MANAGMENT PLAN 2011/12 –
REVIEW OF PROGRAM ACTIVITIES FOR 4th
QUARTER OF 2011/12
GENERAL MANAGER
Program Activity: Good Governance
The purpose of this activity is to provide the resources to ensure that councillors are able to perform their duties in accordance with the Local Government Act and related legislation. The desired outcome of this activity is quality decision making and policy formulation. Activity 1 – To ensure Council operates under good governance principles
Actions Measurement Qtr Revised Qtr
% Comp/ No Officer
Lobby State and Federal Governments for better community outcomes
Number of submissions 1-4
8
GM
Representations and motions submitted through RAMROC and LGSA Divisional forums
1-4
4 GM
COMMENT: Four RAMROC meetings held and attended by Council representative. “F” Division and Western Division Council of NSW meetings were also held during the 3rd Quarter & Shires Association Conference during 4th Quarter
Activity 2 – To develop Council’s strategic planning focus
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Conduct Strategic Planning Workshops
Development and adoption of Council’s Integrated Planning and Reporting (IP&R) Plan.
1-2
100% CDO
Number of Strategic Planning workshops conducted 1
6 CDO
COMMENT: Suite of Plans complete and submitted to the DLG 30 June 2012
Activity 3 – To engage the community
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Maintain good relations with the community, business and government bodies
Functional & up to date information provided on website
2 100% CDO
Review Ward Boundary Requirements
Ward boundaries comply with less than 10% elector variance requirement
1 100% MOD
COMMENT: Report on Ward Boundary requirements for September 2012 elections has already been presented to Council
Program Activity: Risk and Corporate Support
The purpose of this activity is to ensure that the organisation performs to the highest standards and in accordance with the expectations of its stakeholders, and includes the main administrative and financial support services in the achievement of Council’s activities. The desired outcomes of this activity include efficient and effective staff performing support services, processes and systems audited regularly, organisational risk identified and addressed within resource limitations and an increase in overall organisational productivity. Activity 1 – To reduce Council’s risk exposure
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Continue to develop a risk register of all organisational risks
The extent of risk identification 1-4 50% Risk Officer
OHS Consultation Number of OHS Committee Meetings held 1-4 100% Risk
Officer
Improvement in OHS & Risk Management processes
No plant assessments signed off 1-4 100% Risk
Officer Develop and implement a pro-active inspection schedule for all Council facilities
1-4 75% Risk Officer
% compliance with OHS & Public Liability audits 1-4 80% Risk
Officer % of risk assessments & safe work method statements completed by Departments
1-4 75% Risk Officer
Departmental Action plans developed and monitored 1-4 50% Risk
Officer
COMMENT:
Revision of Risk Management Plan register programmed. Inspection schedule – quarterly. PL self-audit and verification process has been replaced by the continuous improvement pathway (CIP). WHS Departmental Plans under revision to reflect new legislation
Activity 2 – To further develop performance systems and improve overall productivity
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Conduct internal audits on a regular basis
Number of audits conducted 1-4 8 GM
Review the Internal Audit & Continuous Improvement Strategy Plan
Completion of review by 30/06/12 4 100% GM
Review Council Salary System
Report to Consultative Committee on strengths & weaknesses of current system
4 10% See comment below
GM
COMMENT: Review of Salary System is planned to be conducted with Consultant during 2012/13. Review has commenced and report went to Consultative Committee Meeting June 2012.
Activity 3 – To review and enhance Council’s strategic planning and consultation processes
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Conduct community planning sessions in each town and village
Planning sessions implemented and number of sessions 1 100%
6 held GM
COMMENT: Two focus meetings held as well as 4 general purpose meetings in villages.
Program Activity: Risk and Corporate Support (Continued)
Activity 4 – To provide well trained and competent staff
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Implement the 2011/12 Training Plan for the Organisation
Program funded and completed 1 2 50% HR
Conduct a climate survey to assess staff needs and issues
Climate survey conducted 2 2 50% HR
Review the Human Resources and EEO Strategy Program
Review completed. 1 2 100% HR Traineeship/cadet program implemented 1 2 50% HR
Number of Consultative Committee meetings held 1 2 100% HR
Annual performance reviews undertaken and effective
All reviews completed and actioned 2-3 2 100% HR
COMMENT: Proposed to conduct a ‘snapshot’ or mini survey in July at annual staff meeting and conduct a comprehensive survey at the end of 2012.Snapshot survey conducted at annual staff meeting. Findings to be collated.
