minutes of the 89th meeting of state environment...

37
1 Minutes of the 89 th meeting of State Environment Impact Assessment Authority held on. 28.03.2016 under the Chairmanship Sh. Bharat Bhushan IAS (Retd.), Chairman, SEIAA held in the meeting room of office of SEIAA Haryana, Sector-2 Panchkula, regarding Environmental Clearance under EIA Notification dated 14.9.2006. The full Authority is present. The Cases recommended by SEAC for Environmental Clearance or otherwise as listed in the Agenda item circulated vide letter No. 223-225 dated 22.03.2016 were discussed. Following decisions were taken:- Item No.[1]Environmental Clearance for construction of Affordable Group Housing Colony Project at Village Sohna & Khaika, Sector-4, Distt Gurgaon, Haryana by M/s GLS Infratech Pvt. Ltd. This case was lastly considered in the 84 th meeting of SEIAA held on 29.10.2015 and the case was referred back to SEAC for reconsideration with the following observations. 1. The project proponent has proposed to develop green area on 15.66% of the project area whereas in the conditions it has been mentioned that the project proponent shall maintain 20% green area. The project proponent on 28.10.2015 submitted revised plan showing 20% green area. The SEAC should examine the same. 2. The SEAC shall ensure that the solid waste generation calculation and parking calculation is as per latest prescribed norms and shall also ensure that the project proponent has furnished details of appropriate technology to be adopted for treatment of bio-degradable waste. The project proponent shall submit plan depicting the area ear marked for composting. 3. The project proponent shall submit latest undertaking on non judicial stamp paper stating that no construction has been raised at site duly signed by the director. The project proponent shall also submit latest photograph of site. 4. The project proponent shall submit solar path analysis. The SEAC in its 127 th meeting held on 16.02.2016 considered the reply dated 24.11.2015 submitted by the project proponent on the above observations and again recommended this case for environmental clearance. The recommendation of SEAC was taken up for consideration in the today’s meeting. The reply submitted by project proponent and considered by SEAC was found in order. After detailed deliberation, the Authority decided to agree with the recommendations of SEAC to accord Environment Clearance to this project by imposing the following condition in addition to the usual conditions in practice. [1] The project proponent shall install solar panel for energy conservation. [2] The project proponent shall provide green area on 20.017% of project area.

Upload: others

Post on 26-May-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

1

Minutes of the 89th meeting of State Environment Impact Assessment Authority

held on. 28.03.2016 under the Chairmanship Sh. Bharat Bhushan IAS (Retd.),

Chairman, SEIAA held in the meeting room of office of SEIAA Haryana, Sector-2

Panchkula, regarding Environmental Clearance under EIA Notification dated

14.9.2006.

The full Authority is present. The Cases recommended by SEAC for

Environmental Clearance or otherwise as listed in the Agenda item circulated vide letter

No. 223-225 dated 22.03.2016 were discussed. Following decisions were taken:-

Item No.[1]Environmental Clearance for construction of Affordable Group Housing

Colony Project at Village Sohna & Khaika, Sector-4, Distt Gurgaon,

Haryana by M/s GLS Infratech Pvt. Ltd.

This case was lastly considered in the 84th meeting of SEIAA held on 29.10.2015

and the case was referred back to SEAC for reconsideration with the following

observations.

1. The project proponent has proposed to develop green area on 15.66% of the

project area whereas in the conditions it has been mentioned that the project

proponent shall maintain 20% green area. The project proponent on 28.10.2015

submitted revised plan showing 20% green area. The SEAC should examine the

same.

2. The SEAC shall ensure that the solid waste generation calculation and parking

calculation is as per latest prescribed norms and shall also ensure that the project

proponent has furnished details of appropriate technology to be adopted for

treatment of bio-degradable waste. The project proponent shall submit plan

depicting the area ear marked for composting.

3. The project proponent shall submit latest undertaking on non judicial stamp paper

stating that no construction has been raised at site duly signed by the director. The

project proponent shall also submit latest photograph of site.

4. The project proponent shall submit solar path analysis.

The SEAC in its 127th meeting held on 16.02.2016 considered the reply dated

24.11.2015 submitted by the project proponent on the above observations and again

recommended this case for environmental clearance. The recommendation of SEAC was

taken up for consideration in the today’s meeting. The reply submitted by project

proponent and considered by SEAC was found in order.

After detailed deliberation, the Authority decided to agree with the

recommendations of SEAC to accord Environment Clearance to this project by imposing

the following condition in addition to the usual conditions in practice.

[1] The project proponent shall install solar panel for energy conservation.

[2] The project proponent shall provide green area on 20.017% of project area.

Page 2: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

2

[3] The project proponent shall essentially provide two numbers of STPs preferably

equivalent to 50% of total capacity or as per the initial occupancy as the case may

be.

[4] Adequate drinking water and sanitary facilities shall be provided for construction

workers at the site. Provision should be made for mobile toilets. Open defecation

by the laboures is strictly prohibited. The safe disposal of solid wastes/ waste water

generated during the construction phase should be ensured. Efforts shall be made to

provide mobile STP for treatment of waste water during the construction phase.

Item No.[2] Environmental Clearance for proposed project 15 Acres “Cyber Park”

at Village-Fazilpur, Jharsa & Bhadshahpur, Sector-69, Gurgaon,

Haryana by M/s Unitech Limited.

The SEAC has recommended this project for Environmental Clearance subject to

stipulation stated therein. The Project Proponent has proposed the construction of “Cyber

Park” at Village-Fazilpur, Jharsa & Bhadshahpur, Sector-69, Gurgaon, Haryana on a plot

area is 60702.75 sqm (15 Acres). The total built up area shall be 349976.90 sqm. The

proposed project shall comprise of 05 Towers in which 4 Basement + GF + maximum 21

floors. The maximum height of the building shall be 95.05 meters. The total water

requirement shall be 1174 KLD. The fresh water requirement shall be 340 KLD. The

waste water generation shall be 878 KLD, which will be treated in the 3 STPs of 500

KLD, 300 KLD & 200 KLD capacities.

The above recommendation of SEAC was taken up for consideration. Detailed

discussions were held regarding water requirement, quality of water, green belt

development plan, Ambient Air Quality, NOC regarding non-involvement of Aravalli

Notification dated 07.05.1992, recycle and reuse of water, parking plan, traffic circulation

etc. It was found that the project proponent submitted the assurance of HUDA for supply

of water along with copies of EDC/IDC paid to HUDA for the services for supply of

water, sewerage connection and drainage system, NOC from DC Gurgaon regarding non

applicability of Aravalli Notification and NOC from AAI regarding height clearance. It

was noticed that the project proponent has proposed to use excavated Top soil for use of

landscaping and has proposed to stack the same in the project area covering the same

with Tarpaulin. The project proponent is required to give exact quantum of Top soil to be

excavated and also brief description for its preservation in order to control its erosion. It

was observed that as a mitigation measure under Water Environment due to improper

disposal of construction debris leading to offsite contamination of water reserves; the

project proponent has proposed disposal of construction debris in low lying area. The

project proponent is required to submit the area identified for the same. It was observed

that the project area is at a distance of 9 km from National Highway and is located along

90 meter wide Southern Peripheral Road and the project proponent on the basis of

PCU/hr calculated for NH-8 and Sohna Road has claimed that since carrying capacity of

Page 3: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

3

NH-8 is much higher than proposed traffic volume therefore the traffic movement from

the proposed Cyber Park will not create any traffic congestion. The project proponent is

required to justify the same with authenticated proof.

In view of the above discussions the Authority decided to defer to this case with

the decision that the project proponent may be asked to submit reply to the below

mentioned observation within 15 days.

[1] The project proponent shall submit the details regarding provisions made for

preservation of Top soil in the project area in order to avoid its erosion.

[2] The project proponent shall submit the details regarding disposal method of

construction debris in the low lying area as reported in the EIA/EMP.

[3] The project proponent shall justify the claim that the carrying capacity of NH-8 is

much higher than the proposed traffic volume and traffic movement from the

proposed project will not create any congestion on NH-8 with calculations and

authenticated proof.

Item No.[3] Environmental Clearance for the proposed ‘Stone Along with

Associated Minor Minerals’ at ‘Ramalwas’ over an area of 12.25 Ha.

In Tehsil-Dadri, District-Bhiwani by M/s Kayden Infra Engineering

Pvt. Ltd.

The SEAC has recommended granting Environment Clearance to M/s Kayden

Infra Engineering Pvt. Ltd. for Mining of Minor Mineral for proposed ‘Ramalwas’ Stone

mines Along with Associated Minor Minerals’ at Village- Ramalwas over an area of

12.25 Ha in Tehsil-Dadri, District-Bhiwani by imposing stipulations stated therein.

The recommendation of SEAC was taken up for consideration in the today’s

meeting. It was noticed that the Mines and Geology Department has granted lease for a

period of 10 years subject to the terms and conditions as indicated in Letter of Intent (LOI)

dated 24.07.2015. The lease has been granted for an area of 12.25 Ha having Khasra no.

105/1, Village- Ramalwas. The project proponent on 12.09.2015 submitted online

application along with copy of approved Mining Plan under category B-2. The validity of

Mining Scheme in the Mining plan is for 5 years. It was noticed that The

Mines & Geology, Department has clarified that no other mine lease exists within 500

meter radius of this mine accordingly the SEAC appraised this project as category B-2.

NOC from Forest Department has been obtained.

Brief details of the project:

1. Category/Item no. (in schedule): 1 (a) B-2

2. Location of Project Village- Ramalwas, Tehsil-Dadri, District-Bhiwani

3. Project Details Khasra No.

Production capacity

Mining of Stone along with Associated

Minerals Ramalwas, Khasra no. 105/1, over an area

of 12.25 Ha

20,00,000 Ton/year

4. Project Cost 8.5 Crores

Page 4: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

4

5. Water Requirement & Source 30 KLD through Tankers

Dust suppression & Wet Drilling 18 KLD

Plantation 9 KLD

Drinking 3 KLD

6. Environment Management Plan

Budget

13.50 lakh

7. CSR Activates Budget 20 Lakh

8. Production (Year wise)

Year Bench mrl Production

First 284 to 254 20,00,000 Ton

Second 254 to 230 20,00,000 Ton

Third 230 to 218 20,00,000 Ton

Fourth 218 to 206 20,00,000 Ton

Fifth 206 to 194 20,00,000 Ton

9. Green belt/ plantation

Year of Plantation Proposed Plantation

I Yr. 250 Trees

II Yr. 250 Trees

III Yr. 250 Trees

IV Yr. 250 Trees

V Yr. 250 Trees

10. Machinery required Excavator, Dozer Crawler Mounted,

Wagon Drill with inbuilt Compressors,

Air Compressor, Rock Breaker,

Diesel Operated Pump, Explosive Van

After detailed deliberations, the Authority decided to agree with the

recommendations of SEAC to accord Environment Clearance to this project by imposing

the following conditions.

