maintenance recommendations

Upload: msalem73

Post on 14-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Maintenance Recommendations

    1/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 1 of15

    Maintenance Considerations for Shuaiba North CCGT

    ** Noted that this information has been extracted from the various Vendor OEM manuals,and should only be used as a Guide, specific maintenance requirements should be sourced by

    the owner using the specific Vendor manuals for detailed maintenance activities.

    Fuel Gas Compressors

    Functional test of safety devices Yearly

    Check function of control mechanism (IGV/DGV) Monthly

    Check oil level (oil tanks) Daily

    Check oil supply motor Daily

    Check oil filter for fouling Daily

    Check condensate trap, drain condensate (unless done

    automatically) Daily

    Check centrifugal compressor for irregular noise/Irregularities, etc. Daily

    Check plant for gas, water and oil leakage DailyOil inspection, Lab test Yearly

    Compare thermodynamic data Yearly

    Minor Inspection plant (includes all of the above) Yearly

    Major Inspection plant 2 years

    Includes all of the above tests

    Gear teeth - Teeth and contact pattern

    Axial bearings - Contact pattern and clearance

    Pinion shaft bearings - Contact pattern and clearance. Replace if necessary.

    Bull wheel shaft bearings - Contact pattern and clearance. Replace if necessary.

    Shaft bearing fits - Contact pattern; check diameter

    Oil seal - Clearance. Replace if necessary

    Shaft seal - Contact pattern, surface, clearances

    Axial shaft position pick-up - Mounting, measuring clearance

    Shaft vibration pick-up - Mounting, measuring clearance

    Adjustable guide vanes - Vanes, ease of adjustment and position, surface

    Suction nozzle - Surface

    Impeller - Inlet edges, surface cleanliness, concentricity with rotor shaft, crack-test

    Coupling - Dismantle spacer, check alignment. Coupling hubs equipped with one shaft key

    must be balanced with half of the shaft key installed. Otherwise it must be verified that the

    required balancing quality is obtained also with un-grooved hub despite the existing

    difference in weight. Vibration and rotor position monitoring calibration check

    Probe, cable and proximitor - calibration check

    Monitor gain adjustment- calibration check

  • 7/30/2019 Maintenance Recommendations

    2/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 2 of15

    GTTwo types of Maintenance

    Running - online

    Shutdown offline (these include Combustion, Hot Gas path, Major)

    Maintenance BasicsIf the GT is offline or will be shutdown for 3 weeks or more with no maintenance activity

    happening, then the GT should be placed on turning gear for at least 1 hour per day to reduce build

    up of corrosive deposits in the blading (specifically the turbine blades) or Run GT at FSNL for 1

    hour to dry out the GT internally.

    Time frame assumptions is if the next items are available. all tooling, parts, labour, planning, no

    repair time just replacement, mechanical side only. (Flange to Flange.)

    Combustion Inspection (Yearly) (Duration 10 x 8 hr shifts)This type of inspection is required to remove and inspect the combustion area components and or

    replace as required, Fuel nozzles, Combustion Liners, Transition pieces and Cross fire tubes. It

    should be noted that if you need to change any 1 of the individual components then the full set

    should done, and kept together. All components can then be cleaned or recalibrated at a later date,to minimise down time.

    It should be noted that a visual should also be done on the Leading edge of the First stage Turbine

    Nozzle partitions at this time.

    Fuel Nozzles

    Combustion Liners

    Transition Pieces

    Cross fire tubes

    At the same time these can be done

    VIGV checks and calibration as required (linkages, hydraulics, Individual pinion movement)

    Hot Gas path Inspection (2.5 Years) (Duration 22 x 8 hr shifts)The Hot Gas Path Inspection requires that the combustion Inspection is also done as well as the

    following; The Turbine Nozzles and Turbine Buckets.

    Removal of the turbine casing shell

    Visual inspection of all nozzle stages

    First stage nozzles are removed

    Complete set of Turbine blade clearances are taken

    Major Inspection (5 yearly)(duration 46 x 8 hr shifts)

    The major Inspection includes both the Combustion and Hot gas path Inspections as well as thefollowing;

    Casings are inspected for cracks and erosion,

    Rotor and stator blades are to be checked for tip clearance, rubs, bowing, cracking, and

    warpage.

