microsoft project 2010 essentials 24 th august 2013, mpug chennai
DESCRIPTION
Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai. Rules. Collaborate Help others Ask Questions Try something new. Agenda. About Project 2010. About Project 2010. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/1.jpg)
Microsoft Project 2010 Essentials
24th August 2013, MPUG Chennai
![Page 2: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/2.jpg)
Rules
1. Collaborate2. Help others3. Ask Questions4. Try something
new
2
![Page 3: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/3.jpg)
Agenda9:40 AM – 11:15 AM
• About Project 2010• Create Project• Customize options
settings• Customize Calendars
Snacks Break
11:30 AM – 1:00 PM
• Create Task Structure• User-controlled
schedule• Link Tasks, critical
path• Add resources, costs
Lunch Break2:00 PM – 4:15 PM
• Assign resources• Task type, effort driven • Resource Leveling• Set and maintain
baseline
Snacks Break
4:30 PM – 6:30 PM
• Keep your schedule up-to-date
• Measure progress • Printing schedules• Q&A
3
![Page 4: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/4.jpg)
About Project 2010
![Page 5: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/5.jpg)
About Project 2010Office Project 2010 delivers project management tools for small ad hoc teams or large organizations with mature management processes and methodologies.
5
![Page 6: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/6.jpg)
A Big Jump in Capability
Microsoft® Fluent™ user interface Zoom In/Out Quickly
Backstage™
Active/Inactive Tasks(PRO)
User-controlled schedule
6
![Page 7: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/7.jpg)
Let’s get the basics right!!
MPP File
Tasks Resources Assignments
TablesView > Tables
ViewsView > Views
FiltersView > Filter:
GroupsView > Group by:
7
![Page 8: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/8.jpg)
Create Project• New project options• Schedule forward/backward• Default start/end time• Default constraints
![Page 9: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/9.jpg)
Customize Project options
• Project defaults the start time and end time to 8:00 AM and 5:00 PM.
• In Options dialog, you can change the default start time and default end time in Schedule tab, Calendar options.
9
![Page 10: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/10.jpg)
Create Project• Click the File tab. This displays Backstage
view• You can create from
• Blank project• Templates• Existing project• Excel workbook
10
![Page 11: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/11.jpg)
Create Project• Before opening files saved in older file
formats change the settings in Legacy Formats tab in Trust Center
• While importing from Excel workbook, make sure the field name is mapped to the right fields
11
![Page 12: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/12.jpg)
Schedule the project• Click the Project tab, and click Project
Information• If you know the Project Start date, choose Project
Start Date in Schedule from: field and select the Start date
• Scheduling forward/backward will set the default constraint type of tasks to “as soon as possible” or “as late as possible”.
12
![Page 13: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/13.jpg)
![Page 14: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/14.jpg)
Customize Calendars• Importance of calendar• Types of calendars• Set working time• Share/rename/delete calendars
![Page 15: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/15.jpg)
Calendar Basics• Project 2010 schedules tasks based on its
predecessors, constraints and calendars set.• Calendars have working days, holidays,
vacations• Project 2010 groups calendars and applied in
the order1. Task Calendar2. Resource Calendar3. Project Calendar
• Generic working time is maintained in Base calendars
15
![Page 16: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/16.jpg)
16
Resource, Task Calendar
Calendar Design work
Work is scheduled as per resource calendar
Server repairs
CalendarWork is scheduled as
per task calendar
Task Calendar has higher priority than Resource Calendar
![Page 17: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/17.jpg)
Calendars and its relationship
17
Base Calendar(location1)
Base Calendar(location2)
![Page 18: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/18.jpg)
18
Global.MPT• Project 2010 copies the base calendars from
Global.MPT • By default, it has 24 hours, Standard and Night
Shift base calendars• Click the Project tab, and click Change
Working time button• Observe the legend to interpret the working and
non-working days
![Page 19: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/19.jpg)
19
Create base calendars• Select the base calendar to be edited (or)
click Create New Calendar button in Change Working time dialog.
