mazagon dock limited mazdock modernisation...
TRANSCRIPT
-
A COMPANY OF
MAZAGON DOCK LIMITED
MAZDOCK MODERNISATION PROJECT
Contract No. MMP/01006/03
DETAILED PROJECT REPORT
FINAL ISSUE
Volume 1, Rev 1, 21st
November 2003
HASKONING NEDERLAND BV
MARITIME
-
A COMPANY OF
Mazagon Dock Limited
Project name Mazdock Modernisation Project
Document title Detailed Project Report Volume 1
Status Final Issue Revision 1
Date 21st November 2003
Royal Haskoning
Project number 3H6543
MMP Contract number MMP/01006/03
Reference 3H6543:R007
Drafted by D.S. Byrom, S R Davies, R C B Potter
Checked by P D Gallagher
Approved by P.D. Gallagher
Marlborough House
Marlborough Crescent
Newcastle upon Tyne NE1 4EE
United Kingdom
+44 (0) 191 211 1300 Telephone
+44 (0) 191 211 1313 Fax
[email protected] E-mail
www.royalhaskoning.com Internet
HASKONING NEDERLAND BV
MARITIME
-
Mazagon Dock Limited
Mazdock Modernisation Project
- i -
Document No. 3H6543/R007Final Issue Rev 1
November 2003
-
Mazagon Dock Limited
Mazdock Modernation Project 1
Document No. 3H6543/R007Final Issue Rev 1
November 2003
MARITIME CIVIL WORKS CONTRACT – the WET BASIN
1.1 Objectives - Re-Statement
Stated simply, the primary objectives of the physical infrastructure of the Wet Basin are
as follows :
� To improve the cost efficiency and productivity of the Yard in the construction,
completion and repair of surface and sub-surface naval vessels, and of merchant
ships as applicable.
� To provide a enclosed or captive outfitting/repair haven generally for naval vessels
but also to be available for merchant tonnage when required.
� To provide a virtually constant yet controllable water level environment such that
vessels undergoing outfit/re-fit or repair are free from the daily fluctuation in water
levels due to tides, and with a negligible but assessable risk of bottom damage even
if the impounding gate is ever breached.
� To provide the necessary mechanical and electrical services in and around the wet
basin to enable efficient outfitting of vessels.
� To be robust and durable in design, requiring minimal maintenance for the design life
of the facility, expected to be more than 75 years before major structural repair is
need
1.2 Introduction
The text below describes and confirms the decisions made following the acceptance of
the design concepts as set out in the PPR. Each significant feature is numbered for
ease of reference and where appropriate, the relevant drawing number is given in the
third column.
1.3 Exact Location, Leading Dimensions and Water Levels & Depths
Wet Basin Feature Drawing No.
3H6543/DPR/
1.3.1 Exact Location of Wet Basin
The final exact location is as finally accepted in the PPR and is such
that :
The Wet Basin lies within the limits and constraints imposed by the
MbPT and CWPRS as far as can be determined accurately.
Ritchie Dry Dock is outside the Basin, and operates independently
The North Quay is aligned parallel to the outer faces of the Ritchie
Dry Dock Extension mitre gate protrusions so as to minimise
restrictions on vessel entry to Ritchie Dock. The north face of the
North Quay is set back 500 mm from this base line to allow for
fenders. The south face (deck edge) is set parallel to the north face
and commencing from the north corner of the submarine dry dock meeting face.
The south rail of the South Quay is aligned exactly with the 300 tonne
Goliath Gantry crane north rail. This then determines the exact
location of the South Quay
The East Quay setting-out is found by joining the extremities of the
North and South Quays
Setting Out:
0013
-
Mazagon Dock Limited
Mazdock Modernation Project 2
Document No. 3H6543/R007Final Issue Rev 1
November 2003
The Wet Basin Gate opening is set at 40 m from the internal face line
of the South Quay
The seaside face of the West Quay (South) wall is set parallel to the
West Quay (North-A) wall, but with the south east corner on a line
with the current berth extensions to Slipway No.2. The south face of
the wall, that closes onto the existing roundhead of crane track no. 9,
is set 4.0 m north of the north wall of Slipway No. 1 to allow future
construction by others of an extension to Slipway No. 1
The Basin side face of the West Quay (North-A) wall intersects the
existing sea wall at the junction with the line of the South Quay south
crane rail
The Basin face of the West Quay (North-B) wall that carries road
access to the Submarine Dry Dock gate area is set at 8.0 m from the
face of the existing East Yard boundary wall
The Basin face of the West Quay (North-C) wall that creates lay-
down space adjacent to the Submarine Dry Dock gate area is set
parallel to the face of the existing dry dock caisson gate
1.3.2 Leading Dimensions of the Wet Basin
(note : dimensions may be rounded for ease of reference)
(a) North Quay internal length = 183 m measured from the meeting
face of the existing submarine dry dock gate
South Quay internal length = 225 m
East Quay internal length including gate = 112 m
Gate opening in East Quay 31 m to permit clear opening of 30 m with
allowance for rubbing strip fenders
West Quay (North-A) internal length = 65 m
Water surface area bounded by the solid faces of the mass concrete
wall structures = 27,000 m2
North Quay overall deck width = 10.0 m , with a 5.5 m crane rail track
gauge
South Quay overall deck width = 16.5 m with a 10.0 m crane rail track
gauge
East Quay (North) and East Quay (South) overall deck width = 14.0
m
West Quay (South) overall deck width = 12.0 m
West Quay (North-A) overall deck width = 12.0 m
West Quay (North-B) overall deck width = 8.0 m
West Quay (North-C) overall deck width = 17.0 m
Closure Wall overall deck width = 5.0 m
