lic cameroon central africa backbone … development bank group cameroon central africa backbone...

40
AFRICAN DEVELOPMENT BANK GROUP CAMEROON CENTRAL AFRICA BACKBONE (CAB) PROJECT CAMEROON COMPONENT OITC DEPARTMENT June 2015 Translated Document Public Disclosure Authorized Public Disclosure Authorized

Upload: letuyen

Post on 24-Mar-2018

217 views

Category:

Documents


1 download

TRANSCRIPT

AFRICAN DEVELOPMENT BANK GROUP

CAMEROON

CENTRAL AFRICA BACKBONE (CAB) PROJECT

CAMEROON COMPONENT

OITC DEPARTMENT

June 2015

Translated Document

P

ub

lic

Dis

clo

sure

Au

tho

rize

d

P

ub

lic

Dis

clo

sure

Au

tho

rize

d

TABLE OF CONTENTS

STRATEGIC THRUST AND RATIONALE ..................................................................................................... 1 1.1. Project Linkages with Country Strategy and Objectives........................................................................... 1 1.2. Rationale for Bank’s Intervention………………………………………………………………………...1 1.3. Donor Coordination ................................................................................................................................ 2

II. PROJECT DESCRIPTION ................................................................................................................. 3 2.1. Project Objectives and Components ....................................................................................................... 3 2.2. Technical Solutions Adopted and Alternatives Explored ......................................................................... 5 2.3. Project Type .............................................................................................................................................. 6 2.4. Estimated Project Costs and Financing Arrangements ............................................................................. 6 2.5. Project Area and Beneficiaries…………………………………………………………………………...8 2.7. Consideration of Bank Group Experience and Lessons Learned in Project Design ................................. 9

III. PROJECT FEASIBILITY ...................................................................................................................10 3.1. Economic and Financial Performance .................................................................................................... 11 3.2. Environmental and Social Impact ........................................................................................................... 11

IV. IMPLEMENTATION .........................................................................................................................13 4.1. Implementation Arrangements…………………………………………………………………………..13 4.2. Procurement Arrangements……………………………………………………………………………...13 4.3. Financial Management and Disbursement Arrangements 14 4.4. Monitoring .............................................................................................................................................. 15 4.5. Governance ............................................................................................................................................. 16 4.6. Sustainability…………………………………………………………………………………………….17 4.7. Risk Management ................................................................................................................................... 18 4.8. Knowledge Building ............................................................................................................................... 18

V. LEGAL INSTRUMENT ..................................................................................................................... 18 5.1. Legal Instrument ..................................................................................................................................... 18 5.2. Conditions Associated with AfDB Intervention ..................................................................................... 18 5.2.1. Conditions Precedent to Effectiveness .................................................................................................... 18 5.2.2. Conditions Precedent to First Disbursement of the Loan ........................................................................ 18 5.2.3. Condition Precedent to First Disbursement of the GEF Grant 19

5.2.4. Other Cconditions ................................................................................................................................... 19 5.2.5. Undertakings ........................................................................................................................................... 19

VI. RECOMMENDATION 19

APPENDIX I: DESCRIPTION OF INSTITUTIONAL SUPPORT AND CAPACITY BUILDING

APPENDIX II: RATIONALE FOR THE LEVEL OF COUNTERPART FINANCING TO THE AFDB ..

PROGRAMME

APPENDIX III: COMPARATIVE SOCIO-ECONOMIC INDICATORS

APPENDIX IV: STATUS OF BANK PORTFOLIO IN CAMEROON AS OF 31 MARCH 2015 APPENDIX

V: MAP OF THE OPTICAL FIBRE INFRASTRUCTURE PROJECT AREA

LIST OF TABLES AND GRAPHS

Table 2.1 - Project Components

Table 2.2 - Alternative Solutions Explored and Reasons for Rejection

Table 2.3: Summary of Estimated Cost by Project Component

Table 2.4: Summary of Cost by Project Expenditure Category

Table 2.5: Project Summary by Source of Financing

Table 2.6: Summary of Project Components by Source of Financing (EUR million)

Table 2.7: Expenditure Schedule by Source of Financing (EUR million)

Table 3.1: Economic and Financial Assessment

Table 3.2: Sensitivity Test

i

Currency Equivalents June 2015

EUR 1 = CFAF 655.96

UA 1 = EUR 1.27

Fiscal Year

1 January - 31 December

ABBREVIATIONS AND ACRONYMS

ADF African Development Fund

AFD French Development Agency

AfDB African Development Bank

ANTIC National ICT Agency

ART Telecommunications Regulatory Authority

CAB Central Africa Backbone

CAMPOST Cameroon Postal Services

CAR Central African Republic

CEAC Centre for Education and Community Action

CEMAC Economic and Monetary Community of Central Africa

CFAF Franc of the Financial Community of Africa

CPF Women's Promotion Centre

CSIRT Computer Security for Incident Response Team

CSP Country Strategy Paper

DAA Sub-Divisional Delegation of Agriculture

DIR Department of Infrastructure and Access Networks

DPU Declaration of Public Utility

ECCAS Economic Community of Central African States

EIRR Economic Internal Rate of Return

ENSPT National School of Post and Telecommunications

ESMP Environmental and Social Management Plan

EU European Union

FO Optical Fibre

GDP Gross Domestic Product

GEF Global Environment Fund

GESP Growth and Employment Strategy Paper

GHG Greenhouse Gas

HDPE High Density Polyethylene

ICB International Competitive Bidding

ICT Information and Communication Technology

IsDB Islamic Development Bank

ITU International Telecommunication Union

JICA Japan International Cooperation Agency

LTS Long Term Strategy

MCIS Market and Climate Information System

MINADER Ministry of Agriculture and Rural Development

MINAS Ministry of Social Affairs

MINEPAT Ministry of Economy, Planning and Regional Development

MINEPDED Ministry of Environment, Nature Conservation and Sustainable Development

MINFI Ministry of Finance

MINPOSTEL Ministry of Post and Telecommunications

ii

MINPROFF Ministry for the Promotion of Women and the Family

MINTP Ministry of Public Works

MPC Multi-partner Committee

NCB National Competitive Bidding

NEPAD New Partnership for Africa's Development

NIS National Institute of Statistics

NPV Net Present Value

PAP Project Affected Person

PCN Project Concept Note

PCU Project Coordination Unit

PIDA Programme for Infrastructure Development in Africa

PIU Project Implementation Unit

PKI Public Key Infrastructure

PRSP Poverty Reduction Strategy Paper

PVC Polyvinyl Chloride

RISP Regional Integration Strategy Paper

STF Special Telecommunications Fund

TCP Multipurpose Community Tele-centre

TFP Technical and Financial Partners

WB World Bank

iii

PROJECT INFORMATION SHEET

Client Information

Borrower : REPUBLIC OF CAMEROON

Project Name : CENTRAL AFRICA BACKBONE (CAB) PROJECT –

CAMEROON COMPONENT

Project Location : CENTRE, EAST, NORTH-WEST, SOUTH AND SOUTH-

WEST REGIONS OF CAMEROON

Executing Agency : MINISTRY OF POST AND TELECOMMUNICATIONS

(MINPOSTEL)

CAB-CAMEROON PROJECT IMPLEMENTATION UNIT

(CAB-CAMEROON/PIU)

1. Financing Plan

Source Amount in

CFAF million

Amount in

EUR million

Amount in

UA million

Amount in

USD million

Instrument

AfDB 24 470 37.304 29.374 41.034 Project Loan

GEF 1 089 1.660 1.307 1.726 Grant

GOVERNMENT OF

CAMEROON 4 872

7.427 5.848 8.170

Public Investment Budget

TOTAL 30 372 46.301 36.458 50.930

2. Key AfDB Financial Information

Loan currency: Euro (EUR)

Loan interest type: Floating (EURIBOR)

Interest rate margin: 60 basis points (bp) + Bank financing margin1

Commitment fee: N/A

Other costs: N/A

Maturity: Six-monthly

Maturity: 20 years

Grace period 60 months

NPV (baseline scenario): EUR 135.9 million

FIRR (baseline scenario) : 19.79%

EIRR (baseline scenario) : 34.14%

1 The financing margin corresponds to the cost of the Bank loan calculated twice a year.

iv

3. Duration – Milestones (expected)

Activities (month, year)

Concept Note approval March 2015

Project approval July 2015

Effectiveness November 2015

Last disbursement December 2019

Completion June 2020

Last reimbursement of AfDB loan December 2035

v

EXECUTIVE SUMMARY

1. Project overview: Building on the objectives set for the Information Technology and

Communication (ICT) sector by the Growth and Employment Strategy Paper (GESP), as well

as on available ICT and other sector strategies, the Government requested the Bank to finance

the national component of the CAB project involving the laying of 916 km of optical fibre

cables comprising approximately five priority links. The project also envisages the

implementation of a number of ICT applications and services (e-Post, e-Banking, Markets and

Climate Information System, etc.), and institutional support relating, among others, to

feasibility studies for the preparation of the next phase of the project, the setting up of an Optical

Fibre Skills Development Centre at ENSPT and support for women’s empowerment.

MINPOSTEL is the project’s executing agency. The project implementation will span four

years. The total project cost is estimated at UA 36.458 million. The Bank will intervene through

the AfDB window to the tune of UA 29.374 million. Other co-financiers are the GEF with a

grant of UA 1.307 million and the Republic of Cameroon whose contribution stands at UA

5.848 million.

2. Needs Assessment: In addition to its regional focus, the project aims to complete the

missing links in the national optical fibre backbone. The project will extend the coverage of the

national optical fibre network in this densely populated region as well as the Cameroon’s

borders with Congo, Nigeria and Central African Republic (CAR). These links with

neighbouring countries (especially CAR) will offer them an alternative service for international

traffic through underwater cables with landfall points in Cameroon. Thus, the costs of

international connectivity should be reduced by the introduction of these new international

outlets. The project also enables Cameroon to take advantage of the extension of its national

optical fibre backbone to modernize the banking and postal sectors with the introduction of e-

Banking and the adoption of hybrid mail by CAMPOST – hence the inclusion of the project in

Cameroon’s new Country Strategy Paper (CSP) for 2015-2019.

3. Bank’s value-added: The Bank’s value-added stems from the experience garnered

through exchanges with countries since the project was initiated in 2007. In coordination with

the World Bank, the Bank has provided substantial resources for the financing of studies on the

regional CAB project, while continuing exchanges with countries involved ever since. The

Bank’s intervention also allows Cameroon to carry out these major infrastructure projects,

particularly its interconnections with neighbouring countries, while complying with

international norms and standards, in order to avoid possible risks of defects that may seriously

undermine the economic spinoffs of the project and its reasonable financing costs.

4. Knowledge building: The project will offer an opportunity to improve knowledge in

the area of national optical fibre infrastructure. Provisions have been made to prepare the first

Broadband Infrastructure Development Master Plan that will benefit all stakeholders in the

sector (MINPOSTEL, ART, CAMTEL, private operators, etc.). This Plan could be used by

ART, among others, by deriving from the outcomes of the study on the profitability thresholds

of optical fibre deployment, the appropriate tools for regulating the broadband infrastructure

sector. Indeed, illegal trenching causes serious damage to costly road infrastructures, some of

which were, incidentally, financed by the Bank.

vi

RESULTS-BASED LOGICAL FRAMEWORK

REPUBLIC OF CAMEROON

Country and Project Name: CAMEROON – Central Africa Backbone (CAB) Project – Cameroon Component Project Goal: Contribute to the diversification of the economy by fostering the emergence of a digital economy in Cameroon

Results Chain Performance Indicators

Means of Verification Risks/Mitigation Measures Indicator (including CSI) Baseline Situation Target

Imp

act

Contribute to the diversification of Cameroonian's economy, breaking the

digital isolation of the project target

areas and regional integration through optical fibre infrastructure enabling

access to neighbouring countries

(Congo, Nigeria and RCA)

Percentage of ICT contribution to the

tertiary sector

Number of potential international outlets

53.5% in 2013 (source

MINFI)

1

60% (at least) in 2019

4

Reports and

Statistics from MINPOSTEL, ART,

etc.

