michael j. griffin, p.e., m.asce august 27, 2008 · 2012-05-09 · • nonstructural damage ... •...
TRANSCRIPT
CCS Group, Inc.
Earthquake Risk to Nonstructural Components & Systems –
what you should know about the Design/Building
Code Processby:
Michael J. Griffin, P.E., M.ASCEAugust 27, 2008
CCS Group, Inc.
Page 2CCS Group, Inc.
Outline
• Earthquake Hazards
• Structural vs Nonstructural Components
• Historical Performance of Nonstructural Components
• Issues Affecting Nonstructural Earthquake Performance
• Importance of Mitigation
Page 4CCS Group, Inc.
Clarendon-Lindon Seismic Zone
EasternTennesse
Seismic Zone
New Madrid Seismic Zone
Anna, Ohio Seismic Zone
Wabash Valley Seismic Zone
St. Lawrence Seismic Zone
Giles County Seismic Zone
Charleston Seismic Zone
Ottawa Seismic Zone
Charlevoix Seismic Zone
Central Virginia Seismic Zone
NY-NJ-PA Seismic Zone
New England Seismic Zone
EARTHQUAKES OF THE CENTRAL AND EASTERN UNITED STATES1627 - 1991
Catalog of the National Center for Earthquake Engineering Research
Page 9CCS Group, Inc.
Structural vs. Nonstructural Components
Structural Components –• Building structure (beams, columns, floors, foundations)• Designed, including seismic, by a Structural Engineer
Nonstructural Components –• Architectural, mechanical, electrical, plumbing, fire
protection, contents, furnishings, etc.; everything that is not part of the building structure
• Designed by respective Discipline Engineer
• Nonstructural components are typically NOT analyzed or designed seismically by a Structural Engineer
Page 10CCS Group, Inc.
Structural & Nonstructural Components
Structural Elements:• Roof
• Floors
• Beams
• Columns
• Foundation
• Braces
• Concrete or Masonry Walls
Non-Structural Elements (Support the Function of the Building):• Architectural Components
• Mechanical & Electrical Components
• Life-safety systems
• Building Contents- Furniture- Production Equipment- Everything else in the
building
Page 11CCS Group, Inc.
Architectural Components
• Building cladding systems (windows, exterior wall envelope, finishes, etc.)
• Chimney’s, stacks, parapets, etc.
• Penthouses
• Interior partition walls, ceiling systems, lights, & finishes
• Raised access floors
• Storage racks
• Elevator Systems
Page 12CCS Group, Inc.
Mechanical, Electrical, & Piping
• Mechanical Systems –(HVAC equipment, air handling units, cooling towers, water heaters, boilers, pumps, chillers, compressors, etc.)
• Electrical Power Systems-(transformers, panelboards, MCC’s, control panels, conduit & cable tray)
• Piping and plumbing
Page 13CCS Group, Inc.
Life-Safety Equipment
• Fire Protection Systems –Piping, pumps, tanks, valves, etc.
• Safety Systems -Alarm, smoke detection, emergency lighting
• Emergency Power Systems -Engine-generators, start batteries, fuel oil systems, fuel oil storage tanks, control equipment, disconnect switches, etc.
• Security/communication Systems -
Page 14CCS Group, Inc.
Building Contents & Furnishings
• Office Contents –Desks, files, cabinets, book cases, etc.
• Critical Records –File cabinets, high density files, etc.
• Computer Systems –Servers, desk-top CPUs,file storage, UPS systems,etc.
• Production Systems –Manufacturing equipment, systems, etc.
• Production Inventories -Racking systems, parts storage, etc.
Page 15CCS Group, Inc.
Summary
HANGER WIRESFOR CEILING
AIRDIFFUSER
LIGHT FIXTURE
STUDS
AIR CONDITIONING DUCT
FURNISHINGSAND EQUIPMENT
BEAMFIRE SPRINKLERSYSTEM
ELECTRICALCONDUIT FORWIRING
SUSPENDEDCEILINGACOUSTICALTILE EXTERIOR
CURTAIN WALL,WINDOWS,CLADDING
STEEL ORCONCRETECOLUMNS
STEEL COLUMN SHOWN ENCASED IN FIREPROOFING
CONCRETE SLAB ON METAL DECK OR CONCRETE SLAB
MASONRY ORCONCRETESTRUCTURALWALL
NON-LOAD BEARING PARTITION
Page 17CCS Group, Inc.