1601
1.3.3 Water Levels and Water Depths
The finally agreed water levels and water depths associated with the Wet Basin will be
:-
-
Mazagon Dock Limited
Mazdock Modernation Project 3
Document No. 3H6543/R007Final Issue Rev 1
November 2003
Level to CD
in metres
Design nominal finished level of Wet Basin decks (N, E, S) + 7.000 CD
Design nominal finished level of West Quay decks approx. + 6.500 CD
Design nominal finished level of Lead-in Jetty Dolphins + 6.500 CD
Highest astronomical tide (HAT) + 5.400 CD
Highest recorded tide (HRT) + 5.380 CD
Maximum normal operating impounded level in Wet Basin + 4.500 CD
Maximum impounded level in Wet Basin controlled by
overflow pipe invert level
+ 5.500 CD
Mean High Water Springs (MHWS) + 4.420 CD
Mean High Water Neaps (MHWN) +3.300 CD
Mean Sea Level (MSL) + 2.510 CD
Minimum normal operating impounded level in Wet Basin + 2.500 CD
Mean Low Water Neaps (MLWN) +1.850 CD
Mean Low Water Springs (MLWS) + 0.760 CD
Minimum emergency water level in Wet Basin = Chart Datum +/- 0.000 CD
Lowest Recorded Tide (LRT) - 0.440 CD
Wet Basin Gate sill level - 5.000 CD
Design excavated level within Wet Basin - 6.000 CD
Design dredged level outside of Wet Basin North wall As existing
Design dredged level outside of Wet Basin South wall As existing
Design dredged level outside of Wet Basin East wall North As existing
Design dredged level outside of Wet Basin East Wall South for
full length of quay
- 6.0m CD to
existing in 20m
Design dredged level along Lead-in Jetty, south side - 6.000 CD
Approx design dredged level of Turning Circle (by Others)* - 3.000 CD
Minimum level at which impounding pumps will operate +2.5m CD
Minimum level at which equalising valves will operate +1.5m CD
Minimum level at which the gate will be opened or closed +2.5m CD
Water Depth
in metres
Maximum normal operating water depth in Wet Basin 11.5 metres
Minimum normal operating water depth in Wet Basin 8.5 metres
Emergency minimum water depth in Wet Basin 6.0 metres
* The Turning Circle will need to be relocated to suit the location of the Wet Basin
entrance. This should be done before the completion of the Wet Basin. This work is
outside the scope of the HNBV specification and cost estimates.
1.4 Dredging, Excavation in the ‘Dry’ and Contamination Issues
Wet Basin Features Drawing No.
3H6543/DPR/
1.4.1 Dredging
1. For the reasons of economy, quality of work, and flexibility in
construction including the ability to excavate in parallel with
constructing the Stage 2 works, sea dredging (involving floating
dredging plant and possibly the use of controlled explosives, see
1.4.2 below) will be limited in scope to :
1642
-
Mazagon Dock Limited
Mazdock Modernation Project 4
Document No. 3H6543/R007Final Issue Rev 1
November 2003
(a) dredging minimum areas for Stage 1 wall construction.
(b) dredging the Lead-in Jetty channel for 200m out toward the
turning circle.
(c) Limited dredging of the wet basin area as required for
construction operations.
(d) dredging a gradual slope from the face of the East Quay
(South) wall toward the turning circle for a distance of 20m to
minimise the effects of siltation on the performance of the
impounding pumps and discharge valves.
2. It is presently estimated from the results of the geophysical
survey and the existing boreholes undertaken in 2002, that the
quantities of ‘soft’ and ‘hard’ dredging are :-
• 56,000 m3 of ‘soft’ dredging
• 30,000 m3 of ‘hard clay’ dredging
• 70,000 m3 of ‘weathered rock dredging
3. Unfortunately the seismic survey was not able to establish the
difference between hard clay and weathered rock. The volume
of rock excavation has therefore yet to be finalised by further
geotechnical investigation. The volumes stated above are based
solely on the limited number of boreholes undertaken in 2002.
The volumes of hard clay dredging and rock dredging could
therefore be subject to significant variation.
1.4.2 Methods of Dredging
1. In dredging terms, the volumes to be excavated for this project
are relatively small. The depth of water in which dredging plant is
able to operate is also very limited across the site area. These
two factors, together with the materials to be dredged, will
probably lead the contractor to utilise a barge-mounted backactor
or a crane operated grab type dredgers.
2. This equipment will be able to remove the soft silt and the hard
clay layers and possibly the weathered rock, depending on its
strength. The dredging arisings will be loaded into a dump barge
for disposal at the MbPT dump sites.
3. Rock excavation will probably need to be assisted by controlled
blasting techniques. To prevent damage to existing MDL
waterfront structures, the peak particle velocity will be defined by
initial test blasting.
4. The need to undertake capital dredging in the approach channel
to the lead in jetty will be assessed following the further ground
investigation works discussed in section Error! Reference
source not found.. If no hard rock is found in the approach
channel above the -5.0m CD level, MDL will defer the dredging
until later.
1.4.3 Excavation in the ‘dry’
-
Mazagon Dock Limited
Mazdock Modernation Project 5
Document No. 3H6543/R007Final Issue Rev 1
November 2003
1. Unless the actual contractors tenders show otherwise, it is the
intention to remove the large majority seabed materials from
within the Wet Basin area by land excavation techniques in the
‘dry’. The ‘dry’ condition will be achieved after the Wet Basin
Stage 1 water-retaining walls and entrance works temporary
cofferdam have been completed and the water pumped out. This
material will be dumped at sea in an approved location.