Activity 5 – To provide adequate support systems
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Develop and implement a human resources database
Human Resources Management System developed including HR policy manual, induction manual and database
1 2 50% HR / Risk Officer
Develop Council’s Business Continuity Plan
Plan developed and tested for offices, library and depots 3 2 10% HR / Risk
Officer
COMMENT:
Policy and Induction manual completed. Using EasyOHS as a HR database – still to be fully implemented. Statewide Mutual will assist to review draft BCP, make amendments and implement in 2012.
Activity 6 – To enhance the relationship between Council and customers
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Media releases and Council newsletters promote positive image of Council
No of media releases issued on key issues 1-4 100% GM
COMMENT: Positive relationship continued with media including radio and TV interviews. Monthly Council Corner produced and distributed to residents.
Program Activity: Economic Development Tourism and Business Undertakings
The purpose of this activity is to create a place that people not only wish to live and work in but will also be a place that people wish to visit. This will require in part that the Shire encourages tourism and economic development by actively promoting the regions attributes. The desired outcome of this activity is increased economic activity, greater tourism numbers and the efficient maintenance of a number of business undertakings. Activity 1 – To explore economic opportunities for the Shire
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Actively promote the sale of Council land
Articles in Council Corner p.a. Newspaper advertisements p.a.
1-4 100% CDO
Participate in the “C Change” program
Level of interest in the area as a result of the program 1-4 100% CDO
COMMENT: During 4rd Quarter of 2011/12, 15 enquiries were made regarding the “C” Change program largely driven by the Sydney Country and Regional Living Expo and the Victorian Regional Living Expo
Activity 2 – To stimulate increase visitations and other tourism activity in the Shire
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Promote the benefits of the Shire at regional shows
Number of shows attended and/or material provided 1-4 100%
2 shows CDO
Produce relevant tourism information for use internally and externally
Development of website information. Amount of promotional material
1-4 100% CDO
Implement the Shire’s Tourism Strategy
Number of initiatives pursued 1-4 100% CDO
COMMENT: Material was provided for 2 shows although no physical presence due to other commitments. Work is ongoing with the website and facebook presence.
Activity 3 – To support communities and their events
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Administer the 2011/12 Shire Community Grant Scheme
Scheme maintained and the number of worthwhile projects pursued
1-3 100% CDO
Identify and disseminate grant information to relevant community groups
Number of successful grant applications 1-4 100% CDO
COMMENT: All projects funded under the 2011/12 Community Grant Scheme acquitted
Program Activity: Community Services & Access The purpose of this activity is to promote access to a range of services, programs and facilities across the Shire and to assist in the cohesive development of cohesive communities. The desired outcome of this activity is increased capacity building, better coordinated and supported community activities and delivery of activities for the elderly and youth. Activity 1 – To provide services to youth
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Organise Youth Week 2012 Number attending 4 100% CDO
COMMENT: 20 youth attended the Totem Skate School event on April 19 at the new skate park in Hillston.
MANAGER ORGANISATION DEVELOPMENT Program Activity: Good Governance The purpose of this activity is to provide the resources to ensure that Councillors are able to perform their duties in accordance with the Local Government Act and related legislation. The desired outcome of this activity is quality decision making and policy formulation. Activity 1 – To ensure Council operates under good governance principles
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Provision of accurate and timely business papers, minutes, and relevant information
Accurate documentation provided within required timeframes
1-4 100% MOD
Accurate documentation provided within required timeframes
Training conducted in accordance with Councillor professional development program
1-4 100% MOD
Monitor the health of governance functions
% compliance with the Department of Local Government's Best Practice Review Program
1 3-4 50% MOD
COMMENT: Emphasis on Councillor training for new Council next financial year Assessment of compliance with Best Practice Review Program 3 and 4 quarters
Activity 2 – To develop Council’s strategic planning focus
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Review all Council policies
Policy review program implemented 1-4 20% MOD
COMMENT: Governance policies reviewed to meet statutory guidelines but policy register to be reviewed over remainder of the year
Activity 3 – To engage the community
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Maintain good relations with the community, business and government bodies
Number of newsletters issued
Number of complaints received
1-4
100% 0
MOD
COMMENT: Comments from 2011 community survey indicate Council Corner is worthwhile
Activity 4 – To review and enhance Council’s strategic planning and consultation processes
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Conduct community surveys on Council services and other matters
Survey issued & % responses addressed 1 3 100% MOD