Historical Performance of Nonstructural Components• Damage to Non-Structural Systems and Components
Typically:• Majority of earthquake financial losses• Losses typically exceed 50%
of the total value of a facility
• Nonstructural Damage Impacts:
• Life-safety• Property damage or loss• Recovery & restoration time• Loss of function• Business interruption
Page 18CCS Group, Inc.
Nonstructural Earthquake Losses16
.78
134.
25
3.3
154.
33
12.0
3
74.1
5
1.75
86.1
8
8.62
71.6
166.
40
0
20
40
60
80
100
120
140
160
180
Bui
ldin
gs
Equ
ipm
ent
Inve
ntor
y
Tota
l Dire
ctE
xpos
ure
and
Loss
Cle
anup
&R
ecov
ery
Bus
ines
sIn
terru
ptio
n
Tota
lE
xpec
ted
Loss
Cos
t (M
illio
ns $
)
Direct Property Financial Exposure
Expected Losses
Expected Earthquake Losses For MidWest Company Product Manufacturing Facility
Page 28CCS Group, Inc.
Nonstructural Component Performance Issues
• Building Code Design Philosophy
• Nonstructural Component Seismic Design
• Construction Process
• Quality Control & Enforcement
Page 29CCS Group, Inc.
Building Code Design Philosophy
Joe’s Bldg.
Loss0% 100%
ContinuedOperations
ImmediateOccupancy
Life Safety
CollapsePrevention
Building Code Design Level
Page 30CCS Group, Inc.
Building Code Design Philosophy
• Predominantly Life-safety Performance• Cladding and wall systems• MEP equipment & systems
carrying flammable, combustible or highly toxic contents
• HVAC ductwork transporting hazardous materials
• Emergency or standby power systems• Life-safety Systems
• Not intended to protect against property damage
• Minimum set of design requirements
Page 31CCS Group, Inc.
Nonstructural Component Seismic Design
• Structural/Seismic Design Requirements:
• International Building Code & ASCE 7-05 Chapter 13
• MEP Design Requirements:• International Mechanical Code
• International Electrical Code
• International Plumbing Code
• International Fire Code
⎥⎦⎤
⎢⎣⎡ +
⎥⎦⎤
⎢⎣⎡
=hz
IR
WSaF
p
p
pDSpp 214.0
yAxAp δδD −=
Page 33CCS Group, Inc.
Nonstructural Component Seismic Design
Structural Engineer’s solution to nonstructural component seismic design:
Page 34CCS Group, Inc.
Nonstructural Component Seismic Design
• Arch, MEP Performance Specifications/Typical Details for Contractor Implementation
• Architect
• Electrical engineer
• Mechanical engineer
• IT/Communications engineer
• Fire protection engineer
Page 35CCS Group, Inc.
Construction Process
SubcontractorsSteel Erector
Concrete WorkMechanicalElectrical
Fire ProtectionIT Systems
Etc.
Seismic Design?(Must Implement thru Performance Specs)
Constructs the Seismic Design (on design drawings)
Building Structure
Nonstructural Components
GENERAL CONTRACTOR
Page 36CCS Group, Inc.
Construction Process
• Contractor designed
• Construction sequencing
• Field routed/installedcomponents:
• Conduit
• Piping
• Cable Tray
• Ducting
Page 37CCS Group, Inc.
Quality Control & Enforcement
Why is Proper Construction Important? Assures:• Expected earthquake design performance objectives are met• Reduction in risk or damage to the component itself• Reduction in risk or damage to
adjacent or closely located items –falling, overturning, swinging and impacting, leaking, etc.
• Reduction in life-safety risk to building occupants
• For critical facilities the needed operability assurances necessary for Immediate Occupancy (e.g., hospitals, fire stations, police stations, other critical facilities, etc.)
Improper construction more prevalent than you think!
Page 43CCS Group, Inc.