ITU, ECCAS and CEMAC reports

Ou

tco

mes

Outcome 1: Improved access of the

population, government services and

businesses to telecommunications / ICT services

Penetration of Internet services

Tele-density (mobile)

6% (2013)

76% (2014)

20% (2019)

90% (2019)

Reports and Statistics

from MINPOSTEL,

ART, etc. Reports from

MINADER,

CAMPOST, etc. Project impact

assessments

produced by the PCU/CAB-

Cameroon

Reports by ITU, ECCAS, CEMAC,

etc.

Risks: (i) Non-compliance with

commitments regarding the laying of

optical fibre cables; (ii) no impact on prices; (iii) premature degradation of the

optical fibre due to lack of maintenance

(iv) lack of maintenance and upgradeability of the various applications

installed.

Mitigation measures: (i) Government's

commitment to implement the guidelines of the International Telecommunication

Union (ITU); (ii) technical assistance for

ART; (iii) commitment by CAMTEL and CAMPOST to ensuring the sustainability

of infrastructure put in place.

Outcome 2: Reduced cost of access to telecommunications and Internet

services

Internet access costs

Improvement of the ICT legal and regulatory

framework

Rates for Internet services

2015: Dissatisfaction of

private operators with the

implementation of the “open access” principle

50 % reduction (at least) in 2019 in the price of Internet

subscription

2019: Greater compliance by

private operators with

conditions of access to shared optical fibre

infrastructure

Outcome 3: Contribution to the social,

economic and financial inclusion of residents of the country's hinterland

Number of people having access to banking

services thanks to e-Banking

Number of farmers / stockbreeders with

access to market and weather information

Number of people benefiting from solar

electric terminal systems

0 (2015)

0 (2015)

0 (2015)

17 000 new customers

(2019)

20 000 (2019)

20 000 (2019)

vii

Outcome 4: Improved availability of training and access to ICT in institutions

of higher learning

Number of persons entering the Optical Fibre Skills Development Centre at ENSPT

for initial and continuing training

Number of students with Internet access on

campuses of Yaoundé I, Bamenda and

Maroua Universities

0 (2015)

0 (2015)

1345 (2019) -> Initial (1060 in Yaoundé and Buea 285),

50% of them women

500 (2019) -> Continuing (300 in Yaoundé and Buea

200), 50% of them women

65 000 students (2019)

Ou

tpu

ts

Output 1: Optical fibre infrastructure

Optical fibre connections built

Technical sites built

Linear distance of optical fibre

Number of technical sites along project links

≈ 6.000 km (2015)

0 (2015)

≈ 7 000 km (2019) at least

7 (2019)

PCU / CAB-

Cameroon progress

reports

Control mission reports

Project supervision

reports Project completion

reports.

Risks: (i) Slow pace and lack of

transparency in the procurement process;

(ii) escalation of the cost of works; (iii)

non-compliance with technical and functional specifications in the context of

various project applications; (iv) delays in

compensation of project-affected persons (PAPs) along the Batouri-Bertoua-

Kentzou road section.

Mitigation measures: (i) Close cooperation between MINPOSTEL and

the Ministry in charge of Public

Procurement; (ii) consideration of physical contingencies in the project; (iii)

PCU/CAB capacity building; (iv)

prioritization of the compensation of PAPs in the national counterpart funding.

Output 2: ICT applications

andservices

ICT applications (e-Post, e-Banking, Market and Climate

Information System) installed

Number of new ICT applications developed

and put in operation

0 (2015)

4 (2019)

Output 3: Institution and capacity

building

Development and preservation of optical

fibre infrastructure

Conduct of feasibility studies to prepare the

next phase of the project: (i) laying of optical

fibre cables along the Foumban-Tibati-Ngaoundéré-Tignère, Bamenda-Fundong-

Wum, Ngaoundéré-Touboro road sections;

(ii) a CSIRT+ PKI project; (iii) a technology park project (including a Datacentre); (iv) an

integrated electronic system for the

identification of persons (SIGIEP); and (v) a mobile financial service development project

Number of TCP, CEAC / DAA and Women’s Promotion Centres (CPF)

equipped

Number of reference optical fibre training

centres

Number of students awarded doctoral

scholarships at ENSPT

2015: Lack of strategic

framework for the

development of the national

optical fibre backbone

2015: Absence of

foundations for a large-scale

deployment of ICT applications/services

0 (2015)

0 (2015)

0 (2015)

2019: Strategic decision-

making documents prepared

(Master Plan and study on

profitability thresholds)

2019: Feasibility studies on

the delivery of electronic

administrative services to the public and private sector

52 (2019)

2 (2019) on the ENSPT sites

in Yaoundé and Buea

4 (including 3 female

students) during the project's

lifespan

PCU/CAB-

Cameroon progress

reports

Control mission

reports Project supervision

reports

ENSPT monitoring and evaluation report

UN Women reports

MINPROFF statistics

Project Completion

Reports.

viii

Output 4: Project management

Support for CPU/CAB-Cameroon;

Monitoring and evaluation of the technical implementation as well as

the socio-economic and

environmental impacts; Project accounting and financial

audit;

Project technical audit.

Audit reports Monitoring and evaluation reports of the

various aspects of the project

Technical audit reports

2015: No report

2019: At least 4 audit reports, at least 3 monitoring

and evaluation reports and 1

technical audit produced, etc.

Progress reports of PCU/CAB-

Cameroon

Control mission reports

Project supervision

reports Project completion

reports.

Key

Acti

vit

ies

Components Resources

A. Optical fibre infrastructure

B. ICT applications and services C. Institutional support and capacity building

D. Project management

Components In EUR million

Optical fibre infrastructure (Component A) 23.622 ICT applications and services (Component B) 9.158 Institutional support and capacity building

(Component C) 6.916

Project management (Component D) 2.316

Base cost 42.012

Physical contingencies 2.941

Financial contingencies 1.348

Total project cost 46.301

ix

PROJECT IMPLEMENTATION SCHEDULE

1

MANAGEMENT’S REPORT AND RECOMMENDATION TO THE BOARDS OF

DIRECTORS ON A PROPOSAL TO GRANT A FEM GRANT OF USD 1 726 484 AND

AN ADB LOAN OF EUR 37 304 000 TO THE REPUBLIC OF CAMEROON FOR

FINANCING THE CENTRAL AFRICA BACKBONE (CAB) PROJECT - CAMEROON

COMPONENT

I. STRATEGIC THRUST AND RATIONALE

1.1 Project Linkages with National Strategy and Objective

1.1.1. Cameroon potentially occupies a strategic position for ICT development in Central

Africa in view of the underwater cables (SAT3, WACS and ACE) that have landfall points on

its coast and which could provide international data connectivity for the entire sub-region. Yet,

of all its neighbours, the country has only one optical fibre link with Chad. Moreover, its own

use of connectivity for data is still limited. In addition to the low Internet penetration rate, with

only 6% of the population enjoying Internet access, the online service industry is barely starting

to emerge.

1.1.2. Given the significant needs in terms of regional and national connectivity, and the

catalytic effect of ICT in all sectors of the country, it was agreed that the Bank’s intervention

will follow the multi-phased project implementation method. The project is consistent with the

Growth and Employment Strategy Paper (GESP), which places the challenge of growth and job

creation at the centre of Government’s poverty reduction efforts, and is now the overall

framework for the action of public authorities over the period 2010-2020. The recent adoption

of the new telecommunications and ICT development strategy is in line with GESP and aims

to provide widespread ICT access to the Cameroonian population. The major objective of this

strategy is to increase the supply of high-quality broadband electronic communication services

at competitive prices. The project is also consistent with the Growth Acceleration Emergency

Plan launched in December 2014 by the country's authorities, which aims to boost the

implementation of GESP meant to transform Cameroon into an emerging economy by 2035.

Lastly, it aligns with Pillar I of Cameroon’s 2015-2019 CSP and the Regional Integration

Strategy Paper (RISP) 2011-2015 for the Central African Region. It also contains positive

externalities that will strengthen sector governance (Pillar II of the said CSP).

1.1.3. Beyond the strictly infrastructural aspects, this project is intended to help Cameroon

develop a genuine digital economy in order to ultimately create enough jobs by improving

factors of production. The introduction of the e-Post and e-Banking project for CAMPOST will

complement the optical fibre system through new electronic products and services. In addition,

the implementation of the technology park, the feasibility study of which is included in this

project with a view to the implementation of the second CAB project, will help to create an ICT

cluster housing in one place all players in the technology value chain, i.e. innovative companies

(start-ups in particular), training institutions, research laboratories, etc.

1.2 Rationale for Bank’s Intervention

1.2.1. The project aligns with the Bank’s Ten-Year Strategy (2013-2022), particularly the

two pillars on infrastructure development and promotion of regional integration as well as the

ICT Sector Strategy. It also addresses the issue of green growth and inclusive development

(especially gender) through the following initiatives: (i) capacity building of various

community centres (TCP, CEAC and CPF); (ii) implementation of a mobile banking (e-

banking) system; (iii) establishment of a Markets and Climate Information System (MCIS); (iv)

women's empowerment activities; and (v) monitoring of project environmental and social

2

impacts. The Bank’s environmental and social safeguards requirements will guide the

implementation of all these activities.

1.2.2. The Bank’s intervention in this project is justified by the fact that broadband

connectivity is a key component for the development, adoption and use of ICT in various

economic activities, with a view to promoting social and economic inclusion in the country.

Based on several studies conducted notably by the World Bank in 2010 in Africa, it is now

proven that a 10% increase in the number of Internet broadband connections will lead, among

others, to a 1.3% boost in economic growth. The ICT sector has already created 65 000 direct

jobs in Cameroon and contributes an estimated 4% to gross domestic product (GDP). It could

be even more beneficial provided that the infrastructure and application prerequisites are in

place, since it already makes up at least 50% of the tertiary sector.

1.2.3. It should also be noted that the construction of the CAB-Cameroon optical fibre link

project aligns seamlessly with Bank-financed road projects in Cameroon, among others. In

constructing the roads, duct-laying has systematically been required since 2008. All that is

required is to procure the optical fibre cables for the roads involved in the project, given that

most of the costs will be borne by the civil engineering component. This is the case with the

Kumba-Mamfe road (187 km), Mamfe-Ekok road (82 km) and most of the Sangmelima-

Djoum-Mintom-Ntam road (266 km) under this project. These links with neighbouring

countries, particularly Nigeria, will induce competition between the various underwater cables

to which Cameroon will be connected and will result, in turn, in a sharp drop in prices for

international capacity. This will then have an impact on end-user access costs.