A. SPECIFIC CONDITIONS:

[1] This Environment Clearance is granted for Production of Stone along with

Associated Minerals as per below mentioned figures.

Year Bench mrl Production

First 284 to 254 20,00,000 Ton

Second 254 to 230 20,00,000 Ton

Third 230 to 218 20,00,000 Ton

Fourth 218 to 206 20,00,000 Ton

Fifth 206 to 194 20,00,000 Ton

[2] The project proponent shall obtain prior CTO under Air Act and Water Act from

HSPCB and effectively implement all the conditions stipulated by the HSPCB.

[3] The project proponent shall carry out mining activity strictly as per the approved

Mining Plan.

[4] The project proponent shall ensure that the mining operations shall not intersect

groundwater table and the mining operation should be restricted at least 3 meter

above the ground water table.

Page 5: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

5

[5] Topsoil shall be stacked temporarily at earmarked sites only and it shall not be

kept unutilized for a period more than three years; it shall be used for land

reclamation and plantation in mined out areas.

[6] The project proponent shall ensure that no natural water course/water body shall

be obstructed due to any mining operations.

[7] The over burden generated shall be stacked at earmarked dump site (s) only and it

shall not be kept active for long period of time. The maximum height of the

already existing waste dumps shall not exceed 5 meter in single terraces and the

slope angle shall not exceed 28o as per norms.

[8] The dumping site selected and proposed shall be used for OB dump at the

designated site within the lease area as per the approved mine plan. In no case the

overburden should be dumped outside the lease area.

[9] The benches height and slope shall be maintained as per approved mining plan.

[10] Waste dump shall be terraced. The height of the dump and its slope shall not

exceed as suggested in the approved mining plan. A retaining wall shall be

constructed at the toe of the dump.

[11] Garland drains shall be constructed to prevent the flow of the water in the dumps.

[12] Check dams shall be constructed in the seasonal rivulets to prevent the flow of

fines to low lying areas during rains.

[13] The total waste generated in the present plan period shall be as envisaged, which

shall be accommodated in old dumpsite in addition to the waste already dumped.

Monitoring and management of rehabilitated areas shall continue until the

vegetation becomes self sustaining. Compliance status shall be submitted to

HSPCB and MOEF Zonal Office, Chandigarh on six monthly bases.

[14] Drills shall either be operated with dust extractors or equipped with water injection

system.

[15] The higher benches of excavated void/mining pit shall be terraced and plantation

done to stabilize the slopes. The slop of higher benches shall be made gentler for

easy accessibility by local people to use the water body. Peripheral fencing shall

be carried out along the excavated area.

[16] Catch drains and siltation ponds of appropriate size shall be constructed for the

working pit, OB dumps and mineral dumps to arrest flow of silt and sediment. The

water so collected shall be utilized for watering the mine area, roads, green belt

development etc. The drains shall be regularly de-silted, particularly after

monsoon and maintained properly.

[17] Garland drains; setting tanks and check dams of appropriate size, gradient and

length shall be constructed both around the mine pit and over burden dumps and

sump capacity shall be designed keeping 50% safety margin over and above peak

Page 6: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

6

sudden rainfall (based on 50 years data) and maximum discharge in the area

adjoining the mine site. Sump capacity shall also provide adequate pits shall be

constructed at the corners of the garland drains and de-silted.

[18] Dimension of the retaining wall at the toe of dumps and OB benches within the

mine to check run-off and siltation shall be based on the rainfall data.

[19] Green belt should be developed as per the proposed plantation as given in the

proposal. Plantation should be carried out in phased manner. The green belt

should be developed in the safety zone around the mining lease by planting the

native species around ML area, OB dumps, backfilled and reclaimed around water

body, road etc. in consultation with the local DFO/Agriculture Department.

[20] Regular water sprinkling shall be carried out in critical areas prone to air pollution

and having high levels of SPM and RPM such as haul road, loading and unloading

point and transfer points. It shall be ensured that the Ambient Air Quality

Parameters conform to the norms prescribed by the CPCB.

[21] The project authority shall implement suitable conservation measures to augment

ground water resources in the area in consultation with the Regional Director,

Central Ground Water Board.

[22] Regular monitoring of ground water level and quality shall be carried out in and

around the mine lease. The monitoring shall be carried out four times in a year-pre

monsoon (April-May), monsoon (August), post monsoon (November); winter

(January) and the data thus collected may be sent regularly to MOEF Regional

Office, Chandigarh and Regional Director CGWB.

[23] Data on ambient air quality and stack emissions shall be submitted to Haryana

Pollution Control Board once in six months carried out by

MOEF/NABL/CPCB/Government approved lab.

[24] Vehicular emissions shall be kept under control and regularly monitored.

Measures shall be taken for maintenance of vehicles used in mining operations and

in transportation of mineral. The vehicles shall be covered with a tarpaulin and

shall not be overloaded. The project proponent shall ensure that the vehicle must

have pollution under control certificate.

[25] Blasting operation shall be carried out only during the daytime. Controlled

blasting shall be practiced. The mitigation measures for control of ground

vibrations and to arrest fly rocks and boulders shall be implemented.

[26] The blasting operation will be carried out as per the norms of Director (Mines &

Safety), Gaziabad. Take all safety measures as per the various mining regulations.

[27] The project proponent shall take all precautionary measures during mining

operations for conservation and protection of endangered fauna, if any, spotted in

the study area. A plan for conservation shall be drawn and approved by the State

Page 7: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

7

Wildlife Department. Necessary allocation of funds for implementation of the

conservation plan shall be made and the funds so allocated shall be included in the

project cost. All the safeguard measures brought out in the wildlife conservation

plan so prepared specific to the project site shall be effectively implemented. A

copy of action plan may be submitted to the HSPCB and MOEF, Regional Office,

Chandigarh within 3 months.

[28] As envisaged, the Project Proponent shall invest at least an amount of Rs. 13.50

lakh as cost for implementing various environmental protection measures

including recurring expenses per year.

[29] A sum of Rs. 20 lakh shall be earmarked by the Project proponent for

investment as CSR on socio economic up-liftment activities of the area

particularly in the area of habitat, health or education, training programme of rural

women & man provide the kit for employment generation. The proposal should

contain provision for monthly medical camps, distributions of medicines and

improvement in educational facilities in the nearby schools. Details of such

activity along with time bound action plan be submitted to HSPCB/SEIAA

Haryana before the start of operation.

[30] Budgetary provision of Rs. 05 lakh per year earmarked for the labours working in

the Mine for all necessary infrastructure facilities such as health facility, sanitation

facility, fuel for cooking, along with safe drinking water, medical camps and

toilets for women, crèche for infants should be made and submitted to HSPCB at

the time of CTO/SEIAA Haryana. The housing facilities should be provided

for mining labours.

[31] A Final Mine Closure Plan along with details of corpus fund shall be submitted to

the SEIAA well within the stipulated period as prescribed in the minor mineral

concession rules 2012.

[32] The water reservoir, which would be created/available during post closure (all

pits), shall be provided with suitable benches and fencing to provide the access to

the water body and safety.

[33] The project proponent shall ensure that the EC letter as well as the status of

compliance of EC conditions and the monitoring data are placed on company’s

website and displayed at the project site.

[34] The project proponent shall ensure that loading in Trucks do not exceed the norms

fixed by the Transport Department as per relevant rules.

[35] The project proponent shall ensure approach roads are widened and strengthened

as per requirements fixed by PWD and district administration before the start of

the work.

Page 8: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

8

[36] The project proponent shall ensure that all measures are taken simultaneously for

safeguard and maintenance of the health of the workers.

[37] The project proponent shall ensure supply of drinking water through RO.

GENERAL CONDITIONS:

[i] Any change in mining technology/scope of working shall not be made without

prior approval of the SEIAA.

[ii] Any change in the calendar plan including excavation, quantum of mineral and

waste shall not be made.

[iii] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5,

SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided

based on the meteorological data, topographical features and environmentally and

ecologically sensitive targets and frequency of monitoring shall be decided in

consultation with the Haryana State Pollution Control Board (HSPCB). Six

monthly reports of the data so collected shall be regularly submitted to the

HSPCB/CPCB including the MOEF, Regional office, Chandigarh.

[iv] Measures shall be taken for control of noise levels below 85 dBA in the work

environment. Workers engaged in operations of HEMM etc. shall be provided

with earplugs/muffs.

[v] Waste water (workshop and waste water from the mine) shall be properly

collected & treated so as to conform to the standards prescribed under GSR 422

(E) dated 19th May 93 and 31st December 1993 (amended to date). Oil and grease

trap shall be installed before discharge.

[vi] Personnel working in dusty areas shall wear protective respiratory devices they

shall also be provided with adequate training and information on safety and health

aspects.

[vii] Occupational health surveillance program of the workers shall be undertaken

periodically to observe any contractions due to exposure to dust and take

corrective measures, if needed.

[viii] The funds earmarked for environmental protection measures shall be kept in

separate account and shall not be diverted for other purpose. Year wise

expenditure shall be reported to the HSPCB and the Regional office of MOEF

located at Chandigarh.

[ix] The project proponent shall also submit six monthly reports on the status of

compliance of the stipulated EC conditions including results of monitored data

(both in hard copies as well as by e-mail) to the northern Regional Office of

MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana.

[x] The SEIAA, Haryana reserves the right to add new conditions, modify/annual any

of the stipulated conditions and/or to revoke the clearance if implementation of

Page 9: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

9

any of the condition stipulated by SEIAA, Haryana or any other competent

authorities is not satisfactory.

[xi] Failure to comply with any of the conditions mentioned above may result in

withdrawal of this clearance and attract action under the provisions of

Environment (Protection) Act, 1986.

[xii] The above conditions will be enforced, inter alia, under the provision of the Water

(Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of

Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public

Liability Insurance Act 1991 (all amended till date) and rules made hereunder and

also any other orders passed by the Honb’le Supreme Court of India/High Court of

Haryana and other Court of law relating to the subject matter.

[xiii] The Project proponent should inform the public that the project has been accorded

Environment Clearance by the SEIAA and copies of the clearance letter are

available with the Haryana State Pollution Control Board & SEIAA. This should

be advertised within 7 days from the date of issue of the clearance letter at least in

two local newspapers that are widely circulated in the region and the copy of the

same should be forwarded to SEIAA Haryana. A copy of Environment Clearance

conditions shall also be put on project proponent’s web site for public awareness.

