Life Cycle Plan (LCP)
Smart Locks Control
Team 05
Team Member:
Vaibhav Vishal Project Manager, Life Cycle Planner,
Trainer
Diego Brandao IV&V, Software Architect, Developer
Zhe Wang Feasibility Analyst, NDI/NCS Acquirer
Mohammadreza Barazesh Software Architect, Developer
Alejandro Monroy Prototyper, Evaluator, Tester, Developer
Hao-Yun Yang Requirements Engineer
Katarzyna Ruszowska Quality Focal Point, UML Modeler,
Developer
Life Cycle Plan (LCP) Template Version x.x
LCP_DCP_F17_T05_V1.1 07/30/12
Version History
Date Author Version Changes made Rationale
10/13/17 Vaibhav Vishal 1.0 Created the original document
with the midterm deliverables
Initial draft for use with phase plan
for foundation, development,
operation.
10/16/17 Zhe Wang 1.1 Create section 6.1. Add
COCOMO II Results
Create future plan for next iteration
Life Cycle Plan (LCP) Template Version x.x
LCP_DCP_F17_T05_V1.1 iv Version Date: 10/16/17
Table of Contents Life Cycle Plan (LCP) ........................................................................................................................................................... i Version History .................................................................................................................................................................... iii Table of Contents ................................................................................................................................................................ iv Table of Tables ..................................................................................................................................................................... v Table of Figures ................................................................................................................................................................... vi
1. Introduction ........................................................................................................................................................ 1
1.1 Purpose of the LCP ............................................................................................................................................ 1
1.2 Status of the LCP ............................................................................................................................................... 1
1.3 Assumptions ....................................................................................................................................................... 1
2. Milestones and Products .................................................................................................................................... 1
2.1 Overall Strategy ................................................................................................................................................. 2
2.2 Project Deliverables ........................................................................................................................................... 2
3. Responsibilities ................................................................................................................................................... 6
3.1 Project-specific stakeholder’s responsibilities ................................................................................................. 6
3.2 Responsibilities by Phase ................................................................................................................................... 6
3.3 Skills .................................................................................................................................................................... 9
4. Approach .......................................................................................................................................................... 11
4.1 Monitoring and Control .................................................................................................................................. 11
4.2 Methods, Tools and Facilities .......................................................................................................................... 11
5. Resources .......................................................................................................................................................... 13 6. Iteration Plan .................................................................................................................................................................. 18
6.1 Plan ........................................................................................................................................................................... 18
6.1.1 Capabilities to be implemented ............................................................................................................................ 18
6.1.2 Capabilities to be tested ........................................................................................................................................ 18
6.1.3 Capabilities not to be tested .................................................................................................................................. 19
6.1.4 CCD Preparation Plans ........................................................................................................................................ 19 6.2 Iteration Assessment ............................................................................................................................................... 19
6.2.1 Capabilities Implemented, Tested, and Results .................................................................................................. 19
6.2.2 Core Capabilities Drive-Through Results ........................................................................................................... 19 6.3 Adherence to Plan ................................................................................................................................................... 19
Life Cycle Plan (LCP) Template Version x.x
LCP_DCP_F17_T05_V1.1 07/30/12
Table of Tables
Table 1: Artifacts Deliverables in Exploration Phase ................................................................................................... 3 Table 2: Artifact deliverable in Exploration Phase ....................................................... Error! Bookmark not defined. Table 3: Artifact deliverable in Valuation Phase .......................................................................................................... 3 Table 4: Artifact deliverable in Foundations Phase ...................................................................................................... 4 Table 5: Artifact deliverable in Development Phase ..................................................................................................... 5 Table 6: Stakeholder's Responsibilities in each phase .................................................................................................. 6 Table 7: COCOMOII Scale Driver .............................................................................................................................. 13 Table 8: COCOMOII Cost Driver ............................................................................................................................... 13 Table 9: Application Count: Screens ........................................................................................................................... 14 Table 10: Application Count: Reports ........................................................................... Error! Bookmark not defined. Table 11: Application Count: 3GL components ............................................................ Error! Bookmark not defined. Table 12: Application Point Parameters ....................................................................... Error! Bookmark not defined. Table 13: Construction iteration capabilities to be implemented ................................................................................ 18 Table 14: Construction iteration capabilities to be tested ........................................................................................... 18 Table 15: Capabilities implemented, tested, and results ............................................................................................. 19
Life Cycle Plan (LCP) Template Version x.x
LCP_DCP_F17_T05_V1.1 07/30/12
Table of Figures
No table of figures entries found.