1.3 Donor Coordination

1.3.1. The Ministry of Economy, Planning and Regional Development (MINEPAT) is

responsible for coordinating aid and cooperation with donors at national level. The Ministry

includes the Department of Regional Integration (DIR), the focal point of the Bank's economic

and technical cooperation. With regard to technical and financial partners (TFPs), the Multi-

Partner Committee (CMP) monitoring GESP, which was set up in June 2001, is a platform for

dialogue and exchange on all key development issues in Cameroon. Technical and thematic

sub-committees dedicated to the alignment and harmonization agenda actively support this

structure. The Bank is a member of all these thematic and sector-based groups and, with the

World Bank, participates in IMF review missions in Cameroon. The Bank was leader of the

MPC Sector Committee on Public Finance from 2008 to 2014, before passing the mantle to the

European Union.

1.3.2. Regarding the ICT sector, in particular, there is a forum for constant dialogue between

the World Bank and the Bank, in consultation with MINPOSTEL. The discussions have been

expanded to JICA and the Islamic Development Bank (IsDB), which would like to participate

in financing the next project. Moreover, the World Bank would like to continue financing the

CAB project in Cameroon beyond March 2016 (end date of the current funding) and is therefore

willing to work closely with the Bank for its implementation, particularly through a joint

PCU/CAB-Cameroon, shared documents and information, joint meetings and mutual

monitoring of the progress of actions undertaken.

3

1.3.3. The Bank has acquired extensive experience through its exchange with all countries

of the sub-region since the project was initiated in 2007. In coordination with the World Bank,

the Bank allocated substantial resources to finance studies on the initial regional CAB project.

Its intervention also allows Cameroon to carry out these major infrastructure projects,

particularly its interconnections with neighbouring countries, while complying with

international norms and standards, in order to avoid possible risks of defects that could seriously

undermine the economic spinoffs of the project and its reasonable financing costs.

1.3.4. During the project identification, preparation and appraisal missions, the Bank team

held discussions with these key TFPs (WB, IsDB and JICA). The discussions helped to

harmonize views concerning specific project components and the joint financing of the Project

Coordination Unit (PCU/CAB Cameroon) with the World Bank. All these partners have

acknowledged the importance and relevance of the project, which is fully consistent with the

operation of other partners. This explains the interest shown by the IsDB and JICA in co-

financing the subsequent project.

II. PROJECT DESCRIPTION

2.1. Project Objectives and Components

2.1.1 The overall objective of this project is to contribute to reduce the impact of the high

cost of telecommunications/ICT on the business climate in the sub-region, create all forms of

jobs and expand the production of goods and services, thus helping to reduce poverty.

2.1.2 The construction of optical fibre infrastructure will help to reduce the cost of accessing

high-quality ICT services. It will also generate additional resources for Cameroon not only

through induced economic activities within the country itself, but also through taxes on data

streams passing through the international underwater cables with landfall points in Cameroon.

2.1.3 In terms of infrastructure, the project will: (i) extend the national optical fibre

backbone on five major sections (missing links and interconnection with neighbouring

countries) for about 916 km of fibre; (ii) provide solar office automation and IT equipment for

Multi-purpose Community Tele-Centres (TCPs); Education and Community Action Centres

(CEAC) and Women Promotion Centres (CPF) with the deployment of photovoltaic solar

panels, thanks to additional funding from the Global Environment Facility (GEF); and (iii)

support to institutions of higher learning (ENSPT, Universities of Yaoundé I, Bamenda and

Maroua).

2.1.4 In terms of legal and regulatory framework of the ICT sector, the Government of

Cameroon decided to grant CAMTEL (the traditional national operator), an exclusive

concession on intercity connections which include the five links covered by this project.

However, it should be noted that CAMTEL has the obligation to provide the capacities required

by other operators throughout the national optical fibre backbone, under the strict control of the

Telecommunications Regulatory Authority (ART), a public administrative establishment

endowed with legal personality and financial autonomy set up by Law No. 2010/013 of 21

December 2010. Conversely, operators have the right to deploy their own infrastructure for

urban links as they wish.

4

2.1.5 The project will support the regulation of the wholesale data market under the

responsibility of the Telecommunications Regulatory Authority (ART), by fully enforcing the

"open access" principle on each optical fibre link financed by the Bank in order to ensure

minimal competitive conditions on access costs, to the benefit of Cameroon’s end users. In this

regard, a specific provision has been made concerning ART, which involves preparing an

economic model fixing the cost of access to national and international connectivity, with a view

to lifting barriers to entry into the optical fibre segment. All these activities will be part and

parcel of activities to extend TIC sector reforms funded by the World Bank within the

framework of the CAB project.

2.1.6 In addition, and through its “ICT Applications and Services” component, the project

also envisages the implementation of several ICT applications to support the diversification of

the Cameroon’s economy. Currently, the bank access rate in Cameroon is quite low (less than

10%, even with the inclusion of microfinance institutions), not forgetting the significant

productivity gains that the postal sector can derive from ICT applications. Thus, it is expected

that the implementation of CAMPOST’s e-Post and e-Banking projects will strengthen the

financial inclusion of rural residents, particularly through the networking of post offices

nationwide. It is worth noting that since end-2013, CAMPOST has a modern, high-capacity

Datacentre which will serve as a hub for the development of postal e-services.

2.1.7 The project also plans to support Cameroon Government’s rural development efforts

through the establishment of a Market and Climate Information System (MCIS) for the Ministry

of Agriculture and Rural Development (MINADER) aimed at enabling farmers and

stockbreeders to access the prices of agricultural products and livestock, as well as weather

forecasts, through the TCP and CEAC. This system will ultimately lead to a significant

reduction in post-harvest loss of agricultural production in Cameroon estimated at 25% (source:

MINADER) through the combined effects of farmer education and needs/production balance.

2.1.8 The project also includes several feasibility studies relating, among others, to ICT

infrastructure and applications/services that will be considered as part of subsequent (second)

CAB project, preparation of which should start by end-2017 using a programme-based

approach. Thus: (i) studies are planned on the Foumban-Tibati-Tignère-Ngaoundéré, Bamenda-

Fundong-Wum, Ngaoundéré-Touboro road links, for the extension of the existing backbone;

(ii) a CSIRT+ PKI; (iii) a technology park (including a Datacentre); (iv) an integrated electronic

system for the identification of persons (SIGIEP); and (v) the development of mobile financial

services in Cameroon. The project also envisages a component to build the capacity of key

national stakeholders and provide support for the Project Coordination Unit (PCU/ CAB). To

attain these objectives, project activities have been grouped into the four components

summarized in the table below:

5

Table 2.1

Project Components

No.

Component Name

Description

A OPTICAL FIBRE

INFRASTRUCTURE

(EUR 23.622 million)

A.1 - Optical fibre infrastructure execution works,

A.2 - Monitoring and evaluation of impacts and population awareness,

A.3 - Control and supervision of optical fibre works.

B ICT APPLICATIONS

AND SERVICES

(EUR 9.158 million)

B.1 - Establishment of e-post and e-banking, B.2 - Establishment of a Market and Climate Information System (MCIS).

C INSTITUTIONAL

SUPPORT AND

CAPACITY BUILDING (EUR 6.916 million)

C.1 - Studies, C.2 - Technical assistance - Telecommunications Regulatory Board (ART),

C.3 - Capacity-building for TCP, ECAC and CPF,

C.4 - Support for higher education institutions (ENSPT, Yaoundé I, Bamenda and Maroua Universities), C.5 - Support for women's empowerment.

D PROJECT

MANAGEMENT

(EUR 2.316 million)

D.1 - Support for PCU/CAB-Cameroon,

D.2 - Support for operation of various committees, D.3 - Technical accounting and financial audits.

2.2 Technical Solutions Adopted and Alternatives Explored

2.2.1 This project involves the installation and commissioning of 916 km of optical fibre

cables, also comprising active equipment as well as power and cooling systems. It is made up

of five sections, namely Kumba-Mamfe, Mamfe-Ekok, Bamenda-Ndop-Kumbo, Bertoua-

Batouri-Kentzou and Sangmélima-Djoum-Mintom-Ntam, located in the South-West, North-

West, East and South Regions, respectively. These sections are part of the critical links of the

national optical fibre backbone (with terminals to neighbouring countries) that Cameroon

intends to cover with a view to rapidly extending its network to reach 20 000 km of optical fibre

by 2035.

2.2.2 Currently, there are two main technical alternatives for the deployment of optical fibre:

satellite or microwave links. The use of satellite links suffers from the combined effect of

prevailing high access cost and service quality that is far below that offered by optical fibre, not

to mention the capacity limitations inherent in the technologies used (even the latest). Even with

the development of new satellite facilities (for instance O3b) using low orbit satellites, the cost

difference is significant. In fact, satellite remains a redundancy technology, allowing operators

to compensate for the unavailability (due to technical damage, especially) of optical fibre, but

at operating costs two to ten times higher than the latter. In short, satellite is not a sustainable

alternative compared to optical fibre.

2.2.3 For its part, microwave links allow extension broadband service coverage, particularly

to underserved areas. However, while useful for point-to-point traffic (connection of base

stations and collection networks), they cannot carry the huge amount of data expected to be

transmitted through an optical fibre backbone. The migration of mobile operators in Cameroon

to 3G and even 4G in the near future will induce significant increase in the level of Internet

access and the bandwidth required. To this end, optical fibre is the only option that meets all

these requirements (particularly to serve as support for the potential international traffic of

neighbouring countries).

2.2.4 Furthermore, it should be noted that, based on technical studies conducted, the manual

laying of fibre (as opposed to the mechanical method) was selected for this project. This option

(despite its slightly higher cost compared with the mechanical method) induces beneficial

effects in terms of revenue generation for the population concerned and indirect support under

the project’s population awareness component.

6

Table 2.2

Alternative Solutions Explored and Reasons for Rejection Alternative Solution Brief Description Reasons for Rejection

Mechanized laying of optical

fibre cables

Using slicers in digging ducts along the five

sections identified in this project phase.

Quality risks related to the non-mastery of the

various reliefs concerned, reason for which this

method would not be easy to use. In addition,

manual laying generates income for labour from

the localities crossed, making the project

favourable to local residents.

Supply of dark fibre (without

active equipment)

In this case, it means supplying only optical

fibre cables without the transmission equipment.

Solution chosen by CAMTEL because it would

be operational from the first day of commissioning of the installed links.

Using CAMPOST data centre to

host ICT applications and

services planned under the project.

This option would mean using the CAMPOST

Datacentre in its current state, for all planned

ICT applications (hybrid mail, EDM and e-Banking).

This solution is not technically viable because

current capacity is not even enough to meet

intrinsic needs in CAMPOST. Moreover, there are plans to extend the same Datacentre in order

to implement the e-Post and e-Banking project.

2.3 Project Type

The AfDB loan will help to finance most of the project with the notable exception of the

capacity building of the Multi-purpose Community Tele-centre (TCP), the Education and

Community Action Centre (CEAC) and the Women's Promotion Centre (CPF) which will be

financed with the GEF grant. The investments to be financed are specifically defined.

Therefore, the loan was deemed considered appropriate as an instrument for Bank intervention

in the project. As comparison, World Bank interventions in the ICT sector in Cameroon are

funded through this type of operation (investment projects).

2.4 Estimated project costs and financing arrangements

2.4.1 The project cost net of taxes and customs duties amounts to EUR 46,301 million (UA

36,458 million). The provision for physical contingencies is 7% of the base cost. The provision

for price escalation is equal to 3% of the base cost plus physical contingencies. This cost was

established on the basis of feasibility studies carried out, exchanges with other partners and

similar contracts recently implemented or being implemented by CAMTEL. The equivalent of

the taxes and customs duties calculated within the project framework and considered as

counterpart funding, will supplement the financing provided by the GEF and earmarked for the

strengthening of TCP, CEAC and CPF (procurement of solar and IT equipment).