COMMENT: Community consultation meetings held and water/sewer survey issued
Program Activity: Good Governance (Continued) Activity 5 – To provide adequate support systems
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Develop the new electronic document management system (EDRMS) to meet digital recordkeeping requirements
EDRMS System fully implemented 1-4 80% MOD
Records Management Program revised and updated
1 4 20% MOD
Staff trained in new system requirements 1-4 70% MOD
COMMENT: New system operational but further development required
DIRECTOR WORKS Program Activity: Engineering Services The purpose of this activity is to provide a range of engineering services to complement the wide range of functions in the areas of water, waste, construction and amenity services. The desired outcomes of this activity include efficient and effective staff performing engineering services. Activity 1 – To enhance engineering skill levels
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Develop in-house skill levels and engage external assistance as required
Provision of reliable engineering input to design and projects in a timely manner
2 100% DW
COMMENT:
Resource sharing agreement with GCC in place for water &sewer, GIS Projects & Design Officer completed RTA Traffic Management Trainee completing Dip. Civil Eng Design (Year 2) External assistance retained as necessary
Activity 2 – To provide sound engineering technical and administrative support services
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Enhance computer based mapping capability
Production of high quality and accurate maps, plans and support documents
2 40% DW
COMMENT: In-house training of new staff on MapInfo commenced – formal training required Resource sharing agreement with GCC entered for GIS capacity building Receiving external consulting assistance on GIS use for Asset Management
Activity 3 – To provide interface with Government Departments, external funding bodies and other entities in relation to provision of infrastructure and services
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Develop and submit grant applications, funding submissions and lobbying to attract project funding or services to support local initiatives
Number of submissions made
Number and value of grants received
2 0
1 $5000
DW
COMMENT: The Department of Families, Housing, Community Services and Indigenous Affairs (FaHCSIA) 2011/12 Volunteer Grants Scheme: Local Emergency Management Committee (LEMC) $5000 grant approved.
Program Activity: Public Order and Safety - Emergency Services The purpose of this activity is to support the activities of the fire brigades, State Emergency Services and general issues of public order to ensure that communities are safe. The desired outcome of this activity is a safer community. Activity 1 – To maintain a strong relationship with the Rural Fire Service
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Provide facilities to assist in the training of volunteers
Venues provided 1-4 50% DW
Provide administrative support to the RFS
Support continuous and effective 1-4 50% DW
Develop submissions to annual Bush Fire Mitigation Funding program
Applications made 2 0 DW
COMMENT:
RFS training venues provided on request – Goolgowi landfill used for village fire-training & Goolgowi Community Hall. Administrative support provided in accordance with Service Agreement. BFMF submissions developed in consultation with RFS – Goolgowi SFAL, Merriwagga SAPZ & Hillston Common & By-pass grading.
Activity 2 – Construction of new joint SES/RFS building at Hillston, and new brigade station at Willanthery
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Build new joint SES/RFS building - Hillston
Completion within 6 months of tendering 2 4 60% DW
Build Fire Brigade Station -. Willanthery (Transportable Building)
Completion within 6 months of tendering 2 4 20% DW
COMMENT: SES component project managed and completed in 2010/11. RFS plans complete. RFS plans for Brigade Station at Willanthery yet to be submitted to Council.
Activity 3 – To provide support to the State Emergency Services
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Maintain contact with SES local Controllers and support staff member SES activities
Relationship with SES maintained and staff supported in SES involvement
1 1 - 4 50% DW
COMMENT: Regular communication and effective relationships maintained. LEMC meetings convened as scheduled and generally well-attended. Council Policy on Emergency Services Leave for Staff under development.
Program Activity: Public Order and Safety - Emergency Services (Continued) Activity 4- To participate & facilitate emergency management initiatives
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Conduct Local Emergency Management Committee meetings (three per year)
Meetings held 1
2 of 3 DW
Attend District Emergency Management Committee meetings (three per year)
Meetings attended 1
3 of 3 DW
Undertake local projects and emergency plan developments and co-ordinated by District Emergency Officer
Number of emergency projects and initiatives completed
1
1 DW
COMMENT: Hillston EOC exercise held Addressed outcomes of Neighbourhood Safer Places audit Liaised with Griffith & Hay Councils regarding evacuation assembly areas
Activity 5- To provide necessary support infrastructure
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Continue hydrant replacement program in townships to improve fire fighting
Number of hydrants replaced 1 16 DW
Implement Rural Addressing program
Progress on Rural Addressing program 1 1 - 4 30% DW
COMMENT: Hydrant replacements proceeding within budget provided Rural Addressing program further delayed due to flood damage. Only signs to be installed.
