Millwood Proposed New Firehouse Lunch & Learn

Presentation to Residents, March 2011

Tonight’s Meeting

! Brief History ! Design Parameters ! Schematic Design

!  Site !  Landscape Plan !  Building Elevation !  Floor Plans !  Schematic Construction Budget

! Fiscal Impact ! Next Steps

The Road to the Bond Vote

Action Date

DEIS Scoping 9/8/09

Pre-Design 3/15/2010

Schematic Design 7/11/2010

DEIS Accepted as Complete 12/6/2010

Public Hearing DEIS 1/12 & 24/2011

Written Comments on DEIS 2/7/2011

FEIS Accepted as Complete 2/28/2011

Statement of Findings Accepted 3/11/2011

New Firehouse Bond Resolution 3/11/2011

BOND VOTE SCHEDULED FOR 4/12/2011

1926 – Station #1 Built for Brockway

Station # built with community donations

For apparatus smaller than many of today’s SUVs

1926 – Calvin Coolidge President

Calvin Coolidge was President

1955 – Two Bays Added

1982 – Station #2 Built

Station # 2 Built to house modern

apparatus

1990 – Recommend Demolish & Rebuild

Helms report commissioned. Recommends Station #1 be

demolished and rebuilt

1999 – $1 Purchase

Firefighters transfer

ownership to District for $1

2001 – Emergency Repairs

Emergency repairs to

stabilize load bearing wall

Firefighters provide

equipment and logistic support at Ground Zero

2007 – Emergency Repairs

Emergency repairs to

stabilize second floor and roof

Time for a New Firehouse

Station #1 has outlived its useful life

Philosophical Approach

! �Build a new firehouse that the community can be proud of.”

Tom Curley, Resident Expert ! A functional, safe building providing a professional work

environment ! A building that respects residents’ tax dollars ! A building that our pride in our firefighters and that

retains and attracts volunteers

JLN Needs Assessment Study

!  5 Back-in Bays !  Radio Room !  Ready Room !  Offices:

!  Chiefs’ office (3 work stations) !  Line Officers’ office (2 work stations) !  Company office (2 work stations) !  District office (2 work stations) !  Ladies Aux. office (1 work station)

!  Multi-purpose room (max capacity = 100) !  Kitchen !  Membership Room !  Exercise Room !  Lobby Space for Antique Apparatus

New firehouse building program

based on independent review of the Millwood Fire District and

NFPA standards.

Cost Estimate

Construction Assumptions

"  Building Envelope !  Standard Concrete Foundation

System (Footings/Piers/Walls) !  No Basement (Slab on Grade) !  Structural Steel Frame & Metal Floor

and Roof Decking !  Exterior Cavity Wall Construction (8”

CMU & Roman Brick Veneer) !  EPDM Roofing System !  Energy Efficient Aluminum Curtain

Wall & Window System !  14’ x 14’ Apparatus Bay Doors

"  Interiors !  Glazed 8” CMU Walls in Apparatus

Bays !  Metal Stud & Drywall Interior Walls

"  Interiors (cont.) !  Spray on Fireproofing on Structural

Steel !  Skylights in Apparatus Bays !  Hollow Metal Frames/Doors &

Windows !  Acoustic Sheetrock & Ceiling Systems !  Sheet Resilient Flooring !  Ceramic & Porcelain Tiles !  Commercial Kitchen !  2-Stop Elevator !  Motorized Operable Wall System !  Metal Lockers/Toilers Accessories Etc.

Construction Assumptions

"  MEP !  Roof Top A/C Units and Ducted

Systems !  Fire Protection Sprinkler System !  Oil-fired Burner and Fin Tube

Radiation !  Apparatus Bay Radiant Heating !  Energy Efficient Lighting

Green Initiatives Included

!  Dark Sky Compliant !  Lighting sensors !  Focused parking lights !  Driveway lighting

!  Wetlands Enhancement !  Pond manages storm water &

encourages biodiversity !  Bio swales

!  No-Mow Areas !  Water Mitigation

!  Permeable pavers !  Grasscrete

!  Paving Surfaces (reduce heat-sink effect) !  Permeable pavers !  Grasscrete !  Light-colored concrete apron

!  Energy Star Compliant Construction !  Insulation, windows,

construction, mechanicals !  Appliances

!  Building Orientation !  Significantly Reduced Steep

Slopes Disturbance

Green Alternatives NOT included

!  Green Roof !  Apparatus Roof !  Building Roof

!  Solar Hot Water Heating

!  Geothermal Well

!  Photovoltaics

The cost of these alternatives were not financially viable.