Summary Recommendations for Improving Nonstructural Component Seismic Performance• Understand Building Code design philosophy is Life-
Safety• Question Design Professionals
regarding proper seismic design for nonstructural components
• Enforce project seismic design requirements during construction
• Inspect & verify compliance after construction prior to system turn-over
• Consider an annual reviewMissing anchor bolt
Page 45CCS Group, Inc.
Mitigation Options
• Do nothing – ignore the risk
• Accept the risk
• Risk transfer through appropriate levels of earthquake insurance
• Modify emergency response & business recovery plans
• Adjust business operations
• Relocate critical functions to lower risk buildings
• Locate non-critical functions to higher risk buildings
• Sell the facility & move
• Perform facility strengthening
• Perform nonstructural component strengthening and anchorage improvements
• Combination of the above
Page 46CCS Group, Inc.
Importance of Mitigation
• Mitigation Benefits
Reduced:• Property damage
• Repair & restoration costs
• Business interruption
• Reduced CAT insurance premiums
• Loss of market share
• Supply chain impacts
Page 47CCS Group, Inc.
Mitigation First Steps
• Identify critical business operations or functions
• What’s important?
• Assess back-up, recovery, & redundancy capabilities
• Back-up procedures
• Emergency response & recovery
• Off-site storage integrity, is it earthquake safe?
• Quantify facility earthquake risk• How earthquake safe are your facilities?
Page 48CCS Group, Inc.
Facility Risk Assessment
• Existing facility risk must be known before any action can be taken• Initial Facility Risk Assessment:
• Desk-top survey $• Rapid visual survey of the facility $$• Comprehensive facility risk assessment of $$$
building and nonstructural components
• Rank & Prioritize the risks• Develop a Mitigation Plan from the assessment findings and
recommendations• Capitalize and begin to implement the Mitigation Plan• Use Risk Assessment results to procure appropriate levels of
earthquake insurance
Remember – reducing earthquake risk cannot be achieved overnight. Earthquake Mitigation is a long term process.
Page 49CCS Group, Inc.
Benefits of Mitigation
Earthquake Risk Exposure Before and After Strengthening vs. Strengthening Cost for Midwest Facility
16.7
8
134.
25
3.30
154.
33
12.0
3
74.1
5
1.75
87.9
3
8.90
71.6
0
168.
43
2.20
11.8
1
0.27
14.2
8
1.50 6.
00
21.7
8
4.21
0.8
0.05 5.
06
5.06
0
20
40
60
80
100
120
140
160
180
Build
ings
Equi
pmen
t
Inve
ntor
y
Tota
l Dire
ctEx
posu
re a
ndLo
ss
Cle
anup
&R
ecov
ery
Busi
ness
Inte
rrup
tion
Tota
l Exp
ecte
dLo
ss
Cos
t (M
illio
ns $
)
Direct Property Financial ExposurePrior to StrengtheningAfter StrengtheningStrengthening Costs
Benefits:-Protect Employees, Life- Safety-Reduced Direct Losses-Reduction in Clean-up & Recovery-Reduction in Business Interruption
Page 50CCS Group, Inc.
Benefits of Mitigation
20.9
1.2 0.5
5.0 5.5
36.9
2.0 2.2
119.1
97.0 97.4
50.0
39.2
10.3
0.1
10.8
35.1
20.1
9.710.3
0
20
40
60
80
100
120
140
Buildings Equipment Inventory Total DirectExposure and
Loss
Cleanup &Recovery
Demand Surge BusinessInterruption
Total ExpectedLoss
Cos
t (M
illio
ns$)
Direct Property Financial ExposureExpected Losses Prior to RetrofitExpected Losses Following Retrofit
Page 51CCS Group, Inc.
Nonstructural Mitigation
• Nonstructural strengthening results in highest benefit-to-cost ratios
• Business impacts avoided:• Direct component damage &
replacement• Clean-up & recovery• Business interruption
• Strengthening is straight forward:• Predominantly anchorage
improvements• Maintenance staff implementation
Page 52CCS Group, Inc.
Mitigation Implementation
• Develop Long-term Strategy:• New construction• Planned facility outages• Renovations and
remodels• New equipment
installations• Aging equipment replacement• During equipment maintenance activities
Earthquake mitigation does not happen overnight
Mitigation Opportunities