Program Activity: Water Services & Flood Mitigation The purpose of this activity is to provide potable water supplies to Hillston, Carrathool, Goolgowi and Merriwagga and to provide effective raw water supplies to Rankins Springs and rural schemes. The desired outcome of this activity is potable and raw water supplies to towns and villages within required environmental and health standards. Activity 1 – To provide the necessary infrastructure to mitigate the effects of flooding
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Continue to implement the Floodplain Risk Management Plan
Applications submitted 1
100% DW
Conduct Urban Floodplain Management Committee to oversee implementation
Number of meetings held 2
2 DW
Complete Lachlan Street investigation and undertake strengthening as needed, subject to receiving grant funding
Lachlan Street works completed 1
60% DW
One Committee meeting held Quarter 2 to consider draft Levee Concept Design reports. Second meeting held to formalise final design. REF complete.
Activity 2 – To implement best practice water guidelines
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Continue transition to best practice water pricing user pays
% of schemes on full cost recovery 1 4
Approx 50% of urban customers
DW
Develop Drought and Demand Management Plans
Plans adopted by Council 1 100% DW
Information developed for Community consultations (three sessions) held regarding new water charging arrangements.
Activity 3 – To develop sustainable water & sewer charges
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Consult with the community and develop staged restructuring of water charges to ensure financial viability of schemes
Community consultations held
New charging regime developed as part of Council’s long term financial plan
1 3 100% DW
Monitor and revise as necessary Drought and Demand Management Plans
Plans adopted by Council 1-3 100% DW
Community consultations held during January 2012. Council has adopted Drought & Demand Management Plans
Program Activity: Water Services & Flood Mitigation (Continued) Activity4 – To provide a secure and reliable flow of water to communities
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Conduct and implement Rankins Springs Groundwater investigation
Number of test bores dug New bore completed
1 2
1 (100%) 100%%
DW
Enhance Asset Management practices across the networks
Completion of comprehensive Asset Management Plan
1 4 25% DW
Construct new bore 5 for Hillston Bore integrated into system 1 3 95% DW
Consult with community regarding major capital works for the next 10 years
Community consultations held
Works specification and contract documentation prepared
1 3 Nil Multiple
DW
New bore Rankins Springs completed on schedule & budget December 2011 New bore Hillston completed December 2011 but requires further development. Asset registers under review in advance of Asset Management Plans Community consultations held during for January 2012 Capital works specified and procured progressively throughout the year
Activity 5 – Melbergen & Rankins Springs Water Supply
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Call for tenders and replace 3.8 kms of mains supply pipes in Melbergen and 6.6km in Rankins Springs
% of works completed
1-3 4 10% DW
Planned work now re-scheduled for 2012/13
Program Activity: Sewerage Services The purpose of this activity is to provide sewerage services to Hillston, Goolgowi and Rankins Springs. The desired outcome of this activity is a sewerage service provided to customers that meets the service, public health and environmental expectations of the community. Activity 1 – To provide sewerage disposal systems in Hillston, Goolgowi and Rankins Springs
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Reduce OH&S and environmental risks associated with operating the systems
Works completed and risk level reduced 1 1 - 4 90% Risk
Officer/DW
Refurbish sludge lagoon Hillston Works completed 1 2 100% Risk
Officer/DW Upgrade switchboards in Hillston and Goolgowi
Works completed 1 2 100% Risk Officer/DW
Safety barrier erected at Hillston STP Sludge lagoon de-watering in progress – delayed by rain All switch-boards in Hillston upgraded and one pending in Goolgowi SWMS under review Quarter 1.
Activity 2 – To improve efficiency of sewer operation
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Consult with community regarding major capital works for the next 10 years
Community consultations held Works specification and contract documentation prepared
1-3 100% DW
Community consultations were held in January 2012. Draft Operational Plan for 2012/13 presented to Council in May 2012 Works re-scheduled for 2012/13
Activity 3 – To provide interface with Government Departments, external funding bodies and other entities in relation to provision of infrastructure and services
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Respond to Federal and State programs such as telecommunications roll-out and local or regional capacity building programs
Number of responses, correspondence 2 6 DW
Five submissions to Federal Minister, DCBDE, and Federal member regarding Hillston Digital Switch-over – four adverse responses received. Subsequent favourable response to Hillston Retransmitter upgrade.
