machine utilization at krishan and co
TRANSCRIPT
Introduction
Product manufactured ◦ Speedometers
◦ Pressure gauges
◦ Temperature indicators
◦ Tachographs
◦ Cables
◦ Warning lamps
Manufacturing facility
Machine room◦ Lathes
Semi automatic
Manual
◦ Gear hobbing machine
◦ Milling machines
Assembly room
Testing bay
Current problems
Difficulties in meeting the sales order Planning is pinpointing manufacturing dept.
for under utilization of machines Manufacturing are blaming improper
scheduling But sales are growing and GM wants to know
current m/c utilization and future capacity requirements
And GM is interested in building in two months inventory stock
Steps for work sampling
Classification and grouping of activities
Designing of forms
Properly randomized times of observation were obtained
Activities were observed and data were recorded
Pilot study to compute number of observations to get desired accuracy and confidence level
Work categories
Machine working
Set up, loading and unloading,
machining, inspection and
cleaning
Machine not working
Breakdown
Electrical
Mechanical
Waiting for tools
To bring tools
Grinding of tool
Waiting for material
Waiting for operator
Personal work
Machine interference
No reason
For instructions
Machine open
Machine grouping
Group Machine type No of machines
1 Automates 10
2 Lathes 13
3 Hobbing 6
4 Milling 3
5 Drilling 9
Obtaining random numbers
Random number table was used
950, the first digit indicates the hour and second indicates fraction of the hour
That is 950 would mean 9.30 am
12 observations were made in a day
Random no. falling outside the working hours and excluded
Pilot study
Cares taken during study◦ Observations at proper time
◦ Avoid biasing
◦ Record what observed without an anticipation
◦ Random approach during taking observations
Pilot study was carried out to find approx. value of p
On the basis of calculated p value for different groups of machines actual observations needed were calculated using the formula
n=4(1-p)p/L², L=error%
Total observations for each group
Group no No of observations
1 815
2 1025
3 1115
4 1055
Drilling machines were excluded from study as from sample study it was revelled that they were not critically loaded and had ample capacity to take up additional load
Summery of the results of study
category automats Lathes Hobbers Millers
Working 69.70 41.38 51.46 47.10
Idle for operator 15.82 33.00 47.91 39.85
Idle for material 2.30 3.62 0 4.35
Idle for tool 1.22 2.10 0 1.52
Breakdown 7.69 14.73 0 0.87
Machine open 2.08 4.33 0 2.83
Others 1.21 0.9 0.6 3.48
Results and discussion
01020304050607080
working
operator
material
tool
breakdown
machine open
others
Poor machine utilization for all machines except automates
Contribution to total time
working52%operator
34%
material3%
tool1%
breakdwon6%
machine open2%
others2%
contribution to total time
Discussions
Idle for operator is major about 34% total time which requires in detail further study
Reasons for operator idle time◦ Time waste in personal work
◦ Put on other jobs like material handling
◦ Too early cleaning of machine at the time of shift end
◦ Machine interference in case of Hobbing machine(47.91%)
Idle for material is another major concern Breakdowns are on higher side
Machine time available
Group 1 2 3 4
m/c hours / year 45000 58500 27000 13500
Allowances % 16 22 20 15
Net hours/ year 37800 45630 21600 11500
Allowances to get net machine hours available
Activity 1 2 3 4
Set up 5 4 5 5
Operators personal time, Interference, etc.
5 6 8 5
Breakdowns 5 8 5 1
Waiting for tools 1 2 2 2
Waiting for material 0 2 0 2
Total 16 22 20 15
Calculations of machine hours required
Considerations◦ Grouping of similar instruments
◦ List of components being made was made and this was in turn used to calculate load due to particular part.
◦ Operation time was taken from time study data
◦ For unavailable time study data, time was estimated
◦ For some operations stop watch time study was done to find out operation time
Allowances for Rejection
A survey was carried out for about 50 odd items and considerations from quality departments taken to decide on the rejection %
Group Rejection allowance
Automatics 2
Lathes 10
Hobbies 10
Milling 5
Machine hours required for production plan
Product 1 2 3 4
Speedometer 12600 13400 19000 0
Pressure gauges 5200 19300 0 3700
Temp gauges 0 10000 0 100
Tachographs 3100 3000 2700 440
Fare meters 30 300 53 0
Cables 19800 2100 0 3900
Hub wires 765 200 500 250
Warning lamps 1240 440 0 420
Total 42735 48740 22253 9710
Capacity expansion
S.N. 1 2 3 4
1 Net hours/ year 37800 45630 21600 11500
2 Total required 42735 48740 22253 9710
3 Additional 4900 3300 653 -1800
4 OT/week/machine 10 5 3 0
5 M/c hours for 2 months inventory
7094 7974 3028 1596
6 Total (3+5) 11994 11274 3681 -204
7 hours/machine/year 3780 3510 3600 3825
8 Additional machines (6/7) 3 3 1 Nil