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 1 Version Date: 10/16/17
1. Introduction
1.1 Purpose of the LCP
Develop Project Plan, track resource spent and estimate cost in each of the incremental phase.
• Define the workflow and identify individual and team responsibility.
• Track and update progress over each iteration of the project.
1.2 Status of the LCP
The status of the LCP is currently at the Foundation Commitment Package version no 1.0. This
is the initial version that is being developed at the end of FCR-ARB presentation.
The major attributes of this package are:
• Foundation phase work
• Development Phase and Operation Phase plan
• Cost Estimation using COCOMO II
1.3 Assumptions
• The duration of the project is 12 weeks in Fall 2017.
• The overall strategy that the team will be following is NDI/NCS.
• The team will be using 7 personnel, 6 on campus students and 1 DEN student.
• The plan is being followed as drawn in MS Project without any delay.
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 2 Version Date: 10/16/17
2. Milestones and Products
2.1 Overall Strategy
The overall strategy that our project is following is of Incremental Development with the tasks
being divided into 4 phases, Exploration, Foundation, Development and Operation.
The ICSM process that we have adopted for the project is NDI/NCS as our system uses
COTS/services like PHP, AngularJS and SQLite.
Exploration Phase
Duration: 08/23/17 – 09/13/17
Concept: Identify operational concept, system and software requirements and,
life cycle plan for the next phase.
Deliverables: Client Meeting Notes
Milestone: Valuation Commitment Review
Strategy: One Incremental Commitment Cycle, Project deliverable strategy,
Win-Win Negotiation Session #1 with the client.
Valuation Phase
Duration: 09/14/17 – 09/29/17
Concept: Identify project requirement, user hierarchy, Constraints and Priorities,
Gather data on project feasibility evidence, prototype the top risk items,
plan and manage project.
Deliverables: Prototype Presentation, Progress Report and Risk/Defects Report
Milestone: Prototype Presentation
Strategy: Risk Analysis Assessment, Core Capabilities Identification,
Win-Win Negotiation Session, Planning Poker
Foundation Phase
Duration: 09/30/17 – 10/15/17
Concept: Project Requirements, Plan and Manage Project, Project Quality,
Develop Prototype, Fix Defects, Develop Software Architecture
Deliverables: Development Commitment Package,
Draft Transition Readiness Review Package
Milestone: Development Commitment Review
Strategy: One Incremental Commitment Cycle, Risk assessment analysis
Development Phase
Duration: 10/16/17 – 12/5/17
Concept: Core Capability Drive, Developing and implementing the full system
with required features, performing unit, Project plan, Training the
client, Transition Readiness Review.
Deliverables: Core Capability Drive-Through Report, Transition Readiness
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 3 Version Date: 10/16/17
Review Package
Milestone: CCD, Transition Readiness Review
Strategy: Development, Testing, Training, Development
Operation Phase
Duration: 12/6/17 – 12/6/17
Concept: Product Deliverable
Deliverables: Final service of the project.
Milestone: Commercial Release of the project
Strategy: Deployment
2.2 Project Deliverables
This section consists of project deliverables in each phase for Smart Locks Control project and
its due date, format and medium.
