mercedes-benz u.s. international, inc.management (adem) during which each plant was issued a...
TRANSCRIPT
Mercedes-Benz U.S. International, Inc.
Plantwide Applicability Limit Permit Renewal Application
Vance, Alabama – Tuscaloosa County
February 2018
Submitted by Mercedes-Benz U.S. International, Inc.
Vance, Alabama – Facility No. 413-0034
TABLE OF CONTENTS
i MBUSI PAL Renewal Application February 2018
1. INTRODUCTION................................................................................................................ 1-1
1.1 FACILITY DESCRIPTION ......................................................................................... 1-1
1.2 PAL RENEWAL APPLICATION REQUIREMENTS ............................................... 1-2
2. EMISSIONS UNITS ............................................................................................................ 2-1
2.1 VOC PTE ...................................................................................................................... 2-1
2.2 DESIGNATION OF EMISSIONS UNITS .................................................................. 2-2
2.3 LIST OF APPLICABLE FEDERAL AND STATE REGULATORY
REQUIREMENTS........................................................................................................ 2-3
2.4 LIST OF APPLICABLE EMISSIONS LIMITATIONS ............................................ 2-10
2.5 LIST OF APPLICABLE WORK PRACTICES PLANS ........................................... 2-13
3. BASELINE ACTUAL VOC EMISSIONS CALCULATION ......................................... 3-1
4. PROPOSED PAL LEVEL .................................................................................................. 4-1
5. MONITORING, RECORDKEEPING AND NOTIFICATION REQUIREMENTS ... 5-1
LIST OF TABLES
ii MBUSI PAL Renewal Application February 2018
Table 2-1 MBUSI Facility-wide VOC PTE................................................................................. 2-2
Table 2-2 PTE and Designation of Emissions Units at MBUSI .................................................. 2-3
Table 2-3 Federal Requirements Applicable to MBUSI.............................................................. 2-4
Table 2-4 State Requirements Applicable to MBUSI.................................................................. 2-6
Table 4-1 Comparison of MBUSI VOC PTE and Permit Limits ................................................ 4-2
LIST OF APPENDICES
iii MBUSI PAL Renewal Application February 2018
Appendix A - VOC PTE Calculations
Appendix B - Baseline Actual VOC Emissions
Mercedes-Benz U.S. International, Inc.
Plantwide Applicability Limit Renewal Application
1-1 MBUSI PAL Renewal Application February 2018
1. INTRODUCTION
Mercedes-Benz U.S. International, Inc. (MBUSI) manufactures motor vehicles in a state-of-the-
art motor vehicle assembly facility (Facility) located in Vance, Alabama in Tuscaloosa County.
MBUSI is requesting a renewal of its current Plantwide Applicability Limit (PAL) for volatile
organic compound (VOC) emissions for this Facility.
1.1 FACILITY DESCRIPTION
The Facility was once comprised of two main production plants – Plant 1 (built between 1995 and
1997) and Plant 2 (built between 2002 and 2004). Both plants were taken through Prevention of
Significant Deterioration (PSD) permitting with the Alabama Department of Environmental
Management (ADEM) during which each plant was issued a plantwide limit for VOC – 488.0 tons
per year (tpy) for Plant 1 and 640.0 tpy for Plant 2. On August 11, 2008, ADEM issued a PAL
permit for VOC. The PAL level of 859.55 tpy of VOC was established for both Plant 1 and Plant
2 combined. In 2009, MBUSI ceased operation of the Plant 1 paintshop. In October 2011, MBUSI
received an ADEM air permit approving modifications to the Facility including an expansion of
the remaining paintshop to reestablish some of the lost capacity when the Plant 1 paintshop was
shutdown, as well as other modifications needed to accommodate production of the Mercedes-
Benz C-class vehicle.
The current Title V Operating Permit (TVOP) still retains the VOC limit of 640.0 tpy, which
applies to what was once referred to as “Plant 2,” and which was set prior to the PAL permit
issuance in August 2008. MBUSI believes the 640.0 tpy limit should have been removed when
the PAL was set since the PAL was set Facility-wide, inclusive of all VOC sources regardless of
whether the sources were at Plant 1 or Plant 2. In this application, MBUSI is requesting that the
PAL for VOC be retained at its current level, based on an assessment of the potential to emit (PTE)
of the current operations. MBUSI is also requesting that this subordinate limit of 640.0 tpy be
removed at the time of the PAL renewal.
Mercedes-Benz U.S. International, Inc.
Plantwide Applicability Limit Renewal Application
1-2 MBUSI PAL Renewal Application February 2018
1.2 PAL RENEWAL APPLICATION REQUIREMENTS
MBUSI is requesting a renewal of the PAL for VOC emissions for its Facility. ADEM Rule 335-
3-14-.04(23)(j)(3) lists the information that is required to be included in a PAL renewal
application. This includes:
1. A list of all emissions units at the source designated as small, significant, or major
based on their PTE. In addition, the owner or operator of the source shall indicate
which, if any, Federal or State applicable requirements, emissions limitations, or work
practices apply to each unit.
2. Calculations of the baseline actual emissions (with supporting documentation).
Baseline actual emissions are to include emissions associated not only with operation
of the units, but also emissions associated with startup and shutdown.
3. The sum of the PTE of all emissions units under the PAL (with supporting
documentation).
4. A proposed PAL level.
5. The calculation procedures that the major stationary source owner or operator proposes
to use to convert the monitoring system data to monthly emissions and annual
emissions based on a 12-month rolling total for each month as required by
subparagraph ADEM Rule 335-3-14-.04(23)(m)1.
These items are covered in the following Sections.
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-1 MBUSI PAL Renewal Application February 2018
2. EMISSIONS UNITS
2.1 VOC PTE
ADEM’s PAL rule requires applicants to provide the PTE for the Facility by emissions unit. The
PTE is meant to reflect the maximum capacity to emit a pollutant based upon its physical and
operational design, taking into account any enforceable limits. The Facility currently operates
under a VOC PAL of 859.55 tpy, which is an enforceable limit that establishes the VOC PTE for
the Facility. However, for the purposes of this application and the evaluation of the appropriate
PAL level for renewal, MBUSI calculated the current Facility-wide VOC PTE assuming that the
current VOC PAL level is not in effect.
In the original PAL application, MBUSI organized the Facility into 10 different emissions units
according to the type of activity carried out by those emissions units. This approach is consistent
with past PSD and TVOP applications that have been submitted to ADEM over the years. For
continuity, we have used the same groups in this application.
