mazagon dock limited mazdock modernisation...

23
A COMP ANY OF MAZAGON DOCK LIMITED MAZDOCK MODERNISATION PROJECT Contract No. MMP/01006/03 DETAILED PROJECT REPORT FINAL ISSUE Volume 1, Rev 1, 21 st November 2003 HASKONING NEDERLAND BV MARITIME

Upload: others

Post on 13-Feb-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

  • A COMPANY OF

    MAZAGON DOCK LIMITED

    MAZDOCK MODERNISATION PROJECT

    Contract No. MMP/01006/03

    DETAILED PROJECT REPORT

    FINAL ISSUE

    Volume 1, Rev 1, 21st

    November 2003

    HASKONING NEDERLAND BV

    MARITIME

  • A COMPANY OF

    Mazagon Dock Limited

    Project name Mazdock Modernisation Project

    Document title Detailed Project Report Volume 1

    Status Final Issue Revision 1

    Date 21st November 2003

    Royal Haskoning

    Project number 3H6543

    MMP Contract number MMP/01006/03

    Reference 3H6543:R007

    Drafted by D.S. Byrom, S R Davies, R C B Potter

    Checked by P D Gallagher

    Approved by P.D. Gallagher

    Marlborough House

    Marlborough Crescent

    Newcastle upon Tyne NE1 4EE

    United Kingdom

    +44 (0) 191 211 1300 Telephone

    +44 (0) 191 211 1313 Fax

    [email protected] E-mail

    www.royalhaskoning.com Internet

    HASKONING NEDERLAND BV

    MARITIME

  • Mazagon Dock Limited

    Mazdock Modernisation Project

    - i -

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

  • Mazagon Dock Limited

    Mazdock Modernation Project 1

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    MARITIME CIVIL WORKS CONTRACT – the WET BASIN

    1.1 Objectives - Re-Statement

    Stated simply, the primary objectives of the physical infrastructure of the Wet Basin are

    as follows :

    � To improve the cost efficiency and productivity of the Yard in the construction,

    completion and repair of surface and sub-surface naval vessels, and of merchant

    ships as applicable.

    � To provide a enclosed or captive outfitting/repair haven generally for naval vessels

    but also to be available for merchant tonnage when required.

    � To provide a virtually constant yet controllable water level environment such that

    vessels undergoing outfit/re-fit or repair are free from the daily fluctuation in water

    levels due to tides, and with a negligible but assessable risk of bottom damage even

    if the impounding gate is ever breached.

    � To provide the necessary mechanical and electrical services in and around the wet

    basin to enable efficient outfitting of vessels.

    � To be robust and durable in design, requiring minimal maintenance for the design life

    of the facility, expected to be more than 75 years before major structural repair is

    need

    1.2 Introduction

    The text below describes and confirms the decisions made following the acceptance of

    the design concepts as set out in the PPR. Each significant feature is numbered for

    ease of reference and where appropriate, the relevant drawing number is given in the

    third column.

    1.3 Exact Location, Leading Dimensions and Water Levels & Depths

    Wet Basin Feature Drawing No.

    3H6543/DPR/

    1.3.1 Exact Location of Wet Basin

    The final exact location is as finally accepted in the PPR and is such

    that :

    The Wet Basin lies within the limits and constraints imposed by the

    MbPT and CWPRS as far as can be determined accurately.

    Ritchie Dry Dock is outside the Basin, and operates independently

    The North Quay is aligned parallel to the outer faces of the Ritchie

    Dry Dock Extension mitre gate protrusions so as to minimise

    restrictions on vessel entry to Ritchie Dock. The north face of the

    North Quay is set back 500 mm from this base line to allow for

    fenders. The south face (deck edge) is set parallel to the north face

    and commencing from the north corner of the submarine dry dock meeting face.

    The south rail of the South Quay is aligned exactly with the 300 tonne

    Goliath Gantry crane north rail. This then determines the exact

    location of the South Quay

    The East Quay setting-out is found by joining the extremities of the

    North and South Quays

    Setting Out:

    0013

  • Mazagon Dock Limited

    Mazdock Modernation Project 2

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    The Wet Basin Gate opening is set at 40 m from the internal face line

    of the South Quay

    The seaside face of the West Quay (South) wall is set parallel to the

    West Quay (North-A) wall, but with the south east corner on a line

    with the current berth extensions to Slipway No.2. The south face of

    the wall, that closes onto the existing roundhead of crane track no. 9,

    is set 4.0 m north of the north wall of Slipway No. 1 to allow future

    construction by others of an extension to Slipway No. 1

    The Basin side face of the West Quay (North-A) wall intersects the

    existing sea wall at the junction with the line of the South Quay south

    crane rail

    The Basin face of the West Quay (North-B) wall that carries road

    access to the Submarine Dry Dock gate area is set at 8.0 m from the

    face of the existing East Yard boundary wall

    The Basin face of the West Quay (North-C) wall that creates lay-

    down space adjacent to the Submarine Dry Dock gate area is set

    parallel to the face of the existing dry dock caisson gate

    1.3.2 Leading Dimensions of the Wet Basin

    (note : dimensions may be rounded for ease of reference)

    (a) North Quay internal length = 183 m measured from the meeting

    face of the existing submarine dry dock gate

    South Quay internal length = 225 m

    East Quay internal length including gate = 112 m

    Gate opening in East Quay 31 m to permit clear opening of 30 m with

    allowance for rubbing strip fenders

    West Quay (North-A) internal length = 65 m

    Water surface area bounded by the solid faces of the mass concrete

    wall structures = 27,000 m2

    North Quay overall deck width = 10.0 m , with a 5.5 m crane rail track

    gauge

    South Quay overall deck width = 16.5 m with a 10.0 m crane rail track

    gauge

    East Quay (North) and East Quay (South) overall deck width = 14.0

    m

    West Quay (South) overall deck width = 12.0 m

    West Quay (North-A) overall deck width = 12.0 m

    West Quay (North-B) overall deck width = 8.0 m

    West Quay (North-C) overall deck width = 17.0 m

    Closure Wall overall deck width = 5.0 m

    1601

    1.3.3 Water Levels and Water Depths

    The finally agreed water levels and water depths associated with the Wet Basin will be

