main south road/sturt road...

72
MAIN SOUTH ROAD/STURT ROAD INTERSECTION Construction Management Plan 6/10/2014 University of South Australia i

Upload: others

Post on 01-Jan-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

MAIN SOUTH ROAD/STURT ROAD INTERSECTIONConstruction Management Plan

6/10/2014University of South Australia

i

CIV Consulting Mawson Lakes Boulevard Mawson Lakes SA 5095 10 June 2014

Attention: Mark Hennessy

University of South Australia School of Natural and Built Environments Mawson Lakes SA 5095

Re: Detailed Design

CIV consulting is pleased to present to you the Construction Management Plan for the Detailed Design for the Main South Road & Sturt Road Intersection Upgrade.

CIV Consulting believes it has the expertise and knowledge to complete the Detailed Design. The Feasibility Study was completed by us and we believe we can carry our knowledge over from this to design the most economical, environmentally and aesthetically friendly underpass.

Please feel free to contact us for any further discussion and concerns.

Yours sincerely,

Matthew PilcherProject Manager CIV Consulting

ii

Proprietary Information StatementThe information contained in this document produced by CIV Consulting is solely for the use of the Client

identified on the cover sheet for the purpose for which it has been prepared and CIV Consulting undertakes

no duty to or accepts any responsibility to any third party who may rely upon this document.

All rights reserved. No section or element of this document may be removed from this document,

reproduced, electronically stored or transmitted in any form without the written permission of CIV

Consulting.

Project Manager Quality Assurance Manager

Revision HistoryRevision Date Prepared Reviewed Approved0 2/6/14 Construction

ManagementM. Cluse

1 3/6/14 Construction Management

M. Pilcher  2 5/6/14 Construction

ManagementM. Cluse  

3  8/6/14  Construction Management

M. Cluse  M. Pilcher 

Table of Contents

iii

1 Introduction.................................................................................................................................................1

2 Overview....................................................................................................................................................... 1

3 Phase 1 – Site Setup and Demolition................................................................................................2

3.1 Allotments on the western side of the road.................................................................2

3.2 Allotments on the eastern side of the road..................................................................3

3.3 South-western side of intersection...............................................................................4

3.4 Demolition Time.........................................................................................................5

3.5 Perimeter......................................................................................................................5

3.6 Area.............................................................................................................................5

3.7 Site Setup.....................................................................................................................5

3.8 Services........................................................................................................................5

4 Phase 2 – Service Relocation................................................................................................................6

4.1 SA Power.....................................................................................................................6

4.2 Telecommunication Cables.........................................................................................8

4.3 AMCOM......................................................................................................................9

4.4 SA Water.....................................................................................................................9

4.5 Wastewater................................................................................................................10

4.6 Gas.............................................................................................................................11

4.7 Stormwater................................................................................................................11

4.8 Phase 2 Services........................................................................................................11

5 Phase 3 – Northern Underpass and Bridge.................................................................................13

5.1 Temporary traffic lanes.............................................................................................13

5.2 Piling..........................................................................................................................13

5.3 Excavation.................................................................................................................14

5.4 Benching....................................................................................................................16

5.5 Services......................................................................................................................19

5.6 Bridge Construction...................................................................................................19

iv

5.6.1 Bridge pier piles, pile caps and side headstocks................................................20

5.6.2 Piers and Middle Headstock...............................................................................21

5.6.3 Super T Storage..................................................................................................21

5.6.4 Super T Erection................................................................................................22

5.6.5 Decking..............................................................................................................23

5.6.6 Parapet Installation.............................................................................................24

5.7 Pavement + Amenities...............................................................................................25

5.7.1 Pavement............................................................................................................27

5.7.2 Curbing...............................................................................................................28

5.7.3 Line Marking......................................................................................................28

5.7.4 Traffic Signals....................................................................................................28

5.7.5 Lighting..............................................................................................................29

5.7.6 Signage...............................................................................................................29

6 Phase 4 – Southern Underpass and North Bound Interchange Ramps..........................30

6.1 Relocate traffic..........................................................................................................30

6.2 Piling..........................................................................................................................30

6.3 Excavation.................................................................................................................31

6.4 Services......................................................................................................................31

6.5 Pavement + Amenities...............................................................................................31

6.5.1 Pavement............................................................................................................32

6.5.2 Curbing...............................................................................................................33

6.5.3 Line Marking......................................................................................................33

6.5.4 Lighting..............................................................................................................33

6.5.5 Signage...............................................................................................................33

6.6 Northbound Interchange Ramps................................................................................33

6.6.1 Pavement............................................................................................................34

6.6.2 Curbing...............................................................................................................35

v

6.6.3 Line Marking......................................................................................................35

6.6.4 Traffic Signals....................................................................................................35

6.6.5 Lighting..............................................................................................................35

6.6.6 Signage...............................................................................................................36

7 Phase 5 – South Bound Interchange Ramps...............................................................................37

7.1 Relocate traffic..........................................................................................................39

7.2 Remove existing surface............................................................................................39

7.3 Pavement...................................................................................................................39

7.4 Curbing......................................................................................................................40

7.5 Line Marking.............................................................................................................40

7.6 Traffic Signals...........................................................................................................40

7.7 Lighting.....................................................................................................................41

7.8 Signage......................................................................................................................41

8 Phase 6 – Closing.................................................................................................................................... 42

8.1 Open road..................................................................................................................42

8.2 Disassemble Site........................................................................................................42

9 References................................................................................................................................................. 43

10 Appendices................................................................................................................................................ 44

10.1 Appendix A – Construction Gantt Chart...................................................................44

vi

List of Figures

Figure 1. Land acquisition on western side of Main South Road......................................2

Figure 2. Land acquisition on eastern side of Main South Road.......................................3

Figure 3. Land to the southwest of the intersection...........................................................4

Figure 4: Truck Route to Dump.......................................................................................15

Figure 5: Galena Slope Stability – Benching...................................................................18

Figure 6, Bearing plate fitted to the beam prior to transportation....................................22

Figure 7, Dolly trailer transport super T within the construction site..............................23

Figure 8, Concrete parapets fixing...................................................................................24

Figure 9 – Construction Phase 3 – Pavement + Amenities Gantt Chart..........................26

Figure 10 - Construction Phase 4 – Pavement + Amenities Gantt Chart.........................32

Figure 11 - Construction Phase 4 – North Bound Interchange Ramps Gantt Chart........34

Figure 12 - Construction Phase 4 Gantt Chart.................................................................38

vii

List of Tables

Table 1. Details of land acquisition on western side of Main South Road........................3

Table 2. Details of land acquisition on eastern side of Main South Road.........................4

Table 3 - Areas output of 10-14 t BOMAG Articulated Tandem Rollers.......................28

viii

1 Introduction

Any construction project has numerous aspects and tasks, many of which are interdependent

on others. To ensure that the project is completed with maximum efficiency and minimal

cost, planning ahead is imperative. This is especially the case in large public works, where

delays can have an enormous cost to the public, both in time and taxpayer funds. A

construction management plan is an essential document to provide timelines, milestones and

other important considerations. The construction management plan also allows third parties,

such as governing bodies which may need to grant approval, to assess the impacts the

development has on stakeholders. As the longstanding saying goes “Failure to plan, is

planning to fail (Churchill 1942).”