Construction Costs

Construction Cost

Building Construction $6,826,308

Site Work $2,334,014

Landscape $528,805

Traffic Light $150,000

Total $9,839,127 Building Cost/SF $379

Construction Cost/SF $546

Construction Costs

Soft & Other Costs

Consultant Fees $1,681,411

Owner Fees $295,000

Testing & Inspection $45,000

Interior Systems & Furnishings $100,000

Soft & Other Costs $2,121,411

Total Costs

TOTAL

Construction $9,839,127

Soft Costs & Other Fees $2,121,411

Contingency $1,501,801

TOTAL $13,462,339

• FINANCING TO INCLUDE up to $2.25 million in Capital Reserve, Sale of 108 Millwood Road and 60 Millwood Road and a 25-year Bond.

• Bond = $9.95 million

Fiscal Impact Analysis

Fire District Levy History

Year Tax Levy

House Value/2010 Assessed Value $500,000 $750,000 $1,000,000

Tax Rate/ $000 AV $83,1000 $124,650 $166,200

2011 $1,489,775 $4.57 $380 $570 $760

2010 $1,411,768 $4.33 $360 $540 $720

2009 $1,709,090 $5.17 $429 $644 $859

2008 $1,690,008 $5.15 $428 $642 $856

2007 $1,437,885 $4.32 $360 $538 $718

2006 $1,489,223 $4.42 $367 $551 $735

Source: Westchester.gov and 2010 RAR, 2011 MFD Budget

Long-Range Planning Assumptions

!  Major Purchase Planning (Equipment Reserve) !  2010-2025 Apparatus and

Equipment !  Purchases > $25,000

!  Inflation !  Operating Expenses: 3%

annual inflation !  Major Purchase: 3% inflation

between 2012-2014; 5% inflation between 2017-2020; 7% inflation 2023-2025

!  LOSAP reasonably funded

!  Operating Budget Base = 2010 !  Station #1 utilities & grounds

costs increase by 50% once new firehouse complete

!  Bond !  Rating AA !  Rate = 4.25% !  Term = 25 Years

!  Short-Term Financing !  Rate = 1% !  Term = 2 Years

!  All Volunteer Fire Company

Major Equipment Purchase

Vehicle Cost ($ 2010) Purchase Year Years in Service

Chief’s Car $58,000 2010 11

Mini Attack $325,000 2010 21

Cascade/Compressor $65,000 2012 22

Chief’s Car $58,000 2012 10

Rescue/Engine* $650,000 2014 24

Chief’s Car $58,000 2015 10

Tanker $675,000 2018 24

E-247* $600,000 2020 23

E-248 $600,000 2024 20

TOTAL $3,089,000 **$167,000 annual contribution to ER is budgeted

** The Board is considering a combined rescue pumper that saves money with no loss of safety. That evaluation is not complete as of this meeting.

Risks to Projections

!  “Combo” or “career” firefighting force is required !  Bond interest rate increase !  Cost of ConEd easement !  Environmental mitigation at Station #1 !  Additional LOSAP funding required

10-YEAR LEVY PROJECTION

YEAR OPERATING BUDGET

EQUIP RESERVE

CAPITAL RESERVE

LONG TERM FINANCING

SHORT TERM

FINANCING TOTAL % Change

Avg. 2007-2010 $711,000* $240,000 $691,000 – – $1,661,000 –

2011 $639,766** $100,000 $750,000 $0 $9,000 $1,489,775 5%

2012 $738,021*** $167,000 $50,000 $656,600 $18,000 $1,629,621 9%

2013 $778,162 $167,000 $50,000 $656,600 $1,651,762 1%

2014 $801,506 $167,000 $50,000 $656,600 $1,675,106 1%

2015 $825,552 $167,000 $50,000 $656,600 $1,699,152 1%

2016 $850,318 $167,000 $50,000 $656,600 $1,723,918 1%

2017 $875,828 $167,000 $50,000 $656,600 $1,749,428 1%

2018 $902,103 $167,000 $50,000 $656,600 $1,775,703 2%

2019 $929,166 $167,000 $50,000 $656,600 $1,802,766 2%

2020 $957,041 $167,000 $50,000 $656,600 $1,830,641 2%

• 2010 Operating Expense; ** 2011 Budget; *** 2012 + $18,000 for increased heat, electricity, grounds • Note: 2011 increase of 5 % versus 2010