Two submissions to State Roads Minister & RTA regarding intersection treatment at Kidman Way & Springs Road Hillston. Favourable response received from Minister. Liaison with Graincorp re future strategies for grain movement – to be reported to Council.
DIRECTOR PLANNING AND ENVIRONMENT Program Activity: Environmental Management & Health Services The purpose of this activity is to manage the natural environment and to enhance community wellbeing by providing a range of public health programs. This activity also includes the noxious plants and pest control program. The desired outcome of this activity is a good quality of life. Activity 1 – To promote a high standard of public health and environmental responsibility
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Inspect premises to ensure compliance with the Public Health Act 1991 and Food Act 2003
Number of inspections in the year.
Number of substantiated complaints concerning food premises
1-4 1-4 50% DPE
Participate in Cancer Community Partnership Program To help lower the impact of cancer in the community
Attendance at bi-annual meetings
No of promotional releases 1-4 1-4 0% DPE
Absence of staff/staff unavailable to meet targets.
Activity 2 – To maintain an environmental management strategy
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Contribute to a Regional State of Environment Report
Regional Plan prepared by statutory guidelines 3 1
2012/13 20% DPE
Due for completion September 2012.
Activity 3 – To maintain a noxious plants and pest control program
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Conduct an education program for farmers
Education ongoing, field days and field trips organised 1 1 100% DPE
Council to endorse Noxious Weeds Management Plans and Shire Wide Management Plan
Plans produced and authorised by Council 1 4 80% DPE
One Field day. Ongoing education program. Noxious Weeds Management Plan drafted shire-wide.
Activity 4 – Computer aided mapping of weed infestations
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Mapping of known infestations of weeds undertaken to DPI requirements
All known weed infestations mapped and stored on appropriate software
1-3 1-3 80% DPE
Mapping in progress. Did not achieve 100% due to the HBS resignation and lack of mapping skills.
Program Activity: Environmental Management & Health Services (Continued) Activity 5 – To maintain animal control over the Shire within resource limitations
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Carry out regular surveillance of each town and village
No. of unregistered dogs and cats
No. of complaints received 1-4 1-4 100% DPE
Ongoing program.
Program Activity: Planning & Building Services The purpose of this activity is to provide assessment and processing of development applications and constructions certificates, provision of plumbing and drainage permits for all development carried in the Shire, planning services and the provision of basic public amenities. The desired outcome of this activity is that development in the Shire meets the required standards and fulfils its statutory obligations within the context of providing sensible and practical solutions for proposed developments and the provision of appropriate public facilities. Activity 1 – To provide planning services to complement the development approval process
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Finalise the develop of the Shire’s Local Environmental Plan (LEP)
LEP fully implemented by December 2011 1-2 4 100% DPE
Process development applications, constructions certificates etc within statutory requirements and timelines
95% compliance 1-4 1-4 100% DPE
Draft LEP with Dept of Planning & Infrastructure. DA’s met statutory requirements.
Activity 2 – To maintain council dwellings to an appropriate standard
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Implement the maintenance program for all council dwellings
Maintenance program carried out within budget 1-4 1-4 100% DPE
12 month program.
Activity 3 – To provide an operate cemetery operation
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Cemeteries administered in accordance with relevant legislation
Burial records maintained and checked on a quarterly basis 1-4 1-4 100% DPE
Ongoing process.
Activity 4 – To maintain the health and Safety of Residential Areas
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Overgrown properties and properties with accumulations of rubbish
Complaints responded to within 14 days and appropriate action commenced
1-4 1-4 100% DPE
Derelict buildings addressed
Action under the EP&A act commenced 1-4 1-4 75% DPE
Nil complaints. Matters relating to derelict buildings are unresolved due to an ongoing compliance action in Rankins Springs
Program Activity: Recreation The purpose of this activity is to provide a range of community facilities including the Hillston Swimming Pool, Goolgowi Swimming Pool, sporting grounds, and parks and gardens. The desired outcome of this activity is well run facilities that conform with quality standards and expectations of the community. Activity 1 – To provide shaded areas in Parks within the Shire
Actions Measurement Qtr Revised Qtr % Comp /
No Officer
Provision of shade structures and tree planting in parks and gardens within the Shire
Number of recreation areas provided with shaded areas 1-4 1-4 0% DPE
No grant funding provided during 3rd Quarter
MANAGER ROADS AND BRIDGES Program Activity: Engineering Services The purpose of this activity is to provide a range of engineering services to complement the wide range of functions in the areas of water, waste, construction and amenity services. The desired outcomes of this activity include efficient and effective staff performing engineering services. Activity 1 – To administer contracts efficiently
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Provide contract services to RTA for State roads
Satisfactory audit of RMCC contract 1-4 0% MRB
Use contract services for bitumen surfacing and quarry operations
Administer contracts in accordance with documents 1-4 4 100% MRB
Use contract services for crushing & blasting at Quarries
Administer contracts in accordance with documents 1-4 4 100% MRB
COMMENTS: RMS has not conducted audit this year. Contracts are operating efficiently.
