mod_18_10_v2 : sem intra-day trading 6 december 2011

18
Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

Upload: gannon-hoover

Post on 03-Jan-2016

13 views

Category:

Documents


0 download

DESCRIPTION

Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011. Background. Why Intra-Day Trading?. The EU is moving towards greater integration of electricity market arrangements, particularly to facilitate greater trading across Europe. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

Mod_18_10_v2 : SEM Intra-Day Trading

6 December 2011

Page 2: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

2

Background

Page 3: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

3

• The EU is moving towards greater integration of electricity market arrangements, particularly to facilitate greater trading across Europe.

• EU Congestion Management Guidelines require re-allocation of unused Interconnector capacity on both D-1 and D.

• Ireland Infringement Letter - June 2010

Continuing infringement cases against Ireland for violating Electricity Regulations.

Key concerns are:1) no intra-day congestion management mechanism at all interconnections2) no common co-ordinated congestion management method

• SEM Committee Decision (SEM-10_011)

RAs to develop a Modification to facilitate intra-day trading

RAs to set up a Working Group to discuss proposal and alternatives

RAs to bring a proposed Modification (agreed by the Modifications Committee) to the SEM Committee.

Why Intra-Day Trading?

Page 4: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

4

Development of the IDT High Level Design

Intra-Day Trading Modification Mod_18_10 raised March 2010:

• Phase 1 (development and approval of High Level Design)

Working Groups 1 to 7: development of High Level Design.

25 Nov 2010 - Modifications Committee Meeting 32 – Modifications Committee recommended to approve High Level Design.

02 Mar 2011 - SEM Committee approved implementation of High Level Design.

01 Feb 2011 - Modifications Committee Meeting 33 – SEMO asked to develop legal text based on High Level Design.

Page 5: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

5

Development of IDT Legal Drafting

• Phase 2 (development of detailed Code changes to deliver HL Design)

The legal text has been developed and considered by the IDT Working Group on an incremental basis, in three “Functional Groups”:

• Functional Group 1 – Registration and Participant Submissions.

• Functional Group 2 – Other Data Transactions and MSP Software.

• Functional Group 3 – Settlement and Credit Risk Management.

Working Group schedule:

• 10 May 2011, Working Group 8: Functional Group 1

• 29 June 2011, Working Group 9: Functional Group 3

• 27 September 2011, Working Group 10: Functional Group 2

• 10 November 2011, Working Group 11: Entire “final” Mod

In addition, eight conference calls have been held as part of the Working Group process.

Page 6: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

6

IDT Legal Drafting and Plain English Documents

• Mod_18_10 v2 combines all of the proposed IDT changes for FG1 + FG2 + FG3:

All FG1 changes are highlighted in yellow, and changed marked.

All FG2 are change marked, but are not highlighted.

All FG3 changes are highlighted in cyan, and changed marked.

Note: all highlighting is not part of the legal drafting changes and will be removed.

• A series of “Plain English Documents” accompanies the legal drafting of the IDT Modification:

Separate PEDs for each of: FG1, FG2 and FG3.

Additional PED for Transitional Provisions (see Mod_34_11).

These are designed to facilitate the understanding of the legal drafting changes to the Code.

Page 7: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

7

Participant/Regulatory Authority Comment Summary

• FG1 Review (following WG8) - 80 comments addressed

Topics including: typos/drafting suggestions; Gate Windows/Trading Windows; registration processes; query processes; and definitions.

• FG1+FG3 Review (following WG9) - 125 comments addressed

Topics including: typos/drafting suggestions; calculation of credit exposure/exclusion of PQ Pairs; issue of Notices; calculation of EEP/ECP; and definitions.

• FG1+FG2+FG3 Review (following WG10) - 100 comments addressed

Topics including: typos/drafting suggestions; credit cover calculations; publication/reporting timings; MSP Software Run Cancellation impacts; responses to WG10 actions; and definitions.

• Entire Modification Review (following WG11) - 8 comments addressed

Topics including: COD for Interconnector Unit in WD1 Ending Overlap Optimisation Period; SEMO manual publication processes; and MSP Software Run Cancellation impacts.

