method statement and risk assessment for scaffold erection

Upload: barry-hart

Post on 06-Feb-2018

293 views

Category:

Documents


7 download

TRANSCRIPT

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    1/24

    Method Statement &Risk Assessment

    For the Erection & Installation ofA Pedestrian Access Gantry and

    Temporary Scaffold Ladder Access Platforms.

    At the Project of:

    No. 8 Wellington Place,St Johns Wood,

    London NW8.

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    2/24

    Contents

    1. Description of works.

    2. Method of working.

    3. Sequence of operations.

    4. Arrangements

    4.1 Permits to work.

    4.2 Emergency Arrangements

    4.3 Environmental control.

    4.4

    Equipment.

    4.5 First-aid arrangements.

    4.6 Housekeeping

    4.7 Manual Handling Operations

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    3/24

    1. Description of works.

    The operations considered within this method statement comprises of ourarrival to site, delivery and transportation of scaffolding components, i.e.traditional tube and fitting components and subsequent erection of anindependent tied scaffold access gantry and temporary working platforms tofacilitate the provision of a safe means of access onto site for futureconstruction operations at no. 8 Wellington Place, St John s Wood, LondonNW8.

    It is envisaged that this contract shall commence on or around the 20thAugust 2014 and shall have contract duration of approximately 2 days.

    Personnel:

    Managing Director: Mr Pat Hazlett 07850 586 860

    Contracts Manager: T.B.C.Health & Safety Advisor: Mr Barry Hart TechIOSH, MIIRSM, RMaPS

    (M) 07707 050 721Scaffolding Supervisor: Thomas Karablikovas (Advanced CISRS)First Aider: Thomas Karablikovas (AP)

    Our Site Normal Working Hours are as follows:

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    4/24

    2. Method of working.

    Operation

    2.1 Capital Construction Limited will obtain authorisation from the Clientand the adjacent hospital (The Wellington Hospital), to commencework on site and will confirm the working areas, welfare arrangements,first aid and emergency arrangements, storage & temporary laydownlocations and ensure that this information is communicated by way of

    the site safety induction and daily task briefings.

    Operatives will be required to provide details of training andCSCS/CISRS accreditation details at the induction together with asigned copy of the method statement/risk assessment register.

    2.2 Following the arrival of the scaffolding materials the delivery shall be

    offloaded initially using a vehicle mounted HIAB (in the interest ofavoiding unnecessary manual handling of materials and working atheight) and fully certified associated certified lifting accessoriestogether with a trained operator and competent personnel to an areaspecifically dedicated to the laydown of the scaffolding materials withinthe perimeter of the site.

    All deliveries shall be directed to report to the Site Manager or

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    5/24

    2.4 Once all necessary barrier protection and hazard warning signage has

    been erected/prominently displayed around any working areas, ourskilled and competent operatives shall confirm the sequencing of workand shall confirm that the area has been cleared of any pre-existingservices or other obstructions that may impinge upon the erection ofthe scaffold.

    2.5 Once satisfied that the areas have been made ready and that a suitable

    level foundation for the scaffold is available, our competent (CISRS 1 &2 Card carrying operatives shall agree the sequence of erection andensure that any necessary permissions have been obtained from thehospital for the purpose of providing a temporary safe means of accessinto the existing ground floor area of the main house.

    2.6 The initial phase of these operations will be to provide a scaffold

    platform and ladder access into the existing ground floor of No. 8Wellington Place. Any such access will be subject to prior approvalfrom the Hospital as the platform position will encroach onto theirproperty by approximately 1.2 metres (see photo 1.0 below).

    Photo 1.0 Photograph of Access for Temporary Scaffold Platformand Access Ladder

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    6/24

    2.9 The 2nd phase of the operation will be to manually transport thenecessary components using a Ginny wheel and rope, where necessary

    to the ground floor for the purpose of erecting an internal tower andcantilevered access platform and ladder access into the basement.

    2.10 The scaffold design shall be checked for the purpose of establishingthe correct bay widths and setting out details for the standards, beforesiting the sole boards, upon which the standards shall be founded,using the footplates and locating shank to accurately position the

    standard central to the sole board.

    2.11 The standards shall then be set out and jointed using right angled loadbearing fittings to join the ledgers and transoms, checking the tubesfor alignment, plumb and level so as to ensure adherence to the designprovided or recognised standard configuration in accordance withBSEN12811 and TG20:13 i.e. maximum and minimum lift heights, bay

    widths, and transom centres Etc.

    2.12 The scaffolders shall ensure that the harness and lanyard issued toeach individual is worn at all times and scaffolders shall be madeaware that they must ensure that they are clipped on to the nearestavailable suitable anchor point when working at a height likely to causeinjury in the event of a fall, in accordance with SG04.

