measurement beng. 010-1

56
1 MEASUREMENT OF BUILDINGS AND CIVIL WORKS (CEQ 216)

Upload: richard-westony

Post on 07-Aug-2015

94 views

Category:

Documents


18 download

TRANSCRIPT

Page 1: Measurement Beng. 010-1

1

MEASUREMENT

OF

BUILDINGS

AND

CIVIL WORKS (CEQ 216)

Page 2: Measurement Beng. 010-1

2

COURSE OUTLINE

Measuring the quantities of building works and the use of SMM (BW)

Measurement of Building services and the use of SMM (BW)

Measurement of Civil Works the use of CESMM

Preparation of bills of quantities

Importance, requirements, definition and pricing preliminaries

Integrated Method of Assessment

Written examination, Course work and Assignment

Continuous Assessment Components 40%

Final Examination 60%

1. Two Assignments

2. Two Tests

3. End Semester Examination

References

1. Seeley I. (1993), Quantity surveying, Mac Millan Education Ltd London

2. N.A. Shah (1988), Quantity Surveying & Valuation, Khanna Publishers. Delhi

3. Seeley. I (1974) Building Quantities explained, Macmillan Press Ltd. Great

Britain,

4. Drawings of different structures.

5. SMM for building works

Page 3: Measurement Beng. 010-1

3

INTRODUCTION When a person wants to build a house, he goes to an Architect or a Consulting

Engineer and places his requirements before him. After the Architect prepares the

plans to the owner‟s requirements, the owner‟s question is, as to what the house will

cost. If one wants to find out exactly what a house will cost, he has to take out the

quantities of the different items of construction involved in the house, and then,

assuming suitable market rates he has to arrive at the cost of the proposed house. The

subject of taking out the quantities, assuming suitable rates and working out the costs

of a house or any other civil engineering structure, is known as quantity surveying. This

Module will deal with one part of taking out the quantities of the different items of

construction involved in the house and other civil engineering works assuming that

other jobs (preparation of drawings and assuming suitable rates and working out the

costs have already done or will be done by the concerned parties.

Page 4: Measurement Beng. 010-1

4

CIVIL ENGINEERING WORKS AND BUILDING WORKS Civil Engineering Works Vs Building Works There are two separate and distinct practice of measurement operating for civil

engineering works and building works such as:-

(i) Building works are generally measured in accordance with Standard Method

of Measurement (SMM) FOR East Africa

(ii) Civil Engineering works are generally measured in accordance with Civil

Engineering Method of Measurement (CESMM)

Methods of measurement in Civil Engineering Works and Building Works.

The comparisons between the two types of works that necessitate different method of

measurement are as follows:-

(i) Details in measurement

The details of building works are usually in a far more precise stage at

the time of preparation of Bills of Quantities than in the case of Civil

Engineering works.

Building works cover more trade/works sections and in consequence

subject to more detailed measurement. Much large number of items

has to be measured separately with various labors and other

incidental works itemized but this is not in civil engineering works, e.g.

in building works, backfilling trenches, leveling and compacting bottom

trench can each be measured separately, whereas in civil works, most

of these items are included in excavation rates. In Civil Engineering

works, one big item is deemed to include different other smaller items.

Page 5: Measurement Beng. 010-1

5

(ii) Small rates

Some rates in building works are very small as a result of small items

measured separately.

(iii) Risk in pricing

There is a greater risk in pricing civil works than building works due to the

uncertainty nature of the works involved.

(iv) Variations

In building works, no much variations since almost all the items can be

measured with certainty. In the absence of variations in design most

building works with the exception of sub-structure, drainage and external

works will not be subject to re-measurements and the contractor will be

paid for the quantities incorporated in the Bills of Quantities.

(v) Bills of Quantities

Building work Bills of Quantities full describes and accurately represents

the works to be executes. If this cannot be achieved the works is described

as provisional or given a bill of approximate quantities. In the Introduction to

BW – SMM state that more detailed information than is demanded in the

documents should be given where necessary in order to define the precise

nature and extent of the required. CE BOQ – a list of items giving brief

identifying description and estimated quantities of the woks comprised in

contract.

In building contracts the specification is not a contract documents hence

the BOQ in building works is lengthier and more detailed than CE BOQ as

it contained the specification / preamble.

(vi) Mixed types of works

In some larger civil engineering contracts, there are also some building

works, take for example a large Power Station contract. The best

procedure would appear to measure the main superstructure, the

Page 6: Measurement Beng. 010-1

6

supplementary buildings and probably the chimneys in accordance with the

SMM for building works. The reminder of the power station comprising

heavy foundation of piling, cooling towers, roads, sewers etc. are best

measured in accordance with CESMM.

(vii) Administration.

The structure of the team concerned with the construction of a civil

engineering project is similar to that for building works. In Civil engineering

works, the head of construction team is an engineer assisted by Resident

engineer while for buildings is an Architect assisted by the clerks of works.

Page 7: Measurement Beng. 010-1

7

MEASUREMENT OF BUILDING WORKS

HISTORICAL BACKGROUND Measurement of building works is also known as quantity surveying. According to the

records available, the earliest quantity surveying firm to operate was in 1785 in the

United Kingdom (UK). In 1802, a number of Scottish quantity surveyors met and

produced the first method of measurement. Up to the middle of 19th century it was the

practice to measure and value the building work after it had been completed.

The architect was responsible for the creation of buildings as well as their design, and

he/she employed a number of master craftsmen who performed the work in each trade.

On completion each master craftsmen submitted an account for the materials used and

labor employed on the work.

The need of quantity surveyors became obvious for the following reasons:-

(i) Building work increased in volume.

(ii) Building owners became dissatisfied with the method adopted for settling the

costs of the work.

(iii) Some craftsmen were not conversant on the preparation of these cost

accounts and hence they engaged surveyors or measurers.

(iv) There were problems on making reconciling the amount of materials listed on

invoices with the measured quantity on the completed job.

(v) Some of the craftsmen made extravagant claims for the waste of material on

being worked on the site.

Due to the above reasons, general contractors became established during the period of

the industrial revolution and they submitted inclusive estimates covering the work of all

trade. Furthermore, they engaged surveyors to prepare bills of quantities on which their

estimates were based.

Page 8: Measurement Beng. 010-1

8

As competitive tendering became more common the general contractors began to

combine to appoint a single surveyor to prepare a bill of quantities, which all the

contractors priced.

In addition, the architect on behalf of the building owner usually appointed a second

surveyor, who collaborated with the surveyor for the contractors in preparing the bill of

quantities, which was used for tendering purposes.

In later years, it became the practice to employ one surveyor only who prepared an

accurate bill of quantities and measured any variation that arose during the progress of

the job. This was the origin of the independent and unbiased quantity surveyor as he

operates today.

