levelized cost of energy. summary levelized costs are calculated as a proxy for the ppa price...

13
LEVELIZED COST OF ENERGY

Upload: alexander-bridges

Post on 22-Dec-2015

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: LEVELIZED COST OF ENERGY. Summary Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility LCOEs amortize

LEVELIZED COST OF ENERGY

Page 2: LEVELIZED COST OF ENERGY. Summary Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility LCOEs amortize

Summary

• Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility

• LCOEs amortize all capital and operating costs incurred over the plant’s economic lifetime, accounting for tax impacts and tax credits

RPS Calculator Valuation Framework

Levelized Cost of Energy

Transmission Cost

Capacity Value

Energy Value

Net Resource Cost

Integration Cost*

=

+

++

*Not currently quantified in RPS Calculator

Page 3: LEVELIZED COST OF ENERGY. Summary Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility LCOEs amortize

Levelized Cost of Energy Calculation of LCOEs has been adjusted to incorporate plausible

changes over time for projects that come online in the future

Version 6.0

Renewable LCOEs calculated for each year to incorporated changes over time:

Capital costs

Financing costs

Tax credits and benefits

Versions 2.0 – 5.0

Renewable LCOEs calculated based on cost and performance of present-day technology

Page 4: LEVELIZED COST OF ENERGY. Summary Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility LCOEs amortize

Goals for New Methodology

4

Model Functionality Versions 2-5 Version 6

Differentiate costs of renewable PPAs by technology

Account for future capital cost reductions Account for sunsets of federal and state tax credits and incentives Account differences in near-term and long-term costs of project finance

Page 5: LEVELIZED COST OF ENERGY. Summary Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility LCOEs amortize

Translating Resource Cost & Performance to LCOEs

Resource Cost & Performance

Capital Cost

Fixed O&M

Variable O&M

Fuel Cost

Capacity Factor

Degradation

Financing & Tax Inputs

Cost of Capital

Capital Structure

Tax Credits

MACRS

Pro-Forma Cash Flow

Model

Levelized Resource Costs(cost-based PPA

prices)

Financing Life

RPS Calculator

RPS Calculator pairs cost & performance assumptions modeled by B&V with a simple pro-forma financing model to calculate the levelized cost of energy for each generating technology

Page 6: LEVELIZED COST OF ENERGY. Summary Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility LCOEs amortize

Pro Forma Parameters

Pro-forma cash flow model accounts for: Capital investment cost and the availability of debt and equity financing Operating and maintenance costs Federal and state income taxes Tax benefits of accelerated depreciation Federal tax credits for renewable resources

The price calculated is sufficient to cover operating costs, provide sufficient debt service coverage, and ensure an adequate return of and on equity to investors Minimum debt service coverage ratio of 1.40

Page 7: LEVELIZED COST OF ENERGY. Summary Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility LCOEs amortize

Key Inputs The table below summarizes the key technology-specific input assumptions

for resources installed in 2013:

Assumes all resources must meet a minimum DSCR of 1.40

Federal and state income tax rates are 35% and 7%, respectively

TechnologyFinancing

Lifetime (yrs)Debt Tenor

(yrs)WACC (%)

Debt Cost(%)

MACRS (yrs)

PTC($/MWh)

ITC(%)

Biogas 20 18 7.10% 5.15% 10 $11

Biomass 20 18 7.10% 5.15% 10 $23

Geothermal 20 18 7.10% 5.15% 5 $23

Hydro 20 18 7.10% 5.15% 20 $11

Solar Thermal 20 18 7.10% 5.15% 5 30%

Solar PV* 25 20 7.25% 5.45% 5 30%

Wind 20 18 7.10% 5.15% 5 $23

* Higher cost of capital for solar PV is assumed due to the longer financing lifetime

Page 8: LEVELIZED COST OF ENERGY. Summary Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility LCOEs amortize

Modeling Future Changes in LCOEs Estimating future costs of renewable resources is a challenging exercise, as many of the factors

that will affect prices are surrounded by large uncertainty

Most significant levers to our estimates: Capital cost reductions: technological improvement over the coming decades may drive

renewable resource costs down Long run financing: projects financed in the future will not benefit from the low-cost

financing available in today’s low interest rate environment, which is inconsistent with long-run macroeconomic projections of inflation

Bonus depreciation: the eligibility of projects to claim bonus MACRS depreciation ends after 2013

Property tax exemption: the exemption of solar facilities from California property tax is not available to facilities installed after 2016

Federal tax credit sunsets: in 2017, the ITC reverts from its current level (30%) back to 10%; the PTC for renewable resources is currently scheduled to expire at the end of 2013

Assumption: credits and subsidies will expire as currently stated by law One exception: Assumes PTC applies to all projects constructed by 2017 (same lifetime as

ITC)

Page 9: LEVELIZED COST OF ENERGY. Summary Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility LCOEs amortize