2. It is presently estimated from the results of the geophysical
survey and the existing boreholes undertaken in 2002, that the
quantities of ‘soft’ and ‘hard’ ‘dry’ excavation are :-
• 54,000 m3 of ‘soft’ material
• 40,200 m3 of ‘hard’ material
• 60,800 m3 of ‘weathered rock dredging
3. As stated in 1.4.1, the volumes stated above are based solely on
the limited number of boreholes undertaken in 2002. The
volumes of hard clay excavation and rock excavation could
therefore be subject to significant variation.
1.4.4 Contamination Issues
In respect of dredging and ‘dry’ excavation procedures will be put in
place to :-
• ensure that the materials arising from dredging activities (and
excavation) are dumped in dumping grounds or tips that are
approved by the competent Authority, the Mumbai Port Trust
(MbPT). It is currently understood that MbPT have two
designated dumping areas, one for dumping dredged materials
during ebb tides and the other for use during flood tides. The
location of and Authority for approved land-fill tipping sites is not
known at present.
Contaminated materials dumped at sea can seriously harm sea
life forms, whilst land tipped contaminated materials can
adversely affect ground water (and hence potable water) quality
• carry out tests (on samples from the proposed new boreholes) to
ascertain whether contaminants are likely to be present in the
dredged/excavated materials. Such contaminants could arise
from natural sources in the soils or probably more likely from the
activities of the shipyard over its many years of existence. Tests
will be essential to determine the levels, if any, of heavy metals
and organic compounds (eg. TBTs) in particular. The procedure
will be that appropriate tests will be undertaken and the results
discussed with MDL prior to deciding the correct course of action
to be taken.
1.5 Structural Walls
1.5.1 Re-statement of Function Drawings:
1601
-
Mazagon Dock Limited
Mazdock Modernation Project 6
Document No. 3H6543/R007Final Issue Rev 1
November 2003
The Stage 1 structural walls have the following functions and
requirements:
• main water retaining structures for the wet basin, to keep the water
level in the basin approximately constant
• soil retaining structures along the line of the West Quay
• provision of berthing faces for vessels
The Stage 2 structures provide the basin side part of the quay walls
and the top deck structure. This includes plantrooms, services
trenches and other deck features.
1602
1604
1.5.2 Location
The setting out of the basin walls is shown on the drawings.
1602
1604
1.5.3 Stage 1 Structural Walls
1. The Stage 1 Basin walls are mass concrete structures cast
underwater on the dredged rock surface.
2. Walls will be constructed within a ‘controlled environment’ to
minimise the problems associated with placing concrete
underwater. See section 1.9.2.
3. Walls will be constructed with each concrete pour being the full
width of the wall ensuring the wall will act as a monolithic structure.
4. The walls are designed to resist the following loads:
• Differential water levels
• Berthing
• Imposed deck loads
• Wave loads
• Earthquake loads
• Accidental vessel impact loads
• Silt level up to 0.0m CD
5. The founding levels of the basin walls is generally -6.0m CD.
6. The top of the Stage 1 walls will generally be 1.0m below the final
deck level. The Stage 1 walls will accommodate recesses for
plantrooms, services trenches and other features as appropriate.
7. The width of the Stage 1 walls varies and is shown on the
drawings.
8. The walls are designed to resist accidental impact loads from
vessels in the channel of size up to 3,000 dwt with velocities of up
to 0.3m/s. Vessels larger than this would run aground before
reaching the wet basin structures.
9. The quay walls have been designed to accommodate a silt level of
up to 0.0m CD on the northern face of the quay. MDL are to
maintain this as a maximum level by periodic dredging.
1602
1.5.4 General Main Features
1. The Stage 2 structural wall for the East Quay (North) comprises
1601
1604
-
Mazagon Dock Limited
Mazdock Modernation Project 7
Document No. 3H6543/R007Final Issue Rev 1
November 2003
reinforced concrete pier structures at 7.5m spacing along the
inside face of the mass concrete wall.
2. The Stage 2 concrete works on the North Quay consist of the deck
slab and the services gallery along the basin side of the wall.
3. The Stage 2 structural wall for the South Quay comprises
reinforced concrete buttress structures at 7.5m spacing along the
inside face of the mass concrete wall. The buttresses are 1.7m
wide and 5.35m deep. There is a gap of 1.75m between the face
of the mass concrete wall and the inside face of the piers. The
services gallery on the basin side is included in the Stage 2
concrete works.
4. The West Quay (South) and East Quay (South) have no Stage 2
structural walls although the construction of the pump houses,
valve and winch chamber and main deck will form part of the
Stage 2 construction.
5. The West Quay (South) will be constructed “in the wet”, together
with West Quay North A and the Closure Wall. West Quay North B
and C will be constructed in the dry.
6. The pumphouse structure will be constructed “in the dry”, as part
of the stage 2 reinforced concrete works.
1.5.5 Deck Fittings
See Section 1.6
1.5.6 North Quay
1. The width of the North Quay deck structures is 10m.
2. The North Quay wall is designed to accommodate a range of
vessels but with the assumption that it will be used primarily for submarines berthed on submarine launch barges (SLB).
3. The deck loading over the services gallery is 2.5tonnes/m2 (normal
quay loading).
1616
1617
1618
1625
1629
1630
1.5.7 South Quay
1. The width of the South Quay deck structures is 16.5m.
The South Quay wall is designed to accommodate a range of
vessels but with the assumption that it will be used primarily for
frigates and other surface vessels.