2.2.1 Exploration Phase
Table 1: Artifacts Deliverables in Exploration Phase
Artifact Due date Format Medium
Client Interaction Report 09/13/2017 .doc, .pdf Soft copy
Win Condition Report 09/16/2017 .pdf Soft copy
Jira Weekly Survey Weekly Monday Jira ticket Jira website
Risk and Defects Report Bi-weekly Wednesday .xlsx Soft copy
Project Plan Bi-weekly Wednesday .mpp Soft copy
Progress Report Bi-weekly Wednesday .xlsx Soft copy
2.2.2 Valuation Phase
Table 2: Artifact deliverable in Valuation Phase
Artifact Due date Format Medium
Top Risk Prototype
Presentation
09/29/2017 .pptx Soft Copy
Jira Weekly Survey Weekly Monday Jira
ticket
Jira website
Risk and Defects
Report
Bi-weekly Wednesday .xlsx Soft copy
Project Plan Bi-weekly Wednesday .mpp Soft copy
Progress Report Bi-weekly Wednesday .xlsx Soft copy
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 4 Version Date: 10/16/17
2.2.3 Foundations Phase
Table 3: Artifact deliverable in Foundations Phase
Artifact Due date Format Medium
Development
Commitment Review
Presentation
10/13/2017 .pptx, .pdf Hard Copy, Soft Copy
Development
Commitment Package
• Operation
Concept
Description
(OCD)
• Life Cycle Plan
(LCP)
• Prototype (PRO)
• System and
Software
Architecture
Description
(SSAD)
• Feasibility
Evidence
Document (FED)
• Test Planning
and Cases (TPC)
10/16/2017 .doc, .pdf Soft Copy
Jira Weekly Survey Weekly Monday Jira ticket Jira website
Risk and Defects Report Bi-weekly
Wednesday
.xlsx Soft copy
Project Plan Bi-weekly
Wednesday
.mpp Soft copy
Progress Report Bi-weekly
Wednesday
.xlsx Soft copy
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 5 Version Date: 10/16/17
2.2.4 Development Phase
Table 4: Artifact deliverable in Development Phase
Artifact Due date Format Medium
Transition Readiness
Review Presentation
11/27/2017 .pptx, .pdf Hard Copy, Soft Copy
Transition Readiness
Review Package
• Operation
Concept
Description
(OCD)
• Life Cycle Plan
(LCP)
• Prototype (PRO)
• System and
Software
Architecture
Description
(SSAD)
• Feasibility
Evidence
Document (FED)
• Test Planning
and Cases (TPC)
12/4/2017 .doc, .pdf Soft Copy
Jira Weekly Survey Weekly Monday Jira ticket Jira website
Risk and Defects Report Bi-weekly
Wednesday
.xlsx Soft copy
Project Plan Bi-weekly
Wednesday
.mpp Soft copy
Progress Report Bi-weekly
Wednesday
.xlsx Soft copy
Technical Debt Report Bi-weekly Friday .doc, .pdf Soft Copy
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 6 Version Date: 10/16/17
3. Responsibilities
3.1 Project-specific stakeholder’s responsibilities
Other than typical stakeholders of CSCI577ab which are client, user, maintainer, developer and
IIV&V, we do not have any project-specific stakeholder.
3.2 Responsibilities by Phase
Table 5: Stakeholder's Responsibilities in each phase
Team Member
/ Role
Primary / Secondary Responsibility
Exploration Valuation Foundations Development-
Construction
Iteration
Development-
Transition
Iteration Name: Igor
Shneyderman
Role: Client,
Maintainer,
Program
Coordinator, Smart
Locks Control
Primary
Responsibility
Explain the
project
deliverables
Secondary
Responsibility
Provide details of
the core features
that need to be
implemented.
Primary
Responsibility
Deliver the Locks
and Hubs
required for the
project
Secondary
Responsibility
Identify any
existing system or
current system he
is using.
Primary
Responsibility
-Discuss new
project model.
-New user
hierarchy
description.
Secondary
Responsibility
Identify target
customers.
Develop
Business Model.
Primary
Responsibility
Review the
progress and final
implemented
product.
Secondary
Responsibility
Identify any
project deliverable
that may become
obsolete.
Primary
Responsibility
Receive Training
for the new
system.
Secondary
Responsibility
Understand how
to maintain the
same.
Name: Vaibhav
Vishal
Role: Project
Manager, Life
Cycle Planner,
Trainer
Primary
Responsibility
-Create and
follow up action
items.
-Schedule
Weekly
meetings.
Secondary
Responsibility
-Record project
progress.
-Identify
responsibilities
and skills.
Primary
Responsibility
-Facilitate client
interaction and
follow up after
win win sessions.
-Create and
follow up action
items.
-Schedule
Weekly meetings.
Secondary
Responsibility
-Record project
progress bi-
weekly.
Primary
Responsibility
-Create and
follow up action
items.
-Facilitate review
of prototype
presentation with
client for new
project
deliverables.