2 Overview

This construction management plan details the upgrade of the intersection of Main South

Road and Sturt Road in Bedford Park, SA. The project is separated into six discreet phases,

with work beginning on the 1st of September 2014. The main construction phases begin with

the bridge and northern section of the underpass, followed by the southern section of the

underpass, and finally the southbound interchange ramps. It is expected these works will take

approximately 8 months and the opening date of the underpass will be 11th April 2015. By

starting works in early spring, it will allow the largest window of opportunity for the works to

be completed without inclement weather. The key part of this management plan is the Gantt

chart, which details each individual task to be completed and its expected timeframe. The

Gantt chart is shown in Appendix A.

ix

3 Phase 1 – Site Setup and Demolition

3.1 Allotments on the western side of the road

Thirteen allotments will be used under the plan for the offset vertical alignment (Figure 1).

These include lots 1 through to 9 of Gum Terrace, 34 Oak Avenue and 1 Mimosa Terrace.

This will gain an extra thirty seven metres perpendicular to Main South Road. The blocks

include six house and land, five units and one business. Two blocks are currently owned by

the state government and will not need purchasing. The blocks could reasonably be expected

to be compulsorily acquired for around $3.5 million (Table 1).

x

Figure 1. Land acquisition on western side of Main South

Road

Table 1. Details of land acquisition on western side of Main South Road

Block Street Size m2 Est. Cost ($) Last Sold Last Sold price Notes1 Gum Ave 900 750000 3x units @ 250k2 Gum Ave 758 364-4100003 Gum Ave 799 364-410001 2005 2354 Gum Ave 587 364-410002 2004 2405 Gum Ave 620 364-410003 2005 210 Government Owned6 Gum Ave 622 364-410004 96 48 Government Owned7 Gum Ave 717 360-4070008 Gum Ave 306 100000 Car park/vacant9 Gum Ave 701 372-420000

34 Oak Ave 424 500000 2x units @ 250/ hammerhead1 Mimosa Tce 1575 Business

Total Area (m2) 8009Total Cost $3,500,000

3.2 Allotments on the eastern side of the road

A further thirteen allotments will be required for acquisition on the eastern side of Main

South Road (Figure 2). This is the entire block between Maidstone Drive and Sutton Road.

This land includes eight residences, two businesses (Repco Auto Parts and Bedford Park

Crash Repair) and three vacant blocks. The vacant blocks are currently owned by the state

government. The land on this side of the road could be acquired for around $4.4 million

(Table 2).

Figure 2. Land acquisition on eastern side of Main South Road

xi

Table 2. Details of land acquisition on eastern side of Main South Road

Block Street Size (m2) Estimated Cost ($) Use Notes1351 Main South Road 608 395000 Residential1353 Main South Road 608 395000 Residential1355 Main South Road 608 395000 Residential1357 Main South Road 608 395000 Residential1359 Main South Road 608 395000 Residential1361 Main South Road 608 395000 Residential1363 Main South Road 608 395000 Residential1365 Main South Road 608 395000 Residential

1367-71 Main South Road 1824 1250000 Repco & Bedford Park Crash1373 Main South Road 608 0 Vacant State Government owned1375 Main South Road 608 0 Vacant State Government owned1377 Main South Road 608 0 Vacant State Government owned

Total Cost ($) 3160000Total area (m2) 8512perimeter (m) 530

land Buildings Relocation costs total costRepco 300000 150000 100000 550000Bedford Crash 300000 250000 150000 700000

Total (Commercial) $1,250,000Total (Residential) $3,160,000Grand Total $4,410,000

3.3 South-western side of intersection

The state government currently own the land on the south-western side of the intersection so

it will not need to be bought (Figure 3). This land has an old restaurant and car park, which

will be utilized as site office and parking, as well as a yard for machinery etc.

Figure 3. Land to the southwest of the intersection

This will require 700m of temporary fencing. This area is approx. 23000m2

xii

3.4 Demolition Time

The average demolition time for a residential house is 3-5 days. However, with several

houses next to each other it could reasonably be expected that all could be demolished in 3-4

weeks. It generally takes one day to remove the asbestos from houses being demolished. The

houses are generally constructed from brick or stone, which should limit the amount of

asbestos present. Also, due to the nature of the project, salvageable materials may simply be

scrapped due to time constraints. CIV may opt to use the more time consuming option of

recycling all possible materials because CIV is an environmentally friendly corporation.

3.5 Perimeter

The perimeter of the acquired land that will need to be fenced off during demolition and

construction of the intersection is 1769m.

3.6 Area

The total area of the acquired land is 16521m2 plus the 23000m2 on the south western side of

the intersection.

3.7 Site Setup

The vacant restaurant on the south-western side of the intersection will serve as the site

office; there is also ample car parking space. Services such as telecommunication, electricity

and water will need to be reconnected and office equipment moved in. The site will also

provide storage for contractor’s machinery. Machinery will also be parked in the acquired

residential lots once demolition has been completed and on Flinders oval, if necessary. While

the restaurant should have good facilities, due to the amount of construction workers

employed, extra amenities will need to be rented for the duration of the construction phases.

3.8 Services

The full work for service will be explained in section 4. In construction phase 1 the following

will occur.

LV Cable - Gum terrace and Mimosa terrace cables terminated and then removed HV 11KV Cable – Terminate cable crossing Main South road to Mimosa terrace Minor Cable – Gum terrace cables terminated and then removed SA Water Supply - Gum terrace, Maple avenue and Mimosa avenue cables terminated SA Wastewater - Gum terrace, Maple avenue cables terminated APA GAS – Gum terrace cables terminated

Note: Colours refer to Construction Management drawings CM 2 of 50 to CM 18 of 50

xiii

4 Phase 2 – Service Relocation

For phase 2 of the construction procedure a range of services must be relocated prior to the

construction of the underpass. This must be achieved before construction in phase 3, as a

large majority of cables and pipes will be affected either by the piling or excavation of the

northern side of the underpass.

In phase 2, new high voltage SA power cables and optic fibre cables will be installed on the

eastern side of Main South road as final service locations for the project. Also temporary

cables and pipes will have to be installed in order to terminate affected services in

construction phase 3. These include an optic fibre cable, a critical telecommunication cable

and temporary water supply and waste water pipes. These services are only temporary

relocations so excavation can be achieved and the bridge can be constructed. Once the bridge

is complete these services will be attached to the underside of the bridge, in order for the

services to cross the underpass.

A new APA Gas pipe will be installed on Sturt road and Main South road which will be

strategically placed to avoid future excavation for both northern and southern sides. The high

speed internet cable AMCOM will be relocated to avoid Mimosa Avenue. A minor

telecommunication cable will have to be installed on Oak Avenue to connect existing minor

cables, which will allow affected major telecommunication cables to be terminated.

Due to the large number of critical services, only crucial preparation work will take place in

construction phase 2. This will include installation of new and temporary services and

termination of void services. All other service work will be completed when most suitable in

phases 1, 3 & 4, when site preparation and excavation occurs and pipes and cables are

exposed. A detail construction schedule for services is included for each construction page

throughout the report (sections 3.8, 4.8, 5.5, and 6.4).

Note: Colours refer to Construction Management drawings CM 2 of 50 to CM 18 of 50.

