lightening strikes twice: california faces a real risk of a second power crisis lake tahoe energy...
TRANSCRIPT
Lightening Strikes Twice: California Faces a Real Risk of A Second Power Crisis
Lake Tahoe Energy Conference
July 30, 2004
CONFIDENTIAL
This report is solely for the use of client personnel. No part of it may be circulated, quoted, or reproduced for distribution outside the client organization without prior written approval from McKinsey & Company. This material was used by McKinsey & Company during an oral presentation; it is not a complete record of the discussion.
Taking The Right Steps To Ensure A Powerful Future
2
5 steps that will ensure a long-term sustainable market for power
THE STATE IS AT RISK OF ANOTHER POWER CRISIS, BUT 5 KEY STEPS WILL HELP TO ENSURE A SUSTAINABLE POWER MARKET
Action needs to be taken today to prevent another energy crisis
1. New generation needs to be built today, given the long lead time, and a mechanism for market-based contracts with utilities needs to be introduced
2. California should introduce mandatory time-of-use metering for all classes of customers
3. New transmission needs to be built and facilitated through a expedited and coordinated approval process by the PUC, ISO, CEC, and FERC
4. A formal capacity market combined with a mandatory planning reserve target (e.g., 15-20%) needs to be in place by 2006
5. The State should re-introduce elements of retail choice, providing an opportunity for large consumers to shop for power
• CEC estimates indicate that operating reserves could drop below typical “emergency” levels if we have a hot summer
• Unfortunately, the CEC’s demand estimates appear low relative to trend and a “high demand case” (i.e., hot summer) may be as likely as a 1-in-5 occurrence
• Taking into account realistic levels of future demand, operating reserves could be extremely tight by 2006 – as low as 5.8% (in a 1-in-5 year demand case)
3
THE STATE’S ENERGY AGENCIES PROJECT A NEAR-TERM RISK OF LOW RESERVE MARGINS IN A HOT YEAR
*Operating reserve margin calculated as (Available Supply – Peak Demand)/(Peak Demand)Source: California Energy Commission (July 8, 2004 update to June 24, 2004 report)
1-in-10 year (hot)
1-in-2 year (average)
CEC ESTIMATES
August 2005 August 2006 August 2007 August 2008
Projected California state operating reserve margin*Percent
11.6
13.212.7
11.611.1
6.7
5.24.7
6.25.1
August 2004
7% target = Stage One emergency level
5% target = Stage Two emergency level
Reserve margins consistently drop beginning in 2006
Demand
4
ENERGY AGENCY FORECASTS OF FUTURE DEMAND ARE OPTIMISTIC COMPARED TO ALTERNATIVE PROJECTIONS
ESTIMATES OF 1-IN-2YEAR PEAK DEMAND
30
35
40
45
50
55
60
65
1982 1985 1988 1991 1994 1997 2000 2003 2006
Peak demand (average weather), after conservationGW
*Regression projection based on historic weather, historic GSP, current GSP projections (5.6%), and average weather**Based on historic CAGR for peak demand growth before including conservation (underlying growth of 1.88% for 1983-2003) and adjusted for expected 2004-2008 conservation in California (provided by CEC)
Source:California Energy Commission; Bureau of Economic Analysis; Economy.com
Regression model*
CEC-July 2004
Trend**
Different models of demand
CEC-May 2003
For 2006, the CEC’s estimate is ~1,000 MW below trend-line estimates and ~2,100 MW below a regression model estimate
5
1
3
4 4
6
1
5
7
6
1 1
93-94
94-95
95-96
96-97
97-98
98-99
99-100
100-101
101-102
102-103
103-104
THE POTENTIAL FOR A “HIGH DEMAND CASE” IS AS HIGH AS A 1-IN-5 EVENT, RATHER THAN JUST A 1-IN-10 EVENT
1 in 2 demand
1 in 5 demand
1 in 10 demand
57,541
59,12159,501
Distribution of average statewide peak temperatureNumber of years observed over past 40 years
*Based on BAEF regression-model estimates of 2006 peak demand
Source: California Energy Commission
Temperature rangeDegrees Fahrenheit
• 8 out of the last 40 years (or 20%), peak temperatures have been 101 degrees or higher
• There is little demand difference, though, between 101 degrees and 101.5 degrees
1 in 10101.5°
1 in 5101°
Potential 2006 peak demand*GW
BASED ONHISTORIC DATA
+3.4%+2.7%
6
9.9
8.7
6.5
5.45.8
3.8
2.7
6.9
TAKING INTO ACCOUNT A DIFFERENT VIEW OF FUTURE DEMAND, THE RISK OF SHORTAGES IS EVEN STARKER
*Operating reserve margin calculated as (Available Supply – Peak Demand)/(Peak Demand)**As much as 2,000 MW would be required to maintain a planning reserve margin of 15% for the 1-in-5 case, which would equate to a 1-in-2 operating reserve of 12.1% and a 1-in-5 operating reserve of 9.1%
Source: California Energy Commission (July 8, 2004 update to June 24, 2004 report); McKinsey analysis