Activity 2 – To provide sound engineering technical and administrative support services
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Complete statutory returns for water, roads, construction & engineering
Number of returns submitted 1-4
4 9 for
Roads MRB
Conduct Local Traffic Committee meeting with NSW Police and RTA
Number of traffic and safety improvements
Number of compliments and complaints
1-4
4 4 MRB
COMMENTS: Returns and meetings are conducted as required. Nil complaints.
Program Activity: Transport - Road Infrastructure The purpose of this activity is to provide a state, regional and local network of assets such as roads, kerbs and gutters, flood controls, street trees, bus shelters etc. The desired outcome of this activity is a level of service that is delivered based on safety, amenity, practicability, risk and affordability. Activity 1 – To maintain state, regional, and local roads in a safe and trafficable condition
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Local and Regional roads maintained in accordance with program
% works carried out in accordance with program 1-4 100% MRB
Works carried out in accordance with the Road Maintenance Council Contract (RMCC)
% works carried out in accordance with contract 1-4 100% MRB
COMMENTS: Roads are being maintained within budget.
Activity 2 – To review all RTA systems to ensure high level of compliance
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Conduct annual internal audit of quality, OH&S and environmental systems
Audits completed
Systems compliance improved 3 4 65% MRB
COMMENTS: Most RMCC Management Plans have been revised. OHS Plan has been started and will be completed in 2012/13.
Activity 3 – To administer R2R program efficiently)
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Works carried out on R2R Programs
% works carried out on R2R Program
1-4 4 100% MRB
COMMENTS:
One project has been deferred to next financial year. Annual report to be completed.
Program Activity: Transport - Other Infrastructure The purpose of this activity is to provide other transport infrastructure such as aerodromes in Hillston and Goolgowi, and infrastructure such as footpaths. The desired outcome of this activity is a level of service that is delivered based on safety, amenity, practicability, risk and affordability. Activity 1 – Works in Hillston
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Maintain/construct kerb and gutter, reconstruct shoulder and reseal McGregor & Regent Streets
% of works completed 1-4 4 100% MRB
COMMENTS: Work in Hillston is complete for 2011/12.
Activity 2 – Works in Village
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Maintain/construct kerb and gutter, reconstruct shoulder in the Villages as identified
% of works completed 3 4 100% MRB
COMMENTS: This work is complete for 2011/12.
Activity 3 – Stormwater Drainage
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Development of Shire Wide Plan and commencement of works Stage 1 Works for 2011/12
% of works completed 2 4 100% MRB
COMMENTS: Flood damage work major priority during 4th Quarter and will be during 2012/13.
MANAGER FLEET AND TOWN SERVICES Program Activity: Engineering Services The purpose of this activity is to provide a range of engineering services to complement the wide range of functions in the areas of water, waste, construction and amenity services. The desired outcomes of this activity include efficient and effective staff performing engineering services. Activity 1 – Plant traded-in and replaced in accordance with Budget Estimate
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Review plant and fleet requirements prior to purchase in accordance with the budget
The number of plant items replaced within budget estimates
1-4 1-4 100% MFTS
COMMENT: $150,000 under Budget Estimate
Activity 2 – To provide sound engineering technical and administrative support services
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Ensure procurement of goods and materials achieved to provide best value for money
Procurement decisions meet Council Procurement & Tendering policy
1-4 1-4 100% MFTS
COMMENTS: Current practice is to receive at least three quotations.
Program Activity: Public Amenities & Waste Management The purpose of this activity is to provide essential community facilities and amenities such as cemeteries, public conveniences, aerodromes, managed waste facilities and stormwater drainage. The desired outcome of this activity is clean and environmentally conforming amenities and the management of waste within environmental standards that meet community needs. Activity 1 – To provide public conveniences in Hillston, Goolgowi, Merriwagga, Rankins Springs and Carrathool
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Maintain public amenities in accordance with programmed maintenance meeting with health and environmental standards
Number of complements and substantiated complaints 1-4 1-4 100% MFTS
COMMENT: Some minor complaints but acted upon immediately.
