m e m o r a n d u m · 2020-07-27 · the additional storm water controls include a runon control...
TRANSCRIPT
17 East Main St. PO Box 431
White Sulphur Springs, MT 59645 Tel: (406) 547-3466
M E M O R A N D U M
DATE: October 29, 2018
TO: Rainie DeVaney
Jeff May
FROM: Jerry Zieg
SUBJECT: Addendum to Integrated Discharge Permit Application for the Black Butte
Copper Project
Tintina Montana, Inc. (Tintina) is submitting this memorandum as an addendum to the Integrated
Discharge Permit Application (Permit Application) for the Black Butte Copper Project (Project).
This addendum adds a contingency to the water management plan for storage of treated water
during the seasonal period when the total nitrogen standard is applied (July 1 to September 30,
for Middle Rockies Ecoregion). Below is a description of the water management plan for the
storage contingency, a description of the TWSP, and an update to the Storm Water Discharge
Systems.
Water Management Storage Contingency
Tintina is proposing to discharge water as described in the Integrated Discharge Permit
Application Narrative (Hydrometrics, 2018) if the discharge water meets the seasonal effluent
limits for total nitrogen in the MPDES permit. However, if the total nitrogen concentration is
greater than the effluent limit, the treated water will be discharged to the Treated Water Storage
Pond (TWSP) from July 1st to September 30
th. Starting October 1
st, the stored water will be
routed back to the WTP and blended with the WTP effluent prior to discharge to Outfall 001.
Prior to discharge the blended water will be sampled/monitored as required in the MPDES
permit. In the event that storage is necessary, the average seasonal discharge (October 1st to June
30th
) to Outfall 001 will be 531 gpm (133 gpm from the TWSP and 398 gpm from the WTP). An
updated water balance schematic (revised Figure 3.8) and contingency discharge schematic
(Figure 3.8A) is provided in Attachment A.
Treated Water Storage Pond Description
The TWSP will be located southeast of the WTP and west of Brush Creek as shown the revised
Figure 1.3 included in Attachment 1. The design of the TWSP was based on an average seasonal
flow rate from the WTP of 405 gpm. The average seasonal flow rate is slightly larger than the
average annual discharge due to minor differences in seasonal flows from Mill Catchment
Runoff associated with the seasonal precipitation and evaporation at the site. The TWSP has
been designed to store up to 53.7 million gallons of treated water, providing enough temporary
storage for treated water from July 1 to September 30 at an average flow rate of 405 gpm. The
pond will be lined with a 60 mil HDPE geomembrane liner installed over a 12 oz/yd2 non-woven
geotextile cushion. Treated water from the water treatment plant will be pumped through a 6-
inch (150mm) diameter HDPE pipeline to the TWSP. Water stored in the TWSP will then be
pumped back to the water treatment plant via a 6-inch (150mm) diameter HDPE pipeline, where
it will be mixed with the WTP effluent and allow for the blended water to be sampled prior to
being discharged per the MPDES permit.
Storm Water Discharge Systems Update
The addition of the TWSP requires updates to the site drainage controls and storm water permit.
The additional storm water controls include a runon control berm on the northwest portion of the
pond, drainage ditches along the remainder of the facility, and two storm water outfalls (Outfalls
012 and 013). An update to Figure 3.1 shows the storm water controls and outfalls for the
project. Storm water flows to each of the new outfalls were simulated using the same methods
and modeling software for the other outfalls (See Section 4.2 of permit). In addition, storm
water quality is assumed to be similar to that summarized in Section 4.3 of the permit. Below is
a description of the new drainage controls and a summary of the changes to the permit
application.
Storm water Outfall 012 discharges water from approximately 8.75 acres from areas south and
west of the TWSP. Discharge will include storm water from native lands and a portion of the
TWSP embankment (constructed from non-waste rock materials). Diversion ditches collect
runoff from the drainage areas and directs flow to the outfall. The storm water simulations
indicate that peak flow will be 9.72 cfs with a total runoff volume of 0.5 acre-feet during a 10-
year/24-hour storm event. A summary of the flow calculations and SEDCAD4 output are
provided in Attachment B.