2. MDL have now confirmed that the southern side of the quay will not be used for berthing.
3. The deck loading over the services gallery is 2.5tonnes/m2 (normal
quay loading).
4. An underground electrical switchroom is located at the east end of
the South Quay
1610
1611
1612
1626
1627
1628
1.5.8 East Quay
1. The width of the East Quay (North) and East Quay (South) deck
structures is 14m.
2. The East Quay wall is designed to accommodate only small
1614
1615
1616
-
Mazagon Dock Limited
Mazdock Modernation Project 8
Document No. 3H6543/R007Final Issue Rev 1
November 2003
vessels. Small boat access stairs landing will be provided for this
purpose. See section 1.7
3. East Quay (South) houses the gate winch chamber, the
pumphouse and the valve chamber. All the chambers are located within the body of the East Quay (South) wall.
1.5.9 West Quay
1. The West Quay is in four distinct sections: West Quay (South)
which is to the south of the South Quay, outside the basin; West
Quay (North-A), West Quay (North-B) and West Quay (North-C)
which are within the basin between the South Quay and the
submarine dry dock roundhead.
2. The width of the West Quay deck structures is generally 12m.
3. The West Quay walls are designed to accommodate only small
vessels. Two sets of small boat access stairs within the basin and one set outside the basin are provided for this purpose.
4. The West Quay forms the interface between the Wet Basin
contract and the land side contracts.
1619
1620
1621
1622
1623
1624
1.6 Deck Fittings and Features
1.6.1 General
A schedule of the deck fittings and features is included in Appendix G.
1.6.2 Fenders
MDL have specified that the fenders for the wet basin shall be arch
type fenders. This type of fender results in relatively high hull contact
pressures. Therefore, in order to prevent damage to the thin hulls of
frigates during berthing, the berthing velocities must be kept low by
very careful berthing operations.
The fender sizes have therefore been chosen based on the normal
berthing of merchant vessels or SLB’s.
The proposed Fenders are as follows:
1. North Quay, North side (sea side)
Due to the limit on protrusion from the quay face, the fenders will
be 500mm deep arch fenders (e.g. Bridgestone SM500H). These
are mounted vertically at 7.5m centres and horizontally in between
at 7.5m centres in a single line at the top of the wall.
2. North Quay, South side (basin side)
Fenders will be arch fenders (e.g. Bridgestone SM600H) mounted
vertically at 7.5m centres.
3. South Quay, North side (basin side)
Fenders will be arch fenders (e.g. Bridgestone SM600H) mounted
at the ends of the buttresses at 7.5m centres. The fenders will extend from +4.55m CD to +1.85m CD.
4. South Quay, South side (sea side)
1601
9004
9002
1613
1614
1616
1617
1619
1620
1622
1623
1624
1625
1626
1627
1628
1629
1630
1641
-
Mazagon Dock Limited
Mazdock Modernation Project 9
Document No. 3H6543/R007Final Issue Rev 1
November 2003
Fenders will be arch fenders (e.g. Bridgestone SM500H). These
are mounted vertically at 7.5m centres. Due to the tidal range the
fenders will extend down to +1m CD.
5. West Quay and East Quay (basin side) Fenders will be arch fenders (e.g. Bridgestone SM400H).
6. West Quay South
Fenders will be arch fenders. (e.g. Bridgestone SM500H).
7. East Quay (sea side)
Fenders will be arch fenders. (e.g. Bridgestone SM500H).
8. East Quay (Basin side)
Fenders will be arch fenders. (e.g. Bridgestone SM400H).
9. Lead-in jetty
Fenders will be a combination of cone fenders (e.g. Fentek SCN
900 / 1100) with front panels mounted on each of the dolphin
structures. Horizontally mounted “D” fenders, 500mm deep, will be
provided around the cone fenders, covering the front chamfered
faces of the dolphins. The fenders shall be mounted at
approximately 1.5m vertical centres. The outermost dolphin shall
have similar fenders fixed to the eastern face of the concrete
structure. The main cone fenders will be designed for an abnormal
berthing velocity of 0.5m/s.
10. Entrance - Horizontally mounted arch fenders (e.g. Bridgestone
SM500H). Vertically mounted arch fenders (e.g. Bridgestone
SM600H) will be mounted on the chamfered faces of the entrance
structure.
11. All fenders shall be fixed to the concrete structures with proprietary
marine grade stainless steel fixings. Generally threaded sockets
shall be cast into / fixed into the concrete.
1.6.3 Capstans
1. 10 tonne capstans are provided for assisting the handling of
vessels. 10 No. capstans are provided around the wet basin and
lead-in jetty at locations shown on the drawings. The capstans are
electric driven with the horizontally mounted motors recessed
below deck level.
2. MDL have a preference for a capstan that stands approximately
1.0m high, with a drum height of approximately 0.65m. The motor
and gearbox should be located in a covered pit next to the capstan
such that maintenance of the motor can be undertaken without
removing the capstan drum. A footbrake is to be provided via an
umbilical control.
3. The capstan brake shall remain activated when not in use.
4. Capstans are to operate in both directions with 2 - 3 speed levels.
1601
1.6.4 Bollards
1. 40 tonne capacity bollards are provided at a spacing of generally
22.5m along the edges of the wet basin, except for the south side
1601
-
Mazagon Dock Limited
Mazdock Modernation Project 10
Document No. 3H6543/R007Final Issue Rev 1
November 2003
of the South Quay where the spacing is increased to 30m. MDL
have requested cast iron type bollards.
