lhc machine protection: an introduction
DESCRIPTION
LHC Machine Protection: an introduction . J ö rg Wenninger OP training March 2006. Acknowledgments to my colleagues of the MPWG for input and material. Machine protection at the LHC. - PowerPoint PPT PresentationTRANSCRIPT
LHC Machine Protection:LHC Machine Protection:an introduction an introduction
JJöörg Wenninger rg Wenninger
OP training OP training
March March 20062006Acknowledgments to my colleagues of the MPWGfor input and material.
2
Machine protection at the LHCMachine protection at the LHC
• Machine protection activities of the LHC are coordinated by the LHC Machine Protection Working Group (MPWG), co-chaired by R. Schmidt & J. Wenninger.http://lhc-mpwg.web.cern.ch/lhc-mpwg/
• Since 2004 the MPWG is also coordinating machine protection at the SPS (ring & transfer lines).
OutlineOutline
• Energy stored in the LHC magnets and beams• Charging the energy• LHC dipole magnets – quench protection• Beam induced damage – what is a safe beam?• Beam dumping system• Collimation system• Strategy for Protection of the LHC machine
OutlineOutline
• Energy stored in the LHC magnets and beams• Charging the energy• LHC dipole magnets – quench protection• Beam induced damage – what is a safe beam?• Beam dumping system• Collimation system• Beam interlock system
Energy stored in a dipole magnetEnergy stored in a dipole magnet
Most energy is stored in the magnetic field of the dipoles
Dipole magnetfield map for one
aperture
B = 8.33 Tesla I = 11800 A L = 0.108 H
Energy stored in LHC magnetsEnergy stored in LHC magnets
Approximation: energy is proportional to volume inside magnet aperture and to the square of the magnet field
about 5 MJ per magnet
Accurate calculation with the magnet inductance:
E dipole = 0.5 L dipole I 2dipole
Energy stored in one dipole is 7.6 MJoule
For all 1232 dipoles in the LHC: 9.4 GJ
0
22
2
dipoledipoledipolestored
RLBE
Energy stored in the beamsEnergy stored in the beams
Stored beam energy: Proton Energy Number of Bunches Number of protons per
bunch
Proton Energy: 7 TeV
In order to achieve very high luminosity:
Number of bunches per beam: 2808
Number of protons per bunch: 1.05 ×1011
Stored energy per beam: 362 MJoule
25 ns
3×1014 protons / beam
8
Stored energy comparisonStored energy comparison
0.01
0.10
1.00
10.00
100.00
1000.00
10000.00
1 10 100 1000 10000Momentum [GeV/c]
En
erg
y s
tore
d in
th
e b
ea
m [
MJ
]
LHC topenergy
LHC injection(12 SPS batches)
ISR
SNSLEP2
SPS fixed target HERA
TEVATRON
SPSppbar
SPS batch to LHC
Factor~200
RHIC proton
LHC energy in magnets
9
The energy stored in the magnets The energy stored in the magnets corresponds to ..corresponds to .. an A380 flying at 700 km/han A380 flying at 700 km/h
a US aircraft carrier at battle-speed of a US aircraft carrier at battle-speed of 55 km/h55 km/h
10
The stored energy also corresponds to …The stored energy also corresponds to …
10 GJoule corresponds to…
• the energy of 1900 kg TNT• the energy of 400 kg Chocolate
• the energy required to heat and melt 12 tons of copper
• the energy produced by a nuclear power plant during 10 seconds
An important point to determine if there is an equipment damage issue:
How fast can this energy be released?