Storm water discharges to Outfall 013 originate from 2.6 acres of the southern and western
portion of the vegetated TWSP embankment. Diversion ditches collect runoff from the drainage
areas and directs flow to the outfall. Storm water modeling simulated a peak flow of 1.76 cfs
with a total runoff volume of 0.1 acre-feet from a 10-year/24-hour storm event.
There is a small area (0.4 acres) of sheet flow from the vegetated embankment on the northeast
corner of the TWSP. The simulated peak flow for this area is estimated at 0.27 cfs with a total
volume of 0.01 acre-feet from a 10-year/24-hour storm event.
Outfalls 012 and 013 share a runon control structure along the northwest side of the TWSP. The
runon control structure will consist of a berm above the cut slope of the northwest portion of the
pond. The northeast corner of the TWSP embankment extends into a natural drainage channel.
The embankment will be protected from scouring via a riprap covering on the northeast corner
and a modified drainage channel as shown on revised Figure 3.1. The geometry of the diversion
channel will be similar to that shown on Figure 4.2 in the permit application.
The information for the two additional outfalls (012 and 013) required for Form 2F is provided
below:
I. Outfall Location
Outfall No. Latitude Longitude Receiving Water
012 46° 45' 58.68" 110° 54' 22.68" Brush Creek
013 46° 46' 2.28" 110° 54' 16.92" Brush Creek
II. Improvements
No additional information
III. Site Drainage Map
A revised Site Drainage Map (Figure 3.1) is included with this memorandum
IV. Narrative Description of Pollutant Sources
Outfall No. Area of Impervious Surface Total Drained Area
012 No Impervious Surface 8.75 acres
013 No Impervious Surface 2.60 acres
No additional information for Parts B and C.
V. Nonstormwater Discharges
Not Applicable
VI. Significant Leaks or Spills
ATTACHMENT A
REVISED FIGURES
1800
1805
1810
1745
1735
1725
1750
1740
1730
1795
1785
1775
1765
1755
1790
1780
1770
1760
1865
1855
1845
1835
1825
1870
1860
1850
1840
1830
1815
1820
1815
1805
1795
1785
1775
1765
1755
1745
173518
20
1810
1800
1790
1780
1770
1760
1750
1740
1730
1785
17751765
1790
17801770
1735
1740
1730
1795
1785
1775
1800
1790
1780
17601765
1770177517801785
1755
N 5,178,500E 5
10
,0
00
N 5,181,000E 5
08
,5
00
N 5,178,500E 5
08
,5
00
N 5,181,000E 5
06
,0
00
N 5,178,500E 5
06
,0
00
N 5,181,000E 5
10
,0
00
2019
24
29
30
25
36
31
32
T12N
R
6E
T12N
R
7E
STRAWBERRYBUTTE
RECLAMATIONMATERIALSSTOCKPILE
SOUTH
FIBER-OPTIC VAULT LOCATION
PORTAL
PORTAL PAD(EL. 1785 m)
ADIT ALIGNMENTPROJECTED TO SURFACE
NON-CONTACT WATERRESERVOIR (NCWR)
CEMENT TAILINGSFACILITY (CTF)
CTF DIVERSION DITCHING
FIBER-OPTIC VAULT LOCATION
CONTACT WATER POND (CWP)
POWER LINE AND PIPINGTO WATER WELL (PW-6)
TOPSOILSTOCKPILE
SUBSOIL STOCKPILE
BURIED SOLID PIPE (TYP.)
BURIED PERFORATED PIPE (TYP.)
APPROX. TOP OF CUTOR TOE OF FILLS (TYP.)
POWER LINE
VENT RAISE (TYP.)