Activity 2 – To provide a domestic garbage service and waste disposal sites in the Shire
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Maintain a weekly domestic garbage service for Hillston, Merriwagga and Goolgowi
Number of missed bins 1-4 1-4 100% MFTS
Implement Councils mandate to convert Merriwagga, Goolgowi, Rankins Springs and Carrathool to transfer station and facilitate a change of users behaviour to the new method of waste disposal
Supervision of Goolgowi landfill and restricted opening times leading to better compliance with relevant legislation
1-4 1-4 100% MFTS
COMMENT:
Activity 3 – To provide effective stormwater management and drainage systems in urban areas
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Conduct investigations, design and costing for needed urban stormwater drainage upgrades
Progressive improvements to urban stormwater drainage network and reduced incidence of local flooding
Number of compliments and complaints received
1-4 3-4 50% MFTS
COMMENTS:
Program Activity: Public Amenities & Waste Management (continued) Activity 4 – To provide and operate well managed cemeteries
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Cemeteries operated effectively and maintained to high standard
Number of compliments and complaints received 1-4 1-4 100% MFTS
COMMENT:
Program Activity: Recreation The purpose of this activity is to provide a range of community facilities including the Hillston Swimming Pool, Goolgowi Swimming Pool, sporting grounds, parks and gardens The desired outcome of this activity is well run facilities that conform with quality standards and expectations of the community. Activity 1 – To provide neat and tidy parks and gardens in each town and village
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Maintain and improve Parks and Gardens to meet community needs
Number of compliments and substantiated complaints
Number of parks and gardens improvement projects completed
1-4 100% MFTS
Provide relevant and well maintained playground or other recreation equipment
Routine playground inspections carried out 1-4 100% MFTS
COMMENTS:
Activity 2 – To maintain swimming pools in Hillston and Goolgowi
Actions Measurement Qtr Revised Qtr
% Comp / No
Officer
Maintain financial assistance in the provision of lifeguard training for swimming pool attendants
Number of persons trained 3 4 100% DPE
Water quality maintained to meet required standard
Days pools unavailable 3 4 75% DPE
Monitor pool patronage
Number of active swimmers per annum 3 4 100% DPE
COMMENTS: One person trained for the 2011/12 summer period. Four days Goolgowi pool closed (water contamination) Two days Hillston pool closed (activities)
Activity 4 – To provide well maintained urban streetscape
Actions Measurement Qtr Revised Qtr
% Comp / No
Officer
Provide attractive and well-maintained street landscaping and plantings in urban areas
Number of compliments and complaints received
1-4 100% MFTS
Develop and enhance existing urban street landscaping over time subject to funding
Number of street improvements 1-4 75% MFTS
COMMENTS:
As per Budget forecast
Program Activity: Transport - Other Infrastructure The purpose of this activity is to provide other transport infrastructure such as aerodromes in Hillston and Goolgowi, and infrastructure such as footpaths. The desired outcome of this activity is a level of service that is delivered based on safety, amenity, practicability, risk and affordability. Activity 1 – To maintain safe and effective footpaths
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Conduct regular surveillance on footpaths in accordance with operational policies
Surveillances carried out 1-4 100% MFTS
COMMENT: Periodic inspections as required
Activity 2 – To provide useable airports in Goolgowi and Hillston
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Carry out necessary safety and maintenance check on aerodromes
Checks carried out 1-4 100% MFTS
COMMENTS: Regular inspections carried out & documented
Activity 3 – Hillston Depot
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Ensure arrangements for EPA compliance and OH&S are met
% of works completed 1-4 100% MFTS
COMMENTS:
Activity 4 – Goolgowi Depot
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Ensure arrangements for EPA compliance and OH&S are met
% of works completed 1-4 100% MFTS
COMMENTS:
DIRECTOR CORPORATE SERVICES Program Activity: Risk and Corporate Support The purpose of this activity is to ensure that the organisation performs to the highest standards and in accordance with the expectations of its stakeholders, and includes the main administrative and financial support services in the achievement of Council’s activities. The desired outcomes of this activity include efficient and effective staff performing support services, processes and systems audited regularly, organisational risk identified and addressed within resource limitations and an increase in overall organisational productivity. Activity 1 – To reduce Council’s risk exposure
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Ensure cost effective management of insurances
Insurance cover in place for all Council risks 1 100% DCS
COMMENTS: All relevant insurance policies have been renewed for 2011/12