Page 8: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

8

Summary of SEM Intra-Day Trading Design

Page 9: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

9

• The SEM Intra-Day Trading design is detailed in the High Level Design:

Bidding to multiple Gate Windows (EA1, EA2 and WD1) for the relevant Trading Day.

Restriction of Interconnector Unit bidding in the EA1 Gate Window to Capacity Holders.

Reallocation of unused Interconnector Capacity to any Interconnector Unit (with no requirement to be a Capacity Holder) in EA2 and WD1 MSP Software Runs.

Trading Window for EA1/EA2 is the entire Trading Day and for WD1 is the second portion of the Trading Day

Fixing of Interconnector Unit capacity allocations from EA1 MSP Software Run (MIUNs) in the EA2 and WD1 MSP Software Runs.

Fixing of Interconnector Unit capacity allocations from EA1 MSP Software Run (MIUNs) in the EA2 and WD1 MSP Software Runs.

Limiting total Interconnector Unit Nominations in EA2 and WD1 by the Available Transfer Capacity.

MSP Software Cancellation to occur when certain conditions are met. If this occurs, COD and TOD will continue to be used in subsequent MSP Software Runs.

Changes to Credit Cover arrangements in respect of Interconnector Units.

Summary of the SEM Intra-Day Trading Design

Page 10: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

10

SEM Intra-Day Trading Design:Three Gate Windows / Trading Windows

Start Overlap Opt’n Period

Trading Day - 1 Trading Day

Gate Window Closure(GWC)

EA1

Gate Window Opening(GWO)e.g. as per current

GWC

EA2

GWO

GWC

WD1

GWO

GATE WINDOW10:00 TD-29 to 09:30 TD-1

GATE WINDOW09:30 TD-1 to 11:30 TD-1

GATE WINDOW11:30 TD-1 to 08:00 TD

EA1 Trading Window

EA2 Trading Window

WD1 Trading Window

Ending OverlapOpt’n Period

Ending OverlapOpt’n Period

Ending OverlapOpt’n Period

EA1 Interconnector Unit trades fixed

EA1 and EA2 Interconnector Unit trades fixed

OPTIMISATION TIME HORIZON

Only Interconnector Users with Capacity Holdings can submit COD

Note: Settlement will continue to be Ex-Post, based on Dispatch and Generator Unit performance against Dispatch. No changes are proposed to settlement payments or charges.

Page 11: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

11

SEM Intra-Day Trading Design:Summary of EA1, EA2 and WD1 MSP Software Runs

EA1

EA2

WD1

Load/Wind Forecasts

EA1 COD

EA1 TOD (Forecast Availability etc)

EA1 VTOD setEA1 MIUNs

Load/Wind Forecasts

EA2 COD

EA2 TOD (Forecast Availability etc)

EA2 VTOD set

Load/Wind Forecasts

EA2/WD1 COD

WD1 TOD (Forecast Availability etc)

EA2 VTOD set

EA1 MSQs, SMPsOptimisation Time Horizon 06:00 – 11:30Trading Window 06:00 – 05:30

EA1, EA2 MIUNs

EA2 MSQs, SMPsOptimisation Time Horizon 06:00 – 11:30Trading Window 06:00 – 05:30

WD1 MSQs, SMPsOptimisation Time Horizon 06:00 – 11:30Trading Window 18:00 – 05:30

WD1 (TD-1) Initial Conditions

WD1 (TD-1) Initial Conditions

EA2 Initial Conditions

EA1 Registration Data & Other TOD

EA1 Registration Data & Other TOD

EA1 Registration Data & Other TOD

Starting Gate Window Data• For EA1, Default Data• For EA2, latest Accepted at EA1 Gate Window Closure• For WD1, latest Accepted at EA2 Gate Window Closure

Page 12: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

12

SEM Intra-Day Trading Design:Contingency Data and MSP Software Cancellation rules

• As Intra-Day timescales are compressed, contingency rules have been developed to allow timelines to be met:

Load Forecast / Wind Forecast / ATC – use latest data received.