• Use the Work Weeks tab to set up the normal working time for the week
• Use the Exceptions tab to set variances to the normal working times for the selected calendar.
![Page 20: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/20.jpg)
20
Work Weeks, Exceptions• Work weeks:
[Default] work week should have the normal working time of the selected calendar
Insert additional work weeks with start and finish to set working time between the start and finish
![Page 21: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/21.jpg)
21
Work Weeks, Exceptions• Exceptions:
Insert exceptions for working times with recurrence pattern
Working times in Exceptions override the working time in Work Weeks
![Page 22: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/22.jpg)
22
Project Calendar• Project Calendar is set to one of the base
calendars• Project 2010 schedules tasks without
resources and task calendar using Project Calendar
• Click Project tab, and click Project Information
• Select the project calendar from the Calendar list
![Page 23: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/23.jpg)
23
Share/rename/delete base calendars
• You can copy Project elements between files, or between a file and the global template.
• Click File tab, click Info and then click Organizer.
• The list on the right box contains the custom elements in the currently opened project
• The list on the left box contains the elements in the global template.
![Page 24: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/24.jpg)
24
Share/rename/delete base calendars
• By default, new views are automatically saved to the global template file.
• To turn off this behavior click File tab, click Options, and then click Advanced.
• Uncheck Automatically add new views, tables, filters and groups to the global in the Display section
![Page 25: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/25.jpg)
25
Working Days report• Working Days report specifies which days are
working days and which are nonworking days for each base calendar used in the project.
• Click Project tab, click Reports in Reports group.
• On the Reports Dialog, click Overview and Working Days
![Page 26: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/26.jpg)
![Page 27: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/27.jpg)
Break
![Page 28: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/28.jpg)
Create Task Structure• Build WBS• User-controlled feature• Set dependencies• Display the critical path
![Page 29: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/29.jpg)
Work Breakdown Structure
• WBS is a deliverable-oriented group of project elements that defines the total project scope.
• WBS is the required for schedule development.
• The hierarchy in WBS can be created by Project Summary Task Summary Task Normal (Detail) tasks Milestones
29
![Page 30: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/30.jpg)
30
Insert Project Summary task
• Project Summary task is used to hold the project vision statement.
• Click Format tab, check Project Summary Task in Show/Hide group to display the project summary task
Show
![Page 31: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/31.jpg)
31
User controlled scheduling
• Project 2010 allows or prevents calculation of duration, start, finish dates of tasks.
• This is achieved by setting the Task Mode field to either Auto scheduled or Manually scheduled
• Right click the task and then click Information, click the General tab, and then change the Schedule Mode:
![Page 32: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/32.jpg)
32
Default duration and work units
• Default duration units is set to days and the default work units is set to hours
• Click File tab, click Options and then click Schedule.
• Change the default units, hours per day, hours per week, days per month can be set
![Page 33: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/33.jpg)
Insert Tasks• Normal (Detail) Task: Tasks with non-zero
duration
• Milestones: Tasks with zero duration
![Page 34: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/34.jpg)
Insert Tasks• Summary Task: They groups set of other
tasks.
• Recurring Task: Same type of task executed repeatedly over a period of time.
![Page 35: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/35.jpg)
35
Task Calendar
• By default, tasks are scheduled based upon the project calendar.• To define unique or specific exceptions/work weeks you can
create a task calendar.• A task calendar that is associated with a task overrides the
project calendar.• To create a task calendar click the Project tab, and click
Change Working Time. Click Create New Calendar and, set the exceptions and workweeks.
• After you create a base calendar, you assign it to the task by selecting the calendar in Calendars list in Advanced tab of Task Information.
Calendar
Server repairs
Calendar
Work is scheduled as per task calendar
![Page 36: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/36.jpg)
36
Task Calendar
• If the task has non-intersecting task and resource calendars, Project alerts Not enough common working time.