The summary of estimated cost by project component is provided in the table below:

Table2.3

Summary of Estimated Cost by Project Component

Components

In EUR million In UA million

F.E. L.C. Total F.C. L.C. Total

A. OPTICAL FIBRE CABLE

INFRASTRUCTURE 18.898 4.724 23.622 14.880 3.720 18.600

B. ICT APPLICATIONS AND SERVICES 7.326 1.832 9.158 5.769 1.442 7.211

C. INSTITUTIONAL SUPPORT AND

CAPACITY BUILDING 5.533 1.383 6.916 4.356 1.089 5.446

D. PROJECT MANAGEMENT 1.853 0.463 2.316 1.459 0.365 1.824

BASE COST 33.609 8.402 42.012 26.464 6.616 33.080

Physical contingencies (7%) 2.353 0.588 2.941 1.852 0.463 2.316

Financial contingencies (3%) 1.079 0.270 1.349 0.849 0.212 1.062

TOTAL 37.041 9.260 46.301 29.166 7.292 36.458

The summary of estimated cost by expenditure category is given in the table below:

7

Table 2.4

Summary of Estimated Cost by Expenditure Category

Expenditure Categories In EUR million In UA million

F.E. L.C. Total F.E. L.C. Total

A. GOODS 6.500 1.625 8.125 5.118 1.279 6.397

B. WORKS 18.923 4.731 23.654 14.900 3.725 18.625

C. SERVICES 5.717 1.429 7.146 4.501 1.125 5.627

D. OPERATION 1.280 0.320 1.600 1.008 0.252 1.260

E. MISCELLANEOUS 1.189 0.297 1.487 0.937 0.234 1.171

BASE COST 33.609 8.402 42.012 26.464 6.616 33.080

Physical contingencies (7%) 2.353 0.588 2.941 1.852 0.463 2.316

Financial contingencies (3%) 1.079 0.270 1.349 0.849 0.212 1.062

TOTAL 37.041 9.260 46.301 29.166 7.292 36.458

2.4.2 The project will be financed by the Bank Group, the Global Environment Facility

(GEF) and the national counterpart in accordance with the financing plan below. The Bank

Group will provide an AfDB loan of UA 29.374 million, representing a total of 80.6% of the

project cost. The provisions justifying this level of counterpart financing under the policy on

expenditure eligible for Bank Group financing are detailed in Appendix II.

Table 2.5

Summary of Estimated Cost by Source of Financing

Financing Sources In EUR million In UA million

Percentage F.E. L.C. Total F.E. L.C. Total

AfDB 29.844 7.461 37.304 23.499 5.875 29.374 80.57%

GEF 1.256 0.314 1.569 0.989 0.247 1.236 3.39%

Government of Cameroon 5.942 1.485 7.427 4.679 1.170 5.848 16.04%

TOTAL 37.041 9.260 46.301 29.166 7.292 36.458 100%

Table 2.6

Summary by Project Components by Source of Financing (in EUR million)

Components AfDB GEF Government of

Cameron Total

Component A: Optical Fibre Cable

Infrastructure 20.040 0.000 5.994 26.034

Component B: ICT Applications and Services 8.659 0.000 1.433 10.093

Component C: Institutional Support and

Capacity Building 6.053 1.569 0.000 7.622

Component D: Project Management 2.553 0.000 0.000 2.553

TOTAL 37.304 1.569 7.427 46.301

2.4.3 The expenditure schedule (in UA million) by source of financing is given in the

following table:

8

Table 2.7

Expenditure Schedule by Source of Financing (in UA million)

Source 15% 20% 35% 30% 100%

2016 2017 2018 2019 Total

AfDB 5,077 6,770 11,847 10,155 33,849

GEF 0,214 0,285 0,498 0,427 1,424

Government of Cameroun 1,011 1,348 2,359 2,022 6,739

BASE COST 6,302 8,402 14,704 12,604 42,012

Physical contingencies (7%) 0,441 0,588 1,029 0,882 2,941

Financial contingencies (3%) 0,202 0,270 0,472 0,405 1,349

TOTAL 6,945 9,260 16,205 13,890 46,301

2.5 Project Area and Beneficiaries

2.5.1 Project area: This is a nationwide project with regional ambitions. The deployment of

916 km-long optical fibre will be carried out along the following roads: (i) Mamfe-Ekok

(interconnection with Nigeria - 82 km) in the South-West Region; (ii) Bertoua-Batouri-Kentzou

(interconnection with CAR - 206 km) in the East Region; (iii) Kumba-Mamfe (187 km) in the

South-West Region; (iv) Sangmélima-Djoum-Mintom-Ntam (interconnection with Congo -

331 km) in the South Region; and (v) Ndop-Kumbo-Bamenda (110 km) in the North-West

Region. In addition to the local residents of these areas, the project will impact all inhabitants

of Cameroon and indirectly the population of the sub-region through the expected reduction in

the cost of ICT services following the integration of the telecommunications systems of Central

African countries. Moreover, the deployment of e-Banking and Markets and Climate

Information System (MCIS) will improve the socio-economic inclusion of the rural population

nationwide, especially farmers and stockbreeders, who will be provided with access to banking

services and to information on prices and quantities of agricultural products to improve their

productivity and strengthen their resilience to climate change.

2.5.2 Direct project beneficiaries: In Cameroon, the beneficiaries of the extended project

area stands at 2 604 248 persons. For their part, the direct beneficiaries of the direct project

impact area total 616 468 persons. At the sub-regional level, once the links are built to connect

the neighbouring countries to the Cameroon optical fibre backbone, the beneficiaries will

comprise the populations of Central African Republic, Nigeria and Congo. These are

predominantly rural residents whose main activities are agriculture and stockbreeding.

Specifically, the project will lead to the hiring and training of 208 people, who will operate and

run the 52 ICT promotion structures (21 TCPs, 20 CEAC/DAAs and 11 CPFs) for the benefit

of residents of the immediate project area. Furthermore, at least 7 800 people, including no less

than 3 000 women, are expected to be initiated in the use of ICT tools. Lastly, four (4) students,

three (3) of them girls, will be granted training scholarships for degree-awarding programmes

that will enable them to become part of the industry's elite. The sector's private operators

(CAMPOST, telephone companies, etc.) will also benefit from project achievements, as they

would be able to easily extend their services to all localities served by optical fibre facilities.

Similarly, they stand to gain from the improved institutional arrangements brought about by the

project.

9

2.6 Participatory Approach for Project Identification, Design and Implementation,

including Active Private Sector Participation

2.6.1 The participatory approach was adopted during the preliminary studies, the

environmental and social assessment, and the preparation and appraisal missions. These

consultations contributed to better project design both in terms of component formulation and

implementation arrangements.

2.6.2 During the identification, preparation and appraisal missions, all stakeholders were

consulted both in Government services (MINPOSTEL, MINADER, ART, CAMTEL

CAMPOST, etc.) and the private sector (MTN Cameroon, Orange Cameroon, Nexttel, etc.).

Discussions with these entities were helpful, for example, in the definition of the content of the

technical assistance to be offered to ART, as planned under the “Institutional Support and

Capacity Building” component, to ensure the effective implementation of the “open access”

principle in the operation of the optical fibre infrastructure envisaged under the project.

2.6.3 As part of the environmental and social assessment exercise, public consultations were

organized on the Kumba-Mamfe road link from 16 to 18 December 2014; on the Ndop-Kumbo-

Bamenda, Sangmélima-Djoum-Mintom-Kumba-Mamfe and Ntam-Ekok links from 16 to 22

December 2014; on the Bertoua-Batouri-Kentzou link from 8 to 15 September 2013 for the

preparation of the Environmental and Social Impact Assessment (ESIA), and in December 2014

for the Abbreviated Resettlement Plan (ARP). Community meetings took place and were

attended by an average of 50 to 100 people, 50% of them women in most cases. The people

expressed their main concerns and expectation, as well as their support for the project in a

development perspective. Minutes of these meetings were prepared and are available as Annex

to the public consultation reports.

2.6.4 Community meetings took place and were attended by an average of 50 to 100 people,

50% of them women in most cases. The people expressed their main concerns and expectation,

as well as their support for the project from a development perspective. Minutes of these

meetings were prepared and are available as Annex to the public consultation reports.

2.6.5 Generally, MINPOSTEL will prepare and implement a communication plan for the

information, education and social mobilization of local communities, and public and private

operators in the sector during the implementation phase.

2.7 Bank Group Experience and Lessons Reflected in Project Design

2.7.1 As of 31 December 2014, the Bank's active portfolio in Cameroon - all operations

combined - comprised 17 projects for a total net commitment of UA 507.220 million. The

overall portfolio performance is also satisfactory: no project in the national public portfolio is

classified as project at risk.

2.7.2 The major constraints and problems encountered, especially in the implementation of

infrastructure projects, include: (i) the slow pace of procedures for the procurement of goods,

works and services; (ii) the delayed mobilization of national counterpart funding; and (iii) the

financing of compensations.

2.7.3 In view of the foregoing, during project implementation, the Bank will capitalize on

the following measures already taken or planned: (i) use of the advance contracting (AC)

method to minimize procurement delays; (ii) steps taken by MINPOSTEL and MINEPAT to

ensure the inclusion of national counterpart financing in the budgets of the various fiscal years

throughout the project. For the management of compensation, MINPOSTEL will build on the

experience of the Ministry of Public Works (MINTP), which has developed an environmental

10

management procedures manual during the implementation of road projects as well as a

procedures manual for expropriation and resettlement related to road projects.

2.7.4 Lastly, this operation draws on the lessons learned from the implementation of

Cameroon's previous CSP (2010-2014). Hence, the ICT sector-related challenges in the country

were anticipated by taking into consideration the strengthening of the regulatory framework. It

is undeniable that this project is highly inclusive by virtue of its diverse components. Moreover,

the activities targeted by the co-financing provided by GEF will strengthen the project's green

growth objectives.

2.8 Key Project Performance Indicators

2.8.1 The key performance indicators and expected project outputs are presented in the

logical framework along with the timeframes. The core sector indicators (CSIs) on which the

project will focus are: (i) the number of additional international connections installed; (ii) the

fixed tele-density (especially for wired Internet) and mobile services in the regions concerned

by the project; (iii) the number of CAMPOST’s mobile banking (e-Banking) customers; (iv)

the costs of access to ICT services for the regions and at national level; (v) the number of people

likely to benefit from the initial and continuing training offered by the various entities

concerned (ENSPT, TCP, CEAC, CPF, etc.); (vi) the number of students with Internet access

on the campuses of Yaoundé I, Bamenda and Maroua Universities; (vii) the number of

farmers/stockbreeders with access to market and weather information; (viii) the number of

people benefiting from solar electric terminal systems; and (ix) institutional support and

capacity building for the ICT sector.

2.8.2 MINPOSTEL will be responsible for data collection and analysis; it may be supported

by Cameroon’s National Institute of Statistics (NIS). In this case, the NIS, which is familiar

with this type of exercise may: (i) establish the baseline situation of these indicators at project

start-up; (ii) conduct an impact assessment at project completion; and (iii) continue the

assessment after the commissioning of the planned connections.

2.8.3 To ensure that all these operations are performed on time, in addition to these output

indicators, implementation performance indicators were established in line with the Bank's

institutional performance indicators. These relate mainly to: (i) the effectiveness timeframe; (ii)

the timeframe for fulfilling conditions precedent to first disbursement; (iii) the procurement

timeframe; (iv) the mean indicator of progress in project implementation (IP); and (v) the trend

of disbursement in relation to the expenditure schedule. These indicators will be monitored

during supervision missions and the day-to-day management of the project.