Table 2-1 lists the 10 emissions units at the Facility and the VOC PTE for each emissions unit.
MBUSI has determined that the Facility-wide VOC PTE, excluding the current PAL, is 860.44
tpy. In general, the VOC PTE is based on recent actual operating information and material usage
and production rates that were then adjusted to assume maximum possible operation of three
shifts/day, seven days per week and 50 weeks per year. Appendix A provides detailed emissions
calculations of the VOC PTE for each of these emissions units and the assumptions used.
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-2 MBUSI PAL Renewal Application February 2018
Table 2-1 MBUSI Facility-wide VOC PTE
Emissions Unit VOC PTE (tpy)
Body Shop Negligible
Paintshop 664.56
Touch-Up 40.61
Assembly Shop 1.35
Energy Center Boilers 5.32
Emergency Engines 1.47
Other Natural Gas Combustion 6.11
Tank Farm 3.07
Fueling 0.42
Miscellaneous VOC 137.54
TOTAL 860.44
2.2 DESIGNATION OF EMISSIONS UNITS
ADEM’s PAL rule requires the application to include a designation of whether an emissions unit
is classified as small (less than 40 tpy, the significance threshold for VOC), significant (40 to 100
tpy), or major (100 tpy and greater) based on their PTE. Table 2-2 provides this designation for
the 10 emissions units at MBUSI.
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-3 MBUSI PAL Renewal Application February 2018
Table 2-2 PTE and Designation of Emissions Units at MBUSI
Emissions Unit Designation
(Small, Significant, Minor)
Body Shop Small
Paintshop Major
Touch-Up Significant
Assembly Shop Small
Energy Center Boilers Small
Emergency Engines Small
Other Natural Gas Combustion Small
Tank Farm Small
Fueling Small
Miscellaneous VOC Major
2.3 LIST OF APPLICABLE FEDERAL AND STATE REGULATORY REQUIREMENTS
As required by ADEM’s PAL rule, MBUSI has included a list of the Federal and State regulatory
requirements applicable to the emissions units denoted in Section 2.1 in Table 2-3 and Table 2-4.
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-4 MBUSI PAL Renewal Application February 2018
Table 2-3 Federal Requirements Applicable to MBUSI
Statutory/
Regulatory
Requirement
Citation
Description of Requirement Applicability Emissions Units to Which
Requirement is Applicable
40 CFR 60
Subpart A
New Source Performance
Standards (NSPS):
General Provisions
Procedural guidelines for construction and
startup, performance testing schedules and
procedures, and other notification and
recordkeeping requirements apply when a
facility is subject to one or more NSPS.
Paintshop
Touch-Up
Miscellaneous VOC
Energy Center Boilers
40 CFR 60
Subpart Dc
NSPS: Small Industrial-
Commercial-Institutional
Steam Generating Units
Constructed, Modified, or
Reconstructed After June 9,
1989
Daily fuel use recordkeeping requirement
applies to the Energy Center boilers
[maximum heat input rates between 10 -
100 million British thermal units per hour
(MMBtu/hr)].
Energy Center Boilers
40 CFR 60
Subpart MM
NSPS: Automobile and Light-
Duty Truck Surface Coating
Operations
VOC standards apply to prime coat,
guidecoat and topcoat automobile coating
operations.
Paintshop
40 CFR 60
Subpart IIII
NSPS: Stationary
Compression Ignition Internal
Combustion Engines
Certain work practice and recordkeeping
requirements apply to the emergency
generators and fire pumps.
Emergency Engines
40 CFR 60
Subpart JJJJ
NSPS: Stationary Spark
Ignition Internal Combustion
Engines
Certain work practice and recordkeeping
requirements apply to the emergency
generators and fire pumps.
Emergency Engines
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-5 MBUSI PAL Renewal Application February 2018
Statutory/
Regulatory
Requirement
Citation
Description of Requirement Applicability Emissions Units to Which
Requirement is Applicable
40 CFR 63
Subpart A
National Emission Standard
for Hazardous Air Pollutants
(NESHAP) for Source
Categories: General Provisions
Certain general provisions apply including
requirements for performance tests,
notifications, monitoring, recordkeeping,
and reporting.
Paintshop
Touch-Up
Miscellaneous VOC
40 CFR 63
Subpart IIII
NESHAP: Automotive and
Light-Duty Truck Surface
Coating
The rule applies to MBUSI, including
emission limits, monitoring,
recordkeeping, and reporting requirements,
work practices, and compliance
demonstration requirements.
Paintshop
Touch-Up
Miscellaneous VOC
40 CFR 63
Subpart
ZZZZ
NESHAP: Stationary
Reciprocating Internal
Combustion Engines
Certain work practice and recordkeeping
requirements apply to the emergency
generators and fire pumps.
Emergency Engines
40 CFR 63
Subpart
DDDDD
NESHAP: Industrial,
Commercial and Institutional
Boilers and Process Heaters
Certain work practices (annual tune-up and
one-time energy assessment),
recordkeeping and notifications apply.
Energy Center Boilers
40 CFR 64 Compliance Assurance
Monitoring (CAM)
Applies to the regenerative thermal
oxidizers (RTOs). Paintshop
40 CFR 82
Subpart F
Protection of Stratospheric
Ozone
Recycling and Emissions
Reduction
Applies to appliances using Class I and
Class II refrigerants. Facility
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-6 MBUSI PAL Renewal Application February 2018
Table 2-4 State Requirements Applicable to MBUSI
Statutory/
Regulatory
Requirement
Citation
Description of Requirement Applicability
Emissions Units to
Which Requirement is
Applicable
Code of Alabama
§22-28-16(d)
Alabama Pollution Control Act
Permits Requirement to have a permit applies. Facility
ADEM Rule
335-1-7
Air Division Operating Permit Fees
Fee Schedule
Requirements to pay fees associated with
air emissions apply. Facility
ADEM Rule
335-3-1-.04
General Provisions: Monitoring,
Records, and Reporting
Requirements to conduct monitoring,
maintain records, submit reports using
methods and procedures as prescribed
apply.
Facility
ADEM Rule
335-3-1-.05
General Provisions: Sampling &
Test Methods
Requirements to use approved sampling
and test methods, and procedures apply. Facility
ADEM Rule
335-3-1.07
General Provisions: Maintenance
and Malfunctioning of Equipment
Requirement to notify ADEM of equipment
shutdowns and malfunctions applies. Facility
ADEM Rule
335-3-1-.08 Prohibition of Air Pollution Prohibition of air pollution applies. Facility
ADEM Rule
335-3-1-.10 Circumvention
Prohibition of installation of a device or
using other means to conceals or dilutes
emissions without reducing the total
amount of air contaminant applies.
