“med programme” zeroco (2 ) zero emission communities financial management system
DESCRIPTION
“MED Programme” ZeroCo (2 ) Zero emission COmmunities Financial management system Kick Off Meeting June 17° 18° 2010 . First Level Control. When will be performed? Checks to be performed each time before submitting a payment claim in accordance with: - PowerPoint PPT PresentationTRANSCRIPT
“MED PROGRAMME”
ZEROCO(2)
ZERO EMISSION COMMUNITIES
FINANCIAL MANAGEMENT SYSTEM
KICK OFF MEETING
JUNE 17° 18° 2010
First Level ControlWhen will be performed?
Checks to be performed each time before submitting a payment claim in accordance with:
Article 16 of Regulation 1080/2006 Article 13 of Regulation 1828/2006
What will be verified?
The reality of the declared expenditure The delivery of the products and services co-financed
(as described in the approved Application Form) The soundness of the declared expenditure The compliance of such expenditure with Programme,
Community and national rules
First Level Control
Why it will be performed? Aims at checking the legality and the regularity of the
expenditures declared by each partner
What will be controlled? Covers 100% of all declared expenses
Which kind of control will be performed? Administrative verifications.
On-the-spot checks are recommended at least once during the project lifetime
National control systems Each Member State (MS):
Sets up a First Level Control system
Determines the selection mode for controllers
Each partner must refer to the control system of the Member State where it is located
Please refer to the information provided by the national bodies for more details about the procedure
Spain1. Administration that has an independent control unit for
European programmes System must be authorized by the Ministry of Economy and
Finance
2. Partners must propose an independent external controller registered in the Spanish official register of auditors
Selection through public procurement Ministry of Economy must validate the selection
In both cases, certifications must be validated by the Ministry of Economy
Only costs related to external controllers are eligible
Greece The responsible body supported by controllers
recruited for this purpose
Partners should request to be allocated a controller prior to the submission of their application No need to await the allocation to submit the proposal Once allocated, a contract will be signed by the contracting parties
Certifications to be signed by the national Authority
Costs paid by the partner and eligible
Italy
1. Public bodies Internal control office Separation of functions provided and knowledge of English/French Cost supported by the public body
2. Private bodies (or public bodies not opting out for the internal control office)
Selection through public procurement Controllers registered either in the “Albo dei Dottori Commercialisti e degli
Esperti Contabili” or in the “Registro dei Revisori Contabili” Honorability, professionalism, independence and knowledge of
English/French Costs paid by the partner and eligible
Choice of controller in both cases to be validated by the multilevel Commission State-Regions
Portugal External controller
Selection through public procurement
Eligible costs
Choice to be validated within 3 months after approval of the project
Accounting authority Familiar with Community regulations Portuguese and English Complete certification within a month following the reception
of documents
Validations issued by the controller must be confirmed by the Instituto Financeiro par o Desenvolvimento Regional (IFDR)
Expenditure reporting procedure
Step 1
The partners collect the invoices and the accounting files of the expenditure and
payments
Step 2
All partners must use the PRESAGE CTE application to enter all activities completed and expenditure made in the relevant period.
The Lead Partner controls that expenses are coherent with the initial distribution per activity and per budgetary heading
The Lead Partner ensures that the expenditure presented by the beneficiaries participating in the operation has been incurred for the purpose of implementing the operation and corresponds to the activities agreed between those beneficiaries
Step 3
Once the partner has entered in PREAGE tool all the activity and financial data related to the relevant period, it must notify it to its Lead partner for validation on PRESAGE and to its First Level Controller
The partner sends the proof of payments and the related documents and reports (activity report and financial report) to the first level control according to the national procedure which has been defined (centralized or decentralized)
Step 4The first level control returns to the partner, within 3 months maximum (art.16.2 of the Regulation CE 1080/2006) and after presentation of complete and correct documentation:
Validates the eligible expenditure, with indication of the validated amounts and the amounts possibly excluded
Generate a certificate of validation (from PRESAGE CTE)
In Spain and Portugal: certificate has to be sent to the national authority in order to get the final validation
Step 5
Once the confirmation of the expenditures has been obtained, the partner transmits it to the Lead Partner together with the copy of related forms and copy of the proofs of payment.
Step 6 The Lead Partner collects and keeps all the certifications of expenses and the
copy of supporting documents of its partners
It verifies that the expenditure presented by the beneficiaries participating in the operation has been validated by the controllers.