11

III. PROJECT FEASIABILITY

3.1. Economic and Financial Performance

3.1.1. A study of the financial and economic rate of return was carried out on the following

projects: (i) implementation of optical fibre infrastructure; (ii) establishment of an e-Banking

system; (iii) establishment of a hybrid mail system; and (iv) deployment of an Electronic

Document Management (EDM) system.

3.1.2. The macro-economic assumptions are based on a 3% inflation rate and a stable

CFAF/EUR exchange rate. The fixed interest rate on the AfDB loan is estimated at

approximately 1%. The financial discount rate is 2%. The retained economic discount rate is

10%.

Based on these assumptions, the main outcomes are listed below.

Table 3.1

Economic and Financial Assessment

FIRR. NPV: 19.79%. EUR 135.86 million @ 2%

EIRR 34.14%

3.1.3. The economic lifespan of the project is 15 years. Based on the assumptions used, it

follows that the FIRR is 19.79% and the EIRR 34.14%. The economic and financial analysis

shows that the project is economically and financially feasible.

Moreover, a project sensitivity test was performed based on the following three parameters: (i)

a 10% increase in the investment costs; (ii) a 10% increase in operating costs; and (iii) a

combination of the two previous parametres. The outcomes of the sensitivity analysis shown in

the table below (the details of which are included in the Technical Annex B.7) indicate slight

variations which do not diminish the financial and economic viability of the project.

Table 3.2

Sensibility Test

ASSUMPTIONS

FNPV

(EUR million)

ENPV

(EUR million)

FIRR (%)

EIRR (%)

Baseline scenario 135.9 103.4 19.79 34.14

10% increase in investment costs 129.1 98.4 17.73 31.06

10 % drop in income 115.5 88.1 17.52 30.76

Combination of the two

assumptions above

108.7 83.1 15.63 28.03

3.2. Environmental and Social Impact

3.2.1. Environmental aspect: The project is classified under Category 2, in accordance with the

requirements of the Bank's Integrated Safeguard System. The Environmental and Social Impact

Assessment (ESIA) and the Environmental and Social Management Plan (ESMP) were prepared in

2014 for the Bertoua-Batouri Kentzou and Bamenda-Mamfe Ekok trunks. The project is also

underpinned by the ESIA of the Sangmélima-Djoum-Mintom-Ntam and Congo (Mbalam) Border

road project, as well as that of the Kumba Mamfe road link prepared in 2012. The studies were

validated by the Ministry of Environment, Nature Protection and Sustainable Development

12

(MINEPDED) and were issued acceptance certificates. The optical fibre cable will be deployed

along these road links, for which a Declaration of Public Utility (DUP) has been issued

3.2.2. Regarding the deployment links selected, the project environment is nationwide in

scope. The optical fibre cables and chambers will be installed strictly following the right-of-

way of identified existing roads links. Impact-generating activities are the civil works that will

be carried out on roads without ducts for the deployment of optical fibre cables. On roads that

already have ducts, deployment will be the major activity.

3.2.3. Impacts expected to be generated by civil works are: (i) risk of disruption of access roads

used by local residents due for lack of signalling devices and trenches that are not covered to ease

crossing; (ii) obstruction of access by various deposits; and (iii) risk of road accidents faced by

workers improperly positioned on the road. The deployment of optical fibre cables by portage will

generate occasional noise, but of very short duration (compressor for compressed air). The natural

and physical environments, poor waste management (small pieces of ducts and fibre, abandoned

strands, rejected cement mortar laitance, packaging, etc.).

3.2.4. These identified impacts will be offset for the most part by appropriate measures to enable

the project’s environmental integration. PCU/CAB will be responsible for monitoring the mitigation

measures recommended during the implementation phase. It will be supported in its task by a

Contracting Authority Assistance (CAA) mission.

3.2.5. The “ICT Applications and Services” component does not generate any adverse impacts

on the environment. It makes for the economy of movement and, as a result, reduces noise pollution,

traffic accidents and greenhouse gas emissions. Hence, the positive impacts are extensive, as

reflected, among others, in: (i) the creation of jobs directly related to equipment operation; and (ii)

the improved living conditions of local residents of project areas and across the country, thanks to

the increased connectivity and access to information of all kinds.

3.2.6. Climate Change: The project will help to reduce the carbon footprint of the electricity

sector in Cameroon by providing TCP, CPF CEAC and DAA data centres with solar panels

producing 190 000 kWh. It will prevent the emission of 47.5 tonnes of CO2 per year. ICT

services also substantially reduce greenhouse gas emissions. Indeed, the implementation of the

e-Post and e-Banking projects will lead to the substitution of transfers with data transmission,

thus eliminating the movement of persons estimated at 400 000 km/year. These avoided

movements therefore represent 74 t CO2/ year. Hence, a total emission of 121.5 t CO2 will be

avoided.

3.2.7. Social impacts: The extended project impact area is home to a population of 2 604 248

people. The direct impact area is inhabited by 616 468 people. Moreover, the project's positive

externalities will benefit the population of Cameroon and the sub-region as a whole. The main

positive impacts of the project are: (i) improved living conditions of rural residents with the

enhancement of TCP, CEAC/DAA and CPF capacity in the project area; (ii) opening up of the

project area; (iii) creation of employment opportunities and income improvement; (iv)

development of agricultural activities with access to agricultural data banks at the central level;

and (v) improved functioning of school and health infrastructure. Businesses will be encouraged

to recruit local labour for trenching, laying of ducts, optical fibre cables, etc.

3.2.8. Involuntary Resettlement: The project implementation will affect 30 people as follows:

owners of 24 screeds, 2 walls and 4 stairs. They are all located in the cities of Bertoua, Mandjou,

Batouri, Ngoura 2 and Kentzou, on the only road that affects local residents. The other 3 roads

do not affect any property owner. The cost of rehabilitation of destroyed property amounts to

CFAF 20 380 800, the running cost of the divisional commissions, local compensation and

13

awareness committee stands at to CFAF 33 000 000, while the contingencies are estimated at

CFAF 5 338 080.

3.2.9. Gender and women-specific activities: The gender aspect of the project was analysed

within the context of the laying of optical fibre in communities along the roads (see Technical

Annex B.8). It highlighted gender disparities in education, health, employment, security and

access to ICT. To fill the gaps identified by the analysis, the project will develop support for

the empowerment of women by: (i) strengthening the logistics of 11 Women's Promotion

Centres (CPFs); (ii) awarding doctoral scholarships to three girls; (iii) providing community

training for the initiation of at least 3 000 women; (iv) updating and validating CPF training

modules; producing an ICT benchmark; and (v) producing an entrepreneurship training manual

(common core), etc.

IV. IMPLEMENTATION

4.1. Implementation Arrangements

4.1.1. The project executing agency is the Ministry of Post and Telecommunications

(MINPOSTEL) acting through the CAB Cameroon Project Coordination Unit (PCU/CAB-

Cameroon) set up since 2008 by the Bank and World Bank. This Unit currently consists of a

Coordinator, an Administrative and Finance Officer (RAF), an Accountant, an Internal Auditor,

a Procurement Specialist (SPM), an Administrative and Finance Assistant and a Procurement

Assistant. It has a procedures manual that governs its operation. This Unit has the necessary

experience to conduct the sector's operations. To implement this project, this staff will be

strengthened by a technical expert (an ICT engineer) whose CV will be submitted to the Bank

for non-objection. Staff performance will be regularly evaluated at least yearly.

4.1.2. Specifically, the Unit will be responsible for the technical monitoring of project

implementation. In this regard, it will: (i) ensure that the State's commitments are honoured; (ii)

conduct monitoring and evaluation; (iii) ensure compliance with the project implementation

schedule; (iv) prepare semi-annual and annual project progress reports; (v) prepare counterpart

budgets and ensure their timely availability; (vii) ensure the financial management of the project

(verification of detailed accounts, transmission of direct payment requests to the Bank); (viii)

ensure timely submission of accounting and financial audit reports of the project; and (ix)

prepare the Borrower’s completion report for submission to the Bank.

4.2. Procurement Arrangements

4.2.1. All procurement of goods and works by international competitive bidding (ICB) and

consultancy services financed by the Bank will be in accordance with Bank Rules and

Procedures for the Procurement of Goods and Works (May 2008 edition, revised in July 2012)

or Bank Rules and Procedures for the Use of Consultants (May 2008 edition, revised in July

2012), whichever applies, using appropriate standard Bank bidding documents. Procurement of

goods and works through national competitive bidding (NCB) will be conducted in accordance

with national legislation on public procurement (Decree No. 2004/275 of 24 September 2004),

using the country's standard bidding documents and in line with the provisions set forth in the

financing agreement.

4.2.2. MINPOSTEL, acting through PCU/CAB, will be responsible for managing project-

related procurement. PCU/CAB was set up since 2008 as part of the CAB project financed by

the World Bank. This project plans to recruit a Procurement Assistant in order to strengthen the

procurement team in place.

14

4.2.3. A procurements plan (PP) was prepared during the appraisal mission and will be

regularly updated during the project implementation phase. The procurement arrangements are

detailed in Annex B.

4.2.4. The Government expressed the wish to use advance contracting (AC) to accelerate the

contract award process and thus ensure rapid implementation. In that regard, the Government

will submit a request to the Bank for that purpose, which would enable it to use the advance

contracting arrangement for optical fibre infrastructure works, control and monitoring. The

Bank will examine the request and notify the Government of its decision.

.

4.3. Financial Management and Disbursement Arrangements

4.3.1 The CAB Cameroon Project Coordination Unit (PCU/CAB-Cameroon), at the

Ministry of Post and Telecommunications (MINPOSTEL), will be responsible for the

administrative, financial and accounting management of the project. The fiduciary team will

comprise the Administrative and Financial Manager (RAF), a qualified accountant experienced

in managing development projects, an internal auditor (all three of them consultants recruited

on a competitive basis with World Bank financing), and a procurement specialist (PS).

4.3.2 The Unit will be responsible for the conduct of all control necessary to ensure: (i) the

use of project funds solely for the intended purposes with due regard for economy and

efficiency; (ii) preparation of accurate, reliable and timely periodic financial reports; and (iii)

safeguard of project assets. It will also be charged with producing quarterly Financial

Monitoring Reports (FMR) analysing activities financed by the Bank, monitoring activities by

source of financing (AfDB, GEF and Government of Cameroon) and consolidating the

accounting data of these three source of financing. An administrative, financial, and accounting

manual has been available since 2010, and will be updated to reflect the project’s specificities.

4.3.3 The fiduciary risk for project financial management is deemed moderate. Based on

project implementation arrangements, the Project Coordination Unit (PCU) under the Ministry

of Post and Telecommunications (MINPOSTEL) will be responsible for the financial

management of project activities. This task will be performed by the existing staff

(Administrative, Financial and Accounting Manager), which is already well versed in the

procedures of technical and financial partners, including those of the World Bank (WB).

4.3.4 The fiduciary arrangements within the PCU in Yaoundé were assessed and deemed

acceptable in light of the Bank's minimum requirements defined under the policy on the

“Financial Management of Projects Financed by the African Development Bank”, February

2014 edition. The implementation of mitigation measures and the action plan recommended in

annex should enable the financial provisions designed for the project to continue to provide

financial information that is reliable and compliant with Bank's minimum requirements, with

reasonable assurance.