CULVERT CROSSING 5
CULVERTCROSSING
CULVERT CROSSINGCULVERT CROSSING
ACCESS ROAD
PROCESS WATERPOND (PWP)
SERVICE ROAD
CONSTRUCTION ACCESSROAD AND CULVERT
ACCESS GATE
CULVERT CROSSING
COPPER-ENRICHEDROCK STOCKPILE
TEMP. WASTE ROCK STORAGE(EL. 1792.98 m)
MILL PAD(EL. 1785 m)
EXTEND EXISTINGROAD TO VENT RAISE
CONNECT EXISTINGROAD TO VENT RAISE
NCWR DIVERSIONDITCHING
SERVICE ROADPWP DIVERSION
DITCHING
APPROXIMATE AREA FORRECLAMATION MATERIAL
STOCKPILE NORTH
TEMP. POWDER MAGAZINEFOUNDATIONDRAIN POND
FOUNDATIONDRAIN POND
CORE SHACKS
COON CREEK
SPILLWAY
US 89
MINE PERMIT BOUNDARY(APPROXIMATE)
CTF ROAD
MINE PERMIT BOUNDARY(APPROXIMATE)
FENCING
ALLUVIAL UIG
SEPTIC DRAINFIELD
METEOROLOGICAL STATION
SHEEP CREEK
LITTLE SHEEP CREEK
SHEEP CREEK COUNTY ROADBUTTE CREEKCOUNTY ROAD
BRUSH CREEK
SECONDARY ESCAPEWAYACCESS ROUTE TOWATER WELL (PW-6)
BURIED PERFORATEDUIG PIPE (IN CLOSURE)
JAW CRUSHERCONVEYOR
TEMP. CONSTRUCTION STOCKPILE
UCZ PROJECTED TO SURFACE
LCZ PROJECTED TO SURFACE
CULVERT CROSSING
CULVERTCROSSING
CULVERT CROSSING
TREATED WATERSTORAGE POND (TWSP)
FOUNDATION DRAININFILTRATION POND
WET WELL PIPELINE
BURIED WET WELL PIPELINE
FIGURE 1.3Facilities Site Plan
Black Butte Copper Project
Mine Operating Permit Application
Meagher County, Montana
0 250Scale: 1: 15 000 (metres)
500
N 1,000E 1
,0
00
LEGEND
Prepared by Tetra Tech Inc. (Revised October 2018 to include alluvial UIG as included in the December 2018 Integrated Discharge Permit Application Narrative Report by Hydrometrics that was revised in February 2018; Completeness Determination by MT DEQ on May 25, 2018.)
STREAMS
WETLANDS
POWER LINE ROUTEAPPROX. TOES / TOP OF CUT
CULVERT CROSSING
MINE PERMIT BOUNDARY (APPROX.)
NEW FENCE
BURIED ALLUVIAL CONVEYANCE PIPELINE
COUNTY ROAD
NEW MINE ROAD
VENT RAISEWATER WELL
UTM Z12N NAD83 COORDINATES
US ROUTE 89
DIVERSION DITCH
WETLANDS (OUTSIDE PROJECT BOUNDARY: SEENOTE BELOW)
Some streams and wetlands shown outside of the project boundarywere determined via photo-interpretation and were not delineatedaccording to USACE methodology. These features are presented fordisplay purposes only and do not represent jurisdictional features.
Streams within the project boundary represent jurisdictional featuresthat were determined during field inventory to have an ordinary highwater mark (OHWM) consistent with 33 CFR § 328.3.
Topographic base map from US Geological Survey (2011):Strawberry Butte 7.5 Minute Quadrangle.Map Projection: UTM Zone 12NMap Datum: NAD83Contour Interval: 5m
SECTION NUMBER32
SECTION LINEPRIVATE ROAD
BURIED WATER LINE
FOUNDATION DRAIN POND
Scale: 1" = 1250'0 1250625
STREAMS (OUTSIDE PROJECT BOUNDARY: SEENOTE BELOW)
ALLUVIAL INFILTRATION TRENCH
BURIED UNDERGROUND INFILTRATION GALLERY(UIG) - SOLID PIPE IN CLOSURE
WET WELL PIPELINEBURIED WET WELL PIPELINE
DRY
WATER TANK
5,000 GAL
OFFICE
SHOP
PARKING
WPDSL
LAYDOWN
AREA
WATER WELL
EQUIP
PRKG
CO
NE
X
PASTE PLANT
TRUCK SHOP COMPLEX
W.T.P.
