materials requirements planning -...

34
Materials Requirements Planning

Upload: others

Post on 13-Sep-2019

17 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

Materials Requirements Planning

Page 2: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

Independent and Dependent Demand

Independent Demand

A

B(4) C(2)

D(2) E(1) D(3) F(2)

Dependent Demand

Independent demand is uncertain.

Dependent demand is certain.

Page 3: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

Dependent demand: Demand for items that are

subassemblies or component parts to be used in

production of finished goods.

Once the independent demand is known, the dependent

demand can be determined.

Dependent Demand

Page 4: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

Material Requirements Planning

DefinedMaterials requirements planning (MRP) is a

computerized inventory planning and control system for determining when (no earlier and no later) and how many of each of the parts, components, and materials should be ordered or produced.

It translates master schedule requirements from end items into time-phased requirements for subassemblies, components and raw materials.

Dependent demand drives MRP

MRP is a software system

Page 5: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

Material Requirements Planning System

Based on a master production schedule, a material requirements planning system:

Creates schedules identifying the specific parts

and materials required to produce end items

Determines exact unit numbers needed

Determines the dates when orders for those

materials should be released, based on lead

times

Page 6: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

6

©The McGraw-Hill Companies, Inc., 2004

Firm orders

from known

customers

Forecasts

of demand

from random

customers

Aggregate

production

plan

Bill of

material

file

Engineering

design

changes

Inventory

record file

Inventory

transactions

Master production

Schedule (MPS)

Primary reportsSecondary reports

Planned order schedule for

inventory and production

control (work orders,

purchase orders),

rescheduling notices

Exception reports

Planning reports

Reports for performance

control

Material

planning

(MRP

computer

program)

Page 7: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

MRP Inputs MRP Processing MRP Outputs

Master

schedule

Bill of

materials

Inventory

records

MRP computer

programs

Changes

Order releases

Planned-order

schedules

Exception reports

Planning reports

Performance-

control

reports

Inventory

transaction

Primary

reports

Secondary

reports

MRP System

Page 8: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

MRP Inputs 1: Master Production Schedule

Drives MRP process with a schedule of finished products;

states which end items are to be produced, when these

are needed, and in what quantities

Quantities may consist of a combination of customer

orders & demand forecasts

Quantities represent what needs to be produced, not what

can be produced

Page 9: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

Master Production Schedule (MPS)

Time-phased plan specifying how many and when the

firm plans to build each end item

Aggregate Plan

(Product Groups)

MPS

(Specific End Items)

Page 10: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

Master Production Schedule

Item / Week Oct 3 Oct. 10 Oct. 17 Oct.24 Oct. 31

Clipboard 85 95 120 100 100

Lapdesk 0 50 0 50 0

Lapboard 75 120 47 20 17

Pencil Case 125 125 125 125 125

Shows items to be produced

Derived from aggregate planExample:

Page 11: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

MRP Inputs 2: Bill-of-Materials

Bill of materials (BOM): One of the three primary inputs of MRP; a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product.

Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels.

Page 12: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

Product Structure Tree: Example 1Chair

Seat

Legs (2)Cross

bar

Side

Rails (2)

Cross

bar

Back

Supports (3)

Leg

Assembly

Back

Assembly

Level

0

1

2

3

Page 13: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

Bicycle(1)P/N 1000

Handle Bars (1)

P/N 1001

Frame Assembly (1)

P/N 1002

Wheels (2)

P/N 1003Frame (1)P/N 1004

Product Structure Tree: Example 2

Page 14: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

Product Drawing: Example 3

Top clip (1) Bottom clip (1)

Pivot (1) Spring (1)

Rivets (2)

Finished clipboard Pressboard (1)

Clipboard

Page 15: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

Product Structure Tree ( Example 3)

Clipboard Level 0

Level 1

Level 2Spring

(1)Bottom Clip

(1)Top Clip

(1)Pivot

(1)

Rivets (2)

Clip Ass’y (1)

Pressboard (1)

Page 16: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

13-16 MRP and ERP

Gross Requirements: needed during each period.

