mechanics of project cost control
TRANSCRIPT
by H. Carl Bauman American Cyanamid Co.
COSTS A W O R K B O O K F E A T U R E
Mechanics of Project Cost Control
Control is the key to survival in a competitive society
Λ Ν Υ estimate of capital cost, no matter how painstakingly prepared, is meaningless without provisions for subsequent control of expenditures.
The exercise of adequate capital cost control starts with preliminary engineering considerations when the project is initially conceived. Physical development of the process should be based on criteria of simplicity and availability of standard materials of construction. Every profitable process is potentially subject to obsolescence by a competitor's entry into the field with improved process or method. In the high-obsolescence chemical industry particularly, conservation of design becomes a practical necessity.
It is during the preliminary engineering phase that most benefit may be had from a careful examination and review of alternatives. Should one large storage tank be used instead of two smaller ones? Are the compressors somewhat overdesigned to be sure to deliver full capacity under all circumstances? Are safety factors conservatively large? To overcome inherent extra cost resulting from a pessimistic design approach, some companies are ready to accept a process unit which performs at somewhat less than 100% of design capacity when delivered
to the operators. Experience has taught that minor alterations, improved operating efficiency, and clarification of product requirements invariably result in increased productivity after initial operation.
All steps thus taken in engineering to minimize cost are reflected in the details of the project control estimate. Responsibility for the next step in cost control passes to the purchasing department for negotiating and placing orders sufficiently within the estimate to allow for minor variances
and normal contractor's extras. From here on in, expenditures of remaining project funds are made in the field and amount to 30 to 60% of the total. Since such expenditures include all labor, construction equipment and materials, and remaining process piping, electrical, instrumentation, and insulation materials, the application of cost control centers at the job site is desirable.
Figure 1 outlines a typical field organization for a large cost-plus project, showing responsibilities in
MANAGER CONSTRUCTION COST ENG. MANAGER
ι 1
PROJECT COST ENG.
RESIDENT ENGINEER
PROJECT MANAGER
OR ENGINEER 1 1 1
FIELD COST ENO.
CONTRACTORS GEN'L SUPER.
SPECIALTY ENGINEERS WAREHOUSE
FIELD ACCOUNTING
1 I "A"
SUPER. CONSTRUCTION SUPERS.
TIME KEEPER
1 1 1 I 1
t - -| QUANTITY SURVEYOR
1
t_ Figure 1 . Outl ine of α typ ica l f ie ld organizat ion for a la rge cost-plus project shows responsibilities in cost control
I / E C Q O R K B O O K F,EJft.TT_rjR.J3]S 6 7 A
E C
I
E 3 E H 3 COSTS . A Workbook Feature
ENGINEERING
ENG. β DRAFT
HRS. DRAW.
β SPECS
ACCOUNTANTS - TIME KEEPER
EXPENDITURES
a COMMITMENTS
MAN-HOURS
QUANTITY SURVEYORS
QUANTITIES
PURCHASING
HOME OFFICE β
FIELD PURCHASE
ORDERS
WAREHOUSE
INVENTORY
DETAIL COST ANALYSIS COST PROJECTION
SUMMARY
COST REPORT
(De ta i l s Avai lab le)
TO ALL CONCERNED
Figure 2. Flow of information for cost control
the cost control function. The resident engineer or client's construction superintendent is responsible for the smooth operation of the construction organization. He reports to his company's construction manager. During the life of the job, a close liaison is maintained with the project manager or project engineer.
The field cost engineer assigned to the project is functionally responsible to the manager of cost engineering, but has a "bed and board" responsibility to the resident engineer. It is the duty of the field cost engineer working with the project cost engineer in the home office to coordinate, assist in administering, and report
periodically the status of all job costs compared with the project control estimate. To keep the price of cost control at a minimum, he draws his information from job personnel necessary to the construction effort, and limits his staff to a clerk or two, depending on job size and complexity. In a well planned organization the cost engineer depends on the job accountant, timekeeper, and construction engineers to provide, through their normal records using the job cost code, the information necessary for project control.