1 in 5 year
1 in 2 year
BAEF ESTIMATE
7% target = Stage One emergency level
• 750 MW of new capacity will be needed before 2006 to maintain a 7% operating reserve under a 1-in-5 case**
• Given the lead time for new construction, permitting and demand side management needs to begin today
August 2005 August 2006 August 2007 August 2008
Projected California state operating reserve margin*Percent
5% target = Stage Two emergency level
Demand
7
THE STATE IS AT RISK OF ANOTHER POWER CRISIS, BUT 5 KEY STEPS WILL HELP TO ENSURE A SUSTAINABLE POWER MARKET
5 steps that will ensure a long-term sustainable market for power
Action needs to be taken today to prevent another energy crisis
1. New generation needs to be built today, given the long lead time, and a mechanism for market-based contracts with utilities needs to be introduced
2. California should introduce mandatory time-of-use metering for all classes of customers
3. New transmission needs to be built and facilitated through a expedited and coordinated approval process by the PUC, ISO, CEC, and FERC
4. A formal capacity market combined with a mandatory planning reserve target (e.g., 15-20%) needs to be in place by 2006
5. The State should re-introduce elements of retail choice, providing an opportunity for large consumers to shop for power
• CEC estimates indicate that operating reserves could drop below typical “emergency” levels if we have a hot summer
• Unfortunately, the CEC’s demand estimates appear low relative to trend and a “high demand case” (i.e., hot summer) may be as likely as a 1-in-5 occurrence
• Taking into account realistic levels of future demand, operating reserves could be extremely tight by 2006 – as low as 5.8% (in a 1-in-5 year demand case)
8
0
10
20
30
40
50
60
70
80
90
100
2003 2005 2007 2009 2011
MARKET-BASED LONG-TERM CONTRACTS SHOULD BE ADOPTED TO FACILITATE GENERATION CONSTRUCTION
… and what market-based prices would look like under the contracts
DWR contract price (2003 average)
California cost of generationDollars per MWh
Capacity payment**
Electricity price under new market-based contracts*
ILLUSTRATIVE
* All-in wholesale electricity price including capacity payment, gas price, energy costs** Assumes 15% ROE, 8% cost of debt, $450/kW CCGT investment cost, 10-year return period
Source: California DWR; NYMEX; McKinsey analysis
How contracts would work…
Who will buy:• In the near term, utilities will be
responsible for signing contracts with the winning bidders, with guaranteed rate recovery of contract costs
Who will build:• Competitive RFP process allowing
utility affiliates or merchant generators to bid
How will contracts be priced:• Will be market based contracts, with
an ROE on capital investment and pass through of variable generation costs– Capacity payment will provide
return on capital investment– Energy payment will be based on a
specified plant efficiency and indexed to natural gas prices
1
9
THERE ARE A NUMBER OF SOURCES OF CAPACITY THAT COULD BE BROUGHT ON LINE BY 2006 IF THE STATE ACTS NOW
*Includes projects under construction delayed more than 24 months from initial planned online date**Assumes most of these plants are 40% complete (as of July 2004)
Source:California Energy Commission; McKinsey analysis
Plants partly constructed , but incomplete due to financing or lack of contracts*
Plants with permits from the CPUC but not under construction
0.5
3.7
6.5
California capacityGigawatts
Estimated time to onlineMonths
Plants that have been mothballed, but could be brought back on line
To ensure new capacity is brought on line by the summer of 2006, the CPUC must act now to ensure that long-term contracts are available to generators to complete existing projects
Steps to bring capacity online
• Relaxed environmental restrictions
• Short term contracts • E.g., Etiwanda
• Mid-long term contracts (5-10 years)
• E.g., Metcalf, Pico
• Long term contracts (5-10 years)
• Extended permit shelf life
• E.g., Tesla, San Joaquin
3-6
8-12**
12-18
1
10
6.6 5.9 5.6 4.7 4.6 3.7 3.7 3.4 3.3 3.1 2.7 2.6 2.3 2.3 2.1 2.0 1.7 1.6 1.4 1.4 1.2 1.1 1.0
7.3
17.4
NE SD MN DC AR LA CO FL MD ME WY OK VT PA IA GA NC UT AK CA AL AZ VA DE NY
CALIFORNIA LAGS OTHER STATES IN ITS DEMAND SAVINGS FROM LOAD MANAGEMENT PROGRAMS
Note:Includes only utilities reporting DSM activities
Source:EIA; state disclosures
Top 25 states in load management DSM savings2002 annual load management savings as percent of (Savings + Peak), MW
774 646 593 558 510 468274 269 264 244 214 208 205 202 200 183 120 103 98 97 94 75 67
970
1,691
FL MN CA GA NC NE ND PA CO OH MD IA DC OK NY AL VA AR IL WI AZ SD IN MO ME
