minutes of the 468 meeting of the state level expert ... minutes of the 468th i.pdfpage 1 of 41 468...
TRANSCRIPT
Page 1 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 1 of 41
Minutes of the 468th meeting of the State Level Expert Appraisal Committee held on 03/01/2019
at Geer Foundation, Sector 9, Indroda Park, Gandhinagar.
The 468th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 3rd January
2019 at Geer Foundation, Sector 9, Indroda Park, Gandhinagar. Following members attended the
meeting:
1. Dr. Dinesh Misra, Chairman, SEAC
2. Shri S. C. Srivastav, Vice Chairman, SEAC
3. Shri V. N. Patel, Member, SEAC
4. Shri R. J. Shah, Member, SEAC
5. Dr. V.K. Jain, Member, SEAC
6. Shri A.K. Muley, Member, SEAC
The agenda of TOR/Scoping cases and Appraisal was taken up. The applicants made presentations on
the activities to be carried out along with other details furnished in the Form-1, PFR, EIA-EMP reports
and other reports.
14 SIA/GJ/IND2/29542/2017 Tvisha Impex Plot No. 501/B, GIDC Estate, Ankleshwar, Bharuch
Appraisal
Category of the unit : 5(f)
Project status: New Project
• PP has submitted online application vide no. SIA/GJ/IND2/29542/2017 dated 18/11/2018 for obtaining
Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated 26/07/2017.
• Project proponent has submitted EIA Report prepared by Aqua-Air Environmental Engineers Pvt Ltd. based on
the TOR issued by SEIAA
• This is a new proposed project for Synthetic organic chemicals as tabulated below:
Sr.
No.
Name of the
Products
CAS no. /CI no. Quantity
MT/Month
End-use of products
1 Disperse Red
F3BS
99031-78-6 35 Dyeing Industries
2 Disperse Blue
GSL
41642-51-7 20 ''
3 Disperse Yellow
SG
12236-36-1 12 ''
4 Disperse Yellow
4G
86836-02-4 12 ''
5 Disperse Yellow 61968-66-9 12 ''
Page 2 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 2 of 41
SGL
6 Butyl Pyridone 39108-47-9 6 ''
7 Ethyl Pyridone 29097-12-9 6 ''
8 Methyl Pydridone 1003-56-1 6 ''
9 N,N-Diethyl Meta
Amino Methane
Sulphonilide
134-62-3 10 ''
10 2,6 – Dibromo
Para Toluidine
6968-24-7 15 ''
11 2,6 – Dibromo
Para Nitro Aniline
827-94-1 10 ''
12 Zinc Cyanide 557-21-1 5 ''
13 Copper Cyanide 544-92-3 5 ''
14 Intermediate Of
Disperse Red 343
99035-78-6 10 ''
15 Intermediate Of
Blue 165
41642-51-7 7 ''
16 Para Amino
Acetanilide
122-80-5 6 ''
Total 177.0
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 03/01/2019.
• Salient features of the project are as under:
Sr.
no
.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
2.0 Crores
B Total Plot area( sq. meter)
2196.0 Sq. m.
Green belt area
( sq. meter)
725.0 Sq. m.
C Employment generation
20.0
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc...)
GIDC water supply
Status of permission from the concern authority.
Page 3 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 3 of 41
ii
Water consumption (KLD)
Category
Quantity
KLD
Remarks
(A) Domestic 3.0
(B) Gardening 1.0
(C) Industrial
Process 2.6
Washing 0.5
Boiler 4.5
Cooling 1.5
Others 0.0
Industrial Total
9.10
Total (A + B + C)
13.1
1) Total water requirement for the project: 13.1 KLD
2) Quantity to be recycled: 4.45 .KLD
3) Total fresh water requirement: 8.65 KLD
iii
Waste water generation (KLD)
Category Waste water
KLD
Remarks
(A) Domestic 2.0
(B) Industrial
Process 4.1
Washing 0.5
Boiler 0.2
Cooling 0.15
Others 0.0
Page 4 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 4 of 41
Total Industrial
waste water
4.95
Total [A + B] 6.95
-
iv Treatment facility within premises with capacity
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
ETP : 5.0 KL/Day
MEE : 10.0 KL/Day
v Mode of Disposal & Final meeting point
Domestic:
Septic tank & soak pit System
Industrial:
The industrial effluent (4.95 KL/Day) will be treated in ETP consists
of primary treatment then it will be evaporated In MEE for further
treatment & disposal.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc.
, Name of CF
� N.A
Membership of Common facility (CF)
(For waste water treatment)
� N.A
vii Simplified water balance diagram with reuse / recycle of waste water
viii Reuse/Recycle details (KLD)
Total reuse 4.45 KLD
Source of waste
water for reuse
with quantity in
KLD
Application area with
quantity in KLD
Remarksregarding
feasibility to reuse
i.e. w/w
characteristics
(COD, BOD, TDS
etc.)
MEE condensate Boiler Raw water PH-7.9
COD-250.0
BOD-<10.0
TDS-1000.0
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr,
KVA etc.
Page 5 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 5 of 41
-
Sr. no.
Source of
emission With
Capacity
Stack Height (meter)
Type of
Fuel
Quantity of Fuel MT/Day
Type of emissions
i.e. Air Pollutants
Air Pollution Control
Measures (APCM)
1 Steam Boiler (1.5 TPH)
18.0 Bio
Coal 5
MT/Day
SPM
SO2
NOX
Multi cyclone Separator with bag filter
2 DG set (75 KVA)
9.0 Diese
l 50
Lit/Day
SPM
SO2
NOX
Adequate Stack Height
-
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
-
Sr. no.
Specific Source of emission (Name of
the Product & Process)
Type of emission
Stack/Vent Height (meter)
Air Pollution Control
Measures (APCM)
There shall be no process emission from the manufacturing process as well as Ancillary process.
-
iii Fugitive emission details with its mitigation measures.
As below:
→ Minimum number of flanges, joints and valves in pipelines
→ Selection / use of state-of-the art leak proof valves
→ Provision of mechanical seals in pumps
→ Proper preventive maintenance of roofs and seals for tanks
→ Monitoring and preventive maintenance of valves, flanges, joints, etc.
→ Fugitive emission over reactors, formulation areas, centrifuges, chemical loading,
transfer area, shall be collected through hoods and ducts by induced draft and
controlled by dust collector.
For particulate / dust emissions from the coal handling system: Water will be sprinkled
to control particulate / dust emission from coal storage area.
F Hazardous wastes
(as per the Hazardous and Other Wastes (Management and Transboundary
Movement) Rules 2016.
i
Sr.
no.
Type/Name
of Hazardous
waste
Specific
Source of
generation
(Name of
Category
and
Schedule as
per HW
Quantity
(MT/Annum)
Management
of HW
Page 6 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 6 of 41
the
Activity,
Product
etc.)
Rules.
1 ETP Sludge From
ETP
Sch-1/35.1 10
MT/Month
Collection,
Storage,
Transportatio
n and
disposal to
nearest
TSDF site
(M/s. BEIL)
2 Discarded
Containers/Ba
gs/ Liners
From Raw
Material
Sch-1/33.1 2
MT/Month
Collection,
Storage,
Transportatio
n,
decontaminat
ion & sell to
GPCB
authorized
vendors
3 Iron Oxide
Sludge
From Mfg.
process of
Para
Amino
Acetanilide
Sch-1/26.1 10
MT/Month
Collection,
Storage,
Transportatio
n and given
to cement
industries or
disposal to
nearest
TSDF site
(M/s. BEIL)
4 Process
Waste
From mfg.
Process of
Product no.
1,2
Sch-1/26.1 11.0
MT/Month
Collection,
Storage,
Transportatio
n and given
to cement
industries or
disposal to
nearest
TSDF site
(M/s. BEIL)
5 Acetic Acid From
mfg
process
of Para
Amino
Acetanilide
Sch-1/26.3 3
MT/Month
Collection,
Storage,
Transportatio
n, & sell to
authorized
end users
Page 7 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 7 of 41
having Rule-
9 permission.
6 Used oil From
Plant
Machinery
Sch-1/5.1 0.01
MT/Month
Collection,
Storage,
Transportatio
n & Sell to
GPCB
registered re-
processor
7 Spent Solvent From Mfg.
Process
Sch-1/26.4 45
MT/Month
Collection,
Storage,
Distill & reuse
in process.