COMMON TERMS:-

1. Standard Method of Measurement (SMM) - This is document which provides a

Uniform basis for measuring building works and it represent the essentials of

good practice. It provides the rules of measuring all items in building works. Also

provides the units of items such as cubic, square, linear etc.

2. Taking off – measuring of quantities in which the dimensions are scaled or read

from drawings and entered in a recognized form or specially ruled paper, called

“dimension paper”.

3. Quantities – refers to the estimated amounts of labour and materials required in

the execution of the various items of the work and together these items give the

total requirements of the building contract.

4. Contractor – Is a person or corporate body whose bid to carry out the works

has been accepted by the employer and eventually engaged to undertake the

works.

5. Employer - Is the party who employs the contractor to carry out the works.

Page 9: Measurement Beng. 010-1

9

6. Provisional Sums – works which cannot be measure accurately during taking

off. It is a sum provided for work or for costs which cannot be entirely foreseen,,

defined or detailed at the time tendering documents are issued. Examples are

such as testing of materials, progress photographs and contingencies. The sum

is to be used under instruction.

7. Prime Cost Sum (P.C) – Cost for works provided by nominated sub contractors

for example, electrical installations, telephone installation, lifts installation etc.

Since this is a specialist work carried out by persons other than the general

contractors provision is to be made for profit to the general contractor and for

attendance.

8. Preliminaries - items in the bill of quantities entered for the purpose of setting

out all general liabilities and obligations of the contractor. These are items

required to be executed pre-commencement of the actual required work, during

the work and after the work completion.

9. Variations- the alterations or modifications of the design, quality or quantity of

works as shown upon the contract drawings and described by or referred to in

the contract bills. This includes the additions, omissions or substitution of any

work or the alteration of the type of standard or any materials.

10. Preambles – able clauses inserted at the head of each work section bill

covering matters relating to the specific work section that should be brought to

the attention of the estimator as they will affect the rates that he inserts against

billed items of measured work.

11. Bills of quantities – a fully described and accurately representation of the

works to be executed. Bills of quantities consist of preliminaries, prime cost

sums, provisional sums and measured works.

12. Ditto/do: that which has been said before/above.

Page 10: Measurement Beng. 010-1

10

MEASUREMENT PROCEDURES In any measurement there are a number of essential factors that should always be

considered and applied to follow good established practice as follow:-

1. Examine the drawing carefully to become familiar with the work and to identify

any parts where information is lacking.

2. Interpret carefully and apply in a sound and logical way of provisions in Standard

Method of Measurement of building works. (SMM).

3. Ensure a high standard of accuracy in dimensions.

4. Make full use of sub-headings throughout the dimensions to facilitate

identification and waste to preliminary calculations, explanatory notes and

location description.

5. All descriptions should be adequate, concise and written in a logical and easily

understood format following the sequence adopted in SMM.

6. Adopt a logical sequence of items so that each one following the preceding one

in a natural progression.

7. Seek to achieve a good standard of presentation.

Page 11: Measurement Beng. 010-1

11

GENERAL PRINCIPLES OF TAKING – OFF

1. General rules:-

Bills of quantities shall fully describe and accurately represent the works

to be executed. The billed description is to be comprehensive and

sufficient to enable the estimator to fully understand what is required and

to give a realistic price. Those works whose extent cannot be

determined with reasonable degree of accuracy should be described as

“Provisional”.

Works are to be measured net as fixed in position each measurement are

to be taken to the nearest 10mm i.e > 5mm regarded as 10mm while <

5mm are disregarded.

Openings under the measured area shall be deducted.

The order of stating dimensions in descriptions shall be consistent and

generally in the sequence of length, width and height.

Billed items are generally “deemed to include” i.e. without the need for

specific mention of labour; materials unloading, storing handling, fixing,

use of plant, waste of materials, square cutting, establishment charges

and profit – it is essential that the estimator is fully aware of all these

items as he must include for them when building up unit rates.

Work under water shall be so described stating where canal, river or sea water and the levels of high and low water.

Work in compressed air shall be so described.

2. Dimension paper:

Measured items, scaled or taken from drawings are entered on a special paper

known as „dimension paper‟. This dimension sheet is split into two identically

ruled parts each consisting of four columns as follows:-

1

2

3

4

1

2

3

4

Page 12: Measurement Beng. 010-1

12

Key: Column 1 – “Timesing column” Multiplying figures are entered when there

is more than one of the particular items being measured.

3/ 5.00

This means that the length of 5.00m of the same item appears three times in the measured drawing

Column 2 – “dimension column”. Actual dimension as scaled or taken direct

from the drawing are entered here.

5.00

The length 5.00m is in “dimension column”.

Column 3 - “Squaring column”. The length, area or volume obtained by

multiplying the figures in columns 1 & 2 is recorded.

3/ 5.00 15.00

15.00m is in Squaring column”. This is the result of multiplying column 1 and 2

Column 4 – “Description column”. In which the right description of each

item is entered. Also, the right hand side of this column is used

to accommodate preliminary calculations and other important

information.

3/

5.00

15.00

3.00 1.50 0.50 5.00 Hor. Dpc. 110mm wide of single layer of Hessian base bit. to B.S. 743 Lapped 100mm at jts and bedded in c.m (1:3)

Hor. Dpc……………….. are in “Description column”.

Page 13: Measurement Beng. 010-1

13

1. Entering of Dimensions:- (a) Order of Dimensions- For convenience a constant order of entering

dimensions should be maintained throughout i.e (i) length, (ii) breath or width,

(iii) depth or height.

For example: Concrete item is measured in cubic meter. Say concrete with 10m

long, 690mm wide and 230 deep will be entered as follows:-

10.00 0.69 0.23

Conc. Grade 20 in foundations

(b) Spacing of items - It is essential that ample space is left between all items

on the dimension sheets so that it is possible to enable any items which may

have been omitted when the dimensions were first taken off to be

subsequently inserted without cramping the dimension disproportionately.

10.00 0.69 0.23

4.00 0.69 0.23

Conc. Grade 20 in foundations

(c) Waste - The right hand side of the description column is used for

preliminary calculations, built up lengths, explanation notes, location of

measured work etc. This should not be overlooked. All steps that have been

taken in arriving at dimensions, no matter how elementary or trivial they may

appear should be entered in the waste section.

(d) Timesing – If there were five such items, then this dimension would be

multiplied by five in the timesing column:-

5/ 10.00 0.69 0.23

7.94

Conc. Grade 20

in beds

Page 14: Measurement Beng. 010-1

14

(e) Grouping of Dimensions

(i) Where the same dimension applies to more than one item the best

procedure is to segregate each of the separate description by & sign and to

bracket the descriptions.

