maintenance recommendations
TRANSCRIPT
-
7/30/2019 Maintenance Recommendations
1/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 1 of15
Maintenance Considerations for Shuaiba North CCGT
** Noted that this information has been extracted from the various Vendor OEM manuals,and should only be used as a Guide, specific maintenance requirements should be sourced by
the owner using the specific Vendor manuals for detailed maintenance activities.
Fuel Gas Compressors
Functional test of safety devices Yearly
Check function of control mechanism (IGV/DGV) Monthly
Check oil level (oil tanks) Daily
Check oil supply motor Daily
Check oil filter for fouling Daily
Check condensate trap, drain condensate (unless done
automatically) Daily
Check centrifugal compressor for irregular noise/Irregularities, etc. Daily
Check plant for gas, water and oil leakage DailyOil inspection, Lab test Yearly
Compare thermodynamic data Yearly
Minor Inspection plant (includes all of the above) Yearly
Major Inspection plant 2 years
Includes all of the above tests
Gear teeth - Teeth and contact pattern
Axial bearings - Contact pattern and clearance
Pinion shaft bearings - Contact pattern and clearance. Replace if necessary.
Bull wheel shaft bearings - Contact pattern and clearance. Replace if necessary.
Shaft bearing fits - Contact pattern; check diameter
Oil seal - Clearance. Replace if necessary
Shaft seal - Contact pattern, surface, clearances
Axial shaft position pick-up - Mounting, measuring clearance
Shaft vibration pick-up - Mounting, measuring clearance
Adjustable guide vanes - Vanes, ease of adjustment and position, surface
Suction nozzle - Surface
Impeller - Inlet edges, surface cleanliness, concentricity with rotor shaft, crack-test
Coupling - Dismantle spacer, check alignment. Coupling hubs equipped with one shaft key
must be balanced with half of the shaft key installed. Otherwise it must be verified that the
required balancing quality is obtained also with un-grooved hub despite the existing
difference in weight. Vibration and rotor position monitoring calibration check
Probe, cable and proximitor - calibration check
Monitor gain adjustment- calibration check
-
7/30/2019 Maintenance Recommendations
2/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 2 of15
GTTwo types of Maintenance
Running - online
Shutdown offline (these include Combustion, Hot Gas path, Major)
Maintenance BasicsIf the GT is offline or will be shutdown for 3 weeks or more with no maintenance activity
happening, then the GT should be placed on turning gear for at least 1 hour per day to reduce build
up of corrosive deposits in the blading (specifically the turbine blades) or Run GT at FSNL for 1
hour to dry out the GT internally.
Time frame assumptions is if the next items are available. all tooling, parts, labour, planning, no
repair time just replacement, mechanical side only. (Flange to Flange.)
Combustion Inspection (Yearly) (Duration 10 x 8 hr shifts)This type of inspection is required to remove and inspect the combustion area components and or
replace as required, Fuel nozzles, Combustion Liners, Transition pieces and Cross fire tubes. It
should be noted that if you need to change any 1 of the individual components then the full set
should done, and kept together. All components can then be cleaned or recalibrated at a later date,to minimise down time.
It should be noted that a visual should also be done on the Leading edge of the First stage Turbine
Nozzle partitions at this time.
Fuel Nozzles
Combustion Liners
Transition Pieces
Cross fire tubes
At the same time these can be done
VIGV checks and calibration as required (linkages, hydraulics, Individual pinion movement)
Hot Gas path Inspection (2.5 Years) (Duration 22 x 8 hr shifts)The Hot Gas Path Inspection requires that the combustion Inspection is also done as well as the
following; The Turbine Nozzles and Turbine Buckets.
Removal of the turbine casing shell
Visual inspection of all nozzle stages
First stage nozzles are removed
Complete set of Turbine blade clearances are taken
Major Inspection (5 yearly)(duration 46 x 8 hr shifts)
The major Inspection includes both the Combustion and Hot gas path Inspections as well as thefollowing;
Casings are inspected for cracks and erosion,
Rotor and stator blades are to be checked for tip clearance, rubs, bowing, cracking, and
warpage.