[xiv] All the other statutory clearances such as the approvals for storage of diesel from

the Chief Controller of Explosives, Fire department, Civil Aviation Department,

Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be

obtained, as may be applicable, by Project proponent from the competent authority

before the start of mining operation.

[xv] That the grant of this EC is issued from the environmental angle only, and does

not absolve the project proponent from the other statutory obligations prescribed

under any other law or any other instrument in force. The sole and complete

responsibility, to comply with the conditions laid down in all other laws for the

time being in force, rests with the industry/unit/project proponent. Any appeal

against this environmental clearance shall lie with the National Green Tribunal, if

preferred, within a period of 30 days as prescribed under section 16 of National

Green Tribunal Act, 2010.

Item No.[4] Environmental Clearance for the proposed “Stone Along with

Associated Minor Minerals’ at ‘Maikalan & Maikhurd’ over an area of

3.65 Ha. In Tehsil Dadri, District-Bhiwani by M/s Hari Har Mining

Company.

The SEAC has recommended granting Environment Clearance to M/s Hari Har

Mining Company for Mining of Minor Mineral for proposed ‘‘Maikalan & Maikhurd’

Stone mines Along with Associated Minor Minerals’ at Village- Maikalan & Maikhurd

over an area of 3.65 Ha. In Tehsil Dadri, District-Bhiwani by imposing stipulations stated

therein.

Page 10: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

10

The recommendation of SEAC was taken up for consideration in the today’s

meeting. It was observed that the mine lease area is less than 5 Ha and as such the

environmental clearance in this case is to be granted by DEIAA/DEAC in view of

amendment to the Notification dated 15.01.2016. It was found that MoEF & CC, GoI vide

letter no. Z-11013/8/2016-IA.II (M) dated 15.03.2016 has clarified that where SEAC has

recommended the cases for environmental clearance such cases are to be processed at the

level of SEIAA for grant of environmental clearance. Accordingly it was decided to take

up the case as recommended by SEAC. It was noticed that the Mines and Geology

Department has granted lease for a period of 10 years subject to the terms and conditions

as indicated in Letter of Intent (LOI) dated 24.07.2015. The lease has been granted for an

area of 3.65 Ha having Khasra no. 315, 230 & 233 village- Maikalan & Maikhurd. The

project proponent on 13.08.2015 submitted online application along with copy of approved

Mining Plan under category B-2. The validity of Mining Scheme in the Mining plan is for

5 years. It was noticed that The Mines & Geology, Department has clarified that no other

mine lease exists within 500 meter radius of this mine accordingly the SEAC appraised

this project as category B-2. NOC from Forest Department has been obtained.

Brief details of the project:

1. Category/Item no. (in schedule): 1 (a) B-2

2. Location of Project Village- Maikalan & Maikhurd Tehsil Dadri,

District-Bhiwani

3. Project Details Khasra No.

Production capacity

Mining of Stone along with Associated

Minerals Maikalan & Maikhurd, Khasra no315, 230

& 233, over an area of 3.65 Ha

10,00,000 TPA

4. Project Cost 2.5 Crores

5. Water Requirement & Source 22 KLD through Tankers

Dust suppression & Wet Drilling 14 KLD

Plantation 6 KLD

Drinking 2 KLD

6. Environment Management Plan

Budget

11.50 lakh

7. CSR Activates Budget 17 Lakh

8. Production (Year wise)

Year Bench mrl Production

First 330 to 300 10,00,000 TPA

Second 300 to 289 10,00,000 TPA

Third 289 to 282 10,00,000 TPA

Fourth 282 to 270 10,00,000 TPA

Fifth 270 to 250 10,00,000 TPA

Page 11: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

11

9. Green belt/ plantation

Year of Plantation Proposed Plantation

I Yr. 200 Trees

II Yr. 200 Trees

III Yr. 200 Trees

IV Yr. 200 Trees

V Yr. 200 Trees

10. Machinery required Excavator, Dozer Crawler Mounted,

Wagon Drill with inbuilt Compressors,

Air Compressor, Rock Breaker,

Diesel Operated Pump, Explosive Van

After detailed deliberations, the Authority decided to agree with the

recommendations of SEAC to accord Environment Clearance to this project by imposing

the following conditions.

A. SPECIFIC CONDITIONS:

[1] This Environment Clearance is granted for Production of Stone along with

Associated Minerals as per below mentioned figures.

Year Bench mrl Production

First 330 to 300 10,00,000 TPA

Second 300 to 289 10,00,000 TPA

Third 289 to 282 10,00,000 TPA

Fourth 282 to 270 10,00,000 TPA

Fifth 270 to 250 10,00,000 TPA

[2] The project proponent shall obtain prior CTO under Air Act and Water Act from

HSPCB and effectively implement all the conditions stipulated by the HSPCB.

[3] The project proponent shall carry out mining activity strictly as per the approved

Mining Plan.

[4] The project proponent shall ensure that the mining operations shall not intersect

groundwater table and the mining operation should be restricted at least 3 meter

above the ground water table.

[5] Topsoil shall be stacked temporarily at earmarked sites only and it shall not be

kept unutilized for a period more than three years; it shall be used for land

reclamation and plantation in mined out areas.

[6] The project proponent shall ensure that no natural water course/water body shall

be obstructed due to any mining operations.

[7] The over burden generated shall be stacked at earmarked dump site (s) only and it

shall not be kept active for long period of time. The maximum height of the

already existing waste dumps shall not exceed 5 meter in single terraces and the

slope angle shall not exceed 28o as per norms.

[8] The dumping site selected and proposed shall be used for OB dump at the

designated site within the lease area as per the approved mine plan. In no case the

overburden should be dumped outside the lease area.

Page 12: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

12

[9] The benches height and slope shall be maintained as per approved mining plan.

[10] Waste dump shall be terraced. The height of the dump and its slope shall not

exceed as suggested in the approved mining plan. A retaining wall shall be

constructed at the toe of the dump.

[11] Garland drains shall be constructed to prevent the flow of the water in the dumps.

[12] Check dams shall be constructed in the seasonal rivulets to prevent the flow of

fines to low lying areas during rains.

[13] The total waste generated in the present plan period shall be as envisaged, which

shall be accommodated in old dumpsite in addition to the waste already dumped.

Monitoring and management of rehabilitated areas shall continue until the

vegetation becomes self sustaining. Compliance status shall be submitted to

HSPCB and MOEF Zonal Office, Chandigarh on six monthly bases.

[14] Drills shall either be operated with dust extractors or equipped with water injection

system.

[15] The higher benches of excavated void/mining pit shall be terraced and plantation

done to stabilize the slopes. The slop of higher benches shall be made gentler for

easy accessibility by local people to use the water body. Peripheral fencing shall

be carried out along the excavated area.

[16] Catch drains and siltation ponds of appropriate size shall be constructed for the

working pit, OB dumps and mineral dumps to arrest flow of silt and sediment. The

water so collected shall be utilized for watering the mine area, roads, green belt

development etc. The drains shall be regularly de-silted, particularly after

monsoon and maintained properly.

[17] Garland drains; setting tanks and check dams of appropriate size, gradient and

length shall be constructed both around the mine pit and over burden dumps and

sump capacity shall be designed keeping 50% safety margin over and above peak

sudden rainfall (based on 50 years data) and maximum discharge in the area

adjoining the mine site. Sump capacity shall also provide adequate pits shall be

constructed at the corners of the garland drains and de-silted.

[18] Dimension of the retaining wall at the toe of dumps and OB benches within the

mine to check run-off and siltation shall be based on the rainfall data.

[19] Green belt should be developed as per the proposed plantation as given in the

proposal. Plantation should be carried out in phased manner. The green belt

should be developed in the safety zone around the mining lease by planting the

native species around ML area, OB dumps, backfilled and reclaimed around water

body, road etc. in consultation with the local DFO/Agriculture Department.

[20] Regular water sprinkling shall be carried out in critical areas prone to air pollution

and having high levels of SPM and RPM such as haul road, loading and unloading

Page 13: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

13

point and transfer points. It shall be ensured that the Ambient Air Quality

Parameters conform to the norms prescribed by the CPCB.

[21] The project authority shall implement suitable conservation measures to augment

ground water resources in the area in consultation with the Regional Director,

Central Ground Water Board.

[22] Regular monitoring of ground water level and quality shall be carried out in and

around the mine lease. The monitoring shall be carried out four times in a year-pre

monsoon (April-May), monsoon (August), post monsoon (November); winter

(January) and the data thus collected may be sent regularly to MOEF Regional

Office, Chandigarh and Regional Director CGWB.

[23] Data on ambient air quality and stack emissions shall be submitted to Haryana

Pollution Control Board once in six months carried out by

MOEF/NABL/CPCB/Government approved lab.

[24] Vehicular emissions shall be kept under control and regularly monitored.

Measures shall be taken for maintenance of vehicles used in mining operations and

in transportation of mineral. The vehicles shall be covered with a tarpaulin and

shall not be overloaded. The project proponent shall ensure that the vehicle must

have pollution under control certificate.

[25] Blasting operation shall be carried out only during the daytime. Controlled

blasting shall be practiced. The mitigation measures for control of ground

vibrations and to arrest fly rocks and boulders shall be implemented.

[26] The blasting operation will be carried out as per the norms of Director (Mines &

Safety), Gaziabad. Take all safety measures as per the various mining regulations.

[27] The project proponent shall take all precautionary measures during mining

operations for conservation and protection of endangered fauna, if any, spotted in

the study area. A plan for conservation shall be drawn and approved by the State

Wildlife Department. Necessary allocation of funds for implementation of the

conservation plan shall be made and the funds so allocated shall be included in the

project cost. All the safeguard measures brought out in the wildlife conservation

plan so prepared specific to the project site shall be effectively implemented. A

copy of action plan may be submitted to the HSPCB and MOEF, Regional Office,

Chandigarh within 3 months.

[28] As envisaged, the Project Proponent shall invest at least an amount of Rs. 11.50

lakh as cost for implementing various environmental protection measures

including recurring expenses per year.

[29] A sum of Rs. 17 lakh shall be earmarked by the Project proponent for

investment as CSR on socio economic up-liftment activities of the area

particularly in the area of habitat, health or education, training programme of rural

Page 14: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

14

women & man provide the kit for employment generation. The proposal should

contain provision for monthly medical camps, distributions of medicines and

improvement in educational facilities in the nearby schools. Details of such

activity along with time bound action plan be submitted to HSPCB/SEIAA

Haryana before the start of operation.