Figure 2 shows the flow of information for cost control. At this point it is well to reiterate the necessity for a "frozen'" project control estimate coded to a standard code of accounts. The complexity of construction makes it important to have a clearly defined description of work items, so that errors in communication can be held to a minimum. It provides the common language for quick interchange of information revealing trouble areas needing im-
-STINATE FM Τ I I I I f f - ' M M . I · : Γ ( T U
J O B E S T 1 N A T E I · : Γ ( Ç 5 M " : a u i p m e n t T U
J O B E S T 1 N A T E S h · •t ι
J o b Mo. 10OC ) Revised T« _ ~ i . ;-n-fc
S h ·
J o b Mo. 10OC ) Revised T« _ 8-7-58 J o b Mo. 10OC ) Revised T« _
L o c a t i o n U n i t e d S t a t e s L o c a t i o n U n i t e d S t a t e s
D U C K 1 r T l « N -„ M i e i t U L ESTIMATE REVISIONS TO ESTIIMTI NET CKAHCKS
i.'V'v Έ'. w u a D U C K 1 r T l « N -„ „TY H f l U M É ce-W ( τ , Ι «TV « . f t i . . . «ÏÏÎ. «V i.'V'v Έ'. w u a D U C K 1 r T l « N -„ „TY
-,·. <.·«>• H f l U M É ce-W ( τ , Ι «TV « . f t i . . . «ÏÏÎ. «V i.'V'v Έ'. w u a 10 P r o c e s s E q u i j m c n *
1 0 - 1 T a n k , r . - o r i g · ' , P I , O u . ' p u l , 1„ ' ' i i ; i χ e a . 1 - - 1 5 , 0 0 0 7 5 0 1 5 . 7 5 0 2$C 1 0 0 - ViL I X . 1 0 0 2TO "i*· - L . h o r i z o n t a l , C . ' .
- P TlUBnr S t o r a g e . Μ η ι η Γ 1 ί ; fîïîP • 2 5 ' di& χ e a - 1 _ - - _ Q.QÇC Q . 0 S 0 1 _ . û-Q-ÎG α οςη io.one Iflfl
3 L " b , V e r t i c a l C •::.
r a 1 . 9 0 0 2 0 0 1 . 1 0 0 âJ 1
' - Ί e a . 1 _ . L.00C 2 0 0 1 . 2 0 0 - 1 I 13 I
|| ι C o o l e r . A c i d , 2 5 n o . f t , C E . S h e l l . 3 0 * - 8 B e a . - • - l.Ooi 5 0 1 . 0 5 C :s 1
' I IS .( kv <«x se Q50 IS 1 ·- 1·
tectlM Tit le
Cod· t o . 1 C
D E T A I L C O S T R E P O R T
tectlM Tit le P r o c e s s Equlprr.cn*.
D E T A I L C O S T R E P O R T Sh-MJt
J o b Mo. 1000
P l a n t C h e m i c a l « , . . • a * . 1G L o c a t i o n ' J n i t e d S t a t e s Fai-ind Fndina December 3 1 - l c 5 ? P a y r o l l o f Di-cwEfc^r ^C , lcr,B
C O S T TO D A T E
C O » .
OTV
PLACE
»*rai. E S T I M A T E D C O S T TO C O M P L E T E E S T I M A T E D F I N A L C O S T • • • • " . -
ON OVEftTiMI
.«»», .... C O M M I T * ! •••Sf· C O - T . . C , T O T * c HX"I C O » .
OTV
PLACE L . » i « n »Îiî?«NT C M r u e t « . A t » . - L ..vi"*i. «Jïic, TCTAL
• • • • " . -
ON OVEftTiMI
.«»», .... C O M M I T * ! •••Sf· C O - T . . C , T O T * c HX"I C O » .
OTV
PLACE L . » i « n »Îiî?«NT
C M r u e t « . A t » . - L ..vi"*i. «Jïic, TCTAL u , » t . "" • • • • " . -
ON OVEftTiMI
.«»», .... 10 | , 2
L.I3I = = _ . S
*" — 2 i £ _ 2ûfc3â 2C4 = 7 ι
A U A: ftliO 10 1 1
-* 9 < * 1 6 ' 1 , 15? 5 * 1 o*6 i i - 1 . 1 5 9 1*1 _ . 1 2
1 i l3
1 ! η
087 2 : i l . o l l . ^6 • — " • - - • • 1
1 It 17
8*5 16 LO * 0 B*S 895 19 1»
08
Figure 3. Detailed cost report is compared with project control estimate
A INDUSTRIAL AND ENGINEERING CHEMISTRY
mediate attention. All current job progress is channeled to the field cost engineer. From the home office he receives monthly reports of engineering and drafting man-hours and dollars expended, along with a schedule of drawing and specification completion. From the job ledgers come monthly expenditures and commitments in coded detail. The timekeeper's records provide craft and nonmanual man-hour expenditures. Quantities of equipment and material in place are provided daily by the construction superintendent's quantity surveyors, take-off men, or foremen. All purchase orders placed, either at the home office or in the field, are posted currently and a continuing warehouse inventory is maintained.