Shrouds are checked for clearance, erosion, rubbing and build up.
Seals and hook fits of nozzles and diaphragms are inspected for rubs, erosion, fretting or
thermal deterioration.
The compressor and inlet are inspected for fouling, erosion, corrosion, and leakage.
Bearings and seals are inspected for clearance and wear.
All clearances are checked against their original values.
-
7/30/2019 Maintenance Recommendations
3/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 3 of15
Auxiliary and Control systemsIt should noted that the below information is as a general guide and maybe not specific to the
individual supplier, for specific complete information please refer to the specific vendor manuals.
A Guide of durations
D - Daily InspectionW - Weekly InspectionM - Monthly InspectionQ - Quarterly Inspection
SA - Semi-annual InspectionCI - Combustion InspectionA - Annual InspectionHGP - Hot Gas Path InspectionMaj - Major Overhaul InspectionYrs. - Years
-
7/30/2019 Maintenance Recommendations
4/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 4 of15
PERIODIC INSPECTION
SCHEDULE
Inspection Frequency
INSTRUMENTATION
Pressure Switches and Gauge D
Calibration A
Thermometers (Dial Type) A
Calibration A
Flow-meters A
Leaking Seams and Joints A
Calibration A
Vibration Detectors D A
Liquid level indicators A
Panel Meters D M A
CONTROL DEVICES
Temperature Switches D
Calibration A
Dropout Setting A
Thermostats
Calibration Setting A
Pressure Regulating Valves
(VPRs) Packing Leakage M
Temperature Regulating
Valves (VTR s) Packing Leakage M
HYDRAULIC/MECHANICAL EQUIPMENT
Relief Valves
Chattering and Leakage M
Settings A
Full Test A HGP
Solenoid Valves
Leakage M
Proper Operation A
Servo-valves
Verify proper torque (17-19 inch pounds) A
OrificesErosion or Corrosion A
-
7/30/2019 Maintenance Recommendations
5/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 5 of15
Plugging, Orifice Deterioration A
Sharp Edges or Irregular Chamfer A
Check Valves
Leakage SA
Corrosion Maj
STRAINERS
Gas/Liquid SA
Filters, Lube D M
Leaking Seams and Joints Dirty Elements SA
Hydraulic Supply Filter D
Leaking Seams and Joints Dirty Elements M SA
Air Filters
(Air Extraction Valve) Moisture Accumulation M
Dirty Filter S A
HEATING COOLING AND VENTILATION
Air Conditioners
Dirty Filter W
Improper Thermostat Setting W
Dirty Condenser Coil
Space Heaters
Improper Operation A
Dirty Heating Elements, Blades and A
Louvers A
Improper Thermostat Setting A
Accessory and Turbine
Compartment Vent Fans Excessive Fan Wheel Wear A
Vibration A
Cleanliness A
MOTORS AND PUMP COUPLINGs
Motors
Excessive Vibration A
Dirty Louvers and Screens A
Loose Mounting Bolts and Electrical Connections A
Dirty Windings, Collector Rings, A
Commutator, Brush Rigging, Brush Condition A
Loose Bolts and Grease Plugs AEvidence of Wear A
-
7/30/2019 Maintenance Recommendations
6/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 6 of15
LUBE SYSTEM
Lube Oil Pumps
Excessive Noise Wear D M
Ring Clearance Maj
Thrust Bearing Wear Maj
Bearing Seal Wear Maj
Lube Oil Tank
Oil Levels D
Peeling Paint A
Loose Hardware, Fittings on Internal Piping and Tubing Maj
Presence of Sludge and Unusual Foreign Matter in Bottom of Tank Maj
Lube Oil Properties
Irregular Physical Properties of Lubricant Sample Taken from Tanks
and Presence of Contaminants M
Heat Exchangers
Improper Operation D M
Leakage D M
Contaminated Water M
Plugging of Leaking Tubes 3 Yrs
Lube Oil Immersion Heaters
Improper Operation M
Mist Eliminator
Excessive Pressure Drop across Unit M
Oil Vapour Leakage D M
Dirty Filter Element M
Condition of Filter Element Fibre Bed M
Mist Eliminator Fan
Dirty Fan Housing M
Loose Mounting Bolts M