-Schedule
weekly work
schedule.
Secondary
Responsibility
Primary
Responsibility
-Create and follow
up action items.
-Schedule Weekly
work.
- Review the
project with the
client.
Secondary
Responsibility
- Record project
bi-weekly
progress.
- Plan for risk
mitigation and
Primary
Responsibility
-Create and
follow up action
items.
-Schedule
Weekly work.
- Training
session with
client.
Secondary
Responsibility
- Record project
bi-weekly
progress.
- Plan for risk
mitigation and
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 7 Version Date: 10/16/17
-Identify Life
Cycle
Management
Approach.
-Estimation on
project effort and
schedule.
-Assign issues to
team on JIRA and
track progress.
-Record project
bi-weekly
progress.
- Plan for risk
mitigation.
- Prepare the
team for
documentation.
- Assign issues to
team on JIRA
and track
progress.
technical debt
identification.
- Review the
development
iteration.
-Develop
transition plan.
- Assign issues to
team on JIRA and
track progress.
technical debt
identification.
-Develop
Support plan.
- Assign issues to
team on JIRA
and track
progress.
-Review the
transition
iterations.
Name: Mohammadreza Barazesh Role: Software Architect, Operational Concept Engineer, Developer
Primary Responsibility -Analyze the current system Secondary Responsibility Identify Shared Vision
Primary Responsibility - Analyze NDI Interoperability for NDI / NCS project - Assess and evaluate NDI and NCS components Candidates Secondary Responsibility - Explore Alternatives - Identify Objectives, Constraints and Priorities
Primary Responsibility - Assess System Architecture -Review Feasibility evidence for NDI NCS project Secondary Responsibility - Establish New Operational Concept
Primary Responsibility - Specify Architecture Styles, Patterns and Frameworks - Develop and implement backend. -Review the frontend and backend codes and merge the work. Secondary Responsibility - Assess Operational Concept
Primary Responsibility - Review the implemented features. Secondary Responsibility - Verify whether the implemented system satisfies the operational concept.
Name: Alejandro Monroy Role: Software Developer, Prototyper, Evaluator, Tester
Primary Responsibility -Understand the current system
Primary Responsibility - Analyze and understand Smartthings API and the trigger commands on the application - Explore alternatives for developing the frontend. Secondary Responsibility - Analyze and Prioritize Capabilities to Prototype
Primary Responsibility - Develop Frontend Prototype -Make changes as per API call events.
Primary Responsibility - Develop and implement the features in detail. -Fix Defects after review - Integrate Components
Primary Responsibility - Fix defects if any - Upload the system over the client’s server.
Name: Hao-Yun Yang
Primary Responsibility
Primary Responsibility
Primary Responsibility
Primary Responsibility
Primary Responsibility
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 8 Version Date: 10/16/17
Role: Requirements Engineer
- Understand the features of current system
- Capture and Score MMF and Win-conditions - Capture progress of win-win negotiation
- Develop the Database queries for storing user information. Secondary Responsibility - Test the functionality of the Database.
- Verify whether the implemented features address all the win conditions and all the requirements are satisfied. Secondary Responsibility - Check the architecture and the OCD diagrams are according to the system implemented.
- Final Review of implemented features to match with requirements Secondary Responsibility - Verify the fixed defects. -Final round of testing the system.
Name: Diego Brandao Role: IV and V, Software Architect, Developer
Primary Responsibility -Analyze the current system Secondary Responsibility Check the Smartthings API
Primary Responsibility - Analyze Business Case - Explore Alternatives -Assess and Plan to Mitigate Risks Secondary Responsibility Assess and evaluate NDI and NCS components Candidates - Provide recommendation about NDI /NCS components
Primary Responsibility - Develop the API calls for the SmartApp. Secondary Responsibility - Verify and validate the prototype.
Primary Responsibility - Verify and Validate RESTApi Calls and the backend PHP.
Primary Responsibility - Verify and Validate all the implemented features of the website
Name: Zhe Wang Role: Feasibility Analyst, NDI/NCS Acquirer.