8 Distillation
Residue
From
Solvent
Recovery
Plan
Sch-1/36.1 2.5
MT/Month
Collection,
Storage,
Transportatio
n & sale to
cement
industries for
co-
processing or
send to
CHWIF
Incineration
Site.
9 MEE Salt From MEE
Plant
-- 5.0
MT/Month
Collection,
Storage,
Transportatio
n and
disposal to
nearest
TSDF site
(M/s. BEIL)
-
ii Membership details of TSDF, CHWIF etc.
(For HW management)
BEIL/ANK/2017
iii Details of Non-Hazardous waste & its disposal
(MSW and others)
there is no non-hazardous
waste
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered
Solvents
• Solvent recovery Plan
Collection, storage and transportation to In house Distillation.
Page 8 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 8 of 41
Name of Solvent
B.P V.P Total Solvent Input Kg
Qty of Solvent Recycled Kg
Qty of Losses Kg
% Recovery
% Loss
DMF 153.0 C 0.3 Kpa(@ 20 C)
45.0 43.65 1.35 98.0 3.0
ii VOC emission sources and its mitigation measures
Enclosed process,
-Pumps will be having double mechanical seals
-Proper ventilation with hood
-Regular maintenance & monitoring
Adequate PPE’s
• During the meeting dated 03/01/2019, technical presentation made during the meeting by project proponent.
• During the meeting, the project was appraised based on the information furnished in the EIA Report, various
issues raised during the public hearing and details presented during the meeting.
• The baseline environmental quality has been assessed for various components of the environment viz. air,
noise, water, biological and socioeconomic aspect. The baseline environmental study has been conducted for
the study area of 10 km radial distance from project site for the period March 2017 to May 2017. Ambient Air
Quality monitoring was carried out for PM10, PM2.5, SO2, NOx, HCl, NH3, O3, Pb, As, Ni, C6H6, HC, CO and
VOC at nine locations, including the project site. Values conform to the prescribed standards for Ambient Air
Quality. The incremental Ground Level Concentration (GLC) has been computed using AIRMOD view. The
resultant concentrations are within the NAAQS. The modelling study proved that the air emissions from the
proposed plant would not affect the ambient air quality of the region in any significant manner. The ambient air
quality around the proposed project site will remain within the National Ambient Air Quality Standards
(NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency Plan
has been covered in the RA report.
• It is noted that proposal is new in GIDC Ankleshwar. Proposal products are dye intermediates. Total plot area
is 2196 sq.mt. Source of water is bore well. Generated waste water will be treated in ETP followed by MME.
Condensate will be reused and salt will be send to TSDF. Unit will maintain ZLD. One boiler of 1.5 MT will be
installed. Fuel used would be bio coal. There will be no any process gas emission. Solvent used will be DMF
which will be recovered up to 98%. PP addressed hazardous waste as per HWR – 2016.
• PP address impact on surface water and ground water quality and Noise. EMP, CER with details of budgetary
provisions and were found satisfactory.
Page 9 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 9 of 41
• Compliance of the ToR was found satisfactory.
• After detailed discussion, it was decided to recommend the project to SEIAA Gujarat for grant of
Environmental Clearance with the following specific conditions:
1. Unit shall provide separate ETP for cyanide bearing stream and ensure the quality of waste water as
per the norms prescribed by GPCB.
15 SIA/GJ/IND2/21631/2018 M/s. Shiv Corporation
Plot No. 502/22, Near GIL, GIDC -Ankleshwar, Dist: Bharuch-393002, Gujarat.
Appraisal
Category of the unit : 5(f)
Project status: Expansion
• PP has submitted online application vide no. SIA/GJ/IND2/21631/2018 dated 18/11/2018 for obtaining
Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated 31/07/2018.
• The SEAC has issued TOR to PP vide letter no. SEIAA/GUJ/TOR/5(f)/771/2018.
• Project proponent has submitted EIA Report prepared by M/s. Aqua Air Environmental Engineering Pvt. Ltd.
based on the TOR issued by SEIAA
• This is an existing unit engaged in Synthetic organic chemicals and now proposes for expansion as tabulated
below:
Sr. no.
Name of the Products
CAS no. / CI no.
Quantity MT/Month
End-use of the products
Existing Proposed Total
1 Dispersing Agent 045 --- 8 - 8 0
Dyes used in Textile Industries & Dyes Intermediates
Used in Dyes Manufacturing
Industries.
2 Dispersing Agent
NKS 9084-06-4 5 95 100
3 Disperse Red 3 B --- 0 10 10
4 Disperse Blue D --- 0 2 2
5 Acid Orange 7 or II --- 0 50 50
6 2,6 DBPT (2:6 Di Bromo Para Toludine)
6368-24-7
0
15 15
7 6 Bromo 2,4 DNA (6 Bromo 2,4 Dinitro Aniine)
187-73-8
8
6 Chloro 2,4 DNA (6 chloro 2,4 Dinitro Aniine)
3631-19-8
9 2,6 DBPNA (2:6 Di Bromo Para Nitro Aniline)
827-94-1
10 M-22 (N,N-Biscyano Ethyl Aniline)
1555-66-4 0 15 15
Page 10 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 10 of 41
11 M-12(N,N Diethyl Meta Amino Acetanilide)
637-46-8
12 DEMT(Diethyl Meta Toludine)
121-72-2
Total 13 179 192
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 03/01/2019.
• Salient features of the project are as under:
Sr. no.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
Existing: 520 Crores Proposed:375 Crores Total: 895 Crores
B Total Plot area
( sq. meter)
Existing: 671090.20 Sq. m. (165.28 Acres) Proposed: Nil Total: 671090.20 Sq. m. (165.28 Acres)
Green belt area
( sq. meter)
Garden to the extent of 3000 sq.m maintained. Existing: 0 Sq. m. Proposed: 4046.85 Sq. m. (1 Acre)
C Employment generation Existing: 175 Proposed: 85 Total: 260
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water,
Tanker supply etc...)
Water sourced from Narmada as well as
from road tankers through private vendors
Status of permission from the
concern authority.
-Nil-
ii Water consumption (KLD)
Existing KLD
Proposed (Additional)
KLD
Total after Expansion
KLD
Remarks
(D) Domestic 1.65 3.35 5 Sent to Septic Tank
(E) Gardening 10 -- 10
Industrial
Process -- -- --
Washing 1 1 2 DM plant washing
Boiler 70.2 167.8 238 Condensate recovered and reused.
Cooling 19 16 35 Blow down Sent to ETP
Others 2 2 4 Fire Water
Page 11 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 11 of 41
Makeup
Industrial Total 92.2 186.8 279
Grand Total (A+B+C)
103.85 190.15 294
4) Total water requirement for the project: 294 KLD
5) Quantity to be recycled: 239 KLD
6) Total fresh water requirement: 55 KLD
iii Waste water generation (KLD)
Category Existing
KLD
Proposed (Additional)
KLD
Total after Expansion
KLD
Remarks
(C) Domestic 1.65 3.35 5 Sent to Septic Tank
Industrial
Process
Washing 1 1 2 DM Plant regeneration sent to ETP
Boiler 7 13 20 Treated in ETP
Cooling 7.6 2.4 10 Treated in ETP
Others -- -- --
Total Industrial waste water
15.6 16.4 32
iv Treatment facility within premises with capacity [For existing and Proposed]
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc.
� Existing ETP of 99 KLD is already available with primary secondary and tertiary
treatment.
� Expansion of existing ETP or New ETP are not proposed.
v Mode of Disposal & Final meeting point
Domestic: Septic Tank
Industrial: Treated water reuse for process & sludge to TSDF
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE,
CHWIF etc.
Name of Common facility
� -Nil-
Membership of Common facility (CF)
(For waste water treatment)
-Nil-
vii Simplified water balance diagram with reuse / recycle of waste water
Page 12 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 12 of 41
vii Reuse/Recycle details (KLD)
[Source of reuse & application area]
Total reuseHH.KLD
Source of waste water
for reuse with quantity
in KLD
Application area with
quantity in KLD
Remarks regarding
feasibility to reuse i.e.
w/w <characteristics
(COD, BOD, TDS etc.)