    Shrouds are checked for clearance, erosion, rubbing and build up.

    Seals and hook fits of nozzles and diaphragms are inspected for rubs, erosion, fretting or

    thermal deterioration.

    The compressor and inlet are inspected for fouling, erosion, corrosion, and leakage.

    Bearings and seals are inspected for clearance and wear.

    All clearances are checked against their original values.

  • 7/30/2019 Maintenance Recommendations

    3/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 3 of15

    Auxiliary and Control systemsIt should noted that the below information is as a general guide and maybe not specific to the

    individual supplier, for specific complete information please refer to the specific vendor manuals.

    A Guide of durations

    D - Daily InspectionW - Weekly InspectionM - Monthly InspectionQ - Quarterly Inspection

    SA - Semi-annual InspectionCI - Combustion InspectionA - Annual InspectionHGP - Hot Gas Path InspectionMaj - Major Overhaul InspectionYrs. - Years

  • 7/30/2019 Maintenance Recommendations

    4/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 4 of15

    PERIODIC INSPECTION

    SCHEDULE

    Inspection Frequency

    INSTRUMENTATION

    Pressure Switches and Gauge D

    Calibration A

    Thermometers (Dial Type) A

    Calibration A

    Flow-meters A

    Leaking Seams and Joints A

    Calibration A

    Vibration Detectors D A

    Liquid level indicators A

    Panel Meters D M A

    CONTROL DEVICES

    Temperature Switches D

    Calibration A

    Dropout Setting A

    Thermostats

    Calibration Setting A

    Pressure Regulating Valves

    (VPRs) Packing Leakage M

    Temperature Regulating

    Valves (VTR s) Packing Leakage M

    HYDRAULIC/MECHANICAL EQUIPMENT

    Relief Valves

    Chattering and Leakage M

    Settings A

    Full Test A HGP

    Solenoid Valves

    Leakage M

    Proper Operation A

    Servo-valves

    Verify proper torque (17-19 inch pounds) A

    OrificesErosion or Corrosion A

  • 7/30/2019 Maintenance Recommendations

    5/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 5 of15

    Plugging, Orifice Deterioration A

    Sharp Edges or Irregular Chamfer A

    Check Valves

    Leakage SA

    Corrosion Maj

    STRAINERS

    Gas/Liquid SA

    Filters, Lube D M

    Leaking Seams and Joints Dirty Elements SA

    Hydraulic Supply Filter D

    Leaking Seams and Joints Dirty Elements M SA

    Air Filters

    (Air Extraction Valve) Moisture Accumulation M

    Dirty Filter S A

    HEATING COOLING AND VENTILATION

    Air Conditioners

    Dirty Filter W

    Improper Thermostat Setting W

    Dirty Condenser Coil

    Space Heaters

    Improper Operation A

    Dirty Heating Elements, Blades and A

    Louvers A

    Improper Thermostat Setting A

    Accessory and Turbine

    Compartment Vent Fans Excessive Fan Wheel Wear A

    Vibration A

    Cleanliness A

    MOTORS AND PUMP COUPLINGs

    Motors

    Excessive Vibration A

    Dirty Louvers and Screens A

    Loose Mounting Bolts and Electrical Connections A

    Dirty Windings, Collector Rings, A

    Commutator, Brush Rigging, Brush Condition A

    Loose Bolts and Grease Plugs AEvidence of Wear A

  • 7/30/2019 Maintenance Recommendations

    6/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 6 of15

    LUBE SYSTEM

    Lube Oil Pumps

    Excessive Noise Wear D M

    Ring Clearance Maj

    Thrust Bearing Wear Maj

    Bearing Seal Wear Maj

    Lube Oil Tank

    Oil Levels D

    Peeling Paint A

    Loose Hardware, Fittings on Internal Piping and Tubing Maj

    Presence of Sludge and Unusual Foreign Matter in Bottom of Tank Maj

    Lube Oil Properties

    Irregular Physical Properties of Lubricant Sample Taken from Tanks

    and Presence of Contaminants M

    Heat Exchangers

    Improper Operation D M

    Leakage D M

    Contaminated Water M

    Plugging of Leaking Tubes 3 Yrs

    Lube Oil Immersion Heaters

    Improper Operation M

    Mist Eliminator

    Excessive Pressure Drop across Unit M

    Oil Vapour Leakage D M

    Dirty Filter Element M

    Condition of Filter Element Fibre Bed M

    Mist Eliminator Fan

    Dirty Fan Housing M

    Loose Mounting Bolts M

    Excessive Vibration Noise D M

    Pipe CouplingsOil Leakage/Hardware Security D

    Seal Brittleness A

  • 7/30/2019 Maintenance Recommendations

    7/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 7 of15

    WATER SYSTEM

    Cooling System Checks

    System Fouled with Contaminants Maj

    Improper Water Flow Maj

    Incorrect Flow Versus Pressure Drop Maj

    Water Tank

    Evidence of Tank Leakage A

    Improper Pressure Cap Setting HGP

    Poor Condition of Cap Gasket and Gasket Surface M

    Damaged Filler Neck A

    Dirt Inside Tank A

    Corrosion Inhibition Q

    (Or Every Water Addition)