100.00 50.00

Site clearance by removing up bushes, shrubs and the like including grubbing up their roots & Exc. O`site av. 150m deep to remove all veg. matter wheel 20m then spread and level.

20.00 18.00

100 mm thick bed of conc. (1:2:4/20 mm apg) laid on ashes (m/s)

& 50m thick bed of ashes laid and consolidated to rec. cons. bed incl. levllg and compactg grd.under

(ii) Where more than one set of dimensions relate to the same

description, the dimensions should be suitably bracketed.

25.00 3.50 17.00 3.50 15.00 3.50 10.00 3.50

21.10 20.30 15.10 12.50 18.75 10.00

230 mm bwk laid &

jtd in c.m (1.3)

Exc o’site av.

150mm db to

revome all

veg. matter

wheel 20m

then s &l

Page 15: Measurement Beng. 010-1

15

(f) Abbreviations

Abbreviations are used in the description space in order to save space and time.

There are standard and acceptable abbreviations used in measurement such as

follows:-

conc. - Concrete a.b - as before a.b.d - as before described n.e - not exceeding bldg - building B.S - British Standard Bwk - Blockwork Ddt - Deduct

b & j - bed and joint bott. - Bottom (g) Deductions

After measuring an item of construction it is sometimes necessary to deduct for

voids or opening in the main area or volume.

When measuring areas of excavation, concrete oversite, blockwork etc the best

practice is to measure the full area in the first instance and, subsequently adjust

for any voids or openings. e.g Adjustment for blockwork are done when “taking

off the windows & door openings.

21.30 20.30

5.00 4.50 2.00 2.00

Exc. o`site av. 150m dp to remove all veg. matter wheel 20m then S & L

Ddt ditto

Note: underline the word Ddt

3/ 2.10

0.90

Ddt: solid bllockwall

Page 16: Measurement Beng. 010-1

16

2. Measurement of Irregular figures It is often necessary to measure the areas of triangles and circles, the

circumferences of circles and volumes of cylinders, etc., and the usual method

of entering the dimensions is illustrated in the following examples:

½/ 22 7 ½ /2/ 22

7

22 7

4.00 3.00

2.00 2.00

2.00

0.50 0.50 3.00

3. Alterations to dimensions

It is sometimes necessary to substitute amended dimensions in place of those

which have already been entered on the dimension paper. It is advised never to

alter the original figures, as apart from looking most untidy it is often extremely

difficult to read between the lines the correct figures. If it is necessary to amend

figures the better procedure is to cross out the original figures and neatly write

the new figures above them.

Where it is required to omit dimensions which have previously been recorded

the easiest method is to write the word “nil” in the squaring column as shown in

the following example.

Area of triangle with a base of

4m and a height of 3m

(area=½base x height)

Area of circle with 2 m radius

(area = πr2)

Circumference of semi-circle

with 2 m radius (circumference

of whole circle = 2πr) Volume of cylinder, 1 m

diameter and 3 m high.

(area of circle x height of

cylinder)

Page 17: Measurement Beng. 010-1

17

23.50 0.75 0.80

8.20 0.75 0.80

|

Nil

|

Exc. fdn. tr. n.e. 1.50m dp.comm.at stripd.level

&

Backfill exc. mat. ard. fdns

4. Figured Dimensions

When taking-off it is most desirable to use figured dimensions on the drawing in

preference to scaling, as the drawing are almost invariably in the form of prints,

which are not always true-to-scale. It is sometimes necessary to build-up overall

dimensions from a series of figured dimensions and this work is best set down in

“waste” on the right-hand site of the description column.

5. Number & titles of dimension Sheets

a. Sheets should be suitably headed with the title and section of the job at

the top and numbered at the bottom. Example Drawing 10, doors section

can be seen as below.

CONSTRUCTION OF PHYSCIS LABORATORY –Drwgs,,,,,,,,,,,,,,,,,,,,,,,,,

.

Site Clearance

1.1

.

Doors

10.1

b. At the top of the first dimension sheet for a job, it is good practice to enter

a list of the drawings from which the measurements have been taken with

the precise drawing number of each contract drawing carefully recorded.

Page 18: Measurement Beng. 010-1

18

6. Order or “Taking – off”

The order of “taking off mostly follows the order of construction. In simple

building the order of taking off would probably be as follows:-

a. Site clearance

b. Foundations

c. Blockwork

d. Floors

e. Roof

f. Finishing (Plaster, ceiling & floors )

g. Windows

h. Doors

i. Fittings

j. Plumbing installation

k. Drainage work

l. Other services (electrical etc)

m. External works (roads, paths, fences and grassed areas)

7. Descriptions

a. General requirements – description must abide with or cover all matters

detailed in the SMM and include all information which the estimator will

require to build-up a realistic price for the item in question.

b. Order of wording – the first few words of a description should clearly

indicate the nature of the item being described.

c. Number of units – in some cases it necessary to give the number of units

involved in a superficial or linear item, in order that the estimator can

determine the average area or length of unit being priced.

4/

20.00 3.00

230mm Thick c&s solid blockwall ……...

excavations

concrete footing

blockwork

hard core

Concrete bed

cover bed

Page 19: Measurement Beng. 010-1

19

8. Query Sheet

When “taking – off” any doubt/queries will be forwarded to the architect on

query sheets normally divided down the centre to accommodate the queries on

the left-hand side and the answers on the right hand side. During examinations

the candidate will have to decide the queries as they arise, but it will often be

desirable for him/her to indicate briefly in “waste” why the has adopted a

certain cause of action.

QUERY SHEET

S/N QUERY ANSWER

Page 20: Measurement Beng. 010-1

20

SUBSTRUCTURES

The Substructure of any building is a base or the underneath or the foundations of that

building. Building construction can be divided into two faces namely,- the Substructure

and the Superstructure. The constructions after the foundations are of the

Superstructure.

MEASUREMENT OF EXCAVATION & FOUNDATIONS

It is very important to that the „taking off‟ process is done in logical order. This simplifies

the process and reduces the risk of omission of items.

A. EXCAVATIONS

In a small building, a satisfactory order of items would be as follows:-

1. Site clearance/site preparation this will include:-

(i) Site preparation generally including anti-termite treatment if any. This is

given in square meters.

(ii) Excavating vegetable soil - This normally forms the first item in the

„Excavation‟ section of the Bill. The area is measured in square meters to

the extremities of the foundations and the average depth, often 150mm, is

included in the description together with the method of disposal on the

site.

15.00 12.00

Exc. veg. soil, av.150mm dp. & dep. on site in spoil heaps, av. 20 m from excavn

(iii) Removing trees and hedges SMM D4

(iii)(a) Cutting down trees and grubbing up their roots shall be enumerated in

groups stating their girth starting with 600mm. girth and in further

stages of 300mm.