10-Year Fiscal Impact Projection

Year Tax Levy Tax Rate/

$000 AV

House Value/Levy

$500,000 $750,000 $1,000,000

Avg. 2007-2010 $1,661,000 $5.09 $423.35 $635.02 $846.69

2011 $1,489,755 $4.58 $380.00 $570.00 $760.00

2012 $1,629,621 $5.00 $415.35 $623.02 $830.70

2013 $1,651,762 $5.07 $420.99 $631.49 $841.98

2014 $1,675,106 $5.14 $426.94 $640.41 $853.88

2015 $1,699,152 $5.21 $433.07 $649.60 $866.14

2016 $1,723,918 $5.29 $439.38 $659.07 $878.76

2017 $1,749,428 $5.37 $445.88 $668.83 $891.77

2018 $1,775,703 $5.45 $452.58 $678.87 $905.16

2019 $1,802,766 $5.53 $459.48 $689.22 $918.96

2020 $1,830,641 $5.61 $466.58 $699.87 $933.17

10-Year Fiscal Impact By Parcel Quartile

Quartile 1 Quartile 2 Quartile 3 Quartile 4

Parcels 487 487 487 487

% of AV 9% 18% 26% 47%

Median AV $59,250 $120,000 $163,800 $260,000

Residential MV $356,598 $722,021 $986,560 $1,564,380

2007-2010 Tax Rate $5.09 $5.09 $5.09 $5.09

2007-2010 Avg. Levy $301.58 $610.9 $833.74 $1,323.40

2020 Tax Rate $5.69 $5.69 $5.69 $5.69

2020 Levy $332.39 $673.20 $932.02 $1,479.40

Median Levy Variance 2020 v. 2010 $30.81 $62.30 $98.28 $156.00

% Change 2020 Levy v.. Avg. 2007-2010 Levy = 12%

Fiscal Impact Summary

! The new firehouse impact is tax neutral !  It is a good time to borrow – interest rates are low !  The Millwood Fire District tax levy will not exceed the

2007-2010 average until 2014 !  The District anticipates a 1-2% per year increase in tax levy

driven by inflation on the operating budget using reasonable assumptions

!  Retaining an all-volunteer fire department is the most cost effective approach for the District !  Going “combo” would increase taxes by $400,00 - $800,000

based on staffing needs !  Going “paid” would increase taxes by $2.5 - $3.2 million

“Build a new firehouse that the community can be proud of.”

!  A functional, safe building providing a professional

workspace !  Space requirements based on JLN needs assessment study of

the Millwood Fire District using NFPA standards !  Design input from SCN, the nation’s leading firematic consultant !  Millwood Fire Company an equal partner in program and design

development !  Site plan and internal layout emphasizes firematic efficiency

“Build a new firehouse that the community can be proud of.”

!  A building that respects residents’ tax dollars

!  Site plan minimizes work on a challenging property !  High-quality, proven construction !  Honest, straightforward materials and finishes !  Energy efficiency, durability and low maintenance are priorities !  Building designed to retain and attract volunteer manpower (but

allows for conversion should a career force become needed) !  Design plan allows for additional bay – future expansion !  Building designed to beat or meet strict budget parameters

which keep construction “tax neutral”

“Build a new firehouse that the community can be proud of.”

!  A building that shows pride in our volunteer

firefighters !  Distinctive appearance !  Safe, efficient and modern work environment !  Comfortable, practical amenities promoting morale !  New firehouse is a “draw” in a competitive environment for

committed volunteer firefighters !  Improved interior training facilities

!  All-weather bailout training, mass confidence course, flexible classroom space

!  Firehouse reflects our community’s support for all-volunteer MFC Company #1

Questions?

Please share your thoughts!

BoFC PO Box 140

Millwood, NY 10546 [email protected]

Risks to Projections

Volunteer firefighters save money in addition to lives and property

!  NFPA recommends a shift of 6 (2 in/2 out + incident commander and

pump operator) for Millwood’s population density !  Economic demands placed on volunteers living in Millwood may erode

the volunteer base !  The first-need for career/paid firefighters will be daytime drivers !  Once a department goes “career”, pressure to go fully-paid is almost

inevitable

Risks to Projections

Volunteer firefighters save money in addition to lives and property

!  Profile of a full-time career department for Millwood based on NFPA

recommendations: !  One Chief Officer !  Two Assistant Chief Officers !  4 Captain or Lt. Officers !  8 Drivers/Firefighters (assuming Ladder/Rescue and Engine Company) !  24 Firefighters (2 firefighters for Engine ops, 4 firefighters for Ladder/Rescue

per Shift) !  One Administrative Clerk

!  Total 32-40 Employees = $2.5-$3.2 million approx (salary + benefits)