    Radiator Header Assemblies

    Leaking Seams and Joints M

    Corrosion and Erosion of Fins and Tubes M

    Damaged Parts M

    Cleanliness A

    Anti-Freeze Protection Improper Concentration A

    Cooling Water Radiator Fan Dirty Wheel Housing, Ducts and Module

    Screens A

    Excessive Vibration Noise A

    Damaged Blades A

    Loose Mounting Bolts A

    Air Flow Obstructed A

    Rust, Corrosion and Peeling A

    Cooling Water Pump

    Leakage Shaft Seal M

    Dirty Shaft Seal Cooling Water Line and Filter Element A

    Excessive Wear Ring Clearance Maj

    Excessive Mechanical Seal Wear Maj

    FUEL GAS SYSTEM

    Gas Control Valve

    Gas Leakage at Stem, Packing Leak Off or Vent M

    Hydraulic Cylinder Rod Seal Leakage M

    Rough Operation SA

    Improper Operation of Trip Relay S A

    Damage Control Surfaces of Valve Plug and Seat M a j

    Trip Action with Loss of Hydraulic Trip Oil S A

  • 7/30/2019 Maintenance Recommendations

    8/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 8 of15

    HIGH PRESSURE CONTROL OIL, SYSTEM HYDRAULIC SUPPLY

    Main Hydraulic Supply

    Pump

    Excessive Vibration or Unusual Noise,

    Improper Discharge Pressure M

    Relief Valve Leaking D

    Leakage at Shaft and Mounting A

    Flanges M

    Auxiliary Hydraulic Supply

    Pump

    Low Discharge Pressure A

    Leakage around Shaft and Mounting Flanges M

    Excessive Vibration or Unusual Noise M

    Hydraulic Supply Manifold

    Connections Loose or Leaking A

    Air Bleed Valves

    Air Bleed Valve Operation A

    Accumulator

    Check charge Pressure A

    Accumulator Safety Disc A

    Hydraulic System Piping

    Leaking Pipe Connections (All Units) HGP

    INLET GUIDE VANE CONTROL SYSTEM

    Operation and Calibration Control

    Inlet Guide Vanes Proper Operation Specification, Calibration D

    20TV Trip Servo Valve for Proper Operation A

    Check Trip Action of Inlet Guide Vanes with Loss of Hydraulic Trip Oil SA

    Check Operation and Sequencing of -

    - Specification Compressor Bleed Valves SALeakage in the System M

  • 7/30/2019 Maintenance Recommendations

    9/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 9 of15

    COOLING AND SEALING AIR SYSTEM

    PipingOrifice Plates A

    Orifice Unions A

    Leakage D

    Loose Hardware, Hangers and Clamps M

    Vibration M

    Compressor Bleed Valve

    Sluggish Movement Open/Close SA

    Leakage M

    Compressor DischargePressure Transmitter Calibration A

    STARTING SYSTEM

    Starting

    See Vendors Preventive Maintenance

    A or 90 Starts

    Starting Motor

    See Vendors Preventive Maintenance Procedure in

    Starting System Tab A

    Starting Clutch

    Improper Clearance of Clutch Jaws at Engaged and

    Disengaged Positions SA

    Improper Operation of Limit Switch SA

    Worn Clutch Jaws A

    Torque Converter

    External Oil Leaks at Shaft Seals,

    Bolted Flanges, Cover Plates D

    Tubing Connections andHydraulic Hoses

    Leakage, Wear, Chafing and Abrasions Q

    Ratchet System

    Oil Leakage D

    Dirt in Commutator A

    Faulty Pump A

  • 7/30/2019 Maintenance Recommendations

    10/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 10 of15

    FIRE PROTECTION SYSTEM

    System Package LaggingLeakage at Lagging A

    Open Joints Between Bases, Roof Joints and Door Fits A

    Pilot Operated Cylinders Show Improper Pressure at Gauges A