10

Cutting down small trees n.e 600mm girth and grubbing up their roots

Page 21: Measurement Beng. 010-1

21

(iii)(b) Cutting down hedges and grubbing up their roots shall be given in

linear meters stating the nature and height of each hedge or its location.

15.00

Cutting down Michongoma hedges and grubbing up their roots.

(iii)(c) Clearing site of bushes, scrub, undergrowth and the like and grubbing

up their roots shall be given in square meters or hectares.

15.00 12.00

Clearing site of bushes, scrub, undergrowth and the like and grubbing up their roots.

2. Excavation and Earthworks:- SMM D5 – D15

(i) Excavation to reduce levels - Where the site is sloping and further

excavation is required to reduce the level of the ground down to the specified

formation level, this excavation is measured as surface excavation in square

meters when not exceeding 300mm in depth, otherwise in cubic meters.

Measurement of Earthwork

The following is an example of measuring the volume of earthworks on

sloping sites:

It is frequently difficulty in measuring the volume of earthworks, particularly

on sloping sites. The following examples are designed to indicate the main

principles involved and generally clarity the method of approach.

Sloping site excavation

Page 22: Measurement Beng. 010-1

22

The quantity surveyor is often called upon to calculate the volume of

excavation and /or fill requirement on a sloping site and the following

example indicates a comparatively simple method of approach.

12m

12m

Assuming that in the example illustrated above, it is required to excavate

down to a level of 2.00m, including excavating vegetable soil to a depth of

150 mm. In this case the whole of the site is to be excavated.

The average depth of excavation over the site is most conveniently found by

suitably weighting the depth at each point on the grid of levels, according to

the area that each level affects. This involves taking the depths at the

extreme corners of the area once, intermediate points on the boundary twice

and all other intermediate points four times. The sum of the weighted depths

is divided by the total number of weightings (number of squares x 4) to give

the average weighted depth for the whole area. This method can only be

used when the levels are spaced the same distance apart in both directions.

2.500 3.000

2.750 3.000 3.250 3.500

3.500

3.750 4.000

r

r

Page 23: Measurement Beng. 010-1

23

The volume in this example is now calculated:

Corner depths 2.50-2.00= 0.50 3.00-2.00= 1.00 4.00-2.00= 2.00 3.50-2.00= 1.50 Depths at intermediate 2.75-2.00=0.75x2= 1.50 point on boundary 3.00-200=1.00x2= 2.00 3.50-200=1.50x2= 3.00 3.75-200=1.75x2= 3.50 Depth at centre point 3.25-2.00=1.25x4= 5.00

Sum of weighted depths 16) 20.00 Average total depth 1.25

less vegetable soil 0.15 average adjusted depth 1.10m

The dimensions would then appear as follows:

12.00 12.00 12.00 12.00 1.10

Exc. veg. soil, av.150mm dp. & dep. on site in spoil heaps, av. 20 m from excavn Exc. surf. to red. levels.

& Remove from site

(ii) Excavation of foundation trenches – Foundation trench excavation is

measured in cubic meters in 1.50m stages of depth, stating the starting

level of excavation, which is usually stripped level. For example for

foundation trench 2m deep below the stripped level will have to be split in

two sections:-

(1) Not exceeding 1.50m deep, and (2) Exceeding 1.50m deep and not

exceeding 3.00m deep. It is advisable to separate the trenches to

external and internal walls.

Page 24: Measurement Beng. 010-1

24

Excavation in rock and in silt or running sand shall be given in cubic

meters as extra over all kind of excavations irrespective of the depth.

These are to be separated from normal excavations because they have

different cost implication during pricing.

Example: Excavation of foundation trenches

22.50 0.75 1.50 22.50 0.75 0.50

Exc. fdn. tr. n.e 1.5m. dp starting at stripped lev.

& Backfill exc. mtls. ard. Fdns Ditto .exc/over 1.5m. dp

but n.e 3.0m dp starting at stripped lev.

& Backfill exc mtls. ard. fdns

22.50 0.75 1.00 22.50 0.75 1.00

Extra over exc. in rock & Backfill exc. mtls. ard. Fdns Extra over exc. in running silt & Backfill exc mtls. ard. Fdns

Girth of Buildings e.g Rectangular buildings

Girth is a perimeter of a building. This length is required for foundations, external walls

etc. also it is a base to calculate dimensions for trench excavation, planking and

strutting, concrete in foundations, blockwork and damp proof course.

Example

10.00m

20.00m

Say 230mm wall

Page 25: Measurement Beng. 010-1

25

59.08 0.70 1.20

Girth l = 20.00 w = 10.00 sum of l & w 2/30.00 sum of all for sides – 60.00 less corners 4/230 - 0.92 girth of bldg 59.08

Fdn depth – 1.20m Fdn width – 700mm

Exc. fdn. tr. n.e 1.5m. dp starting at stripped lev.

& Backfill exc. mtls. ard. Fdns

Working space allowances. D5 (f)

Note: The working space is required if the face requires formwork. All

reinforced insitu concrete require formwork hence working space should be

provided.

For insitu plain concrete footing, concrete is poured against the sides of

trenches hence no working space is required.

(a) Working space of 0.30 from the face work requiring the formwork not

exceeding 1m high

(b) 2m for trenches to receive post tensioned concrete ground beams

(c) 1m for work which is over 1m high from below the starting level of

excavation

Page 26: Measurement Beng. 010-1

26

formwork

690mm

Width of foundation trench = 0.69

Add working space allowance = 2/0.30 0.60

Total width 1 .29

(iii) Excavation of pits for column bases (if any)

Excavating pits to receive columns, isolated piers and the like are given in

cubic meters stating the starting level and the depth. Allowances for

working space are to be considered depending on the depth of pits and

the formwork requirements.

For example, a column of 1.50m height and 1.00m base can be recorded

as follows:-

3.00 3.00 1.50

Exc. column pit. n.e

1.5m. dp starting at stripped lev.

& Backfill exc. mtls. ard. Fdns

Page 27: Measurement Beng. 010-1

27

3. Disposal of excavated materials

(a) Disposal of excavated materials – Except in case of vegetable soil, the

subsequent disposal of the excavated material forms a separate billed item,

either of soil to be backfilled or to be removed from site. In the first instance,

when measuring the trench excavation, it is usual to take the full volume as

backfill.

22.50 0.75 1.50

Exc. fdn. tr. n.e 1.5m. dp starting at stripped lev.

& Backfill exc. mtls. ard. Fdns

(b) Surplus spoil is given in cubic meter. Either deposited on site in

permanent spoil heaps or spread on site shall be so described stating the

location or the average distance from the excavations.