Primary Responsibility -Understand the current system Secondary Responsibility Acquire NDI or NCS components
Primary Responsibility - Analyze and Prioritize Capabilities to Prototype - Analyze and understand NDI/NCS required for feature implementation Secondary Responsibility -Explore alternatives for
Primary Responsibility - Develop Prototype -Make changes as per feedback Secondary Responsibility - Provide Feasibility Evidence for NDI NCS project
Primary Responsibility - Develop and implement the features in detail. - Implement the front-end deliverable. -Fix Defects after review - Integrate Components
Primary Responsibility - Fix defects if any - Transition the System
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 9 Version Date: 10/16/17
developing features.
Name: Katarzyna Ruszowska Role: Quality Focal Point, UML Modeler, Tester.
Primary Responsibility - Understand the features of current system
Primary Responsibility - Identify Quality Management Strategy -Identify Configuration Management -Construct Traceability Matrix
Primary Responsibility - Assess Quality Management Strategy Secondary Responsibility - Test the prototype.
Primary Responsibility - Perform unit, integration and regression testing for implemented features.
Primary Responsibility - Final round of regression testing.
3.3 Skills
Team members Role Skills
Vaibhav Vishal Project Manager, Lifecycle Planner, Trainer
Current Skills: Project management, configuration management, COCOMO and MS project Java, HTML5, CSS, MySQL Required Skills: IoT enabled Locks and Smartthings API, COCOMO II
Mohammadreza Barazesh Software Architect, Operational Concept Engineer, Developer
Current Skills: HTML5, CSS, PHP, JavaScript, AngularJS , MySQL, NodeJS Required Skills: IoT enabled Locks and Smartthings API
Alejandro Monroy Software Developer, Prototyper, Evaluator,
Tester
Current Skills: C/C++, SQL, HTML, CSS, JavaScript, PHP, jQuery Required Skills: IoT enabled Locks and Smartthings API
Hao-Yun Yang Requirements Engineer Current Skills: Winbook, QoS, C/C++, IP/ MPLS, Routing and Switching, Automation Testing,
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 10 Version Date: 10/16/17
Required Skills: IoT enabled Locks and Smartthings API
Zhe Wang Feasibility Analyst, NDI/NCS Acquirer
Current Skills : HTML5, CSS, PHP, JavaScript, MySQL Required Skills: IoT enabled Locks and Smartthings API, COCOMO II
Katarzyna Ruszowska Quality Focal Point, UML Modeler, Tester
Current Skills: Quality Management HTML, CSS, JavaScript, Unit Testing Required Skills: IoT enabled Locks and Smartthings API
Diego Brandao IIV and V, Developer, Software Architect
Current Skills: MySQL, HTML, CSS, JavaScript, RESTApi, Visual Paradigm Required Skills: IoT enabled Locks and Smartthings API
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 11 Version Date: 10/16/17
4. Approach
4.1 Monitoring and Control
➢ Bi-Weekly reports: o Project Plan: Plan for the next 2 weeks work and assign jobs to team members. o Progress Report: Track the progress of the project, list third-party
components, and SLOC. o Risk and Defect Report: Analyses top risks, defects, problems and concerns
about project. ➢ Jira: Tracking issue, and project progress. ➢ Win Book: Catch requirements and their priority. Make sure about design
consistency. ➢ Team Meetings: Have team meetings at least 4 days in a week, discuss about project
progress, risks and their mitigation strategy. Discuss the progress on the development of frontend and backend.
➢ Client Meeting: Collect feedback from client often, check requirements consistency.
4.1.1 Closed Loop Feedback Control
➢ Slack: We have created a team group in Slack for team members to discuss project, check schedule, assign work and share documents.
➢ Jira: Assign tasks to team members, check progress of each task, and log the work. ➢ Team meetings: We have team meetings at least 4 times a week. ➢ Google Drive: Upload documents and create shared doc, ppt files that everyone can
work on at the same time.
4.1.2 Reviews
➢ Peer Review: Teammates do review for each other with respect to feature implementation.
➢ Client Review: Collect feedback from client often with respect to functionalities of website.
➢ ARB: Collect feedback from clients and reviewers. Check if we are on the right track,
and check if there are any change in feature requirements and win conditions.
4.2 Methods, Tools and Facilities
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 12 Version Date: 10/16/17
Tools Usage Provider
MS Office Bi-weekly reports and project documents. Microsoft,
USC
Winbook Capture win conditions and prioritize them. USC
Slack Discuss project related work, schedule team meetings and
keep track of the progress and documents.