    :-

  • Mazagon Dock Limited

    Mazdock Modernation Project 3

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    Level to CD

    in metres

    Design nominal finished level of Wet Basin decks (N, E, S) + 7.000 CD

    Design nominal finished level of West Quay decks approx. + 6.500 CD

    Design nominal finished level of Lead-in Jetty Dolphins + 6.500 CD

    Highest astronomical tide (HAT) + 5.400 CD

    Highest recorded tide (HRT) + 5.380 CD

    Maximum normal operating impounded level in Wet Basin + 4.500 CD

    Maximum impounded level in Wet Basin controlled by

    overflow pipe invert level

    + 5.500 CD

    Mean High Water Springs (MHWS) + 4.420 CD

    Mean High Water Neaps (MHWN) +3.300 CD

    Mean Sea Level (MSL) + 2.510 CD

    Minimum normal operating impounded level in Wet Basin + 2.500 CD

    Mean Low Water Neaps (MLWN) +1.850 CD

    Mean Low Water Springs (MLWS) + 0.760 CD

    Minimum emergency water level in Wet Basin = Chart Datum +/- 0.000 CD

    Lowest Recorded Tide (LRT) - 0.440 CD

    Wet Basin Gate sill level - 5.000 CD

    Design excavated level within Wet Basin - 6.000 CD

    Design dredged level outside of Wet Basin North wall As existing

    Design dredged level outside of Wet Basin South wall As existing

    Design dredged level outside of Wet Basin East wall North As existing

    Design dredged level outside of Wet Basin East Wall South for

    full length of quay

    - 6.0m CD to

    existing in 20m

    Design dredged level along Lead-in Jetty, south side - 6.000 CD

    Approx design dredged level of Turning Circle (by Others)* - 3.000 CD

    Minimum level at which impounding pumps will operate +2.5m CD

    Minimum level at which equalising valves will operate +1.5m CD

    Minimum level at which the gate will be opened or closed +2.5m CD

    Water Depth

    in metres

    Maximum normal operating water depth in Wet Basin 11.5 metres

    Minimum normal operating water depth in Wet Basin 8.5 metres

    Emergency minimum water depth in Wet Basin 6.0 metres

    * The Turning Circle will need to be relocated to suit the location of the Wet Basin

    entrance. This should be done before the completion of the Wet Basin. This work is

    outside the scope of the HNBV specification and cost estimates.

    1.4 Dredging, Excavation in the ‘Dry’ and Contamination Issues

    Wet Basin Features Drawing No.

    3H6543/DPR/

    1.4.1 Dredging

    1. For the reasons of economy, quality of work, and flexibility in

    construction including the ability to excavate in parallel with

    constructing the Stage 2 works, sea dredging (involving floating

    dredging plant and possibly the use of controlled explosives, see

    1.4.2 below) will be limited in scope to :

    1642

  • Mazagon Dock Limited

    Mazdock Modernation Project 4

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    (a) dredging minimum areas for Stage 1 wall construction.

    (b) dredging the Lead-in Jetty channel for 200m out toward the

    turning circle.

    (c) Limited dredging of the wet basin area as required for

    construction operations.

    (d) dredging a gradual slope from the face of the East Quay

    (South) wall toward the turning circle for a distance of 20m to

    minimise the effects of siltation on the performance of the

    impounding pumps and discharge valves.

    2. It is presently estimated from the results of the geophysical

    survey and the existing boreholes undertaken in 2002, that the

    quantities of ‘soft’ and ‘hard’ dredging are :-

    • 56,000 m3 of ‘soft’ dredging

    • 30,000 m3 of ‘hard clay’ dredging

    • 70,000 m3 of ‘weathered rock dredging

    3. Unfortunately the seismic survey was not able to establish the

    difference between hard clay and weathered rock. The volume

    of rock excavation has therefore yet to be finalised by further

    geotechnical investigation. The volumes stated above are based

    solely on the limited number of boreholes undertaken in 2002.

    The volumes of hard clay dredging and rock dredging could

    therefore be subject to significant variation.

    1.4.2 Methods of Dredging

    1. In dredging terms, the volumes to be excavated for this project

    are relatively small. The depth of water in which dredging plant is

    able to operate is also very limited across the site area. These

    two factors, together with the materials to be dredged, will

    probably lead the contractor to utilise a barge-mounted backactor

    or a crane operated grab type dredgers.

    2. This equipment will be able to remove the soft silt and the hard

    clay layers and possibly the weathered rock, depending on its

    strength. The dredging arisings will be loaded into a dump barge

    for disposal at the MbPT dump sites.

    3. Rock excavation will probably need to be assisted by controlled

    blasting techniques. To prevent damage to existing MDL

    waterfront structures, the peak particle velocity will be defined by

    initial test blasting.

    4. The need to undertake capital dredging in the approach channel

    to the lead in jetty will be assessed following the further ground

    investigation works discussed in section Error! Reference

    source not found.. If no hard rock is found in the approach

    channel above the -5.0m CD level, MDL will defer the dredging

    until later.