Facility
ADEM Rule
335-3-3-.02
Control of Open Burning and
Incineration: Incinerators
Odor minimization requirement applies to
RTOs. Paintshop
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-7 MBUSI PAL Renewal Application February 2018
Statutory/
Regulatory
Requirement
Citation
Description of Requirement Applicability
Emissions Units to
Which Requirement is
Applicable
ADEM Rule
335-3-4-.01
Control of Particulate Emissions:
Visible Emissions
Visible emissions of limit of 20% opacity
(and up to 40% for not more than six
minutes in any 60-minute period) applies.
Paintshop
Energy Center Boilers
Emergency Engines
Other Natural Gas
Combustion
ADEM Rule
335-3-4-.02
Control of Particulate Emissions:
Fugitive Dust and Fugitive
Emissions
Requirement to minimize airborne dust
from roads and material handling applies. Facility
ADEM Rule
335-3-4-.03
Control of Particulate Emissions:
Fuel Burning Equipment
Particulate matter emissions limit of 0.5 to
0.2 lb/MMBtu of heat input applies to fuel
burning operations.
Energy Center Boilers
Emergency Engines
Other Natural Gas
Combustion
ADEM Rule
335-3-4-.04
Control of Particulate Emissions
Process Industries: General (raw
materials)
Particulate emissions limit based on hourly
process weight of raw materials is met with
more stringent BACT particulate limits.
Body Shop
Paintshop
ADEM Rule
335-3-5-.01
Control of Sulfur Compound
Emissions: Fuel Combustion
Sulfur dioxide emissions limit of 4.0
lb/MMBtu applies to fuel burning
equipment.
Paintshop
Energy Center Boilers
Emergency Engines
Other Natural Gas
Combustion
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-8 MBUSI PAL Renewal Application February 2018
Statutory/
Regulatory
Requirement
Citation
Description of Requirement Applicability
Emissions Units to
Which Requirement is
Applicable
ADEM Rule
335-3-6-.03
Control of Organic Emissions:
Storage of VOC
Applies to VOCs with a true vapor pressure
greater than or equal to 1.5 psia under
storage conditions. Requirement to use
pressure vessels or to equip tanks with
submerged fill pipes, floating roof, or vapor
recovery system applies to storage tanks
with capacity greater than 1,000 gallons.
Tank Farm
ADEM Rule
335-3-6-.07
Control of Organic Emissions:
Gasoline Dispensing Facilities –
Stage 1
Vapor control and fuel use recordkeeping
requirements apply to MBUSI storage tanks
and filling station.
Tank Farm
ADEM Rule
335-3-6-.11(5)
Control of Organic Emissions:
Surface Coating
(Automobile and Light Duty Truck
Manufacturing)
VOC limits apply to coating operations.
Paintshop
Touch-up
Miscellaneous VOC
ADEM Rule
335-3-6-.12 Solvent Metal Cleaning
Cold cleaner operating practices relating to
freeboard height, container labeling, drip
time, cover closure when not in use apply.
Miscellaneous VOC
ADEM Rule
335-3-6-.20
Leaks from Gasoline Tank Trucks
and Vapor Collection Systems
Requirements for design and operation of
vapor collection system and loading
equipment and for repair and retesting
vapor collection or control systems apply.
Tank Farm
ADEM Rule
335-3-10 NSPS
NSPS requirements in 40 CFR 60
incorporated by reference.
Paintshop
Touch-up
Energy Center Boilers
Miscellaneous VOC
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-9 MBUSI PAL Renewal Application February 2018
Statutory/
Regulatory
Requirement
Citation
Description of Requirement Applicability
Emissions Units to
Which Requirement is
Applicable
ADEM Rule
335-3-11-.01 NESHAP: General NESHAP incorporated by reference.
Paintshop
Touch-up
Energy Center Boilers
Miscellaneous VOC
ADEM Rule
335-3-11-.06(86)
NESHAP: Surface Coating of
Automobiles and Light-Duty
Trucks
NESHAP incorporated by reference.
Paintshop
Touch-up
Miscellaneous VOC
ADEM Rule
335-3-14
Air Permits
Requirement to obtain air permit and
maintain copy on-site applies. Requirement
to provide sampling and testing facilities
applies.
Facility
ADEM Rule
335-3-16
Major Source Operating Permits
Requirement to submit permit application
within 12 months of startup applies;
requirement to file permit onsite will apply
after the permit for which application is
being made is issued; requirement to
maintain sampling and testing facilities
applies.
Facility
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-10 MBUSI PAL Renewal Application February 2018
2.4 LIST OF APPLICABLE EMISSIONS LIMITATIONS
As required by ADEM’s PAL rule, MBUSI has included a list of the emissions limitations for the
Facility from the current TVOP No. 413-0034 dated April 2, 2017.