Slack
Project
Website
Store information about the project, and store all the
documents.
USC
JIRA To log time and effort spent on each task of the project by
different members of the team
USC
COCOMO II Estimate the project cost estimation USC
Smartthings
API
To create event calls to interact with the locks over the
internet.
Samsung
POSTMAN Test the event calls over the web. POSTMAN
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 13 Version Date: 10/16/17
5. Resources
Below is the required information in order to estimate the software cost: - Estimated CSCI577a Effort: 7 team members at 12 hrs/week for 10 weeks - Total estimated effort: 12 hrs/week x 7 members x 10 weeks = 840 hours - Budget information: $0 - Project duration: 12 weeks - Component modules in your development project: Device Status, Lock Management
System, User Control System - Programming language/ Tools used: PHP, AngularJS, NodeJS, REST, HTML, CSS
Table 6: COCOMOII Scale Driver
Scale Driver Value Rationale
Precedentedness Low No existing system and new to SmartThings.
Development Flexibility
High Client amenable with regard to requirements. Some initial requirements removed by client.
Architecture/Risk Resolution
Nominal Majority of the risk can be mitigated by buying information.
Team Cohesion High Meeting almost every day and client is available most of the time.
Process Maturity Nominal Following ICSM guidelines.
Table 7.1: COCOMOII Cost Driver
Cost Driver Value Rationale
RELY High This module is required for the whole system to be
successful.
DATA Nominal Data is easily available based on requirements.
DOCU Nominal As this is completely new module and different from
client’s previous system, client does not have any
previous knowledge on this, it requires documentation
in detail.
CPLX Nominal This module is not complex to develop, as it requires
basic form designing.
RUSE Nominal It has nominal reusability, as form basic template
remains the same.
TIME Nominal There are many forms to develop, time is kept nominal
STOR Nominal It requires good amount of storage as it maintains all the
registration details
PVOL Low No complex hardware/software is required.
ACAP High Team have good understanding about the customer’s
requirements and priorities.
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 14 Version Date: 10/16/17
PCAP Very
High
Developers have basic experience in web development
platforms
PCON Very
High
Maintainer needs to keep updating the information as
and when required.
APEX Nominal Not everyone in team have experience in web
development
LTEX Nominal Team has not worked on PHP before.
PLEX Nominal Not much advance platforms are required to develop
this module.
TOOL Nominal This module needs to be show the user dashboard.
SITE Extra
High
One member is remote who is in Canada. We use Slack,
zoom, hangouts. In addition, we plan to have regular
meeting in person 4 times a week.
Table 7.2: COCOMOII Cost Driver - BackEnd
Cost Driver Value Rationale
RELY High This module is based on PHP and RESTAPI and is
required for the whole system to be successful.
DATA Low Functions and data are present to test.
DOCU Nominal As this is completely new module and different from
client’s previous system, client does not have any
previous knowledge on this, it requires documentation
in detail.
CPLX High This module is complex to develop, as it requires basic
form designing.
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 15 Version Date: 10/16/17
RUSE Nominal It has nominal reusability, as form basic template
remains the same.
TIME Nominal There are many calls to develop, time is kept nominal
STOR Nominal It requires good amount of storage as it maintains all the
registration details
PVOL Nominal No complex hardware/software is required.
ACAP Nominal Team have good understanding about the customer’s
requirements and priorities.
PCAP High Developers have limited experience in backend
RestAPI.
PCON Very
High
Maintainer needs to keep updating the information as
and when required.
APEX High Not everyone in team have experience in RestAPI Calls.
LTEX High Team has not worked on IoT Projects before.
PLEX High Advance platforms are required to develop this module.
TOOL High This module needs to be integrated with Front End and
SmartApp.
SITE Very
High
One member is remote who is in Canada. We use Slack,
zoom, hangouts. In addition, we plan to have regular
meeting in person 4 times a week.
Table 7.3: COCOMOII Cost Driver - SmartApp
Cost Driver Value Rationale
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 16 Version Date: 10/16/17
RELY High The Module used is Samsung Smartthings, which needs
to be understood and tested.
