meter management group 91010 - usaid sari/energy integration · – testing of meters for mri...
TRANSCRIPT
11/10/2010 1
METER MANAGEMENT GROUP Functions & Organization
by
Mr. Avinash Karanpuria
11/10/2010 2
Agencies
• Generation • Transmission• Distribution
11/10/2010 3
Organization Chart of Distribution Utility
MD
Material Management Distribution Metering (MMG) Vigilance Revenue
& Finance Planning Admin & HR
Chief EngineerCommercial
SE (M & P)
XEN (Distribution Circle)
Meter Testing Lab(AEN & JEN)
11/10/2010 4
Functions of MMG…..
• Selection of metering equipment.• Installation of metering system.• Calibration of metering equipment at site on regular
intervals as per the guidelines of regulator.• Meter Reading & Billing of consumers for Revenue
Recovery.• Testing of metering equipment in the Lab. • Energy & Loss Accounting.• DT Metering.
11/10/2010 5
Selection of metering equipment… • It depends upon the load/Voltage/Demand Level of the
consumer.– Single phase meters installed up to 5 KW load.– Three phase direct current meter installed between 5KW to18KW. – LTTV meters are installed for load above 18 KW & maximum
demand up to 50 KVA. – 11/0.110 KV HTTV meters are installed for maximum demand
between 50 KVA to 800 KVA.– 33/0.110 KV HTTV meters are installed for maximum demand
between 800 KVA to 5000 KVA.– 132/0.110 KV HTTV meters are installed for maximum demand
between 5000 KVA to 8000 KVA.– 220/0.110 KV HTTV meters are installed for maximum demand
above 8000 KVA.– ABT meters are installed on open access consumers.
11/10/2010 6
• Tariff is divided into three parts
• Consumers are billed on the basis of KWh consumed.• Meters for all consumers below 18 KW load will be billed on the
basis of KWh consumed.
• Fixed charges are levied on the basis of sanctioned connected load/ maximum demand.
• For connected load above 5 KW but maximum demand up to 50 KVA fixed charges are levied on the basis of connected load.
• Fixed charges are levied on the basis of maximum demand where maximum demand exceeds 50 KVA.
• It will be obligatory on the part of consumer to maintain the PF of 0.9. Incentive will be allowed if the PF is above 0.9 & penalization if PF falls below 0.9.
• This clause is applicable for connected load above 18 KW.
Selection of metering equipment…
Energy ChargesEnergy Charges
Fixed ChargesFixed Charges
Power Factor (PF)Power Factor (PF)
11/10/2010 7
Installation Of Metering System
Metering is done at• Generating Station• EHV Sub Station • HV Sub Station • Distribution Sub Station• Consumer’s Premises :-
– Single Phase meters.– Three Phase meters. – LTTV( LT Tri vector) meters– HTTV( HT Tri vector) meters– ABT( Availability Based Tariff) meters
LT-TV-MetersLT-TV-MetersHT-TV-MetersHT-TV-MetersSingle Phase MeterSingle Phase MeterThree Phase MeterThree Phase MeterABT MetersABT Meters
11/10/2010 8
Metering equipment calibration at site• It is to be done as per the guideline of the regulatory
Commission.• Regulator is an independent body constituted under the
provision of Indian Electricity Act 2003.• Regulatory body is at central & state level both.• Intra state affairs of Generation/ Transmission/ Distribution of
power are governed by Central Regulator.• Central commission also advises government for formulation
of National electricity policy and tariff policy.• Electricity affairs with in the state are governed by state
regulatory body.• As per the regulator, the metering equipments installed at
different location/level are to be calibrated on site at regular interval to check the performance of metering system.
• The calibration system ensures proper functioning of metering at all ends.
11/10/2010 9
Meter Reading & Billing of consumers for Revenue Recovery.
• In old days electromechanical meters were used for measurement of Energy.