4.1 SA Power

LV Cable – The low voltage cables on Gum terrace and Mimosa terrace are only servicing

properties which will be purchased and demolished for construction, therefore cables will be

terminated and then removed in phase 1 when site preparations occur. Also other low voltage

cables along the eastern side of Main South road and also along the northern side of Sturt

road will be unaffected and will remain in their current position.

xiv

HV 11KV Cable –The high voltage cable which crosses Sturt road prior to the intersection

and also the cable which runs in an ‘L’ shape in the intersection and down the western side of

Main South road, will all be relocated to avoid the excavation and piling area.

Additionally, the high voltage cable on Mimosa terrace which crosses Main South road will

be terminated and removed. This cable is only servicing properties that will be purchased for

demolition, therefore making the cable void. The cable will be terminated in phase 1 site

preparations, and removed in phase 3 with the northern excavation.

The relocation of the other high voltage cables are shown by the dotted line, which avoids the

underpass excavation and will be relocated under the on-grade road. The relocation will

connect to the existing cable which runs on the eastern side of Main South road. The

relocation of the high voltage cable will be done in construction phase 2, before any

excavation or piling of the Northern side is completed and will be operational before void

cables are terminated. A new trench across Sturt road to lay the new cable will be dug first,

and the vehicles on Sturt road will avoid the intersection, crossing to the southern side of the

intersection. Once completed the cars will then return to the intersection and South road will

lose 2 lanes on the eastern side of the road while the new high voltage cable is installed. Once

the new cable is operational, the removal of the high voltage cable will be completed in

construction phase 3 when the northern excavation is completed.

Optic Fibre - The optic fibre cable that crosses Sturt road prior to the intersection and runs

down Main South road will be relocated in a two stage process to avoid the piling and

excavation area. The first stage of relocation will place a temporary cable that crosses Sturt

road and runs through the site office to connect to the existing cable running down the

western side of Main South road.

Also in the first stage the newly proposed optic fibre cable that runs down the eastern side of

Main South road will be installed. Finally the existing cable that crosses Sturt road and runs

down Main South road can be terminated up to a certain point, once temporary cables are

operational. All this work will be completed in construction phase 2, and is shown by the

dotted line in drawing CM 3.

In the second stage of the relocation process the final optic fibre cable will be relocated under

the newly constructed bridge, this will occur in construction phase 3. Removal of the existing

cables running in the intersection will be completed in construction phase 3, while excavation

xv

occurs. Removal of the temporary cables that cross Sturt road and the site office will be

completed in the final part of the phase 3 constructions, once the new cable under the bridge

is operational. Finally removal of existing cable running down the western side of Main

South road will be completed in construction phase 4, when southern side excavation occurs.

When installation of the temporary cable in the first stage of construction phase 2 occurs,

vehicles will avoid the installation by crossing to the northern side of the intersection, once

complete, traffic can return to the intersection. Also when the preparation cable is installed on

the eastern side of South road, 2 lanes along the eastern side of the road will be temporarily

closed while the new high voltage cable is installed.

4.2 Telecommunication Cables

Minor Cable – It is assumed that the minor cable on Gum terrace is only servicing properties

which will be purchased and demolished for construction, therefore cables will be terminated

and removed in construction phase 1, when site preparations are completed. Also the minor

cables on Oak Avenue will be connected, so that the major cables that run up the western side

of Main South road and also the cable that crosses the intersection can be removed. The

minor cable connection and consequently, the major cable termination, will be completed in

construction phase 2.

Major Cable - The major cables crossing the intersection and also the cable that runs up

Main South road side will be removed in construction phase 3, when excavation occurs. As

previously mentioned the connection of the minor cable on Oak Avenue and the termination

of major cables will occur in construction phase 2.

Critical Cable - The critical cable that crosses the intersection and runs north up Main South

road will be relocated in a two stage process to avoid the excavated area.

The first stage of relocation is shown by the dotted line, which crosses Sturt road and cuts

through the site office to avoid the northern underpass excavation, which will be done in

construction phase 2. Similarly with the temporary relocation of the optic fibre cable,

vehicles will avoid the cable installation by crossing on the northern side of the intersection.

Once the temporary cable is operational, the existing cable crossing the intersection can be

terminated and removed in construction phase 3, when excavation occurs. Once the bridge is

complete in construction phase 3, the final critical cable can be attached to the bridge. Once

xvi

operational the temporary cables will be terminated, and then removed in construction phase

4, when excavation of the southern side is completed.

4.3 AMCOM

The AMCOM cable running on Mimosa Avenue and Main South road will need to be

relocated to avoid the northern excavation. The relocation is shown by the dotted line in

drawing CM 9, and will be placed on Bradley Grove, eventually connecting to Main South

road. The relocation will be completed in phase 2, prior to the excavation in construction 3.

Once the relocation is completed and operational, the void AMCOM cable will be terminated

and then removed when excavating in phase 3.

4.4 SA Water

SA Water Supply – Water supply pipes and connections on Gum terrace, Maple Avenue and

Mimosa Avenue are only servicing properties that will be purchased and demolished for

construction; therefore all pipes will be terminated in construction phase 1. These pipes and

connections will then be removed when excavating the underpass in construction phase 3.

All other water supply pipes along South road running north will be unaffected due to the

alignment of the underpass, therefore the pipes will either be under the nature strip or under

the on-grade roads.

The only other relocation that has to occur is the relocation of the 200mm main pipe running

along Sturt road directly through the intersection. As the pipe will have to maintain its

position travelling through the intersection, the pipe will be attached to the bridge after

construction. Therefore while construction occurs, the pipe will be relocated in two stages.

First a temporary pipe will be installed straight through the site area, connect to the pipe

running on Main South road and then divert the intersection. This will be completed in

construction phase 2, and then the void water pipe will be terminated. In construction phase 3

when excavation on the northern side is complete, the void water pipe running through the

intersection will be removed.

For the second stage of relocation, a new water pipe will be attached to the newly constructed

bridge and connect to the existing service in the latter part of construction phase 3. Once the

final water supply pipe is operational, then the temporary pipe will be terminated, also in the

xvii

latter part of construction phase 3. The temporary pipe will be removed in construction phase

4, when the excavation occurs on the southern side of the intersection. Similarly to the

temporary optic fibre cable and critical cable installation, the temporary water supply pipe

will be installed across Sturt road; therefore vehicles will avoid the installation by crossing on

the northern side of the intersection in construction phase 2. Finally as the water pipe is less

than 675mm, the angle of change in direction does not have to be 45 degrees, thus the most

suitable angle of relocation will be selected.

4.5 Wastewater

SA Wastewater – Similarly to the water supply pipes, the wastewater pipes and property

connections on Gum terrace and Mimosa Avenue are only servicing properties which will be

purchased and demolished for construction. Therefore all pipes and connections will be

terminated in construction phase 1 and will be removed in construction phase 3. All other

wastewater pipes along South road running north will be unaffected due to the alignment of

the underpass; therefore the pipes will either be under the nature strip or under the on-grade

roads.

The only other relocation that has to occur is the 525mm main pipe running along Sturt road

directly through the intersection. As the pipe will have to maintain its position travelling

through the intersection, the pipe will be attached to the bridge after construction. Therefore

while construction occurs, the pipe will be relocated in two stages.