Operating Permit Summary No. 02: Storage Tanks with Stage I Recovery
• Stage 1
o Maintain proper Stage I recovery system on two 12,000-gallon gasoline storage
tanks
Operating Permit Summary No. 03: 97.9 MMBtu/hr Natural Gas-Fired Boiler
• Opacity of Boiler Stacks
o 10% opacity limit
• Fuel Usage
o Only natural gas will be used for these units
• Continuous Compliance
o Annual tune-ups will be conducted
Operating Permit Summary No. 010: Motor Vehicle Assembly Plant
• VOC Emissions
o Facility-wide: 640.0 tpy per rolling 12-month period
• NSPS
o Primecoat: E-coat – 1.34 lb VOC/gallon of applied coating solids (gacs)
o Guidecoat: Primer/Surfacer and Sealer/Deadener – 11.68 lb VOC/gacs
o Topcoat: Topcoat and Clearcoat – 12.27 lb VOC/gacs
• NESHAP
o E-Coat, Primer/Surfacer/Topcoat/Final Repair/Glass Bonding Primer and
Adhesive Operations/Adhesives and Sealers Not Used for Glass Bonding Systems
– 0.60 lb HAP/gacs
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-11 MBUSI PAL Renewal Application February 2018
o Adhesive/Sealers Not Used for Glass Bonding Systems – 0.010 lb HAP/lb of
material used
o Deadener – 0.010 lb HAP/lb of material used
• BACT VOC Limits
o Primecoat: E-coat – 0.20 lb/gacs
o Guidecoat: Primer/Surfacer and Oven – 5.10 lb/gacs
o Topcoat: Topcoat and Clearcoat Booths and Oven – 7.10 lb/gacs
o Sealer/Deadener/Adhesive – 0.40 lb/gal, as applied
o Blackout – 1.00 lb/gal, as applied
o RTO Nos. 3-1, 3-2, 3-3 and 3-4: 95% removal efficiency
• BACT Particulate Matter (PM) Limits (gr/acf)
o Primer/Surfacer Booth Exhausts – 0.0021
o Primer Sanding Exhausts – 0.0015
o Basecoat Booth Exhausts – 0.0011
o Clearcoat Manual Exhaust – 0.0015
o Clearcoat Robot Exhaust – 0.0019
o Final Repair Exhausts – 0.0007
• BACT Nitrogen Oxides (NOx) Limits (lb/MMBtu heat input, except as noted)
o E-Coat Oven – 0.10
o Sealer/Deadener Ovens – 0.10
o Primer/Surfacer Ovens – 0.10
o Topcoat/Clearcoat Ovens – 0 .10
o Primecoat Booth Air Supply Houses – 0.10
o Topcoat Booth Air Supply Houses – 0.10
o Touchup Air Supply Houses – 0.10
o Blackout/Cavity Wax Air Supply Houses – 0.10
o Incinerator RTO 3-1, 3-2 – 3.6 lb/hr
o Incinerator RTO 3-3 – 3.6 lb/hr
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-12 MBUSI PAL Renewal Application February 2018
• BACT Carbon Monoxide (CO) Limits
o Incinerator RTO 3-1, 3-2 – 5.0 lb/hr
o Incinerator RTO 3-3 – 5.0 lb/hr
• Other VOC Limits
o E-Coat Oven No. 2 Integrated Oxidizer – 90% removal efficiency
o Sealer Oven No. 3 Integrated Oxidizer – 90% removal efficiency
• Fuel Usage
o Only natural gas will be used in combustion equipment other than diesel emergency
engines and gasoline engines
• Tank Filling
o Stage II vapor control system or onboard vapor recovery system required
Operating Permit Summary No. 011: 33.4 MMBtu/hr Natural Gas-Fired Boiler
• Opacity of Boiler Stacks
o 10% opacity limit observation of 5% or greater requires investigation and corrective
action
• NOX Emissions
o 1.35 lb/hr or 0.04 lb/MMBtu
• CO Emissions
o 5.6 lb/hr or 0.165 lb/MMBtu
• PM/PM10 Emissions
o 0.27 lb/hr or 0.008 lb/MMBtu
• Fuel Usage
o Only natural gas will be used
Operating Permit Summary No. 012: 98 MMBtu/hr Natural Gas-Fired Boiler
• Opacity of Boiler Stacks
o 10% opacity
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-13 MBUSI PAL Renewal Application February 2018
• Continuous Compliance
o Annual tune-ups will be conducted
Operating Permit Summary No. 013: Abrasive Blasting Units (3) with Dust Collector
• Opacity
o 10% opacity limit
• PM Emissions
o Unit shall not discharge in excess of E = 3.59(P0.62) where P is the process weight
in tons/hr
Operating Permit Summary No. 020 and 021
• Opacity
o 10% opacity limit
2.5 LIST OF APPLICABLE WORK PRACTICES PLANS
As required by ADEM’s PAL rule, MBUSI is identifying applicable work practice plans. The
Facility has three work practice plans in place that affect the paintshop emissions units. The first
two work practice plans are required by 40 CFR §63.3094(b):
• A work practice plan to minimize organic HAP emissions from the storage, mixing, and
conveying of coatings, thinners, and cleaning materials used in, and waste materials
generated by, all coating operations for which emission limits are established under the 40
CFR 63 Subpart IIII.
• A work practice plan to minimize organic HAP emissions from cleaning and from purging
of equipment associated with all coating operations for which emission limits are
established under the 40 CFR 63 Subpart IIII.
The third work practice plan is required pursuant to 40 CFR §63.3100(f). The Facility is required
to implement the following plan for affected coating operations for which compliance is
demonstrated by taking credit for an emissions reduction associated with any control device:
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
2-14 MBUSI PAL Renewal Application
February 2018
• A written startup, shutdown, and malfunction plan (SSMP) for each such control device
and any associated emissions capture system according to 40 CFR §63.6(e)(3).
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
3-1 MBUSI PAL Renewal Application February 2018
3. BASELINE ACTUAL VOC EMISSIONS CALCULATION
As required by the ADEM PAL rule, MBUSI has provided baseline actual emissions for the
Facility from 2013 through 2017. Typically, a baseline period is a 24-month period from the past
10 years. MBUSI limited its determination of the baseline period to a 24-month period within the
last five years since the Facility went through significant equipment and operating changes prior
to those five years. As noted earlier, MBUSI ceased operation of the original Plant 1 paintshop in
2009, and subsequently went through an expansion to recapture some of the lost production
capacity and to accommodate production of the Mercedes-Benz C-class vehicle. MBUSI believes
that a baseline period selected from 2013 through 2017 is most representative of existing
operations.
Appendix B provides detailed baseline actual emissions that were compiled using monthly VOC
reports and annual emissions reports that MBUSI has submitted to ADEM for calendar years 2013
through 2017. The highest annual VOC emissions averaged over a consecutive 24 months during
2013 through 2017 was 436.60 tpy. That 24-month period was June 2015 through May 2017.
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
4-1 MBUSI PAL Renewal Application February 2018
4. PROPOSED PAL LEVEL
ADEM Rule 335-3-14-.04(23)(j)(4) specifies how the PAL level is to be adjusted at the time a
PAL is renewed. In particular, the rule states that ADEM “may set the PAL at a level that he or
she determines to be more representative of the source's baseline actual emissions, or that he or
she determines to be more appropriate considering air quality needs, advances in control
technology, anticipated economic growth in the area, desire to reward or encourage the source's
voluntary emissions reductions, or other factors as specifically identified by the Director in his or
her written rationale.” However, pursuant to ADEM Rule 335-3-14-.04(23)(j)(4)(iii), ADEM is
not permitted to set a PAL level greater than the applicant’s PTE.