2. Three 40 tonne capacity bollards are to be provided on the West
Quay (South) as indicated on the drawings.
3. Similar 40 tonne cast iron bollards will be provided on each of the
lead-in jetty dolphins.
4. A single 100 tonne bollard is provided for the purpose of engine
testing and is located at the east end of the South Quay. This
bollard type is embedded steel tubular, filled with concrete and
with solid steel crossbars. The edge of the quay adjacent to this
bollard shall be rounded to prevent damage to the test ropes.
1.6.5 Cable Access Slots
In a central location along the South Quay, two cable access slots will
be provided to allow cables from portable equipment to pass beneath
the crane rails and into the service gallery. The slots shall be 300mm
high and 1000mm wide. The two slots shall be 2.0m between the
centres. The entry to the slot on top of the quay shall be covered with
a suitable galvanised cover, set flush with the deck and be capable of
carrying the quay loading.
1.6.6 Handrailing
1. Handrailing is generally not provided around the edge of the Wet
Basin quay structures. There are no statutory requirements for
such handrails.
2. Handrailing is provided on the walkways between the lead-in jetty
dolphins.
3. Collapsible Handrailing will be provided around the edge of the
small boat access stairs. See section 1.7.
1641
1.6.7 Deck Drainage
1. The surface of the quay decks have shallow gradient slopes to
facilitate the drainage of rain and other surface water off the quays.
The gradients are generally between 1 in 50 and 1 in 100. Water
will either flow directly off the edge of the quay or will discharge
through drainage gullies spaced at 15m along the length of the
deck.
2. The outer edges of the quay have been detailed with falls away
from the edge of the quay. This is to prevent tools or other
equipment rolling over the edge of the quay. Notches are provided
to allow drainage.
1611
1617
1619
1620
1623
1626
1.6.8 Overflow Pipes
In order to prevent the water level in the basin rising above the top of
the submarine dry dock gate following heavy rainfall, overflow pipes
are provided through the wet basin walls at 15m spacing. These are
set at with the pipe invert at +5.5m CD which is above highest tide
level but is below the top of the dock gate. The diameter of the pipes
1611
1614
1617
-
Mazagon Dock Limited
Mazdock Modernation Project 11
Document No. 3H6543/R007Final Issue Rev 1
November 2003
is 500mm.
1.6.9 Emergency Ladders
Emergency ladders provide a means for persons to escape from the
water after accidentally falling in. Ladders are at 30m spacing along
the edge of the quay walls. The ladders are either recessed into the
wall or have timber protection strips either side of the ladder to protect
the ladder from damage by vessels. Ladders will be fabricated from
galvanised mild steel to enable easy maintenance / replacement by
MDL in the future.
1611
1.6.10 Tide Gauges
Two timber tide gauges will be provided on the East Quay (South)
near the basin entrance. One will be on the seaward side and the
other on the basin side.
1601
1.6.11 Transit Marker
A transit marker shall be provided on the East Quay (North) adjacent
to the basin entrance. The marker will consist of an 8m high tower
with a diamond shaped marker at the top. MDL will finalise and
provide the location of the second, land based, marker when the basin
has been completed.
1601
1.6.12 Office Space
Since on the quay wall no permanent structure can be created, it is
suggested that MDL procure Portacabins of approximately 3m x 12m
dimensions for placement where required. It is further suggested that
these 12No. could be provided along the South Quay and 6No. on the
North Quay. A locked storage space for safe keeping of fittings and
special tools for minor maintenance as required by MDL may also be
provided in one of the Portacabins that MDL would procure / place on
quay walls.
1.6.13 Fire Tender Bays
As discussed in section 1.16.3 below, fire hydrants with a direct
connection to the wet basin are provided along the wet basin South
Quay and North Quay at 15m centres. The deck surface shall be
marked with a hatched area to leave clear for fire tenders at each
location. The bay shall be orientated at 45 degrees to the line of the
quay and shall be 3m wide.
1.7 Small Boat Access Stairs
1.7.1 Re-statement of Function
Small boat access stairs provide an easy and safe means of access to
small boats.
1641
1.7.2 Location
4 sets of access stairs are provided at the following locations:
1601
-
Mazagon Dock Limited
Mazdock Modernation Project 12
Document No. 3H6543/R007Final Issue Rev 1
November 2003
• 2 sets inside the basin at West Quay North B and West Quay
North C.
• 2 sets outside the basin at West Quay South and East Quay
South.
• An access ladder will be provided at the East Quay North where
provision of access stairs is made more awkward by the
suspended deck in this area.
1.7.3 Main Features
1. The sets of stairs inside the basin extend to +2.6m CD
2. The sets of stairs outside the basin extend to +0.9m CD
3. The stairs are recessed into the mass concrete walls of the quays.
4. The stairs are 1.0m wide with a handrail on the wall side of the
stairs. MDL require this handrail to be made from wrought iron for
its corrosion resistant properties.
5. Collapsible handrailing will be provided around the top edge of the
stairs.
6. The steps will be non-slip concrete
7. Mooring rings will be provided for tying up of small vessels.
1641
1.8 Basin Entrance Works
1.8.1 Re-statement of Function
The entrance works provide the gate abutment, gate quoins, gate sill,
gate apron and commencement to the lead-in jetty.
1.8.2 Main Features
1. The clear width of the entrance between the fendering is 30m.
The width between concrete faces of the abutments is 31m.
2. Horizontal arch fenders are provided on the face of the gate
abutments.
3. Roller fenders are provided at the outer corners of the entrance
structure.
