    Getting a Community to embrace

    Wind Energy

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    2/20

    The Town of Falmouths Experience

    Formed Energy Committee to take stock of

    municipal energy consumption

    Joined ICLEI Cities for Climate Protection

    program

    Completed two energy inventories 5 years

    apart

    Began wind project in a climate context

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    3/20

    The Local Picture

    Many more energy dollars remain in our local economy with renewable energy and energy

    efficiency.

    For every dollar spent in the local economy, there is an economic multiplier effect of $2.50with in the region.

    We are residents of a coastal ecosystem that has a Nitrogen problem and an air quality

    problem.

    Image from EPA

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    4/20

    A Snapshot of Falmouth

    The Town of Falmouth uses 11,500,000 kilowatt hours annuallyThe 1.65 megawatt wind turbine will produce between 3.5 and4.5 million kilowatt hours annually-depending on the wind.

    Falmouth has committed to reducing its greenhouse gas emissionsand energy use by 10% by 2010.

    Wind I will reduce the amount of fossil based electricity FalmouthConsumes to 8 million kilowatt hours.

    Wind II will reduce the amount of fossil based electricity FalmouthConsumes to 4.5 million kilowatt hours.

    Each turbine will offset 2,514 metric tons of CO2

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    5/20

    How did we get support?

    Sent out surveys to neighbors letting them know we

    were thinking about a wind turbine at the WWTF Went door-to-door in the neighborhood near the

    WWTF

    Took bus trips to Hull

    Conducted many Wind 101 workshops in thecommunity

    Provided outreach at precinct meetings

    Did articles in local paper and sent letters keepingabutters informed of our progress

    Provided annual update on project at televisedselectmens meeting

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    6/20

    Education needs to come first!

    Get to your neighbors before the pressannounces the project

    Ask for their feedback, questions & concerns

    Provide factual, full disclosure education toaddress their concerns and interests

    Keep them in the loop as much as possible

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    7/20

    Avoid Others Mistakes

    Review the lessons learned from otherprojects

    Do not overlook the lessons from failed or

    delayed projects Have discussions with the stakeholders to

    find out what went wrong

    and what worked

    Whatever it is, Im against it!

    Horsefeathers, 1932

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    8/20

    Keep the Information Simple

    Be sure your sources are peer reviewed andbased on factual science.

    Be sure you ask reputable people to present

    the information.

    Remember that there are many people willing

    to support these projects in many ways.

    Peoples relationship with the issues matters alot. The more engaged and informed people

    are, the better.

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    9/20

    Choose an Ownership Model that

    Speaks to the People

    Be sure your site is viable for what you are

    proposing

    Think about things from all sides

    Take into consideration the need for the

    taxpayers to benefit from the project

    Ownership matters

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    10/20

    Our first 1.65 megawatt Vestas wind turbine

    at the wastewater treatment facility

    Photo simulationActual installation

    Credit: KEMA

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    11/20

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    12/20

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    13/20

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    14/20

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    15/20

    Why Wind over

    Photovoltaics?

    Example

    PV/Solar Wind

    Cost $3M $3M

    Output 515,088 kWh $1,892,160 kWh

    $/Watt $6.00 -$10.00 $3.00

    Annual

    Benefit $78,871 $306,769

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    16/20

    Project Summary

    Single 1.65 MW Vestas V82 wind turbine generator

    Located at Waste Water Treatment Facility BOP construction and turbine installation to be performed by

    D&C Construction selected through competitive process.

    Turbine will be owned by the Town of Falmouth

    Turbine will be a net metering generator

    O&M will be performed by 3rd party under long-term contract

    Est. annual production = 3,624 MWh ( 25% NCF)

    Useful life modeled as 20 years

    Decommissioning reserve funded via operations

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    17/20

    Keys to Projects Viability

    Wind Resource

    FAA Due Diligence

    Bridge Financing prepayment of REC contract Municipal Borrowing Unexcluded

    Long Term REC Agreements

    Net Metering

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    18/20

    Installed Cost, Avoided Cost &

    REC Revenue

    Project Cost: Turbine & Installation (winning bid): $4,332,000

    Financing costs, Nstar interconnection costs, owners engineer,reserves, other: $660,000

    Total Project Cost: $4,992,000

    Avoided Cost: Net metering generator: avoids kWh generation, transmission,transition & distribution charges. $161/MWh in year 1

    TOD- and load-weighted average of all Falmouth accounts

    Generation rates forecasted based on NYMEX; T&D based on CPI

    Revenue: REC revenue from sales to 3rd party

    For 100% of production in yrs 1-5; for 10% of production thereafter

    MTC pays in advance for 90% of RECs from years 6 through 20

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    19/20

    Falmouth WWTF

    Wind Turbine II

    Turbine I

    Turbine II

  • 8/9/2019 Megan Amsler presentation at SSC Energy Workshop 4-8-2010

    20/20

    Falmouths turbine

    is on-line!!

    People are welcome

    to come visit,

    preferably when the

    wind is

    blowingThe gates

    are open from 7:30

    am until 3:30 pmMonday-Friday.