THICKENER
MOBILE GEN
SETS
BATCH
PLANT
OFF/WASH DRY
CONC.
THICKENER
CONC.
STORAGE
PROCESS
PLANT
FLY ASH/SLAG SILOS
DIESEL STORAGE 50kL CAP.CONTAINMENT BERM
REFUELING STA
PROC. WAT. TANK
FRESH/FIRE WAT. TANK
POTABLE WAT. TANK
SURGE BIN
EMERGENCYGENSETS
CONVEYOR
SUB
STATION
RECLAMATIONMATERIALSSTOCKPILE
SOUTH
FIBER-OPTIC VAULT LOCATION
PORTALPORTAL PAD(EL. 1785 m)
ADIT ALIGNMENTPROJECTED TO SURFACE
NON-CONTACT WATERRESERVOIR (NCWR)
CEMENT TAILINGSFACILITY (CTF)
CTF DIVERSION DITCHING
FIBER-OPTIC VAULT LOCATION
CONTACT WATER POND (CWP)
POWER LINE AND PIPINGTO WATER WELL (PW-6)
TOPSOILSTOCKPILE
SUBSOILSTOCKPILE
APPROX. TOP OF CUTOR TOE OF FILLS (TYP.)
VENT RAISE (TYP.)
CULVERT CROSSING 5
CULVERTCROSSING 4
CULVERT CROSSING 1CULVERT CROSSING 2
ACCESS ROAD
PROCESS WATERPOND (PWP)
SERVICE ROAD
CONSTRUCTIONACCESS ROAD
CULVERT
ACCESS GATE
CULVERT CROSSING 3
COPPER-ENRICHEDROCK STOCKPILE
TEMP. WASTE ROCKSTORAGE
(EL. 1792.98 m)
MILL PAD(EL. 1785 m)
EXTEND EXISTINGROAD TO VENT RAISE
CONNECT EXISTINGROAD TO VENT RAISE
NCWR DIVERSIONDITCHING
SERVICE ROAD
PWP DIVERSIONDITCHING
APPROXIMATE AREA FORRECLAMATION MATERIAL
STOCKPILE NORTH
TEMP. POWDER MAGAZINE
FOUNDATIONDRAIN POND
FOUNDATIONDRAIN POND
CORE SHACKS
SPILLWAY
CTF ROAD
MINE PERMIT BOUNDARY(APPROXIMATE)
E 5
10
,0
00
N 5,178,500E 5
08
,5
00
N 5,178,500E 5
06
,0
00
SEPTIC DRAINFIELD
METEOROLOGICAL STATION
SHEEP CREEK
SHEEP CREEK ROADBUTTE CREEK ROAD
29
30
25
36
31
32
T12N
R
6E
T12N
R
7E
ACCESS ROUTE TOWATER WELL (PW-6)
STRAWBERRYBUTTE
TEMP. CONSTRUCTIONSTOCKPILE
CULVERTCROSSING
CULVERTCROSSING
ROCK-LINEDCHANNEL
ROCK-LINEDCHANNEL
ALLUVIAL UIG
B
R
U
S
H
C
R
E
E
K
L
I
T
T
L
E
S
H
E
E
P
S
H
E
E
P
C
R
E
E
K
S
H
E
E
P
C
R
E
E
K
L
IT
T
L
E
S
H
E
E
P
C
R
E
E
K
004
002
007
006
003
009
010
005
C
O
O
N
C
R
E
E
K
2
5
.
1
1
5
.
7
1
.
2
9
.
3
4
.
3
4
9
.
2
1.4
1.3
0.7
28724.638
1.3
4
.
0
2
.
1
6
.
3
1.5
2
.
4
1
.
7
8.0
7.5
7.0
3
1
.
3
1.3
1.7
1
0
.
0
2.0
0.9
7
.
7
0.3
0.4
0.5
6
.
2
3
.