4. Gate jambs and sill are reinforced concrete structures, built as
stage 2 concrete.
5. Quoin stones are pre-cast concrete units with stainless steel face
plates.
6. The level of the sill is -5.0mCD.
7. The sill structure has a silt jetting system connected to one of the
impounding pumps.
8. The sill structure houses the gate bearing castings.
9. The apron structure incorporates the gate rests to support the gate
when it is in the ‘down’ position and reverse load support posts to
-
Mazagon Dock Limited
Mazdock Modernation Project 13
Document No. 3H6543/R007Final Issue Rev 1
November 2003
prevent the bottom of the gate moving under a reverse head.
10. Suitable tide and Basin water level gauges will be installed near
the Basin entrance on the East Quay structures.
1.9 Construction Methods
1.9.1 Temporary Cofferdam
1. The construction of the Stage 2 wet basin walls and the entrance
works will be carried out in the dry. A contractor-designed and
installed temporary cofferdam will be used for this purpose. The
design of the contractors cofferdam will be reviewed by HNBV, but
the responsibility for its adequacy will remain with the contractor.
This remains the case for all the contractors temporary works.
2. The profile of the north gate abutment at the east quay has been
chosen to also form an abutment of the cofferdam.
1.9.2 Construction of Basin Walls Underwater
1. The Stage 1 wet basin walls, which are generally 10m thick
(except on the East Quay South where the walls are 14m thick),
will be constructed by placing concrete underwater within a
controlled environment. The controlled environment may be
created by placing steel shutter box or equivalent, extending from
bed level to above high water level in which silt will be removed
and into which filtered, silt-free seawater will be pumped.
2. The contractor, in the “clean water” environment, can then clean
the founding rock to the satisfaction of the Engineer. It is
envisaged that a combination of air-lifting and water jetting will
enable the contractor to remove any sediments over the rock to a
sufficient degree to achieve a sound foundation for the mass
concrete walls. Proof of the cleanliness of the rock surface will be
proven by the use of underwater video.
3. The concrete will be placed underwater by tremie pipe with shear
keys provided at all horizontal and vertical joints. Each section of
wall will be cast the full width of the Stage 1 wall so that there are
no vertical joints running parallel to the length of the walls.
4. The contract specification will define the requirements of placing
concrete underwater by a tremie pipe.
5. The cleanliness of horizontal “day joints” will also be an important
factor to specify correctly to ensure that any laitence is removed
before fresh concrete is placed on top.
1.10 Wet Basin Gate
Please refer to Section Error! Reference source not found. (Wet Basin Gate Contract)
-
Mazagon Dock Limited
Mazdock Modernation Project 14
Document No. 3H6543/R007Final Issue Rev 1
November 2003
1.11 Impounding Pumps and Housing
1.11.1 Re-statement of Function
The impounding pumps are designed to raise the level of water within
the confines of the Wet Basin to maintain water level control. This
function may be necessary because of water loss by evaporation,
leakage through the Basin walls, leakage past the gate, loss through
underlying rock permeability, or generally after the gate has been
opened and closed following entry or exit of a vessel or vessels.
1605
1.11.2 Location
The impounding pumps and their electric motors are located within the
Pump House adjacent to the Valve Chamber and Gate Winch
Chamber in the structure of the East Quay (South) wall.
1601
1.11.3 Main Features
The main features of the impounding pumps are as follows :-
1. 3 (three) No. approximately 600 mm internal diameter self-priming
centrifugal pumps, housed in a dry chamber, with connected inlet
and discharge pipework passing through the walls of the chamber
structure.
2. Each of the three pumps is designed to discharge an average of
4,000 m3 per hour against the varying head conditions. The
pumping system for normal usage is based on two duty pumps
with one standby pump on a rotating duty basis.
3. Each pump is designed to discharge to the Wet Basin through
siphonic discharge to improve pump efficiency and to minimise
accidental pump house flooding risks.
4. The pumps are designed with an intake pipe-culvert of 1.0m
internal diameter and a discharge of approximately 600mm
diameter, tapered expanding over the last 1.5 m to 1.0 m at final
discharge for two pumps. The intake pipe will end in a 90 degree
bend facing downward with a bottom level of +1.0m CD. This pipe
bend may project beyond the face of the wall by up to 1.3m.
5. The third pump is designed to discharge through approximately
600mm diameter pipework, reducing to nozzles located along the
Basin side face of the sill to act as a jetting system for silt disturbance in the gate pit.
6. Each pump may be isolated by means of a gate valve on the
intake side and an engineered stoplog. The stoplogs are housed
within the sea-side walls of the pump house together with
removable trash screens. The screens are removed for
maintenance purposes or installed, in the case of the stoplogs, by
using the Level Luffing crane on the South Quay.
7. The associated electrical switchgear and panels are housed within
a watertight room below the deck of the East Quay (South) wall,
directly beneath the transformer room.
8. The centre-line level of each pump intake is to be defined by the
1605
-
Mazagon Dock Limited
Mazdock Modernation Project 15
Document No. 3H6543/R007Final Issue Rev 1
November 2003
physical size of the pump, but it is expected that the top of the
pump volute will be at around +2.0m CD to ensure the pump is self
primed at the minimum pumping level of +2.5m CD.
9. Large reinforced concrete ‘lift-off’ cover slabs set within the deck
permit the complete withdrawal of a pump and associated
equipment for maintenance. The lift-off covers are within reach of
the 100t level luffing crane on the South Quay wall
10. Man access to the pump house is by means of a staircase housing
on the deck, adjacent to the Control Building on the East Quay
(South) wall, and by robust galvanised steel companionway stairs
with safety landings and handrails. An emergency exit is provided
by a ladder located beneath the above ground transformer house
on the quay. Access to this ladder is through the valve chamber.