• To change how this task is scheduled, either change the task or resource calendar (or) select the Scheduling ignores resource calendars check box in Advanced tab
Calendar
Server repairs
Calendar
Work is scheduled as per task calendar
![Page 37: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/37.jpg)
37
Date Constraints• Constraints are a restriction set on the start
or finish of a task.• You can set date constraints only for auto
scheduled tasksFlexible Moderate Inflexible
As Soon As Possible Start No Earlier Than Must Start On
As Late As Possible Finish No Earlier Than Must Finish On
Start No Later Than
Finish No Later Than
![Page 38: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/38.jpg)
38
Date Constraints• The default task constraint type is set to “As
Soon As Possible” when scheduling forward• Right click the task and then click Information,
click the Advanced tab, and then change the Constraint type: and Constraint date:
• Click View tab, click Tables dropdown, click More Tables … and then click Constraint Dates, click Apply
![Page 39: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/39.jpg)
39
Deadline• Deadline is a target date that indicates
when you want a task to be completed• Right click the task and then click
Information, click the Advanced tab, and then set the Deadline:
• If the task finishes pasts its deadline a Missed Deadline Indicator appears in Indicators field
![Page 40: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/40.jpg)
40
Milestones Report• The Milestones report filters your project tasks to
show only milestone tasks and associated information
• Click Project tab, click Reports in Reports group.
• On the Reports Dialog, click Overview and Milestones
![Page 41: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/41.jpg)
41
Task Dependencies• You should identify the predecessor and
successor with its dependency type before linking them.
• Predecessor: Driving task; Successor: Driven task
• Dependency type can be Finish-to-Start (Default), Start-to-Start (SS), Finish-to-Finish (FF) and Start-to-Finish (SF)
![Page 42: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/42.jpg)
42
Task Dependencies• Select the tasks and then click Task tab, click
. This will link the tasks in a sequence• Right click the task and then click
Information, click the Predecessors tab, and then add a link click the Task Name field on the blank row
• Set multiple predecessors and successors by using the Task Form view (Predecessors & Successors variant).
• Hint: You can split the screen by Split View option in View tab
![Page 43: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/43.jpg)
43
Delay or overlap tasks• Lag is the delay between linked tasks and lead is the
overlap between linked tasks• Lag is entered as positive value and lead is entered as
negative value• Value can be duration or a percentage of the duration of
the predecessor
![Page 44: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/44.jpg)
44
Critical path• Critical path is the longest path and the shortest
time to complete the project• Click View tab, click Tables dropdown, click
More Tables … and then click Schedule, click Apply to display slack
• Click Format tab, check Critical Tasks to show the critical tasks in red
![Page 45: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/45.jpg)
45
Critical Tasks report• This report provides critical tasks with a sub
table containing successor task that will be affected by progress on the critical task.
• Click Project tab, click Reports in Reports group.
• On the Reports Dialog, click Overview and Critical Tasks
![Page 46: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/46.jpg)
46
Critical Tasks Status report
• Use this report to view a diagram showing the work and remaining work for both critical and non-critical tasks.
• Click Project tab, click Visual Reports in Reports group.
• On the Visual Reports dialog, click Task Summary and choose Critical Tasks Status Report
![Page 47: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/47.jpg)
![Page 48: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/48.jpg)
Record resources• Add work/material/cost• Set resource cost• Set resource availability• Customize resource calendar
![Page 49: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/49.jpg)
Resources• Resources are people, facilities, equipment,
materials or money necessary to create project deliverables.
49
![Page 50: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/50.jpg)
50
Work Resources• Click View tab, click Resource Sheet in the Resource
Views group• Work resources have the following attributes
Working time Availability Standard rate, overtime rate and per-use cost
• Set the working time by selecting the Change Working Time button
• Set the availability by adding/removing rows in Resource Availability table in Resource Information
• Set the standard rate, overtime rate and per-use cost in Cost tab in Resource Information
![Page 51: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/51.jpg)
51
Material Resources• Material resources have the following
attributes Standard rate General resource-related fields
• Set the standard rate in Cost tab in Resource Information
• Standard rate is the unit price of the material resource
![Page 52: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/52.jpg)
52
Cost Resources• Cost resources are used to apply
miscellaneous costs (such as airfare, lodging, or dining) to tasks in your project
• They do not work and have no effect on the scheduling of a task
• You enter cost value of a cost resource only when you assign it to a task.