    High pressure system

    Ventilation dampers operate freely and no obstructions A

    High Pressure Storage

    Loss of cylinder weight SA

    Fire Detectors operation A

    High Pressure System Solenoid Pilot Valve Puff test

    Confirm operation of the system A

    Ventilation dampers operate freely A

    Low pressure CO2 System Electric release and Puff Tests

    Confirm operation of the system A

    Ventilation dampers operate freely A

    WATER INJECTION SYSTEM

    Control Systems Maintenance

    Calibration Electronic Circuits A

    Calibration of Control Valve Circuits A

    Calibration of Flow-meter Circuits A

    Check Flow-meter Accuracy 3 Yrs

    Check Control Valve for Leakage A

    Check Stop Valve Operation A

    Check Stop Valve for Leakage A

    Check Forwarding Pump Oil Level M

    Check that Water Flow is per Control Specifications DCheck Accumulator charge A

    Check Water Spray Nozzles for Plugging and Spray Pattern A

  • 7/30/2019 Maintenance Recommendations

    11/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 11 of15

    STATION AUXILIARIES AND SERVICE

    BatteryImproper Specific Gravity at Pilot Cell M

    Low Electrolyte Level at Pilot Cell M

    Loose and Dirty Connections M

    Damaged Containers and Cell Covers M

    Faulty Sealing or Missing Vent Plugs M

    Improper Specific Gravity and Low Electrolyte at any One Cell A

    Battery Charger

    Check Cleanliness of Charger A

    Voltmeter Calibration SA

    Check Capacitors and Diodes (if Faulty) A

    MOTOR CONTROL CENTRE

    Indicating Lamps

    Burned Out Lamps (or as necessary)

    M

    Improper Operating Lighting Sequence M

    Main Bus Insulators Dirty Bus Insulators and Barriers A

    Main Vertical Bus Joints and Main Bus Supports Loose Connections A

    Magnetic Contactors and StartersDirty Contactors and Starters A

    Loose Connections A

    Contacts Welded Together, Worn and Arcing A

    Magnetic Relays

    Dirt, Dust, Oil, Grease A

    General Purpose Contactors

    Damaged Arc Chute A

    Improper Arcing Horn Clearances A

    Improper Armature Spring Adjustment AWeak Contact Pressure A

    Loose Screws, Nuts and Bolts A

    General

    Improper Closing and Latching of Control Panel Doors A

    Nameplates Missing A

    Cleanliness of Panel A

  • 7/30/2019 Maintenance Recommendations

    12/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 12 of15

    Starting Motor Limit amp Contactor

    Loose Screws, Nuts and Bolts Loose,

    Electrical Interlocks Contacts, General Condition A

    DC Magnet Assembly Alignment per Specification A

    Collars on Each Side of Movable Power Tips for Proper Fit and

    Alignment A

    Accumulation of Dust, Dirt and Foreign Material on

    Contactor and Arc Chutes A

    COLLECTOR COMPARTMENTS

    Fibreglass Expansion Joints

    Loose joints M

    Cleanliness MCooling Air discharge vents

    M

    Generator Ends and Compartment interfaces

    Seals Damaged/Watertightness M

    Collector compartment Air filters

    Filter Cleanliness A

    INLETAIR SYSTEMS

    Inlet Screens

    Obstructions D

    By-Pass Door System

    Correct Seal M

    L im it S wi tc h O pe ra ti on ( Mo nt h- Ch ec k, A nn ua l- O pe ra te ) M A

    Inlet Ductwork/Silencers

    Sealing A

    Cleanliness AF i l te r C a rt r i dg e s( M on t h- c o nf i r m D P , A n nu a l- P hy s ic a l c h ec k ) M A