22.50 0.75 1.50

Remove from site and

deposit on site in permanent spoil heaps 100m away from excavations

(c) Earth filling to make up levels:-

If the filling is over than 300mm thick shall be given in cubic meters and

for the filling less than 300mm thick, shall be given in square meters

stating the average thickness.

Page 28: Measurement Beng. 010-1

28

20.00 15.00 0.45

Imported sand to make

up levels

20.00 15.00

Imported sand 280mm average depths to make up levels

4. Leveling and compacting trench bottoms

Surface treatment including leveling and compacting – This is done at the

bottom of excavations to receive concrete. Ii is measured in square meters.

22.50 0.75

L. & C. bott. of excns.to rec. conc.

5. Disposal of water

Disposal of water –This is done to keep excavation free from water and is

given as item

Item

Allow for keeping excavations free from general water

6. Planking and strutting

Planking and strutting - Earthwork support which include the use of timber

Planking and strutting to uphold the sides of excavation, plywood trench

sheeting and light steel trench sheeting and strutting. It is measured to the

sides of trenches and given as an item. section D19 or can be measured in

square meters

Item

Planking and strutting to uphold the sides of excavations

23.00 1.20

Planking and strutting to uphold the sides of excavations

Page 29: Measurement Beng. 010-1

29

B. MEASUREMENT OF FOUNDATIONS

When the excavation is complete, the excavated trench is filled with foundations

which include:-

1. Concrete in foundations including adjustment shall be given in cubic

meters as stating the mix and thickness (SMM F3). The adjustment of

excavated soil disposal will be taken with this item (i.e. Ddt. Backfill and

Add. Removal from site)

20.00 0.75 0.23

3.45

Conc.(1:3:6/40mm agg) in fdns. & Ddt. Backfill & Add. Remove from site

10.00 0.75 0 .23

1.725

Conc.(1:3:6/40mm agg) in fdns. & Ddt. Backfill & Add. Remove from site

2. Reinforcements – Bar reinforcement will be entered by length on the

dimension sheets and are billed in kilogrammes. (Section F16)

Weights of Groups of Bars per Metre

Size (mm)

Number of Bars

1 2 3 4 5 6 7 8 9 10

6 0.222

0.444 0.666 0.888 1.110 1.332 1.554 1.776 1.998 2.220

8 0.395

0.790 1.185 1.580 1.975 2.370 2.765 3.160 3.555 3.950

10 0.616

1.232 1.848 2.464 3.080 3.696 4.312 4.928 5.544 6.160

12 0.888

1.776 2.664 3.552 4.440 5.328 6.216 7.104 7.992 8.880

16 1.579

3.158 4.737 6.316 7.895 9.474 11.053

12.632

14.211

15.790

20 2.466

4.932 7.398 9.864 12.330

14.796

17.262

19.728

22.194

24.660

Page 30: Measurement Beng. 010-1

30

25 3.854

7.708 11.562

15.416

19.270

23.123

26.978

30.832

34.686

38.540

32 6.315

12.630

18.945

25.260

31.575

37.890

44.205

50.520

56.835

63.150

40 9.866

19.732

29.598

39.464

49.330

59.196

69.062

78.928

88.794

98.660

Page 31: Measurement Beng. 010-1

31

Example: If the foundation footing is reinforced with mild steel bars, the

measurements and entries will be as follows:-

4/ 4/ 4/

8.50 4.00 3.80

34.00 16.00 15.20

34.00 16.00 15.20 65.20 12mm dia. Mild steel bars in fdn footing

65.20x 0.888kg/m = 57.8976 Say 58kg

3. Formwork section F19

Formwork for most of the surfaces are given in square meters classifying

them in groups according to the position requiring formwork.

4. Blockwork/ walling (SMM G) in foundations is measured in square meters

stating the thickness, mix of mortar for bedding and jointing. The

adjustment of excavated soil disposal will be taken with this item (i.e. Ddt.

Backfill and Add. Removal from site)

Example: Measurement of blockwork

8.00 1.20

9.60

230mm blk b & j in c.m (1:3) & Ddt. Backfill 9.6 x 0.23 = 2.208 & Add. Remove from site 9.6 x 0.23 = 2.208

Page 32: Measurement Beng. 010-1

32

Example

10.00m

57.20 1.19

Girth l = 20.00

Less sprd 2/235 0.47 19.53

w = 10.00

Less sprd 2/235 0.47 9.53

sum of l & w 2/29.06 sum of all for sides – 58.12

less corners 4/230 - 0.92 Length of blkwk 57.20

Blkwk thickness– 230mm depth – 1.19

230mm blk b & j in c.m (1:3) & Ddt. Backfill ……x 0.23 = ………….. & Add. Remove from site …….. x 0.23 = ……………..

5. Damp proof course – Normally measured in linear meter. The description

of Damp proof course must include particulars of materials used,

thickness/gauge, number of layers and the nature of bedding (section

G96 –G97)

20.00m

Say 230mm wall

Page 33: Measurement Beng. 010-1

33

Example: Measurement of Damp proof course

80.00

Hor dpc 110mm wide of single layer of Hessian base bit. To b.s.743. lapped 100mmat jts &bedded in c.m (1 3)

Solid floors

(a) Ground floor consisting of a concrete bed usually supported on a bed of hardcore

Hardcore – This is measured as equal to the area of the void being filled (D20 in

SMM). It is measured in square meters if it does not exceed 300mm

thick, otherwise it is in cubic meters.

Damp proof membrane – This is laid on top of the hardcore and normally

measured in square meter. The description of Damp

proof membrane must include particulars of materials

used, thickness/gauge, number of layers and the

nature of bedding (section G96 –G97)

Example: Measurement of Hardcore & Damp proof membrane

4.50 5.70

Hardcore filling av.150mm. th., consisting of gravel rejects, blinded to receive conc. Including levellg and compacting. & Polythene hor. Membrane not less than 0.125 mm th., lapped 100mm at jts. & laid on hardcore

Concrete bed – Rarely exceeds 300mm in thickness and so are normally

measured in square meters stating the thickness. (SMM. section F5)

Page 34: Measurement Beng. 010-1

34

Example: Measurement of Concrete bed

4.50 5.70

25.65

1oomm th.conc. bed (1:2:4/20 agg.)

(b) Upper floors consisting of suspended concrete slabs. (SMM. section F7 (a))

Suspended floors and the like shall be given in square meters stating the

thickness.

The floors will be measured together with the associated items such as

reinforcements Section F16 and formwork section F19

Page 35: Measurement Beng. 010-1

35

SUPERSTRUCTURES

Superstructure elements of any building are those constructed on top of a base or of

the foundations of that building. Building construction can be divided into two faces

namely,- the Substructure and the Superstructure. For a simple building, superstructure

elements are such as walling, roofing, floors, doors, windows, staircases, fittings,

electrical installation, plumbing installation etc.