15

4.3.5 Audit arrangements: Audits will be conducted yearly by an independent external audit

firm recruited on a competitive basis and in accordance with the Bank's standard Terms of

Reference (TOR). The external auditor will be recruited by the executing agency and audit costs

will be borne by the project. The ToR of the external auditor will be tailored to and harmonized

with those of the World Bank to account for project specificities validated during the

negotiation for the recruitment of an independent firm with experience in the audit of Bank-

financed projects. Audits will be conducted according to ISA/ISSAI international standards.

The financial statements audited by the independent firm will be forwarded (see table for

frequency) to the Bank not later than six months following the end of the financial year

concerned.

4.3.6 Arrangements relating to disbursement methods: Funds will be disbursed at the Bank

using the method of reimbursement of authorised advances made by the Government, the

working capital/special account method (mainly for operating expenditure) and the direct

payment method (for the procurement of goods and services, including audit costs).

4.3.7 A special account in CFA francs will be opened in a commercial bank acceptable to

the Bank to receive the AfDB funds, in accordance with the provisions set forth in the CAA

Procedures Manual and the Bank's Disbursement Handbook for the management of special

accounts. It will be managed by the fiduciary team of the executing agency and used exclusively

to finance the project's operating costs and, in particular, defray management expenses relating

to: (i) capacity building activities for the Project Management Unit; (ii) salaries and allowances;

and (iii) other operating expenses.

4.3.8 An account will be opened in CFA francs in Yaoundé to receive the funds of the

Cameroonian counterpart. It will operate in accordance with the provisions of the project's

administrative, financial and accounting procedures manual. The account will be used to

finance the following activities: (i) procurement of a portion of the solar equipment intended

for TCP, CEAC/DAA and CPF; (ii) procurement of technical sites (for the road links included

in this project); (iii) compensation for project-affected persons (PAPs), in particular, the laying

of optical fibre cables along the Bertoua-Batouri-Kentzou road; (iv) management of the “optical

fibre infrastructure” component; (v) logistical development works for CAMPOST as part of the

Electronic Document Management (EDM) system; (vi) support to the Procurement Committee;

and (vii) strengthening of the PCU/CAB technical support staff.

4.4. Monitoring

4.4.1. The implementation of various project components will be monitored by

MINPOSTEL’s Department of Infrastructure and Access Networks (DIR) through the CAB

Cameroon Project Coordination Unit (PCU/CAB-Cameroon). Joint supervision missions

(donors and Government) and inter-donor coordination meetings will also report on the

performance of the project in terms of physical and financial outputs.

4.4.2. To strengthen the system in place, it was agreed with the Cameroonian authorities that

a Technical Committee led by MINPOSTEL will be set up to support the Unit in preparing the

terms of reference, technical specifications and specifications relating to infrastructure building,

assessment of various bids and proposals submitted for the procurement of various items

envisaged, in cooperation with the technical expert, review and approval of reports and

documents submitted by the contractor responsible for works implementation, etc.

4.4.3. In addition to the above-mentioned committees and the Project Steering Committee

already in place, it is planned to set up a Project Communication Committee, which will be

coordinated by the Head of MINPOSTEL’s Communication Unit, which will work in

16

cooperation with the officials in charge of communication in each of the entities involved in the

project. It will coordinate activities relating, among others, to the publication of press articles,

press briefing, television infomercials, etc., covering the project implementation.

4.4.4. Regarding the assessment of the level of achievement of development objectives, a

socio-economic impact monitoring and evaluation mechanism will be put in place and

implemented by the PCU/CAB. Project environmental and social impacts will be monitored by

a local firm as part of ESMP implementation by the parties concerned, in cooperation with

MINEPDED, in an effort to overcome the PCU/CAB limitations identified in that area.

Regarding the implementation of the “ICT Applications and Services” component, a technical

audit of each planned project achievement will be conducted to ensure compliance with the

initial specifications, given that the implementation of the optical fibre infrastructure will be

entrusted to a separate manager who will supervise works scheduled on behalf of the

beneficiary.

Table 4.1

Project Monitoring and Supervision Deadline Stage Process Feedback Loop

T1 -2016 Project launch Field mission Progress reports

T1 – 2016 Project review – procurement,

resettlement

Field mission/Supervision Progress reports/Aide-memoire

T3&T4-2016, FO Infrastructure Works Field mission/Supervision Progress reports/Aide-memoire

T1&T2&T3&T6-2017-2018 FO Infrastructure Works Field mission/Supervision Progress reports/Aide-memoire

T1 -2019

T1 -2020

Guarantee period and first year

of operations

Field mission Progress reports/Aide-memoire

Progress reports/Aide-memoire

4.5. Governance

4.5.1. The risks of poor governance in the areas of procurement and financial management

were analysed during the project appraisal and presented as annex to this report. Since 2008,

progress has been achieved in budget management, but significant weaknesses still limit the

public expenditure efficiency. The enactment of the State Financial Systems Law (LRFE) in

2007 was accompanied by significant reform in results-based management. The reform

strengthens the responsibilities of the contracting authority in designing sector reforms and

preparing the Medium-Term Expenditure Framework (MTEF). However, the weaknesses

inherent in the entire Planning-Programming-Budgeting-Monitoring (PPBM) chain and the

absence of an integrated public finance management system are major drawbacks to public

expenditure efficiency.

4.5.2. Generally, the implementation of the public finance modernization plan will mitigate

these risks by strengthening public expenditure efficiency in the ICT sector. Furthermore, to

improve the sector's governance, the Bank made a review of public expenditure in 2013, and

the recommendations emanating therefrom will be the subject of regular dialogue aimed at

strengthening public expenditure efficiency in the transport sector.

4.5.3. In the procurement process, especially as concerns international bid invitations, the

governance-related risk would be mitigated by the Bank’s strict enforcement of its relevant

rules and procedures, and the conduct of prior reviews. The Bank's supervision missions and

technical and financial audits will ensure consistency between the specifications, actual services

provided and work performed, disbursements and the loan agreement.

4.5.4. In the ICT sectors, the market was liberalized, particularly with the authorization of

mobile operators to provide data services (Orange and MTN were authorized to provide 3G

17

licenses in 2015, in addition to Nexttel which was licensed since 2012). This should help to

support the use of wholesale market capabilities. For its part, the Telecommunications

Regulatory Authority (ART) guarantees competition in the telecommunications market. It

should, however, be mentioned that the difficulty faced by the Regulatory Authority in

controlling CAMTEL's prices is a major constraint. That is why this operation includes the

development of an economic model for the costing of access to national and international

connectivity. That will be beneficial to ART, since it will enable the entity to sift through the

catalogue of prices charged by the traditional operator and thus ensure the implementation of

the “open access” principle guaranteed by regulating the sector for all private operators with

licenses.

4.5.5. Regarding procurement, despite a number of gaps related to the Bank's fiduciary

requirements, the procurement procedures for the national competitive bidding (NCB) process

are deemed largely compliant. In view of the findings of Bank assessment and Government's

efforts, plans have been made to propose the use of national procedures for national competitive

bidding (NCB) to the Government. A letter of agreement to be signed with the Government will

identify weaknesses which should be remedied. As usual, the specific measures for mitigating

the governance-related risks of this project include: (i) recruitment of an independent financial

audit firm to ensure that funds are used rationally and for their intended purposes; (ii) prior

review and approval by the Bank of all procurement activities for the project; and (iii) the use

of direct payment disbursement method to transfer project funds directly to contractors and

service providers.

4.6. Sustainability

4.6.1. The national optical fibre backbone maintenance management in Cameroon devolves

on MINPOSTEL, which delegates the function to the incumbent operator, CAMTEL, except

for urban local loops that belong to private operators. CAMTEL will be responsible for

programming and implementing optical fibre maintenance on a force account basis. Indeed,

within CAMTEL, there are two technical directorates in charge of network maintenance and

servicing, namely the Directorate of Access Networks and the Directorate of Transport

Networks. The latter Directorate is responsible for the maintenance of the national optical fibre

network and has branches in CAMTEL regional representations. It employs more than 500

people nationwide.

4.6.2. Financing is done with CAMTEL's own resources. The Special Telecommunications

Fund (TSF) assists CAMTEL in installing certain segments, in particular the urban loops that

are also used for the interconnection of the sites of government services as part of the

government intranet system.

4.6.3. However, the revenue generated by the project focus areas is largely sufficient to cover

the cost of equipment maintenance (fibre and assets) during the lifespan of the various

components. The same is true for business applications (hybrid mail, EDM and e-Banking) that

will be procured by CAMPOST under this project. As part of its dialogue with the country, the

Bank will ensure the actual availability of resources for the maintenance and upgrade of the

systems (physical and software) in place.

18

4.7. Risk Management

4.7.1 Risks that may hinder the achievement of results include: (i) non-compliance with

undertakings relating to the laying of optical fibre cables; (ii) failure to produce an impact on

prices; (iii) premature degradation of the optical fibre due to lack of maintenance; (iv) lack of

maintenance and upgrade of the various applications installed.

4.7.2 Mitigation measures: (i) The Government's commitment to implement the guidelines

of the International Telecommunication Union (ITU); (ii) Bank support in the form of technical

assistance to enable the necessary reform of the ICT sector; (iii) commitment by CAMTEL to

allocate a substantial portion of the resources generated by the new connections for the

maintenance of the road links and more generally the national backbone; and (iv) commitment

by CAMPOST, in particular, to further invest in the extension of the reach of its existing

products and services (hybrid mail, electronic document management (EDM), etc.) to ensure

coverage of the entire country.

4.7.3 Risks that may hinder achievement of the outputs are: (i) the slow pace and lack of

transparency in the procurement process; (ii) escalation of the cost of works; (iii) non-compliance

with technical and functional specifications in the context of the various applications envisaged

in the project; and (iv) delay in compensating project-affected persons (PAPs) on the Batouri-

Bertoua-Kentzou road.

4.7.4 Mitigation measures: (i) expand competition by taking advantage of the size of works

contracts and the key reforms introduced by the Government through the establishment of a

Ministry in charge of Public Procurement; (ii) take physical contingencies into account in the

project financing plan; (iii) strengthen the Project Coordination Unit by including a technical

expert in charge of project supervision; and (iv) prioritize the compensation of PAPs when

allocating the national counterpart financing.

4.8. Knowledge Building

4.8.1. The project will provide an opportunity to improve knowledge in the area of national

ICT infrastructure. To better derive lessons from this project, a monitoring and evaluation

mechanism will be set up by the Unit. Establishing key impact indicators prior to the project

start-up and conducting impact assessment at the end of the project will help to provide useful

information on the project outcomes and impacts. The lessons, experiences and knowledge that

will thus be derived from implementing this project will be managed from MINPOSTEL’s

Department of Infrastructure and Network Access (DIR) and disseminated through annual

reports and the Bank's website. The knowledge will be very useful, among others, for

implementing the next CAB project.

19

V. LEGAL INSTRUMENT

5.1. Legal Instrument

The project will be financed through an AfDB loan and a GEF grant awarded to the Republic

of Cameroon.

5.2. Conditions Associated with AfDB Intervention

5.2.1. Conditions Precedent to Effectiveness

Effectiveness of the Loan Agreement shall be subject to fulfilment by the Borrower of the

conditions set out in Section 12.01 of the General Conditions, to the Bank’s satisfaction. The

GEF grant will be effective from the date of its signature by the Donee and the Bank.