MBUSI is proposing that ADEM renew the Facility’s PAL permit while retaining the current VOC
PAL level of 859.55 tpy. As shown in Section 2, MBUSI determined that the VOC PTE for the
Facility is higher than the VOC PAL level, even using the current equipment and while still being
able to demonstrate compliance with applicable BACT and NSPS limits for VOC as shown in
Table 4-1. The original PAL level of 859.55 tpy was set based on production projections of
285,000 vehicles per year (90,000 from Plant 1 and 195,000 from Plant 2). After the paintshop
expansion addressed in the 2011 air permit, MBUSI projected an actual future production rate of
304,000 vehicles per year. MBUSI estimates that the Facility has the capacity to produce up to
371,000 vehicles under a maximum operating schedule of three shifts per day, seven days per week
and 50 weeks a year. MBUSI believes that it is critical to retain the flexibility it has under the
existing PAL permit to be able to respond quickly to changes in market demand and technologies.
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
4-2 MBUSI PAL Renewal Application February 2018
Table 4-1 Comparison of MBUSI VOC PTE and Permit Limits
Source VOC Limit
(lb/gacs)
Emissions Based on
VOC PTE1
(lb/gacs)
E-Coat BACT 0.20 0.15
Guidecoat/Primer Surfacer
BACT 5.10 1.30
Topcoat BACT 7.10 5.69
E-Coat NSPS 1.34 0.15
Guidecoat/Primer Surfacer (plus
sealer and deadener) NSPS 11.68 0.24
Topcoat NSPS 12.27 5.69
1 See Table A-2 in Appendix A for supporting calculations.
Mercedes-Benz U.S. International
Plantwide Applicability Limit Renewal Application
5-1 MBUSI PAL Renewal Application February 2018
5. MONITORING, RECORDKEEPING AND NOTIFICATION REQUIREMENTS
ADEM Rule 335-3-14-.04(23)(1) through (23)(n) specifies the minimum monitoring
recordkeeping and notification requirements for a PAL permit. MBUSI proposes to satisfy these
requirements by using the same emissions calculation, monitoring, recordkeeping and notification
requirements in the current PAL permit.
APPENDIX A - VOC PTE CALCULATIONS
Emissions UnitVOC PTE
(tons/yr)
Designation (Small,
Significant, Major)
Body Shop Negligible Small
Paint Shop 664.56 Major
Touch-Up 40.61 Significant
Assembly Shop 1.35 Small
Energy Center Boilers 5.32 Small
Emergency Engines 1.47 Small
Other Natural Gas Combustion 6.11 Small
Tank Farm 3.07 Small
Fueling 0.42 Small
Miscellaneous VOC 137.54 Major
TOTAL 860.44 --
MBUSI Potential to Emit VOC
Facility-wide Emissions and Designation of Emissions Units
Table A-1
MBUSI PAL Renewal Application.xlsx February 2018
Coating
CategoryProduct Name
MSC
NumberUsage1
(gal/vehicle)
Total
Gallons
Used2
VOC3
(lb/gal)
Solids
(% vol)Repair Split
Gallons in
Coating
Line
Gallons for
Repair/
Touch-Up
Transfer
Efficiency4
Booth Split
(Non-
Oven)4
CC Auto
Split
Oven
Capture
Efficiency4
RTO Control
Efficiency5
Coating Line
Gross VOC
(lbs)
Coating Line
Net
Uncontrolled
VOC
(lbs)
Coating Line
Controlled
VOCs
(lbs)
Touch-Up/
Repair VOC
Emissions
(lbs/year)
Touch-Up/
Repair VOC
Emissions
(tons/year)
VOC Emissions
Not Including
Repair/
Touch-Up
(lbs/year)
VOC Emissions
Not Including
Repair/
Touch-Up
(tons/year)
Applied
Solids
(gallons)
lbs VOC/
gal ACS
E-Coat Cathoguard Paste 2409 0.21 77,478 0.01 48.92% 0% 77,478 0.00 100.0% 20.0% 0.0% 80.0% 95% 774.78 154.96 30.99 0.00 0.00 185.95 0.09 37,902
E-Coat Cathoguard Resin 2407 1.63 605,508 0.22 35.82% 0% 605,508 0.00 100.0% 20.0% 0.0% 80.0% 95% 130,790 26,158 5,232 0.00 0.00 31,390 15.69 216,893
E-Coat Dowanol PNB 2480 0.01 3,434 7.34 0.00% 0% 3,434 0.00 100.0% 20.0% 0.0% 80.0% 95% 25,204 5,041 1,008 0.00 0.00 6,049 3.02 0.00
0.00 0.00 37,624 18.81 254,795 0.15
Guidecoat Silver Gray Hemmelrath 3298 1.06 393,962 1.10 33.80% 0% 393,962 0.00 85.0% 30.6% 0.0% 69.4% 95% 433,358 132,608 15,038 0.00 0.00 147,645 73.82 113,185
0.00 0.00 147,645 73.82 113,185 1.30
Basecoat Brilliant Blue 3353 1.02 377,808 1.83 20.46% 5% 358,918 18,890 75.9% 98.1% 0.0% 1.9% 95% 656,820 644,340 623.98 34,569 17.28 644,964 322.48 58,670
Clearcoat ProGloss 40A-Comp 3000 0.48 178,166 4.05 44.16% 5% 169,257 8,908 75.9% 69.0% 55.1% 31.0% 95% 685,616 95,301 29,516 36,085 18.04 124,816 62.41 59,717
Clearcoat ProGloss 40B-Comp 3001 0.16 59,668 2.64 64.00% 5% 56,685 2,983 75.9% 69.0% 55.1% 31.0% 95% 149,648 20,801 6,442 7,876 3.94 27,243 13.62 28,984
78,531 39.27 797,024 398.51 147,371 5.41
Sealer One Component Adhesive 2440 2.12 789,168 0.21 95.11% 0% 789,168 0.00 100.0% 30.6% 0.0% 69.4% 95% 165,725 50,712 5,751 0.00 0.00 56,463 28.23 750,596
0.00 0.00 56,463 28.23 750,596 0.08
Touch-up Only Glasurit 352-500 2577 9.65E-04 358.59 7.50 1.00% 100% 0.00 358.59 100.0% 0.0% 0.0% 0.0% 95% 0.00 0.00 0.00 2,689 1.34 0.00 0.00 3.59
2,689 1.34 0.00 0.00 3.59 0.00
81,220 40.61 1,038,756 519.38 -- --1 Usage rates are based on values from the 2016 annual report plus 10%.2 Based on a maximum potential annual production of:
371,543 vehicles/year based on maximum operating hours of 3 shifts/day, 7 days/week, 50 weeks/year3 For guidecoat and basecoat, used VOC content for highest VOC content coating in this category used within the last five years.4 For guidecoat, basecoat, clearcoat and sealer, based on lowest test value in last five years. For e-coat, based on assumption that 80% of emissions is captured within the oven. 5 Based on permit requirement for minimum destruction efficiency.