WALLING (SMM SECTION G)

Walling can be of blocks, bricks, concrete, natural stones and other light materials

recommended be the design team to be used for walling.

MEASUREMENTS

It is essential to measure the wall in a sequential order starting with external wall,

internal wall together with their incidental works if any.

(a) Particulars of the following shall be given:-

(i) Material, kind, type, finish and size of blocks shall be so described.

(ii) Any requirement as to the stone and the quarry

(iii) Type of bond for blockwork

(iv) Composition and mix of mortar for bedding and jointing

(b) External walls The length of external walling will be obtained by the method of girthing and the

height will normally be taken up to some convenient level, such as the general

eaves line. Any additional areas of the external wall such as gables parapets, wall

up to higher eaves level, etc, will be then taken off.

In measuring the wall the measurer takes the whole area regardless that there are

some voids and the adjustment of wall for window and doors openings will be made

when measuring the windows and doors.

Page 36: Measurement Beng. 010-1

36

The measurement of areas of external walls will be followed by incidental labours,

etc, such as rough cutting, eaves-filling, projecting courses etc.

(c) Internal walls

The measurement of external wall is usually followed by the internal walls. A careful

check should be made on the type and thickness of each partition, and where there

are a number of different types of partition it is often helpful to color each type in a

different color on the floor plan. Internal wall is also measured in square meters

stating all essential particulars as before described.

MEASUREMENT OF ROOFS - (SMM SECTION J, K AND SECTION L

Roofs are of two types namely; Pitched roofs and flat roofs. Both types can

conveniently be subdivided into two main sections for purposes of measurement, i.e.

construction and coverings. The order of measurement of these two sections varies in

practice, but on balance it is probably better to take the construction first as this follows

the order of construction on site.

PITCHED ROOFS

(a) Construction

The order of items should follow a logical sequence such as plates, rafters, ceiling joist,

collars, purlins, struts, ridge boards, and hip and valley rafters.

(i) a Timber works

The roof timbers such as rafters, ceiling joist, collars, purlins, struts, fascia

board, barge board, hip and valley rafters are all measured in linear

meters stating the size (thickness x width)

Page 37: Measurement Beng. 010-1

37

60 50 50

25X250mm hardwood/softwood timber Fascia board 150x150mm h/wd Wall plate 50x100mm swd ceiling joist

Size – Thickness x Width

Kind and quality of timber

Preliminary treatment of timber ( e.g. Pressure impregnated) The quantity of timber required can be calculated by various formulas:-

For example, L/S - 1 = number of Trusses

L = Length

S = Spacing of Truss

Now if the length is 18m and the spacing of rafters is 1.5m, then the number of Trusses

will be 18/1.5 - 1 = 11 Trusses

18m Hipped ends Ni of Trusses 7m L/S -1 =11

18m No of Trusses = Gable ends L/S + 1 18/1.5 +1 = 13

Page 38: Measurement Beng. 010-1

38

18m

One Hipped end and No of Trusses One Gabled end L/S 18/1.5 =12 If the length of rafters is calculated as 5m in each side, then the „taking off‟ will be as follows:-

11/2/

5.00

50X150mm Rafters

(i) b Lengths of Rafters

Where roof sections are drawn to a sufficiently large scale, the easiest method is

to scale the length of rafter off the drawing, taking the length from one extremity

to other of the rafter.

Another alternative is to calculate the length by multiplying the natural secants of

the angle of pitch by half the total span of the roof. The natural secants of the

more usual pitches of the roof are as follows:-

The use of four figure mathematical table for values of natural secants is

recommended.

Pitch of roof 15° 30° 40° 45° 50° Natural secant 1.036 1.155 1.305 1.414 1.555

Page 39: Measurement Beng. 010-1

39

40° 4.175m Half total span of roof is 4.175m, and the secant 40° is 1.305, therefore, Length of rafter = 4.175 x 1.305 = 5.448m (b) Coverings Roof covering are of various types such as slates or tiles, corrugated or toughed

sheets, thatch, bitumen felt , etc.

Slates or Tile roofing (SMM K2 -K15)

Particulars of the following shall be given:-

Kind, size, type and quality of slates or tiles

Extent of lap

Method of fixing and the number of nails or pags per slate or tile

Size and type of laths or battens

Measurements:-

Roof coverings shall be measured in square meters

Page 40: Measurement Beng. 010-1

40

Square cutting around openings, raking cuttings , curved cuttings, valleys, hips

and vertical angles shall be given in linear meter separately.

Corrugated or troughed sheets SMM K16 –K26

Particulars of the following shall be given:-

Kind of sheeting

Quality and gauge of sheeting and type

Extent of side and end laps

Nature and general spacing of the structural supports ( eg. Purlins)

Method of fixing the sheeting

Roof coverings shall be measured in square meters

Measurements:-

12.00 6.00

26 Gauge (SWG) Corrugatted Alumium roofing Sheet 150mm both sides and ends laps fixed to timber purlins with galv. Screws and plastic washers

Square cutting around openings, raking cuttings , curved cuttings, valleys, hips

and vertical angles shall be given in linear meter separately.

FLAT ROOF COVERINGS (a) Asphalt (SMM SECTION J)– The main areas of asphalt are measured in square

meters stating the thickness and number coats of asphalt. Furthermore, the asphalt

item is to include the underlay of felt, cork, fiberboard or similar material and any

reinforcement.

(b) Bitumen felt (SMM K36) – The unit of measurement is the square meter and it is

classified by slope. Full particulars of felt are to be given such as extent of laps, nature

Page 41: Measurement Beng. 010-1

41

of base and method of securing felt to it and the nature of surface treatment if any. The

measurement of the main areas of roof covering will be followed by such linear items.

FINISHING (SECTION S)

Major Finishing classifications are walls, floors and ceiling. The classifications depend

on which kind of materials eg.

-Cement sand screed

-Terrazo

-Ceramic floor tiles etc

Materials can be further grouped into:-

- Insitu finishing

- Tiles, slab, block finishing

- Plain sheeting finishing e.g plywood, soft board

They should be stated either

- Internal finishing work or

- External finishing work

INSITU FINISHINGS

A) SAND & CEMENT SCREED FINISHING

(i) Composition and mix ratio ( i.e, 1:3, 1:4)

(ii) Thickness – 20 – 60mm thick ( common 40mm)

(iii) Number of coats normally laid one coat

(iv) Nature of surface treatment such as

- wood floated

- Steel trowelled smooth

- Nature of base eg. Concrete blockwork background

(v) Preparatory work so as to form keys e.g. hacking concrete

(vi) Any other special curing on finishing such as steam curing, should be given in

your description

Page 42: Measurement Beng. 010-1

42

Typical description

40mm Thick cement and sand screed (1:3) steel trowelled smooth laid to floor to

keyed concrete base.