    1.4.3 Excavation in the ‘dry’

  • Mazagon Dock Limited

    Mazdock Modernation Project 5

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    1. Unless the actual contractors tenders show otherwise, it is the

    intention to remove the large majority seabed materials from

    within the Wet Basin area by land excavation techniques in the

    ‘dry’. The ‘dry’ condition will be achieved after the Wet Basin

    Stage 1 water-retaining walls and entrance works temporary

    cofferdam have been completed and the water pumped out. This

    material will be dumped at sea in an approved location.

    2. It is presently estimated from the results of the geophysical

    survey and the existing boreholes undertaken in 2002, that the

    quantities of ‘soft’ and ‘hard’ ‘dry’ excavation are :-

    • 54,000 m3 of ‘soft’ material

    • 40,200 m3 of ‘hard’ material

    • 60,800 m3 of ‘weathered rock dredging

    3. As stated in 1.4.1, the volumes stated above are based solely on

    the limited number of boreholes undertaken in 2002. The

    volumes of hard clay excavation and rock excavation could

    therefore be subject to significant variation.

    1.4.4 Contamination Issues

    In respect of dredging and ‘dry’ excavation procedures will be put in

    place to :-

    • ensure that the materials arising from dredging activities (and

    excavation) are dumped in dumping grounds or tips that are

    approved by the competent Authority, the Mumbai Port Trust

    (MbPT). It is currently understood that MbPT have two

    designated dumping areas, one for dumping dredged materials

    during ebb tides and the other for use during flood tides. The

    location of and Authority for approved land-fill tipping sites is not

    known at present.

    Contaminated materials dumped at sea can seriously harm sea

    life forms, whilst land tipped contaminated materials can

    adversely affect ground water (and hence potable water) quality

    • carry out tests (on samples from the proposed new boreholes) to

    ascertain whether contaminants are likely to be present in the

    dredged/excavated materials. Such contaminants could arise

    from natural sources in the soils or probably more likely from the

    activities of the shipyard over its many years of existence. Tests

    will be essential to determine the levels, if any, of heavy metals

    and organic compounds (eg. TBTs) in particular. The procedure

    will be that appropriate tests will be undertaken and the results

    discussed with MDL prior to deciding the correct course of action

    to be taken.

    1.5 Structural Walls

    1.5.1 Re-statement of Function Drawings:

    1601

  • Mazagon Dock Limited

    Mazdock Modernation Project 6

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    The Stage 1 structural walls have the following functions and

    requirements:

    • main water retaining structures for the wet basin, to keep the water

    level in the basin approximately constant

    • soil retaining structures along the line of the West Quay

    • provision of berthing faces for vessels

    The Stage 2 structures provide the basin side part of the quay walls

    and the top deck structure. This includes plantrooms, services

    trenches and other deck features.

    1602

    1604

    1.5.2 Location

    The setting out of the basin walls is shown on the drawings.

    1602

    1604

    1.5.3 Stage 1 Structural Walls

    1. The Stage 1 Basin walls are mass concrete structures cast

    underwater on the dredged rock surface.

    2. Walls will be constructed within a ‘controlled environment’ to

    minimise the problems associated with placing concrete

    underwater. See section 1.9.2.

    3. Walls will be constructed with each concrete pour being the full

    width of the wall ensuring the wall will act as a monolithic structure.

    4. The walls are designed to resist the following loads:

    • Differential water levels

    • Berthing

    • Imposed deck loads

    • Wave loads

    • Earthquake loads

    • Accidental vessel impact loads

    • Silt level up to 0.0m CD

    5. The founding levels of the basin walls is generally -6.0m CD.

    6. The top of the Stage 1 walls will generally be 1.0m below the final

    deck level. The Stage 1 walls will accommodate recesses for

    plantrooms, services trenches and other features as appropriate.

    7. The width of the Stage 1 walls varies and is shown on the

    drawings.

    8. The walls are designed to resist accidental impact loads from

    vessels in the channel of size up to 3,000 dwt with velocities of up

    to 0.3m/s. Vessels larger than this would run aground before

    reaching the wet basin structures.

    9. The quay walls have been designed to accommodate a silt level of

    up to 0.0m CD on the northern face of the quay. MDL are to

    maintain this as a maximum level by periodic dredging.

    1602

    1.5.4 General Main Features

    1. The Stage 2 structural wall for the East Quay (North) comprises

    1601

    1604

  • Mazagon Dock Limited

    Mazdock Modernation Project 7

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    reinforced concrete pier structures at 7.5m spacing along the

    inside face of the mass concrete wall.

    2. The Stage 2 concrete works on the North Quay consist of the deck

    slab and the services gallery along the basin side of the wall.

    3. The Stage 2 structural wall for the South Quay comprises

    reinforced concrete buttress structures at 7.5m spacing along the

    inside face of the mass concrete wall. The buttresses are 1.7m

    wide and 5.35m deep. There is a gap of 1.75m between the face

    of the mass concrete wall and the inside face of the piers. The

    services gallery on the basin side is included in the Stage 2

    concrete works.

    4. The West Quay (South) and East Quay (South) have no Stage 2

    structural walls although the construction of the pump houses,

    valve and winch chamber and main deck will form part of the

    Stage 2 construction.

    5. The West Quay (South) will be constructed “in the wet”, together

    with West Quay North A and the Closure Wall. West Quay North B

    and C will be constructed in the dry.

    6. The pumphouse structure will be constructed “in the dry”, as part

    of the stage 2 reinforced concrete works.

    1.5.5 Deck Fittings

    See Section 1.6

    1.5.6 North Quay

    1. The width of the North Quay deck structures is 10m.

    2. The North Quay wall is designed to accommodate a range of

    vessels but with the assumption that it will be used primarily for submarines berthed on submarine launch barges (SLB).

    3. The deck loading over the services gallery is 2.5tonnes/m2 (normal

    quay loading).