[30] Budgetary provision of Rs. 05 lakh per year earmarked for the labours working in

the Mine for all necessary infrastructure facilities such as health facility, sanitation

facility, fuel for cooking, along with safe drinking water, medical camps and

toilets for women, crèche for infants should be made and submitted to HSPCB at

the time of CTO/SEIAA Haryana. The housing facilities should be provided

for mining labours.

[31] A Final Mine Closure Plan along with details of corpus fund shall be submitted to

the SEIAA well within the stipulated period as prescribed in the minor mineral

concession rules 2012.

[32] The water reservoir, which would be created/available during post closure (all

pits), shall be provided with suitable benches and fencing to provide the access to

the water body and safety.

[33] The project proponent shall ensure that the EC letter as well as the status of

compliance of EC conditions and the monitoring data are placed on company’s

website and displayed at the project site.

[34] The project proponent shall ensure that loading in Trucks do not exceed the norms

fixed by the Transport Department as per relevant rules.

[35] The project proponent shall ensure approach roads are widened and strengthened

as per requirements fixed by PWD and district administration before the start of

the work.

[36] The project proponent shall ensure that all measures are taken simultaneously for

safeguard and maintenance of the health of the workers.

[37] The project proponent shall ensure supply of drinking water through RO.

GENERAL CONDITIONS:

[i] Any change in mining technology/scope of working shall not be made without

prior approval of the SEIAA.

[ii] Any change in the calendar plan including excavation, quantum of mineral and

waste shall not be made.

[iii] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5,

SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided

based on the meteorological data, topographical features and environmentally and

ecologically sensitive targets and frequency of monitoring shall be decided in

consultation with the Haryana State Pollution Control Board (HSPCB). Six

Page 15: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

15

monthly reports of the data so collected shall be regularly submitted to the

HSPCB/CPCB including the MOEF, Regional office, Chandigarh.

[iv] Measures shall be taken for control of noise levels below 85 dBA in the work

environment. Workers engaged in operations of HEMM etc. shall be provided

with earplugs/muffs.

[v] Waste water (workshop and waste water from the mine) shall be properly

collected & treated so as to conform to the standards prescribed under GSR 422

(E) dated 19th May 93 and 31st December 1993 (amended to date). Oil and grease

trap shall be installed before discharge.

[vi] Personnel working in dusty areas shall wear protective respiratory devices they

shall also be provided with adequate training and information on safety and health

aspects.

[vii] Occupational health surveillance program of the workers shall be undertaken

periodically to observe any contractions due to exposure to dust and take

corrective measures, if needed.

[viii] The funds earmarked for environmental protection measures shall be kept in

separate account and shall not be diverted for other purpose. Year wise

expenditure shall be reported to the HSPCB and the Regional office of MOEF

located at Chandigarh.

[ix] The project proponent shall also submit six monthly reports on the status of

compliance of the stipulated EC conditions including results of monitored data

(both in hard copies as well as by e-mail) to the northern Regional Office of

MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana.

[x] The SEIAA, Haryana reserves the right to add new conditions, modify/annual any

of the stipulated conditions and/or to revoke the clearance if implementation of

any of the condition stipulated by SEIAA, Haryana or any other competent

authorities is not satisfactory.

[xi] Failure to comply with any of the conditions mentioned above may result in

withdrawal of this clearance and attract action under the provisions of

Environment (Protection) Act, 1986.

[xii] The above conditions will be enforced, inter alia, under the provision of the Water

(Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of

Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public

Liability Insurance Act 1991 (all amended till date) and rules made hereunder and

also any other orders passed by the Honb’le Supreme Court of India/High Court of

Haryana and other Court of law relating to the subject matter.

[xiii] The Project proponent should inform the public that the project has been accorded

Environment Clearance by the SEIAA and copies of the clearance letter are

Page 16: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

16

available with the Haryana State Pollution Control Board & SEIAA. This should

be advertised within 7 days from the date of issue of the clearance letter at least in

two local newspapers that are widely circulated in the region and the copy of the

same should be forwarded to SEIAA Haryana. A copy of Environment Clearance

conditions shall also be put on project proponent’s web site for public awareness.

[xiv] All the other statutory clearances such as the approvals for storage of diesel from

the Chief Controller of Explosives, Fire department, Civil Aviation Department,

Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be

obtained, as may be applicable, by Project proponent from the competent authority

before the start of mining operation.

[xv] That the grant of this EC is issued from the environmental angle only, and does

not absolve the project proponent from the other statutory obligations prescribed

under any other law or any other instrument in force. The sole and complete

responsibility, to comply with the conditions laid down in all other laws for the

time being in force, rests with the industry/unit/project proponent. Any appeal

against this environmental clearance shall lie with the National Green Tribunal, if

preferred, within a period of 30 days as prescribed under section 16 of National

Green Tribunal Act, 2010.

Item No.[5] Environmental Clearance for proposed “Stone Along with Associated

Minor Minerals” at Karota over an area of 9.55 Ha. under Category

“B2” in Tehsil-Narnaul, District-Mahendergarh by M/s HGEL

Integrated Pvt. Ltd.

The SEAC has recommended to accord Environment Clearance to M/s HGEL

Integrated Pvt. Ltd. for Mining of Minor Mineral for proposed “Karota” Stone mines

Along with Associated Minor Minerals’ at Village- Karota over an area of 9.55 Ha in

Tehsil-Narnaul, District-Mahendergarh by imposing stipulations stated therein.

The recommendation of SEAC was taken up for consideration in the today’s

meeting. It was noticed that the Mines and Geology Department has granted lease for a

period of 10 years subject to the terms and conditions as indicated in Letter of Intent (LOI)

dated 02.09.2015. The lease has been granted for an area of 9.55 Ha having Khasra no. 61

min village- Karota. The project proponent on 19.10.2015 submitted online application

along with copy of approved Mining Plan under category B-2. The validity of Mining

Scheme in the Mining plan is for 5 years. It was noticed that The Mines & Geology,

Department has clarified that no other mine lease exists within 500 meter radius of this

mine accordingly the SEAC appraised this project as category B-2. NOC from Forest

Department has been obtained.

Brief details of the project:

1. Category/Item no. (in schedule): 1 (a) B-2

2. Location of Project Village- Karota Tehsil-Narnaul, District-

Mahendergarh

Page 17: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

17

3. Project Details Khasra No.

Production capacity

Mining of Stone along with Associated

Minerals Karota, Khasra no. 61 min, over an area of

9.55 Ha

15,00,000 TPA

4. Project Cost 7.30 Crores

5. Water Requirement & Source 30 KLD through Tankers

Dust suppression & Wet Drilling 19 KLD

Plantation 8 KLD

Drinking 3 KLD

6. Environment Management Plan

Budget

16 lakh

7. CSR Activates Budget 23 Lakh

8. Production (Year wise)

Year Bench mrl Production

First 348 to 330 15,00,000 TPA

Second 330 to 318 15,00,000 TPA

Third 318 to 300 15,00,000 TPA

Fourth 300 to 282 15,00,000 TPA

Fifth 282 to 270 15,00,000 TPA

9. Green belt/ plantation

Year of Plantation Proposed Plantation

I Yr. 200 Trees

II Yr. 200 Trees

III Yr. 200 Trees

IV Yr. 200 Trees

V Yr. 200 Trees

10. Machinery required Excavator, Dozer Crawler Mounted,

Wagon Drill with inbuilt Compressors,

Air Compressor, Rock Breaker,

Diesel Operated Pump, Explosive Van

After detailed deliberations, the Authority decided to agree with the

recommendations of SEAC to accord Environment Clearance to this project by imposing

the following conditions.

A. SPECIFIC CONDITIONS:

[1] This Environment Clearance is granted for Production of Stone along with

Associated Minerals as per below mentioned figures.

Year Bench mrl Production

First 348 to 330 15,00,000 TPA

Second 330 to 318 15,00,000 TPA

Third 318 to 300 15,00,000 TPA

Fourth 300 to 282 15,00,000 TPA

Fifth 282 to 270 15,00,000 TPA

[2] The project proponent shall obtain prior CTO under Air Act and Water Act from

HSPCB and effectively implement all the conditions stipulated by the HSPCB.

Page 18: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

18

[3] The project proponent shall carry out mining activity strictly as per the approved

Mining Plan.

[4] The project proponent shall ensure that the mining operations shall not intersect

groundwater table and the mining operation should be restricted at least 3 meter

above the ground water table.

[5] Topsoil shall be stacked temporarily at earmarked sites only and it shall not be

kept unutilized for a period more than three years; it shall be used for land

reclamation and plantation in mined out areas.

[6] The project proponent shall ensure that no natural water course/water body shall

be obstructed due to any mining operations.

[7] The over burden generated shall be stacked at earmarked dump site (s) only and it

shall not be kept active for long period of time. The maximum height of the

already existing waste dumps shall not exceed 5 meter in single terraces and the

slope angle shall not exceed 28o as per norms.

[8] The dumping site selected and proposed shall be used for OB dump at the

designated site within the lease area as per the approved mine plan. In no case the

overburden should be dumped outside the lease area.

[9] The benches height and slope shall be maintained as per approved mining plan.

[10] Waste dump shall be terraced. The height of the dump and its slope shall not

exceed as suggested in the approved mining plan. A retaining wall shall be

constructed at the toe of the dump.

[11] Garland drains shall be constructed to prevent the flow of the water in the dumps.

[12] Check dams shall be constructed in the seasonal rivulets to prevent the flow of

fines to low lying areas during rains.

[13] The total waste generated in the present plan period shall be as envisaged, which

shall be accommodated in old dumpsite in addition to the waste already dumped.

Monitoring and management of rehabilitated areas shall continue until the

vegetation becomes self sustaining. Compliance status shall be submitted to

HSPCB and MOEF Zonal Office, Chandigarh on six monthly bases.

[14] Drills shall either be operated with dust extractors or equipped with water injection

system.

[15] The higher benches of excavated void/mining pit shall be terraced and plantation

done to stabilize the slopes. The slop of higher benches shall be made gentler for

easy accessibility by local people to use the water body. Peripheral fencing shall

be carried out along the excavated area.

[16] Catch drains and siltation ponds of appropriate size shall be constructed for the

working pit, OB dumps and mineral dumps to arrest flow of silt and sediment. The

water so collected shall be utilized for watering the mine area, roads, green belt

Page 19: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

19

development etc. The drains shall be regularly de-silted, particularly after

monsoon and maintained properly.

[17] Garland drains; setting tanks and check dams of appropriate size, gradient and

length shall be constructed both around the mine pit and over burden dumps and

sump capacity shall be designed keeping 50% safety margin over and above peak

sudden rainfall (based on 50 years data) and maximum discharge in the area

adjoining the mine site. Sump capacity shall also provide adequate pits shall be

constructed at the corners of the garland drains and de-silted.