Active Capacity Holdings (EA1 only) – email and fax from IA (ACHS to be sent as early as possible to IA and from IA to MO).

MIUNs – MIUNs from previous run for the same period, else IUNs from previous run for the same period, else zero.

• MSP Software Run Cancellation:

EA1, EP1 and EP2 MSP Software Runs will not be cancelled (paragraph 4.82D).

EA2 MSP Software Runs will be cancelled if any of the conditions in paragraph 4.82E are satisfied.

WD1 MSP Software Runs will be cancelled if any of the conditions in paragraph 4.82F are satisfied.

Page 13: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

13

SEM Intra-Day Design: Elements of Credit Exposure Calculation

Amounts invoiced and payment outstanding (netted)

Amounts calculated but not yet invoiced (netted)

Invoiced

Settled

Traded

Offered

For Interconnector Units only, amounts calculated based on traded values where Initial Settlement has not occurred (Energy or Capacity), based on export MIUNs and PQ Pairs Accepted.

For Interconnector Units only, the maximum export exposure is implied by a set of Price Quantity Pairs submitted to a particular Gate Window.

• Credit exposure will in future be a comprised of:

• After each Gate Window Closure and MSP Software Run, the Available Credit Cover will be calculated for each Participant: Sufficiency checks to be carried out after each Gate Window Closure, for

Interconnector Users. If sufficient Available Credit Cover, Offered Modified PQ Pairs = Accepted PQ Pairs. If insufficient Available Credit Cover, Offered Modified PQ Pairs will exclude or amend

Accepted PQ Pairs in order to ensure adequate credit cover is in place to cover possibly trading exposure.

Page 14: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

14

SEM Intra-Day Design: Publication of Market Schedules and Market Prices

• The Working Group process included discussion of the scenario where the Market Schedule and SMPs can be calculated, but that the “Central Market System reporting function is not operable”.

• Following Participant comment, SEMO will be developing a business process which will:

enable Market Schedules/Prices/MIUNs to be provided to Participants by other means

define a cut-off time at which time the business process will be enacted (3pm has been suggested by Participants).

• Once the business process is developed, SEMO will raise a Modification Proposal that will seek to include relevant obligations within an Agreed Procedure (AP7?).

Page 15: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

15

Legal Review of IDT Drafting

Page 16: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

16

• Legal review initiated by Modifications Committee (Sept 2011).

• McCann Fitzgerald appointed to undertake the legal review.

• The objectives of the legal review were to:

review the drafting changes proposed for SEM Intra-Day Trading;

identify any issues with the drafting where it is not legally robust, or where there are inconsistencies, and propose changes to address;

agree with SEMO the drafting changes that are required to address the issues identified by the legal review and confirm that these have been correctly completed, such that the revised drafting is legally robust; and

draft a report to the Modifications Committee and Regulatory Authorities, detailing the outcome of the legal review and confirming that the issues raised have been addressed in the updated legal drafting, thereby giving the Committee sufficient assurance that the Modification is legally robust.

Legal Review - Objectives

Page 17: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

17

Legal Review - Opinion

• The Legal Review Report is included in Mod_18_10_v2 and was separately published to the SEMO website on 23 November 2011.

• Section 1.2“On the basis of the scope of work as described below, under the assumptions and

subject to the qualifications and reservations set out in Schedule 1 hereto, and to any matters or documents not described to us, we are satisfied that the final form of the legal drafting for the Intra-Day Trading Modification proposal effectively and accurately reflects and implements the proposal”.

• Section 5.3 “As opined at Section 1, we are satisfied that the final form of the legal drafting for the

Intra Day Trading effectively and accurately reflects the proposal therefore, as set out in the PEDs. We also note that no material concerns were raised in the course of our review, which (as described above) was an iterative process in relation to a large number of drafting comments and not a negotiation in relation to net material aspects”.

Page 18: Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011

18

Discussion and Vote