First a temporary pipe will be installed straight through the site area, across Main South road

and then divert back to the centre of the Sturt road pipe after the intersection. This will be

done in construction phase 2, and then the void water pipe will be terminated. In construction

phase 3 when excavation on the northern side is completed, the void water pipe running

through the intersection will be removed.

For the second stage of relocation a new water pipe will be attached to the newly constructed

bridge and connect to the existing service in the latter part of construction phase 3. Once the

final water supply pipe is operational, then the temporary pipe will be terminated, also in the

latter part of construction phase 3. The temporary pipe will then be removed in construction

phase 4, when the excavation occurs on the southern side of the intersection.

xviii

Similarly to the temporary water supply installation, the temporary waste water pipe will be

installed across Sturt road, therefore Sturt road will lose 2 lanes while installation occurs.

When the temporary pipe is installed across Main South road, further delays will occur and

vehicles will have to divert from left to right of Main South road to avoid the installation.

Finally as the waste water pipe is less than 675mm, the angle of change in direction does not

have to be 45 degrees, thus the most suitable angle of relocation will be selected.

4.6 Gas

APA Gas - The APA Gas pipe on Gum terrace is only servicing properties that will be

purchased and demolished for construction, therefore will be terminated in construction phase

1 and removed in phase 3. Also the pipe that runs down the middle of Main South road and

connects to Sturt road on the western side of the intersection will have to be relocated. A new

gas pipe will be installed parallel to the existing pipe along Main South road and will connect

to the existing pipe running on the eastern side of the intersection on Sturt road. The pipe will

be installed in construction phase 2, by diverting 2 lanes along Main South road and also

Sturt road. Once the new APA gas pipe is in service, the void pipe will be terminated in the

latter stages of construction phase 2. The removal of the Sturt road pipe will then occur in

phase 3 when excavation occurs and finally the removal of the pipe along Main South road

will occur in construction phase 4.

4.7 Stormwater

The Stormwater pipe and pits on Main South road, Gum Terrace and to the western side of

the intersection on Sturt road will all be removed when excavation occurs in construction

phase 3. The new stormwater layout will be detailed in the stormwater plan.

4.8 Phase 2 Services

HV 11KV Cable – Lay cable crossing Sturt road HV 11KV Cable – Lay cable running eastern side on Main South road Optic Fibre – Stage 1 temporary cable laid crossing site office Optic Fibre - Preparation cable running on the eastern side of Main South road laid Optic Fibre - Terminate cable crossing intersection Minor Cable – Oak Ave cables connected Major Cable (Gum/South Road) – Terminated Critical Cable - Stage 1 temporary cable crossing site office and crossing south road

laid

xix

AMCOM - Relocated SA Water Supply – Stage 1 temporary pipe laid and then terminate old SA Wastewater – Stage 1 temporary pipe laid and then terminate old APA GAS – Lay new pipe on Sturt road and Main South road APA GAS – Terminate old pipe on Sturt road and Main South road

xx

5 Phase 3 – Northern Underpass and Bridge

Phase 3 of the construction involves the works done on the northern part of the underpass and

the bridge. This includes the piling, excavation, bridge construction road pavement and the

final amenities. However before any of these works can begin, temporary traffic lanes must

be set up to maintain traffic flow through the intersection.

By the conclusion of phase three, the bridge will be completed and able to take traffic. The

northern end of the under pass will be suitable for traffic however, it cannot be used until the

southern part is complete.

5.1 Temporary traffic lanes

Due to the construction of the northern part of the underpass and the bridge, traffic will be

moved around the current intersection. Due to the new horizontal alignment, the eastern side

of the current Main South road can be used throughout this phase.

To avoid the current intersection, temporary traffic lanes will be moved slightly south. A

temporary road surface is required on the area that is currently un-occupied land, while the

current pavement will be used as long as possible. At the very northern end of the excavation,

a temporary road surface on the eastern side is also required to avoid the construction area.

There will be two lanes in either direction along Main South road as well as an emergency

lane, heading towards Flinder’s Medical Centre. Sturt road will use the current lanes where

possible and will have a minimum of two lanes in either direction.

During the morning peak period, an extra lane will be added along Main South road with

traffic heading north. During the Afternoon peak period, an extra lane will be added along

Main South road with traffic heading south.

The temporary traffic lane set up can be seen in drawings CM 22 of 50 to CM 30 of 50

Where a temporary road surface is required, the soil will be graded with a Motor Grader and

compacted with articulated tandem rollers. A Bitumen spray seal will then be applied using a

bitumen spray truck. This is a small area and so it will only take one day to complete.

xxi

5.2 Piling

The concrete piles are one of the most major aspects in this project. The retaining wall along

each side of the underpass is to be constructed of secant piles and the piers that the support

the bridge sits on a pile group. Due to the noise and vibration issues of driven piles, all piles

are to be cast in-situ. There are to be 1606 secant piles and 25 pier support piles. The secant

piles are to be 900mm diameter and there is a total linear length of 30,082 metres. The pier

support piles are to be a group of 5, with a diameter of 900mm and a total linear length of 500

metres. The pier support piles will have starter bars cast into them to tie to the piers.

As one piling machine can pile approximately 90 linear meters a day, it will be necessary to

hire 4 machines. This will bring the total piling time to around 100 days. The piling will be

split into two sections, the bridge and northern section of the underpass first, and the southern

section of the underpass afterwards, as per the drawings.

Secant piles intersect each other to form one continuous member. In this case the overlap is

112.5 mm on each side. Secant piles walls consist of primary unreinforced piles and

secondary reinforced piles. The primary piles are weaker concrete (25 MPa), so that they can

be drilled through to lay the stronger secondary piles (40 MPa). The concrete used in primary

piles is slow curing so that it is easier to drill through the secondary piles.

The construction of the piles will be staggered for maximum efficiency. Firstly, all 4

machines will drill primary piles. After an adequate amount of primary piles have been

completed, approximately one week after beginning, 2 of the machines will begin building

the secondary piles. This will allow for the retaining wall to be completed in sections and

thus allow the excavation to begin in the shortest possible timeframe.

There are 918 piles in the northern section, with a total linear length of 16,756 metres. This

will take 61 days. Two machines will begin work on each side of the southernmost extent of

the northern section i.e. the southern edge of Sturt Road. The remaining two machines will

begin where the other two machines will approximately finish their first weeks’ working.

This will allow one pair of machines to go back to the southern edge and drill the secondary

piles. By the time the secondary piles are completed to the extent of the first weeks’ primary

piling, the other piling machines will have completed another weeks’ worth of primary piles.

Thus, leapfrogging along each wall, the piling will be completed with maximum efficiency.

xxii

5.3 Excavation

The Northern excavation volume calculated to approximately 72,440m³. Therefore after

piling is completed, excavation will take place to remove the soil to construct the underpass.

The dumping site chosen is ResourceCo Lonsdale Landfill, located at 8 Meyer Road,

Lonsdale. The dumping site was chosen as it accepts clean fill, demolition waste and also

asphalt, which are all the materials that will be required to dump, plus due to its location

being relatively close to the site.

The only negative about the site is that it is closed on Sundays and also doesn’t except

vegetation waste. This means excavated soil will have to be piled up on Sundays ready to

dump on Monday. Vegetation waste will be dumped at Lonsdale Waste & Recycling Depot

at 10 Donegal Road, Lonsdale. The Lonsdale Waste & Recycling Depot is open 7 days a

week and accepts all green organic waste.