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    7/24

    2.16 Tubes ends shall be capped to reduce the risk of impalement; cuts and

    abrasions, standards projecting through the platform must eitherextend a minimum of 950mm above the platform or be cut off flush tothe working platform level, so as to reduce the risks associated withtrips and falls.

    2.17 Gaps within the platform boards shall be closed using either anadditional ledger tube or ScaffGap proprietary void closer, (see

    below) in the interest of reducing the risk of any materials, fittings etcfalling through any gaps. Notching of platform boards shall beprohibited.

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    8/24

    3. Sequence of operations.

    3.1 Delivery of materials and equipment

    Arrangements will be made to ensure that adequate time allowance isavailable for the movement and set down of materials. All deliveriesmust be pre-booked at least 48hrs in advance.

    In addition, Capital Construction Limited shall ensure that any planned

    deliveries are notified to the Site Manager as soon as reasonablypracticable, so as to facilitate good communication between all partiesi.e. Hospital Staff/Personnel and neighbouring properties, therebyreducing the potential for impacting upon other residents, theneighbouring construction project and other traffic, in particular servicecontractors to the Hospital and Emergency Services.

    Materials will be brought to the work site by a suitable sign written,long wheel base, flat bed, commercial vehicle and will report to the SiteManager before being directed to the designated loading/unloadingareas.

    The attending delivery vehicle shall incorporate edge protection aroundthe bed of the trailer in the interest of reducing the risk of falls from

    h i ht d i l di / l di f ff ld t

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    9/24

    A restriction will be placed on the amount of materials placed in onearea at any one time on site to ensure that there is no overloading of

    the existing ground or rc slab and that trip hazards are reduced withaccess / egress routes remaining clear.

    In particular, the areas will be carefully monitored for any loose fittingsrolling stock or off-cuts, any such materials or debris will be clearedimmediately and securely stored within a stillage or Hessian sack forsubsequent disposal.

    All materials will be placed to as close to the work area as possible(given the space constraints), in the prevention of manual handlingtasks.

    3.2 Preparation.

    Others within the work area will be advised of the works to beundertaken in the area and of any risks present e.g. slippery surfaces,uneven ground conditions or unstable ground conditions etc. Whereexcavation works are in progress, signage will be displayed uponbarriers warning of dangers e.g. Danger Scaffolding in Progress, NoUnauthorised Admittance etc.

    O ti ill b i l d i k t lk t di thi th d

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    10/24

    3.4 Site Clearance

    Given the nature and scope of works outlined above, very little wastewill be generated, however all debris and excess materials will becollected and removed from the work area, by bagging any wastematerials, for subsequent collection, awaiting removal by a licensedwaste removal contractor.

    Should materials and/or debris become a hazard due to the volume,fire risk or due to trip and slip hazards of wet materials it will beremoved from the work area/site immediately.

    At all times Capital Construction Limited will take particular care toensure that trip hazards are reduced or removed and access / egressroutes remain clear.

    4. Arrangements

    4.1 Permits to work.

    Given the nature and scope of the work considered within this methodstatement, it is foreseeable that a hot works permit will be required

    h it b t t ff ld t b

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    11/24

    4.2 Emergency procedures.

    Emergency procedures will be arranged on site and will becommunicated to the persons undertaking the works. There will be amobile telephone on site at all times, as a minimum requirement toensure that emergency services can be contacted. Should anemergency occur on site, which may affect other occupants of thebuilding, or neighbouring premises they will be contacted and made

    aware at the first opportunity.

    In the event of a fall from height, which is subsequently arrested byway of the energy absorbing lanyards supplied to each operative, theattending personnel shall effect an immediate rescue of the individualusing a gotcha system or similar personnel retrieval system suppliedto the erection team.

    Special consideration must be afforded to any first aid provision, in sofar as the treatment extends to suspension trauma or treatment oftoxic shock i.e. Retrieval must be affected within 10-15 minutes andthe individual NOT placed into recovery position but positioned in amanner that allows the gradual recovery of the circulatory system i.e.seated position with the knees bent.

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    12/24

    4.4 Equipment.

    All materials are checked prior to loading; however the attendingoperatives shall again check all tube and fitting components before firstuse, following its delivery to site, so as to ensure that all materials arein good condition, oiled and free from rust/corrosion.

    Equipment and materials required include: -

    Galvanised Scaffold Tube + beams 48.3mm OD to BS1139Scaffold Boards 252 x 35mm to BS2482Double Couplers 6.1 KN SWLSwivel Couplers 6.1 KN SWLSleeve Couplers 3.6 KN SWLBand & Plate Couplers 6.25 KN SWLSingle Couplers 0.63 KN SWL

    All materials and equipment, when practicable will be taken to the workarea via mechanical means, as this will reduce the requirement forexcessive manual handling.