Each month after the project accountant has struck a trial balance from the ledgers, the field cost engineer assembles all current information on a detailed cost report form similar to that shown in Figure 3, compared with a replica of the detailed project control estimate. At this point fact is now history and the cost engineer assumes his role as evaluator and estimator to project job costs to completion. Armed with daily reports of unit cost progress (Figure 4) for concrete, excavation, masonry, steel, piping, electrical, and others, he is prepared to predict an over- or underrun for the work items. Analysis of these reports and comparison with the original estimate turn up trouble spots for attention before they become too serious. When this occurs between monthly report periods, the item is "red-flagged" to the resident and project engineers for remedial measures. This approach is cost control at its effective best.
Philosophically, the mere existence of a cost control system is the best insurance for keeping project costs within a tight estimate. The more widely the base of cost consciousness is spread among personnel involved in the capital program, the better the possibility of consistently good cost performance. Not the least of the cost engineer's functions is to keep promoting cost awareness even in such unromantic areas as job housekeeping and construction equipment maintenance.
To be most effective, cost reports should be brief but revealing. Publishing a many-paged detailed re-
LOCATION U.S.A. JOB ORDER NO.1000
'./EEKLY LABOR COST MEMO
FOR WEEK ENDING December 20, 1958 Aluminum Piping CLASS OF '..'ORK Coded (152 &650)-506-Size V Diameter UNIT Joint (Weld and/or Screwed)
LAST WEEK
ENDING 1 2 - 1 3 - 5 8 ENDING
THIS '.ΓΕΕΚ
1 2 - 2 0 - 5 8
TO DATE
QUANTITY TOTAL UNIT COST QUANTITY TOTAL UNIT COST QUANTITY TOTAL UNIT COST
26
M. H. H . H . / U n i t
13
M. H. M . H . / U n i t
39
H. H. M . H . / U n i t
26 90 3.1*6 13 k? 3Λ6 39 135 3Λ6 26 » 5 / U n i t
13 Î 5 / U n i t
39 V S / U n i t
26
303 .50 1 1 . 6 7
13
L51-75 1 1 . 6 7
39
*55-25 I I . 6 7
REMARKS
TO DATE: ADD 0.L5 H.H. AND $ 0 Λ 7 PER UNIT FOR EQUIPMENT LABOR. TO DATE: ADD $ 0.025
PREPARED BY
PER UNIT FOR EQUIPMENT RENTAL.
Figure 4 . Reports of unit cost progress turn up trouble spots before they are serious
JOB 0PIJER IÎ0. 1000
CH2KICAL PLAOT
UNITED STATE
SCfr'-ASY COST REPORT - AS 0? DjEE-IBIK 31, J956
PfGcrlptioi
Estimated Present to Expected
Complete Cost
Present Indicated Overrun
(Underrun) vs.
Budget Author. Physical ly
Complete
Estimated Completion
Date
350
500 530
Process Equipment S i t e ^velopment Auxiliary Equipment Pipine E lec t r i ca l
261,10c 38,210 299,310 305,000 (5,690) 30,320 3,68c 3^,000 33,500 500 8,000 50C 8,500 8,700 (200)
32,700 3,20C 35,900 36,000 (100) 78.000 6.500 8U.500 82.000 2.500
^ • TOYAI. ÏETIMATE
^ 8*0,OOC 110, CC-J 950,000 962,000 (12,000; φ
Figure 5. A cost report to be effective should be br ief
port is almost a guarantee that it will not be read by the busy people to whom it is directed. The cost engineer therefore prepares a summary-cost report for distribution. This is generally a one-page document set up as shown in Figure 5. It reports expenditures and commitments, estimated costs to complete, and expected over- or underruns of the authorized budget for each important item of cost. Brief explanatory notes bring significant changes in predicted cost to the attention of those concerned. Any large inherent overrun has already been studied in detail and reported separately to the project and construction managers for immediate attention. In the event an expected overrun cannot be contained, the current summary cost report serves as the instrument for requesting additional funds to complete the project.
Properly organized, the cost control procedure should require no more paper work than needed for normal operation of the construction program. Efficient use of the written records needed for craft labor time, warehouse inventory control, and accounting purposes will also serve the cost engineer's purpose without duplicating expenditures. The returns brought by control are often handsome in terms of fixed capital dollars saved.
Our authors like to hear from readers. If you have questions or comments, or both, send them via The Editor, l/EC, 1155 16th Street N.W., Washington 6, D.C. Letters will be forwarded and answered promptly.
VOL. 51 , NO. 7 · JULY 1959 6 9 A