Below are calculations to determine a suitable duration for excavation:

Travel path for trucks for soil dumping:

xxiii

Figure 4: Truck Route to Dump

Main South road Right on Majors road Left on Lonsdale road Right on Meyer

road

Total Travel Time: 14mins

The total time for excavation was calculated by using a formula that determined the total

duration by working with variables, including truck capacity, truck cycle time, loading time

and production rate of loader.

Truck capacity=TruckCapacityLoading time=TruckCapacity / Production rate of loaderTruck cycle time=Loading time+Goingtime+Returntime+Dumping timeNumber of required trucks=Truck cycle time / loading time

Truck Capacity=20m3

Loading time=¿24 minutes

Travel time=14∗2=28minutes

Cycle time=24+28+5=57 minutes

Number of trucks=5724

=2.375 trucks

Therefore if 9 trucks and 3 excavators are used, 180m³ of soil moved / hour:

72,440.13m3

180m3 =402hours

Assuming 7 hours of excavating a day:

4027

=57days

Maybe say what these mean?

xxiv

5.4 Benching

Between excavation of the northern side of the underpass in construction phase 3 and the

southern side in phase 4, there will be difference in soil elevation of 8m. Therefore to

decrease the risk on site with issues regarding the slope stability, a form of stabilisation of the

soil was required. Possibilities of a temporary retaining wall were postulated but through

slope stability analysis on Galena, final conclusions were found that benching of the soil is

the most feasible option.

The benching was designed in Galena to measure the horizontal distance required of the

benching geometry to achieve a Factor of Safety of 2.3. Galena required the soil parameters,

an initial design of the benching and a surcharge of the diverted traffic which would flow

relatively close to the excavation. The final output is shown below in figure 5, with the final

benching designs with the achieved F.O.S. The benching will be excavated to design, with

the excavators on site, at the completion of construction phase 3.

xxv

2.5mm

1.5m

2m

14.5m17m

Input for Galena

Hard Stiff Clay

Unit Weight (γ)=21 kN /m3

Cohension(c)=15 kN /m2

Phi(φ)=270

Surcharge=10 kPa

Output Galena

Individual slopes will have dimensions of 2.5m x 2m, with a horizontal bench of 1.5m,

providing a total horizontal distance of 14.5m to achieve a stable slope of 8m of soil. Finally

the vehicles that will provide an additional surcharge to the slope will have to be at least 17m

from the start of the slope, which is 2.5m from the final edge of the slope.

xxvi

Figure 5: Galena Slope Stability – Benching

5.5 Services

HV 11KV Cable – Remove cable crossing Mimosa avenue HV 11KV Cable – Terminate and remove cable crossing intersection and Sturt road Optic Fibre - Attach new cable to bridge and then connect to preparation cable Optic Fibre - Remove existing cables in intersection Optic Fibre - Remove temporary cables Major Cable (Gum/Main South Road & intersection) – Removed Critical Cable – Terminate then remove cable running up the centre of South road

and then intersection Critical Cable – Attached new cable to the bridge Critical Cable –Temporary cable terminated AMCOM – Cable on Mimosa avenue and Main South road terminated and then

removed SA Water Supply - Gum terrace, Maple avenue and Mimosa avenue removed SA Water Supply – Remove old pipe running through intersection SA Water Supply – Attach new pipe to bridge running through intersection SA Water Supply – Terminate temporary pipe SA Wastewater - Gum terrace, Maple avenue pipes removed SA Wastewater - Remove old pipe running through intersection SA Wastewater - Attach new pipe to bridge running through intersection SA Wastewater - Terminate temporary pipe APA Gas – Gum terrace and Sturt road cables removed Stormwater – Pipes and pits on Gum Terrace, Main South road and Sturt road

removed

Note: Colours refer to Construction Management drawings CM 2 of 50 – CM 18 of 50

5.6 Bridge Construction

The bridge is the designed to carry the current Sturt Road traffic over Main South Road.

There will be three lanes in each direction. The main super structure of the bridge consists of

30 precast pre-stressed super T beams which are simply supported on middle piers and two

side secant pile walls. There will be headstocks running underneath all super T beams to

distribute loads to both sides of support.

A precise survey control network is required prior to any construction and it will be done

during the site preparation stage. These survey marks will be check regularly throughout the

construction.

xxvii

Please refer to CM-33 – Bridge construction sequence for entire process of bridge

construction.

A request for tender should be sent out for tendering of the entire bridge construction,

excluding all piles construction. The piling contract will include the secant pile wall and

middle pier piles.

5.6.1 Bridge pier piles, pile caps and side headstocks

The bridge secant piles and piers will be the support of headstocks which will then hold the

super T structures. Construction of the secant piles is described in section 5.2 of this report.

5.6.1.1 Pier piles and pile caps

There are five 1m x 1m rectangular piers in the middle of the bridge and they run parallel to

Main South Road. Each middle pier transfers the load to the pile cap and then distributes the

load to the supporting 5 piles. Firstly, 25 piles (5 piles x 5 piers) need to be drilled by SR-30

piling rig with 900mm diameter drill. Secondly, pre-fabricated steel cages are placed in each

drill hole. Make sure the starter bar for cast pile cap is sufficient and meet the requirements of

BD 13. Finally, to pour 40 MPa early strength concrete to all pile holes.

The pile cap will need to be constructed after the piles have gained 90% of strength and it

should be within 7 days of pouring. To place the pile caps steel cage, a 90T crane is sufficient

for the lifting. Moreover, the same concrete as the piles will be poured and compacted

carefully. With similar consideration, pier starter bars will need to be considered and satisfy

the design specification.

The entire construction of the pier piles and pile caps will be finished within 30 days. During

this time, two side headstocks will be casted.

5.6.1.2 Casting Headstock

As long as secant piles have gained sufficient strength, the two side headstocks can be cast

in-situ. There will be reinforcement left protruding from the secant wall piles, which will be

the starter bars for connection steels with cast in-situ headstocks. The pile and side

headstocks were designed by the Earthwork/Roadwork and Bridge Design teams

respectively; for details of these designs, please refer to BD 13 for piles and BD 5 for side

headstocks.

xxviii

The first step is steelwork, which the headstock cage will be pre-fabricated and deliver to site

and then connect to the piles reinforcements. For details on the reinforcement connection

please refers to BD 13 and BD 5. The recommended procedure of casting the headstocks are

as following:

Place the pre-fabricated steel cage to the correct location and check the alignment and

levels at the same time.

Fix and adjust reinforcements, the site engineer is responsible for checking that the

reinforcement’s lapping comply with the design.

Placement of headstock’s formworks by qualified concrete contractors.

Pour 40MPa concrete and compact concrete properly with vibrator.

Cover this section to protect concrete for curing.

During the construction of the west side headstock, appropriate traffic management will be

applied.

5.6.2 Piers and Middle Headstock

Piers and the middle headstock will support the super T’s. The load will migrate through the

pile cap and then to the pile groups underground. While the piers and headstock can be cast

in-situ in order after the pile cap has gained sufficient strength by using 40 MPa high early

strength concrete.

Again, the starter bar is important for connecting the pier steel to the pile cap. All steel cages

will be pre-fabricated and fixed to the correct location. A 90T crane will be used through the

construction for lifting and placement of all formworks precisely. Fresh concrete will be

pumped by a truck mounted boom pump from the top of the pier. An extended vibrator will

be needed at the start of pouring to ensure concrete at bottom of pier is compacted properly.