![Page 53: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/53.jpg)
![Page 54: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/54.jpg)
Break
![Page 55: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/55.jpg)
Assignment, Optimization• Set the right task type• Assign resources to tasks• Delay/contour the assignment• Spot and resolve overallocation
![Page 56: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/56.jpg)
56
Task type• Formula: Duration = Work ÷ Resource Units• Task type provides choices that control the
effect that editing work, units, duration as on the other two fields.
In a... If you revise units...
If you revise duration...
If you revise work...
Fixed-units task Duration is recalculated.
Work is recalculated.
Duration is recalculated.
Fixed-work task Duration is recalculated.
Units are recalculated.
Duration is recalculated.
Fixed-duration task
Work is recalculated.
Work is recalculated.
Units are recalculated
![Page 57: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/57.jpg)
57
Task type• By default, task type is Fixed Units.• Right click the task and then click
Information, click the Advanced tab, and then choose the task type
![Page 58: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/58.jpg)
58
Effort-driven scheduling• Effort-driven means that when you assign
or remove people from a task, Project lengthens or shortens the duration of the task based on the amount of resource units assigned to it, but it doesn't change the total amount of work for the task.
• Effort-driven calculations are applied only after the first time one or more resources is assigned to the task.
![Page 59: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/59.jpg)
59
Effort-driven scheduling• By default, effort driven is turned off for
tasks• Right click the task and then click
Information, click the Advanced tab, and then check/uncheck the Effort driven
![Page 60: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/60.jpg)
60
What’s the difference?• Task types determine what happens to the
other two variables in the scheduling formula.
• Effort-driven scheduling determines what happens to the duration or resource units for a task when you add or remove resources.
![Page 61: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/61.jpg)
61
Ready. Set. Go.• Common methods for assignment
• Team Planner view• Assign Resources dialog box• Task Usage (or) Resource Usage view
![Page 62: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/62.jpg)
62
Team Planner view• Click View tab, and then click Team Planner• On the top, you have one row for each resource. On the
bottom, you have the unassigned tasks• You can move tasks to different time or assign it to a
different person by dragging the task or right click on the task and then click Reassign To
• Project updates the constraint of the moved tasks
![Page 63: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/63.jpg)
63
Assign Resources dialog • Click Resource tab, in Assignments group, click Assign
Resources.• Use this dialog to enter, review, or change resource
assignments for the selected task. • As you assign resources, task type and effort driven will
affect the calculation of duration, work and resource units.• As you remove assigned resources from tasks, the
durations for those tasks might change• When you remove a resource from a task, the actual work
and actual cost will be deleted• To keep the actual costs for the task, set the remaining
work of the resource to zero before removing the resource
![Page 64: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/64.jpg)
64
Usage views• Click View tab, in Resource Views
group, click Resource Usage• On the left the resource and its
assignments are displayed. On the right the day-by-day work is displayed.
• Insert Start, Finish columns on the left to know the assignment start and finish
• You can edit the day-by-day work, start, finish of the assignments.
![Page 65: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/65.jpg)
65
Who Does What When report• The Who Does What When report is an
amplification of the information given in the Who Does What report, adding the daily breakdown of hours of work assigned
• Click Project tab, click Reports in Reports group.
• On the Reports Dialog, click Assignments and Who Does What When
![Page 66: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/66.jpg)
66
To-do list report• Use the To-Do List to generate a list of tasks to
provide to assigned resources• Click Project tab, click Reports in Reports
group. • On the Reports Dialog, click Assignments and
To-do List
![Page 67: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/67.jpg)
67
Resource Work Availability report• Use this report to view a bar graph with total
capacity, work, and remaining availability for work resources
• Click Project tab, click Visual Reports in Reports group.