Top 25 states in peak DSM savings from energy efficiency 2002 annual peak savings from energy efficiency, MW
If California achieved levels of Florida, It could see a reduction of demand by ~2 GW in load management alone
Even though California is a leader in energy efficiency, there is room to improve by ~900MW
Florida
California
2
11
TIME OF USE PRICING IN CALIFORNIA IS A DEMAND SIDE MANAGEMENT PROGRAM THAT COULD PAY FOR ITSELF
*Assumes real-time prices will cause large C&I customers to shift 4%-6% and curtail 1%-2% of their load, and time-of-use prices will cause small C&I and residential customers to shift 5%-7% and curtail 9%-11% of their load**Includes one-time real-time meter equipment capital cost and incremental maintenance costs for the remaining 70% of large C&I customers in California without meters and one-time interval meter equipment capital cost for 50% of small C&I and residential customers
Source:1999 CalPX hourly data; interviews; McKinsey analysis
Benefits of time-of-use pricing
• Ratepayers would save approximately $270 million-$380 million annually
• Fewer new peaker plants needed
• Gas demand reduced
• Environmental benefits (NOx reduction, water conservation, etc.)10-year
savings from demand response (load shifting and curtailing*)
Total 10-year savings
Cost of program**
4.8-5.1
1.0-1.72.7-3.8
Californians will benefit in many ways from time-of-use pricing$ Billions
2
12
MULTIPLE AGENCIES HAVE JURISDICTION OVER TRANSMISSION PLANS, SLOWING SITING AND CONSTRUCTION
Source: CEC reports
Required approval
Participating transmission owners
• System impact study
• Facilities studies
Typical time
• 30-60 days
CAISO
CPUC • Certificate of Public Convenience and Necessity (above 200kV)
Evaluation criteria
• Scope and cost of transmission upgrades necessary for interconnection
Shared
Duplicate
• Economic and reliability impact on overall grid
• Environmental, societal and aesthetic factors
• System impact study and facilities studies
• Integrated grid assessment
• Verifies PTO analysis
• Economic and reliability impact on overall grid
• 60-90 days
• 12-30 months
3
13
OTHER STATES WITH RESERVE TARGETS AND CAPACITY MARKETS HAVE SEEN STABLE CAPACITY AND LOW VOLATILITY
*Measured by standard deviation divided by average of monthly wholesale prices. Later of April 1998 or market open through June 2004 (except California, through Jan 2001)**Operating reserve margin calculated as (Available Supply – Peak Demand)/(Peak Demand)
Source:California PX; Alberta Power Pool; PJM ISO; CAMMESA; New England ISO; New York ISO; Platt’s PowerDat
Wholesale electricity price volatility*Percent
Mandated quantity of
reserves
Incentive payments
for capacity
No market constraints
2
16
25
18
20
49
2004 summer reserve margin**Percent
125
71
30
26
40
34
California (2001)
Alberta
ISO-NE
NYISO
PJM
Argentina
4
14
70
30
80
20
RETAIL CHOICE IS SOUGHT AFTER MOST BY LARGE CONSUMERS, BUT BENEFITS ALL CUSTOMER CLASSES
In the UK, large consumers have been the most frequent users of competitive suppliers
All consumers have seen lower electricity bills with market restructuring and retail choice
Case example: United Kingdom
Industrial
Switched
Not switched
Commercial
Switched
Not switched
20
80Residential
Switched
Not switched
Estimated savings per customer**Percent
30.1
33.1
34.1
*Estimated savings in customer bills since privatization/deregulation adjusting for the effects of inflation
Source:EA Electricity Industry Review; EU-EPNG M&A Database, UK Power Market PD Dec. 2001; OFGEM
5
15
IMPLEMENTING A CORE/NON-CORE MARKET STRUCTURE IN CALIFORNIA WILL REQUIRE CAREFUL PLANNING
Concerns
• Controlling the market influence
of a dominant player or players
Key success factors
• Strict market oversight committee and penalties
• Sufficient generation capacity to limit gamingMarket power
Resource adequacy
Environmental issues
Switching behavior
• Ensuring sufficient new capacity built to serve core and non-core customers
• Capacity market mechanism to provide liquidity for trading capacity reserves
• Reserve margin targets (15-20%) required for utility and non-utility suppliers
• Lead time required for long-term planning by utilities
• Reasonable notice period required by non-core customers who plan to switch linked to the time to build new capacity
DWR cost overhang
• Significant stranded costs from DWR long-term power contract obligations
• Equitable sharing of costs between core and non-core market customers, with no ability to avoid costs by shifting to a new supplier
• Mixed results for market mechanisms to manage emissions
• Renewable portfolio standard• Credits for reduced emissions and cleaner
burning technologies
5