Headstock will be casted after all columns are ready to support the heavy middle headstock.

The total length of middle headstock will be 44 m. Therefore the steel cage will be pre-

fabricated by 4 sections for transport and then they will be welded on site. Scaffolding will be

built up to 7m height for workers to place formwork. Concrete boom pump will be used to

deliver the concrete to the top of headstock.

5.6.3 Super T Storage

The dimension of each super T is 2.5m wide x 1.5m height x 24m long. Each of them weighs

approximately 48 tonnes. Due to the special requirement and dimension, super T’s can only

xxix

be transported on weekends and the Bianco Precast cannot transport 30 super T in two days.

Therefore, an empty site is designated for super T storage at the northwest of the bridge

construction (refer to drawing CM-31 bridge construction part 1).

The super T manufacturer will be responsible for transport products. But a crane contractor

(200T crane) will be required to unload them. Hardwood bearers will be used when stacking

the super T. Two piles of the stacked super T will be located on the storage site.

All unloading and loading of super T will happen in the closed construction area which will

be fenced away from traffic, therefore there will be no temporary traffic management

involved.

5.6.4 Super T Erection

Before all super Ts are transported to the storage site bearing plate Elastomeric Laminated

Bearing GJE-03(refer to figure 6) should be installed to the underside of the beam.

Furthermore there will be a bottom part of the bearing plate installed on the headstock to

support the super T. The Super T analysis and design are located in sections 1.5.1 and 1.6 or

the Bridge Design, Detailed Design report respectively. The design detail of the bearing plate

is in section 1.12 of the Bridge Design, Detailed Design report.

Figure 6, Bearing plate fitted to the beam prior to transportation

Once all headstocks, piles and piers gained the sufficient strength, the erection can be taken

place by using dual crane lift. The entire erection will be broken to two stages, stage one and

xxx

stage two.

Stage one is to install the west section of bridge. A 350T crane will set up on the west side of

underpass and it is on the bank. A 400T crane will set up on the bottom of underpass. Stage

two is to install the east section of bridge. The 350T crane will move to the east bank. During

this erection, one lane needs to be closed for safety concern.

The following erection sequence is a guide for contractors to install the super T (refer to

drawing CM-30 and CM-31 Bridge construction). Stage one and stage two of erection will be

similar except the 350T carne set up.

There will be a 200T carne lifting each stored super T to two dolly trailers (refer to

figure 7) and transport to west side of bridge.

A 350T carne on the bank lift one side of super T and drag over to allow super T half

hanging and half supported on one dolly trailer.

A 400T carne will set up at the bottom of excavated Northern underpass. This crane

will take over the half hanging side of super T. The 350T crane will connect to the

dolly trailer side of super T. A 15m cherry picker will be used for connecting the

crane arm to shackle pin embedded in super T.

Two cranes then will move the super T into place carefully.

Figure 7, Dolly trailer transport super T within the construction site

xxxi

5.6.5 Decking

Once all of super T erections are completed, the decking will be casted in-situ. Deck

reinforcement will connect to the super T stirrup. Total 310 m3 of concrete will pour on the

top of super Ts by using 40Mpa high early strength concrete. At the bottom of each super T

wings, there will be formworks to prevent the concrete leaking through the gap. All concrete

will be compacted properly. After 7 days curing, pavement and footpath pavers will be laid to

the top of bridge. Please refer to BD 2 for deck detail design.

5.6.6 Parapet Installation

All parapets will be pre-casted and then transported to the correct location. At the edges of

bridge deck, a series of steel bars will be designed and left protruding for install parapets.

Once the parapets are placed correctly, all penetration needs to be grouted by 40 MPa

concrete. Figure 8 is an example of this design. Please refer to BD 10 for final design of

parapet.

Figure 8, Concrete parapets fixing

Around the bridge piers, it is necessary to install parapets to prevent car crashes into the pier,

which can potentially cause failure of bridge. The same installation method will be used for

these parapets. The pier parapets should be installed by small crane (20T carne) to prevent

damage to bridge structure.

xxxii

xxxiii

5.7 Pavement + Amenities

The pavement and amenities in the final step of phase 3 involves paving the roads, setting the

curbs, marking the road lines and installing the traffic signals, street lights and road signs. All

up it will take 11 days. A breakdown of how the time will be spent is shown in figure 9

below.

xxxiv

Figure 9 – Construction Phase 3 – Pavement + Amenities Gantt Chart

35

5.7.1 Pavement

In Phase 3 the final road pavement will be laid for the northern part of Main South Road as

well as on Sturt road over and to the west of the bridge. The paving process includes grading

and compacting the soil before laying and compacting the base and sub-base when required.

After a primer has been sprayed onto the base (or sub-grade when there is no base) the

asphalt will be laid. Each layer is rolled and then tested before moving on.

A motor grader will be used to grade the soil and five articulated tandem rollers will be used

to compact it. This can be done in one day for each road. On Sturt road there is currently old

pavement that must be first removed. This can be done while the grader is being used on

Main South Road.

While Sturt road is being graded, Main South road will be laid with the sub-base and base

layers. Four of the rollers will be used to compact this while one will be used on Sturt road.

Next the asphalt will be laid. The duration estimates for the paving process are based on a Cat

AP1000E Paver which has a maximum operating speed of 25 m/min and a maximum

operating width of 8 m. Both Main South road and Sturt road will require four passes of the

paver to cover the entire surface. With a length of approximately 440m, the pavement on the

northern part of Main South road can be laid in approximately 70 minutes per layer while the

single pavement layer, with a length of 150m on Sturt can be laid in 24 minutes.

Table 3 below shows the area output of BOMAG’s 10-14 tonne articulated tandem rollers. To

be conservative, the minimum value has been assumed. The pavement on Main South road

has a volume of approximately 11,000m3 and a layer thickness of 50mm. With four rollers

and two asphalt layers, this pavement can be rolled in approximately 5 hours and 30 minutes.

The pavement on Sturt road has an approximate volume of 3,100m3 and a layer thickness of

150mm. With one roller, Sturt road can be rolled in approximately 5 hours and 15 minutes.

Since there are five rollers, there is enough equipment to pave both roads on the same day.

36

Weight (t) 10-14 Assume (conservative):

Area output (t = 20-40 mm) (m2/h) 1000-2200 1000

Area output (t = 60-80 mm) (m2/h) 800-1200 800

Area output (t = 100-140 mm) (m2/h)

600-900 600

Table 3 - Areas output of 10-14 t BOMAG Articulated Tandem Rollers

5.7.2 Curbing

After the pavement has be laid, the curbs along the sides of the road and the median strips

will be set. This can be done in-situ with a curber. The Power Curber 5700-C will set the

concrete curbs at a speed of approximately 15m/min.

The combined length of curb on the northern part of Main South road is approximately

1,850m and will be set in approximately 2 hours. The curbs on Sturt road have a combined

length of approximately 410m and will be set in approximately 30 minutes.

5.7.3 Line Marking

The best assumption for the speed of the line marking is approximately 2 km worth of road

lines per day.

Main South road has 8 road lines for a length of approximately 440m. This can be done in

approximately 1 day and 6 hours (assuming an 8 hour day).

