mechanical design of astor bunker peirone vdenim2020

31
Mario A Peirone Virtual DENIM 2020 Mechanical Design of ASTOR Bunker LABORATORIO ARGENTINO DE HACES DE NEUTRONES LAHN September 14-17, 2020 1 San Carlos de Bariloche, Argentina

Upload: others

Post on 12-Mar-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Mario A Peirone

Virtual DENIM 2020Mechanical Design of ASTOR Bunker

LABORATORIO ARGENTINODE HACES DE NEUTRONESLAHN

September 14-17, 2020 1San Carlos de Bariloche, Argentina

Contents1. Introduction to LAHN and ASTOR 2. Scope and Bunker´s function3. Design process first iteration4. Description of concepts:

a. Homogeneous material: Heavy Concrete b. Steel and Boron Polyethylene

5. Comparision of the two conceptsa. Estimated Materials and Costb. General Evaluation

September 14-17, 2020 2San Carlos de Bariloche, Argentina

ASTOR: Advanced System for TOmography and Radiography

It is the neutron imaging instrument under developmentfor the LAHN project.

1. Introduction to ASTOR

September 14-17, 2020 3San Carlos de Bariloche, Argentina

Its main function is to guarantee a dose of less than 3µSv/h in the reactor hall2. The Bunker’s function

Flux (n/cm2.s)for Min. collimation position• Cold 3.7 e8• Thermal 1.4 e8• Epithermal 4.3 e7• Fast 5.2 e6

SCOPEIntroduce, in the context of ASTOR's mechanical design, the approach being taken to make a comprehensive evaluation of possible shielding materials to be used for the ASTOR Bunker

September 14-17, 2020 4San Carlos de Bariloche, Argentina

1st Concept generation• Steel blocks filled with

shielding material• Wall thickness considered:

750mm• Roof thickness considered:

550mm

Radiologial shieldingdesign of ASTOR. Feedback: Estimationof required thicknessesfor different shieldingmaterials

Work in progress: exploring 2 differentsolutions. • Multilayered walls• Steel blocks filled with

homogeneous shieldingmaterials

3.Design process first iteration

• Two Rooms• Collimator and Secondary Shutter embedded• Beam stop embedded• Blocks: Metallic blocks filled with shielding material• Lateral opening doors

INTERNAL DIMENSIONS

• 3.6m wide• 17m long• Beam Conformation

room 2.5m high• Experimental room

3.7m high

September 14-17, 2020 5San Carlos de Bariloche, Argentina

1st Concept generation• Steel blocks filled with

shielding material• Wall thickness considered:

750mm• Roof thickness considered:

550mm

Radiologial shieldingdesign of ASTOR. Feedback: Estimationof required thicknessesfor different shieldingmaterials

Work in progress: exploring 2 differentsolutions. • Multilayered walls• Steel blocks filled with

homogeneous shieldingmaterials

3.Design process first iteration

1st Concept generation• Steel blocks filled with

shielding material• Wall thickness considered:

750mm• Roof thickness considered:

550mm

Radiologial shieldingdesign of ASTOR. Feedback: Estimationof required thicknessesfor different shieldingmaterials

Work in progress: exploring 2 differentsolutions. • Multilayered walls• Steel blocks filled with

homogeneous shieldingmaterials

3.Design process first iteration

• 20ton Polar Crane capacity• Polar crane reach• Building roof is 5.9m high• 20ton/m2 maximum load on

the floor• A Bunker that can be

assembled and disassembled at any time

• Length of Bunker

Some design constraints:

September 14-17, 2020 7San Carlos de Bariloche, Argentina

A) Description of the Heavy Concrete concept:

B) Description of Steel and Polyethylene concept

Aspects used for concepts evaluation :

• The least number of type of blocks• Estimated Cost. The bunker cost should not be greater than 55% of the

budget of the instrument.• Wall thickness required• Ease of construction• Ease of assembly • Achieved tolerances in the blocks dimensions

September 14-17, 2020 8San Carlos de Bariloche, Argentina

• The interior dimensions • 20tons/m2 maximum load

on the floor• A Bunker that can be

assembled and disassembled at any time

• Avoid any free path for neutrons and radiation in the gaps between blocks

• The shielding material is heavy concrete 3400kg/m3

• The thickness is 980mm

Design requirements:

4.a Description of the Heavy Concrete concept

September 14-17, 2020 9San Carlos de Bariloche, Argentina

• Divide the Bunker into an internal and an external part.

• The internal part is 573mm thick and the external part is 413mm thick

• Most of the blocks are rectangular.

Strategy:

4.a Description of the Heavy Concrete concept

September 14-17, 2020 10San Carlos de Bariloche, Argentina

• A frame of UPN profiles

Strategy:

4.a Description of the Heavy Concrete concept

September 14-17, 2020 11San Carlos de Bariloche, Argentina

• The block is finished with L profile beams and steel sheets.

• It is built in halves that are joined and then the concrete is poured.• 4 threaded bars are welded in the top, these are the lifting points.