• On the Visual Reports dialog, click Resource Usage and choose Resource Work Availability Report
![Page 68: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/68.jpg)
68
Resource Work Summary report
• Use this report to view a bar graph with total resource capacity, work, remaining availability, and actual work
• Click Project tab, click Visual Reports in Reports group.
• On the Visual Reports dialog, click Resource Usage and choose Resource Work Summary Report
![Page 69: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/69.jpg)
Workload Leveling• Project schedules the work for a resource
based on his calendar but not based on availability
• Scenarios for resource overallocations• Resource total work on a task is more than
availability• Resource is assigned work outside his
availability• Resource is working full time on two or more
parallel tasks• Workload Leveling is a process of
resolving the overallocations with the goal of making the forecast realistic
![Page 70: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/70.jpg)
70
Spot overallocations• Overallocated Resource Report• Resource Work Availability Report• Gantt Chart view• Resource Sheet view• Resource Graph view• Team Planner view
![Page 71: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/71.jpg)
71
Overallocated Resources Report
• This report lists only the resources that have been assigned work in excess of their availability, as reflected in their resource calendars
• Click Project tab, click Reports in Reports group. • On the Reports Dialog, click Assignments and
Overallocated
![Page 72: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/72.jpg)
72
Resource Availability Report
• Use this report to view a diagram that shows the work and remaining availability for your project's resources
• A red flag is displayed next to each resource that is overallocated.
• Click Project tab, click Visual Reports in Reports group. • On the Visual Reports dialog, click Resource Usage and
choose Resource Availability Report
![Page 73: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/73.jpg)
73
Gantt Chart view• On any task related view, you can see
only few icons in Indicators column• You can right click the task and choose to
• Fix in Task Inspector• Reschedule to Available date• Ignore Problems for This Task
![Page 74: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/74.jpg)
74
Resource Sheet view• Click View tab, in Resource Views
group, click Resource Sheet• The indicator field for overallocated
resources includes the Resource leveling indicator , which indicates that the resource be leveled
![Page 75: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/75.jpg)
75
Resource Graph view• Click View tab, in Resource Views
group, click Other Views dropdown and click Resource Graph
![Page 76: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/76.jpg)
76
Team Planner view• Click View tab, in Resource Views
group, click Team Planner
![Page 77: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/77.jpg)
77
Level resource workload• Resource leveling
• Start and finish are adjusted based on the resource constraints
• This technique can often cause the original critical path to change, usually to increase
• Resource smoothing• Adjust start and
finish such that the resource requirements doesn’t exceed predefined resource limits
• This technique the critical path is not changed and project finish date is not delayed.
![Page 78: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/78.jpg)
78
You can level workload• Options to level workloads
• Add/Remove/Replace resources• Split long tasks into many shorter ones• Customize resource calendar• Delay task start date/assignment start date
![Page 79: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/79.jpg)
79
Project can level workload
• Click Resource tab, in Level group, click Leveling Options.
• These options will affect only work resources.
• The Leveling calculations trigger a automatic leveling or manual leveling
![Page 80: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/80.jpg)
80
Resource Leveling dialog• Leveling range for …
• Select Level entire project to level workloads across the project
• Select Level From: … To … to level workloads within the specified period
• Leveling order• Select ID Only to level tasks based on their ID
numbers• Select Standard to level tasks based on their slack• Select Priority, Standard to level task priority and
slack
![Page 81: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/81.jpg)
81
Resource Leveling dialog• Resolving overallocations
• Select Level only within available slack to solve as many overallocations as possible but still meeting the target date
• Select Leveling can adjust individual assignments on a task to schedule assignments individually instead of a group
• Select Leveling can create splits in remaining work to split task bars but tasks become fragmented
![Page 82: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/82.jpg)
82
Resource Leveling dialog
• Options to start leveling• Level All : If Leveling calculations is set to Manual,
this button triggers a one-time leveling of workloads• Level Selection : Resolves resource conflicts of the
selected tasks by delaying/splitting them based on Leveling options
• Level Resource: Resolves resource conflicts of the selected resource by delaying/splitting them based on the Leveling options
![Page 83: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/83.jpg)
![Page 84: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/84.jpg)
Set Baseline• First baseline• Revise baseline• Backup baselines• Compare multiple baselines
![Page 85: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/85.jpg)
85
Baseline• The baseline plan is a snapshot of your
schedule at the time that you save the baseline
• This includes information about tasks, resources, and assignments.