[18] Dimension of the retaining wall at the toe of dumps and OB benches within the

mine to check run-off and siltation shall be based on the rainfall data.

[19] Green belt should be developed as per the proposed plantation as given in the

proposal. Plantation should be carried out in phased manner. The green belt

should be developed in the safety zone around the mining lease by planting the

native species around ML area, OB dumps, backfilled and reclaimed around water

body, road etc. in consultation with the local DFO/Agriculture Department.

[20] Regular water sprinkling shall be carried out in critical areas prone to air pollution

and having high levels of SPM and RPM such as haul road, loading and unloading

point and transfer points. It shall be ensured that the Ambient Air Quality

Parameters conform to the norms prescribed by the CPCB.

[21] The project authority shall implement suitable conservation measures to augment

ground water resources in the area in consultation with the Regional Director,

Central Ground Water Board.

[22] Regular monitoring of ground water level and quality shall be carried out in and

around the mine lease. The monitoring shall be carried out four times in a year-pre

monsoon (April-May), monsoon (August), post monsoon (November); winter

(January) and the data thus collected may be sent regularly to MOEF Regional

Office, Chandigarh and Regional Director CGWB.

[23] Data on ambient air quality and stack emissions shall be submitted to Haryana

Pollution Control Board once in six months carried out by

MOEF/NABL/CPCB/Government approved lab.

[24] Vehicular emissions shall be kept under control and regularly monitored.

Measures shall be taken for maintenance of vehicles used in mining operations and

in transportation of mineral. The vehicles shall be covered with a tarpaulin and

shall not be overloaded. The project proponent shall ensure that the vehicle must

have pollution under control certificate.

[25] Blasting operation shall be carried out only during the daytime. Controlled

blasting shall be practiced. The mitigation measures for control of ground

vibrations and to arrest fly rocks and boulders shall be implemented.

Page 20: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

20

[26] The blasting operation will be carried out as per the norms of Director (Mines &

Safety), Gaziabad. Take all safety measures as per the various mining regulations.

[27] The project proponent shall take all precautionary measures during mining

operations for conservation and protection of endangered fauna, if any, spotted in

the study area. A plan for conservation shall be drawn and approved by the State

Wildlife Department. Necessary allocation of funds for implementation of the

conservation plan shall be made and the funds so allocated shall be included in the

project cost. All the safeguard measures brought out in the wildlife conservation

plan so prepared specific to the project site shall be effectively implemented. A

copy of action plan may be submitted to the HSPCB and MOEF, Regional Office,

Chandigarh within 3 months.

[28] As envisaged, the Project Proponent shall invest at least an amount of Rs. 16

lakh as cost for implementing various environmental protection measures

including recurring expenses per year.

[29] A sum of Rs. 23 lakh shall be earmarked by the Project proponent for

investment as CSR on socio economic up-liftment activities of the area

particularly in the area of habitat, health or education, training programme of rural

women & man provide the kit for employment generation. The proposal should

contain provision for monthly medical camps, distributions of medicines and

improvement in educational facilities in the nearby schools. Details of such

activity along with time bound action plan be submitted to HSPCB/SEIAA

Haryana before the start of operation.

[30] Budgetary provision of Rs. 05 lakh per year earmarked for the labours working in

the Mine for all necessary infrastructure facilities such as health facility, sanitation

facility, fuel for cooking, along with safe drinking water, medical camps and

toilets for women, crèche for infants should be made and submitted to HSPCB at

the time of CTO/SEIAA Haryana. The housing facilities should be provided

for mining labours.

[31] A Final Mine Closure Plan along with details of corpus fund shall be submitted to

the SEIAA well within the stipulated period as prescribed in the minor mineral

concession rules 2012.

[32] The water reservoir, which would be created/available during post closure (all

pits), shall be provided with suitable benches and fencing to provide the access to

the water body and safety.

[33] The project proponent shall ensure that the EC letter as well as the status of

compliance of EC conditions and the monitoring data are placed on company’s

website and displayed at the project site.

Page 21: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

21

[34] The project proponent shall ensure that loading in Trucks do not exceed the norms

fixed by the Transport Department as per relevant rules.

[35] The project proponent shall ensure approach roads are widened and strengthened

as per requirements fixed by PWD and district administration before the start of

the work.

[36] The project proponent shall ensure that all measures are taken simultaneously for

safeguard and maintenance of the health of the workers.

[37] The project proponent shall ensure supply of drinking water through RO.

GENERAL CONDITIONS:

[i] Any change in mining technology/scope of working shall not be made without

prior approval of the SEIAA.

[ii] Any change in the calendar plan including excavation, quantum of mineral and

waste shall not be made.

[iii] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5,

SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided

based on the meteorological data, topographical features and environmentally and

ecologically sensitive targets and frequency of monitoring shall be decided in

consultation with the Haryana State Pollution Control Board (HSPCB). Six

monthly reports of the data so collected shall be regularly submitted to the

HSPCB/CPCB including the MOEF, Regional office, Chandigarh.

[iv] Measures shall be taken for control of noise levels below 85 dBA in the work

environment. Workers engaged in operations of HEMM etc. shall be provided

with earplugs/muffs.

[v] Waste water (workshop and waste water from the mine) shall be properly

collected & treated so as to conform to the standards prescribed under GSR 422

(E) dated 19th May 93 and 31st December 1993 (amended to date). Oil and grease

trap shall be installed before discharge.

[vi] Personnel working in dusty areas shall wear protective respiratory devices they

shall also be provided with adequate training and information on safety and health

aspects.

[vii] Occupational health surveillance program of the workers shall be undertaken

periodically to observe any contractions due to exposure to dust and take

corrective measures, if needed.

[viii] The funds earmarked for environmental protection measures shall be kept in

separate account and shall not be diverted for other purpose. Year wise

expenditure shall be reported to the HSPCB and the Regional office of MOEF

located at Chandigarh.

Page 22: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

22

[ix] The project proponent shall also submit six monthly reports on the status of

compliance of the stipulated EC conditions including results of monitored data

(both in hard copies as well as by e-mail) to the northern Regional Office of

MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana.

[x] The SEIAA, Haryana reserves the right to add new conditions, modify/annual any

of the stipulated conditions and/or to revoke the clearance if implementation of

any of the condition stipulated by SEIAA, Haryana or any other competent

authorities is not satisfactory.

[xi] Failure to comply with any of the conditions mentioned above may result in

withdrawal of this clearance and attract action under the provisions of

Environment (Protection) Act, 1986.

[xii] The above conditions will be enforced, inter alia, under the provision of the Water

(Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of

Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public

Liability Insurance Act 1991 (all amended till date) and rules made hereunder and

also any other orders passed by the Honb’le Supreme Court of India/High Court of

Haryana and other Court of law relating to the subject matter.

[xiii] The Project proponent should inform the public that the project has been accorded

Environment Clearance by the SEIAA and copies of the clearance letter are

available with the Haryana State Pollution Control Board & SEIAA. This should

be advertised within 7 days from the date of issue of the clearance letter at least in

two local newspapers that are widely circulated in the region and the copy of the

same should be forwarded to SEIAA Haryana. A copy of Environment Clearance

conditions shall also be put on project proponent’s web site for public awareness.

[xiv] All the other statutory clearances such as the approvals for storage of diesel from

the Chief Controller of Explosives, Fire department, Civil Aviation Department,

Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be

obtained, as may be applicable, by Project proponent from the competent authority

before the start of mining operation.

[xv] That the grant of this EC is issued from the environmental angle only, and does

not absolve the project proponent from the other statutory obligations prescribed

under any other law or any other instrument in force. The sole and complete

responsibility, to comply with the conditions laid down in all other laws for the

time being in force, rests with the industry/unit/project proponent. Any appeal

against this environmental clearance shall lie with the National Green Tribunal, if

preferred, within a period of 30 days as prescribed under section 16 of National

Green Tribunal Act, 2010.

Page 23: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

23

Item No.[6] Environmental Clearance for proposed Mining of Boulder, Gravel and

Sand (Minor Mineral) at Bhood Kalan Block /YNR B-19 over an area

of 12.62 Ha. in District Yamuna Nagar, Haryana by M/s Ganga

Yamuna Mining Co.

The SEAC has recommended to grant Environment Clearance to M/s Ganga

Yamuna Mining Co. for Mining of Boulder, Gravel and Sand of “Bhood Kalan Block

/YNR B-19” at Village- Bhood Kalan over an area of 12.62 Ha by imposing stipulations

stated therein.

The recommendation of SEAC was taken up for consideration in the today’s

meeting. It was noticed that the Mines and Geology Department has granted lease for a

period of 07 years subject to the terms and conditions as indicated in Letter of Intent (LOI)

dated 19.06.2015. The lease has been granted for an area of 12.62 Ha having Village-

Bhood Kalan Block /YNR B-19. The project proponent on 11.09.2015 submitted online

application along with copy of approved Mining Plan under category B-2. The validity of

Mining Scheme in the Mining plan is for 5 years. It was noticed that The

Mines & Geology, Department has clarified that no other mine lease exists within 500

meter radius of this mine accordingly the SEAC appraised this project as category B-2.

NOC from Forest Department has been obtained.

Brief details of the project:

1. Category/Item no. (in schedule): 1 (a) B-2

2. Location of Project Village- Bhood Kalan Block /YNR B-19 District

Yamuna Nagar

3. Project Details Khasra No.

Production capacity

Mining of Boulder, Gravel and Sand (Minor

Mineral) Bhood Kalan Block /YNR B-19, over area

of 12.62 Ha

2,59,000 TPA @35 Trips/day (25 Mt/Trip)

4. Project Cost 4 Crores

5. Water Requirement & Source 26 KLD through Tankers

Dust suppression & Wet Drilling 12 KLD

Plantation 12 KLD

Drinking 2 KLD

6. Environment Management Plan

Budget

9.25 lakh

7. CSR Activates Budget 10.25 Lakh

8. Production The proposed production for the five years is @

2,59,000 TPA. The ultimate depth of Mining will

be 9 meter. The alivation range of mine site is 297-

298 armsl.

9. Corner Coordinates of the lease

area

Corners Latitudes Longitudes

A N 30O 15’21.9” E077O 29’37.4”

B N 30O 15’29.8” E077O 29’37.5”

C N 30O 15’17.5” E077O 29’52.7”

D N 30O 15’21.6” E077O 29’42.2”

Page 24: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

24

10. Green belt/ plantation

Year of Plantation Proposed Plantation

I Yr. 400 Trees

II Yr. 400 Trees

III Yr. 400 Trees

IV Yr. 400 Trees

V Yr. 400 Trees

11. Machinery required Excavator, Tipers/Trucks, Water Tanker Light

Vehicles/Geep and Maintaniance Van

After detailed deliberations, the Authority decided to agree with the

recommendations of SEAC to accord Environment Clearance to this project by imposing

the following conditions.

