of grid data sets (TSOs, ENTSO-E, Open data
projects) improve the quality of transmission grid models a lot.
20
www.ffe.de/mona
Discussion? Questions? Thanks a lot for your attention!
Questions? Discussion
!
? ENTSO-E
Contact:
Simon Köppl, Felix Böing,
Christoph Pellinger
+49 (89) 158121-78
Research center for energy
economics
(Forschungsstelle für
Energiewirtschaft e.V.)
Am Blütenanger 71
80995 Munich
www.ffe.de/en
21
www.ffe.de/mona
Backup: Integration of grid data in energy system models: virtual network in peripheral regions
No detailed data available
„copper plate“
Centroids of
countries
Specific
process
definition
Transfer capacity =
sum of all cross border lines
between countries
Reduced simplified
network
Virtual dummy
transmission lines
22
www.ffe.de/mona
2. Public grid data sets: different development paths for the expansion of the transmission grid
2 For every grid project which is implemented in the grid model, the following
information has to be available:
• Starting and ending point of the line
• electrical parameters (current thermal limit, R/C/X)
e.g. „all projects of the TYNDP
will be built on time“
e.g. „only projects of the Federal
Requirements Plan will be built“
1 For an appropriate integration of grid projects and resilient grid planning, different
development paths have to considered
Example of the NEP
380kV-quadruplicate line (overhead line) from
Altenfeld to Redwitz
After calibration with 12f-data set:
• 2 curcuits with high current cables
• S_th = 2369,45 MVA
Example of the TYNDP
380kV-line from Feroleto (IT) to Maida (IT)
• Number of curcuits?
• Which type of cable?
• Which electrical parameters?
• Overhead line/underground cable?