![Page 86: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/86.jpg)
86
Entire Project Baseline• To see baseline data
• Click View tab, click Tables dropdown and then click Tables, More Tables.
• Click Baseline table in More tables and click Apply.
• To set the baseline• It is recommend all tasks are auto scheduled• Click Project tab, in Schedule group, click
Set Baseline dropdown and then click Set Baseline …
• You have set 11 baselines in Project 2010
![Page 87: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/87.jpg)
87
Copy baseline or start/finish
• Click Project tab, in Schedule group, click Set Baseline dropdown and then click Set Baseline …
• In Set Baseline dialog, select Set Interim Plan and choose the source and target in Copy: and Into: dropdown
![Page 88: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/88.jpg)
88
Up-to-date schedule• Project 2010 maintains current plan as
well as the baseline set• Click View tab, in Data group, click
Tables dropdown and then click Entry
![Page 89: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/89.jpg)
89
Before you revise the estimates …
• Copy the current Start and Finish to Start1 and Finish1 fields by using the Set Baseline feature
• In Entry table, revise the estimate - insert the new tasks, inactivate tasks, change dependencies, etc
• Now compare the current Start/Finish with Start1/Finish1
![Page 90: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/90.jpg)
90
Revise the baseline• Select the impacted tasks to be updated in
baseline• Click Project tab, click Set Baseline dropdown
and then click Set Baseline …• Select the option For: Selected Tasks• Under Roll up baselines
• Select To all summary tasks to update baseline information on all higher level summary tasks of the normal task selected
• Select From subtasks into selected summary task(s) to update only the summary tasks that you have selected
![Page 91: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/91.jpg)
91
Compare multiple baselines
• If you want to keep record of revisions in baseline, you may want to use Set Baseline feature to backup baselines
• To view baselines graphically, click View tab, in Task Views group, click Other Views dropdown and click More Views.
• In More Views dialog, click Multiple Baselines Gantt and click Apply.
![Page 92: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/92.jpg)
92
Baseline Work Report• Use this report to view a bar graph with baseline
work, planned work, and actual work for your project illustrated across tasks.
• Click Project tab, click Visual Reports in Reports group.
• On the Visual Reports dialog, click Assignment Usage and choose Baseline Work Report
![Page 93: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/93.jpg)
93
Baseline Report• Use this report to view a diagram of your project
broken down by quarter, then by task• Click Project tab, click Visual Reports in
Reports group. • On the Visual Reports dialog, click
Assignment Usage and choose Baseline Report
![Page 94: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/94.jpg)
![Page 95: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/95.jpg)
Break
![Page 96: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/96.jpg)
Update schedule• Tracking fields• Update tasks• Update assignments
![Page 97: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/97.jpg)
97
Keep your plan up-to-date
• Some of the many common mistakes by schedulers• Use the schedule itself to reflect promises and keep
it static• Set up schedule with few dependencies and more
constraints• They just enter actual progress without revising the
forecast• There are two strategies for updating your
schedule:• Updating tasks• Updating assignments
![Page 98: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/98.jpg)
Updating Tasks• Tasks that ran as scheduled
• On the Task ribbon, click or enter 100% in % complete• Tasks that run as scheduled
• On the Task ribbon, click• Tasks that run behind
• Enter Actual duration, revise the remaining duration for the task• On the Task ribbon, , select Incomplete Parts to
Status Date• Tasks that will take longer or shorter
• On the Task ribbon, click• Revise the Remaining Duration for the task
• Tasks that started early or late• On the Task ribbon, click , update Actual Start
field
![Page 99: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/99.jpg)
99
Updating assignments• Click View tab, in Resource Views group, click
Resource Usage• Right click the assignment and click
Information. Track the actuals and remaining in Tracking tab
• Click Format tab, in Details group, click Actual Work. Now, the actual work will be displayed in timescale portion
![Page 100: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/100.jpg)
![Page 101: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/101.jpg)
Measure Progress• Project Status• Task Status• Critical Tasks
![Page 102: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/102.jpg)
Project Summary Report• This report includes high-level summary of
rolled-up dates, duration, work, costs, work and resource status, and notes.