Scheduled Receipts: Existing orders that arrive at beginning of period.

On-hand or available balance:

(depending on software convention, could be at the beginning of each period or end):

Book: Inventory balance at end of each period.

Net requirements: What is need to meet requirements and safety stock.

Planned order receipt: arrives at beginning of period.

Planned order release: Addresses lead time.

Page 17: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

MRP Inputs 3: Inventory Records File

One of the three primary inputs of MRP

Includes information on the inventory status of each item by time period

Gross requirements

Scheduled receipts

Amount on hand

Lead times

Lot sizes

And more....

Page 18: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

MRP Terminology (1 of 3)

Gross requirements

Scheduled receipts

Projected on hand

Net requirements

Planned-order receipts

Planned-order releases

Page 19: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

MPR Terminology (2 of 3)

Gross requirements

Total expected demand

Scheduled receipts

Open orders scheduled to arrive

Projected on hand

Expected inventory on hand at the beginning

of each time period

Page 20: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

MRP Processing Terminology (3 of 3)Net requirements

Actual amount needed in each time period

Gross requirements – available inventory

Planned-order receipts

Quantity expected to be received at the beginning of the

period

Offset by lead time

Planned-order releases

Planned amount to be ordered in each time period

Page 21: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

MRP Processing:

Example 1-School Mate ProductsMaster Production Schedule

1 2 3 4 5

Clipboard 85 95 120 100 100

Lapdesk 0 60 0 60 0

Item Master File (ınventory record file

CLIPBOARD LAPDESK PRESSBOARD

On hand 25 20 150

On order 175 (Period 1) 0 0

(sch receipt)

LLC 0 0 1

Lot size L4L Mult 50 Min 100

Lead time 1 1 1

Page 22: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

School Mate ProductsProduct Structure Record

Clipboard

Lapdesk

Pressboard(2)

Trim(3’)

Beanbag(1)

Glue(4 oz)

Level 0

Level 0

Pressboard(1)

Clip Ass’y(1)