    1616

    1617

    1618

    1625

    1629

    1630

    1.5.7 South Quay

    1. The width of the South Quay deck structures is 16.5m.

    The South Quay wall is designed to accommodate a range of

    vessels but with the assumption that it will be used primarily for

    frigates and other surface vessels.

    2. MDL have now confirmed that the southern side of the quay will not be used for berthing.

    3. The deck loading over the services gallery is 2.5tonnes/m2 (normal

    quay loading).

    4. An underground electrical switchroom is located at the east end of

    the South Quay

    1610

    1611

    1612

    1626

    1627

    1628

    1.5.8 East Quay

    1. The width of the East Quay (North) and East Quay (South) deck

    structures is 14m.

    2. The East Quay wall is designed to accommodate only small

    1614

    1615

    1616

  • Mazagon Dock Limited

    Mazdock Modernation Project 8

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    vessels. Small boat access stairs landing will be provided for this

    purpose. See section 1.7

    3. East Quay (South) houses the gate winch chamber, the

    pumphouse and the valve chamber. All the chambers are located within the body of the East Quay (South) wall.

    1.5.9 West Quay

    1. The West Quay is in four distinct sections: West Quay (South)

    which is to the south of the South Quay, outside the basin; West

    Quay (North-A), West Quay (North-B) and West Quay (North-C)

    which are within the basin between the South Quay and the

    submarine dry dock roundhead.

    2. The width of the West Quay deck structures is generally 12m.

    3. The West Quay walls are designed to accommodate only small

    vessels. Two sets of small boat access stairs within the basin and one set outside the basin are provided for this purpose.

    4. The West Quay forms the interface between the Wet Basin

    contract and the land side contracts.

    1619

    1620

    1621

    1622

    1623

    1624

    1.6 Deck Fittings and Features

    1.6.1 General

    A schedule of the deck fittings and features is included in Appendix G.

    1.6.2 Fenders

    MDL have specified that the fenders for the wet basin shall be arch

    type fenders. This type of fender results in relatively high hull contact

    pressures. Therefore, in order to prevent damage to the thin hulls of

    frigates during berthing, the berthing velocities must be kept low by

    very careful berthing operations.

    The fender sizes have therefore been chosen based on the normal

    berthing of merchant vessels or SLB’s.

    The proposed Fenders are as follows:

    1. North Quay, North side (sea side)

    Due to the limit on protrusion from the quay face, the fenders will

    be 500mm deep arch fenders (e.g. Bridgestone SM500H). These

    are mounted vertically at 7.5m centres and horizontally in between

    at 7.5m centres in a single line at the top of the wall.

    2. North Quay, South side (basin side)

    Fenders will be arch fenders (e.g. Bridgestone SM600H) mounted

    vertically at 7.5m centres.

    3. South Quay, North side (basin side)

    Fenders will be arch fenders (e.g. Bridgestone SM600H) mounted

    at the ends of the buttresses at 7.5m centres. The fenders will extend from +4.55m CD to +1.85m CD.

    4. South Quay, South side (sea side)

    1601

    9004

    9002

    1613

    1614

    1616

    1617

    1619

    1620

    1622

    1623

    1624

    1625

    1626

    1627

    1628

    1629

    1630

    1641

  • Mazagon Dock Limited

    Mazdock Modernation Project 9

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    Fenders will be arch fenders (e.g. Bridgestone SM500H). These

    are mounted vertically at 7.5m centres. Due to the tidal range the

    fenders will extend down to +1m CD.

    5. West Quay and East Quay (basin side) Fenders will be arch fenders (e.g. Bridgestone SM400H).

    6. West Quay South

    Fenders will be arch fenders. (e.g. Bridgestone SM500H).

    7. East Quay (sea side)

    Fenders will be arch fenders. (e.g. Bridgestone SM500H).

    8. East Quay (Basin side)

    Fenders will be arch fenders. (e.g. Bridgestone SM400H).

    9. Lead-in jetty

    Fenders will be a combination of cone fenders (e.g. Fentek SCN

    900 / 1100) with front panels mounted on each of the dolphin

    structures. Horizontally mounted “D” fenders, 500mm deep, will be

    provided around the cone fenders, covering the front chamfered

    faces of the dolphins. The fenders shall be mounted at

    approximately 1.5m vertical centres. The outermost dolphin shall

    have similar fenders fixed to the eastern face of the concrete

    structure. The main cone fenders will be designed for an abnormal

    berthing velocity of 0.5m/s.

    10. Entrance - Horizontally mounted arch fenders (e.g. Bridgestone

    SM500H). Vertically mounted arch fenders (e.g. Bridgestone

    SM600H) will be mounted on the chamfered faces of the entrance

    structure.

    11. All fenders shall be fixed to the concrete structures with proprietary

    marine grade stainless steel fixings. Generally threaded sockets

    shall be cast into / fixed into the concrete.

    1.6.3 Capstans

    1. 10 tonne capstans are provided for assisting the handling of

    vessels. 10 No. capstans are provided around the wet basin and

    lead-in jetty at locations shown on the drawings. The capstans are

    electric driven with the horizontally mounted motors recessed

    below deck level.

    2. MDL have a preference for a capstan that stands approximately

    1.0m high, with a drum height of approximately 0.65m. The motor

    and gearbox should be located in a covered pit next to the capstan

    such that maintenance of the motor can be undertaken without

    removing the capstan drum. A footbrake is to be provided via an

    umbilical control.

    3. The capstan brake shall remain activated when not in use.

    4. Capstans are to operate in both directions with 2 - 3 speed levels.

    1601

    1.6.4 Bollards

    1. 40 tonne capacity bollards are provided at a spacing of generally

    22.5m along the edges of the wet basin, except for the south side

    1601

  • Mazagon Dock Limited

    Mazdock Modernation Project 10

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    of the South Quay where the spacing is increased to 30m. MDL

    have requested cast iron type bollards.