Cooling Tower (10) Treated water in ETP will
be used for fire water
make up. Gardening and
Cooling tower
TDS < 2000
Boiler (20)
DM Plant Regeneration
(2)
-
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr,
KVA etc.
Existing & Proposed
-
Page 13 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 13 of 41
SR. no.
Source of emission
With Capacity
Stack Height (meter)
Type of
Fuel
Quantity of Fuel MT/Day
Type of emissions
i.e. Air Pollutants
Air Pollution Control
Measures (APCM)
1
Existing DG sets Power backup (1 x 3125 kVA)
20 HSD
0.5 KL/ Month
PM, SO2 & NOx
Adequate stack height as CPCB norms
DG sets Power backup (1 x 725 kVA)
10 HSD PM, SO2 &
NOx
Adequate stack height as CPCB norms
2 Boilers (2 x 14 TPH)
15 LPG 3TPD PM, SO2 &
NOx
Adequate stack height as CPCB norms
3 Proposed DG (2 x 3125 kVA)
20 HSD 1KL / Month
PM, SO2 & NOx
Adequate stack height as CPCB norms
4 Proposed Boilers (1 x 28 TPH)
15 LPG 3TPD PM, SO2 &
NOx
Adequate stack height as CPCB norms
5 Hot Flare 45 LPG Provided for Emergency usage
-
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
Existing & Proposed
-
Sr. no.
Specific Source of emission
(Name of the Product & Process)
Type of emission
Stack/Vent Height (meter)
Air Pollution Control Measures
(APCM)
1 Ethyl Mecpatan Vent 1.5 NA
Ethyl Mercaptan vapors generated are passed through vertical column scrubber where it is broken down into millions of particles and allowing lighter air to escape to the atmosphere where as denser Ethyl Mercaptan particles settled down thus avoiding any bleed liquor generating and flared to atmosphere. Collected Mercaptan after scrubbing is sent back to storage system.
iii Fugitive emission details with its mitigation measures.
Fugitive emissions are from DG sets which are used as power backup source only. Individual stack with adequate height is provided. HC emissions are envisaged as fugitive emissions from leakages. LDAR are conducted on regular intervals and leaks are controlled if any.
F Hazardous waste
Page 14 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 14 of 41
(as per the Hazardous and Other Wastes (Management and Transboundary
Movement) Rules 2016.
Existing & Proposed
i
Sr. no.
Type/Name of Hazardous
waste
Source of generation
Category and Schedule as
per HW Rules.
Quantity (MTPA)
Disposal Method
1 Existing
Used oil/spent oil
DG sets 5.1 4.46
Collection, storage & disposal to authorized recyclers
2 Proposed
Used oil/spent oil
DG sets 5.1 10.4
Collection, storage & disposal to authorized recyclers
-
ii Membership details of TSDF, CHWIF etc.
(For HW management)
-Nil-
iii Details of Non-Hazardous waste & its
disposal(MSW and others)
MSW - Local Bins
Sewage waste to Septic tanks/ Soak
pits
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered
Solvents
Nil
ii VOC emission sources and its mitigation measures
Fugitive emissions are from DG sets which are used as power backup source only. Individual stack with adequate height is provided. HC emissions are envisaged as fugitive emissions from leakages. LDAR are conducted on regular intervals and leaks are controlled if any.
• During the meeting dated 03/01/2019, technical presentation made during the meeting by project proponent.
• During the meeting, the project was appraised based on the information furnished in the EIA Report, various
issues raised during the public hearing and details presented during the meeting.
• The baseline environmental quality has been assessed for various components of the environment viz. air,
noise, water, biological and socioeconomic aspect. The baseline environmental study has been conducted for
the study area of 10 km radial distance from project site for the period March 2017 to May 2017. Ambient Air
Quality monitoring was carried out for PM10, PM2.5, SO2, NOx, HCl, NH3, O3, Pb, As, Ni, C6H6, HC, CO and
VOC at nine locations, including the project site. Values conform to the prescribed standards for Ambient Air
Quality. The incremental Ground Level Concentration (GLC) has been computed using AIRMOD view. The
Page 15 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 15 of 41
resultant concentrations are within the NAAQS. The modelling study proved that the air emissions from the
proposed plant would not affect the ambient air quality of the region in any significant manner. The ambient air
quality around the proposed project site will remain within the National Ambient Air Quality Standards
(NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency Plan
has been covered in the RA report.
• The proposal is for expansion. Compliance of CCA conditions, action taken by GPCB were deliberated at
length. PP mentioned that unit is complying with all the conditions stipulated in existing CC&A. It is noted that
there is no public compliant and public litigation pending against the unit. PP mentioned they will surrender
existing membership of ETL. Source of water is GIDC. All the generated w/w will be treated in primary ETP
followed by MEE, Condensate will be recycled and salt will be sent to TSDF. PP has proposed one new 2 TPH
boiler along with HAG along with their respective APCM. Unit will surrender existing 400 kg/hr boiler after
proposed expansion. Fuel used in HAG and boiler will be imported coal/agro waste. PP has also proposed one
additional HAG & TFH in which NG will be used as fuel. Two process reaction vessel are proposed along with
APCM. PP addressed Hazardous waste disposal as per HWR – 2016. PP mentioned that Hypo & NaBr
solution generated from scrubber will be disposed of to end users having necessary permission under rule-9.
• PP address impact on surface water and ground water quality and Noise. EMP, CER with details of budgetary
provisions and were found satisfactory.
• Compliance of the ToR was found satisfactory.
After detailed discussion, it was decided to recommend the project to SEIAA Gujarat for grant of
Environmental Clearance.
16 SIA/GJ/IND2/21268/2017 Arochem Industries Pvt Ltd Plot No. 153/A, 154/1, 154/2, Phase-II GIDC Vapi, Pardi, Valsad
Appraisal
Category of the unit : 5(f)
Project status: Expansion
• PP has submitted online application vide no. SIA/GJ/IND2/21268/2017 dated 19/11/2018 for obtaining
Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated 11/09/2018.
• Project proponent has submitted EIA Report prepared by Eco Chem Sales & Services, Surat based on the
TOR issued by SEIAA
• This is an existing unit engaged in Synthetic organic chemicals and now proposes for expansion as tabulated
below:
# Product CAS No.
Capacity (TPM) End-use of
product Existing Proposed Total
Page 16 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 16 of 41
1. Resist Salt 127-68-4 80 320 400 Metal Plating, pigment & high performance
pigment, Dyes & dyes
intermediates, Optical
brightener, Pharma
industries, high resistance
resin, poultry Industry,
Single super phosphate.
2. Metanilic Acid 121-47-1 20 250 270
3. 3,3 Di nitro Di phenyl sulphone
(DNDS)
1228-53-1
0 26.2 26.2
4. 3- Amino- 4- Chloro Benzoic
Acid
2840-28-0
0 25 25
5. P- Amino Benzoic acid
150-13-0
6. P- Amino Benzamide
2835-68-9
7. 2 -Amino Di Methyl
Teraphthalate
120-61-6 6 14 20
8. 2,5- Di Methyl-P- Phenylene
diamine
6393-01-7
0 20
20
9. 2,5 Di Chloro-P- Phenylene di
amine
20103-09-7
10. 2- Chloro-P- Phenylene di
amine
615-66-7
11. 2- Chloro-5- methyl-p-
Phenylene di amine
5307-03-9
12. 2- Amino-p- xylene
95-78-3 0 25 25
13. m- Chloro aniline 108-42-9 0 50 50
14. Phenoxy Ethane (2,2- Di Amino Di Phenoxy ethane)
52411-34-4
0 15 15
15. 3-3 Di Amino Di phenyl Sulphone
599-61-1 0 18.34 18.34
16. Aniline-2,5- Di Sulphonic acid
98-44-2 20 55 75
17. Nitro Benzene 98-95-3 0 300 300
18. 2- Nitro Di Methyl Teraphthalate
5292-45-5
0 25 25
19. 3- Nitro-4 Chloro Benzoic acid
96-99-1 0 20 20
20. 2,5- Di Methyl 4- Nitro Aniline
3460-29-5
21. 2-Chloro-5-Methyl-4- Nitro
Aniline
70902-72-6
22. 2,5 Di Chloro Para Nitro Aniline
6627-34-5
23. Nitro P-Xylene 89-58-7 0 25 25
24. Di Calcium Phosphate
7757-93-9
0 625 625
25. N-N Di Ethyl-m- 91-68-9 0 10 10
Page 17 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 17 of 41
Amino Phenol
26. Meta Amino Phenol
591-27-5
Total 126.0 1823.54 1949.54
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 03/01/2019.