A. SPECIFIC CONDITIONS:

[1] This Environment Clearance is granted for the proposed production for the five

years @ 2,59,000 TPA. The ultimate depth of Mining will be 9 meter. The

alivation range of mine site is 297-298 armsl. The Corner Coordinates of the

leased area are:

Corners Latitudes Longitudes

A N 30O 15’21.9” E077O 29’37.4”

B N 30O 15’29.8” E077O 29’37.5”

C N 30O 15’17.5” E077O 29’52.7”

D N 30O 15’21.6” E077O 29’42.2”

[2] The project proponent shall carry out mining activity strictly as per the approved

Mining Plan.

[3] Environmental Clearance is subject to obtaining clearance, under the Wildlife

(Protection) Act, 1972 from the National Board of Wildlife, as applicable to the

project.

[4] No mining activities will be allowed in forest area, if any, for which the Forest

Clearance is not available.

[5] The Project proponent shall obtain consent to Operate from the State Pollution

control Board, Haryana and effectively implement all the conditions stipulated

therein.

[6] Project Proponent shall appoint an Occupational Health Specialist for Regular and

Periodical medical examination of the workers engaged in the project and records

maintained; also, Occupational health check-ups for workers having some

aliments like BP, diabetes, habitual smokers, etc. shall be undertaken once in six

months and necessary remedial/preventive measures taken accordingly.

Recommendations of National Institute for labour for ensuring good occupational

environment for mine workers would also be adopted.

Page 25: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

25

[7] Project Proponent shall appoint a Monitoring Committee to monitor the

replenishment study, traffic management, levels of production, River Bank erosion

and maintenance of Road etc.

[8] The number of trips of the trucks shall not exceed the estimated quantity of 875

Mt/day @35 Trips/day (25 Mt/Trip). Transport of minerals shall be done either by

dedicated road or it should be ensured that the trucks/dumpers carrying the mineral

should not be allowed to pass thought the villages.

[9] Project Proponent shall ensure that the road may not be damaged due to

transportation of the mineral; and transport of minerals will be as per IRC

Guidelines with respect to complying with traffic congestion and density.

[10] Excavation will be carried out up to a maximum depth of 3 meters from surface of

mineral deposit and not less than one meter from the water level of the River

channel whichever is reached earlier.

[11] The pollution due to transportation load on the environment will be effectively

controlled & water sprinkling will also be done regularly. Vehicles with PUCC

only will be allowed to ply. The mineral transportation shall be carried out through

covered trucks only and the vehicles carrying the mineral shall not be overloaded.

Project should obtain ‘PUC’ certificate for all the vehicles from authorized

pollution testing centre.

[12] Washing of all transport vehicles should be done inside the mining lease.

[13] Permanent pillars has to be constructed to demarcate width of extraction of ROM

leaving 25% of River width from the bank with depth of 1.5m below the ground

and 1.2 m above the ground to observe its stability.

[14] There shall be planning, developing and implementing facility of rainwater

harvesting measures on long term basis in consultation with Regional Director,

Central Groundwater Board and implementation of conservation measures to

augment ground water resources in the area in consultation with Central Ground

Water Board.

[15] The Project Proponent shall also take all precautionary measures during mining

operation for conservation and protection of endangered flora/fauna, if any,

spotted in the study area.

[16] Main haulage road in the mine should be provided with permanent water

sprinklers and other roads should be regularly wetted with water tankers fitted

with sprinklers.

[17] Provision shall be made for the housing of construction labour within the site with

all necessary infrastructure and facilities such as fuel for cooking, mobile toilets,

mobile STP, safe drinking water, medical health care, crèche etc. The housing may

Page 26: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

26

be in the form of temporary structures to be removed after the completion of the

project.

[18] No River sand mining shall be allowed in rainy season.

[19] The project proponent shall submit annual replenishment report certified by an

authorized agency. In case the replenishment is lower than the approved rate of

production, then the mining activity/ production levels shall be decreased/ stopped

accordingly till the replenishment is completed.

[20] In River flood plain mining a buffer of 3 meter to be left from the River bank for

mining.

[21] The project proponent shall ensure that no natural water course/water body shall

be obstructed due to any mining operations.

[22] The dumping site selected and proposed shall be used for OB dump at the

designated site within the lease area as per the approved mine plan. In no case the

overburden should be dumped outside the lease area.

[23] Garland drains shall be constructed to prevent the flow of the water in the dumps.

[24] Green belt should be developed as per the proposed plantation as given in the

proposal. Plantation should be carried out in phased manner. The green belt

should be developed in the safety zone around the mining lease by planting the

native species around lease boundary and haul roads , backfilled and reclaimed

around water body, road etc. in consultation with the local DFO/Agriculture

Department.

[25] Regular water sprinkling shall be carried out in critical areas prone to air pollution

and having high levels of SPM and RPM such as haul road, loading and unloading

point and transfer points. It shall be ensured that the Ambient Air Quality

Parameters conform to the norms prescribed by the CPCB.

[26] Regular monitoring of ground water level and quality shall be carried out in and

around the mine lease. The monitoring shall be carried out four times in a year-pre

monsoon (April-May), monsoon (August), post monsoon (November); winter

(January) and the data thus collected may be sent regularly to MOEF Regional

Office, Chandigarh and Regional Director CGWB.

[27] Data on ambient air quality and stack emissions shall be submitted to Haryana

Pollution Control Board once in six months carried out by

MOEF/NABL/CPCB/Government approved lab.

[28] Vehicular emissions shall be kept under control and regularly monitored.

Measures shall be taken for maintenance of vehicles used in mining operations and

in transportation of mineral. The vehicles shall be covered with a tarpaulin and

shall not be overloaded. The project proponent shall ensure that the vehicle must

have pollution under control certificate.

Page 27: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

27

[29] The project proponent shall take all precautionary measures during mining

operations for conservation and protection of endangered fauna, if any, spotted in

the study area. A plan for conservation shall be drawn and approved by the State

Wildlife Department. Necessary allocation of funds for implementation of the

conservation plan shall be made and the funds so allocated shall be included in the

project cost. All the safeguard measures brought out in the wildlife conservation

plan so prepared specific to the project site shall be effectively implemented. A

copy of action plan may be submitted to the HSPCB and MOEF, Regional Office,

Chandigarh within 3 months.

[30] As envisaged, the Project Proponent shall invest at least an amount of Rs. 9.25

lakh as cost for implementing various environmental protection measures

including recurring expenses per year.

[31] A sum of Rs. 10.25 lakh shall be earmarked by the Project proponent for

investment as CSR on socio economic up-liftment activities of the area

particularly in the area of habitat, health or education, training programme of rural

women & man provide the kit for employment generation. The proposal should

contain provision for monthly medical camps, distributions of medicines and

improvement in educational facilities in the nearby schools. Details of such

activity along with time bound action plan be submitted to HSPCB/SEIAA

Haryana before the start of operation.

[32] Budgetary provision of Rs. 05 lakh per year earmarked for the labours working in

the Mine for all necessary infrastructure facilities such as health facility, sanitation

facility, fuel for cooking, along with safe drinking water, medical camps and

toilets for women, crèche for infants should be made and submitted to HSPCB at

the time of CTE/CTO/SEIAA Haryana. The housing facilities should be provided

for mining labours.

[33] A Final Mine Closure Plan along with details of corpus fund shall be submitted to

the SEIAA well within the stipulated period as prescribed in the minor mineral

concession rules 2012..

[34] The project proponent shall ensure that the EC letter as well as the status of

compliance of EC conditions and the monitoring data are placed on company’s

website and displayed at the project site.

[35] The project proponent shall ensure that loading in Trucks do not exceed the norms

fixed by the Transport Department as per relevant rules.

[36] The project proponent shall ensure approach roads are widened and strengthened

as per requirements fixed by PWD and district administration before the start of

the work.

[37] The project proponent shall ensure supply of drinking water through RO.

Page 28: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

28

GENERAL CONDITIONS:

[i] Concealing factual data or submission of false/fabricated data and failure to

comply with any of the conditions mentioned above may result in withdrawal of

this clearance and attract action under the provisions of the Environment

(Protection) Act, 1986.

[ii] Any change in mining technology/scope of working shall not be made without

prior approval of the SEIAA.

[iii] Any change in the calendar plan including excavation, quantum of mineral and

waste shall not be made.

[iv] Periodic monitoring of ambient air quality shall be carried out for PM10, PM2.5,

SO2 and NOx monitoring. Location of the stations (minimum 6) shall be decided

based on the meteorological data, topographical features and environmentally and

ecologically sensitive targets and frequency of monitoring shall be decided in

consultation with the Haryana State Pollution Control Board (HSPCB). Six

monthly reports of the data so collected shall be regularly submitted to the

HSPCB/CPCB including the MOEF, Regional office, Chandigarh.

[v] Personnel working in dusty areas shall wear protective respiratory devices they

shall also be provided with adequate training and information on safety and health

aspects.

[vi] Occupational health surveillance program of the workers shall be undertaken

periodically to observe any contractions due to exposure to dust and take

corrective measures, if needed.

[vii] The funds earmarked for environmental protection measures shall be kept in

separate account and shall not be diverted for other purpose. Year wise

expenditure shall be reported to the HSPCB and the Regional office of MOEF

located at Chandigarh.

[viii] The project proponent shall also submit six monthly reports on the status of

compliance of the stipulated EC conditions including results of monitored data

(both in hard copies as well as by e-mail) to the northern Regional Office of

MoEF, the respective Office of CPCB, HSPCB and SEIAA Haryana.

[ix] The above conditions will be enforced, inter alia, under the provision of the Water

(Prevention & Control of Pollution) Act, 1974 the Air (Prevention & Control of

Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public

Liability Insurance Act 1991 (all amended till date) and rules made hereunder and

also any other orders passed by the Honb’le Supreme Court of India/High Court of

Haryana and other Court of law relating to the subject matter.

[x] The Project proponent should inform the public that the project has been accorded

Environment Clearance by the SEIAA and copies of the clearance letter are

Page 29: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

29

available with the Haryana State Pollution Control Board & SEIAA. This should

be advertised within 7 days from the date of issue of the clearance letter at least in

two local newspapers that are widely circulated in the region and the copy of the

same should be forwarded to SEIAA Haryana. A copy of Environment Clearance

conditions shall also be put on project proponent’s web site for public awareness.