Sturt road has 8 road lines for a length of approximately 150m as well as 12 arrows. This can

be done in approximately 6 hours.

5.7.4 Traffic Signals

Three traffic signals will be erected on Sturt road in phase 3. A pole borer, such as the Proline

1014 Series Pole Borer will first be used to bore the holes before the bases are concreted in

place. After the concrete has set, the pole borer will come back and be used to erect the poles.

The signals can then be installed onto the poles.

Since the curbing will be done quickly, the holes and bases for the traffic signals can be

installed on the same day that the curbs are set.

37

5.7.5 Lighting

The street lights will be erected in the same way as the traffic signals, using the same pole

borer. In this phase, 14 street lights will be erected on Main South road and 9 on Sturt.

Assuming that a hole can be dug and the base concreted in place every hour, it will take

approximately 1 day and 6.5 hours for Main South road and approximately 1 day and 1 hour

for Sturt.

After the concrete has been allowed to cure, the poles will be erected. Assuming that one pole

can be erected every hour this will also be done in approximately 1 day and 6 hours for Main

South road and approximately 1 day and 1 hour for Sturt.

5.7.6 Signage

There are only 5 medium sized signs to be installed in this phase. There are two speed limit

signs on Main South road, two speed limit signs on Sturt road and a stop sign on Sturt.

It will only take one day to install these signs.

38

6 Phase 4 – Southern Underpass and North Bound Interchange

Ramps

Phase 4 of the construction involves the works done on the southern part of the underpass and

the north bound interchange ramps. This includes the piling, excavation, road pavement and

the final amenities for Main South road and the road pavement and amenities for the

interchange ramps. The traffic lanes will be moved again to avoid the new construction areas.

With the completion of construction phase 4, the Main South road underpass will be

completely finished and open for use, as will the north bound interchange ramps.

6.1 Relocate traffic

Since the southern end of the underpass will be constructed in this phase, the traffic lanes

must be moved to avoid the new construction areas. With the conclusion of phase 3, the

bridge can be used to take traffic. In phase 4 Sturt road will be connected by the new bridge,

and the temporary lanes for Main South road will continue to run down the eastern side.

The temporary lanes on Main South road north of the intersection will remain the same as in

phase 3, while the south side will be change to mirror this. A new temporary road surface will

be required on the southern end of Main South road to avoid the construction. This will be

installed in the same process as phase 3 and will also take one day.

Again an extra lane will be added along Main South road with traffic heading north during

the morning peak period and an extra lane along Main South road with traffic heading south

during the afternoon peak period.

6.2 Piling

The piling on the southern side of the intersection will continue as per the northern side.

Construction will commence as soon as piling the northern section is complete. There are 688

piles to complete in the southern section, with a total linear length of 13,326. All the piles in

this phase are 900mm diameter secant piles for the retaining wall (there are no bridge support

piles in this phase). The 4 machines will again work in a leapfrogging fashion, working north

to south.

39

6.3 Excavation

The Southern excavation volume was calculated to be approximately 26,286m³. The same

dumping sites will be used for soil and vegetation, ResourceCo Lonsdale Landfill and

Lonsdale Waste & Recycling Depot.

Below are calculations to determine a suitable duration for excavation:

Therefore if 9 trucks and 3 excavators are used, 180m³ of soil moved / hour:

26,286 m3

180 m3 =146 hours

Assuming 7 hours of excavating a day:

1467

=21days

6.4 Services

HV 11KV Cable – Remove cable running down western side of Main South road Optic Fibre - Remove void cable running on western side of Main South road Critical Cable – Temporary cable removed SA Water Supply – Remove temporary pipe SA Wastewater– Remove temporary pipe APA GAS –Remove pipe on Main South road

Note: Colours refer to Construction Management drawings CM 2 of 50– CM 18 of 50

6.5 Pavement + Amenities

The Pavement and amenities of Main South road are the final steps of phase 4. Again the

roads will be paved, the curbs will be set, the road lines will be marked and the street lights

and road signs will be installed. There are no traffic signals to be installed on Main South

Road.

It will take 9 days to finish the pavement and amenities for Main South road which is shown

in figure 10 below.

40

Figure 10 - Construction Phase 4 – Pavement + Amenities Gantt Chart

6.5.1 Pavement

The paving for phase 4 will be done in the same way as it was in phase 3 (section 5.7.1).

Main South road will not be paved at the same time as the interchange ramps, therefore all 5

rollers will be used here.

Again 4 passes of the Paver are required to cover the entire width of Main South road. In this

phase, Main South road has a length of approximately 260m, which can be laid in

approximately 45 minutes per layer.

41

Using 5 rollers for an area of approximately 7,000m2 and a layer thickness of 50mm with two

asphalt layers, Main South road can be rolled in approximately 2 hours and 50 minutes.

6.5.2 Curbing

The curbing for phase 4 will be done in the same way as it was in phase 3 (section 5.7.2).

Main south road has a combined length of curb of approximately 1,120m, which will be set in

approximately 1 hour and 15 minutes.

6.5.3 Line Marking

The line marking for phase 4 will be done in the same way as it was in phase 3 (section

5.7.3).

Main south road has 8 road lines with a length of approximately 160m. This can be painted in

one day.

6.5.4 Lighting

The street lighting for phase 4 will be done in the same way as it was in phase 3 (section

5.7.5).

There are 18 street lights to be erected on Main South road. This will take approximately 2

days and 2.5 hours. After the concrete has set it will take another 2 days and 2.5 hours to

erect the poles.

6.5.5 Signage

There are only two speed limit signs to be installed on Main South road, which can easily be

done in one day.

6.6 Northbound Interchange Ramps

The north bound interchange ramps will be constructed at the same time as the underpass is

being excavated. All that will be done for the north bound interchange ramps, is to pave the

road, set the curbs, mark the road lines and install the traffic signals, street lights and traffic

signs. This will be done in 9 days, which is shown in figure 11 below.

42

Figure 11 - Construction Phase 4 – North Bound Interchange Ramps Gantt Chart

6.6.1 Pavement

First the ramps will be graded and compacted then the asphalt will be laid. Due to the

changes in width of the interchange ramps, some parts will require only one pass of the paver

while others will require two.

The north bound exit ramp has approximately 90m of pavement, 7.5 to 10m wide and

approximately 145m, 5.5 to 7.5m wide. This can be laid in approximately 15 minutes.

43

The north bound entry ramp has approximately 165m of pavement, 7.5 to 12.5m wide and

approximately 260m, 5.5 to 7.5m wide. This can be laid in approximately 25 minutes.

The north bound exit ramp has a pavement area of approximately 1500m2, a single asphalt

layer with a thickness of 50mm, and with two rollers, can be rolled in approximately 45

minutes.

The north bound entry ramp has a pavement area of approximately 3600m2, a single asphalt

layer with a thickness of 50mm, and with three rollers, can be rolled in approximately 1 hour

and 15 minutes.

6.6.2 Curbing

With a combined length of approximately 1,300m, the curbs will be laid in approximately 90

minutes.

6.6.3 Line Marking

The north bound interchange ramps contain approximately 1,980m of road lines and three

arrows. This can be done in one day.

6.6.4 Traffic Signals

The traffic signals for the phase 4 north bound interchange ramps will be done in the same

way as it was in phase 3 (section 5.7.4).