Excessive Vibration Noise D M
Pipe CouplingsOil Leakage/Hardware Security D
Seal Brittleness A
-
7/30/2019 Maintenance Recommendations
7/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 7 of15
WATER SYSTEM
Cooling System Checks
System Fouled with Contaminants Maj
Improper Water Flow Maj
Incorrect Flow Versus Pressure Drop Maj
Water Tank
Evidence of Tank Leakage A
Improper Pressure Cap Setting HGP
Poor Condition of Cap Gasket and Gasket Surface M
Damaged Filler Neck A
Dirt Inside Tank A
Corrosion Inhibition Q
(Or Every Water Addition)
Radiator Header Assemblies
Leaking Seams and Joints M
Corrosion and Erosion of Fins and Tubes M
Damaged Parts M
Cleanliness A
Anti-Freeze Protection Improper Concentration A
Cooling Water Radiator Fan Dirty Wheel Housing, Ducts and Module
Screens A
Excessive Vibration Noise A
Damaged Blades A
Loose Mounting Bolts A
Air Flow Obstructed A
Rust, Corrosion and Peeling A
Cooling Water Pump
Leakage Shaft Seal M
Dirty Shaft Seal Cooling Water Line and Filter Element A
Excessive Wear Ring Clearance Maj
Excessive Mechanical Seal Wear Maj
FUEL GAS SYSTEM
Gas Control Valve
Gas Leakage at Stem, Packing Leak Off or Vent M
Hydraulic Cylinder Rod Seal Leakage M
Rough Operation SA
Improper Operation of Trip Relay S A
Damage Control Surfaces of Valve Plug and Seat M a j
Trip Action with Loss of Hydraulic Trip Oil S A
-
7/30/2019 Maintenance Recommendations
8/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 8 of15
HIGH PRESSURE CONTROL OIL, SYSTEM HYDRAULIC SUPPLY
Main Hydraulic Supply
Pump
Excessive Vibration or Unusual Noise,
Improper Discharge Pressure M
Relief Valve Leaking D
Leakage at Shaft and Mounting A
Flanges M
Auxiliary Hydraulic Supply
Pump
Low Discharge Pressure A
Leakage around Shaft and Mounting Flanges M
Excessive Vibration or Unusual Noise M
Hydraulic Supply Manifold
Connections Loose or Leaking A
Air Bleed Valves
Air Bleed Valve Operation A
Accumulator
Check charge Pressure A
Accumulator Safety Disc A
Hydraulic System Piping
Leaking Pipe Connections (All Units) HGP
INLET GUIDE VANE CONTROL SYSTEM
Operation and Calibration Control
Inlet Guide Vanes Proper Operation Specification, Calibration D
20TV Trip Servo Valve for Proper Operation A
Check Trip Action of Inlet Guide Vanes with Loss of Hydraulic Trip Oil SA
Check Operation and Sequencing of -
- Specification Compressor Bleed Valves SALeakage in the System M
-
7/30/2019 Maintenance Recommendations
9/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 9 of15
COOLING AND SEALING AIR SYSTEM
PipingOrifice Plates A
Orifice Unions A
Leakage D
Loose Hardware, Hangers and Clamps M
Vibration M
Compressor Bleed Valve
Sluggish Movement Open/Close SA
Leakage M
Compressor DischargePressure Transmitter Calibration A
STARTING SYSTEM
Starting
See Vendors Preventive Maintenance
A or 90 Starts
Starting Motor
See Vendors Preventive Maintenance Procedure in
Starting System Tab A
Starting Clutch
Improper Clearance of Clutch Jaws at Engaged and
Disengaged Positions SA
Improper Operation of Limit Switch SA
Worn Clutch Jaws A
Torque Converter
External Oil Leaks at Shaft Seals,
Bolted Flanges, Cover Plates D
Tubing Connections andHydraulic Hoses
Leakage, Wear, Chafing and Abrasions Q
Ratchet System
Oil Leakage D
Dirt in Commutator A
Faulty Pump A
-
7/30/2019 Maintenance Recommendations
10/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 10 of15
FIRE PROTECTION SYSTEM
System Package LaggingLeakage at Lagging A
Open Joints Between Bases, Roof Joints and Door Fits A
Pilot Operated Cylinders Show Improper Pressure at Gauges A
High pressure system
Ventilation dampers operate freely and no obstructions A
High Pressure Storage
