mcgraw-hill/irwin© 2008 the mcgraw-hill companies, all rights reserved reducing project duration...
TRANSCRIPT
![Page 1: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/1.jpg)
McGraw-Hill/Irwin © 2008 The McGraw-Hill Companies, All Rights Reserved
Reducing Project Duration
Chapter 9
![Page 2: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/2.jpg)
9-2
![Page 3: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/3.jpg)
9-3
Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs
Reducing the time of a critical activity usually incurs additional direct costs.
o Cost-time solutions focus on reducing (crashing) activities on the critical path to shorten overall duration of the project.
Reasons for imposed project duration dates:o Customer requirements and contract commitments
o Time-to-market pressures
o Incentive contracts (bonuses for early completion)
o Unforeseen delays
o Overhead and goodwill costs
o Pressure to move resources to other projects
![Page 4: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/4.jpg)
9-4
Options for Accelerating Project Completion
Adding Resources
Outsourcing Project Work
Scheduling Overtime
Establishing a Core Project Team
Do It Twice—Fast and Correctly
Fast-Tracking
Critical-Chain
Reducing Project Scope
Compromise Quality
![Page 5: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/5.jpg)
9-5
Explanation of Project Costs Project Indirect Costs
Costs that cannot be associated with any particular work package or project activity
o Supervision, administration, consultants, and interest
Costs that vary (increase) with timeo Reducing project time directly reduces indirect costs.
Direct Costs Normal costs that can be assigned directly to a
specific work package or project activityo Labor, materials, equipment, and subcontractors
Crashing activities increases direct costs
![Page 6: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/6.jpg)
9-6
Reducing Project Duration to Reduce Project Cost
Identifying direct costs to reduce project timeIdentifying direct costs to reduce project timeIdentifying direct costs to reduce project timeIdentifying direct costs to reduce project time
Compute total costs for specific durations and Compute total costs for specific durations and compare to benefits of reducing project time.compare to benefits of reducing project time.
Compute total costs for specific durations and Compute total costs for specific durations and compare to benefits of reducing project time.compare to benefits of reducing project time.
Search critical activities for lowest direct-cost Search critical activities for lowest direct-cost activities to shorten project duration.activities to shorten project duration.
Search critical activities for lowest direct-cost Search critical activities for lowest direct-cost activities to shorten project duration.activities to shorten project duration.
Gather information about direct and indirect Gather information about direct and indirect costs of specific project durations. costs of specific project durations.
Gather information about direct and indirect Gather information about direct and indirect costs of specific project durations. costs of specific project durations.
![Page 7: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/7.jpg)
9-7
Project Cost—Duration Graph
FIGURE 9.1
![Page 8: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/8.jpg)
9-8
Constructing a Project Cost—Duration Graph
Find total direct costs for selected project durations.
Find total indirect costs for selected project durations.
Sum direct and indirect costs for these selected project durations.
Compare additional cost alternatives for benefits.
![Page 9: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/9.jpg)
9-9
Constructing a Project Cost—Duration Graph
Determining Activities to Shorten Shorten the activities with the smallest increase in
cost per unit of time. Assumptions:
o The cost relationship is linear.
o Normal time assumes low-cost, efficient methods to complete the activity.
o Crash time represents a limit—the greatest time reduction possible under realistic conditions.
o Slope represents a constant cost per unit of time.
o All accelerations must occur within the normal and crash times.
![Page 10: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/10.jpg)
9-10
Activity Graph
FIGURE 9.2
![Page 11: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/11.jpg)
9-11
Cost—Duration Trade-off Example
FIGURE 9.3
![Page 12: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/12.jpg)
9-12
Cost—Duration Trade-off Example (cont’d)
FIGURE 9.3 (cont’d)
![Page 13: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/13.jpg)
9-13
Cost—Duration Trade-off Example (cont’d)
FIGURE 9.4
![Page 14: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/14.jpg)
9-14
Cost—Duration Trade-off Example (cont’d)
FIGURE 9.4 (cont’d)
![Page 15: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/15.jpg)
9-15
Cost—Duration Trade-off Example (cont’d)
FIGURE 9.4 (cont’d)
![Page 16: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/16.jpg)
9-16
Summary Costs by Duration
FIGURE 9.5
![Page 17: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/17.jpg)
9-17
Project Cost—Duration Graph
FIGURE 9.6
![Page 18: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/18.jpg)
9-18
Practical Considerations
Using the project cost—duration graph
Crash times
Linearity assumption
Choice of activities to crash revisited
Time reduction decisions and sensitivity
![Page 19: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/19.jpg)
9-19
What if Cost, Not Time Is the Issue?
Commonly Used Options for Cutting Costs
Reduce project scope
Have owner take on more responsibility
Outsourcing project activities or even the entire project
Brainstorming cost savings options
![Page 20: McGraw-Hill/Irwin© 2008 The McGraw-Hill Companies, All Rights Reserved Reducing Project Duration Chapter 9](https://reader036.vdocuments.mx/reader036/viewer/2022062421/56649f4a5503460f94c6c1ee/html5/thumbnails/20.jpg)
9-20
Key TermsCrash point
Crash time
Direct costs
Fast-tracking
Indirect costs
Outsourcing
Project cost–duration graph