[xi] All the other statutory clearances such as the approvals for storage of diesel from

the Chief Controller of Explosives, Fire department, Civil Aviation Department,

Forest Conservation Act, 1980 and Wildlife (protection) Act, 1972 etc. shall be

obtained, as may be applicable, by Project proponent from the competent authority

before the start of mining operation.

[xii] That the grant of this EC is issued from the environmental angle only, and does

not absolve the project proponent from the other statutory obligations prescribed

under any other law or any other instrument in force. The sole and complete

responsibility, to comply with the conditions laid down in all other laws for the

time being in force, rests with the industry/unit/project proponent. Any appeal

against this environmental clearance shall lie with the National Green Tribunal, if

preferred, within a period of 30 days as prescribed under section 16 of National

Green Tribunal Act, 2010.

Item No.[7] Environmental Clearance for proposed Special Economic Zone at Village

Behrampur, Balola & Bandhwari, Gurgaon by M/s G.P.Realtors Pvt.

Ltd.

The SEAC has recommended this project for Environmental Clearance subject to

stipulation stated therein. The Project Proponent has proposed the construction of Special

Economic Zone at Village Behrampur, Balola & Bandhwari, Gurgaon on a plot area of

38.12 acres (1st phase for EC 12.5835 acre). The total built up area shall be 103807.64

sqm. The proposed Project shall comprise of 3 Basement + GF + 5 Floors. The maximum

height of the building shall be 30.45 meter. The total water requirement shall be 636

KLD. The fresh water requirement shall be 370 KLD. The waste water generation shall

be 296 KLD, which will be treated in the STP of 300 KLD capacity. The total power

requirement shall be 6250 KVA which will be supplied by DHBVN. The Project

Proponent has proposed to develop green belt on 34.48% of project area (23% tree

plantation + 11.48% landscaping). The Project Proponent proposed to construct 12 rain

water harvesting pits. The solid waste generation will be 1.5 ton/day (OWC proposed for

1716 kg/day). The total parking spaces proposed are 1299 ECS.

The above recommendation of SEAC was taken up for consideration. Detailed

discussions were held regarding water requirement, HT line, quality of water, green belt

development plan, Ambient Air Quality, NOC regarding non-involvement of Aravalli

Notification dated 07.05.1992, recycle and reuse of water, parking plan, traffic circulation

etc. It was found that the project proponent submitted the assurance of HUDA for supply

Page 30: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

30

of water, NOC from DC Gurgaon regarding non applicability of Aravalli Notification and

NOC from AAI regarding height clearance. It was noticed that the project proponent has

not clearly mentioned the capacity of OWC vis-à-vis the generation of bio-degradable

waste, dimensions of the earmarked area and the process involved for the treatment of

bio-degradable waste. It was noticed that for disposal of 32 KLD of waste water from

labour camp the project proponent has proposed to provide soak pit. It was observed that

the project proponent should provide mobile STP/STP for treatment of waste water

generated from the labour camp during construction phase. It was also noticed that the

capacity of STP proposed to be set up in operation phase is inadequate. The project

proponent is required to revise the capacity of STP from proposed 300 KLD.

In view of the above discussions, the Authority decided to agree with the

recommendations of SEAC to accord Environment Clearance to this project by imposing

the following condition in addition to the usual conditions in practice and subject to the

submission of capacity of OWC vis-à-vis the generation of bio-degradable waste,

dimensions of the earmarked area and the process involved for the treatment of bio-

degradable waste; provision of mobile STP/STP for treatment of waste water generation

from the labour camp and adequately revised capacity of STP within 15 days.

[1] The project proponent shall not raise any construction activity in the ROW

reserved/acquired for High Tension Wire passing through the project area and shall

maintain horizontal and vertical ROW as required under Indian Electricity Rules,

1956/DHBVN latest instructions.

[2] The project proponent shall set up STP of 350 KLD capacity in operation phase.

[3] The project proponent shall provide STP/mobile STP for treatment of 32 KLD of

waste water proposed to be generated from the labour camp during construction

phase.

[4] Adequate drinking water and sanitary facilities shall be provided for construction

workers at the site. Provision should be made for mobile toilets. Open defecation

by the laboures is strictly prohibited. The safe disposal of solid wastes/ waste water

generated during the construction phase should be ensured. Efforts shall be made to

provide mobile STP for treatment of waste water during the construction phase.

[5] The project proponent shall submit the following information within 15 days.

(i) Capacity of OWC vis-à-vis the generation of bio-degradable waste,

dimensions of the earmarked area and the process involved for the treatment

of bio-degradable waste.

(ii) Provision of mobile STP/STP for treatment of 32 KLD of waste water

generation from the labour camp during construction phase.

(iii) Revised capacity of STP to be set up during operation phase.

Page 31: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

31

Item No.[8] Environmental Clearance for proposed Group Housing Project

measuring (18.675 + 5.88472 = 24.55972 acres) at Vilalge Dhorka,

Sector-95, Gurgaon, Haryana by Benchmark Infotech Pvt. Ltd.

The SEAC has recommended this project for Environmental Clearance subject to

stipulation stated therein. The Project Proponent has proposed for construction of Group

Housing Project measuring (18.675 + 5.88472 = 24.55972 acres) at Vilalge Dhorka,

Sector-95, Gurgaon, Haryana on a total plot area of 99389.6 sqm (24.55 Acres). The total

built up area shall be 287179.9 sqm. The proposed Project shall comprise of 3 Basements

+ GF + 17 floors. The maximum height of the building shall be 26.5 meter. The total

water requirement shall be 1201 KLD. The fresh water requirement shall be 694 KLD.

The waste water generation shall be 902 KLD, which will be treated in the STP 1100

capacity.

The above recommendation of SEAC was taken up for consideration. Detailed

discussions were held regarding water requirement, quality of water, green belt

development plan, Ambient Air Quality, NOC regarding non-involvement of Aravalli

Notification dated 07.05.1992, recycle and reuse of water, parking plan, traffic circulation

etc. It was found that the project proponent submitted the assurance of HUDA for supply

of water along with copies of EDC/IDC paid to HUDA for the services for supply of

water, sewerage connection and drainage system, NOC from DC Gurgaon regarding non

applicability of Aravalli Notification and NOC from AAI regarding height clearance. It

was noticed that the project proponent has proposed to use excavated Top soil for use of

landscaping and has proposed to stack the same in the project area covering the same

with Tarpaulin. The project proponent is required to give exact quantum of Top soil to be

excavated and also brief description for its preservation in order to control its erosion. It

was noticed that the project proponent has proposed to reuse construction debris and

demolition debris; the project proponent is required to submit the details of the same. The

project proponent has not discussed the storm water management during construction

phase the project proponent is required to submit the same. It was noticed that the project

proponent has not clearly mentioned the capacity and dimensions of OWC to be installed

for treatment of bio-degradable waste.

In view of the above discussions the Authority decided to defer to this case with

the decision that the project proponent may be asked to submit reply to the below

mentioned observation within 15 days.

[1] The project proponent shall submit details regarding provision made for

preservation of Top Soil in the project area.

[2] The project proponent shall submit details of reuse of construction

debris/demolition debris during construction phase.

[3] The project proponent shall submit capacity and dimensions of OWC proposed to

be installed for treatment of bio-degradable waste.

Page 32: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

32

Item No.[9] Environmental Clearance for construction of commercial colony project

located at Sector-6 & 11 in Revenue Estate of Ratgal, District-

Kurukshetra, Haryana by M/s Divine Vision Infraestate Pvt. Ltd.

The SEAC has recommended initiating legal action against the project proponent

under the Environment (Protection) Act, 1986 as the project proponent has completed the

construction of Commercial Colony project without obtaining prior environmental

clearance. The SEAC has appraised this case in the light of MoEF & CC, GoI OM dated

12.12.2012 and 27.06.2013.

The above recommendation of SEAC was taken up for consideration in the

today’s meeting. It was noticed that Hon’ble NGT has already quashed the operation of

OM of MoEF & CC, GoI OM dated 12.12.2012 and 27.06.2013. The SEIAA vide letter

no. SEIAA/HR/15/634 dated 28.12.2015 has already sought clarification from MoEF &

CC, GoI regarding change in procedure if any in violation cases keeping in view the

quashing of OM dated 12.12.2012 by Hon’ble NGT but no response from the MOEF &

CC, GOI has been received.

In view of the above the Authority decided to keep this case pending till

clarification is received from MoEF & CC, GoI.

Item No.[10] Environmental Clearance for construction of Group Housing Project

at Village Badshahpur, Sector-65, Gurgaon, Haryana by M/s Manglam

Multiplex Pvt. Ltd.

The SEAC in its 128th meeting held on 26-02-2016 has referred this case to the

SEIAA for rejecting the environment clearance application on the grounds that the

project proponent has submitted separate application for the additional licensed area of

3.518 acres (2.081 acres + 1.437 acres of license no. 114 & 122 of 2014) which is in

contagious with the existing project area of 254925.63 sqm (license no. 234 of 2007, 52

of 2009 and 35 of 2010).

The recommendation of SEAC was taken up in the today’s meeting. It was noticed

that the project proponent has submitted fresh application for obtaining environmental

clearance for 3.518 acres of additional license which is in contiguity with the existing

project area of 254925.63 sqm for which the environmental clearance was granted by

SEIAA vides letter no. 1092 dated 28.10.2009 and subsequently the extension of validity

of EC was also granted to the project proponent vide letter no. 61 dated 05.01.2015. The

existing project proposal is under initial stage of construction and the project proponent is

required to submit the application for the additional area of 3.518 acre (license no. 122

and 114 of 2014) in conjunction with the existing project under expansion.

In view of the above the Authority accepted the recommendation of SEAC and

decided to reject the application. It was also decided that the project proponent may be

asked to submit fresh application for additional area of 3.518 acres in conjunction with

the existing project under expansion.

Page 33: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

33

Item No.[11] Environmental Clearance for Revision/Modification of Group Housing

Project (37.512 acres) at Sector-67A, Village Dhumsapur and

Maidawas, District-Gurgaon, Haryana by M/s Precision Realtors Pvt.

Ltd.