OutlineOutline
• Energy stored in the LHC magnets and beams• Charging the energy• LHC dipole magnets – quench protection• Beam induced damage – what is a safe beam?• Beam dumping system• Collimation system• Beam interlock system
0
2000
4000
6000
8000
10000
12000
-4000 -2000 0 2000 4000
time from start of injection (s)
dip
ole
cu
rre
nt (A
)
energy
ramp
preparation and access
beam dump
injection phase
coast
coast
LHC cycle: charging the magnetic energyLHC cycle: charging the magnetic energy
L.Bottura
450 GeV
7 TeV
start of the
ramp
13
Sector
1
5
DC Power feed
3
Oct
ant
DC Power
2
4 6
8
7LHC27 km Circumference
Powering Sector:
154 dipole magnets &about 50 quadrupolestotal length of 2.9 km
LHC Powering in 8 Sectors
Powering Subsectors:
• long arc cryostats• triplet cryostats• cryostats in matching section
Ramping the current in a string of dipole Ramping the current in a string of dipole magnetmagnet
Magnet 1 Magnet 2
Power Converter
Magnet 154Magnet i
• LHC powered in eight sectors, each with 154 dipole magnets• Time for the energy ramp is about 20-30 min (Energy from the grid)• Time for discharge is about the same (Energy back to the grid)• Note : if you switch off the main dipoles PC, the current decays with a time
constant of ~ 6 hours.
0
2000
4000
6000
8000
10000
12000
-4000 -2000 0 2000 4000
time from start of injection (s)
dip
ole
cu
rre
nt (A
)
injection phase12 batches from the SPS (every 20 sec)
one batch 216 / 288 bunches
LHC cycle – charging the beam LHC cycle – charging the beam energyenergy
L.Bottura
450 GeV
7 TeV
OutlineOutline
• Energy stored in the LHC magnets and beams• Charging the energy• LHC dipole magnets – quench protection• Beam induced damage – what is a safe beam?• Beam dumping system• Collimation system• Beam interlock system
17
QuenchQuench
A Quench is the phase transition of a super-conducting to a normal conducting state.
Quenches are initiated by an energy in the order of mJ• Movement of the superconductor by several m (friction and
heat dissipation)• Beam losses• Failure in cooling
To limit the temperature increase after a quench• The quench has to be detected• The energy is distributed in the magnet by force-quenching the
coils using quench heaters• The magnet current has to be switched off within << 1 second
Operational margin of a superconducting Operational margin of a superconducting magnetmagnet
Temperature [K]
App
lied
field
[T]
Superconductingstate
Normal state
Bc
Tc
9 K
Applied Field [T] Bc critical field
1.9 K
quench with fast loss of
~5×109 protons
quench with fast loss of
~5×106 protons
~ 0.00001% total no. protons/beam
8.3 T
0.54 T
QUENCH
Tc critical temperature
Temperature [K]
Power into Power into superconductingsuperconductingcable after a quenchcable after a quench
Cross section : Asc 10 mm2
Current : Isc 10000 A
Length of superconductor : Lsc 1 m
Copper resistance at 300 C: cu 1.76 10 6 ohm cm
Psc cu Isc2
Lsc
Asc Psc 1.76 105 watt
Specific temperature of copper at 300 C : cvcu 3.244joule
K cm3
Temperature increase of copper TPsc
Asc Lsc cvcu
Temperature increase within one second: T 5.425 103K
s
Quench - Quench - transition from superconducting state to transition from superconducting state to normalconducting statenormalconducting state - Emergency discharge of energy - Emergency discharge of energy
Magnet 1 Magnet 2
Power Converter
Magnet 154
Magnet i
To limit the temperature increase after a quench• The quench has to be detected : use voltage increase over coil• The energy is distributed in the magnet by force-quenching using quench heaters• The current in the quenched magnet decays is < 200 ms• The current of all other magnets flows through the bypass diode (triggered by the
voltage increase over the magnet) that can stand the current for 100-200 s.• The current of all other magnets is dischared inot the dump resistors
Discharge resistor
Energy extraction system in LHC Energy extraction system in LHC tunneltunnel
Resistors absorbing the energy
Switches - for switching the resistors into series with the magnets
Challenges for quench protectionChallenges for quench protection
• Detection of quench for all main magnets (1600 magnets in 24 electrical circuits)
• Detection of quench across all HTS current leads (2000) with very low voltage threshold ~ 1 mV across HTS part
• Detection of quench in about 800 other circuits• Firing heater power supplies, about 6000 units
• Failure in protection system• detection when there is no quench: downtime of some hours• no detection when there is a quench: damage of magnet,
downtime 30 days
• Systems must be very reliable
Powering InterlockPowering Interlock
• PLC-based Powering Interlock Controllers (PIC) are used to manage the interlock signal between the power converters and the quench protection system.
