materials requirements planning -...
TRANSCRIPT
Materials Requirements Planning
Independent and Dependent Demand
Independent Demand
A
B(4) C(2)
D(2) E(1) D(3) F(2)
Dependent Demand
Independent demand is uncertain.
Dependent demand is certain.
Dependent demand: Demand for items that are
subassemblies or component parts to be used in
production of finished goods.
Once the independent demand is known, the dependent
demand can be determined.
Dependent Demand
Material Requirements Planning
DefinedMaterials requirements planning (MRP) is a
computerized inventory planning and control system for determining when (no earlier and no later) and how many of each of the parts, components, and materials should be ordered or produced.
It translates master schedule requirements from end items into time-phased requirements for subassemblies, components and raw materials.
Dependent demand drives MRP
MRP is a software system
Material Requirements Planning System
Based on a master production schedule, a material requirements planning system:
Creates schedules identifying the specific parts
and materials required to produce end items
Determines exact unit numbers needed
Determines the dates when orders for those
materials should be released, based on lead
times
6
©The McGraw-Hill Companies, Inc., 2004
Firm orders
from known
customers
Forecasts
of demand
from random
customers
Aggregate
production
plan
Bill of
material
file
Engineering
design
changes
Inventory
record file
Inventory
transactions
Master production
Schedule (MPS)
Primary reportsSecondary reports
Planned order schedule for
inventory and production
control (work orders,
purchase orders),
rescheduling notices
Exception reports
Planning reports
Reports for performance
control
Material
planning
(MRP
computer
program)
MRP Inputs MRP Processing MRP Outputs
Master
schedule
Bill of
materials
Inventory
records
MRP computer
programs
Changes
Order releases
Planned-order
schedules
Exception reports
Planning reports
Performance-
control
reports
Inventory
transaction
Primary
reports
Secondary
reports
MRP System
MRP Inputs 1: Master Production Schedule
Drives MRP process with a schedule of finished products;
states which end items are to be produced, when these
are needed, and in what quantities
Quantities may consist of a combination of customer
orders & demand forecasts
Quantities represent what needs to be produced, not what
can be produced
Master Production Schedule (MPS)
Time-phased plan specifying how many and when the
firm plans to build each end item
Aggregate Plan
(Product Groups)
MPS
(Specific End Items)
Master Production Schedule
Item / Week Oct 3 Oct. 10 Oct. 17 Oct.24 Oct. 31
Clipboard 85 95 120 100 100
Lapdesk 0 50 0 50 0
Lapboard 75 120 47 20 17
Pencil Case 125 125 125 125 125
Shows items to be produced
Derived from aggregate planExample:
MRP Inputs 2: Bill-of-Materials
Bill of materials (BOM): One of the three primary inputs of MRP; a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product.
Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels.
Product Structure Tree: Example 1Chair
Seat
Legs (2)Cross
bar
Side
Rails (2)
Cross
bar
Back
Supports (3)
Leg
Assembly
Back
Assembly
Level
0
1
2
3
Bicycle(1)P/N 1000
Handle Bars (1)
P/N 1001
Frame Assembly (1)
P/N 1002
Wheels (2)
P/N 1003Frame (1)P/N 1004
Product Structure Tree: Example 2
Product Drawing: Example 3
Top clip (1) Bottom clip (1)
Pivot (1) Spring (1)
Rivets (2)
Finished clipboard Pressboard (1)
Clipboard
Product Structure Tree ( Example 3)
Clipboard Level 0
Level 1
Level 2Spring
(1)Bottom Clip
(1)Top Clip
(1)Pivot
(1)
Rivets (2)
Clip Ass’y (1)
Pressboard (1)
13-16 MRP and ERP
Gross Requirements: needed during each period.
Scheduled Receipts: Existing orders that arrive at beginning of period.
On-hand or available balance:
(depending on software convention, could be at the beginning of each period or end):
Book: Inventory balance at end of each period.
Net requirements: What is need to meet requirements and safety stock.
Planned order receipt: arrives at beginning of period.
Planned order release: Addresses lead time.
MRP Inputs 3: Inventory Records File
One of the three primary inputs of MRP
Includes information on the inventory status of each item by time period
Gross requirements
Scheduled receipts
Amount on hand
Lead times
Lot sizes
And more....