• In above meters, meter reading was done manually having no authenticity of correct reading.
• To overcome the issue electromechanical meters were replaced by Static Digital Electronic meters.
• In case of Static meters data is stored in separate register for 00:00 hours of last day of calendar month to be used for billing purpose.
• This data will be available on display for next thirty days. • All the meters are Static digital type meters wherein data is stored on daily
basis.
11/10/2010 10
Different Features of Static Digital meters…Meter Reading & Billing of consumers for Revenue Recovery.
VoltageVoltage
CurrentCurrent
FrequencyFrequency
Power FactorPower Factor
Active, Apparent, Reactive EnergyActive, Apparent, Reactive Energy
Load & DemandLoad & Demand
Real date & timeReal date & time
11/10/2010 11
• Different type of data is stored in meter– Billing History– Half hourly data/ Time stamped data – Tamper event logging with date & time – Analysis of tamper events can reveal the malpractice.– Assessment of energy on account of malpractice– Loss of Energy on account of pilferage is accounted by means of
tamper data. – All the above data can be downloaded electronically & cannot be
edited.
Meter Reading & Billing of consumers for revenue recovery…
11/10/2010 12
• Meter are read by meter readers( ITI/ Technician) & MMG engineers. • Direct connected Single & Three phase meters are read manually by
meter readers or by HHU if required.• CT operated meters are read through HHU • HHU readings are electronically transferred to the billing agency.• High end consumers are remotely read through AMR.• Data is collected remotely on real time basis by means of communication
link like GSM/GPRS/PSTN. • AMR data is directly sent to billing agency ,which will generate the bills• Electronic data ensures zero defect in readings.• The issue of bills is faster leading to timely collection of revenue. • The consumer queries/complaints can be handled by the aid of retrieved
data from meter.
Meter Reading & Billing of consumers for revenue recovery…
Submission of data & MIS reports to utility
Meter(s) data and remark dumping at site office
Validation check of meter data
Preparation of follow up cases and quality checks for cross verification
Bill generation at premises
Start
Creation of consumer database
Meter reading at site (With remarks
Field visit to capture meter reading and remarks
Data dump at site office and preparation of export file
Preparation of MRI/HHU with attached printer
11/10/2010 13
Testing of metering equipment in the Lab.
– Mandatory sample meter testing for each lot as per IS standard
• 1 % Sample is collected from the lot supplied in the DISCOM store.
• Each sample is inspected for accuracy check on sample basis.• If the samples are up to the mark then lot is accepted otherwise
whole lot rejected. – Routine testing of 4% meters from each procured
lot.• After acceptance of mandatory tests, routine tests is carried out
on 4 % of meters supplied.• All the accepted meters are properly sealed for identification.
For single & three phase metersFor single & three phase meters
11/10/2010 14
Testing of metering equipment in the Lab.
• 100% testing of replaced/repaired meters by firm.– The procured materials is warranted for specified period. In case of
any failure during warranty period supplier has to replace/ repair the defective material.
– 100 % meters replaced by supplier in lieu of defective meters under warranty period are tested & sealed.
• Verification of tamper features & MRI communication as per purchase order.– The static meters have a inbuilt feature to record abnormal
conditions such as PT/CT missing etc with date & time stamping. – Meters under test are subjected to such abnormal conditions in the
lab by stimulating tamper conditions. – The conditions recorded by meter are verified through the data
stored in meters with the help of MRI– This data is verified for correctness of MRI communication, MRI
software, communication cord, port & BCS.
11/10/2010 15
• Testing of HT/LT-TV meters.– Routine testing of 100 % HT/LT-TV meters.– Testing of meters for MRI communication and tamper features.
• SEALING – Seals arrangements are available for sealing meter body, terminal
plate, communication port & meter box.
– Seals are provided by the testing laboratory on the meter body.• Rest of sealing arrangement is provided to the filed staff during
installation at meter site. – The seal confirms that the meter has not been tampered & is in the
same condition as delivered from the lot.• The intactness of seal can be verified on any later date.