11. A travelling hoist of 5 tonne capacity will be arranged over the
pumps and motors if required for routine maintenance.
12. The base slab of the pump house will have falls on the floor to
perimeter drain channels, culminating in a small pump sump
suitable for a house pump. The discharge from this pump will be
arranged direct to the Wet Basin.
13. Each siphon will be equipped with a pump-supplier designed ‘fail-
safe’ siphon breaker valve. These breaker valves will be
accommodated in the open on a low raised plinth on the deck
adjacent to the Wet Basin edge.
14. Forced ventilation will be arranged to maintain cooler air through
the pump house and pumps during running periods, with a discharge to atmosphere at deck level.
1.11.4 Electrical Services
Electrical power services to the pump house are as follows :-
1. Power for the pump motors
2. Power for the pump intake gate valves
3. Power for the pump siphon breaker valves
4. Power for controls and instrumentation
5. Power for lighting and emergency lighting
6. Power for small submersible house-pumps when required
7. General power for hand tools and socket outlets
8. Data link cabling to the MDL Yard Control Room if necessary.
MDL to confirm this requirement.
1.11.5 Mechanical and Piped Services
Mechanical and piped services to the pump house are as follows :-
1. Manually operated overhead travelling hoist
2. Compressed air outlet for cleaning purposes
3. Fire hydrants inside and portable fire hose reel system.
4. Hand-held fire extinguishers of appropriate type.
1.12 Equalising Valves and Housing
-
Mazagon Dock Limited
Mazdock Modernation Project 16
Document No. 3H6543/R007Final Issue Rev 1
November 2003
1.12.1 Re-statement of Function
The valve-controlled pipe-culverts, that bypass the gate, are designed
to assist in the control of water levels within the Basin. The use of the
pipe-culverts is only available when the head difference is operating in
the desired direction. The valve type has been selected to operate
equally efficiently for flows into and out of the Basin
1.12.2 Location
The valves and their actuating motors are located within the Valve
Chamber adjacent to the Impounding Pump House in the structure of
the East Quay (South) wall
1605
1.12.3 Main Features
The main features of the equalising valves are as follows :-
1. 2 (two) No. 1.2 m internal diameter gate valves housed in a dry
chamber, with connected inlet and discharge pipework passing
through the walls of the chamber structure.
2. Each of the two valves is designed to discharge an average of a
minimum of 4,000 m3 per hour at neap tides
3. Each valve is operated to open/close by electrically powered
actuators mounted directly on top of the valve body, and controlled
either remotely from the Basin-side control room or from within the
valve chamber.
4. Each valve may be isolated by means of two engineered stoplogs,
one on each side of the valve. The stoplogs are housed within the
walls of the valve chamber. A removable trash screen is to be
provided on the seaward side of the valves.
5. The associated electrical switchgear and panels are housed within
a watertight room below the deck of the East Quay (South) wall,
directly beneath the transformer room.
6. The centre line level of each of the pipe-culverts is set at +2.0m
CD.
7. Large reinforced concrete ‘lift-off’ cover slabs set within the deck
permit the complete withdrawal of a valve and associated
equipment for maintenance. The lift-off covers are within reach of
the 100t level luffing crane on the South Quay wall
8. Man access to the valve chamber is by means of an adjacent
staircase housing on the deck of the East Quay (South) wall, and
by robust vertical galvanised steel ladders with safety hoops.
9. A travelling hoist will be arranged over the valves and actuators of
5tonne capacity.
10. The base slab of the valve chamber will have falls on the floor to
perimeter drain channels, culminating in a small pump sump
suitable for a house pump. The discharge from this pump will be
arranged direct to the Wet Basin.
1605
1.12.4 Electrical Services
Electrical power supplies to the valve chamber are as follows :- 1. Power for the valve actuators
2. Power for controls and instrumentation
-
Mazagon Dock Limited
Mazdock Modernation Project 17
Document No. 3H6543/R007Final Issue Rev 1
November 2003
3. Power for lighting and emergency lighting
4. Power for small submersible house-pumps when required
5. General power for hand tools and socket outlets
6. Data link cabling to the MDL Yard Control Room if necessary.
1.12.5 Mechanical and Piped Services
Mechanical and piped services to the valve chamber are as follows :-
1. Manually operated overhead travelling hoist
2. Compressed air outlet for cleaning purposes
3. Fire hydrants inside and portable fire hose reel system.
4. Hand-held fire extinguishers of appropriate type.
1.13 Cranes
Please refer to Sections Error! Reference source not found. and
Error! Reference source not found. (100t and 15t Level Luffing
crane Contracts)
1.14 Lead-in Jetty
1.14.1 Re-statement of Function
A lead-in jetty provides assistance to the entry/exit of the Basin,
particularly with currents and wind on the broadside of vessels.
1.14.2 Location
The lead-in jetty is located on the north side of the basin entrance and
is orientated such that it is perpendicular to the east quay.
1601
1.14.3 Main Features
1. The lead-in jetty comprises three mass concrete dolphins,
approximately 15 x 15 m and spaced at 30m centres.
2. The total length of the lead-in jetty is 96m measured from the face
of the East Quay.
3. Access between the dolphins is by means of steel or reinforced
concrete pedestrian access walkways. For operational reasons,
handrails will be provided only on the north side of the walkways.
The walkways will be 2.0m wide.