    2. Three 40 tonne capacity bollards are to be provided on the West

    Quay (South) as indicated on the drawings.

    3. Similar 40 tonne cast iron bollards will be provided on each of the

    lead-in jetty dolphins.

    4. A single 100 tonne bollard is provided for the purpose of engine

    testing and is located at the east end of the South Quay. This

    bollard type is embedded steel tubular, filled with concrete and

    with solid steel crossbars. The edge of the quay adjacent to this

    bollard shall be rounded to prevent damage to the test ropes.

    1.6.5 Cable Access Slots

    In a central location along the South Quay, two cable access slots will

    be provided to allow cables from portable equipment to pass beneath

    the crane rails and into the service gallery. The slots shall be 300mm

    high and 1000mm wide. The two slots shall be 2.0m between the

    centres. The entry to the slot on top of the quay shall be covered with

    a suitable galvanised cover, set flush with the deck and be capable of

    carrying the quay loading.

    1.6.6 Handrailing

    1. Handrailing is generally not provided around the edge of the Wet

    Basin quay structures. There are no statutory requirements for

    such handrails.

    2. Handrailing is provided on the walkways between the lead-in jetty

    dolphins.

    3. Collapsible Handrailing will be provided around the edge of the

    small boat access stairs. See section 1.7.

    1641

    1.6.7 Deck Drainage

    1. The surface of the quay decks have shallow gradient slopes to

    facilitate the drainage of rain and other surface water off the quays.

    The gradients are generally between 1 in 50 and 1 in 100. Water

    will either flow directly off the edge of the quay or will discharge

    through drainage gullies spaced at 15m along the length of the

    deck.

    2. The outer edges of the quay have been detailed with falls away

    from the edge of the quay. This is to prevent tools or other

    equipment rolling over the edge of the quay. Notches are provided

    to allow drainage.

    1611

    1617

    1619

    1620

    1623

    1626

    1.6.8 Overflow Pipes

    In order to prevent the water level in the basin rising above the top of

    the submarine dry dock gate following heavy rainfall, overflow pipes

    are provided through the wet basin walls at 15m spacing. These are

    set at with the pipe invert at +5.5m CD which is above highest tide

    level but is below the top of the dock gate. The diameter of the pipes

    1611

    1614

    1617

  • Mazagon Dock Limited

    Mazdock Modernation Project 11

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    is 500mm.

    1.6.9 Emergency Ladders

    Emergency ladders provide a means for persons to escape from the

    water after accidentally falling in. Ladders are at 30m spacing along

    the edge of the quay walls. The ladders are either recessed into the

    wall or have timber protection strips either side of the ladder to protect

    the ladder from damage by vessels. Ladders will be fabricated from

    galvanised mild steel to enable easy maintenance / replacement by

    MDL in the future.

    1611

    1.6.10 Tide Gauges

    Two timber tide gauges will be provided on the East Quay (South)

    near the basin entrance. One will be on the seaward side and the

    other on the basin side.

    1601

    1.6.11 Transit Marker

    A transit marker shall be provided on the East Quay (North) adjacent

    to the basin entrance. The marker will consist of an 8m high tower

    with a diamond shaped marker at the top. MDL will finalise and

    provide the location of the second, land based, marker when the basin

    has been completed.

    1601

    1.6.12 Office Space

    Since on the quay wall no permanent structure can be created, it is

    suggested that MDL procure Portacabins of approximately 3m x 12m

    dimensions for placement where required. It is further suggested that

    these 12No. could be provided along the South Quay and 6No. on the

    North Quay. A locked storage space for safe keeping of fittings and

    special tools for minor maintenance as required by MDL may also be

    provided in one of the Portacabins that MDL would procure / place on

    quay walls.

    1.6.13 Fire Tender Bays

    As discussed in section 1.16.3 below, fire hydrants with a direct

    connection to the wet basin are provided along the wet basin South

    Quay and North Quay at 15m centres. The deck surface shall be

    marked with a hatched area to leave clear for fire tenders at each

    location. The bay shall be orientated at 45 degrees to the line of the

    quay and shall be 3m wide.

    1.7 Small Boat Access Stairs

    1.7.1 Re-statement of Function

    Small boat access stairs provide an easy and safe means of access to

    small boats.

    1641

    1.7.2 Location

    4 sets of access stairs are provided at the following locations:

    1601

  • Mazagon Dock Limited

    Mazdock Modernation Project 12

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    • 2 sets inside the basin at West Quay North B and West Quay

    North C.

    • 2 sets outside the basin at West Quay South and East Quay

    South.

    • An access ladder will be provided at the East Quay North where

    provision of access stairs is made more awkward by the

    suspended deck in this area.

    1.7.3 Main Features

    1. The sets of stairs inside the basin extend to +2.6m CD

    2. The sets of stairs outside the basin extend to +0.9m CD

    3. The stairs are recessed into the mass concrete walls of the quays.

    4. The stairs are 1.0m wide with a handrail on the wall side of the

    stairs. MDL require this handrail to be made from wrought iron for

    its corrosion resistant properties.

    5. Collapsible handrailing will be provided around the top edge of the

    stairs.

    6. The steps will be non-slip concrete

    7. Mooring rings will be provided for tying up of small vessels.

    1641

    1.8 Basin Entrance Works

    1.8.1 Re-statement of Function

    The entrance works provide the gate abutment, gate quoins, gate sill,

    gate apron and commencement to the lead-in jetty.

    1.8.2 Main Features

    1. The clear width of the entrance between the fendering is 30m.

    The width between concrete faces of the abutments is 31m.