Table A-2
Sealer Subtotal:
Touch-up Only Coating Subtotal:
TOTAL VOC EMISSIONS:
MBUSI Potential to Emit VOC
Paintshop Coating and Repair/Touch-Up
E-Coat Subtotal:
Guidecoat Subtotal:
Topcoat Subtotal:
MBUSI PAL Renewal Application.xlsx February 2018
Material Category Product Name1 MSC Number
Density
(lb/gal)
VOC Content
(lb/gal)
Gross
Potential
Gallons
Used/Year2
Estimated
Recovery
Rate3
Net Gallons
Used/Year
VOC After
Purge
Recovery
(lbs/year)
VOC After
Purge
Recovery
(tons/year)
Purge Waterborne Purge 3156 8.29 0.80 108,900 0% 108,900 87,120 43.56
Purge Solventborne Purge 2996 7.34 7.34 60,654 54% 27,689 203,236 101.62
290,356 145.181 Primary materials used in 2016.2 Gross potential annual usage is based on the peak monthly usage in 2016 plus 10% multiplied by 12 .3 Based on lowest annual recovery rate in last five years (i.e., 2014).
MBUSI Potential to Emit VOC
Paintshop Waterborne and Solventborne Purge Solvent
TOTAL VOC EMISSIONS:
Table A-3
MBUSI PAL Renewal Application.xlsx February 2018
Description Number of Tests1 Miles Per TestVOC Emissions Factor2
(g/mi/test)VOC Emissions (lbs/year) VOC Emissions (tons/year)
Vehicle Test Center 349,974 20 0.14 2,158 1.08
Roll Test 349,974 5 0.14 539.61 0.27
2,698 1.351 The number of tests are based on maximum potential annual production.2 Emissions factors are from Daimler.
MBUSI Potential to Emit VOC
Assembly Shop
TOTAL VOC EMISSIONS:
Table A-4
MBUSI PAL Renewal Application.xlsx February 2018
Emissions UnitBoiler Size
(MMBtu/hr)
Maximum Fuel
Use
(MMBtu/year)
VOC Emissions
Factor1
(lb/MMcf)
VOC Emissions2
(lbs/year)
VOC Emissions2
(tons/year)
Boiler 801A 98.0 858,480 5.50 4,540 2.27
Boiler 802A 98.0 858,480 5.50 4,540 2.27
Boiler 803 33.5 293,460 5.50 1,552 0.78
10,632 5.321 Emissions factors based on AP-42, Table 1.4-2.
2 Emissions are based on the following:
Heating Value of Natural Gas: 1,040 Btu/cf
Hours of Operation Per Year: 8,760 hrs/yr
TOTAL VOC EMISSIONS:
MBUSI Potential to Emit VOC
Energy Center Boilers
Table A-5
MBUSI PAL Renewal Application.xlsx February 2018
Generator ID Gen. Size
(kW)
Gen. Size
(hp)
VOC Emissions
Factor1,2
(lb/hp-hr)
VOC Emissions3
(lbs/year)
VOC Emissions3
(tons/year)
GEN-2 45 60 1.59E-03 48.02 0.02
GEN-3 45 60 1.59E-03 48.02 0.02
GEN-4 45 60 1.59E-03 48.02 0.02
GEN-7 45 60 1.59E-03 48.02 0.02
GEN-8 45 60 1.59E-03 48.02 0.02
GEN-9 99 133 1.59E-03 105.74 0.05GEN-10 99 133 1.59E-03 105.74 0.05GEN-11 45 60 1.59E-03 47.70 0.02GEN-12 146 195 1.59E-03 155.03 0.08GEN-13 146 195 1.59E-03 155.03 0.08
GEN-17 (Paint Shop North) 80 122 3.05E-05 1.86 9.30E-04
811.18 0.41
Generator ID Gen. Size
(kW)
Gen. Size
(hp)
VOC Emissions
Factor1
(lb/hp-hr)
VOC Emissions2
(lbs/year)
VOC Emissions2
(tons/year)
GEN-1 (Training Center) 347 465 2.47E-03 574.28 0.29
FP-1 (East) 343 460 2.47E-03 568.10 0.28
FP-2 (West) 343 460 2.47E-03 568.10 0.28GEN-14 60 80 2.47E-03 98.80 0.05GEN-15 74 99 2.47E-03 122.27 0.06
GEN-16 (MLC Building) 200 318 9.86E-04 156.84 0.08
FP-3 (North) 216 289 2.82E-04 40.82 0.02
2,129 1.061 AP-42, Table 3.3-1. Emissions factors for GEN-16 (MLC Generator) and FP-3 (North) are from vendor data.
2,940 1.47
Table A-6
Diesel Emergency Generators Subtotal:
TOTAL VOC EMISSIONS:
2 Based on 500 hours of operation per year.
MBUSI Potential to Emit VOC
Emergency Engines
Natural Gas Emergency Engines
3 Based on 500 hours of operation per year.
Natural Gas Emergency Generators Subtotal:
Diesel Emergency Engines
2 The Btu/hp-hr conversion for natural gas is from http://www.api.org/~/media/Files/EHS/climate-
change/2009_GHG_COMPENDIUM.ashx.
1 AP-42, Table 3.2-2 for a 4-cycle lean-burn engine. VOC factor for the Paint Shop North GEN is from vendor data.
MBUSI PAL Renewal Application.xlsx February 2018
Emissions UnitTotal Heat Input
(MMBtu/hr)VOC Emissions
1
(lbs/year)
VOC Emissions1
(tons/year)
Total Paint Shop Ovens 92.7 4,293 2.15
Total RTOs 32.0 1,482 0.74
Total Air Supply Units 139.0 6,439 3.22
TOTAL VOC EMISSIONS: 263.7 12,215 6.11
1 Emissions are based on the following:
Hours of Operation: 8,760 hours/year
Heating Value of Natural Gas: 1,040 Btu/cf
VOC Emissions Factor: 5.5 lb/MMscf (AP-42 Section 1.4, Table 1.4-2)
Table A-7
MBUSI Potential to Emit VOC
Other Natural Gas Combustion Sources
MBUSI PAL Renewal Application.xlsx February 2018
Tank No. Tank Contents MSC CodeTotal VOC Emissions1
(lbs/yr)
Total VOC Emissions1
(tons/year)
T305 Gasoline (UL)2 125 3,007 1.50
T306 Gasoline (UL)2 125 3,007 1.50
T307 Diesel3 2509 11.09 0.01
T308 Diesel3 2509 11.09 0.01
T303 Coolant (Antifreeze)4 54 0.41 2.04E-04
T302 Windshield Washer 813 100.85 0.05
6,137 3.07
2 Gasoline calculations are based on controlled VOC emissions and HAP weight percent from the MSDSs. 3 Diesel is estimated to contribute trace amounts of benzene.