Loss of cylinder weight SA
Fire Detectors operation A
High Pressure System Solenoid Pilot Valve Puff test
Confirm operation of the system A
Ventilation dampers operate freely A
Low pressure CO2 System Electric release and Puff Tests
Confirm operation of the system A
Ventilation dampers operate freely A
WATER INJECTION SYSTEM
Control Systems Maintenance
Calibration Electronic Circuits A
Calibration of Control Valve Circuits A
Calibration of Flow-meter Circuits A
Check Flow-meter Accuracy 3 Yrs
Check Control Valve for Leakage A
Check Stop Valve Operation A
Check Stop Valve for Leakage A
Check Forwarding Pump Oil Level M
Check that Water Flow is per Control Specifications DCheck Accumulator charge A
Check Water Spray Nozzles for Plugging and Spray Pattern A
-
7/30/2019 Maintenance Recommendations
11/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 11 of15
STATION AUXILIARIES AND SERVICE
BatteryImproper Specific Gravity at Pilot Cell M
Low Electrolyte Level at Pilot Cell M
Loose and Dirty Connections M
Damaged Containers and Cell Covers M
Faulty Sealing or Missing Vent Plugs M
Improper Specific Gravity and Low Electrolyte at any One Cell A
Battery Charger
Check Cleanliness of Charger A
Voltmeter Calibration SA
Check Capacitors and Diodes (if Faulty) A
MOTOR CONTROL CENTRE
Indicating Lamps
Burned Out Lamps (or as necessary)
M
Improper Operating Lighting Sequence M
Main Bus Insulators Dirty Bus Insulators and Barriers A
Main Vertical Bus Joints and Main Bus Supports Loose Connections A
Magnetic Contactors and StartersDirty Contactors and Starters A
Loose Connections A
Contacts Welded Together, Worn and Arcing A
Magnetic Relays
Dirt, Dust, Oil, Grease A
General Purpose Contactors
Damaged Arc Chute A
Improper Arcing Horn Clearances A
Improper Armature Spring Adjustment AWeak Contact Pressure A
Loose Screws, Nuts and Bolts A
General
Improper Closing and Latching of Control Panel Doors A
Nameplates Missing A
Cleanliness of Panel A
-
7/30/2019 Maintenance Recommendations
12/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 12 of15
Starting Motor Limit amp Contactor
Loose Screws, Nuts and Bolts Loose,
Electrical Interlocks Contacts, General Condition A
DC Magnet Assembly Alignment per Specification A
Collars on Each Side of Movable Power Tips for Proper Fit and
Alignment A
Accumulation of Dust, Dirt and Foreign Material on
Contactor and Arc Chutes A
COLLECTOR COMPARTMENTS
Fibreglass Expansion Joints
Loose joints M
Cleanliness MCooling Air discharge vents
M
Generator Ends and Compartment interfaces
Seals Damaged/Watertightness M
Collector compartment Air filters
Filter Cleanliness A
INLETAIR SYSTEMS
Inlet Screens
Obstructions D
By-Pass Door System
Correct Seal M
L im it S wi tc h O pe ra ti on ( Mo nt h- Ch ec k, A nn ua l- O pe ra te ) M A
Inlet Ductwork/Silencers
Sealing A
Cleanliness AF i l te r C a rt r i dg e s( M on t h- c o nf i r m D P , A n nu a l- P hy s ic a l c h ec k ) M A
(replace as necessary in between)
IGVs
Corrosion/Pitting A
Moisture Separators
Cleanliness of Media Section M
Build Up on Blades A
-
7/30/2019 Maintenance Recommendations
13/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 13 of15
Evaporative Cooler
Lubricate Motor A
Tanks for Debris A
Media Build-up A
Nozzles blocking M
Spray Pattern A
Clean Tank A
Water Flow Adjustment
Proper Water Flow to confirm Media Wetness D
Lubrication SchedulesLubrication is required on most turbine external moving parts, Lubrication requirements are
difficult to establish they depend on Air temperature and operating hours, the owner should
set a basic monthly schedule and monitor the lubrication and adjust the schedule to suit.
