mice rfcc module update allan demello lawrence berkeley national lab mice cm26 at riverside...

34
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Lab MICE CM26 at Riverside California March 26, 2010

Post on 21-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

MICE RFCC Module Update

Allan DeMelloLawrence Berkeley National Lab

MICE CM26 at Riverside California

March 26, 2010

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 2Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

MICE RFCC Module Update Overview

• RF Cavities

• RF Cavity Frequency Tuners

• Cavity RF Coupler

• RFCC Schedule

MICE RFCC Module

RF Cavity Update

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 4Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Progress Summary

• Fabrication of first 5 cavities by Applied Fusion finished in December 2009

• In February 2010 the contract was awarded to Applied Fusion for fabrication of the second 5 cavities

• Physical measurement process has been started on the first 5 cavities

• Cavity RF frequency measurements have begun

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 5Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Fabricator - Applied Fusion, Inc.

• Contract for the second 5 cavities was awarded to Applied Fusion in February

• Applied Fusion fabricated the complete RF cavity (minus spinning)

Electron beam welding machine

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 6Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

•The second batch of spun cavity shells were delivered to Applied Fusion in February

•They have started fabrication of the second group of 5 cavities

RF Cavity Shells

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 7Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Beryllium Windows

•Cavity Be windows are being fabricated by Brush Wellman Inc.

•LBNL has received three finished windows

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 8Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Be Window

•Cavity Be window alignment to nose ring looks good

•Some machining of the nose ring may be necessary to flatten mounting surface

• Be window mounted to cavity with clamping ring

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 9Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Physical Inspection

•Cavity being lifted out

of shipping crate

•Cavity mounted in fixture being lifted onto CMM

•Cavity being inspected

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 10

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Inside Profile Measurement

•Special probe to measure the inside profile of the cavity

•Cavity interior profile being measured with special probe

•The profile will be used to verify cavity RF models

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 11

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Frequency Measurement

•Cavities waiting for frequency measurement

•Dr. Li measuring cavity frequency

•The Be windows are installed to give an accurate measure of the frequency

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 12

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Progress Summary

• Fabrication of first 5 cavities by Applied Fusion finished in December 2009

• In February 2010 the contract was awarded to Applied Fusion for fabrication of the second 5 cavities

• Cavity physical measurement process started

• Cavity RF frequency measurements have begun

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 13

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Future Work

•The inside surface of each cavity needs to be electro-polished (done at LBNL)

•Physical and frequency measurements on the remaining 5 cavities when they become available

•Cavities must be “tuned” to each other for best center frequency (10 cavities) by plastic deformation if necessary (will be done at LBNL)

MICE RFCC Module

RF Cavity Frequency Tuner Update

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 15

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Frequency Tuner Progress Summary

• Tuner design is complete

• ¼ scale model has been fabricated to test flexure concept

• One full size tuner arm (for testing the system) has been fabricated

• Aluminum test cylinder (1/6 of cavity) has been fabricated

• Actuator mechanical components have been fabricated

• Actuator bellows have been delivered to LBNL

• Assembly of an actuator has begun at LBNL

• Control system components have been delivered to LBNL

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 16

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Frequency Tuners

• 24 Dynamic Cavity Frequency Tuners per Module• Tuner Actuator

•Tuners operate in a bi-directional “push - pull” mode (±2mm)

•Tuning automatically achieved through a frequency feedback loop

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 17

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Frequency Tuner Components

• Dual – action actuator

• Flexure tuner arm

• Actuator is screwed

intothe tuner

arm• Fixed

connection

• Forces are transmitted to the stiffener ring by means of “push-pull” loads applied to the tuner lever arms by the dual action actuator assembly

•Tuner/actuators are thermally independent of the vacuum vessel

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 18

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

Actuator Design

•Actuator design incorporates a sealed enclosure between vacuum and air.

• Actuator is mounted to the tuner arm only

• Bellows allows angular movement for actuator

• Piston plates are joined at the perimeter

• Piston plates incorporate hard stops

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 19

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

MICE RF Cavity – Mechanical Design and Analysis

• Actuator mechanical components have been fabricated and delivered to LBNL

Prototype Actuator Components

Center plate

Lower piston

Upper piston

Lower support

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 20

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

MICE RF Cavity – Mechanical Design and Analysis

• Actuator design incorporates two bellows attached to the pistons and the center plate

Prototype Actuator Components

Upper bellow

Lower bellow

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 21

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

Tuner System Analysis

• The Von Mises stress at the flexure is 29.7 kpsi

• The input load by the air actuator is 800 lbs

• The tuner arm displacement is 0.214” (~0.43” bi-directional) [movement exaggerated]

• The cavity displacement is 1.05mm per side

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 22

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

Tuner Flexure and Test Ring

• Full size (3” thick) prototype tuner flexure with test ring

• Threaded actuator mounting hole

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 23

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

Emerson ER3000 electronic pressure controller

•± 0.1% accuracy (over 110 psi range)

•110 psi normal operating range (120 Max.)

•Remote computer controlled

•16 required for two RFCC modules

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 24

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Tuner System Schematic

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 25

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Tuner System Components

Computer Interface

Controlled Leak Valve

Regulator

5 Micron Filter

Electronic Pressure Controller

Power Supply

Pressure Sensor

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 26

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Frequency Tuner Progress Summary

• Tuner design is complete

• ¼ scale model has been fabricated to test flexure concept

• One full size tuner arm (for testing the system) has been fabricated

• Aluminum test cylinder (1/6 of cavity) has been fabricated

• Actuator mechanical components have been fabricated

• Actuator bellows have been delivered to LBNL

• Assembly of an actuator has begun at LBNL

• Control system components have been delivered to LBNL

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 27

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Frequency Tuner Future Work

• Complete the assembly of the prototype actuator

• Assemble the complete actuation system• Test the single actuator/tuner and cylinder system

• Work on the interfacing to the RAL computers

• Order parts for 6 actuators (incorporating any refinements from the prototype)

• Fabricate 5 more tuner flexures

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 28

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

RF Cavity Frequency Tuner Future Work

• Build a cavity suspension frame

• Test of the RF tuning system with 6 tuners and actuators on a cavity

• Actuators will be manifolded together

• Frequency measurements will be taken to verify the frequency tuning range

MICE RFCC Module

Cavity RF CouplerDesign Update

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 30

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

Cavity RF Coupler

Section view of cavity RF coupler

•Based on successful SNS design with a Toshiba window

•Detailed fabrication drawings of the major components are complete

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 31

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

Cavity RF Coupler

•Assembly drawing of cavity RF coupler•Prototype of outer coax assembly will be made

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 32

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

• Detail drawings of major components are complete

• Sources for fabrication materials (e.g. 4” outer coax tube) have been identified

• Assembly method has been determined

Cavity RF Coupler Design Summary

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 33

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

Cavity RF Coupler Future Work

•16 Toshiba windows (plus spares) need to be ordered soon because of long lead times

• Myat RF couplers need to be purchased• Prototype of the outer coax will be fabricated to verify assembly method

• Vendor selection process will be started

MICE RFCC Module Update – MICE CM26 at Riverside California

Page 34

Allan DeMello- Lawrence Berkeley National Lab – March 26, 2010

Schedule Summary