Program Activity: Community Services & Access The purpose of this activity is to promote access to a range of services, programs and facilities across the Shire and to assist in the cohesive development of cohesive communities. The desired outcome of this activity is increased capacity building, better coordinated and supported community activities and delivery of activities for the elderly and youth. Activity 1 – Provide various “Community” services to the elderly and others in need in line with funding and other requirements provided by both State and Federal Agencies
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Service Providers Include – HACC – Home Aged Community Care CACP – Community Aged Care Packages CT – Community Transport NRCP – Respite Care MOW – Meals on Wheels
Services provided to satisfaction of clients and various funding bodies
1-4 1-4 75% DPE
COMMENTS: Services maintained during 4th quarter and full year. Five programs were delivered below funding targets for financial year 2011/2012
Activity 2 – Review service with all funding bodies
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Liaise with all funding bodies and seek options to improve and/or consolidate reporting requirements
Satisfactory progress and discussions held 3 4 100% DPE
Following extensive discussions with NSW ADHC and Federal DoHA, the engagement of external providers for CACP and NRCP may occur during 2012/13.
Activity 3 – To provide a range of services to the elderly including HACC services
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Organise Seniors Week 2012 Number attending 3 100% DCS
The Seniors Week trip to Ootha to view the ‘Utes in the Paddock’ outdoor gallery with the Seniors Week Luncheon including special guest Jon Vagg was held.
Program Activity: Cultural Services The purpose of this activity is to continue to provide the community with library facilities including a number of business facilities that would not otherwise be easily available, and the provision of public halls. The desired outcome of this activity is a state of art library with complementary business facilities, up to date public internet facilities at the Library, and Council’s Administration Building during normal operating hours Activity 1 – To provide library facilities and associated services to the community
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Maintain membership of the Western Riverina Community Library
Membership maintained 1 100% DCS
COMMENTS: Membership renewed for 2011/12
Activity 2 – To provide internet access and transaction centre services
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Maintain internet facilities for the public in Hillston and Goolgowi
Number of internet users 1-4 100% DCS
COMMENTS: Facilities maintained during 4th Quarter
Program Activity: Financial Services The purpose of this activity is to provide a viable revenue raising strategy that is fair and equitable to all ratepayers and residents of the Shire. The desired outcome is sufficient revenue sources to maintain operations and service delivery. Activity 1 – To explore alternative revenue sources
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Review the Financial Assistance Grants with a view to maximising return to Council
FAGs application reviewed 2 100% DCS
Review all current revenue sources and explore new sources
Review completed 2 3-4 100% DCS
COMMENTS: Report submitted to Council in relation to FAG. Operational Plan for 2012/13 was presented to May 2012 Council Meeting.
Activity 2 – Revise rating options for future years
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Evaluation of alternate rating structures for future years
To be incorporated in Council’s Long Term Financial Plan, which will be on-going during the first six months of 2011/12
1-3 100% DCS
Continue representations to regional groups and government
Quarterly reports to Council 1-3 100% DCS
COMMENTS:
Water Supply community consultations were held in January 2012. New General Re-Valuations yet to be received. New values to become effective as from July 2013. Operational Plan for 2012/13 adopted by Council on 26 June 2012
Activity 3 – To improve computer system
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
Development of new IT consolidation strategy
Quarterly reports to council 1-2 4 100% DCS
COMMENTS: New servers for the main system installed have been installed, plus new compatible equipment, where necessary. New & better back up arrangements now implemented. Work at Hillston District Office completed during June 2012.
Program Activity: Financial Services (Continued) Activity 4 – Revised revenue raising options
Actions Measurement Qtr Revised Qtr
% Comp / No Officer
In conjunction with other division managers determine future capital works, including Water Supply and Sewer Services and evaluate through community consultation
To be incorporated in Council’s Long Term Financial Plan, which will be on-going during the first six months of 2011/12
1-3 4 100% DCS
COMMENTS:
The Water Supply community consultations were carried out during January 2012, which included a mail out survey to all water supply customers. Future capital works for the next 10 years (mainly to be funded from loan funds) have been incorporated into Council’s Operational Plan for 2012/13 – it’s Long Term Financial Plan.