4 Antifreeze emissions are calculated based on historical data.
Table A-8
MBUSI Potential to Emit VOC
Tank Farm
TOTAL VOC EMISSIONS:1 Tank VOC emissions are calculated monthly. In calendar year 2016, the peak monthly VOC emissions for the tanks were
455.56 lbs (gasoline tanks), 1.68 lbs (diesel tanks), 0.03 lbs (coolant tank), and 7.64 lbs (windshield washer fluid tank) as
documented in MBUSI's monthly VOC reports. Therefore, VOC PTE from tanks is based on peak monthly emissions plus
10% annualized.
MBUSI PAL Renewal Application.xlsx February 2018
Description1
UL Gasoline
Dispensed2
(gal/yr)
VOC Emissions
Factor
(Uncontrolled)3
(lb/1000 gal)
Control
Efficiency4
VOC Emissions
Factor
(Controlled)
(lb/gal)
VOC Emissions
(lbs/yr)
VOC Emissions
(tons/yr)
Fuel filling of production vehicles5 1,350,994 11.0 95% 5.50E-04 743.05 0.37
Fuel filling of vehicles used onsite6 169,976 11.0 95% 5.50E-04 93.49 0.05
836.53 0.42
2 UL gasoline dispensed is based on the peak monthly usage in 2016 plus 10% multiplied by 12 .
5 Assumes use of Stage II or ORVR when production vehicles are filled.
Table A-9
4 VOC control efficiency for vehicles equipped using onboard refueling vapor recovery (ORVR) or Stage II vapor recovery assumed to be at least 95% based
on EPA rulemaking "Air Quality: Widespread Use for Onboard Refueling Vapor Recovery and Stage II Waiver" (May 16, 2012 Federal Register).
6 Assumes onsite vehicles equipped with ORVR.
MBUSI Potential to Emit VOC
Fueling
TOTAL VOC EMISSIONS:1 Fuel filling emissions include only those from gasoline filling. Diesel filling emissions are negligible.
3 Emissions factor for uncontrolled VOC emissions from AP-42 Table 5.2-7 "Evaporative Emissions from Gasoline Service Stations."
MBUSI PAL Renewal Application.xlsx February 2018
137.54 tons per year (based on peak monthly emissions plus 10% annualized)
MSC Number Description / product name
Gross Usage of
Direct Materials
in 2016
Units
Gross
Usage
(gal)
Density
(lb/gal)VOC wt%
Gross
Usage (lbs)
Net Usage
(gal)
VOC
Content
(lb/gal)
18 IPA - Indirect Materials 17,555 gal 17,555.0 6.59 0.90 115,687.5 17,555.0 5.93
272 Glass Bonding Primer 1,883 L 497.5 6.59 1.00 3,277.6 497.5 6.53
2798 Adhesive Betaseal 1893 11,675 L 3,084.2 11.35 0.00 35,005.3 3,084.2 0.00
2673 Betaseal 1970 13 L 3.4 10.43 0.01 35.8 3.4 0.03
3125 Adhesive EFBOND RA 820 107,846 KG 20,356.1 11.68 0.00 237,759.4 20,356.1 0.00
1213 Terostat 1211 33,919 kg 6,400.4 11.68 0.00 74,779.5 6,400.4 0.00
3080 Adhesive Terostat 3225 DC-25 209,571 KG 35,732.8 12.93 0.00 462,024.8 35,732.8 0.00
3284 Silkaflex 250 DM-3 (AC) 360 L 95.1 8.22 0.59 781.5 95.1 4.84
166 Sealing DBL 6069.20 Sikaflex 221 721 KG 148.8 10.68 0.02 1,589.5 148.8 0.24
3266 Versilok 254 Adhesive 1,222 KG 223.3 12.07 0.00 2,694.8 223.3 0.02
3285 Eftec EFBOND UA 248 407 KG 95.3 9.43 0.00 898.4 95.3 0.00
3290 Adhesive Sikaflex-DM6 1,396 KG 299.8 10.26 0.00 3,077.3 299.8 0.05
3267 Versilok 253 Adhesive 1,984 KG 439.5 9.95 0.00 4,373.0 439.5 0.00
3278 EFBOND RA 350 1,150 KG 209.6 12.10 0.20 2,536.3 209.6 0.00
3281 EFBOND RA 310 29,408 KG 5,550.9 11.68 0.00 64,834.3 5,550.9 0.00
3157 Betaseal 1948 Glass Bonding 402,243 KG 78,756.1 11.26 0.00 886,793.9 78,756.1 0.00
3288 Sikaflex 250 DM10 50,430 KG 10,323.1 10.77 0.00 111,179.5 10,323.1 0.00
3216 Sikaflex 234 9,846 KG 1,926.1 11.27 0.00 21,707.5 1,926.1 0.00
275 Glass Bonding Cleaner 1,883 KG 502.8 8.26 0.58 4,151.5 502.8 4.82
2591 Betaprime 5404 4 grams 0.0012 7.59 0.76 0.0 0.0 5.80
406 Brake Fluid 248,361 L 65,610.0 9.00 1.00 590,253.9 65,610.0 9.00
2503/3222 Bonnie Marlin Parts Wash 388 gal 388.0 8.50 0.25 3,298.0 388.0 2.04
18/2592 Prosat Alcohol Wipes 1,724 L 455.5 6.58 1.00 2,997.6 455.5 6.58
3215 BASF Flash Primer 850 L 224.5 12.85 0.05 2,885.4 224.5 0.64
3063 Flash Primer FU03-0101 385 KG 67.7 12.54 0.15 848.8 67.7 1.88
2387 Finesse IT Extra Fine 10 gal 10.0 8.35 0.14 83.5 10.0 1.17
2568 Glasurit 929-93 343 L 90.6 8.35 0.57 756.6 90.6 4.74
2566 Glasurit 352-91 620 L 163.7 7.28 1.00 1,191.4 163.7 7.28
2577 Glasurit 352-500 50 L 13.1 7.59 0.99 99.2 13.1 7.50
2567 Glasurit 923-109 655 L 173.0 8.26 0.47 1,428.7 173.0 3.90