    2. Horizontal arch fenders are provided on the face of the gate

    abutments.

    3. Roller fenders are provided at the outer corners of the entrance

    structure.

    4. Gate jambs and sill are reinforced concrete structures, built as

    stage 2 concrete.

    5. Quoin stones are pre-cast concrete units with stainless steel face

    plates.

    6. The level of the sill is -5.0mCD.

    7. The sill structure has a silt jetting system connected to one of the

    impounding pumps.

    8. The sill structure houses the gate bearing castings.

    9. The apron structure incorporates the gate rests to support the gate

    when it is in the ‘down’ position and reverse load support posts to

  • Mazagon Dock Limited

    Mazdock Modernation Project 13

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    prevent the bottom of the gate moving under a reverse head.

    10. Suitable tide and Basin water level gauges will be installed near

    the Basin entrance on the East Quay structures.

    1.9 Construction Methods

    1.9.1 Temporary Cofferdam

    1. The construction of the Stage 2 wet basin walls and the entrance

    works will be carried out in the dry. A contractor-designed and

    installed temporary cofferdam will be used for this purpose. The

    design of the contractors cofferdam will be reviewed by HNBV, but

    the responsibility for its adequacy will remain with the contractor.

    This remains the case for all the contractors temporary works.

    2. The profile of the north gate abutment at the east quay has been

    chosen to also form an abutment of the cofferdam.

    1.9.2 Construction of Basin Walls Underwater

    1. The Stage 1 wet basin walls, which are generally 10m thick

    (except on the East Quay South where the walls are 14m thick),

    will be constructed by placing concrete underwater within a

    controlled environment. The controlled environment may be

    created by placing steel shutter box or equivalent, extending from

    bed level to above high water level in which silt will be removed

    and into which filtered, silt-free seawater will be pumped.

    2. The contractor, in the “clean water” environment, can then clean

    the founding rock to the satisfaction of the Engineer. It is

    envisaged that a combination of air-lifting and water jetting will

    enable the contractor to remove any sediments over the rock to a

    sufficient degree to achieve a sound foundation for the mass

    concrete walls. Proof of the cleanliness of the rock surface will be

    proven by the use of underwater video.

    3. The concrete will be placed underwater by tremie pipe with shear

    keys provided at all horizontal and vertical joints. Each section of

    wall will be cast the full width of the Stage 1 wall so that there are

    no vertical joints running parallel to the length of the walls.

    4. The contract specification will define the requirements of placing

    concrete underwater by a tremie pipe.

    5. The cleanliness of horizontal “day joints” will also be an important

    factor to specify correctly to ensure that any laitence is removed

    before fresh concrete is placed on top.

    1.10 Wet Basin Gate

    Please refer to Section Error! Reference source not found. (Wet Basin Gate Contract)

  • Mazagon Dock Limited

    Mazdock Modernation Project 14

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    1.11 Impounding Pumps and Housing

    1.11.1 Re-statement of Function

    The impounding pumps are designed to raise the level of water within

    the confines of the Wet Basin to maintain water level control. This

    function may be necessary because of water loss by evaporation,

    leakage through the Basin walls, leakage past the gate, loss through

    underlying rock permeability, or generally after the gate has been

    opened and closed following entry or exit of a vessel or vessels.

    1605

    1.11.2 Location

    The impounding pumps and their electric motors are located within the

    Pump House adjacent to the Valve Chamber and Gate Winch

    Chamber in the structure of the East Quay (South) wall.

    1601

    1.11.3 Main Features

    The main features of the impounding pumps are as follows :-

    1. 3 (three) No. approximately 600 mm internal diameter self-priming

    centrifugal pumps, housed in a dry chamber, with connected inlet

    and discharge pipework passing through the walls of the chamber

    structure.

    2. Each of the three pumps is designed to discharge an average of

    4,000 m3 per hour against the varying head conditions. The

    pumping system for normal usage is based on two duty pumps

    with one standby pump on a rotating duty basis.

    3. Each pump is designed to discharge to the Wet Basin through

    siphonic discharge to improve pump efficiency and to minimise

    accidental pump house flooding risks.

    4. The pumps are designed with an intake pipe-culvert of 1.0m

    internal diameter and a discharge of approximately 600mm

    diameter, tapered expanding over the last 1.5 m to 1.0 m at final

    discharge for two pumps. The intake pipe will end in a 90 degree

    bend facing downward with a bottom level of +1.0m CD. This pipe

    bend may project beyond the face of the wall by up to 1.3m.

    5. The third pump is designed to discharge through approximately

    600mm diameter pipework, reducing to nozzles located along the

    Basin side face of the sill to act as a jetting system for silt disturbance in the gate pit.

    6. Each pump may be isolated by means of a gate valve on the

    intake side and an engineered stoplog. The stoplogs are housed

    within the sea-side walls of the pump house together with

    removable trash screens. The screens are removed for

    maintenance purposes or installed, in the case of the stoplogs, by

    using the Level Luffing crane on the South Quay.

    7. The associated electrical switchgear and panels are housed within

    a watertight room below the deck of the East Quay (South) wall,

    directly beneath the transformer room.

    8. The centre-line level of each pump intake is to be defined by the

    1605

  • Mazagon Dock Limited

    Mazdock Modernation Project 15

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    physical size of the pump, but it is expected that the top of the

    pump volute will be at around +2.0m CD to ensure the pump is self

    primed at the minimum pumping level of +2.5m CD.

    9. Large reinforced concrete ‘lift-off’ cover slabs set within the deck

    permit the complete withdrawal of a pump and associated

    equipment for maintenance. The lift-off covers are within reach of

    the 100t level luffing crane on the South Quay wall

    10. Man access to the pump house is by means of a staircase housing

    on the deck, adjacent to the Control Building on the East Quay

    (South) wall, and by robust galvanised steel companionway stairs

    with safety landings and handrails. An emergency exit is provided

    by a ladder located beneath the above ground transformer house

    on the quay. Access to this ladder is through the valve chamber.