4
CULVERTCROSSING
C
R
E
E
K
008
011
001
BURIED SOLIDPIPE (TYP.) BURIED PERFORATED
PIPE (TYP.)
APPROX. TOP OF CUTOR TOE OF FILLS (TYP.)
MINE PERMIT BOUNDARY(APPROXIMATE)
BURIED PERFORATEDUIG PIPE (IN CLOSURE)
JAW CRUSHER
CONVEYOR
TREATED WATERSTORAGE POND (TWSP)
FOUNDATION DRAININFILTRATION POND WET WELL PIPELINE
BURIED WET WELL PIPELINE
RUNONCONTROL
BERM
RUNOFFCONTROL
DITCH
2
.
6
2
.
7
6
.
0
0
.
4
012
013
NO
RT
H
LEGENDMINE PERMIT BOUNDARY (APPROX.)
BURIED ALLUVIAL CONVEYANCE PIPELINEDISTRIBUTION PIPE UNDER WETLAND INFILTRATION TRENCH
EROSION CONTROL DRAINAGE
DITCH
CTF DIVERSION DITCH
CATCHMENT BOUNDARYUS 89US 89
CULVERTMPDES OUTFALL
STORMWATER OUTFALL
INTERNAL DRAINAGE TO WATERN 5,178,500TREATMENT PLANT (WTP)STORM WATER CAPTURE AREAS DRAINAGE DIVIDE AND FLOW DIRECTIONROAD SEGMENT OR STOCKPILE ACRES DRAINAGE AREA ACRESGENERAL DRAINAGE FLOW DIRECTION
MPDES and Storm Water Discharge Systems
Black Butte Copper Project
Meagher County, Montana
Figure 3.1
7
.
8
1.2
SCALE0
(In Feet)
1050
Mine Portal
Water TreatmentPlant
Process Water Pond(PWP)
Mill
Water with Concentrate
Tailings PastePlant Underground
Infiltration Galleries
UndergroundTailings Storage
Cemented TailingsFacility (CTF)
MillCatchment
Runoff
86.4 gpm 103 gpm
Ore Water24.1 gpm
7.0 gpm
13.1 gpm
5 gpm
42.2 gpm
8 gpm
Treated Water397.7 gpm
189.4 gpm
Mill Water42.4 gpm
UndergroundDewatering500 gpm
1,912.1 gpm
Foundation Drain
20 gpm
RO Brine83 gpm
24.6 gpm
Recycle 14.6 gpm
FreshwaterUses
2,042 gpm
(~90% Recycled)
PrecipitationTransfer
42.2 gpm
NOTES:1. WATER IN TAILINGS PASTE IS ASSUMED TO BE UNRECOVERABLE.2. SEEPAGE IS ASSUMED TO BE ZERO AS THE FACILITIES ARE LINED.3. THE NUMBERS IN THE BOXES CORRESPOND TO TABLE V-1 IN APPENDIX V.Reference: Modified after Knight Piesold (2017a): Report No. VA101-46-/3-2
Unused Freshwater4.5 gpm
8 gpm
FreshwaterLosses5.5 gpm
9
10
12
1
15
17
16
13
2
14 768
5 4
18
19
gpm acre-ft/year
PWP Evaporation 8 13
CTF Void Loss 103 166
Underground Tailings Void Loss 86 139
Water Loss to Concentrate 7 11
Freshwater Losses 6 9
Total Consumptive Use 210 339
Estimated Groundwater Consumptive Use Components
Water use
Consumptive Use
Runoff Precipitation Evaporation
Precipitation
Treated WaterStorage Pond
Details shown on Figure 3.8A
FIGURE 3.8Annual Water Balance Schematic for Mean Case - Year 6
Mine Operating Permit ApplicationBlack Butte Copper Project
Meagher County, Montana
Direct Discharge to UIG Storage with Seasonal Discharge
Treated Water3397 gpm
1333
gpm
Total Discharge3530 gpm
Water TreatmentPlant
UndergroundInfiltration Galleries
(UIG)
Treated Water1397.7 gpm
FIGURE 3.8AMPDES Discharge
Mine Operating Permit ApplicationBlack Butte Copper Project
Meagher County, Montana
Water TreatmentPlant
UndergroundInfiltration Galleries
(UIG)
Treated WaterStorage Pond
(TWSP)
3972gpm
NOTES:1. If effluent total nitrogen concentration is < seasonal effluent limit water will be discharged to UIG continuously.2. If effluent total nitrogen concentration is > seasonal effluent limit water will be stored in TWSP from 7/1 to 9/30.3. Water will be discharged from TWSP by blending water with WTP effluent at an average rate of 530 gpm.