• Salient features of the project are as under:
Sr. no.
Particulars Details
A Total cost of Proposed Project (Rs. in Crores):
Existing: 3.99 Crore Proposed: 14.55 Crores Total: 18.54 Crores
B Total Plot area ( sq. meter)
Existing: 15220.22 m2 Proposed: 0 m2 (Expansion will be done in existing open area) Total: 15220.22 m2
Green belt area ( sq. meter)
Existing:4000 m2 Proposed: 1023 m2 Total: 5023 m2
C Employment generation Existing:60 Proposed:90 Total:150
D Water
i
Source of Water Supply (GIDC Bore well, Surface water, Tanker supply etc...)
GIDC, Vapi Water Supply
Status of permission from the concern authority.
Permission issued by GIDC Vapi vide letter No. GIDC/DEE(W/S)/NA/VAPI/797 on 17/11/2017
ii Water consumption (KLD)
Existing KLD
Proposed (Additional) KLD
Total after Expansion KLD
Remarks
(F) Domestic 2.0 3.0 5.0 -- (G) Gardening 0.0 2.0 2.0 --
Industrial
Process 5.6 97.48 103.08
Processing and Product Washing
Washing 0.0 3.0 3.0
Floor/container/equipment washing
Boiler 0.0 10.0 10.0 --
Cooling 1.0 4.0 5.0 --
Others 0.0 2.0 2.0 Scrubber
Industrial Total 6.6 116.48 123.08
Grand Total (A+B+C)
8.6 121.48 130.08
7) Total water requirement for the project: 130.08 KLD 8) Quantity to be recycled: 0 KLD 9) Total fresh water requirement: 130.08 KLD
Page 18 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 18 of 41
iii Waste water generation (KLD)
Category Existing KLD
Proposed (Additional) KLD
Total after Expansion KLD
Remarks
(D) Domestic 2.0 3.0 5.0 -- Industrial
Process 0.9 48.48 49.38
Processing & product washing
Washing 0.0 3.0 3.0
Floor/container/equipment washing
Boiler 0.0 2.0 2.0 --
Cooling 0.05 2.0 2.05 --
Others (scrubber) 0.0 2.0 2.0 Scrubber
Total Industrial waste water
0.95 57.48 58.43
iv Treatment facility within premises with capacity [For existing and Proposed] [In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
Primary, secondary & tertiary ETP – 0.45 KLD Spray Dryer – 57.48 KLD
v Mode of Disposal & Final meeting point
Domestic:
Domestic Effluent: It is being/will be disposed-off through septic tank.
Industrial:
Industrial Effluent: 0.5 KLD of process effluent will be segregated and sent to CMEE installed at CETP Vapi, 57.48 KLD of effluent will be spray dried in proposed spray dryer and 0.45 KLD of floor wash water will be treated in the primary, secondary and tertiary effluent treatment plant and discharged into underground effluent drainage line to CETP Vapi for further treatment and disposed into tidal zone of River Damanganga.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE, CHWIF etc. Name of Common facility
VGEL
Membership of Common facility (CF)- • VGEL certificate for CETP, CMEE & CSWP facility Vide letter No. VGEL/2016-17/0144-116 dated 03/05/2016 &
VGEL/NOC/2017-18/0404 dated 08/09/2017
• VGEL certificate for CMEE Vide letter No. VGEL/NOC/2015-16/038 dated 05/08/2015
vii Simplified water balance diagram with reuse / recycle of waste water
Page 19 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 19 of 41
vii Reuse/Recycle details (KLD) [Source of reuse & application area]
Total reuse - 54 KLD
Source of waste water for reuse with quantity in KLD
Application area with quantity in KLD
Remarks regarding feasibility to reuse i.e. w/w characteristics (COD, BOD, TDS etc.)
-- -- --
E Air
i Flue gas emission details No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc. Existing & Proposed
S.. No.
Source of
emission
With Capacity e.g.
Boiler (8 TPH)
Stack Heig
ht (mete
r)
Name of the fuel
Quantity of Fuel
MT/hr &
MT/Day
Type of emissions i.e.
Air Pollutan
ts
APCM
Emission
Standard
Remarks
1.
Steam Boiler (0.2 TPH)
30 Coal 1
MT/day
PM SOx NOx
Multi Cyclone separator and Chimney
<PM: 150 mg/Nm3
, <SO2:100 ppm <NOx: 50 ppm
Proposed
2. Thermopak (2.5 Lakh k
30 Coal 1
MT/day
Multi Cyclone
Existing
Page 20 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 20 of 41
cal) separator and Chimney
3.
Thermopak (25 Lakh kcal)
30 Coal 3.6
MT/day
Multi Cyclone separator and Chimney
Proposed
4 D G Set: I (250 kVA)
11 HSD 20 kg/h Exhaust
Existing
5 D G Set: II (500 kVA)
11 HSD 40 kg/h Exhaust
Proposed
6 Hot air generator
30 Imported coal
600 kgs/Hr
MDC followed by bag filter
Proposed
7 Spray Dryer
30
NA (Direct Firing
through HAG)
2500 kg/h
(Liquid)
Cyclone & Water scrubber
Proposed
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.) Existing & Proposed
Sr. no.
Source of emission
Type of emission
Stack/Vent Height (meter)
Air Pollution Control
Measures (APCM)
Remarks
1
Sulphonator & Oleum Storage Tank
SO2 & SO3
11 Acid followed by alkali scrubber
Existing
2 Sulphonator & Nitrator
SO2 & NOx
11 Two stage alkali scrubber
Proposed
iii Fugitive emission details with its mitigation measures.
• Concrete road is already developed within plot premises to avoid fugitive dust due to vehicle movement.
• Manufacturing activity is/will be carried out in closed reactors/vessels and
• Regular checking and maintenance of the same is/will be carried out to avoid any leakages.
• All the raw materials are/will be stored in closed containers and in sealed bags and will be handled through closed system to avoid the handling losses.
F Hazardous waste (as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016. Existing & Proposed
i S.
No.
Type/Name of
Hazardous
Source of generation
Category and
Schedule
Quantity (TPA)
Disposal Method
Existing Proposed Total
Page 21 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 21 of 41
waste as per HW Rules
1. Waste from ETP
ETP Sch: I 35.3 15 185 185 Sell to Cement Industries for co-processing or disposed-off
into TSDF, VGEL,VAPI or SEPPL, Kutch
2. Salt from
Spray Dryer Spray dryer Sch: I 35.3 0 2070 2070
Disposed-off into TSDF,
VGEL,VAPI or SEPPL, Kutch
3. Gypsum waste from the process
Manufacturing process
Sch: I 26.1 145 24491 24636 Send Cement Industries for co-processing
4. Iron waste from
process
Manufacturing process
Sch:I 26.1 345.6 2894.4
3240 Send Cement Industries for co-processing
5. Distillation Residue from the process
Manufacturing process
Sch: I26.1 0 12.96 12.96 Send to GSPL, Palsana for Incineration
6. Used Oil D.G.sets Sch:I 5.1 0.03 0.07 0.1 Sell to registered re-processers
7. Discarded containers
Raw material/ product storage and from utility
Sch:I 33.1 108.0 17 125 Utilized for packing of hazardous
waste or sell to authorized
recycler
8. Salt from the process
Manufacturing process
Sch: I 26.1 0 137.4 137.4 Dispose off into TSDF,
VGEL,VAPI or SEPPL, Kutch
9. Spent Solvent
Manufacturing process
Sch: I 26.4 0 1148 1148 Recycled in process
10. Spent Sulphuric
Acid (70%) - xylene)
from product (Nitro benzene, NDMT, 3- nitro 4- chloro benzoic acid, nitro p
Sch: I 26.3 0 12457.5 12457.5 Utilize for the in-house
manufacturing of product i.e Di Calcium phosphate
Solid Waste
11. Fly Ash Boiler and Thermopak
- 23.1 383.46 406.5 Sell to Brick/Cement Manufacturer
Quantity of discarded containers must be in MT/Annum.