• The PIC also interfaces to the Beam Interlock System and will request a beam dump if the electrical circuit that fails is considered to be critical for beam operation.
OutlineOutline
• Energy stored in the LHC magnets and beams• Charging the energy• LHC dipole magnets – quench protection• Beam induced damage – what is a safe beam?• Beam dumping system• Collimation system• Beam interlock system
A proton injected into the LHC will end its life…A proton injected into the LHC will end its life…
• In a collision with an opposing beam proton• The goal of the LHC !• The experiments are designed to withstand very high particle
fluxes and high doses of radiation.• On the LHC beam dump
• At the end of a fill, be it scheduled or not. • On a collimator or on a protection device/absorber
• The collimators must absorb protons that wander off to large amplitudes to avoid quenches.
• Protons that escape the collimation system or are pushed to large amplitudes by a ‘failure’ (operation or equipment).
• On the machine aperture• Protons that escape the collimation system…
Beam loss into materialBeam loss into material
• Proton losses lead to particle cascades in materials• The energy deposition leads to a temperature increase• The temperature increase may lead to damage : melting, vaporisation, pressure waves…
Magnets could quench…..• beam lost - re-establish condition will take hours
The material could be damaged…..• melting• losing performance (mechanical strength)
Repair could take several weeks or years !
From SPS we (OP) know by experience that ~ 1013 protons at 450 GeV (1 MJ) we can damage equipment !
27
Beam induced damage : SPS Beam induced damage : SPS experimentexperiment
25 cm
Controlled experiment:• Special target installed in the TT40 transfer line• Impact of 450 GeV LHC beam (beam size σx/y = 1.1mm/0.6mm)
Beam
28
Results….Results….
A B D C
Shot Intensity / p+
A 1.2×1012
B 2.4×1012
C 4.8×1012
D 7.2×1012
TT40 damage test presented by
V. Kain at Chamonix 2005:
• Melting point of Copper is reached for an impact of 2.5×1012 p.
• Stainless steel is not damaged, even with 7×1012 p.
• Results agree with simulation
Based on those results the MPWG has adopted for the LHC a limit for safe beams with nominal emittance @ 450 GeV of:
1012 protons ~ 0.3% of the total intensity
Scaling the results yields a limit @ 7 TeV of:
1010 protons ~ 0.003% of the total intensity
Full LHC beam deflected into copper target
Target length [cm]
vaporisation
melting
N.Tahir (GSI) et al.
Copper target
2 m
Energy density [GeV/cm3] on target axis
2808 bunches
The beam will drill a hole along the target axis …
30
Beam absorber challengesBeam absorber challenges
• The stored energy in the LHC beam is so huge that designing absorbers for the beams that are not destroyed by an impact is a real challenge !
• Almost all protection elements are made of Graphite or other forms of Carbon: very robust low density absorber!
• The beam dump block is the ONLY element of the LHC that can safely absorb all the beam – will be discussed in a moment.
• All other absorbers in the LHC (collimators and protection devices) can only stand partial losses – typically up to a full injected beam, i.e. equivalent to the energy stored in the SPS at 450 GeV.