    (replace as necessary in between)

    IGVs

    Corrosion/Pitting A

    Moisture Separators

    Cleanliness of Media Section M

    Build Up on Blades A

  • 7/30/2019 Maintenance Recommendations

    13/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 13 of15

    Evaporative Cooler

    Lubricate Motor A

    Tanks for Debris A

    Media Build-up A

    Nozzles blocking M

    Spray Pattern A

    Clean Tank A

    Water Flow Adjustment

    Proper Water Flow to confirm Media Wetness D

    Lubrication SchedulesLubrication is required on most turbine external moving parts, Lubrication requirements are

    difficult to establish they depend on Air temperature and operating hours, the owner should

    set a basic monthly schedule and monitor the lubrication and adjust the schedule to suit.

  • 7/30/2019 Maintenance Recommendations

    14/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 14 of15

    GT Generator

    Minor Every 30 Months (2.5 years)

    Major - Every 60 months (5 years)After 1 year of duty operation (8760 hours or 300 starts)

    Generator end plates/shields are removed to inspect the stator ends wear inspection.

    Hydrogen cooling system drained and pressure test if required, all Hydrogen fillingstations checked, Hydrogen seals checked or replaced as required.

    After 60 months (5 years) of duty the Stator is removed for full inspection

    Complete inspection of the field and rotor coatings, insulation, wear and tear.

    Listing of assigned checks and durations

    RTD Element Res. - Gas & Winding RTDs

    Checks for calibration & poor connections. Minor/Major

    RTD Ground Insulation - Stator Winding RTDsInsulation condition of RTD. Minor/Major

    Winding Copper Res.- Stator Winding

    Checks for poor connections & breaks. Minor/Major

    Insulation Resistance (aka CE Bearing Contamination

    and/or deterioration of insulation. Minor/Major

    Hydrogen Seal Casing

    Contamination and/or deterioration of insulation. Minor/Major

    Polarization Index - Stator WindingContamination and/or deterioration of insulation. Minor/Major

    DC Leakage Current - Stator Winding

    Contamination and/or deterioration of insulation. Minor/Major

    Over Potential/Hipot - Stator Winding

    Ground wall insulation integrity Minor/Major

    Wedge Tightness Map - Stator WedgesDetect wedge tightness deterioration Minor/Major

    Magnetic Scalar Potential (EL CID) -

    Stator Core Insulation Weak or damaged core enamel. Minor/Major

    Vacuum Decay - Water Cooled Stator Cher Winding Checks the hydraulic integrity of the entire winding. Minor/Major

    Pressure Decay - Water Cooled Stator Winding

    Checks the hydraulic integrity of the entire winding. Minor/Major

    Capacitance Mapping - Water Cooled Stator Winding

    Wet ground wall bar insulation Major

    Helium Tracer Gas - Water Cooled Stator Winding

    Detects minute leaks in the hydraulic circuit. Major

    Visual Inspections

    o Core Laminations Foreign Object Damage Minor/Major

    o Space Blocks Migration, - cooling passage blockage Minor/Major

    o Gas Gap Baffles Cracked welds, looseness Minor/Majoro Stator Wedges Evidence of abrasion or looseness Minor/Major

  • 7/30/2019 Maintenance Recommendations

    15/15

    TechComm Simulation Pty Ltd

    TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 15 of 15

    o Stator Bars Evidence of abrasion or looseness Minor/Major

    o End Windings and connection rings

    o Evidence of relative motion, loose/broken ties, hardware,

    Corona activity Minor/Major

    o Copper Flux Shield Overheating, hardware looseness Minor/Major

    o Overall cleanliness Oil or other contamination