    Plant and tools shall be restricted to 110 Volt, centre tapped to Earthequipment and subjected to regular portable appliance testing (P.A.T.

    t ti ) 3 th i d ith HS (G) 107

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    13/24

    4.5 First-aid arrangements.

    First Aid requirements including the identities of the FirstAider/Appointed person will be arranged on site and the detailscommunicated to all operatives. A First-Aid box will also be provided onsite adequately stocked for risks highlighted by this Method Statement.

    The Scaffolding Supervisor shall also hold an appointed person first aidat work qualification and shall be provided with first aid equipment,

    suitable for the nature of the proposed operations in support of theprovision made by Capital Construction Limited.

    4.6 Housekeeping

    Due to the type of works undertaken waste material will be producedhowever all debris will be removed from the works area to a storage

    place of safety until such time as this material can be removed by alicensed Waste Carrier.

    At all times Capital Construction Limited will take particular care toensure that trip and slip hazards are reduced or removed and access /egress routes remain clear.

    4 7 M l H dli O ti

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    14/24

    4.8 Personal protective equipment.

    In accordance with the Personal Protective Equipment at WorkRegulations 2002. Capital Construction Limited will reduce the risks toemployees as far as is reasonably practical by the implementation ofcontrol measures within systems of work. Should control measures notbe available or they are deemed impractical, as a last resort, operativeswill be provided with the necessary protective equipment.

    The foreseeable safety equipment deemed necessary to control thehazards highlighted by this Method Statement include hard hats,suitable gloves, steel toe and mid-sole boots, hearing protection andmasks in some circumstances. PPE will also be donned as per therequirements of Capital Construction Limited e.g. hi-visibility clothing.

    It is not envisaged that excessive noise will be produced during this

    task however ear protection will be used should noise levels exceed84dB (A).

    It is a mandatory requirement of Capital Construction Limited for thefollowing items of PPE:

    Safety Helmet EN397Steel toe and mid-sole boots EN345

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    15/24

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    16/24

    4.12 Vibration.

    All operatives will be informed of the risks associated with exposure tohigh levels of vibration from plant and tools used on site. The SiteManager shall ensure that all necessary control measures are taken torestrict exposure times in accordance with The Control of Vibration atWork Regulations 2005.

    The Supervisor will be required to record the exposure times of alloperatives engaged in the use of vibrating tools and equipment andensure that operatives are not exposed to levels of vibration likely tocause injury or ill health.

    5.0 Non-standard operations.

    This method statement will be amended as necessary if the works fall outsidethe scope of this document or the sequence of work changes.

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    17/24

    6.1

    Method Statement/Risk Assessment Register

    Before any task is undertaken the Method Statement for that task MUST be read andunderstood.

    To enable Capital Construction Limited to comply with this, please ensure you print yourname, date and sign this register.

    Name Method StatementTitle

    Date Signature

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    18/24

    6.2 Risk AssessmentLegend

    P = Probability 1 = Remote 2 = Unlikely 3 = Possible 4 = Probable 5 = Likely

    S = Severity1 = Injury not requiring First-aid

    2 = First-aid only required 3 = Over 3 day injury 4 = Serious Injury 5 = Fatality

    R = Risk Rating (p x s) 1-3 = Negligible 4-6 = Low 7-12 = Medium 13-16 = High 17-25 = Very High

    RR = Residual Risk

    1-3 = Acceptable

    No further controlsnecessary.

    4-6 = Acceptable.

    Regular close monitoring andreview required.

    7-12 = UnacceptableFurther controls must beimplemented to reduce therisk.

    13-16 = UnacceptableReview the assessment

    process, activity and re-evaluate and apply additionalcontrols.

    17-25 = Activity or processshould be abandoned, no

    works to continue unless afull review of the work hasbeen undertaken.

    Probability x Severity = Risk rating E = Employees C = Contractors T = Third parties

    S

    EV

    E

    RI

    TY

    5 10 15 20 25

    4 8 12 16 20

    3 6 9 12 15

    2 4 6 8 10

    1 2 3 4 5

    PROBABILITY

    13 NEGLIGIBLE

    46 LOW

    7-12 MEDIUM

    13> HIGH

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    19/24

    Risk Rating Matrix

    Processes HazardPersons at Risk Risk

    Control Measures RequiredResidual

    RiskE C T P S R

    Erection ofWorking Platforms

    Working at Height 5 5 25

    Suitable and sufficient working platforms shall beconstructed from traditional tube and fittingScaffold, erected by trained and competentpersonnel (minimum Pt1/Pt 2 CISRS Card holders),inspected to ensure good condition. Any suchplatform shall incorporate suitable and sufficientedge protection by way of guard rail and ladderaccess system.