    11. A travelling hoist of 5 tonne capacity will be arranged over the

    pumps and motors if required for routine maintenance.

    12. The base slab of the pump house will have falls on the floor to

    perimeter drain channels, culminating in a small pump sump

    suitable for a house pump. The discharge from this pump will be

    arranged direct to the Wet Basin.

    13. Each siphon will be equipped with a pump-supplier designed ‘fail-

    safe’ siphon breaker valve. These breaker valves will be

    accommodated in the open on a low raised plinth on the deck

    adjacent to the Wet Basin edge.

    14. Forced ventilation will be arranged to maintain cooler air through

    the pump house and pumps during running periods, with a discharge to atmosphere at deck level.

    1.11.4 Electrical Services

    Electrical power services to the pump house are as follows :-

    1. Power for the pump motors

    2. Power for the pump intake gate valves

    3. Power for the pump siphon breaker valves

    4. Power for controls and instrumentation

    5. Power for lighting and emergency lighting

    6. Power for small submersible house-pumps when required

    7. General power for hand tools and socket outlets

    8. Data link cabling to the MDL Yard Control Room if necessary.

    MDL to confirm this requirement.

    1.11.5 Mechanical and Piped Services

    Mechanical and piped services to the pump house are as follows :-

    1. Manually operated overhead travelling hoist

    2. Compressed air outlet for cleaning purposes

    3. Fire hydrants inside and portable fire hose reel system.

    4. Hand-held fire extinguishers of appropriate type.

    1.12 Equalising Valves and Housing

  • Mazagon Dock Limited

    Mazdock Modernation Project 16

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    1.12.1 Re-statement of Function

    The valve-controlled pipe-culverts, that bypass the gate, are designed

    to assist in the control of water levels within the Basin. The use of the

    pipe-culverts is only available when the head difference is operating in

    the desired direction. The valve type has been selected to operate

    equally efficiently for flows into and out of the Basin

    1.12.2 Location

    The valves and their actuating motors are located within the Valve

    Chamber adjacent to the Impounding Pump House in the structure of

    the East Quay (South) wall

    1605

    1.12.3 Main Features

    The main features of the equalising valves are as follows :-

    1. 2 (two) No. 1.2 m internal diameter gate valves housed in a dry

    chamber, with connected inlet and discharge pipework passing

    through the walls of the chamber structure.

    2. Each of the two valves is designed to discharge an average of a

    minimum of 4,000 m3 per hour at neap tides

    3. Each valve is operated to open/close by electrically powered

    actuators mounted directly on top of the valve body, and controlled

    either remotely from the Basin-side control room or from within the

    valve chamber.

    4. Each valve may be isolated by means of two engineered stoplogs,

    one on each side of the valve. The stoplogs are housed within the

    walls of the valve chamber. A removable trash screen is to be

    provided on the seaward side of the valves.

    5. The associated electrical switchgear and panels are housed within

    a watertight room below the deck of the East Quay (South) wall,

    directly beneath the transformer room.

    6. The centre line level of each of the pipe-culverts is set at +2.0m

    CD.

    7. Large reinforced concrete ‘lift-off’ cover slabs set within the deck

    permit the complete withdrawal of a valve and associated

    equipment for maintenance. The lift-off covers are within reach of

    the 100t level luffing crane on the South Quay wall

    8. Man access to the valve chamber is by means of an adjacent

    staircase housing on the deck of the East Quay (South) wall, and

    by robust vertical galvanised steel ladders with safety hoops.

    9. A travelling hoist will be arranged over the valves and actuators of

    5tonne capacity.

    10. The base slab of the valve chamber will have falls on the floor to

    perimeter drain channels, culminating in a small pump sump

    suitable for a house pump. The discharge from this pump will be

    arranged direct to the Wet Basin.

    1605

    1.12.4 Electrical Services

    Electrical power supplies to the valve chamber are as follows :- 1. Power for the valve actuators

    2. Power for controls and instrumentation

  • Mazagon Dock Limited

    Mazdock Modernation Project 17

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    3. Power for lighting and emergency lighting

    4. Power for small submersible house-pumps when required

    5. General power for hand tools and socket outlets

    6. Data link cabling to the MDL Yard Control Room if necessary.

    1.12.5 Mechanical and Piped Services

    Mechanical and piped services to the valve chamber are as follows :-

    1. Manually operated overhead travelling hoist

    2. Compressed air outlet for cleaning purposes

    3. Fire hydrants inside and portable fire hose reel system.

    4. Hand-held fire extinguishers of appropriate type.

    1.13 Cranes

    Please refer to Sections Error! Reference source not found. and

    Error! Reference source not found. (100t and 15t Level Luffing

    crane Contracts)

    1.14 Lead-in Jetty

    1.14.1 Re-statement of Function

    A lead-in jetty provides assistance to the entry/exit of the Basin,

    particularly with currents and wind on the broadside of vessels.

    1.14.2 Location

    The lead-in jetty is located on the north side of the basin entrance and

    is orientated such that it is perpendicular to the east quay.

    1601

    1.14.3 Main Features

    1. The lead-in jetty comprises three mass concrete dolphins,

    approximately 15 x 15 m and spaced at 30m centres.

    2. The total length of the lead-in jetty is 96m measured from the face

    of the East Quay.

    3. Access between the dolphins is by means of steel or reinforced

    concrete pedestrian access walkways. For operational reasons,

    handrails will be provided only on the north side of the walkways.

    The walkways will be 2.0m wide.