• Click Project tab, in Reports group, click Reports.
• On the Reports Dialog, click Overview and Project Summary
![Page 103: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/103.jpg)
103
Task Status report• Use this report to view a diagram of the work
and percent of work complete for tasks• Click Project tab, click Visual Reports in
Reports group. • On the Visual Reports dialog, click
Assignment Summary and choose Task Status Report
![Page 104: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/104.jpg)
104
Resource Status Report• Use this report to view a diagram of the work
and cost values for each of your project's resources.
• Click Project tab, click Visual Reports in Reports group.
• On the Visual Reports dialog, click Assignment Summary and choose Resource Status Report
![Page 105: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/105.jpg)
105
Resource Remaining Work Report• Use this report to view a bar graph with remaining
work and actual work for each work resource.• Click Project tab, click Visual Reports in Reports group. • On the Visual Reports dialog, click Resource Summary
and choose Resource Remaining Work Report
![Page 106: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/106.jpg)
Variance Analysis• Schedule variance analysis is about comparing
target schedule dates with the forecast start and finish dates.
• Information is useful for the detection of deviations and for the implementation of corrective actions.
• You need to keep a close eye on following information:• Project finish date• Critical Path• Progress of critical tasks• Review schedule variances
![Page 107: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/107.jpg)
107
Critical Tasks Status Report
• Use this report to view a diagram showing the work and remaining work for both critical and non-critical tasks.
• Click Project tab, click Visual Reports in Reports group.
• On the Visual Reports dialog, click Task Summary and choose Critical Task Status Report
![Page 108: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/108.jpg)
108
Slipping tasks• Click View tab, in Task Views group,
click Gantt Chart dropdown and then click Tracking Gantt
• In Data group, click Tables dropdown and click Variance. This compares the baseline and current plan.
• Click Format tab, in Bar Styles group, click Slippage dropdown and then click Baseline
![Page 109: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/109.jpg)
Current activities report• Click Project tab, in Reports group, click
Reports.• In Reports dialog, click Current and
select Apply• Unstarted Tasks report: Tasks in the
project that have not had any actual progress reported
• Tasks Starting Soon report: Similar to unstarted tasks but a date filter is applied
• Tasks In Progress report: This report quickly shows the amount of work that has started
![Page 110: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/110.jpg)
Current activities report• Completed Tasks report: This report is
significant for both historical reference and as a record of the team’s accomplishment.
• Should Have Started Tasks report: Most effective when used regularly, alerts you to all tasks whose scheduled start dates have passed the given date
• Slipping Tasks report: The emphasis of this report is a list of tasks that have started, but that will finish after their baseline finish date
![Page 111: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/111.jpg)
Review critical path• By viewing the critical path, you can
easily see whether you’re still scheduled to hit your target finish date.
• Click View tab, in Data group, click Group by: dropdown and then click Critical
![Page 112: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/112.jpg)
Compress Schedule• Schedule compression shortens the
project schedule without changing the project scope
• Schedule compression techniques include:• Crashing
You determine how to obtain the greatest amount of schedule compression with least incremental cost.
Crashing may result in increased risk and/or cost.• Fast tracking
Activities that normally would be performed in sequence are performed in parallel.
Fast tracking may result in rework and increased risk.
![Page 113: Microsoft Project 2010 Essentials 24 th August 2013, MPUG Chennai](https://reader035.vdocuments.mx/reader035/viewer/2022062501/568163d3550346895dd51e0d/html5/thumbnails/113.jpg)