Testing of metering equipment in the Lab…
11/10/2010 16
• Testing of CTS’ & PTS’– Testing of LTCT purchased by department/ consumer.– Testing of 11kv And 33kv CT/PT sets purchased by department/
consumer.– Testing of LTCT,11kv And 33kv CT/PT set on site (If required).
• Testing consumer complaint/disputed metering equipment.
– Accuracy check at various load.– Findings about meters being tampered.– Providing meter reading /history report to operations & maintenance
when ever required.– Testing of removed CTS’/PTS’ from site.
Testing of metering equipment in the Lab…
11/10/2010 17
• Testing of old & used meters for reusing.– Testing of single and three phase old and used meters removed from
site. – Testing of old and used HT/LT-TV meters removed from site.– Testing of LTCT and CT/PT sets removed from site.– Assessment of energy is computed if accuracy of the removed
metering equipment is found beyond permissible limits.
• Training of field staff– Theoretical & on job training is imparted to staff.– Practical session is also conducted for recording of readings, analysis
of tampers & other features.
Testing of metering equipment in the Lab…
11/10/2010 18
Energy & Loss Accounting..• Measurement of energy at every injection point like :-
GenerationGeneration
Inter grid transmissionInter grid transmission
Distribution level substationDistribution level substation
Distribution transformersDistribution transformers
Consumer metersConsumer meters
11/10/2010 19
Energy & Loss Accounting..
MDI/EM08/5th June 2009
DT-1
DT-2
Consumers
LT Network 1
LT Network 2
Underground Cables
Underground Cables
Jumble of Overhead Cables
Jumble of Overhead Cables
11/10/2010 20
Energy & Loss Accounting..
Benefits of Accounting– Reconciliation of Energy at different levels.– Identification of Losses at every voltage level– Commercial losses at Distribution voltage (DT) level. – Losses at Unit level to judge its performance.– Cash Flow for purchase of power can be forecasted.
11/10/2010 2121
Generation
Interconnected Transmission system (EHV)
Radial distribution system (HV)
Tail-end radial LT distribution
11 kV Feeders
Distribution Transformers (DTs)
Consumers
11/10/2010 22
Distribution Transformer Meters
• They link sub transmission system with the tail end of distribution system – they are “link meters”
• They constitute final stage of distribution system metering & give best benefits
• Their application covers 3 aspects• To monitor operating conditions of the DT • For load flow & energy audit studies• For revenue protection & DMS
11/10/2010 23
Benefits of DT meter….
• Energy Accounting.• Trend data of DT monitoring.• Unbalancing monitoring & its control.• Reactive compensation requirement management.• Supply Reliability.• Segregating up stream & downstream reliability.• Providing data for load flow studies.• Number & nature of faults in LT system.• Indentation of fault maintenance time.• Loss making areas can be identified by DT metering.
11/10/2010 24
Activities of Meter Management Group….
• Daily field Activities -– Testing is performed at Site by Meter Management Group. The Meter at
Site is tested at Consumer load / running load. – Checking & testing of metering equipments for releasing new
connections/Load extension/Change of defective metering equipment.– JIR (Joint Inspection Report) is prepared by field officer.– JIR data is send to billing agency– Accordingly the master data is updated – Load Survey
• To measure Supply Reliability on the feeder.– Assessment on account of tamper events.– The tamper cases are investigated with the help of the Vigilance dept. – Testing of CT & PT.– Updation of data of consumers.
5 kV & 0.5 KV Megger5 kV & 0.5 KV MeggerDG SetDG Set
Red Phase
MRIMRI
11/10/2010 25
Activities of Meter Management group….
• Support activities– Preparation of technical specifications for Procurement of Metering
equipment.– Inspection and Mandatory testing of purchased metering equipment
at manufacturer premises.
• THANKS