    Where necessary, i.e. when storing heavy materials

    upon any platform, consideration shall be affordedto the marking of permissible loading of theplatform and the incorporation of toe-boards toprevent any materials or equipment from fallingfrom the platform.

    In addition, ScaffGap proprietary platform gapclosers shall be incorporated into the design toeliminate the risk of materials falling through theplatform.

    3

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    20/24

    Erection of

    Working Platforms(Contd)

    Working at Height 5 5 25

    All working platforms shall be subject to a dailyScaff Tag inspection where required. In any caseany working platform shall be subject to a full

    inspection by a competent inspector at least every 7days, following substantial alteration or any otherevent likely to affect its stability.

    Consideration shall be afforded to the hierarchy ofcontrols in accordance with the Management ofhealth and Safety at Work Regulations 1999 (Asamended).

    All Scaffolding operatives shall be issued with a full

    body harness and lanyard in the interest of reducingthe risk of falling from height.

    All harnesses and lanyards shall be subjected toregular inspection and thorough examination;Weekly inspections shall be recorded within theregister retained by the scaffolders and thoroughexaminations undertaken at least every 6 months.

    3

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    21/24

    Unloading &

    TransportingMaterials

    Failure of liftingplant/equipment

    3 5 15

    Plant will undergo a statutory inspection once a yearby a fully competent inspector and on a weeklybasis the operator of any lifting equipment or

    accessories will enter into a log, details of theintegrity of the plant.

    All lifting operations will be supervised by abanksman and slinging undertaken by a competentslinger.

    Weights of loads will be gauged before thecommencement of operations and the SWL of thelifting equipment and plant checked.

    3

    Head Injury 2 4 8

    Toe boards will be placed where operatives arerequired to work from any elevated platform givingrise to a risk of falling materials or debris.

    Head Protection shall be worn in accordance withthe Personal Protective Equipment Regulations1992.

    2

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    22/24

    Dropped loads e.g.unstable/damaged

    stillages

    3 5 15

    Materials shall be checked upon delivery to ensurethat all tubes and fittings have been correctlydelivered and that containers, i.e. stillages are in

    good condition to allow for transportation using thepallet truck.

    Stillage bases and lifting points shall be checked fordamage and the proposed route of transit checkedfor any obstructions, slippery surfaces Etc.

    3

    Reversing vehicles 3 4 12

    Vehicles delivering to site shall be advised of therequirements of the site and be directed to thedesignated unloading area by a competent personacting as Traffic Marshal/Banksman.

    Banksmen will be competent to undertake the roleand will have suitable high visibility clothing. Largervehicles will also have reversing warnings fitted.Mobile phones and personal stereos will not bepermitted for use within construction areas on site.

    The adjacent pedestrian routes shall be used andprotection erected (HERRAS or similar suitablealternative barriers) to afford protection and

    demarcate vehicle/pedestrian segregation.

    2

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    23/24

    Vibration 4 3 12

    Plant will be suitably maintained with all dampersetc. present to reduce the risk from vibration.

    New plant will be purchased once consideration hasbeen given to the equipment with the least vibrationproduced to the operator.

    Operatives will only use equipment producingvibration for a limited period and will rotate the taskwith other operatives.

    Operatives will have access to facilities to ensurethat they are kept warm so reducing the risk of

    vibration related injuries.

    Operatives are familiar with the risk from vibrationand are aware that they are to stop work shouldsymptoms occur.

    1

    Third parties /Pedestrians

    3 4 12

    Barriers and signage will be placed to ensure thatoperatives / visitors and public have suitablesegregation to protect the pedestrians fromoperations that are being undertaken.

    Any scaffolding erected to common areas will beclearly demarcated and protection afforded toreduce the risk of injury to third parties i.e. HospitalStaff/Service Personnel.

    1

  • 7/21/2019 Method Statement and Risk Assessment for Scaffold Erection

    24/24

    Manual Handling 3 4 12

    Where a mechanical means is available to perform atask, operatives will not be expected to undertaketasks of manual handling. Where no alternative

    exists loads will be broken down to reduce the riskor team lifting used. All plant and equipment will beloaded/unloaded with the use of a HIAB or GinnyWheel and fall with materials being dropped as closeto the working areas as reasonably practicable.

    1

    Foot and handinjuries

    4 3 12

    During the works general hand and foot injuriesmay occur therefore steel toed boots will be worn byoperatives at all times and gloves will be wornduring periods when knocks, hand injuries orabrasion may occur. Should there be a new hazard

    on account of the use of gloves e.g. entanglementor the dexterity of the hand is needed gloves neednot be worn.

    2