B) TERRAZO FINISHING

(i) Composition and mix ratio

1st coat consist of cement and sand screed (1: 3), (1: 4), (1: 6)

2nd coat consist of cement marble chipping white or any color 1 :21/2

(ii) Thickness 20 – 60mm thick ( minimum thickness is 16)

(iii) Number of coats – 2coat or 1coat it the thickness is less than 30mm

(iv) Nature of surface treatment

- Grind the surface

- Polish the surface

(v) Nature of base – concrete, blockwork or brickwork

(vi) Special curing

Typical description

40mm Thick terrazzo to floor to keyed concrete base in two coats 1st coat of

20mm thick (sand and cement 1:3) 2nd coat of 20mm coloured and marble

chipping 1:21/2) includind grinding the surface and polishing.

Floor and paving (S 3)

- Horizontal floor and paving , cross falls and slopes not exceeding 15 degrees from

horizontal shall be given separately in square meters

Ceiling Finishing (S 4)

Work to walls and ceilings shall each be given separately in square meters describing if

to battering walls, to sloping walls etc.

The area of ceiling is measured between wall surfaces in square meters, followed by

any associated labor such as arises to beams.

Page 43: Measurement Beng. 010-1

43

Wall Finishing (S 4)

The measurement is taken from the floor to ceiling. Work behind wood skirting and the

like shall be dealt with the work of walls disregarding any ground.

Skirting and picture rails (S.8)

Timber skirtings and picture rails as well as cornices, fillets etc. are measured in linear

meters stating the size and describing the labours and including any supporting

grounds.

Dividing strips S. 7

Dividing strips are given in linear meters stating end, angles and intersections shall be

deemed to be included with the item.

Schedule of finishings

Location

Floor

Skirting

Walls

Ceiling

RI

40mm Terrazzo

150X20 Terrazzo

Plaster

Plaster

R2

Ditto

Ditto

Ditto

Ditto

R3

40mm. C & S Screed

150x20 C & S Screed

Ditto

Ditto

R4

Ditto

Ditto

Ditto

Ditto

Page 44: Measurement Beng. 010-1

44

R1 R2 R3 R4

230 230 230 230 230 3000 3500 4000 4000

Page 45: Measurement Beng. 010-1

45

2/

5.00 3.00 5.00 3.50 4.00 5.00

FLOOR FINISHING 40mm. thick terrazzo floor finish

laid to falls and cross falls n.e 15 degree from horizontal to keyed conc. Base in 2 coats 1st coat of 20mm thick c & s (1:3) 2nd coats of 20mm coloured cement and marble (1:21/2) and including grinding the surface with carborundum and polishing internally (R 1)

40mm thick Terrazzo floor finish

laid to keyed conc. base in 2 coats ditto. (R2)

40mm thick Steel toweled smooth laid to floor to keyed concrete R (3 & 4)

WALL FINISHINGS (R(1& 2)

ht = 3.00 Less floor 0.04 Less Skirting 0.15 0.19

Finishing ht 2.81

(R(1& 2) Ht = 3.70 Less 0.19 3.51

2/ 2/ 2/ 2/ 2/2 2/2

3.00 5.00 3.50 5.00 4.00 5.00

SKIRTING 20mm thick x 150

mm high terrazzo skirting with top rounded edge and covered junction with paving in one coat in white and cement marble (1:21/2) to blockwork / concrete work background including grinding with carborundum stone and polishing to the surface.

20mm thick x 150

mm high cement and sand screed (1:3) skirting to blockwork/ – concrete work background.

R (3 8 4)

CEILING FINISHING 15 mm thick plaster to concrete ceiling in two coat 1st coat 12mm thick in cement, sand and line ( 1: 4: 5); 2nd coast 2mm thick in cement sand and line putty (1: 1: 5) with wood floated surface internally.

Page 46: Measurement Beng. 010-1

46

2/ 2/ 2/ 2/ 2/2 2/2

3.00 2.81 5.00 2.81 3.50 2.81 5.00 2.81 4.00 3.51 5.00 3.51

15mm thick plaster to

blockwork/ concrete work or brickwork walls in two coats, 1st coat 12mm thick in cement, sand and lime (1:4:5) 2nd coat 3mm thick.

& 3mm thick in cement, sand

and lime putty ( 1:1:5) with wood floated surface internally

Page 47: Measurement Beng. 010-1

47

DOORS AND WINDOWS - SECTION M

A. DOORS Door shutters The measurement of doors can be subdivided into internal and external doors, and the

dimensions of each of these two classes of door broken down into;

1. Door

2. Adjustment of opening

Measurements

Doors shall be given in square meters stating the thickness and the number of

doors (each leaf being counted as one door).

Doors may also be enumerated stating the size Classification

(i) Flash doors stating the construction of the core, the finished thickness of the

door, the kind, quality and the thickness of the facing materials and the method

of fixing of facing material to the core.

(ii) Boarded doors stating the thickness of the boarding, ledges, braces and

framing and the method of jointing the board covering or filling.

(iii) Panelled doors stating the nominal thickness of the framing, the number and

nominal thickness of the panels and where molded stating whether the moldings

are worked on the solid or planted on and whether on one or both side.

Pannelled doors with open panels for glass shall be so described.

Page 48: Measurement Beng. 010-1

48

Door frames and linings

Door frames and linings are measure in linear meters giving full description of all the

labours and the size of the member.

Adjustments

When adjusting the opening for care must be taken to cover all the appropriate items

by adopting a logical order of „taking off‟ such as deduction of walls, external and

internal finishings, - skirting, and flooring

Sundries

Plugging - Plugging to concrete, blockwork and stonework shall be given in squire

meters or enumerated or may be given in the description.

Holes in timber – Holes for bolts and the like shall each be enumerated separately

stating the size of bolts and the thickness of timber.

Iron-mongery

Particulars of the following shall be given:-

Kind and quality of Iron-mongery

Surface finish

Nature of the background (e.g. timber, metal…) to which items are fixed

Page 49: Measurement Beng. 010-1

49

FIXTURES AND FITTINGS - SECTION M28 Cupboards, Tables, Work-benches, Counters, Bookcase etc., shall be given in detail or

may be enumerated and fully described.

Those of similar character may be grouped together.

Drawers shall be enumerated stating the overall dimensions, the thickness of

component parts and the method of joining.

Applied covering – In square meters stating the method of securing.