OutlineOutline
• Energy stored in the LHC magnets and beams• Charging the energy• LHC dipole magnets – quench protection• Beam induced damage – what is a safe beam?• Beam dumping system• Collimation system• Beam interlock system
LHC Layout
IR3, IR6 and IR7 are devoted to protection and collimation ! IR6: Beam
dumping systemIR4: Radio frequency
acceleration
IR5:CMSexperiment
IR1: ATLASexperiment
IR8: LHC-BexperimentIR2: ALICE
experiment
InjectionInjection
IR3: Momentum Collimation (normal
conducting magnets)
IR7: Collimation (normal conducting magnets)
Beam dump blocks
Schematic layout of beam dump system in Schematic layout of beam dump system in IR6IR6
Q5R
Q4R
Q4L
Q5L
Beam 2
Beam 1
Beam Dump Block
Septum magnet deflecting the extracted beam H-V kicker
for painting the beam
about 700 m
about 500 m
15 kicker magnets
Dumping the LHC beamDumping the LHC beam
about 8 m
concrete shielding
beam absorber (graphite)
about 35 cm
35
Requirements for a clean dumpRequirements for a clean dump
•Strength of kicker and septum magnets must match the beam energy:
•Very safe beam measurement based on the current of the magnets !
•Dump kickers must be synchronized to the « Particle free gap »:
•Accurate and reliable synchronization.
•Abort gap must be free of particles: gap cleaning with damper.
particle free abort gapof 3 s
Kicker magnets constant angle
Beam dump block
Time
Kicker strength
Illustration of kicker risetime
Large graphite absorbers in the beam dump area protect downstream elements (including dump septa themselves) against badly ‘kicked’ particles.
OutlineOutline
• Energy stored in the LHC magnets and beams• Charging the energy• LHC dipole magnets – quench protection• Beam induced damage – what is a safe beam?• Beam dumping system• Collimation system• Beam interlock system
37
Beam collimation (cleaning)Beam collimation (cleaning)The very high stored energy, combined with a very low thresholds for quench requires a
complex two-stage cleaning system:• Large amplitude protons are scattered by the primary collimator (closest to the beam).• The scattered particles impact on the secondary collimators that should absorb them.• The efficiency of the collimation must be larger than 99.9% to be able to run under reasonable
conditions, i.e. with lifetimes that can drop down to less than 1 hours from time to time… This requires settings tolerance of < 0.1 mm.
60 collimators/beam!
38
Beam +/- 3 sigma
56.0 mm
1 mm
+/- 8 sigma = 4.0 mm
Example: Setting of collimators at 7 TeV - with luminosity opticsExample: Setting of collimators at 7 TeV - with luminosity optics Very tight settings Very tight settings orbit feedback !! orbit feedback !!
Ralphs Assmanns EURO
Collimators at Collimators at 7 TeV, 7 TeV, squeezedsqueezedopticsoptics
39
Prototype collimators Prototype collimators
Robustness maximized with Robustness maximized with C-C jawsC-C jaws
and water cooling!and water cooling!
40
Robustness test at SPSRobustness test at SPS
C-C jaw
C jaw
TED Dump
No sign of jaw damage!No sign of jaw damage!(but some deformation (but some deformation was observed on the was observed on the
supporting structures)supporting structures)
Test condition:
each jaw hit 5 times!
• 450 GeV SPS LHC beam• 3×1013 protons• 2 MJ• 1 mm2 beam area• equivalent to:
Full Tevatron beam
½ kg TNT
OutlineOutline
• Energy stored in the LHC magnets and beams• Charging the energy• LHC dipole magnets – quench protection• Beam induced damage – what is a safe beam?• Beam dumping system• Collimation system• Beam interlock system
Beam loss over multiple turnsdue to many types of failures
Passive protection • Avoid such failures (high reliability
systems)• Rely on collimators and beam
absorbers
Active Protection• Failure detection (from beam monitors
and / or equipment monitoring)• Fire Beam Dump
Beam loss over a single turn during injection, beam dump or any other fast ‘kick’.
In case ofIn case of any failureany failure oror unacceptable beam lifetimeunacceptable beam lifetime, , thethe beam beam must must bebe dumped dumped immediately, immediately, safely into thesafely into the beam dump block beam dump block
‘Unscheduled’ beam loss due to failures
Two main classes for failures (with more subtle sub-classes):
43
Beam interlock systemBeam interlock system
BIS Dump kickerBeam ‘Permit’
User permitsignals
Actors and signal exchange for the beam interlock system:Actors and signal exchange for the beam interlock system:
• ‘‘User systemsUser systems’ : systems that survey equipment or beam parameters and that ’ : systems that survey equipment or beam parameters and that are able to detect failures and send a HW signal to the beam interlock system.are able to detect failures and send a HW signal to the beam interlock system.