4. Each dolphin has a 40 tonne bollard
5. The outer dolphin has a 10 tonne capstan
6. As well as general lighting, the dolphins will have navigation lights.
1.15 Electrical Services
-
Mazagon Dock Limited
Mazdock Modernation Project 18
Document No. 3H6543/R007Final Issue Rev 1
November 2003
1.15.1 Re-statement of Function
Electrical services for the Wet Basin comprise the following:
1. Power supplies to DSU’s 2. Power supplies to cranes
3. Power supplies to plantrooms.
4. Power supplies to capstans
5. Lighting
6. Telecommunication cabling.
7. Data cabling.
1.15.2 Wet Basin Substations
1. The main Wet Basin substation is located at the east end of the
South Quay, designated Substation “C”. The incoming HT supply
will come from Substation A.
2. A second electrical switchroom housing only LT switchgear is
located on the East Quay (north), designated substation “D”. (The
designation of “substation” refers only to the fact that the room
contains electrical equipment).
3. The power supplies to the Wet Basin will be fed primarily from
Substation C although DSU power supplies for half the south quay
will be fed from Substation B.
1601
1.15.3 Wet Basin Dockside Supply Units (DSU’s)
1. DSU’s will be provided at 15m spacing along the basin side of the
North Quay and along the basin side of the South Quay.
2. DSU’s will be located in surface mounted galvanised steel boxes with hinged doors.
1601
1.15.4 Power Supplies to South Quay DSU’s
The following electrical supplies are provided at DSU’s on the South
Quay:
1. 415V 50Hz 3 phase supply at 100A. Maximum total power for this
supply is 1000 kVA.
2. 230V 50Hz single phase supply at 30A. Maximum total power for
this supply is 200 kVA.
3. 110V 50Hz 3 phase supply at 100A. Maximum total power for this
supply is 300 kVA.
1612
1628
1.15.5 Power Supplies to North Quay DSU’s
The following electrical supplies are provided at DSU’s on the North
Quay:
1. 415V 50Hz 3 phase supply at 400A with 63 Amp, 12 way DB.
1618
1625
-
Mazagon Dock Limited
Mazdock Modernation Project 19
Document No. 3H6543/R007Final Issue Rev 1
November 2003
2. 115V 50Hz 3 phase supply at 63A.
3. 115V 60Hz 3 phase supply at 200A.
4. To be provided at one location at the intersection of the East and
the North Quay:
• 415V 3 phase 50Hz 1250A MCCB with cable termination box
for outgoing cables. (These supplies are required for
submarine battery charging. The battery charging operation
will be carried out for one submarine at a time. The battery
charging duration is 24 to 30 hours. The frequency of battery
charging is once a month).
5. To be provided at two locations along the quay, within larger
DSU's:
• 415V 3 phase 50Hz 300 Amps.
• 220V DC 300 Amps.
1.15.6 Lighting
1. Four high masts located near the corners of the basin will provide
lighting for the wet basin. The masts will be approximately 30m
high lattice masts.
2. Lighting of the lead-in dolphins will be located on lighting poles at
the rear of the dolphins.
3. Strip lighting will be mounted on the lead-in dolphin walkways.
4. The general illumination level for the basin will be 50 lux.
5. The general illumination level for the lead-in jetty dolphins will be
100 lux.
6. The general illumination level of the plant rooms will be 200 lux.
1601
1.15.7 Power Supplies to Plantrooms
The following plantroom power supplies are provided:
1. Pump house for impounding pumps – see Section 1.11.4
2. Valve chamber - see Section 1.12.4
3. Gate winch chamber
4. Substations and control room
1.15.8 Telecommunications Cabling
Cables will be provided to connect the Wet Basin plantrooms to the
main telecommunications network. MDL are to confirm this
requirement.
1.15.9 Data Cabling
Cables will be provided to send data from the Wet Basin plantrooms to
the main control room. MDL are to confirm this requirement.
1.16 Mechanical Services
1.16.1 Re-statement of Function
-
Mazagon Dock Limited
Mazdock Modernation Project 20
Document No. 3H6543/R007Final Issue Rev 1
November 2003
Mechanical services for the Wet Basin comprise the following:
1. Sea water (fire fighting) system
2. Fresh water
3. Compressed air
4. Oxygen as cutting gas
5. Acetylene as cutting gas
1.16.2 Location of Pipework
The piped services for the Wet Basin will be routed in the services
recesses at the top of the quay walls on the North and South Quay
walls.
1601
1.16.3 Sea Water System
1. The seawater system will provide take-off hydrant connections at
15m spacing along the basin sides of the North Quay and the
South Quay.
2. The nominal pressure will be 8 kg/cm2.
3. In addition to the hydrants, and stand-pipes with hydrant
connection shall be provided to allow a fire tender to pump directly
from the sea. These shall be at the same locations as the
seawater main hydrants.
1612
1618
1.16.4 Fresh Water System
The fresh water system will provide take-off hydrant connections at
15m spacing along the basin sides of the North Quay and the South
Quay.
1612
1618
1.16.5 Compressed Air System
1. The compressed system will provide take-off connections at 15m
spacing along the basin sides of the North Quay and the South
Quay. Three quick release connection points will provided at each
take-off location.
2. The nominal pressure will be 10 kg/cm2.
1612
1618
1.16.6 Oxygen and Acetylene System
Oxygen and acetylene take-off connections will be provided at 15m
spacing along the basin sides of the North Quay and the South Quay. Quick release connection points will provided at each take-off location.
1612
1618
------------------------- End of DPR -------------------------