Line Pipe Specification and Procurement

John Piper

John Piper & Associates Pty Ltd [email protected]

Page 2: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Themes 1. The required attributes for line pipe

carrying petroleum products. – What is really needed and why?

2. Technical Procurement Insights – What can go right when buying pipe!

Page 3: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Context & Constraints • Usage Context

– Need efficient energy transport – Minimum Cost – Drives:

• High strength, thin wall pipe operating at high pressure

– X70 – X80 Pipe Grades operating safely at 0.8 design factor.

• Constraints – Pipelines Designed to AS 2885

• Line pipe to API 5L / ISO 3183 + Supplementary Specifications.

Page 4: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

1. Required Pipe Attributes • Integrity

– There shall only be one hole in each pipe, centrally located. • Strength

– Strong enough to allow successful field pressure test. • Coatability

– A corrosion resistant coating must be easily applied. • Constructability

– Length – Handling Robustness – Field Bendability – Weldability

• Serviceability – Resistance to Crack initiation – Resistance to a Running Fracture (Brittle and Ductile) – Fatigue Resistance

Page 5: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Manufactured-in Integrity

– Effective Manufacturing Process Design • Steel Making, Pipe Making, Coating, Transport & Handling

– Process Control – Inspection and Testing

• Steel – Consistent composition – Segregation and inclusion Control

• Pipe – No leak or burst

• Coating: – No Corrosion

• Effective Factory coating • Effective Joint Coating

• The key to line pipe integrity is:

Page 6: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Strength • All pipe can operate at actual design pressure with integrity

– I.E. Mill tested to 85% or 90% SMYS. • Field Pressure test is the worst case service requirement. • At 0.8 Df all pipes will be tested above nameplate strength:

– at 100 to 110% yield strength.

• Engineers need certainty, so this is a dilemma. • They must rely on excess strength supplied by the

manufacturer. • The better the manufacturer, the less excess strength! • Fortunately Strain-aging, triaxiality effects and manufacturing

excess allow success. • Use sophisticated simulation software – PipeStrain. • For coated (strain aged) pipe, we now need to know:

– Shape of the stress-strain response – Strength Distribution

Page 7: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Coatability • A forgotten attribute. • Pipe must be:

– Straight – Clean – No oil, grease, paint, salt, lizards,

super-phosphate!! – Free of surface defects – Pits, gouges,

seams, slivers or hackles • Often a mismatch between pipe mill and

coating plant expectations: – Specify

Page 8: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Constructability • Constructability – design-it-in.

– Length • Long pipe length reduces the number of girth welds – increases productivity.

– Handling Robustness

– Weldability • Weld-out is the critical rate determining step in pipeline construction.

– Shape control – roundness and bevel dimensions are critical – CEq critical for pre-heat free cellulosic welds without HACC

• High D/t ratio results in dents, collapsed ends etc

• Inverted dents are rupture sites – Cold Field Bendability

• High D/t makes pipe hard to bend – mandrel machines may be needed.

Page 9: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Servicability – Resistance to Crack initiation.

• Weld quality in HFERW is an issue – Resistance to a Running Brittle Fracture

• DWTT performance is critical – Problem (inverse fracture) in seamless pipe

– Resistance to a Running Ductile Fracture • Ongoing issues with the Battelle 2 Curve methodology.

– Fatigue Resistance • Applicable only to storage

pipelines – Others experience too few

cycles • Largely wall thickness

dependent, but weld shape in SAW pipe can be important.

Page 10: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

2. Successful Technical Procurement

• Good Pipeline Design

• Comprehensive Specification

• Capable Mill & Coating Plant

• Comprehensive Technical Agreement.

• Process Validation

When we buy pipe we don’t just buy the pipe we buy the way it is made

Com

munication

Page 11: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Why worry?

The Manufacturing Process is complex! Ample opportunity for things to go wrong!

Page 12: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Good Pipeline Design • Avoid Over-specification

– Eliminates capable mills – Complicates technical negotiation – Adds Cost

• Avoid Under-specification – Project failure? – Increases rework – Compromises pipeline integrity – Adds Cost

• Decide minimum requirements before tendering! – Decide on MAOP, Design factor, Pipe Grade, Location

Class. – Wall thickness, corrosion allowance (Light wall, Heavy

wall, No-penetration pipe. – Fracture control plan.

Page 13: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Comprehensive Specification • Content previously discussed! • Don’t assume API 5L compliance • Remember AS2885 requirements go well

beyond API 5L – Fracture Control – Weldabilty

• Emphasize Sensitive issues E.g. – Length range – Pipe Mass/metre – Surface condition – Dimensional control – weld-out

Page 14: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Capable Pipe Mill

• Prequalify Mills – Else Commercial Imperatives have no answer

• Review each mill for actual capability – Seek performance (historical) data

– The Steel supplier is key – Traceability is critical – Is all the equipment needed

present? – Who is in control – subcontractors?

Page 15: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Capable Coating Plant

• Pre-qualify Coaters – Raw material suppliers are critical – Seek Historical Data

• Plant Capability E.g. – Blasting Capacity – Dew-point control – Inspection availability – Bevel protection

• Handling and transport – Custody Transfer Inspection.

Page 16: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Comprehensive Technical Agreement

• Start with Prequalified Pipe & Steel Mills and Coating plants

• Tailor the Spec to the pipe making method and risk profile of the pipeline.

• Address newly revised AS2885 requirements: – Fracture Control – Field Pressure Test Data

• Require a draft Manufacture Procedure Specification (MPS) on tender response

• A Pre-production meeting is vital – Verifies that the messages have been received

Page 17: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Manufacture Surveillance & Verification

• Starts with acceptable historical data • Review steelmaker’s Test Certificates before

production commences • Require first day tests on big jobs. • Tailor 3rd Party Inspection level to risk profile (both

Manufacturer and Project) • Require a Manufacturer’s Data Record (MDR) on

order completion • At minimum, review TCs before shipment • Extra care if a Type II or Type III Field Pressure

Test – Coated Pipe testing!!

Page 18: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Communication • Key to all activities! • Can be difficult – Long communication lines – language barriers.

Page 19: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Conclusion Achieve Great Line Pipe Procurement through: Careful pipeline design Competent, pre-selected Mills Agreed Specification Strong Communication In-mill Verification

Page 20: Line Pipe Specification and Procurement - apia.net.au · Line Pipe Specification and Procurement ... • Process Validation ... – Decide on MAOP, Design factor, Pipe Grade,

Acknowledgement – I thank the EPCRC which has generously sponsored this