ii Membership details of TSDF, CHWIF etc. (For HW management)
• VGEL certificate for CETP, CMEE & CSWP facility Vide letter No. VGEL/2016-17/0144-116 dated 03/05/2016 & VGEL/NOC/2017-18/0404 dated 08/09/2017
Page 22 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 22 of 41
• VGEL certificate for CMEE Vide letter No. VGEL/NOC/2015-16/038 dated 05/08/2015
• GSPL membership for TSDF & CHWIF certificate No. CPAW1A0037
• SEPPL membership for TSDF & CHWIF certificate No. CSA123
iii Details of Non-Hazardous waste & its disposal(MSW and others)
Fly Ash-406.5 TPA Disposal: It will be sold to Brick/Cement Manufacturer
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents
S.No. Name of the Solvent Total Consumption
(TPM)
Recovery (TPM)
Loss/with residue (TPM)
% Recovery
1. Methanol 366.15 330.89 35.26 98.4
2. MonoChlorobenzene(MCB) 438.77 433.42 5.35 98.8
3. Dimethylformamide (DMF) 119.69 115.01 4.68 96.0
4. Toluene 219.38 212.36 7.02 96.8
5. Ethyl Acetate 58.98 57.28 1.70 97.1
ii VOC emission sources and its mitigation measures
Source: Process Reactor • Raw material Handling & Storage Mitigation Measures: • The raw materials will be stored in closed containers and will be handled through closed system to avoid the handling losses • Reactor and solvent handling pumps will have mechanical seals to prevent leakages. Reactors shall also be provided with breather valve to prevent losses.
• During the meeting dated 03/01/2019, technical presentation made during the meeting by project proponent.
• During the meeting, the project was appraised based on the information furnished in the EIA Report, various
issues raised during the public hearing and details presented during the meeting.
• The baseline environmental quality has been assessed for various components of the environment viz. air,
noise, water, biological and socioeconomic aspect. The baseline environmental study has been conducted for
the study area of 10 km radial distance from project site for the period October 2017 to December 2017.
Ambient Air Quality monitoring was carried out for PM10, PM2.5, SO2, NOx, at eight locations, including the
project site. Values conform to the prescribed standards for Ambient Air Quality. The incremental Ground Level
Concentration (GLC) has been computed using AIRMOD view. The resultant concentrations are within the
NAAQS. The modelling study proved that the air emissions from the proposed plant would not affect the
ambient air quality of the region in any significant manner. The ambient air quality around the proposed project
site will remain within the National Ambient Air Quality Standards (NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency Plan
has been covered in the RA report.
• The proposal is for expansion. Compliance of CCA conditions, action taken by GPCB were deliberated at
length. PP mentioned that unit is complying with all the conditions stipulated in existing CC&A. It is noted that
Page 23 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 23 of 41
there is no public compliant and public litigation pending against the unit. Source of water is GIDC. PP
mentioned that they will segregate High TDS/ High COD w/w and will sent to CMEE. The floor washing w/w will
be treated in ETP and further sent to CETP Vapi. Additional proposed quantity of effluent will be treated in
ETP. PP has proposed additional TFH, Boiler, Spray Dryer & HAG along with their respective APCM. Fuel
used will be coal. PP mentioned that they have proposed additional reaction vessel with their respective
APCM. PP address about Spent sulphuric acid (70%) generated from the manufacturing of Nitro Benzene,
NDMT, 3-Nitro 4-Chloro Benzoic Acid & Nitro P and informed that they shall be utilized in-house in the
manufacturing of Di-Calcium Phosphate completely. PP address Hazardous waste as per HWR – 2016.
• PP address impact on surface water and ground water quality and Noise. EMP, CER with details of budgetary
provisions and were found satisfactory.
• Compliance of the ToR was found satisfactory.
• After detailed discussion, it was decided to recommend the project to SEIAA Gujarat for grant of
Environmental Clearance.
17 SIA/GJ/THE/18824/2017 M/s. Bellfield Power Inception Pvt. Ltd. Survey No: 1382/1, 1382/2, 1383/1, 1383/2 and 1413/1P, Village: Naika, Ta & Dist: Kheda (Gujarat).
Appraisal
Category of the unit : 1(d)
Project status: New
• PP has submitted online application vide no. SIA/GJ/THE/18824/2017 dated 18/11/2018 for obtaining
Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated 30/04/2017.
• Public Hearing was conducted by Gujarat Pollution Control Board on 07/07/2018 at project site of M/s. Bellfield
Power Inception Pvt. Ltd., Survey No: 1382/1, 1382/2, 1383/1, 1383/2 and 1413/1P, Village: Naika, Ta & Dist:
Kheda (Gujarat).
• Project proponent has submitted EIA Report prepared by M/s. Kadam Environmental Consultants based on the
TOR issued by SEIAA.
• The is a new project of Power Plant and falls under Category B of project activity 1(d) as per the schedule of
EIA Notification 2006 and details of the power plant is tabulated as below.
Sr. No.
Name of the Products
Quantity MT/Month
End-use of products
1 Power Plant 23 MW Will be supplied to nearby industries and textile units
• The project falls under the Category B of project activity 1(d) as per the schedule of EIA Notification 2006.
• Public Hearing on the project was held on 07/07/2018
• PP was called for presentation in the SEAC meeting dated 03/01/2019.
• Salient features of the project are as under:
Sr. Particulars Details
Page 24 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 24 of 41
no.
A Total cost of Proposed Project
(Rs. in Crores):
73.9 Crores
1. Capital cost for EMS (Environmental Management System): 3.77 Crores
2. Recurring cost towards the environmental protection measures: 0.68 Crores
per Annum.
B Total Plot area ( sq. meter) 16,844 Sq. m.
Green belt area,/Tree Plantation area ( sq. meter)
5,665 Sq. m.
C Employment generation
1. Direct 50
2. Indirect 25
Total 75
D Water
i
Source of Water Supply (GIDC Bore well, Surface water, Tanker supply r etc...)
Bore well
Status of permission from the concern authority.
CGWA Application done.
ii
Water consumption (KLD)
Category
Water Consumption KLD
Remarks
(A) Domestic 5
(B) Gardening 20
(C) Industrial 585
Process
Washing
Boiler 441
Cooling 144
Others 737 Primary RO
Industrial Total 585
Total (A + B + C)
610
1) Total water requirement for the project: 757 KLD
2) Quantity to be recycle: 191 KLD
Page 25 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 25 of 41
3) Total fresh water requirement: 566 KLD
iii Waste water generation (KLD)
-
Category KLD Remarks
(A) Domestic 4 To soak pit & Septic tank
(B) Industrial 217
Process
Washing
Boiler 53
Cooling 17
Others 147 Primary RO
Total Industrial waste water
217
-
iv Treatment facility with capacity (ETP, CETP, MEE, STP, Spray Dryer etc).
Recycling RO will be provided at the site to reduce freshwater consumption.
v Mode of Disposal & Final meeting point
Domestic: to septic tank and soak pit.
Industrial: reuse in coal dust suppression.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc. , name of CF
--
Membership of Common facility (CF) --
vii Reuse/Recycle details (KLD) 191
E Air
i Flue gas emission details No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
-
SR. no.
Source of emission
With Capacity
Stack Height (meter)
Type of Fuel
Quantity of Fuel MT/Day
Type of emissions
i.e. Air Pollutants
Air Pollution Control
Measures (APCM)
1 Boiler 1 & 2 (55 TPH each)
80
Imported coal & Rice husk.
565 MTPD
SPM, SO2 & NOX
ESP
2
DG Set-1.5 MW (for Emergency Purpose only)
15 HSD 400 LPH SPM, SO2 &
NOX Adequate stack height
-
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
Page 26 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 26 of 41
-
Sr. no.
Source of emission
Type of emission
Stack/Vent Height (meter)
Air Pollution Control
Measures (APCM)
1 Not Applicable
-
iii Fugitive emission details with its mitigation measures. As below:
Dust generation in the material handling section, fugitive emission of limestone dust, coal
dust, fly ash dust are possible. As per the norms of GFR, following control measures will be
taken to ensure a safe and healthy work place environment:
● Enclosed conveyors for the transportation of the solid fuel;
● Water sprinkling system in the material storage yard to suppress the dusting due to winds;
● Storage of the fly Ash only in the closed silo;
● Transportation of the fly Ash in the Bunker
F Hazardous waste (as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016.
i
Sr. no.