Rivets(2) Level 1

Level 1

Page 23: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

School Mate Products

ITEM: CLIPBOARD LLC: 0 PERIOD

LOT SIZE: L4L LT: 1 1 2 3 4 5

Gross Requirements 85 95 120 100 100

Scheduled Receipts 175

Projected on Hand 25

Net Requirements

Planned Order Receipts

Planned Order Releases

Page 24: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

School Mate Products

ITEM: CLIPBOARD LLC: 0 PERIOD

LOT SIZE: L4L LT: 1 1 2 3 4 5

Gross Requirements 85 95 120 100 100

Scheduled Receipts 175

Projected on Hand 25 115

Net Requirements 0

Planned Order Receipts

Planned Order Releases

(25 + 175) = 200 units available

(200 - 85) = 115 on hand at the end of Period 1

Page 25: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

School Mate Products

ITEM: CLIPBOARD LLC: 0 PERIOD

LOT SIZE: L4L LT: 1 1 2 3 4 5

Gross Requirements 85 95 120 100 100

Scheduled Receipts 175

Projected on Hand 25 115 20

Net Requirements 0 0

Planned Order Receipts

Planned Order Releases

115 units available

(115 - 85) = 20 on hand at the end of Period 2

Page 26: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

School Mate Products

ITEM: CLIPBOARD LLC: 0 PERIOD

LOT SIZE: L4L LT: 1 1 2 3 4 5

Gross Requirements 85 95 120 100 100

Scheduled Receipts 175

Projected on Hand 25 115 20 0

Net Requirements 0 0 100

Planned Order Receipts 100

Planned Order Releases 100

20 units available

(20 - 120) = -100 — 100 additional Clipboards are required

Order must be placed in Period 2 to be received in Period 3

Page 27: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

School Mate Products

ITEM: CLIPBOARD LLC: 0 PERIOD

LOT SIZE: L4L LT: 1 1 2 3 4 5

Gross Requirements 85 95 120 100 100

Scheduled Receipts 175

Projected on Hand 25 115 20 0 0 0

Net Requirements 0 0 100 100 100

Planned Order Receipts 100 100 100

Planned Order Releases 100 100 100

Following the same logic Gross Requirements in Periods 4

and 5 develop Net Requirements, Planned Order Receipts, and

Planned Order Releases

Page 28: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

School Mate Products

ITEM: LAPDESK LLC: 0 PERIOD

LOT SIZE: MULT 50 LT: 1 1 2 3 4 5

Gross Requirements 0 60 0 60 0

Scheduled Receipts

Projected on Hand 20

Net Requirements

Planned Order Receipts

Planned Order Releases

Page 29: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

School Mate Products

ITEM: LAPDESK LLC: 0 PERIOD

LOT SIZE: MULT 50 LT: 1 1 2 3 4 5

Gross Requirements 0 60 0 60 0

Scheduled Receipts

Projected on Hand 20 20 10 10 0 0

Net Requirements 0 40 50

Planned Order Receipts 50 50

Planned Order Releases 50 50

Following the same logic, the Lapdesk MRP matrix is

completed as shown

Page 30: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

School Mate Products

ITEM: PRESSBOARD LLC: 0 PERIOD

LOT SIZE: MIN 100 LT: 1 1 2 3 4 5

Gross Requirements

Scheduled Receipts

Projected on Hand 150

Net Requirements

Planned Order Receipts

Planned Order Releases

ITEM: CLIPBOARD LLC: 0 PERIOD

LOT SIZE: L4L LT: 1 1 2 3 4 5

Planned Order Releases 100 100 100

ITEM: LAPDESK LLC: 0 PERIOD

LOT SIZE: MULT 50 LT: 1 1 2 3 4 5

Planned Order Releases 50 50

Page 31: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

School Mate Products

ITEM: PRESSBOARD LLC: 0 PERIOD

LOT SIZE: MIN 100 LT: 1 1 2 3 4 5

Gross Requirements 100 100 200 100 0

Scheduled Receipts

Projected on Hand 150

Net Requirements

Planned Order Receipts

Planned Order Releases

ITEM: CLIPBOARD LLC: 0 PERIOD

LOT SIZE: L4L LT: 1 1 2 3 4 5

Planned Order Releases 100 100 100

ITEM: LAPDESK LLC: 0 PERIOD

LOT SIZE: MULT 50 LT: 1 1 2 3 4 5

Planned Order Releases 50 50

x2 x2

x1 x1x1

Page 32: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

School Mate Products

ITEM: PRESSBOARD LLC: 0 PERIOD

LOT SIZE: MIN 100 LT: 1 1 2 3 4 5

Gross Requirements 100 100 200 100 0

Scheduled Receipts

Projected on Hand 150 50 50 0 0 0

Net Requirements 50 150 100

Planned Order Receipts 100 150 100

Planned Order Releases 100 150 100

ITEM: CLIPBOARD LLC: 0 PERIOD

LOT SIZE: L4L LT: 1 1 2 3 4 5

Planned Order Releases 100 100 100

ITEM: LAPDESK LLC: 0 PERIOD

LOT SIZE: MULT 50 LT: 1 1 2 3 4 5

Planned Order Releases 50 50

Page 33: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

School Mate Products

Planned Order Report

PERIOD

ITEM 1 2 3 4 5

Clipboard 100 100 100

Lapdesk 50 50

Pressboard 100 150 100

Page 34: Materials Requirements Planning - rbvrrwomenscollege.netrbvrrwomenscollege.net/wp-content/uploads/2018/05/MRP1-1.pdf · Material Requirements Planning Defined Materials requirements

Capacity

Usually expressed as standard machine

hours or labor hours

Capacity = (no. machines or workers)

x (no. shifts) x (utilization)

x (efficiency)