MRP Terminology (1 of 3)
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Planned-order receipts
Planned-order releases
MPR Terminology (2 of 3)
Gross requirements
Total expected demand
Scheduled receipts
Open orders scheduled to arrive
Projected on hand
Expected inventory on hand at the beginning
of each time period
MRP Processing Terminology (3 of 3)Net requirements
Actual amount needed in each time period
Gross requirements – available inventory
Planned-order receipts
Quantity expected to be received at the beginning of the
period
Offset by lead time
Planned-order releases
Planned amount to be ordered in each time period
MRP Processing:
Example 1-School Mate ProductsMaster Production Schedule
1 2 3 4 5
Clipboard 85 95 120 100 100
Lapdesk 0 60 0 60 0
Item Master File (ınventory record file
CLIPBOARD LAPDESK PRESSBOARD
On hand 25 20 150
On order 175 (Period 1) 0 0
(sch receipt)
LLC 0 0 1
Lot size L4L Mult 50 Min 100
Lead time 1 1 1
School Mate ProductsProduct Structure Record
Clipboard
Lapdesk
Pressboard(2)
Trim(3’)
Beanbag(1)
Glue(4 oz)
Level 0
Level 0
Pressboard(1)
Clip Ass’y(1)
Rivets(2) Level 1
Level 1
School Mate Products
ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: 1 1 2 3 4 5
Gross Requirements 85 95 120 100 100
Scheduled Receipts 175
Projected on Hand 25
Net Requirements
Planned Order Receipts
Planned Order Releases
School Mate Products
ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: 1 1 2 3 4 5
Gross Requirements 85 95 120 100 100
Scheduled Receipts 175
Projected on Hand 25 115
Net Requirements 0
Planned Order Receipts
Planned Order Releases
(25 + 175) = 200 units available
(200 - 85) = 115 on hand at the end of Period 1
School Mate Products
ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: 1 1 2 3 4 5
Gross Requirements 85 95 120 100 100
Scheduled Receipts 175
Projected on Hand 25 115 20
Net Requirements 0 0
Planned Order Receipts
Planned Order Releases
115 units available
(115 - 85) = 20 on hand at the end of Period 2
School Mate Products
ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: 1 1 2 3 4 5
Gross Requirements 85 95 120 100 100
Scheduled Receipts 175
Projected on Hand 25 115 20 0
Net Requirements 0 0 100
Planned Order Receipts 100
Planned Order Releases 100
20 units available
(20 - 120) = -100 — 100 additional Clipboards are required
Order must be placed in Period 2 to be received in Period 3
School Mate Products
ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: 1 1 2 3 4 5
Gross Requirements 85 95 120 100 100
Scheduled Receipts 175
Projected on Hand 25 115 20 0 0 0
Net Requirements 0 0 100 100 100
Planned Order Receipts 100 100 100
Planned Order Releases 100 100 100
Following the same logic Gross Requirements in Periods 4
and 5 develop Net Requirements, Planned Order Receipts, and
Planned Order Releases
School Mate Products
ITEM: LAPDESK LLC: 0 PERIOD
LOT SIZE: MULT 50 LT: 1 1 2 3 4 5
Gross Requirements 0 60 0 60 0
Scheduled Receipts
Projected on Hand 20
Net Requirements
Planned Order Receipts
Planned Order Releases
School Mate Products
ITEM: LAPDESK LLC: 0 PERIOD
LOT SIZE: MULT 50 LT: 1 1 2 3 4 5
Gross Requirements 0 60 0 60 0
Scheduled Receipts
Projected on Hand 20 20 10 10 0 0
Net Requirements 0 40 50
Planned Order Receipts 50 50
Planned Order Releases 50 50
Following the same logic, the Lapdesk MRP matrix is
completed as shown
School Mate Products
ITEM: PRESSBOARD LLC: 0 PERIOD
LOT SIZE: MIN 100 LT: 1 1 2 3 4 5
Gross Requirements
Scheduled Receipts
Projected on Hand 150
Net Requirements
Planned Order Receipts
Planned Order Releases
ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: 1 1 2 3 4 5
Planned Order Releases 100 100 100
ITEM: LAPDESK LLC: 0 PERIOD
LOT SIZE: MULT 50 LT: 1 1 2 3 4 5
Planned Order Releases 50 50
School Mate Products
ITEM: PRESSBOARD LLC: 0 PERIOD
LOT SIZE: MIN 100 LT: 1 1 2 3 4 5
Gross Requirements 100 100 200 100 0
Scheduled Receipts
Projected on Hand 150
Net Requirements
Planned Order Receipts
Planned Order Releases
ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: 1 1 2 3 4 5
Planned Order Releases 100 100 100
ITEM: LAPDESK LLC: 0 PERIOD
LOT SIZE: MULT 50 LT: 1 1 2 3 4 5
Planned Order Releases 50 50
x2 x2
x1 x1x1
School Mate Products
ITEM: PRESSBOARD LLC: 0 PERIOD
LOT SIZE: MIN 100 LT: 1 1 2 3 4 5
Gross Requirements 100 100 200 100 0
Scheduled Receipts
Projected on Hand 150 50 50 0 0 0
Net Requirements 50 150 100
Planned Order Receipts 100 150 100
Planned Order Releases 100 150 100
ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: 1 1 2 3 4 5
Planned Order Releases 100 100 100
ITEM: LAPDESK LLC: 0 PERIOD
LOT SIZE: MULT 50 LT: 1 1 2 3 4 5
Planned Order Releases 50 50
School Mate Products
Planned Order Report
PERIOD
ITEM 1 2 3 4 5
Clipboard 100 100 100
Lapdesk 50 50
Pressboard 100 150 100
Capacity
Usually expressed as standard machine
hours or labor hours
Capacity = (no. machines or workers)
x (no. shifts) x (utilization)
x (efficiency)