Type of Hazardous
waste
Source of generation
Category and Schedule as
per HW Rules.
Quantity (MT/Annum)
Disposal Method
1 Used/Spent oil Maintenance Operations
5.1 5 Sold to GPCB authorised Reprocessors
2 Oil Stained Cloth
Maintenance operations, material spillage clean-up
5.2 2 sent it to GPCB authorised incineration facility
Quantity of discarded containers must be in MT/Annum.
ii Membership details of TSDF, CHWIF etc. SEPPL Membership for Incineration.
ii Details of Non-Hazardous waste & its disposal (MSW and others)
Waste Name Disposal Method
Municipal Solid
Waste
Shall be handled as per
the Solid Waste
Management Rules,
2016 as amended from
time to time
Biomedical Wastes
Shall be handled as per
the Bio-Medical Waste
Management Rules,
2016 as amended from
time to time
Used Lead Acid
Batteries
Shall be handled as per
the Batteries
(Management &
Page 27 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 27 of 41
Handling) Rules, 2010 as
amended from time to
time
Electronic wastes
Shall be handled as per
the E-Waste
(Management) Rules,
2016 as amended from
time to time
Construction and
Demolition (-C&D)
Wastes
Shall be handled as per
the Construction and
Demolition Waste
Management Rules,
2016 as amended from
time to time
G Solvent management & VOC emissions etc.
i Details of Solvent recovery (As per respective ToR) Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents
Not Applicable
ii VOC emission sources and its mitigation measures
Not Applicable
• During the meeting dated 03/01/2019, technical presentation made during the meeting by project proponent.
• During the meeting, the project was appraised based on the information furnished in the EIA Report, various
issues raised during the public hearing and details presented during the meeting.
• The baseline environmental quality has been assessed for various components of the environment viz. air,
noise, water, biological and socioeconomic aspect. The baseline environmental study has been conducted for
the study area of 10 km radial distance from project site for the period March 2017 to June 2017. Ambient Air
Quality monitoring was carried out for PM10, PM2.5, SO2, NOx, Hg, HC and CO at eight locations, including
the project site. Values conform to the prescribed standards for Ambient Air Quality. The incremental Ground
Level Concentration (GLC) has been computed using AIRMOD view. The resultant concentrations are within
the NAAQS. The modelling study proved that the air emissions from the proposed plant would not affect the
ambient air quality of the region in any significant manner. The ambient air quality around the proposed project
site will remain within the National Ambient Air Quality Standards (NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency Plan
has been covered in the RA report.
• It is noted that proposal is new in Village Naika. Proposal is for establishment of thermal power plant for nearby
textile units. Source of water is bore well. PP has yet not received CGWA permission for extraction of Ground
water. PP has proposed 2 nos. 55 TPH boiler with ESP as APCM. Fuel used is Husk/Coal.
After deliberation, SEAC unanimously decided to consider the proposal after submission of the following
details.
Page 28 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 28 of 41
• Justification for proposed project unit size.
• Technical Feasibility of 26 KLPD RO-Reject that is to be reused along with Justification.
• Third scenario of 70/30, Husk/Coal Ratio in baseline study and its impact on the surrounding area and the
gaseous emission taking place from the same.
• CGWA permission for extraction of ground water.
• Rice Husk Storage & Transportation Management Plan within 50 KM area.
18 SIA/GJ/IND2/20399/2017 M/s. Asiatic Composite Limited Survey No. 1963/185/24-B-Paiki, Village: Mankol, Tal: Sanand-382110, Dist: Ahmedabad, Gujarat
Appraisal
Category of the unit : 5(f)
Project status: Expansion
• PP has submitted online application vide no. SIA/GJ/IND2/20399/2017 dated 06/09/2017 for obtaining
Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated 16/02/ 2018.
• Project proponent has submitted EIA Report prepared by B. S. Rana based on the TOR issued by SEIAA.
• Public Hearing was conducted by Gujarat Pollution Control Board on 18/06/2018 at project site of M/s. Asiatic
Composite Limited Survey No. 1963/185/24-B-Paiki, Village: Mankol, Tal: Sanand-382110, Dist: Ahmedabad,
Gujarat.
• This is an existing unit engaged in Synthetic organic chemicals and now proposes for expansion as tabulated
below:
Sr. no.
Name of the Products
CAS no. / CI no.
Quantity MT/Month
End-use of the products Existing Proposed Total
1 FRP Tank,
Pultrsion
Profile,
FR Sheet
- 600 - 600
Storage of materials
2 Unsaturated Polyester Resins
9003-01-4
- 700 700
FRP Tank 3 Saturated
Polyester Resins
61926-16-7
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• Public Hearing of the project was held on 18/06/2018.
• PP was called for presentation in the SEAC meeting dated 03/01/2019.
• Salient features of the project are as under:
Sr. Particulars Details
Page 29 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 29 of 41
no.
A Total cost of Proposed Project
(Rs. in Crores):
Existing: 5.50 Crores Proposed: 1.50 Crores Total: 7.00 Crores
(1) Capital cost for EMS (Environmental Management System):15 Lacs
(2) Recurring cost towards the environmental protection measures:3 Lacs per Annum.
B Total Plot area
( sq. meter)
Existing: 2,12.056 .Sq. meter Proposed: Nil (1249.02 sq. meter required but within the premises) Total: 2,12,056 Sq. meter
Green belt area
(sq. meter)
Existing: 64000 Sq. meter Proposed: 1000 Sq. meter Total: 65000 Sq. meter
C Employment generation
1. Direct Existing: 61 Proposed: 3 Total: 64
2. Indirect Existing: 20 Proposed: 10 Total: 30
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply
etc...)
Bore well Supply
Status of permission from the concern authority.
Applied for CGWA permission. Application Number :- 21-
4466/GJ/2018
ii
Water consumption (KLD)
Existing
KLD
Proposed
(Additional)
KLD
Total after
Expansion
KLD
Remarks
(H) Domestic 2.5 0.2 2.7 -
(I) Gardening
Reuse of STP treated
sewage
Reuse of STP treated
sewage
(J) Industrial
Page 30 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 30 of 41
Process - - - -
Washing 0.0 0.0 0.0 -
Boiler 0.2 0.5 0.7 -
Others - - - -
Industrial Total 0.2 0.5 0.7 -
Grand Total
(A+B+C)
2.7 0.7 3.4 -
10) Total water requirement for the project: 3.4KLD
11) Quantity to be recycled:
� 0.7 KLD R.O. permeate will be Reused for make up in cooling tower,
� Treated sewage will be Reused for gardening
12) Total fresh water requirement after recycled: 2.7 KLD
iii
Waste water generation (KLD)
Category Existing
KLD
Proposed
(Additional)
KLD
Total after
Expansion
KLD
Remarks
(E) Domestic 2.0 0.1 2.1 -
(F) Industrial
Process Nil 0.862 0.862 -
Washing - - - -
Boiler 0.05 0.038 0.088 -
Cooling - - - -
Others 0.05 0.9 0.95 -
Total Industrial
waste water
Nil 0.862 0.862 -
iv Treatment facility within premises with capacity [For existing and Proposed]
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
ETP: Primary Treatment ETP Capacity: 2.2 KLD ETP details are given in Page No. 101, Table 2.13 of chapter 2
v Mode of Disposal & Final meeting point
Domestic: Treated sewage will be reused
Industrial: ZLD
Page 31 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 31 of 41
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE,
CHWIF etc.
Name of Common facility
NA
Membership of Common facility (CF)
(For waste water treatment)
vii Simplified water balance diagram with reuse / recycle of waste water
Note: All figures are in KLD
vii Reuse/Recycle details (KLD)
[Source of reuse & application area]
Total reuse 0.7 KLD
Total water consumption: 3.4 KLD
Water consumption after recycling :2.7 KLD
Source of waste water
for reuse with
quantity in KLD
Application area with
quantity in KLD
Remarks regarding
feasibility to reuse
i.e. w/w
characteristics
(COD, BOD, TDS
etc.)