Strategy:

4.a Description of the Heavy Concrete concept

September 14-17, 2020 12San Carlos de Bariloche, Argentina

• Most of the panels are rectangular but some of

the panels on the roof are not rectangular and some of the panels on the wall are angled

Strategy:

4.a Description of the Heavy Concrete concept

September 14-17, 2020 13San Carlos de Bariloche, Argentina

• Wall thickness achieved: 400+560+4x6.35=985,5mmStrategy:

4.a Description of the Heavy Concrete concept

September 14-17, 2020 14San Carlos de Bariloche, Argentina

• Panels can be joined by using a beam, also built with UPN profiles and

filled with heavy concrete.

Strategy:

4.a Description of the Heavy Concrete concept

September 14-17, 2020 15San Carlos de Bariloche, Argentina

• Assembly of the inner part of the Bunker

Strategy:

4.a Description of the Heavy Concrete concept

September 14-17, 2020 16San Carlos de Bariloche, Argentina

Strategy:• Assembly of the inner part of the Bunker

4.a Description of the Heavy Concrete concept

September 14-17, 2020 17San Carlos de Bariloche, Argentina

• Design criteria: Avoid free path

Strategy:

4.a Description of the Heavy Concrete concept

September 14-17, 2020 18San Carlos de Bariloche, Argentina

• The interior dimensions • 20tons/m2 maximum load

on the floor• A Bunker that can be

assembled and disassembled at any time

• Avoid any free path for neutrons and radiation in the gaps between blocks

• The shielding material is a mixture of 80% of steel and 20% of borated polyethylene

• The thickness is 580mm

Design criteria:

4.b Description of the Steel and Boron-Polyethylemeconcept

September 14-17, 2020 19San Carlos de Bariloche, Argentina

• Divide the Bunker into an internal and an external part with the same thickness.

• Most of the blocks are rectangular.

Strategy:

4.b Description of the Steel and Boron-Polyethylemeconcept

September 14-17, 2020 20San Carlos de Bariloche, Argentina

• The panels sandwiches are made of ¼’’ rectangular steel plates and

25mm thick boron-polyethylene plates.• 3 groups of 12 steel plates and 2 layers of polyethylene in one panel.

5. Description of the Steel and Boron-Polyethylemeconcept

Strategy:

September 14-17, 2020 21San Carlos de Bariloche, Argentina

• 2 sandwiches in the wall, the thickness achieved is

582mm with a 78.5% of steel

5. Description of the Steel and Boron-Polyethylemeconcept

Strategy:

September 14-17, 2020 22San Carlos de Bariloche, Argentina

• Most of the panels are rectangular but some of the roof panels are not

rectangular and some of the wall panels have sheets of different dimensions.

5. Description of the Steel and Boron-Polyethylemeconcept

Strategy:

September 14-17, 2020 23San Carlos de Bariloche, Argentina

• Assembly: The Bunker is divided

into 5 parts

5. Description of the Steel and Boron-Polyethylemeconcept

Strategy:

September 14-17, 2020 24San Carlos de Bariloche, Argentina

• Assembly: The Bunker is

divided into 5 parts

Strategy:

4.b Description of the Steel and Boron-Polyethylemeconcept

September 14-17, 2020 25San Carlos de Bariloche, Argentina

• Design constrain: Avoid free path

Strategy:

4.b Description of the Steel and Boron-Polyethylemeconcept

September 14-17, 2020 26San Carlos de Bariloche, Argentina

• 355 UPN200 beams x6m

• 90 UPN160 beams x6m

• 200 L profile beams x6m

• 100 steel sheets 1.5m x3m x6.35mm

• 45m of round bars of 60mm and 80mm

• 320 screws DIN912 M30 x175mm

• 320 washers M30

• 180m3 of heavy concrete

• 3600 steel sheets 1.5m x3m x6.35mm

• 1100 boron-polyethylene plates

• 1000 threaded bars M30 x300mm

• 2000 nuts and washers M30

NOTE: An internal steel structure is needed to

support the roof, which is not included here.

Heavy concrete Steel and Ployethylene

5.Comparision of the two concepts-

Estimated Materials and Costs

• 180 m3 of heavy concrete @ 250 US$/m3

US$ 46,000

• 70 tons of steel @ 3 US$/kg

US$ 210,000

• Total estimated cost

US$ 256,000

• 800 tons of steel @ 3 US$/kg

US$ 2,400,000

• 25 tons of boron-polyethylene @ 20 US$/kg

US$ 500,000

• Total cost of material

US$ 2,900,000

September 14-17, 2020 27San Carlos de Bariloche, Argentina

Steel blocks filled withshielding material

Multilayered: Steel andBorated Polyethylen

Least number of types ofblocks

Wall Thickness required

Estimated cost. (Limit1.925MU$S)

Ease of construction

Ease of assembly

Achieved tolerances

Better WorseSimilar

September 14-17, 2020 28San Carlos de Bariloche, Argentina

• Both concepts are feasible in terms of manufacture

• Heavy Concrete concept seems to be much less expensive. • Although Steel and borated polyethylene would exceed the budget allocated

for the bunker, some hybrid solutions may still be considered. a) Using steel and borated polyethylene only in some placesb) Considering different thicknesses in some places

Conclusion

September 14-17, 2020 29San Carlos de Bariloche, Argentina

On behalf of the LAHN team

Thanks for your attention...

September 14-17, 2020 30San Carlos de Bariloche, Argentina

Questions ???

September 14-17, 2020 31San Carlos de Bariloche, Argentina