lessons learned from hardware-in-the-loop testing of microgrid control systems · 2017-10-31 ·...
TRANSCRIPT
-
2017 MIT-LL and SEL
Lessons Learned From Hardware-in-the-Loop Testing of Microgrid Control Systems
E. Limpaecher, R. Salcedo, and E. CorbettMassachusetts Institute of Technology Lincoln Laboratory
S. Manson, B. Nayak, and W. AllenSchweitzer Engineering Laboratories, Inc.
-
DMS
Modbus
Modbus
GovernorGovernor InverterInverter
C-HIL ModelMacrogrid
BansheeMicrogrid
Loads
LoadsLoads LoadsLoads LoadsLoadsPV + BESSPV + BESS
SDG CHP
PCC1 PCC2 PCC3
C-HIL System
MGC System
DER Interface High-Speed Digital Interface
C-HIL Real-Time Simulator
C-HIL ModelMacrogrid
BansheeMicrogrid
Loads
LoadsLoads LoadsLoads LoadsLoadsPV + BESSPV + BESS
SDG CHP
PCC1 PCC2 PCC3
ControllerModbus PCC
Relay
DIO Module
24 V
TTL
24 V
TTL
DIO Module
24 V
TTL
IEC-61850
-
Standardized Test Sequence for All Microgrid Controller Suppliers
-
Macrogrid
Microgrid
PCC Relay
Trip/ClosePCC
DERs Controller
Microgrid Control System Grid reconnection
Unintentional islanding
Protection for expensive assets
IEEE 1547 compliance
Metering
Pass-through control
Protective Relay at PCC Provides ~50% of Control Functionality
Trip/CloseTrip/CloseTrip/Close
-
Load shedding Intentional islanding PCC dispatch PF control Voltage regulation Frequency regulation
Microgrid Controller Load Shedding, Dispatch, and Islanded Regulation
Macrogrid
Microgrid
PCCRelay
Trip/ClosePCC
DERs Controller
Microgrid Control System
Loads
-
NormalLoading
PCC
V
(0.8 pf)
I
I
(+0.8 pf)Loads
High CurrentLow Voltage
Normal Load Angle
Trip PCC Fast (67)
Directional Current Protection (67)Opens PCC During Short-Circuit Conditions
Import Export
(0.8 pf)I
I
(+0.8 pf)
Fault FAULTI
Trip PCC Fast (67)
-
Relay Recording of Utility Disconnection Event in 2016
Loads
Loads
PCCRelay
Fault Starts
Relay Trips Load
Current Interrupted
Frequency Recovers!
Microgrid Controller
Sheds Load
CB Opens
-
Macrogrid Disturbance
Conventional Blackout
t
60
Frequency (Hz)
57
PCC Relay Trips
PCC Opens
DER Trips
PCC TripDER Trip
Fast 81RF Element Detects Open Circuit Conditions
Trip RegionMicrogrid
Blackout
IEEE 1547-2003
df/dt (Hz/s)
Frequency (Hz)
81RF Microgrid Survival
PCC Opens
PCCRelay Trips
-
Fast 81RF Element Improves Seamless Islanding
Trip RegionMicrogrid
Blackout
IEEE 1547-2003
df/dt (Hz/s)
Frequency (Hz)
Grid Connection
Microgrid Survives
81RF Trips
PCC Opens
Load Shedding
Macrogrid Disturbance
Conventional Blackout
t
60
Frequency (Hz)
57
PCC Relay Trips
PCC Opens
DER Trips
PCC TripDER Trip
81RF Microgrid Survival
PCC Opens
PCCRelay Trips
-
MacrogridMacrogrid
MicrogridMicrogrid
PCC Relay
Controller
DERDER
V, Slip
Dispatch
Simple Grid Reconnecting MethodWorks With All DERs
(slip)
V
VMACROGRIDVMICROGRID
-
Two Types of Load-Shedding Systems Employed
Problem to Mitigate Load-Shedding Speed
Frequency collapse Fast
Voltage collapse Fast
DERs out of step Fast
DER overload Slow
Synchronization assist Slow
PCC curtailment Slow
PCC demand charge avoidance Slow
Subcycle(faster than 16 ms)
Slow(~1 second)
-
Controller Redispatches DER Power Contribution After Sudden Loss of Load
Rea
l Pow
er (M
W)
Diesel BESS PV UtilityCHP
Time (s)0 15010050
5
4
3
2
1
0
1
-
Controller Redispatches DER Reactive Power Contribution After Sudden Loss of Load
Rea
ctiv
e P
ower
(MV
AR
)
Diesel BESS PV UtilityCHP
Time (s)0 15010050
2.0
1.5
1.0
0.5
0.0
0.5
1.0
-
Macrogrid
Microgrid
Loads
Loads Loads LoadsPV + BESS
SDG CHP
PCC1 PCC2 PCC3
The Ultimate: Triple Seamless Islanding Event!Only Possible With Integrated Relays and Controllers
59.84
59.88
59.92
59.96
60
60.04
12000 14000 16000 18000 20000
Freq
uenc
y (H
z)
VAB (rms)
Volts vs. Hz
-
Triple Seamless Islanding Event Only Possible With Fast, Intelligent Load Shedding
FB203FB204FB103 FB306
Time (s)
Freq
uenc
y (H
z)
Time (s)
Freq
uenc
y (H
z) Area 2
Area 3
Area 1
0
0
50 100 150
2010
56
57
58
59
60
6261
56
57
58
59
60
61
62
-
MGC Drives Bus Voltage Back to Normal After Same Triple Islanding Event
VB203VB204VB103 VB306
Time (s)
Bus
Vol
tage
(pu)
Time (s)
Bus
Vol
tage
(pu)
Area 2
Area 3
Area 1
Load Restoration EventDecoupling Event
20100 30 40 50
1500 50 100
1.10
1.05
1.00
0.95
0.90
1.10
1.05
1.00
0.95
0.90
-
Grid-Tied Operation
Islanded Operation
Controller
Reconnection Unintentional Islanding
PCC Relay
Relays and Controllers Work Together
-
Differences Between Industrial and Community Microgrids
Community Microgrid
Industrial Microgrid
Power Reliability Energy Efficiency Payback Period Years Days
Intermittent Energy Sources Inverter-Based Generation
-
Questions?
Lessons Learned From Hardware-in-the-Loop Testing of Microgrid Control SystemsSlide Number 2Standardized Test Sequence for All Microgrid Controller SuppliersProtective Relay at PCC Provides ~50% of Control FunctionalityMicrogrid Controller Load Shedding, Dispatch, and Islanded RegulationDirectional Current Protection (67)Opens PCC During Short-Circuit ConditionsRelay Recording of Utility Disconnection Event in 2016Fast 81RF Element Detects Open Circuit ConditionsFast 81RF Element Improves Seamless IslandingSimple Grid Reconnecting MethodWorks With All DERsSlide Number 11Two Types of Load-Shedding Systems EmployedController Redispatches DER Power Contribution After Sudden Loss of LoadController Redispatches DER Reactive Power Contribution After Sudden Loss of LoadThe Ultimate: Triple Seamless Islanding Event!Only Possible With Integrated Relays and ControllersTriple Seamless Islanding Event Only Possible With Fast, Intelligent Load SheddingMGC Drives Bus Voltage Back to Normal After Same Triple Islanding Event Relays and Controllers Work TogetherDifferences Between Industrial and Community MicrogridsQuestions?