PAINTING AND DECORATIONS – SECTION (U)

Work is grouped into:-

Internal work

External work

Generally, work on surface over 300mm girth shall be given in square meters.

Those not exceeding 300mm girth shall be in linear meters

Those not exceeding 0.10 square meter shall be enumerated

Particulars of the following shall be given

1. Kind and quality of material

2. Nature of work (e.g. lime whiting, painting, varnishing)

3. Nature of base on which work is executed

4. Preparatory work- (rubbing down, repairing cracks, scrubbing)

5. Number of priming or sealing coats

6. Number of undercoat

7. Number of finishing coat

Page 50: Measurement Beng. 010-1

50

Measured on groups according to the nature of the background such as:-

On general surfaces

On wood, frames, wood windows and glazed wood doors

On metal windows and glazed metal doors

On structural steelwork

On grilles, balustrades, railing and mesh

On gutters

On pipes

On bars, cables, conduits, straps and ducting

Page 51: Measurement Beng. 010-1

51

BILLS OF QUANTITIES

Bills of quantities is a fully described and accurately representation of the works to be

executed. Bills of quantities consist of preliminaries, prime cost sums, provisional sums

and measured works.

Purposes of bill of quantities

(a) It enables all contractors tendering for a job to price on exactly the same

information with a minimum effort. In the absence of a bill of quantities being

prepared by the building owner each contractor would have to preparing his own

Bill of Quantities in the limited amount of time allowed for tendering. These

places a heavy burden on each contractor and also involve him, in additional

costs.

(b) It provides a basis for the valuation of variations which often occur during the

progress of the work.

(c) It gives an itemized list of the component parts of the building, with a full

description and the quantity of each part, and this may assist the successful

contractor in ordering materials and assessing his labour requirements for the

job.

(d) After being priced, it provides a good basic for “cost planning and cost analysis

work”.

Forms of Bills of Quantities

Elemental bills

In Elemental bills, items are grouped according to their position in the building. Each

element comprises an integral part of the building such as external walls, roofs or

floors, which each perform a certain design of function. Within each element, the items,

may be billed in trade order or grouped in building sequence.

Page 52: Measurement Beng. 010-1

52

Trade bills

In Trade bills, items are arranged in trade order under the main headings of the

separate trades.

Sectionalized Trades bills

This can be presented either as a trade bill or with elements as the main subdivision.

Operational bills

The description of the billed work follows the actual building process, with materials

shown separately from labour, all described in terms of the operations necessary for

the construction of the building. An operation for the purpose of the operational bill is

the work performed by a man or gang between definite breaks in the pattern, such as

bricklaying from damp-proof course to first floor joists in housing work.

BILL PREPARATION PROCESSES

Working – up

After the „taking - off‟ the quantities, squaring the dimensions and entering the resultant

lengths, areas and volumes in the third or squaring column on the dimension paper

follows. The next stage is transferring the squared dimensions to the abstract or

transferring the items directly from the dimension sheet to the bill. In the bill of

quantities, the various items of work making up the job are listed under the appropriate

trade or section headings, with descriptions printed in full and quantities given in

recognized units of measurement as per SMM. The above narrated process is known

as „working – up‟.

Page 53: Measurement Beng. 010-1

53

Ruling of Bill of Quantities

1

2

3

4

5

6

Column No. Use of column

1 Item

2 Description

3 Quantity

4 Unit

5 Rate

6 Amount

Item

Description

Quantity

Unit

Rate

Amount

A B C D E

SUBSTRUCTURE

Vegetable soil

Excavation of vegetable. soil, average150mm deep and deposit. on site in spoil heaps, average. 20 metres away from excavations

Trees and Hedges Cutting down small trees n.e 600mm girth and grubbing up their roots

Cutting down Michongoma hedges and grubbing up their roots. ……………………. ………………………..

20

10

15

M2

NO M

20,000 3000 1500

400,000 30,000 22,500

TO COLLECTION

Pg. 8/3/1/1

Page 54: Measurement Beng. 010-1

54

Item

Description

Quantity

Unit

Rate

Amount

A B C D E

ELEMENT NO 1: SUBSTRUCTURE

Trench excavation and Disposal

Excavation of foundation trenches.. not exceeing 1.5 meter deep starting at stripped levels. Backfill excavation materials around foundation

…………………….. ……………………. Concrete bed 100mm Thick concrete bed (1:2:4) mix

ratio 20) aggregate.

20

5 30

M3

M3

M2

………

…….

…………

………… ………… ………….

TO COLLECTION

COLLECTION

Pg. 8/3/1/1 xxxxxx

Pg. 8/3/1/2 xxxYYY

TOTAL COLLECTION ELEMENT NO.1 CARRIED

TO SUMMARY

YXYXY

Pg. 8/3/1/2

Page 55: Measurement Beng. 010-1

55

Item

Description

Quantity

Unit

Rate

Amount

A B C D E

ELEMENT NO 2: ROOFING

Roof structure

………………………………… …………………………………

…………………….. …………………….

Roof coverings ……………………………….

…..

…. …

M

M

M2

………

……

…..

……….

………. ……….. ……….. ………..

TOTAL ELEMENT NO 2 CARRIED TO SUMMARY

…………

Pg. 8/3/2/1

Units of Measurement

The commonly used in the Bills of Quantities are Linear, Square and cubic respectively

They are abbreviated as M, M2, M3, Kg, Prs

Entering Quantities in the Bill

Quantities are to be billed to the nearest whole unit. Fractions of units which are

less than one – half are. Disregarded

When the above application causes an entire item to be eliminated, the item is to

be enumerated stating the size or weight.

Page 56: Measurement Beng. 010-1

56

General Rule of Billing

Items will be grouped under suitable section and sub-section headings and will

follow the order and terms adopted in the SMM.

The preamble clauses will be inserted at the head of each section

Each item to be priced in the bill is indexed by letters and or numbers in the first

column

Words in the bill will written in full without any abbreviation

Provision is made for the total sum on each page of the bill relating to a given

section of work to be transferred to a collection at the end of the section

The total of each of the collections is transferred to a summary at the end of the

bill

Note: On completion of the draft bill must be very carefully checked against the

abstract or the squared items and those items suitably marked in colored

ink or pencil as each item is dealt with.

Numbering the BOQ Pages

The bidding document is divided in various sections such as:-

Section 1 - Invitation to Tender

Section 2 - Instruction to Tenderers

Section 3 - Tender Data Sheet

Section 4 -General conditions of contract

Etc. etc

Numbering of the pages in the Bill of Quantities follows the sequence of section; bill

No., Element No and the page No.

For example the page below indicate that, fencing work is placed at section number 9,

it is in bill number 3, Element No. 1 on page 1.

Here below is an example of the Bill of Quantities