5.2.2. Conditions Precedent to First Disbursement of the AfDB Loan

In addition to the effectiveness of this Agreement, the first disbursement of AfDB loan

resources shall be subject to fulfilment of the following conditions by the Borrower, to the

satisfaction of the Bank:

(i) Provide the Bank with evidence of opening a special account in a bank

acceptable to the Bank, intended exclusively to receive the counterpart funds for

financing certain project-related activities and compensating projec-affected

persons (PAPs); and

(ii) Provide the Bank with evidence of opening a special account, in the name of the

project and with a bank acceptable to the Bank, to receive the loan resources;

5.2.3. Condition Precedent to First Disbursement of the GEF Grant

The first disbursement of the GEF grant resources shall be subject to the effectiveness of the

GEF Protocol Agreement.

5.2.4. Other Conditions

Other Conditions: The Borrower shall also:

(i) Provide, not later than 30 June of each year, evidence of the inclusion of the

amount of the Government's counterpart funding for the projet in the finance act

of the fiscal year concerned;

(ii) As the works progress and prior to works start-up in any area that is yet to have

reservations, provide evidence of compensation of project-affected persons in

the area, in accordance with the Bank's relevant rules and procedures, the

Environmental Management Plan (ESMP) and the Abbreviated Resettlement

Plan (ARP).

5.2.5. Undertakings

The Borrower underatkes, to the satisfaction of the Bank, to:

20

(i) Open discussions with the Bank on practical arrangements for the effective

implementation of "open access" to the optical fiber planned under the project

within six (6) months following the first disbursement of loan resources;

(ii) Implement the project, the Environmental and Social Management Plan (ESMP)

and Abbreviated Resettlement Plan (ARP), and ensure their proper

implementation by its contractors, in accordance with: (a) the Bank’s rules and

procedures; (b) national law; and (c) the recommendations, provisions and

procedures contained in the ESMP and ARP;

(iii) Referain from starting up works in an area with no reservations without having

fully compensated project-affected persons (PAPs; and

(iv) Provide the Bank half-yearly reports on the implementation of the ESMP and

ARP, including, where applicable, any weaknesses and corrective measures

initiated or envisaged.

VI. RECOMMENDATION

The Management recommends: (i) that the Boards of Directors of the Bank and the Fund should

approve the award of a GEFgrant, not exceeding USD 1 726 484, to the Republic of Cameroon

and (ii) that the Board of Directors of the Bank should approve the proposal to award an ADB

loan of EURO 37 304 000 to the Republic of Cameroon; for the Central Africa Optical Fibre

Backbone Project (Central Africa Backbone - CAB) - Cameroon Component, subject to

conditions set forth in this Report.

I

APPENDIX I

DESCRIPTION OF THE INSTITUTIONAL SUPPORT AND CAPACITY

This institutional support operation will focus on strengthening the governance sector through

support for structural reform of the sector, including by strengthening its legal and regulatory

framework by the Telecommunications Regulatory Authority (ART), improving available ICT

training (especially in the optical fibre field) offered in the country by the National School of

Post and Telecommunications (ENSPT), and strengthening various entities in charge of

community development in Cameroon (TCP, CEAC / DAA and CPF). In addition to these

measures, there are several studies preparing, among others, the next CAB project which is

largely devoted to the development of the application layer with a view to consolidating the

foundations of the digital economy in Cameroon and supporting women's empowerment. The

support will focus on the following four activities:

i- Studies: The objective of this project in Cameroon is twofold. It is intended to lay the

groundwork, in terms of infrastructure (optical fibre, in particular), for the launch of the

development of an ICT economy and industry in the country. Meanwhile, Cameroonian

authorities wanted this initiative to include feasibility studies on a second CAB project which

aims to accelerate the leveraging of the growth and job creation sources underlying the ICT

sector. Thus, it is expected, among other things, that a comprehensive feasibility study will be

conducted on the establishment of an ICT technology park, which includes the first National

Data Centre, to serve as the bedrock for the development of e-government in the country. Also

worthy of mention is the establishment of a Citizen Electronic Identification System, which will

enhance the reliability of the official and mandatory, permanent and continuous registration of

events (births, deaths, marriages and divorces) relating to the status of individuals and their

characteristics, from birth to death, for administrative and legal purposes. This component also

includes two major assessments on the use of renewable energies in the development of ICT in

rural communities, in particular, and the study on the establishment of an Optical Fibre Skills

Development Centre at ENSPT. It also comprises a study on the development of mobile

financial services available in Cameroon, particularly to promote financial inclusion in rural

areas.

ii- Technical assistance for ART: The three studies envisaged in this component are

intended to support the development of the national optical fibre backbone by building the

capacity of the Telecommunications Regulatory Authority (ART) to contribute to achieving the

project’s development objectives (access to better quality ICT services at lower costs by private

operators and indirectly by users wherever they may be across the country). They concern the

development of: (i) an economic model on fixing the costs of access to national and

international connectivity; (ii) a study on the regulation of the “open access” arrangement; and

(iii) a business model on the profitability thresholds of optical fibre (OF) deployment in the

country.

iii- Support for institutions of higher learning (ENSPT, Yaoundé I, Bamenda and

Maroua Universities: The efficiency of Cameroon’s ICT sector depends on the availability of

high-quality training locally. In this regard, the country has long had a training school - the

National Advanced School of Post and Telecommunications (ENSPT) - which trains

technicians and engineers in various fields connected to postal and ICT services. However, this

institution has real needs in terms of equipment and capacity, especially in the optical fibre

field. The establishment of a centre for the development of skills in optical fibre

communications technology and techniques, as envisaged under this project, aims to: (i) create

an optimal learning environment, through the procurement of laboratory equipment for practical

II

work on optical fibre communications; (ii) create a favourable environment for optical fibre

research/development and engineering for students and staff researchers; (iii) facilitate the

understanding of theoretical teaching through hands-on training with practicals; (iv) increase

the competitiveness of ENSPT products nationally and internationally; (v) build the capacity of

trainers; and (vi) reduce the cost of further training for the sector’s employees by bringing back

to the sub-region specialized training in optical fibre technologies. The project also involves the

design and implementation of an Internet access pilot project for three university campuses

(Yaoundé I, Bamenda and Maroua) to support the expected growth in value-added services

based on mobile telephony, in the wake of the recent introduction of 3G in Cameroon. The goal

of this pilot project is to understand the barriers to Internet penetration in the school and

particularly university environment. The lessons from this first experiment will be utilized in

the next CAB project.

iv- Capacity Building for TCP, CEAC and CPF: Under the GEF component of the

project that aims to support the various TCP and ECAC, these entities will be provided with

solar, office automation and IT equipment to make them fully functional as places of meeting

and training, with access to basic services (Internet access, document copying and printing

facilities, especially for students, etc.). Moreover, this initial experiment on the use of renewable

energy in these centres will be evaluated for subsequent replication on a larger scale with

financing from the Bank and other partners. The experiment will also help to assess the

feasibility and sustainability of a pilot system of solar-powered electrical terminals for use in

recharging mobile phones, among others, in rural areas. The outcomes of the evaluation of this

model will be taken into account in the next CAB project.

v- Support for women's empowerment: To contribute to the promotion of gender

equality, the project plans to: (i) support the design and implementation of training programmes

(ICT, entrepreneurship, etc.) for Women’s Promotion Centres (CPF); and (ii) award doctoral

scholarships to four ENSPT students per year (including three female students) throughout the

lifespan of the project and support the Ministry for the Promotion of Women (MINPROF) in

implementing this component. Additionally, it comprises the organization of awareness

sessions for young female students (high school girls, in particular) in streams leading to ICT

professions, in an effort to contribute to the promotion of gender equality in public and private

institutions providing ICT-related training.

III

APPENDIX II

RATIONALE FOR THE LEVEL OF COUNTERPART CONTRIBUTION TO AFDB

FINANCING

The project will be financed by the Bank Group, GEF and the national counterpart contribution,

according to the financing plan below. The Bank Group's contribution will be an AfDB loan of

UA 29.374 million, representing a total of 80.6% of the project cost. The project will also

receive the sum of UA 1.236 million as a GEF grant. The national counterpart contribution was

estimated at UA 5.848 million, corresponding to CFAF 4.872 billion, or 16.0% of the total

project cost. This amount of counterpart financing represents the current level of contribution

affordable by the country.

The level of AfDB contribution is less than 50% of the total project cost as stipulated by Section

4.2.2 of the Policy on Expenditure Eligible for Bank Group Financing (revised version of 19

March 2008), which provides that the level of counterpart funding complementary to the

financing from the AfDB window will be determined on the basis of the following criteria:

the country's commitment to implement its overall development programme;

the financing allocated by the country to sectors targeted by Bank assistance;

the risk of fiscal sustainability posed by the drop in oil prices;

the impact of the crowding out of priority spending by security and humanitarian

spending generated by the Boko Haram terrorist threats in the Extreme North,

on the one hand, and the crisis in Central African Republic, on the other

The Country’s Commitment to Implement its Overall Development Programme

Drawing lessons from the implementation of its poverty reduction strategy following the

achievement of the HIPCI completion point in 2006, the Government formulated in 2010 a

Vision for its development by 2035 (Vision 2035). This long-term vision aims to make

Cameroon an emerging democratic country, united in its diversity. Specifically, the Vision

constitutes a benchmark for: (i) reducing poverty to a socially acceptable level; (ii) reaching

middle-income country status; (iii) becoming a newly industrialized country; and (iv)

consolidating the democratic process and strengthening national unity.

These specific objectives have guided the orientations of the Growth and Employment Strategy

Paper (GESP) for the 2010-2020 period, covering the first ten years of the long-term Vision.

The main issue concerning the implementation of GESP will be to focus on growth acceleration,

creation of formal jobs and poverty reduction. It is, therefore, planned to: (i) increase growth to

an annual average of 5.5% over the 2010-2020 period; (ii) reduce under-employment from

75.8% to below 50% in 2020; and (iii) reduce the monetary poverty rate from 39.9% in 2007

to 28.7% in 2020. To achieve these objectives, the Government intends to implement, in a

coherent and integrated manner with the support of Technical and Financial Partners including

the Bank, a three-pronged strategy: (a) a growth strategy; (b) a strategy to improve governance

and central government’s strategic management; and (c) an employment strategy.

IV

The presentation of this operation to the Board is taking place in a special context marked by

the graduation of Cameroon to the Blend Country status of the AfDB window. Indeed, based

on its recent macro-economic performance, Cameroon graduated in 2014 to the non-

concessional windows of the World Bank and the AfDB Group, respectively. This dual

graduation reflects the confidence of multilateral institutions and enables the country to benefit

from the resources of both the concessional and non-concessional windows of the Bank Group.

It should allow the country to finance its development, especially its ambitious infrastructure

programme, in a more cost-effective manner. The country's new ambition is to graduate from a

“Blend Country” to an “AfDB Country” status.

Financing Provided by the Country to the Sector Targeted by Bank Assistance:

Given the recent establishment of OITC.3 Division in charge of public sector ICT operations,

this project is the Bank's first investment in Cameroon. In this regard, it may be noted that the

ICT sector figures prominently in the pipeline of projects identified under Pillar I

(Strengthening infrastructure for inclusive and sustainable growth) of Cameroon's Country

Strategy Paper (CSP) for 2015-2019.

The implementation of the Cameroonian component of the CAB project demonstrates the

central role the country could play in a broadband network interconnecting all the countries of

the sub-region. This project stems not only from the weight of Cameroon's economy in the

Central African region, but also from the need to strengthen the country's competitiveness by

lowering the cost of factors, especially telephony, to which the project will contribute.

Based on the foregoing, and at the request of the Government, it is proposed that the AfDB

Window limit the counterpart funding to 16.3% of the total project cost net of taxes, for the

partial financing of the procurement of technical sites, compensation of project-affected

persons, management of the component relating to optical fibre infrastructure, logistics

development works relating to the e-Post project and the tax and customs duty exemptions

associated with this project.