ATTACHMENT B
FLOW CALULATIONS AND SEDCAD4 OUTPUT
SF-03
Drainage Areas 1 2 3 1 2 1
Total Acres 6.01 1.95 0.79 0.90 1.70 0.40
Channel Flow*
Slope % 15.3 21.1 10.7 11.4 5.6Horizontal Distance (ft) 392.0 202.0 299.4 317.0 750.0Vertical Distance (ft) 60.0 42.6 32.0 36.0 42.0Time (hr) 0.1 0.0 0.0 0.0 0.0
Hydraulic Soil Group P(D) CF (B) CF (B) CF (B) CF (B) CF (B)Vegetation Type Shrubland Grass Cover Grass Cover Grass Cover Grass Cover Grass Cover
Upland Flow ***
CN 83 73 73 73 73 73
Slope % 7.6 33.3 31.4 30.8 25.9 32.8Horizontal Distance (ft) 105.0 64.0 68.0 64 57 65Vertical Distance (ft) 8.0 21.3 21.3 20 15 21S (in) 2.0 3.7 3.7 3.699 3.699 3.699Time (hr) 0.029 0.013 0.014 0.013 0.013 0.013Tc (Total) 0.084 0.021 0.030 0.030 0.033 0.013
Time of Concentration
Compacted Fill
Outfall 012 Outfall 013
Soil Type (1)Poin Compacted
FillCompacted
FillCompacted
FillCompacted
Fill
Subwatershed Hydrology Detail:
Stru#
SWS#
SWS Area
(ac)
Time ofConc
(hrs)
Musk K
(hrs)Musk X
Curve
NumberUHS
PeakDischarge
(cfs)
RunoffVolume
(ac-ft)
#1 1 6.010 0.084 0.085 0.346 83.000 S 9.18 0.447
2 1.950 0.021 0.000 0.000 73.000 S 1.32 0.073
3 0.790 0.030 0.000 0.000 73.000 S 0.54 0.027
8.750 9.72 0.547
#2 8.750 9.72 0.547
Filename: S012.sc4 Printed 10-24-2018
SEDCAD 4 for WindowsCopyright 1998 -2010 Pamela J. SchwabCivil Software Design, LLC 1
Subwatershed Hydrology Detail:Stru#
SWS#
SWS Area
(ac)
Time ofConc
(hrs)
Musk K
(hrs)Musk X
Curve
NumberUHS
PeakDischarge
(cfs)
RunoffVolume
(ac-ft)
#1 1 0.900 0.030 0.000 0.000 73.000 S 0.61 0.033
2 1.700 0.033 0.000 0.000 73.000 S 1.15 0.064
2.600 1.76 0.097
#2 2.600 1.76 0.097
Filename: S013.sc4 Printed 10-24-2018
SEDCAD 4 for WindowsCopyright 1998 -2010 Pamela J. SchwabCivil Software Design, LLC 1
013
Subwatershed Hydrology Detail:Stru#
SWS#
SWS Area
(ac)
Time ofConc
(hrs)
Musk K
(hrs)Musk X
Curve
NumberUHS
PeakDischarge
(cfs)
RunoffVolume
(ac-ft)
#1 1 0.400 0.013 0.000 0.000 73.000 S 0.27 0.011
0.400 0.27 0.011
#2 0.400 0.27 0.011
Filename: SF-3.sc4 Printed 10-24-2018
SEDCAD 4 for WindowsCopyright 1998 -2010 Pamela J. SchwabCivil Software Design, LLC 1
SF-0