• Each user system provides a HW status signal, the Each user system provides a HW status signal, the user permituser permit signal. signal.
• The beam interlock system combines the user permits and produces the beam The beam interlock system combines the user permits and produces the beam permit.permit.
• The The beam permitbeam permit is a HW signal that is provided to the dump kicker (also is a HW signal that is provided to the dump kicker (also injection or extraction kickers) : injection or extraction kickers) : absence of beam permit absence of beam permit dump triggered ! dump triggered !
Hardware links and systems
Core of the Machine Core of the Machine Protection SystemProtection System
Beam Interlock System
Fire kicker magnets
Beam Dumping System
User system detects failure
Beam dump request to Beam Interlock
System
Beam dump request to Beam Dumping System
dump beam
Protection for powering operation• Quench Protection System (4000 channels)• Power Interlocking Controller (36 crates for
800 electrical circuits)
Protection for beam operation• Beam Loss Monitors System (3500 channels)• Special beam instrumentation (few channels) • Beam Interlock System (16 crates for 150 user
connections)• Beam Dumping System (2 complex systems)
45
Schematic of the beam interlock systemSchematic of the beam interlock system
BEAMINTERLOCK
CONTROLLERMODULE
(BIC)
BEAM1_PERMIT
BEAM_PERMIT STATUS SIGNALS
BEAM2_PERMIT
to User Systems
SPS Extraction System for beam 1
SPS Extraction System for beam 2
for beam 2
Beam Dumping System
USER_PERMIT SIGNALS
UN
MA
SK
AB
LE
INP
UT
SM
AS
KA
BLE
IN
PU
TS
MaskSettings
Safe Beam Flag
PM event Trigger TimingSystem
LHC protectionsystems
User System #2
User System #9
User System #16
User System #1
User System #8
User System #10
for beam 1
Beam Dumping System
for beam 1LHC Injection System
for beam 2
LHC Injection System
ArchitectureArchitecture of the BEAM INTERLOCK SYSTEM of the BEAM INTERLOCK SYSTEM
Beam-1 / Beam-2 are Independent!
- fast reaction time (~ s)- safe- limited no. of inputs- Some inputs maskable for safe beam intensity
Up to 20 Users per BIC system:
6 x Beam-18 x Both-Beam
6 x Beam-2
Connected to injection IR2/IR8:-In case of an interlock (=NO beam permit),
the beam is dumped & injection is inhibited.
- It is not possible to inhibit injection
ALONE.
47
BIS reaction timesBIS reaction times
UserSystemprocess
a failure has been detected… beam dump
request
Beam Dumping System waiting for beam gap
89μs max
Signalssend
to LBDS
t2 t3
Beam Interlocksystemprocess
~70μs max.
t1
> 10μs
USER_PERMIT signal changesfrom TRUE to FALSE
Kicker fired
t4
all bunches have been extracted
~ 89μs
Achievable response time ranges between 100 s and 270 s
(between the detection of a dump request and the completion of a beam dump)
SummarySummary
• The LHC is one of the most complex instruments that has ever been The LHC is one of the most complex instruments that has ever been conceived.conceived.
• The LHC is the first accelerator where the machine protection systems The LHC is the first accelerator where the machine protection systems are vital.are vital.
• LHC commissioning progress will be strongly influenced by the LHC commissioning progress will be strongly influenced by the understanding of the components of the protection systems.understanding of the components of the protection systems.
• The LHC performance will be strongly affected by the protection The LHC performance will be strongly affected by the protection systems: systems:
• due to the large number of interlock channels the reliability of the systems must be very high/ Reliability studies have been performed (and there are more to come).
• The very tight tolerance on machine parameters and collimation will make LHC operation totally different from SPS or LEP:
Play once and the beam is gone !