Page 32 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 32 of 41
Condensate water of ETP Evaporator
Cooling tower feed water: 0.7 KLD
Distillate Water pH:7.0 COD:18 mg/l BOD:6 mg/L TDS: 210 mg/L
-
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr,
KVA etc.
Existing & Proposed
-
Sr.
no.
Source of
emission
With
Capacity
Stack
Height
(meter)
Type
of
Fuel
Quantity
of Fuel
MT/Day
Type of
emissions
i.e. Air
Pollutants
Air
Pollution
Control
Measures
(APCM)
1
Thermic
Fluid Heater
(2 Lac K
cal)
12
LDO 25 Lit/hr
PM SO2 NOx
Adequate Stack Height
2
D.G Set
(125 KVA)
(existing)
5
Diesel 7 Lit/hr PM SO2 NOx
Adequate Stack Height
-
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
Existing & Proposed
- There is no process gas emission from manufacturing process
iii Fugitive emission details with its mitigation measures.
Fugitive emission details: • Fugitive emission will due to the leakages in pump, storage container, material
transferring, and packing.
Mitigation measures: • Proper storage of raw materials, products and fuels
• Ensuring closed feeding and sampling.
• Establishing SOPs for start-up, shut down and maintenance operational procedure. Regular work place and ambient air quality monitoring will be done.
F Hazardous waste
(as per the Hazardous and Other Wastes (Management and Transboundary
Movement) Rules 2016.
Page 33 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 33 of 41
Existing & Proposed
i Sr. no.
Type/Name of Hazardous waste
Source of generation
Category and Schedule as per HW Rules.
Quantity (MT/Annum)
Disposal Method
1 ETP Sludge
ETP 33.4
2.4
Collection,
Storage,
Transportation,
Disposal at
TSDF
site
2
FRP Board
(FRP Sheet)(Trimming
of the edges)
Process 21.1
0.96
3
Evaporation
residue
Process -
0.36
4
Used oil/ spent
oil
DG set 5.1
0.03
Collection,
Storage,
Transportation, sell to Registered Pre-processor/
Used as
lubricant in
premises
5
Drum /
Discarded
Container
Raw
material
packing
33.3
300
Nos./year
Sold to
Registered
Re-processor/
Sand back to
supplier
Bags
10000
Nos./year
Sold to
Registered
Recycler/ Sand
back to supplier
ii Membership details of TSDF, CHWIF etc.
(For HW management)
TSDF membership will be done after
getting EC.
iii Details of Non-Hazardous waste & its
disposal(MSW and others)
Plastic waste shall send to the registered
recycler.
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered
Solvents
No use of Any solvent.
ii VOC emission sources and its mitigation measures
Pumps will be provided for liquid transferring and hopper will be provided for solid transferring.
Page 34 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 34 of 41
• During the meeting dated 03/01/2019, technical presentation made during the meeting by project proponent.
• During the meeting, the project was appraised based on the information furnished in the EIA Report, various
issues raised during the public hearing and details presented during the meeting.
• The baseline environmental quality has been assessed for various components of the environment viz. air,
noise, water, biological and socioeconomic aspect. The baseline environmental study has been conducted for
the study area of 10 km radial distance from project site for the period November 2017 to January 2018.
Ambient Air Quality monitoring was carried out for PM10, PM2.5, SO2, NOx, and VOC at ten locations,
including the project site. Values conform to the prescribed standards for Ambient Air Quality. The incremental
Ground Level Concentration (GLC) has been computed using AIRMOD view. The resultant concentrations are
within the NAAQS. The modelling study proved that the air emissions from the proposed plant would not affect
the ambient air quality of the region in any significant manner. The ambient air quality around the proposed
project site will remain within the National Ambient Air Quality Standards (NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency Plan
has been covered in the RA report.
• The proposal is for expansion. Compliance of CCA conditions, action taken by GPCB were deliberated at
length. PP mentioned that unit is complying with all the conditions stipulated in existing CC&A. It is noted that
there is no public compliant and public litigation pending against the unit. Source of water is Bore well. PP
mentioned that they will segregate High TDS/ High COD w/w and will sent to CMEE. PP mentioned that the
w/w generated will be treated ETP followed by RO. RO permeate will be reused back in process while RO
Reject will be evaporated in evaporator, hence unit will maintain ZLD. The salt of Evaporator will be send to
TSDF. PP has proposed one TFH. Fuel used will be LDO. PP addressed Hazardous waste as per HWR-2016
satisfactorily.
• PP address impact on surface water and ground water quality and Noise. EMP, CER with details of budgetary
provisions and were found satisfactory.
• Compliance of the ToR was found satisfactory.
• After detailed discussion, it was decided to recommend the project to SEIAA Gujarat for grant of
Environmental Clearance.
19 SIA/GJ/IND2/19974/2017 Advaitya Dye Chem
Plot No. 4785-4786, GIDC Estate,
Ankleshwar, Dist. Bharuch, Gujarat-
393002
Appraisal
Category of the unit : 5(f)
Project status: Expansion
• PP has submitted online application vide no. SIA/GJ/IND2/19974/2017 dated 22/09/2017 for obtaining
Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide their letter dated 20/01/2018.
Page 35 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 35 of 41
• Project proponent has submitted EIA Report prepared by Ramans Enviro Services Pvt. Ltd based on the TOR
issued by SEIAA
• This is an existing unit engaged in Synthetic organic chemicals and now proposes for expansion as tabulated
below:
Sr.
no.
Name of the
Products
CAS no. /
CI no.
Quantity
MT/Month
End-use
of the
products
Existing
Proposed Total
1 Pigment Yellow – 1 2512-29-0
13
27
40
Used in
textiles,
printing,
etc
2 Pigment Yellow –
3(10 G) 6486-23-3
Pigment Yellow - 12 6358-85-6
Pigment Yellow – 13 5102-83-0
Pigment Yellow – 14 5468-75-7
Pigment Yellow – 17 4531-49-1
Pigment Yellow – 62
12286-66-
7
Pigment Yellow – 65 6528-34-3
Pigment Yellow – 74 6358-31-2
Pigment Yellow – 83 5567-15-7
Pigment Yellow –
168
71832-85-
4
Pigment Yellow –
183
65212-77-
3
Pigment Yellow –
191:1
129423-
54-7
Pigment Red – 8 6410-30-6
Pigment Red – 170 2786-76-7
Pigment Red – 210
61932-63-
6
Pigment Orange –
13 3520-72-7
Pigment Orange –
34
15793-73-
4
Page 36 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 36 of 41
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 03/01/2019.
• Salient features of the project are as under:
Sr. no.
Particulars Details
A Total cost of Proposed Project (Rs. in Crores):
Existing: 0.65 Proposed: 0.95 Total: 1.6
B Total Plot area ( sq. meter)
Existing: 2000 Sq. m. Proposed: Nil Sq. m. Total: 2000 Sq. m.
Green belt area ( sq. meter)
Existing: 100 Sq. m. Proposed: Nil Sq. m. Total: 100 Sq. m.
C Employment generation Existing: 20-25 Proposed: 5 Total: 25-30
D Water
i
Source of Water Supply (GIDC Bore well, Surface water, Tanker supply etc...)
GIDC
Status of permission from the concern authority.
Permission letter incorporated in REIA report
ii
Water consumption (KLD)
Existing KLD
Proposed (Additional) KLD
Total after Expansion KLD
Remarks
(K) Domestic 0.4 0.8 1.2 (L) Gardening 0 2 2 (M) Industrial
Process 6.5 14.1 20.6 3.6 KLD will be reused in process.
Washing 2.5 5.5 8 6 KLD will be reused in washing.
Boiler 0.8 9.2 10
Cooling -- -- --
Others -- -- --
Industrial Total
9.8 30.8 43.6
Grand Total (A+B+C)
10.2 31.6 41.8
Page 37 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 37 of 41
13) Total water requirement for the project: 41.8 KLD 14) Quantity to be recycled: 9.6 KLD 15) Total fresh water requirement: 32.2 KLD
iii Waste water generation (KLD)
Category Existing KLD
Proposed (Additional) KLD
Total after Expansion KLD
Remarks
(G) Domestic 0.3 0.6 0.9 (H) Industrial
Process 4.5 9.5 14 Net disposal will be 23.0 KLD.7.0 KLD will disposed to CETP & 6.4 KLD will be disposed through common spray drier of Abad Group of companies.