DATA Low This module requires good testing, as there are separate
forms for each course.
DOCU High As this is completely new module and different from
client’s previous system, client does not have any
previous knowledge on this, it requires documentation
in detail.
CPLX High This module is complex to develop, as it requires basic
event calls designing.
RUSE Nominal It has Nominal reusability, as basic application remains
the same.
TIME Nominal Since it is not hard to develop but there are many forms
to develop, time is kept nominal
STOR Nominal It requires good amount of storage as it maintains all the
registration details
PVOL Low No complex hardware/software is required.
ACAP High Team have good understanding about the customer’s
requirements and priorities.
PCAP Nominal Developers have good experience in Android
application required to run the demo application.
PCON Very
High
Maintainer needs to keep updating the information as
and when required.
APEX Very
Low
Basic application is already available.
LTEX Nominal API calls are already present.
PLEX Very
Low
Not much advance platforms are required to develop
this module.
TOOL Low This module needs to be integrated with Front and
BackEnd
SITE Extra
High
One member is remote who is in Canada. We use Slack,
zoom, hangouts. In addition, we plan to have regular
meeting in person 4 times a week.
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 17 Version Date: 10/16/17
COCOMO II Result:
Analysis Results: SLOC: 3045
Estimate Effort: 6.0 (most likely)
Assumptions:
10 of 12 weeks fill COCOMO II Construction phase
(72% of total effort estimate)
120 hrs/person-month
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 18 Version Date: 10/16/17
Member works 12 hrs/week
One team member effort:
12 hrs/week * 10 weeks = 120 hrs
(Factor) * (120 hrs/person-month) * (0.72) = 120 hrs
Thus:
One team member effort = 1.39 CII person-month
Total team effort:
7 * 1.39 person-month = 9.73 CII person-month
6. Iteration Plan
6.1 Plan
6.1.1 Capabilities to be implemented
Table 2: Construction iteration capabilities to be implemented
ID Capability Description Priority Iteration
1 Grouping
Lock
Group the locks and perform actions
at the same time
Medium Development
Phase
2 View Log Allowing administrator and house
manager to view log of locks
activities
High Development
Phase
6.1.2 Capabilities to be tested
Table 3: Construction iteration capabilities to be tested
ID Capability Description Priority Iteration
1 Grouping
Lock
Test grouping the locks and perform
actions at the same time
Medium Development
Phase
2 View Log Build testing logs and test on
administrator and house manager
dashboard to view log of locks
activities
High Development
Phase
Life Cycle Plan (LCP) Version no 1.1
LCP_DCP_F17_T05_V1.1 19 Version Date: 10/16/17
6.1.3 Capabilities not to be tested
Every Capabilities in our project will be tested in the next iteration.
6.1.4 CCD Preparation Plans
- Implement new capabilities
- Meeting with client to discuss core capabilities
- Get feedback from client
- Adjust project due to client’s feedback
- site preparation dry runs
6.2 Iteration Assessment
6.2.1 Capabilities Implemented, Tested, and Results
<< Describes, in brief, the capabilities that were implemented and the test results. The
capabilities implemented and tested do not necessarily need to match the ones listed in section
6.1 because some capabilities may have been pushed to the next iteration. >>
Table 4: Capabilities implemented, tested, and results
ID Capability Test Case Test Results If fail, why?
< ID > < Capability > < TC-XX > Pass/Fail < comments >
…
6.2.2 Core Capabilities Drive-Through Results
<< Briefly summarize the feedback you received from your client(s). You need to be specific
enough to cover the critical capabilities or scenarios that were discussed, demoed, or shown.
Your descriptions MUST, but not limited to, cover the following areas:
• Positive feedbacks
• Improvements needed/suggested
• Changes to‐be considered (Reprioritized capabilities, requirements, GUI, etc.)
• Risks (New risks introduced, risks mitigated, etc.)
Note: Make sure to be specific to the capabilities shown/demonstrated/driven-through.
Simply stating that the clients liked the capabilities is not sufficient. >>
6.3 Adherence to Plan
<< Describe how well the iteration ran according to plan. Was it on budget and on time? Is there
any uncertainty in the Software Development Status? Provide some insight to avoid mistakes for
future iterations. >>