The Lead Partner writes a payment claim containing copies of the certifications provided by the partners as well as a report containing information on the activities corresponding to the amount of expenditures. It is sent to the Managing Authority accompanied by a progress report
If a partner can not transmit to the Lead Partner its confirmation of the expenditures in due time, it should transmit it within the following progress report
Step 7 The Managing Authority verifies that payment claims
correspond to the activities of the project specified in the Subsidy Contract signed between the Lead Partner and the Managing Authority
The Managing Authority transmits a “recommendation for payment” to the Certifying Authority within 15 working days from the reception of the payment claim. Any problem concerning the payment claim can postpone the deadline.
Step 8
The Certifying Authority controls the recommendation for payment and proceeds as soon as possible to the payment to the Lead Partner if the recommendation for payment is complete.
Step 9
From the reception of the funds, the Lead Partner must pay its partners within a period of 1 month maximum. The Lead Partner transmits to the JTS (and to the relevant National Contact Point, and/or national controllers or approbation bodies) the detail of these payments. The Lead Partner must justify in the progress report that all the payments of the former period have carried out. If not, the progress report cannot be approved.
Financial Reporting Period
ERDF € Total Eligible €
Starting report not related to payment 31st August 2010
I period of implementation
from 1st June 2010 to 31st August 2009 52.500,00 70.000,00 31st October 2010
II period of implementation
from 1stSeptember 2010 to 28thFebruary 2011 300.000,00 400.000,00 30th April 2011
III period of implementation
from 1st March 2011 to 31st August 2011 412.500,00 550.000,00 31st October 2011
IV period of implementation
from 1st September 2011 to 28th February 2012 487.500,00 650.000,00 30th April 2012
V period of implementation
from 1st March 2012 to 31st May 2012 151.060,73 201.414,31 31st July 2012
Final Report 31st October 2012
Payment claim (estimated)Progress report Time Frame Deadline for submission
of the report to the JTS
Threshold for Partner I° Reporting Period
Partner ERDF € Total Eligible
€ of the period
Total certified
Budget at the beginning of the period
Budget at the end of the
period Deadline for submission
to LP
Massa Carrara 6.750,00 9.000,00 9.000,00 339.640,00 330.640,00 30st September 2010
Kyoto Club 3.000,00 4.000,00 4.000,00 142.350,00 138.350,00 30st September 2010
Legambiente 26.250,00 35.000,00 35.000,00 282.597,00 247.597,00 30st September 2010
ANETKY 2.250,00 3.000,00 3.000,00 257.280,00 254.280,00 30st September 2010
CRES 4.500,00 6.000,00 6.000,00 186.410,00 180.410,00 30st September 2010
l’Alcúdia 2.250,00 3.000,00 3.000,00 171.880,00 168.880,00 30st September 2010
AER 4.500,00 6.000,00 6.000,00 156.280,00 150.280,00 30st September 2010
CIMAA 1.500,00 2.000,00 2.000,00 224.977,30 222.977,30 30st September 2010
AREANATejo 3.000,00 4.000,00 4.000,00 110.000,00 106.000,00 30st September 2010
Total 54.000,00 72.000,00 72.000,00 1.871.414,30 1.799.414,30 30st September 2010
I period of implementation - from 1st June 2010 to 31st August 2009
Threshold for Partner II° Reporting Period
Partner ERDF € Total Eligible
€ of the period
Total certified
Budget at the beginning of the period
Budget at the end of the
period Deadline for submission
to LP
Massa Carrara 37.500,00 50.000,00 59.000,00 330.640,00 280.640,00 31th March 2011
Kyoto Club 30.000,00 40.000,00 44.000,00 138.350,00 98.350,00 31th March 2011
Legambiente 52.500,00 70.000,00 105.000,00 247.597,00 177.597,00 31th March 2011