The SEAC in its 128th meeting held on 26.02.2016 has recommended this project

for environment clearance. The project proponent for seeking environment clearance for

Revision/Modification of Group Housing Project (37.512 acres) at Sector-67A, Village

Dhumsapur and Maidawas, District-Gurgaon, Haryana with the proposal as given under:

Details EC Granted After revision Difference

Plot Area 37.512 acres nil nil

Built up area 812877.08 sqm 804646.73 sqm -8230.35 sqm

Green Area 45.02% 45.02% Nil

No. of Dwelling

units

1780 1685 -95

EWS units 315 315 Nil

Parking 3545 ECS 3752 ECS 208 ECS

Power Demand 15174.7 KW 14845.1 KW -329.5 KW

RWH pits 20 pits 26 pits 6 pits

Solid Waste 4.8 TPD 4.410 TPD -0.390 TPD

Total Water

Requirement

2359 KLD 1758 KLD -601 KLD

Waste water

generation

1320 KLD 1120 KLD -200 KLD

Treated Water 1254 KLD 923 KLD -331 KLD

STP capacity 2300 KLD 2300 KLD nil

In the today’s meeting the recommendation of SEAC and the project details were

taken up for consideration. It was observed by the Authority that:

[1] The project proponent has not proposed any change in the DG set configuration

whereas water consumption for cooling has been reduced in the revised

submission. The project proponent is required to clarify the same.

[2] The project proponent has proposed to reduce Dwelling units by 5.4% in revision

application whereas the water requirement has been proposed to be reduced by

24.43% .The project proponent is required to clarify the same.

[3] The project proponent in the revised proposal has reduced the water demand for

maintenance/Arboriculture by 60.54%. The project proponent is required to justify

the same.

[4] The project proponent in the revised proposal has reduced the water requirement

by 24.77% . The project proponent is required to justify the same.

[5] The project proponent in the revised proposal has proposed the reduction of waste

water generation by 15% whereas the treated waste water has been shown reduced

by 26%. The project proponent is required to justify the same.

[6] On page 50 of presentation the diameter of recharge pit has been shown as 25

meter against the requirement of 2.5 meter. The project proponent is required to

clarify the same.

Page 34: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

34

[7] The project proponent in the revision application has calculated water requirement

for visitors @ 10% whereas the solid waste generation has been calculated @ 5%.

The project proponent is required to clarify the same.

[8] The project proponent has not submitted the details regarding treatment of bio-

degradable waste. The project proponent is required to submit the details regarding

treatment of bio-degradable waste within the project area and should submit a plan

earmarking space for management of bio-degradable waste.

In view of the above observations the Authority decided to defer to this case with

the decision that the project proponent may be asked to submit reply to the above

observation within 15 days.

Item No.[12] Environmental Clearance for construction of “Affordable Group

Housing” project at Village-Mujeri, Sector-70, Faridabad, Haryana by

M/s Agrasain Spaces.

The SEAC has recommended this project for Environmental Clearance subject to

stipulation stated therein. The Project Proponent has proposed the construction of

“Affordable Group Housing” project at Village-Mujeri, Sector-70, Faridabad, Haryana on

a total plot area of 21650.85 sqm (5.35 acre). The total built up area shall be 49375.498

sqm. The Group Housing project shall have 07 Towers Stilt + 14 Floors & Stilt + 06

Floors. The Group Housing project shall have 720 Dwelling Units, Commercial 1 & 2,

Aaganwadi cum Creche, Community Hall. The maximum height of the building shall be

44.5 meter. The total water requirement shall be 519 KLD. The fresh water requirement

shall be 346 KLD. The waste water generation shall be 427 KLD, which will be treated in

the STP of 515 KLD capacity. The total power requirement shall be 3044 KW which will

be supplied by DHBVN. The Project Proponent has proposed to develop green belt on

4256.79 sqm (21.04%) of project area (13.04 tree plantation + 8% landscaping). The

Project Proponent proposed to construct 05 rain water harvesting pits. The solid waste

generation will be 1688 kg/day. The bio-degradable waste will be treated in the project

area by installation of OWC (organic waste converter). The total parking spaces proposed

are 720 Scooter 390 ECS.

In the today’s meeting the recommendation of SEAC and the project details were

taken up for consideration. Detailed discussions were held regarding HT line, gas pipe

line, water requirement, quality of water, green belt development plan, Ambient Air

Quality, NOC regarding non-involvement of Forest land, recycle and reuse of water,

parking plan, traffic circulation etc. It was noticed that the project proponent has

submitted copy of EDC/IDC paid to HUDA for the services for supply of water,

sewerage connection and drainage system and NOC from DFO regarding Non

involvement of Forest land. It was observed that the project proponent has submitted

calculations and detail of the capacity of OWC vis-à-vis the generation of bio-degradable

waste and the process involved for the treatment of bio-degradable waste.

Page 35: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

35

In view of the above discussions, the Authority decided to agree with the

recommendations of SEAC to accord Environment Clearance to this project by imposing

the following condition in addition to the usual conditions in practice.

[1] The project proponent shall install solar panel for energy conservation.

[2] The project proponent shall provide green area on 21.04% of project area.

[3] The project proponent shall essentially provide two numbers of STPs preferably

equivalent to 50% of total capacity or as per the initial occupancy as the case may

be.

[4] The project proponent shall not raise any construction activity in the ROW

reserved/acquired for High Tension Wire passing through the project area and

shall maintain horizontal and vertical ROW as required under Indian Electricity

Rules, 1956/DHBVN latest instructions.

[5] The project proponent shall not raise any construction in the ROW reserved

for Gas Pipe Line.

[6] Adequate drinking water and sanitary facilities shall be provided for construction

workers at the site. Provision should be made for mobile toilets. Open defecation

by the laboures is strictly prohibited. The safe disposal of solid wastes/ waste water

generated during the construction phase should be ensured. Efforts shall be made to

provide mobile STP for treatment of waste water during the construction phase.

Item No.[13] Environmental Clearance for Regarding Extension of validity period

by 5 years of Environmental Clearance Letter issued for the project

“Uniworld Resorts”-Residential ploted colony with other

infrastructure Amenities at Sector-33 & 48, Gurgaon by M/s Unitech

Residential Resorts Ltd.

The project proposal relates to grant of extension of validity of EC. The project

proponent on 12.06.2013 submitted application seeking extension of validity of EC of the

environmental clearance granted by MoEF & CC, GoI on 03.12.2007 for the project. The

case was lastly taken up by SEIAA in its 77th meeting held on 14.11.2014. The project

proponent vide letter 13.11.2014 informed that the civil construction work of the project

has already been completed as per approved plans and within the validity of EC letters

and requested for withdrawal of the application. The SEIAA decided to refer back this

case to SEAC to inspect the site and to assess the status of construction. The sub-

committee tried to contact the project proponent for doing inspection. The report is

incomplete and not signed by other member.

The case was taken up in the today’s meeting, it was observed that the project

proponent vide letter on. URRL/Uniworld Resorts/EC/2402/2016 dated 24.02.2016 has

intimated that they have obtained Consent to Operate from the HSPCB on 13.02.2016 it

was noticed that the MoEF & CC, GoI has granted EC to the project proponent under

category 8(b) as the project area is more than 50 Ha and as per provision contained in

Page 36: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

36

para 9 of EIA Notification 14.09.2006 the validity period of item 8(b) is limited only to

such activities as may be the responsibility of the applicant as a developer. It was not

clear whether the project proponent has carried out construction of the project as per

approved plans. The Authority decided that a Sub-Committee comprising of Shri

Hitender Singh and Dr. S.N. Mishra, Members SEAC shall visit the site to check whether

the construction raised by the project proponent is in accordance with the approved plans

or not and shall submit the report to the SEIAA. Accordingly the case was deferred.

Item No.[14] Environmental Clearance for Expansion and Modernization of DLF

Commercial Project Corporate Green (IT Office, Retail and

Studio/Service Apartment) at Sector-74A, Gurgaon by M/s DLF

Universal Ltd.

The case was lastly considered in the 87th meeting held on 05.02.2016 wherein the

Authority decided that a Sub-Committee comprising of Shri Hitender Singh and Dr. S.N.

Mishra, Members SEAC shall monitor the compliance of the conditions imposed in the

EC letter and shall submit the report to the SEIAA and the case was deferred.

In the today’s meeting the report dated 14.03.2016 of sub-committee was taken up

for consideration. It was found that the sub-committee in its report has reported that the

project proponent is complying with the conditions imposed in the EC letter. The

Authority decided to accept the recommendation of SEAC and to grant environmental

clearance for Expansion and Modernization of DLF Commercial Project Corporate Green

(IT Office, Retail and Studio/Service Apartment) at Sector-74A, Gurgaon by imposing

standard conditions as recommended by SEAC and subject to the following additional

conditions.

[1] The project proponent shall ensure that no construction activity is undertaken

either on surface or below or above surface of revenue rasta passing through the

project area.

[2] The project proponent shall indicate the width and length of revenue rasta passing

through the project area on sign board and shall display the same at both the ends

of revenue rasta stretch, for awareness of public. Sign board shall also display the

message that this is a public rasta/road and any citizen can use it. There shall not

be any gate with or without guards on revenue rasta further project proponent shall

not encroach revenue rasta and shall not cross internal roads over revenue rasta.

[3] The project proponent shall not raise any construction activity in the ROW

reserved/acquired for High Tension Wire passing through the project area and

shall maintain horizontal and vertical ROW as required under Indian Electricity

Rules, 1956/DHBVN latest instructions.

[4] Adequate drinking water and sanitary facilities shall be provided for construction

workers at the site. Provision should be made for mobile toilets. Open defecation

by the laboures is strictly prohibited. The safe disposal of solid wastes/ waste water

Page 37: Minutes of the 89th meeting of State Environment …environmentclearance.nic.in/writereaddata/Form-1A/...Fourth 218 to 206 20,00,000 Ton Fifth 206 to 194 20,00,000 Ton 9. Green belt

37

generated during the construction phase should be ensured. Efforts shall be made to

provide mobile STP for treatment of waste water during the construction phase.

Item No.[15] Environmental Clearance for Mining of “Brick Earth”

The matter regarding grant of environmental clearance to the project proponents

engaged in mining of “Brick Earth” required for brick-kiln units was taken up in the

today’s meeting. It was informed that in compliance of the Hon’ble Supreme Court

Orders the SEIAA started receiving the applications from Brick-Kiln owners for

environmental clearance of their Mining projects. The SEIAA in October 2012 received

118 applications for environmental clearance. The applications could not be appraised as

there was no set procedure and the requirement of environmental clearance was

challenged in the Hon’ble NGT. Now MoEF&CC, GoI vide amended Notification SO

141 (E) dated 15.01.2016 has prescribed procedure for granting environmental clearance

to the Mining projects having project area less than 5 Ha. As per this amended

Notification the 118 applications pending with SEIAA now require environment

clearance from the DEIAA/DEAC under category B2.

In view of the above it was decided to file all the 118 applications pending with

SEIAA as environmental clearance applications in case of these projects shall now be

processed at the level of DEIAA/DEAC under category B2 projects.

******