    4. Each dolphin has a 40 tonne bollard

    5. The outer dolphin has a 10 tonne capstan

    6. As well as general lighting, the dolphins will have navigation lights.

    1.15 Electrical Services

  • Mazagon Dock Limited

    Mazdock Modernation Project 18

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    1.15.1 Re-statement of Function

    Electrical services for the Wet Basin comprise the following:

    1. Power supplies to DSU’s 2. Power supplies to cranes

    3. Power supplies to plantrooms.

    4. Power supplies to capstans

    5. Lighting

    6. Telecommunication cabling.

    7. Data cabling.

    1.15.2 Wet Basin Substations

    1. The main Wet Basin substation is located at the east end of the

    South Quay, designated Substation “C”. The incoming HT supply

    will come from Substation A.

    2. A second electrical switchroom housing only LT switchgear is

    located on the East Quay (north), designated substation “D”. (The

    designation of “substation” refers only to the fact that the room

    contains electrical equipment).

    3. The power supplies to the Wet Basin will be fed primarily from

    Substation C although DSU power supplies for half the south quay

    will be fed from Substation B.

    1601

    1.15.3 Wet Basin Dockside Supply Units (DSU’s)

    1. DSU’s will be provided at 15m spacing along the basin side of the

    North Quay and along the basin side of the South Quay.

    2. DSU’s will be located in surface mounted galvanised steel boxes with hinged doors.

    1601

    1.15.4 Power Supplies to South Quay DSU’s

    The following electrical supplies are provided at DSU’s on the South

    Quay:

    1. 415V 50Hz 3 phase supply at 100A. Maximum total power for this

    supply is 1000 kVA.

    2. 230V 50Hz single phase supply at 30A. Maximum total power for

    this supply is 200 kVA.

    3. 110V 50Hz 3 phase supply at 100A. Maximum total power for this

    supply is 300 kVA.

    1612

    1628

    1.15.5 Power Supplies to North Quay DSU’s

    The following electrical supplies are provided at DSU’s on the North

    Quay:

    1. 415V 50Hz 3 phase supply at 400A with 63 Amp, 12 way DB.

    1618

    1625

  • Mazagon Dock Limited

    Mazdock Modernation Project 19

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    2. 115V 50Hz 3 phase supply at 63A.

    3. 115V 60Hz 3 phase supply at 200A.

    4. To be provided at one location at the intersection of the East and

    the North Quay:

    • 415V 3 phase 50Hz 1250A MCCB with cable termination box

    for outgoing cables. (These supplies are required for

    submarine battery charging. The battery charging operation

    will be carried out for one submarine at a time. The battery

    charging duration is 24 to 30 hours. The frequency of battery

    charging is once a month).

    5. To be provided at two locations along the quay, within larger

    DSU's:

    • 415V 3 phase 50Hz 300 Amps.

    • 220V DC 300 Amps.

    1.15.6 Lighting

    1. Four high masts located near the corners of the basin will provide

    lighting for the wet basin. The masts will be approximately 30m

    high lattice masts.

    2. Lighting of the lead-in dolphins will be located on lighting poles at

    the rear of the dolphins.

    3. Strip lighting will be mounted on the lead-in dolphin walkways.

    4. The general illumination level for the basin will be 50 lux.

    5. The general illumination level for the lead-in jetty dolphins will be

    100 lux.

    6. The general illumination level of the plant rooms will be 200 lux.

    1601

    1.15.7 Power Supplies to Plantrooms

    The following plantroom power supplies are provided:

    1. Pump house for impounding pumps – see Section 1.11.4

    2. Valve chamber - see Section 1.12.4

    3. Gate winch chamber

    4. Substations and control room

    1.15.8 Telecommunications Cabling

    Cables will be provided to connect the Wet Basin plantrooms to the

    main telecommunications network. MDL are to confirm this

    requirement.

    1.15.9 Data Cabling

    Cables will be provided to send data from the Wet Basin plantrooms to

    the main control room. MDL are to confirm this requirement.

    1.16 Mechanical Services

    1.16.1 Re-statement of Function

  • Mazagon Dock Limited

    Mazdock Modernation Project 20

    Document No. 3H6543/R007Final Issue Rev 1

    November 2003

    Mechanical services for the Wet Basin comprise the following:

    1. Sea water (fire fighting) system

    2. Fresh water

    3. Compressed air

    4. Oxygen as cutting gas

    5. Acetylene as cutting gas

    1.16.2 Location of Pipework

    The piped services for the Wet Basin will be routed in the services

    recesses at the top of the quay walls on the North and South Quay

    walls.

    1601

    1.16.3 Sea Water System

    1. The seawater system will provide take-off hydrant connections at

    15m spacing along the basin sides of the North Quay and the

    South Quay.

    2. The nominal pressure will be 8 kg/cm2.

    3. In addition to the hydrants, and stand-pipes with hydrant

    connection shall be provided to allow a fire tender to pump directly

    from the sea. These shall be at the same locations as the

    seawater main hydrants.

    1612

    1618

    1.16.4 Fresh Water System

    The fresh water system will provide take-off hydrant connections at

    15m spacing along the basin sides of the North Quay and the South

    Quay.

    1612

    1618

    1.16.5 Compressed Air System

    1. The compressed system will provide take-off connections at 15m

    spacing along the basin sides of the North Quay and the South

    Quay. Three quick release connection points will provided at each

    take-off location.

    2. The nominal pressure will be 10 kg/cm2.

    1612

    1618

    1.16.6 Oxygen and Acetylene System

    Oxygen and acetylene take-off connections will be provided at 15m

    spacing along the basin sides of the North Quay and the South Quay. Quick release connection points will provided at each take-off location.

    1612

    1618

    ------------------------- End of DPR -------------------------