ANETKY 11.250,00 15.000,00 18.000,00 254.280,00 239.280,00 31th March 2011
CRES 52.500,00 70.000,00 76.000,00 180.410,00 110.410,00 31th March 2011
l’Alcúdia 11.250,00 15.000,00 18.000,00 168.880,00 153.880,00 31th March 2011
AER 52.500,00 70.000,00 76.000,00 150.280,00 80.280,00 31th March 2011
CIMAA 7.500,00 10.000,00 12.000,00 222.977,30 212.977,30 31th March 2011
AREANATejo 37.500,00 50.000,00 54.000,00 106.000,00 56.000,00 31th March 2011
Total 292.500,00 390.000,00 462.000,00 1.799.414,30 1.409.414,30 31th March 2011
II period of implementation - from 1st September 2010 to 28th February 2011
Threshold for Partner III° Reporting Period
Partner ERDF € Total Eligible
€ of the period
Total certified
Budget at the beginning of the period
Budget at the end of the
period Deadline for submission
to LP
Massa Carrara 82.500,00 110.000,00 169.000,00 280.640,00 170.640,00 30st September 2011
Kyoto Club 33.750,00 45.000,00 89.000,00 98.350,00 53.350,00 30st September 2011
Legambiente 60.000,00 80.000,00 185.000,00 177.597,00 97.597,00 30st September 2011
ANETKY 67.500,00 90.000,00 108.000,00 239.280,00 149.280,00 30st September 2011
CRES 30.000,00 40.000,00 116.000,00 110.410,00 70.410,00 30st September 2011
l’Alcúdia 45.000,00 60.000,00 78.000,00 153.880,00 93.880,00 30st September 2011
AER 22.500,00 30.000,00 106.000,00 80.280,00 50.280,00 30st September 2011
CIMAA 63.750,00 85.000,00 97.000,00 212.977,30 127.977,30 30st September 2011
AREANATejo 18.750,00 25.000,00 79.000,00 56.000,00 31.000,00 30st September 2011
Total 423.750,00 565.000,00 1.027.000,00 1.409.414,30 844.414,30 30st September 2011
III period of implementation - from 1st March 2011 to 31st August 2011
Threshold for Partner IV° Reporting Period
Partner ERDF € Total Eligible
€ of the period
Total certified
Budget at the beginning of the period
Budget at the end of the
period Deadline for submission
to LP
Massa Carrara 97.500,00 130.000,00 299.000,00 170.640,00 40.640,00 31th March 2012
Kyoto Club 33.750,00 45.000,00 134.000,00 53.350,00 8.350,00 31th March 2012
Legambiente 60.000,00 80.000,00 265.000,00 97.597,00 17.597,00 31th March 2012
ANETKY 82.500,00 110.000,00 218.000,00 149.280,00 39.280,00 31th March 2012
CRES 37.500,00 50.000,00 166.000,00 70.410,00 20.410,00 31th March 2012
l’Alcúdia 60.000,00 80.000,00 158.000,00 93.880,00 13.880,00 31th March 2012
AER 22.500,00 30.000,00 136.000,00 50.280,00 20.280,00 31th March 2012
CIMAA 78.750,00 105.000,00 202.000,00 127.977,30 22.977,30 31th March 2012
AREANATejo 18.750,00 25.000,00 104.000,00 31.000,00 6.000,00 31th March 2012
Total 491.250,00 655.000,00 1.682.000,00 844.414,30 189.414,30 31th March 2012
IV period of implementation - from 1st September 2011 to 28th February 2012
Threshold for Partner V° Reporting Period
Partner ERDF € Total Eligible
€ of the period
Total certified
Budget at the beginning of the period
Budget at the end of the
period Deadline for submission
to LP
Massa Carrara 30.480,00 40.640,00 339.640,00 40.640,00 0,00 30st June 2012
Kyoto Club 6.262,50 8.350,00 142.350,00 8.350,00 0,00 30st June 2012
Legambiente 13.197,75 17.597,00 282.597,00 17.597,00 0,00 30st June 2012
ANETKY 29.460,00 39.280,00 257.280,00 39.280,00 0,00 30st June 2012
CRES 15.307,50 20.410,00 186.410,00 20.410,00 0,00 30st June 2012
l’Alcúdia 10.410,00 13.880,00 171.880,00 13.880,00 0,00 30st June 2012
AER 15.210,00 20.280,00 156.280,00 20.280,00 0,00 30st June 2012
CIMAA 17.232,98 22.977,30 224.977,30 22.977,30 0,00 30st June 2012
AREANATejo 4.500,00 6.000,00 110.000,00 6.000,00 0,00 30st June 2012
Total 142.060,73 189.414,30 1.871.414,30 189.414,30 0,00 30st June 2012
V period of implementation - from 1st March 2012 to 31st May 2012