Washing 2.3 5.7 8
Boiler 0.2 0.8 1
Cooling -- -- --
Others -- -- --
Total Industrial waste water
7 16 23
iv Treatment facility within premises with capacity [For existing and Proposed] [In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
Present System: The present system consisting of 1. Collection cum equalization cum neutralization tank 2. Plate & frame type of filter press (1200 X 1200 X 48 plates) 3. Final treated collection tank for sending effluent to ETL Proposed System: Proposed system will include secondary & tertiary treatment followed by UF+RO.RO reject will be disposed through common spray drier of Abad Group of Companies.
v Mode of Disposal & Final meeting point
Domestic: Domestic sewage will continue to be disposed to septic tank/Soak pit system.
Industrial: 7 KLD will be continued to be disposed at CETP. @ 16.0 KLD will be subjected to primary and secondary treatment followed by UF+RO.Treated water from UF+RO @ 9.6 KLD will be reused back in the plant, whereas, @ 6.4 KLD will be disposed to common spray drier/MEE facility established separately by Abad Group of companies at plot No. : 4782, GIDC, Ankleshwar.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE, CHWIF etc. Name of Common facility
� 7 KLD will disposed to CETP of Enviro technology Limited. � 6.4 KLD will be disposed to Common spray Dryer which is established by Abad Group of
Companies namely AMITA CHEMICAL INDUSTRIES UNIT-II
Membership of Common facility (CF)
� Covered in REIA report.(Annexure-H)
Page 38 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 38 of 41
(For waste water treatment)
Domestic:
Domestic sewage will continue to be disposed to septic tank/Soak pit system.
Industrial:
7 KLD will be continued to be disposed at CETP. @ 16.0 KLD will be subjected to primary and secondary treatment followed by UF+RO.Treated water from UF+RO @ 9.6 KLD will be reused back in the plant, whereas, @ 6.4 KLD will be disposed to common spray drier/MEE facility established separately by Abad Group of companies at plot No. : 4782, GIDC, Ankleshwar.
vii Simplified water balance diagram with reuse / recycle of waste water
vii Reuse/Recycle details (KLD) [Source of reuse & application area]
Total reuse 9.6 KLD
Source of waste water for reuse with quantity in KLD
Application area with quantity in KLD
Remarks regarding feasibility to reuse i.e. w/w characteristics (COD, BOD, TDS etc.)
9.6 KLD Secondary treated wastewater followed by ACF, PSF & UF+RO.
To be mixed with fresh water being recieved from GIDC for various uses in manufacturing process and washing.
COD:Practically Nil BOD:Practically Nil TDS:100-200 mg/L
E Air
i Flue gas emission details No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc. Existing & Proposed
Sr. no.
Source of emission
With Capacity
Stack Height (meter)
Type of Fuel
Quantity of Fuel MT/Day
Type of emissions
i.e. Air Pollutants
Air Pollution Control
Measures (APCM)
Permeate (9.6)
Reuse Stream
(9.6)
(0.9
Domestic (1.2)
Washing +
Boiler (18)
(1)
Process
(20.6)
Gardening (2)
Septic Tank & Soak Pit
(0.9)
UF + RO(16.0)
(1)
(7.0) Reject
GIDC Supply (41.8)
ETL CETP (7.0) Common Spray Dryer Facility (6.4)
(8) (7.0)
Page 39 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 39 of 41
1 Boiler (1 TPH)
11
Natural Gas
@ 200 cu.m /hr
200 cu.m /hr
PM (mg/NM3
SO2 (ppm) NOx (ppm
--
2
Thermic Fluid Heater(4 lakh cal/hr)
9
3 D.G. Set (110 kVA)
Diesel
35 L/hr
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.) Existing & Proposed
Sr. no.
Specific Source of emission (Name of the
Product & Process)
Type of emission
Stack/Vent Height (meter)
Air Pollution Control Measures
(APCM)
1 Air Classifier Mill
(Pulverizer) PM 07 In-built bag filter
2
Common fume extraction hood
with reaction vessel
NOx 07 Caustic Scrubber
-
iii Fugitive emission details with its mitigation measures.
Fugitive emissions are envisaged from the handling of chemicals and manufacturing operations. Hence, the chemical handling & feed systems are automated & pneumatic, also the reactions take place in closed vessels.
F Hazardous waste (as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016. Existing & Proposed
i
Sr. no.
Type/Name of Hazardous waste
Specific Source of generation (Name of the Activity, Product etc.)
Category and Schedule as per HW Rules.
Quantity (MT/Annum)
Management of HW
Existing
Proposed
Total
1 Discarded containers, bags, liners
33.1
3.75 MT/year
Collection, storage, transportation, disposal by sale to
Page 40 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 40 of 41
authorized traders / CHWIF
2
Used Oil
5.1
250 L/Year
Collection, storage and sale to registered recycler.
3
ETP Sludge
35.1
36 MT/Year
Collection, storage, transportation and disposal at TSDF.
-
ii Membership details of TSDF, CHWIF etc. (For HW management)
At present, there is no ETP sludge generation in absence of physio-chemical treatment. However, after expansion membership of TSDF site will be obtained for sludge disposal.
iii Details of Non-Hazardous waste & its disposal(MSW and others)
--
G Solvent management, VOC emissions etc
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents
• Not Applicable
ii VOC emission sources and its mitigation measures
• Not Applicable
• During the meeting dated 03/01/2019, technical presentation made during the meeting by project
proponent.
• During the meeting, the project was appraised based on the information furnished in the EIA Report,
various issues raised during the public hearing and details presented during the meeting.
• The baseline environmental quality has been assessed for various components of the environment viz. air,
noise, water, biological and socioeconomic aspect. The baseline environmental study has been conducted
for the study area of 10 km radial distance from project site for the period October 2017 to January 2018.
Ambient Air Quality monitoring was carried out for PM10, PM2.5, SO2, NO2 & VOC at Nine locations,
including the project site. Values conform to the prescribed standards for Ambient Air Quality. The
incremental Ground Level Concentration (GLC) has been computed using AREMOD model. The resultant
concentrations are within the NAAQS. The modelling study proved that the air emissions from the
proposed plant would not affect the ambient air quality of the region in any significant manner. The ambient
air quality around the proposed project site will remain within the National Ambient Air Quality Standards
(NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios
has been carried out. The detail proposed safeguard measures including On-Site / Off-Site Emergency
Page 41 of 41
468thmeeting of SEAC-Gujarat, Dated 03.01.2019
Page 41 of 41
Plan has been covered in the RA report.
• The proposal is for expansion. Compliance of CCA conditions, action taken by GPCB were deliberated at
length. PP mentioned that unit is complying with all the conditions stipulated in existing CC&A. It is noted
that there is no public compliant and public litigation pending against the unit. Source of water is GIDC. PP
mentioned that out of total w/w generation of 23 KLD, 7 KLD will be sent to CETP of ETL as per existing
CCA condition and proposed 16 KLD will be treated in ETP followed RO. RO permeate 9.6 KLD will be
reused in process and RO reject 6.4 KLD will be sent to Amita Chemical Industries, Unit – II. Committee
asked to submit CC&A to which PP mentioned that CTE of the common spray drying facility is under
process and they will not produce and send treated wastewater to common facility till it obtains CC&A of
GPCB. An undertaking in this regard is submitted by the project proponent. PP has proposed one Boiler &
TFH. Fuel used will be Natural Gas. PP has proposed one air classifier (Pulveriser) & one reaction vessel
in process gas along with respective APCM. PP addressed Hazardous waste as per HWR-2016
satisfactorily.
• PP address impact on surface water and ground water quality and Noise. EMP, CER with details of
budgetary provisions and were found satisfactory.
• Compliance of the ToR was found satisfactory.
• After detailed discussion, it was decided to recommend the project to SEIAA Gujarat for grant of
Environmental Clearance.
Meeting ended with thanks to the Chair and the Members.
Minutes approved by:
1. Dr. Dinesh Misra, Chairman, SEAC 2. Shri S. C. Srivastav, Vice Chairman, SEAC
3. Shri V. N. Patel, Member, SEAC
4. Shri. R. J. Shah, Member, SEAC
5. Dr. V. K. Jain, Member, SEAC
6. Shri A.K. Muley, Member, SEAC