-
7/30/2019 Maintenance Recommendations
14/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 14 of15
GT Generator
Minor Every 30 Months (2.5 years)
Major - Every 60 months (5 years)After 1 year of duty operation (8760 hours or 300 starts)
Generator end plates/shields are removed to inspect the stator ends wear inspection.
Hydrogen cooling system drained and pressure test if required, all Hydrogen fillingstations checked, Hydrogen seals checked or replaced as required.
After 60 months (5 years) of duty the Stator is removed for full inspection
Complete inspection of the field and rotor coatings, insulation, wear and tear.
Listing of assigned checks and durations
RTD Element Res. - Gas & Winding RTDs
Checks for calibration & poor connections. Minor/Major
RTD Ground Insulation - Stator Winding RTDsInsulation condition of RTD. Minor/Major
Winding Copper Res.- Stator Winding
Checks for poor connections & breaks. Minor/Major
Insulation Resistance (aka CE Bearing Contamination
and/or deterioration of insulation. Minor/Major
Hydrogen Seal Casing
Contamination and/or deterioration of insulation. Minor/Major
Polarization Index - Stator WindingContamination and/or deterioration of insulation. Minor/Major
DC Leakage Current - Stator Winding
Contamination and/or deterioration of insulation. Minor/Major
Over Potential/Hipot - Stator Winding
Ground wall insulation integrity Minor/Major
Wedge Tightness Map - Stator WedgesDetect wedge tightness deterioration Minor/Major
Magnetic Scalar Potential (EL CID) -
Stator Core Insulation Weak or damaged core enamel. Minor/Major
Vacuum Decay - Water Cooled Stator Cher Winding Checks the hydraulic integrity of the entire winding. Minor/Major
Pressure Decay - Water Cooled Stator Winding
Checks the hydraulic integrity of the entire winding. Minor/Major
Capacitance Mapping - Water Cooled Stator Winding
Wet ground wall bar insulation Major
Helium Tracer Gas - Water Cooled Stator Winding
Detects minute leaks in the hydraulic circuit. Major
Visual Inspections
o Core Laminations Foreign Object Damage Minor/Major
o Space Blocks Migration, - cooling passage blockage Minor/Major
o Gas Gap Baffles Cracked welds, looseness Minor/Majoro Stator Wedges Evidence of abrasion or looseness Minor/Major
-
7/30/2019 Maintenance Recommendations
15/15
TechComm Simulation Pty Ltd
TechComm Simulation Inspection and Maintenance Guide Shuaiba North CCGT Page 15 of 15
o Stator Bars Evidence of abrasion or looseness Minor/Major
o End Windings and connection rings
o Evidence of relative motion, loose/broken ties, hardware,
Corona activity Minor/Major
o Copper Flux Shield Overheating, hardware looseness Minor/Major
o Overall cleanliness Oil or other contamination