There is one traffic signal on the north bound exit ramp. The hole will be dug and the base

concreted in place in one day, and the pole will be erected and the signals installed on

another.

6.6.5 Lighting

There are 4 street lights on the exit ramp and 9 on the entry ramp.

It will take approximately 4 hours to dig the holes and install the bases on the exit ramp, and

another 4 hours to install the poles after the concrete has been allowed to cure.

It will take approximately 1 day and 1 hour to dig the holes and install the bases on the entry

ramp, and another 1 day and 1 hour to install the poles after the concrete has been allowed to

cure.

44

6.6.6 Signage

There is a speed limit sign and a give way sign on the exit ramp and a give way sign, a stop

sign and a speed limit sign on the entry ramp. These can be installed in one day.

There is also a large exit sign on the north bound exit ramp which will require the pole borer.

The hole will be bored and the base set on the same day that the other signs are installed,

which is also the same day that the traffic signal is installed. The sign will then be erected on

the same day that the traffic signal pole is erected.

45

7 Phase 5 – South Bound Interchange Ramps

This is the final phase that involves construction works and disruptions to traffic. The

majority of the project works will be completed and open for use while the south bound

interchange ramps will be constructed. The pavement on the eastern side of Sturt road will

also be re-laid. This will be constructed in two stages so that the traffic can always flow. The

two stages are shown in drawings CM 43 of 50 to CM 50 of 50.

The schedule of the works is shown in figure 12 below.

46

Figure 12 - Construction Phase 4 Gantt Chart

47

7.1 Relocate traffic

After the completion of phase 4, the underpass, the bridge and the northern bound

interchange ramps will be completed and open for use. Temporary lanes will only be required

for the south bound interchange ramps. Due to the new horizontal alignment, there is enough

space on the eastern side of the under pass to accommodate the temporary traffic lanes while

the new south bound interchange ramps are under construction.

However it is impossible to construct the entire south bound interchange at once without the

temporary lanes crossing the construction area. Therefore phase 5 will be done in two stages

and the traffic lanes will be shifted so that the construction can continue. The location of the

temporary lanes can be seen in drawings CM 43 of 50 to CM 50 of 50.

Traffic will also be directed around the repaving of the eastern side of Sturt road.

During this phase, the temporary lanes will be located on existing pavement and will not

require any additional temporary road surfaces.

7.2 Remove existing surface

For each stage of construction phase 5, the existing pavement on the eastern part of Main

South road must be removed. This will be done with an excavator and will require

approximately two days for each stage.

7.3 Pavement

The paving for phase 5 will be done in the same way as it was in phases 3 and 4 (section

5.7.1). In total there is a length of approximately 710m of pavement along the interchange

ramps with width varying from 5.5 to 16m. This can be laid in approximately 30 minutes per

stage.

Sturt road will require 2 passes of the paver per stage with a length of approximately 130m.

This can be laid in approximately 10 minutes per stage.

The south bound exit ramp has a pavement area of approximately 1,100m2 per stage, a single

asphalt layer with a thickness of 50mm, and with one roller, can be rolled in approximately 1

hour and 10 minutes per stage.

48

The south bound entry ramp has a pavement are of approximately 1,700m2 per stage, a single

asphalt layer with a thickness of 50mm, and with two rollers, can be rolled in approximately

1 hour per stage.

Sturt road has a pavement are of approximately 1,750m2 per stage, a single asphalt layer with

a thickness of 150mm, and with two rollers, can be rolled in approximately 1 hour and 30

minutes per stage.

7.4 Curbing

The curbing for phase 5 will be done in the same way as it was in phases 3 and 4 (section

5.7.2).

The south bound exit ramp has approximately 380m of curb per stage, which will be set in

approximately 30 minutes per stage.

The south bound entry ramp has approximately 370m of curb per stage, which will be set in

approximately 30 minutes per stage.

Sturt road has approximately 160m of curb per stage, which will be set in approximately 15

minutes per stage.

7.5 Line Marking

The line marking for phase 5 will be done in the same way as it was in phases 3 and 4

(section 5.7.3).

The south bound exit ramp has 3 road lines with a length of approximately 180m per stage.

There are also 3 arrows to be painted in the first stage. This can be painted in approximately 2

hours per stage.

The south bound exit ramp has 3 road lines with a length of approximately 180m per stage.

This can be painted in approximately 2 hours per stage.

Sturt road has 4 road lines with a length of approximately 130m per stage. There are also 4

arrows to be painted in the first stage. This can be painted in approximately 2 hours per stage.

7.6 Traffic Signals

The traffic signals for phase 5 will be done in the same way as it was in phases 3 and 4

(section 5.7.4).

49

There is one traffic signal on the south bound exit ramp and one on Sturt road. These will

both be installed in the first stage.

The holes will be bored and the bases concreted in place in one day, and the poles will be

erected and the signals installed on another.

7.7 Lighting

The street lighting for phase 5 will be done in the same way as it was in phases 3 and 4

(section 5.7.5).

There are 4 street lights to be erected on the south bound exit ramp for the first stage and 3

for the second. There are 4 street lights to be erected on the entry ramp per stage and 6 on

Sturt road per stage.

It will take approximately 1 day and 6 hours per stage to bore the holes and install the bases.

After the concrete has set it will take another 1 day and 6 hours per stage to erect the poles.

7.8 Signage

There is a give way sign and a stop sign to be installed on the south bound exit ramp in the

first stage and a speed limit sign and a stop sign in the second stage. There is a give way sign

and a speed limit sign to be installed on the south bound entry ramp in the first stage and a

speed limit sign in the second stage. Finally there is a speed limit sign to be installed on Sturt

road in the first stage and a speed limit sign and a stop sign in stage 2.

These can all be installed in one day per stage.

There is also a large exit sign on the south bound exit ramp to be installed in stage 2, which

will require the pole borer. The hole will be bored and the base set on the same day that the

other signs are installed in the second stage. The sign will then be erected after the concrete

had been allowed to cure.

50

8 Phase 6 – Closing

8.1 Open road

A site opening ceremony will be held upon completion of the project. Public tours will be

taken through to educate the general population on the features and innovations of the new

intersection.

Upon the opening of the upgraded intersection, the temporary lanes will be removed. The

spray seal laid will be ripped up with a motor grader, and loaded into trucks for disposal.

The ground covered in drawing 50 will be landscaped to match the rest of the verge on

Flinders University's boundary.

8.2 Disassemble Site

With construction complete, the rented equipment may be returned and any surplus items

disposed of. An auction will be held to sell excess tools, computers and other articles that will

have been acquired for the project. If public land, such as Flinders University’s grounds, has

been damaged, it will be rejuvenated to its original condition or better.

51

9 References

City of Onkaparinga, 2010, viewed 6/5/2014,

<http://www.onkaparingacity.com/onka/living_here/waste_recycling/waste_disposal_sites.js

p>

Dr. E Elbeltagi, Estimating work items costs, idirect costs, markup and contract pricing, pg

98, viewed 10/5/2014, <http://osp.mans.edu.eg/elbeltagi/Cost%20Ch5.pdf>

ResourceCo, viewed 6/5/2014,

<http://www.resourceco.com.au/products-services/resourceco/pricing/disposal.html>

52

10 Appendices

10.1 Appendix A – Construction Gantt Chart

53