Country’s Fiscal Situation and Debt Level:

Fiscal policy over the past three years was moderately expansionary, on account of investment

expenditure on major infrastructure projects in the energy and transport sectors, in response to

the strong demand for goods and services in a context of economic recovery and infrastructural

gap accumulated over more than two decades. The increased spending is financed primarily by

external borrowing and oil revenue.

Table 1

Cameroon: Macro-economic Indicators

2010 2011 2012 2013 2014

Real GDP growth 3.3% 4.1% 4.6% 5.5% 5.3%

Inflation 1.3% 2.9% 2.4% 2.1% 2.2%

Overall cash-based fiscal balance as % of

GDP -1.1% -3.6% -1.9% -4.1% -5.2%

Current account balance as % of GDP -3.4% -2.8% -3.3% -3.8% -4.2%

This expansionary fiscal policy has remained sustainable, resulting in a budget deficit (cash

basis) of approximately 5.2% of GDP in 2014, compared with 4.1% and 1.9% respectively in

2013 and 2012. A key reform that characterized fiscal years 2013 and 2014 was the

implementation of a programme budget, in accordance with CEMAC Directive No. 01/11-

V

UEAC-190-CM-22.2.

The debt ratios are below the thresholds. Since the debt cancellation under the HIPC Initiative

in 2006, the risk of debt distress has remained low. At end-September 2014, Cameroon's ratio

of public debt to nominal GDP stood at 19.1%, one of the lowest in the CEMAC zone, where

the Community debt ceiling is set at 70% of GDP. Based on this CEMAC community debt

threshold, and considering the financing needs, especially in the area of structuring

infrastructure, and given the country's debt sustainability in relation to the performance of its

economy, the authorities have set a debt target for the 2013-2017 period which should not

exceed 35% of GDP (equivalent to 50% of the CEMAC ceiling set at 70% of nominal GDP).

The annual external debt increase to reach this 35% ceiling does not seem to comply with debt

ratios, according to recent debt sustainability analysis conducted by the IMF and the World

Bank in June 2014.

While there is no denying that the country’s efforts have begun to bear fruit, the fact remains

that the situation is still fragile, and donor assistance continues to be a necessity for the country

and will enable the Government to meet its budget commitments. In addition, this aid, though

non-concessional, is less costly than that offered by the market and will thus contribute to better

management of the country’s debt.

2 This directive on finance laws etablishes the transition from a resource budget to a programme budget.

VI

APPENDIX III COMPARATIVE SOCIO-ECONOMIC INDICATORS

Year Cameroon Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2014 475 30 067 80 386 53 939Total Population (millions) 2014 22,8 1 136,9 6,0 1,3Urban Population (% of Total) 2014 53,8 39,9 47,6 78,7Population Density (per Km²) 2014 48,0 37,8 73,3 24,3GNI per Capita (US $) 2013 1 290 2 310 4 168 39 812Labor Force Participation - Total (%) 2014 70,4 66,1 67,7 72,3Labor Force Participation - Female (%) 2014 45,7 42,8 52,9 65,1Gender -Related Dev elopment Index Value 2007-2013 0,872 0,801 0,506 0,792Human Dev elop. Index (Rank among 187 countries) 2013 152 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2008-2013 27,6 39,6 17,0 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2014 2,5 2,5 1,3 0,4Population Grow th Rate - Urban (%) 2014 3,6 3,4 2,5 0,7Population < 15 y ears (%) 2014 42,8 40,8 28,2 17,0Population >= 65 y ears (%) 2014 3,2 3,5 6,3 16,3Dependency Ratio (%) 2014 77,5 62,4 54,3 50,4Sex Ratio (per 100 female) 2014 100,0 100,4 107,7 105,4Female Population 15-49 y ears (% of total population) 2014 23,8 24,0 26,0 23,0Life Ex pectancy at Birth - Total (y ears) 2014 55,5 59,6 69,2 79,3Life Ex pectancy at Birth - Female (y ears) 2014 56,7 60,7 71,2 82,3Crude Birth Rate (per 1,000) 2014 36,8 34,4 20,9 11,4Crude Death Rate (per 1,000) 2014 11,5 10,2 7,7 9,2Infant Mortality Rate (per 1,000) 2013 60,8 56,7 36,8 5,1Child Mortality Rate (per 1,000) 2013 94,5 84,0 50,2 6,1Total Fertility Rate (per w oman) 2014 4,7 4,6 2,6 1,7Maternal Mortality Rate (per 100,000) 2013 590,0 411,5 230,0 17,0Women Using Contraception (%) 2014 28,3 34,9 62,0 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2012 7,7 46,9 118,1 308,0Nurses (per 100,000 people)* 2004-2012 43,8 133,4 202,9 857,4Births attended by Trained Health Personnel (%) 2009-2012 63,6 50,6 67,7 ...Access to Safe Water (% of Population) 2012 74,1 67,2 87,2 99,2Healthy life ex pectancy at birth (y ears) 2012 48,0 51,3 57 69Access to Sanitation (% of Population) 2012 45,2 38,8 56,9 96,2Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2013 4,3 3,7 1,2 ...Incidence of Tuberculosis (per 100,000) 2013 235,0 246,0 149,0 22,0Child Immunization Against Tuberculosis (%) 2013 82,0 84,3 90,0 ...Child Immunization Against Measles (%) 2013 83,0 76,0 82,7 93,9Underw eight Children (% of children under 5 y ears) 2005-2013 15,1 20,9 17,0 0,9Daily Calorie Supply per Capita 2011 2 586 2 618 2 335 3 503Public Ex penditure on Health (as % of GDP) 2013 1,8 2,7 3,1 7,3

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2011-2014 110,6 106,3 109,4 101,3 Primary School - Female 2011-2014 103,2 102,6 107,6 101,1 Secondary School - Total 2011-2014 50,4 54,3 69,0 100,2 Secondary School - Female 2011-2014 46,4 51,4 67,7 99,9Primary School Female Teaching Staff (% of Total) 2012-2014 51,2 45,1 58,1 81,6Adult literacy Rate - Total (%) 2006-2012 71,3 61,9 80,4 99,2Adult literacy Rate - Male (%) 2006-2012 78,3 70,2 85,9 99,3Adult literacy Rate - Female (%) 2006-2012 64,8 53,5 75,2 99,0Percentage of GDP Spent on Education 2009-2012 3,0 5,3 4,3 5,5

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2012 13,1 8,8 11,8 9,2Agricultural Land (as % of land area) 2012 0,2 43,4 43,4 28,9Forest (As % of Land Area) 2012 41,2 22,1 28,3 34,9Per Capita CO2 Emissions (metric tons) 2012 0,3 1,1 3,0 11,6

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

CameroonCOMPARATIVE SOCIO-ECONOMIC INDICATORS

juin 2015

0

10

20

30

40

50

60

70

80

90

100

2000

2005

2008

2009

2010

2011

2012

2013

Infant Mortality Rate( Per 1000 )

Came roon Africa

0

500

1000

1500

2000

2500

2000

2005

2007

2008

2009

2010

2011

2012

2013

GNI Per Capita US $

Came roon Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

2000

2005

2008

2009

2010

2011

2012

2013

2014

Population Growth Rate (%)

Cameroon Africa

01020304050607080

2000

2005

2008

2009

2010

2011

2012

2013

2014

Life Expectancy at Birth (years)

Came roon

Africa

VII

APPENDIX IV: STATUS OF APPENDIX IV: STATUS OF BANK PORTFOLIO IN CAMEROON AS OF 31 MARCH 2015 OF 31

MARCH 2015

SECTORS

PROJECTS Approval

Date

Signature

Date Effectiveness

Fulfilment of

disburs.

conditions

Date of 1st

disbursement Closing

Bank Financing (in UA million)

AfDB

Loan

ADF/NTF

Loan

ADF

Grant

Disburs.

Rate.

Governance

Cadastral Survey Project (PAMOCCA 1). 15.11.2010 05.01.2011 17.05.2011 10.02.2012 21.03.2012 31.12.2015 7.00 16.40%

Cadastral Survey Project (PAMOCCA 2). 17.12.2013 08.06.2014 29.10.2014 29.10.2014 30.03.2018 5.00 0%

Transport Kumba-Mamfe Road Project 21.11.2012 09.02.2013 16.09.2013 07.11.2013 27.01.2014 31.12.2017 47.26 17.30%

Batchenga-Lena Road Programme 1 26.11.2014 28.03.2015 123.039 12.45 0%

Water and Sanitation

Yaoundé Sanitation Project (PADY 2)

19.06.2013 11.09.2013 17.03.2014 01.10.2014 13.11.2014 31.12.2018 20.99 0.72%

Semi–Urban DWSS Project 28.01.2009 13.05.2009 02.11.2009 28.05.2010 14.10.2010 31.12.2014 40.00 27.68%

Rural DWSS Project 12.05.2010 29.06.2010 14.04.2011 02.05.2011 21.09.2011 29.02.2016 10.00 4.63 59.60%

Energy

Strengthening of Electricity Transport and Distribution Networks (PREREDT).

15.09.2010 15.10.2010 20.04.2011 22.01.2013 25.02.2013 31.12.2015 31.64 8.89%

Lom Pamgar Hydro-Electricity Development Project

10.11.2011 18.01.2012 14.06.2012 14.12.2012 25.07.2013 31.12.2017 44.93 2.26%

Agriculture Rural Infrastructure Support - Grassfield 2 23.10.2013 16.12.2013 10.04.2014 15.09.2014 07.10.2014 31.12.2019 13.61 3.19 1.44%

Emergency Humanitarian Aid to Refugees 13.01.2015 13.07.2015 724.91 0%

Private Sector

Shipyard and Industrial Engineering. (CNIC)

12.12.2002 02.06.2003 29.04.2005 29.04.2005 13.05.2005 31.12.2014 29.48 41.67%

AES-SONEL Investment Programme 10.05.2006 08.12.2006 13.02.2007 15.02.2007 20.02.2007 31.12.2020 53.17 100%

Dibamba Thermal Power Plant 28.04.2010 11.05.2011 11.05.2011 15.07.2011 22.07.2011 01.06.2023 19.74 100%

Kribi Thermal Power Plant 15.07.2011 22.12.2011 22.12.2011 27.08.2012 13.09.2012 15.11.2025 25.33 100 %

Regional Environment

Safeguarding elephants in Central Africa 22/07/2013 16.12.2013 11.11.2014 16.01.2015

31.12.2017 0.25 0%

Regional Energy

Chad–Cameroon Interconnection Study 07.10.2013 29.01.2014 03.09.2014 23.10.2014 15.12.2014 31.12.2016 1.25 15.75%

Regional Transport

Bamenda – Enugu Corridor Transport Facilitation

25.11.2008 13.05.2009 04.11.2009 01.12.2009 24.12.2009 30.06.2017 90.39 45.18%

Brazzaville -Yaoundé (Ketta –Djoumn Road) Corridor Transport Facilitation

25.09.2009 11.01.2010 29.03.2010 13.02.2012 24.04.2012 31.12.2015 59.27 61.21%

VIII

APPENDIX V

MAP OF THE AREA OF THE OPTICAL FIBRE INFRASTRUCTURE PROJECT

This map was provided by the staff of the African Development Bank

exclusively for the use of readers of the report to which it is attached. The names used and the borders shown do not imply on the part of the Bank Group and its

members any judgement concerning the legal status of a territory or any

approval or acceptance of its borders.