Capital Costs Over Time

Solar Thermal -Storage

$0$1,000$2,000$3,000$4,000$5,000$6,000$7,000$8,000$9,000

2013 2030

2013

$/M

Wh

Axis Title

Biomass -Large

$0$1,000$2,000$3,000$4,000$5,000$6,000$7,000$8,000$9,000

2013 2030

2013

$/k

W

Axis Title

Wind

$0

$1,000

$2,000

$3,000

$4,000

2013 2030

2013

$/M

Wh

Installation Vintage

Solar PV -Tracking -20MW+

$0

$1,000

$2,000

$3,000

$4,000

2013 2030

2013

$/k

W

Installation Vintage

LCOE calculations integrate projected capital cost trends developed by Black & Veatch Relatively stable for more mature renewable technologies Cost reductions shown for emerging technologies

Page 10: LEVELIZED COST OF ENERGY. Summary Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility LCOEs amortize

Trajectories of Resource Costs Long-term trajectories of PPA prices reflect input assumptions:

Near-term price increases are driven by expiration of tax benefits and credits, increase in financing costs

Over a longer period, reductions in capital costs continue to translate to declining PPA prices for emerging technologies

Solar Thermal -Storage

$0

$50

$100

$150

$200

$250

$300

2013 2030

2013

$/M

Wh

Axis Title

Biomass -Large

$0

$50

$100

$150

$200

$250

$300

2013 2030

2013

$/M

Wh

Axis Title

Wind

$0

$50

$100

$150

$200

2013 2030

2013

$/M

Wh

Installation Vintage

Solar PV -Tracking -20MW+

$0

$50

$100

$150

$200

2013 2030

2013

$/M

Wh

Installation Vintage

Page 11: LEVELIZED COST OF ENERGY. Summary Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility LCOEs amortize

Drivers of Cost Changes Over Time

Based on assumed capital cost reductions and the proposition that tax credits will not be renewed, future renewable costs will be higher than today

$81

$117

$11 $5

$9

$30 $19

$0

$20

$40

$60

$80

$100

$120

$140

$160

2012

$/M

Wh

Solar PV - Tracking - 20MW+

Modeled 2013 PPA

Prices

Low Interest

Rate Financing

Bonus Depreciation

(expires 2013)

Property Tax Exemption

(expires 2016)

ITC (reverts to 10% in 2017)

Predicted Cost Reduction (16%

from 2013 to 2030)

Modeled 2030 PPA

Price

$81

$119

$10 $5$0

$25 $3

$0

$20

$40

$60

$80

$100

$120

$140

$160

2012

$/M

Wh

Wind - In-State

Modeled 2013 PPA

Prices

Low Interest

Rate Financing

Bonus Depreciation

(expires 2013)

No Property Tax Exemption for

Wind

PTC (not renewed after

2016)

Predicted Cost Reduction (3% from 2013 to

2030)

Modeled 2030 PPA

Price

Page 12: LEVELIZED COST OF ENERGY. Summary Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility LCOEs amortize

Summary of LCOEs Over Time• Future increases in costs

are driven by expiration of tax credits & benefits, which are partially offset for some technologies by capital cost reductions

Technology2013

($/MWh)2020

($/MWh)2030

($/MWh)

Biogas – Distributed $ 116 $ 164 $ 164

Biomass – Distributed $ 182 $ 226 $ 226

Biomass – Large $ 121 $ 165 $ 165

Geothermal $ 98 $ 135 $ 135

Hydro – Small $ 301 $ 445 $ 445

Solar Thermal - No Storage $ 181 $ 270 $ 249

Solar Thermal - Storage $ 173 $ 259 $ 236

Solar PV - Distributed $ 132 $ 200 $ 183

Solar PV - Fixed Tilt - 1MW $ 108 $ 165 $ 150

Solar PV - Fixed Tilt - 5MW $ 101 $ 153 $ 140

Solar PV - Fixed Tilt - 10MW $ 92 $ 141 $ 128

Solar PV - Fixed Tilt - 20MW+ $ 88 $ 135 $ 123

Solar PV - Tracking - 1MW $ 97 $ 150 $ 140

Solar PV - Tracking - 5MW $ 91 $ 140 $ 130

Solar PV - Tracking - 10MW $ 84 $ 130 $ 121

Solar PV - Tracking - 20MW+ $ 81 $ 126 $ 117

Wind $ 81 $ 120 $ 119

Wind - Distributed $ 116 $ 162 $ 159

• All costs expressed in 2013 dollars

• LCOEs presented represent a plant with ‘average’ cost and performance attributes for each technology

Page 13: LEVELIZED COST OF ENERGY. Summary Levelized costs are calculated as a proxy for the PPA price between a third-party developer and a utility LCOEs amortize

RPS Calculator Guide

• The parameters that affect resource LCOEs can be found on the following tabs:– Resource_Char: cost and performance input assumptions for

each major category of renewable technology– Pro_Forma: financial model of a cost-based PPA between utility

and third-party developer used to calculate LCOEs used in RPS Calculator

– Resource_Cost: results of LCOE calculations for each technology and each installation vintage (2013-203), expressed by component

• Results hard-coded by macro