828 Nalco 71D5+ 5 gal 4.9 7.00 0.58 34.0 4.9 4.17
3261 Nalco 71306 1,228 gal 1,228.0 9.00 0.27 11,052.0 1,228.0 2.45
3205 Nalco PD9604 3,844 gal 3,844.2 7.32 0.02 28,137.6 3,844.2 0.15
3442 Nalco 71309 926 gal 926.5 8.50 0.28 7,875.1 926.5 2.40
812 Nalco Pol-EZ 6500 660 gal 660.0 8.55 0.14 5,643.0 660.0 1.21
2837 Nalco 7768 200 gal 200.0 8.80 0.26 1,760.0 200.0 2.31
2498 Nalco PC-11 1,037 gal 1,037.3 10.40 0.10 10,787.6 1,037.3 1.02
2978 Biocide 2,045 gal 2,045.0 8.50 0.01 17,382.5 2,045.0 0.07
2947 Chemico 7915 3,165 gal 3,165.0 8.37 0.25 26,491.1 3,165.0 2.09
2946 Chemico 7831 2,220 gal 2,220.0 8.57 0.15 19,025.4 2,220.0 1.28
2688 Chemico 2500 88 gal 88.0 8.01 0.10 704.9 88.0 0.80
2578 Oakite 318 1,210 gal 1,210.0 6.77 1.00 8,191.7 1,210.0 6.77
1213 Sealer (Body Shop) 33,919 kg 6,404.5 11.68 0.00 74,779.5 6,404.5 0.00
2743 Sealer (Body Shop Betamate 1044-3) 0 kg 0.0 11.01 0.03 0.0 0.0 0.37
3081 BETAMATE 1041G 59,620 kg 12,506.2 10.51 0.02 131,440.1 12,506.2 0.19
574 Formic Acid 1,154 gal 1,154.5 10.10 0.95 11,660.0 1,154.5 9.60
VOCs are generated through the use of miscellaneous VOC-containing products throughout the plant, such as cleaners, polishing materials, sealers, adhesives,
and automotive fluids. The particular products and the mix in which they are used change from month to month. Miscellaneous VOC emissions are tracked
monthly. In calendar year 2016, the peak monthly VOC emissions for miscellaneous materials was 10.42 tons (December 2016) as documented in MBUSI's
monthly VOC reports. Therefore, VOC PTE from miscellaneous materials is:
Some example materials and the total amounts used in calendar year 2016 are provided below to illustrate the types of emissions included with the
Miscellaneous VOC category.
MBUSI Potential to Emit VOC
Miscellaneous VOC from Miscellaneous Material Usage
Table A-10
MBUSI PAL Renewal Application.xlsx February 2018
APPENDIX B - BASELINE ACTUAL VOC EMISSIONS
MonthVOC Emissions
1
(ton/month)
12-Month Rolling Total for
VOC Emissions (tons/yr)
Baseline Annual Actual VOC
Emissions (tons/yr)2
Jan-13 18.28 - -
Feb-13 25.20 - -
Mar-13 15.61 - -
Apr-13 22.10 - -
May-13 22.10 - -
Jun-13 22.54 - -
Jul-13 21.88 - -
Aug-13 21.28 - -
Sep-13 17.86 - -
Oct-13 19.63 - -
Nov-13 24.64 - -
Dec-13 17.08 248.21 -
Jan-14 13.94 243.87 -
Feb-14 27.47 246.14 -
Mar-14 23.85 254.38 -
Apr-14 26.86 259.13 -
May-14 20.74 257.77 -
Jun-14 24.34 259.57 -
Jul-14 28.13 265.82 -
Aug-14 38.48 283.01 -
Sep-14 36.97 302.13 -
Oct-14 38.87 321.37 -
Nov-14 25.65 322.38 -
Dec-14 30.94 336.25 292.23
Jan-15 27.89 350.20 297.03
Feb-15 30.59 353.32 299.73
Mar-15 36.27 365.74 310.06
Apr-15 35.29 374.18 316.65
May-15 30.40 383.83 320.80
Jun-15 34.66 394.15 326.86
Jul-15 38.81 404.83 335.32
Aug-15 39.48 405.83 344.42
Sep-15 35.59 404.45 353.29
Oct-15 40.78 406.36 363.86
Nov-15 30.34 411.04 366.71
Dec-15 29.06 409.16 372.70
Jan-16 32.23 413.50 381.85
Feb-16 34.65 417.55 385.44
Mar-16 34.28 415.56 390.65
Apr-16 41.25 421.52 397.85
May-16 40.24 431.36 407.60
Table B-1
MBUSI Baseline Actual Emissions
VOC Emissions from January 2013 to December 2017
MBUSI PAL Renewal Application.xlsx February 2018
MonthVOC Emissions
1
(ton/month)
12-Month Rolling Total for
VOC Emissions (tons/yr)
Baseline Annual Actual VOC
Emissions (tons/yr)2
Table B-1
MBUSI Baseline Actual Emissions
VOC Emissions from January 2013 to December 2017
Jun-16 36.24 432.94 413.55
Jul-16 28.30 422.44 413.63
Aug-16 45.44 428.40 417.12
Sep-16 38.86 431.67 418.06
Oct-16 40.77 431.66 419.01
Nov-16 39.43 440.75 425.90
Dec-16 36.08 447.77 428.46
Jan-17 31.68 447.22 430.36
Feb-17 37.23 449.80 433.68
Mar-17 37.28 452.79 434.18
Apr-17 31.68 443.22 432.37
May-17 38.86 441.84 436.60
Jun-17 26.57 432.18 432.56
Jul-17 27.69 431.57 427.00
Aug-17 42.34 428.46 428.43
Sep-17 34.52 424.13 427.90
Oct-17 34.54 417.90 424.78
Nov-17 31.26 409.73 425.24
Dec-17 27.94 401.59 424.68
1 Baseline annual actual emissions represent an annualized rolling 24-month period.
1 VOC emissions data from monthly VOC reports and annual emissions inventories previously submitted to ADEM.
MBUSI PAL Renewal Application.xlsx February 2018